Jackup Barge
Client: Project:
M/s. MUNDRA SPECIAL ECONOMIC ZONE LTD. JACK UP BARGE
AHMEDABAD.
Doc # Rev Document Title Prepared by JK
A B - 0 5 - 1 0 1 4 / 0 4 0 0 Checked Bhasker Rao
Sheet
Scale
Size
Date Sheet Technical Specifications Reviewed
0 1 0 7 2 0 0 5 1 OF 36
AB Marine Consultants
(Division of Cyber Marine Knowledge Systems Pvt. Ltd.)
511, Hermes Atrium, Sector – 11, CBD Belapur.
Navi Mumbai- 400 614., Mumbai.
E-mail: abmarine@vsnl.com Website: www.cybermarine.net
INDEX
SECTION 1: GENERAL
SECTION 3: STRUCTURE
3.01 GENERAL 22
3.02 BOTTOM CONSTRUCTION 22
3.03 SHELL PLATING WITH FRAMING 22
3.04 LEGS 22
3.05 BULKHEADS 23
3.06 JACK HOUSE 23
3.07 DECKS 23
3.08 TANKS 23
3.09 FOUNDATIONS 23
3.10 DECK HOUSE 24
3.11 RAILING 24
3.12 FUNNEL 24
3.13 ENGINE CASING & SKYLIGHTS 25
3.14 MASTS 25
3.15 LADDERS AND STAIRWAYS 25
3.16 SKEG 25
3.17 FENDER 25
3.18 PAINTING 26
3.19 CATHODIC PROTECTION 27
SECTION 4: MACHINERY, EQUIPMENTS AND MISCELLANEOUS ITEMS
6.01 GENERAL 31
6.02 HYDRAULIC JACKING SYSTEM 31
6.03 GENERATORS 32
7.01 GENERAL 33
7.02 PUMPS 33
7.03 PIPING MATERIAL 34
SECTION 8 : VENTILATION 35
SECTION 1: GENERAL
VESSEL PARTICULARS
DESIGN CODES
• ABS Rules for Building and Classing Mobile Offshore Drilling Units
1.02 CLASSIFICATION
CLASS NOTATION
1.03 CAPACITIES
Fuel Oil …. 10 KL
Fresh Water …. 100 KL
1.04 CERTIFICATES
A B Marine Consultants 5
Jack Up Barge Technical Specifications
1.06 REGISTRATION
Dead weight capacity of the fully equipped vessel, i.e. Deck Load for
construction materials , fuel oil, fresh water, sanitary, misc
consumables &stores, Personnel and effects, provision, Construction
equipment etc. shall be around 670T
1. Inclining Test
2. Anchor trials
3. Jacking System Trials.
4. All Machinery/Equipment Trials
A B Marine Consultants 6
Jack Up Barge Technical Specifications
1.11 GENERAL
The name of the vessel and the port of registration are cut out of 6 mm
plating and welded to the side shell at the usual locations, as per
Statutory Rules. Size of lettering shall be as per class requirements.
Draft marks are carefully marked on the hull before launching. Marks
are made of 6mm steel plates, are in metric units and are positioned
forward, aft, and mid-ship.
A B Marine Consultants 7
Jack Up Barge Technical Specifications
1 Design
The barge will be designed by M/s AB Marine Consultants and class
approved drawings will be supplied to the shipyard
2 Steel
The steel required for the barge shall be supplied by the owner
3 Jacking system
The jacking system used for elevating the hull to the desired height and
also to lower it into the water.
• Limit switches
4 Mooring system
5 Gensets
A B Marine Consultants 8
Jack Up Barge Technical Specifications
The Unit shall be designed as a pontoon with 4 legs and shall be provided
with Hydraulic Jacking System. The equipment shall be mounted on the
Main Deck and Piling and drilling operations shall be carried out from the
deck. All generators and hydraulic power packs shall be mounted below the
Main deck. Rest rooms and office spaces shall be provided above Main
deck.
VESSEL PARTICULARS
LEG DETAILS
The vessel will be built under the classification of ABS/IRS and shall be
eligible to be classed as ‘A1 Self Elevating Unit, Restricted Service” as an
unmanned barge as per ABS or “SUL Self Elevating Platform for Indian
Coastal Service, IY”: as an unmanned barge
A B Marine Consultants 9
Jack Up Barge Technical Specifications
DESIGN CODES
The vessel shall be designed in accordance with the followings codes:
• ABS Rules for Building and Classing Mobile Offshore Drilling Units.
