Академический Документы
Профессиональный Документы
Культура Документы
INSTALLATION
OVERVIEW
PART 2 - PIPELINES
CONVENTIONAL OFFSHORE
INSTALLATION
C.MARGOT
SUMMARY
• PIPELAYING VESSELS 3
• PIPELAYING OPERATIONS 15
• BURIAL 74
• RISERS 81
• ABOVE WATER TIE-IN 88
• DIVING WORKS 97
• PRE-COMMISSIONING 123
• ANNEXES 163
Semac 1 production welding
SONSUB ROVs presentation
BELUGA animation
Offshore course 2
M
m
p
nS
itra
d
e
rvis
e
S
Llc
PIPELAYING VESSELS
C. MARGOT
SAIPEM PIPELAYING VESSELS
Offshore course 4
SAIPEM PIPELAYING VESSELS
SAIPEM 7000 J-Lay + HLV
Offshore course 5
SAIPEM PIPELAYING VESSELS
SAIBOS FDS J-Lay
Offshore course 6
SAIPEM PIPELAYING VESSELS
SEMAC 1
Offshore course 7
SAIPEM PIPELAYING VESSELS
CASTORO II DLB
Offshore course 8
SAIPEM PIPELAYING VESSELS
CASTORO 6
Offshore course 9
SAIPEM PIPELAYING VESSELS
CASTORO 8 + HLV
Offshore course 10
SAIPEM PIPELAYING VESSELS
CASTORO 10 + Postrenching
Offshore course 11
SAIPEM PIPELAYING VESSELS
CRAWLER DLB
Offshore course 12
SAIPEM PIPELAYING VESSELS
BOS 355
Offshore course 13
SAIPEM PIPELAYING VESSELS
SAIBOS 230
Offshore course 14
1: INSTALLATION OF PIPELINES AND
RISERS
Offshore course 15
1: INSTALLATION OF PIPELINES ET RISERS
Offshore course 18
PIPELAYING
SEMAC 1 Fixed STINGER
Offshore course 19
1: INSTALLATION OF PIPELINES ET RISERS
Reel lay is generally used for steel pipes up-to 16” OD without concrete
coating.
Offshore course 20
PIPE LAYING
Reel Lay
Offshore course 21
1: INSTALLATION OF PIPELINES AND
RISERS
S7000 FDS
Canyon express
12” OD
1” wt
2220 m WD
Offshore course 23
PIPE LAYING
STEEP – S Lay
Offshore course 24
1: INSTALLATION OF PIPELINES AND
RISERS
Offshore course 27
Castoro 8 firing line
Offshore course 28
Foxtrot Project
Offshore course 29
12 / 4 inches bundle line-up on Foxtrot with Castoro 8
Offshore course 30
WS 1 – Root & 1st pass with PASSO two bugs single torch
Offshore course 31
Grinding of the weld
Offshore course 32
Piggy-back saddle
Offshore course 33
Offshore course 34
SCHEMATIC LAYING CYCLE WITH CASTRO 10
Offshore course 35
CASTORO 10 - Pipe Construction Sequence
Plan View
CASTORO 10 - Pipe Construction Sequence
Loadout Barge and Tug.
AHT
Tug
Loadout Barge
CASTORO 10 - Pipe Construction Sequence
Pipe joints are lifted from the pipehaul vessel to pipe storage racks
on Castoro 10.
Bevelling Stations
3” Piggyback line
Banding Station
12” Pipeline
Side View
CASTORO 10 - Pipe Construction Sequence
Pipe joints enter the firing line from the bevelling stations at
Station No.1
Station No.1
Root / Hot Pass
Station No.1
Root / Hot Pass
Station No.1
Root / Hot Pass
Station No.1
Root / Hot Pass
Station No.2
Fill
3
Weld Deposit
CASTORO 10 - Pipe Construction Sequence
Station No.3 Station No.2
Cap
Weld Cap
CASTORO 10 - Pipe Construction Sequence
Station No.4 Station No.2
Cap
6m
* Taut wire
One wire cable sling is installed from the surface and connected to the
mid-level of the jacket. The upper eye of this wire is connected to the
head of the pipe on the stern of the barge.
Offshore course 51
1: INSTALLATION OF PIPELINES AND
RISERS
* Launched riser
Offshore course 52
1: INSTALLATION OF PIPELINES AND
RISERS
Offshore pipelines have very often an interface with the onshore works.
