Вы находитесь на странице: 1из 56

BEST PRACTICE GUIDE

PRESSURE SYSTEMS
A response to risks identified on construction sites working with pressure systems

ENERGISED SYSTEMS

MOVING LONDON FORWARD


Best Practice Guide – Pressure Systems Page 1 of 54
EA501_H&S_LM
A best practice guide produced in collaboration between

Acknowledgements
The Pressure Systems Booklet has from the review will be published in an
been developed in collaboration with amended version. This document does
the above key industry stakeholders. not purport to include all the necessary
provisions of a contract. Users are
This booklet will be reviewed at
responsible for its correct application.
intervals, and any amendments arising

Best Practice Guide – Pressure Systems Page 1 of 54


Index
Introduction
Preface and Purpose 3
Best Practice Guide - Pressure Systems 3
Part A – Planning
Concrete Pumping and Spray Concrete Lining (SCL) 6
Jet Wash Operations 7
Single Sourcing Components 8
Part B – Competency / Training
Selection 12
Training 12
Best Practice - Sprayed Concrete Lining 16
Part C – Execution and Control
Concrete Pumping and Spray Concrete Lining 18
Pump Set-up 18
Concrete Delivery area 18
Receiving hopper and hopper guarding 19
Operational safety zone 19
Delivery Pipeline Set-up 19
Pipe Clamps 20
Pipeline Movement 21
End-hose 21
End-hose and reducer combination 21
During Pumping Operations 22
Hose-whip 22
Controls which reduces likelihood of hose-whip 23
Cleaning / Blowing Out 24
Pipeline 24
Best Practice Concrete - ‘Blow-out’ Chambers with Exclusion Zones 25
Best Practice - Protection of concrete flexi-hoses 27
Pressure Wash Operations 28
Jet Washing / Pressure washers 37
Part D - Inspection and Maintenance
Concrete Pumping 32
Concrete Pump Examination and testing 32
Concrete Pump Maintenance 33
Pipeline Components 33
Best Practice - High Pressure Hose Compensation Grouting 35
Best Practice - Safetrak Electronic Inspection 36
Appendices
A. Concrete Pumping Operation Check Sheet 40
B. Concrete pipe Blow Out Check Sheet 42
C. Cleaning Concrete Lines with Compressed Air 44
D. Jet Washing Operation Check Sheet 47
E. Examination Checklist for Concrete Pumps 49
F. Crossrail Vehicle Safety Kit 50
G. References 53

Best Practice Guide – Pressure Systems Page 2 of 54


Introduction
Preface • Operator error
The Crossrail project consists of multiple • Poor training/supervision.
work sites and contractors where The main hazards from pressure are:
exposure to pressurised systems and
stored energy release is significant. • Impact from the blast of an
This guide brings together information explosion or release of compressed
collected in response to risks identified liquid or gas under pressure
on Crossrail construction sites, to ensure • Impact from parts of equipment
pressurised systems are operated safely that fail or any flying debris
across the Crossrail project.
• Contact with the released liquid or
This document has been produced by gas, such as steam
consolidating the specialist knowledge
from the Crossrail Contractors, JVs, • Fire resulting from the escape of
supply chain and industry partners flammable liquids or gases.
identified on Page 2 of this document. This Best Practice Guide suggests
Purpose minimum requirements for the safe
use of pressure systems, provides
Pressure Systems are defined as: best practice, competency and training
1. A system comprising of one or guidance.
more pressure vessels of rigid
construction, any associated
Best Practice Guide—
pipework and protective devices Pressure Systems
2. The pipework with its protective This Best Practice Guide applies to all
devices to which a transportable personnel with an involvement with the
pressure receptacle is, or is intended procurement, operation and supervision
to be, connected of pressurised working systems and
stored energy release; the guide
3. A pipeline and its protective devices specifically covers the following types of
which contain or is liable to contain a Pressurised Systems: Concrete Pumping,
“relevant fluid”. Spray Concrete Lining (SCL), Grouting,
The principal causes of pressure-related Compressed Air and Jet/Pressure
incidents are: Washing.

• Poor design, installation and/or The aim of this document is to raise


maintenance of equipment awareness of the consequences of
working with pressurised and storage
• Inadequate repairs or modifications energy release systems and promote
to the equipment a safer working environment for all
• An unsafe system of work operatives working on Crossrail.

Best Practice Guide – Pressure Systems Page 3 of 54


This Best Practice Guide should be used
alongside:
• Pressure Equipment Regulations
1999 (PER)
• Pressure Systems Safety
Regulations 2000 (PSSR)
• Provision and use of Work
Equipment Regulations 1998
(PUWER)
• BS EN 12001:2012, Conveying,
spraying and placing machines
for concrete and mortar—Safety
requirements
• BS 8476:2007, Code of Practice for
Safe Use of Concrete Pumps 2012.

Best Practice Guide – Pressure Systems Page 4 of 54


Section A –
Planning

Best Practice Guide – Pressure Systems Page 5 of 54


Concrete Pumping and • Up to date, maintenance log books
Spray Concrete Lining (SCL) and parts catalogue are with the
pump and boom
Planning and preparation are essential
in order to ensure that concrete • Maintenance and repairs to the
pumping and sprayed concrete lining equipment are only carried out
is done safely. In order to maintain by competent, qualified and
awareness and ensure sufficient experienced personnel who have
resources are made available, it is been authorized to carry out the
recommended that regular planning work
meetings are held. At these meetings, • The couplings are suitable and of
consideration should be given to ensure a consistent type across the
that: system, of higher pressure rating
People than the pump, are complete with
a seal and safety pin and are clean
• The pump operator is competent, and undamaged
qualified and experienced
• The pipeline is fixed on both
• There is a sufficient number the horizontal and vertical runs
of competent, qualified and and that the brackets used are
experienced operatives, including adequate for the task, clean and
a competent person, present at all undamaged
times
Process
• Appropriate personal protective
equipment is worn and other • There is an understanding of events
relevant safety equipment is or circumstances that would require
available as necessary. the operation to be stopped

Plant • There is an agreed sequence of


steps to be carried out to ensure
• The concrete pump is suitable to complete and safe stoppage
complete the pour safely and within
the required time frame • There is an understanding of the
impact of stoppages on other
• The location of the pump is operations
suitable taking account of the
footprint of the pump, the ground • There is an understanding of the
conditions and the access / egress impact of other operations on the
requirements for delivery trucks pressure system

• A relevant, up to date operating • There has been an assessment


instruction manual is with both the of manual tasks that may cause
pump and the boom muscle/ ligament strains or other
injuries
• Relevant, up to date maintenance/
repair manuals are with the pump • There is safe access eliminating
trip, slip and fall hazards

Best Practice Guide – Pressure Systems Page 6 of 54


• All systems of work comply with • Implement an exclusion zone
electrical safety legislation around the operation with
sufficient safety signage to warn
• Whether enough operatives are
other operators
available, including a competent
person being present at all times • The work area around the
equipment should be clean and
• Events or circumstances that would
free of debris. Oil spillages result in
require the operation to be stopped
slippery floors and must be cleaned
• The pipeline is suitable to complete up immediately
the pour safely and within the
• Shield and bundle equipment
required time frame, the wall
hoses and cables so they do not
thickness is sufficient to withstand
obstruct the operator’s freedom
the maximum pressure that the
of movement. Refer to Section
pump can exert and the pipeline
D for further suggested control
must be clean and undamaged
measures.
• The end placing hoses are suitable
Personal Protective Equipment
to complete the pour safely
(PPE) Requirements:
and within the required time
frame—they are of higher pressure PPE should always be regarded as the
rating that the pump, clean and ‘last resort’, as it protects the operator
undamaged. without changing the level of hazard.
Always consider that other control
measures may be needed in addition
to PPE which could reduce the level of
protection needed from PPE. Standard
PPE for operators should include:
Eye/Face Protection:
• Safety Glasses/Goggles/Face shield
(EN 166 Class A or B). Goggles and
face shields should be suitable
to use with other PPE (helmets,
Jet Wash Operations hearing protection etc.).
Jet Wash operations have the potential i
to affect a large number of surrounding What do operators do when visibility is
reduced by splashes, mist or fog?
operations if not properly controlled.
The following considerations during Systems of work should consider how this
will be addressed.
planning will result in a safer working
environment for the operator and others Anti fogging googles/glasses are available,
but try different models first to find which
in the area: performs best for your condition.

