BUILDING  CONSTRUCTION  1  
Project  2:  Construction  Activities  and  Process  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Ibrahim  Adhnan  
0314694  
 
 
 
WEEK  1  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

 
 
 
 

 
Construction  Activity1:  Site  Setting  and  Site  Clearance  
Duration:  5  days  
Materials:  Steel  Fencing  
Equipment:    Excavator,  Bump  Truck,  Dozer,  Chain  Saw,  Survey  Equipment  
Skilled  Worker:  5  General  Workers,  2  Truck/Dozer  Operators  
Technical  Information:    
• Prior  to  the  commencement  of  the  site  clearing  Contractor  shall  establish  the  site  
boundary  
• Contractor  shall  erect  sufficient  safety  sign  to  notify  public  on  the  construction  
activities  shall  any  need  arise.  
• Contractor  shall  also  submit  their  proposed  dumping  site  for  approval  prior  to  
site  clearing  to  the  superintending  officer  
 
 
   
   
 
 
 
 
 

2   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
 
WEEK  2  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
   
  Construction  Activity  2:  Excavation  and  Earth  Works  
  Duration:  5  days  
  Materials:  Natural  Soil  
  Equipment:  Excavator,  Pay  loader,  Six  Wheel  Truck,  Bob  Cat,  Shovel,  Meter  Tape  
  Skilled  Worker:  5  General  Workers,  Truck  Driver,  Excavator  Operator  
  Technical  Information:    
  • The  area  to  be  excavated  shall  be  properly  mark  and  clear  before  starting  the  works  
  • The  depth  of  excavation  shall  be  periodically  checked  by  a  surveyor  to  avoid  over  
  excavation  
   
   
 
 
 
 
 
 
 
 

3   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
 
WEEK  3  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Construction  Activity:    Pile  boring  and  reinforcement  installation  (Grid  a-­‐c)                                                                                                                  
Duration:    6  days  
Materials:  Steel  Bore,  Reinforcement  bar,  bar  bender                                                                                                                                                                                                            
Equipment:  Rebar  Bending  machine,  Boring  Machine  
Skilled  Worker:  5  General  Workers,  Boring  Machine  Operator,  Bar  Bending  Machine  
Technical  Information:  
• Survey  and  record  the  existing  ground  level  at  each  pile  location.    
• Refer  to  the  reference  points  in  drawings  
   
 
 
 
   
 
 
 
 
 
 

4   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
 
WEEK  4  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

 
Construction  Activity  1:    Pile  boring  and  reinforcement  installation  (Grid  e-­‐j)                                                                                                    
Duration:    6  days  
Materials:  Steel  Bore,  Reinforcement  bar,  bar  bender                                                                                                                                                                                                    
Equipment:  Rebar  Bending  machine,  Boring  Machine  
Skilled  Worker:  5  General  Workers,  Boring  Machine  Operator,  Bar  Bending  Machine  
Technical  Information:  
• Survey  and  record  the  existing  ground  level  at  each  pile  location.    
• Refer  to  the  reference  points  in  drawings  
• The  reinforcement  cage  will  be  fabricated  in  lay-­‐down  sections  
• type  and  size  of  the  steel  cage  will  be  according  to  drawings  
   
   
   
   
   
 
 

5   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
 
WEEK  5  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
   
 
 
 
 
 
 
 
Construction  Activity  :    Pile  Filling    
Duration:    6  days  
Materials:  Concrete  
Equipment:  Concrete  mixer,  Concrete  dispenser,  Concrete  vibrator                                                                                                                                                    
Skilled  Worker:  5  General  Workers  
Technical  Information:  
• The  self-­‐compacting  mixed  concrete  will  be  discharged  through  a  tremie  pipe,  which  
is  lowered  centrally  to  the  bottom  of  the  bored  hole  prior  to  filling  it  with  concrete.  
• All  completed  piles  shall  be  temporarily  barricaded  and  to  be  backfilled  to  ground  
level  with  a  suitable  material  the  next  day.  
   
