1 Whether Reporters of Local Papers may be allowed to see Yes the judgment ?
=====[========================================
GUJARAT MINERAL DEVELOPMENT CORPORATION LTD....Appellant(s) Versus
S I M P L E X I N F R A S T R U C T U R E L I M I T E D . . . . D e f e n d a n t ( s )
============================================= Appearance:
F I R S T A P P E A L N o . 6 1 8 o f 2 0 1 7
MR. S.N. SOPARKAR, LD. SR ADV WITH GURSHARAN H VIRK, ADVOCATE for
t h e A p p e l l a n t ( s ) N o . 1
MR. PERCY C KAVINA, LD. SR ADV WITH MS. GARIMA MALHOTRA WITH
MR.BHASH H MANKAD, CAVEATOR for the Defendant(s) No. 1 FIRST APPEAL No.778 of 2017
MR. PERCY C KAVINA, LD. SR ADV WITH MS. GARIMA MALHOTRA WITH
M R . B H A S H H M A N K A D f o r t h e a p p e l l a n t
MR. S.N. SOPARKAR, LD. SR ADV WITH GURSHARAN H VIRK, ADVOCATE for the defendant
=============================================
CORAM: HONOURABLE MR.JUSTICE M.R. SHAH and HONOURABLE MR.JUSTICE B.N. KARIA
Date : 09 /06/2017 CAV JUDGMENT HC-NIC Page 1 of 53 Created On Sun Aug 13 04:15:17 IST
2017 (PER : HONOURABLE MR.JUSTICE M.R. SHAH) 1.0.
As both these appeals arise out of the impugned judgment and order passed by the learned
2.0. Feeling aggrieved and dissatisfied with the impugned judgment and order passed by
t h e l e a r n e d C o m m e r c i a l C o u r t ,
Ahmedabad passed in Commercial Civil Miscellaneous Application
No. 52 of 2016, passed under Section 34 of the Arbitration Act, the original respondent −
Gujarat Mineral Development Corporation Limited (hereinafter referred to as "the
GMDC") has preferred present First Appeal No. 618 of 2017 under Section 13(1) of the
Commercial Court Act r/w Section 37(1)(c) of the Arbitration and
Conciliation Act, 1996 (hereinafter referred to as "Arbitration Act") [.
2.1. Feeling aggrieved and dissatisfied with the impugned judgment and order passed by the
learned Commercial Court, Ahmedabad passed in Commercial Civil Miscellaneous Application
No. 52 of 2016, passed under Section 34 of the Arbitration Act, the original applicant − Simplex
I n f r a s t r u c t u r e L i m i t e d ( h e r e i n a f t e r
referred to as "SIL") has preferred present First Appeal No. 778 of HC-NIC Page 2 of 53 Created On
Sun Aug 13 04:15:17 IST 2017 2017 under Section 13(1) of the Commercial Court Act r/w Section
37(1)(c) of the Arbitration and Conciliation Act, 1996.
3.0. The facts leading to the present First Appeals in nutshell are as under:
3.1. That the GMDC invited and issued tender notice for
execution of general, civil and architectural work for 2 x 125 MW
Akrimota Thermal Power Project. That the said contract came to be
awarded to the original applicant − SIL vide letter of intent dated
27.11.2001. That the work order came to be issued by the GMDC
on dated 07.02.2002. That total estimated value of the work was
Rs.5,80,71,292/− with firm price and no escalation clause. That as
per the clause 4.0 of the work order / contract time was essence of the contract and the entire
w o r k w a s r e q u i r e d t o b e c o m p l e t e d
within 22 months from the date of issuance of letter of intent. It
also further provided tow months grace period and as per the said
clause, the accepted rates will be valid for a further period of two months grace period. Since
the letter of intent was issued on 27.11.2001, the work was to be completed by
27.11.2003 including two months' grace period. That according to the SIL,
there was a delay on the part of the GMDC in releasing drawing
works and due to non providing the fronts / drawings and details of drawings by the GMDC
from the very beginning, the construction could not be completed within the time prescribed in
the work order. According to the SIL, prior to schedule completion date, SIL wrote a letter
dated 23.10.2003 giving notice of its HC-NIC Page 3 of 53 Created On Sun Aug 13 04:15:17
IST 2017 intention to claim compensation for the work which may be
executed beyond the contract period in the form of escalation and extra costs and
p u r s u a n t t h e r e t o , S I L r a i s e d s e v e n p e r i o d i c a l b i l l s
pertaining to the escalation and extra costs. According to the SIL,
after a period of one year of the schedule date of completion, the
work order came to be amended by the GMDC vide its letter dated
24.11.2004 and the value of the work almost reached double from
rs. 5,80,71,292/− to Rs. 10,78,21,292/−. According to the SIL, vide its reply dated 24.11.2004
to the GMDC, SIL expressed its intention with regard to the conditions stipulated in
the amendment that the rates would be firmed and no escalation
would be allowed, which was not acceptable to the SIL as it was
practically impossible to execute the work at the rate determined prior thereto. That thereafter,
t h e S I L c o m p l e t e d t h e w o r k o n
30.09.2006. Since the request of the SIL seeking the payment of escalation and over stay were
n o t c o n s i d e r e d b y t h e G M D C a n d
GMDC failed to make payment towards escalation and additional costs, the dispute arose
between the parties and therefore, SIL invoked the arbitration. The Arbitral Tribunal
came to be constituted consisting of sole Arbitrator. The SIL submitted the
statement of claim before the Arbitrator as under:
(3) Claim for an amount of Rs.2,01,16,402/towards extra costs incurred due to overstay;
3.3. Feeling aggrieved and dissatisfied with the award passed by the learned Arbitrator
in disallowing the claim nos. 3,4,5,6 and 7, SIL submitted the application before the
learned District Court under Section 34 of the Arbitration Act being Civil
"(a) modify/set aside the impugned award dated HC-NIC Page 5 of 53 Created On Sun Aug 13
04:15:17 IST 2017 December 9, 2011 to the extent it relates to the rejection of the applicant's
claims for escalation and extra costs incurred on account of overstay at
the Project as contained in paragraphs 13 to 27 and the last paragraph of the Award;
