Академический Документы
Профессиональный Документы
Культура Документы
Fayad Hanady
Khalil Maria
Richa Manuella
Comments
…………………………………………………………………………………
…………………………………………………………………………………
…………………………………………………………………………………
NB: All documents (Project, HW, Research) have to cover this page, otherwise it will not be marked)
Cover Page GCV-310- Rev A
0|Page
GROUP A Fall 2018-2019
Table of contents
INTRODUCTION:
Introduction…………………………………………3
Building elevations …………………………...........4
Building sections …………………………………..6
GENERAL STUDY: …………..……………………...7
Slab thickness ………………………………...........8
Load calculations:
Dead Load …………………………………………9
Live Load ………………………………………….11
Super Imposed Dead Load …………………..........12
Wind Load ………………………………………...12
LOAD ON COLUMNS AND RUNDOWN:
Service load rundown……………………………..15
Ultimate load rundown…………………………….19
LOAD ON BEAMS
Shear diagram …………………………………....24
Moment diagram…………………………….........26
LOAD ON RIBS
Shear diagram……………………..……………...28
Moment diagram………………………………….30
1|Page
GROUP A Fall 2018-2019
BEAMS DESIGN
Positive moment……………………………….32
Negative moment……………………………....33
Shear……………………………………………34
RIBS DESIGN
Positive moment………………………………..36
Negative moment………………………….……37
Shear…………………………………………....38
COLUMNS DESIGN …………………………….40
FOUNDATION
Wall Footings Design …………………………...44
Columns Footings Design………………………..46
Foundation …………………………………….....50
REFERENCES …………………………………......51
2|Page
GROUP A Fall 2018-2019
INTRODUCTION
This project will study the structural system of a residential building in Feghal.
This building includes a basement, ground floor, first floor, and a roof (pale), having
areas as follows: basement 212m2, ground floor 210m2, first floor 242m2, roof
137m2.
The parking is located at the basement and the rest of the floors are residential.
The floors are connected by stairs to each other.
This project will deal with the calculations of the loads in each floor from
vertical loads as: dead load, super imposed dead load, live load to lateral loads as
wind load.
The loads on the slab are transferred by the ribs to the beams that transmit
them to the columns and walls and finally to the foundation and to the soil.
In the calculations of the dead load, live load, and super imposed dead load
we will rely to the ASCE/ESI 7-10 standards. We will also rely on the tables
provided by the ACI-318-14 in our calculation.
For the design part of the project we have chosen the first floor CSP, for which
we have designed the ribs, beams, in addition to the columns, footings of the walls
and columns.
3|Page
GROUP A Fall 2018-2019
BUILDING ELEVATION
Figure 1
Figure 2
4|Page
GROUP A Fall 2018-2019
Figure 3
Figure 4
5|Page
GROUP A Fall 2018-2019
BUILDING SECTIONS
Figure 5
Figure 6
6|Page
GROUP A Fall 2018-2019
GENERAL STUDY
The plan below shows the beams, the columns, and the direction of the ribs in
our project.
Figure 7
7|Page
GROUP A Fall 2018-2019
1. Slab thickness:
Table 1
In order to determine the thickness of the slab, we divide the span of the beams
of a floor by its corresponding coefficient referring to the table shown above
provided by the ACI. This calculation will lead us to many values, so we choose the
thickness that is closer to the majority of these values. In our project the thickness is
30cm.The table below shows an example of our calculations: 𝑇ℎ𝑖𝑐𝑘𝑛𝑒𝑠𝑠 =
ACI Thickness
Span (m)
Coefficient (m)
Beam 1B01 5.54 18.5 0.29
Beam 1B02 5.6 18.5 0.30
Beam 1B03 6 18.5 0.32
Beam 1B03 4.2 18.5 0.22
Beam 1B04 5.5 18.5 0.29
Beam 1B05 4.89 18.5 0.26
Table 2
8|Page
GROUP A Fall 2018-2019
2. Dead Load:
The dead load is the self-weight of the structural elements that are
connected to the structural system such as walls, columns, beams, slabs, etc…
The calculation of the dead load of the ribbed slab of 30cm thickness is
shown below.
(𝐿 + 𝑙)
𝑉 = ×ℎ×𝑊
2
(0.42 + 0.38)
= × 0.24 × 0.2
2
= 0.0192𝑚 Figure 8
Figure 9
𝑉 = 5 × 0.0192 = 0.096𝑚
𝑉 = 1 × 0.57 × 0.3 = 0.171𝑚
𝑉 =𝑉 −𝑉 = 0.075𝑚
9|Page
GROUP A Fall 2018-2019
0.2931T in 0.57m2
× .
