Gas turbine compressor & turbine Deblading & blading timing

GT-12 Damage rectification 2003-2004

Major Activities Date Remarks


GT damage 05.11.2003
Top casing removed 13.11.2003
Rotor removal 15.11.2003
Rotor sent to Alstom works, 26.12.2003
Vadodara
Start of repair works on Comp. 05.01.2004
Casing
Finish with repair works on 29.01.2004
Comp. Casing
Start with re-assembly of 05.02.2004
Combustor
Blading works completed 21.02.2004
Complete pre-assembly of 28.02.2004
Combustor
Rotor received back from Alstom 04.03.2004
Works
Install Thermal block 13.03.2004
Motoroll 23.03.2004

GT-11 Damage rectification 2008

Major Activities Date Remarks


GT damage 03.07.2008
Top casing removed 12.07.2008
Rotor removal 13.07.2008 (Day shift)
Turbine & compressor 14.07.2008
blades/vanes removal started
Turbine & compressor 17.07.2008
blades/vanes removal
completed
Compressor Blades & vanes 18.09.2008 Two bladder (Day + Night shift)
Blading work started for 5 days & than after Day shift
Compressor Blades & vanes 07.10.2008
Blading work completed
Rotor positioning done 09.10.2008
Top casing positioning done 11.10.2008
1st Motoroll 15.10.2008
History of the compressor blades & vanes procurement

1. PR no 1100003170 DT 22.07.2008 raise.


2. PO no 4100004675 DT 23.07.2008 placed to M/s Alstom
3. Material received on 09.09.2008. Except Blade row-3 & 4 received on 04.10.2008 & Blade row-12
25.09.2008.

GT-11 C inspection 2011 Bladder schedule

Major Activities Date Remarks


Disassembly started 21.04.2011
Disassembly completed 22.04.2011
Assembly started 23.04.2011
Assembly completed 29.04.2011* * Material SHS A,B and Vane 1,2
arrived at site on 27.04.2011 @14.00
hrs