3.4. That the said Commercial Miscellaneous Application was vehemently opposed by GMDC.
3.5. That by impugned judgment and order the learned Judge Commercial Court,
A h m e d a b a d h a s p a r t l y a l l o w e d t h e
Section 34 application and has quashed and set aside the award
declared by the learned Arbitrator with respect to the claim no.3
i.e. claim for escalation and has allowed the entire claim no.3 as
per the Claim Statement lodged before the learned Sole Arbitrator.
Rest of the award declared by the learned Arbitrator in disallowing
the claim nos. 4,5,6 and 7 came to be confirmed by the learned
Judge, Commercial Court, Ahmedabad.
3.6. Feeling aggrieved and dissatisfied with the impugned judgment and order passed by
the learned Commercial Court, Ahmedabad in so far as allowing the claim no.3 i.e.
claim for HC-NIC Page 6 of 53 Created On Sun Aug 13 04:15:17 IST 2017
escalation, the original opponent GMDC has preferred present First Appeal No.618 of 2017.
3.7. Feeling aggrieved and dissatisfied with the impugned judgment and order passed by
t h e l e a r n e d C o m m e r c i a l C o u r t ,
Ahmedabad in so far as confirming rest of the award passed by the
learned Arbitrator disallowing the claim nos. 4, 5, 6 and 7, the SIL
has preferred present First Appeal No.778 of 2017.
First Appeal No. 618 of 2017 5.0. Shri S.N. Soparkar, learned counsel appearing on
behalf of the GMDC has vehemently submitted that in the facts and circumstances of the case
t h e l e a r n e d C o m m e r c i a l C o u r t h a s
materially erred in modifying the award declared by the learned sole Arbitrator and in allowing
the claim no.3 i.e. claim with respect to escalation, which was disallowed by the
learned Arbitrator and that too, in exercise of powers under Section 34 of the Arbitration Act.
HC-NIC Page 7 of 53 Created On Sun Aug 13 04:15:17 IST 2017 5.2. It is further submitted by
Shri Soparkar, learned counsel for the GMDC that though the Arbitrator had nowhere held
GMDC solely responsible for delay, the learned Commercial Court
has materially erred in holding that such was the finding of the Arbitrator.
5.4. It is further submitted by Shri Soparkar, learned counsel for the GMDC that even
learned Commercial Court has substituted the standard of evidence and has
re−appreciated the evidence which is not permissible while considering the application
under Section 34 of the Arbitration Act.
Sun Aug 13 04:15:17 IST 2017 claim no.3 and has decided the matter on equity and fairness and
has ignored the contract altogether.
5.8. It is further submitted by Shri Soparkar, learned counsel for the GMDC that
l e a r n e d C o m m e r c i a l C o u r t h a s
materially erred in not properly appreciating the fact that as per the
contract between the parties and as per the terms and conditions of
the work order, there was no provision for escalation even for the period beyond the time
prescribed under the contract, more particularly, with respect to the extended period of
time. It is further submitted by Shri Soparkar, learned counsel for the GMDC
that therefore, though the escalation was alien to the contract, the
learned Commercial Court has awarded escalation in violation of contractual provisions.
5.9. It is further submitted by Shri Soparkar, learned counsel for the GMDC that
though in the award learned sole Arbitrator though not given any findings that the
delay was attributable to GMDC and though even Simplex did not make such allegation in its
correspondence, learned Commercial Court has materially erred in coming to the
conclusion that delay was attributable to the GMDC.
5.11. It is vehemently submitted by Shri Soparkar, learned counsel for the GMDC that Section
37 of the Act is co−terminus with the narrow scope and limited expanse of the power of
the Commercial Court under Section 34 of the Act.
5.12. It is vehemently submitted by Shri Soparkar, learned counsel for the GMDC that in the
present case though not permissible and while allowing the claim no.3 with respect
to escalation, the learned Commercial Court has re−appreciated the
evidence and as such has passed an order on equity and fairness
ignoring the contractual provisions.
5.14. It is vehemently submitted by Shri Soparkar, learned counsel for the GMDC that as the
view taken by the learned Arbitrator was correct view and even if the Commercial Court was
of the opinion that the another view is possible, in that case also,
learned Commercial Court is not justified in rigors in the finding of
the award declared by the learned Arbitrator with respect to the claim no.3 − claim for escalation.
5.15. It is vehemently submitted by Shri Soparkar, learned counsel for the GMDC that the
l e a r n e d C o m m e r c i a l C o u r t h a s
materially erred in allowing the claim for escalation by treating the computation rendered by SIL
a s a v a l i d c o m p u t a t i o n , w i t h o u t
either calling upon GMDC to rebut the computation, or verifying the authenticity of the claim
or manner of computation, or appreciating the evidence based on which the claim
appears to have been allowed. It is submitted that, therefore, the learned Commercial
Court has erred in summarily granting a claim and
reversing the reasoned view of the Arbitrator.