 
 
 
 
 
 
 

6   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
 
WEEK  6  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Construction  Activity  1:  Pile  Cap  construction  (Grid  a-­‐g)  
Duration:    5  days  
Materials:  Concrete,  Reinforcement,  Timber  formwork  
Equipment:  Bar  Bending  Machine,  Saw,  Vibrating  Machine,  Concrete  Mixer  
Skilled  Worker:  3  General  Workers,  3  Bar  benders,  2  carpenters  
Technical  Information:  
• Formwork  is  erected  according  to  the  design  
• Fix  pile  cap  reinforcement  in  the  framework  
• Apply  sufficient  vibration    
• Pile  caps  distributes  the  load  from  the  above  structure  evenly  through  to  the  piles  
below.  
 
 
 
 
 
 
 

7   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
 
WEEK  7  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Construction  Activity  1:  Pile  Cap  construction  (grid  h)  
Duration:    5  days  
Materials:  Concrete,  Reinforcement,  Timber  formwork  
Equipment:  Bar  Bending  Machine,  Saw,  Vibrating  Machine,  Concrete  Mixer  
Skilled  Worker:  3  General  Workers,  3  Bar  benders,  2  carpenters  
Technical  Information:  
• Formwork  is  erected  according  to  the  design  
• Fix  pile  cap  reinforcement  in  the  framework  
• Apply  sufficient  vibration    
• Pile  caps  distributes  the  load  from  the  above  structure  evenly  through  to  the  piles  
below.  
 
   
 Construction  Activity  2:  Stump  on  Pile  Cap  
Duration:    5  days  
Materials:  Concrete,  Reinforcement,  Timber  formwork  
Equipment:  Bar  Bending  Machine,  Saw,  Vibrating  Machine  
Skilled  Worker:  3  General  Workers,  3  Bar  benders,  2  carpenters  
Technical  Information:  
• To  realign  the  level  of  the  substructure  to  ensure  the  ground  floor  and    
corresponding  floors  are  level  
 
 

 
   

8   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
 
WEEK  8  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

 
Construction  Activity  1:  Ground  Beam  Construction  (Grid  a-­‐c)  
Duration:    5  days  
Materials:  Concrete,  reinforcements,  timber  formworks  
Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                          
Skilled  Worker:  3  General  Workers,  3  Bar  benders,  2  carpenters  
Technical  Information:  
 
 
 
 
Construction  Activity  2:  Stump  on  Pile  Cap  (Grid  d-­‐i)  
Duration:    5  days  
Materials:  Concrete,  Reinforcement,  Timber  formwork  
Equipment:  Bar  Bending  Machine,  Saw,  Vibrating  Machine  
Skilled  Worker:  3  General  Workers,  3  Bar  benders,  2  carpenters  
Technical  Information:  
• To  realign  the  level  of  the  substructure  to  ensure  the  ground  floor  and    
corresponding  floors  are  level  
 
 

 
 

9   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
 
WEEK  9  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Construction  Activity:  Ground  Beam  Construction  (Grid  c-­‐h)  
Duration:    5  days  
Materials:  Concrete,  reinforcements,  timber  formworks  
Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                
Skilled  Worker:  3  General  Workers,  3  Bar  benders,  2  carpenters  
Technical  Information:  Ground  beams  resist  applied  loads  with  a  rebar  spanning  
above  stumps  and  connect  piles  caps  together  into  a  web  network,  concrete  is  then  cast-­‐
in-­‐situ  
 
 
 
 
 
 
 
 

10   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
 
WEEK  10  
 
 
 
 
 
   
 
 
 
 
 
 
 
 
 
 
 
 
 
   
 
 
 
 
   

 
Construction  Activity:  Ground  Floor  Slab  Construction  (grid  a-­‐e)  
Duration:    5  days  
Materials:  Concrete,  reinforcement  bars,  timber  formworks,  Damp  Proof  Membrane  
(DPM),  Rigid  Floor  Insulation                                                                                                                                                                                              
Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                              
Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  
Technical  Information:  :  Structural  engineers  typically  call  for  slabs  to  be  casted  
between  4  and  20  inches  (100  and  500  millimeters)  thick,  thinner  slabs  are  also  used  for  
exterior  paving.  Slabs  are  supported  on  the  foundation  or  directly  on  the  subsoil,  it  will  
be  the  eventual  the  ground  floor  of  a  building.  The  slab  is  made  uniformly  thick,  
reinforced  in  one  or  more  directions  and  casted  intergrally  with  the  parallel  ground  
beams.  
 