• AISC – Manual of steel construction
• IMO code on Intact stability
Case A
Case B
Case C
Case D
A B Marine Consultants 11
Jack Up Barge Technical Specifications
Case E
Water Depth (Incl. Tide) 26.00 M
Wave Height 2.00 M
Wave Period 8.00 Sec
Current (Uniform) 6.00 Knots
Wind 20.00 Knots
Air Gap 1.25 M
Maximum Soil Penetration 6.00 M
Soil Strength 25.00 T/M2
Min Air temperature 10 0C
Min Sea Temperature 15 0C
Variable Load 535 T
Case F
Water Depth (Incl. Tide) 32.00 M
Wave Height 2.00 M
Wave Period 8.00 Sec
Current (Uniform) 6.00 Knots
Wind 20.00 Knots
Air Gap 1.25 M
Maximum Soil Penetration 0.00 M (Scouring)
Soil Strength 25.00 T/M2
Min Air temperature 10 0C
Min Sea Temperature 15 0C
Variable Load 535 T
Case G
Water Depth (Incl. Tide) 26.00 M
Wave Height 2.00 M
Wave Period 8.00 Sec
Current (Tidal ) 8.00 Knots
Wind 20.00 Knots
Air Gap 1.25 M
Maximum Soil Penetration 6.00 M
Soil Strength 25.00 T/M2
Min Air temperature 10 0C
Min Sea Temperature 15 0C
Variable Load 535 T
A B Marine Consultants 12
Jack Up Barge Technical Specifications
Case H
Water Depth (Incl. Tide) 30.00 M
Wave Height 2.00 M
Wave Period 8.00 Sec
Current (Tidal ) 8.00 Knots
Wind 20.00 Knots
Air Gap 1.25 M
Maximum Soil Penetration 0.00 M (Scouring)
Soil Strength 25.00 T/M2
Min Air temperature 10 0C
Min Sea Temperature 15 0C
Variable Load 535 T
Case I
Water Depth (Incl. Tide) 37.00 M
Wave Height 2.00 M
Wave Period 8.00 Sec
Current (Surface) 4.00 Knots
Wind 20.00 Knots
Air Gap 1.25 M
Maximum Soil Penetration 6.00 M
Soil Strength 25.00 T/M2
Min Air temperature 10 0C
Min Sea Temperature 15 0C
Variable Load 300 T
Case J
Water Depth (Incl. Tide) 43.00 M
Wave Height 2.00 M
Wave Period 8.00 Sec
Current (Surface) 4.00 Knots
Wind 20.00 Knots
Air Gap 1.25 M
Maximum Soil Penetration 0.00 M (Scouring)
Soil Strength 25.00 T/M2
Min Air temperature 10 0C
Min Sea Temperature 15 0C
Variable Load 300 T
A B Marine Consultants 13
Jack Up Barge Technical Specifications
Case A
Water Depth (Incl. Tide) 26.00 M
Wave Height 2.00 M
Wave Period 8.00 Sec
Current (Uniform) 6.00 Knots
Wind 50.00 Knots
Air Gap 1.25 M
Maximum Soil Penetration 6.00 M
Soil Strength 25.00 T/M2
0
Min Air temperature 10 C
0
Min Sea Temperature 15 C
Variable Load 600 T
Case B
Water Depth (Incl. Tide) 32.00 M
Wave Height 2.00 M
Wave Period 8.00 Sec
Current (Uniform) 6.00 Knots
Wind 50.00 Knots
Air Gap 1.25 M
Maximum Soil Penetration 0.00 M (Scouring)
Soil Strength 25.00 T/M2
0
Min Air temperature 10 C
0
Min Sea Temperature 15 C
Variable Load 600 T
A B Marine Consultants 14
Jack Up Barge Technical Specifications
Case C
Water Depth (Incl. Tide) 26.00 M
Wave Height 2.00 M
Wave Period 8.00 Sec
Current (Tidal ) 8.00 Knots
Wind 50.00 Knots
Air Gap 1.25 M
Maximum Soil Penetration 6.00 M
Soil Strength 25.00 T/M2
0
Min Air temperature 10 C
0
Min Sea Temperature 15 C
Variable Load 600 T
Case D
Water Depth (Incl. Tide) 30.00 M
Wave Height 2.00 M
