Академический Документы
Профессиональный Документы
Культура Документы
Enclosed are the ballot results for consideration at the Fall 2007 meeting of the API Task Group
on Inspection Codes. This attachment includes the following ballots:
Scorecard
Ballot # Title
Item #
These large vessels must have structural integrity to support external loads, as well as
pressurized system integrity to contain a fluid or fluids in the operational context to prevent
consequences of failure.
Notes: 1) Discussed at the API Fall 2006 Conference Task Group on Codes. A number of
committee members were uncomfortable with the wording which was being added to
Section 1.2.2. Therefore, the ballot was completely changed and new wording more to
the point, leaving the owner-user the discretion to determine which large vessels the
Code may apply to, was drafted.
2) OSHA citations refer to requirement to include equipment that is important for safety in
the Mechanical Integrity element of PSM. “If equipment types other than those listed in
paragraph j(1) are important to safety, then MI applies to those types of equipment also
(PSM Standard Preamble, OSHA letter of 5/24/94, OSHA letter of 7/11/94, OSHA letter
of 11/30/94, OSHA letter of 12/7/95) “
3) Discussed in Spring 2007 conference. Dennis Layman suggested dropping “large”
vessel reference to include all pressure vessels that the owner-user may include based
on consequence of failure.
4) Bill Neill raised an inquiry March, 2007, as follows: Ken Tam indicated in his email, the
Appendix A d. (should be c.) exemption for volume and pressure first appeared in the
first edition of API 510, Sept. 1980. Please note. The ASME Sec. VIII Div. 1 Introduction
exemptions U-1 (j) are believed to be for new construction. I am not clear on why a new
construction exemption should be used for in-service exemptions.
Page 1 of 2
Ballot 510-25-07
1.1.1 Coverage
This inspection code covers the in-service inspection, repair, alteration, and rerating activities
for pressure vessels and the pressure-relieving devices protecting these vessels. This
inspection code applies to all refining and chemical process vessels that have been placed in
service unless specifically excluded per 1.2.2. This includes:
d. non-standard vessels - a vessel fabricated to a recognized construction code but has lost
it’s nameplate or stamping;
e. vessels that are exempted in accordance with the criteria in ASME Section VIII: Division 1
should be considered for inclusion based on risk (potential degradation and consequence
of failure) as determined by the owner-user.
Page 2 of 2
API Ballot Summary Sheet
9/10/2007
Ballot: 510-25-07 Inspection of Vessels Excluded by ASME Limits Ballot ID: 1216
VotingCategory
Vote Results
Voter Interest Category Company Comments Affirmative Negative Abstain Did Not Vote
Moraya Al-Gahtani Operator-User Saudi Aramco No X
Gregory Alvarado Contractor Equity Engineering Group, Inc. No X
Roger Armstrong Operator-User Monsanto Company No X
John Britton Contractor Det Norske Veritas (USA), Inc. No X
Robert Dolejs Contractor UOP LLC Yes X
Roger Duvic Contractor Vessel Statistics Inc. No X
Wayne Elliott Contractor Elliott Services, Inc. No X
Eric Ellis Operator-User Lyondell Houston Refining, LP No X
Nat Faransso Contractor KBR No X
John Fiore Contractor FTS, Inc. No X
Frank Furillo Operator-User ExxonMobil Corp. No X
Mark Geisenhoff Operator-User Flint Hills Resources, LP No X
Craig Harley Contractor General Physics Corp. No X
Gary Heath Contractor All Tech Inspection No X
Peter Hunt Operator-User Suncor Energy, Inc. No X
Morris Kline Contractor HMT Inspection No X
Owen Konski Operator-User Syncrude Canada Ltd. No X
Dennis Layman Operator-User BP p.l.c. No X
John Ludman Operator-User DuPont Engineering No X
John McMillan Contractor Mechanical Integrity Inc. No X
Rick Nichols Contractor Roddey Engineering Services, Inc. No X
Robert Pechacek Contractor General Electric Inspection Services No X
John Reynolds Consultant Shell Global Solutions (US) Inc. Yes X
Delano Richie Manufacturer PetroChem Inspection Services No X
James Riley Operator-User Chevron Energy & Technology Company Yes X
Richard Roberts Contractor Quest TruTec No X
Clay Rodery Operator-User BP North America Inc. No X
1
API Ballot Summary Sheet
9/10/2007
Ballot: 510-25-07 Inspection of Vessels Excluded by ASME Limits Ballot ID: 1216
VotingCategory
Roy Schubert Operator-User Shell Canada Energy, Ltd. No X
Michael Shallis Contractor Acuren Inspection, Inc. No X
Larry Siqueiros Operator-User Marathon Petroleum Company LLC No X
Ryan Sitton Consultant Pinnacle Asset Integrity Services No X
Robert Smallwood Consultant No X
Kelly Smith Operator-User ConocoPhillips No X
Nick Sowa Contractor Conam Inspection & Engineering Service No X
Kenneth Tam Consultant No X
Roland Valdes Contractor Inspection Solutions, LLC No X
John Watson Operator-User Dow Chemical No X
Steven Wells Contractor Pro-Inspect Inc. No X
Total Responses: 32
Total Ballots: 38
Response Rate (Affirmative / Total Ballots): 82% Must be > 50%
Approval Rate (Affirmative / [Affirmative + Negative] ): 97% Must be > 67%
Consensus: YES
2
API Ballot Comments and Resolution
Ballot: 510-25-07 Inspection of Vessels Proposal: Add a provision to the scope to consider the need to Ballot ID: 1216 Date: September 10, 2007
Excluded by ASME Limits inspect vessels that are excluded from ASME code limits.
1 2 3 4 5 6
Voter Name Clause No./ Type of Comment (justification for change) by the Voting Proposed change by the Voting Member Comment Resolution
# (Vote) Subclause Comment Member
No./Annex
(e.g. 3.1)
1 John Reynolds 1.1.1 Technical I think we should draw paricular attention to the Note: Specific attention is drawn to
Shell Global large process vessels operating at less than 15 large vacuum process vessels
Solutions (US) Inc. psig, like vacuum flashers. Hence, I suggest we containing hydrocarbon fluids, like
add the following note. vacuum flashers.
(Affirmative)
2 Robert Dolejs 1.1.1.e Editorial I would slightly change the wording to make it read
UOP LLC better by adding the word "which" as such:
(Affirmative) .....criteria in ASME Section VIII, Div 1 which
should be considered.....
3 Roland Goodman 1.1.1e Editorial Delete "that are" in the beginning of this sentence. "vessels exempted in accordance with
American the criteria in ASME . . ."
Petroleum Institute
(NonVoter)
4 James Riley Technical Refer to revisions and comments suggested in
Chevron Energy & ballot return by John O'Brien to eliminate the
Technology Appendix A
Company
(Negative)
Page 1 of 1
API electronic balloting template/version April 2003
Ballot 510-26-07
Page 1 of 2
Ballot 510-26-07
7.8.2 Pressure vessel and pressure-relieving device records shall contain four types of
information pertinent to mechanical integrity as follows:
c. Repair, alteration, and rerating information. For example, (1) repair and alteration forms like
that shown in Appendix D; (2) reports indicating that equipment still in-service with either
identified deficiencies, temporary interim repairs or recommendations for repair, are suitable
for continued service until repairs can be completed; and (3) rerating documentation
(including rerating calculations, new design conditions, and evidence of stamping).
