Вы находитесь на странице: 1из 57

Barely two days later or on July 14, 1993, petitioner filed with the Regional Trial

Court of Pasig a complaint for collection of the balance due under the construction
agreement. Named defendants therein were SPI and members of its board of
directors namely, Alfredo C. Ramos, Rufo B. Colayco, Antonio B. Olbes, Gerardo O.
[G.R. No. 120105. March 27, 1998]
Lanuza, Jr., Maximo G. Licauco III and Benjamin C. Ramos.
On August 3, 1993, SPI and its co-defendants filed a motion to suspend
proceedings instead of filing an answer. The motion was anchored on defendants
BF CORPORATION, petitioner, vs. COURT OF APPEALS, SHANGRI-LA allegation that the formal trade contract for the construction of the project provided for
PROPERTIES, COLAYCO, ALFREDO C. RAMOS, INC., RUFO B. a clause requiring prior resort to arbitration before judicial intervention could be
MAXIMO G. LICAUCO III and BENJAMIN C. RAMOS, respondents. invoked in any dispute arising from the contract. The following day, SPI submitted a
copy of the conditions of the contract containing the arbitration clause that it failed to
append to its motion to suspend proceedings.
DECISION
Petitioner opposed said motion claiming that there was no formal contract
ROMERO, J.: between the parties although they entered into an agreement defining their rights and
obligations in undertaking the project. It emphasized that the agreement did not
The basic issue in this petition for review on certiorari is whether or not the provide for arbitration and therefore the court could not be deprived of jurisdiction
contract for the construction of the EDSA Plaza between petitioner BF Corporation conferred by law by the mere allegation of the existence of an arbitration clause in the
and respondent Shangri-la Properties, Inc. embodies an arbitration clause in case of agreement between the parties.
disagreement between the parties in the implementation of contractual provisions.
In reply to said opposition, SPI insisted that there was such an arbitration clause
Petitioner and respondent Shangri-la Properties, Inc. (SPI) entered into an in the existing contract between petitioner and SPI. It alleged that suspension of
agreement whereby the latter engaged the former to construct the main structure of proceedings would not necessarily deprive the court of its jurisdiction over the case
the EDSA Plaza Project, a shopping mall complex in the City of Mandaluyong. and that arbitration would expedite rather than delay the settlement of the parties
respective claims against each other.
The construction work was in progress when SPI decided to expand the project
by engaging the services of petitioner again. Thus, the parties entered into an In a rejoinder to SPIs reply, petitioner reiterated that there was no arbitration
agreement for the main contract works after which construction work began. clause in the contract between the parties. It averred that granting that such a clause
indeed formed part of the contract, suspension of the proceedings was no longer
However, petitioner incurred delay in the construction work that SPI considered proper. It added that defendants should be declared in default for failure to file their
as serious and substantial.[1] On the other hand, according to petitioner, the answer within the reglementary period.
construction works progressed in faithful compliance with the First Agreement until a
fire broke out on November 30, 1990 damaging Phase I of the Project. [2] Hence, SPI In its sur-rejoinder, SPI pointed out the significance of petitioners admission of
proposed the re-negotiation of the agreement between them. the due execution of the Articles of Agreement. Thus, on page D/6 thereof, the
signatures of Rufo B. Colayco, SPI president, and Bayani Fernando, president of
Consequently, on May 30, 1991, petitioner and SPI entered into a written petitioner appear, while page D/7 shows that the agreement is a public document duly
agreement denominated as Agreement for the Execution of Builders Work for the notarized on November 15, 1991 by Notary Public Nilberto R. Briones as document
EDSA Plaza Project. Said agreement would cover the construction work on said No. 345, page 70, book No. LXX, Series of 1991 of his notarial register. [5]
project as of May 1, 1991 until its eventual completion.
Thereafter, upon a finding that an arbitration clause indeed exists, the lower
According to SPI, petitioner failed to complete the construction works and court[6] denied the motion to suspend proceedings, thus:
abandoned the project.[3] This resulted in disagreements between the parties as
regards their respective liabilities under the contract. On July 12, 1993, upon SPIs It appears from the said document that in the letter-agreement dated May
initiative, the parties respective representatives met in conference but they failed to 30, 1991 (Annex C, Complaint), plaintiff BF and defendant Shangri-La
come to an agreement.[4] Properties, Inc. agreed upon the terms and conditions of the Builders Work
for the EDSA Plaza Project (Phases I, II and Carpark), subject to the
execution by the parties of a formal trade contract. Defendants have Notice of the demand for arbitration of a dispute shall be filed in writing with
submitted a copy of the alleged trade contract, which is entitled `Contract the other party to the contract and a copy filed with the Project
Documents For Builders Work Trade Contractor dated 01 May 1991, page Manager. The demand for arbitration shall be made within a reasonable
2 of which is entitled `Contents of Contract Documents with a list of the time after the dispute has arisen and attempts to settle amicably have
documents therein contained, and Section A thereof consists of the failed; in no case, however, shall the demand he made be later than the
abovementioned Letter-Agreement dated May 30, 1991. Section C of the time of final payment except as otherwise expressly stipulated in the
said Contract Documents is entitled `Articles of Agreement and Conditions contract.
of Contract which, per its Index, consists of Part A (Articles of Agreement)
and B (Conditions of Contract). The said Articles of Agreement appears to Against the above backdrop, the lower court found that per the May 30, 1991
have been duly signed by President Rufo B. Colayco of Shangri-La agreement, the project was to be completed by October 31, 1991. Thereafter, the
Properties, Inc. and President Bayani F. Fernando of BF and their contractor would pay P80,000 for each day of delay counted from November 1, 1991
witnesses, and was thereafter acknowledged before Notary Public Nilberto with liquified (sic) damages up to a maximum of 5% of the total contract price.
R. Briones of Makati, Metro Manila on November 15, 1991. The said The lower court also found that after the project was completed in accordance
Articles of Agreement also provides that the `Contract Documents' therein with the agreement that contained a provision on progress payment billing, SPI took
listed `shall be deemed an integral part of this Agreement, and one of the possession and started operations thereof by opening the same to the public in
said documents is the `Conditions of Contract which contains the November, 1991.SPI, having failed to pay for the works, petitioner billed SPI in the
Arbitration Clause relied upon by the defendants in their Motion to Suspend total amount of P110,883,101.52, contained in a demand letter sent by it to SPI on
Proceedings. February 17, 1993. Instead of paying the amount demanded, SPI set up its own claim
This Court notes, however, that the `Conditions of Contract referred to, of P220,000,000.00 and scheduled a conference on that claim for July 12, 1993. The
contains the following provisions: conference took place but it proved futile.

`3. Contract Document. Upon the above facts, the lower court concluded:

Three copies of the Contract Documents referred to in Considering the fact that under the supposed Arbitration Clause invoked by
the Articles of Agreement shall be signed by the defendants, it is required that `Notice of the demand for arbitration of a
parties to the contract and distributed to the Owner and dispute shall be filed in writing with the other party x x x x in no case x x x x
the Contractor for their safe keeping. (underscoring later than the time of final payment x x x x which apparently, had elapsed,
supplied) not only because defendants had taken possession of the finished works
and the plaintiffs billings for the payment thereof had remained pending
And it is significant to note further that the said `Conditions of Contract is since November, 1991 up to the filing of this case on July 14, 1993, but
not duly signed by the parties on any page thereof --- although it bears the also for the reason that defendants have failed to file any written notice of
initials of BFs representatives (Bayani F. Fernando and Reynaldo M. de la any demand for arbitration during the said long period of one year and eight
Cruz) without the initials thereon of any representative of Shangri-La months, this Court finds that it cannot stay the proceedings in this case as
Properties, Inc. required by Sec. 7 of Republic Act No. 876, because defendants are in
default in proceeding with such arbitration.
Considering the insistence of the plaintiff that the said Conditions of
Contract was not duly executed or signed by the parties, and the failure of The lower court denied SPIs motion for reconsideration for lack of merit and
the defendants to submit any signed copy of the said document, this Court directed it and the other defendants to file their responsive pleading or answer within
entertains serious doubt whether or not the arbitration clause found in the fifteen (15) days from notice.
said Conditions of Contract is binding upon the parties to the Articles of
Agreement. (Underscoring supplied.) Instead of filing an answer to the complaint, SPI filed a petition
for certiorari under Rule 65 of the Rules of Court before the Court of Appeals. Said
The lower court then ruled that, assuming that the arbitration clause was valid appellate court granted the petition, annulled and set aside the orders and stayed the
and binding, still, it was too late in the day for defendants to invoke arbitration. It proceedings in the lower court.In so ruling, the Court of Appeals held:
quoted the following provision of the arbitration clause:
The reasons given by the respondent Court in denying petitioners motion to remained pending since November, 1991 up to the filing of this case on July 14, 1993,
suspend proceedings are untenable. but also for the reason that defendants have failed to file any written notice of any
demand for arbitration during the said long period of one year and eight months, x x x.
1. The notarized copy of the articles of agreement attached as Annex A to petitioners
reply dated August 26, 1993, has been submitted by them to the respondent Court Respondent Court has overlooked the fact that under the arbitration clause
(Annex G, petition). It bears the signature of petitioner Rufo B. Colayco, president of
petitioner Shangri-La Properties, Inc., and of Bayani Fernando, president of Notice of the demand for arbitration dispute shall be filed in writing with the other party
respondent Corporation (Annex G-1, petition). At page D/4 of said articles of to the contract and a copy filed with the Project Manager. The demand for arbitration
agreement it is expressly provided that the conditions of contract are `deemed an shall be made within a reasonable time after the dispute has arisen and attempts to
integral part thereof (page 188, rollo). And it is at pages D/42 to D/44 of the conditions settle amicably had failed; in no case, however, shall the demand be made later than
of contract that the provisions for arbitration are found (Annexes G-3 to G-5, petition, the time of final payment except as otherwise expressly stipulated in the contract
pp. 227-229). Clause No. 35 on arbitration specifically provides: (underscoring supplied)

Provided always that in case any dispute or difference shall arise between the Owner quoted in its order (Annex A, petition). As the respondent Court there said, after the
or the Project Manager on his behalf and the Contractor, either during the progress or final demand to pay the amount of P110,883,101.52, instead of paying, petitioners set
after the completion or abandonment of the Works as to the construction of this up its own claim against respondent Corporation in the amount of P220,000,000.00
Contract or as to any matter or thing of whatsoever nature arising thereunder or in and set a conference thereon on July 12, 1993. Said conference proved futile. The
connection therewith (including any matter or being left by this Contract to the next day, July 14, 1993, respondent Corporation filed its complaint against petitioners.
discretion of the Project Manager or the withholding by the Project Manager of any On August 13, 1993, petitioners wrote to respondent Corporation requesting
certificate to which the Contractor may claim to be entitled or the measurement and arbitration. Under the circumstances, it cannot be said that petitioners resort to
valuation mentioned in clause 30 (5) (a) of these Conditions or the rights and liabilities arbitration was made beyond reasonable time. Neither can they be considered in
of the parties under clauses 25, 26, 32 or 33 of these Conditions), the Owner and the default of their obligation to respondent Corporation.
Contractor hereby agree to exert all efforts to settle their differences or dispute
amicably. Failing these efforts then such dispute or difference shall be referred to
Arbitration in accordance with the rules and procedures of the Philippine Arbitration Hence, this petition before this Court. Petitioner assigns the following errors:
Law. A.

The fact that said conditions of contract containing the arbitration clause bear only the THE COURT OF APPEALS ERRED IN ISSUING THE
initials of respondent Corporations representatives, Bayani Fernando and Reynaldo EXTRAORDINARY WRIT OF CERTIORARI ALTHOUGH THE
de la Cruz, without that of the representative of petitioner Shangri-La Properties, Inc. REMEDY OF APPEAL WAS AVAILABLE TO RESPONDENTS.
does not militate against its effectivity. Said petitioner having categorically admitted B.
that the document, Annex A to its reply dated August 26, 1993 (Annex G, petition), is
the agreement between the parties, the initial or signature of said petitioners THE COURT OF APPEALS ERRED IN FINDING GRAVE ABUSE OF
representative to signify conformity to arbitration is no longer necessary. The parties, DISCRETION IN THE FACTUAL FINDINGS OF THE TRIAL COURT
therefore, should be allowed to submit their dispute to arbitration in accordance with THAT:
their agreement.
(i) THE PARTIES DID NOT ENTER INTO AN
AGREEMENT TO ARBITRATE.
2. The respondent Court held that petitioners `are in default in proceeding with such
arbitration. It took note of `the fact that under the supposed Arbitration Clause invoked (ii) ASSUMING THAT THE PARTIES DID ENTER INTO
by defendants, it is required that Notice of the demand for arbitration of a dispute shall THE AGREEMENT TO ARBITRATE,
be filed in writing with the other party x x x in no case x x x later than the time of final RESPONDENTS ARE ALREADY IN DEFAULT
payment, which apparently, had elapsed, not only because defendants had taken IN INVOKING THE AGREEMENT TO
possession of the finished works and the plaintiffs billings for the payment thereof had ARBITRATE.
On the first assigned error, petitioner contends that the Order of the lower court However, the question of jurisdiction, which is a question of law depends on the
denying the motion to suspend proceedings is a resolution of an incident on the determination of the existence of the arbitration clause, which is a question of fact. In
merits. As such, upon the continuation of the proceedings, the lower court would the instant case, the lower court found that there exists an arbitration
appreciate the evidence adduced in their totality and thereafter render a decision on clause. However, it ruled that in contemplation of law, said arbitration clause does not
the merits that may or may not sustain the existence of an arbitration clause. A exist.
decision containing a finding that the contract has no arbitration clause can then be
elevated to a higher court in an ordinary appeal where an adequate remedy could be The issue, therefore, posed before the Court of Appeals in a petition for
obtained. Hence, to petitioner, the Court of Appeals should have dismissed the certiorari is whether the Arbitration Clause does not in fact exist. On its face, the
petition for certiorari because the remedy of appeal would still be available to private question is one of fact which is not proper in a petition for certiorari.
respondents at the proper time.[7] The Court of Appeals found that an Arbitration Clause does in fact exist. In
The above contention is without merit. resolving said question of fact, the Court of Appeals interpreted the construction of the
subject contract documents containing the Arbitration Clause in accordance with
The rule that the special civil action of certiorari may not be invoked as a Republic Act No. 876 (Arbitration Law) and existing jurisprudence which will be
substitute for the remedy of appeal is succinctly reiterated in Ongsitco v. Court of extensively discussed hereunder. In effect, the issue posed before the Court of
Appeals[8] as follows: Appeals was likewise a question of law. Being a question of law, the private
respondents rightfully invoked the special civil action of certiorari.
x x x. Countless times in the past, this Court has held that `where appeal is the proper It is that mode of appeal taken by private respondents before the Court of
remedy, certiorari will not lie. The writs of certiorari and prohibition are remedies to Appeals that is being questioned by the petitioners before this Court. But at the heart
correct lack or excess of jurisdiction or grave abuse of discretion equivalent to lack of of said issue is the question of whether there exists an Arbitration Clause because if
jurisdiction committed by a lower court. `Where the proper remedy is appeal, the an Arbitration Clause does not exist, then private respondents took the wrong mode
action for certiorari will not be entertained. x x x. Certiorari is not a remedy for errors of appeal before the Court of Appeals.
of judgment. Errors of judgment are correctible by appeal, errors of jurisdiction are
reviewable by certiorari. For this Court to be able to resolve the question of whether private respondents
took the proper mode of appeal, which, incidentally, is a question of law, then it has to
Rule 65 is very clear. The extraordinary remedies of certiorari, prohibition answer the core issue of whether there exists an Arbitration Clause which, admittedly,
and mandamus are available only when `there is no appeal or any plain, speedy and is a question of fact.
adequate remedy in the ordinary course of law x x x. That is why they are referred to Moreover, where a rigid application of the rule that certiorari cannot be a
as `extraordinary. x x x. substitute for appeal will result in a manifest failure or miscarriage of justice, the
provisions of the Rules of Court which are technical rules may be relaxed. [10] As we
The Court has likewise ruled that certiorari will not be issued to cure errors in shall show hereunder, had the Court of Appeals dismissed the petition for certiorari,
proceedings or correct erroneous conclusions of law or fact. As long as a court acts the issue of whether or not an arbitration clause exists in the contract would not have
within its jurisdiction, any alleged errors committed in the exercise of its jurisdiction been resolved in accordance with evidence extant in the record of the case.
will amount to nothing more than errors of judgment which are reviewable by timely Consequently, this would have resulted in a judicial rejection of a contractual
appeal and not by a special civil action of certiorari.[9]v. Court of Appeals, 327 Phil. 1, provision agreed by the parties to the contract.
41-42 (1996).9
In the same vein, this Court holds that the question of the existence of the
This is not exactly so in the instant case. While this Court does not deny the arbitration clause in the contract between petitioner and private respondents is a legal
eventual jurisdiction of the lower court over the controversy, the issue posed basically issue that must be determined in this petition for review on certiorari.
is whether the lower court prematurely assumed jurisdiction over it. If the lower court
indeed prematurely assumed jurisdiction over the case, then it becomes an error of Petitioner, while not denying that there exists an arbitration clause in the
jurisdiction which is a proper subject of a petition for certiorari before the Court of contract in question, asserts that in contemplation of law there could not have been
Appeals. And if the lower court does not have jurisdiction over the controversy, then one considering the following points. First, the trial court found that the conditions of
any decision or order it may render may be annulled and set aside by the appellate contract embodying the arbitration clause is not duly signed by the parties. Second,
court. private respondents misrepresented before the Court of Appeals that they produced
in the trial court a notarized duplicate original copy of the construction agreement The Court finds that, upon a scrutiny of the records of this case, these requisites
because what were submitted were mere photocopies thereof. The contract(s) were complied with in the contract in question. The Articles of Agreement, which
introduced in court by private respondents were therefore of dubious authenticity incorporates all the other contracts and agreements between the parties, was signed
because: (a) the Agreement for the Execution of Builders Work for the EDSA Plaza by representatives of both parties and duly notarized. The failure of the private
Project does not contain an arbitration clause, (b) private respondents surreptitiously respondents representative to initial the `Conditions of Contract would therefor not
attached as Annexes `G-3 to `G-5 to their petition before the Court of Appeals but affect compliance with the formal requirements for arbitration agreements because
these documents are not parts of the Agreement of the parties as there was no formal that particular portion of the covenants between the parties was included by reference
trade contract executed, (c) if the entire compilation of documents is indeed a formal in the Articles of Agreement.
trade contract, then it should have been duly notarized, (d) the certification from the
Records Management and Archives Office dated August 26, 1993 merely states that Petitioners contention that there was no arbitration clause because the contract
the notarial record of Nilberto Briones x x x is available in the files of (said) office incorporating said provision is part of a hodge-podge document, is therefore
as Notarial Registry Entry only, (e) the same certification attests that the document untenable. A contract need not be contained in a single writing. It may be collected
entered in the notarial registry pertains to the Articles of Agreement only without any from several different writings which do not conflict with each other and which, when
other accompanying documents, and therefore, it is not a formal trade contract, and connected, show the parties, subject matter, terms and consideration, as in contracts
(f) the compilation submitted by respondents are a mere hodge-podge of documents entered into by correspondence.[13] A contract may be encompassed in several
and do not constitute a single intelligible agreement. instruments even though every instrument is not signed by the parties, since it is
sufficient if the unsigned instruments are clearly identified or referred to and made
In other words, petitioner denies the existence of the arbitration clause primarily part of the signed instrument or instruments. Similarly, a written agreement of which
on the ground that the representatives of the contracting corporations did not sign the there are two copies, one signed by each of the parties, is binding on both to the
Conditions of Contract that contained the said clause. Its other contentions, same extent as though there had been only one copy of the agreement and both had
specifically that insinuating fraud as regards the alleged insertion of the arbitration signed it.[14]
clause, are questions of fact that should have been threshed out below.
The flaw in petitioners contentions therefore lies in its having segmented the
This Court may as well proceed to determine whether the arbitration clause various components of the whole contract between the parties into several parts. This
does exist in the parties contract. Republic Act No. 876 provides for the formal notwithstanding, petitioner ironically admits the execution of the Articles of
requisites of an arbitration agreement as follows: Agreement. Notably, too, the lower court found that the said Articles of Agreement
also provides that the `Contract Documents therein listed `shall be deemed an
Section 4. Form of arbitration agreement. A contract to arbitrate a controversy integral part of this Agreement, and one of the said documents is the `Conditions of
thereafter arising between the parties, as well as a submission to arbitrate an existing Contract which contains the Arbitration Clause.It is this Articles of Agreement that was
controversy, shall be in writing and subscribed by the party sought to be charged, or duly signed by Rufo B. Colayco, president of private respondent SPI, and Bayani F.
by his lawful agent. Fernando, president of petitioner corporation. The same agreement was duly
subscribed before notary public Nilberto R. Briones. In other words, the subscription
of the principal agreement effectively covered the other documents incorporated by
The making of a contract or submission for arbitration described in section two hereof, reference therein.
providing for arbitration of any controversy, shall be deemed a consent of the parties
of the province or city where any of the parties resides, to enforce such contract of This Court likewise does not find that the Court of Appeals erred in ruling that
submission. (Underscoring supplied.) private respondents were not in default in invoking the provisions of the arbitration
clause which states that (t)he demand for arbitration shall be made within a
The formal requirements of an agreement to arbitrate are therefore the following: reasonable time after the dispute has arisen and attempts to settle amicably had
(a) it must be in writing and (b) it must be subscribed by the parties or their failed. Under the factual milieu, private respondent SPI should have paid its liabilities
representatives. There is no denying that the parties entered into a written contract under the contract in accordance with its terms. However, misunderstandings
that was submitted in evidence before the lower court. To subscribe means to write appeared to have cropped up between the parties ostensibly brought about by either
underneath, as ones name; to sign at the end of a document.[11] That word may delay in the completion of the construction work or by force majeure or the fire that
sometimes be construed to mean to give consent to or to attest. [12] partially gutted the project. The almost two-year delay in paying its liabilities may not
therefore be wholly ascribed to private respondent SPI.
Besides, private respondent SPIs initiative in calling for a conference between
the parties was a step towards the agreed resort to arbitration. However, petitioner Facts
posthaste filed the complaint before the lower court. Thus, while private respondent
SPIs request for arbitration on August 13, 1993 might appear an afterthought as it In a complaint for Violation of the NIL and Damages, Visitacion and Asuncion
was made after it had filed the motion to suspend proceedings, it was because Flores seek therecovery of the amount of P900,913.60 which petitioner charged
petitioner also appeared to act hastily in order to resolve the controversy through the against their current account by virtue of the 16 checks drawn by them despite
courts. the apparent alterations therein with respect to the name of the payee, that is, the
name Filipinas Shell was erased and substituted with Ever Trading and DBL Trading
The arbitration clause provides for a reasonable time within which the parties by their supervisor Jeremias Cabrera, without their knowledge and consent.
may avail of the relief under that clause. Reasonableness is a relative term and the Petitioner claimed that the subject checks appeared to have been regularly issued
question of whether the time within which an act has to be done is reasonable and free from any irregularity which would excite or arouse any suspicion or warrant
depends on attendant circumstances.[15] This Court finds that under the their dishonor when the same were negotiated and honored by it. Petitioner filed a
circumstances obtaining in this case, a one-month period from the time the parties TPC against PCIB, Far East Bank and City Trust for reimbursement, contribution,
held a conference on July 12, 1993 until private respondent SPI notified petitioner that indemnity for being the collecting banks of the subject checks and by virtue of their
it was invoking the arbitration clause, is a reasonable time. Indeed, petitioner may not bank guarantee for all checks sent for clearing to the Philippine Clearing House
be faulted for resorting to the court to claim what was due it under the Corporation (PCHC), as provided for in Section 17, (PCHC), as provided for in
contract. However, we find its denial of the existence of the arbitration clause as an Section 17, PCHC Clearing House Rules and Regulations. Citytrust and PCIB
attempt to cover up its misstep in hurriedly filing the complaint before the lower court. claimed that the checks were complete and regular on their face.
In this connection, it bears stressing that the lower court has not lost its A Motion To Dismiss was filed by Security Bank on the grounds that petitioner
jurisdiction over the case. Section 7 of Republic Act No. 876 provides that failed to resort to arbitration as provided for in Section 36 of the Clearing House
proceedings therein have only been stayed. After the special proceeding of Rules and Regulations of the Philippine Clearing House Corporation. Petitioner
arbitration[16] has been pursued and completed, then the lower court may confirm the maintains that this Court has jurisdiction over the suit as the provisions of the
award[17] made by the arbitrator. Clearing House Rules and Regulations are applicable only if the suit or action is
between participating member banks, whereas the Floreses are private persons
It should be noted that in this jurisdiction, arbitration has been held valid and and the third-party complaint between participating member banks is only a
constitutional. Even before the approval on June 19, 1953 of Republic Act No. 876, consequence of the original action initiated by the plaintiffs. The trial court
this Court has countenanced the settlement of disputes through dismissed the TPC for lack of jurisdiction citing Section 36 of the Clearing
arbitration.[18] Republic Act No. 876 was adopted to supplement the New Civil Codes House Rules and Regulations of the PCHC providing for settlement of disputes
provisions on arbitration.[19] Its potentials as one of the alternative dispute resolution andncontroversies involving any check or item cleared through the body with
methods that are now rightfully vaunted as the wave of the future in international the PCHC.
relations, is recognized worldwide. To brush aside a contractual agreement calling for It ruled— citing the Arbitration Rules of Procedure — that the decision or award of the
arbitration in case of disagreement between the parties would therefore be a step PCHC through its arbitration committee/arbitrator is appealable only on questions
backward. of law to any of the Regional Trial Courts in the National Capital Region where the
head office of any of the parties is located. The CA affirmed
WHEREFORE, the questioned Decision of the Court of Appeals is hereby
AFFIRMED and the petition for certiorari DENIED. This Decision is immediately Issue
executory. Costs against petitioner. Whether or not the case should be dismissed for failure to arbitrate
SO ORDERED.
Narvasa, C.J., (Chairman), Kapunan, and Purisima, JJ., concur.
Held
Yes. The Clearing House Rules and Regulations on Arbitration of the Philippine
Clearing House Corporation are clearly applicable to petitioner and private
Associated Bank vs CA 233 SCRA 137 (1994)
respondents. Petitioner’s third party complaint in the trial court was one for
reimbursement, contribution and indemnity against PCIB, FarEast, Security Bank,
and CityTrust, in connection with petitioner’s having honored sixteen checks which participation their consent to these rules, but such participation is deemed
said banks supposedly (their) written and subscribed consent to the binding effect of arbitration
endorsed to the former for collection in 1989. Under the rules and regulations of the agreements under the PCHC rules. Moreover, a participant subject to the Clearing
PCHC, the mere act of participation of the parties concerned in its operations in House Rules and Regulations of the PCHC may go on appeal to any of the Regional
effect amounts to a manifestation of agreement by the parties to abide by its Trial Courts in the
rules and regulations. National Capital Region where the head office of any of the parties is located only
after a decision or award has been rendered by the arbitration committee or
As a consequence of such participation, a party cannot invoke the jurisdiction of arbitrator on questions of law.
the courts over disputes and controversies which fall under the PCHC Rules Clearly therefore, petitioner, by its voluntary participation and its consent to the
and Regulations without first going through the arbitration processes laid out arbitration rules cannot go directly to the RTC when it finds it convenient to do
by the so.
body. Since claims relating to the regularity of checks cleared by banking institutions The jurisdiction of the PCHC under the rules and regulations is clear, undeniable and
are among those claims which should first be submitted for resolution by the PCHC’s is particularly applicable to all the parties in the third party complaint under their
Arbitration Committee, petitioner, having voluntarily bound itself to abide by such rules obligation to first seek redress of their disputes and grievances with the PCHC before
and regulations, is estopped from seeking relief from the RTC on the coattails of a going to the trial
private claim and in the guise of a third party complaint without first having obtained a court. Finally, the contention that the third party complaint should not have been
decision adverse to its claim from the said body. It cannot bypass the arbitration dismissed for being a necessary and inseparable offshoot of the main case over
process on the basis of its which the court a quo had already exercised The applicable PCHC provisions on the
averment that its third party complaint is inextricably linked to the original complaint in question of jurisdiction
the RTC. provide:

Pursuant to PCHC’s function involving the clearing of checks and other clearing 1) Sec. 3 — AGREEMENT TO THESE RULES
items, the PCHC has adopted rules and regulations designed to provide member It is the general agreement and understanding, that any participant in the PCHC
banks with a procedure whereby disputes involving the clearance of checks MICR clearing operations, by the mere act of participation, thereby manifests its
and other negotiable instruments undergo a process of arbitration prior to agreement to these Rules and Regulations, and its subsequent amendments.
submission to the courts below. This procedure:
2) Sec. 36 — ARBITRATION
(1) ensures a uniformity of rulings relating to factual disputes involving checks and a) 36.1 Any dispute or controversy between two or more clearing participants
other negotiable instruments involving any check/item cleared thru PCHC shall be submitted to the Arbitration
(2) provides a mechanism for settling minor disputes among participating and Committee, upon written complaint of any involved participant by filing the same with
member banks which would otherwise go directly to the trial courts. While the PCHC the PCHC serving the same upon the other party or parties, who shall within fifteen
Rules and Regulations allow appeal to the Regional Trial Courts only on (15) days after receipt thereof, file with the Arbitration Committee its written answer to
questions of law, this does not preclude our lower courts from dealing with such written complaint and also within the same period serve the same upon the
questions of fact complaining participant. This period of fifteen (15) days may be extended by the
already decided by the PCHC arbitration when warranted and appropriate. Committee not more than once for another period of fifteen (15) days, but upon
agreement in writing of the complaining party, said extension may be for such period
In Banco de Oro Savings and Mortgage Banks vs. Equitable Banking Corporation this as the latter may agree to.
Court had the occasion to rule on the validity of these rules as well as the
jurisdiction of the PCHC as a forum for resolving disputes and controversies b) Section 36.6 is even more emphatic:
involving checks and other clearing items when it held that "the participation of two
banks. . . in the Clearing 36.6 The fact that a bank participates in the clearing operations of PCHC shall
Operations of the PCHC (was) a manifestation of its submission to its jurisdiction. be deemed its written and subscribed consent to the binding effect of this
arbitration agreement as if it had done so in accordance with Section 4 of the
Under the PCHC Rules and Regulations,7 not only do the parties manifest by Republic Act No. 876
mere otherwise known as the Arbitration Law. jurisdiction misses the fundamental point
about such pleading. A third party complaint is a mere procedural device which
under the Rules of Court is allowed only with the court’s permission. It is an LEONARDO-DE CASTRO, J.:
action "actually independent of, separate and distinct from the plaintiffs’
complaint" (s)uch that, were it not for the Rules of Court, it would be necessary to file Before the Court is a special civil action for certiorari assailing the
the action separately from the original complaint by the defendant against the third Decision[1] dated December 7, 2001 and the Resolution dated October 30, 2002 of
party. the Court of Appeals (CA) in CA-G.R. SP No. 56166 which set aside the Joint
Orders[2] dated August 26, 1999 and October 29, 1999 issued by the Regional Trial
Court (RTC) of Ormoc City, Branch 12 upholding petitioners legal personality to
demand arbitration from respondents and directing respondents to nominate two
ORMOC SUGARCANE PLANTERS G.R. No. 156660 arbitrators to represent them in the Board of Arbitrators.
ASSOCIATION, INC.
(OSPA),OCCIDENTAL LEYTE Petitioners are associations organized by and whose members are individual
FARMERS MULTI-PURPOSE sugar planters (Planters). The membership of each association follows: 264 Planters
COOPERATIVE, INC. (OLFAMCA), were members of OSPA; 533 Planters belong to OLFAMCA; 617 Planters joined
UNIFARM MULTI-PURPOSE Present: UNIFARM; 760 Planters enlisted with ONDIMCO; and the rest belong to BAP-MPC
COOPERATIVE, INC. (UNIFARM) and which did not join the lawsuit.
ORMOC NORTH DISTRICT IRRIGATION PUNO, C.J., Chairperson,
MULTI-PURPOSE COOPERATIVE, INC. CARPIO, Respondents Hideco Sugar Milling Co., Inc. (Hideco) and Ormoc Sugar
(ONDIMCO), CORONA, Milling Co, Inc. (OSCO) are sugar centrals engaged in grinding and milling sugarcane
Petitioners, LEONARDO-DE CASTRO, and delivered to them by numerous individual sugar planters, who may or may not be
BERSAMIN, JJ. members of an association such as petitioners.
-versus-
Petitioners assert that the relationship between respondents and the
THE COURT OF APPEALS (Special individual sugar planters is governed by milling contracts. To buttress this claim,
Former Sixth Division), HIDECO petitioners presented representative samples of the milling contracts. [3]
SUGAR MILLING CO., INC., and
ORMOC SUGAR MILLING CO., INC., Notably, Article VII of the milling contracts provides that 34% of the sugar
Respondents. Promulgated: and molasses produced from milling the Planters sugarcane shall belong to the
centrals (respondents) as compensation, 65% thereof shall go to the Planter and the
August 24, 2009 remaining 1% shall go the association to which the Planter concerned belongs, as aid
to the said association. The 1% aid shall be used by the association for any purpose
that it may deem fit for its members, laborers and their dependents. If the Planter was
not a member of any association, then the said 1% shall revert to the centrals. Article
XIV, paragraph B[4] states that the centrals may not, during the life of the milling
contract, sign or execute any contract or agreement that will provide better or more
benefits to a Planter, without the written consent of the existing and recognized
associations except to Planters whose plantations are situated in areas beyond thirty
(30) kilometers from the mill. Article XX provides that all differences and controversies
which may arise between the parties concerning the agreement shall be submitted for
discussion to a Board of Arbitration, consisting of five (5) memberstwo (2) of which
shall be appointed by the centrals, two (2) by the Planter and the fifth to be appointed
by the four appointed by the parties.
x----------------------------------------------------------------------------------------x
On June 4, 1999, petitioners, without impleading any of their individual
DECISION members, filed twin petitions with the RTC for Arbitration under R.A. 876, Recovery of
Equal Additional Benefits, Attorneys Fees and Damages, against HIDECO and through a Petition for Certiorari with Prayer for the Issuance of Temporary Restraining
OSCO, docketed as Civil Case Nos. 3696-O and 3697-O, respectively. Order and/or Writ of Preliminary Injunction.

