Академический Документы
Профессиональный Документы
Культура Документы
6
Constructors Ltd. the mechanics of project cost
estimation. That was to be
followed by a discussion of various
management tools, for example Proj
IN BRIEF ect Definition Rating Index (PDRI) [7],
CLASS OF ESTIMATE that are used to validate the input to
the estimate. But it was apparent that
WISHING DOESN'T MAKE
IT COME TRUE
there were other factors at play, given
the anecdotal and very public records of
UNDERSTAND YOUR numerous project delays and cost over
EXPERIENCE runs, that went beyond simply not follow
DON'T CHANGE YOUR ing a procedure and going through some
MIND management check-list gate. As one of
the owners ofmy company pointed out in a
KNOW THE PROJECT
ENVIRONMENT
recent meeting, to Manage With Certainty,
one must focus on the input and not just
THE ESTIMATE GOT A the outcome.
GREAT PDRI About four decades ago, in my first
RESOURCES ALLOCATED job with Union Carbide Corp. (UCC), I
FOR THE ESTIMATE was given an assignment to find out why
many of the plant projects were plagued
with delays and cost overrun. In the late
1970s, the Bound Brook plant was suffering
from a very tight capital budget constraint.
The era was in the mid stage of factory reloFIGURE 1. There are a number of pitfalls one may encoun
ter while following the standard methods for generating a
cation away from the Northeast and mid-Atcost estimate
lantic regions. The conclusions that I drew,
after interviewing many of my coworkers at Fast-forward to 2018, in a recent news
the site, were rather simplistic and seemed article, a large public utility company an
to be just common sense. Being a newly nounced another 15% increase in a project’s
minted engineer at the time, I thought it wascost, making the current estimate double
because I did not fully appreciate the com from the project announcement just four
plexity of project execution; and I suppose, years ago (2). What happened? Was there
so did the senior managers. some kind of evil mastermind at work? Was
Over the years, the problem of project it the dreaded tariff? How can a company
cost and schedule overrun persisted in the that is more than fifty years old, working with
chemical process industries (CPI) and the well qualified contractors, make these mis
energy sector. It was apparently prevalent takes? As most of this cost overrun will likely
enough that many companies were willing tobe borne by the public utility rate payers, the
expend scarce resources to hire consultantstruth of the matter may eventually come to
to work on this riddle. A lot of brain power light after some years of investigation. Even
was being brought to bear on the problem, then, the fog of project execution will make
but it seemed to be more stubborn than thatit difficult, if not impossible, to separate facts
grass stain in the laundry commercial. from fabrications.
44 CHEMICAL ENGINEERING WWW.CHEMENGONLINE.COM DECEMBER 2018
Source GAO
In this article, I assume that the
reader can access multiple well-writ-
%
ten articles and websites on the Inter >a
net [3] that discuss various methods
to generate a cost estimate. Instead
of delving deeply into the mechan
ics, this article discusses some of the
pitfalls that one may encounter while Uncertainty is low
following those procedures (Figure 1).
Hopefully, the reader will find the sim
ple solutions to be easy to apply to [f0M
everyday project execution. If nothing Cost estimate becomes mo»ecerta^
Estimate
baseline ttmeasrtsks are *
else, the article may help one sleep Estimate tends to grow
better, and it also helps explain how a
kitchen remodeling can balloon from
$10,000 to $20,000.
Start of program and start of
Concept refinement gateTechnology development gate integration gate
system
Class of estimate
The “class of estimate” is a generallyFIGURE 2. As a project develops from the conceptual stage to increasingly detailed definition, the cost es
accepted term to signify the claimed timates and schedule are also progressing in the cone ot uncertalnity towards smaller probability of error
range of accuracy of cost estimates Wishing does’t make it come true costs his business plan can sup
from one to five [4], the most accu Human nature being what it is, I port. Second, evaluate the qual
rate being one and the least being admit that I still tend to wish my projity of inputs and assumptions that
five. During the development of a ect estimates to be lower and the are going into the estimate. Finally,
project, the estimate accuracy im project schedules shorter. Warning: third, delete or revise the scope so
proves as more information is gen self-delusion is a very bad way to runthat the project cost fits within the
erated to put into the estimating ef a project. It is beyond bad if one is economic model. Along the way,
fort. Presumably, the project team successful in coercing a subordinatehe would have found the engineers
is busily checking off those boxes or a contractor to abet in that lie. that he could trust and who would
specifying the required inputs. So, A friend told me about a meeting be on board with his objectives.
if all the boxes are checked, then with a potential client for a very large Along that same line of thought,
the estimate must be accurate as project who was adamant about make a sound estimate and sched
defined. There is an often repeated competitively bidding every phase ule a reality by clearly defining the
phrase in the information technol of the work, from front-end load scope of the project. This scope
ogy (IT) world: “Garbage in equals ing (FEL) through construction and then drives the discipline details,
garbage out." startup. The logic was that he would which are verified with the cost
Beware, just because there is a easily find the contractor most des estimator. Note: the ends are not
document transmittal fitting the de perate for his business and thereforeachieved by reducing quality of the
scription, it does not necessarily give him the lowest price with little orinputs and hoping that the estimator
mean that there is a real contributionno contingencies and minimal profit can come up with assumptions.
to improving the accuracy of the es margin. He was clearly choosing to Unfortunately, when the project is
timate. In fact, it could be quite the ignore the lessons of the time value driven into a competitive, fixed-cost
opposite. Bad information is invari of money [5], as the schedule would bidding process, it is not likely that
ably worse than no information at all.have stretched out more than a yearthe contractors would reveal the sa
It is incumbent upon the manage to allow for the bidding process. lient information to a project manager.
ment team to make sure that the in There was a definite lack of under Without it, the project manager is left
puts are properly vetted. standing of human nature. What to scan through the qualifications and
The engineering disciplines of the would anyone expect from desper exclusions like a first-year law student,
project team must be encouraged ate businessmen trying make their perhaps not wanting to believe that the
to question and evaluate every as commission or to save their com submitted bid is just a book of fiction.
sumption and calculation. Project pany? If he was not secretly wishing
management must be encouraged his project to be plagued by endless Understand your experience
to foster an environment of honesty change orders, he must have opti “I have eaten more salt than the
and openness so that team mem mistically assumed that the contrac grains of rice that you have eaten,”
bers can talk about any difficulties tor estimated correctly or equally goes a Chinese saying emphasizing
encountered. It is also necessary to unlikely, intended to make up for anythe importance of life experience.
be realistic and admit, if substan overrun out of his own pocket. However, another common saying
tial input is lacking, that the desired The better approach for this cli goes, “If I had a dollar every time a
objective of estimate accuracy is ent's problem would be to do his project manager demands to know
not feasible. homework. First, understand what why an estimate did not match the