8.1.5.1.1 General
Temporary repairs Interim repairs may only be suitable for short-term service and should be
removed and replaced with suitable permanent repairs a more permanent repair at the next
available maintenance opportunity. The anticipated life of the interim repair depends on many
circumstances, including consideration of risk. Temporary Interim repairs may remain in place
for a longer period of time only if the technical considerations that affect the expected life of the
interim repair are evaluated, approved, and documented by the engineer and inspector.
Documentation of temporary interim repairs should shall include
b. specific details about the interim repair design and implementation, e.g. engineering basis
summary, material of construction, thickness, size of welds, NDE performed.
Page 2 of 2
API Ballot Summary Sheet
9/10/2007
VotingCategory
Vote Results
Voter Interest Category Company Comments Affirmative Negative Abstain Did Not Vote
Moraya Al-Gahtani Operator-User Saudi Aramco No X
Gregory Alvarado Contractor Equity Engineering Group, Inc. No X
Roger Armstrong Operator-User Monsanto Company No X
John Britton Contractor Det Norske Veritas (USA), Inc. No X
Robert Dolejs Contractor UOP LLC No X
Roger Duvic Contractor Vessel Statistics Inc. No X
Wayne Elliott Contractor Elliott Services, Inc. No X
Eric Ellis Operator-User Lyondell Houston Refining, LP No X
Nat Faransso Contractor KBR Yes X
John Fiore Contractor FTS, Inc. No X
Frank Furillo Operator-User ExxonMobil Corp. No X
Mark Geisenhoff Operator-User Flint Hills Resources, LP Yes X
Craig Harley Contractor General Physics Corp. No X
Gary Heath Contractor All Tech Inspection No X
Peter Hunt Operator-User Suncor Energy, Inc. Yes X
Morris Kline Contractor HMT Inspection No X
Owen Konski Operator-User Syncrude Canada Ltd. Yes X
Dennis Layman Operator-User BP p.l.c. No X
John Ludman Operator-User DuPont Engineering No X
John McMillan Contractor Mechanical Integrity Inc. No X
Rick Nichols Contractor Roddey Engineering Services, Inc. No X
Robert Pechacek Contractor General Electric Inspection Services No X
John Reynolds Consultant Shell Global Solutions (US) Inc. Yes X
Delano Richie Manufacturer PetroChem Inspection Services No X
James Riley Operator-User Chevron Energy & Technology Company No X
Richard Roberts Contractor Quest TruTec No X
Roy Schubert Operator-User Shell Canada Energy, Ltd. No X
1
API Ballot Summary Sheet
9/10/2007
VotingCategory
Michael Shallis Contractor Acuren Inspection, Inc. No X
Larry Siqueiros Operator-User Marathon Petroleum Company LLC No X
Ryan Sitton Consultant Pinnacle Asset Integrity Services No X
Robert Smallwood Consultant No X
Kelly Smith Operator-User ConocoPhillips No X
Nick Sowa Contractor Conam Inspection & Engineering Service No X
Kenneth Tam Consultant Yes X
Roland Valdes Contractor Inspection Solutions, LLC No X
John Watson Operator-User Dow Chemical No X
Steven Wells Contractor Pro-Inspect Inc. No X
Total Responses: 32
Total Ballots: 37
Response Rate (Affirmative / Total Ballots): 81% Must be > 50%
Approval Rate (Affirmative / [Affirmative + Negative] ): 94% Must be > 67%
Consensus: YES
2
API Ballot Comments and Resolution
Ballot: 510-26-07 Interim Repairs Proposal: Replace the term “temporary repairs” with” interim Ballot ID: 1217 Date: September 10, 2007
repairs” to better describe the potential longevity of such repairs.
1 2 3 4 5 6
Voter Name Clause No./ Type of Comment (justification for change) by the Voting Proposed change by the Voting Member Comment Resolution
# (Vote) Subclause Comment Member
No./Annex
(e.g. 3.1)
1 Mark Geisenhoff 3.60 Editorial Suggest eliminating the phrase "to be" 3.60 temporary interim repairs
Flint Hills temporary
interim 3.60 temporary interim repairs Repairs made to pressure vessels to
Resources, LP restore sufficient integrity to continue
repairs Repairs made to pressure vessels to restore
(Affirmative) safe operation for an interim period
sufficient integrity to continue safe operation for an until permanent repairs are conducted
interim period until permanent repairs are to be
conducted
2 Roland Goodman 3.60 Editorial Add the word "that" before restore, "mechanical" Repairs made to pressure vessels that
American before integrity and delete "to be" at the end of the restore sufficient mechanical integrity
Petroleum Institute sentence. to continue safe operation for an
interim period until permanent repairs
(NonVoter) are conducted.
3 Ken Gottselig 8.1.5.1.2.1 Technical Change first sentence from "Fillet-welded patches change to
Lyondell Chemical may be used to make temporary repairs to
damaged, corroded, or eroded areas of pressure "Fillet-welded patches may be used to
Company make interim repairs to damaged,
vessel components"
(NonVoter) corroded, or eroded areas of pressure
vessel components"
4 John Reynolds 8.1.5.1.1e Technical Although I'm OK with most of this change; however Suggest changing "e" to read "due
Shell Global I see a potential problem with making a "due date date for installing a more permanent
Solutions (US) Inc. for installing a permanent repair" as mandatory i.e. repair, where necessary".
following a "shall" statement because of the
(Negative) previous statement that these interim repairs "may
remain in place for longer periods of time....".
5 Peter Hunt 3.6, 7.8, Technical I have no idea what the difference is between leave temporary as the operative word
Suncor Energy, Inc. 2, interim and temporary. unless in the definition we can
8.1.5.1.1 differentiate between the two words
(Negative) Here is a definition I found for interim:
"serving as a temporary measure until something
more complete and permanent can be established"
They appear to be one and the same.
Page 1 of 2
API electronic balloting template/version April 2003
API Ballot Comments and Resolution
Ballot: 510-26-07 Interim Repairs Proposal: Replace the term “temporary repairs” with” interim Ballot ID: 1217 Date: September 10, 2007
repairs” to better describe the potential longevity of such repairs.
1 2 3 4 5 6
Voter Name Clause No./ Type of Comment (justification for change) by the Voting Proposed change by the Voting Member Comment Resolution
# (Vote) Subclause Comment Member
No./Annex
(e.g. 3.1)
6 Owen Konski Technical Overall, I agree with the ballot. I still have difficulty Some how place or document a
Syncrude Canada with "interim" as it is still subjective and can be requirement (in the risk
Ltd. open to selective adjustment. Too many times assessment?)that defines a time frame
'interim' winds up being longer than first thought or for the interim repair. Can this time
(Affirmative) anticipated - for various reasons. parameter be part of a definition for
'interim'?
7 Nat Faransso 8.1.5.1.1 Technical The word "suitable" has been removed due to I Recommend deleting "more" before
KBR being subjective. The replacement word "more" is permanent repairs.
also subjective and does not seem to serve the
(Affirmative) intent.
8 Kenneth Tam Editorial 8.1.5.1.2.1 - In the first line, change the word
(Affirmative) temporary to interim to read ....to make interim
repairs ....