Petitioners claimed that respondents violated the Milling Contract when they On December 7, 2001, the CA rendered its challenged Decision, setting
gave to independent planters who do not belong to any association the 1% share, aside the assailed Orders of the RTC. The CA held that petitioners neither had an
instead of reverting said share to the centrals. Petitioners contended that respondents existing contract with respondents nor were they privy to the milling contracts
unduly accorded the independent Planters more benefits and thus prayed that an between respondents and the individual Planters. In the main, the CA concluded that
order be issued directing the parties to commence with arbitration in accordance with petitioners had no legal personality to bring the action against respondents or to
the terms of the milling contracts. They also demanded that respondents be penalized demand for arbitration.
by increasing their member Planters 65% share provided in the milling contract by
1%, to 66%. Petitioners filed a motion for reconsideration, but it too was denied by the CA
in its Resolution[7] dated October 30, 2002. Thus, the instant petition.
Respondents filed a motion to dismiss on ground of lack of cause of action
because petitioners had no milling contract with respondents. According to At the outset, it must be noted that petitioners filed the instant petition for
respondents, only some eighty (80) Planters who were members of OSPA, one of the certiorari under Rule 65 of the Rules of Court, to challenge the judgment of the CA.
petitioners, executed milling contracts. Respondents and these 80 Planters were the Section 1 of Rule 65 states:
signatories of the milling contracts. Thus, it was the individual Planters, and not
petitioners, who had legal standing to invoke the arbitration clause in the milling Section 1. Petition for Certiorari. When any tribunal, board or officer
contracts. Petitioners, not being privy to the milling contracts, had no legal standing exercising judicial or quasi-judicial functions has acted without or in
whatsoever to demand or sue for arbitration. excess of its jurisdiction, or with grave abuse of discretion
amounting to lack or excess of its or his jurisdiction and there is no
On August 26, 1999, the RTC issued a Joint Order [5] denying the motion to appeal, or any plain, speedy and adequate remedy in the
dismiss, declaring the existence of a milling contract between the parties, and course of law, a person aggrieved thereby may file a verified
directing respondents to nominate two arbitrators to the Board of Arbitrators, to wit: petition in the proper court, alleging the facts with certainty and
praying that judgment be rendered annulling or modifying the
When these cases were called for hearing today, counsels for the proceedings of such tribunal, board or officer, and granting such
petitioners and respondents argued their respective stand. The incidental relief as law and justice require. xxx xxx xxx (emphasis
Court is convinced that there is an existing milling contract between ours)
the petitioners and respondents and these planters are represented The instant recourse is improper because the resolution of the CA was a final order
by the officers of the associations. The petitioners have the right to from which the remedy of appeal was available under Rule 45 in relation to Rule
sue in behalf of the planters. 56. The existence and availability of the right of appeal proscribes resort to certiorari
because one of the requirements for availment of the latter is precisely that there
This Court, acting on the petitions, directs the respondents to should be no appeal. It is elementary that for certiorari to prosper, it is not enough that
nominate two arbitrators to represent HIDECO/HISUMCO and the trial court committed grave abuse of discretion amounting to lack or excess of
OSCO in the Board of Arbitrators within fifteen (15) days from jurisdiction; the requirement that there is no appeal, nor any plain, speedy and
receipt of this Order. xxx adequate remedy in the ordinary course of law must likewise be satisfied. [8] The
proper mode of recourse for petitioners was to file a petition for review of the CAs
However, if the respondents fail to nominate their two arbitrators, decision under Rule 45.
upon proper motion by the petitioners, then the Court will be
compelled to use its discretion to appoint the two (2) arbitrators, as Petitioners principally argue that the CA committed a grave error in setting
embodied in the Milling Contract and R.A. 876. aside the challenged Joint Orders of the RTC which allegedly unduly curtailed the
xxx right of petitioners to represent their planters-members and enforce the milling
contracts with respondents. Petitioners assert the said which orders were issued in
Their subsequent motion for reconsideration having been denied by the RTC accordance with Article XX of the Milling Contract and the applicable provisions of
in its Joint Order[6] dated October 29, 1999, respondents elevated the case to the CA Republic Act (R.A.) No. 876.
contract must appear, including an agreement to arbitrate some specific thing, and an
Where the issue or question involved affects the wisdom or legal soundness agreement to abide by the award, either in express language or by implication.
of the decision not the jurisdiction of the court to render said decision the same is
beyond the province of a special civil action for certiorari. Erroneous findings and The requirements that an arbitration agreement must be written and
conclusions do not render the appellate court vulnerable to the corrective writ of subscribed by the parties thereto were enunciated by the Court in B.F. Corporation v.
certiorari. For where the court has jurisdiction over the case, even if its findings are CA.[12]
not correct, they would, at most constitute errors of law and not abuse of discretion
correctable by certiorari.[9] During the proceedings before the CA, it was established that there were
more than two thousand (2,000) Planters in the district at the time the case was
Moreover, even if this Court overlooks the procedural lapse committed by commenced at the RTC in 1999. The CA further found that of those 2,000 Planters,
petitioners and decides this matter on the merits, the present petition will still not only about eighty (80) Planters, who were all members of petitioner OSPA, in fact
prosper. individually executed milling contracts with respondents. No milling contracts signed
by members of the other petitioners were presented before the CA.
Stripped to the core, the pivotal issue here is whether or not
petitioners ― sugar planters associations ― are clothed with legal personality to file a By their own allegation, petitioners are associations duly existing and
suit against, or demand arbitration from, respondents in their own name without organized under Philippine law, i.e. they have juridical personalities separate and
impleading the individual Planters. distinct from that of their member Planters. It is likewise undisputed that the eighty
(80) milling contracts that were presented were signed only by the member Planter
On this point, we agree with the findings of the CA. concerned and one of the Centrals as parties. In other words, none of the petitioners
were parties or signatories to the milling contracts. This circumstance is fatal to
Section 2 of R.A. No. 876 (the Arbitration Law)[10] pertinently provides: petitioners' cause since they anchor their right to demand arbitration from the
respondent sugar centrals upon the arbitration clause found in the milling
Sec. 2. Persons and matters subject to arbitration. Two or contracts. There is no legal basis for petitioners' purported right to demand arbitration
more persons or parties may submit to the arbitration of one when they are not parties to the milling contracts, especially when the language of the
or more arbitrators any controversy existing between them at arbitration clause expressly grants the right to demand arbitration only to the parties
the time of the submission and which may be the subject of an to the contract.
action, or the parties to any contract may in such contract
agree to settle by arbitration a controversy thereafter arising Simply put, petitioners do not have any agreement to arbitrate with
between them. Such submission or contract shall be valid, respondents. Only eighty (80) Planters who were all members of OSPA were shown
enforceable and irrevocable, save upon such grounds as exist at to have such an agreement to arbitrate, included as a stipulation in their individual
law for the revocation of any contract. xxx (Emphasis ours) milling contracts. The other petitioners failed to prove that any of their members had
milling contracts with respondents, much less, that respondents had an agreement to
The foregoing provision speaks of two modes of arbitration: (a) an arbitrate with the petitioner associations themselves.
agreement to submit to arbitration some future dispute, usually stipulated upon in a
civil contract between the parties, and known as an agreement to submit to Even assuming that all the petitioners were able to present milling contracts
arbitration, and (b) an agreement submitting an existing matter of difference to in favor of their members, it is undeniable that under the arbitration clause in these
arbitrators, termed the submission agreement. Article XX of the milling contract is contracts it is the parties thereto who have the right to submit a controversy or dispute
an agreement to submit to arbitration because it was made in anticipation of a dispute to arbitration.
that might arise between the parties after the contracts execution.
Section 4 of R.A. 876 provides:
Except where a compulsory arbitration is provided by statute, the first step
toward the settlement of a difference by arbitration is the entry by the parties into a Section 4. Form of Arbitration Agreement A contract to arbitrate a
valid agreement to arbitrate. An agreement to arbitrate is a contract, the relation of the controversy thereafter arising between the parties, as well as a
parties is contractual, and the rights and liabilities of the parties are controlled by the submission to arbitrate an existing controversy, shall be in writing
law of contracts.[11] In an agreement for arbitration, the ordinary elements of a valid
and subscribed by the party sought to be charged, or by his lawful We held in Oco v. Limbaring[14] that:
agent. As applied to the present case, this provision has two requirements:
1) to institute an action, the plaintiff must be the real party in
The making of a contract or submission for arbitration interest; and 2) the action must be prosecuted in the name of the
described in section two hereof, providing for arbitration of any real party in interest. Necessarily, the purposes of this provision are
controversy, shall be deemed a consent of the parties to the 1) to prevent the prosecution of actions by persons without any
jurisdiction of the Court of First Instance of the province or city right, title or interest in the case; 2) to require that the actual party
where any of the parties resides, to enforce such contract of entitled to legal relief be the one to prosecute the action; 3) to avoid
submission. a multiplicity of suits; and 4) to discourage litigation and keep it
within certain bounds, pursuant to sound public policy.
The formal requirements of an agreement to arbitrate are therefore the Interest within the meaning of the Rules means
following: (a) it must be in writing and (b) it must be subscribed by the parties or material interest or an interest in issue to be affected by the
their representatives. To subscribe means to write underneath, as ones name; to sign decree or judgment of the case, as distinguished from mere
at the end of a document. That word may sometimes be construed to mean to give curiosity about the question involved. One having no material
consent to or to attest.[13] interest to protect cannot invoke the jurisdiction of the court as the
plaintiff in an action. When the plaintiff is not the real party in
Petitioners would argue that they could sue respondents, notwithstanding interest, the case is dismissible on the ground of lack of cause
the fact that they were not signatories in the milling contracts because they are the of action.
recognized representatives of the Planters. xxx xxx xxx
The parties to a contract are the real parties in interest
This claim has no leg to stand on since petitioners did not sign the milling in an action upon it, as consistently held by the Court. Only the
contracts at all, whether as a party or as a representative of their member contracting parties are bound by the stipulations in the
Planters. The individual Planter and the appropriate central were the only signatories contract; they are the ones who would benefit from and could
to the contracts and there is no provision in the milling contracts that the individual violate it. Thus, one who is not a party to a contract, and for whose
Planter is authorizing the association to represent him/her in a legal action in case of benefit it was not expressly made, cannot maintain an action on
a dispute over the milling contracts. it. One cannot do so, even if the contract performed by the
contracting parties would incidentally inure to ones
Moreover, even assuming that petitioners are indeed representatives of the benefit. (emphasis ours)
member Planters who have milling contracts with the respondents and assuming
further that petitioners signed the milling contracts as representatives of their In Uy v. Court of Appeals,[15] this Court held that the agents of the parties to
members, petitioners could not initiate arbitration proceedings in their own name as a contract do not have the right to bring an action even if they rendered some service
they had done in the present case. As mere agents, they should have brought the suit on behalf of their principals. To quote from that decision:
in the name of the principals that they purportedly represent. Even if Section 4 of R.A.
No. 876 allows the agreement to arbitrate to be signed by a representative, the [Petitioners] are mere agents of the owners of the land subject of
principal is still the one who has the right to demand arbitration. the sale. As agents, they only render some service or do something
in representation or on behalf of their principals. The rendering of
Indeed, Rule 3, Section 2 of the Rules of Court requires suits to be brought such service did not make them parties to the contracts of sale
in the name of the real party in interest, to wit: executed in behalf of the latter. Since a contract may be violated
only by the parties thereto as against each other, the real parties-
Sec. 2. Parties in interest. A real party in interest is the in-interest, either as plaintiff or defendant, in an action upon
party who stands to be benefited or injured by the judgment in the that contract must, generally, either be parties to said contract.
suit, or the party entitled to the avails of the suit. Unless otherwise (emphasis and words in brackets ours)
authorized by law or these Rules, every action must be prosecuted
or defended in the name of the real party in interest. The main cause of action of petitioners in their request for arbitration with the
RTC is the alleged violation of the clause in the milling contracts involving the
proportionate sharing in the proceeds of the harvest. Petitioners essentially demand To summarize, the requisites of a stipulation pour autrui or a stipulation in
that respondents increase the share of the member Planters to 66% to equalize their favor of a third person are the following: (1) there must be a stipulation in favor of a
situation with those of the non-member Planters. Verily, from petitioners' own third person, (2) the stipulation must be a part, not the whole, of the contract, (3) the
allegations, the party who would be injured or benefited by a decision in the arbitration contracting parties must have clearly and deliberately conferred a favor upon a third
proceedings will be the member Planters involved and not petitioners. In sum, person, not a mere incidental benefit or interest, (4) the third person must have
petitioners are not the real parties in interest in the present case. communicated his acceptance to the obligor before its revocation, and (5) neither of
the contracting parties bears the legal representation or authorization of the third
Assuming petitioners had properly brought the case in the name of their members party.[17] These requisites are not present in this case.
who had existing milling contracts with respondents, petitioners must still prove that
they were indeed authorized by the said members to institute an action for and on the Article VI of the Milling Contract is the solitary provision that mentions some
members' behalf. In the same manner that an officer of the corporation cannot bring benefit in favor of the association of which the planter is a member and we quote:
action in behalf of a corporation unless it is clothed with a board resolution authorizing VI
an officer to do so, an authorization from the individual member planter is a sine qua SHARE IN THE SUGAR
non for the association or any of its officers to bring an action before the court of Thirty four per centrum (34%) of the sugar ad molasses
law. The mere fact that petitioners were organized for the purpose of advancing the resulting from the milling of the PLANTERs sugarcane, as
interests and welfare of their members does not necessarily mean that petitioners computed from the weight and analysis of the sugarcane delivered
have the authority to represent their members in legal proceedings, including the by the PLANTER, shall belong to the CENTRAL; sixty five per
present arbitration proceedings. centum (65%) thereof to the PLANTER, and one per centum (1%)
as aid to the association of the PLANTER; provided that, if the
As we see it, petitioners had no intention to litigate the case in a PLANTER is not a member of any association recognized by the
representative capacity, as they contend. All the pleadings from the RTC to this Court CENTRAL, said one per centum (1%) shall revert to the
belie this claim. Under Section 3 of Rule 3, where the action is allowed to be CENTRAL. The 1% aid shall be used by the association for any
prosecuted by a representative, the beneficiary shall be included in the title of the purpose that it may deem fit for its members, laborers and their
case and shall be deemed to be the real party in interest. As repeatedly pointed out dependents, or for its other socio-economic projects.
earlier, the individual Planters were not even impleaded as parties to this case. In
addition, petitioners need a power-of-attorney to represent the Planters whether in the The foregoing provision cannot, by any stretch of the imagination, be
lawsuit or to demand arbitration.[16] None was ever presented here. considered as a stiputation pour autrui or for the benefit of the petitioners. The
primary rationale for the said stipulation is to ensure a just share in the proceeds of
Lastly, petitioners theorize that they could demand and sue for arbitration the harvest to the Planters. In other words, it is a stipulation meant to benefit the
independently of the Planters because the milling contract is a contract pour Planters. Even the 1% share to be given to the association as aid does not redound to
autrui under Article 1311 of the Civil Code. the benefit of the association but is intended to be used for its member Planters. Not
only that, it is explicit that said share reverts back to respondent sugar centrals if the
ART. 1311. Contracts take effect only between the parties, their contracting Planter is not affiliated with any recognized association.
assigns and heirs, except in case where the rights and obligations
arising from the contract are not transmissible by their nature, or by To be considered a pour autrui provision, an incidental benefit or interest,
stipulation or by provision of law. The heir is not liable beyond the which another person gains, is not sufficient. The contracting parties must have
value of the property he received from the decedent. clearly and deliberately conferred a favor upon a third person. [18] Even the clause
stating that respondents must secure the consent of the association if respondents
If a contract should contain some stipulation in favor of a grant better benefits to a Planter has for its rationale the protection of the member
third person, he may demand its fulfillment provided he Planter. The only interest of the association therein is that its member Planter will not
communicated his acceptance to the obligor before its revocation. A be put at a disadvantage vis a vis other Planters. Thus, the associations interest in
mere incidental benefit or interest of a person is not sufficient. The these milling contracts is only incidental to their avowed purpose of advancing the
contracting parties must have clearly and deliberately conferred a welfare and rights of their member Planters.
favor upon a third person.
In all, the Court finds no grave abuse of discretion nor reversible error Governments contractor under a Financial and Technical Assistance
committed by the CA in setting aside the Joint Orders issued by the RTC. Agreement (FTAA). On 20 June 1994, Arimco Mining Corporation obtained the
FTAA[2] and carried out work under the FTAA.
WHEREFORE, petition is hereby DISMISSED.
Respondents executed the Operating and Financial Accommodation
Costs against petitioners. Contract[3] (between Climax-Arimco Mining Corporation and Climax Mining Ltd., as
first parties, and Australasian Philippines Mining Inc., as second party) dated 23
SO ORDERED. December 1996 and Assignment, Accession Agreement[4] (between Climax-Arimco
Mining Corporation and Australasian Philippines Mining Inc.) dated 3 December 1996.
Respondent Climax Mining Corporation (Climax) and respondent Australasian
Philippines Mining Inc. (APMI) entered into a Memorandum of Agreement[5] dated 1
June 1991 whereby the former transferred its FTAA to the latter.
[G.R. No. 161957. February 28, 2005]
On 8 November 1999, petitioner Gonzales filed before the Panel of Arbitrators,
Region II, Mines and Geosciences Bureau of the Department of Environment and
Natural Resources, against respondents Climax-Arimco Mining Corporation (Climax-
Arimco), Climax, and APMI,[6] a Complaint[7] seeking the declaration of nullity or
JORGE GONZALES and PANEL OF ARBITRATORS, petitioners, vs. CLIMAX termination of the Addendum Contract, the FTAA, the Operating and Financial
MINING LTD., CLIMAX-ARIMCO MINING CORP., and AUSTRALASIAN Accommodation Contract, the Assignment, Accession Agreement, and
PHILIPPINES MINING INC., respondents. the Memorandum of Agreement. Petitioner Gonzales prayed for an unspecified
amount of actual and exemplary damages plus attorneys fees and for the issuance of
DECISION a temporary restraining order and/or writ of preliminary injunction to restrain or enjoin
respondents from further implementing the questioned agreements. He sought said
TINGA, J.: releifs on the grounds of FRAUD, OPPRESSION and/or VIOLATION of Section 2,
Article XII of the CONSTITUTION perpetrated by these foreign RESPONDENTS,
Petitioner Jorge Gonzales, as claimowner of mineral deposits located within the conspiring and confederating with one another and with each other.[8]
Addendum Area of Influence in Didipio, in the provinces of Quirino and Nueva
On 21 February 2001, the Panel of Arbitrators dismissed the Complaint for lack
Vizcaya, entered into a co-production, joint venture and/or production-sharing letter-
of jurisdiction. Petitioner moved for reconsideration and this was granted on 18
agreement designated as the May 14, 1987 Letter of Intent with Geophilippines, Inc,
October 2001, the Panel believing that the case involved a dispute involving rights to
and Inmex Ltd. Under the agreement, petitioner, as claimowner, granted to
mining areas and a dispute involving surface owners, occupants and claim
Geophilippines, Inc. and Inmex Ltd. collectively, the exclusive right to explore and
owners/concessionaires. According to the Panel, although the issue raised in
survey the mining claims for a period of thirty-six (36) months within which the latter
the Complaint appeared to be purely civil in nature and should be within the
could decide to take an operating agreement on the mining claims and/or develop,
jurisdiction of the regular courts, a ruling on the validity of the assailed contracts
operate, mine and otherwise exploit the mining claims and market any and all
would result to the grant or denial of mining rights over the properties; therefore, the
minerals that may be derived therefrom.
question on the validity of the contract amounts to a mining conflict or dispute. Hence,
On 28 February 1989, the parties to the May 14, 1987 Letter of the Panel granted the Motion for Reconsideration with regard to the issues of nullity,
Intent renegotiated the same into the February 28, 1989 Agreement whereby the termination, withdrawal or damages, but with regard to the constitutionality of
exploration of the mining claims was extended for another period of three years. the Addendum Agreement and FTAA, it held that it had no jurisdiction.[9]

On 9 March 1991, petitioner Gonzales, Arimco Mining Corporation, Respondents filed their motion for reconsideration but this was denied on 25
Geophilippines Inc., Inmex Ltd., and Aumex Philippines, Inc. signed a document June 2002. The Panel of Arbitrators maintained that there was a mining dispute
designated as the Addendum to the May 14, 1987 Letter of Intent and February 28, between the parties since the subject matter of the Complaint arose from contracts
1989 Agreement with Express Adhesion Thereto (hereafter, the Addendum between the parties which involve the exploration and exploitation of minerals over
Contract).[1] Under the Addendum Contract, Arimco Mining Corporation would apply the disputed area.[10]
to the Government of the Philippines for permission to mine the claims as the
Respondents assailed the orders of the Panel of Arbitrators via a petition for ii.
certiorari before the Court of Appeals.
On 30 July 2003, the Court of Appeals granted the petition, declaring that the WHETHER THE HONORABLE COURT OF APPEALS DEPARTED FROM THE
Panel of Arbitrators did not have jurisdiction over the complaint filed by RULES AND ESTABLISHED JURISPRUDENCE WHEN IT DID NOT DISMISS THE
petitioner.[11] The jurisdiction of the Panel of Arbitrators, said the Court of Appeals, is PETITION A QUO FILED BY RESPONDENT CLIMAX DESPITE THE LACK OF THE
limited only to the resolution of mining disputes, defined as those which raise a REQUISITE AUTHORITY TO FILE THE PETITION A QUO.
question of fact or matter requiring the technical knowledge and experience of mining
authorities. It was found that the complaint alleged fraud, oppression and violation of B.
the Constitution, which called for the interpretation and application of laws, and did
not involve any mining dispute. The Court of Appeals also observed that there were SUBSTANTIVE GROUND
no averments relating to particular acts constituting fraud and oppression. It added
that since the Addendum Contract was executed in 1991, the action to annul it should
have been brought not later than 1995, as the prescriptive period for an action for THE HONORABLE COURT OF APPEALS ERRED IN GRANTING THE PETITION A
annulment is four years from the time of the discovery of the fraud.[12] When petitioner QUO FILED BY RESPONDENTS AND IN DENYING MOTION FOR
filed his complaint before the Panel in 1999, his action had already prescribed. Also, RECONSIDERATION FILED BY PETITIONER FOR UTTER LACK OF BASIS IN
the Court of Appeals noted that fraud and duress only make a contract FACT AND IN LAW.
voidable,[13] not inexistent, hence the contract remains valid until annulled. The Court
of Appeals was of the opinion that the petition should have been settled through i.
arbitration under Republic Act No. 876 (The Arbitration Law) as stated in Clause 19.1
of the Addendum Contract. The Court of Appeals therefore declared as invalid the WHETHER THE HONORABLE COURT OF APPEALS DEPARTED FROM THE
orders dated 18 October 2001 and 25 June 2002 issued by the Panel of Arbitrators. RULES AND ESTABLISHED JURISPRUDENCE WHEN IT HELD THAT
On 28 January 2004, the Court of Appeals denied petitioners motion for PETITIONER CEDED HIS CLAIMS OVER THE MINERAL DEPOSITS LOCATED
reconsideration for lack of merit.[14] WITHIN THE ADDENDUM AREA OF INFLUENCE.
Petitioner filed on 22 March 2004 this Petition for Review on Certiorari Under
Rule 45 assailing the decision and resolution of the Court of Appeals. Petitioner raises ii.
the following issues:
A. WHETHER THE HONORABLE COURT OF APPEALS DEPARTED FROM THE
RULES AND ESTABLISHED JURISPRUDENCE WHEN IT HELD THAT THE PANEL
OF ARBITRATORS IS BEREFT OF JURISDICTION OVER THE SUBJECT MATTER
PROCEDURAL GROUND OF CASE NO. 058.

THE HONORABLE COURT OF APPEALS SHOULD HAVE SUMMARILY iii.


