CONTENTS
1. Scope
2. References
3. Definitions
4. Responsibilities
5. Special care
6. Construction Procedure
9. Resources
10. Records
➢ References: -
IS 3764
1200 pt. I-1992
Relevant Approved Drawings
Excavation Plan
➢ Definitions: -
Permanent work: - the permanent work constructed, serviced and maintain
for client in accordance with contract
ER: - Employer representative
ITP: - inspection testing plan
Safe Slope: - The steepest slope, at which an excavated face is stable against
slips and slides, having regard to the qualities of the material in the face, the
height of the face, the load above the face and the moisture conditions.
Barricade: - Any object or structure that creates a barrier obstacle to control,
block passage or force the flow of traffic in the desired direction.
➢ Responsibilities: - (RACI Matrix)
Project Construc Consulta Site Superv Safety
WORK Manage tion nt/ Engine isor Office
r Manager surveyor er r
Permit Requirements A R C I
Study geo-technical report and, A C R I
dewatering plan, Railing work
Fix reference lines and reference A C R I
points, dimension, column center pt. &
checking
Measure and confirm Plot dimensions, A C R I
Take levels of entire Plot at required
grids
levels are to be recorded as per strata A C R I
Classification likes soil, etc.
Check excavated size at bottom of pit / A C R I
trench and mark P.C.C. size as per
drawing and formation level
Worker & Public safety C R I A
➢ Special care: -
1. For water logged area.
2. For environmental sensitive area.
3. For Slope.
➢ Construction Procedure: -
▪ Pre-Excavation Activity: -
Prior to the start of work the excavation permit shall be obtained from the Engineer
In-Charge Before starting the excavation, ensure that no underground electrical
cable, Water line, Sewer line passing through the excavation area Utility services if
any observed in the underground of excavation area shall be brought to the notice
of Engineer-In Charge and the services shall be terminated as agreed.
Permit Requirements: -
1. Excavation Permit.
2. De-watering permit.
3. No-objection certification from all services providers such as
drainage, water supply, telephone, gas, irrigation, optic fiber
4. Verify existing utilities
5. Refer to as built plans
6. Emergency / Contingency Plan
7. Public safety
Construct corner
point pillars &
Demarcate and line out exact
mark face of each
excavation Area / Pits, Trench
building
Reconfirm with Client, Engineer In-
charge.
▪ Safety:
Environment: -
1. Before the start of site cleaning, sprinkle water to reduce dust and prevent air
pollution
2. Use mask, safety shoes for site cleaning and line out.
3. Excavated earth should be stacked properly and sprinkle light water on
surface.
4. Maintain record of excavated and reused earth.
9. Before digging check underground utilities like, water, gas, electricity etc.
10.While excavation by machine, keep visual controls, movement of
unauthorized Persons should not be allowed
11.Ensure snake bite kit is available & used whenever required
➢ Resources: -
Machinery/ Tools
1. Excavators
2. Dumpers,
3. Dozers
4. Graders
5. Pickaxe
6. Baskets
Tools
1. Shovel
2. Pickax
3. Pneumatic hammer
Manpower: -
1. Supervising Engineer
2. Supervisor / Foremen
3. Operator
4. Driver
5. Skilled Workers
6. Surveyor
7. Unskilled Workers
➢ Records: -
1. Inspection records, generated by this procedure are, to be managed in
accordance with the project Quality Plan.
2. Records of monitoring, analysis and improvement Shall be maintained
on site throughout the contract period following which they shall be
passed to the Corporate Quality Department. Such records shall be
maintained for a period of five years, after which they may be
disposed.