(4). Simplex had, therefore, by its letter dated 18.08.2001, withdrawn its deviation in
respect of escalation and had clearly submitted to firm contractual rates;
(5). Therefore, the work order dated 07.02.2002 was awarded to Simplex. Clause 3 of the Work
Order (pg. 19) clearly mandated that the prices under the contract were firm and no
escalation would be allowed. It was also clarified that the rates would remain
firm (without escalation) without any upper ceiling limit;
(6). The letters dated 23.10.2003 (pg. 25) and 17.08.2004 (pg.
HC-NIC Page 12 of 53 Created On Sun Aug 13 04:15:17 IST 2017 (7). Even during course
of argument before this Hon'ble Court, Simplex does not contend that delay was ONLY
attributable to GMDC. Therefore, at best, the case of Simplex is that delay was allegedly
attributable to both parties. However, there is no
evidence in support of the said baseless contention of Simplex;
(8). By its letter dated 24.11.2004 (pg. 31) and 22.02.2007 (pg.
(9). Even otherwise, neither the Hon'ble Arbitrator nor the Hon'ble Commercial Court
h a v e e n g a g e d i n t o t h e e x e r c i s e o f
computing the claims or verifying their authenticity or arithmetic accuracy;
(10.1). The Arbitrator did not reject GMDC's claim for LD on merits.
GMDC was required to refund the amount so deducted by GMDC HC-NIC Page 13 of 53 Created On
Sun Aug 13 04:15:17 IST 2017 as per the prescriptions under the Contract.
5.18. It is vehemently submitted by Shri Soparkar, learned counsel for the GMDC that neither
the Arbitrator nor the Commercial Court have engaged into the exercise of computation
of the claim for escalation.
5.20. It is vehemently submitted by Shri Soparkar, learned counsel for the GMDC that the
learned Arbitrator arrived at a conclusion that since SIL did not become eligible to
claim escalation or extra−cost in the first place, inter alia, on account of lack of evidence to
establish its said claims, the question of engaging into the exercise of computing the
said claims was unnecessary and redundant. Therefore, the learned Arbitrator had
no occasion to consider the escalation claim on merits and more particularly with respect to the
computation made by the SIL of escalation claim.
5.21. It is vehemently submitted by Shri Soparkar, learned counsel for the GMDC that
as such neither learned Commercial Court while exercising the powers under Section 34
of the Arbitration Act nor even this Court while exercising the power
under Section 37 of the Arbitration Act can remand the matter to
5.22. It is vehemently submitted by Shri Soparkar, learned counsel for the GMDC that
a s s u c h t h e i s s u e o f r e m a n d i n g t h e
matter was considered by the learned Commercial Court, however
both the parties refused for remanding the matter to the learned
Arbitrator and therefore, the matter is not required to be remitted HC-NIC Page 15 of 53 Created
On Sun Aug 13 04:15:17 IST 2017 to the learned Arbitrator. It is submitted that even
otherwise remanding the matter to the learned Arbitrator by the Court while exercising the
powers under Section 34 of the Arbitration Act is
wholly impossible as once the learned Arbitrator has declared the
award thereafter the learned Arbitrator becomes the functus officio.
5.23. Shri Soparkar, learned counsel for the GMDC has further submitted that it would
be pointless to remit the matter back to the Commercial Court as the Commercial
Court cannot adduce additional evidence in the present matter, lack of which is
the reason for even considering remittance in the first place.
Making above submissions and relying upon the above decisions, it is requested to
a l l o w t h e A p p e a l p r e f e r r e d b y t h e
GMDC and quash and set aside the impugned judgment and order passed by the learned
C o m m e r c i a l C o u r t i n s o f a r a s a l l o w i n g
claiming no.3 while modifying the award declared by the learned Arbitrator.
F i r s t A p p e a l N o s . 6 1 8 o f 2 0 1 7 & 7 7 8 o f 2 0 1 7 6 . 0 .
Shri P.C. Kavina, learned counsel for the original applicant −
SIL has vehemently submitted that in the facts and circumstances
of the case, the learned Commercial Court has not committed any error in modifying the award
declared by the learned Arbitral HC-NIC Page 16 of 53 Created On Sun Aug 13 04:15:17 IST
2017 Tribunal thereby granting claim of escalation to original applicant.
6.1. It is further submitted by Shri Kavina, learned counsel for the SIL that it is an
admitted position that as per the work order / contract between the parties the work
was to be completed by 27.11.2003 including two months grace period. It is submitted that
it was the obligation of the GMDC to provide drawings / fronts.
However, SIL was not provided with the fronts/ drawings / details
of drawings by GMDC from the very beginning. As a consequence,
the construction plan was jeopardized from the very beginning and
the execution of the work was delayed. It is submitted that SIL
wrote various letters to GMDC from time to time, requested for use
of the drawings and work fronts and pointing out the delay on the
part of the GMDC. However, GMDC never replied to such letters or
otherwise controverted the delay alleged by the SIL. It is submitted
that thus, the GMDC accepted that SIL was not responsible for the delay.
