Location: F&HC
The training and skill required for the job: Tool box meeting, Training for hot work regarding safe work procedure and work briefing with all workers.
Personal Protective Equipment Required: Safety Shoes, Hard hat, Hi-vis Jacket, Safety glasses, Shield, leather hand gloves, Nose mask, Safety Harness.
1.Pipe 1.Small metal Piece 1.1.Site supervisor to ensure that all work personnel are issued
Cleaning work Fall on eye with safety glasses and Gloves
1.2.Site supervisor to ensure that all work personnel wear their EHS personnel,
safety glasses while doing work Site supervisor
2.grooving 1.Falling objects 1.1.Ensure the proper support to pipe while grooving work EHS personnel,
work 1.2.Other person should not allowed in work area Site supervisor
3.Mobilization 1.Collision with People and Property 1.1.Scissor lift /Boom lift shall be inspected by M+W EHS
s of scissor lift department
1.2. Scissor lift /Boom lift Operator must be trained Supervisor,
1.3. Maintain inspection checklist. Safety person
1.4. Training Records must be submitted to M+W EHS Dept.
1.5. Scissor lift must be positioned on firm level ground and to be
operated only by a qualified operator
1.6. SWL signs to be displayed on the scissor lifts and safe
working loads shall be compiled to at all times.
1.7. Banks Man must be designated to guide the movements of the
scissor lifts at site Speed limit 12 Km/h
1.8. Ensure No hand phone usage except for emergencies.
1.9. Ensure access is firm and even.
1.10 Warning lights to be provided while night work
1.11. Ensure don’t move lift keeping height.
1.12.Ensure Swing alarm at boom lift
4. Drilling of 1.Electrical hazards 1.1. All electrical tools & equipments have to certify LEW before
Roof use. Ensure stickers are to be pasted on the equipment and
appliances. All inspected equipment or appliances are colour
coded.
1.2. To ensure extension cable are routed above 2 meter from
ground or hang on cable stand.
1.3. Workers to ensure when handling tools according to
manufactures instruction. All user must be briefed before use the
electrical tools.
1.4. To check on physical condition of cable to ensure it is free
from defect before use.
1.5. Ensure all electrical tools equipped with a dead man switch.
1.6. Always use ELCB of 30mA when connect to main power
supply.
1.7. Ensure that all plugs and sockets used are of the approved
industrial type.
1.8. When working external stop using electrical tools when rain
starts. Kept all electrical tools in dry place ensure unplug from the
power source.
1.9.Task supervisor should ensure there is no live electrical cable
through drilling area
2.1.Site supervisor to ensure that all work personnel are issued
2.Flying particles during drilling and wear safety glasses / face shield
2.2.Drilling machine operator should not wear any loose cloth
2.3.operator not wear the cotton gloves
2.4. Ensure drill bit length should not exceed slab concrete
thickness
5.Pipe erection 1.Toppling of Scissor lift 1.1. Operator must be Trained and Certified by M+W EHS Dept
use by Scissor 1.2. Banks man to be trained on emergency lower controls of EHS personnel,
Lift & chain assigned scissor lift. Site supervisor
pulley block 1.3. Barricade the working area at all times and display warning
signage's
1.4. No other incompatible work shall be performed near the
scissor lifts
1.5. Access ground for scissor lift must be firm and level
1.6.The scissor lift have out rigger that is fully extended
1.7.scissor lift is certified
1.8. ensure only operate the platform control panel don’t operate
bottom control panel
2.1. Banksman to ensure no personnel or property movement Signal man,
2.Hit to man and machinery during operation in progress. Site supervisor
2.2. Operator to be trained an understand before can operate
scissor lift.
2.3. Work area to be barricaded
2.4. Signage’s to be displayed
2.5.Swing alarm to be provided at boom lift
8.1.Remove key from scissor lift while operator leave that area
8.2.Lock arrangement to be provided at boom lift control panel EHS personnel,
Site supervisor
6.Scaffold 1.Scaffold collapse 1.1.Engage an approved scaffold erectors. Full time supervision
Erection during erection of scaffold Supervisor &
1.2. Scaffold supervisor & Erectors must be qualified and trained EHS person
for the job and must be appointed.
1.3. All scaffolds to be registered. Register to be kept up-to date by
Scaffold supervisor.
1.4.All scaffold materials must be checked before use and if found
to be defective, must be remove from site
1.5. Barricade to be provided around scaffold erection areas.
Warning signs to be placed.
1.6.Ensure all Personnel not to overload scaffold with working
materials
1.7Scaffold to be erect to as per designing
1.8If possible scaffold to be tied with permanent structure
1.9Floor level is even and surface
7.Usage of 1.Scaffold topple 1.1Check scaffold green tag is in place, valid (7days) and safe to
Scaffold/ use & no work shall proceed with red tag.
Mobile 1.2 Inform scaffold supervisor if scaffold seems to be unsafe to
scaffold use.
1.3Do not remove or modify scaffold components.
1.3Do not over loaded the scaffold 02 workers max per bay
1.4Scaffolds to be erected by qualified scaffold erectors only and
with immediate supervision by scaffold supervisor.