Page 2 of 2
API electronic balloting template/version April 2003
Ballot 510-27-07
a. originally designed and fabrication based on an applicable construction code with additional
consideration of cyclic service operation;
c. potential for fatigue cracking of the vessel and contributing fatigue propagation from internal
supports attached to the vessel;
d. the need for appropriate NDE to detect fatigue failure or distortion [such as external
ultrasonic shearwave flaw detection, external and/or internal wet fluorescent magnetic
particle testing, time-of-flight diffraction ultrasonics (TOFD), out-of-roundness measurement,
and measurements of weld seams for peaking or flattening].
Page 1 of 1
API Ballot Summary Sheet
9/10/2007
VotingCategory
Vote Results
Voter Interest Category Company Comments Affirmative Negative Abstain Did Not Vote
Moraya Al-Gahtani Operator-User Saudi Aramco No X
Gregory Alvarado Manufacturer Equity Engineering Group, Inc. Yes X
Roger Armstrong Operator-User Monsanto Company No X
John Britton Manufacturer Det Norske Veritas (USA), Inc. No X
Robert Dolejs Manufacturer UOP LLC No X
Roger Duvic Contractor Vessel Statistics Inc. No X
Wayne Elliott Manufacturer Elliott Services, Inc. No X
Eric Ellis Operator-User Lyondell Houston Refining, LP No X
Nat Faransso Contractor KBR Yes X
John Fiore Manufacturer FTS, Inc. No X
Frank Furillo Operator-User ExxonMobil Corp. No X
Mark Geisenhoff Operator-User Flint Hills Resources, LP No X
Craig Harley Contractor General Physics Corp. No X
Gary Heath Manufacturer All Tech Inspection No X
Peter Hunt Operator-User Shell Canada Ltd. No X
Peter Hunt Operator-User Shell Canada Ltd. No X
Morris Kline Manufacturer HMT Inspection No X
Owen Konski Operator-User Syncrude Canada Ltd. No X
Dennis Layman Operator-User BP p.l.c. Yes X
John Ludman Operator-User DuPont Engineering No X
John McMillan Manufacturer Mechanical Integrity Inc. No X
Rick Nichols Manufacturer Roddey Engineering Services, Inc. Yes X
Robert Pechacek Manufacturer General Electric Inspection Services No X
John Reynolds Consultant Shell Global Solutions (US) Inc. Yes X
Delano Richie Manufacturer PetroChem Inspection Services No X
James Riley Operator-User Chevron Energy & Technology Company No X
Clay Rodery Operator-User BP North America Inc. No X
1
API Ballot Summary Sheet
9/10/2007
VotingCategory
Roy Schubert Operator-User Shell Canada Energy, Ltd. Yes X
Michael Shallis Manufacturer Acuren Inspection, Inc. No X
Larry Siqueiros Operator-User Marathon Petroleum Company LLC No X
Ryan Sitton Consultant Pinnacle Asset Integrity Services No X
Robert Smallwood Contractor No X
Kelly Smith Operator-User ConocoPhillips No X
Nick Sowa Manufacturer Conam Inspection & Engineering Service No X
Kenneth Tam Consultant No X
Roland Valdes Manufacturer Inspection Solutions, LLC No X
John Watson Operator-User Dow Chemical No X
Steven Wells Manufacturer Pro-Inspect Inc. No X
Total Responses: 31
Total Ballots: 38
Response Rate (Affirmative / Total Ballots): 74% Must be > 50%
Approval Rate (Affirmative / [Affirmative + Negative] ): 93% Must be > 67%
Consensus: YES
2
API Ballot Comments and Resolution
Ballot: 510-27-07 Cyclic Service Vessels Proposal: Incorporates relevant information from the SCI Ballot ID: 1209 Date: September 10, 2007
(Reballot) Roundtable on PSA and other related cyclic service.
1 2 3 4 5 6
Voter Name Clause No./ Type of Comment (justification for change) by the Voting Proposed change by the Voting Member Comment Resolution
# (Vote) Subclause Comment Member
No./Annex
(e.g. 3.1)
1 Gregory Alvarado Technical See changes below. 5.4.4 Vessels in cyclic service (cycles
Equity Engineering of pressure, temperature, or
Group, Inc. combinations of both pressure and
temperature) should be evaluated for
(Negative)
potential failures. The following
considerations should be evaluated
where applicable for vessels in cyclic
service:
a. originally designed and fabrication
based on an applicable construction
code with additional consideration of
cyclic service operation;
b. potential for internal or external
corrosion (e.g. corrosion under
insulation), cracking, or other types of
damage during cycling and at steady
state;
c. potential for fatigue cracking of the
vessel and contributing fatigue
propagation from internal or external
vessel attachments, repairs,
modifications, corrosion, damage (e.g.
gouges);
d. engineering analysis to determine
maximum tolerable flaw sizes and
critical locations to assist in selection of
NDE of suitable sensitivity and areas
for inspection;
e. the need for appropriate NDE to
detect fatigue failure or distortion [such
as external ultrasonic shearwave flaw
detection, external and/or internal wet
fluorescent magnetic particle testing,
Page 1 of 4
API electronic balloting template/version April 2003
API Ballot Comments and Resolution
Ballot: 510-27-07 Cyclic Service Vessels Proposal: Incorporates relevant information from the SCI Ballot ID: 1209 Date: September 10, 2007
(Reballot) Roundtable on PSA and other related cyclic service.
1 2 3 4 5 6
Voter Name Clause No./ Type of Comment (justification for change) by the Voting Proposed change by the Voting Member Comment Resolution
# (Vote) Subclause Comment Member
No./Annex
(e.g. 3.1)
Page 2 of 4
API electronic balloting template/version April 2003
API Ballot Comments and Resolution
Ballot: 510-27-07 Cyclic Service Vessels Proposal: Incorporates relevant information from the SCI Ballot ID: 1209 Date: September 10, 2007
(Reballot) Roundtable on PSA and other related cyclic service.
1 2 3 4 5 6
Voter Name Clause No./ Type of Comment (justification for change) by the Voting Proposed change by the Voting Member Comment Resolution
# (Vote) Subclause Comment Member
No./Annex
(e.g. 3.1)
7 John Reynolds 5.4.4 Technical While I whole heartedly agree with the need for this Delete 5.4.4b and revise 5.4.4a a to
Shell Global addition since it closes a long standing "hole" in our read: "Was the vessel originally
Solutions (US) Inc. code, I disagree that we need a statement about designed and fabricated based on an
consideration for CUI. CUI is covered elsewhere in applicable construction code with due
(Negative)
510 and applies to all vessels regardless of consideration to cyclic service
whether they are in cyclic service or not. The other operation?" Then revise the other two
three considerations are specific to cyclic service, considerations to make them questions
where CUI service is not. I have no problem with to match the format of "a" above.
mentioning CUI as a potentially compounding issue
in a follow-on sentence, but don't think we should Stike the word "internal" from "c", since
confuse the fatigue issue by adding it to the list in fatigue crack can eminate from either
the manner shown. internal or external support
attachments.
Also revise the list of considerations into questions
for consideration, as shown below, and make these Then make the lead-in sentence a
fatigue "considerations" a requirement, not a "shall" statement instead of a "should"
suggestion. Also revise the lead-in sentence to statement to read" The following
draw attention to the fact that these considerations considrations shall be evaluated for
are for their impact on inspection plans, which is their impact on inspection plans where
sort-of assumed but not implicitly stated. applicable for vessels in cyclic service"
Add "cracking" before failures at the
end of the first sentence.