DLslab in 1m2: 𝐷𝐿 = = 0.5142 𝑇
.
The percentage of the beams in each floor should be calculated in order to find
the average dead load of each slab:
Beam area
Slab Area (m2) Percentage
(m2)
Ground floor
241.87 107.88 44.6%
slab
Table 3
10 | P a g e
GROUP A Fall 2018-2019
We will choose the highest percentage of beams to find the average dead load of
the slab:
𝐷𝐿 = (% × 𝑡ℎ𝑖𝑐𝑘𝑛𝑒𝑠𝑠 × 𝜌 × 𝑔) + (% ×
𝐷𝐿 ) = (0.5145 × 0.3 × 2.5 × 9.81) + (0.4855 × 5.04) = 6.23 𝐾𝑁/𝑚
DLaverage= 6.23 KN/m2
3. Live Load:
It’s the weight of everything superimposed on, or temporarly attached to the
structure such as people, machinery and equipment, furniture, appliances, etc… but
not that of the materials used in the construction process or anything permanently
attached to it.
Refering to the ASCE standards:
Table 4
11 | P a g e
GROUP A Fall 2018-2019
The basement, ground floor, and first floor are residential so their live load is
LL= 1.92 KN/m2
We will assume LL=2KN/m2 in the calculations
Refering to ACI code:
Table 5
The live load of the roof is LL= 0.24 KN/m2
5. Wind Load:
It’s the force on a structure arising from
the impact of wind on it. It’s calculated using
the formula: 𝑞 =
0.613𝐾 𝐾 𝐾 𝑉
Assume that the velocity of the wind is
V= 53.64m/s
Flat ground: Kzt=1.0
Table 6
Wind acting alone: Kd=1.0
12 | P a g e
GROUP A Fall 2018-2019
qz=1763.75Kz
𝑃 = 𝑞 𝐺𝐶 − 𝑞 (𝐺𝐶 )
G= 0.85
GCpi = ±0.18
H= 8.5m
By interpolation: Kh=0.96
qh=1693.2 N/m2
a) Roof:
Windward:
.
= = 0.47
.
By interpolation:
Cp=0.312
P1=753.8 N/m2 Table 7
P2=144.26 N/m2
Leeward:
Cp=-0.6
P1=-558.7 N/m2
P2=-1168.3 N/m2
a) Walls:
13 | P a g e
GROUP A Fall 2018-2019
b) Walls:
Table 8
Windward: Cp=0.8
Table 9
Leeward: Cp=-0.5
P1=-414.8 N/m2
P2=-1024.38 N/m2
Side walls: Cp=-0.7
P1=-702.678 N/m2
P2= -1312.23 N/m2
14 | P a g e
GROUP A Fall 2018-2019
Table 10
15 | P a g e
GROUP A Fall 2018-2019
Table 11
16 | P a g e
GROUP A Fall 2018-2019
Tables 12-13
17 | P a g e
GROUP A Fall 2018-2019
Table 14
18 | P a g e
GROUP A Fall 2018-2019
Table 15
Table 16
19 | P a g e
GROUP A Fall 2018-2019
Table 17
20 | P a g e
GROUP A Fall 2018-2019
Table 18
21 | P a g e
GROUP A Fall 2018-2019
Table 19
22 | P a g e
GROUP A Fall 2018-2019
LOADS ON BEAMS
To study the loads on the beams we have chosen the first floor slab plan
We divided the tributary areas for the beams as shown below
Figure 9
23 | P a g e
GROUP A Fall 2018-2019
Figure 10
Beam 2B02:
Figure 11
24 | P a g e
GROUP A Fall 2018-2019
Beam 2B03:
Figure 12
Beam 2B04:
25 | P a g e
Figure 13
GROUP A Fall 2018-2019
Beam 2B01:
Figure 14
Beam 2B02:
Figure 15
26 | P a g e
GROUP A Fall 2018-2019
Beam 2B03:
Figure 16
Beam 2B04:
Figure 17
27 | P a g e
GROUP A Fall 2018-2019
Load on Ribs
1. Shear diagram(KN):
Rib 1-2-3-5:
Figure 18
Rib 7-8:
Figure 19
28 | P a g e
GROUP A Fall 2018-2019
Rib 9-10:
Figure 20
Rib 11:
Figure 21
29 | P a g e
GROUP A Fall 2018-2019
2.Moment diagram(KN.m):
Rib 1-2-3-5:
Figure 22
Rib 7-8:
Figure 23
30 | P a g e
GROUP A Fall 2018-2019
Rib 9-10:
Figure 24
Rib 11:
Figure 25
31 | P a g e
GROUP A Fall 2018-2019
Beams design
Cover = 50mm.