DISMISSED RESPONDENTS PETITION A QUO FOR FAILURE TO COMPLY WITH
PROCEDURAL REQUIREMENTS.
WHETHER THE HONORABLE COURT OF APPEALS DEPARTED FROM THE
RULES AND ESTABLISHED JURISPRUDENCE WHEN IT HELD THAT THE
i. COMPLAINT FILED BY THE PETITIONER FAILED TO ALLEGE ULTIMATE FACTS
OR PARTICULARS OF FRAUD.
WHETHER THE HONORABLE COURT OF APPEALS DEPARTED FROM THE
RULES AND ESTABLISHED JURISPRUDENCE WHEN IT DID NOT DISMISS THE iv.
PETITION A QUO DESPITE RESPONDENTS FAILURE TO COMPLY WITH THE
RULES ON DISCLOSURE IN THE VERIFICATION AND CERTIFICATION PORTION
OF THEIR PETITION A QUO.
WHETHER THE HONORABLE COURT OF APPEALS DEPARTED FROM THE Arbitration seeks the implementation of the arbitration clause in the agreement
RULES AND ESTABLISHED JURISPRUDENCE WHEN IT HELD THAT between the parties.
PETITIONER AND RESPONDENTS SHOULD SUBMIT TO ARBITRATION UNDER
R.A. 876. Petitioner next alleges that there was no authority granted by respondent Climax
to the law firm of Sycip Salazar Hernandez & Gatmaitan to file the petition before the
Court of Appeals. There is allegedly no Secretarys Certificate from respondent Climax
v. attached to the petition. The Verification and Certification only contains a statement
made by one Marianne M. Manzanas that she is also the authorized representative of
WHETHER THE HONORABLE COURT OF APPEALS DEPARTED FROM THE [respondent Climax] without presenting further proof of such authority. Hence, it is
RULES AND ESTABLISHED JURISPRUDENCE WHEN IT HELD THAT THE argued that as to respondent Climax, the petition filed before the Court of Appeals is
ACTION TO DECLARE THE NULLITY OF THE ADDENDUM CONTRACT, FTAA, an unauthorized act and the assailed orders of the Panel of Arbitrators have become
OFAC AND AAAA ON THE GROUND OF FRAUD HAS PRESCRIBED. final.
Under Section 3, Rule 46 of the Rules of Court, a petitioner is required to
The issues for resolution in this petition for review are: submit, together with the petition, a sworn certification of non-forum shopping, and
(a) Whether there was forum-shopping on the part of respondents for their failure to comply with this requirement is sufficient ground for dismissal of the petition.
failure to disclose to this Court their filing of a Petition to Compel for The requirement that petitioner should sign the certificate of non-forum shopping
Arbitration before the Regional Trial Court of Makati City, Branch 148, which is applies even to corporations, the Rules of Court making no distinction between
currently pending. natural and juridical persons. The signatory in the case of the corporation should be a
duly authorized director or officer of the corporation who has knowledge of the matter
(b) Whether counsel for respondent Climax had authority to file the petition for being certified.[15] If, as in this case, the petitioner is a corporation, a board resolution
certiorari before the Court of Appeals considering that the signor of the petition for authorizing a corporate officer to execute the certification against forum-shopping is
certioraris Verification and Certification of Non-forum Shopping was not authorized necessary. A certification not signed by a duly authorized person renders the petition
to sign the same in behalf of respondent Climax. subject to dismissal.[16]

(c) Whether the complaint filed by petitioner raises a mining dispute over which On this point, we have to agree with petitioner. There appears to be no
the Panel of Arbitrators has jurisdiction, or a judicial question which should properly subsequent compliance with the requirement to attach a board resolution authorizing
be brought before the regular courts. the signor Marianne M. Manzanas to file the petition in behalf of respondent Climax.
Respondent also failed to refute this in its Comment.[17] However, this latter issue
(d) Whether the dispute between the parties should be brought for arbitration becomes irrelevant in the light of our decision to deny this petition for review for lack
under Rep. Act No. 876. of jurisdiction by the Panel of Arbitrators over the complaint filed by petitioner, as will
be discussed below.
Let us deal first with procedural matters.
We now come to the meat of the case which revolves mainly around the
Petitioner claims that respondents are guilty of forum-shopping for failing to
question of jurisdiction by the Panel of Arbitrators: Does the Panel of Arbitrators have
disclose before this Court that they had filed a Petition to Compel for
Arbitration before the RTC of Makati City. However, it cannot be determined from jurisdiction over the complaint for declaration of nullity and/or termination of the
subject contracts on the ground of fraud, oppression and violation of the Constitution?
petitioners mere allegations in the Petition that the Petition to Compel for
This issue may be distilled into the more basic question of whether
Arbitration instituted by respondent Climax-Arimco, involves related causes of action
the Complaint raises a mining dispute or a judicial question.
and the grant of the same or substantially the same reliefs as those involved in the
instant case. Petitioner did not attach copies of the Petition to Compel for A judicial question is a question that is proper for determination by the courts, as
Arbitration or any order or resolution of the RTC of Makati City related to that case. opposed to a moot question or one properly decided by the executive or legislative
branch.[18] A judicial question is raised when the determination of the question
Furthermore, it can be gleaned from the nature of the two actions that the issues
involves the exercise of a judicial function; that is, the question involves the
in the case before the RTC of Makati City and in the petition for certiorari before the
determination of what the law is and what the legal rights of the parties are with
Court of Appeals are different. A petition for certiorari raises the issue of whether or
not there was grave abuse of discretion, while the Petition to Compel for respect to the matter in controversy.[19]
On the other hand, a mining dispute is a dispute involving (a) rights to mining fraud which vitiated petitioners consent, and under Article 1390 of the Civil Code, is
areas, (b) mineral agreements, FTAAs, or permits, and (c) surface owners, occupants one of the grounds for the annulment of a voidable contract. Voidable or annullable
and claimholders/concessionaires.[20] Under Republic Act No. 7942 (otherwise known contracts, before they are set aside, are existent, valid, and binding, and are effective
as the Philippine Mining Act of 1995), the Panel of Arbitrators has exclusive and and obligatory between the parties.[28] They can be ratified.[29]
original jurisdiction to hear and decide these mining disputes. [21] The Court of
Appeals, in its questioned decision, correctly stated that the Panels jurisdiction is Petitioner insists that the Complaint is actually one for the declaration of nullity of
limited only to those mining disputes which raise questions of fact or matters requiring void contracts. He argues that respondents, by their lack of financial and technical
the application of technological knowledge and experience.[22] competence to carry out the mining project, do not qualify to enter into a co-
production, joint venture or production sharing agreement with the Government, in
In Pearson v. Intermediate Appellate Court,[23] this Court observed that the trend circumvention of and in patent violation of the spirit and purpose of the Constitution,
has been to make the adjudication of mining cases a purely administrative particularly Section 2, Article XII thereof. Petitioner relies on the Civil Code for
matter.[24] Decisions[25] of the Supreme Court on mining disputes have recognized a support:[30]
distinction between (1) the primary powers granted by pertinent provisions of law to
the then Secretary of Agriculture and Natural Resources (and the bureau directors) of Art. 1409. The following contracts are inexistent and void from the beginning:
an executive or administrative nature, such as granting of license, permits, lease and
contracts, or approving, rejecting, reinstating or canceling applications, or deciding
conflicting applications, and (2) controversies or disagreements of civil or contractual (1) Those whose cause, object or purpose is contrary to law, morals, good customs,
nature between litigants which are questions of a judicial nature that may be public order or public policy;
adjudicated only by the courts of justice. This distinction is carried on even in Rep. Act
No. 7942. ....
The Complaint charged respondents with disregarding and ignoring the
provisions of the Addendum Contract, violating the purpose and spirit of the May 14, (7) Those expressly prohibited or declared void by law.
1987 Letter of Intent and February 28, 1989 Agreement, and acting in a fraudulent
and oppressive manner against petitioner and practicing fraud and deception against ....
the Government.[26] Petitioner alleged in his Complaint that under the original
agreements (the May 14, 1987 Letter of Intent and February 28, 1989 Agreement) Petitioner asserts that for circumventing and being in patent violation of the
respondent Climax-Arimco had committed to complete the Bankable Feasibility Study Constitution, the Addendum Contract, the FTAA and the other contracts are void
by 28 February 1992, but the same was not accomplished. Instead, respondent contracts. As such, they do not produce any effect and cannot be ratified.
Climax-Arimco, through false and insidious representations and machinations by
alleging technical and financial capacity, induced petitioner to enter into However, whether the case involves void or voidable contracts is still a judicial
the Addendum Contract and the FTAA in order to repeatedly extend the option period question. It may, in some instances, involve questions of fact especially with regard to
within which to conduct the feasibility study. In essence, petitioner alleges that the determination of the circumstances of the execution of the contracts. But the
respondents, conspiring and confederating with one another, misrepresented under resolution of the validity or voidness of the contracts remains a legal or judicial
the Addendum Contract and FTAA that respondent Climax-Arimco possessed question as it requires the exercise of judicial function. It requires the ascertainment of
financial and technical capacity to put the project into commercial production, when in what laws are applicable to the dispute, the interpretation and application of those
truth it had no such qualification whatsoever to do so. By so doing, respondents have laws, and the rendering of a judgment based thereon. Clearly, the dispute is not a
allegedly caused damage not only to petitioner but also to the Republic of the mining conflict. It is essentially judicial. The complaint was not merely for the
Philippines.[27] determination of rights under the mining contracts since the very validity of those
contracts is put in issue.
It is apparent that the Panel of Arbitrators is bereft of jurisdiction over
the Complaint filed by petitioner. The basic issue in petitioners Complaint is the The Complaint is not about a dispute involving rights to mining areas, nor is it a
presence of fraud or misrepresentation allegedly attendant to the execution of dispute involving claimholders or concessionaires. The main question raised was the
the Addendum Contract and the other contracts emanating from it, such that the validity of the Addendum Contract, the FTAA and the subsequent contracts. The
contracts are rendered invalid and not binding upon the parties. It avers that petitioner question as to the rights of petitioner or respondents to the mining area pursuant to
was misled by respondents into agreeing to the Addendum Contract. This constitutes these contracts, as well as the question of whether or not petitioner had ceded his
mining claims in favor of respondents by way of execution of the questioned itself. A party cannot rely on the contract and claim rights or obligations under it and at
contracts, is merely corollary to the main issue, and may not be resolved without first the same time impugn its existence or validity. Indeed, litigants are enjoined from
determining the main issue. taking inconsistent positions. As previously discussed, the complaint should have
been filed before the regular courts as it involved issues which are judicial in nature.
The Complaint is also not what is contemplated by Rep. Act No. 7942 when it
says the dispute should involve FTAAs. The Complaint is not exclusively within the WHEREFORE, in view of the foregoing, the Petition for Review on Certiorari
jurisdiction of the Panel of Arbitrators just because, or for as long as, the dispute Under Rule 45 is DENIED. The Orders dated 18 October 2001 and 25 June 2002 of
involves an FTAA. The Complaint raised the issue of the constitutionality of the FTAA, the Panel of Arbitrators are SET ASIDE. Costs against petitioner Jorge Gonzales.
which is definitely a judicial question. The question of constitutionality is exclusively
within the jurisdiction of the courts to resolve as this would clearly involve the exercise SO ORDERED.
of judicial power. The Panel of Arbitrators does not have jurisdiction over such an
issue since it does not involve the application of technical knowledge and expertise
KOREA TECHNOLOGIES CO., G.R. No. 143581
relating to mining. This the Panel of Arbitrators has even conceded in its Orders dated
LTD.,
18 October 2001 and 25 June 2002. At this juncture, it is worthy of note that in a
Petitioner,
case,[31] which was resolved only on 1 December 2004, this Court upheld the validity
Present:
of the FTAA entered into by the Republic of the Philippines and WMC (Philippines),
Inc. and constitutionality of Rep. Act No. 7942 and DENR Administrative Order 96-
- versus - QUISUMBING, J., Chairperson,
40.[32] In fact, the Court took the case on an original petition, recognizing the
CARPIO,
exceptional character of the situation and the paramount public interest involved, as
CARPIO MORALES,
well as the necessity for a ruling to put an end to the uncertainties plaguing the mining
HON. ALBERTO A. LERMA, in TINGA, and
industry and the affected communities as a result of doubts case upon the
his capacity as Presiding Judge of VELASCO, JR., JJ.
constitutionality and validity of the Mining Act, the subject FTAA and future FTAAs,
Branch 256 of Regional Trial
and the need to avert a multiplicity of suits.[33]
Court of Muntinlupa City, and
Arbitration before the Panel of Arbitrators is proper only when there is a PACIFIC GENERAL STEEL Promulgated:
disagreement between the parties as to some provisions of the contract between MANUFACTURING
them, which needs the interpretation and the application of that particular knowledge CORPORATION,
and expertise possessed by members of that Panel. It is not proper when one of the Respondents. January 7, 2008
parties repudiates the existence or validity of such contract or agreement on the
ground of fraud or oppression as in this case. The validity of the contract cannot be Doctrine: Established in this jurisdiction is the rule that the law of the place where the
subject of arbitration proceedings. Allegations of fraud and duress in the execution of contract is made governs. Lex loci contractus. A contract perfected in the Philippines
a contract are matters within the jurisdiction of the ordinary courts of law. These will be governed by Philippine laws. Nonetheless, Art. 2044 of the Civil Code
questions are legal in nature and require the application and interpretation of laws and sanctions the validity of mutually agreed arbitral clause or the finality and binding
jurisprudence which is necessarily a judicial function. effect of an arbitral award without prejudice to Articles 2038, 2039 and 2040, which
refer to instances where a compromise or an arbitral award, as applied to Art. 2044
Petitioner also disagrees with the Court of Appeals ruling that the case should pursuant to Art. 2043, may be voided, rescinded, or annulled, but these would not
be brought for arbitration under Rep. Act 876, pursuant to the arbitration clause in denigrate the finality of the arbitral award.
the Addendum Contract which states that [a]ll disputes arising out of or in connection While the RTC does not have jurisdiction over disputes governed by arbitration
with the Contract, which cannot be settled amicably among the Parties, shall finally be mutually agreed upon by the parties, still the foreign arbitral award is subject to
settled under R.A. 876. He points out that respondents Climax and APMI are not judicial review by the RTC which can set aside, reject, or vacate it.
parties to the Addendum Contract and are thus not bound by the arbitration clause in Summary: Korea Tech and Pacific General entered into a contract where Korea Tech
said contract. would set up an LPG Cylinder Manufacturing Plant in Carmona, Cavite for Pacific
General. The contract was executed in the Philippines and it contained an Arbitration
We agree that the case should not be brought under the ambit of the Arbitration
Clause which provided that disputes must be referred to a tribunal body in Korea.
Law, but for a different reason. The question of validity of the contract containing the
During the performance of the contract, issues arose regarding the non-delivery of
agreement to submit to arbitration will affect the applicability of the arbitration clause
certain equipment and the delivery of equipment of lesser quality than that agreed 5. Korea Tech wrote to Pacific General, informing the latter that Pacific General
upon. Pacific General wanted to unilaterally rescind the contract, while Korea Tech could not unilaterally rescind their contract nor dismantle and transfer the
opposed, arguing that the dispute should be referred to arbitration. Pacific General machineries and equipment on mere imagined violations by Korea Tech. It also
argued that the arbitration clause was void for being violative of public policy as it oust insisted that their disputes should be settled by arbitration as agreed upon in
jurisdiction from the Courts. RTC and CA ruled for Pacific General. SC reversed Article 15, the arbitration clause of their contract.
upholding the validity of the arbitration clause. It explained that by the principle of lex
loci contractus, contract executed in the Philippines should be governed by Philippine 6. Korea Tech initiated arbitration before the Korea Commercial Arbitration Board
law, however, the law also provides that where parties mutually agree on an [KCAB] in Seoul, Korea pursuant to Art. 15 of the Contract as amended..
arbitration clause, the courts must refer such case to arbitration. The arbitral award is
however subject to judicial confirmation to be final, binding and enforceable, thus, it is 7. Korea Tech filed a Complaint for Specific Performance against Pacific General
wrong to argue that the courts are oust from jurisdiction. Hence, the parties must before the RTC. In its complaint, Korea Tech alleged that Pacific General had
submit to arbitration. initially admitted that the checks that were stopped were not funded but later on
Facts: claimed that it stopped payment of the checks for the reason that their value was
1. Korea Technologies Co., Ltd. (Korea Tech), a Korean corporation, entered into a not received as the former allegedly breached their contract by altering the
contract with Pacific General Steel Manufacturing Corporation (Pacific General), quantity and lowering the quality of the machinery and equipment installed in the
a domestic corporation. The contract was executed in the Philippines. It also plant and failed to make the plant operational. Likewise, Korea Tech averred
contains an Arbitration Clause (Art. 15 of the Contract) which provided that that Pacific General violated Art. 15 of their Contract, as amended, by
disputes must be referred to a tribunal body in Korea. unilaterally rescinding the contract without resorting to arbitration. The Court
“Article 15. Arbitration.All disputes, controversies, or differences which may arise granted a TRO which restrained Pacific General from dismantling and
between the parties, out of or in relation to or in connection with this Contract or for transferring the machinery and equipment installed in the plant.
the breach thereof, shall finally be settled by arbitration in Seoul, Korea in accordance
with the Commercial Arbitration Rules of the Korean Commercial Arbitration Board. 8. Pacific General opposed the application and argued that the arbitration clause
The award rendered by the arbitration(s) shall be final and binding upon both parties was null and void, being contrary to public policy as it ousts the local court of
concerned.” jurisdiction.

2. Under the contract, Korea Tech would set up an LPG Cylinder Manufacturing 9. The trial court denied the application for a writ of preliminary injunction,
Plant in Carmona, Cavite. The contract was later amended, which then provided reasoning that Pacific General had paid Korea Tech the value of the
that Korea Tech undertook to ship and install in Pacific General’s site in machineries and equipment as shown in the contract such that Korea Tech no
Carmona, Cavite the machinery and facilities necessary for manufacturing LPG longer had proprietary rights over them. It also ruled that arbitration clause of the
cylinders, and to initially operate the plant after it is installed. Contract as amended was invalid as it tended to oust the trial court or any other
court jurisdiction over any dispute that may arise between the parties.
3. The last payments made by Pacific General to Korea Tech consisted of
postdated checks which were dishonored upon presentment by reason of 10. The Court of Appeals affirmed the trial court and found that Pacific General had
“stopped payment”. Pacific General stopped payment because it was alleged paid the value of the machineries and declared the arbitration clause against
that Korea Tech had delivered a hydraulic press which was different in kind and public policy.
of lower quality than that agreed upon and that Korea Tech also failed to deliver Issue:
equipment parts already paid for by Pacific General. W/N the arbitration clause stated in Article 15 of the contract is to be deemed null and
void for being against public policy - NO, hence parties must submit to arbitration
4. Pacific General later informed Korea Tech that it was was canceling their W/N the RTC is oust of its jurisdiction on a foreign arbitral award. - NO, although the
Contract on the ground that Korea Tech had altered the quantity and lowered court is mandated to refer cases to arbitration in proper cases, foreign arbitral awards
the quality of the machineries and equipment it delivered to Pacific General, and must still be confirmed by the RTC
that Pacific General would dismantle and transfer the machineries, equipment, HELD:
and facilities installed in the Carmona plant. Five days later, Pacific General filed 11. The arbitration clause not contrary to public policy. The arbitration clause which
before the Office of the Public Prosecutor an Affidavit-Complaint for Estafa. stipulates that the arbitration must be done in Seoul, Korea in accordance with
the Commercial Arbitration Rules of the KCAB, and that the arbitral award is
final and binding, is not contrary to public policy. This Court has sanctioned the party so requests not later than the pre-trial conference, or upon the request of both
validity of arbitration clauses in a catena of cases. parties thereafter, refer the parties to arbitration unless it finds that the arbitration
agreement is null and void, inoperative or incapable of being performed.
12. Established in this jurisdiction is the rule that the law of the place where the
contract is made governs. Lex loci contractus. The contract in this case was 17. Foreign arbitral awards while mutually stipulated by the parties in the arbitration
perfected here in the Philippines. Therefore, our laws ought to govern. clause to be final and binding are not immediately enforceable or cannot be
Nonetheless, Art. 2044 of the Civil Code sanctions the validity of mutually implemented immediately. Sec. 35[43] of the UNCITRAL Model Law stipulates
agreed arbitral clause or the finality and binding effect of an arbitral award. Art. the requirement for the arbitral award to be recognized by a competent court for
2044 provides, “Any stipulation that the arbitrators’ award or decision shall be enforcement, which court under Sec. 36 of the UNCITRAL Model Law may
final, is valid, without prejudice to Articles 2038, 2039 and 2040.” Arts. 2038, refuse recognition or enforcement on the grounds provided for. RA 9285
2039, and 2040 abovecited refer to instances where a compromise or an arbitral incorporated these provisos to Secs. 42, 43, and 44 relative to Secs. 47 and 48
award, as applied to Art. 2044 pursuant to Art. 2043, may be voided, rescinded,
or annulled, but these would not denigrate the finality of the arbitral award. 18. While the RTC does not have jurisdiction over disputes governed by arbitration
mutually agreed upon by the parties, still the foreign arbitral award is subject to
13. The arbitration clause was mutually and voluntarily agreed upon by the parties. judicial review by the RTC which can set aside, reject, or vacate it. In this sense,
It has not been shown to be contrary to any law, or against morals, good what this Court held in Chung Fu Industries (Phils.), Inc., 206 SCRA 545 (1992),
customs, public order, or public policy. There has been no showing that the relied upon by Korea Tech is applicable insofar as the foreign arbitral awards,
parties have not dealt with each other on equal footing. We find no reason why while final and binding, do not oust courts of jurisdiction since these arbitral
the arbitration clause should not be respected and complied with by both parties. awards are not absolute and without exceptions as they are still judicially
reviewable. Chapter 7 of RA 9285 has made it clear that all arbitral awards,
14. Having said that the instant arbitration clause is not against public policy, we whether domestic or foreign, are subject to judicial review on specific grounds
come to the question on what governs an arbitration clause specifying that in provided for.
case of any dispute arising from the contract, an arbitral panel will be constituted
in a foreign country and the arbitration rules of the foreign country would govern 19. Thus, foreign arbitral awards when confirmed by the RTC are deemed not as a
and its award shall be final and binding. judgment of a foreign court but as a foreign arbitral award, and when confirmed,
are enforced as final and executory decisions of our courts of law.
15. For domestic arbitration proceedings, we have particular agencies to arbitrate
disputes arising from contractual relations. In case a foreign arbitral body is 20. Having ruled that the arbitration clause of the subject contract is valid and
chosen by the parties, the arbitration rules of our domestic arbitration bodies binding on the parties, and not contrary to public policy; consequently, being
would not be applied. As signatory to the Arbitration Rules of the UNCITRAL bound to the contract of arbitration, a party may not unilaterally rescind or
Model Law on International Commercial Arbitration of the United Nations terminate the contract for whatever cause without first resorting to arbitration.
Commission on International Trade Law (UNCITRAL) in the New York
Convention on June 21, 1985, the Philippines committed itself to be bound by 21. The issues arising from the contract between Pacific General and Korea Tech
the Model Law. We have even incorporated the Model Law in Republic Act No. on whether the equipment and machineries delivered and installed were
(RA) 9285, otherwise known as the Alternative Dispute Resolution Act of 2004 properly installed and operational in the plant in Carmona, Cavite; the ownership
entitled An Act to Institutionalize the Use of an Alternative Dispute Resolution of equipment and payment of the contract price; and whether there was
System in the Philippines and to Establish the Office for Alternative Dispute substantial compliance by Korea Tech in the production of the samples, given
Resolution, and for Other Purposes, promulgated on April 2, 2004. Secs. 19 and the alleged fact that Pacific General could not supply the raw materials required
20 of Chapter 4 of the Model Law are the pertinent provisions. to produce the sample LPG cylinders, are matters proper for arbitration. Indeed,
we note that on July 1, 1998, Korea Tech instituted an Application for Arbitration
16. Under Sec. 24 of RA 9285, the RTC does not have jurisdiction over disputes before the KCAB in Seoul, Korea pursuant to Art. 15 of the Contract as
that are properly the subject of arbitration pursuant to an arbitration clause, and amended. Thus, it is incumbent upon Pacific General to abide by its commitment
mandates the referral to arbitration in such cases, thus: to arbitrate.
SEC. 24. Referral to Arbitration.—A court before which an action is brought in a
matter which is the subject matter of an arbitration agreement shall, if at least one
perfected here in the Philippines. Therefore, our laws ought to govern.
Nonetheless, Art. 2044 of the Civil Code sanctions the validity of mutually
Korea Technologies Co., Ltd. vs. Lerma agreed arbitral clause or the finality and binding effect of an arbitral award.
Doctrine: Established in this jurisdiction is the rule that the law of the place where the Art. 2044 provides, “Any stipulation that the arbitrators’ award or decision
contract is made governs. Lex loci contractus. A contract perfected in the Philippines shall be final, is valid, without prejudice to Articles 2038, 2039 and 2040.”
will be governed by Philippine laws. Nonetheless, Art. 2044 of the Civil Code Arts. 2038, 2039, and 2040 abovecited refer to instances where a
sanctions the validity of mutually agreed arbitral clause or the finality and binding compromise or an arbitral award, as applied to Art. 2044 pursuant to Art.
effect of an arbitral award without prejudice to Articles 2038, 2039 and 2040, which 2043, may be voided, rescinded, or annulled, but these would not denigrate
refer to instances where a compromise or an arbitral award, as applied to Art. 2044 the finality of the arbitral award.
pursuant to Art. 2043, may be voided, rescinded, or annulled, but these would not
denigrate the finality of the arbitral award.  For domestic arbitration proceedings, we have particular agencies to
While the RTC does not have jurisdiction over disputes governed by arbitration arbitrate disputes arising from contractual relations. In case a foreign arbitral
mutually agreed upon by the parties, still the foreign arbitral award is subject to body is chosen by the parties, the arbitration rules of our domestic arbitration
judicial review by the RTC which can set aside, reject, or vacate it. bodies would not be applied. As signatory to the Arbitration Rules of the
Facts: UNCITRAL Model Law on International Commercial Arbitration of the United
 Korea Technologies Co., Ltd. [Korea Tech], a Korean corporation, entered Nations Commission on International Trade Law (UNCITRAL) in the New
into a contract with Pacific General Steel Manufacturing Corporation [Pacific York Convention on June 21, 1985, the Philippines committed itself to be
General], a domestic corporation. The contract was executed in the bound by the Model Law. We have even incorporated the Model Law in
Philippines. It also contains an Arbitration Clause which provided that Republic Act No. (RA) 9285, otherwise known as the Alternative Dispute
disputes must be referred to a tribunal body in Korea. Resolution Act of 2004 entitled An Act to Institutionalize the Use of an
 Korea Tech undertook to ship and install in Pacific General’s site in Alternative Dispute Resolution System in the Philippines and to Establish the
Carmona, Cavite the machinery and facilities necessary for manufacturing Office for Alternative Dispute Resolution, and for Other Purposes,
LPG cylinders, and to initially operate the plant after it is installed. promulgated on April 2, 2004. Secs. 19 and 20 of Chapter 4 of the Model
 The last payments made by Pacific General to Korea Tech consisted of Law are the pertinent provisions.
postdated checks which were dishonored upon presentment., it stopped
payment because Korea Tech had delivered a hydraulic press which was
different in kind and of lower quality than that agreed upon.  Under Sec. 24, the RTC does not have jurisdiction over disputes that are
 Korea Tech also failed to deliver equipment parts already paid for by it. properly the subject of arbitration pursuant to an arbitration clause, and
 Korea Tech initiated arbitration before the Korea Commercial Arbitration mandates the referral to arbitration in such cases, thus: SEC. 24. Referral to
Board [KCAB] in Seoul, Korea. Arbitration.—A court before which an action is brought in a matter which is
 Pacific General opposed the application and argued that the arbitration the subject matter of an arbitration agreement shall, if at least one party so
clause was null and void, being contrary to public policy as it ousts the local requests not later than the pre-trial conference, or upon the request of both
court of jurisdiction. parties thereafter, refer the parties to arbitration unless it finds that the
 The trial court declared the arbitration agreement null and void. arbitration agreement is null and void, inoperative or incapable of being
 Korea Tech filed a petition for certiorari before the Court of Appeals performed.
[CA]. The court dismissed the petition and held that an arbitration clause
which provided for a final determination of the legal rights of the parties to  While the RTC does not have jurisdiction over disputes governed by
the contract by arbitration was against public policy. arbitration mutually agreed upon by the parties, still the foreign arbitral award
Issue: is subject to judicial review by the RTC which can set aside, reject, or vacate
Whether or not the arbitration clause stated in Article 15 of the contract is to be it. In this sense, what this Court held in Chung Fu Industries (Phils.), Inc.,
deemed null and void. 206 SCRA 545 (1992), relied upon by KOGIES is applicable insofar as the
Whether or not the RTC is oust of its jurisdiction on a foreign arbitral award. foreign arbitral awards, while final and binding, do not oust courts of
HELD: jurisdiction since these arbitral awards are not absolute and without
 Established in this jurisdiction is the rule that the law of the place where the exceptions as they are still judicially reviewable. Chapter 7 of RA 9285 has
contract is made governs. Lex loci contractus. The contract in this case was
made it clear that all arbitral awards, whether domestic or foreign, are that the Employment Agreement is terminated for cause, effective November
subject to judicial review on specific grounds provided for. 19, 1995, in accordance with Section 7 (a) (v) of the said agreement, on
[G.R. No. 129916. March 26, 2001] account of his breach of Section 12 thereof. Respondent Zosa was further
advised that he shall have no further rights under the said Agreement or any
MAGELLAN CAPITAL MANAGEMENT CORPORATION and MAGELLAN claims against the Manager or the Corporation except the right to receive
CAPITAL HOLDINGS CORPORATION, petitioners, vs. ROLANDO M. within thirty (30) days from November 19, 1995, the amounts stated in
ZOSA and HON. JOSE P. SOBERANO, JR., in his capacity as Presiding Section 8 (a) (i) (ii) of the Agreement.[8]
Judge of Branch 58 of the Regional Trial Court Of Cebu, 7th Judicial
Region, respondents. Disagreeing with the position taken by petitioners, respondent Zosa invoked
the Arbitration Clause of the Employment Agreement, to wit:
DECISION
23. Arbitration. In the event that any dispute, controversy or claim arises out
BUENA, J.: of or under any provisions of this Agreement, then the parties hereto agree
to submit such dispute, controversy or claim to arbitration as set forth in this
Under a management agreement entered into on March 18, 1994, Magellan Section and the determination to be made in such arbitration shall be final
Capital Holdings Corporation [MCHC] appointed Magellan Capital and binding. Arbitration shall be effected by a panel of three arbitrators. The
Management Corporation [MCMC] as manager for the operation of its Manager, Employee and Corporation shall designate one (1) arbitrator who
business and affairs.[1] Pursuant thereto, on the same month, MCHC, shall, in turn, nominate and elect who among them shall be the chairman of
MCMC, and private respondent Rolando M. Zosa entered into an the committee. Any such arbitration, including the rendering of an arbitration
"Employment Agreement" designating Zosa as President and Chief award, shall take place in Metro Manila. The arbitrators shall interpret this
Executive Officer of MCHC. Agreement in accordance with the substantive laws of the Republic of the
Philippines. The arbitrators shall have no power to add to, subtract from or
Under the "Employment Agreement", the term of respondent Zosa's otherwise modify the terms of Agreement or to grant injunctive relief of any
employment shall be co-terminous with the management agreement, or until nature. Any judgment upon the award of the arbitrators may be entered in
March 1996,[2] unless sooner terminated pursuant to the provisions of the any court having jurisdiction thereof, with costs of the arbitration to be borne
Employment Agreement.[3] The grounds for termination of employment are equally by the parties, except that each party shall pay the fees and
also provided in the Employment Agreement. expenses of its own counsel in the arbitration.

On May 10, 1995, the majority of MCHCs Board of Directors decided not to On November 10, 1995, respondent Zosa designated his brother, Atty.
re-elect respondent Zosa as President and Chief Executive Officer of MCHC Francis Zosa, as his representative in the arbitration panel[9] while MCHC
on account of loss of trust and confidence[4] arising from alleged violation of designated Atty. Inigo S. Fojas[10] and MCMC nominated Atty. Enrique I.
the resolution issued by MCHC's board of directors and of the non- Quiason[11] as their respective representatives in the arbitration panel.
competition clause of the Employment Agreement.[5] Nevertheless, However, instead of submitting the dispute to arbitration, respondent Zosa,
respondent Zosa was elected to a new position as MCHC's Vice- on April 17, 1996, filed an action for damages against petitioners before the
Chairman/Chairman for New Ventures Development.[6] Regional Trial Court of Cebu[12] to enforce his benefits under the
Employment Agreement.
On September 26, 1995, respondent Zosa communicated his resignation for
good reason from the position of Vice-Chairman under paragraph 7 of the On July 3, 1996, petitioners filed a motion to dismiss[13] arguing that (1) the
Employment Agreement on the ground that said position had less trial court has no jurisdiction over the instant case since respondent Zosa's
responsibility and scope than President and Chief Executive Officer. He claims should be resolved through arbitration pursuant to Section 23 of the
demanded that he be given termination benefits as provided for in Section 8 Employment Agreement with petitioners; and (2) the venue is improperly laid
(c) (i) (ii) and (iii) of the Employment Agreement.[7] since respondent Zosa, like the petitioners, is a resident of Pasig City and
thus, the venue of this case, granting without admitting that the respondent
In a letter dated October 20, 1995, MCHC communicated its non-acceptance has a cause of action against the petitioners cognizable by the RTC, should
of respondent Zosa's resignation for good reason, but instead informed him be limited only to RTC-Pasig City.[14]
Agreement. In an order dated December 13, 1996, the trial court denied the
Meanwhile, respondent Zosa filed an amended complaint dated July 5, motion of petitioners MCMC and MCHC.
1996.
On January 17, 1997, petitioners MCMC and MCHC filed a petition for
On August 1, 1996, the RTC Branch 58 of Cebu City issued an Order certiorari and prohibition under Rule 65 of the Rules of Court with the Court
denying petitioners motion to dismiss upon the findings that (1) the validity of Appeals, questioning the trial court orders dated August 1, 1996,
and legality of the arbitration provision can only be determined after trial on September 5, 1996, and December 13, 1996.[21]
the merits; and (2) the amount of damages claimed, which is over
P100,000.00, falls within the jurisdiction of the RTC.[15] Petitioners filed a On March 21, 1997, the Court of Appeals rendered a decision, giving due
motion for reconsideration which was denied by the RTC in an order dated course to the petition, the decretal portion of which reads:
September 5, 1996.[16]
WHEREFORE, the petition is GIVEN DUE COURSE. The respondent court
In the interim, on August 22, 1996, in compliance with the earlier order of the is directed to resolve the issue on the validity or effectivity of the arbitration
court directing petitioners to file responsive pleading to the amended clause in the Employment Agreement, and to suspend further proceedings in
complaint, petitioners filed their Answer Ad Cautelam with counterclaim the trial on the merits until the said issue is resolved. The questioned orders
reiterating their position that the dispute should be settled through arbitration are set aside insofar as they contravene this Courts resolution of the issues
and the court had no jurisdiction over the nature of the action.[17] raised as herein pronounced.

