Project No. : 506111-1923 Rev.

: 0

Document No. : DSCZ5-IC-ADB-000-001 Sheet : 1 of 4

Document title:

ADDENDUM TO INSTRUMENT DESIGN BASIS

0 04-Apr-18 - IMPLEMENTATION SVD SAP SAP

Rev. Issue Date PEM Status Issued for Prepared by Checked by Approved by

Project : Dariba Zinc Smelter Expansion Phase IV - 100 KTPA Expansion (234 to 334 KTPA)

Client : Hindustan Zinc Limited

PC1923003_R0
Aker Powergas Pvt. Ltd www.akersolutions.com

© 2017 Aker Solutions. No part of this document or the information it contains may be reproduced or
transmitted in any form or by any means without the permission of Aker Solutions .
Project No. : 506110-1923 Rev. : 0

Document No. : DSCZ5-IC-ADB-000-001 Sheet : 2 of 4

Document Title : ADDENDUM TO INSTRUMENT DESIGN BASIS

Amendment to Instrument Design basis

General – Wherever vendor is specified, same shall be read as Contractor.

2.0 SCOPE OF WORK

2.1 Scope of work is as given in following table:

DESCRIPTION E S I ER COM
Inputs for DCS Engineering (I/O list, Alarm set-point, Graphics V V V V V
etc.)

Abbreviations:

V : By EPC Contractor

5.0 GENERAL DESIGN CONSIDERATIONS

5.15 All instruments and control panels JBs etc. operating with 24V and above must be earthed.

6.0 GENERAL CONTROL PHILOSOPHY

Clause 6.1 is amended as follows:

In general, Local panel supplied by the Contractor is to be used for measurement and control of all the
process parameters. Relay logic panels are not acceptable. Only specific signals shall be repeated
(hardwired) to DCS. DCS is in Contractor’s scope of supply. Contractor shall develop engineering
documents (I/O list, Graphics, Logic’s and trip and alarm set-point) necessary for DCS engineering and
software configuration. Contractor supplied DCS shall also monitor Contractor supplied package PLCs as
well as FIM PLCs through serial links. Refer System architecture drawing..

7.0 GENERAL SPECIFICATIONS FOR INSTRUMENTATION

Vendor shall furnish list of local panels mentioning quantity and dimensions within 2 weeks of award
of contract.

Local panels envisaged in this package unit shall be as specified in clause 7.1 below. Vendor to
note that relay logic panels are not acceptable.

7.1.1 Construction Details

PC1923003_R0
Aker Powergas Pvt. Ltd www.akersolutions.com

© 2017 Aker Solutions. No part of this document or the information it contains may be reproduced or
transmitted in any form or by any means without the permission of Aker Solutions.
Project No. : 506110-1923 Rev. : 0

Document No. : DSCZ5-IC-ADB-000-001 Sheet : 3 of 4

Document Title : ADDENDUM TO INSTRUMENT DESIGN BASIS

f. Mounting : Floor mounted on 100 mm channel


frame (For Microprocessor or PLC
Based Panel)
Wall mounted Panel for Local operation
(via DCS / PLC in control room)

9.0 CONTROL VALVES

9.3 Accessories

9.3.2 I/P Converters And Positioners


Smart Positioners with integral I/P convertors shall be used to convert controller/manual loader
output signal of 4-20 mA to 0.2 to 1.0 bar (g) pneumatic signal for control valve Actuator. All control
valves shall be considered with pneumatic positioner with three gauges for supply, input and output
indications and one air filter regulator without output gauge mounted and tubed. For special cases,
volume boosters shall be considered for control valve positioners to get fast operation as per
process requirement.

9.3.3 Position Transmitters


Position transmitter shall be considered based on process requirements. Such transmitter shall be
generally electronic 2 wire type only with isolated 4 - 20 mA DC HART output. Zero and range
adjustments shall be provided; shall be integral to the Smart Positioner for control valves.

ANNEXURE-VI
LIST OF FORMATS

1) Modbus Format

Modbus Format will be provided during detail engineering stage.

PC1923003_R0
Aker Powergas Pvt. Ltd www.akersolutions.com

© 2017 Aker Solutions. No part of this document or the information it contains may be reproduced or
transmitted in any form or by any means without the permission of Aker Solutions.
Project No. : 506110-1923 Rev. : 0

Document No. : DSCZ5-IC-ADB-000-001 Sheet : 4 of 4

Document Title : ADDENDUM TO INSTRUMENT DESIGN BASIS

Addendum to Instrument Design basis

1. Surge protector shall be provided in all field transmitters for transient surge protection.
2. All field instrumentation shall be with IP 67 protection.

PC1923003_R0
Aker Powergas Pvt. Ltd www.akersolutions.com

© 2017 Aker Solutions. No part of this document or the information it contains may be reproduced or
transmitted in any form or by any means without the permission of Aker Solutions.