8 Roland Goodman 5.4.4 Editorial Delete "pressure and temperature" in the 5.4.4 Vessels in cyclic service (cycles
American parenthesis. of pressure, temperature, or
Petroleum Institute combinations of both) should be
Add commas before and after "where applicable".
evaluated for potential failures. The
(NonVoter)
Replace "an" with "the" in item (a). following considerations should be
evaluated, where applicable, for
vessels in cyclic service:
a. originally designed and fabrication
based on the applicable construction
code with additional consideration of
cyclic service operation;
Page 3 of 4
API electronic balloting template/version April 2003
API Ballot Comments and Resolution
Ballot: 510-27-07 Cyclic Service Vessels Proposal: Incorporates relevant information from the SCI Ballot ID: 1209 Date: September 10, 2007
(Reballot) Roundtable on PSA and other related cyclic service.
1 2 3 4 5 6
Voter Name Clause No./ Type of Comment (justification for change) by the Voting Proposed change by the Voting Member Comment Resolution
# (Vote) Subclause Comment Member
No./Annex
(e.g. 3.1)
9 Dennis Layman 5.4.4 Technical BP supports the proposal; however, adding a more
BP p.l.c. clear definition of what constitutes "cyclic service"
should be considered. Most vessels are subject to
(Affirmative) pressure and/or temperature changes. The
magnitude and frequency are the concerns. As an
alternative to a definition, perhaps adding a few
examples of cyclic service vessels may be
beneficial.
Page 4 of 4
API electronic balloting template/version April 2003
Ballot 510-28-07
SECTION 2—REFERENCES
The most recent editions of the following standards, codes, and specifications are cited in this
inspection code.
ASME
PCC-2-2006 Repair of Pressure Equipment and Piping
Page 1 of 2
Ballot 510-28-07
Page 2 of 2
API Ballot Summary Sheet
9/10/2007
VotingCategory
Vote Results
Voter Interest Category Company Comments Affirmative Negative Abstain Did Not Vote
Moraya Al-Gahtani Operator-User Saudi Aramco No X
Gregory Alvarado Manufacturer Equity Engineering Group, Inc. No X
Roger Armstrong Operator-User Monsanto Company No X
John Britton Manufacturer Det Norske Veritas (USA), Inc. No X
Robert Dolejs Manufacturer UOP LLC No X
Roger Duvic Contractor Vessel Statistics Inc. No X
Wayne Elliott Manufacturer Elliott Services, Inc. No X
Eric Ellis Operator-User Lyondell Houston Refining, LP No X
Nat Faransso Contractor KBR No X
John Fiore Manufacturer FTS, Inc. No X
Frank Furillo Operator-User ExxonMobil Corp. No X
Mark Geisenhoff Manufacturer Flint Hills Resources, LP No X
Craig Harley Contractor General Physics Corp. No X
Gary Heath Manufacturer All Tech Inspection No X
Peter Hunt Operator-User Shell Canada Ltd. Yes X
Morris Kline Manufacturer HMT Inspection No X
Owen Konski Operator-User Syncrude Canada Ltd. No X
Dennis Layman Operator-User BP p.l.c. No X
John Ludman Operator-User DuPont Engineering No X
John McMillan Manufacturer Mechanical Integrity Inc. No X
Rick Nichols Manufacturer Roddey Engineering Services, Inc. Yes X
Robert Pechacek Manufacturer General Electric Inspection Services No X
John Reynolds Consultant Shell Global Solutions (US) Inc. Yes X
Delano Richie Manufacturer PetroChem Inspection Services No X
James Riley Operator-User Chevron Energy & Technology Company No X
Richard Roberts Contractor Quest TruTec No X
Clay Rodery Operator-User BP North America Inc. No X
1
API Ballot Summary Sheet
9/10/2007
VotingCategory
Roy Schubert Operator-User Shell Canada Energy, Ltd. Yes X
Michael Shallis Manufacturer Acuren Inspection, Inc. No X
Larry Siqueiros Operator-User Marathon Petroleum Company LLC No X
Ryan Sitton Consultant Pinnacle Asset Integrity Services No X
Robert Smallwood Contractor No X
Kelly Smith Operator-User ConocoPhillips No X
Nick Sowa Manufacturer Conam Inspection & Engineering Service No X
Kenneth Tam Consultant No X
Roland Valdes Manufacturer Inspection Solutions, LLC No X
John Watson Operator-User Dow Chemical No X
Steven Wells Manufacturer Pro-Inspect Inc. No X
Total Responses: 31
Total Ballots: 38
Response Rate (Affirmative / Total Ballots): 82% Must be > 50%
Approval Rate (Affirmative / [Affirmative + Negative] ): 100% Must be > 67%
Consensus: YES
2
API Ballot Comments and Resolution
Ballot: 510-28-07 ASME PCC-2 References Proposal: Adds references to ASME PCC-2 covering vessel Ballot ID: 1210 Date: September 10, 2007
component repair and pressure/tightness testing.
1 2 3 4 5 6
Voter Name Clause No./ Type of Comment (justification for change) by the Voting Proposed change by the Voting Member Comment Resolution
# (Vote) Subclause Comment Member
No./Annex
(e.g. 3.1)
1 David Martinez Other I have reviewed the ballot item and agree with the
Hovensa, LLC proposed changes as written.
(NonVoter)
2 Takayasu Tahara Technical
Petroleum
Association of
Japan
(NonVoter)
3 Rick Nichols 8.1.5.2.1 Editorial If there is any chance that the Section numbers will
Roddey change in the PCC document, suggest that we not
Engineering include specific section number references. The
Services, Inc. user can look in the table of contents or index to
find the right section. If the section numbers
(Affirmative) should change, the S/C will have to come back and
edit 510.
4 Roy Schubert 8.1.5.1.5 Technical remove the word for after the words"welded leak when using a welded leak box as an
Shell Canada box" interim
Energy, Ltd. repair, may be found in ASME PCC-2,
(Affirmative) Part 2.
5 Peter Hunt 8.1.5.1.5 Editorial Leak boxes may also be mechanical types (i.e. "A welded or mechanical leak box
Shell Canada Ltd. bolted) as well as welded. Add mechanical leak consists of an ..."
boxes to "A welded leak box consists of an ..." The
(Affirmative) PCC includes mechanical leak boxes even though
the title is Welded Leak Boxes (working off a draft
of this document)
6 John Reynolds 8.1.5.1.5 Technical In 8.1.5.2.1, put the new "f" right after the current Add a new paragraph 5.1.5.1.6 which
Shell Global and "c", since they are closely related. would read substantially the same as
Solutions (US) Inc. 8.1.5.2.1 8.1.5.1.5, but refer to the PCC-2
Why not reference the rest of the articles in PCC-2, mechanical clamps article.
(Affirmative) especially the mechanical clamps article in an
additional paragraph 5.1.5.1.6?
Page 1 of 2
API electronic balloting template/version April 2003
API Ballot Comments and Resolution
Ballot: 510-28-07 ASME PCC-2 References Proposal: Adds references to ASME PCC-2 covering vessel Ballot ID: 1210 Date: September 10, 2007
component repair and pressure/tightness testing.
