DETAILED ESTIMATE
Name of Project :- Bidhya Mandir Ma.Bhi Fiscal Year:- 2075/76
Location :- Ba.Na.Pa-3, Baglung Date :- 2075/10/22
Name of Work :- Compound Wall Construction & Fenching Works

S.N. Description of works No Length Breadth Height Quantity Remarks


A) Civil Work
Compound Wall Construction Work &
Fenching
Earthwork excavation in Hard clay and silty soil including disposal upto (1.5m lift & 10m
1 M3
lead).
West side of Campus
Foundation for Support Block 52.33 0.40 0.40 0.25 2.10
East side of Campus
For Wall Foundation 1.0 20.40 0.23 0.25 1.15
Foundation for Support Block 11.0 0.40 0.40 0.25 0.44
Grand Total 3.69 M3

2 Boulder filling in foundation with levelling (Transporting from 30m) M3


West side of Campus
Foundation for Support Block 52.33 0.40 0.40 0.15 1.26
East side of Campus
For Wall Foundation 1.00 20.40 0.23 0.15 0.69
Foundation for Support Block 11.00 0.40 0.40 0.15 0.27
Grand Total 2.22 M3

Cement concrete work (1:2:4) in foundation, floor, walls & abutment including Supply of
3 M3
materials and haulage distance upto 30m.
West side of Campus
Foundation for Support Block 52.33 0.40 0.40 0.40 3.35
At Top 52.33 0.40 0.40 0.08 0.67
East side of Campus
For Wall Foundation 1.00 20.40 0.23 0.10 0.46
Foundation for Support Block 11.00 0.40 0.40 0.40 0.71
Grand Total 5.19 M3

4 Brick Masonary work in 1:6 mortar per M3 M3


East side of Campus
For Wall Foundation 1.00 20.40 0.23 1.52 7.00
Grand Total 7.00 M3

5 Finishing wire net fitting works for fenching (10 guage GI wire 40x40 mm) M2
West side of Campus
1.00 157.00 1.52 239.33
East side of Campus
1.00 25.00 0.91 22.87
1.00 30.00 1.52 45.73
Grand Total 307.93 M2

6 Angle post - 2.5 m long iron angle pole ( 40 mm - 40 mm- 3mm ) Kg

Prepared By : Checked By : Approved By :


Page 2 of 67
Government of Nepal
Ministry of Federal Affairs and Local Development
OFFICE OF MUNICIPAL EXECUTIVE
BAGLUNG MUNICIPALITY
BAGLUNG, GANDAKI PROVINCE
DETAILED ESTIMATE
Name of Project :- Bidhya Mandir Ma.Bhi Fiscal Year:- 2075/76
Location :- Ba.Na.Pa-3, Baglung Date :- 2075/10/22
Name of Work :- Compound Wall Construction & Fenching Works

S.N. Description of works No Length Breadth Height Quantity Remarks


West side of Campus
Iron angle (40x40x3) 52.33 2.50 130.83 R.m
East side of Campus
Iron angle (40x40x3) 11.00 2.50 27.50
Sub Total 158.33 R.m
Unit Weight
158.33 5.90 934.80
(kg/m)
Grand Total 934.80 Kg

7 Transportation cost for non -local materials from nearest market area to site Job
1.00 1.00
Grand Total 1.00 Job

Prepared By : Checked By : Approved By :


Page 3 of 67
Government of Nepal
Ministry of Federal Affairs and Local Development
OFFICE OF MUNICIPAL EXECUTIVE
BAGLUNG MUNICIPALITY
BAGLUNG, GANDAKI PROVINCE
ABSTRACT OF COST
Name of Project :- Bidhya Mandir Ma.Bhi Fiscal Year:- 2075/76
Location :- Ba.Na.Pa-3, Baglung Date :- 2075/10/22
Name of Work :- Compound Wall Construction & Fenching Works

S.No. Description of works Unit Quantity Rates Amounts Remarks


A Civil Works
1 Earthwork excavation in Hard clay and silty soil Cu.m 3.69 576.80 2128.39
including disposal upto (1.5m lift & 10m lead).
2 Boulder filling in foundation with levelling Cu.m 2.22 2781.00 6173.82
(Transporting from 30m)
Cement concrete work (1:2:4) in foundation, floor,
3 walls & abutment including Supply of materials and Cu.m 5.19 13974.17 72525.97
haulage distance upto 30m.
4 Brick Masonary work in 1:6 mortar per M3 Cu.m 7.00 13710.39 95972.74
5 Finishing wire net fitting works for fenching (10 Sq.m 307.93 678.00 208774.39
guage GI wire 40x40 mm)
6 Angle post - 2.5 m long iron angle pole ( 40 mm - 40 Kg 934.80 90.40 84505.92
mm- 3mm )
7 Transportation cost for non -local materials from Job 1.00 20000.00 20000.00
nearest market area to site

Grand-Total 490081.23

In words,
Four Lakhs Ninety Thousand Eighty One Rupees & Twenty Three Paisa Only /-

Prepared By : Checked By : Approved By :


BAGLUNG MUNICIPALITY
OFFICE OF MUNICIPAL EXECUTIVE
PROVINCE NO: 4, BAGLUNG
SUMMARY OF RATE ANALYSIS "GENERAL WORKS"( F/Y 74-75 )

Rate
S.N. Description unit
User Tender
Earthwork excavation Work
Earthwork in excavation for Hard clay and silty soil
with 10 m lead and 1.5 m lift per m3, (S.N.2, item Cu.
2 no.2 ) m. 576.8 663.32
Boulder Soling & levelling works in foundation including 30m lead.
Stone soling (pitching) work in foundation with 30m Cu.
16 lead per M3 (S.N.6 item no.5 ) m. 2781.00 3198.15
Brick masonry works including materials collection, preparation of mortar
withBrick
30mMasonary work in 1:6 mortar per M3 (S.N.5
transportation. Cu.
19 item no.Kha-3) m. 13710.39 14456.23
Plain cement concrete works in foundation including material collection &
30mPCC.
leadWork for Foundation in 1:2:4 per M3 (S.N.7, Cu.
21 item no.2,Gha ) m. 13974.17 15203.06
( F/Y 74-75 )

Remark
s

lead.

n of mortar

collection &
Steel Tubes
Light Medium Heavy
Nominal
bore(mm Outside Wall Outside Wall Outside Wall
) diameter( thickness( Weight kgf diameter( thickness( Weight kgf diameter( thickness( Weight kgf
mm) mm) mm) mm) mm) mm)
15 21.3 2 0.962 21.3 2.65 1.22 21.3 3.25 1.45
20 26.9 2.35 1.42 26.9 2.65 1.58 26.9 3.25 1.9
25 33.7 2.65 2.04 33.7 3.25 2.46 33.7 4.05 2.99
32 42.4 2.65 2.61 42.4 3.25 3.15 42.4 4.05 3.86
40 48.3 2.9 3.27 48.3 3.25 3.61 48.3 4.05 4.43
50 60.3 2.9 4.14 60.3 3.65 5.1 60.3 4.5 6.17
65 76.1 3.55 5.84 76.1 3.65 6.53 76.1 4.5 7.92
80 88.9 3.25 6.86 88.9 4.05 8.48 88.9 4.85 10.1
100 114.3 3.65 9.97 114.3 4.5 12.1 114.3 5.4 14.5
125 139.7 4.5 14.9 139.7 4.85 16.2 139.7 5.4 17.9
150 165.1 4.5 17.8 165.1 4.85 19.2 165.1 5.4 21.2
Almunium tube λ=2.7 kgf/dm₃ Brasstube λ=8.5 kgf/dm₃ Copper tube λ=8.9 kgf/dm₃
Government of Nepal
Ministry of Federl Affairs and Locl Development
Office of District Development Committee
DISTRICT TECHNICAL OFFICE
Chitwan
SUMMARY OF RATE ANALYSIS for Users Committee Fiscal Year :- 2073/074

MKS FPS
S.N. Description of works Norms No.
Unit Rate Unit
1 Site Preparation

Surface dressing pots filling, levelling of undulated


1.1 ground, landscaping all complete work, and Norms S.N. 1-7 m² 5.25 Sq.ft
Surface levelling etc.(Survice road)

Removal of grasses, small trees, levelling of


undulated ground, landscaping all complete work,
1.2 Norms S.N. 1-8 m² 84.00 Sq.ft
and disposal of existing earth materials away from
construction site (thickness 15- 20 cm)

Top soil spreading in manner sloped/Spreading top


1.3 Norms S.N. 1-9 m² 21.00 Sq.ft
soils at the required slope.

2 Earthwork work

Earthwork excavation in soft clay and silt soil


2.1 Norms S.N. 2-1 m³ 378.53 Cu.ft
including disposal upto (1.5m lift & 10m lead).

Earthwork excavation in hard soil including


2.2 Norms S.N. 2-2 m³ 432.60 Cu.ft
disposal upto (1.5m lift & 10m lead).

Earthwork excavation in medium types of


2.4 stone/rocks without blasting including disposal Norms S.N. 2-4 m³ 1622.25 Cu.ft
upto(1.5m lift & 10m lead)
Earthwork in excavation in hard rock without
2.5 Norms S.N. 2-6ka m³ 2703.75 Cu.ft
Chiseling(1.5m lift & 10m lead)
Earthwork in excavation in hard rock with
2.6 Norms S.N. 2-6kha m³ 13086.15 Cu.ft
Chiseling(1.5m lift & 10m lead)

Earthwork excavation in soft soil including


2.7 Norms S.N. 2-9 m³ 540.75 Cu.ft
disposal upto (1.5m lift & 10m lead).

Ditch cutting in hard soil including disposal upto


2.8 Norms S.N. 2-12 m³ 675.94 Cu.ft
(10m lead & 1.5m lift)
Earthwork in excavation in foundation, drain and
2.9 pipeline in boulder mixed soil (10m lead & Norms S.N. 2-14 m³ 859.79 Cu.ft
1.5m lift)
Earthwork in excavation in foundation, drain etc.
2.10 in medium rock without blasting (10m lead & Norms S.N. 2-15-Kha m³ 2433.38 Cu.ft
1.5m lift)
Earthwork in excavation in foundation,
2.11 drain,tunnel etc. by chiseling in hard rock Norms S.N. 2-16-Kha m³ 13626.90 Cu.ft
without blasting (10m lead & 1.5m lift)
3 Earth / Sand filling & compaction
Earth filling & compaction in 15 cm layers with
3.1 Norms S.N. 2-25-Ka m³ 262.50 Cu.ft
sprinkling water (Transporting from 10m)

Earth filling & compaction in 15 cm layers without


3.2 Norms S.N. 2-25 Kha m³ 131.25 Cu.ft
sprinkling water (Transporting from 10m)

Earth filling & compaction in 15 cm layers with


3.3 sprinkling water (Transporting from 10m) soil Norms S.N. 2-25 Kha m³ 832.50 Cu.ft
from out of side
Earth filling & compaction in 15 cm layers with
3.4 sprinkling water (Transporting from 10m)Gravel Norms S.N. 2-25 Kha m³ 862.50 Cu.ft
mixed soil from out of side
Sand filling & compaction with sprinkling water
3.5 Norms S.N. 2-42 m³ 2127.50 Cu.ft
(Transporting from 10m)
4 Refilling of pipe line trench
Refilling of pipe line trench with soft soil including
4.1 watering and ramming every 20 cm layers (Lead Norms S.N. 2-39-Ka m³ 270.38 Cu.ft
10m)
Refilling of pipe line trench with medium soil
4.2 including watering and ramming every 20 cm Norms S.N. 2-39-Kha m³ 297.41 Cu.ft
layers (Lead 10m)
Refilling of pipe line trench with hard soil
4.3 including watering and ramming every 20 cm Norms S.N. 2-39-Ga m³ 340.67 Cu.ft
layers (Lead 10m)
Refilling of pipe line trench with gravel and
4.4 boulder mixed soil including watering and Norms S.N. 2-39-Gha m³ 324.45 Cu.ft
ramming every 20 cm layers (Lead 10m)
5 Land slide clearance work/Prevantion of land slide in
5.1 A)Ordinary Soil Norms S.N. 2-45-a m³ 227.12 Cu.ft
5.2 B)Gravel and Boulder mix soils Norms S.N. 2-45-b m³ 286.60 Cu.ft
5.3 C)Soft Rocks Norms S.N. 2-45-c m³ 475.86 Cu.ft
5.4 D)Hard rocks Norms S.N. 2-45-d m³ 594.83 Cu.ft
6 Collection and stacking of required size stone
Collection,screeding and providing of sand Norms S.N. 3-1-d
6.1 m³ 750.75 Cu.ft
(haulage distance 10 m)
Collection of rubble stone of required size Norms S.N. 3-4
6.2 m³ 735.00 Cu.ft
including stacking. (haulage distance 10 m)

Making and stacking of required size stone by


6.3 Norms S.N. 3-11 m³ 2887.50 Cu.ft
using Chisel including 10m lead (without blasting)

7 Brick Masonry
Brick masonry work in 1:3 cement mortar in
7.1 foundation with providing chimney made Norms S.N. 5-1-Kha-1 m³ 12656.82 Cu.ft
bricks (Transporting from 30m)
Brick masonry work in 1:4 cement mortar in
7.2 foundation with providing chimney made Norms S.N. 5-1-Kha-2 m³ 12272.80 Cu.ft
bricks (Transporting from 30m)
Brick masonry work in 1:6 cement mortar in
7.3 foundation with providing chimney made Norms S.N. 5-1-Kha-3 m³ 11904.78 Cu.ft
bricks (Transporting from 30m)
Brick masonry work in 1:3 cement mortar in
Norms S.N. 5-1-Kha-1
7.4 ground floor with providing chimney made & 5-2-Ka m³ 12832.92 Cu.ft
bricks (Transporting from 30m)
Brick masonry work in 1:4 cement mortar in
Norms S.N. 5-1-Kha-2
7.5 ground floor with providing chimney made & 5-2-Ka m³ 12448.90 Cu.ft
bricks (Transporting from 30m)
Brick masonry work in 1:6 cement mortar in
Norms S.N. 5-1-Kha-3
7.6 ground floor with providing chimney made & 5-2-Ka m³ 12080.88 Cu.ft
bricks (Transporting from 30m)
Brick masonry work in 1:3 cement mortar above
Norms S.N. 5-1-Kha-1
7.7 ground floor with providing chimney made & 5-2-Kha m³ 13103.30 Cu.ft
bricks (Transporting from 30m)
Brick masonry work in 1:4 cement mortar above
Norms S.N. 5-1-Kha-2
7.8 ground floor with providing chimney made & 5-2-Kha m³ 12719.28 Cu.ft
bricks (Transporting from 30m)
Brick masonry work in 1:6 cement mortar above
Norms S.N. 5-1-Kha-3
7.9 ground floor with providing chimney made & 5-2-Kha m³ 12351.26 Cu.ft
bricks (Transporting from 30m)
8 Stone Masonry
Random rubble masonry work in 1:3 cement
8.1 mortar including providing block stone up to Norms S.N. 6-1-Ka-1 m³ 8385.30 Cu.ft
5m height (Transporting from 10m)
Random rubble masonry work in 1:4 cement
8.2 mortar including providing block stone up to Norms S.N. 6-1-Ka-2 m³ 7966.61 Cu.ft
5m height (Transporting from 10m)
Random rubble masonry work in 1:6 cement
8.3 mortar including providing block stone up to Norms S.N. 6-1-Ka-3 m³ 7291.90 Cu.ft
5m height (Transporting from 10m)
Random rubble masonry work in dry including
8.4 providing block stone up to 5m height Norms S.N. 6-2-1 m³ 3181.50 Cu.ft
(Transporting from 30m)
Random rubble masonry work in mud mortar
8.5 including providing block stone up to 5m height Norms S.N. 6-2-2 m³ 3312.75 Cu.ft
(Transporting from 30m)
9.0 Stone Soling Work
Boulder filling in foundation with levelling
9.1 Norms S.N. 6-5 m³ 2305.50 Cu.ft
(Transporting from 30m)
9.2 Dry stone soling Norms S.N. 11-16 m³ 3969.00 Cu.ft
Masonry Work in Block
Masonry work in 1:6 cement mortar including
10.0 providing precast block up to 5m height Norms S.N. m³ 8793.18 Cu.ft
(Transporting from 30m)
11 Cement Concrete Work
Cement concrete work in foundation, floor, walls & abutment (plum concrete) including Supply of materials and
11.1
haulage distance upto 30m.
P.C.C. (1:3:6) Norms S.N. 7-1-Ka m³ 7426.48 Cu.ft

P.C.C. (1:2:4) Norms S.N. 7-1-Kha m³ 8643.98 Cu.ft


Cement concrete work in foundation, floor, walls & abutment including Supply of materials and haulage
11.2
distance upto 30m.
P.C.C. (1:3:6) Norms S.N. 7-2-Ga m³ 8241.13 Cu.ft

P.C.C. (1:2:4) Norms S.N. 7-2-Gha m³ 9460.08 Cu.ft


Cement concrete work in abuitment seats,piel caps etc. including supply of materials and haulage distance
11.3
upto 30m
P.C.C. (1:3:6) Norms S.N. 7-3-Ka m³ 11317.13 Cu.ft

P.C.C. (1:2:4) Norms S.N. 7-3-Kha m³ 12536.08 Cu.ft


Cement concrete work in super-structure, deck, slab, beams including providing materials and haulage
11.4
distance upto 30m
P.C.C. (1:2:4) Norms S.N. 7-4-Ka m³ 10887.08 Cu.ft

P.C.C. (1:1.5:3) Norms S.N. 7-4-Kha m³ 11949.05 Cu.ft

P.C.C. (1:1:2) Norms S.N. 7-4-Ga m³ 14728.64 Cu.ft

Cement concrete work in super-structure, deck,


11.5 slab, beams including providing materials and Norms S.N. 7-9 m³ 11078.08 Cu.ft
haulage distance upto 30m-Precast Work

12 Steel Work
Curtailment, bent up, placing & binding the MS
12.1 bar with binding wire as shown in drawings Norms S.N. 7-5 Kg 104.01 Kg
including haulage distance 30m.

