Вы находитесь на странице: 1из 142

CHAPTER NO.

9
ROOFING
Note 1. Rates for all finished works include the removal of surplus debris, unus
material and by products.
Note 2. Add extra 13%, 32% and 51% on labour rates only or 6%, 15% and 23
composite rates for 2nd, 3rd fourth and subsequent floors respectively

DESCRIPTION OF ITEM NO 1: First class tiles roofing consisting of 4" (100mm)


earth and 1" (25mm) mud plaster with Gobri
leaping over ½" (12mm) thick cement plaster 1:6
with 34 Ibs of hot bitumen coating sand blinded
provided over two layers of tiles 12" x 6" x 1¼"
(300x150x32mm) laid in 1:6 cement mortar
with 1" (25mm) thick sand-wiched layer of 1:6
cement mortar including 1:2 cement pointing
under side of tiles, complete including curing etc.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Tiles 12"x6"x1¼" 400 Nos 1150.00 1000 N 460.00


Cement for laying 0.26 Bag
Pointing under side 1:2 0.17 Bag
Plaster of tiles in between and over tiles 1:6 1.10 Bag
Plaster along parapet 0.23 Bag
1.76 Bags 230.00 P. Bag 404.80

Sand for laying in 1:6 mortar 1.96 Cft


Sand for pointing 1:2 0.41 Cft
Sand for Plaster 1:6 8.28 Cft
Sand for Plaster 1:6 along parapet 1.71 Cft
Sand for blinding of bitumen 1.00 Cft
13.36 Cft 3.50 P. Cft 46.76
Earth upto 100' (30 M) lead and lift
upto 20' (6 M)
For 1" (25mm) mud plaster 10.00 Cft
For 4" (100mm) filling over tiles 33.00 Cft
43.00 Cft 1.50 P. Cft 64.50

Page 1
Item No. 1

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Bhoosa for top layer only 17Sr (15 .8)Kg 2.00 P. Kg 31.60
Clay for gobri leeping 0.75 Cft 1.50 P. Cft 1.13
Cowdung for Gobri leeping 0.75Cft ( 15) Kg 50.00 P 100 7.50
Two coats of bitumen 34Lbs(15 .43)Kg 14.00 P. Kg 216.02
Fuel wood 0.2Md (7 .44)Kg 2.75 P. Kg 20.46

Total 1,252.77
Contractor's Profit & Overhead 20 Percent 250.55
Total 1,503.32

Labour
Rate Analysis for 125 Sft
Masons for laying tiles 1.50 Nos
Mason for pointing 0.75 Nos
Mason for cement plaster 1.00 No
Mason for mud plaster 0.40 No
3.65 Nos 300.00 Each 1,095.00

Unskilled Coolies 6.00 Nos 140.00 P. Day 840.00


Bahishti 1.25 Nos 160.00 P. Day 200.00

Total 2,135.00
Sundries 20 Percent 427.00
Total 2,562.00

Contractor's Profit & Overhead 20 Percent 512.40


Total 3,074.40

Item Rates
Labour Rate Per 100 Sft Rs. 2459.52 Say 2,459.50
Labour Rate P/ Sqm Rs. 264.64 264.65
Say
Composite Rate Per 100 S Rs. 3962.84 Say 3,962.85
Composite Rate P/ Sqm Rs. 426.39 Say 426.40

Page 2
DESCRIPTION OF ITEM NO 2: Second class tile roofing consisting of 4" (100mm)
earth and 1" (25mm) mud plaster with gobri leepin
over ½" thick cement plaster 1:6 with 34 lbs per %
Sft or 1.72 Kg/Sqm of hot bitumen coating sand
blinded provided over one layer of 12"x6"x2"
(300x150x50mm) tiles, laid in 1:6 cement pointing
underneath of tiles complete, including curing etc.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material
Per
Tiles 12"x6"x2" 200.00 Nos 1250.00 1000 N 250.00
Cement for laying in 1:6 mortar 0.23 Bag
Cement for plaster 1:6 0.55 Bag
Cement for pointing 1:2 0.17 Bag
Cement for Plaster along parapet 0.23 Bag
1.18 Bags 230.00 P. Bag 271.40

Sand for laying in 1:6 mortar 1.68 Cft


Sand for Plaster 1:6 4.14 Cft
Sand for pointing 1:2 0.43 Cft
Sand for Plaster 1:6 along parapet 1.71 Cft
Sand for blinding of bitumen 1.00 Cft
8.96 Cft 3.50 P. Cft 31.36

Earth upto 100' (30 M) and lift upto


20' (6 M)
For 1" (25mm) mud plaster 10.00 Cft
For 4" (100mm) filling over tiles 33.00 Cft
43.00 Cft 1.50 P. Cft 64.50

Fine clay for gobri 0.75 Cft 1.50 P. Cft 1.13


Bhoosa 17Sr (15. 81) Kg 2.00 P. Kg 31.62
Cowdung 0.75Cft ( 15) Kg 50.00 P 100 7.50
Bitumen for 2 coats 1/16" (2mm) thick 34Lbs(15 .43) K 14.00 P. Kg 216.02
Fuel wood 0.2Mds(7 .44) K 2.75 P. Kg 20.46

Total 893.99
Contractor's Profit & Overhead 20 Percent 178.80
Total 1,072.78

Page 3
Item No. 2

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Labour
Rate Analysis for 125 Sft
Masons 2.50 Nos 300.00 P. Day 750.00
Unskilled Coolies 5.00 Nos 140.00 P. Day 700.00
Bahishti 1.00 No 160.00 P. Day 160.00

Total 1,610.00
Sundries 20 Percent 322.00
Total 1,932.00

Contractor's Profit & Overhead 20 Percent 386.40


Total 2,318.40

Item Rates
Labour Rate Per 100 Sft Rs. 1854.72 Say 1,854.70
Labour Rate Per Sqm Rs. 199.57 199.55
Say
Composite Rate Per 100 S Rs. 2927.50 Say 2,927.50
Composite Rate Per Sqm Rs. 315.00 Say 315.00

Page 4
DESCRIPTION OF ITEM NO 3: Covering mud roof with coaltar and fine sand.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Coaltar 7.72 Kg. 14.00 P. Kg 108.12


Fine sand 1.00 Cft 3.50 P. Cft 3.50
Charcoal for heating coaltar 3.00 Kg. 4.00 P. Kg. 12.00

Total 123.62
Contractor's Profit & Overhead 20 Percent 24.72
Total 148.35

Labour

Mason 0.12 No 300.00 P. Day 36.00


Unskilled Cooly 0.25 No 140.00 P. Day 35.00

Total 71.00
Sundries 20 Percent 14.20
Total 85.20

Contractor's Profit & Overhead 20 Percent 17.04


Total 102.25

Item Rates
Labour Rate Per 100 Sft Rs. 102.25 Say 102.25
Labour Rate Per Sqm Rs. 11.00 11.00
Say
Composite Rate Per 100 Sft Rs. 250.60 Say 250.60
Composite Rate Per Sqm Rs. 26.96 Say 26.95

Page 5
Note. The unit of rate is for filling 100 Sft of roof.

DESCRIPTION OF ITEM NO 4: Filling spaces in between.

a) Wooden battons over beams filled with deodar


wood pieces (spacers).

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Deodar wood 2x10 (9¼"x1"x5") 0.54 Cft


Wastage 20% 0.11 Cft
0.65 Cft 500.00 P. Cft 325.00

Wire Nails 0.28 Kg. 45.00 P. Kg 12.74

Total 337.74
Contractor's Profit & Overhead 20 Percent 67.55
Total 405.28

Labour
Rate Analysis for 150 Sft
Carpenter for making grooves in batten
and fixing of wooden strips 0.50 No 300.00 Each 150.00
Unskilled Cooly 0.50 No 140.00 P. Day 70.00

Total 220.00
Sundries 20 Percent 44.00
Total 264.00

Contractor's Profit & Overhead 20 Percent 52.80


Total 316.80

Item Rates
Labour Rate Per 100 Sft Rs. 211.20 Say 211.20
Labour Rate Per Sqm Rs. 22.73 22.75
Say
Composite Rate Per 100 S Rs. 616.48 Say 616.50
Composite Rate Per Sqm Rs. 66.33 Say 66.35

Page 6
Item No. 4 Filling spaces in between.

b) RCC Battens Filled with C.C. Blocks (1:3:6)

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

9 No ¾x2/3"x5/12" 1.88 Cft


2 No ½x2/3"x5/12" 0.28 Cft

Cement for blocks 0.27 Bag


For laying 0.17 Bag
0.44 Bag 230.00 P. Bag 101.20
Sand for blocks 1.02 Cft
For laying 0.65 Cft
1.67 Cft 3.50 P. Cft 5.85

Bajri 2.04 Cft 18.50 P. Cft 37.74

Total 144.79
Contractor's Profit & Overhead 20 Percent 28.96
Total 173.74

Labour
Rate Analysis for 125 Sft
Mason 0.50 No 300.00 150.00
Unskilled Cooly 1.00 No 140.00 140.00
Bahishti 0.13 No 160.00 11.05

Total 301.05
Sundries 20 Percent 60.21
Total 361.26

Contractor's Profit & Overhead 20 Percent 72.25


Total 433.51

Item Rates
Labour Rate Per 100 Sft Rs. 346.81 Say 346.80
Labour Rate Per Sqm Rs. 37.32 Say 37.30

Composite Rate Per 100 S Rs. 520.55 Say 520.55


Composite Rate Per Sqm Rs. 56.01 Say 56.00

Page 7
Item No. 4 Filling spaces in between.

c) Spaces filled with bricks

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material
Per
Bricks including wastage (30+15) 45.00 Nos 1200.00 1000 N 54.00
Cement 0.20 Bag 230.00 P. Bag 46.00
Sand 0.75 Cft 3.50 P. Cft 2.63

Total 102.63
Contractor's Profit & Overhead 20 Percent 20.53
Total 123.15

Labour
Rate Analysis for 125 Sft
Mason 0.17 No 300.00 P. Day 51.00
Cooly 0.17 No 140.00 P. Day 23.80
Bahishti 0.10 No 160.00 P. Day 16.00

Total 90.80
Sundries 20 Percent 18.16
Total 108.96

Contractor's Profit & Overhead 20 Percent 21.79


Total 130.75

Item Rates
Labour Rate Per 100 Sft Rs. 104.60 Say 104.60
Labour Rate Per Sqm Rs. 11.26 Say 11.25

Composite Rate Per 100 S Rs. 227.75 Say 227.75


Composite Rate Per Sqm Rs. 24.51 Say 24.50

Page 8
DESCRIPTION OF ITEM NO 5: Single layer of tiles 9"x4½x1½" (225 x 112.5 x
40mm) laid over 4" (100mm) earth and 1" (25mm)
mud plaster without Bhoosa grouted with cement
sand 1:3 on top of RCC roof slab provided with 34
Ibs. per % Sft bitumen coating sand blinded.