Wave Period 8.00 Sec
Current (Tidal ) 8.00 Knots
Wind 50.00 Knots
Air Gap 1.25 M
Maximum Soil Penetration 0.00 M (Scouring)
Soil Strength 25.00 T/M2
0
Min Air temperature 10 C
0
Min Sea Temperature 15 C
Variable Load 600 T
Case E
Water Depth (Incl. Tide) 26.00 M
Wave Height 2.00 M
Wave Period 8.00 Sec
Current (Uniform) 6.00 Knots
Wind 50.00 Knots
Air Gap 1.25 M
Maximum Soil Penetration 6.00 M
Soil Strength 25.00 T/M2
0
Min Air temperature 10 C
0
Min Sea Temperature 15 C
Variable Load 460 T
A B Marine Consultants 15
Jack Up Barge Technical Specifications
Case F
Water Depth (Incl. Tide) 32.00 M
Wave Height 2.00 M
Wave Period 8.00 Sec
Current (Uniform) 6.00 Knots
Wind 50.00 Knots
Air Gap 1.25 M
Maximum Soil Penetration 0.00 M (Scouring)
Soil Strength 25.00 T/M2
0
Min Air temperature 10 C
0
Min Sea Temperature 15 C
Variable Load 460 T
Case G
Water Depth (Incl. Tide) 26.00 M
Wave Height 2.00 M
Wave Period 8.00 Sec
Current (Tidal ) 8.00 Knots
Wind 50.00 Knots
Air Gap 1.25 M
Maximum Soil Penetration 6.00 M
Soil Strength 25.00 T/M2
0
Min Air temperature 10 C
0
Min Sea Temperature 15 C
Variable Load 460 T
Case H
Water Depth (Incl. Tide) 30.00 M
Wave Height 2.00 M
Wave Period 8.00 Sec
Current (Tidal ) 8.00 Knots
Wind 50.00 Knots
Air Gap 1.25 M
Maximum Soil Penetration 0.00 M (Scouring)
Soil Strength 25.00 T/M2
0
Min Air temperature 10 C
0
Min Sea Temperature 15 C
Variable Load 460 T
A B Marine Consultants 16
Jack Up Barge Technical Specifications
Case I
Water Depth (Incl. Tide) 37.00 M
Wave Height 2.00 M
Wave Period 8.00 Sec
Current (Uniform) 2.00 Knots
Wind 50.00 Knots
Air Gap 1.25 M
Maximum Soil Penetration 6.00 M
Soil Strength 25.00 T/M2
0
Min Air temperature 10 C
0
Min Sea Temperature 15 C
Variable Load 300 T
Case J
Water Depth (Incl. Tide) 43.00 M
Wave Height 2.00 M
Wave Period 8.00 Sec
Current (Uniform) 2.00 Knots
Wind 50.00 Knots
Air Gap 1.25 M
Maximum Soil Penetration 0.00 M (Scouring)
Soil Strength 25.00 T/M2
0
Min Air temperature 10 C
0
Min Sea Temperature 15 C
Variable Load 300 T
A B Marine Consultants 17
Jack Up Barge Technical Specifications
Design Loads
Variable Load 670 T (Concrete Piling)
535 T (Steel Piling)
300 T (43 m Water Depth)
Variable load is the load of all the cranes & other material carried on the
barge for various operations.
The breakup for the variable load is as follows:
Concrete Piling
A B Marine Consultants 18
Jack Up Barge Technical Specifications
Elevated load is the total load of the hull and the variable load.
Jacking System
The Jacking System comprising of 12 Hydraulic cylinders of 150 T capacity
each, arranged as 3 cylinders per leg with a central power pack powered by
electric motors.
The load transfer between the legs, cylinders and the Hull shall be by means
of a positive locking system comprising being of pins mounted on the Hull
and the Cylinders, the Legs being provided with Holes at a pitch of 750 MM.
