Responsible for the operation of GAS TURBINE,STEAM TURBINE,HRSG,WATER DEIONIZATION PLANT,GAS COMPRESSOR,
DUAL FUEL BOILER and all the plant auxiliaries.
Hot and cold start up Boiler and turbine.
Performing the functions of troubleshooting and breakdown/preventive/corrective maintenance for
reducing downtime to minimum and restore the plant in case of shut down.
Use Maintenace management software like MOGAN.
Involved in commissioning activities of different auxilariies of power plant.
Performance monitoring of combined cycle power plant within a varying range of loads.
Vibration analysis,condition monitoring.
Make daily fuel and energy report.
See less
o TitleASISSTANT ENGINEER
Dates EmployedNov 2014 – 2018
Employment Duration4 yrs
About the Plant:
• Gas Turbine: 5.5 MW 3 Stage Reaction Turbine of SOLAR make
• Steam Turbine: 3 MW 6 stage Impulse Reaction Turbine of TUTHILL make
• HRSG: 16 TPH water tube single pass boiler, JOHNSTON make
• Gas & HFO fired Boiler: 14 TPH fire tube 3 pass boiler, ROBEY make
• Water De-Ionization plant: 120 ton capacity
Key Responsibilities:
• Responsible for operation of Gas Turbine, Steam Turbine, HRSG, D.F. Boiler, Water Deionization Plant and all plant
auxiliaries.
• Hot & Cold start up of boiler & turbine.
• Performing the functions of troubleshooting and breakdown/ preventive/ corrective maintenance for reducing downtime
to minimum and to restore the plant in case of shutdown.
• Use Maintenance management software package like MOGAN.
• Handle emergency situations of desk operation confidently.
• Involved in commissioning activities of different auxiliaries of power plant.
• Performance monitoring of combined cycle power plant within a varying range of loads.
• Implemented Standard Operating Procedures, equipment lockout tag out procedures of power plant.
• Monitored the water treatment systems for cooling Tower and HRSG. Maintain the production level of de-mineralized
water Plant and its chemical consumption.
• Managed safety plans and equipment in order to minimize the risk of health and safety hazards.
• Vibration analysis, condition monitoring.
• Prepared capital and spare parts expenditure budget.
Took an active part in the commissioning of Gas Compressor and its Cooling Tower. Also assist Turbomach representatives in