Best Practice Guide – Pressure Systems Page 7 of 54


Waterproof Clothing Single Sourcing Components
• Waterproof safety boots (EN 345 Single sourcing of components offers
or EN ISO 20345) multiple benefits for an organisation,
• Waterproof gloves: Operators need these benefits include:
to ensure gloves are maintained • Reductions in product variation,
and in good condition to ensure
proper grip and personal hygiene • Streamlined training is possible
due to consistent product,
i • Reduced downtime and
Waterproof garments only protect the
operator from spray and flying debris. inefficiencies caused by
They do NOT deflect direct jet impact. interoperability issues.
With regards to safety of pressurised
• Warm Clothing: The risk of systems components, the procurement
finger blanching (due to reduced of complete product/component ranges
circulation of blood) increases from a single, reputable manufacturer/
at low temperatures. Operators supplier is highly recommended.
working outdoors in cold weather
The hazards inherent in pressurised
should have adequate protection
systems necessitates that all
• Safety helmet: (EN 397) or of components of the system are
higher standard if specified through compatible and securely fitted.
risk assessment
To ensure that single sourcing of
• Hearing protection: (as identified components provide adequate risk
by the Risk Assessment) to be control, the following additional checks
worn at all times. Ear defenders are recommended:
should not be worn over clothing
• Ensure that detailed and complete
or PPE likely to interfere with the
product requirements are defined
effectiveness of the defenders
and included in any purchase
• Respiratory Protection: if agreement
identified in the Risk Assessment
• The requirements must address
for the activity, which must
form, fit, and function
consider the possibility that the
activity may generate a water mist • It should also define delivery time
/ aerosol that contains harmful and packaging, including clear and
material. consistent labelling

Best Practice Guide – Pressure Systems Page 8 of 54


• Periodically inspect and test the product to ensure continuous compliance with
the requirements.
Always confirm specifications of supplied components. Be aware that equipment
could be supplied with metric connections when it is expected to have imperial
connections.

90O elbow with


metric dimension
across the collar
diamter of 148MM 148MM

148MM

Imperial hose Imperial hose clamp


clamp designed to to suit 148mm
accomodate d 1/2” diameter collar
imperial hose ends
with 148mm O/D 148MM

Rig “Drophose”,
with imperial collar
dimension. This hose
hangs veritcally from the
90o elbow. Pipework at
the rotary table

Best Practice Guide – Pressure Systems Page 9 of 54


Best Practice Guide – Pressure Systems Page 10 of 54
Section B –
Competency / Training

Best Practice Guide – Pressure Systems Page 11 of 53


The safe operation of pressurised Training
systems is heavily reliant on the
selection and training of operators to The Construction Plant Competence
ensure they are competent to not only Scheme (CPCS) provides a registration
carry out their respective operations, but card scheme acknowledged by industry
also to identify and react safely to any for those involved in plant operations
abnormalities in the standard operation by recognizing skills. Knowledge and
of equipment. understanding, competence and
qualifications. The scheme offers awards
in the following categories:
Selection
• A06 Concrete Pump = Truck
When selecting operators to work with
Mounted Boom—Note: LGV license
pressurised systems, ensure they are:
must be held
• Competent and over 18 years of age.
• A44 Concrete Pump Trailer Mounted
In some cases a higher standard
is required eg. for lorry-mounted • A72 Static Concrete Placing Boom
concrete pumps the recommended • A06 additional category award—
age is over 21 years if driving on the A44.
highway
• Physically and mentally fit, with i
particular regard to eyesight, hearing Training needs to be specific to the
equipment and task being undertaken.
and reflexes. Medical reviews to be
held at regular intervals and not Everyone must be familiar with who is
authorised to operate various equipment.
exceeding 5 years between intervals
• Able to judge distances, heights and
clearances
• Adequately trained and certified
for the class of equipment being
operated with sufficient knowledge
of any relevant machinery and
safety devices
• Fully conversant with the duties of
the signaler and should understand
the signals code.

Best Practice Guide – Pressure Systems Page 12 of 54


This Section lists training resources available through Crossrail as
well as training available from outside sources. Most equipment hire
companies provide specialist training for their equipment and can be
contacted directly for arrangements, examples provided here.

Title: Sprayed Concrete Lining (SCL) Training and Assessment


Location: TUCA Ilford, London E12 5LN.
Content: Training with regards to Health and Safety, Equipment
and Spraying, assessments will be done through practical
assessments, observation, discussion and questions.
Who is this Training is intended for experienced and semi-experienced
training for: nozzlemen, who require up-skilling on the use and application
of spray concrete equipment.
Entry SCL experience is mandatory for this programme. Delegates
Requirements: need to hold a current CSCS card.
Duration: 5 days.
Contact: 0300 456 7424.

Best Practice Guide – Pressure Systems Page 13 of 54


Title: Trailer Mounted Concrete Pump/Pressurised Systems
Location: TUCA Ilford, London E12 5LN.
Content: Concrete pumping accidents, concrete pump operational safety
checks, communication, pumping concrete-priming the line, key
issues pumping concrete, problem solving, blockage essential
actions, pump maintenance, safety reminders, Control of
Substances Hazardous to Health.
Who is this Training for those who hold a CPCS Blue Card but have not used
training for: pressurised systems in the last six months, or other operatives
deemed to need refresher training by their employer.
Entry Must be able to demonstrate a background knowledge of
Requirements: pressurised concrete pump systems.
Duration: 2 days refresher + 1 day test.
Contact: Steve Howard 07825 377 036 steven.howard@citb.co.uk
or National Construction College 0344 994 4455.

Title: Safe Use of Low Pressure Washers


Location: Arranged on site.
Content: Pressure Washer Description, Legal requirements and
responsibilities, nature of hazards and identification of causes,
identifying the risks, safe and correct use, Selection of correct
machinery and PPE, Wash down bays, essential maintenance,
Practical assessment.
Who is this This programme is designed for any person who may
training for: be required to use any low pressure jet washer with a
pressure rating below 5000 psi in the workplace or requires
familiarisation with the associated regulations.
Entry Delegates attending this course should be 18+ years and be
Requirements: physically and mentally fit to withstand the rigours of training.
Duration: 2 days refresher + 1 day test.
Contact: 0845 604 6682 / speedy.training@speedyservices.com /
www.speedyservices.com/training.

Best Practice Guide – Pressure Systems Page 14 of 54


Title: Water Jetting Safety Awareness
(WJ Association Approved Course)
Location: Arranged on site or various training centres (eg. Dartford).
Content: To provide practical training in the safe, effective use of jetting
equipment and the supervision of jetting equipment and
operations.
• Identification of potential hazards
• Setting up equipment with regard to the safety of
operators, other staff and the public
• Hands on experience using equipment effectively and
safely
• Immediate procedures to adopt in the event of injury by
the impact of a water jet
• Nozzle selection with regard to the correct application
• Precautions to be taken when using a mains water supply
• How to identify and set up a safe system of work when
jetting as required by the Health and Safety at Work Act
1974
• Selection of the appropriate Personal Protective Equipment
with regard to the P.P.E. Regulations 1992
• Knowledge of the Sewer Jetting Code of Practice as
published by the WRc, June 1997
• Knowledge of the Code of Practice as published by the
Water Jetting Association
• The content of this course is approved by the Water Jetting
Association.
Who is this Those involved in, or about to become involved in, the use
training for: and supervision of high pressure water jetting equipment for
cleaning drains, sewers, pipes, culverts, tanks and manholes.
Entry Participants should bring with them a safety helmet, face visor
Requirements: to BS2092 Grade 1, ear defenders, a waterproof suit, safety
wellingtons and waterproof gloves.
Duration: 1 day.
Contact: Total Protection (UK) Limited / Tel: 0844 567 7423 / info@
totalprotectionuk.com / www.totalprotectionuk.com.