It is submitted that after about one year from the schedule HC-NIC Page 17 of 53 Created On Sun
Aug 13 04:15:17 IST 2017 date of completion, the original work order came to be amended vide
GMDC's letter dated 24.11.2004 and the value of the work
was almost doubled from Rs. 5,80,71,292/− to Rs.10,78,71,292/−. It is submitted that the said
l e t t e r c o n t a i n e d a s t a n d a r d c l a u s e
providing that the prices shall remain firm and no escalation shall
be allowed. It is submitted that the aforesaid letter of the GMDC
was replied to by the SIL on the very same day i.e. 24.11.2004,
wherein it was categorically mentioned that condition stipulated in
the amendment that the rates are firm and no escalation will be
allowed is not acceptable as it was practically impossible to execute
the work at fixed rates. It is submitted that therefore, SIL requested GMDC to make payments
f o r t h e w o r k e x e c u t e d b e y o n d t h e
contractual completion period as per the escalation formula already submitted by the SIL. It is
submitted that communication dated 24.11.2004 was neither replied by the GMDC nor
rejected the escalation and extra costs bills submitted by SIL. It is submitted that in
fact the GMDC continued to accept the work from SIL without any demur or protest
a n d a l s o t h r o u g h i t s v a r i o u s
representatives assured SIL that GMDC would look into the matter
and make provision for appropriate payments and requested SIL to
continue execution of work. It is submitted that the aforesaid is evident from the letter dated
22.2..2007 issued by the GMDC wherein it had recapitulated the discussions in a
meeting held between the representatives of the parties on the said date. It is submitted that
with respect to escalation and overstay, it was
submitted that these points will be taken into consideration during
the contract closure along with penalty, liquidated damages etc. as
per contract. It is submitted that at that time even the SIL replied to HC-NIC Page 18 of 53 Created
On Sun Aug 13 04:15:17 IST 2017 the said letter vide its letter dated 6.3.2007 stating that the points
of penalty and liquidated damages raised by GMDC were
6.5. Shri Kavina, learned counsel for the SIL has submitted that the considering the aforesaid
f a c t s a n d c i r c u m s t a n c e s a n d t h e
material on record, the decision of the Hon'ble Supreme Court in
the case of McDermott International Inc. v.Burn Standard Co. Ltd.,
(2006) 11 SCC 181 and the decision of the Delhi High Court in the
case of Puri Construction Pvt. Ltd. & Ors. v. Larsen & Toubro Ltd. &
Anr. rendered in FAO (OS) 21/2009 shall not be applicable to the facts of the case on hand.
6.6. Shri , learned counsel for the SIL has heavily relied upon the
decision of the Madras High Court in the case of Gaytri Vs. ISG
Novasoft Technologies Ltd. rendered in MANU/TN/2293/2014 in
support of his submission that in the facts and circumstances of the
case, the learned Commercial Court has rightly modified the award declared by the learned
Tribunal in exercise of powers under Section 34 of the Arbitration Act.
Making above submission and relying upon the above decision, it is requested to
dismiss the appeal preferred by the GMDC.
7.1. It is further submitted by Shri Kavina, learned counsel for the SIL that the impugned
order passed by the learned Commercial Court to the extent it relates to claim no.4 (claim for
extra costs due to overstay) erroneously upholds the decision of the learned Tribunal in this
regard, which is unreasoned. It is submitted that there is no reference to copious evidence.
7.3. It is further submitted by Shri Kavina, learned counsel for the HC-NIC Page 21 of 53 Created
On Sun Aug 13 04:15:17 IST 2017 SIL that both the learned Arbitrator and the Commercial
Court have erroneously held that in the instant case, the delay is not attributable only
t o t h e G M D C a n d c l a i m a n t ( S I L ) w a s a l s o
responsible for delay in certain cases. It is submitted that there is
no any material on record that SIL is even partially responsible for
the delay. It is submitted that on the contrary, the SIL placed on
record various uncontroverted letters pointing out the delay on the part of the GMDC.
non−supply of drawings/fronts on part of GMDC. It is submitted that said letters were neither
rebutted nor protested on receipt by GMDC. It is submitted that even the same were
neither controverted by documentary or oral evidence even during the course of
Arbitration.
that sum of Rs. 31,58,299.55 was due and payable towards extra costs. It is
submitted that therefore, in view of such admission by the GMDC,
the same ought to have been considered by the learned Arbitrator and learned Commercial Court.
7.9. Shri Kavina, learned counsel for the SIL has submitted that as
such by not allowing the claim no.4 with respect to the extra costs due to overstay, both, the
learned Arbitrator as well as learned Commercial Court have disregarded the contractual
terms operating between the parties. It is submitted that clause no.4 of
the order dated February 7, 2002 provides that "prices are firm and
no escalation will be allowed during the currency of the contract period".
It is submitted that therefore, necessary corollary of the
same is that if SIL was required to undertake any work beyond the
contract period on account of reasons not attributable to SIL, the
prices would not be considered fixed. It is submitted that in such a
situation the fixed price clause or no−escalation clause would not
survive nor would be binding on SIL. It is submitted that clause 4 of HC-NIC Page 24 of 53 Created
On Sun Aug 13 04:15:17 IST 2017 the work order provides that the entire work shall be completed
within a period of twenty two (22) calendar months but the accepted rates will be
v a l i d f o r a f u r t h e r t w o ( 2 ) m o n t h s ' g r a c e
period. It is submitted that letter of intent was issued on November 27, 2001 and thus, the
t e n d e r r a t e s w e r e v a l i d f o r a p e r i o d o f
twenty four (24) months from the said date, i.e. up to November
27, 2003. It is submitted that therefore, both the learned Arbitrator
as well as learned Commercial Court have completely ignored the aforesaid contractual terms.
