NOTE: Complete only relevant sections. If certain sections are not considered relevant, you must
state why it is not relevant. Incomplete reporting is unacceptable.
In this section record the entire key data regarding the equipment’s primary function.
1 What is the operating context for this equipment you have worked on?
(State the primary function and the performance, throughput, in a specified time, i.e. pressure,
temperature, etc?)
2 State what the standard primary function performance standard is, i.e., it is the datum for
comparison, and who has set this performance standard?
Page 1 of 11
C) Functional Failure How has ‘it’ not done what it should?
In what way has this piece of equipment been deemed to have failed to fulfil its function?
3 Provide a brief statement of the ‘problem’ or failure that Maintenance was asked to
investigate/resolve. [This may be the key point from the maintenance work order.]
4
What change or deviation was observed from the normal operating condition?
Compared to the function details previously in Q1 & Q2, e.g. was deterioration, slow down,
increases noted, etc? State how? By how much? Over what time frame, etc?
6
State in words briefly what happened when the failure occurred? Consider the effect on
the equipment, system, and plant.
Page 2 of 11
E) Action to Restore Function
State clearly what exactly has been done physically to overcome this functional failure?
8
Explain beneath:-
9 If the item was replaced please state the condition of the fitted item:
3 Action Code
Replaced with new item
Replaced with refurbished item
Refurbished and then replaced
Replaced with modified item
Other
Lost/Discarded
Available for review (tagged and stored)
Refurbished and reinstalled
A) Good as new
B) Better than old
Refurbished and returned to store
Returned to vendor
Other, explain ________________________
11 Has this equipment been returned to as good as new condition and function?
Yes? No?
If Yes how did you verify, test and confirm that the equipment meets the required performance
standards following the response?
• Requirement _________________
• Due date: _______________________
• Consequence if due date missed ______________________________________________________________
• Follow on MWO Number _______________________________________
Page 3 of 11
13 How long will the equipment run now ? ______________________________.
Until what next datum? _________________________________________.
When? ____________________________.
F) Change Control
14 If you have performed a modification that alters the original fit, form or function, (this includes the
substitution of components, different manufacturers, in house made) then this may significantly
change its life.
Please explain technically the reason, purpose and who authorised this modification, -
• Reason [s] _____________________________________________________
• Purpose _____________________________________________________
• Authority To Modify Is _____________________________________________________
(Letter No., Engineering Package No, etc)
15 Detail what effect this modification will have on the function and performance of the
equipment/component?
Page 4 of 11
G Failure Mode/Cause
17 What are the initial recorded CMMS Failure Codes for the work that was conducted?
Failure _________________
Failure Code _________________
Problem _________________
Problem Code _________________
Cause Description _________________
Cause Code _________________
19 What was the failed component(s) and its mode of failure, e.g., Oil Filter Blocked?
21 Have you conducted a five-why or other technique to arrive at the Root Cause?
Yes? No?
Be aware that the initial reported cause is rarely the root cause codes and a further level of detailed,
analysis and comparison is necessary to arrive at the real root cause.
Please list the possible Root Cause of failure into the table below.
NOTE if further investigation is ongoing or required do not complete this section until the investigation is
complete.
Page 5 of 11
Root Cause Yes No
Maintenance Related
Skills (Competency Deficiency Of Craftsmen)
Incorrect Tooling or Equipment Utilised
Improper Previous Repair (Rework Issue)
Improper Alignment or Field Installation
None Standard or Original Materials, Parts Used
Original Design or Selection In Question
Operational Related
Mal-operation. (Improper Operation/Sequence/Etc)
Improper Start-up or Shutdown
Equipment Overloaded, Operated Too Hard or Too Slow
Operating Context/Condition has Changed Since Design
Lubrication Issue (Insufficient/Incorrect/Contaminated)
Other, explain
E.g., design related
E.g., purchasing related
You must say what it may be and what it is not; i.e. a Y or N is required for each. No omissions allowed.
23
Evaluate the Reliability of this failure?
Based upon the initially reported fault codes, the historical data that has been gathered, the evidence of this
event/failure and the basic causes of failure from the table above, from a maintenance perspective would
you say this failure is:-
If you indicated Yes to either of the last two questions above. Please compare
I.e. [abnormal/unusual or chronic/repetitive] these to Nos.1&2
(on Page 1 to
define the
What is the historical frequency (number of occurrences)? ___________ deviation in
Attach the support through the relevant CMMS Reports. performance
Page 6 of 11
H) Consequences of Failure Does it matter? How much?