12-20mm dia. Reinforcement bar fixing in window


12.2 Norms S.N. 10-21 Kg 111.85 Kg
frame including drilling works ( Analysis for 1MT )

13 Form Work
Form work for beams, slab in structure including, screening, fitting, oiling, dismantling, removing and transporting up
13.1
to 30m
A) For Slab Norms S.N. 8-2-Ka m² 642.60 Sq.ft

B) For Column-circumfrance upto 2m height Norms S.N. 8-3-Ka m² 952.90 Sq.ft

C) For Beam-Depth of beam upto 30cm Norms S.N. 8-4-Ka m² 991.39 Sq.ft
14 Roofing Work
Roofing work by 26 gauge(0.38mm thick) non-
14.1 coloured CGI sheets (Medium) including Norms S.N. 9-1 m² 825.72 Sq.ft
providing CGI sheets
Roofing work by 26 gauge(0.38mm thick)
14.2 coloured CGI sheets (Medium) including Norms S.N. 9-1 m² 995.52 Sq.ft
providing CGI sheets
Ridge covering with 28 gauge non-colour G. I.
plain sheet including supplying of materials, J
14.3 or L hooks, nut bolts, washers, fixing of C.G.I Norms S.N. 9-2 rm 572.39 Sq.ft
sheet over roofing members in proper slope
and size

Ridge covering with 28 gauge colour G. I. plain


sheet including supplying of materials, J or L
14.4 Norms S.N. 9-2 rm 848.42 Sq.ft
hooks, nut bolts, washers, fixing of C.G.I sheet over
roofing members in proper slope and size

14.5 Roofing work by providing slate Norms S.N. 9-5 m² 0.00


Wood work for 20mm thick ceiling with 40*20mm
14.6 Norms S.N. 9-10 m² 1624.98 Sq.ft
beading joint by providing materials

15 Wood Work
15.1 Local wood work for choukosh Norms S.N. 10-1 m³ 87675.80 Cu.ft
15.2 Sal wood work for choukosh Norms S.N. 10-1 m³ 222918.60 Cu.ft
15.3 Sisaum wood work for choukosh Norms S.N. 10-1 172253.92 Cu.ft
15.4 38 mm thick solid panelled shutter using sal wood Norms S.N. 10-2 m² 11180.56 Sq.ft

38 mm thick solid panelled shutter using Local


15.5 Norms S.N. 10-2 m² 6295.21 Sq.ft
Wood
38 mm thick solid panelled shutter using Sisauml
15.6 Norms S.N. 10-2 m² 9350.41 Sq.ft
Wood
Openable glazed shutter with 38 x 75mm sal wood
15.7 Norms S.N. 10-4 m² 7643.78 Sq.ft
frame & 4mm thick glass supply
Openable glazed shutter with 38 x 75mm Local
15.8 Norms S.N. 10-4 m² 4942.23 Sq.ft
Wood frame & 4mm thick glass supply

Openable glazed shutter with 38 x 75mm Sisaum


15.9 Norms S.N. 10-4 m² 6631.73 Sq.ft
Wood frame & 4mm thick glass supply

Flush shutter 38mm thick Sal wood frame with


15.10 4mm thick commercial plywood on both side Norms S.N. 10-7 m² 6769.59 Sq.ft
of shutter

Flush shutter 38mm thick Sal wood frame with


15.11 4mm thick commercial plywood on both side m² 7187.06 Sq.ft
of shutter including one side plane sheet

Flush shutter 38mm thick Sisaum wood frame with


15.12 4mm thick commercial plywood on both side of Norms S.N. 10-7 m² 6059.72 Sq.ft
shutter

Flush shutter 38mm thick Sisaum wood frame with


15.13 4mm thick commercial plywood on both side of m² 6477.19 Sq.ft
shutter including one side plane sheet

Flush shutter 38mm thick Local wood frame with


15.14 4mm thick commercial plywood on both side of Norms S.N. 10-7 m² 4874.71 Sq.ft
shutter
Flush shutter 38mm thick Local wood frame with
15.15 4mm thick commercial plywood on both side of m² 5292.18 Sq.ft
shutter including one side plane sheet

Sal wood shutter with38 mm thick wooden frame


15.16 Norms S.N. 10-9 m² 7052.57 Sq.ft
including 24gauge plane sheet both side

Sisaum wood shutter with38 mm thick wooden


15.17 Norms S.N. 10-9 m² 6342.70 Sq.ft
frame including 24gauge plane sheet both side

Local wood shutter with38 mm thick wooden frame


15.18 Norms S.N. 10-9 m² 5157.69 Sq.ft
including 24gauge plane sheet both side

Sal wood shutter with38 mm thick wooden frame


15.19 including 24gauge G.I.mosquito proof net wire Norms S.N. 10-10 m² 4368.79 Sq.ft
mesh
Sal wood shutter with38 mm thick wooden frame
15.20 including 24gauge G.I.mosquito proof net wire m² 4577.86 Sq.ft
mesh with expended metal Net
Sisaum wood shutter with38 mm thick wooden
15.21 frame including 24gauge G.I.mosquito proof net Norms S.N. 10-10 m² 3835.37 Sq.ft
wire mesh
Local wood shutter with38 mm thick wooden frame
15.22 including 24gauge G.I.mosquito proof net wire Norms S.N. 10-10 m² 2944.90 Sq.ft
mesh
Norms S.N. 10-11-
15.23 Fixed glazed shutter with 4mm thick glass Kha m² 897.30 Sq.ft
Fixed shutter with 4mm thick Commercial ply wood
15.24 Norms S.N. 10-12 m² 559.46 Sq.ft
and wooden listy
Making wooden partition wall from frame of size
0.61m*0.915m using wood of size 38mm*75mm
15.25 and attaching 4mm thick commercial plywood on Norms S.N. 10-14-a m² 1817.85 Sq.ft
both sides including covering of the joints by
timber beats.
Flush ceiling work by using 50mm*75mm salwood
15.26 frame of size 0.60m*0.90m including 3mm thick Norms S.N. 10-16-ka m² 3125.76 Sq.ft
plywood.

15.27 Wood work for beam,column etc.using local wood Norms S.N. 10-17 m³ 70320.90 Sq.ft

15.28 Wood work for truss using local wood Norms S.N. 10-18 m³ 83306.90 Sq.ft
15.29 25mm thick local wood work for eaves board Norms S.N. 10-19 m² 1591.17 Sq.ft
16 Flooring works

16.1 25mm thick 1:2:4 cement concrete flooring Norms S.N. 11-1-Ka m² 343.86 Sq.ft

16.2 38mm thick 1:2:4 cement concrete flooring Norms S.N. 11-1-Kha m² 469.30 Sq.ft

16.3 50mm thick 1:2:4 cement concrete flooring Norms S.N. 11-1-Ga m² 576.24 Sq.ft

16.4 75mm thick 1:2:4 cement concrete flooring Norms S.N. 11-1-Gha m² 782.66 Sq.ft

25mm thick mosaic flooring with 20mm thick p.c.c


1:2:4 base coarse sand and 5mm thick marble
16.5 Norms S.N.11-2 m² 1377.79 Sq.ft
chips white cement (1:1) surface coarse including
rubbing and polishing
25mm thick mosaic flooring with 20mm thick
cement plaster 1:2 base coarse sand and 6mm thick
16.6 Norms S.N.11-3 m² 2567.95 Sq.ft
marble chips white cement (1:1) surface coarse
including rubbing and polishing

20mm thick mosaic flooring with 12.5mm thick


cement plaster 1:2 base coarse sand and 6mm thick
16.7 Norms S.N.11-4 m² 2537.09 Sq.ft
marble chips white cement (1:1) surface coarse
including rubbing and polishing

20mm thick terrazo tiles flooring on 20mm thick


16.8 1:4 cement sand mortar including rubbing and Norms S.N.11-5 m² 2620.81 Sq.ft
polishing .
25mm thick marble(200x200)mm flooring on 20mm
(Norms S.N.11-
16.9 thick 1:2 cement sand mortar including rubbing 6)combination m² 2413.57 Sq.ft
and polishing .
Glazed Ceramic Tile of approved size and colour
16.10 with 1:4 cement sand mortar Norms S.N. 11-7 m² 2859.65 Sq.ft
Glazed Ceramic Tile of approved size and colour
16.11 Norms S.N. 11-7 m² 2859.65 Sq.ft
with 1:4 cement sand mortar
Flat brick soling in 1:2 cement sand mortar use for
16.12 Norms S.N. 11-12 m² 1109.44 Sq.ft
jointing.
16.13 Flat brick soling Norms S.N. 11-15-Ka m² 820.08 Sq.ft

16.14 Dry brick on edge soling Norms S.N. 11-15-Kha m² 1459.98 Sq.ft
16.15 Dry stone soling Norms S.N. 11-16 m³ 5528.50 Cu.ft

125mm thick on edge soling of bricks including


16.16 sand filling and flush pointing on the top surface of Norms S.N. 11-17 m² 1502.42 Sq.ft
the joint by 1:3 cement sand mortar.

1:1 Cement sand mortar pointing on joints of stone


16.17 pavement works(stone size is 460mm*460mm). Norms S.N. 11-18 m² 69.33 Sq.ft

Sand Filling Work including water sprinkling and


16.18 ramming all complete Norms S.N. 11-19 Ka m³ 2241.00 Cu.ft
Brick Blast Filling Work including all complete
16.19 Norms S.N. 11-19 Kha m³ 2500.00 Cu.ft
16.20 3mm thick cement punning Norms S.N. 11-20 m² 197.44 Sq.ft
25mm thick planking work using 50mm*75mm
16.21 Norms S.N. 11-21 m² 2779.92 Sq.ft
wooden frame @600mm*600mm size

17 Plastering Work
17.1 12.5mm thick 1:2 cement sand plaster Norms S.N. 12-1-Ka m² 312.33 Sq.ft

17.2 12.5mm thick 1:3 cement sand plaster Norms S.N. 12-1-Kha m² 276.62 Sq.ft

17.3 12.5mm thick 1:4 cement sand plaster Norms S.N. 12-1-Ga m² 267.90 Sq.ft

17.4 12.5mm thick 1:6 cement sand plaster Norms S.N. 12-1-Gha m² 248.86 Sq.ft

17.5 12.5mm thick 1:2 cement sand plaster on ceiling Norms S.N. 12-1-Ka m² 355.53 Sq.ft

17.6 12.5mm thick 1:3 cement sand plaster on ceiling Norms S.N. 12-1-Kha m² 319.82 Sq.ft

17.7 12.5mm thick 1:4cement sand plaster on ceiling Norms S.N. 12-1-Ga m² 311.10 Sq.ft

17.8 12.5mm thick 1:6 cement sand plaster on ceiling Norms S.N. 12-1-Gha m² 292.06 Sq.ft

17.9 20mm thick 1:3 cement sand plaster Norms S.N. 12-4-Ka m² 362.56 Sq.ft

17.10 20mm thick 1:4 cement sand plaster Norms S.N. 12-4-Kha m² 346.56 Sq.ft

17.11 20mm thick 1:6 cement sand plaster Norms S.N. 12-4-Ga m² 316.95 Sq.ft

17.12 20mm thick 1:3 cement sand plaster on ceiling Norms S.N. 12-4-Ka m² 413.39 Sq.ft

17.13 20mm thick 1:4 cement sand plaster on ceiling Norms S.N. 12-4-Kha m² 397.39 Sq.ft

17.14 20mm thick 1:6 cement sand plaster on ceiling Norms S.N. 12-4-Ga m² 367.79 Sq.ft

18 Painting works
18.1 1 coat white washing on new surface Norms S.N. 13-1-Ka m² 14.31 Sq.ft

18.2 2 coat white washing on new surface Norms S.N. 13-1-Kha m² 25.51 Sq.ft
18.3 1 coat white washing on new surface on ceiling Norms S.N. 13-1-Ka m² 16.71 Sq.ft

18.4 2 coat white washing on new surface on ceiling Norms S.N. 13-1-Kha m² 29.73 Sq.ft

18.5 Applying distemper paint- Primer Norms S.N. 13-3-Ka m² 56.94 Sq.ft
Applying distemper paint- One coat excluding
18.6 Norms S.N. 13-3-Kha m² 45.50 Sq.ft
primer

Applying distemper paint- Second coat and


18.7 Norms S.N. 13-3-Ga m² 38.31 Sq.ft
every other additional coats excluding primer

Applying distemper paint- One coat including


18.8 m² 102.44 Sq.ft
primer
Applying distemper paint- two coat including
18.9 m² 140.75 Sq.ft
primer
18.10 Applying one coat water proof cement paint Norms S.N. 13-4-Ka m² 29.30 Sq.ft

18.11 Applying two coat water proof cement paint Norms S.N. 13-4-Kha m² 75.86 Sq.ft
Applying readymade enamel paint or plastic
18.12 Norms S.N. 13-5-Ka m² 69.99 Sq.ft
emulsion paint-Primer Coat
Applying readymade enamel paint or plastic
18.13 emulsion paint-First Coat including Primer Norms S.N. 13-5-Kha m² 196.31 Sq.ft
Coat
Applying readymade enamel paint or plastic
18.14 emulsion paint-Second Coat including Primer Norms S.N. 13-5-Ga m² 302.96 Sq.ft
Coat
Applying two coat readymade aluminium paint on
18.15 Norms S.N. 13-6 m² 246.19 Sq.ft
one coat primer
18.16 Applying varnish- First coat Norms S.N. 13-9-Ka m² 59.14 Sq.ft
Applying varnish- Second coat and every other
18.17 Norms S.N. 13-9-Kha m² 54.74 Sq.ft
additional coats
18.18 Applying one coat bitumen paint Norms S.N. 13-10-Ka m² 38.50 Sq.ft