Yield strength capacity of bars = 420Mpa.
Concrete compressive strength: f’c = 28Mpa.
εcu =0.003
We used robot software to obtain the values of Mu.
We will take beam 2B01 as an example for the detailed calculation.
2. Positive Moment:
Mu=17 KN/m
B=800mm
D=250mm
∗
Rn= = =0.37778
∅∗ ∗ . ∗ ∗
0.85 ∗ 𝑓′𝑐 2 ∗ 𝑅𝑛
Ƿ= ∗ 1− 1− = 0.000906
𝑓𝑦 0.85 ∗ 𝑓 𝑐
𝐴𝑠 = Ƿ ∗ b ∗ d = 180𝑚𝑚
1.4 ∗ 𝑏 ∗ 𝑑
𝐴𝑠(min) = = 666.67𝑚𝑚
𝑓𝑦
As ≤ As(min)
Steel 6 Ø12
As = 678 mm2
a=15mm.
c= = 17.6mm.
32 | P a g e
GROUP A Fall 2018-2019
Table 20
3. Negative Moment:
Mu=143 KN/m
B=800mm
D=250mm
∗
Rn= = =3.17778
∅∗ ∗ . ∗ ∗
0.85 ∗ 𝑓′𝑐 2 ∗ 𝑅𝑛
Ƿ= ∗ 1− 1− = 0.00815
𝑓𝑦 0.85 ∗ 𝑓 𝑐
𝐴𝑠 = Ƿ ∗ b ∗ d = 1630𝑚𝑚
1.4 ∗ 𝑏 ∗ 𝑑
𝐴𝑠(min) = = 666.67𝑚𝑚
𝑓𝑦
As ≥ As(min)
Steel 6 Ø20
As =1884mm2
a=42mm.
c= = 48.89mm.
33 | P a g e
GROUP A Fall 2018-2019
4. Shear : Table 21
We will take the first span of beam 2B01 (the cantilever span) as an
example for shear design.
Vu=143KN.
𝑉𝑢 = 125.125
Span length: L=2000mm.
Ø Vc =0.75*0.17*1* 𝑓′𝑐*b*d = 134.933
Ø Vc
= 67.4667
2
Ø
𝑉𝑢 ≥ → in need for stirrups
𝑉𝑢 − Ø Vc
𝑉𝑠 = = 13.0778
Ø
0.33* 𝑓′𝑐*b*d = 349.23917 ≥ Vs
Assuming s = = 125
∗
Av= = 15.5688
∗
. ∗ ∗
Av(min) = = 83.333
Av(min) ≥ Av
Steel 2 Ø8
As =100.6mm2
34 | P a g e
GROUP A Fall 2018-2019
Ø
Vu ≤ at 943.59mm → no more need for stirrups
Table 22
Figure 26
35 | P a g e
GROUP A Fall 2018-2019
Ribs Design
Cover = 50mm.
Yield strength capacity of bars = 420Mpa.
Concrete compressive strength: f’c = 28Mpa.
εcu =0.003
We used robot software to obtain the values of Mu.
We will take Rib 1-2-3-5 as an example for the detailed calculation.
1. Positive Moment:
Mu=18 KN/m
b=420mm (Ac ≤ A(flange) )
d=250mm
∗
Rn= = =0.7619
∅∗ ∗ . ∗ ∗
0.85 ∗ 𝑓′𝑐 2 ∗ 𝑅𝑛
Ƿ= ∗ 1− 1− = 0.00184
𝑓𝑦 0.85 ∗ 𝑓 𝑐
𝐴𝑠 = Ƿ ∗ b ∗ d = 193.2𝑚𝑚
1.4 ∗ 𝑏 ∗ 𝑑
𝐴𝑠(min) = = 125𝑚𝑚
𝑓𝑦
As ≥ As(min)
Steel 2 Ø12
As = 226 mm2
36 | P a g e
GROUP A Fall 2018-2019
a=9.4958mm.
c= = 11.1715mm.
Table 23
2. Negative Moment:
Mu=23.5 KN/m
B=150mm
D=250mm
. ∗
Rn= = =2.78159
∅∗ ∗ . ∗ ∗
0.85 ∗ 𝑓′𝑐 2 ∗ 𝑅𝑛
Ƿ= ∗ 1− 1− = 0.00705
𝑓𝑦 0.85 ∗ 𝑓 𝑐
𝐴𝑠 = Ƿ ∗ b ∗ d = 264.375𝑚𝑚
1.4 ∗ 2𝑏 ∗ 𝑑
𝐴𝑠(min) = = 250𝑚𝑚
𝑓𝑦
As ≥ As(min)
Steel 2Ø14
As =308mm2
a=36.2353mm.