Detail Unit Rate (British System) per 100 Sft


Qty Rate
Per Unit (Rs.) Amount (Rs.)
Material Per
Brick tiles 225 x 112.5 x 40 mm (9"x41/2"x1½") 360.00 Nos 1050.00 1000 N 378.00
Sand for grouting 2.50 Cft
Sand for blinding 1.25 Cft
3.75 Cft 3.50 P. Cft 13.13
Cement 0.75 Bag 230.00 P. Bag 172.50
Good earth lead upto 100' (30 M) and lift
upto 20' (6 M) 43.00 Cft 1.50 P. Cft 64.50
Two coats of bitumen 15.4234Lbs(15 .42) K 14.00 P. Kg 215.88

Total 844.01
Contractor's Profit & Overhead 20 Percent 168.80
Total 1,012.81

Labour
Rate Analysis for 150 Sft
Plasterer 0.125 No
Mason for Laying 0.500 No
Mason for Grouting 0.125 No
0.75 No 300.00 Each 225.00
Cooly for and plaster 0.50 No
Cooly for grouting laying 0.65 No
Cooly for grouting 0.25 No
1.40 Nos 140.00 Each 196.00
Painter for bitumen 0.50 No 170.00 Each 85.00
Bahishti 0.50 No 160.00 Each 80.00
Total 586.00
Sundries 20 Percent 117.20
Total 703.20
Contractor's Profit & Overhead 20 Percent 140.64
Total 843.84

Item Rates
Labour Rate Per 100 Sft Rs. 562.56 Say 562.55
Labour Rate Per Sqm Rs. 60.53 Say 60.55
Composite Rate Per 100 S Rs. 1575.37 Say 1,575.35
Composite Rate Per Sqm Rs. 169.51 Say 169.50

Page 9
DESCRIPTION OF ITEM NO 6: Jack arch roofing 4½" (112.5mm) thick laid in 1:5
cement mortar including an average depth of 4"
(100mm) thick cement concrete in haunches and
over crown with 3" (75mm) earth and 1" (25mm)
plaster soffits of arches cement plastered 1:6
and ½" (12mm) thick. The rate also includes
bitumen coating centering, laying skew bricks in
cement sand mortar 1:3 and encasing exposed fla
of the joints with fine cement concrete 1:2:4. Using
stone aggregate.
a) Cement concrete in haunches. (1:6:12)

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material
Per
Bricks 9"x4½"x3" 550.00 Nos 1200.00 1000 N 660.00
Cement for laying 1.60 Bag
Cement for plastering Soffits 0.57 Bag
Cement for concrete in haunches 2.00 Bag
Cement for concrete in flanges 0.60 Bag
4.77 Bags 230.00 P. Bag 1,097.10

Sand for laying 10.00 Cft


Sand for plastering soffit 4.26 Cft
Sand for concrete in haunches 16.20 Cft
Sand for concrete in flanges 1.50 Cft
31.96 Cft 3.50 P. Cft 111.86

Stone aggregate for concrete in haunches 32.00 Cft


Stone aggregate for concrete in flanges 3.00 Cft
35.00 Cft 18.50 P. Cft 647.50

Earth for filling and plastering 33.00 Cft 1.50 P. Cft 49.50
Bhoosa 17Lbs(15 .81) K 2.00 P. Kg 31.62
Fine Clay 0.75 Cft 1.50 P. Cft 1.13
Cowdung 0.75 Cft ( 15) Kg 50.00 P. 100 7.50

Page 10
a) Cement concrete in haunches. (1:6:12)

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Bitumen 34Lbs(15 .42) K 14.00 P. Kg 215.82


Fuel 0.2Mds(7 .44) K 2.75 P. Kg 20.46
Kail wood for centring 0.4 Cft. 350.00 P. Cft 144.20

Total 2,986.69
Contractor's Profit & Overhead 20 Percent 597.34
Total 3,584.03

Labour
Rate Analysis for 125 Sft
Masons 3.50 Nos 300.00 P. Day 1,050.00
Carpenter 0.50 No 300.00 P. Day 150.00
Unskilled Coolies 7.00 Nos 140.00 P. Day 980.00
Bahishti 1.00 No 160.00 P. Day 160.00

Total 2,340.00
Sundries 20 Percent 468.00
Total 2,808.00

Contractor's Profit & Overhead 20 Percent 561.60


Total 3,369.60

Item Rates
Labour Rate Per 100 Sft Rs. 2695.68 Say 2,695.70
Labour Rate Per Sqm Rs. 290.06 Say 290.05

Composite Rate Per 100 S Rs. 6279.71 Say 6,279.70


Composite Rate Per Sqm Rs. 675.70 Say 675.70

Page 11
Item No. 6 Jack arch roofing 4½" (112.5mm) thick laid in 1:5
cement mortar including an average depth of 4"
(100mm) thick cement concrete in haunches and
over crown with 3" (75mm) earth and 1" (25mm)
plaster soffits of arches cement plastered 1:6
and ½" (12mm) thick. The rate also includes
bitumen coating centering, laying skew bricks in
cement sand mortar 1:3 and encasing exposed
flanges of the joints with fine cement concrete
1:2:4. Using stone aggregate.

b) Cement concrete in haunches (1:3:6)

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material Per
Bricks 9"x4½"x3" 550.00 Nos 1200.00 1000 N 660.00
Cement for laying 1.60 Bag
Cement for plastering Soffits 0.57 Bag
Cement for concrete in haunches 4.10 Bag
Cement for concrete in flanges 0.60 Bag
6.87 Bags 230.00 P. Bag 1,580.10

Sand for laying 10.00 Cft


Sand for plastering soffit 4.26 Cft
Sand for concrete in haunches 15.40 Cft
Sand for concrete in flanges 1.50 Cft
31.16 Cft 3.50 P. Cft 109.06

Stone aggregate for concrete in haunches 31.00 Cft


Stone aggregate for concrete in flanges 3.00 Cft
34.00 Cft 18.50 P. Cft 629.00

Earth for filling and plastering 33.00 Cft 1.50 P. Cft 49.50
Bhoosa 17Lbs(15 .81) K 2.00 P. Kg 31.62
Fine Clay 0.75 Cft 1.50 P. Cft 1.13
Cowdung 0.75Cft ( 15) Kg 50.00 P.% Kg 7.50
Bitumen 34Lbs(15 .43) K 14.00 P. Kg 216.02
Fuel 0.2Mds(7 .44) K 2.75 P. Kg 20.46
Kail wood for centring 0.411 Cft. 350.00 P. Cft 144.00

Total 3,448.39
Contractor's Profit & Overhead 20 Percent 689.68
Total 4,138.07

Page 12
b) Cement concrete in haunches (1:3:6)

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Labour
Rate Analysis for 125 Sft
Masons 3.50 Nos 300.00 P. Day 1,050.00
Carpenter 0.50 No 300.00 P. Day 150.00
Unskilled Coolies 7.00 Nos 140.00 P. Day 980.00
Bahishti 1.00 No 160.00 P. Day 160.00

Total 2,340.00
Sundries 20 Percent 468.00
Total 2,808.00

Contractor's Profit & Overhead 20 Percent 561.60


Total 3,369.60

Item Rates
Labour Rate Per 100 Sft Rs. 2695.68 Say 2,695.70
Labour Rate Per Sqm Rs. 290.06 Say 290.05

Composite Rate Per 100 S Rs. 6833.75 Say 6,833.75


Composite Rate Per Sqm Rs. 735.31 Say 735.30

Page 13
DESCRIPTION OF ITEM NO 7: Jack arch roofing 4½" (112.5mm) thick laid in 1:5
cement mortar including an average depth of 4"
(100mm) thick cement concrete in haunches and
over crown with ½" (12mm) thick cement plaster
1:6 on top (Except earth filling, plaster and gobri),
soffits of arches cement plastered. The rate also
includes bitumen coating centering, laying skew
bricks in cement sand mortar 1:3 and encasing
exposed flanges of the joints with fine cement
concrete 1:2:4. Using stone aggregate.

a) Cement concrete in haunches. (1:6:12)

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material
Per
Bricks 9"x4½"x3" 550.00 Nos 1200.00 1000 N 660.00
Cement for laying 1.60 Bag
Cement for plastering top 0.51 Bag
Cement for plastering soffits 0.57 Bag
Cement for concrete in haunches 2.00 Bag
Cement for concrete in flanges 0.60 Bag
5.28 Bags 230.00 P. Bag 1,214.40

Sand for laying 10.00 Cft


Cement for plastering top 3.84 Cft
Sand for plastering soffits 4.26 Cft
Sand for concrete in haunches 16.20 Cft
Sand for concrete in flanges 1.50 Cft
35.80 Cft 3.50 P. Cft 125.30

Stone aggregate for concrete in haunches 32.00 Cft


Stone aggregate for concrete in flanges 3.00 Cft
35.00 Cft 18.50 P. Cft 647.50

Page 14
a) Cement concrete in haunches. (1:6:12)

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Bitumen 34Lbs(15 .43) K 14.00 P. Kg 216.02


Fuel 0.2Mds(7 .44) K 2.75 P. Kg 20.46
Deodar wood (2nd Class) 0.50 Cft 500.00 P. Cft 247.50

Total 3,131.18
Contractor's Profit & Overhead 20 Percent 626.24
Total 3,757.42

Labour
Rate Analysis for 125 Sft
Masons 2.75 Nos 300.00 P. Day 825.00
Carpenter 0.50 No 300.00 P. Day 150.00
Unskilled Coolies 5.50 Nos 140.00 P. Day 770.00
Bahishti 1.00 No 160.00 P. Day 160.00

Total 1,905.00
Sundries 20 Percent 381.00
Total 2,286.00

Contractor's Profit & Overhead 20 Percent 457.20


Total 2,743.20

Item Rates
Labour Rate Per 100 Sft Rs. 2194.56 Say 2,194.55
Labour Rate Per Sqm Rs. 236.13 Say 236.15

Composite Rate Per 100 S Rs. 5951.98 Say 5,952.00


Composite Rate Per Sqm Rs. 640.43 Say 640.45

Page 15
Item No. 7 Jack arch roofing 4½" (112.5mm) thick laid in 1:5
cement mortar including an average depth of 4"
(100mm) thick cement concrete in haunches and
over crown with ½" (12mm) thick cement plaster
1:6 on top (Except earth filling, plaster and gobri),
soffits of arches cement plastered. The rate also
includes bitumen coating centering, laying skew
bricks in cement sand mortar 1:3 and encasing
exposed flanges of the joints with fine cement
concrete 1:2:4. Using stone aggregate.

b) Cement concrete in haunches. (1:3:6)

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material
Per
Bricks 9"x4½"x3" 550.00 Nos 1200.00 1000 N 660.00
Cement for laying 1.60 Bag
Cement for plastering soffits 0.57 Bag
Cement for concrete in haunches 4.10 Bag
Cement for concrete in flanges 0.60 Bag
6.87 Bags 230.00 P. Bag 1,580.10

Sand for laying 10.00 Cft


Cement for plastering top 3.84 Cft
Sand for plastering soffits 4.26 Cft
Sand for concrete in haunches 15.40 Cft
Sand for concrete in flanges 1.50 Cft
35.00 Cft 3.50 P. Cft 122.50

Stone aggregate for concrete in haunches 31.00 Cft


Stone aggregate for concrete in flanges 3.00 Cft
34.00 Cft 18.50 P. Cft 629.00

Page 16
b) Cement concrete in haunches. (1:3:6)

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Bitumen 34Lbs(15 .43) K 14.00 P. Kg 216.02


Fuel 0.2Mds(7 .44) K 2.75 P. Kg 20.46
Kail wood centring 0.411 Cft. 350.00 P. Cft. 144.00

Total 3,372.08
Contractor's Profit & Overhead 20 Percent 674.42
Total 4,046.50

Labour
Rate Analysis for 125 Sft
Masons 2.75 Nos 300.00 P. Day 825.00
Carpenter 0.50 No 300.00 P. Day 150.00
Unskilled Coolies 5.50 Nos 140.00 P. Day 770.00
Bahishti 1.00 No 160.00 P. Day 160.00

Total 1,905.00
Sundries 20 Percent 381.00
Total 2,286.00

Contractor's Profit & Overhead 20 Percent 457.20


Total 2,743.20

Item Rates
Labour Rate Per 100 Sft Rs. 2194.56 Say 2,194.55
Labour Rate Per Sqm Rs. 236.13 Say 236.15