8. Now, so far as submission on behalf of the GMDC that while exercising powers under Section
3 4 o f t h e A r b i t r a t i o n A c t , t h e
Commercial Court has no jurisdiction to re−appreciate the evidence
on record and / or finding recorded by the learned Arbitrator is
concerned, Shri Kavina, learned counsel for the original applicant −
SIL has submitted that it is a settled law where a finding is based
on no evidence; or Arbitral Tribunal takes into account something irrelevant to the decision
w h i c h i t a r r i v e s a t ; o r i g n o r e d v i t a l
evidence in arriving at a decision, such decision would necessarily be perverse and therefore,
t h e C o u r t i n e x e r c i s e o f p o w e r s u n d e r
Section 34 of the Arbitration Act will be justified in interfering with such a perverse decision.
8.1. Now, so far as submission on behalf of the GMDC that assuming the Court under
S e c t i o n 3 4 o f t h e A c t C o u r t c a n
appreciate the evidence, however it has power to either accept the
award or set aside the award, but the Court cannot pass a decree,
but the parties shall have recourse to fresh arbitration is concerned, HC-NIC Page 25 of 53 Created
On Sun Aug 13 04:15:17 IST 2017 it is submitted by Shri Kavina, learned counsel for the SIL that by
such contention GMDC seeks to narrow the scope of jurisdiction of
8.2. It is submitted that even the words "set aside" used in Section
34 of the Act need to be given "purposive interpretation" so as to
envisage that the power to set aside or confirm the Arbitral award
brings within its fold, the power to undo the miscarriage of justice caused by a perverse award
or an award vitiated by the grounds mentioned in Section 34 since the intention of the
legislature cannot be interpreted to mean that Courts are to turn a blind eye HC-NIC Page 26 of 53
Created On Sun Aug 13 04:15:17 IST 2017 despite the perversities and patent illegalities of
an order challenged before it. It is submitted that if such a narrow interpretation is
given effect to then the entire purpose behind
having a recourse of Section 34 of the Act shall be rendered futile
and would be nothing but a mere recourse on paper.
8.3. Shri Kavina, learned counsel for the SIL has submitted that
even in the present case Section 55 and 70 of the Contract Act shall squarely be applicable.
8.4. Shri Kavina, learned counsel for the SIL has submitted that
due to following facts the case of the SIL squarely falls within the
provisions of Section 55, Part III of the Contract Act:
GMDC makes it apparent that the case of Simplex falls within Section 55 of the Contract Act
and GMDC is liable to pay Simplex the escalation and extra costs claimed by it."
8.5. It is further submitted by Shri Kavina, learned counsel for the original applicant−SIL that
even assuming though not admitting that Section 55 of the Contract
Act does not apply, as the work HC-NIC Page 27 of 53 Created On Sun Aug 13 04:15:17 IST 2017
executed by the SIL under the a commercial contract and the same was executed with no
i n t e n t i o n o f s a m e b e i n g a g r a t u i t o u s a c t ,
considering Section 70 of the Contract Act, for the work executed
by the SIL beyond the contractual period and with a specific notice
of claiming compensation in the form of escalation and extra−costs,
the SIL will be entitled to escalation price as well as extra costs due to overstay.
Making above submissions and relying upon the following decisions, it is requested to
d i s m i s s t h e a p p e a l p r e f e r r e d b y t h e
GMDC and allow the appeal preferred by the SIL and modify the
award declared by the learned Arbitrator rejecting the other claims
and consequently to allow other claims including claim no.3.
368. (4). Food Corporation of India V. A.M. Ahmed and Co reported in (2006) 13 SCC 779.
First Appeal No. 618 of 2017 9.0. Heard the learned advocates for the respective parties at
length.
HC-NIC Page 28 of 53 Created On Sun Aug 13 04:15:17 IST 2017 9.1. At the outset, it is
required to be noted that present First Appeal is an appeal under Section 37 of the
Arbitration Act, challenging the impugned judgment and order passed by the learned
Commercial Court, Ahmedabad, by which, learned
Commercial Court in exercise of powers under Section 34 of the Arbitration Act has partially
m o d i f i e d t h e a w a r d p a s s e d b y t h e
learned Arbitral Tribunal and has allowed the claim for escalation
in favour of the SIL, however has confirmed the rest of the award declared by the learned
Arbitral Tribunal confirming the award declared by the learned Arbitral Tribunal
confirming the award declared by the learned Arbitral Tribunal rejecting other claims.
14. Section 34 of the Arbitration and Conciliation Act reads as follows− "34.
Application for setting aside arbitral award.−(1)
Recourse to a Court against an arbitral award may be made only by an
application for setting aside such award in
accordance with sub−section (2) and sub−section (3).
(2) An arbitral award may be set aside by the Court only if−
(a) the party making the application furnishes proof that− HC-NIC Page 31 of 53 Created
On Sun Aug 13 04:15:17 IST 2017
(ii) The arbitration agreement is not valid under the law to which the parties have subjected it or,
failing any indication thereon, under the law for the time being in force; or
(iii) the party making the application was not given proper notice of the appointment
of an arbitrator or of the arbitral proceedings or was otherwise unable to present his case; or
(iv) the arbitral award deals with a dispute not contemplated by or not falling within the terms of
the submission to arbitration, or it contains decisions on matters beyond the scope of
the submission to arbitration:
(v) the composition of the arbitral tribunal or the arbitral procedure was not in accordance with the
agreement of the parties, unless such agreement was in conflict with a provision of this Part from
which the parties cannot derogate, or, failing such agreement, was not in accordance with this Part;
or
(i) the subject−matter of the dispute is not capable of settlement by arbitration under the law for the
time being in force, or
(ii) the arbitral award is in conflict with the public policy of India.
