Академический Документы
Профессиональный Документы
Культура Документы
IJETSR
www.ijetsr.com
ISSN 2394 – 3386
Volume 4, Issue 10
October 2017
Aruna Mohan
Department of Infrastructure Engineering and Management,
Thiagarajar College of Engineering, Madurai, Tamil Nadu
ABSTRACT
Offshore projects are characterized as very complex projects, where uncertainty comes from various sources.
Offshore projects gather big number of stakeholders, which makes it difficult to control as a whole. Uncertainties are
magnified for offshore structures compared to on-land structures owing to the relative severity and unfamiliarity of the
ocean environment, the scarcity of data about loads and materials, and the expense of data-gathering.Offshore projects
are always unique and risks raises from a number of different sources. It has an inherited risk in all of the processes
starting from the conceptual phase of a project, engineering design, placing the bid and going through scheduling,
material procurement, construction, changing orders and ending with the commissioning, final payment and closing-up
of the project.Due to the undulations prevailing in Offshore projects there is high necessity of risk management in these
projects.
KEYWORDS – Risk management, Offshore construction, Risk identification
1.1 INTRODUCTION
Risk is defined as “the problem or issue which is expressed in the form of probability with its chance
of occurrence and the severity of the impact it can cause. It is used in many different ways and with many
different words, such as ‘‘hazard’’ or ‘‘uncertainty.’’ Every activity we do is, to a degree, characterized by the
presence of risk. It is the expression of the likelihood and impact of an uncertain, sudden and extreme event
that, if it occurs, has may impact positively (opportunity) or negatively (threat) on the achievement of a
project or program objective.
involving collection, compilation, analysis and summarization of results from questionnaire survey. This is
shown in figure 2.1
• LITERATUREREVIEW
2
• DESIGN OFQUESTIONNAIRE
3
• DATACOLLECTION
4
• DATACOMPILATION
5
• ANALYSIS OF COMPILEDDATA
6
• RESULT ANDSUMMARIZATION
7
• CONCLUSION
8
Red color represents Risk factors falling under Severe Risk Categories.
Yellow color represents Risk factors falling under Moderate Risk Categories.
Green color represents Risk factors falling under Low Risk Categories.
2.1.4.2 RISK CATEGORIZATION
In risk categorization eight types of risk was categorized on the basis of percentages of intensity of factors
affecting each type of risk.
Table 2.1.4.2: Risk Categorization Table
PERCENTAGE OF PERCENTAGE OF
S.No TYPES OF RISK SEVERE RISK MODERATE RISK
Architect- consultant Risk Factor and Project Manager Specific Risk Factor falls completely under Severe
Risk Category. Based on this analysis the above two Factors must be given Higher Importance. External
Environmental Specific Risk Factors and Finance Specific Risk Factors must be given Lesser Importance,
Since it has less percentage of severe risk factors.
From this comparative study 15 risks were shortlisted on the basis of common occurrence. These risk were
correlated with control charts in the analysis and their occupancy in upper control are and lower control area
This study discusses the risk factors affecting the offshore construction. It studies the importance of risk
factors based on their probability of occurrence and degree of impact. By the use of previous studies in risk
management 38 risk factors were identified and combined into 8 major groups relating to their sources. This
study is made by field survey through a structured questionnaire directed to the people working in offshore
construction. Those will give the statement of the problem, study objectives, study scope and need for the
study. It was shown that there are many risk factors affecting the offshore construction.
The field survey was composed of 10 members working in this field. The questionnaire had two parts: one
part for general information about the respondents and the second related to the respondents opinion on
probability of occurrence and impact of risk factors. The data was compiled by plurality voting method. All
collected data were analyses by several methods. From this analysis critical risk factors were shortlisted and
risk response suggestions were given.
REFERENCES
1.PatelAnkitMahendra, JayeshkumarR.Pitroda, J.J. Bhavasar( 2013) “A Study of Risk Management Techniques for
Construction Projects in Developing Countries” International Journal of Innovative Technology and Exploring
Engineering ,Volume 3,Issue No. 5 , Page No 139-142.
2.Mohamed El-Shehaby, Ibrahim Nosair, Abd El-MoniemSanad(2014) “Risk Assessment and Analysis for the
Construction of Offshore Oil ana Gas Projects” International journal of Scientific Research And Education, Volume 2,
Issue No 2, Page No 317-333.
3.Diana Stiller, Peter Joehnk (2014) “ Risk Management in Companies-A Questionnaire as an Instrument for Analysing
the Special Situations” Faculty of materials Science and Technology in Trnava,Volume 22, ,Page No. 83-88.
4.Vivian.W.Y.Tam,L.Yshen (2012)“Risk Management for Contractors in Marine Project” Organisation,Technology and
Management in Construction-An International Journal volume 5,Page No: 403-410.
5.Linus Hammer, Diana Perry, Martin Gullsterom “Offshore Wind Power for Marine Conservation” Open Journal of
Marine Science,Volume-8, Year -2016,Page No 66-78.
6.AbdelhakChallal , Mohamed Tkiouat “Qualitative Approach Risk Period in Construction Projects” Journal of Financial
Risk Management, Volume-1, Issue No. 3 Year -2012, Page No: 42-51.
7.Er. AmitBijonDutta ,Dr.M.J.Kolhatkar (2014) “Study of Risk Management in Construction Projects” International
Journal Of Management , Volume 5, Issue No 6 ,Page No:32-39.
8.Lefayet sultan Lipol and JahirulHaq (2011) "Risk analysis method: FMEA/FMECA IN the organizations"
Intrenational Journal of Basic andAppliedSciences,Volume- 11,Issue No 5,Page No:74-82.
9.Kamalesh Panthi,S.M Ahmed and Ogunlana S.O (2008) "Contingency Estimation for Projects through Risk Analysis"
Intrnational Journal of Construction Education and Research,Volume 2,Issue No 5,Page No.;79-94.
10.ErikVanmarcke,M.ASCE and Demosthenes and Angelides (1983) "Risk Assessment for Offshore Structures:A
Review" Journal of Structural Engineering,Volume 2,Issue No 109,Page No.;555-571.
11.PMBOK-5th edition