24 State the consequences of this failure in terms of safety, environment, production, and
costs?
24a Safety: Was there an actual safety loss associated with this event /failure? (This refers to a
quantifiable safety loss that was sustained.) Yes? No?
If Yes - then how can this actual safety loss be quantified in financial terms? Indicate the value of this safety
loss in the box provided
Environmental: Was there an actual environmental loss associated with this event/failure?
24b
(This refers to a quantifiable environmental loss that was sustained.) Yes? No?
If Yes – then how can this actual safety loss be quantified in financial terms? Indicate the value of this
environmental loss in the box provided.
<X $’s> for ___________________________
As this was an actual safety and/or environmental loss, has this been documented separately, accompanied
with the near miss or preliminary incident reportage and channelled through to population of, e.g., HAZOP
databases? Yes? No?
If Yes, - record the transmittal reference to Safety & Environmental Department ______________________
If No, - why not?
Production: - Was there an actual production loss associated with this failure/event?
24c
Note. This refers to a quantifiable loss that was sustained that was not recovered by increasing
throughput through the plant/unit/equipment once the failure/event was dealt with.
Yes? No?
If Yes, - then how can this actual production loss be quantified in financial terms? Indicate the value of this
loss in the box provided. (You may need to discuss this with a performance-monitoring engineer.)
24d Maintenance: When maintenance responded to this event/failure. (It is important to understand if
this was a completely unbudgeted/unplanned response.)
What were the total maintenance costs associated with the response to this event/failure?
Total _________________
Labour _________________
Materials _________________
Other _________________
Hr’s
Page 7 of 11
What was the total maintenance time within this total downtime?
Where is the balance of the downtime to be attributed to if the maintenance downtime is less than 50% of
the total?
Did this event/failure result in other non operational cost other than the direct costs of response/repair?
Perhaps taxes, penalties, logistics etc. Yes? No?
If Yes what were these costs by type and cost?
• _____$’s
• For _______<what>
25
Determine the Total Financial Cost Of This Event/Failure. (Add together numbers 24a –24e.)
______ $’s
I) Preventive Action
<Why> -------------------------------------------------------------------------------------------------------------------------------------------------
<How>--------------------------------------------------------------------------------------------------------------------------------------------------
<By when>---------------------------------------------------------------------------------------------------------------------------------------------
27 Define the tasks or ideas that your work group should do to resolve this issue?
1. _______________________________________________________________________________________
2. _______________________________________________________________________________________
3. _______________________________________________________________________________________
4. ________________________________________________________________________________________
5. Approximate Cost?_______________ ROI v/s cost @ Number 25 = x:1 in y period
28
Have you any other suggestions that would prevent a re-occurrence? (Perhaps outside of
your control.)
29
Do you consider your suggestions to be: -
An in-house maintenance activity(s) Yes? No?
A outsourced specialist maintenance activity Yes? No?
A redefined operations activity (s). Yes? No?
A modification or enhancement. Yes? No?
Page 8 of 11
J) Maintenance Strategy Review
30 Would checking the equipment at different intervals have been sufficient to detect the failure
before it occurred? How would it then become detectable and preventable? Please explain.
31
Should we consider a scheduled overhaul / strip down for this equipment? Would the timely
replacement of a component have retained the original system resistance to failure as a whole?
Please expand/support below.
If NO - What are the reasons why it should be included in the PM program ? What specific individual
failure modes would be targeted and how, in the revised preventative maintenance checks?
If YES - Why didn’t the current preventative measures avoid this current failure?
The equipment is in the PM program and the current PM activities did not prevent this current failure because
_____________________________________________________________________________________________
_____________________________________________________________________________________________
My support/evidence for this conclusion is ___________________________________________________________
If YES - What was the date of the last PM?__________ Type/Code Used ___________
Have the PM’s been conducted on time/schedule in the last year? Yes? No?
(Please attach the proof that the scheduled PM’s have been completed on schedule and completed.
Explain _______________________________________________________________________________
Explain _______________________________________________________________________________
Page 9 of 11
Do we need to change ‘it’?
K) Design out.
What should be done if no suitable preventative task can be found? Is there an inherent
34 systemic or equipment ‘problem’ that can only be resolved by a redesign action?
Page 10 of 11
Scratchpad - Anything To Add or Record?
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
Team Leader/Title/Department
Name:_______________________
Title:_________________________
Department:___________________
Team Members/Discipline/Dept
Page 11 of 11