Activity Name Performance Original Start Finish 2018
% Complete Duration Nov Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
SACASUN PRELIMINARY WORK SCHEDULE 0% 248 22-Jan-18 26-Sep-18
GENERAL REQUIREMENTS 0% 248 22-Jan-18 26-Sep-18 PRELIMINARIES 0% 248 22-Jan-18 26-Sep-18 Contract Award/ Notice to Proceed 0% 0 22-Jan-18* Contract Award/ Notice to Proceed Bonds and Insurances 0% 15 05-Feb-18 19-Feb-18 Bonds and Insurances Construction Permits and Licenses 0% 30 05-Feb-18 06-Mar-18 Construction Permits and Licenses Material Procurement 0% 57 05-Feb-18 02-Apr-18 Material Procurement Mobilization 0% 70 19-Feb-18 29-Apr-18 Mobilization Temporary Facilities and Utilities 0% 35 19-Feb-18 25-Mar-18 Temporary Facilities and Utilities Clean-Up /Demobilization 0% 60 27-Jul-18 25-Sep-18 Clean-Up /De Turn-Over 0% 0 26-Sep-18 Turn-Over CONSTRUCTION MILESTONE 0% 187 26-Feb-18 31-Aug-18 START MILESTONE 0% 121 26-Feb-18 27-Jun-18 Piling Works 0% 0 26-Feb-18 Piling Works Road Works 0% 0 26-Feb-18* Road Works Building Works 0% 0 25-Apr-18* Building Works Outstanding Works 0% 0 30-Apr-18* Outstanding Works Relocation of Existing Cables and Equipment 0% 0 27-Jun-18* Relocation of Existing Cables and Equipment FINISH MILESTONE 0% 122 01-May-18 31-Aug-18 Piling Works 0% 0 01-May-18 Piling Works Outstanding Works 0% 0 22-Aug-18 Outstanding Works Road Works 0% 0 23-Aug-18 Road Works Building Works 0% 0 29-Aug-18 Building Works Relocation of Existing Cables and Equipment 0% 0 31-Aug-18 Relocation of Existing CONSTRUCTION DRAWINGS 0% 20 22-Jan-18 10-Feb-18 Design review stage 0% 15 22-Jan-18 05-Feb-18 Design review stage Issued for construction 0% 15 27-Jan-18 10-Feb-18 Issued for construction CONSTRUCTION PHASE 0% 186 26-Feb-18 30-Aug-18 PILING WORKS 0% 65 26-Feb-18 01-May-18 Mobilization of Equipment & Materials 0% 21 26-Feb-18 18-Mar-18 Equipment Mobilization 0% 10 26-Feb-18 07-Mar-18 Equipment Mobilization Site location inspection /Site Access Works 0% 10 26-Feb-18 07-Mar-18 Site location inspection /Site Access Works Temporary Facilities and Utilities 0% 15 26-Feb-18 12-Mar-18 Temporary Facilities and Utilities Material and deliverables 0% 20 27-Feb-18 18-Mar-18 Material and deliverables Site Development prior for Bored Piling Works 0% 26 05-Mar-18 30-Mar-18 Demolition and disposal of existing pavement 0% 22 05-Mar-18 26-Mar-18 Demolition and disposal of existing pavement Soil Stripping 0% 25 06-Mar-18 30-Mar-18 Soil Stripping Bored Piling Works 0% 51 12-Mar-18 01-May-18 Initial Drilling up to 5m 0% 30 12-Mar-18 10-Apr-18 Initial Drilling up to 5m Installation of temporary casing 0% 35 12-Mar-18 15-Apr-18 Installation of temporary casing Regular Drilling 0% 40 13-Mar-18 21-Apr-18 Regular Drilling Cleaning / Thinning/ Sounding 0% 41 13-Mar-18 22-Apr-18 Cleaning / Thinning/ Sounding
Page 1 of 4 Prepared By: KJA Morales
Remaining Work SACASUN 58.98MW SOLAR POWER PLANT PROJECT Date Revision Checked Approved Critical Remaining Work 22-Jan-18 00 Building Works JD Taypa AG Agor Milestone (Bgry. Punao, San Carlos, Negros Occidental )
BUILDING WORKS , ROAD WORKS & OUTSTANDING WORKS
PRELIMINARY CONSTRUCTION SCHEDULE SACASUN PRELIMINARY WORK SCHEDULE DATE: 26-Jan-18
Activity Name Performance Original Start Finish 2018