No of Hydraulic Cylinders 12
No of Jacking Systems 4
Jacking Capacity 1800.00 T
Stroke 1600 MM
MOORING SYSTEM
Design Environment
The Mooring System shall be designed for the following environment.
Current 4.00 Knots
Wind 10.00 Knots
A Four Point Mooring System shall be provided to station the barge with
reasonable accuracy before jacking up for construction.
4 no. Anchors of Weight 4.50T each shall be provided on the Barge. The
Anchors may be Stockless Bower Anchors or High Holding Power AC 14
Anchors. IWRC Ropes of 32mm dia and 300 mm length per anchor shall be
provided.
STABILITY CRITERIA
In the afloat condition the vessel shall satisfy the following stability
criteria.
Intact Stability
The Metacentric Height shall be to be at least 0.5 M.
The area under the righting moment curve to the second intercept, or a
lesser angle, shall be not to be less than 40% in excess of the area under the
wind heeling moment curve to the same limiting angle, the wind velocity of
50 Knots.
The second intercept of the righting moment and the heeling moment curves
shall be to occur at an angle of heel of at least 30 deg associated with a wind
velocity of 70 Knots.
The curves for the wind heeling moments are to be calculated according to
Chapter 3, Section 2 of the IMO code for the Construction and Equipment of
Mobile offshore Drilling Units.
Minimum Standard of closing of openings leading to spaces which are
assumed buoyant, for the purpose of achieving the necessary area under the
GZ curve shall be to be as follows:
- When immersed before equilibrium position (I intercept) taking into
account the effect of wind: Watertight Closed.
- When immersed beyond equilibrium position up to the Dynamic angle :
Weather-tight closed.
A B Marine Consultants 20
Jack Up Barge Technical Specifications
SECTION 3: STRUCTURE
3.01 GENERAL
The hull has a double chine form with a transom stern and a tapered
bow as per G.A. plan. Construction of the vessel to be with
Shipbuilding quality steel plates & sections of IRS/ABS Grades as per
the respective drawings.
The transom stern to be well attached to the keel plating and transom
floor plate.
A B Marine Consultants 21
Jack Up Barge Technical Specifications
3.04 LEGS
LEG DETAILS
LEG INSTALLATION
3.05 BULKHEADS
Watertight transverse bulkheads stiffened on one side to be arranged
as shown in the G.A. Plan.
A jack house constructed above deck with steel encircles the jack up
leg with suitable stiffening to house/mount the jacking system. The
material grade for jack house has to be ABS/IRS Grades as per the
drawings.
3.07 DECKS
3.09 FOUNDATIONS
Three tier deck house is to be arranged aft as shown in G.A. plan. The
deck house is made of steel and has welded construction. The form
and layout is according to the G.A. plan. Scantlings of deck house to
be as per Class requirements.
All outside walls and engine casing including the inner wall of galley,
WCs & lavatories to be of mild steel bulkheads with necessary
stiffeners.
SEA CHEST
Two sea inlet wells shall be provided in the engine room. These shall
be of dimensions as given in the drawings and the openings in the
shell shall be fitted with galvanized mild steel grids held in position by
bolts and nuts. The area of flow through the grid shall be a minimum of
2.1/2 times the area of flow through the respective pipelines.
The sea valves attached to the wells shall be class approved. For each
sea chest, one strainer and isolating valve shall be fitted on the suction
line immediately after skin opening.
The sea chests shall be inter connected with a pipe line of adequate
diameter.
3.11 RAILING
A B Marine Consultants 23
Jack Up Barge Technical Specifications
3.12 FUNNEL
The Owner’s insignia shall be marked and painted on either side of the
funnel.
3.14 MASTS
A mast shall be provided on the Control cabin top as shown in the G.A.
Plan.
The masts, made of steel pipes shall be fixed type and shall be
supported by means of wire rope stays with rung ladders for mounting.
Ladders and stairs are made of steel and as per Class and Statutory
requirements as applicable. Stairs from main deck to control cabin
shall be of 600 mm width. The machinery Room stairs shall be made
of steel. All stairways shall have handrails of galvanised pipe.