On October 21, 1996, the trial court issued its pre-trial order declaring the The petitioner is required to remit to this Court the sum of P81.80 for cost
pre-trial stage terminated and setting the case for hearing. The order states: within five (5) days from notice.

ISSUES: SO ORDERED.[22]

The Court will only resolve one issue in so far as this case is concerned, to Petitioners filed a motion for partial reconsideration of the CA decision
wit: praying (1) for the dismissal of the case in the trial court, on the ground of
lack of jurisdiction, and (2) that the parties be directed to submit their dispute
Whether or not the Arbitration Clause contained in Sec.23 of the to arbitration in accordance with the Employment Agreement dated March
Employment Agreement is void and of no effect: and, if it is void and of no 1994. The CA, in a resolution promulgated on June 20, 1997, denied the
effect, whether or not the plaintiff is entitled to damages in accordance with motion for partial reconsideration for lack of merit.
his complaint and the defendants in accordance with their counterclaim.
In compliance with the CA decision, the trial court, on July 18, 1997,
It is understood, that in the event the arbitration clause is valid and binding rendered a decision declaring the arbitration clause in the Employment
between the parties, the parties shall submit their respective claim to the Agreement partially void and of no effect. The dispositive portion of the
Arbitration Committee in accordance with the said arbitration clause, in decision reads:
which event, this case shall be deemed dismissed.[18]
WHEREFORE, premises considered, judgment is hereby rendered partially
On November 18, 1996, petitioners filed their Motion Ad Cautelam for the declaring the arbitration clause of the Employment Agreement void and of no
Correction, Addition and Clarification of the Pre-trial Order dated November effect, only insofar as it concerns the composition of the panel of arbitrators,
15 1996,[19] which was denied by the court in an order dated November 28, and directing the parties to proceed to arbitration in accordance with the
1996.[20] Employment Agreement under the panel of three (3) arbitrators, one for the
plaintiff, one for the defendants, and the third to be chosen by both the
Thereafter, petitioners MCMC and MCHC filed a Motion Ad Cautelam for the plaintiff and defendants. The other terms, conditions and stipulations in the
parties to file their Memoranda to support their respective stand on the issue arbitration clause remain in force and effect."[23]
of the validity of the arbitration clause contained in the Employment
In view of the trial courts decision, petitioners filed this petition for review on It is error for the petitioners to claim that the case should fall under the
certiorari, under Rule 45 of the Rules of Court, assigning the following errors jurisdiction of the Securities and Exchange Commission [SEC, for brevity].
for the Courts resolution: The controversy does not in anyway involve the election/appointment of
officers of petitioner MCHC, as claimed by petitioners in their assignment of
I. The trial court gravely erred when it ruled that the arbitration clause under errors. Respondent Zosas amended complaint focuses heavily on the
the employment agreement is partially void and of no effect, considering illegality of the Employment Agreements Arbitration Clause initially invoked
that: by him in seeking his termination benefits under Section 8 of the
employment contract. And under Republic Act No. 876, otherwise known as
A. The arbitration clause in the employment agreement dated March 1994 the Arbitration Law, it is the regional trial court which exercises jurisdiction
between respondent Zosa and defendants MCHC and MCMC is valid and over questions relating to arbitration. We thus advert to the following
binding upon the parties thereto. discussions made by the Court of Appeals, speaking thru Justice Minerva P.
Gonzaga-Reyes,[25] in C.A.-G.R. S.P. No. 43059, viz:
B. In view of the fact that there are three parties to the employment
agreement, it is but proper that each party be represented in the arbitration As regards the fourth assigned error, asserting that jurisdiction lies with the
panel. SEC, which is raised for the first time in this petition, suffice it to state that
the Amended Complaint squarely put in issue the question whether the
C. The trial court grievously erred in its conclusion that petitioners MCMC Arbitration Clause is valid and effective between the parties. Although the
and MCHC represent the same interest. controversy which spawned the action concerns the validity of the
termination of the service of a corporate officer, the issue on the validity and
D. Respondent Zosa is estopped from questioning the validity of the effectivity of the arbitration clause is determinable by the regular courts, and
arbitration clause, including the right of petitioner MCMC to nominate its own do not fall within the exclusive and original jurisdiction of the SEC.
arbitrator, which he himself has invoked.
The determination and validity of the agreement is not a matter intrinsically
II. In any event, the trial court acted without jurisdiction in hearing the case connected with the regulation and internal affairs of corporations (see
below, considering that it has no jurisdiction over the nature of the action or Pereyra vs. IAC, 181 SCRA 244; Sales vs. SEC, 169 SCRA 121); it is rather
suit since controversies in the election or appointment of officers or an ordinary case to be decided in accordance with the general laws, and do
managers of a corporation, such as the action brought by respondent Zosa, not require any particular expertise or training to interpret and apply (Viray
fall within the original and exclusive jurisdiction of the Securities and vs. CA, 191 SCRA 308).[26]
Exchange Commission.
Furthermore, the decision of the Court of Appeals in CA-G.R. SP No. 43059
III. Contrary to respondent Zosas allegation, the issue of the trial courts affirming the trial courts assumption of jurisdiction over the case has become
jurisdiction over the case below has not yet been resolved with finality the law of the case which now binds the petitioners. The law of the case
considering that petitioners have expressly reserved their right to raise said doctrine has been defined as a term applied to an established rule that when
issue in the instant petition. Moreover, the principle of the law of the case is an appellate court passes on a question and remands the cause to the lower
not applicable in the instant case. court for further proceedings, the question there settled becomes the law of
the case upon subsequent appeal.[27] To note, the CAs decision in CA-G.R.
IV. Contrary to respondent Zosas allegation, petitioners MCMC and MCHC SP No. 43059 has already attained finality as evidenced by a Resolution of
are not guilty of forum shopping. this Court ordering entry of judgment of said case, to wit:

V. Contrary to respondent Zosas allegation, the instant petition for review ENTRY OF JUDGMENT
involves only questions of law and not of fact.[24]
This is to certify that on September 8, 1997 a decision/resolution rendered in
We rule against the petitioners. the above-entitled case was filed in this Office, the dispositive part of which
reads as follows:
G.R. No. 129615 (Magellan Capital Management Corporation, et al. vs. Agreement based on the said law, which is the arbitration clause but only as
Court of Appeals, Rolando Zosa, et al.).- Considering the petitioners regards the composition of the panel of arbitrators. The arbitration clause in
manifestation dated August 11, 1997 and withdrawal of intention to file question provides, thus:
petition for review on certiorari, the Court Resolved to DECLARE THIS
CASE TERMINATED and DIRECT the Clerk of Court to INFORM the parties In the event that any dispute, controversy or claim arise out of or under any
that the judgment sought to be reviewed has become final and executory, no provisions of this Agreement, then the parties hereto agree to submit such
appeal therefore having been timely perfected. dispute, controversy or claim to arbitration as set forth in this Section and the
determination to be made in such arbitration shall be final and binding.
and that the same has, on September 17, 1997, become final and executory Arbitration shall be effected by a panel of three arbitrators. The Manager,
and is hereby recorded in the Book of Entries of Judgments. [28] Employee, and Corporation shall designate one (1) arbitrator who shall, in
turn, nominate and elect as who among them shall be the chairman of the
Petitioners, therefore, are barred from challenging anew, through another committee. Any such arbitration, including the rendering of an arbitration
remedial measure and in any other forum, the authority of the regional trial award, shall take place in Metro Manila. The arbitrators shall interpret this
court to resolve the validity of the arbitration clause, lest they be truly guilty Agreement in accordance with the substantive laws of the Republic of the
of forum-shopping which the courts consistently consider as a contumacious Philippines. The arbitrators shall have no power to add to, subtract from or
practice that derails the orderly administration of justice. otherwise modify the terms of this Agreement or to grant injunctive relief of
any nature. Any judgment upon the award of the arbitrators may be entered
Equally unavailing for the petitioners is the review by this Court, via the in any court having jurisdiction thereof, with costs of the arbitration to be
instant petition, of the factual findings made by the trial court that the borne equally by the parties, except that each party shall pay the fees and
composition of the panel of arbitrators would, in all probability, work injustice expenses of its own counsel in the arbitration. (Emphasis supplied).
to respondent Zosa. We have repeatedly stressed that the jurisdiction of this
Court in a petition for review on certiorari under Rule 45 of the Revised From the foregoing arbitration clause, it appears that the two (2) defendants
Rules of Court is limited to reviewing only errors of law, not of fact, unless [petitioners] (MCMC and MCHC) have one (1) arbitrator each to compose
the factual findings complained of are devoid of support by the evidence on the panel of three (3) arbitrators. As the defendant MCMC is the Manager of
record, or the assailed judgment is based on misapprehension of facts.[29] defendant MCHC, its decision or vote in the arbitration proceeding would
naturally and certainly be in favor of its employer and the defendant MCHC
Even if procedural rules are disregarded, and a scrutiny of the merits of the would have to protect and preserve its own interest; hence, the two (2) votes
case is undertaken, this Court finds the trial courts observations on why the of both defendants (MCMC and MCHC) would certainly be against the lone
composition of the panel of arbitrators should be voided, incisively correct so arbitrator for the plaintiff [herein defendant]. Hence, apparently, plaintiff
as to merit our approval. Thus, [defendant] would never get or receive justice and fairness in the arbitration
proceedings from the panel of arbitrators as provided in the aforequoted
From the memoranda of both sides, the Court is of the view that the arbitration clause. In fairness and justice to the plaintiff [defendant], the two
defendants [petitioner] MCMC and MCHC represent the same interest. defendants (MCMC and MCHC)[herein petitioners] which represent the
There is no quarrel that both defendants are entirely two different same interest should be considered as one and should be entitled to only
corporations with personalities distinct and separate from each other and one arbitrator to represent them in the arbitration proceedings. Accordingly,
that a corporation has a personality distinct and separate from those persons the arbitration clause, insofar as the composition of the panel of arbitrators is
composing the corporation as well as from that of any other legal entity to concerned should be declared void and of no effect, because the law says,
which it may be related. Any clause giving one of the parties power to choose more arbitrators than
the other is void and of no effect (Article 2045, Civil Code).
But as the defendants [herein petitioner] represent the same interest, it could
never be expected, in the arbitration proceedings, that they would not protect The dispute or controversy between the defendants (MCMC and MCHC)
and preserve their own interest, much less, would both or either favor the [herein petitioners] and the plaintiff [herein defendant] should be settled in
interest of the plaintiff. The arbitration law, as all other laws, is intended for the arbitration proceeding in accordance with the Employment Agreement,
the good and welfare of everybody. In fact, what is being challenged by the but under the panel of three (3) arbitrators, one (1) arbitrator to represent the
plaintiff herein is not the law itself but the provision of the Employment plaintiff, one (1) arbitrator to represent both defendants (MCMC and
MCHC)[herein petitioners] and the third arbitrator to be chosen by the DECISION
plaintiff [defendant Zosa] and defendants [petitioners].
MARTINEZ, J.:
x x x x x x x x x[30]
This proceeding involves the enforcement of a foreign judgment rendered by the
In this connection, petitioners attempt to put respondent in estoppel in Civil Judge of Dehra Dun, India in favor of the petitioner, OIL AND NATURAL GAS
assailing the arbitration clause must be struck down. For one, this issue of COMMISSION and against the private respondent, PACIFIC CEMENT COMPANY,
estoppel, as likewise noted by the Court of Appeals, found its way for the INCORPORATED.
first time only on appeal. Well-settled is the rule that issues not raised below
cannot be resolved on review in higher courts.[31] Secondly, employment The petitioner is a foreign corporation owned and controlled by the Government
agreements such as the one at bar are usually contracts of adhesion. Any of India while the private respondent is a private corporation duly organized and
ambiguity in its provisions is generally resolved against the party who drafted existing under the laws of the Philippines. The present conflict between the petitioner
the document. Thus, in the relatively recent case of Phil. Federation of Credit and the private respondent has its roots in a contract entered into by and between
Cooperatives, Inc. (PFCCI) and Fr. Benedicto Jayoma vs. NLRC and both parties on February 26, 1983 whereby the private respondent undertook to
Victoria Abril,[32] we had the occasion to stress that where a contract of supply the petitioner FOUR THOUSAND THREE HUNDRED (4,300) metric tons of oil
employment, being a contract of adhesion, is ambiguous, any ambiguity well cement. In consideration therefor, the petitioner bound itself to pay the private
therein should be construed strictly against the party who prepared it. And, respondent the amount of FOUR HUNDRED SEVENTY-SEVEN THOUSAND THREE
finally, respondent Zosa never submitted himself to arbitration proceedings HUNDRED U.S. DOLLARS ($477,300.00) by opening an irrevocable, divisible, and
(as there was none yet) before bewailing the composition of the panel of confirmed letter of credit in favor of the latter. The oil well cement was loaded on
arbitrators. He in fact, lost no time in assailing the arbitration clause upon board the ship MV SURUTANA NAVA at the port of Surigao City, Philippines for
realizing the inequities that may mar the arbitration proceedings if the delivery at Bombay and Calcutta, India. However, due to a dispute between the
existing line-up of arbitrators remained unchecked. shipowner and the private respondent, the cargo was held up in Bangkok and did not
reach its point of destination. Notwithstanding the fact that the private respondent had
We need only to emphasize in closing that arbitration proceedings are already received payment and despite several demands made by the petitioner, the
designed to level the playing field among the parties in pursuit of a mutually private respondent failed to deliver the oil well cement. Thereafter, negotiations
acceptable solution to their conflicting claims. Any arrangement or scheme ensued between the parties and they agreed that the private respondent will replace
that would give undue advantage to a party in the negotiating table is the entire 4,300 metric tons of oil well cement with Class G cement cost free at the
anathema to the very purpose of arbitration and should, therefore, be petitioners designated port. However, upon inspection, the Class G cement did not
resisted. conform to the petitioners specifications. The petitioner then informed the private
respondent that it was referring its claim to an arbitrator pursuant to Clause 16 of their
WHEREFORE, premises considered, the petition is hereby DISMISSED and contract which stipulates:
the decision of the trial court dated July 18, 1997 is AFFIRMED.
Except where otherwise provided in the supply order/contract all questions and
SO ORDERED. disputes, relating to the meaning of the specification designs, drawings and
instructions herein before mentioned and as to quality of workmanship of the items
ordered or as to any other question, claim, right or thing whatsoever, in any way
arising out of or relating to the supply order/contract design, drawing, specification,
instruction or these conditions or otherwise concerning the materials or the execution
[G.R. No. 114323. July 23, 1998]
or failure to execute the same during stipulated/extended period or after the
completion/abandonment thereof shall be referred to the sole arbitration of the
persons appointed by Member of the Commission at the time of dispute. It will be no
objection to any such appointment that the arbitrator so appointed is a Commission
OIL AND NATURAL GAS COMMISSION, petitioner, vs. COURT OF APPEALS employer (sic) that he had to deal with the matter to which the supply or contract
and PACIFIC CEMENT COMPANY, INC. respondents. relates and that in the course of his duties as Commissions employee he had
expressed views on all or any of the matter in dispute or difference.
The arbitrator to whom the matter is originally referred being transferred or vacating Total amount of award - - - US $ 899,603.77
his office or being unable to act for any reason the Member of the Commission shall
appoint another person to act as arbitrator in acordance with the terms of the In addition to the above, the respondent would also be liable to pay to the claimant
contract/supply order. Such person shall be entitled to proceed with reference from the interest at the rate of 6% on the above amount, with effect from 24.7.1988 upto
the stage at which it was left by his predecessor. Subject as aforesaid the provisions the actual date of payment by the Respondent in full settlement of the claim as
of the Arbitration Act, 1940, or any Statutary modification or re-enactment there of and awarded or the date of the decree, whichever is earlier.
the rules made there under and for the time being in force shall apply to the arbitration
proceedings under this clause.
I determine the cost at Rs. 70,000/- equivalent to US $5,000 towards the expenses on
Arbitration, legal expenses, stamps duly incurred by the claimant. The cost will be
The arbitrator may with the consent of parties enlarge the time, from time to time, to shared by the parties in equal proportion.
make and publish the award.
Pronounced at Dehra Dun to-day, the 23rd of July 1988.[2]
The venue for arbitration shall be at Dehra dun. [1]
To enable the petitioner to execute the above award in its favor, it filed a Petition
On July 23, 1988, the chosen arbitrator, one Shri N.N. Malhotra, resolved the before the Court of the Civil Judge in Dehra Dun, India (hereinafter referred to as the
dispute in petitioners favor setting forth the arbitral award as follows: foreign court for brevity), praying that the decision of the arbitrator be made the Rule
of Court in India. The foreign court issued notices to the private respondent for filing
NOW THEREFORE after considering all facts of the case, the evidence, oral and objections to the petition. The private respondent complied and sent its objections
documentarys adduced by the claimant and carefully examining the various written dated January 16, 1989. Subsequently, the said court directed the private respondent
statements, submissions, letters, telexes, etc. sent by the respondent, and the oral to pay the filing fees in order that the latters objections could be given consideration.
arguments addressed by the counsel for the claimants, I, N.N. Malhotra, Sole Instead of paying the required filing fees, the private respondent sent the following
Arbitrator, appointed under clause 16 of the supply order dated 26.2.1983, according communication addressed to the Civil Judge of Dehra Dun:
to which the parties, i.e. M/S Oil and Natural Gas Commission and the Pacific Cement
Co., Inc. can refer the dispute to the sole arbitration under the provision of the The Civil Judge
Arbitration Act. 1940, do hereby award and direct as follows:- Dehra Dun (U.P.) India
Re: Misc. Case No. 5 of 1989
M/S Pacific Cement Co.,
The Respondent will pay the following to the claimant :- Inc. vs. ONGC Case

1. Amount received by the Respondent Sir:


against the letter of credit No. 11/19
dated 28.2.1983 - - - US $ 477,300.00
1. We received your letter dated 28 April 1989 only last 18 May 1989.
2. Re-imbursement of expenditure incurred
by the claimant on the inspection teams 2. Please inform us how much is the court fee to be paid. Your letter did not
visit to Philippines in August 1985 - - - US$ 3,881.00 mention the amount to be paid.

3. L. C. Establishment charges incurred 3. Kindly give us 15 days from receipt of your letter advising us how much to
by the claimant - - - US $ 1,252.82 pay to comply with the same.

4. Loss of interest suffered by claimant Thank you for your kind consideration.
from 21.6.83 to 23.7.88 - - - US $ 417,169.95 Pacific Cement Co., Inc.
By:
Jose Cortes, Jr. INSTRUCTIONS HEREIN BEFORE MENTIONED and as to the QUALITY OF
WORKMANSHIP OF THE ITEMS ORDERED or as to any other questions, claim,
President"[3] right or thing whatsoever, but qualified to IN ANY WAY ARISING OR RELATING TO
THE SUPPLY ORDER/CONTRACT, DESIGN, DRAWING, SPECIFICATION, etc.,
repeating the enumeration in the opening sentence of the clause.
Without responding to the above communication, the foreign court refused to
admit the private respondents objections for failure to pay the required filing fees, and
thereafter issued an Order on February 7, 1990, to wit: The court is inclined to go along with the observation of the defendant that the breach,
consisting of the non-delivery of the purchased materials, should have been properly
ORDER litigated before a court of law, pursuant to Clause No. 15 of the Contract/Supply
Order, herein quoted, to wit:
Since objections filed by defendant have been rejected through Misc. Suit No. 5 on
7.2.90, therefore, award should be made Rule of the Court. JURISDICTION

ORDER All questions, disputes and differences, arising under out of or in connection with this
supply order, shall be subject to the EXCLUSIVE JURISDICTION OF THE COURT,
Award dated 23.7.88, Paper No. 3/B-1 is made Rule of the Court. On the basis of within the local limits of whose jurisdiction and the place from which this supply order
conditions of award decree is passed. Award Paper No. 3/B-1 shall be a part of the is situated.[6]
decree. The plaintiff shall also be entitled to get from defendant (US$ 899, 603.77
(US$ Eight Lakhs ninety nine thousand six hundred and three point seventy seven The RTC characterized the erroneous submission of the dispute to the arbitrator as a
only) alongwith 9% interest per annum till the last date of realisation. [4] mistake of law or fact amounting to want of jurisdiction. Consequently, the
proceedings had before the arbitrator were null and void and the foreign court had
Despite notice sent to the private respondent of the foregoing order and several therefore, adopted no legal award which could be the source of an enforceable
demands by the petitioner for compliance therewith, the private respondent refused to right.[7]
pay the amount adjudged by the foreign court as owing to the petitioner. Accordingly, The petitioner then appealed to the respondent Court of Appeals which affirmed
the petitioner filed a complaint with Branch 30 of the Regional Trial Court (RTC) of the dismissal of the complaint. In its decision, the appellate court concurred with the
Surigao City for the enforcement of the aforementioned judgment of the foreign court. RTCs ruling that the arbitrator did not have jurisdiction over the dispute between the
The private respondent moved to dismiss the complaint on the following grounds: (1) parties, thus, the foreign court could not validly adopt the arbitrators award. In
plaintiffs lack of legal capacity to sue; (2) lack of cause of action; and (3) plaintiffs addition, the appellate court observed that the full text of the judgment of the foreign
claim or demand has been waived, abandoned, or otherwise extinguished. The court contains the dispositive portion only and indicates no findings of fact and law as
petitioner filed its opposition to the said motion to dismiss, and the private respondent, basis for the award. Hence, the said judgment cannot be enforced by any Philippine
its rejoinder thereto. On January 3, 1992, the RTC issued an order upholding the court as it would violate the constitutional provision that no decision shall be rendered
petitioners legal capacity to sue, albeit dismissing the complaint for lack of a valid by any court without expressing therein clearly and distinctly the facts and the law on
cause of action. The RTC held that the rule prohibiting foreign corporations which it is based.[8] The appellate court ruled further that the dismissal of the private
transacting business in the Philippines without a license from maintaining a suit in respondents objections for non-payment of the required legal fees, without the foreign
Philippine courts admits of an exception, that is, when the foreign corporation is suing court first replying to the private respondents query as to the amount of legal fees to
on an isolated transaction as in this case. [5] Anent the issue of the sufficiency of the be paid, constituted want of notice or violation of due process. Lastly, it pointed out
petitioners cause of action, however, the RTC found the referral of the dispute that the arbitration proceeding was defective because the arbitrator was appointed
between the parties to the arbitrator under Clause 16 of their contract erroneous. solely by the petitioner, and the fact that the arbitrator was a former employee of the
According to the RTC, latter gives rise to a presumed bias on his part in favor of the petitioner.[9]

[a] perusal of the above-quoted clause (Clause 16) readily shows that the matter A subsequent motion for reconsideration by the petitioner of the appellate courts
covered by its terms is limited to ALL QUESTIONS AND DISPUTES, RELATING TO decision was denied, thus, this petition for review on certiorari citing the following as
THE MEANING OF THE SPECIFICATION, DESIGNS, DRAWINGS AND grounds in support thereof:
RESPONDENT COURT OF APPEALS GRAVELY ERRED IN AFFIRMING specification, instruction or these conditions x x x. The absence of a comma between
THE LOWER COURTS ORDER OF DISMISSAL SINCE: the words supply order/contract and design indicates that the former cannot be taken
separately but should be viewed in conjunction with the words design, drawing,
A. THE NON-DELIVERY OF THE CARGO WAS A MATTER PROPERLY specification, instruction or these conditions. It is thus clear that to fall within the
COGNIZABLE BY THE PROVISIONS OF CLAUSE 16 OF THE CONTRACT; purview of this phrase, the claim, right or thing whatsoever must arise out of or relate
to the design, drawing, specification, or instruction of the supply order/contract. The
B. THE JUDGMENT OF THE CIVIL COURT OF DEHRADUN, INDIA WAS AN petitioner also insists that the non-delivery of the cargo is not only covered by the
AFFIRMATION OF THE FACTUAL AND LEGAL FINDINGS OF THE foregoing phrase but also by the phrase, x x x or otherwise concerning the materials
ARBITRATOR AND THEREFORE ENFORCEABLE IN THIS JURISDICTION; or the execution or failure to execute the same during the stipulated/extended period
or after completion/abandonment thereof x x x.
C. EVIDENCE MUST BE RECEIVED TO REPEL THE EFFECT OF A
PRESUMPTIVE RIGHT UNDER A FOREIGN JUDGMENT.[10] The doctrine of noscitur a sociis, although a rule in the construction of statutes,
is equally applicable in the ascertainment of the meaning and scope of vague
The threshold issue is whether or not the arbitrator had jurisdiction over the contractual stipulations, such as the aforementioned phrase. According to the
dispute between the petitioner and the private respondent under Clause 16 of the maxim noscitur a sociis, where a particular word or phrase is ambiguous in itself or is
contract. To reiterate, Clause 16 provides as follows: equally susceptible of various meanings, its correct construction may be made clear
and specific by considering the company of the words in which it is found or with
Except where otherwise provided in the supply order/contract all questions and which it is associated, or stated differently, its obscurity or doubt may be reviewed by
disputes, relating to the meaning of the specification designs, drawings and reference to associated words.[13] A close examination of Clause 16 reveals that it
instructions herein before mentioned and as to quality of workmanship of the items covers three matters which may be submitted to arbitration namely,
ordered or as to any other question, claim, right or thing whatsoever, in any way
arising out of or relating to the supply order/contract design, drawing, specification, (1) all questions and disputes, relating to the meaning of the specification
instruction or these conditions or otherwise concerning the materials or the execution designs, drawings and instructions herein before mentioned and as to
or failure to execute the same during stipulated/extended period or after the quality of workmanship of the items ordered; or
completion/abandonment thereof shall be referred to the sole arbitration of the (2) any other question, claim, right or thing whatsoever, in any way arising
persons appointed by Member of the Commission at the time of dispute. It will be no out of or relating to the supply order/contract design, drawing,
objection to any such appointment that the arbitrator so appointed is a Commission specification, instruction or these conditions; or
employer (sic) that he had to deal with the matter to which the supply or contract
relates and that in the course of his duties as Commissions employee he had (3) otherwise concerning the materials or the execution or failure to
expressed views on all or any of the matter in dispute or difference. [11] execute the same during stipulated/extended period or after the
completion/abandonment thereof.
The dispute between the parties had its origin in the non-delivery of the 4,300 The first and second categories unmistakably refer to questions and disputes
metric tons of oil well cement to the petitioner. The primary question that may be relating to the design, drawing, instructions, specifications or quality of the materials
posed, therefore, is whether or not the non-delivery of the said cargo is a proper of the supply/order contract. In the third category, the clause, execution or failure to
subject for arbitration under the above-quoted Clause 16. The petitioner contends that execute the same, may be read as execution or failure to execute the supply
the same was a matter within the purview of Clause 16, particularly the phrase, x x order/contract. But in accordance with the doctrine of noscitur a sociis, this reference
x or as to any other questions, claim, right or thing whatsoever, in any way arising or to the supply order/contract must be construed in the light of the preceding words with
relating to the supply order/contract, design, drawing, specification, instruction x x which it is associated, meaning to say, as being limited only to the design, drawing,
x.[12] It is argued that the foregoing phrase allows considerable latitude so as to instructions, specifications or quality of the materials of the supply order/contract. The
include non-delivery of the cargo which was a claim, right or thing relating to the non-delivery of the oil well cement is definitely not in the nature of a dispute arising
supply order/contract. The contention is bereft of merit. First of all, the petitioner has from the failure to execute the supply order/contract design, drawing, instructions,
misquoted the said phrase, shrewdly inserting a comma between the words supply specifications or quality of the materials. That Clause 16 should pertain only to
order/contract and design where none actually exists. An accurate reproduction of the matters involving the technical aspects of the contract is but a logical inference
phrase reads, x x x or as to any other question, claim, right or thing whatsoever, in considering that the underlying purpose of a referral to arbitration is for such technical
any way arising out of or relating to the supply order/contract design, drawing,
matters to be deliberated upon by a person possessed with the required skill and order/contract x x x, thus indicating that the jurisdiction of the arbitrator is not all
expertise which may be otherwise absent in the regular courts. encompassing, and admits of exceptions as may be provided elsewhere in the supply
order/contract. We believe that the correct interpretation to give effect to both
This Court agrees with the appellate court in its ruling that the non-delivery of stipulations in the contract is for Clause 16 to be confined to all claims or disputes
the oil well cement is a matter properly cognizable by the regular courts as stipulated arising from or relating to the design, drawing, instructions, specifications or quality of
by the parties in Clause 15 of their contract: the materials of the supply order/contract, and for Clause 15 to cover all other claims
or disputes.
All questions, disputes and differences, arising under out of or in connection with this
supply order, shall be subject to the exclusive jurisdiction of the court, within the local The petitioner then asseverates that granting, for the sake of argument, that the
limits of whose jurisdiction and the place from which this supply order is situated. [14] non-delivery of the oil well cement is not a proper subject for arbitration, the failure of
the replacement cement to conform to the specifications of the contract is a matter
clearly falling within the ambit of Clause 16. In this contention, we find merit. When
The following fundamental principles in the interpretation of contracts and other the 4,300 metric tons of oil well cement were not delivered to the petitioner, an
instruments served as our guide in arriving at the foregoing conclusion: agreement was forged between the latter and the private respondent that Class G
cement would be delivered to the petitioner as replacement. Upon inspection,
"ART. 1373. If some stipulation of any contract should admit of several meanings, it however, the replacement cement was rejected as it did not conform to the
shall be understood as bearing that import which is most adequate to render it specifications of the contract. Only after this latter circumstance was the matter
effectual."[15] brought before the arbitrator. Undoubtedly, what was referred to arbitration was no
longer the mere non-delivery of the cargo at the first instance but also the failure of
ART. 1374. The various stipulations of a contract shall be interpreted together, the replacement cargo to conform to the specifications of the contract, a matter clearly
attributing to the doubtful ones that sense which may result from all of them taken within the coverage of Clause 16.
jointly.[16] The private respondent posits that it was under no legal obligation to make
replacement and that it undertook the latter only in the spirit of liberality and to foster
Sec. 11. Instrument construed so as to give effect to all provisions. In the construction good business relationship.[20] Hence, the undertaking to deliver the replacement
of an instrument, where there are several provisions or particulars, such a cement and its subsequent failure to conform to specifications are not anymore
construction is, if possible, to be adopted as will give effect to all. [17] subject of the supply order/contract or any of the provisions thereof. We disagree.
As per Clause 7 of the supply order/contract, the private respondent undertook
Thus, this Court has held that as in statutes, the provisions of a contract should to deliver the 4,300 metric tons of oil well cement at BOMBAY (INDIA) 2181 MT and
not be read in isolation from the rest of the instrument but, on the contrary, interpreted CALCUTTA 2119 MT.[21] The failure of the private respondent to deliver the cargo to
in the light of the other related provisions. [18] The whole and every part of a contract the designated places remains undisputed. Likewise, the fact that the petitioner had
must be considered in fixing the meaning of any of its parts and in order to produce a already paid for the cost of the cement is not contested by the private respondent.
harmonious whole. Equally applicable is the canon of construction that in interpreting The private respondent claims, however, that it never benefited from the transaction
a statute (or a contract as in this case), care should be taken that every part thereof as it was not able to recover the cargo that was unloaded at the port of
be given effect, on the theory that it was enacted as an integrated measure and not Bangkok.[22] First of all, whether or not the private respondent was able to recover the
as a hodge-podge of conflicting provisions. The rule is that a construction that would cargo is immaterial to its subsisting duty to make good its promise to deliver the cargo
render a provision inoperative should be avoided; instead, apparently inconsistent at the stipulated place of delivery. Secondly, we find it difficult to believe this
provisions should be reconciled whenever possible as parts of a coordinated and representation. In its Memorandum filed before this Court, the private respondent
harmonious whole.[19] asserted that the Civil Court of Bangkok had already ruled that the non-delivery of the
The petitioners interpretation that Clause 16 is of such latitude as to contemplate cargo was due solely to the fault of the carrier. [23] It is, therefore, but logical to assume
even the non-delivery of the oil well cement would in effect render Clause 15 a mere that the necessary consequence of this finding is the eventual recovery by the private
superfluity. A perusal of Clause 16 shows that the parties did not intend arbitration to respondent of the cargo or the value thereof. What inspires credulity is not that the
be the sole means of settling disputes. This is manifest from Clause 16 itself which is replacement was done in the spirit of liberality but that it was undertaken precisely
prefixed with the proviso, Except where otherwise provided in the supply because of the private respondents recognition of its duty to do so under the supply
order/contract, Clause 16 of which remains in force and effect until the full execution This Court had occasion to make a similar pronouncement in the earlier case
thereof. of Romero v. Court of Appeals,[28] where the assailed decision of the Court of Appeals
adopted the findings and disposition of the Court of Agrarian Relations in this wise:
We now go to the issue of whether or not the judgment of the foreign court is
enforceable in this jurisdiction in view of the private respondents allegation that it is
bereft of any statement of facts and law upon which the award in favor of the We have, therefore, carefully reviewed the evidence and made a re-assessment of
petitioner was based. The pertinent portion of the judgment of the foreign court reads: the same, and We are persuaded, nay compelled, to affirm the correctness of the trial
courts factual findings and the soundness of its conclusion. For judicial convenience
and expediency, therefore, We hereby adopt by way of reference, the findings of facts
ORDER and conclusions of the court a quo spread in its decision, as integral part of this Our
decision.[29] (Underscoring supplied)
Award dated 23.7.88, Paper No. 3/B-1 is made Rule of the Court. On the basis of
conditions of award decree is passed. Award Paper No. 3/B-1 shall be a part of the Hence, even in this jurisdiction, incorporation by reference is allowed if only to avoid
decree. The plaintiff shall also be entitled to get from defendant ( US$ 899, 603.77 the cumbersome reproduction of the decision of the lower courts, or portions thereof,
(US$ Eight Lakhs ninety nine thousand six hundred and three point seventy seven in the decision of the higher court.[30] This is particularly true when the decision sought
only) alongwith 9% interest per annum till the last date of realisation.[24] to be incorporated is a lengthy and thorough discussion of the facts and conclusions
arrived at, as in this case, where Award Paper No. 3/B-1 consists of eighteen (18)
As specified in the order of the Civil Judge of Dehra Dun, Award Paper No. 3/B- single spaced pages.
1 shall be a part of the decree. This is a categorical declaration that the foreign court
adopted the findings of facts and law of the arbitrator as contained in the latters Furthermore, the recognition to be accorded a foreign judgment is not
Award Paper. Award Paper No. 3/B-1, contains an exhaustive discussion of the necessarily affected by the fact that the procedure in the courts of the country in
respective claims and defenses of the parties, and the arbitrators evaluation of the which such judgment was rendered differs from that of the courts of the country in
same. Inasmuch as the foregoing is deemed to have been incorporated into the which the judgment is relied on.[31] This Court has held that matters of remedy and
foreign courts judgment the appellate court was in error when it described the latter to procedure are governed by the lex fori or the internal law of the forum.[32] Thus, if
be a simplistic decision containing literally, only the dispositive portion.[25] under the procedural rules of the Civil Court of Dehra Dun, India, a valid judgment
may be rendered by adopting the arbitrators findings, then the same must be
The constitutional mandate that no decision shall be rendered by any court accorded respect. In the same vein, if the procedure in the foreign court mandates
without expressing therein clearly and distinctly the facts and the law on which it is that an Order of the Court becomes final and executory upon failure to pay the
based does not preclude the validity of memorandum decisions which adopt by necessary docket fees, then the courts in this jurisdiction cannot invalidate the order
reference the findings of fact and conclusions of law contained in the decisions of of the foreign court simply because our rules provide otherwise.
inferior tribunals. In Francisco v. Permskul,[26] this Court held that the following
memorandum decision of the Regional Trial Court of Makati did not transgress the The private respondent claims that its right to due process had been blatantly
requirements of Section 14, Article VIII of the Constitution: violated, first by reason of the fact that the foreign court never answered its queries as
to the amount of docket fees to be paid then refused to admit its objections for failure
to pay the same, and second, because of the presumed bias on the part of the
MEMORANDUM DECISION arbitrator who was a former employee of the petitioner.

