Вы находитесь на странице: 1из 12

Bill of Quantities

Project Name: At Taybeh-Jericho Road Project


Contents
Item Page

1 Description of the Works 1

2 Preambles 2

3 Preliminaries 4

4 Earth Works (Excavation & Embankment) 5

5 Sub-Base & Base Coarse Works 7

6 Bituminous Construction 8

7 Concrete and Utility Works 9

8 Total 11

IIS/Roads407817506.xls 1
Work Description
Project Name: At Taybeh-Jericho Road Project

DESCRIPTION OF THE PROJECT


The road is a narrow rural collector mountainous road which links Ramllah District with with
Jericho District. It has a total length of 20.0 kilometers and a width of about 6 meters. The road
serves the passenger and freight traffic between the central part of the West Bank and the Jordan
Valley as well as Jordan.

The road is considered to be one of the most dangerous roads in the West Bank with a high number
of car accidents. Therefore, people’s safety is another important concern which will be addressed
through this project. This is because the project will not only focus on infrastructural work, but
also on the provision of road safety measures.

The road is designed to have 7.2m asphalted concrete layer for the traffic lanes with two paved
shoulders; the one on the valley side of 2.4m width, and the other on the hill side of 1.5m width. In
addition, side ditches and culverts are provided where needed. Moreover, the design includes
furnishing the required signing, marking and guard rails, which come under another package.

The current project covers the section from station 0+270-2+400

IIS/Roads407817506.xls 2
Preambles
A. These Bills of Quantities are to be read in conjunction with the Tender Conditions of Contract, agreement,

Specifications, and Drawings. The various documents making up the contract shall be deemed to be mutually

explanatory. The method of measurement followed shall be the “principles of measurement (international) for

works of construction “ amended to suit local practice.


B. The general direction and descriptions of works given in the specifications are not Necessarily repeated in the bills
of quantities. Reference must be made to the specification for this information.
C. The contractor shall be deemed to have revised all the tender documents, inspected and examined the site and it's

surroundings, and have satisfied himself to the nature of the ground and subsoil before submitting his tender. He

shall also be deemed to have taken into account the form and nature of the site, the extent and nature of the work

and materials necessary for the completion of the works, the means of communication with and access to the site,

the accommodation he may require and in general to have obtained for himself all necessary information as to the

risks, contingencies and any other circumstances influencing and affecting his tender.
D. The contractor shall be deemed to have satisfied himself before submitting his tender as to the correctness and
sufficiency of the tender and of the rates and prices stated in the bill of quantities or price schedule, where shall,
save where otherwise provided, cover all his obligations under the contract.
E. Any discrepancy between the Specifications and Drawings and Bills of Quantities shall be brought to the notice of
the Engineer in writing before work which is the subject of the discrepancy is commenced. Dimensions and sizes
shown in the drawings shall generally take precedence over those stated in the Specifications.

F. Since the contractor is deemed to have determined his price on the basis of his own calculations, operations and
estimates, he shall, at no additional charge, carry out any work that is the subject of any item whatsoever in his
tender for which he indicates neither a unit price nor a lump sum.
G. Quantities stated in the Bill of Quantities are approximate and not to be considered as limiting for extending the
amount of work to be carried out and/or materials to be supplied by contractor.
H. The Contractor should note that the cost of all work carried out in the construction of junctions, access roads or

access to properties shall be based on tendered rates under the appropriates items in the Bills of Quantities and no

claim for additional payment for this work shall be considered.


I. The Contractor shall note that there are no haulage items given in these Bill of Quantities, and that allowance must
be made in the tendered rates for any haulage in the appropriate items. However, as for the cut material, the
Contractor may dump the material into the opposite wadi, except the removed pavement structure, which should be
hauled and dumped in an authorized dumping place.
J. Payments due under the contract shall be determined by applying the unit rates to the quantities executed for the
respective items, in accordance with the BoQ and contract.
K. The utility diversions work shall include the workmanship needed. The work shall be according to the
Specifications and Engineer’s satisfaction.
L. Unless otherwise mentioned in the Bill item, all services items expect relocation works, not directly measured

under this bill item shall include for excavation (including rock), back filling, dewatering, compaction, temporary

works and placement and testing of pipes etc. Excavation width for various services shall be as agreed by Engineer

on site. The width of trench excavation for the relocation of existing cables shall be as directed by the Engineer

on site.
M. Items for the preparation of formation to receive subsequent embankment layers shall include for shaping,

watering and compaction.