1 2 3 4 5 6
Voter Name Clause No./ Type of Comment (justification for change) by the Voting Proposed change by the Voting Member Comment Resolution
# (Vote) Subclause Comment Member
No./Annex
(e.g. 3.1)
7 Roland Goodman 5.8.1.3 Editorial See editorial changes. 5.8.1.3 See ASME PCC-2, Part 5,
American Article 5.1, for information on
Petroleum Institute determining the reasons for and type of
test, the test pressure, and a
(NonVoter) procedure for pressure and tightness
testing.
8 Roland Goodman 8.1.5.1.5 Editorial See editorial changes on the last sentence. See ASME PCC-2, Part 2, for
American precautions, limitations, and
Petroleum Institute considerations when using a welded
leak box for as an interim repair.
(NonVoter)
9 Roland Goodman 8.1.5.2.1 Technical Add paragraph numbers for ease of reference and 8.1.5.2.2 Repairing a crack at a
American delete the titles of the PCC-2 sections (the titles will discontinuity, where stress
Petroleum Institute be included in references section). concentrations are high, (e.g. crack in
a nozzle-to-shell weld) should not be
(NonVoter)
attempted without prior consultation
with an engineer.
8.1.5.2.3 See the following sections in
ASME PCC-2 for information on the
permanent repair techniques listed in
8.1.5.2.1 and other permanent repairs:
-- Part 2, Article 2.1;
-- Part 2, Article 2.2;
-- Part 3, Article 3.1;
-- Part 3, Article 3.3;
-- Part 3, Article 3.4.
10 Roland Goodman 8.1.5.2.2 Editorial See editorial changes. See ASME PCC-2, Part 2, Article 2.1,
American for information on replacing portions of
Petroleum Institute pressure-retaining vessel shells by
using insert plates.
(NonVoter)
Page 2 of 2
API electronic balloting template/version April 2003
Ballot 510-29-07
Page 1 of 3
Ballot 510-29-07
Current API 510 9th Edition wording with inserted changes to be made (Changes in
bold/underline)
7.4.2.1 For a corroded area of considerable size the wall thicknesses may be averaged over a
length not exceeding the following:
Page 2 of 3
Ballot 510-29-07
For vessels with inside diameters less than or equal to 60 in. (150 cm), one-half the vessel
diameter or 20 in. (50 cm), whichever is less.
For vessels with inside diameters greater than 60 in. (150 cm), one-third the vessel diameter or
40 in. (100 cm), whichever is less.
7.4.2.2 Along the designated length, the thickness readings should be equally spaced. For
areas of considerable size, multiple lines in the corroded area may have to be evaluated to
determine which length has the lowest average thickness.
7.4.2.3 If circumferential stresses govern, (typical for most vessels) the thickness readings are
taken along a longitudinal length. If longitudinal stresses govern (because of wind loads or other
factors), the thickness readings are taken along a circumferential length (an arc).
7.4.2.4 When performing corrosion averaging near structural continuities (e.g. a nozzle,
conical section transition, and flange connection), the limits for thickness averaging shall be
considered separately for the reinforcement window area and the area outside/adjacent to the
reinforcement window a nozzle, the designated length shall not extend within the limits of the
reinforcement as defined in the construction code.
a. When performing corrosion averaging near a nozzle, the designated length shall not extend
within the limits of the reinforcement as defined in the construction code. Consideration shall be
given to any extra reinforcement included in the nozzle reinforcement design (e.g. a larger
extended reinforcing pad diameter to address piping load considerations).
b. Technical considerations for corrosion averaging within the reinforcement window for
structural discontinuities is provided in API 579-1/ASME FFS-1, Part 4.
7.4.2.5 When performing remaining life calculations in 7.2, the lowest average of any length in
the corroded area is substituted for tactual.
Page 3 of 3
API Ballot Summary Sheet
9/10/2007
VotingCategory
Vote Results
Voter Interest Category Company Comments Affirmative Negative Abstain Did Not Vote
Moraya Al-Gahtani Operator-User Saudi Aramco No X
Gregory Alvarado Manufacturer Equity Engineering Group, Inc. Yes X
Roger Armstrong Operator-User Monsanto Company No X
John Britton Manufacturer Det Norske Veritas (USA), Inc. No X
Robert Dolejs Manufacturer UOP LLC No X
Roger Duvic Contractor Vessel Statistics Inc. No X
Wayne Elliott Manufacturer Elliott Services, Inc. No X
Eric Ellis Operator-User Lyondell Houston Refining, LP No X
Nat Faransso Contractor KBR No X
John Fiore Manufacturer FTS, Inc. No X
Frank Furillo Operator-User ExxonMobil Corp. No X
Mark Geisenhoff Manufacturer Flint Hills Resources, LP No X
Craig Harley Contractor General Physics Corp. No X
Gary Heath Manufacturer All Tech Inspection No X
Peter Hunt Operator-User Shell Canada Ltd. No X
Morris Kline Manufacturer HMT Inspection No X
Owen Konski Operator-User Syncrude Canada Ltd. No X
Dennis Layman Operator-User BP p.l.c. No X
John Ludman Operator-User DuPont Engineering No X
John McMillan Manufacturer Mechanical Integrity Inc. No X
Rick Nichols Manufacturer Roddey Engineering Services, Inc. No X
Robert Pechacek Manufacturer General Electric Inspection Services No X
John Reynolds Consultant Shell Global Solutions (US) Inc. Yes X
Delano Richie Manufacturer PetroChem Inspection Services No X
James Riley Operator-User Chevron Energy & Technology Company Yes X
Richard Roberts Contractor Quest TruTec No X
Clay Rodery Operator-User BP North America Inc. No X
1
API Ballot Summary Sheet
9/10/2007
VotingCategory
Roy Schubert Operator-User Shell Canada Energy, Ltd. No X
Michael Shallis Manufacturer Acuren Inspection, Inc. No X
Larry Siqueiros Operator-User Marathon Petroleum Company LLC No X
Ryan Sitton Consultant Pinnacle Asset Integrity Services No X
Robert Smallwood Contractor No X
Kelly Smith Operator-User ConocoPhillips No X
Nick Sowa Manufacturer Conam Inspection & Engineering Service No X
Kenneth Tam Consultant No X
Roland Valdes Manufacturer Inspection Solutions, LLC No X
John Watson Operator-User Dow Chemical No X
Steven Wells Manufacturer Pro-Inspect Inc. No X
Total Responses: 31
Total Ballots: 38
Response Rate (Affirmative / Total Ballots): 76% Must be > 50%
Approval Rate (Affirmative / [Affirmative + Negative] ): 100% Must be > 67%
Consensus: YES
2
API Ballot Comments and Resolution
Ballot: 510-29-07 Corrosion Averaging in Proposal: Clarify the limit for corrosion averaging within and near Ballot ID: 1211 Date: September 10, 2007
Reinforced Areas structural discontinuities, and reference the applicable parts of
API 579 covering corrosion thickness averaging in areas where
there are structural discontinuities.
1 2 3 4 5 6
Voter Name Clause No./ Type of Comment (justification for change) by the Voting Proposed change by the Voting Member Comment Resolution
# (Vote) Subclause Comment Member
No./Annex
(e.g. 3.1)
1 Gregory Alvarado 7.4.2.4 Technical Simply stated, all FFS rules should be removed
Equity Engineering from API 510 and API 570 and replaced with a
Group, Inc. direct reference to API 579-1/ASME FFS-1. The
thickness averaging rules in API 510 and API 570
(YetToVote)
are not correct and may result in unconservative
assessments. In addition, what is in these
documents is confusing and of limited.
