Januari 2017

ID Task Task Name Duration Start Finish % Scheduled Complete Actual Progress % Cost 2016 2017 2018 2019
Mode H1 H2 H1 H2 H1 H2 H1
1 Cadangan Pembinaan Semula Giatmara 518 days Thu 8/25/16 Mon 8/20/18 5.52% 4.47% RM 10,518,297.00 16%
Wilayah Persekutuan Labuan
2 Preliminaries 518 days Thu 8/25/16 Mon 8/20/18 19.00% 19.00% RM 515,179.00 19%
35 Piling Works 86 days Mon 2/6/17 Mon 6/5/17 0.00% 0.00% RM 702,010.00 0%
79 Building Works 340 days Mon 2/6/17 Fri 5/25/18 0.00% 0.00% RM 5,058,364.00 0%
80 C1 - Blok Pentadbiran 286 days Wed 3/29/17 Wed 5/2/18 0.00% RM 1,306,130.20 0%
312 C2 - Bengkel Kursus Pendawaian Elektrik 282 days Thu 4/13/17 Fri 5/11/18 0.00% RM 746,172.00 0%
(Piling)
494 C3 - Bengkel Kursus Teknologi Kimpalan & 281 days Fri 4/28/17 Fri 5/25/18 0.00% RM 746,172.00 0%
Fabrikasi Logam (Piling)
676 C4 - Blok Transit (Piling) 264 days Tue 5/9/17 Fri 5/11/18 0.00% RM 1,031,586.60 0%
857 C5 - Surau 248 days Mon 2/6/17 Wed 1/17/18 0.00% RM 393,573.80 0%
995 C6 - Rumah Contoh 233 days Fri 3/17/17 Tue 2/6/18 0.00% RM 162,984.60 0%
1132 C7 - Pondok Pengawal 159 days Wed 4/26/17 Mon 12/4/17 0.00% RM 72,510.20 0%
1262 C8 - Inkubator (Piling) 229 days Fri 5/19/17 Wed 4/4/18 0.00% RM 368,580.80 0%
1431 C9 - Rumah Sampah 115 days Thu 6/1/17 Wed 11/8/17 0.00% RM 42,754.40 0%
1508 C10 - Pencawang Elektrik (Piling) 191 days Tue 5/30/17 Tue 2/20/18 0.00% RM 187,899.40 0%
1634 External Works 435 days Tue 10/18/16 Mon 6/18/18 18.31% 14.10% RM 2,638,942.00 11%
1635 Demolation, Site Preparation & 48 days Tue 10/18/16 Thu 12/22/16 100.00% 82.70% RM 450,078.00 78%
Earthworks
1636 Site Clearence 5 days Tue 10/18/16 Mon 10/24/16 100.00% 84.38% RM 27,592.20 88%
1637 Clearing all site 1 day Tue 10/18/16 Tue 10/18/16 100.00% 79.00% RM 14,092.20 79%
1638 Cutting down trees 4 days Wed 10/19/16 Mon 10/24/16 100.00% 90.00% RM 13,500.00 90%
1639 Demolition Work 20 days Tue 10/25/16 Mon 11/21/16 100.00% 99.97% RM 200,000.80 94%
1640 Demolish existing building 20 days Tue 10/25/16 Mon 11/21/16 100.00% 99.97% RM 200,000.80 94%
1641 Bengkel 1 1 day Tue 10/25/16 Tue 10/25/16 100.00% 100.00% RM 25,000.00 100%
1642 Bengkel 2 1 day Wed 10/26/16 Wed 10/26/16 100.00% 100.00% RM 57,450.00 100%
1643 Bengkel 3 1 day Thu 10/27/16 Thu 10/27/16 100.00% 100.00% RM 33,900.00 100%
1644 Garaj 1 day Fri 10/28/16 Fri 10/28/16 100.00% 100.00% RM 10,200.00 100%
1645 Pejabat 1 day Mon 10/31/16 Mon 10/31/16 100.00% 100.00% RM 42,000.00 100%
1646 Rumah Konkrit 1 day Tue 11/1/16 Tue 11/1/16 100.00% 100.00% RM 13,050.00 100%
1647 Rumah Papan 1 day Wed 11/2/16 Wed 11/2/16 100.00% 100.00% RM 20,850.00 100%
1648 Tandas 1 1 day Wed 11/2/16 Wed 11/2/16 100.00% 100.00% RM 3,300.00 100%