18.19 Applying two coat bitumen paint Norms S.N. 13-10-Kha m² 66.97 Sq.ft
Applying three coat Chapra(resin) polish Norms S.N. 13-11
18.20 m² 155.62 Sq.ft
application work
Applying cement paint (snowcem) on plastered Norms S.N. 13-12-Ka
18.21 m² 64.62 Sq.ft
surface-First coat
Applying cement paint (snowcem) on plastered
18.22 surface-Second coat and every other Norms S.N. 13-12-Kha m² 116.13 Sq.ft
additional coats
19 Pointing Works
Flush pointing works in 1:1 cement sand mortar on
19.1 Norms S.N. 14-1-Ka m² 186.36 Sq.ft
brick masonry
Flush pointing works in 1:2 cement sand mortar on
19.2 Norms S.N. 14-1-Kha m² 173.34 Sq.ft
brick masonry
Flush pointing works in 1:3 cement sand mortar on
19.3 Norms S.N. 14-1-Ga m² 166.49 Sq.ft
brick masonry
Flush rulled pointing works in 1:1 cement sand
19.4 Norms S.N. 14-2-Ka m² 235.98 Sq.ft
mortar on random rubble masonry
Flush rulled pointing works in 1:2 cement sand
19.5 Norms S.N. 14-2-Kha m² 211.02 Sq.ft
mortar on random rubble masonry
Flush rulled pointing works in 1:3 cement sand
19.6 Norms S.N. 14-2-Ga m² 198.38 Sq.ft
mortar on random rubble masonry

1:3 cement sand mortar pointing works on flat


19.7 Norms S.N. 14-4 m² 69.33 Sq.ft
stone pavement(stone size 450mm*450mm.

19.8 3mm flushing plaster in 1:1 cement sand mortar Norms S.N. 14-6 m² 174.98 Sq.ft
19.9 3mm thick flush plaster in cement Norms S.N. 14-8 m² 195.57 Sq.ft
20 Waterproofing Works
38mm thick Damp Proof Course(DPC) of cement concrete
20.1 with all complete Norms S.N.18-9 m² 513.87 Sq.ft
25mm thick Damp Proof Course(DPC) of cement concrete
20.2 with all complete Norms S.N.18-8 m² 420.03 Sq.ft
21 Dismantling & repair works
Dismantling work of stone masonry in mud mortar
21.1 Norms S.N. 19-1 m³ 556.50 Cu.ft
including disposal upto 10 m

Dismantling work of stone masonry in cement


21.2 Norms S.N. 19-2 m³ 1113.00 Cu.ft
sand mortar including disposal upto 10 m

Dismantling work of R.C.C./R.B.C. structure


21.3 Norms S.N. 19-3 m³ 5775.00 Cu.ft
including disposal upto 10 m
Dismantling work of P.C.C./R.B.C. structure
21.4 Norms S.N. 19-4 m³ 2100.00 Cu.ft
including disposal upto 10 m
Dismantling work of cement sand plaster including
21.5 Norms S.N. 19-5 m² 56.70 Cu.ft
disposal upto 10 m
22 Iron/Metal and other Works
Making 3mm*20mm iron grill & fixing including
cleaning by sand paper, applying aluminium Norms S.N.24-1-1
22.1 m² 1823.82 Sq.ft
paint.etc.complete.Take Weight of
grill=13.45kg/sq.m
Making 4.5mm*20mm iron grill & fixing including
cleaning by sand paper, applying aluminium
22.2 Norms S.N.24-1-2 m² 2302.49 Sq.ft
paint.etc.complete.Take Weight of
grill=16.98kg/sq.m
Making iron rolling shutter gate & fixing including
22.3 painting & wages complete.Take Weight of Norms S.N.24-2 m² 4049.92 Sq.ft
grill=25.6kg/sq.m

Making iron gate & fixing including painting & Norms S.N.24-3
22.4 m² 4255.58 Sq.ft
wages complete.Take Weight of grill=26.9kg/sq.m

Making iron gate & fixing including painting & Norms S.N.24-3
22.5 m² 5695.20 Sq.ft
wages complete.Take Weight of grill=36kg/sq.m

Making tubular truss & fixing complete..Take Norms S.N.24-5


22.6 m² 1792.46 Sq.ft
Weight of grill=11.75kg/sq.m
23 G.I barbed wire fencing work
G.I barbed wire fencing work Norms S.N.24-6 m 52.83 R.ft
24 Barbed wire extention work
Barbed wire extention work including material
providing with 5 line horizontal and 2 line Norms S.N.24-7
m 527.41 R.ft
diagonal@3 m c/c apart wooden pole (size of pole
75mm*100mm*2100mm)
25 Gabion work
Gabion boxes preparation work including supplying GI wire,cutting,rolling weaving,streching,boulder packing,binding
and tyieng all complete.According to DOLIDAR Norms
Hexagonal Mesh size: 100mm*120mm,Mesh wire : 10 SWG,Selvedge wire: 7 SWG,Binding wire : 12 SWG
Norms Serial No.
Box Size : 3m*1m*1m 44.1-B-ii-a & 44.2-i-a m³ 3437.09 Cu.ft

Norms Serial No.


Box Size : 2m*1m*1m 44.1-B-ii-a & 44.2-i-a m³ 3490.90 Cu.ft

26 Gabion work for River Training


Gabion boxes preparation work including supplying GI wire,cutting,rolling weaving,streching,boulder packing,binding
and tyieng all complete.According to General Norms
Hexagonal Mesh size: 100mm*120mm,Mesh wire : 10 SWG,Selvedge wire: 7 SWG,Binding wire : 12 SWG
Norms Serial No. 16-
Box Size : 2m*1m*1m 5ka,16-7ka &16-11 m³ 3287.10 Cu.ft

Norms Serial No. 16-


Box Size : 2m*1m*0.5m 5Ga,16-7Ga &16-11 m³ 4018.78 Cu.ft

Norms Serial No. 16-


Box Size : 2m*1m*0.3m 5NGa,16-7NGa &16- m³ 4679.25 Cu.ft
11

Norms Serial No. 16-


Box Size : 3m*1m*1m 5kha,16-7kha& 16-11 m³ 3214.56 Cu.ft

Norms Serial No. 16-


Box Size : 3m*1m*0.5m 5Gha,16-7Gha& 16- m³ 3805.73 Cu.ft
11

Norms Serial No. 16-


Box Size : 3m*1m*0.3m 5Cha,16-7Cha& 16-11 m³ 4701.46 Cu.ft

Square Mesh size: 100mm*100mm( Mesh wire : 10 SWG,Selvedge wire: 7 SWG)


Norms Serial No. 16-
Box Size : 3m*1.5m*0.75m 9Ka& 16-11 m³ 2790.17 Cu.ft
Square Mesh size: 150mm*150mm( Mesh wire : 10 SWG,Selvedge wire: 7 SWG)
Norms Serial No. 16-
Box Size : 3m*1.5m*0.75m 9Kha& 16-11 m³ 2343.84 Cu.ft
27 Miscellaneous Items
Fixing of 4mm thick commercial plywood by using Norms S.N. 10-11-
27.1 Kha m² 483.16 Sq.ft
nails
Fixing of mosquitoproof net and expended metal Norms S.N.:-Similar
27.2 to 10-12 m² 701.85 Sq.ft
net(Barfi Jali) using wooden listy
Norms S.N.:-Similar
27.3 Fixing of mosquitoproof net using wooden listy to 10-12 m² 470.48 Sq.ft
Fixing of expended metal net(Barfi Jali) using Norms S.N.:-Similar
27.4 to 10-12 m² 405.22 Sq.ft
wooden listy
- 2073/074

FPS
Rate

0.49

7.81

1.95

10.73

12.26

45.98

76.64

370.92

15.33

19.16

24.37

68.97

386.25
7.44

3.72

23.6

24.45

60.3

7.66

8.43

9.66

9.2

6.44
8.12
13.49
16.86

21.28

20.83

81.85

358.75

347.87

337.44
363.74

352.86

342.43

371.41

360.52

350.09

237.68

225.81

206.69

90.18

93.9

65.35
112.5

249.24

ply of materials and

210.5

245.01
s and haulage

233.59

268.14
nd haulage distance

320.78

355.33
s and haulage

308.59

338.69

417.48

314

104.01

111.85

ing and transporting up

59.72

88.56

92.14

76.74

92.52

53.2

78.85

151.02

2485.14
6318.55
4882.48
1039.09

585.06

869

710.39

459.32

616.33

629.14

667.94

563.17

601.97

453.04

491.84

655.44

589.47

479.34

406.02

425.45

356.45
273.69

83.39

51.99

168.95

290.5

6535.4

7742.28
147.88

31.96

43.62

53.55

72.74

128.05

238.66

235.79

243.57

224.31

265.77

265.77

103.11
76.22

135.69
156.7

139.63

6.44

63.52

70.86
18.35

258.36

29.03

25.71

24.9

23.13

33.04

29.72

28.91

27.14

33.7

32.21

29.46

38.42

36.93

34.18

1.33

2.37
1.55

2.76

5.29

4.23

3.56

9.52

13.08

2.72

7.05

6.5

18.24

28.16

22.88

5.5

5.09

3.58

6.22

14.46

6.01

10.79

17.32

16.11

15.47

21.93
19.61

18.44

6.44

16.26
18.18

47.76

39.04

15.77

31.55

163.69

59.52

1.61

169.5

213.99

376.39

395.5

529.29

166.59

16.1
160.75

boulder packing,binding
re : 12 SWG

97.42

98.95

boulder packing,binding
re : 12 SWG

93.17

113.91

132.63

91.12

107.87

133.26

79.09

66.44

44.9

65.23

43.72

37.66
Government of Nepal
Ministry of Federal Affairs and Local Development
Office of District Development Committee
DISTRICT TECHNICAL OFFICE
Chitwan

RATE ANALYSIS FOR Users Committee


Fiscal Year:2073/074
Site Preparation
Surface dressing pots filling, levelling of undulated ground, landscaping all complete work, and Surface levelling etc.
(Survice road)
Analyzed for: 1 m² Norms S.N. 1-7
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 0.01 no. 525.00 5.25
Grand-Total 5.25

Removal of grasses, small trees, levelling of undulated ground, landscaping all complete work, and disposal of existing
earth materials away from construction site (thickness 15- 20 cm)
Analyzed for: 1 m² Norms S.N. 1-8
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 0.16 no. 525.00 84.00
Sub-Total 84.00

Top soil spreading in manner sloped/Spreading top soils at the required slope.
Analyzed for: 1 m³ Norms S.N. 1-9
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 0.04 no. 525.00 21.00
Sub-Total 21.00

Earthwork/ Sand work


Earthwork excavation in soft clay and silt soil including disposal upto (1.5m lift & 10m lead).
Analyzed for: 1 m³ Norms S.N. 2-1
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 0.7 no. 525.00 367.50
Tools & equipments @ 3% of total labour cost 11.03
Sub-Total 378.53

Earthwork excavation in hard soil including disposal upto (1.5m lift & 10m lead).
Analyzed for: 1 m³ Norms S.N. 2-2
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 0.8 no. 525.00 420.00
Tools & equipments @ 3% of total labour cost 12.60
Sub-Total 432.60

Removal of stones including disposal upto (1.5m lift & 10m lead).
Analyzed for: 1 m³ Norms S.N. 2-3
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 1 no. 525.00 525.00
Tools & equipments @ 3% of total labour cost 15.75
Sub-Total 540.75

Earthwork excavation in medium types of stone/rocks without blasting including disposal upto(1.5m lift & 10m lead)
Analyzed for: 1 m³ Norms S.N. 2-4
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 3 no. 525.00 1575.00
Tools & equipments @ 3% of total labour cost 47.25
Sub-Total 1622.25

Earthwork in excavation in hard rock without Chiseling(1.5m lift & 10m lead)
Analyzed for: 1 m³ Norms S.N. 2-6ka
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 5 no. 525.00 2625.00
Tools & equipments @ 3% of total labour cost 78.75
Sub-Total 2703.75

Earthwork in excavation in hard rock with Chiseling(1.5m lift & 10m lead)
Analyzed for: 1 m³ Norms S.N. 2-6kha
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 24.2 no. 525.00 12705.00
Tools & equipments @ 3% of total labour cost 381.15
Sub-Total 13086.15

Earthwork excavation in soft soil including disposal upto (1.5m lift & 10m lead).
Analyzed for: 1 m³ Norms S.N. 2-9
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 1 no. 525.00 525.00
Tools & equipments @ 3% of total labour cost 15.75
Sub-Total 540.75
Ditch cutting in hard soil including disposal upto (10m lead & 1.5m lift)
Analyzed for: 1 m³ Norms S.N. 2-12
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 1.25 no. 525.00 656.25
Tools & equipments @ 3% of total labour cost 19.69
Sub-Total 675.94

Earthwork in excavation in foundation, drain and pipeline in boulder mixed soil (10m lead & 1.5m lift)
Analyzed for: 1 m³ Norms S.N. 2-14
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 1.59 no. 525.00 834.75
Tools & equipments @ 3% of total labour cost 25.04
Sub-Total 859.79

Earthwork in excavation in foundation, drain etc. in medium rock without blasting (10m lead & 1.5m lift)
Analyzed for: 1 m³ Norms S.N. 2-15-Kha
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 4.5 no. 525.00 2362.50
Tools & equipments @ 3% of total labour cost 70.88
Sub-Total 2433.38

Earthwork in excavation in foundation, drain,tunnel etc. by chiseling in hard rock without blasting (10m lead & 1.5m lift)
Analyzed for: 1 m³ Norms S.N. 2-16-Kha
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 25.2 no. 525.00 13230.00
Tools & equipments @ 3% of total labour cost 396.90
Sub-Total 13626.90
Earth filling & compaction
Earth filling & compaction in 15 cm layers with sprinkling water (Transporting from 10m)
Analyzed for: 1 m³ Norms S.N. 2-25-Ka
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 0.5 no. 525.00 262.50
Materials Soil 1.2 Cu.m 0.00 Soil from out of side
Tools & equipments @ 3% of total labour cost 0.00
Sub-Total 262.50

Earth filling & compaction in 15 cm layers without sprinkling water (Transporting from 10m)
Analyzed for: 1 m³ Norms S.N. 2-25 Kha
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 0.25 no. 525.00 131.25
Materials Soil 1.2 Cu.m 0.00 Soil from out of side
Tools & equipments @ 3% of total labour cost 0.00
Sub-Total 131.25

Earth filling & compaction in 15 cm layers with sprinkling water (Transporting from 10m)
Analyzed for: 1 m³ Norms S.N. 2-25-Ka
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 0.5 no. 525.00 262.50
Materials Soil 1.2 Cu.m 475.00 570.00 Soil from out of side
Tools & equipments @ 3% of total labour cost 0.00
Sub-Total 832.50

Earth filling & compaction in 15 cm layers with sprinkling water (Transporting from 10m)
Analyzed for: 1 m³ Norms S.N. 2-25-Ka
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 0.5 no. 525.00 262.50
Materials Soil 1.2 Cu.m 500.00 600.00 Gravel Mixed Soil
Tools & equipments @ 3% of total labour cost 0.00
Sub-Total 862.50
Earth filling & compaction in 15 cm layers without sprinkling water (Transporting from 10m)
Analyzed for: 1 m³ Norms S.N. 2-25 Kha
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 0.25 no. 525.00 131.25
Materials Soil 1.2 Cu.m 0.00 Soil from out of side
Tools & equipments @ 3% of total labour cost 0.00
Sub-Total 131.25
Sand filling & compaction with sprinkling water (Transporting from 10m)
Analyzed for: 1 m³ Norms S.N. 2-42
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 0.7 no. 525.00 367.50
Materials Sand 1.1 m³ 1600.00 1760.00
Tools & equipments @ 3% of total labour cost 0.00
Sub-Total 2127.50

