Вы находитесь на странице: 1из 4

I.

STEEL WORKS
1.0 Materials. Roof framing

Quanti Bottom chord Top chord Web members


Truss Total length
ty (2 bars welded) (2 bars welded) (1 bar)
Truss 1 14 5.23 m 5.44 m 8.34 m 415.52 m
Truss 2 2 2.62 m 2.7 m 2.40 m 26.08 m
Truss 3 4 1.97 m 2.33 m 1.17 m 39.08 m
Total 480.68 m

1.0 Roof Framing


Particulars Quantity Unit Unit cost Amount
5mm x 38mm x 38mm x 6m angle bar 81 Length 470.00 38,070.00
1.5mm thk x 50mm x 100mm x 6m cee-purlins 10 Length 620.00 6,200.00
12mm φ x 6m round bar stiffener & brace 30 Pcs 260.00 7,800.00
12mm φ turn buckle 15 Pcs 75.00 1,125.00
10mm φ x6m round bar tension bar 20 Pcs 180.00 3,600.00
5mm x 1.2 x 2.4 steel plate 3 Shts. 5,400.00 16,200.00
Welding rod R12 (20kg/box) 15 Boxes 2,300.00 34,500.00
Hacksaw blade 24 Pcs 85.00 2,040.00
Total 109,535.00

2.0 Labor
Particulars Quantity No. Of days Rate Amount
Welder 4 10 450.00 18,000.00
Helper 4 10 358.00 14,320.00
Total 32,320.00
II. FALSEWORKS

Formworks: Three uses

Vertical area: Column (1.2 x 7)16 = 134.4 𝑚2

Horizontal area: Beam 1.24(24.5 x 2) + 1.24(11.29)+ 1.24(10.141 x 2) = 99.91 𝑚2

Total = 234.31 𝒎𝟐

1.0 Materials
Particulars Quantity Unit Unit cost Amount
2"x2"x12' Gmelina Lumber 3,000 bd ft. 25.00 72,000.00
5mmx1.2mx2.4m ordinary plywood 100 Pcs 260.00 35,500.00
C.W nails # 4" (40kg/box) 4 Boxes 1,760.00 7,040.00
C.W nails # 3" (40kg/box) 3 Boxes 1,760.00 5,280.00
C.W nails # 2.5" (40kg/box) 2 Boxes 1,760.00 3,520.00
C.W nails # 1" (40kg/box) 1 Boxes 1,760.00 1,760.00
Total 125,100.00

III. TINSMITHRY

1.0 Materials
Unit
Particulars Quantity Unit cost Amount
0.40 mm x 1110 m effective length rib type pre-painted
color roofing long span (brown) 98 L.m. 490.00 48,020.00
0.40 mm x 2.40 m pre-painted spanish gutter (brown) 10 L.m. 490.00 4,900.00
Tekscrew for C-purlins 2240 Pcs 2.00 4,480.00
Blind rivets 1/8" x 1/2" (1000pcs/box) 3 Boxes 350.00 1,050.00
Total 58,450.00

2.0 Labor
Particulars Quantity No. Of days Rate Amount
Tinsmither/carpenter 5 12 450 27,000.00
Helper 5 12 358 21,480.00
Total 48,480.00
TOTAL COST OF MATERIAL = 292,760.00

TOTAL COST OF LABOR = 88,880.00

TOTAL COST OF EQUIPMENT RENTAL = 29,700.00

TOTAL = 411,340.00
COST ESTIMATE OF THE PROPOSED TWO-STOREY BUILDING
CE 82 CONSTRUCTION COST ENGINEERING

NULADA, BRIX BRYAN P.

DECEMBER 2018