Composite Rate Per 100 S Rs. 6241.06 Say 6,241.05


Composite Rate Per Sqm Rs. 671.54 Say 671.55

Page 17
DESCRIPTION OF ITEM NO 8: Extra for vaulted jack arch roofing

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Labour
Rate Analysis for 125 Sft
Masons 1.00 No 300.00 P. Day 300.00
Carpenter 1.00 No 300.00 P. Day 300.00

Total 600.00
Sundries 20 Percent 120.00
Total 720.00

Contractor's Profit & Overhead 20 Percent 144.00


Total 864.00

Item Rates
Labour Rate for Per 100 S Rs. 691.20 691.20

Labour Rate for P/ Sqm Rs. 74.37 74.35

Page 18
DESCRIPTION OF ITEM NO 9: Jack arch roofing of shingle and cement concrete
(1:3:6), 4½" (112.5mm) thick at crown, with ½"
(12mm) cement plaster including cost of
supplying erecting and dismantling centering.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Cement 7.46 Bags 230.00 P. Bag 1,715.80


Sand 28.00 Cft 3.50 P. Cft 98.00
Shingle 56.00 Cft 18.50 P. Cft 1,036.00
Kail wood 0.411 Cft. 350.00 P. Cft. 144.00

Total 2,993.80
Contractor's Profit & Overhead 20 Percent 598.76
Total 3,592.56

Labour

Masons 0.50 No 300.00 P. Day 150.00


Coolies for stacking & mixing 3.00 Nos 140.00 P. Day 420.00
Coolies for ramming 3.00 Nos 140.00 P. Day 420.00
Coolies for carrying 2.00 Nos 140.00 P. Day 280.00
Coolies for carpenter 1.00 No 140.00 P. Day 140.00

Carpenter 1.00 No 300.00 P. Day 300.00


Bahishti 1.00 No 160.00 P. Day 160.00

Total 1,870.00
Sundries 20 Percent 374.00
Total 2,244.00

Contractor's Profit & Overhead 20 Percent 448.80


Total 2,692.80

Item Rates
Labour Rate Per 100 Sft Rs. 2692.80 Say 2,692.80
Labour Rate Per Sqm Rs. 289.75 Say 289.75

Composite Rate Per 100 S Rs. 6285.36 Say 6,285.35


Composite Rate Per Sqm Rs. 676.31 Say 676.30

Page 19
DESCRIPTION OF ITEM NO 10: Earth filling over roof including watering
ramming with 1" (25mm) mud plaster finished
with gobri leeping.

a) 3" (75mm) thick earth filling and 1" (25mm) mud


plaster.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Earth lead upto 100' (30 M) and lift upto


20' (6 M) 33 Cft 1.50 P. Cft 49.50
Bhoosa 17Lbs(15 .81) K 2.00 P. Kg 31.62
Clay 0.75 Cft 1.50 P. Cft 1.13
Cowdung 0.75Cft ( 15) Kg 50.00 P % Kg 7.50

Total 89.75
Contractor's Profit & Overhead 20 Percent 17.95
Total 107.69

Labour
Rate Analysis for 125 Sft
Bahishti 0.12 No 160.00 P. Day 19.20
Coolies for lifting and ramming earth 1.00 No 140.00 P. Day 140.00
Mason 0.12 No 300.00 P. Day 36.00

Total 195.20
Sundries 20 Percent 39.04
Total 234.24

Contractor's Profit & Overhead 20 Percent 46.85


Total 281.09

Item Rates
Labour Rate Per 100 Sft Rs. 224.87 Say 224.85
Labour Rate Per Sqm Rs. 24.20 Say 24.20

Composite Rate Per 100 S Rs. 332.56 Say 332.55


Composite Rate Per Sqm Rs. 35.78 Say 35.80

Page 20
Item No. 10 Earth filling over roof including watering
ramming with 1" (25mm) mud plaster finished
with gobri leeping.

b) 4" (100mm) thick earth filling and 1" (25mm)


mud plaster.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Earth lead upto 100' (30 M) and lift upto


20' (6 M) 43 Cft 1.50 P. Cft 64.50
Bhoosa 17Lbs(15 .81) K 2.00 P. Kg 31.62
Fine clay for gobri 0.75 Cft 1.50 P. Cft 1.13
Cowdung 0.75 Cft ( 15) Kg 50.00 P % Kg 7.50

Total 104.75
Contractor's Profit & Overhead 20 Percent 20.95
Total 125.69

Labour

Bshishti 0.18 No 160.00 P. Day 28.80


Coolies for lifting and ramming earth 1.00 No 140.00 P. Day 140.00
Mason 0.12 No 300.00 P. Day 36.00

Total 204.80
Sundries 20 Percent 40.96
Total 245.76

Contractor's Profit & Overhead 20 Percent 49.15


Total 294.91

Item Rates
Labour Rate Per 100 Sft Rs. 294.91 Say 294.90
Labour Rate Per Sqm Rs. 31.73 Say 31.75

Composite Rate Per 100 S Rs. 420.61 Say 420.60


Composite Rate Per Sqm Rs. 45.26 Say 45.25

Page 21
DESCRIPTION OF ITEM NO 11: 1/8"(3mm) thick gobri leeping on roofs or floors.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Fine clay 0.75 Cft 1.50 P. Cft 1.13


Cowdung 0.75 Cft ( 15) Kg 50.00 P. 100 7.50

Total 8.63
Contractor's Profit & Overhead 20 Percent 1.73
Total 10.35

Labour
Rate Analysis for 150 Sft
Mason 0.12 No 300.00 P. Day 36.00
Bahishti 0.06 No 160.00 P. Day 9.60

Total 45.60
Sundries 20 Percent 9.12
Total 54.72

Contractor's Profit & Overhead 20 Percent 10.94


Total 65.66

Item Rates
Labour Rate Per 100 Sft Rs. 43.78 Say 43.80
Labour Rate Per Sqm Rs. 4.71 Say 4.70

Composite Rate Per 100 S Rs. 54.13 Say 54.15


Composite Rate Per Sqm Rs. 5.82 Say 5.80

Page 22
DESCRIPTION OF ITEM NO 12: 2 coats of bitumen laid hot using 34 lbs
(1.72Kg/Sqm) per % Sft over roof and
blinded with sand at 1 Cft per % Sft.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Bitumen 34Lbs(15 .43) K 14.00 P. Kg 216.02


Sand 1.00 Cft 3.50 P. Cft 3.50
Fuel wood 0.12Mds( 4.46)K 2.75 P. Kg 12.27

Total 231.79
Contractor's Profit & Overhead 20 Percent 46.36
Total 278.15

Labour
Rate for 125 Sft
Cooly for heating & laying 1.00 No 140.00 P. Day 140.00

Total 140.00
Sundries 20 Percent 28.00
Total 168.00

Contractor's Profit & Overhead 20 Percent 33.60


Total 201.60

Item Rates
Labour Rate for Per 100 S Rs. 161.28 Say 161.30
Labour Rate for P/ Sqm Rs. 17.35 Say 17.35

Composite Rate for Per 1 Rs. 439.43 Say 439.45


Composite Rate for P/ Sq Rs. 47.28 Say 47.30

Page 23
DESCRIPTION OF ITEM NO 13: Fixing corrugated galvanized iron sheets with
G.I. bolts, nuts, limpet and bitumen washers,
wind ties complete in all respect without valleys
and ridges.

a) 20 - S. W. G.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material
Sheets of 20 gauge = 100 Sft.
wastage & overlaping @ 20% = 20 Sft
=120 Sf 102.65Cwt (102 .65) K 36.00 P. Kg 3,695.40
Wind tie (rod) 22Lbs(9 .98) K 2.00 P. Kg 19.96
G.I. bolts and nuts 2.00 Doz 20.00 Doz 40.00
Limpet washers 2.00 Doz 6.00 Doz 12.00
G.I. Hook, bolts & nuts 1.50 Doz 20.00 Doz 30.00
Bitumen washers 3.85 Doz 11.00 Doz 42.35
Charcoal 3.75 4 Sr. (3. 75) Kg 4.00 P. Kg 15.00

Total 3,854.71
Contractor's Profit & Overhead 20 Percent 770.94
Total 4,625.65

Labour (for 150 Sft.)

Blacksmith 1.00 No 170.00 P. Day 170.00


Cooly 1.00 No 140.00 P. Day 140.00

Total 310.00
Sundries 20 Percent 62.00
Total 372.00

Contractor's Profit & Overhead 20 Percent 74.40


Total 446.40

Item Rates
Labour Rate Per 100 Sft Rs. 297.60 Say 297.60
Labour Rate Per Sqm Rs. 32.02 Say 32.00

Composite Rate Per 100 S Rs. 4923.25 Say 4,923.25


Composite Rate Per Sqm Rs. 529.74 Say 529.75

Page 24
Item No. 13 Fixing corrugated galvanized iron sheets with
G.I. bolts, nuts, limpet and bitumen washers, wind
ties complete in all respect without valleys and
ridges.

b) 22 - S. W. G.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

C.G.I. Sheets of 22 gauge including over


lapping and wastage. 120 Sft 1.7Cwt (8 6.39)K 40.00 P. Kg 3,455.60

Wind tie (rod) 22Lbs(9 .98) K 2.00 P. Kg 19.96


G.I. bolts and nuts 2.00 Doz 20.00 Doz 40.00
Limpet washers 2.00 Doz 6.00 Doz 12.00
G.I. Hook, bolts & nuts 1.50 Doz 20.00 Doz 30.00
Bitumen washers 3.82 Doz 11.00 Doz 42.00
Charcoal 4 Sr. (3. 72) Kg 4.00 P. Kg 14.88

Total 3,614.44
Contractor's Profit & Overhead 20 Percent 722.89
Total 4,337.33

Labour for 150 Sft.

Blacksmith 1.00 No 170.00 P. Day 170.00


Cooly 1.00 No 140.00 P. Day 140.00

Total 310.00
Sundries 20 Percent 62.00
Total 372.00

Contractor's Profit & Overhead 20 Percent 74.40


Total 446.40

Item Rates
Labour Rate for Per 100 S Rs. 297.60 Say 297.60
Labour Rate for P/ Sqm Rs. 32.02 Say 32.00

Composite Rate for Per 1 Rs. 4634.93 Say 4,634.95


Composite Rate for P/ Sq Rs. 498.72 Say 498.70

Page 25
Item No. 13 Fixing corrugated galvanized iron sheets with
G.I. bolts, nuts, limpet and bitumen washers, wind
ties complete in all respect without valleys and
ridges.

c) 24 - S. W. G.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

C.G.I. Sheets of 24 gauge including over


lapping and wastage. 120 Sft 1.34Cwt(6 8.10)K 40.00 P. Kg 2,724.00

Wind tie 22Lbs(9 .98) K 2.00 P. Kg 19.96


G.I. bolts and nuts 2.00 Doz 20.00 Doz 40.00
Limpet washers 2.00 Doz 6.00 Doz 12.00
G.I. Hook, bolts & nuts 1.50 Doz 20.00 Doz 30.00
Bitumen washers 3.82 Doz 11.00 Doz 42.00
Charcoal 4 Sr. (3. 72) Kg 4.00 P. Kg 14.88

Total 2,882.84
Contractor's Profit & Overhead 20 Percent 576.57
Total 3,459.41

Labour
Rate for 150 Sft
Blacksmith 1.00 No 170.00 P. Day 170.00
Cooly 1.00 No 140.00 P. Day 140.00

Total 310.00
Sundries 20 Percent 62.00
Total 372.00

Contractor's Profit & Overhead 20 Percent 74.40


Total 446.40

Item Rates
Labour Rate Per 100 Sft Rs. 297.60 Say 297.60
Labour Rate Per Sqm Rs. 32.02 Say 32.00

Composite Rate Per 100 S Rs. 3757.01 Say 3,757.00


Composite Rate Per Sqm Rs. 404.25 Say 404.25

Page 26
DESCRIPTION OF ITEM NO 14: Khassi parnalas in cement and sand mortar (1:2)
12" (300mm) outside width finished smooth with
a floating coat of neat cement.