Best Practice Guide – Pressure Systems Page 15 of 54


Best Practice
Sprayed Concrete Lining
A logbook has been designed to record
and monitor the progress of trainees
during their formative / initial tenure
on the project. The logbook will provide
documented evidence of progress and
achievement and includes:



Personal Details
Training & Qualifications
Medicals and Occupational


ü
SCL Operations
Major Projects information.
On completion of SCL works the logbooks
will be issued to the operatives as
evidence of competence and experience.
The Logbook will undoubtedly provide
future employers with credible details
of competence and performance. The
logbook can also be used in the pursuit of
construction NVQ’s.
Health Monitoring
CRL1-XRL-Z7-AAG-CR001-50001

Best Practice Guide – Pressure Systems Page 16 of 54


Section C –
Execution and Control

Best Practice Guide – Pressure Systems Page 17 of 54


Concrete Pumping and pumping operation, should be in the
Spray Concrete Lining operational safety zone during concrete
pumping.
Concrete in pumps and/or pipelines
is often under considerable pressure Concrete Delivery area
and failure of pipeline can result in The concrete truck delivery area,
significant damage or injury. A concrete including the area around the pump
pump may give up to 85 bar pressure hopper, should be set up to ensure that:
into the pipeline whereas a compressor
will give 7 or 8 bar. Also the pump has a • Workers are safe from other
pulsing effect whereas the compressor vehicles
will apply the pressure more evenly. • Adequate lighting is provided if
Pump Set-up pumping in non-daylight hours

The concrete pumping area should be • Appropriate signage is posted


level, solid and free of obstructions, • There is clear access for delivery
with careful attention paid to the trucks.
positioning of the pumping equipment
and any stabilising devices. In particular,
the area should be:
• Clear of excavations, trenches or
holes in the ground
• Clear of inadequately compacted or
soft ground
• Clear of cellars, basements, pits or Keep clear when truck is reversing into position -
back-filled ground, unless stability don’t stand between the truck and hopper.
is approved in writing by a qualified
engineer
• Clear of overhead power lines and
fixed electrical equipment
• Of a size enough to allow for safe
operation
• Of a size enough to allow for the
safe discharge from the concrete Keep clear when truck is reversing into position -
delivery trucks. ensure that you remain in the driver’s view.
Where the pumping or pipeline set-up If multiple concrete deliveries
is for a longer duration, the isolation are expected and on-site traffic
methods should be made more management is not provided, only one
permanent. No person, other than those delivery truck should approach and
workers directly involved in the concrete discharge into the hopper at a time.

Best Practice Guide – Pressure Systems Page 18 of 54


If a designated on-site traffic controller be used. The use of one or more of the
is provided, the following safety rules following controls is recommended:
should be followed:
• Barricades
• All personnel connected with
• Posts and safety mesh
discharging from concrete trucks
are to wear appropriate high- • Posts and danger tape or flags
visibility safety vests
• Covered walkways
• All concrete delivery trucks must
• The traffic controller and truck
have operational reversing beepers.
driver should be in positions which
All vehicles entering Crossrail are prevent them from being caught
subject to requirements detailed in between the hopper and a reversing
the Crossrail Vehicle Safety Kit (see truck
Appendix F).
• The traffic controller should be in
Receiving hopper a position visible to the reversing
and hopper guarding driver and where the hopper area
can be observed
The concrete pump should be positioned
so the receiving hopper is at a height • Delivery drivers should ensure that
that allows a gravity flow of concrete their vehicles remain clear of the
from the pre-mix delivery trucks into discharge area until signaled to
the hopper. reverse into position by the traffic
controller.
The concrete pump should not be
operated unless the hopper is equipped Delivery Pipeline Set-up
with a grille with a fitted and working When installing a pipeline, ensure that:
safety interlock. The grille should:
• All specifications contained in
• Be constructed of parallel or mesh BS EN 12001:2012, Section 5.3,
bars are adhered to, particularly with
• Be designed to prevent access to regards to factors of safety when
the moving parts in the hopper considering maximum delivery
pressure
• Be designed so it requires a tool to
be removed • The safe working pressure of the
pipeline is equal to or greater
• Not, under any circumstances, be than the rated maximum concrete
used to stand on. pressure of all pumps to be used
Operational safety zone • All pipes and pipeline components
Access to areas around the concrete are identified and inspected before
pump and delivery pipeline should installation
be restricted - the most appropriate • The pipeline is set up along the
method of isolating the area should shortest possible route

Best Practice Guide – Pressure Systems Page 19 of 54


• The pipeline is set up using as few and rated at a working pressure greater
bends as is possible than the maximum deliverypressure
specified above. All pipe clamps used on
• Hoses are only used to distribute
any pipeline system must be:
the concrete at the end of a line,
never used in the middle of a • Able to sustain the maximum
pipeline and/ or as an alternative to concrete pressure applied to the
a bend pipeline by the pump
• A safety pin should be used to • Regularly inspected by a competent
secure each and every coupling person for signs of wear or fatigue
• Each section of the pipeline is • Immediately replaced if deformed
adequately supported and secured or damaged.
to the structure
Clamps should also be permanently
• The pipeline should not be secured marked with the manufacturer’s name
to a cranes or hoist towers, (or trademark), and the maximum
scaffolding or framework unless permissible operating pressure.
the bottom or footed bend (or bend
When using quick-release pipe clamps
cast into a ballast block) is used
on fixed lines (horizontal or vertical),
when the pipeline changes from
ensure that:
horizontal to the vertical.
• The pipe clamps used are able to
sustain the maximum concrete
pressure
• Locking pins are used and are
engaged
• Pipe clamps are regularly inspected
for signs of wear by a competent
person
• Clamps showing any deformation
or damage are replaced before
pumping begins
• Safety pins are fitted to all clamps.
Clamps which
do not allow for
safety pins to
be fitted should
Securely fix the pipeline to avoid movement.
be removed
prior to pumping
Pipe Clamps
operations
Clamps connecting concrete piping need
to be of the correct size, maintained

Best Practice Guide – Pressure Systems Page 20 of 54


• Clamps are locked as per the End-hose
manufacturer’s instructions.
Using a hammer or other means The rubber delivery end-hose should:
to force a clamp closed can cause • Where connected to a boom, be
unnecessary wear and result in secured by a safety chain, sling or
failure of components. other restraining device and not be
All pipeline connections from the boom longer than specified by the pump
must be secured by safety chains or manufacturer
wire strops (whip-check devices) to • Be inspected for excessive wear or
prevent the pipeline falling to the damage prior to being fitted and on
ground if a clamp fails. a regular basis
• Be single ended, in the case of the
final hose/ end placing hose.
If concrete pumping has stopped and
the hose is maneuvered over a work
or public area, the operator must use
the hose shut off valve, if fitted, to
prevent concrete falling from the hose
outlet. If such a valve is not fitted, the
boom should not be moved until all of
Pipeline Movement the excess concrete has fallen from the
boom and hose under gravity and the
The pipeline should be adequately
path the boom must travel is clear of
secured to the building or structure,
people.
with attention given to the reaction
forces generated where high pump End-hose and
pressures are involved. The mounting reducer combination
system should be designed to ensure
the pipeline remains in place. If the delivery end-hose is replaced by
a hose and reducer combination, only
Support brackets in a vertical pipeline those combinations assembled to the
should be spaced no more than three manufacturer’s instructions should be
meters apart. Expansion anchors of used, and:
the high-load slip control type or other
fixing methods of at least the same • Locking pins are to be engaged on
structural strength should be used if all quick-release pipe clamps in the
fixed to masonry. assembly
The surging action of the pump should • Each piece must be capable of
not cause excessive pipe movement. If withstanding the rated maximum
required, additional anchor brackets or pressure of the pump
other suitable methods to restrict pipe • Each hanging piece is tethered by
movement should be used. a safety cable, sling or chain

Best Practice Guide – Pressure Systems Page 21 of 54


• Be able to carry out daily
maintenance tasks (greasing,
topping up fluids, inspections etc.)

End-hose and reducer with safety slings.