Refilling of pipe line trench


Refilling of pipe line trench with soft soil including watering and ramming every 20 cm layers (Lead 10m)
Analyzed for: 1 m³ Norms S.N. 2-39-Ka
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 0.5 no. 525.00 262.50
Tools & equipments @ 3% of total labour cost 7.88
Sub-Total 270.38

Refilling of pipe line trench with medium soil including watering and ramming every 20 cm layers (Lead 10m)
Analyzed for: 1 m³ Norms S.N. 2-39-Kha
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 0.55 no. 525.00 288.75
Tools & equipments @ 3% of total labour cost 8.66
Sub-Total 297.41

Refilling of pipe line trench with hard soil including watering and ramming every 20 cm layers (Lead 10m)
Analyzed for: 1 m³ Norms S.N. 2-39-Ga
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 0.63 no. 525.00 330.75
Tools & equipments @ 3% of total labour cost 9.92
Sub-Total 340.67

Refilling of pipe line trench with gravel and boulder mixed soil including watering and ramming every 20 cm layers (Lead
10m)
Analyzed for: 1 m³ Norms S.N. 2-39-Gha
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 0.6 no. 525.00 315.00
Tools & equipments @ 3% of total labour cost 9.45
Sub-Total 324.45

Land slide clearance work/Prevantion of land slide in


A)Ordinary Soil
Analyzed for: 1 m³ Norms S.N. 2-45-a
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 0.42 no. 525.00 220.50
Tools & equipments @ 3% of total labour cost 6.62
Sub-Total 227.12

B)Gravel and Boulder mix soils


Analyzed for: 1 m³ Norms S.N. 2-45-b
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 0.53 no. 525.00 278.25
Tools & equipments @ 3% of total labour cost 8.35
Sub-Total 286.60
C)Soft Rocks
Analyzed for: 1 m³ Norms S.N. 2-45-c
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 0.88 no. 525.00 462.00
Tools & equipments @ 3% of total labour cost 13.86
Sub-Total 475.86
D)Hard rocks
Analyzed for: 1 m³ Norms S.N. 2-45-d
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 1.1 no. 525.00 577.50
Tools & equipments @ 3% of total labour cost 17.33
Sub-Total 594.83
Collection and stacking of required size stone
Collection,screeding and providing of sand (haulage distance 10 m)
Source Capacity>65%
Analyzed for: 1 m³ Norms S.N. 3-1-d
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 1.43 no. 525.00 750.75
Sub-Total 750.75

Collection of rubble stone of required size including stacking. (haulage distance 10 m)


Analyzed for: 1 m³ Norms S.N. 3-4
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 1.4 no. 525.00 735.00
Sub-Total 735.00

Making and stacking of required size stone by using Chisel including 10m lead (without blasting)
Analyzed for: 1 m³ Norms S.N. 3-11
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 5.5 no. 525.00 2887.50
Sub-Total 2887.50

Brick Masonry
Brick masonry work in 1:3 cement mortar in foundation with providing chimney made bricks (Transporting from 30m)
Analyzed for: 1 m³ Norms S.N. 5-1-Kha-1
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1.5 no. 740.00 1110.00
Labours
Unskilled 2.2 no. 525.00 1155.00
Bricks 560 no. 14.69 8226.40
Materials Cement 0.13 MT 13334.00 1733.42
Sand 0.27 m³ 1600.00 432.00
Sub-Total 12656.82

Brick masonry work in 1:4 cement mortar in foundation with providing chimney made bricks (Transporting from 30m)
Analyzed for: 1 m³ Norms S.N. 5-1-Kha-2
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1.5 no. 740.00 1110.00
Labours
Unskilled 2.2 no. 525.00 1155.00
Bricks 560 no. 14.69 8226.40
Materials Cement 0.1 MT 13334.00 1333.40
Sand 0.28 m³ 1600.00 448.00
Sub-Total 12272.80
Grand-Total 12272.80
Brick masonry work in 1:6 cement mortar in foundation with providing chimney made bricks (Transporting from 30m)
Analyzed for: 1 m³ Norms S.N. 5-1-Kha-3
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1.5 no. 740.00 1110.00
Labours
Unskilled 2.2 no. 525.00 1155.00
Bricks 560 no. 14.69 8226.40
Materials Cement 0.07 MT 13334.00 933.38
Sand 0.3 m³ 1600.00 480.00
Sub-Total 11904.78

Brick masonry work in 1:3 cement mortar in ground floor with providing chimney made bricks (Transporting from 30m)
Analyzed for: 1 m³ Norms S.N. 5-1-Kha-1 & 5-2-Ka
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1.5 no. 740.00 1110.00
Labours
Labours
Unskilled 2.2 no. 525.00 1155.00
Bricks 560 no. 14.69 8226.40
Materials Cement 0.13 MT 13334.00 1733.42
Sand 0.27 m³ 1600.00 432.00
Unskilled 0.2 no. 525.00 105.00
Scaffolding
Materials 3% of Labour cost 71.10 71.10
Sub-Total 12832.92

Brick masonry work in 1:4 cement mortar in ground floor with providing chimney made bricks (Transporting from 30m)
Analyzed for: 1 m³ Norms S.N. 5-1-Kha-2 & 5-2-Ka
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1.5 no. 740.00 1110.00
Labours
Unskilled 2.2 no. 525.00 1155.00
Bricks 560 no. 14.69 8226.40
Materials Cement 0.1 MT 13334.00 1333.40
Sand 0.28 m³ 1600.00 448.00
Unskilled 0.2 no. 525.00 105.00
Scaffolding
Materials 3% of Labour cost 71.10 71.10
Sub-Total 12448.90

Brick masonry work in 1:6 cement mortar in ground floor with providing chimney made bricks (Transporting from 30m)
Analyzed for: 1 m³ Norms S.N. 5-1-Kha-3 & 5-2-Ka
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1.5 no. 740.00 1110.00
Labours
Unskilled 2.2 no. 525.00 1155.00
Bricks 560 no. 14.69 8226.40
Materials Cement 0.07 MT 13334.00 933.38
Sand 0.3 m³ 1600.00 480.00
Unskilled 0.2 no. 525.00 105.00
Scaffolding
Materials 3% of Labour cost 71.10 71.10
Sub-Total 12080.88

Brick masonry work in 1:3 cement mortar above ground floor with providing chimney made bricks (Transporting from 30m)
Analyzed for: 1 m³ Norms S.N. 5-1-Kha-1 & 5-2-Kha
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1.5 no. 740.00 1110.00
Labours
Unskilled 2.2 no. 525.00 1155.00
Bricks 560 no. 14.69 8226.40
Materials Cement 0.13 MT 13334.00 1733.42
Sand 0.27 m³ 1600.00 432.00
Unskilled 0.7 no. 525.00 367.50
Scaffolding
Materials 3% of Labour cost 78.98 78.98
Sub-Total 13103.30

Brick masonry work in 1:4 cement mortar above ground floor with providing chimney made bricks (Transporting from 30m)
Analyzed for: 1 m³ Norms S.N. 5-1-Kha-2 & 5-2-Kha
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1.5 no. 740.00 1110.00
Labours
Unskilled 2.2 no. 525.00 1155.00
Bricks 560 no. 14.69 8226.40
Materials Cement 0.1 MT 13334.00 1333.40
Sand 0.28 m³ 1600.00 448.00
Unskilled 0.7 no. 525.00 367.50
Scaffolding
Scaffolding
Materials 3% of Labour cost 78.98 78.98
Sub-Total 12719.28

Brick masonry work in 1:6 cement mortar above ground floor with providing chimney made bricks (Transporting from 30m)
Analyzed for: 1 m³ Norms S.N. 5-1-Kha-3 & 5-2-Kha
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1.5 no. 740.00 1110.00
Labours
Unskilled 2.2 no. 525.00 1155.00
Bricks 560 no. 14.69 8226.40
Materials Cement 0.07 MT 13334.00 933.38
Sand 0.3 m³ 1600.00 480.00
Unskilled 0.7 no. 525.00 367.50
Scaffolding
Materials 3% of Labour cost 78.98 78.98
Sub-Total 12351.26

Stone Masonry
Random rubble masonry work in 1:3 cement mortar including providing block stone up to 5m height (Transporting from 10m)
Analyzed for: 1 m³ Norms S.N. 6-1-Ka-1
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1.5 no. 740.00 1110.00
Labours
Unskilled 5 no. 525.00 2625.00
Cement 0.194 MT 13334.00 2586.80
Sand 0.42 m³ 1600.00 672.00
Materials
Block Stone 1 m³ 1265.00 1265.00
Bond Stone 0.1 m³ 1265.00 126.50
Sub-Total 8385.30

Random rubble masonry work in 1:4 cement mortar including providing block stone up to 5m height (Transporting from 10m)
Analyzed for: 1 m³ Norms S.N. 6-1-Ka-2
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1.5 no. 740.00 1110.00
Labours
Unskilled 5 no. 525.00 2625.00
Cement 0.159 MT 13334.00 2120.11
Sand 0.45 m³ 1600.00 720.00
Materials
Block Stone 1 m³ 1265.00 1265.00
Bond Stone 0.1 m³ 1265.00 126.50
Sub-Total 7966.61

Random rubble masonry work in 1:6 cement mortar including providing block stone up to 5m height (Transporting from 10m)
Analyzed for: 1 m³ Norms S.N. 6-1-Ka-3
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1.5 no. 740.00 1110.00 997.5
Labours
Unskilled 5 no. 525.00 2625.00 2350.00
Cement 0.106 MT 13334.00 1413.40 1413.40
Sand 0.47 m³ 1600.00 752.00 681.50
Materials
Block Stone 1 m³ 1265.00 1265.00 1500.00
Bond Stone 0.1 m³ 1265.00 126.50 150.00
Sub-Total 7291.90

Random rubble masonry work in dry including providing block stone up to 5m height (Transporting from 30m)
Analyzed for: 1 m³ Norms S.N. 6-2-1
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1 no. 740.00 740.00
Labours
Labours
Unskilled 2 no. 525.00 1050.00
Block Stone 1 m³ 1265.00 1265.00
Materials
Bond Stone 0.1 m³ 1265.00 126.50
Sub-Total 3181.50

Random rubble masonry work in mud mortar including providing block stone up to 5m height (Transporting from 30m)
Analyzed for: 1 m³ Norms S.N. 6-2-2
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1 no. 740.00 740.00
Labours
Unskilled 2.25 no. 525.00 1181.25
Block Stone 1 m³ 1265.00 1265.00
Materials Bond Stone 0.10 m³ 1265.00 126.50
Mud 0.42 m³ 0.00
Sub-Total 3312.75

Boulder filling in foundation with levelling (Transporting from 30m)


Analyzed for: 1 m³ Norms S.N. 6-5
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 1.5 no. 525.00 787.50
Block Stone 1 m³ 1265.00 1265.00
Materials
Bond Stone 0.20 m³ 1265.00 253.00
Sub-Total 2305.50

Dry Stone soling ( 1cu.m/35.28 cft ) Norms S.N. 11-16


Analyzed for: 1 m³
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1 no. 740.00 740.00
Labours
Unskilled 3.5 no. 525.00 1837.50
Materials Stone 1.1 m³ 1265.00 1391.50
Sub-Total 3969.00

Masonry Work in Block


Masonry work in 1:6 cement mortar including providing precast block up to 5m height (Transporting from 30m)
Analyzed for: 1 m³ Provided by Municipality Norms S.N.
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1.5 no. 740.00 1110.00
Labours Unskilled 2.2 no. 525.00 1155.00
Unskilled 0.2 no. 525.00 105.00
Cement 0.07 MT 13334.00 933.38
Sand 0.3 m³ 1600.00 480.00
Materials Precast Block(6''*8''*16'') 80 no. 62.15 4972.00
other materials for 3% of unskilled no. 37.80
scafolding
Sub-Total 8793.18

Cement Concrete Work


Cement concrete work in foundation, floor, walls & abutment (plum concrete) including Supply of materials and haulage
distance upto 30m.
P.C.C. (1:3:6)
Analyzed for: 1 m³ Norms S.N. 7-1-Ka
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 0.30 no. 740.00 222.00
Labours
Unskilled 4.00 no. 525.00 2100.00
Cement 0.22 MT 13334.00 2933.48
Coarse Sand 0.47 m³ 1600.00 752.00
Materials 20mm River bed Aggregate 0.60 m³ 1485.00 891.00
10mm River bed Aggregate 0.20 m³ 1485.00 297.00
225mm Boulder 0.14 m³ 1650.00 231.00
Sub-Total 7426.48

P.C.C. (1:2:4)
Analyzed for: 1 m³ Norms S.N. 7-1-Kha
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 0.30 no. 740.00 222.00
Labours
Unskilled 4.00 no. 525.00 2100.00
Cement 0.32 MT 13334.00 4266.88
Coarse Sand 0.45 m³ 1600.00 712.00
Materials 20mm River bed Aggregate 0.57 m³ 1485.00 846.45
10mm River bed Aggregate 0.19 m³ 1485.00 282.15
225mm Boulder 0.13 m³ 1650.00 214.50
Sub-Total 8643.98

Cement concrete work in foundation, floor, walls & abutment including Supply of materials and haulage distance upto 30m.
P.C.C. (1:3:6)
Analyzed for: 1 m³ Norms S.N. 7-2-Ga
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1 no. 740.00 740.00
Labours
Unskilled 4 no. 525.00 2100.00
Cement 0.22 MT 13334.00 2933.48
Sand 0.47 m³ 1600.00 752.00
Materials
40mm Aggregate 0.65 m³ 1925.00 1251.25
20mm Aggregate 0.24 m³ 1935.00 464.40
Sub-Total 8241.13

P.C.C. (1:2:4)
Analyzed for: 1 m³ Norms S.N. 7-2-Gha
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1 no. 740.00 740.00
Labours
Unskilled 4 no. 525.00 2100.00
Cement 0.32 MT 13334.00 4266.88
Sand 0.445 m³ 1600.00 712.00
Materials 40mm Aggregate 0.52 m³ 1925.00 1001.00
20mm Aggregate 0.22 m³ 1935.00 425.70
10mm Aggregate 0.11 m³ 1950.00 214.50
Sub-Total 9460.08

Cement concrete work in abuitment seats,piel caps etc. including supply of materials and haulage distance upto 30m
P.C.C. (1:3:6)
Analyzed for: 1 m³ Norms S.N. 7-3-Ka
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 0.9 no. 740.00 666.00
Labours
Unskilled 10 no. 525.00 5250.00
Cement 0.22 MT 13334.00 2933.48
Sand 0.47 m³ 1600.00 752.00
Materials
40mm Aggregate 0.65 m³ 1925.00 1251.25
20mm Aggregate 0.24 m³ 1935.00 464.40
Sub-Total 11317.13
Grand-Total 11317.13

P.C.C. (1:2:4)
Analyzed for: 1 m³ Norms S.N. 7-3-Kha
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 0.9 no. 740.00 666.00
Labours
Unskilled 10 no. 525.00 5250.00
Cement 0.32 MT 13334.00 4266.88
Sand 0.445 m³ 1600.00 712.00
Materials 40mm Aggregate 0.52 1925.00 1001.00
20mm Aggregate 0.22 m³ 1935.00 425.70
10mm Aggregate 0.11 m³ 1950.00 214.50
Sub-Total 12536.08

Cement concrete work in super-structure, deck, slab, beams including providing materials and haulage distance upto 30m
P.C.C. (1:2:4)
Analyzed for: 1 m³ Norms S.N. 7-4-Ka
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 0.8 no. 740.00 592.00
Labours
Unskilled 7 no. 525.00 3675.00
Cement 0.32 MT 13334.00 4266.88
Sand 0.445 m³ 1600.00 712.00
Materials 40mm Aggregate 0.52 m³ 1925.00 1001.00
20mm Aggregate 0.22 m³ 1935.00 425.70
10mm Aggregate 0.11 m³ 1950.00 214.50
Sub-Total 10887.08

