Main Contractor Progress Report No. 1
Held on 27/6/2018
Content Table
11.0 Others
11.1 Site Environmental Report No. 1
11.2 Safety Report No. 1
第 1 頁,共 14 頁
Main Contractor Progress Report No. 1
Held on 27/6/2018
Main Contract for Property Improvement Works at Lei Yue Mun Public Riding School for The Hong Kong Jockey Club
Remarks:
(a) Notice of Delay (N.O.D.) in respect of the following are issued:
Item Issued Date Subject EOT Claimed EOT Granted Further
Nil
第 2 頁,共 14 頁
Main Contractor Progress Report No. 1
Held on 27/6/2018
Main Contract for Property Improvement Works at Lei Yue Mun Public Riding School for The Hong Kong Jockey Club
B. This Report
A: Builder's B: B.S.
Programme 1.80% 0.00%
Actual Progress 2.43% 0.00%
Ahead / Behind 0.63% 0.00%
第 3 頁,共 14 頁
Main Contractor Progress Report No. 1
Held on 27/6/2018
Main Contract for Property Improvement Works at Lei Yue Mun Public Riding School for The Hong Kong Jockey Club
9 Package 1 Admin Block Site Setting out, mobilization, Site survey & condition survey/ mapping survey
Site work for Ground Treatment, Excavation trial trench to identify the underground
10
obstruction & others
Section 1A
46 Material Submission
第 4 頁,共 14 頁
Main Contractor Progress Report No. 1
Held on 27/6/2018
Main Contract for Property Improvement Works at Lei Yue Mun Public Riding School for The Hong Kong Jockey Club
第 5 頁,共 14 頁
Chi Sum Engineering Ltd.
Lei Yue Mun Public Riding School
Master Programme (Rev.0) 27/5/18
11/6/2018 26/7/2018
識別碼 任務名稱 工期 開始時 完成時間
2018年下半年 2019年上半年 2019年下半年
間
六月 七月 八月 九月 十月 十一月 十二月 一月 二月 三月 四月 五月 六月 七月 八月 九月 十月 十一月
1 Whole of work 534 days? 2018/6/11 2019/11/26
2 Section 1- Lei Yue Mun Public Riding school 414 days? 2018/6/11 2019/7/29
3 Package 1&2 Contact Period 414 days 2018/6/11 2019/7/29
5 Set up 3 nos container , 1 no Stores, Contractor office at car park area 36 days? 2018/6/11 2018/7/16
6 Package 1 Administration Block New Annex Block 413 days? 2018/6/11 2019/7/29
7 Submission of form BA10 A&A work Notice of Commencement 7 days 2018/6/11 2018/6/17
8 Consent Application for ground Treatment 29 days 2018/6/18 2018/7/16
9 Site Setting out ,mobilization, Site survey & condition survey/ mapping 36 days 2018/6/11 2018/7/16
survey
10 Site work for Ground Treatment ,Excavation trial trench to identify the 29 days 2018/7/17 2018/8/14
underground obstruction & others
11 Site Test and Laboratory test for Soil Condition 29 days 2018/8/15 2018/9/12
14 Submission of Method Statement for Plate Load Test 64 days 2018/7/17 2018/9/18
39 (Omission Removal of Existing car park Shelter)(Provisional Sum for 30 days 2019/6/16 2019/7/16
Change to Make good the Structural member and Cladding completing with
Painting work only)
40 Package 2 Paddock & Car Park 30 days? 2019/6/16 2019/7/15
41 Omission : removal & construction of Judge's stand(Provisional 30 days? 2019/6/16 2019/7/15
sum)(change to painting)
42 Section 1A (120days) 116 days 2018/7/24 2018/11/16
43 Package 1 - Stable Block (Remodeling works of Mafoo's Quarter and 116 days 2018/7/24 2018/11/16
Senior Instructor Unit at 2/F)
56 Stable Block -Straw Store floor finish remove and apply new, Existing 30 days 2018/11/17 2018/12/16
Chute to be removed ,opening to be deck up at 1/F
57 Stable Block -Protective barrier at 1/F( Existing railing & Gate to be 30 days 2018/12/17 2019/1/15
replaced)
58 Stable Block -bi Folding partition 1/F (Folding door to be replaced at 30 days 2018/12/17 2019/1/15
corridor)
59 External -removal external existing Wood shaving Store at G/F (near 30 days 2018/12/17 2019/1/15
washing bay)
60 Package 2-Paddock & External 60 days? 2019/1/16 2019/3/16
61 External -Omission for Remodeling of existing washing bay( Provisional 30 days 2019/1/16 2019/2/14
sum Change to Make good work only)
62 Paddock- Omission for Removal and Construction of Shelter (Provisional 30 days 2019/2/15 2019/3/16
sum for Change to painting under Section 1 package 1)
63 Modification of existing paddock fence rail and gate 60 days? 2019/1/16 2019/3/16
64 Relocation of existing water spray point 30 days? 2019/2/15 2019/3/16
65
66 Section 3 (90 days) 90 days 2019/3/17 2019/6/14
68 Remodeling of existing Farrier and store at G/F(BA 14)and (omission metal 90 days 2019/3/17 2019/6/14
roof , Provisional sum change to Painting )
69 Omission work: Removal and Construction of Manure Chute(BA 14) 90 days 2019/3/17 2019/6/14
70 Omission work:Removal and Construction of A/C rack & cat 90 days 2019/3/17 2019/6/14
ladder(provisional sum for make good)
71 Package -2 - stable block 90 days 2019/3/17 2019/6/14
79 Construction of golf cart parking (BA 14) 120 days 2019/7/30 2019/11/26
80 Remodelling of existing Senior Instructor Quarter at 1/F (BA 14) 120 days 2019/7/30 2019/11/26
第 7 頁,共 14 頁
Chi Sum Engineering Ltd 2018/6/26
Project: Main Contract for Property Improvement Works at Lei Yue Mun Publi Riding School for The Hong Kong Jockey Club
Shop Drawing Submission Schedule For Builder's Work
Initial Issue Date : Prepared By :
Updated on: 26-Jun-18 Revision : 0 Checked By :
ACTUAL
Distribution Drawing
Letter 1st Submission Letter 2nd Submission Letter 3rd Submission Letter Approval Date
Drawing No Rev Drawing Title Date Reference Rev Remarks
Ref. Date Reference Ref. Date Reference Ref. Date Reference Ref.