HC-NIC Page 32 of 53 Created On Sun Aug 13 04:15:17 IST 2017 (3) An application for setting
aside may not be made after three months have elapsed from the date on which the party
making that application had received the arbitral award or, if a request had been made under
Section 33, from the date on which that request had been disposed of by the arbitral
tribunal:
Provided that if the Court is satisfied that the applicant was prevented by sufficient cause from
making the application within the said period of three months it may entertain the application
within a further period of thirty days, but not thereafter.
16. It is important to note that the 1996 Act was enacted to replace the 1940 Arbitration Act in
order to provide for an arbitral procedure which is fair, efficient and capable of meeting
the needs of arbitration; also to provide that the
tribunal gives reasons for an arbitral award; to ensure that the
tribunal remains within the limits of its jurisdiction; and to
minimize the supervisory roles of courts in the arbitral process.
Patent Illegality
40.We now come to the fourth head of public policy namely, patent illegality.
It must be remembered that under the explanation to section 34 (2) (b), an
award is said to be in conflict with the
public policy of India if the making of the award was induced or
affected by fraud or corruption. This ground is perhaps the earliest
ground on which courts in England set aside awards under English
law. Added to this ground (in 1802) is the ground that an arbitral award would be
set aside if there were an error of law by the arbitrator. This is
explained by Lord Justice Denning in R v.
Northumberland Compensation Appeal Tribunal. Ex Parte Shaw.,
1952 1 All ER 122 at page 130:
41. This, in turn, led to the famous principle laid down in Champsey
Bhara Company v. The Jivraj Balloo Spinning and
Weaving Company Ltd., AIR 1923 PC 66, where the Privy Council
referred to Hodgkinson and then laid down:
"The law on the subject has never been more clearly stated than by Williams, J.
in the case of Hodgkinson v. Fernie (1857) 3 C.B.N.S. 189.
"The law has for many years been settled, and remains so at this day,
that, where a cause or matters in difference are referred to an arbitrator a
lawyer or a layman, he is constituted the sole and final judge of all questions
both of law and of fact ...... The only exceptions to that rule are cases
where the award is the result of corruption or fraud,
and one other, which though it is to be regretted, is now, I think firmly
established viz., where the question of law necessarily arises on the face of the
award or upon some paper accompanying and
forming part of the award. Though the propriety of
this latter may very well be doubted, I think it may be considered as established."
"28. Rules applicable to substance of dispute.− (3) In all cases, the arbitral
tribunal shall decide in accordance with the terms of the contract and
shall take into account the usages of the trade applicable to the
transaction."
"112. It is trite that the terms of the contract can be express or implied. The
conduct of the parties would also be a
relevant factor in the matter of construction of a contract. The construction of
the contract agreement is within the jurisdiction of the arbitrators having
regard to the wide nature, scope and ambit of the arbitration agreement and
they cannot be said to have misdirected themselves in
passing the award by taking into consideration the conduct
of the parties. It is also trite that correspondences exchanged
by the parties are required to be taken into consideration for
the purpose of construction of a contract. Interpretation of a
contract is a matter for the arbitrator to determine, even if
it gives rise to determination of a question of law. (See Pure
Helium India (P) Ltd. v. ONGC [(2003) 8 SCC 593] and
D.D. Sharma v. Union of India [(2004) 5 SCC 325]).
113. Once, thus, it is held that the arbitrator had the jurisdiction, no
further question shall be raised and the
court will not exercise its jurisdiction unless it is found that
there exists any bar on the face of the award."
the award in any way perverse. Nor can one substitute one's own view in
such a situation, in place of the one taken by the
umpire, which would amount to sitting in appeal. As
held by this Court in Kwality Mfg. Corpn. v. Central
Warehousing Corpn. [(2009) 5 SCC 142 : (2009) 2 SCC (Civ) 406] the Court
while considering challenge to arbitral award does not sit in appeal over
the findings and decision of the arbitrator,
which is what the High Court has practically done in this matter. The umpire is
legitimately entitled to HC-NIC Page 38 of 53 Created On Sun Aug 13 04:15:17 IST
2017 take the view which he holds to be the correct one after considering
the material before him and after interpreting the provisions of the
agreement. If he does so, the decision of the umpire has to be accepted
as final and binding."
10.2. Applying the law laid down by the Hon'ble Supreme Court in
the aforesaid decisions, this Court is required to examine and / or consider whether the learned
C o m m e r c i a l C o u r t i s j u s t i f i e d i n
modifying the award declared by the learned Arbitral Tribunal and
in allowing the claim no.3 i.e. claim with respect to the escalation
which was rejected by the learned Tribunal, in exercise of powers
under Section 34 of the Arbitration Act ? This Court is also required to consider whether in the
facts and circumstances of the case learned Commercial Court is justified in rejecting
Section 34 application in so far as confirming the award declared by the
Arbitral Tribunal rejecting the claim no.4 i.e. claim with respect to
extra costs on account of overstay ?
11. Now, so far as the claim no.3 with respect to escalation price
is concerned, at the outset, it is required to be noted that in the contract/ agreement / work
o r d e r , i t w a s s p e c i f i c a l l y m e n t i o n e d t h a t
prices are "firm and no escalation will be allowed during the currency of the contract period."