 
 
 
11   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  
 
WEEK  11  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Construction  Activity:  Ground  Floor  Slab  Construction  (grid  e-­‐k)    
Duration:    5  day  
Materials:  Concrete,  reinforcement  bars,  timber  formworks,  Damp  Proof  Membrane  
(DPM),  Rigid  Floor  Insulation                                                                                                                                                                                              
Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                        
Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  
Technical  Information:  Structural  engineers  typically  call  for  slabs  to  be  casted  
between  4  and  20  inches  (100  and  500  millimeters)  thick,  thinner  slabs  are  also  used  for  
exterior  paving.  Slabs  are  supported  on  the  foundation  or  directly  on  the  subsoil,  it  will  
be  the  eventual  the  ground  floor  of  a  building.  The  slab  is  made  uniformly  thick,  
reinforced  in  one  or  more  directions  and  casted  intergrally  with  the  parallel  ground  
beams.  
   
   
   
   
 

12   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
WEEK  12  
 
   
 
 
 
 
 
   

 
Construction  Activity:  Ground  Floor  Columns  (grid  a-­‐c)  
Duration:    5  days  
Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          
Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                
Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  
Technical  Information:  Structural  columns  are  built  to  bear  the  load  from  super  
structure  above  and    transfer  it  downwards  into  foundation.  The  timber  formwork  is  
built  around  the  starter  bars  protruding  from  the  ground  floor  slab.  A  cage  is  bent  and  
placed  inside  before  concrete  is  vibrated  into  the  mould.  The  12”  (305cm)  column  can  
support  up  to  2000  square  ft  of  floor  area.  
 
 
 

13   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
WEEK  13  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

 
Construction  Activity:  Ground  Floor  Columns  (grid  e-­‐k)  
Duration:    5  days  
Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                    
Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                        
Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  
Technical  Information:  Structural  columns  are  built  to  bear  the  load  from  super  
structure  above  and    transfer  it  downwards  into  foundation.  The  timber  formwork  is  
built  around  the  starter  bars  protruding  from  the  ground  floor  slab.  A  cage  is  bent  and  
placed  inside  before  concrete  is  vibrated  into  the  mould.  The  12”  (305cm)  column  can  
support  up  to  2000  square  ft  of  floor  area.  
 
 
   
   
 
 
 
 
 
 

14   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
WEEK  14  
 
 
 
 
 
 
 
 
   

 
Construction  Activity:  First  Floor  Beam  
Duration:    5  days  
Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                        
Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                          
Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  
Technical  Information:  Super  structure  columns  are  connect  together  via  beams,  they  
resist  applied  loads     with  a  rebar  from  the  columns.      
 
 
 

15   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
WEEK  15  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

 
Construction  Activity:  First  Floor  Beam  
Duration:    5  days  
Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                      
Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                        
Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  
Technical  Information:  :  Super  structure  columns  are  connect  together  via  beams,  they  
resist  applied  loads     with  a  rebar  from  the  columns.      
 
 
     
 
 

16   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
WEEK  16  
 
 
 
 
 
 
 
 
 
 
 
 
   
 
   

 
Construction  Activity:  First  Floor  Slab  (Grid  a-­‐g)  
Duration:    5  days  
Materials:  Concrete,  reinforcement,  timber  formwork,  DPM                                                                                                                                                                          
Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                    
Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  
Technical  Information:  The  slab  is  cast  intergally  with  the  beams  which  provide  
support  in  two  direction  
 
 
 

17   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
WEEK  17  
 
 
 
 
   

Construction  Activity  1:  First  Floor  Slab  (Grid  g-­‐k)  


Duration:    5  days  
Materials:  Concrete,  reinforcement,  timber  formwork,  DPM                                                                                                                                                            
Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                      
Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  
Technical  Information:  The  slab  is  cast  intergally  with  the  beams  which  provide  
support  in  two  direction  
 
 
 
 
Construction  
  Activity  2:  Ground  Floor  Wall  (Grid  a-­‐e)  
Duration:    5  days  
Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                  
Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                      
Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  
Technical  Information:  Walls  seperate  exterior  and  interior  as  well  as  rooms.  Bricks  
are  laid  with  a  50/50  overlap  running  bond.  
 
 
 
18   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  
 
WEEK  18  
 
 
 
 
   

 
Construction  Activity  1:  Ground  Floor  Wall  (Grid  c-­‐j)  
Duration:    5  days  
Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          
Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                        
Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  
Technical  Information:  Walls  seperate  exterior  and  interior  as  well  as  rooms.  Bricks  
are  laid  with  a  50/50  overlap  running  bond.  
 