P.C.C. (1:1.5:3)
Analyzed for: 1 m³ Norms S.N. 7-4-Kha
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 0.8 no. 740.00 592.00
Labours
Unskilled 7 no. 525.00 3675.00
Cement 0.4 MT 13334.00 5333.60
Sand 0.425 m³ 1600.00 680.00
Materials
20mm Aggregate 0.57 m³ 1935.00 1102.95
10mm Aggregate 0.29 m³ 1950.00 565.50
Sub-Total 11949.05

P.C.C. (1:1:2)
Analyzed for: 1 m³ Norms S.N. 7-4-Ga
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 0.8 no. 740.00 592.00
Labours
Unskilled 7 no. 525.00 3675.00
Cement 0.61 MT 13334.00 8133.74
Sand 0.425 m³ 1600.00 680.00
Materials
20mm Aggregate 0.64 m³ 1935.00 1238.40
10mm Aggregate 0.21 m³ 1950.00 409.50
Sub-Total 14728.64

Cement concrete work in super-structure, deck, slab, beams including providing materials and haulage distance upto 30m-Precast Work
P.C.C. (1:2:4)
Analyzed for: 1 m³ Norms S.N. 7-9
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1.20 no. 740.00 888.00
Labours
Unskilled 6.80 no. 525.00 3570.00
Cement 0.32 MT 13334.00 4266.88
Sand 0.445 m³ 1600.00 712.00
Materials 40mm Aggregate 0.52 m³ 1925.00 1001.00
20mm Aggregate 0.22 m³ 1935.00 425.70
10mm Aggregate 0.11 m³ 1950.00 214.50
Sub-Total 11078.08
Steel Work
Curtailment, bent up, placing & binding the MS bar with binding wire as shown in drawings including haulage distance 30m.
Analyzed for: 1 MT Norms S.N. 7-5
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 12.00 no. 740.00 8880.00
Labours
Unskilled 12.00 no. 525.00 6300.00
MS Bar 1.05 MT 83702.50 87887.63
Materials
Binding Wire 10.00 kg 94.36 943.60
Sub-Total 104011.23
For 1 kg 104.01

Form Work
Form work for beams, slab in structure including, screening, fitting, oiling, dismantling, removing and transporting up to 30m
A) For Slab
Analyzed for: 10 m² Norms S.N. 8-2-Ka
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1.72 no. 740.00 1272.80
Labours
Unskilled 2.57 no. 525.00 1349.25
Wood* 0.06575 m³ 53558.00 3521.44
Materials
Nails 2.5 kg 113.00 282.50
Sub-Total 6425.99
For 1 m² 642.60
* Assuming timber and ballies will become unserviceable after being used for 8 times

B) For Column-circumfrance upto 2m height


Analyzed for: 10 m² Norms S.N. 8-3-Ka
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 3.748 no. 740.00 2773.52
Labours
Unskilled 5.622 no. 525.00 2951.55
Wood* 0.06575 m³ 53558.00 3521.44
Materials
Nails 2.5 kg 113.00 282.50
Sub-Total 9529.01
For 1 m² 952.90
* Assuming timber and ballies will become unserviceable after being used for 8 times
C) For Beam-Depth of beam upto 30cm
Analyzed for: 10 m² Norms S.N. 8-4-Ka
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 4 no. 740.00 2960.00
Labours
Unskilled 6 no. 525.00 3150.00
Wood* 0.06575 m³ 53558.00 3521.44
Materials
Nails 2.5 kg 113.00 282.50
Sub-Total 9913.94
For 1 m² 991.39
* Assuming timber and ballies will become unserviceable after being used for 8 times

Roofing Work
Roofing work by 26 gauge(0.38mm thick)non-coloured CGI sheets (Medium) including providing CGI sheets
Analyzed for: 10 m² Norms S.N. 9-1
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1.1 no. 740.00 814.00
Labours
Unskilled 1.25 no. 525.00 656.25
22*24 C.G.I.Sheet 12 m² 492.06 5904.72
8mm Nut Bolt 30 no. 11.30 339.00
Materials
J Hooks 25 no. 20.98 524.50
Bitumen Washer 55 no. 0.34 18.70
Sub-Total 8257.17
For 1 m² 825.72

Roofing work by 26 gauge coloured CGI sheets including providing CGI sheets
Analyzed for: 10 m² Norms S.N. 9-1
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1.1 no. 740.00 814.00
Labours
Unskilled 1.25 no. 525.00 656.25
22*24 C.G.I.Sheet 12 m² 633.56 7602.72
8mm Nut Bolt 30 no. 11.30 339.00
Materials
J Hooks 25 no. 20.98 524.50
Bitumen Washer 55 no. 0.34 18.70
Sub-Total 9955.17
For 1 m² 995.52

Ridge covering with 28 gauge non-colour G. I. plain sheet including supplying of materials, J or L hooks, nut bolts, washers, fixing of C.G.I sheet over
roofing members in proper slope and size
Analyzed for: 10 r.m. Norms S.N. 9-2
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 2 no. 740.00 1480.00
Labours
Unskilled 3 no. 525.00 1575.00
Plane Sheet 12 r.m. 187.44 2249.28
Materials
J Hooks 20 no. 20.98 419.60
Sub-Total 5723.88
For 1 rm 572.39
Ridge covering with 28
gauge colour G. I. plain sheet including supplying of materials, J or L hooks, nut bolts, washers, fixing
of C.G.I sheet over roofing members in proper slope and size
Analyzed for: 10 r.m. Norms S.N. 9-2
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 2 no. 740.00 1480.00
Labours
Unskilled 3 no. 525.00 1575.00
Plane Sheet 12 r.m. 417.47 5009.64
Materials
J Hooks 20 no. 20.98 419.60
Sub-Total 8484.24
For 1 rm 848.42
Roofing work by providing slate
Analyzed for: 10 m² Norms S.N. 9-5
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 4 no. 740.00 2960.00
Labours
Unskilled 5 no. 525.00 2625.00
Slate 24 m² 0.00
Materials
Nails 0.75 kg 113.00 84.75
Sub-Total
For 1 m² 0.00

Wood work for 20mm thick ceiling with 40*20mm beading joint by providing materials
Analyzed for: 10 m² Norms S.N. 9-10
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1.8 no. 740.00 1332.00
Labours
Unskilled 1.5 no. 525.00 787.50
Wood 0.26 m³ 53558.00 13925.08
Materials Nails 0.40 kg 113.00 45.20
40mm Screws 160.00 no. 1.00 160.00
Sub-Total 16249.78
For 1 m² 1624.98
Wood Work
Local wood work for choukosh
Analyzed for: 1 m³ Norms S.N. 10-1
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 34 no. 740.00 25160.00
Labours
Unskilled 3.4 no. 525.00 1785.00
Local Wood 1.1 m³ 53558.00 58913.80
Materials Holdfast 92.00 no. 17.75 1633.00
Screw 184.00 no. 1.00 184.00
Sub-Total 87675.80

Sal wood work for choukosh


Analyzed for: 1 m³ Norms S.N. 10-1
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 34 no. 740.00 25160.00
Labours
Unskilled 3.4 no. 525.00 1785.00
Sal Wood 1.1 m³ 176506.00 194156.60
Materials Holdfast 92.00 no. 17.75 1633.00
Screw 184.00 no. 1.00 184.00
Sub-Total 222918.60

Sisaum wood work for choukosh


Analyzed for: 1 m³ Norms S.N. 10-1
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 34 no. 740.00 25160.00
Labours
Unskilled 3.4 no. 525.00 1785.00
Sisaum Wood 1.1 m³ 130447.20 143491.92
Materials Holdfast 92.00 no. 17.75 1633.00
Screw 184.00 no. 1.00 184.00
Sub-Total 172253.92

38 mm thick solid panelled shutter using Sal wood


Analyzed for: 2.114 m² (Size 1.07m x 1.982m) Norms S.N. 10-2
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 10 no. 740.00 7400.00
Labours
Unskilled 1 no. 525.00 525.00
sal Wood 0.084 m³ 176506.00 14826.50
100mm Hinges-Kabja 6 no. 33.90 203.40
150mm Towerbolt-Chheskini 1 no. 67.80 67.80
Materials 300mm Towerbolt 1 no. 169.50 169.50
250mm Locking Set 1 no. 282.50 282.50
Materials

6'' Handles 2 no. 56.50 113.00


Screws* 48 LS 1.00 48.00
Sub-Total 23635.70
Rate per m² 11180.56
*About 1/2 kg

38 mm thick solid panelled shutter using Local Wood


Analyzed for: 2.114 m² (Size 1.07m x 1.982m) Norms S.N. 10-2
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 10 no. 740.00 7400.00
Labours
Unskilled 1 no. 525.00 525.00
Local Wood 0.084 m³ 53558.00 4498.87
100mm Hinges-Kabja 6 no. 33.90 203.40
150mm Towerbolt-Chheskini 1 no. 67.80 67.80
Materials 340mm Towerbolt 1 no. 169.50 169.50
250mm Locking Set 1 no. 282.50 282.50
6'' Handles 2 no. 56.50 113.00
Screws* 48 LS 1.00 48.00
Sub-Total 13308.07
Rate per m² 6295.21
*About 1/2 kg

38 mm thick solid panelled shutter using Sisauml Wood


Analyzed for: 2.114 m² (Size 1.07m x 1.982m) Norms S.N. 10-2
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 10 no. 740.00 7400.00
Labours
Unskilled 1 no. 525.00 525.00
Sisaum Wood 0.084 m³ 130447.20 10957.56
100mm Hinges-Kabja 6 no. 33.90 203.40
150mm Towerbolt-Chheskini 1 no. 67.80 67.80
Materials 340mm Towerbolt 1 no. 169.50 169.50
250mm Locking Set 1 no. 282.50 282.50
6'' Handles 2 no. 56.50 113.00
Screws* 48 LS 1.00 48.00
Sub-Total 19766.76
Rate per m² 9350.41
*About 1/2 kg

Openable glazed shutter with 38 x 75mm Sal wood frame & 4mm thick glass supply
Analyzed for: 2.23 m² (Size 1.829m x 1.22m) Norms S.N. 10-4
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 9 no. 740.00 6660.00
Labours
Unskilled 0.9 no. 525.00 472.50
Sal Wood 0.049 m³ 176506.00 8648.79
4mm Glass 1.085 m² 723.45 784.94
75mm Hinges 8 no. 16.95 135.60
Materials
100mm Towerbolt 4 no. 45.20 180.80
Handles 2 no. 56.50 113.00
Screws* LS kg 50.00 50.00
Sub-Total 17045.63
Rate per m² 7643.78
*About 1/2 kg

Openable glazed shutter with 38 x 75mm Local Wood frame & 4mm thick glass supply
Analyzed for: 2.23 m² (Size 1.829m x 1.22m) Norms S.N. 10-4
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 9 no. 740.00 6660.00
Labours
Unskilled 0.9 no. 525.00 472.50
Local Wood 0.049 m³ 53558.00 2624.34
4mm Glass 1.085 m² 723.45 784.94
75mm Hinges 8 no. 16.95 135.60
Materials
100mm Towerbolt 4 no. 45.20 180.80
Handles 2 no. 56.50 113.00
Screws* LS kg 50.00 50.00
Sub-Total 11021.18
Rate per m² 4942.23
*About 1/2 kg

Openable glazed shutter with 38 x 75mm Sisaum Wood frame & 4mm thick glass supply
Analyzed for: 2.23 m² (Size 1.829m x 1.22m) Norms S.N. 10-4
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 9 no. 740.00 6660.00
Labours
Unskilled 0.9 no. 525.00 472.50
Sisaum Wood 0.049 m³ 130447.20 6391.91
4mm Glass 1.085 m² 723.45 784.94
75mm Hinges 8 no. 16.95 135.60
Materials
100mm Towerbolt 4 no. 45.20 180.80
Handles 2 no. 56.50 113.00
Screws* LS kg 50.00 50.00
Sub-Total 14788.75
Rate per m² 6631.73
*About 1/2 kg

Flush shutter 38mm thick Sal wood frame with 4mm thick commercial plywood on both side of shutter
Analyzed for: 2.245 m² (Size 1.092m x 2.058m) Norms S.N. 10-7
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 7 no. 740.00 5180.00
Labours
Unskilled 0.7 no. 525.00 367.50
Sal Wood 0.0346 m³ 176506.00 6107.11
4mm Commercial Plywood 4.65 m² 367.25 1707.71
100mm Hinges 3 no. 33.90 101.70
Materials
150mm Towerbolt 2 no. 67.80 135.60
Mortise Lock 1 no. 1548.10 1548.10
Screw Nails LS kg 50.00 50.00
Sub-Total 15197.72
Rate per m² 6769.59
*About 1/2 kg
Flush shutter 38mm thick Sal wood frame with 4mm thick commercial plywood on boyh side and plane sheet on one side
of shutter
Analyzed for: 2.245 m² (Size 1.092m x 2.058m) Norms S.N. 10-7
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 7 no. 740.00 5180.00
Labours
Unskilled 0.7 no. 525.00 367.50
Sal Wood 0.0346 m³ 176506.00 6107.11
4mm Commercial Plywood 4.65 m² 367.25 1707.71
26 gauge colouredPlane
2.245 m² 417.47 937.22 including one side plane sheet
Sheet
Materials
100mm Hinges 3 no. 33.90 101.70
150mm Towerbolt 2 no. 67.80 135.60
Mortise Lock 1 no. 1548.10 1548.10
Materials

Screw Nails LS kg 50.00 50.00


Sub-Total 16134.94
Rate per m² 7187.06
*About 1/2 kg

Flush shutter 38mm thick Sisaum wood frame with 4mm thick commercial plywood on both side of shutter
Analyzed for: 2.245 m² (Size 1.092m x 2.058m) Norms S.N. 10-7
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 7 no. 740.00 5180.00
Labours
Unskilled 0.7 no. 525.00 367.50
Sisaum Wood 0.0346 m³ 130447.20 4513.47
4mm Commercial Plywood 4.65 m² 367.25 1707.71
100mm Hinges 3 no. 33.90 101.70
Materials
150mm Towerbolt 2 no. 67.80 135.60
Mortise Lock 1 no. 1548.10 1548.10
Screw Nails LS kg 50.00 50.00
Sub-Total 13604.08
Rate per m² 6059.72
*About 1/2 kg

Flush shutter 38mm thick Sisaum wood frame with 4mm thick commercial plywood on both side of shutter
Analyzed for: 2.245 m² (Size 1.092m x 2.058m) Norms S.N. 10-7
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 7 no. 740.00 5180.00
Labours
Unskilled 0.7 no. 525.00 367.50
Sisaum Wood 0.0346 m³ 130447.20 4513.47
4mm Commercial Plywood 4.65 m² 367.25 1707.71
26 gauge colouredPlane
2.245 m² 417.47 937.22 including one side plane sheet
Sheet
Materials
100mm Hinges 3 no. 33.90 101.70
150mm Towerbolt 2 no. 67.80 135.60
Mortise Lock 1 no. 1548.10 1548.10
Screw Nails LS kg 50.00 50.00
Sub-Total 14541.30
Rate per m² 6477.19
*About 1/2 kg

Flush shutter 38mm thick Local wood frame with 4mm thick commercial plywood on both side of shutter
Analyzed for: 2.245 m² (Size 1.092m x 2.058m) Norms S.N. 10-7
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 7 no. 740.00 5180.00
Labours
Unskilled 0.7 no. 525.00 367.50
Local Wood 0.0346 m³ 53558.00 1853.11
4mm Commercial Plywood 4.65 m² 367.25 1707.71
100mm Hinges 3 no. 33.90 101.70
Materials
150mm Towerbolt 2 no. 67.80 135.60
Mortise Lock 1 no. 1548.10 1548.10
Screw Nails LS kg 50.00 50.00
Sub-Total 10943.72
Rate per m² 4874.71
*About 1/2 kg