However, subsequently SIL insisted for escalation price even at the time when the period of
contract was extended. However, GMDC did not agree for the same and therefore, SIL at the
relevant time did not pursue their insistence for escalation
clause. It is true that thereafter the SIL continued the work and complete the work within the
extended HC-NIC Page 39 of 53 Created On Sun Aug 13 04:15:17 IST 2017
period. It is also true that subsequently when the SIL submitted the
invoices, the same were with escalation price as per formula earlier
suggested by it but was not accepted by the GMDC. However, it
was the case on behalf of the SIL that in the communication dated
22.02.2007 the GMDC agreed to consider their claim of escalation
price. It appears that entire claim of the escalation by the SIL was
based on the premise that GMDC did not object to their letter dated
17.08.2004 written by the SIL and that if allowed the claimant to
proceed with the work. It was also the case on behalf of the SIL
that officer of the GMDC assured that the escalation price would be
paid. However, in absence of any specific evidence with respect to time and name of the officer
b y w h o m s u c h r e p r e s e n t a t i o n w a s
made and in absence of any evidence led by SIL with respect to
such assurance, learned Arbitrator did not accept the case of the
SIL. At this stage, it is required to be noted that as such SIL had not
led any oral evidence. From the reasons and the findings recorded by learned Arbitral Tribunal,
i t a p p e a r s t h a t t h e l e a r n e d A r b i t r a l
Tribunal rejected the claim no.3 i.e. claim with respect to escalation on the ground that (1)
C l a i m n o t s u p p o r t e d b y d o c u m e n t a r y
evidence; (2) GMDC specifically denied escalation; (3) No evidence
/ corroborative as regards delinquent or officer of the GMDC (4)
Section 55 of the Indian Contract Act shall not be applicable.
11.2. Now, so far as the letter dated 22.02.2007 which was heavily relied upon by the SIL and
i n w h i c h , a c c o r d i n g t o t h e S I L , t h e
GMDC stated that question of escalation will be considered by it, it is required to be noted that
i n t h e s a i d c o m m u n i c a t i o n d a t e d
22.02.2007 there does not appear to be any such assurance given
by the GMDC to consider the claim regarding escalation. What is stated is that "Mr. U.B.Singh
has also raised points regarding escalation & over run of contract. It is informed that
during contract closure these points alongwith penalty, liquidated
damages etc. as per contract will be taken in consideration as per the Contract". The learned
A r b i t r a t o r h a s o b s e r v e d t h a t t h e
communication/ letter dated dated 22.02.2007 cannot be said to be acceptance of escalation
price. However, the learned Commercial Court has reversed the finding recorded by the learned
Arbitral Tribunal in relation to the letter dated 22.02.2007 by observing that "even
a s s u r a n c e s g i v e n b y t h e r e s p o n s i b l e a n d
authorized representative of the respondent cannot be given a go−
bye as it emerges from the correspondence appears to have been HC-NIC Page 41 of 53 Created On
Sun Aug 13 04:15:17 IST 2017 find force and, therefore, no cogent reasons even has been adduced
by the respondent for not believing the same." From the aforesaid,
Considering the aforesaid facts and circumstances, it appears that learned Commercial Court
h a s m a t e r i a l l y e r r e d i n r e v e r s i n g
the finding recorded by the learned Arbitral Tribunal in relation to the escalation. The learned
Commercial Court has exceeded its jurisdiction in exercising the powers under Section
34 of the Arbitration Act as an Appellate Court, which is not permissible.
11.7. Even otherwise it is required to be noted that there are no such powers of remand vested
w i t h t h e C o u r t e x e r c i s i n g t h e
powers either under Section 34 or Section 37 of the Arbitration Act.
The only power the Court possesses is under Section 34(4) of the Arbitration Act, which
is the repository of power invested in the Court. Section 34(4) of the Arbitration reads as under:
"34. .....
A c t s e t t i n g a s i d e t h e a w a r d o n a
written request made by a party to the arbitration proceedings to facilitate the Arbitral Tribunal
by resuming the arbitration proceedings or to take such other action as in the opinion of the
Arbitral Tribunal will eliminate the grounds for setting aside the Arbitral Award. The
quintessence for exercising the the power under this provision is that the Arbitral Award
has not been set aside. The challenge to the said award has been set up under Section
34 of the Arbitration Act about the deficiencies in the Arbitral Award which may be
c u r a b l e b y a l l o w i n g t h e A r b i t r a l
Tribunal to take such measures which can eliminate the grounds
for setting aside the Arbitral Award. No power has been invested by
the Parliament in the Court to remand the matter to the Arbitral
Tribunal except to adjourn the proceedings for the limited purpose
mentioned in sub−section (4) of section 34. The view which we are expressing is supported by
the decision of the Hon'ble Supreme Court in the case of McDermott International Inc.
vs. Burn Standard Ltd. reported in (2006) 11 SCC 181.
11.8. Now, so far as reliance placed upon the decision in the case
of A.M. Ahmed and Co (supra) relied upon by Shri Kavina, learned
counsel for the SIL is concerned, at the outset, it is required to be
noted that in the said decision it was specific finding recorded by
the learned Arbitrator that there was a delay in execution of the contract due to the conduct of
F o o d C o r p o r a t i o n o f I n d i a a n d
therefore, Corporation was liable for the consequence of the delay
viz. increase in statutory wages. It is required to be noted that in the present case there is no
s u c h f i n d i n g g i v e n b y t h e l e a r n e d
Arbitrator and / or even learned Commercial Court that the delay
was attributable to the GMDC. The learned Arbitrator specifically
observed that in the facts and circumstances of the case, it is not
necessary to go into the merits of the rival contention as regards the reasons of delay
attributable to whom. Despite the above, learned Commercial Court has observed that
GMDC never appeared to have fulfilled its obligation of providing drawings and
work fronts in time resulting in delay in completion of the project.