We are now on the second edition of API 579, the
expertise for FFS assessments reside in the
API/ASME FFSJC, its time to remove all FFS rules
from API 510 and API 570. This is duplication of
material, duplication of effort, and likely a waste of
committee members time.
In addition, we just published the joint API/ASME
document to enhance acceptance by jurisdictions.
Duplication of rules in API 510 and API 570 only
confuse the issue. In fact, a jurisdiction may
decide to limit FFS evaluations based on the old
FFS rules in API 510 and API 570, not a good
situation.
We should be pointing users of 510. 570 and 653
inspection documents to the API/ASME joint
standard for the reasons stated above.
Greg Alvarado on behalf of D.A. Osage
2 David Martinez Other I have reviewed the ballot item and agree with the
Hovensa, LLC proposed changes as written.
(NonVoter)
Page 1 of 3
API electronic balloting template/version April 2003
API Ballot Comments and Resolution
Ballot: 510-29-07 Corrosion Averaging in Proposal: Clarify the limit for corrosion averaging within and near Ballot ID: 1211 Date: September 10, 2007
Reinforced Areas structural discontinuities, and reference the applicable parts of
API 579 covering corrosion thickness averaging in areas where
there are structural discontinuities.
1 2 3 4 5 6
Voter Name Clause No./ Type of Comment (justification for change) by the Voting Proposed change by the Voting Member Comment Resolution
# (Vote) Subclause Comment Member
No./Annex
(e.g. 3.1)
3 John Reynolds 7.4.2.4 Technical I support this improvement to this section. My 7.4.2.4 When performing corrosion
Shell Global comments are minor editorial attempts to averaging near structural
Solutions (US) Inc. improvement understanding and wording. Revise discontinuities (such as a nozzle,
to add other areas of high local stress, as shown. conical section transition, and flange
(Affirmative) Structural continuities did not seem like the right connection), the limits for thickness
description, so I changed it to "discontinuties", but averaging must be considered
I'm not sure that's the right word, but separately for the reinforcement
"reinforcement window area" is not all inclusive of window area (or other area of local
the type of joint that we're addressing, though it high stress) and the area
obviously covers nozzles. outside/adjacent to the reinforcement
window (or other area of local high
stress).
a) revise second sentence to add wind
loads: Consideration must be given to
any extra reinforcement included in the
nozzle reinforcement design (such as a
larger extended reinforcing pad
diameter to address piping load
considerations, or wind loads).
4 John Reynolds 7.4.2.4a Technical Para a: "When performing corrosion averaging Perhaps simply stating this is cleaner/
Shell Global near a nozzle, the designated length shall not better : " b. Fitness-for-service for
Solutions (US) Inc. extend within the limits of the reinforcement as corroded areas within the
defined in the construction code." clashes with reinforcement window for structural
(Affirmative) Para b. Technical considerations for corrosion discontinuities is provided in API 579-
averaging within the reinforcement window for 1/ASME FFS-1, XXXX 2007 (API 579
structural discontinuities is provided in API 579- SECOND EDITION) Part 4. "
1/ASME FFS-1, XXXX 2007 (API 579 SECOND
EDITION) Part 4.
Page 2 of 3
API electronic balloting template/version April 2003
API Ballot Comments and Resolution
Ballot: 510-29-07 Corrosion Averaging in Proposal: Clarify the limit for corrosion averaging within and near Ballot ID: 1211 Date: September 10, 2007
Reinforced Areas structural discontinuities, and reference the applicable parts of
API 579 covering corrosion thickness averaging in areas where
there are structural discontinuities.
1 2 3 4 5 6
Voter Name Clause No./ Type of Comment (justification for change) by the Voting Proposed change by the Voting Member Comment Resolution
# (Vote) Subclause Comment Member
No./Annex
(e.g. 3.1)
5 Roland Goodman 7.4.2.4b Editorial See editorial change. b. See 579-1/ASME FFS-1, Part 4, for
American technical considerations when
Petroleum Institute performing corrosion averaging within
the reinforcement window for structural
(NonVoter) discontinuities.
6 James Riley Technical Correct the typo for the wording "structural
Chevron Energy & continuities" to read correctly as "structural
Technology discontinuities"
Company
(Affirmative)
7 John O'Brien 7.4.2.4 Editorial 7.4.2.4 line one has a typo I believe and it should Make the correction as identified in the
Chevron Energy read 'When performing corrosion averaging near comment.
Technology structural discontinuities'
Company
(NonVoter)
Page 3 of 3
API electronic balloting template/version April 2003
Ballot 570-25-07
The physical, technical, environmental, business and process safety constraints within which a
process unit must be operated. The operating parameters that provide for just the mechanical
integrity limitations are referred to as the integrity operational envelope.
The monitoring of key and critical process parameters that are needed to ensure that the
process stays within the operational envelope. Those process parameters that greatly influence
corrosiveness and possible materials degradation within an operating process are referred to as
integrity-based process parameters.
The following may effectively be used to ensure safe production and proactively monitor piping
condition:
Page 1 of 1
API Ballot Summary Sheet
9/10/2007
Ballot: 570-25-07 Operational Envelope & Process Parameter Monitoring Ballot ID: 1212
VotingCategory
Vote Results
Voter Interest Category Company Comments Affirmative Negative Abstain Did Not Vote
Moraya Al-Gahtani Operator-User Saudi Aramco No X
Gregory Alvarado Manufacturer Equity Engineering Group, Inc. Yes X
Roger Armstrong Operator-User Monsanto Company No X
John Britton Manufacturer Det Norske Veritas (USA), Inc. No X
Robert Dolejs Manufacturer UOP LLC Yes X
Roger Duvic Contractor Vessel Statistics Inc. No X
Wayne Elliott Manufacturer Elliott Services, Inc. No X
Eric Ellis Operator-User Lyondell Houston Refining, LP No X
Nat Faransso Contractor KBR No X
John Fiore Manufacturer FTS, Inc. No X
Frank Furillo Operator-User ExxonMobil Corp. No X
Mark Geisenhoff Manufacturer Flint Hills Resources, LP No X
Craig Harley Contractor General Physics Corp. No X
Gary Heath Manufacturer All Tech Inspection No X
Peter Hunt Operator-User Shell Canada Ltd. Yes X
Morris Kline Manufacturer HMT Inspection No X
Owen Konski Operator-User Syncrude Canada Ltd. No X
Dennis Layman Operator-User BP p.l.c. No X
John Ludman Operator-User DuPont Engineering No X
John McMillan Manufacturer Mechanical Integrity Inc. No X
Rick Nichols Manufacturer Roddey Engineering Services, Inc. No X
Robert Pechacek Manufacturer General Electric Inspection Services No X
John Reynolds Consultant Shell Global Solutions (US) Inc. Yes X
Delano Richie Manufacturer PetroChem Inspection Services No X
James Riley Operator-User Chevron Energy & Technology Company No X
Richard Roberts Contractor Quest TruTec No X
Clay Rodery Operator-User BP North America Inc. No X
1
API Ballot Summary Sheet
9/10/2007
Ballot: 570-25-07 Operational Envelope & Process Parameter Monitoring Ballot ID: 1212
VotingCategory
Roy Schubert Operator-User Shell Canada Energy, Ltd. No X
Michael Shallis Manufacturer Acuren Inspection, Inc. No X
Larry Siqueiros Operator-User Marathon Petroleum Company LLC No X
Ryan Sitton Consultant Pinnacle Asset Integrity Services No X
Robert Smallwood Contractor No X
Kelly Smith Operator-User ConocoPhillips No X
Nick Sowa Manufacturer Conam Inspection & Engineering Service No X
Kenneth Tam Consultant No X
Roland Valdes Manufacturer Inspection Solutions, LLC No X
John Watson Operator-User Dow Chemical No X
Steven Wells Manufacturer Pro-Inspect Inc. No X
Total Responses: 32
Total Ballots: 38
Response Rate (Affirmative / Total Ballots): 79% Must be > 50%
Approval Rate (Affirmative / [Affirmative + Negative] ): 94% Must be > 67%
Consensus: YES
2
API Ballot Comments and Resolution
Ballot: 570-25-07 Operational Envelope & Proposal: Add definitions for “operational envelope” and Ballot ID: 1212 Date: September 10, 2007
Process Parameter Monitoring “process parameter monitoring” along with new sections that
discuss these practices.