After a careful perusal, evaluation and study of the records of this case, this Court Time and again this Court has held that the essence of due process is to be
hereby adopts by reference the findings of fact and conclusions of law contained in found in the reasonable opportunity to be heard and submit any evidence one may
the decision of the Metropolitan Trial Court of Makati, Metro Manila, Branch 63 and have in support of ones defense[33] or stated otherwise, what is repugnant to due
finds that there is no cogent reason to disturb the same. process is the denial of opportunity to be heard. [34] Thus, there is no violation of due
process even if no hearing was conducted, where the party was given a chance to
explain his side of the controversy and he waived his right to do so. [35]
WHEREFORE, judgment appealed from is hereby affirmed in toto.[27] (Underscoring
supplied.) In the instant case, the private respondent does not deny the fact that it was
notified by the foreign court to file its objections to the petition, and subsequently, to
pay legal fees in order for its objections to be given consideration. Instead of paying Consequently, the party attacking a foreign judgment, the private respondent herein,
the legal fees, however, the private respondent sent a communication to the foreign had the burden of overcoming the presumption of its validity which it failed to do in the
court inquiring about the correct amount of fees to be paid. On the pretext that it was instant case.
yet awaiting the foreign courts reply, almost a year passed without the private
respondent paying the legal fees. Thus, on February 2, 1990, the foreign court The foreign judgment being valid, there is nothing else left to be done than to
rejected the objections of the private respondent and proceeded to adjudicate upon order its enforcement, despite the fact that the petitioner merely prays for the remand
the petitioners claims. We cannot subscribe to the private respondents claim that the of the case to the RTC for further proceedings. As this Court has ruled on the validity
foreign court violated its right to due process when it failed to reply to its queries nor and enforceability of the said foreign judgment in this jurisdiction, further proceedings
when the latter rejected its objections for a clearly meritorious ground. The private in the RTC for the reception of evidence to prove otherwise are no longer necessary.
respondent was afforded sufficient opportunity to be heard. It was not incumbent upon WHEREFORE, the instant petition is GRANTED, and the assailed decision of
the foreign court to reply to the private respondents written communication. On the the Court of Appeals sustaining the trial courts dismissal of the OIL AND NATURAL
contrary, a genuine concern for its cause should have prompted the private GAS COMMISSIONs complaint in Civil Case No. 4006 before Branch 30 of the RTC
respondent to ascertain with all due diligence the correct amount of legal fees to be of Surigao City is REVERSED, and another in its stead is hereby rendered
paid. The private respondent did not act with prudence and diligence thus its plea that ORDERING private respondent PACIFIC CEMENT COMPANY, INC. to pay to
they were not accorded the right to procedural due process cannot elicit either petitioner the amounts adjudged in the foreign judgment subject of said case.
approval or sympathy from this Court.[36]
SO ORDERED.
The private respondent bewails the presumed bias on the part of the arbitrator
who was a former employee of the petitioner. This point deserves scant consideration
in view of the following stipulation in the contract:
x x x. It will be no objection to any such appointment that the arbitrator so
appointed is a Commission employer (sic) that he had to deal with the matter to which FIESTA WORLD MALL CORPORATION, G.R. NO. 152471
the supply or contract relates and that in the course of his duties as Commissions Petitioner,
employee he had expressed views on all or any of the matter in dispute or Present:
difference.[37] (Underscoring supplied.) - versus -
PUNO, J., Chairperson,
Finally, we reiterate hereunder our pronouncement in the case of Northwest SANDOVAL-GUTIERREZ,
Orient Airlines, Inc. v. Court of Appeals[38] that: CORONA,
*AZCUNA, and
LINBERG PHILIPPINES, INC.,
A foreign judgment is presumed to be valid and binding in the country from which it Respondent. GARCIA, JJ.
comes, until the contrary is shown. It is also proper to presume the regularity of the
proceedings and the giving of due notice therein.
Promulgated:
Under Section 50, Rule 39 of the Rules of Court, a judgment in an action in personam
August 18, 2006
of a tribunal of a foreign country having jurisdiction to pronounce the same is
presumptive evidence of a right as between the parties and their successors-in-
interest by a subsequent title. The judgment may, however, be assailed by evidence
of want of jurisdiction, want of notice to the party, collusion, fraud, or clear mistake of
x---------------------------------------------------------------------------------------------x
law or fact. Also, under Section 3 of Rule 131, a court, whether of the Philippines or
elsewhere, enjoys the presumption that it was acting in the lawful exercise of
jurisdiction and has regularly performed its official duty.[39]
DECISION

SANDOVAL-GUTIERREZ, J.:
BER 0.6426 + 0.3224 Pn + 1.345 Fn
For our resolution is the instant Petition for Review on Certiorari[1] assailing 26.40 4.00
the Decision[2] dated December 12, 2001 and Resolution[3] dated February 28, 2002 WHERE:
rendered by the Court of Appeals in CA-G.R. SP No. 63671, entitled Fiesta World
Mall Corporation, petitioner, versus Hon. Florito S. Macalino, Presiding Judge Pn is defined as the average of the Bangko Sentral ng
of the Regional Trial Court (RTC), Branch 267, Pasig City, and Linberg Philippines, Pilipinas published dealing rates for thirty
Inc., respondents. (30) trading days immediately prior to the
new billing rate.
The facts of this case are:
Fn Weighted average of fuel price per liter based on the
Fiesta World Mall Corporation, petitioner, owns and operates Fiesta World average of the last three (3) purchases
Mall located at Barangay Maraouy, Lipa City; while Linberg Philippines, made by LINBERG as evidenced by
Inc., respondent, is a corporation that builds and operates power plants. purchase invoices.
On January 19, 2000, respondent filed with the Regional Trial Court (RTC),
Branch 267, Pasig City, a Complaint for Sum of Money against petitioner, docketed ED Energy delivered in kw-hrs per meter reading.
as Civil Case No. 67755. The complaint alleges that on November 12, 1997,petitioner
and respondent executed a build-own-operate agreement, entitled Contract
Agreement for Power Supply Services, 3.8 MW Base Load Power Plant [4] (the 3. Minimum Energy Off-Take
Contract). Under this Contract, respondent will construct, at its own cost, and operate
as owner a power plant, and to supply petitioner power/electricity at its shopping mall The energy fees payable to LINBERG shall be on the basis of
in Lipa City. Petitioner, on the other hand, will pay respondent energy fees to be actual KWH generated by the plant. However, if the actual
computed in accordance with the Seventh Schedule of the Contract, the pertinent KWH generated is less than the minimum energy off-take
portions of which provide: level, the calculation of the energy fees shall be made as if
2.1 x x x LINBERG has generated the minimum energy off-take
level of 988,888 KW-HR per month.
E1 988,888 kw-hr x BER
E2 (ED-988,888) x BER
The complaint further alleges that respondent constructed the power plant
Where: in Lipa City at a cost of about P130,000,000.00. In November 1997, the power plant
became operational and started supplying power/electricity to petitioners shopping
E1 & E2 Energy fees in pesos for the billing mall in Lipa City. In December 1997, respondent started billing petitioner. As of May
period. Where E1 is based on the 21, 1999, petitioners unpaid obligation amounted to P15,241,747.58, exclusive of
minimum energy off-take of 988,888 kw- interest. However, petitioner questioned the said amount and refused to pay despite
hrs. per month and E2 is based on the respondents repeated demands.
actual meter reading less the minimum
off-take. In its Answer with Compulsory Counterclaim, petitioner specifically denied
the allegations in the complaint, claiming that respondent failed to fulfill its obligations
BER Base energy rate at Ps 2.30/Kw-Hr billing rate based under the Contract by failing to supply all its power/fuel needs. From November 10,
on the exchange rate of Ps 26.20 to the 1998 until May 21, 1999, petitioner personally shouldered the cost of fuel. Petitioner
US dollar, and with fuel oil to be also disputed the amount of energy fees specified in the billings made by
supplied by LINBERG at its own respondent because the latter failed to monitor, measure, and record the
cost. The base energy rate is subject to quantities of electricity delivered by taking photographs of the electricity meter
exchange rate adjustment accordingly to reading prior to the issuance of its invoices and billings, also in violation of the
the formula as follows: Contract.[5] Moreover, in the computation of the electrical billings, the minimum off-
take of energy (E2) was based solely on the projected consumption as computed interpretation of any of the provisions hereto, they shall
by endeavor to meet together in an effort to resolve such dispute
respondent. However, based on petitioners actual experience, it could not consume by discussion between them but failing such resolution the
the energy pursuant to the minimum off-take even if it kept open all its lights Chief Executives of LINBERG and FIESTA WORLD shall meet
and operated all its machinery and equipment for twenty-four hours a day for a to resolve such dispute or difference and the joint decision of
month. This fact was admitted by respondent. While both parties had discussions such shall be binding upon the parties hereto, and in the event that
on the questioned billings, however, there were no earnest efforts to resolve the a settlement of any such dispute or difference is not reached,
differences in accordance with the arbitration clause provided for in the Contract. then the provisions of Article XXI shall apply.

Finally, as a special affirmative defense in its answer, petitioner alleged that Article XXI, referred to in paragraph 17.2 above, reads:
respondents filing of the complaint is premature and should be dismissed on the
ground of non-compliance with paragraph 7.4 of the Contract which provides:
7.4 Disputes ARTICLE XXI
If FIESTA WORLD disputes the amount specified by any
invoice, it shall pay the undisputed amount on or before such JURISDICTION
date(s), and the disputed amount shall be resolved by
arbitration of three (3) persons, one (1) by mutual choice, while The parties hereto submit to the exclusive jurisdiction of the proper
the other two (2) to be each chosen by the parties courts of Pasig City, Republic of the Philippines for the hearing
themselves, within fourteen (14) days after the due date for such and determination of any action or proceeding arising out of or
invoice and all or any part of the disputed amount paid to LINBERG in connection with this Agreement.
shall be paid together with interest pursuant to Article XXV from the
due date of the invoice. It is agreed, however, that both parties must In its Order dated October 3, 2000, the trial
resolve the disputes within thirty (30) days, otherwise any delay in court denied petitioners motion for lack of merit.
payment resulting to loss to LINBERG when converted to $US as a
result of depreciation of the Pesos shall be for the account of Petitioner then filed a Motion for Reconsideration but it was denied in an
FIESTA WORLD. Corollarily, in case of erroneous billings, however, Order dated January 11, 2001.
LINBERG shall be liable to pay FIESTA WORLD for the cost of
such deterioration, plus interest computed pursuant to Art. XXV Dissatisfied, petitioner elevated the matter to the Court of Appeals via a
from the date FIESTA WORLD paid for the erroneous Petition for Certiorari, docketed as CA-G.R. SP No. 63671. On December 12,
billing. (Underscoring supplied) 2001, the appellate court rendered its Decision dismissing the petition and affirming
the challenged Orders of the trial court.

Thereafter, petitioner filed a Motion to Set Case for Preliminary Hearing on Petitioners Motion for Reconsideration of the above Decision was likewise
the ground that respondent violated the arbitration clause provided in the Contract, denied by the appellate court in its Resolution[6] dated February 28, 2002.
thereby rendering its cause of action premature.
Hence, the instant Petition for Review on Certiorari.
This was opposed by respondent, claiming that paragraph 7.4 of the
Contract on arbitration is not the provision applicable to this case; and that since the The sole issue for our resolution is whether the filing with the trial court
parties failed to settle their dispute, then respondent may resort to court action of respondents complaint is premature.
pursuant toparagraph 17.2 of the same Contract which provides: Paragraph 7.4 of the Contract, quoted earlier, mandates
that should petitioner dispute any amount of energy fees in the invoice
17.2 Amicable Settlement and billings made by respondent, the same shall be resolved by arbitration of three
The parties hereto agree that in the event there is any dispute or (3) persons, one (1) by mutual choice, while the other two (2) to be each chosen
difference between them arising out of this Agreement or in the by the parties themselves. The parties, in incorporating such agreement in their
Contract, expressly intended that the said matter in dispute must first be resolved by international relations, is recognized worldwide. To brush aside a
an arbitration panel before it reaches the court. They made such contractual agreement calling for arbitration in case of disagreement
arbitration mandatory. between the parties would therefore be a step backward.

It is clear from the records that petitioner disputed the amount of energy fees In this connection, since respondent has already filed a complaint with the trial court
demanded by respondent. However, respondent, without prior recourse to arbitration without prior recourse to arbitration, the proper procedure to enable an arbitration
as required in the Contract, filed directly with the trial court its complaint, thus violating panel to resolve the parties dispute pursuant to their Contract is for the trial court to
the arbitration clause in the Contract. stay the proceedings.[11] After the arbitration proceeding has been pursued and
completed, then the trial court may confirm the award made by the arbitration panel. [12]
It bears stressing that such arbitration agreement is the law between the In sum, we hold that the Court of Appeals erred in disregarding the arbitration clause
parties. Since that agreement is binding between them, they are expected to abide by in the parties Contract.
it in good faith.[7] And because it covers the dispute between them in the present case,
either of them may compel the other to arbitrate.[8] Thus, it is well within petitioners WHEREFORE, we GRANT the instant petition. The assailed Decision and
right to demand recourse to arbitration. Resolution of the Court of Appeals in CA-G.R. SP No. 63671 are REVERSED. The
parties are ordered to submit their controversy to the arbitration panel pursuant to
We cannot agree with respondent that it can directly seek judicial recourse by paragraph 7.4 of the Contract. The Regional Trial Court, Branch 267, Pasig City is
filing an action against petitioner simply because both failed to settle their directed to suspend the proceedings in Civil Case No. 67755 until after the Arbitration
differences amicably. Suffice it to state that there is nothing in the Panel shall have resolved the controversy and submitted its report to the
Contract providing that the parties may dispense with the arbitration trial court. Costs against respondent.
clause. Article XXI on jurisdiction cited by respondent, i.e., that the parties hereto
submit to the exclusive jurisdiction of the proper courts of Pasig City merely
provides for the venue of any action arising out of or in connection with the SO ORDERED.
stipulations of the parties in the Contract. SOLEDAD BENGSON VS MARIANO CHAN
GR. No. L-27283 July 29 1977
Moreover, we note that the computation of the energy fees disputed by
petitioner also involves technical matters that are better left to an arbitration FACTS:
panel who has expertise in those areas. Alternative dispute resolution methods Bengson entered into a contract for the construction of a six storey building with
or ADRs like arbitration, mediation, negotiation and conciliation are encouraged by Chan as the contractor. Such contract includes an arbitration clause. Later, Bengson
this Court. By enabling the parties to resolve their disputes amicably, they provide filed for damages against Chan for violation of the contract by failing to construct the
solutions that are less time-consuming, less tedious, less confrontational, and more 1st and 2nd stories within the stipulated time. Chan filed for corresponding
productive of goodwill and lasting relationships.[9] To brush aside such agreement counterclaims and alleged failure of appellant to state cause of action as the contract
providing for arbitration in case of disputes between the parties would be a step stipulates that a controversy over it must first be submitted for arbitration. The trial
backward. As we held in BF Corporation v. Court of Appeals,[10] court dismissed the complaint. Hence the appeal.

It should be noted that in this jurisdiction, arbitration has ISSUES:


been held valid and constitutional. Even before the approval 1.Whether or not appellant has a cause of action.
on June 19, 1953 of Republic Act No. 876 (The Arbitration Law), 2.If the answer to the latter is in the affirmative, whether or not arbitration may be
this Court has countenanced the settlement of disputes through resorted to during the pendency of the case.
arbitration (Puromines, Inc. v. Court of Appeals, G.R. No. 91228, HELD:
March 22, 1993, 220 SCRA 281-290). Republic Act No. 876 was 1.Appellant has a cause of action. The cause of action arose from the breach of the
adopted to supplement the New Civil Codes provisions on construction contract caused by a delay on the construction. However, since the
arbitration (Chung Fu Industries Phils., Inc. v. Court of contract includes an arbitration clause, duly agreed by both parties, appellant should
Appeals, G.R. No. 92683, February 25, 1992, 206 SCRA 545, have resorted first to arbitration before filing a case in court.
551). Its potentials as one of the alternative dispute resolution
methods that are now rightfully vaunted as the wave of the future in
2.Arbitration may be resorted to during the pendency of the case. Section 7 of the After trial on the merits, the RTC[14] ruled that the take-over of some work items by
Arbitration Law states, respondent was not equivalent to a termination, but a mere modification, of the Subcontract. The
Section 7. Stay of civil action. If any suit or proceeding be brought upon an issue latter was ordered to give full payment for the work completed by petitioner.
Ruling of the Court of Appeals
arising out of an agreement providing for an arbitration thereof, the court in which
On appeal, the CA reversed the RTC and ordered the referral of the case to
such suit or proceeding is pending upon being satisfied that the issue involved in such arbitration. The appellate court held as arbitrable the issue of whether respondents take-over of
suit is referable to arbitration, SHALL STAY THE ACTION OR PROCEEDING UNTIL some work items had been intended to be a termination of the original contract under Letter K of
AN ARBITRATION HAS BEEN HAD IN ACCORDANCE WITH THE TERMS OF THE the Subcontract. It ruled likewise on two other issues: whether petitioner was liable under the
AGREEMENT PROVIDED THAT THE APPLICANT FOR THE STAY IS NOT IN warranty clause of the Agreement, and whether it should reimburse respondent for the work the
DEFAULT IN PROCEEDING WITH SUCH ARBITRATION. latter had taken over.[15]
Therefore, the proceedings of the case are to be suspended until after the designated Hence, this Petition.[16]
time ordered by the court for arbitration expires without definitely settling the dispute. The Issues
In its Memorandum, petitioner raises the following issues for the Courts consideration:
[G.R. No. 141833. March 26, 2003]
A
LM POWER ENGINEERING CORPORATION, petitioner, vs. CAPITOL INDUSTRIAL
Whether or not there exist[s] a controversy/dispute between petitioner and respondent regarding
CONSTRUCTION GROUPS, INC., respondent.
the interpretation and implementation of the Sub-Contract Agreement dated February 22, 1983
DECISION
that requires prior recourse to voluntary arbitration;
PANGANIBAN, J.: B
Alternative dispute resolution methods or ADRs -- like arbitration, mediation, negotiation In the affirmative, whether or not the requirements provided in Article III [1] of CIAC Arbitration
and conciliation -- are encouraged by the Supreme Court. By enabling parties to resolve their
Rules regarding request for arbitration ha[ve] been complied with[.][17]
disputes amicably, they provide solutions that are less time-consuming, less tedious, less The Courts Ruling
confrontational, and more productive of goodwill and lasting relationships.[1] The Petition is unmeritorious.
The Case
First Issue:
Before us is a Petition for Review on Certiorari[2] under Rule 45 of the Rules of Court, Whether Dispute Is Arbitrable
seeking to set aside the January 28, 2000 Decision of the Court of Appeals [3] (CA) in CA-GR CV Petitioner claims that there is no conflict regarding the interpretation or the implementation
No. 54232. The dispositive portion of the Decision reads as follows:
of the Agreement. Thus, without having to resort to prior arbitration, it is entitled to collect the
WHEREFORE, the judgment appealed from is REVERSED and SET ASIDE. The parties are value of the services it rendered through an ordinary action for the collection of a sum of money
ORDERED to present their dispute to arbitration in accordance with their Sub-contract
from respondent. On the other hand, the latter contends that there is a need for prior arbitration
Agreement. The surety bond posted by [respondent] is [d]ischarged.[4] as provided in the Agreement. This is because there are some disparities between the parties
The Facts
positions regarding the extent of the work done, the amount of advances and billable
On February 22, 1983, Petitioner LM Power Engineering Corporation and Respondent
accomplishments, and the set off of expenses incurred by respondent in its take-over of
Capitol Industrial Construction Groups Inc. entered into a Subcontract Agreement involving petitioners work.
electrical work at the Third Port of Zamboanga.[5] We side with respondent. Essentially, the dispute arose from the parties ncongruent
On April 25, 1985, respondent took over some of the work contracted to
positions on whether certain provisions of their Agreement could be applied to the facts. The
petitioner.[6] Allegedly, the latter had failed to finish it because of its inability to procure instant case involves technical discrepancies that are better left to an arbitral body that has
materials.[7] expertise in those areas. In any event, the inclusion of an arbitration clause in a contract does
Upon completing its task under the Contract, petitioner billed respondent in the amount
not ipso facto divest the courts of jurisdiction to pass upon the findings of arbitral bodies,
of P6,711,813.90.[8] Contesting the accuracy of the amount of advances and billable because the awards are still judicially reviewable under certain conditions. [18]
accomplishments listed by the former, the latter refused to pay. Respondent also took refuge in In the case before us, the Subcontract has the following arbitral clause:
the termination clause of the Agreement.[9] That clause allowed it to set off the cost of the work
6. The Parties hereto agree that any dispute or conflict as regards to interpretation
that petitioner had failed to undertake -- due to termination or take-over -- against the amount it and implementation of this Agreement which cannot be settled between [respondent]
owed the latter. and [petitioner] amicably shall be settled by means of arbitration x x x.[19]
Because of the dispute, petitioner filed with the Regional Trial Court (RTC) of Makati
Clearly, the resolution of the dispute between the parties herein requires a referral to the
(Branch 141) a Complaint[10] for the collection of the amount representing the alleged balance provisions of their Agreement. Within the scope of the arbitration clause are discrepancies as to
due it under the Subcontract. Instead of submitting an Answer, respondent filed a Motion to the amount of advances and billable accomplishments, the application of the provision on
Dismiss,[11] alleging that the Complaint was premature, because there was no prior recourse to
termination, and the consequent set-off of expenses.
arbitration. A review of the factual allegations of the parties reveals that they differ on the following
In its Order[12] dated September 15, 1987, the RTC denied the Motion on the ground that questions: (1) Did a take-over/termination occur? (2) May the expenses incurred by respondent
the dispute did not involve the interpretation or the implementation of the Agreement and was,
in the take-over be set off against the amounts it owed petitioner? (3) How much were the
therefore, not covered by the arbitral clause.[13] advances and billable accomplishments?
The resolution of the foregoing issues lies in the interpretation of the provisions of the All expenses incurred by [respondent], both in foreign and local currencies in
Agreement. According to respondent, the take-over was caused by petitioners delay in connection with the opening of the letters of credit shall be deducted from the
completing the work. Such delay was in violation of the provision in the Agreement as to time Contract Prices.
schedule: xxxxxxxxx
G. TIME SCHEDULE N. OTHER CONDITIONS
[Petitioner] shall adhere strictly to the schedule related to the WORK and complete xxxxxxxxx
the WORK within the period set forth in Annex C hereof. NO time extension shall be 2. All customs duties, import duties, contractors taxes, income taxes, and other
granted by [respondent] to [petitioner] unless a corresponding time extension is taxes that may be required by any government agencies in connection with this
granted by [the Ministry of Public Works and Highways] to the CONSORTIUM.[20] Agreement shall be for the sole account of [petitioner].[23]
Because of the delay, respondent alleges that it took over some of the work contracted to Being an inexpensive, speedy and amicable method of settling disputes,[24] arbitration --
petitioner, pursuant to the following provision in the Agreement: along with mediation, conciliation and negotiation -- is encouraged by the Supreme Court. Aside
K. TERMINATION OF AGREEMENT from unclogging judicial dockets, arbitration also hastens the resolution of disputes, especially of
[Respondent] has the right to terminate and/or take over this Agreement for any of the commercial kind.[25] It is thus regarded as the wave of the future in international civil and
the following causes: commercial disputes.[26] Brushing aside a contractual agreement calling for arbitration between
xxxxxxxxx the parties would be a step backward.[27]
6. If despite previous warnings by [respondent], [petitioner] does not execute Consistent with the above-mentioned policy of encouraging alternative dispute resolution
the WORK in accordance with this Agreement, or persistently or flagrantly methods, courts should liberally construe arbitration clauses. Provided such clause is
neglects to carry out [its] obligations under this Agreement.[21] susceptible of an interpretation that covers the asserted dispute, an order to arbitrate should be
Supposedly, as a result of the take-over, respondent incurred expenses in excess of the granted.[28] Any doubt should be resolved in favor of arbitration.[29]
contracted price. It sought to set off those expenses against the amount claimed by petitioner for Second Issue:
the work the latter accomplished, pursuant to the following provision: Prior Request for Arbitration
If the total direct and indirect cost of completing the remaining part of the WORK exceed the According to petitioner, assuming arguendo that the dispute is arbitrable, the failure to file
sum which would have been payable to [petitioner] had it completed the WORK, the amount of a formal request for arbitration with the Construction Industry Arbitration Commission (CIAC)
such excess [may be] claimed by [respondent] from either of the following: precluded the latter from acquiring jurisdiction over the question. To bolster its position,
1. Any amount due [petitioner] from [respondent] at the time of the termination of this petitioner even cites our ruling in Tesco Services Incorporated v. Vera.[30] We are not persuaded.
Agreement.[22] Section 1 of Article II of the old Rules of Procedure Governing Construction Arbitration
The issue as to the correct amount of petitioners advances and billable accomplishments indeed required the submission of a request for arbitration, as follows:
involves an evaluation of the manner in which the parties completed the work, the extent to SECTION. 1. Submission to Arbitration -- Any party to a construction contract wishing to have
which they did it, and the expenses each of them incurred in connection therewith. Arbitrators recourse to arbitration by the Construction Industry Arbitration Commission (CIAC) shall submit
also need to look into the computation of foreign and local costs of materials, foreign and local its Request for Arbitration in sufficient copies to the Secretariat of the CIAC; PROVIDED, that in
advances, retention fees and letters of credit, and taxes and duties as set forth in the the case of government construction contracts, all administrative remedies available to the
Agreement. These data can be gathered from a review of the Agreement, pertinent portions of parties must have been exhausted within 90 days from the time the dispute arose.
which are reproduced hereunder: Tesco was promulgated by this Court, using the foregoing provision as reference.
C. CONTRACT PRICE AND TERMS OF PAYMENT On the other hand, Section 1 of Article III of the new Rules of Procedure Governing
xxxxxxxxx Construction Arbitration has dispensed with this requirement and recourse to the CIAC may now
All progress payments to be made by [respondent] to [petitioner] shall be subject to be availed of whenever a contract contains a clause for the submission of a future controversy to
a retention sum of ten percent (10%) of the value of the approved quantities. Any arbitration, in this wise:
claims by [respondent] on [petitioner] may be deducted by [respondent] from the SECTION 1. Submission to CIAC Jurisdiction An arbitration clause in a construction contract or
progress payments and/or retained amount. Any excess from the retained amount a submission to arbitration of a construction dispute shall be deemed an agreement to submit an
after deducting [respondents] claims shall be released by [respondent] to [petitioner] existing or future controversy to CIAC jurisdiction, notwithstanding the reference to a different
after the issuance of [the Ministry of Public Works and Highways] of the Certificate of arbitration institution or arbitral body in such contract or submission. When a contract contains a
Completion and final acceptance of the WORK by [the Ministry of Public Works and clause for the submission of a future controversy to arbitration, it is not necessary for the parties
Highways]. to enter into a submission agreement before the claimant may invoke the jurisdiction of CIAC.
xxxxxxxxx The foregoing amendments in the Rules were formalized by CIAC Resolution Nos. 2-91
D. IMPORTED MATERIALS AND EQUIPMENT and 3-93.[31]
[Respondent shall open the letters of credit for the importation of equipment and The difference in the two provisions was clearly explained in China Chang Jiang Energy
materials listed in Annex E hereof after the drawings, brochures, and other technical Corporation (Philippines) v. Rosal Infrastructure Builders et al. [32] (an extended unsigned
data of each items in the list have been formally approved by [the Ministry of Public Resolution) and reiterated in National Irrigation Administration v. Court of Appeals,[33]from which
Works and Highways]. However, petitioner will still be fully responsible for all we quote thus:
imported materials and equipment.
Under the present Rules of Procedure, for a particular construction contract to fall within the The Antecedents
jurisdiction of CIAC, it is merely required that the parties agree to submit the same to voluntary
arbitration Unlike in the original version of Section 1, as applied in the Tesco case, the law as it
now stands does not provide that the parties should agree to submit disputes arising from their
agreement specifically to the CIAC for the latter to acquire jurisdiction over the same. Rather, it On February 19, 1997, this Court ruled that the employees of the respondent
is plain and clear that as long as the parties agree to submit to voluntary arbitration, regardless Toyota Motor Philippines Corporation (TMPC) belonging to the Level 5 positions
of what forum they may choose, their agreement will fall within the jurisdiction of the CIAC, such under its Single Salary Structure set up were supervisory employees. [3] The decision
that, even if they specifically choose another forum, the parties will not be precluded from became final and executory. Thereafter, the respondent put up and implemented its
electing to submit their dispute before the CIAC because this right has been vested upon each Three-Function Salary Structure for its personnel/employees.
party by law, i.e., E.O. No. 1008.[34]
Clearly, there is no more need to file a request with the CIAC in order to vest it with On February 4, 1999, the petitioner Toyota Motor Philippines Corporation
jurisdiction to decide a construction dispute. Workers Association (TMPCWA) filed a petition for certification election in an
The arbitral clause in the Agreement is a commitment on the part of the parties to submit unorganized establishment, particularly for the rank-and-file employees at the Sta.
to arbitration the disputes covered therein. Because that clause is binding, they are expected to Rosa and Bicutan Plants of the respondent TMPC, before the Med-Arbitration Unit of
abide by it in good faith.[35] And because it covers the dispute between the parties in the present
the Department of Labor and Employment, National Capital Region (DOLE-NCR),
case, either of them may compel the other to arbitrate.[36]
Since petitioner has already filed a Complaint with the RTC without prior recourse to arbitration, docketed as NCR-OD-M-9907-017, later redocketed as NCR-OD-M-9902-001. The
the proper procedure to enable the CIAC to decide on the dispute is to request the stay or suspension respondent TMPC opposed the petition on the ground that a case was pending before
of such action, as provided under RA 876 [the Arbitration Law].[37] the Supreme Court between it and another union, the Toyota Motor Philippines
WHEREFORE, the Petition is DENIED and the assailed Decision AFFIRMED. Costs Corporation Labor Union (TMPCLU), whose registration certificate has been
against petitioner. cancelled. It asserted that the petitioners membership is the same as that of the
SO ORDERED. TMPCLU, which sought to represent the same bargaining unit. The respondent TMPC
further asserted that the petition was merely a rehash of its petition, which had been
dismissed on June 18, 1998.
On March 29, 1999, Med-Arbiter Zosima C. Lameyra resolved to dismiss the
[G.R. No. 148924. September 24, 2003] petition.[4] On appeal, the DOLE, thru Undersecretary Rosalinda Dimapilis-Baldoz,
rendered a Decision[5] dated June 25, 1999 reversing the Med-Arbiters decision, and
ordering the conduct of a certification election. The DOLE denied the respondents
motion for reconsideration of the said decision.[6]
TOYOTA MOTOR PHILS. CORPORATION WORKERS ASSOCIATION
The respondent TMPC filed a petition for certiorari under Rule 65 of the Rules of
(TMPCWA), petitioner, vs. COURT OF APPEALS (FOURTH DIVISION)
Court, as amended, with the CA, alleging grave abuse of discretion on the part of the
JUSTICES ROBERTO BARRIOS, RAMON MABUTAS and EDGARDO
Secretary of Labor and Employment (SOLE). However, the CA denied the
CRUZ, and TOYOTA MOTOR PHILS. CORPORATION respondents.
petition.[7] It likewise denied the motion for reconsideration filed by the
respondent.[8] Thus, the June 25, 1999 Decision of the SOLE became final. The
DECISION certification election was set on March 8, 2000.
CALLEJO, SR., J.: During the inclusion and exclusion proceedings before the Med-Arbiter
conducted on February 15, 2000, the respondent submitted a list of 1,110 employees
Before us is a petition for certiorari under Rule 65 of the 1997 Rules of Civil at its Bicutan and Sta. Rosa Plants included in the payroll list. The petitioner,
Procedure filed by Toyota Motor Phils. Corporation Workers Association (TMPCWA) however, questioned the eligibility of the 120 employees in the list, contending that
for the nullification of the June 29, 2001 Resolution [1] of the Court of Appeals, which they were not rank-and-file employees but supervisory employees of the respondent,
granted a writ of preliminary injunction, prayed for by the respondent Toyota Motor on the basis of the decision of this Court in Toyota Motor Phils. Corporation v. Toyota
Philippines Corporation, and the writ of preliminary injunction issued by the CA on Motor Phils. Corporation Labor Union. The respondent, for its part, asserted that the
July 12, 2001.[2] establishment of its Three-Function Salary Structure had already superseded the
decision of this Court, whereby the real supervisors or managers are distinguished
from the rank-and-file employees in terms of the duties/functions of the
employees. Nonetheless, the certification election proceeded as scheduled. During certified as the exclusive bargaining agent of the rank-and-file employees at its Sta.
the certification election, 105 out of the 120 employees whose eligibilities had been Rosa and Bicutan Plants. The respondent further alleged that under the Three-
questioned by the petitioner were able to cast their votes, but these votes were not Function Salary Structure of its personnel which became effective in December 1994,
opened and considered. The results of the election are herein quoted: after the decision of this Court in Toyota Motor Phils. Corp. v. Toyota Motor Phils.
Corp. Labor Union[11] became final and executory, the following were rank-and-file
Bicutan Plant Sta. Rosa Plant Results employees:

The General Staff


Yes Votes 305 198 503

Salary Levels 8 and below for as long as they function as ordinary staff and they have
No votes 302 138 440
no subordinates.

Challenged 91 14 105
Line Employees refers to the factory workers, those who are assigned at the
Votes
manufacturing plants.

Spoiled 4 11 15
Salary Levels 1-4
Ballots

Office Staff
Total Votes Cast 702 361 1,063[9]

Salary Levels 1-6[12]


With 503 affirmative votes and the exclusion of the 105 challenged votes, the
petitioner asserted that it garnered the majority votes of the 943 votes cast (less the
challenged votes); hence, it sought to be declared as the certified bargaining agent of The respondent asserted that out of the 105 challenged voters, at least 103
the respondent at its Sta. Rosa and Bicutan Plants. However, the respondent filed a were members of the General Staff category of Levels 5 to 8 and are rank-and-file
handwritten manifestation on the face of the election results in which it asserted that employees under its Three-Function Salary Structure. The respondent appended to
the petitioner couldnt be certified as having won the election because its vote of 503 its position paper the affidavit of Jose Ma. Aligada, First Vice-President of the General
was 22 votes shy of the majority. It prayed for the opening of the 91 of the 105 Administration Division, as well as the affidavits of eighty-nine of the 105 challenged
challenged votes at the Bicutan Plant to enable the Med-Arbiter to look into and rule votes. The list of the names of the challenged voters was appended to the position
on the qualifications of the said voters and ascertain whether the petitioner indeed paper.
won the election. The manifestation in part reads: After the submission of the petitioners and the respondents respective position
papers, Med-Arbiter Zosima Lameyra issued an Order on May 12, 2000, certifying the
The company through [the] undersigned counsel most respectfully manifest that the petitioner as the exclusive bargaining agent of the rank-and-file employees of Toyota
union cannot be certified as having won in the certification election, because it has in the said plants. She held that the challenged voters were supervisory employees
failed to get the required majority of 50 [%] + 1 votes as there are still 91 valid votes under the Three-Function Salary Structure, thus:
not yet counted, which the company has considered as belonging to bonafide rank-
and-file employees. Hence, the Med-Arbiter has to rule on the opening of said ballots SUPERVISORY employees are those who belong to:
and/or rule on their qualification.[10]

The General Staff


The respondent filed its position paper with the Med-Arbiter on April 25, 2000,
alleging that the 105 challenged votes should have been opened and considered in
the tabulation of the results of the election. It averred that if considered, the outcome Salary Levels 9-10 (Supervisors)
of the election would have been adverse to the petitioner; hence, the latter cannot be Salary Levels 7-8 (Group Heads, if they
function as such, i.e., they are staff with The respondent interposed an appeal from the said order before the DOLE,
subordinates for whom they are responsible alleging that the Med-Arbiter acted with grave abuse of discretion in issuing the
in terms of daily work supervision) same. The respondent asserted that the challenged voters were rank-and-file
employees. The petitioner, on the other hand, insisted that the said employees
Line Employees refers to the factory workers, those who are occupied position Levels 5 and upwards; hence, are supervisory employees, citing
assigned at the manufacturing plants. the ruling of this Court in Toyota Motor Phils. Corporation v. Toyota Motor Corporation
Labor Union.
Salary Levels 9-10 (Foremen) Meanwhile, on June 21, 2000, the employees of the respondent whose votes
Salary Levels 7-8 (Senior Group Chiefs) were challenged filed a petition for declaratory relief with the Arbitration Board of the
Salary Levels 5-6 (Junior Group Chiefs- DOLE, docketed as NLRC-NCR-30-06-02556-00 against the petitioner, praying that:
includes Group Leaders
and Team Leaders) PRAYER

Note: Levels 5-10 are considered supervisors only when their actual WHEREFORE, petitioners respectfully pray that after due consideration, the
functions dictate such categorization. Honorable Office render judgment declaring the petitioners are indeed rank-and-file
employees based on their employment contract, job description, actual duties and
RANK-AND-FILE employees are all other employees, who do not fall responsibilities and affidavits.[15]
under either the Managerial or Supervisory classes, specifically:
There was no appearance for the petitioner. On August 4, 2000, Jimmy Sy and
The General Staff other employees of the respondent who were among the 105 challenged voters filed a
motion to intervene in NCR-OD-M-9902-001 alleging, inter alia, that they had earlier
Salary Levels 8 and below for as long as they function as filed a petition for declaratory relief in NLRC-NCR-30-06-02556-00. On August 7,
ordinary staff and they have no subordinates. 2000, Labor Arbiter Eduardo M. Madriaga rendered a decision granting the petition,
the decretal portion of which reads:
Line Employees refers to the factory workers, those who are
assigned at the manufacturing plants. The Constitution mandates that the State shall accord protection to labor.

Salary Levels 1-4 We are, therefore, constrained to grant the instant petition but only for the sole
purpose that petitioners may exercise all their rights and claim all legal benefits as
rank-and-file workers, as found in the Constitution and the Labor Code.
Office Staff
Otherwise, the rights of workers and their legal benefits may be rendered inutile if
Salary Levels 1-6[13] their status is unresolved.

The decretal portion of the order reads: WHEREFORE, premises considered, the prayer in the Petition is hereby granted.

WHEREFORE, premises considered, judgment is hereby rendered declaring the SO ORDERED.[16]


challenged voters as ineligible and excluding their votes from the totality of the valid
votes cast. Accordingly, TMPCWA is hereby declared to have obtained the majority of
the valid votes cast and is hereby certified as the bargaining agent of the rank-and-file On August 28, 2000, the 105 challenged voters filed a motion in NCR-OD-M-
employees of the company.[14] 9902-001 for the remand of the case to the Med-Arbiter for the opening of the
ballots. They appended to their motion a copy of the order of Labor Arbiter Eduardo
M. Madriaga granting their petition for declaratory relief. On October 19, 2000, the If the petition filed by movants in the NLRC means anything, it is merely intended to
DOLE, thru Undersecretary Rosalinda Dimapilis-Baldoz, issued a Resolution affirming muddle the issue of the appropriate constituency of the bargaining unit which, to
the order of Med-Arbiter Zosima C. Almeyra,[17] holding that (a) since the challenged stress, is within the exclusive jurisdiction of this Office to determine. Quite obviously,
voters were ineligible to vote, there was no need to open the votes of the challenged herein appellant, while ostensibly the respondent in the NLRC case, cannot be said
voters; (b) the respondent should have adduced its evidence on the status of the not to have given its imprimatur on movants to file such case. For movants are, in the
challenged voters as rank-and-file employees during the inclusion-exclusion first place, appellants own witnesses in this case.
proceedings; (c) the respondent had no legal personality to move for the opening of
the challenged voters and delay the proclamation of the winners in the certification This is also an occasion to stress that the NLRC is an attached agency of the
election as the respondent is merely a bystander in certification election; (d) in any Department of Labor and Employment. While the attachment is for program and
event, the respondent failed to prove that the challenged voters were rank-and-file policy coordination only (Article 213, Labor Code), such coordination is nevertheless
employees; (e) the contention of the petitioner that the challenged voters were broad enough to cover common adherence to public policy objectives. The recourse
supervisory employees finds support in the decision of this Court in Toyota Motor taken by movants with the NLRC regrettably amounts to a circumvention of the public
Phils. Corporation v. Toyota Motor Phils. Corporation Labor Union; (f) the affidavits of policy against forum shopping. It also undermines well-established principles on
the challenged voters were barren of probative weight because the same were jurisdiction. And it has led the office of the Labor Arbiter, wittingly or unwittingly, to be
executed only after the certification election; besides, the respondent failed to adduce used as a venue to bring about such undesirable effects.[18]
in evidence the job descriptions of the challenged voters for the year 2000. Anent the
petition of the challenged voters for a declaratory relief in NLRC-NCR (South) Case
No. 30-06-02556-00, the Undersecretary held: The respondent and the challenged voters filed a motion for reconsideration of
the said resolution on the following grounds:
We also take note that a motion to intervene, manifestation and hold proceedings in
abeyance had been filed by Jimmy R. Sy, et. al., dated 4 August 2000. The movants 1. The alleged misapplication of the Supreme Court ruling in Toyota Motor Philippines
are actually among the 105 challenged voters. The reason for the motion is that Corporation v. Toyota Motor Philippines Corporation Labor Union, G.R. No. 121084,
movants, on 21 June 2000, filed a petition for declaratory relief with the Labor Arbiter, 19 February 1997, in view of the distinct factual circumstances obtaining therein vis--
National Labor Relations Commission, docketed as NLRC-NCR (South) Case No. 30- vis the instant case;
06-02556-00, and captioned Jeofre A. De Leon, et al. v. Toyota Motor Philippines
Corporation and Toyota Motor Philippines Corporation Workers Association. The 2. The alleged erroneous finding that the 105 challenged voters are not rank and file
petition prayed for a declaration of whether movants should be considered in view of the alleged substantial and compelling evidence appellant has submitted
supervisory or rank-and-file employees. We also note that movants also filed another vis--vis those submitted by the appellee.
motion, dated 25 August 2000, seeking to remand the case to the Med-Arbiter for the
opening of ballots. Attached to this motion is a decision of Labor Arbiter Edgardo M. 3. The declaration that appellants position is procedurally infirm; and
Madriaga dated 7 August 2000, to whom Case No. 30-06-02556-00 was assigned,
declaring the movants as rank-and-file employees on the reasoning that rights of
workers and their legal benefits may be rendered inutile if their status is unresolved. 4. The alleged misapplication of the bystander rule against the appellant, considering
that this case is one of the recognized exceptions to the rule.[19]
When appellant filed this appeal, the issue it submitted for determination is whether or
not the 105 challenged voters should be classified as rank-and-file or supervisory While the motion was pending, the respondent received on October 27, 2000 a
employees. Indeed, it is within the exclusive jurisdiction of the Med-Arbiter and the letter from the petitioner, through its President Ed Cubelo, and the members of its
Office of the Secretary in certification election proceedings to resolve this issue. When Board of Directors, appending thereto its CBA proposal for the respondents
this case was filed, the Med-Arbiter and later on the Office of the Secretary acquired consideration.[20] On November 7, 2000, the respondent wrote the petitioner that it
jurisdiction over the subject matter of the case and the parties to it, to the exclusion of could not as yet submit any counter-proposal because its motion for reconsideration
all other adjudicating agencies. In so acquiring jurisdiction, the Med-Arbiter and later of the resolution of the SOLE was still pending. On November 15, 2000, Ed Cubelo
on this Office had jurisdiction to resolve the principal issue on the status of the wrote the respondent demanding that the latter submit its counter-proposal to the
workers whose rights, so the Labor Arbiter surmised, may be rendered inutile if their proposed CBA. On November 28, 2000, the respondent reiterated its stand that until
status is unresolved. its motion for reconsideration was resolved, it would not negotiate with the petitioner
on its proposed CBA. On December 8, 2000, the respondent received another letter including their current labor dispute and CBA regulations. For its part, the respondent
from the petitioner giving the respondent a period of ten days within which to reply to filed on March 27, 2001 a petition for certiorari with the CA under Rule 65 of the Rules
its CBA proposal.[21] of Court, as amended, for the nullification of the October 19, 2000 and March 16,
2001 Resolutions of the SOLE, with a plea for the issuance of a preliminary injunction
In the meantime, the hearing of the respondents motion for reconsideration of or at least a temporary restraining order.[26] The respondent alleged, inter alia, that:
the resolution of Undersecretary Rosalinda Dimapilis-Baldoz was set on February 22,
2001. On February 21, 2001, the respondent received a letter from the petitioner that I
its members would absent themselves from work to attend the hearing. [22] The
petitioner informed the respondent that its members were willing to work on their rest PUBLIC RESPONDENT SECRETARY GRAVELY ABUSED HER
day to make up for their absence on February 22, 2001. During the hearing, 22 of the DISCRETION, AMOUNTING TO LACK OR EXCESS OF HER
challenged voters managed to testify on their duties and functions. The other JURISDICTION, IN DECLARING THAT THE CHALLENGED VOTERS,
challenged voters failed to testify because they had to take the place of the EXCEPT FOR EIGHTEEN (18) OF THEM, ARE SUPERVISORY
employees who attended the hearing. EMPLOYEES, AND THUS, INELIGIBLE TO VOTE IN THE
CERTIFICATION ELECTION AMONG THE COMPANYS RANK-AND-
On March 1, 2001, the petitioner voted to stage a strike at the Sta. Rosa and FILE EMPLOYEES.
Bicutan Plants of the respondent and filed a manifestation with the NCR-National
Conciliation and Mediation Board (NCR-NCMB)[23] informing the latter of its intention II
to stage a strike from March 28, 2001 onwards. IT WAS GRAVE ABUSE OF DISCRETION ON THE PART OF
On March 16, 2001, the petitioner filed a manifestation [24] with the NCR-NCMB RESPONDENT SECRETARY WHEN SHE AFFIRMED THE ORDER OF
that the respondent had dismissed three hundred union members and THE MED-ARBITER CERTIFYING PRIVATE RESPONDENT AS THE
officers. Nevertheless, the petitioner gave several days for the respondent to mend its EXCLUSIVE BARGAINING AGENT OF PETITIONER TMPCS RANK-
mind and to cease and desist from committing unfair labor practice. The petitioner AND-FILE EMPLOYEES, DESPITE THE LATTERS FAILURE TO OBTAIN
further stated that the union members would stage a protest in front of the company A MAJORITY OF THE VALID VOTES CAST.[27]
premises. Specifically, the respondent asserted that the petitioner bears the burden of
On the same day, the DOLE, thru Secretary Patricia Sto. Tomas, issued a proving that the 105 challenged voters are supervisory
resolution denying with modification the motion for reconsideration of the employees.[28] Assuming arguendo that the respondent had the burden, nevertheless,
respondent.[25] The SOLE stated that her resolution shall become final and executory it adduced overwhelming evidence that the challenged voters are, indeed, rank-and-
within ten days from notice.She ruled that the respondent had the burden to prove file employees.[29] Proceedings before labor agencies merely require the parties to
that the challenged voters were rank-and-file employees, but that the respondent submit their respective position papers and supporting affidavits. Hence, the affidavits
failed to discharge its burden; the respondent failed to adduce in evidence the job of Jose Ma. Aligada and the challenged voters are admissible in evidence. [30] The
descriptions of the challenged voters; the affidavits of Jose Ma. Aligada and of the public respondent SOLE cannot consider the affidavits of the challenged voters as
challenged voters were barren of probative weight because the affiants were not defective by concluding that the same were not properly notarized, inasmuch as the
presented to the Med-Arbiter to attest the truth of their affidavits; the Three-Function petitioner never challenged the matter before the Med-Arbiter below.[31] All the
Salary Structure adopted by the respondent in December 1994, did not change the affidavits of the challenged employees are admissible in evidence and entitled to
tasks performed by its employees; what is determinative of the classification of credence.[32] The petition for declaratory relief of the challenged voters had already
employees is their actual functions. Only 18 of the challenged voters were rank-and- been granted by the labor arbiter. The decision of the Supreme Court in Toyota Motor
file employees of the respondent, and such number is insufficient to overturn the Philippines Corporation vs. Toyota Motor Philippines Corporation Labor Union is not
result of the election. The SOLE also ruled that the decision of Labor Arbiter Eduardo on all fours with the present case.[33] Meanwhile, the petitioner staged a strike on
C. Madriaga in NLRC-NCR-30-06-02556-00 was irrelevant because the petition in the March 28, 2001.
said case was a case of forum shopping, filed by the challenged voters at the behest In compliance with the resolution of the CA, the petitioner filed its comment on
of the respondent. Entry of judgment was made of record on March 19, 2001. the petition asserting that the CA committed grave abuse of discretion amounting to
On this same date, the petitioner wrote the respondent, suggesting that a lack of jurisdiction, and grave error of law in taking cognizance of the petition and
conference be held between them on March 21, 2002 to settle all issues amicably issuing a temporary restraining order, as on its face the petition seeking to annul the
certification election, and the order certifying the union as the sole and exclusive
bargaining agent, was illegal. The respondent, as employer, is without locus standi to Aggrieved, the petitioner filed on July 27, 2001 the instant petition under Rule 65
appeal from a decision certifying the petitioner as the sole and exclusive bargaining of the Rules of Court, as amended, with a prayer for a temporary restraining
agent. order/preliminary injunction.
The petitioner further alleged that (a) the Court in the earlier Toyota case found The petitioner avers that the CA committed a grave abuse of its discretion
that the categorization of Levels 5 and 6 was for positions occupied by employees, amounting to excess or lack of jurisdiction in granting a writ of preliminary injunction in
not merely for salary purposes; (b) the factual findings of the SOLE and the Med- favor of the respondent. The petitioner asserts that the respondent, as the employer,
Arbiter are binding upon the CA, there being no showing of grave abuse of discretion is not a party in a certification election case; hence, it is a mere bystander. The
and duly supported by the evidence on record; (c) the Union was certified as the sole respondent is not the real party-in-interest to assail the results of the certification
and exclusive bargaining agent of all rank-and-file employees having obtained a election and the proceedings therein. The respondent, as the employer, had no right
majority of the valid votes cast; (d)the alleged decision of Labor Arbiter Madriaga has whatsoever nor an iota of interest in the results of the certification election. The
no bearing in the instant case as the Med-Arbiter and the SOLE has the original and respondent failed to establish a clear right to injunctive relief. The ruling of the SOLE
exclusive jurisdiction over petitions for certification elections, and on issues of who are that the petitioner was the sole and exclusive bargaining agent of all rank-and-file
qualified to vote as members of the bargaining unit; and (e) certain misrepresentation employees of the respondent, having obtained a majority of the valid votes cast was
and false allegation must be exposed for what they are. correct, based as it is on the evidence adduced by the parties.
On April 3, 2001, the CA issued a Resolution granting a Temporary Restraining The respondent, for its part, avers that the contention of the petitioner that the
Order (TRO) effective for a period of sixty (60) days, and directing the petitioner to file respondent lacks the legal standing to assail the certification election results goes into
its Comment on the petition.[34] In the meantime, the SOLE assumed jurisdiction over the merits of its petition in the CA. In resolving the issue in this case of whether or not
the notice to strike, and issued an order to the members and officers of the petitioner the CA committed a grave abuse of its discretion in issuing the writ of preliminary
to return to work. The said members and officers complied with the order and ended injunction, the Court is proscribed from resolving the petition of the respondent with
their strike on April 11, 2001. the CA on its merits. The respondent asserts that it has a clear legal right to deal with
a bona fide bargaining agent. It sought injunctive relief from the CA precisely to
During the hearing of the respondents plea for a writ of preliminary injunction on protect said right pending the resolution of its petition on the merits. The petitioner has
June 13, 2001, the petitioner averred that the respondent was not the real party-in- committed, and is still committing, acts which materially and substantially invade its
interest as it is merely a bystander in a certification election. Since the SOLE had rights to collectively bargain with a bargaining agent properly certified in accordance
already assumed jurisdiction over the petitioners projected strike and the union with law. The writ of injunction issued by the CA restrained the coercive actions of the
members and officers had complied with the return-to-work order, there was no longer petitioner that resulted in serious damages to it. The matter of the issuance of a writ of
a need for the issuance of a writ of preliminary injunction. After the hearing, the preliminary injunction rests entirely within the discretion of the CA. The petitioner
parties were ordered to submit their respective memoranda. On June 29, 2001, the failed to establish that the CA committed a grave abuse of its discretion amounting to
Court of Appeals issued a resolution granting the plea of the respondent herein for a lack or excess of jurisdiction in issuing the writ of preliminary injunction.
writ of preliminary injunction, thus:
The petition is meritorious.
...to GRANT the preliminary injunction prayed for by the petitioner, and upon its In Land Bank of the Philippines v. Court of Appeals,[36] we held, inter alia, that
posting of an injunction bond in the sum of P500,000.00, it is ORDERED of the the writ of certiorari issues for the correction of errors of jurisdiction only or grave
respondents and all those acting for or through them, to cease and desist from abuse of discretion amounting to lack or excess of jurisdiction. Its function is to keep
enforcing, implementing or otherwise acting on and giving effect to the public the inferior court within the bounds of its jurisdiction or to prevent it from committing
respondents assailed Resolutions of October 19, 2000 (Annex A of the Petition, p. 58, such a grave abuse of discretion amounting to lack or excess of jurisdiction. It may
rollo) and March 16, 2001 (Annex B of the Petition, p. 69, rollo) and allied processes issue only when the following requirements are alleged in the petition and
issued in O-A-4-27-99 (NCR-OD-M-9902-001) subject of this petition, pending the established: (1) the writ is directed against a tribunal, a board or any officer exercising
termination of this litigation, and/or unless a contrary Resolution is issued by this judicial or quasi-judicial functions; (2) such tribunal, board or officer has acted without
court.[35] or in excess of jurisdiction, or with grave abuse of discretion amounting to lack or
excess of jurisdiction; and (3) there is no appeal or any plain, speedy and adequate
remedy in the ordinary course of law. Excess of jurisdiction as distinguished from
absence of jurisdiction means that an act, though within the general power of a
tribunal, board or officer is not authorized, and invalid with respect to the particular unmistakable; (c) there is an urgent and paramount necessity for the writ to prevent
proceeding, because the conditions which alone authorize the exercise of the general serious damage.[42] The existence of the right and the violation thereof by the
power in respect of it are wanting. Without jurisdiction means lack or want of legal defendant must appear in the material allegation of the complaint/petition. When the
power, right or authority to hear and determine a cause or causes, considered either complainants right or title is doubtful, a preliminary injunction is not proper. The
in general or with reference to a particular matter. It means lack of power to exercise possibility of irreparable damage without proof of actual existing right is not a ground
authority. for injunction.[43] Moreover, the courts should avoid using a writ of preliminary
injunction, which in effect disposes of the main case without trial. [44] In resolving the
In Placido Urbanes, Jr. v. Court of Appeals,[37] we held that the matter of the petition/application for a writ of preliminary injunction, the trial court or the CA includes
issuance of a writ of preliminary injunction is addressed to the sound discretion of the in its order/resolution the factual and legal laws granting or denying the said
trial court, unless the court commits a grave abuse of discretion. Grave abuse of petition/application.
discretion in the issuance of writs of preliminary injunction implies a capricious and
whimsical exercise of judgment that is equivalent to lack of jurisdiction or whether the In this case, we are convinced that the CA committed a grave abuse of
power is exercised in an arbitrary or despotic manner by reason of passion, prejudice discretion in granting the respondents plea for injunctive relief.
or personal aversion amounting to an evasion of positive duty or to a virtual refusal to
perform the duty enjoined, or to act at all in contemplation of law. For the First. The issue of whether or not the respondent is entitled to injunctive relief is
extraordinary writ of certiorari to lie, there must be a capricious, arbitrary and interwoven with the principal issue on the merits of the petition, whether or not the
whimsical exercise of power. respondent is the real party-in-interest to assail the resolution of the SOLE and the
resolution of the Med-Arbiter. For sure, the petitioner cited a plethora of decisions of
Section 1, Rule 58 of the Rules of Court, as amended, defines a preliminary this Court that in certification elections, the employer is a bystander; it has no right or
injunction as an order granted at any stage of an action prior to the judgment or final material interest to assail the certification election.
order requiring a party or a court, agency or a person to refrain from a particular act or
acts. Injunction is accepted as the strong arm of equity or a transcendent remedy to On the other hand, the stand of the respondent cannot be dismissed as trivial
be used cautiously as it affects the respective rights of the parties, and only upon full and unsubstantial. Central to the issue posed by the parties before the SOLE in this
conviction on the part of the court of its extreme necessity. As an extraordinary case is the application of the doctrine enunciated by this Court in Toyota Motor
remedy, injunction is designed to preserve or maintain the status quo of things and is Philippines Corporation v. Toyota Motor Philippines Corporation Labor Union[45] in
generally availed of to present actual or threatened acts until the merits of the case which the respondent was the petitioner. The petitioner herein, as well as the Med-
can be heard. It may be resorted to only by a litigant for the preservation or protection Arbiter and the SOLE are one in saying that the doctrine enunciated by this Court in
of his rights or interests and for no other purpose during the pendency of the principal said case is determinative of the principal issue posed by the parties in this case. The
action.[38] It is resorted to only when there is a pressing necessity to avoid injurious respondent was as adamant in its pose that the pronouncement of this Court in the
consequences, which cannot be remedied under any standard compensation. [39] The said case is not decisive of the issue because after the decision of this Court in that
resolution of an application for a writ of preliminary injunction rests upon the existence case had become final and executory, the respondent approved and implemented a
of an emergency or of a special recourse before the main case can be heard in due Three-Function Salary Structure for its personnel/employees. Moreover, the
course of proceedings.[40] respondent submits that it can be compelled to negotiate in and enter into a collective
bargaining agreement only with the appropriate bargaining unit of the rank-and-file
In Heirs of Joaquin Asuncion v. Hon. Gervacio, Jr.,[41] we held that the writ of employees of the respondent and not by supervisory employees based on the job
preliminary injunction is issued to prevent threatened or continuous irremediable descriptions of the employees and not on the titles of employment of the
injury to parties before the case can be resolved on its merits. employees.[46] If not elected by the majority of the rank-and-file employees of the
respondent, the petitioner has no legal right to negotiate and bargain with the
We likewise held that the essential conditions for granting such temporary respondent for a collective bargaining agreement. By granting the respondents plea
injunctive relief are that the material averments in the complaint appear to be for a writ of preliminary injunction, the CA, in effect, ruled that the respondent is the
sufficient to constitute a cause of action for injunction and that on the entire showing real party-in-interest, and not merely a bystander in the certification election; hence,
from the parties it appears, in view of all the attendant circumstances, that the has a material and substantial right sought to be protected. Thus, through the
injunctive relief is reasonably necessary to protect the legal rights of the issuance of the writ, the CA may be perceived as having prejudged the principal issue
plaintiff/petitioner pendente lite. The plaintiff/petitioner must establish the following before it.
requisites for preliminary injunctive relief: (a) the invasion of the right sought to be
protected is material and substantial; (b) the right of the complainant is clear and
Second. The CA took into account the pleadings of the parties and their issue because union busting demands dismissal of the union officers and about 200
admissions during the hearing of respondents plea for injunctive relief. plus members. That is the ground for the strike not because of the representation
issue. It is simply false on their part to allege that we are going to go on strike just
In its petition with the CA, the respondent prayed the CA for a writ of preliminary because of this representation issue which we did not in the past and which we do not
injunction on its claim that (a) the petitioner was coercing and urging its members to intend to do now even without any preliminary injunction Your Honor. [47]
force the respondent to start with the negotiation of the CBA despite the serious
question on the status of the petitioner as the exclusive bargaining agent of the rank-
and-file employees; (b) 300 employees refused to render overtime service on In light of the express manifestations and guarantee made by the petitioner,
February 21, 2001 and deliberately did not report for work from February 22-23, 2001; through counsel, which were unrebutted by the respondent, there was no longer any
(c) during the said period, the operation of the respondents production plant was emergency, urgency or a pressing necessity for the CA to still issue a writ of
paralyzed and lost potential sales in the amount of P40,000,000; (d) the government preliminary injunction.There is no showing in the record that despite the assumption
will suffer considerable losses in taxes from the respondent; (e) if the status of the by the SOLE of the dispute between the petitioner and the respondent, the petitioner
challenged voters is not finally resolved, it will result in their mass promotion not on is bent on staging a strike against the respondent in defiance by the petitioner of the
the basis of their work performance but simply on the erroneous dictum of the SOLE; order of the SOLE.
(f) if the operations of the respondent are paralyzed because of the dispute on the WHEREFORE, the petition is GRANTED. The Resolution of the Court of
status of the challenged voters, its 1,600 employees will be adversely affected if the Appeals dated June 29, 2001, and the Writ of Preliminary Injunction issued on July
respondent will be impelled to resort to cost-reduction or even the closure of its 12, 2002 are SET ASIDE and NULLIFIED.
business, thus contributing to the already worsening unemployment condition of the
country. However, during the hearing of the respondents plea for a writ of preliminary SO ORDERED.
injunction, the petitioner, through counsel, manifested to the CA that the SOLE had
assumed jurisdiction over the strike staged by it and that, in compliance with the order
of the SOLE, all the union members and officers who staged the strike had returned
to work. The SOLE had determined that the industry engaged in by the respondent is
indispensable to the national interest. The petitioner assured the CA and the [G.R. NO. 135362. December 13, 1999]
respondent that in view thereof, its members and officers would no longer stage a
strike because of the certification election:

ATTY. MARAVILLA: HEIRS OF AUGUSTO L. SALAS, JR., namely: TERESITA D. SALAS for herself
and as legal guardian of the minor FABRICE CYRILL D. SALAS, MA.
CRISTINA S. LESACA, and KARINA TERESA D. SALAS, petitioners,
... Your Honor, there is no danger at all posed if no injunction is issued. The
vs.LAPERAL REALTY CORPORATION, ROCKWAY REAL ESTATE
submission of counsel that the union would go on strike because of non-issuance of
CORPORATION, SOUTH RIDGE VILLAGE, INC., MAHARAMI
injunction is false Your Honor. Why? First, we say that they are not going to go on
DEVELOPMENT CORPORATION, Spouses THELMA D. ABRAJANO and
strike just because of the issue of this certification election. That is our
GREGORIO ABRAJANO, OSCAR DACILLO, Spouses VIRGINIA D.
guarantee. Second, there has already been an order from the Sec. of Labor assuming
LAVA and RODEL LAVA, EDUARDO A. VACUNA, FLORANTE DE LA
jurisdiction precisely over the issue, the issue of whether the union is the certified
CRUZ, JESUS VICENTE B. CAPELLAN, and the REGISTER OF DEEDS
bargaining agent or not Your Honor. So, since there is now injunction or an
FOR LIPA CITY, respondents.
assumption order, we are banned by law to go there. So there is no point Your Honor
to issue an injunction. It has been mooted Your Honor. Moreover, Your Honor, it was
false on the part of respondent to allege that we even went on strike even after the DECISION
assumption of jurisdiction. That is not true. We went on strike before the assumption
DE LEON, JR., J.:
of jurisdiction. They returned to work when the Sec. of Labor assumed
jurisdiction. They returned to work. As a matter of fact up to now we are still working,
at least those people they have accepted back to return to work. Your Honor, we are Before us is a petition for review on certiorari of the Order[1] of Branch 85 of the
referring to Annex L of our comment. The ground for our strike was not representation Regional Trial Court of Lipa City[2] dismissing petitioners complaint[3] for rescission of
several sale transactions involving land owned by Augusto L. Salas, Jr., their b. One representative of the CONTRACTOR;
predecessor-in-interest, on the ground that they failed to first resort to arbitration.
c. One representative acceptable to both OWNER and CONTRACTOR.[8]
Salas, Jr. was the registered owner of a vast tract of land in Lipa City, Batangas
spanning 1,484,354 square meters. On May 5, 1998, respondent spouses Abrajano and Lava and respondent
Dacillo filed a Joint Answer with Counterclaim and Crossclaim [9] praying for dismissal
On May 15, 1987, he entered into an Owner-Contractor of petitioners Complaint for the same reason.
Agreement[4] (hereinafter referred to as the Agreement) with respondent Laperal
Realty Corporation (hereinafter referred to as Laperal Realty) to render and provide On August 9, 1998, the trial court issued the herein assailed Order dismissing
complete (horizontal) construction services on his land. petitioners Complaint for non-compliance with the foregoing arbitration clause.

On September 23, 1988, Salas, Jr. executed a Special Power of Attorney in Hence this petition.
favor of respondent Laperal Realty to exercise general control, supervision and Petitioners argue, thus:
management of the sale of his land, for cash or on installment basis.
On June 10, 1989, Salas, Jr. left his home in the morning for a business trip to The petitioners causes of action did not emanate from the Owner-Contractor
Nueva Ecija. He never returned. Agreement.
On August 6, 1996, Teresita Diaz Salas filed with the Regional Trial Court of
Makati City a verified petition for the declaration of presumptive death of her husband, The petitioners causes of action for cancellation of contract and accounting are
Salas, Jr., who had then been missing for more than seven (7) years. It was granted covered by the exception under the Arbitration Law.
on December 12, 1996.[5]
Failure to arbitrate is not a ground for dismissal.[10]
Meantime, respondent Laperal Realty subdivided the land of Salas, Jr. and sold
subdivided portions thereof to respondents Rockway Real Estate Corporation and
South Ridge Village, Inc. on February 22, 1990; to respondent spouses Abrajano and In a catena of cases[11] inspired by Justice Malcolms provocative dissent in Vega
Lava and Oscar Dacillo on June 27, 1991; and to respondents Eduardo Vacuna, v. San Carlos Milling Co.[12], this Court has recognized arbitration agreements as
Florante de la Cruz and Jesus Vicente Capalan on June 4, 1996 (all of whom are valid, binding, enforceable and not contrary to public policy so much so that when
hereinafter referred to as respondent lot buyers). there obtains a written provision for arbitration which is not complied with, the trial
court should suspend the proceedings and order the parties to proceed to arbitration
On February 3, 1998, petitioners as heirs of Salas, Jr. filed in the Regional Trial in accordance with the terms of their agreement[13] Arbitration is the wave of the future
Court of Lipa City a Complaint[6] for declaration of nullity of sale, reconveyance, in dispute resolution.[14] To brush aside a contractual agreement calling for arbitration
cancellation of contract, accounting and damages against herein respondents which in case of disagreement between parties would be a step backward. [15]
was docketed as Civil Case No. 98-0047.
Nonetheless, we grant the petition.
On April 24, 1998, respondent Laperal Realty filed a Motion to Dismiss [7]on the
ground that petitioners failed to submit their grievance to arbitration as required under A submission to arbitration is a contract.[16] As such, the Agreement, containing
Article VI of the Agreement which provides: the stipulation on arbitration, binds the parties thereto, as well as their assigns and
heirs.[17] But only they. Petitioners, as heirs of Salas, Jr., and respondent Laperal
Realty are certainly bound by the Agreement. If respondent Laperal Realty, had
ARTICLE VI. ARBITRATION. assigned its rights under the Agreement to a third party, making the former, the
assignor, and the latter, the assignee, such assignee would also be bound by the
All cases of dispute between CONTRACTOR and OWNERS representative shall be arbitration provision since assignment involves such transfer of rights as to vest in the
referred to the committee represented by: assignee the power to enforce them to the same extent as the assignor could have
enforced them against the debtor[18] or in this case, against the heirs of the original
a. One representative of the OWNER; party to the Agreement. However, respondents Rockway Real Estate Corporation,
South Ridge Village, Inc., Maharami Development Corporation, spouses Abrajano,
spouses Lava, Oscar Dacillo, Eduardo Vacuna, Florante de la Cruz and Jesus DEL MONTE CORPORATION-USA, PAUL E. DERBY, JR., DANIEL COLLINS and
Vicente Capellan are not assignees of the rights of respondent Laperal Realty under LUIS HIDALGO, petitioners, vs. COURT OF APPEALS, JUDGE
the Agreement to develop Salas, Jr.s land and sell the same. They are, rather, buyers BIENVENIDO L. REYES in his capacity as Presiding Judge, RTC-Br. 74,
of the land that respondent Laperal Realty was given the authority to develop and sell Malabon, Metro Manila, MONTEBUENO MARKETING, INC., LIONG
under the Agreement. As such, they are not assigns contemplated in Art. 1311 of the LIONG C. SY and SABROSA FOODS, INC., respondents.
New Civil Code which provides that contracts take effect only between the parties,
their assigns and heirs. DECISION
Petitioners claim that they suffered lesion of more than one-fourth (1/4) of the BELLOSILLO, J.:
value of Salas, Jr.s land when respondent Laperal Realty subdivided it and sold
portions thereof to respondent lot buyers. Thus, they instituted action[19]against both
respondent Laperal Realty and respondent lot buyers for rescission of the sale This Petition for Review on certiorari assails the 17 July 1998 Decision[1] of the
transactions and reconveyance to them of the subdivided lots. They argue that Court of Appeals affirming the 11 November 1997 Order [2] of the Regional Trial Court
rescission, being their cause of action, falls under the exception clause in Sec. 2 of which denied petitioners Motion to Suspend Proceedings in Civil Case No. 2637-
Republic Act No. 876 which provides that such submission [to] or contract [of MN. It also questions the appellate courts Resolution[3] of 30 October 1998 which
arbitration] shall be valid, enforceable and irrevocable, save upon such grounds as denied petitioners Motion for Reconsideration.
exist at law for the revocation of any contract.
On 1 July 1994, in a Distributorship Agreement, petitioner Del Monte
The petitioners contention is without merit. For while rescission, as a general Corporation-USA (DMC-USA) appointed private respondent Montebueno Marketing,
rule, is an arbitrable issue,[20] they impleaded in the suit for rescission the respondent Inc. (MMI) as the sole and exclusive distributor of its Del Monte products in the
lot buyers who are neither parties to the Agreement nor the latters assigns or Philippines for a period of five (5) years, renewable for two (2) consecutive five (5)
heirs. Consequently, the right to arbitrate as provided in Article VI of the Agreement year periods with the consent of the parties. The Agreement provided, among others,
was never vested in respondent lot buyers. for an arbitration clause which states -

Respondent Laperal Realty, as a contracting party to the Agreement, has the 12. GOVERNING LAW AND ARBITRATION[4]
right to compel petitioners to first arbitrate before seeking judicial relief. However, to
split the proceedings into arbitration for respondent Laperal Realty and trial for the
respondent lot buyers, or to hold trial in abeyance pending arbitration between This Agreement shall be governed by the laws of the State of California and/or, if
petitioners and respondent Laperal Realty, would in effect result in multiplicity of suits, applicable, the United States of America. All disputes arising out of or relating to this
duplicitous procedure and unnecessary delay. On the other hand, it would be in the Agreement or the parties relationship, including the termination thereof, shall be
interest of justice if the trial court hears the complaint against all herein respondents resolved by arbitration in the City of San Francisco, State of California, under the
and adjudicates petitioners rights as against theirs in a single and complete Rules of the American Arbitration Association. The arbitration panel shall consist of
proceeding. three members, one of whom shall be selected by DMC-USA, one of whom shall be
selected by MMI, and third of whom shall be selected by the other two members and
WHEREFORE, the instant petition is hereby GRANTED. The Order dated shall have relevant experience in the industry x x x x
August 19, 1998 of Branch 85 of the Regional Trial Court of Lipa City is hereby
NULLIFIED and SET ASIDE. Said court is hereby ordered to proceed with the hearing
In October 1994 the appointment of private respondent MMI as the sole and
of Civil Case No. 98-0047.
exclusive distributor of Del Monte products in the Philippines was published in several
Costs against private respondents. newspapers in the country. Immediately after its appointment, private respondent MMI
appointed Sabrosa Foods, Inc. (SFI), with the approval of petitioner DMC-USA, as
SO ORDERED. MMIs marketing arm to concentrate on its marketing and selling function as well as to
manage its critical relationship with the trade.
On 3 October 1996 private respondents MMI, SFI and MMIs Managing Director
Liong Liong C. Sy (LILY SY) filed a Complaint[5] against petitioners DMC-USA, Paul
[G.R. No. 136154. February 7, 2001] E. Derby, Jr.,[6] Daniel Collins[7] and Luis Hidalgo,[8] and Dewey Ltd.[9] before the
Regional Trial Court of Malabon, Metro Manila. Private respondents predicated their On 15 January 1997 petitioners filed a Motion for Reconsideration to which
complaint on the alleged violations by petitioners of Arts. 20, [10] 21[11] and 23[12] of the private respondents filed their Comment/Opposition. On 31 January 1997 petitioners
Civil Code. According to private respondents, DMC-USA products continued to be filed their Reply. Subsequently, private respondents filed an Urgent Motion for Leave
brought into the country by parallel importers despite the appointment of private to Admit Supplemental Pleading dated 2 April 1997. This Motion was admitted, over
respondent MMI as the sole and exclusive distributor of Del Monte products thereby petitioners opposition, in an Order of the trial court dated 27 June 1997.
causing them great embarrassment and substantial damage. They alleged that the
products brought into the country by these importers were aged, damaged, fake or As a result of the admission of the Supplemental Complaint, petitioners filed on
counterfeit, so that in March 1995 they had to cause, after prior consultation with 22 July 1997 a Manifestation adopting their Motion to Suspend Proceedings of 17
Antonio Ongpin, Market Director for Special Markets of Del Monte Philippines, Inc., October 1996 and Motion for Reconsideration of 14 January 1997.
the publication of a "warning to the trade" paid advertisement in leading On 11 November 1997 the Motion to Suspend Proceedings was denied by the
newspapers. Petitioners DMC-USA and Paul E. Derby, Jr., apparently upset with the trial court on the ground that it "will not serve the ends of justice and to allow said
publication, instructed private respondent MMI to stop coordinating with Antonio suspension will only delay the determination of the issues, frustrate the quest of the
Ongpin and to communicate directly instead with petitioner DMC-USA through Paul E. parties for a judicious determination of their respective claims, and/or deprive and
Derby, Jr. delay their rights to seek redress."[15]
Private respondents further averred that petitioners knowingly and surreptitiously On appeal, the Court of Appeals affirmed the decision of the trial court. It held
continued to deal with the former in bad faith by involving disinterested third parties that the alleged damaging acts recited in the Complaint, constituting petitioners
and by proposing solutions which were entirely out of their control. Private causes of action, required the interpretation of Art. 21 of the Civil Code [16] and that in
respondents claimed that they had exhausted all possible avenues for an amicable determining whether petitioners had violated it "would require a full blown trial"
resolution and settlement of their grievances; that as a result of the fraud, bad faith, making arbitration "out of the question." [17] Petitioners Motion for Reconsideration of
malice and wanton attitude of petitioners, they should be held responsible for all the the affirmation was denied. Hence, this Petition for Review.
actual expenses incurred by private respondents in the delayed shipment of orders
which resulted in the extra handling thereof, the actual expenses and cost of money The crux of the controversy boils down to whether the dispute between the
for the unused Letters of Credit (LCs) and the substantial opportunity losses due to parties warrants an order compelling them to submit to arbitration.
created out-of-stock situations and unauthorized shipments of Del Monte-USA
products to the Philippine Duty Free Area and Economic Zone; that the bad faith, Petitioners contend that the subject matter of private respondents causes of
fraudulent acts and willful negligence of petitioners, motivated by their determination action arises out of or relates to the Agreement between petitioners and private
to squeeze private respondents out of the outstanding and ongoing Distributorship respondents. Thus, considering that the arbitration clause of the Agreement provides
Agreement in favor of another party, had placed private respondent LILY SY on that all disputes arising out of or relating to the Agreement or the parties relationship,
tenterhooks since then; and, that the shrewd and subtle manner with which petitioners including the termination thereof, shall be resolved by arbitration, they insist on the
concocted imaginary violations by private respondent MMI of the Distributorship suspension of the proceedings in Civil Case No. 2637-MN as mandated by Sec. 7 of
Agreement in order to justify the untimely termination thereof was a subterfuge. For RA 876[18] -
the foregoing, private respondents claimed, among other reliefs, the payment of
actual damages, exemplary damages, attorneys fees and litigation expenses. Sec. 7. Stay of Civil Action. If any suit or proceeding be brought upon an issue arising
out of an agreement providing for arbitration thereof, the court in which such suit or
On 21 October 1996 petitioners filed a Motion to Suspend
proceeding is pending, upon being satisfied that the issue involved in such suit or
Proceedings[13] invoking the arbitration clause in their Agreement with private
proceeding is referable to arbitration, shall stay the action or proceeding until an
respondents. arbitration has been had in accordance with the terms of the
In a Resolution[14] dated 23 December 1996 the trial court deferred consideration agreement. Provided, That the applicant for the stay is not in default in proceeding
of petitioners Motion to Suspend Proceedings as the grounds alleged therein did not with such arbitration.
constitute the suspension of the proceedings considering that the action was for
damages with prayer for the issuance of Writ of Preliminary Attachment and not on Private respondents claim, on the other hand, that their causes of action are
the Distributorship Agreement. rooted in Arts. 20, 21 and 23 of the Civil Code,[19] the determination of which demands
a full blown trial, as correctly held by the Court of Appeals. Moreover, they claim that
the issues before the trial court were not joined so that the Honorable Judge was not
given the opportunity to satisfy himself that the issue involved in the case was are bound by the Agreement and its arbitration clause as they are the only signatories
referable to arbitration. They submit that, apparently, petitioners filed a motion to thereto. Petitioners Daniel Collins and Luis Hidalgo, and private respondent SFI, not
suspend proceedings instead of sending a written demand to private respondents to parties to the Agreement and cannot even be considered assigns or heirs of the
arbitrate because petitioners were not sure whether the case could be a subject of parties, are not bound by the Agreement and the arbitration clause
arbitration. They maintain that had petitioners done so and private respondents failed therein. Consequently, referral to arbitration in the State of California pursuant to the
to answer the demand, petitioners could have filed with the trial court their demand for arbitration clause and the suspension of the proceedings in Civil Case No. 2637-MN
arbitration that would warrant a determination by the judge whether to refer the case pending the return of the arbitral award could be called for[25] but only as to petitioners
to arbitration. Accordingly, private respondents assert that arbitration is out of the DMC-USA and Paul E. Derby, Jr., and private respondents MMI and LILY SY, and not
question. as to the other parties in this case, in accordance with the recent case of Heirs of
Augusto L. Salas, Jr. v. Laperal Realty Corporation,[26] which superseded that
Private respondents further contend that the arbitration clause centers more on of Toyota Motor Philippines Corp. v. Court of Appeals.[27]
venue rather than on arbitration. They finally allege that petitioners filed their motion
for extension of time to file this petition on the same date [20] petitioner DMC-USA filed In Toyota, the Court ruled that "[t]he contention that the arbitration clause has
a petition to compel private respondent MMI to arbitrate before the United States become dysfunctional because of the presence of third parties is untenable
District Court in Northern California, docketed as Case No. C-98-4446. They insist ratiocinating that "[c]ontracts are respected as the law between the contracting
that the filing of the petition to compel arbitration in the United States made the parties"[28] and that "[a]s such, the parties are thereby expected to abide with good
petition filed before this Court an alternative remedy and, in a way, an abandonment faith in their contractual commitments."[29] However, in Salas, Jr., only parties to the
of the cause they are fighting for here in the Philippines, thus warranting the dismissal Agreement, their assigns or heirs have the right to arbitrate or could be compelled to
of the present petition before this Court. arbitrate. The Court went further by declaring that in recognizing the right of the
contracting parties to arbitrate or to compel arbitration, the splitting of the proceedings
There is no doubt that arbitration is valid and constitutional in our to arbitration as to some of the parties on one hand and trial for the others on the
jurisdiction.[21] Even before the enactment of RA 876, this Court has countenanced other hand, or the suspension of trial pending arbitration between some of the parties,
the settlement of disputes through arbitration. Unless the agreement is such as should not be allowed as it would, in effect, result in multiplicity of suits, duplicitous
absolutely to close the doors of the courts against the parties, which agreement would procedure and unnecessary delay.[30]
be void, the courts will look with favor upon such amicable arrangement and will only
interfere with great reluctance to anticipate or nullify the action of the The object of arbitration is to allow the expeditious determination of a
arbitrator.[22] Moreover, as RA 876 expressly authorizes arbitration of domestic dispute.[31] Clearly, the issue before us could not be speedily and efficiently resolved
disputes, foreign arbitration as a system of settling commercial disputes was likewise in its entirety if we allow simultaneous arbitration proceedings and trial, or suspension
recognized when the Philippines adhered to the United Nations "Convention on the of trial pending arbitration. Accordingly, the interest of justice would only be served if
Recognition and the Enforcement of Foreign Arbitral Awards of 1958" under the 10 the trial court hears and adjudicates the case in a single and complete proceeding. [32]
May 1965 Resolution No. 71 of the Philippine Senate, giving reciprocal recognition
and allowing enforcement of international arbitration agreements between parties of WHEREFORE, the petition is DENIED. The Decision of the Court of Appeals
different nationalities within a contracting state.[23] affirming the Order of the Regional Trial Court of Malabon, Metro Manila, in Civil Case
No. 2637-MN, which denied petitioners Motion to Suspend Proceedings, is
A careful examination of the instant case shows that the arbitration clause in the AFFIRMED. The Regional Trial Court concerned is directed to proceed with the
Distributorship Agreement between petitioner DMC-USA and private respondent MMI hearing of Civil Case No. 2637-MN with dispatch. No costs.
is valid and the dispute between the parties is arbitrable. However, this Court must
deny the petition. SO ORDERED.

The Agreement between petitioner DMC-USA and private respondent MMI is a


contract. The provision to submit to arbitration any dispute arising therefrom and the
relationship of the parties is part of that contract and is itself a contract. As a rule,
contracts are respected as the law between the contracting parties and produce effect [G.R. No. 159586. July 26, 2004]
as between them, their assigns and heirs.[24] Clearly, only parties to the
Agreement, i.e., petitioners DMC-USA and its Managing Director for Export Sales
Paul E. Derby, Jr., and private respondents MMI and its Managing Director LILY SY
EUROPEAN RESOURCES AND TECHNOLOGIES, INC. and DELFIN J. this project. On April 18, 2000, the German Consortium entered into a Joint Venture
WENCESLAO, petitioners, vs. INGENIEUBURO BIRKHAHN + NOLTE, with D.M. Wenceslao and Associates, Inc. (DMWAI) and Ma. Elena B. Villarama
Ingeniurgesellschaft mbh and HEERS & BROCKSTEDT GMBH & (doing business as LBV and Associates), embodied in a Memorandum of
CO., respondents. Understanding[7] (MOU) signed by the parties. Under the MOU, the parties agreed to
jointly form a local corporation to which the German Consortium shall assign its rights
DECISION under the Contract for Services. Pursuant to this agreement, petitioner European
Resources and Technologies, Inc. was incorporated. The parties likewise agreed to
YNARES-SANTIAGO, J.: prepare and finalize a Shareholders Agreement within one (1) month from the
execution of the MOU, which shall provide that the German Consortium shall own
fifteen percent (15%) of the equity in the joint venture corporation, DMWAI shall own
Assailed in this Petition for Review under Rule 45 of the Rules of Court is the
seventy percent (70%) and LBV&A shall own fifteen percent (15%). In the event that
Decision[1] of the Court of Appeals dated May 15, 2003, which sustained the Order of
the parties fail to execute the Shareholders Agreement, the MOU shall be considered
the Regional Trial Court of Angeles City, Branch 61, dated June 28, 2001, and its
null and void.[8]
subsequent Resolution dated August 3, 2003 denying petitioners motion for
reconsideration. On August 1, 2000, without the Shareholders Agreement having been executed,
the German Consortium and petitioner ERTI entered into a Memorandum of
European Resources and Technologies Inc. (hereinafter ERTI), a corporation
Agreement (MOA)[9] whereby the German Consortium ceded its rights and obligations
organized and existing under the laws of the Republic of the Philippines, is joined by
under the Contract for Services in favor of ERTI and assigned unto ERTI, among
Delfin J. Wenceslao as petitioner in this case. Ingenieuburo Birkhan + Nolte
others, its license from CDC to engage in the business of providing environmental
Ingiurgesellschaft mbh and Heers & Brockstedt Gmbh & Co. are German corporations
services needed in the CSEZ in connection with the waste management within the
who are respondents in this case and shall be collectively referred to as the German
CSEZ and other areas.[10] Likewise, the parties agreed that should there be a
Consortium.
disagreement between or among them relative to the interpretation or implementation
The German Consortium tendered and submitted its bid to the Clark of the MOA and the collateral documents including but not limited to the Contract for
Development Corporation (CDC) to construct, operate and manage Services between the German Consortium and CDC, the dispute shall be referred to
the Integrated Waste Management Center at the Clark Special Economic Zone a panel of arbitrators.[11]
(CSEZ). CDC accepted the German Consortiums bid and awarded the contract to
On December 11, 2000, ERTI received a letter from BN Consultants Philippines,
it. On October 6, 1999, CDC and the German Consortium executed the Contract for
Inc., signed by Mr. Holger Holst for and on behalf of the German
Services[2] which embodies the terms and conditions of their agreement.
Consortium,[12] stating that the German Consortiums contract with DMWAI, LBV&A
The Contract for Services provides that the German Consortium shall be and ERTI has been terminated or extinguished on the following grounds: (a) the CDC
empowered to enter into a contract or agreement for the use of the integrated waste did not give its approval to the Consortiums request for the approval of the
management center by corporations, local government units, entities, and persons not assignment or transfer by the German Consortium in favor of ERTI of its rights and
only within the CSEZ but also outside. For waste collected within the CSEZ, the interests under the Contract for Services; (b) the parties failed to prepare and finalize
German Consortium may impose a tipping fee per ton of waste collected from the Shareholders Agreement pursuant to the provision of the MOU; (c) there is no
locators and residents of the CSEZ, which fees shall be subject to the schedule more factual or legal basis for the joint venture to continue; and (d) with the
agreed upon by the parties and specified in the Contract for Services. For its termination of the MOU, the MOA is also deemed terminated or extinguished.
operations outside of the CSEZ, the German Consortium shall pay CDC US$1.50 per
Attached to the letter was a copy of the letter of the CDC, [13] stating that the
ton of non-hazardous solid waste collected.[3] The CDC shall guarantee that nineteen
German Consortiums assignment of an eighty-five percent (85%) majority interest to
thousand eighteen hundred (19,800) tons per year of solid waste volume shall be
another party violated its representation to undertake both the financial and technical
collected from inside and outside the CSEZ.[4] The contract has a term of twenty-five
aspects of the project. The dilution of the Consortiums interest in ERTI is a substantial
(25) years,[5] during which time the German Consortium shall operate the waste
modification of the Consortiums representations which were used as bases for the
management center on a day-to-day basis.[6]
award of the project to it.
Article VIII, Section 7 of the Contract for Services provides that the German
Consortium shall undertake to organize a local corporation as its representative for
On February 20, 2001, petitioner ERTI, through counsel, sent a letter to CDC Hence, this petition arguing that the Court of Appeals committed reversible error
requesting for the reconsideration of its disapproval of the agreement between ERTI in:
and the German Consortium.
Before CDC could act upon petitioner ERTIs letter, the German Consortium filed (a) Ruling that petitioners are estopped from assailing the capacity of the
a complaint for injunction against herein petitioners before respondents to institute the suit for injunction
the Regional Trial Court of Angeles City, Branch 61, docketed as Civil Case No.
10049. The German Consortium claimed that petitioner ERTIs continued (b) Ruling that respondents are entitled to an injunctive writ.
misrepresentation as to their right to accept solid wastes from third parties for
processing at the waste management center will cause irreparable damage to the (c) Not holding that the dispute is covered by the arbitration clause in the
Consortium and its exclusive right to operate the waste management center at the memorandum of agreement.
CSEZ. Moreover, petitioner ERTIs acts destroy the Consortiums credibility and
undermine customer confidence in it. Hence, the German Consortium prayed that a
writ of temporary restraining order be issued against petitioner ERTI and, after (d) Issuing the writ of preliminary injunction that is tantamount to a decision of
hearing, a writ of preliminary injunction be likewise issued ordering petitioner ERTI to the case on the merits.[18]
cease and desist from misrepresenting to third parties or the public that it has any
right or interest in the waste management center at CSEZ.[14] The petition is partly meritorious.
Petitioners filed their Opposition to the application for preliminary injunction There is no general rule or governing principle laid down as to what constitutes
on February 7, 2001. The following day, February 8, 2001, petitioners sent doing or engaging in or transacting business in the Philippines. Thus, it has often
respondents, through Mr. Holger Holst, a letter demanding that the parties proceed to been held that a single act or transaction may be considered as doing business when
arbitration in accordance with Section 17 of the MOA. At the hearings on the a corporation performs acts for which it was created or exercises some of the
application for injunction, petitioners objected to the presentation of evidence on the functions for which it was organized.[19] We have held that the act of participating in a
ground that the trial court had no jurisdiction over the case since the German bidding process constitutes doing business because it shows the foreign corporations
Consortium was composed of foreign corporations doing business in the country intention to engage in business in the Philippines. In this regard, it is the performance
without a license. Moreover, the MOA between the parties provides that the dispute by a foreign corporation of the acts for which it was created, regardless of volume of
should be referred to arbitration. business, that determines whether a foreign corporation needs a license or not.[20]
The trial court overruled the objection and proceeded with the hearing. On June Consequently, the German Consortium is doing business in
28, 2001, the trial court issued an Order granting the writ of preliminary the Philippines without the appropriate license as required by our laws. By
injunction.[15] Petitioners filed a motion for reconsideration, which was denied in a participating in the bidding conducted by the CDC for the operation of the waste
Resolution dated November 21, 2001. management center, the German Consortium exhibited its intent to transact business
in the Philippines. Although the Contract for Services provided for the establishment
On January 17, 2002, petitioners filed a petition for certiorari and prohibition of a local corporation to serve as respondents representative, it is clear from the other
under Rule 65 of the Rules of Court before the Court of Appeals, assailing the trial provisions of the Contract for Services as well as the letter by the CDC containing the
courts Orders dated June 28, 2001 and November 21, 2001. disapproval that it will be the German Consortium which shall manage and conduct
Meanwhile, on February 11, 2002, the temporary restraining order issued was the operations of the waste management center for at least twenty-five
lifted in view of respondents failure to file sufficient bond.[16] On September 6, 2002, years. Moreover, the German Consortium was allowed to transact with other entities
all proceedings in Civil Case No. 10049 were suspended until the petition for certiorari outside the CSEZ for solid waste collection. Thus, it is clear that the local corporation
pending before the Court of Appeals shall have been resolved. [17] to be established will merely act as a conduit or extension of the German Consortium.