1.5Do not pull or shift scaffold when someone is on top of mobile
scaffold.
1.6Ensure castor wheel are lock. Do not over load the scaffold.
1.7Work area keep always clean
1.8Provide sufficient manpower for all work
1.9Don’t use near the pit
1.10Ensure out riggers is fully tightened
2.Falling Object 2.1. Site Supervisor to remind workers not to put loose materials Site supervisor
left on top of ladder.
2.2. Do not leave hand tools on top of ladder. Do not leave ladder
unattended
3.Toppling of ladder 3.1. Ladder shall be fold and kept neatly when not in use. Site supervisor
3.2. Ensure ladder on firm and even ground.
3.3. Ensure buddy system when using ladder.
3.4. Do not leave ladder un attended.
3.5.A frame ladder fully open / do not use fire man ladder
3.6.Ensure ladder base rubber shoe
9.Hydrostatic 1.Pressure Build up & Loose fittings 1.1. Ensure All fittings & Couplings are Properly tightened.
Testing 1.2. Ensure Slow charge of testing medium.
pressure –in 1.3. While Charging the water makes sure there is no leaking.
depending on 1.4. Any modification or Retightening must be carried out only
requirement after depressurizing the system. Then rectify the Leak.
1.5. Ensure that the connections and line from the piping spool to
drain and air blown is properly fixed and secured
Job Executive,&
1.1. Maintain correct posture, while carrying out the job. EHS Personal
2. Surface 1. Health hazard, 1.2. Use painting brush
cleaning & Injury to eyes due to splash of paint, dust, 1.3.Use task related PPE’S
application of rust etc. 1.4 .Wear suitable protective clothing & gloves
paint.
EHS personnel,
1.1 Wheel will be checked before going to use. Site supervisor
12.Cutting 1.2 Ensure it free from damage.
with Abrasive 1.Failure of cutting wheel 1.3 The wheel which will be properly labeled will be used.
wheel cutter 1.4 Ensure the RPM (operating speed) of the wheel will be greater
than the spindle speed of the machine.
1.5 Wheel shall never be used after the expiry date.
1.6 Wheel guard will be in position and fixed properly.
1.7 Wheel will be tightened properly.
1.8 Testing run (trail run) will be taken.
2.1. Double insulated cable will be used.
2.2 Ensure cable will be damage free. EHS personnel,
2.3 Cable will be routed overhead. Site supervisor
2.Electricution 2.4 Work will be carried out dry place
2.5 Use double insulated machines
2.6 Only experienced /trained /authorized persons will be carried out
the work.
2.7 Power supply for machine shall be through ELCB of 30 mA
sensitivity
3.1. Person working nearby area will be protected from flying particles
by shields. EHS personnel,
3.2 Area will be barricaded and unauthorized entry will be restricted. Site supervisor
3.3 sheet barricading is provided for spark & Flying particle
3. Flying particle protection
4.1. Flammable /combustible materials will be removed from the work EHS personnel,
area. Site supervisor
4.2 Suitable fire extinguisher will be kept at work spot.
4.3 Ensure the presence of fire watcher.
4.Fire hazard
4.1 Flammable/combustible materials will be removed from the work EHS personnel,
area. Site supervisor
4.2 Suitable fire extinguisher will be kept at work spot.
4.3 Ensure the presence of fire watcher.
6.Fire Hazard
1.1 Double insulated cable will be used.
1.2 Ensure cable will be damage free.
1.3 Cable will be routed overhead.
1.4 Work will be carried out dry place Site supervisor
1.5 Use double insulated machines
14. 1.6 Only experienced /trained /authorized persons will be carried out
GRINDING 1. Electric hazard the work.
1.7 Power supply for machine shall be through ELCB of 30 mA
sensitivity
1.8 machine is inspected and colour coded
EHS personnel,
Site supervisor
2.1 Wheel will be checked before going to use.
2.2 Ensure it will be damaged free.
2.3 The wheel which will be properly labeled will be used.
2.4 Ensure the RPM(operating speed) of the wheel will be greater than
the spindle speed of the machine.
2.5 Wheel shall never be used after the expiry date.
2.Failure of grinding wheel 2.6Wheel guard should position and fixed properly.
2.7 Wheel will be tightened properly.
2.8 Wet grinding wheel will not be used.
2.9Don’t use cutting wheel for grinding
2.10 Job specific training to be given by M+W EHS team
EHS personnel,
Site supervisor
3. Flying particle 3.1 Person working nearby area must be protected from flying particle
by spark shields.
3.2 Work area to be barricaded
3.3Other person should not allowed inside the work area
4.Fire hazard
EHS personnel,
4.1Flammable /combustible materials will be removed from the work
Site supervisor
area.
4.2Suitable fire extinguisher will be kept at work spot.
4.3 Ensure the presence of fire watcher during the work
15.Night work
&Emergency provide sufficient task light and access light during
precaution night hours
Job executive should ensure sufficient man power to do
night work
Supervisor/Safety Personal to check emergency
preparedness for night work
Emergency vehicle should be available in the site
Emergency contact number should be display at site