Detail Unit Rate (British System) per 100 Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 15 Rft
Material

Cement for ½" (12mm) plaster 0.18 Bag


Cement for floating 0.06 Bag
Cement for side filling 0.26 Bag
0.50 Bags 230.00 P. Bag 115.00
Sand 1.10 Cft 3.50 P. Cft 3.85

Total 118.85
Contractor's Profit & Overhead 20 Percent 23.77
Total 142.62

Labour

Mason 0.67 No 300.00 P. Day 201.00


Unskilled Cooly 0.67 No 140.00 P. Day 93.80
Bahishti 0.09 No 160.00 P. Day 14.40

Total 309.20
Sundries 20 Percent 61.84
Total 371.04

Contractor's Profit & Overhead 20 Percent 74.21


Total 445.25

Item Rates
Labour Rate Per Rft Rs. 29.68 Say 29.70
Labour Rate for Per Rm Rs. 97.36 Say 97.35

Composite Rate Per Rft Rs. 39.19 Say 39.20


Composite Rate Per Rm Rs. 128.55 Say 128.55

Page 27
DESCRIPTION OF ITEM NO 15: Making Khuras, on roof size 2' x 2' x 4" (600 x 600
100mm)

Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Cement 0.20 Bag 230.00 P. Bag 46.00


Sand 0.55 Cft 3.50 P. Cft 1.93
Aggregate (Stone) 1.25 Cft 18.50 P. Cft 23.13

Total 71.05
Contractor's Profit & Overhead 20 Percent 14.21
Total 85.26

Labour for 125 Nos)

Mason 0.20 No 300.00 P. Day 60.00


Unskilled Cooly 0.20 No 140.00 P. Day 28.00
Bahishti 0.05 No 160.00 P. Day 8.00

Total 96.00
Sundries 20 Percent 19.20
Total 115.20

Contractor's Profit & Overhead 20 Percent 23.04


Total 138.24

Item Rates
Labour Rate for Each Rs. 110.59 Say 110.60

Composite Rate for Each Rs. 195.85 Say 195.85

Page 28
DESCRIPTION OF ITEM NO 16: Bottom khuras of brick masonry in cement mortar
(1:6) 4'x2'x4½" (1200x600x114mm) over 3"
(75mm) cement concrete (1:4:8)

Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Cement 0.37 Bag 230.00 P. Bag 85.10


Sand 2.00 Cft 3.50 P. Cft 7.00
Brick Aggregate 2.00 Cft 5.60 P. Cft 11.20
Bricks 42.00 No 1200.00 1000 N 50.40

Total 153.70
Contractor's Profit & Overhead 20 Percent 30.74
Total 184.44

Labour
Rate Analysis for 1.25 No.
Mason 0.20 No 300.00 P. Day 60.00
Cooly 0.20 No 140.00 P. Day 28.00
Bahishti 0.05 No 160.00 P. Day 8.00

Total 96.00
Sundries 20 Percent 19.20
Total 115.20

Contractor's Profit & Overhead 20 Percent 23.04


Total 138.24

Item Rates
Labour Rate for Each Rs. 110.59 Say 110.60

Composite Rate for Each Rs. 295.03 Say 295.05

Page 29
DESCRIPTION OF ITEM NO 17: Plain galvanized iron sheets of 22 S.W.G. rain
water down pipe including clamp and fixing in
position.

a) 4" (100mm) dia down pipe

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

G.I. sheets = 1.05 Sft


Add. 10% for joints and wastage 0.10 Sft
1.15 Sft @ 1.31 Lbs/Sft 1.5Lbs(0. 68) Kg 31.00 P. Kg 21.08
Add for clamps bolts nuts and rivets. 0.125 Kg 48.00 P. Kg. 6.00

Total 27.08
Contractor's Profit & Overhead 20 Percent 5.42
Total 32.50

Labour
Rate Analysis for 1.25 Rft
Blacksmith 0.03 No 170.00 P. Day 5.10
Unskilled Cooly 0.03 No 140.00 P. Day 4.20
Mason 0.03 No 300.00 P. Day 9.00

Total 18.30
Sundries 20 Percent 3.66
Total 21.96

Contractor's Profit & Overhead 20 Percent 4.39


Total 26.35

Item Rates
Labour Rate Per Rft Rs. 21.08 Say 21.10
Labour Rate for Per Rm Rs. 69.15 Say 69.15

Composite Rate Per Rft Rs. 53.58 Say 53.60


Composite Rate Per Rm Rs. 175.73 Say 175.75

Page 30
DESCRIPTION OF ITEM NO 17: Plain galvanized iron sheets of 22 S.W.G. rain
water down pipe including clamp and fixing in
position.

b) 5" (125mm) dia down pipe.

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

G.I. sheets 1.31 Sft


Add. 10% for joints and wastage 0.13 Sft
1.44 Sft @ 1.31 Lbs/Sft 1.90Lbs(0 .86) K 31.00 P. Kg 26.66
Add for clamps bolts nuts and rivets. 0.125 Kg 48.00 P. Kg. 6.00

Total 32.66
Contractor's Profit & Overhead 20 Percent 6.53
Total 39.19

Labour 1.25 Rft

Blacksmith 0.03 No 170.00 P. Day 5.10


Unskilled Cooly 0.03 No 140.00 P. Day 4.20
Mason 0.03 No 300.00 P. Day 9.00

Total 18.30
Sundries 20 Percent 3.66
Total 21.96

Contractor's Profit & Overhead 20 Percent 4.39


Total 26.35

Item Rates
Labour Rate Per Rft Rs. 21.08 Say 21.10
Labour Rate for Per Rm Rs. 69.15 Say 69.15

Composite Rate Per Rft Rs. 60.27 Say 60.25


Composite Rate Per Rm Rs. 197.70 Say 197.70

Page 31
DESCRIPTION OF ITEM NO 18: Plain galvanized iron sheets flashing of 22 gauge.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

G.I. sheets 1.00 Lbs


22 guage 0.96 Sft
0.96 Sft @ 1.31 Lbs/Sft 1.26Lbs(0 .57) K 31.00 P. Kg 17.67
Fixture L.S. 4.00

Total 21.67
Contractor's Profit & Overhead 20 Percent 4.33
Total 26.00

Labour for 1.25 Sft

Blacksmith 0.03 No 170.00 P. Day 5.10


Cooly 0.03 No 140.00 P. Day 4.20
Mason 0.03 No 300.00 P. Day 9.00

Total 18.30
Sundries 20 Percent 3.66
Total 21.96

Contractor's Profit & Overhead 20 Percent 4.39


Total 26.35

Item Rates
Labour Rate Per Sft Rs. 21.08 Say 21.10
Labour Rate Per Sqm Rs. 226.84 Say 226.85

Composite Rate Per Sft Rs. 47.09 Say 47.10


Composite Rate Per Sqm Rs. 506.64 Say 506.65

Page 32
DESCRIPTION OF ITEM NO 19:

Providing and fixing 1/16" (1.5mm) thick lead


flashing over roof expansion joint complete in all
respects.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 100 Sft
Material

Lead flashing 1/16" thick 100.00 Sft 48.00 Sft 4,800.00


Nails (Copper) etc. 1.00 Kg. 120.00 P. Kg. 120.00

Total 4,920.00
Contractor's Profit & Overhead 20 Percent 984.00
Total 5,904.00

Labour

Driller 1.00 No 170.00 P. Day 170.00


Helper 1.00 No 160.00 P. Day 160.00

Total 330.00
Sundries 20 Percent 66.00
Total 396.00

Contractor's Profit & Overhead 20 Percent 79.20


Total 475.20

Item Rates
Labour Rate Per Sft Rs. 4.75 Say 4.75
Labour Rate Per Sqm Rs. 51.13 Say 51.15

Composite Rate Per Sft Rs. 63.79 Say 63.80


Composite Rate Per Sqm Rs. 686.40 Say 686.40

Page 33
DESCRIPTION OF ITEM NO 20: Cast iron rain water down pipe fixed in position,
excluding heads and shoes, but including painting
and clamps, etc.

a) 4" (100mm) dia Cast Iron down pipe.

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 6 Rft
Material

C.I. pipe 4" (100mm) dia 6.00 Rft 80.00 P. Rft 480.00
Hold fasts with bolts 1.00 No 10.00 Each 10.00
Cement mortar for fixing hold fast
Cement 0.07 Bag 230.00 Bag 16.56
Sand 0.58 Cft 350.00 % Cft. 2.03
Pig lead 0.5Lbs(0 .23) K 20.00 P. Kg 4.60
Paint 0.05 Gln 450.00 P. Gln 22.50

Total 535.69
Contractor's Profit & Overhead 20 Percent 107.14
Total 642.83
Rate per Rft 642.83
6 107.14

Labour

Unskilled Cooly 0.20 No 140.00 P. Day 28.00


Mason 0.20 No 300.00 P. Day 60.00

Total 88.00
Sundries 20 Percent 17.60
Total 105.60

Contractor's Profit & Overhead 20 Percent 21.12


Total 126.72

Item Rates
Labour Rate Per Rft Rs. 21.12 Say 21.10
Labour Rate Per Rm Rs. 69.29 Say 69.30

Composite Rate Per Rft Rs. 128.26 Say 128.25


Composite Rate Per Rm Rs. 420.79 Say 420.80

Page 34
Item No. 20 Cast iron rain water down pipe fixed in position,
excluding heads and shoes, but including painting
and clamps, etc.

b) 3" (75mm) dia Cast Iron down pipe.

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 6 Rft
Material

C.I. pipe down 3" (75mm) dia 6.00 Rft 70.00 P. Rft 420.00
Hold fasts with bolts 1.00 No 10.00 Each 10.00
Cement mortar for fixing hold fast
Cement 0.048 Bag 230.00 Bag 11.04
Sand 0.39 Cft 350.00 % Cft. 1.37
Pig lead 0.5Lbs(0 .23) K 20.00 P. Kg 4.60
Paint 0.03 Gln 450.00 P. Gln 13.50

Total 460.51
Contractor's Profit & Overhead 20 Percent 92.10
Total 552.61
Rate for One Reft 552.61
6 92.10
Labour

Cooly 0.20 No 140.00 P. Day 28.00


Mason 0.20 No 300.00 P. Day 60.00

Total 88.00
Sundries 20 Percent 17.60
Total 105.60

Contractor's Profit & Overhead 20 Percent 21.12


Total 126.72

Item Rates
Labour Rate Per Rft Rs. 21.12 Say 21.10
Labour Rate Per Rm Rs. 69.29 Say 69.30

Composite Rate Per Rft Rs. 113.22 Say 113.20


Composite Rate Per Rm Rs. 371.46 Say 371.45

Page 35
DESCRIPTION OF ITEM NO 21: Rain water down pipe cast iron heads fixed in
place, including cost of clamp, holdfast, and
painting.

Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

C.I. Heads 4" Ø 1.00 No 100.00 Each 100.00


Clamps with hold fasts etc. 1.00 No 10.00 Each 10.00
Cement 0.05 Bag 230.00 Bag 11.50
Sand 0.29 Cft 350.00 % Cft. 1.02
Pig lead 0.5Lbs(0 .23) K 20.00 P. Kg 4.60
Paint 0.01 Gln 450.00 P. Gln 4.50

Total 131.62
Contractor's Profit & Overhead 20 Percent 26.32
Total 157.94

Labour

Cooly 0.09 No 140.00 P. Day 12.60


Mason 0.09 No 300.00 P. Day 27.00
Pipe fitter 0.09 No 170.00 P. Day 15.30

Total 54.90
Sundries 20 Percent 10.98
Total 65.88

Contractor's Profit & Overhead 20 Percent 13.18


Total 79.06

Item Rates
Labour Rate for Each Rs. 79.06 Say 79.05

Composite Rate for Each Rs. 236.99 Say 237.00

Page 36
DESCRIPTION OF ITEM NO 22: Shoes bends or offsets for cast iron rain water
down pipe including fixing and painting.

Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

C.I. shoes bend or offsets 4" Ø 1.00 No 80.00 Each 80.00


Pig lead 0.5Lbs ( 0.23)K 20.00 P. Kg 4.60
Paint 0.01 Gln 450.00 P. Gln 4.50

Total 89.10
Contractor's Profit & Overhead 20 Percent 17.82
Total 106.92

Labour

Pipe fitter 0.05 No 170.00 P. Day 8.50


Cooly 0.05 No 140.00 P. Day 7.00

Total 15.50
Sundries 20 Percent 3.10
Total 18.60

Contractor's Profit & Overhead 20 Percent 3.72


Total 22.32

Item Rates
Labour Rate for Each Rs. 22.32 Say 22.30

Composite Rate for Each Rs. 129.22 Say 129.20

Page 37
DESCRIPTION OF ITEM NO 23: Plain G.I. sheet iron spouts fixed in position,
including painting.

Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

G.I. sheets 22 gauge length 28" (712mm)


and width 6" (150mm)
28 x 6 = 1.17 Sft 1.28Lbs ( 0.68)K 31.00 P. Kg 21.08
12 x 12
Cost of cement mortor for fixing
Cement 0.048 Bag 230.00 Bag 11.04
Sand 0.39 Cft 350.00 % Cft. 1.37

Total 33.49
Contractor's Profit & Overhead 20 Percent 6.70
Total 40.18

Labour

Cooly 0.10 No 140.00 P. Day 14.00


Mason 0.10 No 300.00 P. Day 30.00
Blacksmith 0.10 No 170.00 P. Day 17.00

Total 61.00
Sundries 20 Percent 12.20
Total 73.20

Contractor's Profit & Overhead 20 Percent 14.64


Total 87.84

Item Rates
Labour Rate for Each Rs. 87.84 Say 87.85

Composite Rate for Each Rs. 128.02 Say 128.00

Page 38
DESCRIPTION OF ITEM NO 24: Laying ½" (12mm) thick deodar ceiling complete
(including sawing planing and fixing)

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 100 Sft
Material

Deodar wood 5.00 Cft 500.00 P. Cft 2,500.00


Screw 11/2" long 4.50 Doz 3.25 Doz 14.63
Nails of sorts 1.64 .88Sr (1. 64) Kg 43.00 P. Kg 70.52

Total 2,585.15
Contractor's Profit & Overhead 20 Percent 517.03
Total 3,102.17

Labour

Unskillied Cooly 3.00 Nos 140.00 P. Day 420.00


Carpenter 4.00 Nos 300.00 P. Day 1,200.00

Total 1,620.00
Sundries 20 Percent 324.00
Total 1,944.00

Contractor's Profit & Overhead 20 Percent 388.80


Total 2,332.80

Item Rates
Labour Rate Per 100 Sft Rs. 2332.80 Say 2,332.80
Labour Rate Per Sqm Rs. 251.01 Say 251.00

Composite Rate Per 100 S Rs. 5434.97 Say 5,434.95


Composite Rate Per Sqm Rs. 584.80 Say 584.80

Page 39
DESCRIPTION OF ITEM NO 25: Flat sheet roof with galvanized iron sheets
including battens, rolls, screw, clips etc. (planking
to be paid for separately).

a) 22 B. W. G. Sheets Roofing.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 400 Sft

Material

a) 22 B.W.G. sheet of size 6'x4' (1.8x1.20


M) in 400 sft (40 Sm) area including over
lapping and wastage 25% for 100 sft
5.85/4 = 1.46 cwt .
Wastage 25% (400+25%) 500 Sft
@ 1.12 Lbs/Sft 5.85Cwt(29 7.20)K 31.00 P. Kg 9,213.20
Rolls 5" (0.125m) wide 16' (4.86 M)
long or 7 Nos (27 .08) Sf 31.00 P. Kg 839.48
16x5x7/12 = 0.54/4 = 0.14
Deodar wood for battens 2"x1½" size 7

Nos of 16' length = 7x16x1/6x1/8. 2.33 Cft


Add. 23% wastage 0.58 Cft
2.91 Cft 500.00 P. Cft 1,455.00

Bolts, nuts 1.00 Kg. 48.00 P. Kg. 48.00


Limpet Washer 4.00 Doz. 6.00 Doz. 24.00
U.I. Clips 1.29 Kg. 28.00 Per Kg. 36.01

Total 11,615.69
Contractor's Profit & Overhead 20 Percent 2,323.14
Total 13,938.83

Rate for 100 Sft 13938.83 3,484.71


4

Page 40
Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Labour
Rate Analysis for 500 Sft
Cooly 12.00 Nos 140.00 P. Day 1,680.00
Carpenter 1.50 Nos 300.00 P. Day 450.00
Blacksmith 8.00 Nos 170.00 P. Day 1,360.00

Total 3,490.00
Sundries 20 Percent 698.00
Total 4,188.00

Contractor's Profit & Overhead 20 Percent 837.60


Total 5,025.60

Rate for 100 Sft 1,005.12

Item Rates
Labour Rate Per 100 Sft Rs. 1005.12 Say 1,005.10
Labour Rate Per Sqm Rs. 108.15 Say 108.15

Composite Rate Per 100 S Rs. 4489.83 Say 4,489.85


Composite Rate Per Sqm Rs. 483.11 Say 483.10

Page 41
Item No. 25 Flat sheet roof with galvanized iron sheets
including battens rolls screw clips etc. (planking
to be psid for separately).
b) 24 B. W. G. Sheets Roofing.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 400 Sft
Material

b) 24 B.W.G. sheet roofing


24 B.W.G. sheeting 400 Sft
over laping 100 Sft
Wastage 25% 500 Sft

500 Sft @ 1.12 Lbs/Sft = 560 Lbs 254.08 Kg 31.00 P. Kg 7,876.48


Rolls = 47 Sft @ 1.12 = 52.64 Lbs 23.88 Kg 31.00 P. Sft 740.28
Deodar wood 2.90 Cft 500.00 P. Cft 1,450.00
Screws of size 3"&2" 1.60 Kg. 45.00 P. Kg. 72.00
Clips 1.29 Kg. 28.00 P. Kg. 36.01
Total 10,174.77
Contractor's Profit & Overhead 20 Percent 2,034.95
Total 12,209.72

Rate for 100 Sft 12209.72 3,052.43


Labour 4
Rate Analysis for 500 Sft
Cooly 12.00 Nos 140.00 P. Day 1,680.00
Carpenter 1.50 No 300.00 P. Day 450.00
Blacksmith 8.00 Nos 170.00 P. Day 1,360.00
Total 3,490.00
Sundries 20 Percent 698.00
Total 4,188.00

Contractor's Profit & Overhead 20 Percent 837.60


Total 5,025.60

Rate for 100 Sft 5025.60 1,005.12


5
Item Rates
Labour Rate Per 100 Sft Rs. 1005.12 Say 1,005.10
Labour Rate Per Sqm Rs. 108.15 Say 108.15
Composite Rate Per 100 S Rs. 4057.55 Say 4,057.55
Composite Rate Per Sqm Rs. 436.59 Say 436.60

Page 42
DESCRIPTION OF ITEM NO 26: Asbestos cement corrugated sheet roofing
including necessary over laps and G.I. hooks,
bolts, nuts, screws washers and bitumen washers
etc. (excluding valleys and ridges etc.)

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Corrugated A.C. sheets with 25% over


lapping and wastage. 125 Sft 20.00 P. Sft 2,500.00
G.I. or limpet washers and bilumatic
washers. 7 Doz 11.00 Doz 77.00
G.I. bolts with nuts. 2 Doz 20.00 Doz 40.00
G.I. hook bolts and nuts 6"x5/16" 1.5 Doz 20.00 Doz 30.00

Total 2,647.00
Contractor's Profit & Overhead 20 Percent 529.40
Total 3,176.40

Labour
Rate for 150 Sft
Cooly 2.00 Nos 140.00 P. Day 280.00
Carpenter 1.00 No 300.00 P. Day 300.00

Total 580.00
Sundries 20 Percent 116.00
Total 696.00

Contractor's Profit & Overhead 20 Percent 139.20


Total 835.20

Item Rates
Labour Rate Per 100 Sft Rs. 835.20 Say 835.20
Labour Rate Per Sqm Rs. 89.87 Say 89.85

Composite Rate Per 100 S Rs. 4011.60 Say 4,011.60


Composite Rate Per Sqm Rs. 431.65 Say 431.65

Page 43
DESCRIPTION OF ITEM NO 27: Extra labour for erection of G.I. sheets, flat sheet
or asbestos sheet roofing, above 20' height in
difficult position including lifting with care and
special scaffolding along live electric wires.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Rate Analysis for 150 Sft


Labour

Unskillied Cooly 0.50 No 140.00 P. Day 70.00


Fitter 0.06 No 170.00 P. Day 10.20

Total 80.20
Sundries 20 Percent 16.04
Total 96.24

Contractor's Profit & Overhead 20 Percent 19.25


Total 115.49

Item Rates
Labour Rate Per 100 Sft Rs. 76.99 Say 77.00

Labour Rate Per Sqm Rs. 8.28 Say 8.30

Page 44
DESCRIPTION OF ITEM NO 28: Fixing asbestos cement sheet ridges and valleys
¼" (6mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 61 Rft
Material

A.C. ridge sheet for a shed of 60'x30'


(18x15 M) or 61 Rft 61.00 Rft 30.00 P. Rft 1,830.00
G.I. bolts and nut with washers 5.00 Doz 20.00 Doz 100.00
Bituminous washer 5.00 Doz 11.00 Doz 55.00

Total 1,985.00
Contractor's Profit & Overhead 20 Percent 397.00
Total 2,382.00

Rate Per Rft 2382.00 39.05


61
Labour
Rate Analysis for 100 Rft
Cooly 2.00 Nos 140.00 P. Day 280.00
Carpenter 1.50 No 300.00 P. Day 450.00

Total 730.00
Sundries 20 Percent 146.00
Total 876.00

Contractor's Profit & Overhead 20 Percent 175.20


Total 1,051.20

Item Rates
Labour Rate Per Rft Rs. 10.51 Say 10.50
Labour Rate Per Rm Rs. 34.48 Say 34.50

Composite Rate Per Rft Rs. 49.56 Say 49.55


Composite Rate Per Rm Rs. 162.56 Say 162.55

Page 45
DESCRIPTION OF ITEM NO 29: Plain galvanized iron sheet ridging including
fixture, timber for ridge roll and ridge sheeting.

a) 6" (150mm) lap and 18" (450mm) over all of


22 gauge G.I. sheet ridging.

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

G.I. Sheet 22 gauge 1.50 Sft


10% for over lapping 0.15 Sft
1.65 Sft
1.65 Sft @ 1.12 Lbs/Sft = 1.85 Lbs 0.84 Kg 31.00 P. Kg 26.04
Deodar wood 0.08 Cft 500.00 P. Cft 40.00

Total 66.04
Contractor's Profit & Overhead 20 Percent 13.21
Total 79.25

Labour

Cooly 0.03 No 140.00 P. Day 4.20


Carpenter 0.03 No 300.00 P. Day 9.00
Blacksmith 0.03 No 170.00 P. Day 5.10

Total 18.30
Sundries 20 Percent 3.66
Total 21.96

Contractor's Profit & Overhead 20 Percent 4.39


Total 26.35

Item Rates
Labour Rate Per Rft Rs. 26.35 Say 26.35
Labour Rate Per Rm Rs. 86.43 Say 86.45

Composite Rate Per Rft Rs. 105.60 Say 105.60


Composite Rate Per Rm Rs. 346.37 Say 346.35

Page 46
Item No. 29 Plain galvanized iron sheet ridging including
fixture, timber for ridge roll and ridge sheeting.

b) 9" lap and 24" over all of 24 gauge G.I.


sheet ridging.

