PT ASIA PACIFIC RAYON

VISCOSE DEPTT
NDT Checking Schedules and Frequency
DONE NOT DONE Apr-12
Sl Equipments Frequency Parameter Day / Week /
No. to be checked Month 1 2 3 4
A. Critical Equipments

1 Shredders Fortnightly Vibration and 1st & 3rd week


Bearing Condition
2 CD Fans Monthly Vibration and 1st week
Bearing Condition

3 NUCON Blower Weekly Spike energy and Every


Temperature Sautrday

4 Sim Exhaust fans Weekly Spike energy and Every


Temperature Sautrday

5 All Vacuum pumps Weekly Spike energy and Every


Temperature Sautrday

6 Sim two speed GB Monthly Acceleration 2nd week

7 Simplex motor Quarterly Spike energy and Jan, Apr , Jul , Oct

8 Dissolver GB Monthly Acceleration 2nd week

9 Dissolver Motor Monthly Bearing Condition 2nd week

10 NH3 chillers Monthly Vibration 4th week

11 Belt conv and Monthly Bearing Condition 3rd week


Screw conv for Churn

12 Soft water booster, Fortnightly Bearing Condition 2nd week


transfer pumps 4 th week

13 ABS Caustic pumps Fortnightly Bearing Condition 2nd week


4 th week
B Equipments other than
Critical Equipments

Section : A Monthly Bearing Condition 1st week


Sl Pr system ,
NUCON system
Maturing Drum system
Air washer system

Section : B Monthly Bearing Condition 2nd week


Xanthator system,
Dissolver system ,
Blender system

Section : C Monthly Bearing Condition 3rd week


Soda station system,
Pulpers system

Section : D Monthly Bearing Condition 4th week


Refrigeration system
Ripening
Air Compressor
PT ASIA PACIFIC RAYON
NON DESTRUCTIVE TEST
Viscose Critical Schedules and Frequency

Sl Equipments Parameter January February March April May June


No. to be checked 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
A. Critical Equipments

1 Shredders Vibration and


Bearing Condition
2 CD Fans Vibration and
Bearing Condition

3 NUCON Blower Spike energy and


Temperature

4 Sim Exhaust fans Spike energy and


Temperature

5 All Vacuum pumps Spike energy and


Temperature

6 Sim two speed GB Acceleration

7 Simplex motor Spike energy and

8 Dissolver GB Acceleration

9 Dissolver Motor Bearing Condition

10 NH3 chillers Vibration

11 Belt conv and Bearing Condition


Screw conv for Churn

12 Soft water booster, Bearing Condition


transfer pumps

13 ABS Caustic pumps Bearing Condition

Print date : Jan 08


B Equipments other than
Critical Equipments

Section : A Bearing Condition


Sl Pr system ,
NUCON system
Maturing Drum system
Air washer system

Section : B Bearing Condition


Xanthator system,
Dissolver system ,
Blender system

Section : C Bearing Condition


Soda station system,
Pulpers system

Section : D Bearing Condition


Refrigeration system
Ripening
Air Compressor