Академический Документы
Профессиональный Документы
Культура Документы
net/publication/323414160
CITATIONS READS
0 4,779
2 authors, including:
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
Evaluation of Consumer Preference and Assessment of Factors Determining Acceptance of Solar Energy Products View project
All content following this page was uploaded by Jagdish Raj Saini on 27 February 2018.
• All investments being considered for inclusion in the capital budget has
the same risk as those of the existing investments of the firm. – A
simplifying assumption.
• This explains the usage of average cost of capital for project evaluation.
Techniques of risk
analysis
Break-even Hillier
analysis model
• International risk: In case of a foreign project, the earnings and cash flows may
be different than expected due to exchange rate risk or political risk.
Perspectives of Project Risk
• Stand-alone risk: This represents the risk of a project when it is
viewed in isolation.
• Corporate risk: Represents the contribution of a project to risk of
the firm.
• Market risk: Risk of a project from the point of view of a
diversified investor. It is also called systematic risk.
• Sensitivity analysis is a way of analysing change in the project’s NPV (or IRR)
for a given change in one of the variables.
Range NPV
Key Variables Pessimistic Expected Optimistic Pessimistic Expected Optimistic
Investment 24 20 18 - 0.65 2.60 4.22
Sales 15 18 21 - 1.17 2.60 6.40
VC as Sales% 70 66.67 65 0.34 2.60 3.73
Fixed Costs 1.3 1 0.8 1.47 2.60 3.33
Sensitivity Analysis
Merits:
• Indicates how robustness or vulnerability of a project to changes in underlying
variables.
• If NPV is highly sensitive to changes in some factor, it may be worthwhile to
explore how the variability of that critical factor may be contained.
• Articulates the concerns of project evaluators, thus having intuitive appeal.
Limitations:
• Merely shows what happens to NPV when there is a change in some variable.
It doesn’t indicate the likelihood of such variations.
• Typically, in sensitivity analysis only one variable is changed at a time. In real
world, though, variables tend to move together.
• Inherently subjective. Same sensitivity analysis may lead one decision maker to
accept the project while another may reject it.
• It fails to focus on the interrelationship between variables. For example, sale
volume may be related to price and cost. A price cut may lead to high sales and
low operating cost.
Scenario Analysis
• A major limitation of sensitivity analysis amounts to the assumption of only a
single variable varying at a time.
• Scenario Analysis addresses this concern by permitting variations in several key
variables of a project simultaneously.
• Specifically it indicates the impact on project NPV (i.e. DV) resulting from changes
in multiple influencing project variables (i.e. IDVs) at one go.
Limitations:
• Based on assumption that there are a few well-delineated scenarios. This may not
be true in many cases. A situation can exist anywhere on the continuum between
extremes.
Converting a continuum into discrete states of nature leads to loss of information.
• It expands the concept of value estimation. As the number of inputs variables go
up, need for value estimates multiplies exponentially.
PESSIMISTIC, NORMAL AND OPTIMISTIC SCENARIO
• Variable costs to sales is 0.667. This means that every rupee of sales makes a contribution
of Rs. 0.333. Hence, Break-even sales will be:
(Fixed costs + Depreciation) ÷ Contribution margin ratio = (1 + 2) million/0.333 = Rs. 9 million
Contribution Margin Ratio = 1 – (Variable Cost ÷ Sales)
Break Even Analysis
Cash Break-Even Point
• Defined as the level of sales at which the firm neither makes a cash profit
nor incurs a cash loss.
Cash Break-even sales = Fixed costs ÷ Contribution margin ratio
= 1 million ÷ 0.333 = Rs. 3 million
• Financial break even analysis evidences that the annual cash-flow of project
depends on sales.
Break Even Analysis
Financial Break-Even Point
1 Variable Costs 66.67 % of sales
2 Contribution 33.33% of sales
3 Fixed Costs Rs. 1 million
4 Depreciation Rs. 2 million
5 Pre-tax Profit (0.333 x sales) – Rs. 3 million
6 Tax (at 33.3%) 0.333 (0.333 sales – Rs. 3 million)
7 PAT 0.667 (0.333 x sales – Rs. 3 million)
8 Cash flow (4+7) Rs. 2 million + 0.667(0.333 x sales – Rs. 3 million)
= 0.222 sales
Assume the cash flows to be independent. Calculate the expected NPV and
standard deviation of NPV considering a discount rate of 12 percent.
Managing Risk
• Ultimate aim of managers is not merely measuring risk,
but rather containment and mitigation of risks.
• Derivatives:
An option gives its owner the right to buy or sell an underlying asset on or
before a given date at a predetermined price
A futures contract is an agreement between two parties to exchange an
asset for cash at a predetermined future date for a price specified today. It
eliminates price risk.
Managing Risk
• Shorter Time to Market:
A way to reduce uncertainty is cutting time to market.
Enables early generation of revenues on investments.
Reduced risk exposure owing to need for anticipating customers needs and
preferences for a shorter time frame.
• Contingency Planning:
Apart from undertaking risk reduction measures, well managed firms
prepare for the worst.
Listing the things that could go wrong with a decision and then identifying
the actions that would be taken to cope with those adverse developments.
Project Selection under Risk
(Conventional techniques of risk analysis)
• Judgmental Evaluation
k = kf + kr
• RADR accounts for risk by varying the discount rate depending on the degree
of risk of projects.
• A higher discount rate will be used for riskier projects and a lower rate for less
risky projects.
• NPV will decrease with increasing k, indicating less chance of acceptance of
riskier projects.
31
Project Selection Under Risk (Conventional techniques of risk analysis)
• Risk Adjusted Discount Rate (RADR)
Project Risk = Risk of Existing Investments…….Discount Rate = Firm’s WACC
Project Risk > Risk of Existing Investments…….Discount Rate > Firm’s WACC
Project Risk < Risk of Existing Investments…….Discount Rate < Firm’s WACC
K = Kr + n + dk
K: RADR
Kr: Risk free rate of interest,
n: Adjustment for firm’s normal risk, and
dk: Adjustment for the differential risk of project k
dk: Can be either positive or negative
Limitations:
There is no easy way of deriving a risk-adjusted discount rate. CAPM provides
a basis of calculating the risk-adjusted discount rate.
It does not make any risk adjustment in the numerator for the cash flows that
are forecast over the future years.
34
Project Selection Under Risk (Conventional techniques of risk analysis)
Certainty Equivalent Method:
• Reduce the forecasts of cash flows to some conservative levels.
The certainty-equivalent coefficient assumes a value between 0
and 1, and varies inversely with risk. Decision-maker subjectively
or objectively establishes the coefficients.
n
t NCFt
NPV =
(1 kf )
t
t =0
37
Certainty Equivalent Method
A project involves an outlay of Rs. 1,00,000. Its expected cash inflow at the
end of first year is Rs. 40,000. Thereafter it decreases annually by Rs.
2,000. It has an economic life of 6 years. The certainty equivalent factor is
αt = 1 – 0.05t. Calculate NPV of the project if the risk free rate of return is
10%.
Year Expected Certainty Certainty Equivalent Discount Factor@10% Present
Cash Flow Equivalent Factor Value Value
0
1
2
3
4
5
6
NPV = Rs. 31098
References:
• Prasanna Chandra, Financial Management – Theory & Practice 9th
Ed, McGraw Hill Education (ISBN: 978-00-7107-840-5).
• I.M. Pandey, Financial Management 11th Ed, Vikas Publishing