 
Construction  
  Activity  2:  Ground  Floor  Stairs  
Duration:    5  days  
Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          
Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                        
Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  
Technical  Information:  :  Stairs  connect  individual  floors  together  by  means  of  a  series  
of  incremental  steps  that  allow  a  human  to  gradually  climb.  The  stairs  is  built  from  a  
starter  box,  which  is  a  series  of  starter  bars  protruding  from  the  ground  floor  slab.  Then  
timber  form  work  is  make  at  the  desired  pitch.  The  tread(depth)  and  riser(height)  is  
carefully  made  to  a  uniform  specifications.  The  half  turn  stairs  turns  180  degrees  
through      two  right  angles  at  an  intervening  landing.  This  space  floor  space  on  the  
revelant  floor  plans.    
 
 
 
 
19   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  
 
WEEK  19  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

 
Construction  Activity:  First    Floor  Columns  (grid  a-­‐c)  
Duration:    5  days  
Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          
Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                    
Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  
Technical  Information:  Structural  columns  are  built  to  bear  the  load  from  super  
structure  above  and      transfer  it  downwards  into  foundation  
 
 
 

 
 
 
 
 
 
 
 
 
   

20   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
WEEK  20  
 
   

 
Construction  Activity:  First    Floor  Columns  (grid  e-­‐j)  
Duration:    5  days  
Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          
Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                    
Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  
Technical  Information:  Structural  columns  are  built  to  bear  the  load  from  super  
structure  above  and      transfer  it  downwards  into  foundation  
 
 
 
 
 

21   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
WEEK  21  
 
 
   

 
Construction  Activity:  Second  Floor  Beam  (Grid  a-­‐e)  
Duration:    5  days  
Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          
Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                  
Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  
Technical  Information:  Super  structure  columns  are  connect  together  via  beams,  they  
resist  applied  loads     with  a  rebar  from  the  columns.      
 
 
 
 
 

22   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
WEEK  22  
   

 
Construction  Activity:  Second  Floor  Beam  (Grid  c-­‐h)  
Duration:    5  days  
Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          
Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                  
Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  
Technical  Information:  Super  structure  columns  are  connect  together  via  beams,  they  
resist  applied  loads     with  a  rebar  from  the  columns.      
 
 
 
 
 

23   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
WEEK  23  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

 
Construction  Activity:  Second  Floor  Slab  (Grid  a-­‐g)  
Duration:    5  days  
Materials:  Concrete,  reinforcement,  timber  formwork  ,  DPM                                                                                                                                                                
Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                            
Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  
Technical  Information:  The  slab  is  cast  intergally  with  the  beams  which  provide  
support  in  two  direction  
 
 
   
   
   
 
 
 
 
 
 
 

24   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
WEEK  24  
 
 
 
   

 
Construction  Activity:  Second  Floor  Slab  (Grid  g-­‐j)  
Duration:    5  days  
Materials:  Concrete,  reinforcement,  timber  formwork,  DPM                                                                                                                                                          
Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                    
Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  
Technical  Information:  The  slab  is  cast  intergally  with  the  beams  which  provide  
support  in  two  direction  
 
 
 
Construction   Activity:  First  Floor  Wall  (Grid  a-­‐c)  
 
Duration:    5  days  
 
Materials:   Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                      
Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                        
Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  
Technical  Information:  Walls  seperate  exterior  and  interior  as  well  as  rooms.  Bricks  
are  laid  with  a  50/50  overlap  running  bond.  
 
 
 
 
 25   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  
 
WEEK  25  
 
   

 
Construction  Activity  1:  First  Floor  Stairs  
Duration:    5  days  
Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          
Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                  
Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  
Technical  Information:  
 
 
 

Construction  Activity  2:  First  Floor  Wall  (Grid  d-­‐j)  


Duration:    5  days  
Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          
Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                
Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  
Technical  Information:  Walls  seperate  exterior  and  interior  as  well  as  rooms.  Bricks  
are  laid  with  a  50/50  overlap  running  bond.  
 