% Complete Duration Nov Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Rebar installation 0% 37 18-Mar-18 23-Apr-18 Rebar installation Concreting 0% 28 28-Mar-18 24-Apr-18 Concreting Removal of temporary casing 0% 30 02-Apr-18 01-May-18 Removal of temporary casing BUILDING WORKS 0% 128 25-Apr-18 30-Aug-18 BUILDING STRUCTURE 0% 72 25-Apr-18 05-Jul-18 FOOTING /1ST LIFT COLUMNS CONCRETE 0% 38 25-Apr-18 01-Jun-18 Compaction of foundation around pile 0% 25 25-Apr-18 19-May-18 Compaction of foundation around pile Fabrication & installation of rebar (footing) 0% 20 01-May-18 20-May-18 Fabrication & installation of rebar (footing) Lean concrete of footing foundation 0% 20 01-May-18 20-May-18 Lean concrete of footing foundation Fabrication & installation of forms for (footing) 0% 19 03-May-18 21-May-18 Fabrication & installation of forms for (footing) Concrete pouring (footing) 0% 15 08-May-18 22-May-18 Concrete pouring (footing) Curing & dismantling of forms 0% 16 09-May-18 24-May-18 Curing & dismantling of forms Fabrication & installation of rebar (columns) 0% 17 11-May-18 27-May-18 Fabrication & installation of rebar (columns) Fabrication & installation of forms for (columns) 0% 17 13-May-18 29-May-18 Fabrication & installation of forms for (columns) Concrete pouring (columns) 0% 16 15-May-18 30-May-18 Concrete pouring (columns) Curing & dismantling of forms 0% 17 16-May-18 01-Jun-18 Curing & dismantling of forms GROUND SLAB & TIE GIRDER CONCRETE 0% 30 10-May-18 08-Jun-18 Scaffold installation 0% 25 10-May-18 03-Jun-18 Scaffold installation Fabrication & installation of forms 0% 22 14-May-18 04-Jun-18 Fabrication & installation of forms Fabrication & installation of rebar 0% 20 17-May-18 05-Jun-18 Fabrication & installation of rebar Concrete pouring 0% 16 22-May-18 06-Jun-18 Concrete pouring Curing & dismantling of forms 0% 17 23-May-18 08-Jun-18 Curing & dismantling of forms 2ND LIFT COLUMNS CONCRETE 0% 29 23-May-18 20-Jun-18 Fabrication & installation of rebar 0% 20 23-May-18 11-Jun-18 Fabrication & installation of rebar Fabrication & installation of forms 0% 20 26-May-18 14-Jun-18 Fabrication & installation of forms Concrete pouring 0% 18 31-May-18 17-Jun-18 Concrete pouring Curing & dismantling of forms 0% 20 01-Jun-18 20-Jun-18 Curing & dismantling of forms ROOF DECK SLAB & BEAM CONCRETE 0% 35 01-Jun-18 05-Jul-18 Scaffold installation 0% 25 01-Jun-18 25-Jun-18 Scaffold installation Fabrication & installation of forms 0% 21 06-Jun-18 26-Jun-18 Fabrication & installation of forms Fabrication & installation of rebar 0% 20 08-Jun-18 27-Jun-18 Fabrication & installation of rebar Concrete pouring 0% 20 09-Jun-18 28-Jun-18 Concrete pouring Curing & dismantling of forms 0% 26 10-Jun-18 05-Jul-18 Curing & dismantling of forms ARCHITECTURAL WORKS 0% 81 10-Jun-18 29-Aug-18 Masonry Works (CHB & plastering) 0% 30 10-Jun-18 09-Jul-18 Masonry Works (CHB & plastering) Metal Works 0% 32 12-Jun-18 13-Jul-18 Metal Works Wood Works (Plywood Cabinet) 0% 30 16-Jun-18 15-Jul-18 Wood Works (Plywood Cabinet) Thermal and Moisture Protection (Water Proofing of roofdeck & Toilet) 0% 35 19-Jun-18 23-Jul-18 Thermal and Moisture Protection ( Door's & window's installation 0% 30 21-Jun-18 20-Jul-18 Door's & window's installation Ceiling Works & Finishes 0% 31 23-Jun-18 23-Jul-18 Ceiling Works & Finishes Painting Works & Finishes on Walls 0% 30 25-Jun-18 24-Jul-18 Painting Works & Finishes on Walls Toilet, Urinal & Drywall Partitions 0% 29 28-Jun-18 26-Jul-18 Toilet, Urinal & Drywall Partitions Counter Top Finishes 0% 30 01-Jul-18 30-Jul-18 Counter Top Finishes
Page 2 of 4 Prepared By: KJA Morales
Remaining Work SACASUN 58.98MW SOLAR POWER PLANT PROJECT Date Revision Checked Approved Critical Remaining Work 22-Jan-18 00 Building Works JD Taypa AG Agor Milestone (Bgry. Punao, San Carlos, Negros Occidental )
BUILDING WORKS , ROAD WORKS & OUTSTANDING WORKS
PRELIMINARY CONSTRUCTION SCHEDULE SACASUN PRELIMINARY WORK SCHEDULE DATE: 26-Jan-18
Activity Name Performance Original Start Finish 2018