A B Marine Consultants 24
Jack Up Barge Technical Specifications
3.16 SKEG
3.17 FENDER
All half round steel pipes should be of 200 mm. dia. and 8 mm.
thickness, stiffened by semi circular steel brackets are to be used as
fender. Lugs to be welded on the deck for providing tyre fenders all
long the sides.
3.18 PAINTING
PAINTING SCHEME
Plates will be sand blasted to SA 2.5 std. Epoxy based painting scheme is as
follows:
2. Boot Topping
4. Exposed Decks
9. Legs
A B Marine Consultants 26
Jack Up Barge Technical Specifications
A four point mooring system shall be provided to station the barge with
reasonable accuracy before jacking up for construction.
The System is to be complete with power pack, controls, relief & pilot
valves. The whole system is to be designed, manufactured and
supplied with Class certification.
Access hatches with size prescribed by Rules with water tight steel
covers for access, wherever required, to be arranged as shown in GA
Plan. Covers of access hatches are to be provided with stainless steel
swing bolts and butterfly nuts.
A B Marine Consultants 27
Jack Up Barge Technical Specifications
4.06 DOORS
A B Marine Consultants 28
Jack Up Barge Technical Specifications
Light and sound signals to be provided and fitted in accordance with the
rules for Prevention of Collisions at Sea. The following minimum double tier
lights, operating on 220 V AC. and shapes to be provided.
A B Marine Consultants 29
Jack Up Barge Technical Specifications
A B Marine Consultants 30
Jack Up Barge Technical Specifications
6.01 GENERAL
General
The jacking system is intended for use on a Jack-up Barge of the following
dimensions:
The jacking system is used for elevating the hull to the desired height and
also to lower it into the water
Jacking System
The System is to be complete with power pack, controls, relief & pilot valves.
The whole system is to be designed, manufactured and supplied with Class
certification.
A B Marine Consultants 31
Jack Up Barge Technical Specifications
6.03 GENERATORS
General
The gensets shall be suitably installed in the machinery compartment and all
necessary fuel supply, cooling arrangements etc shall be made.
A B Marine Consultants 32
Jack Up Barge Technical Specifications
7.01 GENERAL
All the piping systems shall be installed in accordance with best marine
practice and to be to the satisfaction of classification. The piping system in
general shall be laid out neatly and shall be accessible for maintenance and
repairs. Securing arrangement with proper clamps shall be arranged.
Gun metal non return valves shall be fitted on all overboard discharges. All
sea cocks shall be gun metal screw down valves and readily accessible. All
other valves shall be generally of cast iron body with gunmetal internals.
Suitable bulkhead pieces shall be fitted in each place where pipes pass
through bulkheads, decks, etc. Quick closing valves shall be provided on fuel
oil tanks. Slip on flanges and stud flanges shall be used for pipe joints.
7.02 PUMPS
Bilge/Ballast/Fire system
Two no. Bilge cum Ballast pump and One no. General Service cum Fire
Fighting pump to be provided with inter connection between the pumps.
Bilge/Ballast pump shall be electric driven. The General Service cum Fire
pump to be electric motor driven. Both pumps shall be of BE make, the
engine of KIRLOSKAR make and motor of Crompton make. Capacities to
be suitable for the respective services, (about 65 Cu. M. per Hr. at 30
MWC).
Fresh Water
A B Marine Consultants 33
Jack Up Barge Technical Specifications
The material for various piping system shall be in accordance with the
following table:
The water supply for, bathroom, galley shall be made available through
overhead FW tanks of total 2T capacity. These tanks shall be serviced by
FW pump to supply water from under deck Fresh water tank.
Potable water for drinking purpose shall be stored in portable tanks kept at
suitable height.
A B Marine Consultants 34
Jack Up Barge Technical Specifications
SECTION 8 : VENTILATION
Living spaces shall be naturally ventilated and shall be provided with wall-
mounted fans.
All enclosed spaces to be provided with air pipes / goose neck ventilators.
A B Marine Consultants 35
Jack Up Barge Technical Specifications
GENERAL
SYSTEM OF SUPPLY
MAIN SWITCHBOARD
NAVIGATION LIGHTS
SEARCH LIGHT
One no. Searchlight 1000 W shall be provided with about 1 meter stand and
remote handle in control cabin for movement. To be operational for 24 hrs.
BATTERY BANK
A B Marine Consultants 36