1649 Tandas 2 1 day Thu 11/3/16 Thu 11/3/16 100.00% 100.00% RM 1,500.00 100%
1650 Tangki Pembentung 1 day Fri 11/4/16 Fri 11/4/16 100.00% 100.00% RM 1,800.80 100%
1651 Drainage 1 day Mon 11/7/16 Mon 11/7/16 100.00% 80.00% RM 9,660.00 80%
1652 Cart Away The rubble and debris 10 days Tue 11/8/16 Mon 11/21/16 100.00% 90.00% (RM 18,710.00) 90%
1653 EarthWorks 14 days Tue 11/22/16 Fri 12/9/16 100.00% 90.60% RM 154,085.00 90%
1654 Excavate Top Soil 5 days Tue 11/22/16 Mon 11/28/16 100.00% 93.00% RM 95,600.00 93%
1655 Excavate Premix Surface 5 days Tue 11/29/16 Mon 12/5/16 100.00% 95.00% RM 28,800.00 95%
1656 Cut off and Fill 1 day Tue 12/6/16 Tue 12/6/16 100.00% 100.00% RM 4,275.00 100%
1657 Earth Fill 3 days Wed 12/7/16 Fri 12/9/16 100.00% 75.00% RM 25,410.00 75%
1658 Temporary Works 9 days Mon 12/12/16 Thu 12/22/16 100.00% 13.71% RM 68,400.00 16%
1659 Temporary Earth Drain 2 days Mon 12/12/16 Tue 12/13/16 100.00% 70.00% RM 13,400.00 70%

Page 1
Januari 2017
ID Task Task Name Duration Start Finish % Scheduled Complete Actual Progress % Cost 2016 2017 2018 2019
Mode H1 H2 H1 H2 H1 H2 H1
1660 Temporary Silt Trap 1 day Wed 12/14/16 Wed 12/14/16 100.00% 0.00% RM 15,000.00 0%
1661 Temporary Wash Through 3 days Thu 12/15/16 Mon 12/19/16 100.00% 0.00% RM 20,000.00 0%
1662 Temporary Interlocking Paver 3 days Tue 12/20/16 Thu 12/22/16 100.00% 0.00% RM 20,000.00 0%
1663 Stone Rubble Wall 31 days Fri 12/23/16 Fri 2/3/17 35.91% 0.00% RM 92,028.00 0%
1664 Excavate Trench 1 day Fri 12/23/16 Fri 12/23/16 100.00% 0.00% RM 1,125.00 0%
1665 Blinding Screed 1 day Mon 12/26/16 Mon 12/26/16 100.00% 0.00% RM 1,750.00 0%
1666 Formwork 3 days Tue 12/27/16 Thu 12/29/16 100.00% 0.00% RM 1,530.00 0%
1667 Steel Fabric Reinforcement 1 day Fri 12/30/16 Fri 12/30/16 100.00% 0.00% RM 2,128.00 0%
1668 Weep Hole 1 day Mon 1/2/17 Mon 1/2/17 100.00% 0.00% RM 14,490.00 0%
1669 Concreting 1 day Tue 1/3/17 Tue 1/3/17 100.00% 0.00% RM 12,028.00 0%
1670 Stone Wall 4 days Tue 1/24/17 Fri 1/27/17 0.00% 0.00% RM 52,500.00 0%
1671 Plastering 5 days Mon 1/30/17 Fri 2/3/17 0.00% 0.00% RM 6,477.00 0%
1672 Water Reticulation 50 days Tue 5/30/17 Mon 8/7/17 0.00% 0.00% RM 243,845.00 0%
1695 Sewerage 75 days Tue 8/8/17 Mon 11/20/17 0.00% 0.00% RM 224,228.00 0%
1730 Surface Water Drainage 98 days Tue 11/21/17 Thu 4/5/18 0.00% 0.00% RM 687,770.00 0%
1837 Roads 33 days Fri 4/6/18 Tue 5/22/18 0.00% 0.00% RM 738,645.00 0%
1864 Fencing & Gates 13 days Tue 5/22/18 Thu 6/7/18 0.00% 0.00% RM 154,340.00 0%
1870 Turfing 6 days Fri 6/8/18 Fri 6/15/18 0.00% 0.00% RM 28,008.00 0%
1873 Flag Poles 1 day Mon 6/18/18 Mon 6/18/18 0.00% 0.00% RM 20,000.00 0%
1874 Prime Cost Sum And Provisional Sum 375 days Mon 2/6/17 Fri 7/13/18 0.00% 0.00% RM 1,603,802.00 0%