% Complete Duration Nov Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Flooring & Finishes 0% 57 04-Jul-18 29-Aug-18 Flooring & Finishes ELECTRICAL WORKS 0% 100 23-May-18 30-Aug-18 Installation of Facility Lightning Protection and Grounding System 0% 80 23-May-18 10-Aug-18 Installation of Facility Lightni General Lighting System 0% 76 27-May-18 10-Aug-18 General Lighting System General Power System 0% 78 01-Jun-18 17-Aug-18 General Power System Fire Alarm and Detection System 0% 77 06-Jun-18 21-Aug-18 Fire Alarm and Detection Telephone and Data System 0% 74 11-Jun-18 23-Aug-18 Telephone and Data System CCTV System 0% 73 16-Jun-18 27-Aug-18 CCTV System Assistance for testing and commissioning 0% 73 19-Jun-18 30-Aug-18 Assistance for testing MECHANICAL WORKS 0% 88 04-Jun-18 30-Aug-18 Plumbing System 0% 65 04-Jun-18 07-Aug-18 Plumbing System HVAC System 0% 73 07-Jun-18 18-Aug-18 HVAC System Fire Supression System (FM200) 0% 68 17-Jun-18 23-Aug-18 Fire Supression System Water Line PPR Pipes and Fittings 0% 68 22-Jun-18 28-Aug-18 Water Line PPR Pipes Sanitary,Sewer and Vent Line, PVC Pipes and Fittings 0% 65 27-Jun-18 30-Aug-18 Sanitary,Sewer and V ROAD WORKS (Service and Access Roads) 0% 179 26-Feb-18 23-Aug-18 INNER ROADS 0% 179 26-Feb-18 23-Aug-18 Road 1 Z2 0% 155 26-Feb-18 30-Jul-18 Road 1 Z2 Road 1 Z1 0% 152 04-Mar-18 02-Aug-18 Road 1 Z1 Road 2 0% 150 09-Mar-18 05-Aug-18 Road 2 Road 3 0% 148 14-Mar-18 08-Aug-18 Road 3 Road 4 0% 150 17-Mar-18 13-Aug-18 Road 4 Road 5 0% 140 01-Apr-18 18-Aug-18 Road 5 Road 6 0% 122 21-Apr-18 20-Aug-18 Road 6 Road 7 0% 120 26-Apr-18 23-Aug-18 Road 7 PERIMETER ROADS 0% 146 31-Mar-18 23-Aug-18 Perimeter Road 1 Northwest 0% 130 31-Mar-18 07-Aug-18 Perimeter Road 1 Northwest Perimeter Road 1 Northeast 0% 132 05-Apr-18 14-Aug-18 Perimeter Road 1 Northeast Perimeter Road 1 Southwest 0% 130 10-Apr-18 17-Aug-18 Perimeter Road 1 Southwest Perimeter Road 1 Southeast 0% 128 15-Apr-18 20-Aug-18 Perimeter Road 1 Southeast Perimeter Road 2 0% 129 15-Apr-18 21-Aug-18 Perimeter Road 2 Perimeter Road 3 0% 126 20-Apr-18 23-Aug-18 Perimeter Road 3 OUTSTANDING WORKS 0% 115 30-Apr-18 22-Aug-18 Reinfocred Concrete Box Culvert and Earth Drainage 0% 95 30-Apr-18 02-Aug-18 Reinfocred Concrete Box Culve Grouted Ripprap at Main Station 0% 92 05-May-18 04-Aug-18 Grouted Ripprap at Main Station Fence Repairing 0% 90 10-May-18 07-Aug-18 Fence Repairing Concrete Pavement going to Main Station 0% 88 15-May-18 10-Aug-18 Concrete Pavement going to Punchlisting Works 0% 95 20-May-18 22-Aug-18 Punchlisting Works Pond Levelling 0% 82 25-May-18 14-Aug-18 Pond Levelling Ground Leveling at PV Area 0% 85 30-May-18 22-Aug-18 Ground Leveling at PV Area MAIN EQUIPMENT RELOCATION 0% 65 27-Jun-18 30-Aug-18 Disconnection of existing cable termination and re-laying of disconnected cables. 0% 58 27-Jun-18 23-Aug-18 Disconnection of existing Dismantling and relocation of panels, switchgear and transformer. 0% 47 10-Jul-18 25-Aug-18 Dismantling and relocat
Page 3 of 4 Prepared By: KJA Morales
Remaining Work SACASUN 58.98MW SOLAR POWER PLANT PROJECT Date Revision Checked Approved Critical Remaining Work 22-Jan-18 00 Building Works JD Taypa AG Agor Milestone (Bgry. Punao, San Carlos, Negros Occidental )
BUILDING WORKS , ROAD WORKS & OUTSTANDING WORKS
PRELIMINARY CONSTRUCTION SCHEDULE SACASUN PRELIMINARY WORK SCHEDULE DATE: 26-Jan-18
Activity Name Performance Original Start Finish 2018
% Complete Duration Nov Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Dismantling and relocation of existing cable tray and supports. 0% 45 14-Jul-18 27-Aug-18 Dismantling and reloca Cable pulling of the new Main Station Building. 0% 42 18-Jul-18 28-Aug-18 Cable pulling of the ne Termination of cables. 0% 39 22-Jul-18 29-Aug-18 Termination of cables. Testing and commissioning 0% 36 26-Jul-18 30-Aug-18 Testing and commissi
Page 4 of 4 Prepared By: KJA Morales
Remaining Work SACASUN 58.98MW SOLAR POWER PLANT PROJECT Date Revision Checked Approved Critical Remaining Work 22-Jan-18 00 Building Works JD Taypa AG Agor Milestone (Bgry. Punao, San Carlos, Negros Occidental )