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

G.I. Sheet 24 gauge 2.10 Sft


10% for over lapping 0.21 Sft
2.31 Sft
2.31 Sft @ 0.83 Lbs/Sft = 1.94 Lbs 0.88 Kg 31.00 P. Kg 27.28
Deodar wood 0.07 Cft 500.00 P. Cft 35.00

Total 62.28
Contractor's Profit & Overhead 20 Percent 12.46
Total 74.74

Labour

Cooly 0.06 No 140.00 P. Day 8.40


Carpenter 0.03 No 300.00 P. Day 9.00
Blacksmith 0.03 No 170.00 P. Day 5.10

Total 22.50
Sundries 10 Percent 2.25
Total 24.75

Contractor's Profit & Overhead 20 Percent 4.95


Total 29.70

Item Rates
Labour Rate Per Rft Rs. 29.70 Say 29.70
Labour Rate Per Rm Rs. 97.42 Say 97.40

Composite Rate Per Rft Rs. 104.44 Say 104.45


Composite Rate Per Rm Rs. 342.55 Say 342.55

Page 47
Item No. 29 Plain galvanized iron sheet ridging including
fixture, timber for ridge roll and ridge sheeting.

c) 12" (300mm) lap and 30" (750mm) over all of


22 gauge G.I. sheet ridging.

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

22 Gauge G.I. Sheet 2.50 Sft


Add 10% for over lapping 0.25 Sft
2.75 Sft
2.75 Sft @ 1.12 Lbs/Sft = 3.08 Lbs 1.40 Kg 31.00 P. Kg 43.40
Deodar wood 0.07 Cft 500.00 P. Cft 35.00

Total 78.40
Contractor's Profit & Overhead 20 Percent 15.68
Total 94.08

Labour

Cooly 0.06 No 140.00 P. Day 8.40


Carpenter 0.03 No 300.00 P. Day 9.00
Blacksmith 0.03 No 170.00 P. Day 5.10

Total 22.50
Sundries 10 Percent 2.25
Total 24.75

Contractor's Profit & Overhead 20 Percent 4.95


Total 29.70

Item Rates
Labour Rate Per Rft Rs. 29.70 Say 29.70
Labour Rate Per Rm Rs. 97.42 Say 97.40

Composite Rate Per Rft Rs. 123.78 Say 123.80


Composite Rate Per Rm Rs. 406.00 Say 406.00

Page 48
DESCRIPTION OF ITEM NO 30: Plain 22 Gauge G.I. sheet gutter semi-circular
8" dia meter.

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

G.I. Sheet (22 Guage) 1.38Lbs(0 .63) K 31.00 P. Kg 19.53


Wrought iron bracket complete with bolts,
Nuts and rivets etc. 1.00 No 12.00 Each 12.00

Total 31.53
Contractor's Profit & Overhead 20 Percent 6.31
Total 37.84

Labour

Cooly 0.03 No 140.00 P. Day 4.20


Blacksmith 0.03 No 170.00 P. Day 5.10

Total 9.30
Sundries 10 Percent 0.93
Total 10.23

Contractor's Profit & Overhead 20 Percent 2.05


Total 12.28

Item Rates
Labour Rate Per Rft Rs. 12.28 Say 12.30
Labour Rate Per Rm Rs. 40.27 Say 40.25

Composite Rate Per Rft Rs. 50.11 Say 50.10


Composite Rate Per Rm Rs. 164.37 Say 164.35

Page 49
DESCRIPTION OF ITEM NO 31: Making masonry ventilators in cement sand
mortar (1:4)

Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material
Per
Pacca bricks 50.00 Nos 1200.00 1000 N 60.00
Cement 0.17 Bag 230.00 P. Bag 39.10
Sand 0.88 Cft 3.50 P. Cft 3.08

Total 102.18
Contractor's Profit & Overhead 20 Percent 20.44
Total 122.62

Labour
Rate Analysis for 1.5 No.
Cooly 1.00 No 140.00 P. Day 140.00
Mason 1.00 No 300.00 P. Day 300.00

Total 440.00
Sundries 10 Percent 44.00
Total 484.00

Contractor's Profit & Overhead 20 Percent 96.80


Total 580.80

Item Rates
Labour Rate for Each Rs. 387.20 Say 387.20

Composite Rate for Each Rs. 509.82 Say 509.80

Page 50
DESCRIPTION OF ITEM NO 32: Fixing water spouts or parnalas.

Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Rate Analysis for 1.25 No.


Labour

Unskilled Cooly 0.25 No 140.00 35.00


Mason 0.25 No 300.00 75.00

Total 110.00
Sundries 10 Percent 11.00
Total 121.00

Contractor's Profit & Overhead 20 Percent 24.20


Total 145.20

Item Rates
Labour Rate for Each Rs. 116.16 Say 116.15

Page 51
DESCRIPTION OF ITEM NO 33: Making drip course 2"x½" (50x12mm) under
RCC Slab edges in outer opening, in cement, sand
mortar (1:2)

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 100 Rft
Material

Ready mortar 100 Rft


100x1/6x1/24 = 0.69 Cft Say 0.75 Cft
Cement 0.75 = 0.25 Cft 0.20 Bag 230.00 P. Bag 46.00
3
Sand 0.50 Cft 3.50 P. Cft 1.75

Total 47.75
Contractor's Profit & Overhead 20 Percent 9.55
Total 57.30

Rate Per Rft 57.30 0.57


100
Labour
Rate Analysis for 150 Rft
Unskilled Cooly 1.00 No 140.00 P. Day 140.00
Mason 1.00 No 300.00 P. Day 300.00
Bahishti 0.03 No 160.00 P. Day 4.80

For Making Surface

Unskilled Cooly 0.13 No 140.00 P. Day 9.75


Bahishti 0.44 No 160.00 P. Day 37.40

Total 491.95
Sundries 10 Percent 49.20
Total 541.15

Contractor's Profit & Overhead 20 Percent 108.23


Total 649.37

Item Rates
Labour Rate Per Rft Rs. 4.33 Say 4.35
Labour Rate Per Metre Rs. 14.20 Say 14.20
Composite Rate Per Rft Rs. 4.90 Say 4.90
Composite Rate Per Metr Rs. 16.08 Say 16.10

Page 52
DESCRIPTION OF ITEM NO 34: Supplying and laying twin G.I. sheet 20 SWG
duly painted with bitumen with polythene film 300
gauge in between to provide a sliding joint under
the bearing of beams with 3" long 3/8" (10mm)
bar to act as hold fast on wall & beam.

Detail Unit Rate (British System) per Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

G.I. sheet 20 gauge 2'x1'= 2Sft @ 1.44Lbs 2.88Lbs(1 .31) K 31.00 P. Kg 40.61
Bitumen for paint 2.72Lbs(1 .23) K 14.00 P. Kg 17.22
Polythene film 300 gauge 0.05Lbs(0 .03) K 70.00 P. Kg 2.10
4 Nos x 3" (75mm) long 3/8" (10mm)
dia bar = 0.18 Rft 0.03 Kg 17.00 P. Kg 0.51

Total 60.44
Contractor's Profit & Overhead 20 Percent 12.09
Total 72.53

Labour
Rate Analysis for 2 Sft
Cooly
placing in position 0.02 No 140.00 P. Day 2.80
Blacksmith for cutting of G.I. sheet 0.03 No 170.00 P. Day 5.10
Welding of bars 4 points 4.00 Nos 1.87 P. Point 7.47

Total 15.37
Sundries 10 Percent 1.54
Total 16.90

Contractor's Profit & Overhead 20 Percent 3.38


Total 20.28

Item Rates
Labour Rate Per Sft Rs. 10.14 Say 10.15
Labour Rate Per Sqm Rs. 109.13 Say 109.15

Composite Rate Per Sft Rs. 82.67 Say 82.65


Composite Rate Per Sqm Rs. 889.53 Say 889.55

Page 53
DESCRIPTION OF ITEM NO 35: Providing and laying roof insulation, comprising of
single layer of tiles 9"x4½"x1½" (225 x 112.5 x
40mm) grouted with cement sand mortar 1:3 laid
over 2" thick earth (including Mud Plaster) over
thermopore sheet, over polythene sheet 300 gaug
over a layer of bitumen, complete in all respect.

i) Thermopore sheet ½" (13mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material
Per
Brick tiles 9"x4½"x1½" (225x112.5x40mm) 350.00 Nos 1050.00 1000 N 367.50
Sand 2.00 Cft 3.50 P. Cft 7.00
Cement 0.50 Bag 230.00 P. Bag 115.00
Bitumen 34Lbs(15 .43) K 14.00 P. Kg 216.02
Earth 20.00 Cft 1.50 P. Cft 30.00
Polythene 0.03" (0.08mm) including
wastage 5% 1.58Lbs(0 .72) K 70.00 P. Kg 50.40
Thermopore ½" (12mm) thick 1/c 5%
wastage 105.00 Sft 2.85 P. Sft 299.25

Total 1,085.17
Contractor's Profit & Overhead 20 Percent 217.03
Total 1,302.20

Labour

Plasterer 0.13 No
Mason for laying 0.50 No
Mason for grouting 0.13 No
0.75 No 300.00 P. Day 225.00

Coolies for mud 0.50 No


for mud plaster 0.75 No
for tile laying grouting 0.25 No
1.50 Nos 140.00 P. Day 210.00

240.00

Page 54
i) Thermopore sheet ½" (13mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Painter for painting 0.50 No 170.00 P. Day 85.00


Bahishti 0.50 No 160.00 P. Day 80.00

Total 367.50
Sundries 10 Percent 36.75
Total 404.25

Contractor's Profit & Overhead 20 Percent 80.85


Total 485.10

Item Rates
Labour Rate Per 100 Sft Rs. 485.10 Say 485.10
Labour Rate Per Sqm Rs. 52.20 Say 52.20

Composite Rate Per 100 S Rs. 1787.30 Say 1,787.30


Composite Rate Per Sqm Rs. 192.31 Say 192.30

Page 55
Item No. 35 Providing and laying roof insulation, comprising of
single layer of tiles 9"x4½"x1½" (225 x 112.5 x
40mm) grouted with cement sand mortar 1:3 laid
over 2" thick earth (including Mud Plaster) over
thermopore sheet, over polythene sheet 300 gaug
over a layer of bitumen, complete in all respect.

ii) ¾" (20mm) thick thermopore sheet.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material
Per
Clay tiles 9"x4½"x1½" (225x112.5x40mm) 350.00 Nos 1050.00 1000 N 367.50
Sand 2.00 Cft 3.50 P. Cft 7.00
Cement 0.50 Bag 230.00 P. Bag 115.00
Bitumen 34Lbs(15 .43) K 14.00 P. Kg 216.02
Earth 20.00 Cft 1.50 P. Cft 30.00
Polythene 0.03" (0.08mm) 1/c
wastage 5% 1.58Lbs(0 .72) K 70.00 P. Kg 50.40
Thermopore ¾" (19mm) thick 1/c 5%
wastage 105.00 Sft 4.26 P. Sft 447.30

Total 1,233.22
Contractor's Profit & Overhead 20 Percent 246.64
Total 1,479.86

Labour

Plasterer 0.13 No
Mason for laying 0.50 No
Mason for grouting 0.13 No
0.75 No 300.00 P. Day 225.00
0.75 Say