On May 15, 2003, the Court of Appeals dismissed the petition for As a general rule, unlicensed foreign non-resident corporations cannot file suits
certiorari. Petitioners Motion for Reconsideration was denied in a Resolution in the Philippines. Section 133 of the Corporation Code specifically provides:
dated August 25, 2003.
SECTION 133. No foreign corporation transacting business in the Philippines without
a license, or its successors or assigns, shall be permitted to maintain or intervene in
any action, suit or proceeding in any court or administrative agency of the Philippines, requiring a license is not to prevent the foreign corporation from performing single
but such corporation may be sued or proceeded against before Philippine courts or acts, but to prevent it from acquiring domicile for the purpose of business without
administrative tribunals on any valid cause of action recognized under Philippine laws. taking the steps necessary to render it amenable to suits in the local courts. [24] In
other words, the foreign corporation is merely prevented from being in a position
A corporation has legal status only within the state or territory in which it was where it takes the good without accepting the bad.
organized. For this reason, a corporation organized in another country has no On the issue of whether the respondents were entitled to the injunctive writ, the
personality to file suits in the Philippines. In order to subject a foreign corporation petitioners claim that respondents right is not in esse but is rather a future right which
doing business in the country to the jurisdiction of our courts, it must acquire a license is contingent upon a judicial declaration that the MOA has been validly rescinded. The
from the Securities and Exchange Commission (SEC) and appoint an agent for Court of Appeals, in its decision, held that the MOA should be deemed subject to a
service of process. Without such license, it cannot institute a suit in the Philippines.[21] suspensive condition, that is, that CDCs prior written consent must be obtained for the
However, there are exceptions to this rule. In a number of cases,[22] we have validity of the assignment.
declared a party estopped from challenging or questioning the capacity of an This issue must be resolved in a separate proceeding. It must be noted that the
unlicensed foreign corporation from initiating a suit in our courts. In the case hearing conducted in the trial court was merely a preliminary hearing relating to the
of Communication Materials and Design, Inc. v. Court of Appeals,[23] a foreign issuance of the injunctive writ. In order to fully appreciate the facts of this case and
corporation instituted an action before our courts seeking to enjoin a local corporation, the surrounding circumstances relating to the agreements and contract involved,
with whom it had a Representative Agreement, from using its corporate name, letter further proof should be presented for consideration of the court. Likewise, corollary
heads, envelopes, sign boards and business dealings as well as the foreign matters, such as whether either of the parties is liable for damages and to what
corporations trademark. The case arose when the foreign corporation discovered that extent, cannot be resolved with absolute certainty, thus rendering any decision we
the local corporation has violated certain contractual commitments as stipulated in might make incomplete as to fully dispose of this case.
their agreement. In said case, we held that a foreign corporation doing business in
the Philippines without license may sue in Philippine Courts a Philippine citizen or More importantly, it is evident that CDC must be made a proper party in any
entity that had contracted with and benefited from it. case which seeks to resolve the effectivity or ineffectivity of its disapproval of the
assignment made between petitioners and respondent German Consortium. Where,
Hence, the party is estopped from questioning the capacity of a foreign as in the instant case, CDC is not impleaded as a party, any decision of the court
corporation to institute an action in our courts where it had obtained benefits from its which will inevitably affect or involve CDC cannot be deemed binding on it.
dealings with such foreign corporation and thereafter committed a breach of or sought
to renege on its obligations. The rule relating to estoppel is deeply rooted in the axiom For the same reason, petitioners assertion that the instant case should be
of commodum ex injuria sua non habere debetno person ought to derive any referred to arbitration pursuant to the provision of the MOA is untenable.
advantage from his own wrong.
We have ruled in several cases that arbitration agreements are valid, binding,
In the case at bar, petitioners have clearly not received any benefit from its enforceable and not contrary to public policy such that when there obtains a written
transactions with the German Consortium. In fact, there is no question that petitioners provision for arbitration which is not complied with, the trial court should suspend the
were the ones who have expended a considerable amount of money and effort proceedings and order the parties to proceed to arbitration in accordance with the
preparatory to the implementation of the MOA. Neither do petitioners seek to back out terms of their agreement.[25] In the case at bar, the MOA between petitioner ERTI and
from their obligations under both the MOU and the MOA by challenging respondents respondent German Consortium provided:
capacity to sue. The reverse could not be any more accurate. Petitioners are insisting
on the full validity and implementation of their agreements with the German 17. Should there be a disagreement between or among the Parties relative to the
Consortium. interpretation or implementation of this Agreement and the collateral documents
To rule that the German Consortium has the capacity to institute an action including but not limited to the Contract for Services between GERMAN
against petitioners even when the latter have not committed any breach of its CONSORTIUM and CDC and the Parties cannot resolve the same by themselves, the
obligation would be tantamount to an unlicensed foreign corporation gaining access to same shall be endorsed to a panel of arbitrators which shall be convened in
our courts for protection and redress. We cannot allow this without violating the very accordance with the process ordained under the Arbitration Law of the Republic of the
rationale for the law prohibiting a foreign corporation not licensed to do business in Philippines.[26]
the Philippines from suing or maintaining an action in Philippine courts. The object of
Indeed, to brush aside a contractual agreement calling for arbitration in case of Thus, it is clear that for the issuance of the writ of preliminary injunction to be
disagreement between parties would be a step backward. [27] But there are exceptions proper, it must be shown that the invasion of the right sought to be protected is
to this rule. Even if there is an arbitration clause, there are instances when referral to material and substantial, that the right of complainant is clear and unmistakable and
arbitration does not appear to be the most prudent action. The object of arbitration is that there is an urgent and paramount necessity for the writ to prevent serious
to allow the expeditious determination of a dispute. Clearly, the issue before us could damage.[31] At the time of its application for an injunctive writ, respondents right to
not be speedily and efficiently resolved in its entirety if we allow simultaneous operate and manage the waste management center, to the exclusion of or without
arbitration proceedings and trial, or suspension of trial pending arbitration. [28] any participation by petitioner ERTI, cannot be said to be clear and unmistakable. The
MOA executed between respondents and petitioner ERTI has not yet been judicially
As discussed earlier, the dispute between respondent German Consortium and declared as rescinded when the complaint was lodged in court.[32] Hence, a cloud of
petitioners involves the disapproval by the CDC of the assignment by the German doubt exists over respondent German Consortiums exclusive right relating to the
Consortium of its rights under the Contract for Services to petitioner ERTI. Admittedly, waste management center.
the arbitration clause is contained in the MOA to which only the German Consortium
and petitioner ERTI were parties. Even if the case is brought before an arbitration WHEREFORE, the decision of the Court of Appeals in CA-G.R. SP No. 68923
panel, the decision will not be binding upon CDC who is a non-party to the arbitration dated May 15, 2003 is REVERSED and SET ASIDE. The Orders of the trial court
agreement. What is more, the arbitration panel will not be able to completely dispose dated June 28, 2001 and November 21, 2001 are ANNULLED and SET ASIDE and
of all the issues of this case without including CDC in its proceedings. Accordingly, Civil Case No. 10049 is DISMISSED for lack of legal capacity of respondents to
the interest of justice would only be served if the trial court hears and adjudicates the institute the action. Costs against respondents.
case in a single and complete proceeding.
SO ORDERED.
Lastly, petitioners question the propriety of the issuance of writ of preliminary
injunction claiming that such is already tantamount to granting the main prayer of Home Bankers Savings and Trust Company v. CA (G.R. No. 115412)
respondents complaint without the benefit of a trial. Petitioners point out that the
purpose of a preliminary injunction is to prevent threatened or continuous Facts:
irremediable injury to some of the parties before their claims can be thoroughly Victor Tancuan issued Petitioner Home Bankers Savings and Trust Company a check
studied and decided. It cannot be used to railroad the main case and seek a judgment while Eugene Arriesgado issued Private Respondent Far East Bank and Trust
without a full-blown trial as in the instant case. Company three checks; both checks totaling the amount of P25,250,000.00. Tancuan
and Arriesgado exchanged each other’s checks and deposited them with their
The Court of Appeals ruled that since petitioners did not raise this issue during respective banks for collection. When FEBTC presented Tancuan’s HBSTC check for
the hearing on the application for preliminary injunction before the trial court, the clearing, it was dishonored for being DAIF. Meanwhile, HBSTC sent Arriesgado’s 3
same cannot be raised for the first time on appeal and even in special civil actions for FEBTC checks through the Philippine Clearing House Corporation (PCHC) to FEBTC
certiorari as in this case. but was returned for being DAIF. HBSTC receive the notice of dishonor but refused to
accept the checks and returned them to FEBTC through the PCHC for the reason
At the outset, it must be noted that with the finding that the German Consortium
“Beyond Reglementary Period,” implying that HBSTC already treated the 3 checks as
is without any personality to file the petition with the trial court, the propriety of the
cleared and allowed the proceeds thereof to be withdrawn. FEBTC demanded
injunction writ issued is already moot and academic. Even assuming for the sake of
reimbursement for the returned checks and inquired from HBSTC whether it had
argument that respondents have the capacity to file the petition, we find merit in the
permitted any withdrawal of funds against the unfunded checks. HBSTC, however
issue raised by petitioners against the injunction writ issued.
refused to make any reimbursement and to provide FEBTC with the needed
Before an injunctive writ can be issued, it is essential that the following information. Thus, FEBTC submitted the dispute for arbitration before the PCHC
requisites are present: (1) there must be a right in esse or the existence of a right to Arbitration Committee, under its Supplementary Rules on Regional Clearing to which
be protected; and (2) the act against which injunction to be directed is a violation of FEBTC and HBSTC are bound as participants in the regional clearing operations
such right.[29] The onus probandi is on movant to show that there exists a right to be administered by the PCHC. While the arbitration proceeding was still pending, FEBTC
protected, which is directly threatened by the act sought to be enjoined. Further, there filed an action for sum of money and damages with preliminary attachment against
must be a showing that the invasion of the right is material and substantial and that HBSTC. HBSTC moved to dismiss on the ground that there is no cause of action and
there is an urgent and paramount necessity for the writ to prevent a serious because it seeks to enforce an arbitral award which as yet does not exist. The trial
damage.[30]
court denied the motion to dismiss and the motion for reconsideration. Petitioner then Equipment Supply Sub-Contract Agreement (ESSA), Siemens Building Technologies
filed a petition for certiorari with respondent CA to which it had dismissed. Inc. undertook to deliver the needed electrical equipment for the project for Romago.
Issue: SBTI made deliveries but ROMAGO failed to pay in full. The former made demands,
Whether or not private respondent which commenced an arbitration proceeding under
but they were not paid. Romago refused to pay its obligation which amounted to
the auspices of the PCHC may subsequently file a separate case in court over the
same subject matter despite the pendency of that arbitration, simply to obtain the P16,937,612.68, unless SBTI compensates ROMAGO for the total expenses it
provisional remedy of attachment against the adverse party in the arbitration allegedly incurred in taking over SBTI’s contractual obligations when the earlier
proceeding. demands to pay were unheeded.
Ruling:
We find no merit in the petition. Section 14 of Republic Act 876, otherwise known as SBTI filed a Request for Arbitration with the Philippine Dispute Resolution Center, Inc.
the Arbitration Law, allows any party to the arbitration proceeding to petition the court (PDRCI) which was agreed to by Romago. After due proceedings, the arbitrator
to take measures to safeguard and/or conserve any matter which is the subject of the
awarded to SBTI its claim of the amount above mentioned plus legal interest,
dispute in arbitration.
Petitioner’s exposition of the foregoing provision deserves scant consideration. attorney’s fees and costs.
Section 14 simply grants an arbitrator the power to issue subpoena and SBTI filed a petition for Confirmation of the Arbitrator’s Decision, and instead of filing
subpoena duces tecum at any time before rendering the award. The exercise of such a Motion to Vacate the Award, Romago filed an Answer. The RTC granted the
power is without prejudice to the right of a party to file a petition in court to safeguard petition, confirmed the award and issued a Writ of Execution. This had become final
any matter which is the subject of the dispute in arbitration. In the case at bar, private and executory. Despite receipt of the Order on July 3, 2006, Romago did not
respondent filed an action for a sum of money with prayer for a writ of preliminary interpose an appeal. It was only later on August 22, 2006 when Atty. Barrios withdrew
attachment. Undoubtedly, such action involved the same subject matter as that in
his appearance and the law office of Mutia Venadas entered appearance that
arbitration, i.e., the sum of P25,200,000.00 which was allegedly deprived from private
respondent in what is known in banking as a “kiting scheme.” However, the civil action Romago sought for a petition for relief from judgment. Claiming that Atty. Barrios was
was not a simple case of a money claim since private respondent has included a sick for three weeks and only later were they aware of the orders of the court.
prayer for a writ of preliminary attachment, which is sanctioned by section 14 of the SBTI opposed, and the RTC denied it. MR was denied. And upon petition for certiorari
Arbitration Law. to the CA,Romago raised the issue that the PDRCI had no jurisdiction over the
Simply put, participants in the regional clearing operations of the Philippine Clearing dispute since the contract with SBTI was a construction contract and was within the
House Corporation cannot bypass the arbitration process laid out by the body and
jurisdiction of the CIAC. However, the CA also denied this.
seek relief directly from the courts. In the case at bar, undeniably, private respondent
has initiated arbitration proceedings as required by the PCHC rules and regulations,
and pending arbitration has sought relief from the trial court for measures to Issue: was the contract between the parties a construction contract that would place it
safeguard and/or conserve the subject of the dispute under arbitration, as sanctioned in the jurisdiction of the CIAC?
by section 14 of the Arbitration Law, and otherwise not shown to be contrary to the
PCHC rules and regulations. Ruling:
At this point, we emphasize that arbitration, as an alternative method of dispute No. It was a supply contract, thus, not within the jurisdiction of the CIAC.
resolution, is encouraged by this Court. Aside from unclogging judicial dockets, it also
SBTI’s scope of work under the ESSA was:
hastens solutions especially of commercial disputes. The Court looks with favor upon
such amicable arrangement and will only interfere with great reluctance to anticipate 1.01 x x x to furnish all equipment in accordance with the equipment and
or nullify the action of the arbitrator. Wherefore, premises considered, the petition is delivery schedule x x x
hereby dismissed and the decision of the court a quo is affirmed. 1.02 [to] supply and deliver the equipment in accordance with the Bill of
G.R. No. 181969 October 2, 2009 Quantities and Cost Schedule (Attachment Nos. 1 &2) and equipment
ROMAGO, INC. vs SIEMENS BUILDING TECHNOLOGIES, INC. delivery schedule (Attachment -3) to the jobsite/designated areas including
unloading of equipment from the delivery truck.xxxx
Romago Inc. was awarded the Sub-contract for the Building Services-Electrical
Package for the Insular Life Corporate Center. Under the consortium agreement and
By no stretch of the imagination can the ESSA be characterized as a construction
contract. Crystal clear from the provisions of the ESSA is that SBTI’s role was merely The Republic of the Philippines granted MMIC the exclusive right to explore, develop
to supply the needed equipment for the Insular Life Corporate Center project. The and exploit minerals in the Surigao mineral reservation. The Philippine Government
ESSA is, therefore, a mere supply contract that does not fall within the original undertook to support the financing of MMIC. On July 13, 1981, MMIC, PNB and DBP
and exclusive jurisdiction of CIAC. executed a Mortgage Trust Agreement whereby MMIC, as mortgagor, agreed to
constitute a mortgage in favor of PNB and DBP as mortgagees, over all MMIC’s
We also note that the Consortium Agreement between ROMAGO and SBTI contained assets.
an arbitration clause, wherein the parties agreed to submit any dispute between them By 1984, MMIC had an outstanding loan in the amount of
for arbitration under the Philippine Chamber of Commerce and Industry P22,668,537,770.05, and MMIC was having a difficult time meeting its financial
(PCCI),36 such as the PDRCI. obligations. Thus, a financial restructuring plan (FRP) was designed; however, the
proposed FRP had never been formally adopted, approved or ratified by either PNB
Furthermore, the issue of jurisdiction was rendered moot by ROMAGO's active or DBP.
participation in the proceedings before the PDRCI and the RTC. In fact, during The loans had become overdue, DBP and PNB exercised their right to
the proceedings for the confirmation of the Arbitrator’s award, ROMAGO’s opposition extrajudicially foreclose the mortgages in accordance with the Mortgage Trust
zeroed in on the alleged bias and partiality of the Arbitrator in rendering the decision. Agreement. The foreclosed assets were sold to PNB and were assigned to three
Even in its petition for relief from judgment filed with the RTC, the PDRCI’s alleged newly formed corporations. Thereafter, these assets were transferred to the Asset
lack of jurisdiction was never raised as an issue. It was only in its petition for certiorari Privatization Trust (APT).
with the CA, and after a writ of execution had been issued, that ROMAGO raised the Jesus S. Cabarrus, Sr., together with the other stockholders of MMIC, filed a
issue of lack of jurisdiction. derivative suit against DBP and PNB for Annulment of Foreclosures, Specific
Performance and Damages. In the course of the trial, the parties mutually agreed to
ROMAGO attempted to avoid this final and executory judgment by filing a petition for submit the case to arbitration by entering into a “Compromise and Arbitration
relief from judgment with the RTC. However, under the rules, the equitable remedy is Agreement. The Compromise and Arbitration Agreement limited the issues to the
allowed only under exceptional circumstances of fraud, accident , mistake or following: (a) propriety of the plaintiffs filing the derivative suit; (b) the regularity of the
excusable negligence, which is not applicable in this case. Romago ascribes its foreclosure proceedings. The trial court approved the agreement and ordered that the
failure to appeal due to the negligence of its counsel, Atty. Barrios, who had suffered complaint be dismissed.
from hypertension; but the court is not convinced since the affidavit it submit to prove After conducting several hearings, the Arbitration Committee rendered a
such allegations was filled with blanks of the name of the physician and hospital who majority decision in favor of MMIC. Motions for reconsiderations were filed by both
attended the lawyer. As such, It is settled that clients are bound by the mistakes, parties, but the same were denied.
negligence and omission of their counsel. While, exceptionally, the client may be In 1994, private respondents filed in the same Civil Case No. 9900 an
excused from the failure of counsel,49 the circumstances obtaining in the present “Application/Motion for Confirmation of Arbitration Award.” Petitioner countered with
case do not persuade this Court to take exception. an “Opposition and Motion to Vacate Judgment.Private respondents filed a “reply and
ASSET PRIVATIZATION TRUST, petitioner, opposition” arguing that a dismissal of Civil case No. 9900 was merely a “qualified
vs., dismissal” to pave the way for the submission of the controversy to arbitration, and
COURT OF APPEALS, JESUS S. CABARRUS, SR., JESUS S. CABARRUS, JR., operated simply as “a mere suspension of the proceedings.”
JAIME T. CABARRUS, JOSE MIGUEL CABARRUS, ALEJANDRO S. PASTOR, In an Order dated November 28, 1994, the trial court confirmed the award of
JR., ANTONIO U. MIRANDA, and MIGUEL M. ANTONIO, as Minority Stock the Arbitration Committee.
Holders of Marinduque Mining and Industrial Corporation, respondents. The petitioner filed its motion for reconsideration; special civil action for
certiorari; petition for review on certiorari.
Facts: ISSUE:
 Whether or not the RTC of Makati, Branch 62, has jurisdiction to confirm the granting licenses under the same, and collecting royalties, and for the establishment
arbitral award of herein Petitioner Tuna Processors, Inc. (TPI).
 Whether or not the Arbitration Committee can resolve issues beyond the
scope of the arbitration agreement Due to a series of events not mentioned in the Petition, the tuna processors, including
RULING: Respondent KINGFORD, withdrew from Petitioner TPI and correspondingly reneged
Admittedly the correct procedure was for the parties to go back to the court on their obligations. Petitioner TPI submitted the dispute for arbitration before the
where the case was pending to have the award confirmed by said court. However, International Centre for Dispute Resolution in the State of California, United States
Branch 62 made the fatal mistake of issuing a final order dismissing the case. By its and won the case against Respondent KINGFORD.
own action, Branch 62 had lost jurisdiction over the case. It could not have validly
reacquired jurisdiction over the said case on mere motion of one of the parties. The To enforce the award, Petitioner TPI filed a Petition for Confirmation, Recognition,
Rules of Court is specific on how a new case may be initiated and such is not done by and Enforcement of Foreign Arbitral Award before the RTC of Makati City.
mere motion in a particular branch of the RTC. Consequently, as there was no Respondent KINGFORD filed a Motion to Dismiss, which the RTC denied for lack of
“pending action” to speak of, the petition to confirm the arbitral award should have merit. Respondent KINGFORD then sought for the inhibition of the RTC judge, Judge
been filed as a new case and raffled accordingly to one of the branches of the Alameda, and moved for the reconsideration of the order denying the Motion. Judge
Regional Trial Court. Alameda inhibited himself notwithstanding “[t]he unfounded allegations and
As a rule, the award of an arbitrator cannot be set aside for mere errors of unsubstantiated assertions in the motion.” Judge Ruiz, to which the case was re-
judgment either as to the law or as to the facts. Nonetheless, the arbitrators’ awards is raffled, in turn, granted Respondent KINGFORDS’s Motion for Reconsideration and
not absolute and without exceptions. The arbitrators cannot resolve issues beyond dismissed the Petition on the ground that Petitioner TPI lacked legal capacity to sue in
the scope of the submission agreement. The parties to such an agreement are bound the Philippines. Petitioner TPI is a corporation established in the State of California
by the arbitrators’ award only to the extent and in the manner prescribed by the and not licensed to do business in the Philippines.
contract and only if the award is rendered in conformity thereto. Thus, Sections 24
and 25 of the Arbitration Law provide grounds for vacating, rescinding or modifying an Hence, the present Petition for Review on Certiorari under Rule 45.
arbitration award. Where the conditions described in Articles 2038, 2039 and 2040 of
the Civil Code applicable to compromises and arbitration are attendant, the arbitration ISSUE:
award may also be annulled.
 The arbitrators shall have the power to decide only those matters which have Whether or not a foreign corporation not licensed to do business in the Philippines,
been submitted to them. The terms of the award shall be confined to such but which collects royalties from entities in the Philippines, sue here to enforce a
disputes. (Otherwise, the arbitration award may be vacated, rescinded, foreign arbitral award?
modified or annulled.)
ARGUMENT:
Tuna Processing v. Philippine Kingford
G.R. No. 185582, February 29, 2012
Petitioner TPI contends that it is entitled to seek for the recognition and enforcement
of the subject foreign arbitral award in accordance with RA No. 9285 (Alternative
FACTS:
Dispute Resolution Act of 2004), the Convention on the Recognition and Enforcement
of Foreign Arbitral Awards drafted during the United Nations Conference on
Kanemitsu Yamaoka, co-patentee of a US Patent, Philippine Letters Patent, and an
International Commercial Arbitration in 1958 (New York Convention), and the
Indonesian Patent, entered into a Memorandum of Agreement (MOA) with five
UNCITRAL Model Law on International Commercial Arbitration (Model Law), as none
Philippine tuna processors including Respondent Philippine Kingford, Inc.
of these specifically requires that the party seeking for the enforcement should have
(KINGFORD). The MOA provides for the enforcing of the abovementioned patents,
legal capacity to sue.
e. The award has not yet become binding on the parties, or has been set aside or
RULING: suspended by a competent authority of the country in which, or under the law of
which, that award was made.
YES. Petitioner TPI, although not licensed to do business in the Philippines, may seek
recognition and enforcement of the foreign arbitral award in accordance with the 2. Recognition and enforcement of an arbitral award may also be refused if the
provisions of the Alternative Dispute Resolution Act of 2004. A foreign corporation’s competent authority in the country where recognition and enforcement is sought finds
capacity to sue in the Philippines is not material insofar as the recognition and that:
enforcement of a foreign arbitral award is concerned. a. The subject matter of the difference is not capable of settlement by arbitration
The Resolution of the RTC is REVERSED and SET ASIDE. under the law of that country; or
b. The recognition or enforcement of the award would be contrary to the public policy
RATIO DECIDENDI: of that country.

Sec. 45 of the Alternative Dispute Resolution Act of 2004 provides that the opposing Not one of the abovementioned exclusive grounds touched on the capacity to sue of
party in an application for recognition and enforcement of the arbitral award may raise the party seeking the recognition and enforcement of the award.
only those grounds that were enumerated under Article V of the New York
Convention, to wit: Pertinent provisions of the Special Rules of Court on Alternative Dispute Resolution,
Article V which was promulgated by the Supreme Court, likewise support this position.
1. Recognition and enforcement of the award may be refused, at the request of the
party against whom it is invoked, only if that party furnishes to the competent authority Rule 13.1 of the Special Rules provides that “[a]ny party to a foreign arbitration may
where the recognition and enforcement is sought, proof that: petition the court to recognize and enforce a foreign arbitral award.” The contents of
such petition are enumerated in Rule 13.5. Capacity to sue is not included.
a. The parties to the agreement referred to in Article II were, under the law applicable Oppositely, in the rule on local arbitral awards or arbitrations in instances where “the
to them, under some incapacity, or the said agreement is not valid under the law to place of arbitration is in the Philippines,” it is specifically required that a petition “to
which the parties have subjected it or, failing any indication thereon, under the law of determine any question concerning the existence, validity and enforceability of such
the country where the award was made; arbitration agreement” available to the parties before the commencement of
b. The party against whom the award is invoked was not given proper notice of the arbitration and/or a petition for “judicial relief from the ruling of the arbitral tribunal on a
appointment of the arbitrator or of the arbitration proceedings or was otherwise unable preliminary question upholding or declining its jurisdiction” after arbitration has already
to present his case; commenced should state “[t]he facts showing that the persons named as petitioner or
c. The award deals with a difference not contemplated by or not falling within the respondent have legal capacity to sue or be sued.”
terms of the submission to arbitration, or it contains decisions on matters beyond the
scope of the submission to arbitration, provided that, if the decisions on matters Indeed, it is in the best interest of justice that in the enforcement of a foreign
submitted to arbitration can be separated from those not so submitted, that part of the arbitral award, the Court deny availment by the losing party of the rule that bars
award which contains decisions on matters submitted to arbitration may be foreign corporations not licensed to do business in the Philippines from maintaining
recognized and enforced; a suit in Philippine courts. When a party enters into a contract containing a
d. The composition of the arbitral authority or the arbitral procedure was not in foreign arbitration clause and, as in this case, in fact submits itself to arbitration, it
accordance with the agreement of the parties, or, failing such agreement, was not in becomes bound by the contract, by the arbitration and by the result of arbitration,
accordance with the law of the country where the arbitration took place; or conceding thereby the capacity of the other party to enter into the contract,
participate in the arbitration and cause the implementation of the result. Although not
on all fours with the instant case, also worthy to consider is the wisdom of then
Associate Justice Flerida Ruth P. Romero in her Dissenting Opinion in Asset
Privatization Trust v. Court of Appeals [1998], to wit:

xxx Arbitration, as an alternative mode of settlement, is gaining adherents in


legal and judicial circles here and abroad. If its tested mechanism can simply be
ignored by an aggrieved party, one who, it must be stressed, voluntarily and actively
participated in the arbitration proceedings from the very beginning, it will destroy the
very essence of mutuality inherent in consensual contracts.

Clearly, on the matter of capacity to sue, a foreign arbitral award should be respected
not because it is favored over domestic laws and procedures, but because Republic
Act No. 9285 has certainly erased any conflict of law question.

Finally, even assuming, only for the sake of argument, that the RTC correctly
observed that the Model Law, not the New York Convention, governs the subject
arbitral award, Petitioner TPI may still seek recognition and enforcement of the award
in Philippine court, since the Model Law prescribes substantially identical exclusive
grounds for refusing recognition or enforcement.

Вам также может понравиться