• Carry out a visual inspection of the
pump and pipeline prior to each and
• The combined weight of all pieces every pour
MUST NOT EXCEED manufacturer’s
recommendations. • Be located at the pump controls or,
if using a remote control, have a
During Pumping Operations clear view of either the hose-hand
or the hopper
To safely operate any type of concrete
pumping equipment, it is necessary • Follow the directions of the
to have enough workers to control the hose-hand
pumping operation. These workers
• If using hand signals and out
need to be trained and experienced in
of view of the hose-hand, be
conducting pumping operations.
assisted by another worker to relay
The effective passing of directions from directions
the hose-hand to the pump operator
• Report problems with the pump/
is essential for safe concrete pumping.
pipeline to the pumping supervisor
The following examples may be used:
without delay
Effective communication between the
• Stop pumping, in the event od
hose-hand and the pump operator Is
a serious problem and do not
essential for safe concrete pumping.
re-commence pumping till the
The following examples may be used:
problems have been remedied
• Non-verbal: a set of standard
• Record daily inspections, defects
hand signals which cover all of the
and repairs in the logbook.
pump’s operational functions
Pump operators must not:
• Verbal: standard operational
phrases that may be delivered by a • Leave the pump/ remote control
dedicated two-way radio system. box unattended whilst the pump is
turned on
Regardless of the system used for
communication, signals need to be • Adjust the hydraulic pressure of
agreed by the pump operator and the pump
hose-hand.
• Pump concrete unless the hopper
Pump operators must: guard is in the closed position
• Be competent, qualified and • Stand or allow any other person
experienced to stand on the hopper grille or
beneath the raised boom.
• Be familiar with the pump’s
instruction manuals

Best Practice Guide – Pressure Systems Page 22 of 54


Hose-whip of the pumping cylinders—this can
introduce air into the line
Hose-whip occurs when pressure
in the pipeline is released rapidly • Do not allow the hoses to kink
causing the end placing hoses to whip • Ensure that the delivery hoses are
unmanageably. When a hose-whip clean and undamaged before each
occurs, the hose can strike those in the and every pour.
danger zone violently and can cause
severe injury. Controls that can reduce the danger of
injury due to hose-whip
Controls which reduces
• Use single ended hoses for the final
likelihood of hose-whip hose/ ending placing hose
• Ensure that the concrete pump
• Ensure that all operatives are
operator is competent, qualified
clear of the danger zone when the
and experienced
pipeline is being grouted up and
• Ensure that the concreting at the beginning of a fresh load of
operatives are competent, concrete is being pumped through.
qualified, experienced and aware
Other controls that can reduce the
of the risks and dangers associated
danger of injury while working with
with pressurized hoses
concrete delivery pipelines
• Ensure good communication
• The length of the end hose of a
between the pump operator and
placing boom must not exceed the
the hose-man
manufacturers recommendation
• Use the correct quality and quality
• The hose-hand should stand on
of grout when grouting up
a flat surface and not walls or
• Reject any concrete that is out underground structures edges
of specification/un-pumpable
• The end hose of the boom pump
especially that which is too lean,
should hang vertically, be guided
too stiff, or has been in the mixer
and not forced
for too long
• Where possible, avoid working
• The hose should not be stretched if
directly beneath the placing boom
it cannot reach the pouring location
by guiding the hose from the side
• Do not allow concrete to stand in
• When the pump is stopped, close
the delivery pipeline for too long.
the hose shut off-valve and allow
If necessary, clean out the line, re-
any extra concrete in the hose to
grout re-commence the pumping
fall before moving the boom
operation
• Keep personnel/ members of the
• Do not allow the concrete level in
public clear of the concrete pump
the hopper to drop below the level
pour area

Best Practice Guide – Pressure Systems Page 23 of 54


• Maintain good housekeeping • The blow-out adapter used should
around the pour site to minimize be fitted with an air entry port, a
tripping hazards. large air discharge port, a pressure
gauge and a non return device to
Cleaning / Blowing Out prevent the sponge balls returning
Cleaning out residual concrete from under pressure and blocking the
pumping equipment should only be discharge port
carried out by competent, qualified, • A ball catcher should be attached to
experienced workers in accordance with the discharge end of the pipeline
the manufacturer’s procedures or the
detailed written instructions developed • All workers must stand clear of
by a competent person. When concrete the discharge end while the line is
pumping equipment is being cleaned being cleaned
out, ensure that another person is in • No attempt should be made to split
the immediate vicinity to provide help in or dismantle the pipeline while it is
an emergency. still under pressure.
Pipeline If compressed air is used to clean the
Concrete delivery lines can be cleaned pipeline, the air entry point to the
out after a pour by pumping water pipeline is to be fitted with:
through the line. Short lines and • A large diameter discharge air ball
pipelines in sensitive areas (adjacent valve, to allow de-pressurization
to areas of public access, alongside live (venting) of the line before removal
railway lines, roads etc.) are cleaned
out manually. Longer lines and fixed • A smaller air entry ball valve
lines are usually cleaned out using • A pressure gauge, to show the air
compressed air. pressure in the pipeline.
On some contracts, longer lines are
cleaned out by pumping water through Refer to:
the pipeline but this requires specialist Appendix A: Concrete Pumping
equipment and is therefore not so Operation Check Sheet.
common. Appendix B: Concrete Pipe Blow Out
When cleaning out pipelines using Check Sheet
compressed air, the following safety Appendix C: Cleaning Concrete Lines
precautions should be observed: with Compressed Air
• All hoses should be removed from
the pipeline

Best Practice Guide – Pressure Systems Page 24 of 54


Best Practice
Concrete ‘Blow-out’ Chambers with Exclusion Zones
Concrete pipeline clean-out operations
commonly involve the insertion of
ball(s) that are driven through the line
using compressed air. A ball catcher
that allows the waste concrete to pass
through it catches the sponge ball when
the line is clean. Control of the volume
of air in the line is required to prevent
the potentially dangerous explosive
releases of concrete and the cleaning
ü
After the operation, the chamber can be
disconnected and lifted away. Then the
waste concrete is then allowed to set,
prior to broken up and removed from
site.
Other designs in use on Crossrail are
shown below:

Chamber connected to
balls into the ball catchers. pipeline for blow-out

C512 has developed a bespoke chamber


to control concrete blow-out during
pipeline cleaning at Whitechapel.
This chamber controls concrete blow-
out and allows waste to flow out from
its open base, in this way, the risk of
injury from the release of concrete and/ Chamber has open bottom and is propped
or sponge balls is minimised. up to allow concrete to flow out

Inlet with ball catcher (4”)


GO GO

5”

Best Practice Guide – Pressure Systems Page 25 of 54


**** The top photo shows the pipeline
connected to the discharge chamber
by placing a hose. All hoses should be
removed from the line prior to blowing
it out. setting up a cleaning line follows:
• Set up the main pumping line with
a 1m pipe in the line close to the
pump
• Remove the 1m pipe and replace it
with a bend pointing towards the
discharge chamber
• Set up the cleaning out line from
the bend to the discharge chamber
using all steel pipes and bend—as
few bends as possible
• Connect the cleaning out line to the
discharge chamber
• Secure the cleaning out line
especially close to the discharge
chamber
• When all of this is in place, remove
the bend that diverts the pipeline
to the cleaning out line and replace
the 1m pipe
• It is ready to pump
• After the pumping operation has
been completed, remove the 1m
pipe and replace the bend to divert
to the cleaning line
• Clean the line using compressed
air back to the discharge chamber
(This assumes cleaning back
towards the pump).

Best Practice Guide – Pressure Systems Page 26 of 54


Best Practice
Protection of concrete flexi-hoses
The mechanical pressing-in of the
hose by external forces is the most
frequent cause for premature wearing
of concrete pump hoses. This is what
happens to the concrete pump hose if
a heavy machine drives over it. Another
frequent cause of damage is the hose
rubbing against a sharp steel edge
when flexing during pumping concrete.
ü
The concrete delivery hose contains a
reinforcing layer of steel fibres, similar
to a car tyre. Once the external rubber
skin of the hose has been damaged,
moisture and oxygen come into contact
with the reinforcing steel fabric which
reduces the lifespan of the hose.
To protect the delivery hose, the
following is recommended:

• An additional layer protection. Whilst double-bagging is effective, it prevents


easy inspection of the hose. An alternative is shown on the right which allows for
visual inspection of the hose

Flexi-hose preotection Double-bagging of hoses

• Protection of hoses from site traffic. Some examples of how this might be done
are shown below. The aim should be to prevent of contact between vehicle traffic
and the delivery hoses thus minimising risk of damage.