Flush shutter 38mm thick Local wood frame with 4mm thick commercial plywood on both side of shutter
Analyzed for: 2.245 m² (Size 1.092m x 2.058m) Norms S.N. 10-7
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 7 no. 740.00 5180.00
Labours
Labours
Unskilled 0.7 no. 525.00 367.50
Local Wood 0.0346 m³ 53558.00 1853.11
4mm Commercial Plywood 4.65 m² 367.25 1707.71
26 gauge colouredPlane
2.245 m² 417.47 937.22 including one side plane sheet
Sheet
Materials
100mm Hinges 3 no. 33.90 101.70
150mm Towerbolt 2 no. 67.80 135.60
Mortise Lock 1 no. 1548.10 1548.10
Screw Nails LS kg 50.00 50.00
Sub-Total 11880.94
Rate per m² 5292.18
*About 1/2 kg

Sal wood shutter with38 mm thick wooden frame including 26gauge coloured plane sheet both side
Size of shutter(1.092*2.058=2.245 sq.m)
Analyzed for: Norms S.N. 10-9
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 7 no. 740.00 5180.00
Labours
Unskilled 0.7 no. 525.00 367.50
Sal Wood 0.0346 m² 176506.00 6107.11
26gauge coloured plane
4.65 m² 491.72 2286.50
sheet
100mm Hinges 3.0 no. 33.90 101.70
Materials
150mm Towerbolt 2 no. 67.80 135.60
Mortise Lock 1 no. 1548.10 1548.10
Handle 1 no. 56.50 56.50
Screw LS 50.00 50.00
Sub-Total 15833.01
For 1 m² 7052.57
*About 1/2 kg

Sisaum wood shutter with38 mm thick wooden frame including 26gauge coloured plane sheet both side
Size of shutter(1.092*2.058=2.245 sq.m)
Analyzed for: Norms S.N. 10-9
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 7 no. 740.00 5180.00
Labours
Unskilled 0.7 no. 525.00 367.50
Sisaum Wood 0.0346 m² 130447.20 4513.47
26gauge plane sheet 4.65 m² 491.72 2286.50
100mm Hinges 3.0 no. 33.90 101.70
Materials 150mm Towerbolt 2 no. 67.80 135.60
Mortise Lock 1 no. 1548.10 1548.10
Handle 1 no. 56.50 56.50
Screw LS 50.00 50.00
Sub-Total 14239.37
For 1 m² 6342.70
*About 1/2 kg

Local wood shutter with38 mm thick wooden frame including 26gauge coloured plane sheet both side
Size of shutter(1.092*2.058=2.245 sq.m)
Analyzed for: Norms S.N. 10-9
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 7 no. 740.00 5180.00
Labours
Unskilled 0.7 no. 525.00 367.50
Local Wood 0.0346 m² 53558.00 1853.11
26gauge plane sheet 4.65 m² 491.72 2286.50
100mm Hinges 3.0 no. 33.90 101.70
Materials 150mm Towerbolt 2 no. 67.80 135.60
Mortise Lock 1 no. 1548.10 1548.10
Handle 1 no. 56.50 56.50
Screw LS 50.00 50.00
Sub-Total 11579.01
For 1 m² 5157.69
*About 1/2 kg

Sal wood shutter with38 mm thick wooden frame including 24gauge G.I.mosquito proof net wire mesh
Size of shutter(1.092*2.058=2.245 sq.m)
Analyzed for: Norms S.N. 10-10
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 5 no. 740.00 3700.00
Labours
Unskilled 0.5 no. 525.00 262.50
Sal Wood 0.026 m² 176506.00 4589.16
24 gauge G.I.mosquito
2.13 m² 282.50 601.73
proof net wire mesh
100mm Hinges 3.0 no. 33.90 101.70
Materials
150mm Towerbolt 2 no. 67.80 135.60
spring 1 no. 254.25 254.25
Handle 2 56.50 113.00
Screw LS 50.00 50.00
Sub-Total 9807.94
For 1 m² 4368.79

Sal wood shutter with38 mm thick wooden frame including 24gauge G.I.mosquito proof net wire mesh with expended metal net
Size of shutter(1.092*2.058=2.245 sq.m)
Analyzed for: Norms S.N. 10-10
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 5 no. 740.00 3700.00
Labours
Unskilled 0.5 no. 525.00 262.50
Sal Wood 0.026 m² 176506.00 4589.16
24 gauge G.I.mosquito
2.13 m² 282.50 601.73
proof net wire mesh
Expanded Metal Net 2.13 m² 220.35 469.35 Barphi Jali
Materials 100mm Hinges 3.0 no. 33.90 101.70
150mm Towerbolt 2 no. 67.80 135.60
spring 1 no. 254.25 254.25
Handle 2 56.50 113.00
Screw LS 50.00 50.00
Sub-Total 10277.29
For 1 m² 4577.86
Sisaum wood shutter with38 mm thick wooden frame including 24gauge G.I.mosquito proof net wire mesh
Size of shutter(1.092*2.058=2.245 sq.m)
Analyzed for: Norms S.N. 10-10
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 5 no. 740.00 3700.00
Labours
Unskilled 0.5 no. 525.00 262.50
SisaumWood 0.026 m² 130447.20 3391.63

Materials
24 gauge G.I.mosquito
2.13 m² 282.50 601.73
proof net wire mesh
100mm Hinges 3.0 no. 33.90 101.70
Materials
150mm Towerbolt 2 no. 67.80 135.60
spring 1 no. 254.25 254.25
Handle 2 56.50 113.00
Screw LS 50.00 50.00
Sub-Total 8610.41
For 1 m² 3835.37
Local wood shutter with38 mm thick wooden frame including 24gauge G.I.mosquito proof net wire mesh
Size of shutter(1.092*2.058=2.245 sq.m)
Analyzed for: Norms S.N. 10-10
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 5 no. 740.00 3700.00
Labours
Unskilled 0.5 no. 525.00 262.50
Local Wood 0.026 m² 53558.00 1392.51
24 gauge G.I.mosquito
2.13 m² 282.50 601.73
proof net wire mesh
100mm Hinges 3.0 no. 33.90 101.70
Materials
150mm Towerbolt 2 no. 67.80 135.60
spring 1 no. 254.25 254.25
Handle 2 56.50 113.00
Screw LS 50.00 50.00
Sub-Total 6611.29
For 1 m² 2944.90

Fixed glazed shutter with 4mm thick glass and wooden listy
Analyzed for: 1 m² Norms S.N. 10-11-Kha
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 0.06 no. 740.00 44.40
Labours
Unskilled 0.006 no. 525.00 3.15
4mm Glass 1 m² 723.45 723.45
Materials Wooden Listy 1/2'' 4.05 r.m. 18.84 76.30
Nails* LS kg 50.00 50.00
Sub-Total 897.30
*About 1/2 kg

Fixed shutter with 4mm thick Commercial ply wood and wooden listy
Analyzed for: 1 m² Norms S.N. 10-12
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 0.06 no. 740.00 44.40
Labours
Unskilled 0.006 no. 525.00 3.15
4mm Plywood 1.05 m² 367.25 385.61
Materials Wooden Listy 1/2'' 4.05 r.m. 18.84 76.30
Screw LS kg 50.00 50.00
Sub-Total 559.46
*About 1/2 kg

Making wooden partition wall from frame of size 0.61m*0.915m using wood of size 38mm*75mm and attaching 4mm thick
commercial plywood
Analyzed for: on both
Partition wall sides
size:-including covering of Sq.m.
9.75m*3.65m=35.68 the joints by timber beats. Norms S.N. 10-14-a
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 23 no. 740.00 17020.00
Labours
Unskilled 2.3 no. 525.00 1207.50
Wood 0.35 Cu.m 53558.00 18745.30
4mm Plywood 75 m² 367.25 27543.75
Materials
Wooden Listy 1/2'' 4.05 r.m. 18.84 76.30
Screw LS kg 100.00 100.00
Sub-Total 64692.85
For 1 m² 1817.85

Flush ceiling work by using 50mm*75mm salwood frame of size 0.60m*0.90m including 4mm thick plywood.
Analyzed for:(size of ceiling 9.75m*3.65m=35.68) m² Norms S.N. 10-16-ka
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 23 no. 740.00 17020.00
Labours
Unskilled 2.3 no. 525.00 1207.50
sal Wood 0.45 Cu.m 176506.00 79427.70
4mm Plywood 37.5 m² 367.25 13771.88
Materials
Wooden Listy 1/2'' LS r.m. 18.84 50.00
Nails LS kg 50.00
Sub-Total 111527.08
For 1 m² 3125.76

Wood work for beam,column etc.using local wood


Analyzed for: 1 m³ Norms S.N. 10-17
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 17.65 no. 740.00 13061.00
Labours
Unskilled 1.76 no. 525.00 924.00
Local Wood 1.05 m³ 53558.00 56235.90
Materials
Nails LS kg 100.00 100.00
Sub-Total 70320.90

Wood work for truss using local wood


Analyzed for: 1 m³ Norms S.N. 10-18
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 17.65 no. 740.00 13061.00
Labours
Unskilled 26 no. 525.00 13650.00
Local Wood 1.05 m³ 53558.00 56235.90
Iron strap LS No 160.00 160.00
Materials
Nut Bolts LS kg 100.00 100.00
Nails LS kg 100.00 100.00
Sub-Total 83306.90

25mm thick local wood work for eaves board


Analyzed for: 10 m² Norms S.N. 10-19
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1.43 no. 740.00 1058.20
Labours
Unskilled 0.143 no. 525.00 75.08
Salla Wood 0.275 m³ 53558.00 14728.45
Materials
Nails LS kg 50.00 50.00
Sub-Total 15911.73
For 1 m² 1591.17

12-20mm dia. Reinforcement bar fixing in window frame including drilling works ( Analysis for 1MT )
Analyzed for: 1 MT Norms S.N. 10-21
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 20 no. 740.00 14800.00
Labours
Labours
Unskilled 20 no. 525.00 10500.00
Materials Ms rod 1.05 MT 82430.00 86551.50
Sub-Total 111851.50
For 1 kg 111.85

Flooring works
25mm thick 1:2:4 cement concrete flooring
Analyzed for: 10 m² Norms S.N. 11-1-Ka
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1.1 no. 740.00 814.00
Labours
Unskilled 1.5 no. 525.00 787.50
Cement 0.09 MT 13334.00 1200.06
Materials Sand 0.12 m³ 1600.00 192.00
12mm Aggregate 0.23 m³ 1935.00 445.05
Sub-Total 3438.61
For 1 m² 343.86

38mm thick 1:2:4 cement concrete flooring


Analyzed for: 10 m² Norms S.N. 11-1-Kha
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1.25 no. 740.00 925.00
Labours
Unskilled 2 no. 525.00 1050.00
Cement 0.13 MT 13334.00 1733.42
Materials Sand 0.18 m³ 1600.00 288.00
12mm Aggregate 0.36 m³ 1935.00 696.60
Sub-Total 4693.02
For 1 m² 469.30

50mm thick 1:2:4 cement concrete flooring


Analyzed for: 10 m² Norms S.N. 11-1-Ga
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1.25 no. 740.00 925.00
Labours
Unskilled 2.5 no. 525.00 1312.50
Cement 0.17 MT 13334.00 2266.78
Materials Sand 0.23 m³ 1600.00 368.00
12mm Aggregate 0.46 m³ 1935.00 890.10
Sub-Total 5762.38
For 1 m² 576.24

75mm thick 1:2:4 cement concrete flooring


Analyzed for: 10 m² Norms S.N. 11-1-Gha
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1.25 no. 740.00 925.00
Labours
Unskilled 3 no. 525.00 1575.00
Cement 0.26 MT 13334.00 3466.84
Materials Sand 0.34 m³ 1600.00 544.00
20mm Aggregate 0.68 m³ 1935.00 1315.80
Sub-Total 7826.64
For 1 m² 782.66

25mm thick mosaic flooring with 20mm thick p.c.c 1:2:4 base coarse sand and 5mm thick marble chips white cement (1:1)
surface coarse including rubbing and polishing
Analyzed for:-10Sq.m. Norms S.N.11-2
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 2.50 no. 740.00 1850.00
Labours
Unskilled 16.00 no. 525.00 8400.00
Cement 0.065 M.T. 13334.00 866.71
Sand 0.088 cu.m. 1600.00 140.80
12.5mm agg. 0.176 cu.m. 1935.00 340.56
White cement 0.061 M.T. 26837.50 1637.09
3mm marble chips 0.061 cu.m. 0.00 0.00
Oxalic acid power 0.365 kg. 175.15 63.93
waxpolish 0.118 kg. 587.60 69.34
Tarpen 0.538 lit. 203.40 109.43
Carbon stone Approx. no. 300.00
Sub-Total 13777.86
For 1 Sq.m 1377.79
25mm thick mosaic flooring with 20mm thick cement plaster 1:2 base coarse sand and 6mm thick marble chips white
cement (1:1) surface coarse including rubbing and polishing
Analyzed for:-10Sq.m. Norms S.N.11-3
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 3.50 no. 740.00 2590.00
Labours
Unskilled 36.00 no. 525.00 18900.00
Cement 0.121 M.T. 13334.00 1613.41
Sand 0.165 cu.m. 1600.00 264.00
White cement 0.069 M.T. 25848.75 1783.56
3mm marble chips 0.047 cu.m. 56.50 2.66
Oxalic acid power 0.340 kg. 175.15 59.55
waxpolish 0.110 kg. 587.60 64.64
Tarpen 0.500 lit. 203.40 101.70
Carbon stone Approx. no. 300.00
Sub-Total 25679.52
For 1 Sq.m 2567.95
20mm thick mosaic flooring with 12.5mm thick cement plaster 1:2 base coarse sand and 6mm thick marble chips white
cement (1:1) surface coarse including rubbing and polishing
Analyzed for:-10Sq.m. Norms S.N.11-4
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 3.50 no. 740.00 2590.00
Labours
Unskilled 36.00 no. 525.00 18900.00
Cement 0.089 M.T. 13334.00 1186.73
Sand 0.122 cu.m. 1600.00 195.20
White cement 0.089 M.T. 21893.75 1948.54
3mm marble chips 0.061 cu.m. 113.00 6.89
Oxalic acid power 0.370 kg. 175.15 64.81
waxpolish 0.118 kg. 587.60 69.34
Tarpen 0.538 lit. 203.40 109.43
Carbon stone Approx. no. 300.00
Sub-Total 25370.94
For 1 Sq.m 2537.09
20mm thick terrazo tiles flooring on 20mm thick 1:4 cement sand mortar including rubbing and polishing .
Analyzed for:-10Sq.m. Norms S.N.11-5
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 2.00 no. 740.00 1480.00
Labours
Unskilled 12.60 no. 525.00 6615.00
20mm T- tiles 11.00 Sq.m 1412.50 15537.50
Cement 0.081 M.T. 13334.00 1080.05
Sand 0.220 cu.m. 1600.00 352.00
Materials
Materials Oxalic acid power 0.370 kg. 175.15 64.81
waxpolish 0.118 kg. 587.60 69.34
Tarpen 0.538 lit. 203.40 109.43
Carbon stone Approx. no. 300.00
For no machine, add 13.5 md of
Machine Rub.machine 6.000 hr. 100.00 600.00 unskilled labour.
Sub-Total 26208.13
For 1 Sq.m 2620.81