Even in the reasoning assigned while disposing of the claim no.1, the learned Commercial Court
h a s o b s e r v e d t h a t d e l a y i s n o t
attributable to the claimant only. Therefore, what was required to
be thereafter considered was whether who was responsible for the
delay and to what extent was again required to be considered. As
observed herein above, the learned Arbitrator did not go into the merits of the rival contention
as regards reasons of delay attributable to whom. Under the circumstances, the
aforesaid decision shall not be applicable to the facts of the case on hand.
12. In view of the above and for the reasons stated above, we are
of the opinion that learned Commercial Court has materially erred in allowing claim no.3 which
was rejected by the learned Arbitrator, by reversing the finding recorded by the
learned Arbitrator, while exercising the powers under Section 34 of the
Arbitration Act. Under the circumstances, Appeal preferred by the
GMDC being First Appeal No. 618 of 2017 deserves to be allowed and is accordingly allowed.
13. Now, so far as First Appeal No. 778 of 2017 preferred by the SIL against the impugned
j u d g m e n t a n d o r d e r p a s s e d b y t h e
learned Commercial Court dismissing the application under Section
34 of the Arbitration Act and confirming the award declared by the HC-NIC Page 48 of 53 Created
On Sun Aug 13 04:15:17 IST 2017 learned Tribunal rejecting the claim no.4 i.e. claim with respect to
extra costs on account of overstay is concerned, at the outset, it is
required to be noted that as such there are concurrent findings of fact recorded by the learned
Arbitrator as well as learned Commercial Court. Therefore, the present Appeal which
will be under Section 37 of the Arbitration Act is concerned, the Court would have
very limited scope and the jurisdiction. As observed
and held by the Hon'ble Supreme Court as well as this Court in catena of decisions, against the
order passed by the learned Arbitrator even the first Court exercising the power under Section
34 of the Arbitration Act would have very limited scope and the jurisdiction and as observed
herein above, the Court while considering the application under Section 34/37 of the Act is not
sitting as an Appellate Court against the award declared by the learned Arbitrator.
T h e s c o p e a n d e x e r c i s e o f j u r i s d i c t i o n b y t h i s
Court in exercise of powers under Section 37 of the Arbitration Act by this Court will be
co−terminus with the scope of Section 34 of the Act and therefore,
u n l e s s a n d u n t i l t h e c a s e i s m a d e o u t f o r
interference as per law laid down by the Hon'ble Supreme Court in the case of Associate
Builders (supra), this Court would not be justified in interfering with the findings recorded by
the learned Arbitrator, confirmed by the learned Commercial Court.
adduce any cogent evidence to prove the payment made towards maintenance of the site
machinery, manpower engaged and the payment made by them. Therefore, in absence
of any cogent evidence on record, the learned Arbitrator rightly rejected the said claim. The
aforesaid has been confirmed by the learned Commercial Court. Considering the
aforesaid facts and circumstances of the case and the findings recorded by the learned
Arbitrator recorded while rejecting the claim no.4 i.e. with respect to claim on account of extra
c o s t s i n c u r r e d d u e t o o v e r s t a y , i t
cannot be said that the same deserve any interference of this Court
in exercise of powers under Section 37 of the Arbitration Act. We are in complete agreement
with the view taken by the learned Arbitrator as well as learned Commercial Court.
14.1. As rightly observed by the learned Arbitrator as well as learned Commercial Court
merely because the SIL continued to carry on the work after a period of 22 months,
the SIL is not entitled to compensation for the overstay. The SIL was required to prove
that the overstay was due to the delay on the part of the
GMDC and that SIL was required to be adduced cogent evidence
with respect to the actual claim and the expenditure incurred.
14.4. Under the circumstances, the present First Appeal No. 778 of 2017 preferred by the SIL
deserves to be dismissed and is accordingly dismissed.
15. In view of the above and for the reasons stated above, First
Appeal No. 618 of 2017 preferred by the GMDC is hereby allowed and the impugned judgment
and order passed by the learned Commercial Court, Ahmedabad dated 28.12.2016 in
Commercial Civil Miscellaneous Application No. 52 of 2016 is hereby quashed and set aside in
so far as modifying the award declared by the learned Arbitrator and allowing the
claim no.3 with respect to HC-NIC Page 52 of 53 Created On Sun Aug 13 04:15:17 IST 2017
escalation.
15.1. In view of the above and for the reasons stated above,
First Appeal No. 778 of 2017 is hereby dismissed and the impugned judgment and order passed
by the learned Commercial Court, Ahmedabad dated 28.12.2016 in
Commercial Civil Miscellaneous Application No. 52 of 2016 rejecting Section 34
application and confirming the award declared by the learned Arbitrator with
respect to claim no.4 − with respect to extra costs on account of overstay is hereby confirmed.
In the facts and circumstances of the case, there shall be no order as to costs.
Sd/− (M.R. SHAH, J.) Sd/− (B.N. KARIA, J.) Kaushik HC-NIC Page 53 of 53 Created On
Sun Aug 13 04:15:17 IST 2017