Вы находитесь на странице: 1из 6

Increasing the speed of construction

Tailor Made Concrete Structures – Walraven & Stoelhorst (eds)


© 2008 Taylor & Francis Group, London, ISBN 978-0-415-47535-8

Incremental launching of final composite bridge deck

L. Sasek
Mott MacDonald Prague, Czech Republic

ABSTRACT: Launching of final composite bridge deck has all advantages of launching method such as
erection speed, lower costs and high quality of the bridge. Further innovation for composite bridges is the
position of sliding bearings and the sliding trace structure.

1 INTRODUCTION are of reinforced concrete. The bridge height is


17–20 m above ground. The original design proposed
Erection of 230 m long bridge on the highway D3 launch the steel frame of the composite bridge alone,
(from Prague to Austria) was carried out with a unique with the concrete slab expected to be cast in situ after
construction method never used in the world before. completion of the launch.
With composite bridges the steel frame is normally When a steel structure is launched alone and the
built first and the deck cast in situ afterwards. On concrete deck is cast later, the steel structure is able to
this project, incremental launching of final composite resist small vertical reactions only along its length. On
bridge deck was undertaken and proved to be highly the other hand when, launching a completed composite
effective. Speed of the construction was a source of bridge structure, the weight of the deck is four times
financial savings and building of the whole structure higher, because the concrete slab represents 75–85%
in a workshop a prime advantage in terms of quality. of the total weight of the bridge structure.
The proposed bridge structure is very economi-
cal – the steel consumption index was 97 kg/m2 only
compared to a more usual figure of 130 kg/m2 .
Two bridges have been built by directly launching
the final composite deck, one highway bridge in Ger-
many and the second on UK’s West Coast Main Line
railway. These required use of oversized web plates
to avoid buckling caused by migration of support
reactions.
Our bridge has continuous beam scheme of 7 spans
24.0 + 5 × 36.0 + 24.0 m. The bridge deck consists of
two steel I-beams and a transverse prestressed concrete
deck (Figure 1 and 2). The main girders are joined by
steel diaphragms. The diaphragms above the supports Figure 2. Launching track.

Figure 1. Finished bridge.

1179
Casting of the concrete slab in situ after launch acts as a very rigid stiffener. This solution substan-
of the steel frame causes problems for the contrac- tially decreases the tensile stresses in the concrete
tor and also for the designer. During concreting of slab. Inclined webs were designed for better placing
bridge deck the steel and composite structure change of launch bearings close to the steel webs.
the static system many times. The structure has to be The steel structure was designed specifically to
monitored during all building stages. Errors due to allow for this form of incremental launching. The
geometry of the structure, volume changes of concrete, upper flanges of the beams were made in a straight
change of elasticity modulus etc. must be all taken into alignment and the bottom flanges with a camber. For
consideration. For every building stage the designer this reason it was necessary to monitor the plane slid-
must calculate thousands of surveying points. These ing trace and the differences of the upper flange shape
are necessary to monitor the geometry differences of to avoid increase of tensile stresses in the concrete slab.
the steel structure during deck concreting, settlements The bottom surface of the upper flange that comes
of supports, creep and shrinkage of concrete, ther- in contact with launching bearings must allow for
mal changes, framework structure settlement and the geometrical tolerances.
weight changes caused by differences of concrete deck
thickness.
3 FURTHER INNOVATION WAS IN THE
STRUCTURE OF THE SLIDING TRACE
2 CONCEPTUAL DESIGN
In order to decrease local reactions, one light tem-
With regards to the above mentioned facts, we started
porary pier was used in every span. The permanent
to think about the incremental launching of the final
piers were designed to resist service load only. The
composite bridge deck not by means of steel beams
horizontal friction forces in service stage acting in
but by means of concrete deck. As mentioned pre-
the longitudinal direction are compensated with higher
viously, the final composite bridge deck is 4 times
vertical reaction. On the other hand, during launching,
heavier and if it was launched on steel beams it would
in some accidental cases high horizontal forces can
have caused substantial increase of the web and bottom
arise especially when the launching starts.
flange thickness. The reactions from the launch bear-
A special balanced static indeterminate system was
ing migrate along the whole length of the structure and
developed to decrease the horizontal loading on flex-
a greater steel weight is required.
ible piers and abutments and to ensure the stability of
In order to avoid this problem we decided to launch
temporary piers. The heads of all piers and abutments
the structure supported on the bottom surface of the
were connected by steel bars. The bars were partly
upper flange next to the beam web (Figure 3).
stressed from one abutment to the other and piers were
The concrete slab at this location is connected to
fixed to the bars. The temperature changes along the
the steel flange by means of studs and the beam web
whole bridge length caused the change of stresses in
bars without any deformation of piers. This system is
adjusted so that the stiffness and prestressing forces
are balanced in the way that no allowable stresses or
deformations were exceeded (Figure 4).

4 CONCLUSION

The presented incremental launching of final compos-


ite bridge deck is a unique solution. The construc-
Figure 3. Launching bearings. tion method requires resolution of many problems,

Figure 4. Launching animation.

1180
technological processes and structural details. Launch- there were significant time savings in calculation of
ing of the viaduct has recently been completed. The bridge geometry in many erection stages. The struc-
contractor and investor were satisfied with the speed, ture was constructed with high accuracy. Finally, the
lower costs and high quality of the bridge. Eigh- architectural quality of structural elements is clearly
teen meters of finished bridge deck was produced recognizable and enhances the aesthetic qualities of
in seven days. From the designer’s point of view the bridge.

1181

Вам также может понравиться