If Any
Comment Status Comment Status Comment Status Reference Reference
A : Approved ; B : Approved with condition ; C : Rejected, re-submission required Page 1 of 1 3.1a LYMPRS-Builder Shop Drawing Submission Schedule (2018-06-26)\ Builder
2018/6/26
CSD Drawing
A : Approved ; B : Approved with condition ; C : Rejected, re-submission required Page 1 of 6 3.1b LYMPRS-BS Shop Drawing Submission Schedule (2018-06-26)\ CSD
2018/6/26
CBWD Drawing
A : Approved ; B : Approved with condition ; C : Rejected, re-submission required Page 2 of 6 3.1b LYMPRS-BS Shop Drawing Submission Schedule (2018-06-26)\ CBWD
2018/6/26
EL Installation
A : Approved ; B : Approved with condition ; C : Rejected, re-submission required Page 3 of 6 3.1b LYMPRS-BS Shop Drawing Submission Schedule (2018-06-26)\ EL
2018/6/26
MVAC Installation
A : Approved ; B : Approved with condition ; C : Rejected, re-submission required Page 4 of 6 3.1b LYMPRS-BS Shop Drawing Submission Schedule (2018-06-26)\ AC
2018/6/26
FS Installation
A : Approved ; B : Approved with condition ; C : Rejected, re-submission required Page 5 of 6 3.1b LYMPRS-BS Shop Drawing Submission Schedule (2018-06-26)\ FS
2018/6/26
Plumbing Installation
Drainage Installation
A : Approved ; B : Approved with condition ; C : Rejected, re-submission required Page 6 of 6 3.1b LYMPRS-BS Shop Drawing Submission Schedule (2018-06-26)\ P&D
Main Contractor Progress Report No. 1
Held on 27/6/2018
Main Contract for Property Improvement Works at Lei Yue Mun Public Riding School for The Hong Kong Jockey Club
第 8 頁,共 14 頁
Chi Sum Engineering Ltd Revision Date: 21/6/2018
第1頁
Project:Property Improvement Works at Lei Yue Mun Public Riding Schools
3. Waterproofing
5. Plastering
5.6 Skim Coat Ceiling Plastering (Ceiling & Wall) Optimix / PRC
Chi Sum Engineering Ltd Revision Date: 21/6/2018
第2頁
Project:Property Improvement Works at Lei Yue Mun Public Riding Schools
7 Finishes
8. Furniture
9. Container
9.1 Arch-001 Movable Container Office Chief Container Services Co. Ltd. - 29-May-2018 12-Jun-2018 Arch-009 B B
29-May-2018 31-May-2018 29-May-2018
PTP's comment by email:
1. Please check site condition if any conflict for door opening
2. Lighting Layout is missing at container A.
3. 13A socket outlet marked (*) not match with architectural layout
10.1 Arch-002 Sound Level Meter Aco / Easy-to-use / Japan - 8-Jun-2018 22-Jun-2018 Arch-0023
8-Jun-2018
10.2 SE-001 Vibaration Meter Promat / Nomis / USA - 8-Jun-2018 22-Jun-2018 Arch-0023
8-Jun-2018
10.4 SE-003 Tilt Meter RST / Portable MEMS / Canada - 8-Jun-2018 22-Jun-2018
Plumbing
Drainage
5 EL-05 RCD
6 EL-06 Isolator
12 EL-12 Contactor
14 EL-14 FR Cable
Lighting Fitting
9 AC-09 GI Conduit
第 9 頁,共 14 頁
Main Contractor Progress Report No. 1
Held on 27/6/2018
Main Contract for Property Improvement Works at Lei Yue Mun Public Riding School for The Hong Kong Jockey Club
Consultant's
Item Issued Date Ref. no. Subject Cost Time
Reply
第 10 頁,共 14 頁
Main Contractor Progress Report No. 1
Held on 27/6/2018
Main Contract for Property Improvement Works at Lei Yue Mun Public Riding School for The Hong Kong Jockey Club
Consultant's
Item Issued Date Ref. no. Subject Cost Time
Reply
Nil
第 11 頁,共 14 頁
Main Contractor Progress Report No. 1
Held on 27/6/2018
Main Contract for Property Improvement Works at Lei Yue Mun Public Riding School for The Hong Kong Jockey Club
Building Services This Report Total No. No. Answered No. Outstanding
No. of query sheet issued
第 12 頁,共 14 頁
Main Contractor Progress Report No. 1
Held on 27/6/2018
Main Contract for Property Improvement Works at Lei Yue Mun Public Riding School for The Hong Kong Jockey Club
8.5.2 MVAC
Percentage Completion of
% in Contract Commencement Date Completion Date
Item Description of Work Activities Work Done
Cost
Scheduled Actual Scheduled Actual Scheduled Actual
1
2
3
4
5
Total % in AC Contract: Overall % Completion:
第 13 頁,共 14 頁
Chi Sum Engineering Ltd
11.1 Monthly Environmental Report No.1
(Reporting Period: 11/6/2018 to 26/6/2018)
Project: Main Contract for Property Improvement Works at Lei Yue Mun Public Riding School
for The Hong Kong Jockey Club
Director
Mr. Tsang Ching Lun, Edwin
Project Manager
Mr. Kwan Yuk Lam
Site Agent
Mr. Choi Chi Chiu
Environmental Supervisor
Mr. Yu Jiande
3. Monthly Record Summary to record daily disposal of construction& demolition (C&D) materials from the Site
Total Number of Truck Total Ton of Waste
Date Facility
per month per month
0 0
SL-01
SL-03 SL-04
SL-05
SL-06
SL-07
Chi Sum Engineering Ltd Daily Record for Sound Level Checking
Date: ____________ to ____________
Project: Main Contract for Property Improvement Works at Lei Yue Mun Public Riding School for The Hong Kong Jockey Club (CS/2015/039)
Superstructure Works (Soil Treatment, Drainage Alteration & Addition Works) for Proposed New Toilet Tower
Date: 11-6-2018
SL-01 SL-02 SL-03 SL-04 SL-05 SL-06 SL-07
Initial Readings 56.1 57.7 55.4 59.4 63.7 64.7 55.1
Date: 12-6-2018
SL-01 SL-02 SL-03 SL-04 SL-05 SL-06 SL-07
Initial Readings 56.1 57.7 55.4 59.4 63.7 64.7 55.1
Date: 13-6-2018
SL-01 SL-02 SL-03 SL-04 SL-05 SL-06 SL-07
Initial Readings 56.1 57.7 55.4 59.4 63.7 64.7 55.1
Date: 14-6-2018
SL-01 SL-02 SL-03 SL-04 SL-05 SL-06 SL-07
Initial Readings 56.1 57.7 55.4 59.4 63.7 64.7 55.1
Date: 15-6-2018
SL-01 SL-02 SL-03 SL-04 SL-05 SL-06 SL-07
Initial Readings 56.1 57.7 55.4 59.4 63.7 64.7 55.1
Date: 16-6-2018
SL-01 SL-02 SL-03 SL-04 SL-05 SL-06 SL-07
Initial Readings 56.1 57.7 55.4 59.4 63.7 64.7 55.1
Date: 18-6-2018
SL-01 SL-02 SL-03 SL-04 SL-05 SL-06 SL-07
Initial Readings 56.1 57.7 55.4 59.4 63.7 64.7 55.1
Date: 19-6-2018
SL-01 SL-02 SL-03 SL-04 SL-05 SL-06 SL-07
Initial Readings 56.1 57.7 55.4 59.4 63.7 64.7 55.1
Date: 20-6-2018
SL-01 SL-02 SL-03 SL-04 SL-05 SL-06 SL-07
Initial Readings 56.1 57.7 55.4 59.4 63.7 64.7 55.1
Date: 21-6-2018
SL-01 SL-02 SL-03 SL-04 SL-05 SL-06 SL-07
Initial Readings 56.1 57.7 55.4 59.4 63.7 64.7 55.1
Date: 22-6-2018
SL-01 SL-02 SL-03 SL-04 SL-05 SL-06 SL-07
Initial Readings 56.1 57.7 55.4 59.4 63.7 64.7 55.1
Date: 23-6-2018
SL-01 SL-02 SL-03 SL-04 SL-05 SL-06 SL-07
Initial Readings 56.1 57.7 55.4 59.4 63.7 64.7 55.1
Date: 25-6-2018
SL-01 SL-02 SL-03 SL-04 SL-05 SL-06 SL-07
Initial Readings 56.1 57.7 55.4 59.4 63.7 64.7 55.1
Date: 26-6-2018
SL-01 SL-02 SL-03 SL-04 SL-05 SL-06 SL-07
Initial Readings 56.1 57.7 55.4 59.4 63.7 64.7 55.1
No. of accident: 0 0
No. of Incident:: 0 0
Prepared by:
Joan Tam
Safety Officer