Best Practice Guide – Pressure Systems Page 27 of 54


Pressure Wash Operations • Jet washing can generate a large
amount of noise. A Noise Risk
Pressure washers are used to clean Assessment is required to identify
equipment, materials and work areas the actions required to comply
on the job. Using such equipment with the Control of Noise at Work
often presents the perception that the Regulations 2005.
associated work is low risk when in fact
can cause serious injuries. Because the Key Control Measures
water used in jet washing operations
• Pressure washers must only be
is under high pressure, it moves with
used by suitably trained, competent
enough force to cause damage to the
and authorised persons
eyes or skin and contribute to other
types of injuries. • Manufacturer’s safety information
must be available and briefed to
Jet Wash Operations should only
operatives
be undertaken following a Risk
Assessment of all the tasks where it • Pressure washers should only be
can be clearly demonstrated that there used for the purpose intended, not
is no increase of risk to the operator for cleaning PPE
and/or third parties.
• Residual
pressure
i must always
Ensure welfare facilities are provided
to be used to wash / clean up after be released
work activities from all
washer units
after use
Hazards
• Confirm that lance safety catch is in
• The fast, strong spray can throw position before starting and when
objects, striking and injuring others putting down lance
who are close by
• Start engine
• The strong spray from a pressure and, if
washer can cause serious wounds adjustable,
that might first appear minor. set desired
Wounds that appear minor can pressure.
cause a person to delay treatment, Do not point
increasing risk of infection, lance at anyone, or yourself
disability or amputation
• Hold lance with two hands to
• Electric shock can occur if the ensure control and maintain
pressure washer is not used balance
properly and if safety instructions
• To avoid back blast of debris, pull
are not followed
trigger some distance back from

Best Practice Guide – Pressure Systems Page 28 of 54


point required and move it in slowly • Take care with hoses to avoid trip
hazards
• Set up exclusion zones or
segregation of work area with • Refer to Page 30 for Jet Wash Risk
suitable Categories and recommended
warning signs controls.
prominently
Refer to:
displayed.
Ensure other Appendix D: Jet Washing Operation
operatives Check Sheet example
are properly
briefed on
jet wash
operations
• Avoid/eliminate potential
distractions for jet wash operators
in vicinity of works

Best Practice Guide – Pressure Systems Page 29 of 54


Jet Wash Risk Categories
and Recommended Controls

Risk Category Operating Pressure Controls


Low Up to 1500psi Standard PPE,
(100bar) Segregation of area,
Awareness training, risk assessment briefing,
Pre-use checks.
Medium 1501psi - 3000psi Same as above, with additional:
Exclusion zone (“Authorised personnel only”),
Safety Footwear (EN 345 or EN ISO 20345)
Accredited one-day safety awareness course.
High 3001 - 20000 As above, with additional:
Permit to work required,
Exclusion zone
(“No entry, permit to work area”),
Specialist footwear, gloves and clothing.
Very high 20001psi + As above, with additional:
Re-assessment of task and controls,
Supervision (“ top-man” concept),
Re-assessment of PPE,
Specialist training/competence.

i
Potential damage caused by jet washers
decreases significantly the further
way items are from nozzle. Newer jet
washers have a safety feature: a safety
cone around the nozzle which ensures
a minimum distance is kept from the
object being sprayed.

Best Practice Guide – Pressure Systems Page 30 of 54


Section D –
Inspection and Maintenance

Best Practice Guide – Pressure Systems Page 31 of 54


Concrete Pumping • Following substantial alteration
or repair.
Provision and Use of Work Equipment
Regulations 1998 (PUWER) require The manufacturer of the machine or
that work equipment is maintained in the competent person appointed to
an efficient state, in efficient working examine it may specify a more frequent
order in good repair and any machinery examination period because of the
has a maintenance log, the log is kept machine’s age, its condition or its
up to date. operating conditions, etc.

Concrete Pump The thorough examination should be


completed by a competent person
Examination and testing
who has the necessary knowledge and
Careful consideration should be given experience to carry out that duty.
to the condition of the site where the
In certain conditions, for example after
test is to be conducted. It should be
substantial repairs to the boom, the
remembered that the recommendations
competent person who examines the
provided in the operating instructions
machine may specify the requirement
for the machine relate to operations
for a load test to demonstrate that it
within the safe working load and that
is stable and / or structurally sound.
more stringent requirements apply
Load testing of a concrete-placer boom
when loads are being applied for the
should only be carried out under the
purpose of testing.
direction and close supervision of a
A concrete-placer boom is not an competent person.
item of lifting equipment as defined
A certificate of test and thorough
in the Lifting Operations and Lifting
examination should be issued following
Equipment Regulations 1998. The
each thorough examination; a copy
examination of concrete-placing booms
must be made available for viewing on
is specified in BS EN 12001.
the machine. The test certificate should
Inspections should be completed by state the maximum safe working load
the concrete pump operator, or another of the boom.
competent person, on a weekly basis at
The test certificate should be endorsed
least and by mechanical staff carrying
with the information necessary to
out routine services. A written record of
ensure that there is no ambiguity as
the inspections must be retained and be
to the configuration of the machine
available at all times for examination.
during the test. Certificates of test and
A concrete-placing boom should be thorough examination may be stored
thoroughly examined: in any way appropriate to the owner
• Every 500 operating hours or of the machine, i.e. in paper format,
20,000m3, whichever occurs first, electronically.
but The safe working load of the machine,
• At least once a year and i.e. the maximum length of delivery
hose full of concrete to be suspended

Best Practice Guide – Pressure Systems Page 32 of 54


from the boom, should be clearly structure should be recorded on
marked on the machine and shown on maintenance checklists and handed to
the certificates of test and thorough a manager immediately.
examination.
Defects of a minor, non-safety
Any other conditions, e.g. the related, nature should be recorded on
deployment of stabilisers, must be maintenance checklists. They should be
noted on the certificate. recorded weekly until the defects have
been repaired.
Following the thorough examination,
a record of the examination should be A programme of servicing the chassis,
retained for a period of at least three the boom and its supporting structure
years to prove a regular inspection and the concrete pump should be
regime. devised as a part of a preventative
maintenance system. The period
Refer to:
between services may be determined by
Appendix E: Examination Checklist for the manufacturer or the owner of the
Concrete Pumps. machine and may be based on mileage,
Concrete Pump Maintenance the number of hours worked or a period
of time.
As with all machinery, good
maintenance of a concrete pump is Pipeline Components
paramount to safety. Road safety and In addition to daily/weekly checks of
on-site safety must both be considered the pipeline components, additional
when planning a maintenance system. measures can be taken to ensure
A good defect reporting and repair potential failure is minimised.
system is also vital.
It is important to measure the wall
The concrete pump operator should thickness of concrete delivery pipeline
carry out regular inspections of the on a regular basis. Over time and with
machine to ensure that it is fit for use. use, the wall thickness of a concrete
For Road vehicles, maintenance and delivery pipe will reduce, being worn
inspection schedules should correspond away by the scouring effect of the
to those required by the Vehicle and pumped concrete. As the thickness of
Operator Services Agency (VOSA). the pipe reduces, so does its capacity
to contain pressure. If the pipes are
Any defect affecting vehicle safety allowed to wear excessively they can
in respect of Road Traffic Act burst causing the pressurized concrete
requirements must be reported to explode out and potentially injure
immediately to the maintenance site personnel and members of the
department. public. With testing and recording the
Any defect that, in the opinion of the thickness of pipeline walls at frequent
concrete pump operator would affect intervals, excessive wear and potential
the safe operation of the concrete- failure of the pipeline can be avoided.
placer boom and its supporting

Best Practice Guide – Pressure Systems Page 33 of 54


Wall Thickness Testing Pipeline Test Recording
Wall thickness testing can be conducted To assist operators to detect erroneous
by ultrasonic test instruments or other measurements, cross referencing to
suitable method. All testing must be previous wall thickness measurements
carried out by competent persons and during the testing process is essential.
test equipment calibrated according to A suggested method of recording this
the manufacturer’s requirements. information is to maintain a test sheet
over the life of each component
Any used components in storage
should be tested before being returned This record of pipe component testing
to service. may include:
Pipes must not be used if the • Component identification number
wall thickness is less than that or mark
recommended by the pipe manufacturer
• Minimum allowable wall thickness
for the maximum concrete pressure
of the pump. The suppliers of pipes • Dates of tests
for concrete pumps should provide
• Monthly measurement for each of
data on the minimum wall thickness
the test points.
for differing pump pressures. The safe
minimum wall thickness of single wall Non-Destructive Testing (NDT)
pipe is dependent on the grade of steel,
The presence of flaws in critical
the pipe diameter and the maximum
components (e.g. welding/joints in
working concrete pressure that can be
pipelines) may result in the integrity of
exerted by the pump.
such systems being compromised and
Ultrasonic Testing increase the likelihood of failure.
When using ultrasonic testers, it is Non-Destructive Testing (NDT) is the
essential to have the test instrument application of measurement techniques
calibrated for the material to be in order to identify damage and
tested before carrying out any tests. irregularities in materials.
This can be achieved by using a If done well, NDT can provide
piece of pipe material of a known useful information to assist in the
thickness to calibrate the instrument management of plant safety. However,
and by following the manufacturer’s if inappropriate NDT is applied or NDT
instructions. The test equipment is not applied correctly, then the results
should be maintained according to the are likely to give a false impression of
manufacturer’s requirements, which the integrity and safety of the plant.
may include regular factory calibration
and replacement of worn transducers. Hence, always seek professional
advice with regards to the need and
implementation of NDT.