37 | P a g e
GROUP A Fall 2018-2019
c= = 42.6298mm.
Table 24
3. Shear :
We will take the first span of the Rib 1-2-3-5 (the cantilever span) as an
example for shear design.
Vu=10KN.
𝑉𝑢 = 7.91667
Span length: L=1200mm.
Ø Vc =0.75*0.17*1* 𝑓′𝑐*b*d = 25.3
Ø Vc
= 12.65
2
Ø
𝑉𝑢 ≤ → no need for stirrups.
38 | P a g e
GROUP A Fall 2018-2019
Table 25
Figure 27
39 | P a g e
GROUP A Fall 2018-2019
COLUMNS DESIGN
40 | P a g e
GROUP A Fall 2018-2019
Figure 28
41 | P a g e
GROUP A Fall 2018-2019
Figure 29
Column C11 :
Pu=791KN
ØPn=Pu
ØPn=0.8*0.65*(0.85f’c*(Ag-Ast)+fy*Ast)
791=0.8*0.65*(0.85*30*(600*300-Ast) + 420Ast)
Ast=7780𝑚𝑚 .
Steel 16 Ø25
Ast=7856𝑚𝑚 .
Using Ø12 ties (assumption)
42 | P a g e
GROUP A Fall 2018-2019
16*𝑑 . =400mm
48*𝑑 = 576 mm
Least dimension=300mm → spacing of ties s=300mm
Ƿ= ∗ 100 = 4.36% → Acceptable (1% ≤ Ƿ ≤ 8%)
Figure 30
43 | P a g e
GROUP A Fall 2018-2019
Wall Footings
𝑞 = = 256 𝐾𝑁/𝑚 .
.
0.85 ∗ 𝑓 𝑐 2 ∗ 𝑅𝑛
Ƿ= ∗ 1− 1− = 0.001
𝑓𝑦 0.85 ∗ 𝑓 𝑐
As=0.00948*1000*350=351.2𝑚𝑚 .
As=0.0018*1000*350=630 𝑚𝑚 . ← for temperature and shrinkage.
As(min)=1167𝑚𝑚 . ←
As(min)=1141.1𝑚𝑚 .
Steel 8 Ø14 @ 12.5cm
44 | P a g e
GROUP A Fall 2018-2019
As=1232𝑚𝑚 .
And we will use As=1130𝑚𝑚 for temperature and shrinkage.
Table 26
Figure 31
45 | P a g e
GROUP A Fall 2018-2019
Isolated Footings
A= =2.906 m2
46 | P a g e
GROUP A Fall 2018-2019
=269*0.5
=134.5 KN
Vu ≤ ØVc : d is safe to use
Shear two way – Punching shear:
= =17.5cm
A’’=4((0.3+0.35)-(0.6+0.35))
=2.4m2
Vu=Qu*A’’
=269*2.4
=645.6 KN
B0=0.95+0.95+0.65+0.65=3.2m
ØVc=0.17*0.75*√𝑓′𝑐*b0*d
=782.147KN
Vu ≤ ØVc : d is safe to use
Design:
∗
Mu= = =538 KN.m
Rn= =2.533
Ø
0.85 ∗ 𝑓 𝑐 2 ∗ 𝑅𝑛
Ƿ= ∗ 1− 1− = 0.00617
𝑓𝑦 0.85 ∗ 𝑓 𝑐
As= Ƿ ∗ b ∗ d
=0.00617*2000*350
=4282.25 mm2
Design:
∗ . .
Mu= = =65.905 KN.m - -d+0.35=0.7
47 | P a g e
GROUP A Fall 2018-2019
Rn= =0.2988
Ø
0.85 ∗ 𝑓 𝑐 2 ∗ 𝑅𝑛
Ƿ= ∗ 1− 1− = 0.0007158
𝑓𝑦 0.85 ∗ 𝑓 𝑐
As= Ƿ ∗ b ∗ d
=0.0007158*2000*350
=501.102 mm2
We will use 10Ø16 @ 20cm
Table 27
48 | P a g e
GROUP A Fall 2018-2019
Figure 32
49 | P a g e
GROUP A Fall 2018-2019
Foundation
Figure 33
50 | P a g e
GROUP A Fall 2018-2019
REFERENCES
ACI 318-14, building code requirements for structural concrete and commentary
http://www.civilsimplified.com/resources/what-is-dead-load
http://www.civilengineeringterms.com/steel-structures/definition-of-imposed-load/
http://www.civilsimplified.com/resources/what-is-live-load
51 | P a g e