1 2 3 4 5 6
Voter Name Clause No./ Type of Comment (justification for change) by the Voting Proposed change by the Voting Member Comment Resolution
# (Vote) Subclause Comment Member
No./Annex
(e.g. 3.1)
1 Gregory Alvarado Technical I understand what the authors are attmepting to do 3.xx operational envelope
Equity Engineering with references to words such as physical,
environment and business and process safety. Operating envelopes or limits are
Group, Inc. defined and applied to key and critical
See edits below which try to make the definitions
(Negative) more understandable to an inspector and other process parameters. Operating
technical people who are responsible for following outside the envelope/s could lead to
570 rules and guidelines. premature failure of equiment and
subsequent release of materials. This
release could negatively impact health
and safety, the environment and
business or reliability performance.
3.xx process parameter monitoring
The monitoring of key and critical
process parameters that are needed to
ensure that the process stays within
the operational envelope. Those
process parameters that greatly
influence equipment or materials
degradation within an operating
process are equipment integrity-based
process parameters.
2 David Martinez Other I have reviewed the ballot item and agree with the
Hovensa, LLC proposed changes as written.
(NonVoter)
3 Peter Hunt 3.XX Editorial Need to add regulatory on fisrt sentence. The physical, technical, environmental,
Shell Canada Ltd. business, regulatory and process
safety constraints within which a
(Affirmative)
process unit must be operated.
Page 1 of 3
API electronic balloting template/version April 2003
API Ballot Comments and Resolution
Ballot: 570-25-07 Operational Envelope & Proposal: Add definitions for “operational envelope” and Ballot ID: 1212 Date: September 10, 2007
Process Parameter Monitoring “process parameter monitoring” along with new sections that
discuss these practices.
1 2 3 4 5 6
Voter Name Clause No./ Type of Comment (justification for change) by the Voting Proposed change by the Voting Member Comment Resolution
# (Vote) Subclause Comment Member
No./Annex
(e.g. 3.1)
4 John Reynolds 3.xx Technical Suggest we adopt the definition that has been integrity operating envelope
Shell Global successfully balloted for the ISIJC
integrity operating window
Solutions (US) Inc.
(Negative) Established limits for process variables
that may can affect the integrity of the
equipment if the process operation
deviates from the established limits for
a predetermined amount of time.
5 John Reynolds 6.1.2 Technical Suggest we adopt the wording of the ISIJC for 4.1.2 Integrity operating
Shell Global Integrity Operating Envelopes which has been envelopes (windows) should be
Solutions (US) Inc. successfully balloted. established for all variables process
parameters (both physical and
(Negative) chemical) that could impact equipment
integrity if not properly controlled.
Examples of the process parameters
variables include temperatures,
pressures, fluid velocities, pH, flow
rates, chemical or water injection rates,
levels of corrosive constituents,
chemical composition, etc. Key
process parameters for integrity
operatingor envelopes should be
identified and implemented, upper and
lower limits established, as needed,
and variations deviations from these
limits should be brought to the
attention of inspection/engineering
personnel. Particular attention to
monitoring integrity operating
envelopes should also be provided
during start-ups, shutdowns and
significant process upsets.
6 John Reynolds 3.xx Editorial Slight edit change to allign with IOE terminology First sentence: add "integrity" in front
Shell Global Process from ISIJC of operational
Solutions (US) Inc. Parameter
Monitoring
(Negative)
Page 2 of 3
API electronic balloting template/version April 2003
API Ballot Comments and Resolution
Ballot: 570-25-07 Operational Envelope & Proposal: Add definitions for “operational envelope” and Ballot ID: 1212 Date: September 10, 2007
Process Parameter Monitoring “process parameter monitoring” along with new sections that
discuss these practices.
1 2 3 4 5 6
Voter Name Clause No./ Type of Comment (justification for change) by the Voting Proposed change by the Voting Member Comment Resolution
# (Vote) Subclause Comment Member
No./Annex
(e.g. 3.1)
7 Robert Dolejs 3.xx Editorial 1. Change the second sentence of the operational
UOP LLC envelope definition as follows: The operating
parameters that establish a boundary for just the
(Affirmative)
mechancial integrity limitations are referred to as
the operational envelope.
2. delete the second sentence in the process
parameter monitoring defintion or make it a
separate defintiion.
8 Roland Goodman 3 Editorial The second sentences of both definitions should 3.xx operational envelope
American be included as notes.
The physical, technical, environmental,
Petroleum Institute business and process safety
(NonVoter) constraints within which a process unit
must be operated.
NOTE The operating parameters that
provide for just the mechanical integrity
limitations are referred to as the
integrity operational envelope.
3.xx process parameter monitoring
The monitoring of key and critical
process parameters that are needed to
ensure that the process stays within
the operational envelope.
NOTE Those process parameters
that greatly influence corrosiveness
and possible materials degradation
within an operating process are
referred to as integrity-based process
parameters.
Page 3 of 3
API electronic balloting template/version April 2003
Ballot 570-26-07
An effective inspection program includes the following three four elements, which help identify
the potential for service specific and localized corrosion and select appropriate TMLs:
a. An inspector with knowledge of the service and where corrosion is likely to occur.
c. Communication from operating personnel when process upsets occur that may affect
corrosion rates.
d. Identification of piping that may be missed from the ordinary piping circuit inspection
programs that pose a degradation concern. Examples of piping that may inadvertently be
missed include instrument bridles for equipment connecting to piping circuits, temporary
piping used during maintenance outages, and swing-out spools.
Where a temporary (or swing-out) piping spool has not been removed prior process operation
start-up, the owner-user should verify that the temporary piping is either effectively isolated from
the process (such as double-block valve or isolation blind), or that the temporary piping is of
adequate material and mechanical design for the continued process operation. Particular
concern is raised for temporary piping that may become subject to high temperature sulfidation.
If the temporary piping is isolated and left for a significant period of time, lock-out/tag-out may
be considered to prevent inappropriate and inadvertent service.