This interface consists to built the pipeline transition through the shore
crossing and the surf zone generally called shore approach.
Offshore course 54
CPC shore pull with S355
Offshore course 55
Pipeline Pulling Activities
Offshore course 56
CPC shore pull
Offshore course 57
1: INSTALLATION OF PIPELINES AND
RISERS
Offshore course 58
FTIP
DJENO
Offshore course 59
Djeno warf
Offshore course 60
1: INSTALLATION OF PIPELINES AND
RISERS
Offshore course 61
1: INSTALLATION OF PIPELINES AND
RISERS
Offshore course 62
GAMBA – West Africa
Offshore course 63
Offshore course 64
Pipeline Pulling Activities
Offshore course 65
Offshore course 66
Pipeline Pulling Activities
Offshore course 67
1: INSTALLATION OF PIPELINES AND
RISERS
In case the configuration of the coast does not allow a standard shore
approach (cliffs, rocky coast, extreme slope) or in case the client requires
a very important burial depth at the shore crossing and near shore, one
solution consists in a HDD which could be more economical that a long
cofferdam.
The most common method for HDD briefly consists in drilling from
shore towards the sea side a pilot hole then to perform a back reaming
while injecting bentonite to maintain the hole against collaps. Once the
hole is completed, the drill pipe is connected onto the pre-laid pipeline
string and then pulled through Offshore
the holecourse
using the drilling rig. 68
Schematic River crossing by HDD
Offshore course 69
1: INSTALLATION OF PIPELINES AND
RISERS
*Concrete coating (protects the steel and the anti-corrosion coating from
shocks and increases the submerged weight for stability purpose.
*Burial / backfilling (to protect the pipe from shocks , strong current and
waves effects)
*Rock dumping ( when the soil is too hard to proceed with the burial
below seabed.
*Bitumen or concrete mattress. Generally used on the risers dog-leg or
on crossings.
Offshore course 70
Offshore course 71
Offshore course 72
Offshore course 73
1: INSTALLATION OF PIPELINES AND
RISERS
Offshore course 74
Offshore course 75
Offshore course 76
Offshore course 77
PIPELAYING
PLOWING
Offshore course 78
PIPELAYING
TRENCHING
Offshore course 79
PIPELAYING
TRENCHING
Offshore course 80
1: INSTALLATION OF PIPELINES AND
RISERS
O 1.7 Risers
The connection of a pipeline to a platform is made via a riser.
These risers can be pre-installed on a jacket during fabrication or field
installed afterwards.
In case the riser is pre-installed, the junction pipeline / riser can be
executed only by installing a subsea spool. This spool is generally fixed
by means of flanges, but can also be welded in place using hyperbaric
welding (most costly solution).
In case the riser is installed after the installation of the jacket, it can be
either welded at the extremity of the pipe during initiation (launched
riser) or after pipe installation (riser stalk-on) with pipe lifting to the
surface by means of davits.
Offshore course 81
Riser at TUNU- Kalimatan
Offshore course 82
Offshore course 83
RISER 32” TTM – CKR
Castoro 2
Offshore course 84
Offshore course 85
Offshore course 86
Offshore course 87
M
m
p
nS
itra
d
e
rvis
e
S
Llc
ABOVE WATER
TIE IN
12” SIRRI-IRAN
S355
C. MARGOT
Offshore course 89
Offshore course 90
ABOVE WATER
TIE IN
Offshore course 91
Offshore course 92
Offshore course 93
Offshore course 94
Offshore course 95
Offshore course 96
1: INSTALLATION OF PIPELINES AND
RISERS
O 1.7 Pre-commissioning
Once a pipeline has been laid and its risers connected to the platforms,
the pre-commissioning operations can start.
Offshore course 97
1: INSTALLATION OF PIPELINES AND
RISERS
O 1.7 Pre-commissioning
Then, if the gauging plate inspection is satisfactory, the pressure test of
the entire pipeline is carried out at 1.5 times its operating pressure or
1.25 time the design pressure and shall be held 8, 24 or 48 hours without
pressure drop, with a permanent monitoring and recording of all
parameters. After the successful test, the line is depressurized and if
required, dewatered, dried and purged.
Offshore course 98
Next:
SEMAC 1 PRODUCTION WELDING
ROVs PRESENTATION
BELUGA
C.MARGOT