Coolies for mud 0.50 No


for mud plaster 0.75 No
for tile laying grouting 0.25 No
1.50 Nos 140.00 P. Day 210.00

Page 56
ii) ¾" (20mm) thick thermopore sheet.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Painter for painting 0.50 No 170.00 P. Day 85.00


Bahishti 0.50 No 160.00 P. Day 80.00

Total 600.00
Sundries 10 Percent 60.00
Total 660.00

Contractor's Profit & Overhead 20 Percent 132.00


Total 792.00

Item Rates
Labour Rate Per 100 Sft Rs. 792.00 Say 792.00
Labour Rate Per Sqm Rs. 85.22 Say 85.20

Composite Rate Per 100 S Rs. 2271.86 Say 2,271.85


Composite Rate Per Sqm Rs. 244.45 Say 244.45

Page 57
Item No. 35 Providing and laying roof insulation, comprising of
single layer of tiles 9"x4½"x1½" (225 x 112.5 x
40mm) grouted with cement sand mortar 1:3 laid
over 2" thick earth (including Mud Plaster) over
thermopore sheet, over polythene sheet 300 gaug
over a layer of bitumen, complete in all respect.

iii) Thermopore sheet 1" (25mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material
Per
Brick tiles 9"x4½"x1½" (225x112.5x40mm) 350.00 Nos 1050.00 1000 N 367.50
Sand 2.00 Cft 3.50 P. Cft 7.00
Cement 0.50 Bag 230.00 P. Bag 115.00
Bitumen 34Lbs(15 .43) K 14.00 P. Kg 216.02
Earth 20.00 Cft 1.50 P. Cft 30.00
Polythene 0.03" (0.08mm) 1/c
wastage 5% 1.58Lbs(0 .72) K 70.00 P. Kg 50.40
Thermopore 1" (13mm) thick 1/c 5%
wastage 105.00 Sft 5.68 P. Sft 596.40

Total 1,382.32
Contractor's Profit & Overhead 20 Percent 276.46
Total 1,658.78

Labour

Plasterer 0.13 No
Mason for laying 0.50 No
Mason for grouting 0.13 No
0.76 No 300.00 P. Day 226.50

Coolies for mud 0.50 No


for mud plaster 0.75 No
for tile laying grouting 0.25 No
1.50 Nos 140.00 P. Day 210.00

240.00

Page 58
Item No. 35
iii) Thermopore sheet 1" (25mm) thick.

Detail Unit Rate (British System) per 100 Sft

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Painter for painting 0.50 No 170.00 P. Day 85.00


Bahishti 0.50 No 160.00 P. Day 80.00

Total 367.50
Sundries 10 Percent 36.75
Total 404.25

Contractor's Profit & Overhead 20 Percent 80.85


Total 485.10

Item Rates
Labour Rate Per 100 Sft Rs. 485.10 Say 485.10
Labour Rate Per Sqm Rs. 52.20 Say 52.20

Composite Rate Per 100 S Rs. 2143.88 Say 2,143.90


Composite Rate Per Sqm Rs. 230.68 Say 230.70

Page 59
DESCRIPTION OF ITEM NO 36: Providing and fixing A.C. rain water down pipe
4" (100mm) dia with shoe, T-bend, clamp etc.

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 13 Rft
Material

A.C. pipe 4" (100mm) dia 13.00 Rft 50.00 P. Rft 650.00
A.C. T-bend 4" (100mm) dia 1.00 No 55.00 Each 55.00
A.C. shoe 1.00 No 55.00 Each 55.00
Clamps & Nuts 2.00 Nos 20.00 Each 40.00

Total 800.00
Contractor's Profit & Overhead 20 Percent 160.00
Total 960.00

Rate Per Rft 960.00 73.85


13
Labour
Rate Analysis for 20 Rft
Plumber 0.20 No 170.00 P. Day 34.00
Unskilled Cooly 0.20 No 140.00 P. Day 28.00

Total 62.00
Sundries 10 Percent 6.20
Total 68.20

Contractor's Profit & Overhead 20 Percent 13.64


Total 81.84

Item Rates
Labour Rate Per Rft Rs. 4.09 Say 4.10
Labour Rate Per Rm Rs. 13.42 Say 13.40

Composite Rate Per Rft Rs. 77.94 Say 77.95


Composite Rate Per Rm Rs. 255.64 Say 255.65

Page 60
DESCRIPTION OF ITEM NO 37: Making jharries in existing brick masonry for
providing recesses for bearing of RCC roof slab
including repairing the damaged face.

i) For slab upto 6" (150mm) thick

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 40 Rft
Material

Cement for repairing Jharry 0.11 Bag 230.00 Bag 25.53


Sand 0.57 Cft. 350.00 % Cft. 2.00

Total 27.53
Contractor's Profit & Overhead 20 Percent 5.51
Total 33.03

Rate Per Rft 33.03 0.83


40
Labour
Rate Analysis for 50 Rft
Mason 1.00 No 300.00 P. Day 300.00

Total 300.00
Sundries 10 Percent 30.00
Total 330.00

Contractor's Profit & Overhead 20 Percent 66.00


Total 396.00

Item Rates
Labour Rate Per Rft Rs. 7.92 Say 7.90
Labour Rate Per Rm Rs. 25.98 Say 26.00

Composite Rate Per Rft Rs. 8.75 Say 8.75


Composite Rate Per Rm Rs. 28.69 Say 28.70

Page 61
Item No. 37 Making jharries in existing brick masonry for
providing recesses for hearing of RCC roof slab
including repairing the damaged face.

ii) For slab exceeding 6" (150mm) to 12" (300mm)


thick.

Detail Unit Rate (British System) per Rft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 40 Rft
Material

Cement 0.20 Bag 230.00 Bag 46.00


Sand 1.15 Cft. 350.00 % Cft. 4.01

Total 50.01
Contractor's Profit & Overhead 20 Percent 10.00
Total 60.01

Rate Per Rft 60.01 1.50


Labour 40
Rate Analysis for 50 Rft
Mason 1.50 No 300.00 P. Day 450.00
Cooly 0.25 No 140.00 P. Day 35.00

Total 485.00
Sundries 10 Percent 48.50
Total 533.50

Contractor's Profit & Overhead 20 Percent 106.70


Total 640.20

Item Rates
Labour Rate Per Rft Rs. 12.80 Say 12.80
Labour Rate Per Rm Rs. 42.00 Say 42.00

Composite Rate Per Rft Rs. 14.30 Say 14.30


Composite Rate Per Rm Rs. 46.92 Say 46.90

Page 62
DESCRIPTION OF ITEM NO 38: Making recess in exixting brick masonery for
bearing of beam, girder, R.S. joist, etc. including
repairing damaged face.

i) Upto 1'.0" (300mm) height of girder or beam.

Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 12 Holes
Material

Cement 0.111 Bag 230.00 Bag 25.53


Sand 0.57 Cft. 350.00 % Cft. 2.00

Total 27.53
Contractor's Profit & Overhead 20 Percent 5.51
Total 33.03

Labour

Mason 1.00 No 300.00 P. Day 300.00

Total 300.00
Sundries 10 Percent 30.00
Total 330.00

Contractor's Profit & Overhead 20 Percent 66.00


Total 396.00

Item Rates
Labour Rate for Each Rs. 33.00 Say 33.00

Composite Rate for Each Rs. 35.75 Say 35.75

Page 63
Item No. 38 Making recess in exixting brick masonery for
bearing of beam, girder, R.S. joist, etc. including
repairing damaged face.

ii) For every 6" (150mm) additional height or part


thereof.

Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 25 Holes
Material

Cement 0.111 Bag 230.00 Bag 25.53


Sand 0.57 Cft. 350.00 % Cft. 2.00

Total 27.53
Contractor's Profit & Overhead 20 Percent 5.51
Total 33.03

Labour

Mason 1.00 No 300.00 P. Day 300.00

Total 300.00
Sundries 10 Percent 30.00
Total 330.00

Contractor's Profit & Overhead 20 Percent 66.00


Total 396.00

Item Rates
Labour Rate for Each Rs. 15.84 Say 15.85

Composite Rate for Each Rs. 17.16 Say 17.15

Page 64
DESCRIPTION OF ITEM NO 39: Hoisting R.S. Beams and wooden beams and
placing in position.

Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Labour

Mason 0.20 No 300.00 P. Day 35.00


Unskilled Coolies 0.60 No 140.00 P. Day 45.00

Total 80.00
Sundries 10 Percent 8.00
Total 88.00

Contractor's Profit & Overhead 20 Percent 17.60


Total 105.60

Item Rates

Labour Rate for Each Rs. 52.80 Rs. 52.80

Page 65
DESCRIPTION OF ITEM NO 40: Hoisting and placing in position sahl ballies, over
roof.

Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 35 Nos

Labour

Mason 1.00 No 300.00 P. Day 300.00


Unskilled Coolies 1.00 No 140.00 P. Day 140.00

Total 440.00
Sundries 10 Percent 44.00
Total 484.00

Contractor's Profit & Overhead 20 Percent 96.80


Total 580.80

Item Rates

Labour Rate for Each Rs. 16.59 Rs. 16.60

Page 66
DESCRIPTION OF ITEM NO 41: Hoisting precast RCC/Pre-stressed concrete
battens and placing in position.

Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Labour

Mason 1.00 No 300.00 P. Day 300.00


Unskilled Coolies 3.00 Nos 140.00 P. Day 420.00

Total 720.00
Sundries 10 Percent 72.00
Total 792.00

Contractor's Profit & Overhead 20 Percent 158.40


Total 950.40

a) 5' to 6' (1.5 to 1.8 M) long


Labour per No./ Assumed for 70 Nos 950.40 13.58 Say 13.60
70
b) 6' to 7' (1.8 to 2.10 M) long
Labour per No./ Assumed for 50 Nos 950.40 19.01 Say 19.00
50
c) 7' to 8' (2.10 to 2.40 M) long
Labour per No./ Assumed for 40 Nos 950.40 23.76 Say 23.75
40
d) 8' to 9' (2.40 to 2.70 M) long
Labour per No./ Assumed for 30 Nos 950.40 31.68 Say 31.70
30
e) Above 9' (2.70 M) length
Labour per No./ Assumed for 25 Nos 950.40 38.02 Say 38.00
25

Page 67
DESCRIPTION OF ITEM NO 42: Hoisting and placing in position RC trough.

Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Labour

Mason 1.00 No 300.00 P. Day 300.00


Unskilled Coolies 3.00 Nos 140.00 P. Day 420.00

Total 720.00
Sundries 10 Percent 72.00
Total 792.00

Contractor's Profit & Overhead 20 Percent 158.40


Total 950.40

a) Upto 10' (3 M) length


Labour per No./ Assumed for 25 Nos 950.40 38.02 Say 38.00
25
b) 10' to 11' (3 to 3.30 M) length
Labour per No./ Assumed for 20 Nos 950.40 47.52 Say 47.50
20
c) 11' to 12' (3.30 to 3.60 M) length
Labour per No./ Assumed for 15 Nos 950.40 63.36 Say 63.35
15
d) 12' to 13' (3.60 to 3.90 M) length
Labour per No./ Assumed for 13 Nos 950.40 73.11 Say 73.10
13
e) 13' to 14' (3.90 to 4.20 M) length
Labour per No./ Assumed for 12 Nos 950.40 79.19 Say 79.20
12
f) 14' to 15' (4.20 to 4.50 M) length
Labour per No./ Assumed for 11 Nos 950.40 86.40 Say 86.40
11
g) 15' to 16' (4.50 to 4.80 M) length
Labour per No./ Assumed for 10 Nos 950.40 95.04 Say 95.05
10
h) 16' to 17' (4.80 to 5.1 M) length
Labour per No./ Assumed for 9 Nos 950.40 105.60 Say 105.60
9

Page 68
Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.) Amount (Rs.)

i) 17' to 18' (5.1 to 5.4 M) length


Labour per No./ Assumed for 7 Nos 950.40 135.77 Say 135.75
7
j) 18' to 19' (5.4 to 5.7 M) length
Labour per No./ Assumed for 6.5 Nos 950.40 146.22 Say 146.20
6.5
k) 19' to 20' (5.7 to 6 M) length
Labour per No./ Assumed for 6 Nos 950.40 158.40 Say 158.40
6

Page 69
DESCRIPTION OF ITEM NO 43: Hoisting and placing in position RC inverted
battens.

Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Labour

Mason 1.00 No 300.00 P. Day 300.00


Unskilled Coolies 4.00 Nos 140.00 P. Day 560.00

Total 860.00
Sundries 10 Percent 86.00
Total 946.00

Contractor's Profit & Overhead 20 Percent 189.20


Total 1,135.20

i) Upto 10' (3 M) Span


Labour per No./ Assumed for 40 Nos 1135.20 28.38 Say 28.40
40
ii) From 10' to 12' (3 to 3.6 M) Span
Labour per No./ Assumed for 18 Nos 1135.20 63.07 Say 63.05
18
iii) From 12' to 13' (3.6 to 3.9 M) Span
Labour per No./ Assumed for 15 Nos 1135.20 75.68 Say 75.70
15
iv) From 13' to 14' (3.9 to 4.2 M) Span
Labour per No./ Assumed for 12 Nos 1135.20 94.60 Say 94.60
12
v) From 14' to 15' (4.2 to 4.5 M) Span
Labour per No./ Assumed for 11 Nos 1135.20 103.20 Say 103.20
11
vi) From 15' to 16' (4.5 to 4.8 M) Span
Labour per No./ Assumed for 10 Nos 1135.20 113.52 Say 113.50
10
ii) From 16' to 18' (4.8 to 5.4 M) Span
Labour per No./ Assumed for 8 Nos 1135.20 141.90 Say 141.90
8
ii) From 18' to 20' (5.4 to 6 M) Span
Labour per No./ Assumed for 5 Nos 1135.20 227.04 Say 227.05
5

Page 70
DESCRIPTION OF ITEM NO 44: Reinforced cement concrete spout, including
fixing in position, with top & bottom khurras.

Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Material

Cement 0.25 Bag 230.00 P. Bag 57.50


Sand 1.26 Cft 3.50 P. Cft 4.41
Aggregate 2.53 Cft 18.50 P. Cft 46.81

Total 108.72

Total 108.72

Contractor's Profit & Overhead 20 Percent 21.74


Total 130.46

Labour for 1.5 Nos.

Mason 0.40 No 300.00 P. Day 120.00


Unskilled Coolies 0.40 No 140.00 P. Day 56.00

Total 176.00
Sundries 10 Percent 17.60
Total 193.60

Contractor's Profit & Overhead 20 Percent 38.72


Total 232.32

Item Rates
Labour Rate for Each Rs. 154.88 Say 154.90

Composite Rate for Each Rs. 285.34 Say 285.35

Page 71
nished works include the removal of surplus debris, unused

%, 32% and 51% on labour rates only or 6%, 15% and 23% on
es for 2nd, 3rd fourth and subsequent floors respectively.

Amount (Rs.)

Page 72
Amount (Rs.)

Page 73
Second class tile roofing consisting of 4" (100mm)
earth and 1" (25mm) mud plaster with gobri leeping
over ½" thick cement plaster 1:6 with 34 lbs per %
Sft or 1.72 Kg/Sqm of hot bitumen coating sand

(300x150x50mm) tiles, laid in 1:6 cement pointing


underneath of tiles complete, including curing etc.

Amount (Rs.)

Page 74
Amount (Rs.)

Page 75
Covering mud roof with coaltar and fine sand.

Amount (Rs.)

Page 76
The unit of rate is for filling 100 Sft of roof.

Wooden battons over beams filled with deodar

Amount (Rs.)

Page 77
Amount (Rs.)

Page 78
Amount (Rs.)

Page 79
Single layer of tiles 9"x4½x1½" (225 x 112.5 x
40mm) laid over 4" (100mm) earth and 1" (25mm)
mud plaster without Bhoosa grouted with cement
sand 1:3 on top of RCC roof slab provided with 34

Amount (Rs.)

Page 80
Jack arch roofing 4½" (112.5mm) thick laid in 1:5
cement mortar including an average depth of 4"
(100mm) thick cement concrete in haunches and
over crown with 3" (75mm) earth and 1" (25mm)

bitumen coating centering, laying skew bricks in


cement sand mortar 1:3 and encasing exposed flanges
of the joints with fine cement concrete 1:2:4. Using

Amount (Rs.)

Page 81
Amount (Rs.)

Page 82
Jack arch roofing 4½" (112.5mm) thick laid in 1:5
cement mortar including an average depth of 4"
(100mm) thick cement concrete in haunches and
over crown with 3" (75mm) earth and 1" (25mm)

bitumen coating centering, laying skew bricks in


cement sand mortar 1:3 and encasing exposed
flanges of the joints with fine cement concrete

Amount (Rs.)

Page 83
Amount (Rs.)

Page 84
Jack arch roofing 4½" (112.5mm) thick laid in 1:5
cement mortar including an average depth of 4"
(100mm) thick cement concrete in haunches and
over crown with ½" (12mm) thick cement plaster
1:6 on top (Except earth filling, plaster and gobri),
soffits of arches cement plastered. The rate also
includes bitumen coating centering, laying skew
bricks in cement sand mortar 1:3 and encasing
exposed flanges of the joints with fine cement

Amount (Rs.)

Page 85
Amount (Rs.)

Page 86
Jack arch roofing 4½" (112.5mm) thick laid in 1:5
cement mortar including an average depth of 4"
(100mm) thick cement concrete in haunches and
over crown with ½" (12mm) thick cement plaster
1:6 on top (Except earth filling, plaster and gobri),
soffits of arches cement plastered. The rate also
includes bitumen coating centering, laying skew
bricks in cement sand mortar 1:3 and encasing
exposed flanges of the joints with fine cement

Amount (Rs.)

Page 87
Amount (Rs.)

Page 88
Amount (Rs.)

Page 89
Jack arch roofing of shingle and cement concrete
(1:3:6), 4½" (112.5mm) thick at crown, with ½"

supplying erecting and dismantling centering.

Amount (Rs.)

Page 90
ramming with 1" (25mm) mud plaster finished

3" (75mm) thick earth filling and 1" (25mm) mud

Amount (Rs.)

Page 91
ramming with 1" (25mm) mud plaster finished

Amount (Rs.)

Page 92
1/8"(3mm) thick gobri leeping on roofs or floors.

Amount (Rs.)

Page 93
Amount (Rs.)

Page 94
wind ties complete in all respect without valleys

Amount (Rs.)

Page 95
G.I. bolts, nuts, limpet and bitumen washers, wind
ties complete in all respect without valleys and

Amount (Rs.)

Page 96
G.I. bolts, nuts, limpet and bitumen washers, wind
ties complete in all respect without valleys and

Amount (Rs.)

Page 97
Khassi parnalas in cement and sand mortar (1:2)
12" (300mm) outside width finished smooth with

Amount (Rs.)

Page 98
Making Khuras, on roof size 2' x 2' x 4" (600 x 600 x

Amount (Rs.)

Page 99
Bottom khuras of brick masonry in cement mortar

Amount (Rs.)

Page 100
water down pipe including clamp and fixing in

Amount (Rs.)

Page 101
water down pipe including clamp and fixing in

Amount (Rs.)

Page 102
Plain galvanized iron sheets flashing of 22 gauge.

Amount (Rs.)

Page 103
flashing over roof expansion joint complete in all

Amount (Rs.)

Page 104
Cast iron rain water down pipe fixed in position,
excluding heads and shoes, but including painting

Amount (Rs.)

Page 105
Cast iron rain water down pipe fixed in position,
excluding heads and shoes, but including painting

Amount (Rs.)

Page 106
Amount (Rs.)

Page 107
Shoes bends or offsets for cast iron rain water

Amount (Rs.)

Page 108
Amount (Rs.)

Page 109
Laying ½" (12mm) thick deodar ceiling complete

Amount (Rs.)

Page 110
including battens, rolls, screw, clips etc. (planking

Amount (Rs.)

Page 111
Amount (Rs.)

Page 112
including battens rolls screw clips etc. (planking

Amount (Rs.)

Page 113
bolts, nuts, screws washers and bitumen washers

Amount (Rs.)

Page 114
Extra labour for erection of G.I. sheets, flat sheet
or asbestos sheet roofing, above 20' height in
difficult position including lifting with care and

Amount (Rs.)

Page 115
Fixing asbestos cement sheet ridges and valleys

Amount (Rs.)

Page 116
fixture, timber for ridge roll and ridge sheeting.

Amount (Rs.)

Page 117
fixture, timber for ridge roll and ridge sheeting.

Amount (Rs.)

Page 118
fixture, timber for ridge roll and ridge sheeting.

12" (300mm) lap and 30" (750mm) over all of

Amount (Rs.)

Page 119
Plain 22 Gauge G.I. sheet gutter semi-circular

Amount (Rs.)

Page 120
Amount (Rs.)

Page 121
Amount (Rs.)

Page 122
RCC Slab edges in outer opening, in cement, sand

Amount (Rs.)

Page 123
duly painted with bitumen with polythene film 300
gauge in between to provide a sliding joint under
the bearing of beams with 3" long 3/8" (10mm)

Amount (Rs.)

Page 124
Providing and laying roof insulation, comprising of
single layer of tiles 9"x4½"x1½" (225 x 112.5 x
40mm) grouted with cement sand mortar 1:3 laid
over 2" thick earth (including Mud Plaster) over
thermopore sheet, over polythene sheet 300 gauge
over a layer of bitumen, complete in all respect.

Amount (Rs.)

Page 125
Amount (Rs.)

Page 126
Providing and laying roof insulation, comprising of
single layer of tiles 9"x4½"x1½" (225 x 112.5 x
40mm) grouted with cement sand mortar 1:3 laid
over 2" thick earth (including Mud Plaster) over
thermopore sheet, over polythene sheet 300 gauge
over a layer of bitumen, complete in all respect.

Amount (Rs.)

Page 127
Amount (Rs.)

Page 128
Providing and laying roof insulation, comprising of
single layer of tiles 9"x4½"x1½" (225 x 112.5 x
40mm) grouted with cement sand mortar 1:3 laid
over 2" thick earth (including Mud Plaster) over
thermopore sheet, over polythene sheet 300 gauge
over a layer of bitumen, complete in all respect.

Amount (Rs.)

Page 129
Amount (Rs.)

Page 130
Providing and fixing A.C. rain water down pipe
4" (100mm) dia with shoe, T-bend, clamp etc.

Amount (Rs.)

Page 131
providing recesses for bearing of RCC roof slab

Amount (Rs.)

Page 132
providing recesses for hearing of RCC roof slab

For slab exceeding 6" (150mm) to 12" (300mm)

Amount (Rs.)

Page 133
bearing of beam, girder, R.S. joist, etc. including

Upto 1'.0" (300mm) height of girder or beam.

Amount (Rs.)

Page 134
bearing of beam, girder, R.S. joist, etc. including

For every 6" (150mm) additional height or part

Amount (Rs.)

Page 135
Amount (Rs.)

Page 136
Hoisting and placing in position sahl ballies, over

Amount (Rs.)

Page 137
Amount (Rs.)

Page 138
Amount (Rs.)

Page 139
Amount (Rs.)

Page 140
Amount (Rs.)

Page 141
Amount (Rs.)

Page 142

Вам также может понравиться