N. All draining and sewerage works, if any, to be carried out by a company on the approved Contractors’ list of the
UNDP.
O. All pipes and ducts for drainage works, if used, shall be pre-cast concrete.
P. Rates of concrete works are to include for placing, compacting, forming any joints, all necessary frame works,
curing and protecting, etc

IIS/Roads407817506.xls 3
1.0 Preliminaries

No. Item Unit Quantity Unit Total Cost


NIS NIS
1.01 Mobilization

1.01.1 This item includes site office, equipment, supplies,


maintenance of traffic, temporary works, safety
measures, etc. required for the proper completion of
works as specified in the Special Conditions. It
includes the pre-construction submittals of: work
schedule, quality control plan, safety program,
environmental monitoring and mitigation plan. It
includes also all obligations, and liabilities conferred
on the contractor by the bidding documents, and all
tests required for the completion of the works. The
requirements of the Office for the exclusive use of the
Engineer's Representative and his Staff with all
associated equipment and services are illustrated in
the Special Conditions. L.S. 1

Total of Preliminaries

IIS/Roads407817506.xls 4
2.0 Earth Works

No. Item Unit Quantity Unit Total Cost


NIS NIS
2.01 Excavation

2.01.1 Unclassified excavation in the cut sections of the


road, including removing existing pavement layers
( in cast or fill sections), watercourses, ditches and
Wade relocations all as and where shown on the
drawings including grading, watering, compaction,
testing, all tests required, and hauling the excavated
material either to locations for road embankments or
to stockpiles or to waste, all according to
specifications and as directed by the Engineer. (Note:
Suitable Excavated materials to be used for
embankment of the road widening in the same cross
section of the road will not be paid for as
Embankment Materials) C.M 107500

Total

IIS/Roads407817506.xls 5
2.0 Earth Works

No. Item Unit Quantity Unit Total Cost


M3 NIS NIS
Total Brought From Previous Page

2.02 Embankment Construction

2.02.1 Construction of road embankments and sub-grade


layers (200mm thick each) by selected materials
(Topping) imported from outside site, including
preparation of the areas upon which they are to be
placed, placing and compacting approved material
within areas where unsuitable material has been
removed, ready to receive the pavement structures
and shoulders, including all tests required. All in
accordance with the lines, grades and cross sections
shown on the drawings, specifications and direction
of the Engineer. C.M 7700

Total

IIS/Roads407817506.xls 6
3 . 0 Sub – Base and Base Courses

No. Item Unit Quantity Unit Total Cost


NIS NIS
3.01 Aggregate Base Course

3.01.1 Furnishing crushed aggregate base course material


class A ,200 mm thick after compaction, including
mixing, spreading on prepared sub-base course or
sub-grade, compacting and finishing, and all tests
required. All according to specifications drawings,
cross-sections and directions of the Engineer. C.M 4600

Total of Sub base and Base Courses

IIS/Roads407817506.xls 7
4. 0 Bituminous Construction

No. Item Unit Quantity Unit Total Cost


NIS NIS
4.01 Bituminous Prime and Tack Coat

4.01.1 Furnishing and applying bituminous prime coat (MC-


70) or equivalent (rate of application 1.2 kg/m2) to
previously constructed sub grade, sub-base or
aggregate base course or concrete pavement, all
according to specifications, drawings and directions
of the Engineer. ton 24
4.02 Bituminous Binder and Wearing
Courses
4.02.1 Furnishing, spreading and compacting 6 cm
bituminous wearing course (3/4 inch), including all
tests required. All according to specifications,
drawings and directions of the Engineer. S.M. 24000

Total

IIS/Roads407817506.xls 8
5 . 0 Concrete and Utility Works

No. Item Unit Quantity Unit Total Cost


NIS NIS
5.01 Reinforced Concrete Pipe Culverts

5.01.1 Supplying and placing of precast reinforced concrete


of 2 pipes 1000 mm diameter each (i.e., for the
double pipe culvert, where the indicated quantity is
for each of the pipes comprisong the double pipe
culvert) including excavation, preparation, bedding,
back filling, supplying all necessary materials and
building of head walls and end walls, aprons inlet and
outlet protections, tar or bituminous painting to
surfaces permanently in contact with backfilled
material and all necessary works and steel
reinforcement, including all tests required. All
according to specifications, drawings, and directions
of the Engineer. S.M. 15 500 7500

5.02 Reinforced Concrete Box Culverts

5.02.1 Supplying of all materials required and construction


of reinforced concrete box culverts extension
including excavation, preparation, formworks,
backfilling, headwalls, end walls, aprons, tar or
bituminous painting to surfaces permanently in
contact with backfilled materials, and all necessary
works and steel reinforcement,including all tests
required. All according to specifications, drawings
and directions of the Engineer. C.M 40

Total

IIS/Roads407817506.xls 9
5.0 Concrete and Utility Works

No. Item Unit Quantity Unit Total Cost


NIS NIS
Total Brought From Previous Page

5.01 Supplying, placing and finishing of reinforced


concrete (B250) for lining of side ditches (thickness
10cm, width 2.0m), including steel reinforcement. All
according to specifications, drawings, and directions
of the Engineer. S.M. 2665

Total of Concrete and Utility Works

IIS/Roads407817506.xls 10
No. Item Cost (NIS)
1 Total of Preliminaries

2 Total of Earth Works


3 Total of Sub Base and Base Course
4 Total of Bituminous Construction
5 Total of Concrete and Utility Works

CONTINGENCIES

Total ( NIS)

IIS/Roads407817506.xls 11
PALESTINIAN NATIONAL AUTHORITY

MINISTRY OF PUBLIC WORKS

CONSULTANCY SERVISES FOR DESIGN


AND PREPARATION OF TENDER DOCUMENTS

FOR
AL SAWAHREH ROADS

COST ESTIMATE

Aug. 2000

Вам также может понравиться