Best Practice Guide – Pressure Systems Page 34 of 54


Best Practice
High Pressure Hose Compensation Grouting
Following a small number of cases
where ‘ballooning’ of compensation
grouting hoses occurred (Fig. 2), it was
found that de-bonding of the inner
skin and subsequent ‘kinking’ (that is
not visible from the outside) has led
to these failures. This is most likely
to occur at
either end of
the hose, but

ü
reinforcing bond between the inner
and outer skin (Fig. 3).
The benefits of this solution are:
• More rigid hose—less susceptible to
damage by kinking and separation
of inner hose.
Larger bond surface between inner
and outer hose reducing likelihood
of separation.
progressive
de-bonding • Stronger hose with a working
can allow pressure of 214bar.
the failure to
progress along
Fig.2 Internal the length of
‘ballooning’ failure the hose.
Following collaboration between
Crossrail, the hose supplier and
the manufacturer, a solution was
implemented which resulted in a hose
with a thicker and more integrated Fig.4 Old hose (left), and new hose (right) showing
‘castellated’ bonding with the outer skin

Best
Best Practice
Practice Guide
Guide –– Pressure
Pressure Systems
Systems Page
Page 35
35 of
of 54
54
Best Practice
Safetrak Electronic Inspection
Site teams working at Whitechapel
and Finsbury Circus identified a need to
improve the management of inspection
regimes for pipework used to pump
concrete.
The Safetrak Electronic Inspection
system was implemented to manage
and simplify equipment inspections
and reporting. The system uses mobile
ü
and produce high-level summaries of
inspection outcomes.
Assets can be tagged using a number
of methods, including bar codes,
serial numbering or Radio-frequency
Identification (RFID) tags, with tags
being chosen in response to specific site
conditions (ie. resilient to wear, water,
dirt, chemicals etc.)
computers, in conjunction with visual
tags, to report on the location, usage
and inspection status of pipework. For further details email
This data is then uploaded to a central customer.services@safetrak.com or
database. www.safetrak.com.
The system has additional benefits in
being able to provide asset registers,
schedule reminders for inspections

Best Practice Guide – Pressure Systems Page 36 of 54


Section  E:    Inspection  and  Maintenance    

JetW
Jet   Washing
ashing  /  P/ Pressure
ressure   washers
washers  
accordance with the manufacturer’s
-­‐  Page  1  of  2    
instructions. Records must be kept of
 Regular maintenance is essential
all maintenance and repair work carried
to ensure
Regular   the safe operation
maintenance   is   essential  of
to  jet
ensure   the   safe   operation   of   jet   washers.   This   must   be  
out. Please Records  
refer tomust  
sample inspection
carried  
washers. out  This
in   accordance  
must be carriedwith   the  
out manufacturer's  
in instructions.   be   kept   of   all  
and maintenance check list below.
maintenance  and  repair  work  carried  out.    Please  refer  to  sample  inspection  and  maintenance  
check  list  below.  
   

 
   

Best  Practice  Guide  —Pressure  Systems                                                                                                                                                                                                                                                                                                        

CRL1-­‐XRL-­‐O1-­‐GUI-­‐CRG03-­‐50001,  Rev  1               Page  36  of  50  

Best Practice Guide – Pressure Systems Page 37 of 54


Section  E:    Inspection  and  Maintenance    

   

Best  Practice  Guide  —Pressure  Systems                                                                                                                                                                                                                                                                                                        

CRL1-­‐XRL-­‐O1-­‐GUI-­‐CRG03-­‐50001,  Rev  1               Page  37  of  50  

 
Best Practice Guide – Pressure Systems Page 38 of 54
Section E –
Appendices

Best Practice Guide – Pressure Systems Page 39 of 54


Appendix A: Concrete Pumping Operation Check Sheet

Concrete Pumping Operation Check Sheet


Inspection Date:
Location of pour:
Inspector Name & Job Role:
Date of pour:
Tick confirmation
Concrete Pump operator trained and in possession of proof
Yes No N/A
Pump of competence
setup Concrete pump on level ground Yes No N/A
Load bearing capacity of ground sufficient for
Yes No N/A
pump
Outriggers, where fitted, are fully extended.
The outriggers must be fully extended unless short
Yes No N/A
rigging systems with boom restrictor is fitted by
the pump manufacturer and used
Delivery hopper is guarded by an interlock grille Yes No N/A
Safe access exists for delivery vehicles Yes No N/A
Pedestrians safe access is available
Concrete pump is clear of overhead obstruction
Wind Speed will not affect safe operation of the
placing boom
Has a system of signalling been agreed, i.e. hand
signals or radio
Pipeline All metal pipes and pipeline components are iden-
Checks tified. Checked and visually inspected for damage
prior to each and every pour.
Horizontal pipelines are adequately supported Yes No N/A
A bottom bend/ footed bend is used at the bottom
Yes No N/A
of a vertical pipeline
Unnecessary bends are avoided Yes No N/A
Vertical lines are positively secured to the building Yes No N/A
Flexible hoses are not at risk of being run over by
Yes No N/A
other plant or equipment

Best Practice Guide – Pressure Systems Page 40 of 54


Pipe The pipe clamps used are able to withstand the
Clamps & maximum concrete pressure applied to the pipeline Yes No N/A
Brackets by the pump.
Clamps are locked as per the manufacturer’s
Yes No N/A
instructions
The locking pins are used and are engaged Yes No N/A
All pipe clamps are regularly inspected by a
Yes No N/A
competent person for signs of wear and fatigue
Pipe clamps which show any deformation or
Yes No N/A
damage are immediately replaced
Anchor brackets and tie-downs are used to
adequately secure pipelines (2 brackets on the
top face of slab and 1 bracket on vertical face. A Yes No N/A
competent person to assess whether additional
brackets are required prior to pumping.
During Hopper grill with interlocked guard in place at all times
the pour Ensure the pump is turned off when not in use
Ensure PPE is worn at all times. Long sleeves worn at all times.
Splashes of concrete onto skin should be washed off as soon as possible with
soap and water.
Radio contact maintained between pump operator and other operatives at all
times
Blowing No pipeline connection or fitting should be disconnected unless it has been
Out / established that the pipeline is free of internal pressure.
Cleaning No pipeline is to be left unattended unless it has been confirmed that the
pipeline is free of internal pressure.
Only competent, qualified and experienced
Yes No N/A
operatives are to clean out the pipeline
A ball catcher must be used to catch the sponge
Yes No N/A
balls when the line is being cleaned out
All operatives must be briefed to keep clear from
Yes No N/A
the discharge end while cleaning is in progress
Refer to the Concrete Pipe Blow Out Check Sheet in Appendix B for more
detailed checks which need to be performed prior to every blowout operation

Best Practice Guide – Pressure Systems Page 41 of 54


Appendix  B:  Concrete  Pipe  Blow  Out  Check  Sheet    
Appendix B: Concrete Pipe Blow Out Check Sheet

    Site:       Date:        

Time:                              

Initials  of  Competent                              

Person:  

Drive:                              

    YES   NO   YES   NO   YES   NO   YES   NO   YES   NO   YES   NO   YES   NO   YES   NO  

Are  all  personnel  aware                                                                  


that  blow  out  is  about  to  
commence?  Are  there  
sufficient  competent,  
qualified  and  experienced  
operatives  to  clean  out  the  
pipeline  

Has  the  latest  pipe  line                                                                  


additions  been  checked?  
Has  the  blow  out  adapter  
been  checked  prior  to  the  
pour?  

With  blowing  end  -­‐  is  the                                                                  


cannon  in  good  working  
order?  Have  the  latest  
pipeline  additions  been  
checked  prior  to  the  pour?  

Are  ball  catching                                                                  


arrangements  in  place?  