 
 
 
 

26   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
WEEK  26  
 
 
   

 
Construction  Activity:  Second    Floor  Columns  (grid  a-­‐c)  
Duration:    5  days  
Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                        
Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                            
Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  
Technical  Information:  Structural  columns  are  built  to  bear  the  load  from  super  
structure  above  and      transfer  it  downwards  into  foundation  
 
 
 
 
 

27   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
WEEK  27  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Construction  Activity:  Second    Floor  Columns  (grid  e-­‐j)  
Duration:    5  days  
Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                      
Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                        
Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  
Technical  Information:  Structural  columns  are  built  to  bear  the  load  from  super  
structure  above  and      transfer  it  downwards  into  foundation  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

28   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
WEEK  28    
 
 
 
   

 
 
Construction  Activity:  Roof  Beam  (Grid  a-­‐c)  
Duration:    5  days  
Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          
Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                  
Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  
Technical  Information:  Super  structure  columns  are  connect  together  via  beams,  they  
resist  applied  loads     with  a  rebar  from  the  columns.      
 
 
 
 
 

29   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
WEEK  29  
 
   

 
Construction  Activity:  Third    Floor  Columns  (grid  c-­‐j))  
Duration:    5  days  
Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          
Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                  
Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  
Technical  Information:  Super  structure  columns  are  connect  together  via  beams,  they  
resist  applied  loads     with  a  rebar  from  the  columns.      
 
 
 
 
 

30   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
WEEK  30  
 
   

 
Construction  Activity:  Roof  Truss  (Grid  a-­‐c)  
Duration:    5  days  
Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          
Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                
Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  
Technical  Information:  Trusses  are  built  as  a  support  frame  work  for  the  pitched  roof  
 
 
 

31   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
WEEK  31  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Construction  Activity:  Roof  Truss  (Grid  a-­‐c)  
Duration:    5  days  
Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          
Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                
Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  
Technical  Information:  Trusses  are  built  as  a  support  frame  work  for  the  pitched  roof  
 
 
 
 

32   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
WEEK  32  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

 
Construction  Activity:  Roof  Construction  (Phase  1)  
Duration:    5  days  
Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                              
Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                  
Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  
Technical  Information:  Roofs  are  the  protective  cover  of  a  building  against  rain,  snow  
and  wind  
 
 
 
 
 
 
 
 
 
 
 

33   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
 
 
WEEK  33  
 
   
 
 
   

 
Construction  Activity:  Roof  Construction  (Phase  2)  
Duration:    5  days  
Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          
Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                        
Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  
Technical  Information:  Roofs  are  the  protective  cover  of  a  building  against  rain,  snow  
and  wind  
 
 
 
 
 

34   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
WEEK  34  
 

 
Construction  Activity:  Second  Floor  Walls  
Duration:    5  days  
Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                    
Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                        
Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  
Technical  Information:  :  Walls  seperate  exterior  and  interior  as  well  as  rooms.  Bricks  
are  laid  with  a  50/50  overlap  running  bond  
 
 
 

35   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
WEEK  35  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
   

 
Construction  Activity  1:  Curtain  Walls  Installation    
Duration:    5  days  
Materials:  Glass,  Steel,  Screws  
Equipment:  Wrench,  Level,  Screw  Driver  
Skilled  Worker:  2  General  Workers,  1  Special  Worker  
Technical  Information:  walls  are  to  be  connected  to  the  ground  floor  and  beam  on  the  
upper  floor  
 
 
 
 
Construction  Activity  2:  Railing    Installation    
Duration:    3  days  
Materials:  Aluminium  handrail  (staircase),  Aluminium  guardrail  (balcony)  
Equipment:  Wrench,  Level,  Screw  Driver  
Skilled  Worker:  2  General  Workers,  1  Special  Worker  
Technical  Information:  :  Railing  provide  a  sturdy  barrier  when  walking  around  
unenclosed  area.  The  handrail  is  installed  by  bolting  multiple  segments  of  the  rail  
system  to  the  tread.  Similarly,  guardrails  are  also  bolted  to  the  ground  but  typically  at  
the  edge  of  a     balcony.    
 
 
 

36   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
WEEK  36  
 
   
     

 
Construction  Activity  1:  Ground  Floor  door  framing  and  installation    
Duration:    2  days  
Materials:  Hollow  single  rabbet  metal  frame        
Equipment:  Wrench,  Level,  Screw  Driver,  measuring  tape,  marker                                                                                                                                              
Skilled  Worker:  2  General  Workers,  1  Special  Worker  
Technical  Information:  :  Doors  are  openings  between  exterior  and  interior,  and  
between  rooms.  They  are  carefully  positioned  between  columns  where  the  wall  will  
eventually  be  made.  Doors  are  correctly  oriented  as  to  whether  they  open  in  or  out  and  
stood  up  right  with  wood  temporarily  nailed  to  columns  and  beams.  
 
