PRESUPUESTO DE OBRA (APROXIMADO)

#REF! ANTIG. PANAM. SUR -MIRAMAR MZ. 37 LOTES 1 y 2


#REF! S/. 373,127.08
#REF!

Item Descripción Und. Metrado Precio S/. Parcial S/.

1 ESTRUCTURAS
1.01 TRABAJOS PRELIMINARES
01.01.01 LIMPIEZA DEL TERRENO MANUAL m2 773.00 1.04 803.92
01.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 773.00 1.38 1,066.74
1.02 MOVIMIENTO DE TIERRAS
01.02.01 EXCAVACION PARA CIMIENTOS - ZAPATAS EN TERRENO NORMAL m3 49.56 300.00 14,868.00
01.02.02 EXCAVACION MANUAL EN ZAPATAS total = 17 m3 22.10 100.00 2,210.00
1.03 CONCRETO SIMPLE
01.03.01 CIMIENTO CORRIDO C:H= 1:10 + 30% P.G. m3 5.46 216.00 1,179.36
01.03.02 CONCRETO DE SOBRECIMIENTO C:H=1:8 + 25% P.M. m3 0.90 248.39 223.55
01.03.03 CONCRETO F'C=140 KG/CM2 EN VEREDA m3 10.44 143.00 1,492.92
1.04 CONCRETO ARMADO
01.04.01 ZAPATAS
01.04.01.01 CONCRETO FC' = 210 KG/CM2 PARA ZAPATAS m3 10.20 216.00 2,203.20
01.04.01.02 ACERO FY= 4200 kg/cm2 GRADO 60 (ACERO DE 1/2 EN 17 ZAPATAS ) kg 150.45 5.53 831.99
01.04.02 VIGAS DE CIMENTACION
01.04.02.01 CONCRETO FC' = 210 KG/CM2 PARA VIGA DE CIMENTACION m3 13.92 456.23 6,350.72
01.04.02.02 ENCOFRADO Y DESENCOFRADO NORMAL DE VIGA DE CIMENTACION m2 46.40 35.50 1,647.20
01.04.02.03 ACERO FY= 4200 kg/cm2 GRADO 60 (ACERO DE 5/8 Y DE 3/8 ) kg 863.04 5.53 4,772.61
01.04.03 COLUMNAS
01.04.03.01 CONCRETO f'c=210 kg/cm2 DE COLUMNAS ( 0.6 x 0.3 ) EN 17 COLUMNAS m3 12.24 446.19 5,461.37
01.04.03.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS m2 115.60 50.56 5,844.74
01.04.03.03 ACERO FY= 4200 kg/cm2 GRADO 60 (4 varillas de 5/8 y 2 varillas de 1/2) kg 1,106.16 5.53 6,117.04
01.04.04 PLACAS
01.04.04.01 CONCRETO f'c=210 kg/cm2 DE COLUMNAS m3 14.00 446.19 6,246.66
01.04.04.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS m2 141.00 50.56 7,128.96
01.04.04.03 ACERO FY= 4200 kg/cm2 GRADO 60 kg 3,318.47 5.53 18,351.13
01.04.05 VIGAS
01.04.05.01 CONCRETO f'c=210 kg/cm2 DE VIGAS (30x40) m3 35.76 453.61 16,221.09
01.04.05.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 327.80 96.42 31,606.48
01.04.05.03 ACERO FY= 4200 kg/cm2 GRADO 60 (6 varillas de 5/8 y 2 varillas de 1/2) kg 5,380.69 5.53 29,755.20
01.04.06 LOSA ALIGERADA
01.04.06.01 CONCRETO F'C = 175 KG/CM2 PARA LOSA ALIGERADA m3 56.00 329.32 18,441.92
01.04.06.02 ENCOFRADO Y DESENCOFRADO NORMAL DE LOSA ALIGERADA m2 700.00 96.42 67,494.00
01.04.06.03 ACERO FY= 4200 kg/cm2 GRADO 60 kg 160.09 5.53 885.30
2 ARQUITECTURA
2.01 ALBAÑILERIA
02.01.01 MURO DE LADRILLO KK DE ARCILLA DE SOGA m2 123.00 45.00 5,535.00
2.02 REVOQUES ENLUCIDOS Y DERRAMES
02.02.01 TARRAJEO EN COLUMNAS m2 5.10 66.00 336.60
02.02.02 TARRAJEO MUROS EXTERIORES E INTERIORES m2 246.00 32.00 7,872.00
02.02.03 TARRAJEO EN SUPERFICIE DE VIGAS DE E= 1.5CM m2 327.80 68.00 22,290.40
2.03 BRUÑAS
02.03.01 BRUÑA E= 1 CM. DE LA VEREDA EXTERIOR m 240.00 8.03 1,927.20
2.04 PISOS Y PAVIMENTOS
02.04.01 CONCRETO FC'=140 KG/CM2, VEREDAS m2 1.20 218.23 261.88
02.04.02 ENCOFRADO Y DESENCOFRADO NORMAL DE SARDINEL Y VEREDA EXTERIOR m2 12.00 50.00 600.00
2.05 CARPINTERIA METALICA
02.05.01 PORTON METALICO und 1.00 2,963.54 2,963.54
02.05.02 PUERTA METALICA und 1.00 1,200.00 1,200.00
COSTO DIRECTO 294,190.71
GASTOS GENERALES 16.8317% 16.8317% 49,517.30
UTILIDAD (10.00%) 10.0000% 29,419.07
TOTAL 373,127.08