Page 1 of 2
Ballot 570-26-07
A few examples of where this type of corrosion might be expected to occur include the following:
c. Unanticipated acid or caustic carryover from processes into non alloyed piping systems or
caustic carryover into steel piping systems that are not postweld heat treated.
f. Mixed grades of carbon steel piping in hot corrosive oil service [450°F (230°C) or higher
temperature and sulfur content in the oil greater than 0.5 percent by weight]. Note that non
silicon killed steel pipe, such as A-53 and API 5L, may corrode at higher rates than does
silicon killed steel pipe, such as A-106, especially in high-temperature sulfidic environments.
i. Hot-spot corrosion on piping with external heat tracing. In services that become much more
corrosive to the piping with increased temperature, such as caustic in carbon steel,
corrosion or stress corrosion cracking (SCC) can occur at hot spots that develop under low-
flow conditions.
Page 2 of 2
API Ballot Summary Sheet
9/10/2007
VotingCategory
Vote Results
Voter Interest Category Company Comments Affirmative Negative Abstain Did Not Vote
Moraya Al-Gahtani Operator-User Saudi Aramco No X
Gregory Alvarado Manufacturer Equity Engineering Group, Inc. Yes X
Roger Armstrong Operator-User Monsanto Company No X
John Britton Manufacturer Det Norske Veritas (USA), Inc. No X
Robert Dolejs Manufacturer UOP LLC No X
Roger Duvic Contractor Vessel Statistics Inc. No X
Wayne Elliott Manufacturer Elliott Services, Inc. No X
Eric Ellis Operator-User Lyondell Houston Refining, LP No X
Nat Faransso Contractor KBR Yes X
John Fiore Manufacturer FTS, Inc. No X
Frank Furillo Operator-User ExxonMobil Corp. No X
Mark Geisenhoff Manufacturer Flint Hills Resources, LP No X
Craig Harley Contractor General Physics Corp. Yes X
Gary Heath Manufacturer All Tech Inspection No X
Peter Hunt Operator-User Shell Canada Ltd. Yes X
Morris Kline Manufacturer HMT Inspection No X
Owen Konski Operator-User Syncrude Canada Ltd. No X
Dennis Layman Operator-User BP p.l.c. Yes X
John Ludman Operator-User DuPont Engineering No X
John McMillan Manufacturer Mechanical Integrity Inc. No X
Rick Nichols Manufacturer Roddey Engineering Services, Inc. No X
Robert Pechacek Manufacturer General Electric Inspection Services No X
John Reynolds Consultant Shell Global Solutions (US) Inc. Yes X
Delano Richie Manufacturer PetroChem Inspection Services No X
James Riley Operator-User Chevron Energy & Technology Company Yes X
Richard Roberts Contractor Quest TruTec No X
Clay Rodery Operator-User BP North America Inc. No X
1
API Ballot Summary Sheet
9/10/2007
VotingCategory
Roy Schubert Operator-User Shell Canada Energy, Ltd. No X
Michael Shallis Manufacturer Acuren Inspection, Inc. Yes X
Larry Siqueiros Operator-User Marathon Petroleum Company LLC No X
Ryan Sitton Consultant Pinnacle Asset Integrity Services No X
Robert Smallwood Contractor No X
Kelly Smith Operator-User ConocoPhillips No X
Nick Sowa Manufacturer Conam Inspection & Engineering Service No X
Kenneth Tam Consultant No X
Roland Valdes Manufacturer Inspection Solutions, LLC No X
John Watson Operator-User Dow Chemical No X
Steven Wells Manufacturer Pro-Inspect Inc. Yes X
Total Responses: 31
Total Ballots: 38
Response Rate (Affirmative / Total Ballots): 79% Must be > 50%
Approval Rate (Affirmative / [Affirmative + Negative] ): 97% Must be > 67%
Consensus: YES
2
API Ballot Comments and Resolution
Ballot: 570-26-07 Missed Piping Traps Proposal: Cover piping that may fall outside of a normal piping Ballot ID: 1213 Date: September 10, 2007
circuit inspection program and not be recognized as a being a
localized corrosion concern
1 2 3 4 5 6
Voter Name Clause No./ Type of Comment (justification for change) by the Voting Proposed change by the Voting Member Comment Resolution
# (Vote) Subclause Comment Member
No./Annex
(e.g. 3.1)
1 Gregory Alvarado Technical I added "no flow" to the examples of conditions and Where a temporary (or swing-out)
Equity Engineering suggest wording not be limited to particularly piping spool has not been removed
Group, Inc. sulfidation as this may cause readers to only prior process operation start-up, the
consider this one damage mechanism. We can owner-user should verify that the
(Affirmative) work this at the meeting. temporary piping is either effectively
isolated from the process (such as
double-block valve or isolation blind),
or that the temporary piping is of
adequate material and mechanical
design for the continued process
operation, including no flow. Particular
concern is raised for temporary piping
that may become subject to high
temperature sulfidation.
If the temporary piping is isolated and
left for a significant period of time, lock-
out/tag-out may be considered to
prevent inappropriate and inadvertent
service.
2 Craig Harley General Editorial Replace the term TML with CML.
General Physics
Corp.
(Affirmative)
3 David Martinez Other I have reviewed the ballot item and agree with the
Hovensa, LLC proposed changes as written.
(NonVoter)
4 Nat Faransso 5.3.5.d Editorial needs "to" between prior and process Add "to" between "prior" and "process
KBR (2nd Para,
1st line)
(Affirmative)
Page 1 of 3
API electronic balloting template/version April 2003
API Ballot Comments and Resolution
Ballot: 570-26-07 Missed Piping Traps Proposal: Cover piping that may fall outside of a normal piping Ballot ID: 1213 Date: September 10, 2007
circuit inspection program and not be recognized as a being a
localized corrosion concern
1 2 3 4 5 6
Voter Name Clause No./ Type of Comment (justification for change) by the Voting Proposed change by the Voting Member Comment Resolution
# (Vote) Subclause Comment Member
No./Annex
(e.g. 3.1)
Page 2 of 3
API electronic balloting template/version April 2003
API Ballot Comments and Resolution
Ballot: 570-26-07 Missed Piping Traps Proposal: Cover piping that may fall outside of a normal piping Ballot ID: 1213 Date: September 10, 2007
circuit inspection program and not be recognized as a being a
localized corrosion concern
1 2 3 4 5 6
Voter Name Clause No./ Type of Comment (justification for change) by the Voting Proposed change by the Voting Member Comment Resolution
# (Vote) Subclause Comment Member
No./Annex
(e.g. 3.1)
10 Roland Goodman 5.3.5 Editorial See editorial changes to the last two sentences in Special attention should be given to
American second paragraph. temporary piping that can become
Petroleum Institute subject to high temperature sulfidation.
If the temporary piping is isolated and
(NonVoter) left for a significant period of time, lock-
out/tag-out procedures may be used to
prevent inappropriate and inadvertent
service.
11 Dennis Layman 5.3.5 Technical The addition of paragraph 5.3.5.d is acceptable; "Where a temporary (or swing-out)
BP p.l.c. Service however, the proposed paragraph following item d. piping spool has not been removed
Specific includes recommended maintenance practices, prior to process operation start-up, the
(Affirmative) and which should not be part of an Inspection Code. owner-user should verify that the
Localized temporary piping is effectivey isolated
Corrosion from the process or verify that the
temporary piping is adequate material
and designed for the continued
process operation."
12 James Riley Technical Add the information in the RP 574 recent ballot,
Chevron Energy & definition for "deadlegs", Note list of piping to that
Technology in this ballot.
Company
(Affirmative)
Page 3 of 3
API electronic balloting template/version April 2003