Is  there  good                                                                  
communication  between  
the  blowing  end  and  the  
receiving  end?  Is  the  
pipeline  adequately  fixed  
and  secure?  

   

Best  Practice  Guide  —Pressure  Systems                                                                                                                                                                                                                                                                                                        

CRL1-­‐XRL-­‐O1-­‐GUI-­‐CRG03-­‐50001,  Rev  1               Page  41  of  50  

 
Best Practice Guide – Pressure Systems Page 42 of 54
Appendix  B:  Concrete  Pipe  Blow  Out  Check  Sheet    

Is  everyone  in  a  safe                                                                  


location  30m  from  the  
catcher?  Is  there  good  
communication  between  
the  blowing  end,  and  ball  
follower  and  the  receiving  
end?  

   
Are  all  personnel  aware  
that  blow  out  is  about  to  
commence?  

Is  everyone  in  a  safe                                                                  


location  30m  from  the  
catcher?  

   

 
   

Best  Practice  Guide  —Pressure  Systems                                                                                                                                                                                                                                                                                                        

CRL1-­‐XRL-­‐O1-­‐GUI-­‐CRG03-­‐50001,  Rev  1               Page  42  of  50  

Best Practice Guide – Pressure Systems Page 43 of 53


Appendix C: Briefing-Cleaning out Concrete Lines with Compressed Air
Briefing: Cleaning out Concrete • Confirm that a ball catcher has
Lines with Compressed Air been installed to the discharge end
of the pipeline and the pipeline is
Aim: To provide instruction, training secured adequately
and awareness to allow you to clean
out a concrete pipeline safely using • Inform the person controlling the
compressed air following concrete operation (this is the person with
pumping operations. the radio at the pump outlet) that
you are ready to blowout the lines
Briefing:
• Await instruction to proceed
• On completion of a pour/advance,
stop pumping, reverse the pump a • Ensure that the Blow Out Check
minimum of three strokes to relieve Sheet has been completed
the pressure in the line and then • Do not start until instructed to do
turn the pump off so by the person controlling the
• Check the pressure gauge on the operation underground.
pump is reading Zero Blow out pot adapter configuration.
• Only when this is compete should This configuration MUST be used
you start dismantling the concrete 3
/4” or 1” Air supply Valve
line connected to the pump, ready 2” Dump Valve
for cleaning out.
The cleaning out activity on the surface
must be controlled by the ‘senior’ pump
operator on the shift.
• Disconnect the concrete pump from
the pipeline Pressure Gauge
• Insert a wet hart sponge ball into
the open end of the pipeline • Concrete Pipe Blow Out
Check Sheet
• Re-check the blow out adapter to
ensure that the valves can open
and close properly and that the
pressure gauge is undamaged
• The blow out adapter to the open Ensure any
problems
end of the line with a good clean are corrected
coupling seal and insert the safety BEFORE
pin the blowout
operation
• Connect the airline, ensuring that
the whip checks are in place

Best Practice Guide – Pressure Systems Page 44 of 54


• The person who is operating the important to ensure that the dump
blow out adapter should not leave valve vents in a safe direction
the area for any reason whilst the
• A second flush can be made when
adapter is connected to the line
the line has been blown out by
• Ensure that there are visual blowing two sponge balls with a
communications at all times to slug of water between them
back-up the radio system
• Remember that concrete/ grout
• Before opening the air valve, build up in the lines can cause
ensure that the person controlling problems and potential dangers on
the blow-out underground has subsequent pours.
completed their checks and has
Fail-safe pressure release arrangement
moved everybody to a safe distance
(example at the rear of the compressor)
away from the blowout area
Pressure Gauge
• Once confirmation is received,
open the air valve to introduce
the air while monitoring the Air Supply Valve
pressure increasing on the gauge.
Maintain communication with the 22” Dump Valve
person controlling the blow-out
underground and inform them of
Procedure for ensuring that air pressure
progress
on completion:
• Do not leave the air supply valve
• Close the air supply valve on the
on all the time—introduce air
blow out adapter when instructed
progressively for 15 to 20 sec
to do so and/or when the red light
intervals. The pressure as shown
is displayed
on the gauge will fall when air is
turned off and the concrete moves • Open the dump valve on the blow-
ahead of the ball out adapter to vent any pressure in
the pipeline
• Repeat the above process until all
residual concrete/ grout is cleaned • Check that the gauge is reading
from the line zero.
• Pressure can be released at If there is any doubt as to whether or
any time during the process by not the pressure in the line has been
switching off the air supply valve fully released, take the following steps:
and opening the dump valve
• Close the air supply valve at the
• Be aware that if the line blocks compressor/receiver
and the air pressure is vented via
• Open the dump valve at the
the dump valve, some concrete
compressor/receiver
may also be expelled and so it is

Best Practice Guide – Pressure Systems Page 45 of 54


• Open the air supply valve on the Finally
blow out adaptor
• During the cleaning out operation
• Check that both gauges are reading the concrete lines will have a
zero. considerable amount of stored
energy!
This now ensures that the air pressure
is relieved in the concrete line and air Any uncontrolled release of this energy/
supply pipe. pressure is a serious safety hazard!
• If there is still any doubt, turn off
the compressor and dump the air
from the receiver
• Report any mechanical or
equipment issues immediately
to the Pit Boss or mechanical
department
• When you are certain that there
is no retained air pressure in the
concrete line, the blow adapter can
be uncoupled and removed from
the end of the pipe
• The blow-out adapter must be
cleaned thoroughly after each use
to prevent any grout build up in
valves and gauge and to ensure it is
fit for use each time it is used.
Check
• Before removing the blow-out
adapter at the end of blowing out,
make sure the air supply valve is
closed, the dump valve is open and
the gauge is reading zero.
• If an unsafe condition arises during
any stage of the operation you
must stop immediately!
Release the pressure and do not
restart until the unsafe condition has
been remedied.

Best Practice Guide – Pressure Systems Page 46 of 54


Appendix
Appendix   D:  D:
Jet  Jet Washing
Washing   Operation
Operation   Check
Check   Sheet  Sheet
 

Date:      

Location/Machine  Type:      

Inspector  Name  +  Job  Role:      

    Tick  
confirmationü   Comment  
Yes   No   N/A  

Is  the  work  area  clearly  defined  and  are  proper      


Yes   No   N/A  
warning  signs  posted  (exclusion  zone  if  needed)?  

Have  precautions  been  taken  to  protect  all  electrical      


Yes   No   N/A  
equipment  affected?  

Have  all  persons  working  in  surrounding  area  been      

informed  about  the  intention  to  carry  out  water   Yes   No   N/A  
jetting  operations?  

Are  hoses  and  lines  protected  from  accidental      


Yes   No   N/A  
damage  (vehicles,  other  operations  in  the  area)?  
   
Is  there  an  adequate  water  supply?   Yes   No   N/A  

Have  all  personnel  been  provided  with  the      

appropriate  PPE  for  this  job?.  Consider  people  in  the   Yes   No   N/A  

 
immediate  area  too.  

Have  all  personnel  received  the  proper  training  for      


Yes   No   N/A  
this  job?  

Have  all  personnel  using  the  equipment  been  briefed      


Yes   No   N/A  
and  do  they  know  how  to  use  the  equipment  safely?  

Is  the  location  of  emergency  medical  aid  known?   Yes   No   N/A      

Are  all  fittings  of  the  correct  pressure  rating?   Yes   No   N/A      

Are  all  hoses  of  the  correct  pressure  rating?   Yes   No   N/A      

Are  all  fittings  in  good  operating  condition?   Yes   No   N/A      

Are  all  hoses  in  good  operating  condition?   Yes   No   N/A      

Appendix   D:  Jet  Washing  Operation  Check  Sheet    


Are  HAVs  trigger  times  known  and  a  schedule  of      
Yes   No   N/A  
rotation  in  place  if  trigger  times  are  exceeded?  

Are  g    ood  washing  facilities  available  to  wash  hands      


Yes   No   N/A  
before  
  eating  or  drinking  
Is  the   area  
Best   clear  oGf  uide  
Practice   any  —obstacle  
Pressure  wShich   could  
ystems                                                                                                                                                                                                                                                                                          
             c    ause  
Yes   No   N/A  
slips,  trips  or  falls?  
CRL1-­‐XRL-­‐O1-­‐GUI-­‐CRG03-­‐50001,  Rev  1               Page  47  of  50  

 
 

Important  Notes:  
Best Practice
Wear  Guide
task  –specific  
PressurePPE  
Systems
at  all  times   Page 47 of 54
Important Notes:

Wear task specific PPE at all times

Wash hands before eating, drinking or smoking

Never use trigger-assist devices. Hand operation only.

