Materials:
Type 01 – For top 450mm of embankment
Maximum dry density under standard condition of compaction not less than 1600kgm-3.
Four days soaked CBR at 93% MDD is not less than 7%.
LL < 50 PI < 25
Type 02 – For lower layers
Maximum dry density under standard condition of compaction not less than 1500kgm-3.
Four days soaked CBR at 93% MDD is not less than 5%.
LL < 50 PI < 25.
Type 03 – Soil Upper Sub-base
Maximum dry density under standard condition of compaction not less than 1750kgm-3.
Four days soaked CBR less than 30%.
LL < 40 & PI < 12%
Type 04 – Soil Lower Sub-base
Maximum dry density under standard condition of compaction not less than 1650kgm-3.
Four days soaked CBR less than 15%.
LL < 40 & PI < 15%
Slightly high LL and high PI are allowed if the material passing 75 micron is less than 10%
Material Testing Reports and Soil Selection for Embankment Construction
According to above soil testing results, This soil cam be recommended for top and bottom
embankment construction and lower sub-base construction but not suitable for upper sub-base
construction.
Suitable stabilizing method can be used to reduce PI in order to recommend this material for upper
sub-base construction.
According to above soil testing results, This soil cam be recommended for top and bottom
embankment construction and lower sub-base construction but not suitable for upper sub-base
construction.
Suitable stabilizing method can be used to reduce PI in order to recommend this material for upper
sub-base construction.