The schedule below identifies timelines to complete pending deliverables for the Partner Center of
Excellence (PCoE), Persol Systems Ltd.

S/N Deliverable Dependency Date

1. Knowledge transfer on ITSM 12/10/2018


Processes

2. Persol SAP Landscape integration with  DNS reverse name 15-16/10/2018


Active Directory for Single-Sign On lookup
(SSO)  Active Directory
Service Account

3. ITSM Integration with Exchange for  Mail host and port 15-16/10/2018
Email Notification information.

4. Replicate Fiori App implementation on 17-24/10/2018


QA and Production clients

5. User Acceptance Test  Test Scripts 24-26/10/2018

6. Go-live 29/10/2018