25mm thick marble(200x200)mm flooring on 20mm thick 1:2 cement sand mortar including rubbing and polishing .
Analyzed for:-10Sq.m. (Norms S.N.11-6)combination
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 2.00 no. 740.00 1480.00
Labours
Unskilled 8.00 no. 525.00 4200.00
25mm marble 11.00 Sq.m 1457.70 16034.70
Cement 0.121 M.T. 13334.00 1613.41
Sand 0.165 cu.m. 1600.00 264.00
Materials Oxalic acid power 0.370 kg. 175.15 64.81
waxpolish 0.118 kg. 587.60 69.34
Tarpen 0.538 lit. 203.40 109.43
Carbon stone Approx. no. 300.00
Sub-Total 24135.69
For 1 Sq.m 2413.57
Glazed Ceramic Tile of approved size and colour with 1:4 cement sand mortar
Analyzed for: 10 m² Norms S.N. 11-7
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 13.00 no. 740.00 9620.00
Labours
Unskilled 4.5 no. 525.00 2362.50
Glazed Ceramic Tile 11 m² 1412.50 15537.50
Cement 0.056 MT 13334.00 746.70
Materials
Sand 0.152 m³ 1600.00 243.20
White Cement 3.228 kg 26.84 86.63
Sub-Total 28596.53
For 1 m² 2859.65

Flat brick soling in 1:2 cement sand mortar use for jointing.
Analyzed for: 10 m² Norms S.N. 11-12
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 2.25 no. 740.00 1665.00
Labours
Unskilled 3.25 no. 525.00 1706.25
Bricks 430 no. 14.69 6316.70
Materials Cement 0.078 MT 13334.00 1040.05
Sand 0.229 m³ 1600.00 366.40
Sub-Total 11094.40
For 1 m² 1109.44

Flat brick soling


Analyzed for: 10 m² Norms S.N. 11-15-Ka
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 0.5 no. 740.00 370.00
Labours
Unskilled 1 no. 525.00 525.00
Bricks 420 no. 14.69 6169.80
Materials
Sand 0.71 m³ 1600.00 1136.00
Sub-Total 8200.80
For 1 m² 820.08

Dry brick on edge soling


Analyzed for: 10 m² Norms S.N. 11-15-Kha
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1 no. 740.00 740.00
Labours
Unskilled 3.25 no. 525.00 1706.25
Bricks 750 no. 14.69 11017.50
Materials
Sand 0.71 m³ 1600.00 1136.00
Sub-Total 14599.75
For 1 m² 1459.98
Dry stone soling
Analyzed for: 1 m³ Norms S.N. 11-16
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1 no. 740.00 740.00
Labours
Unskilled 3.5 no. 525.00 1837.50
Stone 1.1 m³ 1650.00 1815.00
Materials
Sand 0.71 m³ 1600.00 1136.00
Sub-Total 5528.50

125mm thick on edge soling of bricks including sand filling and flush pointing on the top surface of the joint by 1:3 cement
sand mortar.
Analyzed for: 10 Sq.m. Norms S.N. 11-17
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 2 no. 740.00 1480.00
Labours
Unskilled 4 no. 525.00 2100.00
Cement 0.02 MT 13334.00 266.68
Materials Brick 750 no. 14.69 11017.50
Sand 0.1 m³ 1600.00 160.00
Sub-Total 15024.18
For 1 m² 1502.42

1:1 Cement sand mortar pointing on joints of stone pavement works(stone size is 460mm*460mm).
Analyzed for: 10 m² Norms S.N. 11-18
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 0.5 no. 740.00 370.00
Labours
Unskilled 0.5 no. 525.00 262.50
Cement 4.2 Kg. 13.33 56.00
Materials
Sand 0.003 m³ 1600.00 4.80
Sub-Total 693.30
For 1 m² 69.33

Sand Filling Work including water sprinkling and ramming all complete
Analyzed for: 10 m³ Norms S.N. 11-19 Ka
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 6.5 no. 740.00 4810.00
Labours
Unskilled 0 no. 525.00 0.00
Cement 0 Kg. 13.33 0.00
Materials
Sand 11 m³ 1600.00 17600.00
Sub-Total 22410.00
For 1 m³ 2241.00
Brick Blast Filling Work including all complete
Analyzed for: 10 m³ Norms S.N. 11-19 Kha
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 10 no. 740.00 7400.00
Labours
Unskilled 0 no. 525.00 0.00
Cement 0 Kg. 13.33 0.00
Materials
Brick blast 11 m³ 1600.00 17600.00
Sub-Total 25000.00
For 1 m³ 2500.00
3mm thick cement punning
Analyzed for: 10 m² Norms S.N. 11-20
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1 no. 740.00 740.00
Labours
Unskilled 1 no. 525.00 525.00
Materials Cement 53.2 kg 13.33 709.37
Sub-Total 1974.37
For 1 m² 197.44

25mm thick planking work using 50mm*75mm wooden frame @600mm*600mm size
Analyzed for: 10 m² Norms S.N. 11-21
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 6.5 no. 740.00 4810.00
Labours
Unskilled 0.65 no. 525.00 341.25
wood 0.421 m³ 53558.00 22547.92
Materials
Nail LS 100.00 100.00
Sub-Total 27799.17
For 1 m² 2779.92
Plastering Work
12.5mm thick 1:2 cement sand plaster wall/floor
Analyzed for: 100 m² Norms S.N. 12-1-Ka
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 12 no. 740.00 8880.00
Labours
Unskilled 16 no. 525.00 8400.00
Cement 0.9 MT 13334.00 12000.60
Materials
Sand 1.22 m³ 1600.00 1952.00
Sub-Total 31232.60
For 1 m² 312.33

12.5mm thick 1:3 cement sand plaster wall/floor


Analyzed for: 100 m² Norms S.N. 12-1-Kha
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 12 no. 740.00 8880.00
Labours
Unskilled 16 no. 525.00 8400.00
Cement 0.625 MT 13334.00 8333.75
Materials
Sand 1.28 m³ 1600.00 2048.00
Sub-Total 27661.75
For 1 m² 276.62

12.5mm thick 1:4 cement sand plaster wall/floor


Analyzed for: 100 m² Norms S.N. 12-1-Ga
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 12 no. 740.00 8880.00
Labours
Unskilled 16 no. 525.00 8400.00
Cement 0.538 MT 13334.00 7173.69
Materials
Sand 1.46 m³ 1600.00 2336.00
Sub-Total 26789.69
For 1 m² 267.90

12.5mm thick 1:6 cement sand plaster wall/floor


Analyzed for: 100 m² Norms S.N. 12-1-Gha
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 12 no. 740.00 8880.00
Labours
Unskilled 16 no. 525.00 8400.00
Cement 0.382 MT 13334.00 5093.59
Materials
Sand 1.57 m³ 1600.00 2512.00
Sub-Total 24885.59
For 1 m² 248.86

12.5mm thick 1:2 cement sand plaster on ceiling


Analyzed for: 100 m² Norms S.N. 12-1-Ka
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 15 no. 740.00 11100.00 Add25%more labour for ceiling
Labours plaster works.
Unskilled 20 no. 525.00 10500.00
Cement 0.9 MT 13334.00 12000.60
Materials
Sand 1.22 m³ 1600.00 1952.00
Sub-Total 35552.60
For 1 m² 355.53

12.5mm thick 1:3 cement sand plaster on ceiling


Analyzed for: 100 m² Norms S.N. 12-1-Kha
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 15 no. 740.00 11100.00 Add25%more labour for ceiling
Labours plaster works.
Unskilled 20 no. 525.00 10500.00
Cement 0.625 MT 13334.00 8333.75
Materials
Sand 1.28 m³ 1600.00 2048.00
Sub-Total 31981.75
For 1 m² 319.82

12.5mm thick 1:4 cement sand plaster on ceiling


Analyzed for: 100 m² Norms S.N. 12-1-Ga
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 15 no. 740.00 11100.00 Add25%more labour for ceiling
Labours plaster works.
Unskilled 20 no. 525.00 10500.00
Cement 0.538 MT 13334.00 7173.69
Materials
Sand 1.46 m³ 1600.00 2336.00
Sub-Total 31109.69
For 1 m² 311.10

12.5mm thick 1:6 cement sand plaster on ceiling


Analyzed for: 100 m² Norms S.N. 12-1-Gha
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 15 no. 740.00 11100.00 Add25%more labour for ceiling
Labours plaster works.
Unskilled 20 no. 525.00 10500.00
Cement 0.382 MT 13334.00 5093.59
Materials
Sand 1.57 m³ 1600.00 2512.00
Sub-Total 29205.59
For 1 m² 292.06
20mm thick 1:3 cement sand plaster on wall/floor
Analyzed for: 100 m² Norms S.N. 12-4-Ka
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 14 no. 740.00 10360.00
Labours
Unskilled 19 no. 525.00 9975.00
Cement 0.96 MT 13334.00 12800.64
Materials
Sand 1.95 m³ 1600.00 3120.00
Sub-Total 36255.64
For 1 m² 362.56

20mm thick 1:4 cement sand plaster on wall/floor


Analyzed for: 100 m² Norms S.N. 12-4-Kha
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 14 no. 740.00 10360.00
Labours
Unskilled 19 no. 525.00 9975.00
Cement 0.81 MT 13334.00 10800.54
Materials
Sand 2.2 m³ 1600.00 3520.00
Sub-Total 34655.54
For 1 m² 346.56

20mm thick 1:6 cement sand plaster on wall/floor


Analyzed for: 100 m² Norms S.N. 12-4-Ga
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 14 no. 740.00 10360.00
Labours
Unskilled 19 no. 525.00 9975.00
Cement 0.57 MT 13334.00 7600.38
Materials
Sand 2.35 m³ 1600.00 3760.00
Sub-Total 31695.38
For 1 m² 316.95

20mm thick 1:3 cement sand plaster on ceiling


Analyzed for: 100 m² Norms S.N. 12-4-Ka
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 17.5 no. 740.00 12950.00 Add25%more labour for ceiling
Labours plaster works.
Unskilled 23.75 no. 525.00 12468.75
Cement 0.96 MT 13334.00 12800.64
Materials
Sand 1.95 m³ 1600.00 3120.00
Sub-Total 41339.39
For 1 m² 413.39

20mm thick 1:4 cement sand plaster on ceiling


Analyzed for: 100 m² Norms S.N. 12-4-Kha
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 17.5 no. 740.00 12950.00 Add25%more labour for ceiling
Labours plaster works.
Unskilled 23.75 no. 525.00 12468.75
Cement 0.81 MT 13334.00 10800.54
Materials
Sand 2.2 m³ 1600.00 3520.00
Sub-Total 39739.29
For 1 m² 397.39

20mm thick 1:6 cement sand plaster on ceiling


Analyzed for: 100 m² Norms S.N. 12-4-Ga
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 17.5 no. 740.00 12950.00 Add25%more labour for ceiling
Labours plaster works.
Unskilled 23.75 no. 525.00 12468.75
Cement 0.57 MT 13334.00 7600.38
Materials
Sand 2.35 m³ 1600.00 3760.00
Sub-Total 36779.13
For 1 m² 367.79

Painting works
One coat white washing on new surface on Wall
Analyzed for: 100 m² Norms S.N. 13-1-Ka
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 0.8 no. 740.00 592.00
Labours
Unskilled 0.7 no. 525.00 367.50
White Lime 12 kg 26.84 322.08
Materials
Gum 0.48 kg 310.75 149.16
Sub-Total 1430.74
For 1 m² 14.31

Two coat white washing on new surface Wall


Analyzed for: 100 m² Norms S.N. 13-1-Kha
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1.5 no. 740.00 1110.00
Labours
Unskilled 1.1 no. 525.00 577.50
White Lime 22 kg 26.84 590.48
Materials
Gum 0.88 kg 310.75 273.46
Sub-Total 2551.44
For 1 m² 25.51

One coat white washing on new surface on ceiling


Analyzed for: 100 m² Norms S.N. 13-1-Ka
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1.00 no. 740.00 740.00 Add25%more labour for ceiling
Labours plaster works.
Unskilled 0.875 no. 525.00 459.38
White Lime 12 kg 26.84 322.08
Materials
Gum 0.48 kg 310.75 149.16
Sub-Total 1670.62
For 1 m² 16.71

Two coat white washing on new surface on ceiling


Analyzed for: 100 m² Norms S.N. 13-1-Kha
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1.875 no. 740.00 1387.50 Add25%more labour for ceiling
Labours plaster works.
Unskilled 1.375 no. 525.00 721.88
White Lime 22 kg 26.84 590.48
Materials
Gum 0.88 kg 310.75 273.46
Sub-Total 2973.32
For 1 m² 29.73

Applying distemper paint


A. Primer
Analyzed for: 100 m² Norms S.N. 13-3-Ka
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 2 no. 740.00 1480.00
Labours
Labours
Unskilled 2 no. 525.00 1050.00
Materials Primer 8 litres 395.50 3164.00
Sub-Total 5694.00
For 1 m² 56.94

B. One coat
Analyzed for: 100 m² Norms S.N. 13-3-Kha
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 2 no. 740.00 1480.00
Labours
Unskilled 2 no. 525.00 1050.00
Materials Dry Distemper Powder 6.5 kg 310.75 2019.88
Sub-Total 4549.88
For 1 m² 45.50
C. Second coat and every other additional coats
Analyzed for: 100 m² Norms S.N. 13-3-Ga
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1.8 no. 740.00 1332.00
Labours
Unskilled 1.8 no. 525.00 945.00
Materials Dry Distemper Powder 5 kg 310.75 1553.75
Sub-Total 3830.75
For 1 m² 38.31
For one coat on primer 102.44
For two coat on primer 140.75

Applying one coat water proof cement paint


Analyzed for: 100 m² Norms S.N. 13-4-Ka
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1.7 no. 740.00 1258.00
Labours
Unskilled 1.7 no. 525.00 892.50
Materials Water Proof Cement Paint 30 kg 25.99 779.70
Sub-Total 2930.20
For 1 m² 29.30

Applying two coat water proof cement paint


Analyzed for: 100 m² Norms S.N. 13-4-Kha
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 5 no. 740.00 3700.00
Labours
Unskilled 5 no. 525.00 2625.00
Materials Water Proof Cement Paint 48.5 kg 25.99 1260.52
Sub-Total 7585.52
For 1 m² 75.86

Applying readymade enamel paint or plastic emulsion paint


A. Primer Coat
Analyzed for: 100 m² Norms S.N. 13-5-Ka
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 3 no. 740.00 2220.00
Labours
Unskilled 3 no. 525.00 1575.00
Materials Primer 8.1 lit 395.50 3203.55
Sub-Total 6998.55
For 1 m² 69.99

B. First Coat
Analyzed for: 100 m² Norms S.N. 13-5-Kha
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 5 no. 740.00 3700.00
Labours
Unskilled 2 no. 525.00 1050.00
Materials Readymade Enamel Paint 9 lit 875.75 7881.75
Sub-Total 12631.75
For 1 m² 126.32

C. Second Coat
Analyzed for: 100 m² Norms S.N. 13-5-Ga
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 4 no. 740.00 2960.00
Labours
Unskilled 3 no. 525.00 1575.00
Materials Readymade Enamel Paint 7 lit 875.75 6130.25
Sub-Total 10665.25
For 1 m² 106.65
For one coat enamel paint on primer 196.31
For two coat enamel paint on primer 302.96

Applying two coat readymade aluminium paint on one coat primer


Analyzed for: 100 m² Norms S.N. 13-6
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 10.75 no. 740.00 7955.00
Labours
Unskilled 10.75 no. 525.00 5643.75
Primer 8.1 Liter 395.50 3203.55
Materials Aluminium Paint 10.76 Liter 724.33 7793.79
Sand Paper 4 no. 5.65 22.60
Sub-Total 24618.69
For 1 m² 246.19

Applying varnish
A. First coat
Analyzed for: 100 m² Norms S.N. 13-9-Ka
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 3 no. 740.00 2220.00
Labours
Unskilled 2 no. 525.00 1050.00
Materials Varnish 6 litres 440.70 2644.20
Sub-Total 5914.20
For 1 m² 59.14
*Rate of Local Varnish