 
   
  Construction  Activity  2:  Ground  Floor  window  framing  and  installation    
Duration:    3  days  
Materials:  Aluminium  casement  frame,  glass  window,  screws                                                                                                                                                              
Equipment:  Wrench,  Level,  Screw  Driver,  measuring  tape,  marker                                                                                                                                            
Skilled  Worker:  2  General  Workers,  1  Special  Worker  
Technical  Information:  :  :  Windows  provide  ventilation  for  a  building,  a  casement  
window  provides  100%  ventilation.  A  window  frame  is  first  installed,  followed  by  the  
two  smaller  windows  and  their  pivot  brackets,  the  unit  is  topped  off  with  trimming  for  
aesthetics.      
 
 
 
 

37   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
WEEK  37  
 
     

 
Construction  Activity  2:  First  Floor  window  framing  and  installation    
Duration:    3  days  
Materials:  Aluminium  casement  frame,  glass  window,  screws                                                                                                                                                        
Equipment:  Wrench,  Level,  Screw  Driver,  measuring  tape,  marker                                                                                                                                      
Skilled  Worker:  2  General  Workers,  1  Special  Worker  
Technical  Information:  :  :  Windows  provide  ventilation  for  a  building,  a  casement  
window  provides  100%  ventilation.  A  window  frame  is  first  installed,  followed  by  the  
two  smaller  windows  and  their  pivot  brackets,  the  unit  is  topped  off  with  trimming  for  
aesthetics.      
 
 
 
Construction  
  Activity  1:  First  Floor  door  framing  and  installation    
Duration:    2  days  
Materials:  Hollow  single  rabbet  metal  frame        
Equipment:  Wrench,  Level,  Screw  Driver,  measuring  tape,  marker                                                                                                                                      
Skilled  Worker:  2  General  Workers,  1  Special  Worker  
Technical  Information:  :  Doors  are  openings  between  exterior  and  interior,  and  
between  rooms.  They  are  carefully  positioned  between  columns  where  the  wall  will  
eventually  be  made.  Doors  are  correctly  oriented  as  to  whether  they  open  in  or  out  and  
stood  up  right  with  wood  temporarily  nailed  to  columns  and  beams.  
 
 
 
 

38   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
   
WEEK  38  
 
     

 
Construction  Activity  1:  second    Floor  door  framing  and  installation    
Duration:    2  days  
Materials:  Hollow  single  rabbet  metal  frame        
Equipment:  Wrench,  Level,  Screw  Driver,  measuring  tape,  marker                                                                                                                                                      
Skilled  Worker:  2  General  Workers,  1  Special  Worker  
Technical  Information:  :  Doors  are  openings  between  exterior  and  interior,  and  
between  rooms.  They  are  carefully  positioned  between  columns  where  the  wall  will  
eventually  be  made.  Doors  are  correctly  oriented  as  to  whether  they  open  in  or  out  and  
stood  up  right  with  wood  temporarily  nailed  to  columns  and  beams.  
 
 
 
Construction  Activity  2:  second    Floor  window  framing  and  installation    
 
Duration:    3  days  
 
Materials:  Aluminium  casement  frame,  glass  window,  screws                                                                                                                                                                
Equipment:  Wrench,  Level,  Screw  Driver,  measuring  tape,  marker                                                                                                                                              
Skilled  Worker:  2  General  Workers,  1  Special  Worker  
Technical  Information:  :  :  Windows  provide  ventilation  for  a  building,  a  casement  
window  provides  100%  ventilation.  A  window  frame  is  first  installed,  followed  by  the  
two  smaller  windows  and  their  pivot  brackets,  the  unit  is  topped  off  with  trimming  for  
aesthetics.      
 
 
 
 
39   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  
 
   
WEEK  39  
 
 
Construction  Activity:  Electrical  Wiring    
Duration:    7  days  
Materials:  insulated  cooper  wires,  electrical  tape,  connector                                                                                                                                                                              
Equipment:  Test  pen,  voltage  meter                                                                                                                                                                                                                                                                          
Skilled  Worker:  2  electricians  
Technical  Information:  Electrical  cables  are  pulled  through  PVC  pipe  ambedded  in  the  
concrete  walls  or  along  the  wall  surface.  
 