Never try to clean PPE using pressure washers

Never point the jet at other people, regardless of distance

No line connection or fitting should be disconnected unless it has been


established that the line is free of internal pressure.

No line is to be left unattended unless it has been confirmed that the line
is free of internal pressure.

ü ü

Best Practice Guide – Pressure Systems Page 48 of 54


Appendix E: Examination Checklist for Concrete Pumps
A thorough examination should include • The mounting fixtures for the
as a minimum (where applicable): pump sub-frame and the boom
pedestal to the chassis
• A visual inspection of all sections of
the boom, its supporting structure, • The workings of levers and switches
securing devices and stabilisers on the remote control box(es)
• Non-destructive testing of the • The condition of the remote control
structure and welds when it box lead
is deemed necessary by the
• The workings of manual control
competent person
levers
• The opening up of concealed
• The operation of all emergency stop
or encased parts to the extent
controls
required by the competent person
• The clear marking of all controls
• Measurement of backlash / play in
the slewing system • The satisfactory operation of safety
switches, e.g. slewing limits
• Measurement of wear in the
slewing rack thrust pad • The operation of interlock systems,
e.g. on the receiving hopper
• Lift in the slewing ring
• The integrity of the receiving
• The integrity of the slewing ring
hopper grille
bolts
• The guarding of the concrete pump
• Measurement of wear in pins and
cylinders’ flushing box
bushes at the boom joints
• The guarding of the machine’s
• A check on the security of boom
prop-shaft
pins
• The condition of the machine steps
• The condition of boom pipe
and walkway
brackets
• The condition of the washing-out
• The presence of security pins in
adaptor and the sponge cleaning
pipe couplings on the boom pipeline
ball catching basket
• The condition of the boom tip
• Working lights
safety chain and its anchorage
• Appropriate warning signs
• The correct operation of lock valves
on the boom’s hydraulic rams • The manufacturer’s identification
plates.
• The stabiliser locking system for
both travelling and working

Best Practice Guide – Pressure Systems Page 49 of 54


Appendix F: Crossrail Vehicle Safety Kit

2015 DRIVER INDUCTION INFORMATION &


CROSSRAIL VEHICLE SAFETY KIT

Supplementary Guide
1 2

04/11/2015 15:56

MIRRORS AND Item Location

VISUAL AIDS Class IV Mirror* Front nearside

Class V Mirror* Front nearside


Applies for:
Small lorries 3.5 to 7.5 tonne Class VI Mirror* Front of cab
ü
ü Medium lorries >7.5 tonne
Rear view
Concrete mixer Mirror In Cab (if applicable)
ü
ü 2/3 Axle Rigid Fresnel Lens
or camera Near side window
ü Grab or skip lorry system (below)
ü 4 or multi axle tipper
Side Camera
Front mounted
ü Articulated Low Loaders System*
rear facing
(optional)
ü All other vehicles >7.5 tonne

12

EA487 Leaves Crossrail Safety Kit supplementary guide.indd 12 04/11/2015 15:54

Best Practice Guide – Pressure Systems Page 50 of 54


STICKERS, Item Location

SIGNS AND Cyclist

DECALS
warning sign Rear nearside

Pedestrian
Near side only
warning sign
Applies for:
Drugs & Alcohol
In the cab
ü Small lorries 3.5 to 7.5 tonne warning

ü Medium lorries >7.5 tonne


Seat belt
ü Concrete mixer In the cab
reminder

ü 2/3 Axle Rigid


DAILY INSPECTIONS Daily inspection In the cab
ü Grab or skip lorry MUST BE CARRIED OUT
reminder

ü 4 or multi axle tipper THE MAXIMUM LEGAL


CAPACITY OF THIS VEHICLE
Maximum
Passengers* In the cab
ü Articulated Low Loaders IS:-

ü All other vehicles >7.5 tonne


High visibiltity
Rear/Sides
markings

14 * Passenger carrying vehicles only e.g. minibus

EA487 Leaves Crossrail Safety Kit supplementary guide.indd 14 04/11/2015 15:54

LIGHTING AND Item Location

CAB INTERIOR Rear fog lights Rear of vehicle

Amber flashing
Beacon Top of cab
(All vehicles)

Applies for: Daytime


running lights Front of the vehicle
(or sidelights on)

ü Small lorries 3.5 to 7.5 tonne


Spare bulb kit Stored on the vehicle
ü Medium lorries >7.5 tonne
ü Concrete mixer
Warning Stored on the vehicle
ü 2/3 Axle Rigid triangle

ü Grab or skip lorry Fire Stored on the vehicle


extinguisher
ü 4 or multi axle tipper
ü Articulated Low Loaders Seat belts
Fitted to each seat
to be worn
ü All other vehicles >7.5 tonne
No additional
On any window
tinting

16

EA487 Leaves Crossrail Safety Kit supplementary guide.indd 16 04/11/2015 15:54

Best Practice Guide – Pressure Systems Page 51 of 54


OUTSIDE Item Location

THE VEHICLE Side scan Nearside step or


detection kit wheel arch area

Applies for: Side under


run guards Fitted both sides

ü Small lorries 3.5 to 7.5 tonne


Reversing
ü Medium lorries >7.5 tonne
alarm Rear of the vehicle
(can incorporate sensors
ü Concrete mixer and or a camera)

ü 2/3 Axle Rigid


External spoken
ü Grab or skip lorry Nearside of the vehicle
warning alert*
ü 4 or multi axle tipper
ü Articulated Low Loaders
Hi Vis Clothing Orange
ü All other vehicles >7.5 tonne (See Principle Contractor
site rules) Driver PPE

18

EA487 Leaves Crossrail Safety Kit supplementary guide.indd 18 04/11/2015 15:54

For further information contact: November 2015 DRIV


Crossrail Logistics
Traffic Coordination Centre
CROS
Tel: 020 3229 9885
pdptcc@crossrail.co.uk

Driver name:

Company:

Contact:

www.crossrail.co.uk

EA487
1

EA487 Cover Crossrail Safety Kit supplementary guide.indd 2

Best Practice Guide – Pressure Systems Page 52 of 54


Appendix G: References

Abbreviations

PPE Personal Protective Equipment

RFID Radio-Frequency Identification

SCL Sprayed Concrete Lining

TUCA Tunnelling and Underground Construction Academy

References

BS EN 12001 Conveying, spraying and placing machines for BS


concrete and mortar safety requirements.

Health and Safety at Work Act 1974 HASWA

Lifting operations and Lifting Equipment Regulations 1998 LOLER

Pressure Equipment Regulations 1999 PER

Pressure Systems Safety Regulations 2000 PSSR

Provision and use of Work Equipment Regulations 1998 PUWER

Road Traffic Act

Vehicle and Operator Services Agency VOSA

Best Practice Guide – Pressure Systems Page 53 of 54


Further sources of information
All of the documents listed in the ‘Reference documents’ section can be found at the
following sites which are also extremely useful for information on all other aspects of
site safety.

Health and Safety Executive www.hse.gov.uk

UK Government legislation www.legislation.gov.uk

Construction Industry Publications www.cip-books.com

Fire Protection Association www.thefpa.co.uk

RISCAuthority www.riscauthority.co.uk

Loss Prevention Certification Board (LPCB) www.bre.co.uk

Institution of Engineering & Technology (IET) www.theiet.org

British Standards Institution (BSI) www.bsigroup.co.uk

Phonetic alphabet
A Alpha J Juliet S Sierra

B Bravo K Kilo T Tango

C Charlie L Lima U Uniform

D Delta M Mike V Victor

E Echo N November W Whiskey

F Foxtrot O Oscar X X-ray

G Golf P Papa Y Yankee

H Hotel Q Quebec Z Zulu

I India R Romeo

Numerals should be spelled out, not given as whole numbers:


121 is ‘one-two-one’, NOT ‘one hundred and twenty one’.

Best Practice Guide – Pressure Systems Page 54 of 54


MOVING
HEALTH & SAFETY
FORWARD

Best Practice Guide – Pressure Systems Page 55 of 54

Вам также может понравиться