   
   
WEEK  40  
 
 

Construction  Activity:  Plumbing    


Duration:    7  days  
Materials:  assorted  dimensions  of  PVC  pipe,  connectors,  PVC  glue                                                                                                                                                        
Equipment:  Saw,  measuring  tape                                                                                                                                                                                                                                                                                    
Skilled  Worker:  Plumber    
Technical  Information:  Plumbing  is  essential  for  bringing  in  clean  water  into  a  building  
and  taking  waste  products  away.  PVC  pipes  are  pieced  together,  in  order  to  connect  
various  systems  together.  
 
 
 
WEEK  41  
 
 
   

Construction  Activity:  Sanitary  Fittings  


Duration:    5  days  
Materials:  Ceramics  
Equipment:  Saw,  Measuring  tape,  drill                                                                                                                                                                                                                                                                
Skilled  Worker:  Special  Worker,  2  General  Workers  
Technical  Information:  Sanitary  fittings  such  as  sick,  water  closet  and  shower  are  
usually  bought  as  modular  units  and  are  easily  installed.  Just  connect  the  plumbing  to  
the  inlet  and     outlet,  and  ensure  the  fastening  is  secure.  
 
 
 

40   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
WEEK  42  
 
 
Construction  Activity  :  Tiling    (Ground  Floor)  
Duration:    5  days  
Materials:  Mortar,  Grout,  homogenenous  ceramic  tiles                                                                                                                                                                                                
Equipment:  Putty  knife,  spacers,  level                                                                                                                                                                                                                                                              
Skilled  Worker:  2  Tilers  
Technical  Information:  Tiles  are  a  durable,  easy  to  clean  modular  finish  that  requires  
careful  installation  in  order  to  last  a  long  time.  A  tiling  pattern  is  first  determined  and  
the  tiler  spread  mortar  on  the  floor  surface.  The  tiles  are  uniformly  spaced  and  align  
with  the  aid  of  spacers.  The  gaps  are  made  to  allow  for  expansion  and  are  filled  with  
grout.    
.  
   
   
WEEK  
  43  
 
Construction  Activity      :  Tiling    (Second    Floor)  
Duration:    5  days  
Materials:  Mortar,  Grout,  homogenenous  ceramic  tiles                                                                                                                                                                                              
Equipment:  Putty  knife,  spacers,  level                                                                                                                                                                                                                                                              
Skilled  Worker:  2  Tilers  
Technical  Information:  Tiles  are  a  durable,  easy  to  clean  modular  finish  that  requires  
careful  installation  in  order  to  last  a  long  time.  A  tiling  pattern  is  first  determined  and  
the  tiler  spread  mortar  on  the  floor  surface.  The  tiles  are  uniformly  spaced  and  align  
with  the  aid  of  spacers.  The  gaps  are  made  to  allow  for  expansion  and  are  filled  with  
grout.    
.  
   
   
   
WEEK  44  
 
   
Construction  Activity      :  Tiling    (Second    Floor)  
Duration:    5  days  
Materials:  Mortar,  Grout,  homogenenous  ceramic  tiles                                                                                                                                                                                                
Equipment:  Putty  knife,  spacers,  level                                                                                                                                                                                                                                                              
Skilled  Worker:  2  Tilers  
Technical  Information:  Tiles  are  a  durable,  easy  to  clean  modular  finish  that  requires  
careful  installation  in  order  to  last  a  long  time.  A  tiling  pattern  is  first  determined  and  
the  tiler  spread  mortar  on  the  floor  surface.  The  tiles  are  uniformly  spaced  and  align  
with  the  aid  of  spacers.  The  gaps  are  made  to  allow  for  expansion  and  are  filled  with  
grout.    
.  
 
 
 

41   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
WEEK  45  
 
 
Construction  Activity    :  Plastering  (Ground  Floor)  
Duration:    5  days  
Materials:  Plaster  Board    
Equipment:  Ramset  concrete  nailer,  Makita  concrete  driller,  Laser  Level  machine,    
Plumbs,  Basic  hand  tools,  Makita  steel  bench  cutters,  Ceiling  gun,  Ladder,  Steel  square  
ruler,  Drilling  Machine  
Skilled  Worker:  3  General  Workers  
Technical  Information:  All  leveling  set  out  coordinates  shall  be  based  on  the  setting  
out  levels  provided  on  design.  
 
   
WEEK  46  
 
 
 
Construction  Activity    :  Plastering  (first  Floor)  
Duration:    5  days  
Materials:  Plaster  Board    
Equipment:  Ramset  concrete  nailer,  Makita  concrete  driller,  Laser  Level  machine,    
Plumbs,  Basic  hand  tools,  Makita  steel  bench  cutters,  Ceiling  gun,  Ladder,  Steel  square  
ruler,  Drilling  Machine  
Skilled  Worker:  3  General  Workers  
Technical  Information:  All  leveling  set  out  coordinates  shall  be  based  on  the  setting  
out  levels  provided  on  design.  
 
   
WEEK  47  
 
 
 
Construction  Activity    :  Plastering  (first  Floor)  
Duration:    5  days  
Materials:  Plaster  Board    
Equipment:  Ramset  concrete  nailer,  Makita  concrete  driller,  Laser  Level  machine,    
Plumbs,  Basic  hand  tools,  Makita  steel  bench  cutters,  Ceiling  gun,  Ladder,  Steel  square  
ruler,  Drilling  Machine  
Skilled  Worker:  3  General  Workers  
Technical  Information:  All  leveling  set  out  coordinates  shall  be  based  on  the  setting  
out  levels  provided  on  design.  
 
 

42   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
WEEK  48  
 
 

Construction  Activity      :  Painting  (Ground  Floor  and  Part  of  First  Floor)  
Duration:    5  days  
Materials  roller  brush.  Brush  extention  pole,  Masking  tape                                                                                                                                                                          
Equipment:  large  bucket,  wheelbarrow,  trowel,  garden  hose    
Skilled  Worker:  3  General  Workers  
Technical  Information:  Paint  provides  an  added  layer  of  protection  to  the  applied  
surface.  There  3  components  to  paint;  primer  (improves  the  adhension  of  subsequent  
coats),  base  (pigmentation  give  colour)  and  sealer  (reduces  absorption  of  moisture)  
 
 
WEEK  49  
 
 

Construction  Activity      :  Painting  (First  Floor  and  second    Floor)  


Duration:    5  days  
Materials  roller  brush.  Brush  extention  pole,  Masking  tape                                                                                                                                                                          
Equipment:  large  bucket,  wheelbarrow,  trowel,  garden  hose    
Skilled  Worker:  3  General  Workers  
Technical  Information:  Paint  provides  an  added  layer  of  protection  to  the  applied  
surface.  There  3  components  to  paint;  primer  (improves  the  adhension  of  subsequent  
coats),  base  (pigmentation  give  colour)  and  sealer  (reduces  absorption  of  moisture)  
 
 
 
 
WEEK  50  
 

Construction  Activity      :  Hardware  Installation  


Duration:    5  days  
Materials:  Stove  ventilation  hood,  kitchen  cabinets,  etc    
Equipment:  Measuring  tape,  level,  screwdriver                                                                                                                                                                                                                                
Skilled  Worker:  3  General  Workers  
Technical  Information:  :  After  wall  and  floor  finishs  are  completed,  fixed  furniture  and  
appliances  can  be  installed.  

43   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694  


 
WEEK  51  
 
 

Construction  Activity      :  Exterior  Finishes  


Duration:    5  days  
Materials:  lime  ,sand  ,water  
Equipment:  large  bucket,  wheelbarrow,  trowel,  garden  hose    
Skilled  Worker:  3  General  Workers  
Technical  Information:  :  Apply  the  render  to  the  wall  as  forcefully  as  possible  to  ensure  
that  it  keys  into  the  wall  well.  Once  the  first  coat  of  render  is  applied  but  not  yet  set,  
scratch  the  surface  throughout  the  wall  to  provide  a  key  for  the  next  layer  to  adhere  to.  
Best  done  on  cool  and  cloudy  day.  
 
 
 
 
WEEK  52  
 
 

Construction  Activity      :  Cleaning  


Duration:    5  days  
Materials:    
Equipment:  Mop,  cloth,  vacumn                                                                                                                                                                                                                                                                                    
Skilled  Worker:  3  General  Workers  
Technical  Information:  To  remove    all  the  dirt  before    Handing  over.  
 