B. Second coat and every other additional coats


Analyzed for: 100 m² Norms S.N. 13-9-Kha
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 3 no. 740.00 2220.00
Labours
Unskilled 2 no. 525.00 1050.00
Materials Varnish* 5 litres 440.70 2203.50
Sub-Total 5473.50
For 1 m² 54.74
For one coat 59.14
For two coats 113.88
For three coats 168.62
*Rate of Local Varnish
Applying one coat bitumen paint
Analyzed for: 100 m² Norms S.N. 13-10-Ka
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1.5 no. 740.00 1110.00
Labours
Unskilled 1 no. 525.00 525.00
Materials Bitumen Paint 7 litres 316.40 2214.80
Sub-Total 3849.80
For 1 m² 38.50

Applying two coat bitumen paint


Analyzed for: 100 m² Norms S.N. 13-10-Kha
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 2.5 no. 740.00 1850.00
Labours
Unskilled 2 no. 525.00 1050.00
Materials Bitumen Paint 12 litres 316.40 3796.80
Sub-Total 6696.80
For 1 m² 66.97
Applying three coat Chapra(resin) polish application work
Analyzed for: 100 m² Norms S.N. 13-11
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 10 no. 740.00 7400.00
Labours
Unskilled 5 no. 525.00 2625.00
Chapra 2 Kg. 2316.50 4633.00
Materials
Sprit 10 Lt. 90.40 904.00
Sub-Total 15562.00
For 1 m² 155.62

Applying cement paint (snowcem) on plastered surface


A. First coat
Analyzed for: 100 m² Norms S.N. 13-12-Ka
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 3.5 no. 740.00 2590.00
Labours
Unskilled 3.5 no. 525.00 1837.50
Materials Snowcem Paint 30 kg 67.80 2034.00
Sub-Total 6461.50
For 1 m² 64.62

B. Second coat and every other additional coats


Analyzed for: 100 m² Norms S.N. 13-12-Kha
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 3 no. 740.00 2220.00
Labours
Unskilled 3 no. 525.00 1575.00
Materials Snowcem Paint 20 kg 67.80 1356.00
Sub-Total 5151.00
For 1 m² 51.51
For one coat 64.62
For two coats 116.13
For three coats 167.64

Pointing Works
Flush pointing works in 1:1 cement sand mortar on brick masonry
Analyzed for: 100 m² Norms S.N. 14-1-Ka
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 10.5 no. 740.00 7770.00
Labours
Unskilled 12 no. 525.00 6300.00
Cement 0.316 MT 13334.00 4213.54
Materials
Sand 0.22 m³ 1600.00 352.00
Sub-Total 18635.54
Grand-Total 18635.54
For 1 m² 186.36

Flush pointing works in 1:2 cement sand mortar on brick masonry


Analyzed for: 100 m² Norms S.N. 14-1-Kha
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 10.5 no. 740.00 7770.00
Labours
Unskilled 12 no. 525.00 6300.00
Cement 0.21 MT 13334.00 2800.14
Materials
Sand 0.29 m³ 1600.00 464.00
Sub-Total 17334.14
For 1 m² 173.34

Flush pointing works in 1:3 cement sand mortar on brick masonry


Analyzed for: 100 m² Norms S.N. 14-1-Ga
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 10.5 no. 740.00 7770.00
Labours
Unskilled 12 no. 525.00 6300.00
Cement 0.155 MT 13334.00 2066.77
Materials
Sand 0.32 m³ 1600.00 512.00
Sub-Total 16648.77
For 1 m² 166.49

Flush rulled pointing works in 1:1 cement sand mortar on random rubble masonry
Analyzed for: 100 m² Norms S.N. 14-2-Ka
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 10 no. 740.00 7400.00
Labours
Unskilled 14 no. 525.00 7350.00
Cement 0.612 MT 13334.00 8160.41
Materials
Sand 0.43 m³ 1600.00 688.00
Sub-Total 23598.41
For 1 m² 235.98

Flush rulled pointing works in 1:2 cement sand mortar on random rubble masonry
Analyzed for: 100 m² Norms S.N. 14-2-Kha
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 10 no. 740.00 7400.00
Labours
Unskilled 14 no. 525.00 7350.00
Cement 0.408 MT 13334.00 5440.27
Materials
Sand 0.57 m³ 1600.00 912.00
Sub-Total 21102.27
For 1 m² 211.02

Flush rulled pointing works in 1:3 cement sand mortar on random rubble masonry
Analyzed for: 100 m² Norms S.N. 14-2-Ga
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 10 no. 740.00 7400.00
Labours
Unskilled 14 no. 525.00 7350.00
Cement 0.306 MT 13334.00 4080.20
Materials
Sand 0.63 m³ 1600.00 1008.00
Sub-Total 19838.20
For 1 m² 198.38

1:3 cement sand mortar pointing works on flat stone pavement(stone size 450mm*450mm.
Analyzed for: 100 m² Norms S.N. 14-4
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 5 no. 740.00 3700.00
Labours
Unskilled 5 no. 525.00 2625.00
Cement 0.042 MT 13334.00 560.03
Materials
Sand 0.03 m³ 1600.00 48.00
Sub-Total 6933.03
For 1 m² 69.33

3mm flushing plaster in 1:1 cement sand mortar


Analyzed for: 100 m² Norms S.N. 14-6
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 10 no. 740.00 7400.00
Labours
Unskilled 10 no. 525.00 5250.00
Cement 0.336 MT 13334.00 4480.22
Materials
Sand 0.23 m³ 1600.00 368.00
Sub-Total 17498.22
For 1 m² 174.98

3mm thick flush plaster in cement


Analyzed for: 100 m² Norms S.N. 14-8
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 10 no. 740.00 7400.00
Labours
Unskilled 10 no. 525.00 5250.00
Materials Cement 0.518 MT 13334.00 6907.01
Sub-Total 19557.01
Grand-Total 19557.01
For 1 m² 195.57

Waterproofing Works
38mm thick Damp Proof Course(DPC) of cement concrete with all complete
P.C.C. for DPC (1:2:4)
Analyzed for: 10 m² Norms S.N.18-9
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1.00 no. 740.00 740.00
Labours
Unskilled 2.00 no. 525.00 1050.00
Cement 0.12 MT 13334.00 1600.08
Sand 0.17 m³ 1600.00 272.00
Water Proof Compound 2.88 Lit. 282.50 813.60
Materials
40mm Aggregate 0.00 m³ 1925.00 0.00
20mm Aggregate 0.00 m³ 1935.00 0.00
10mm Aggregate 0.34 m³ 1950.00 663.00
Sub-Total 5138.68
For 1 m² 513.87
25mm thick Damp Proof Course(DPC) of cement concrete with all complete
P.C.C. for DPC (1:2:4)
Analyzed for: 10 m² Norms S.N.18-8
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1.00 no. 740.00 740.00
Labours
Unskilled 1.25 no. 525.00 656.25
Cement 0.1125 MT 13334.00 1500.08
Sand 0.113 m³ 1600.00 180.80
Water Proof Compound 2.25 Lit. 282.50 635.63
Materials
40mm Aggregate 0.00 m³ 1925.00 0.00
20mm Aggregate 0.00 m³ 1935.00 0.00
10mm Aggregate 0.25 m³ 1950.00 487.50
Sub-Total 4200.26
For 1 m² 420.03
Dismantling & repair works
Dismantling work of stone masonry in mud mortar including disposal upto 10 m
Analyzed for: 1 m3 Norms S.N. 19-1
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 1.06 no. 700.00 742.00
Sub-Total 742.00
Grand-Total 742.00

Dismantling work of stone masonry in cement sand mortar including disposal upto 10 m
Analyzed for: 1 m3 Norms S.N. 19-2
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 2.12 no. 700.00 1484.00
Sub-Total 1484.00
Grand-Total 1484.00

Dismantling work of R.C.C./R.B.C. structure including disposal upto 10 m


Analyzed for: 1 m3 Norms S.N. 19-3
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 11.00 no. 700.00 7700.00
Sub-Total 7700.00
Grand-Total 7700.00

Dismantling work of P.C.C./R.B.C. structure including disposal upto 10 m


Analyzed for: 1 m3 Norms S.N. 19-4
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 4.00 no. 700.00 2800.00
Sub-Total 2800.00
Grand-Total 2800.00
Dismantling work of cement sand plaster including disposal upto 10 m
Analyzed for: 1 m2 Norms S.N. 19-5
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Labours Unskilled 0.108 no. 700.00 75.60
Sub-Total 75.60
Grand-Total 75.60
Iron/Metal and other Works
Making 3mm*20mm iron grill & fixing including cleaning by sand paper, applying aluminium paint.etc.complete.
Analyzed for:-10 Sq.m. Norms S.N.24-1-1
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 0.00 no. 740.00 0.00
Labours
Unskilled 0 no. 525.00 0.00
3mm*20mm grill& fitting Included wages also. 1 sq
Materials 10.0 Sq.m 1823.82 18238.20
including making m=13.45kg
Sub-Total 18238.20
For 1 Sq.m 1823.82

Making 4.5mm*20mm iron grill & fixing including cleaning by sand paper, applying aluminium paint.etc.complete.
Analyzed for:-10 Sq.m. Norms S.N.24-1-2
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 0.00 no. 740.00 0.00
Labours
Unskilled 0 no. 525.00 0.00
4.5mm*20mm grill& fitting Included wages also. 1
Materials 10.0 Sq.m 2302.49 23024.90
including making sq=16.98kg
Sub-Total 23024.90
For 1 sq.m 2302.49

Making iron rolling shutter gate & fixing including painting & wages complete.
Analyzed for:-10 Sq.m. Norms S.N.24-2
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 0.00 no. 740.00 0.00
Labours
Unskilled 0 no. 525.00 0.00
20 gaugeIron rolling
Materials 10.0 Sq.m 4049.92 40499.20 Take25.6kg/sq.m
shutter
Sub-Total 40499.20
For 1 sq.m 4049.92

Making iron gate & fixing including painting & wages complete.
Analyzed for:-10 Sq.m. Norms S.N.24-3
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 0.00 no. 740.00 0.00
Labours
Unskilled 0 no. 525.00 0.00
Iron gate-18 gauge MS
Materials sheet and 40mm equal 10.0 Sq.m 4255.58 42555.80 Take 26.90kg/sq.m
angle
Sub-Total 42555.80
For 1 sq.m 4255.58

Making Collabsiable iron gate & fixing including painting & wages complete.
Analyzed for:-10 Sq.m. Norms S.N.24-3
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 0.00 no. 740.00 0.00
Labours
Unskilled 0 no. 525.00 0.00
Collabsiable Iron gate-18
Materials 10.0 Sq.m 5695.20 56952.00 Take 36.0kg/sq.m
gauge MS sheet
Sub-Total 56952.00
For 1 sq.m 5695.20

Making tubular truss & fixing complete.


Analyzed for:-10 Sq.m. Norms S.N.24-5
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 0.00 no. 740.00 0.00
Labours
Unskilled 0 no. 525.00 0.00
Included wages also.11.75
Materials Making& fixing tubular truss 10.0 Sq.m 1792.46 17924.63
kg/Sq.m
Sub-Total 17924.63
For 1 sq.m 1792.46
G.I barbed wire fencing work
For:- 100 rm Norms S.N.24-6
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1.076 no. 955.00 1027.58
Labours
Unskilled 5.38 no. 700.00 3766.00
Barbed wire 110.0 m 14.21 1562.63 Take 1kg=10m
Materials
Nails Ls 100.00
Grand-Total 6456.21
For 1m 64.56

Barbed wire extention work


Barbed wire extention work including material providing with 5 line horizontal and 2 line diagonal@3 m c/c apart wooden
pole (size of pole 75mm*100mm*2100mm)
For:- 30 rm Norms S.N.24-7
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 1.00 no. 955.00 955.00
Labours
Unskilled 2 no. 700.00 1400.00
Wood 0.19 m3 53558.00 10176.02
Materials Barbed wire 250 m 14.21 3551.43 Take 1kg=10m
Nail/U-hooks 77 no. 3.96 304.92
Grand-Total 16387.37
For 1m 546.25
Miscellaneous Items
Fixing of 4mm thick commercial plywood by using nails
Analyzed for: 1 m² Norms S.N. 10-11-Kha
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 0.06 no. 740.00 44.40
Labours
Unskilled 0.006 no. 525.00 3.15
4mm commercial plywood 1.05 m² 367.25 385.61
Materials
Nails* LS kg 50.00 50.00
Sub-Total 483.16
*About 1/2 kg

Fixing of mosquitoproof net and expended metal net(Barfi Jali) using wooden listy
Analyzed for: 1 m² Norms S.N.:-Similar to 10-12
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 0.06 no. 740.00 44.40
Labours
Unskilled 0.006 no. 525.00 3.15
Mosquitoprrof net 1.05 m² 282.50 296.63
Expended metal net 1.05 m² 220.35 231.37
Materials
Wooden Listy 1/2'' 4.05 r.m. 18.84 76.30
Screw LS kg 50.00 50.00
Sub-Total 701.85

Fixing of mosquitoproof net using wooden listy


Analyzed for: 1 m² Norms S.N.:-Similar to 10-12
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 0.06 no. 740.00 44.40
Labours
Unskilled 0.006 no. 525.00 3.15
Mosquitoprrof net 1.05 m² 282.50 296.63
Expended metal net m² 220.35 0.00
Materials
Wooden Listy 1/2'' 4.05 r.m. 18.84 76.30
Screw LS kg 50.00 50.00
Sub-Total 470.48
Fixing of expended metal net(Barfi Jali) using wooden listy
Analyzed for: 1 m² Norms S.N.:-Similar to 10-12
Resources Level / Type Quantity Unit Rate per unit Amount Remarks
Skilled 0.06 no. 740.00 44.40
Labours
Unskilled 0.006 no. 525.00 3.15
Mosquitoprrof net m² 282.50 0.00
Expended metal net 1.05 m² 220.35 231.37
Materials
Wooden Listy 1/2'' 4.05 r.m. 18.84 76.30
Screw LS kg 50.00 50.00
Sub-Total 405.22
2370.00
71.1
Government of Nepal
Ministry Federal Affairs and of Local Development
Office of District Development Committee
DISTRICT TECHNICAL OFFICE
Chitwan

RATE OF HDPE PIPES


Rate of HDPE pipe per kg = 250.00
Weight per meter Rate per meter
Size of
S.N. pipe 2.5 6 10 2.5 kg/cm2 4 kg/cm2
(mm) kg/cm2 4 kg/cm kg/cm2 kg/cm2
2

Without VAT With VAT Without VAT With VAT


1 16 0.092
2 20 0.135
3 25 0.202
4 32 0.226 0.335
5 40 0.251 0.35 0.514 62.75 70.91
6 50 0.378 0.542 0.797 94.50 106.79
7 63 0.403 0.586 0.851 1.27 100.75 113.85 146.50 165.55
8 75 0.557 0.846 1.191 1.783 139.25 157.35 211.50 239.00
9 90 0.799 1.221 1.717 2.569 199.75 225.72 305.25 344.93
10 110 1.186 1.777 2.545 3.891 296.50 335.05 444.25 502.00
11 125 1.53 2.289 3.293 4.963 382.50 432.23 572.25 646.64
12 140 1.897 2.902 4.1 6.21 474.25 535.90 725.50 819.82
13 160 2.449 3.796 5.355 8.08 612.25 691.84 949.00 1072.37
14 180 3.148 4.762 6.801 10.258 787.00 889.31 1190.50 1345.27
15 200 3.876 5.89 8.392 12.623 969.00 1094.97 1472.50 1663.93
16 225 4.822 7.431 10.544 16.017 1205.50 1362.22 1857.75 2099.26
17 250 6.012 9.187 13.041 19.761 1503.00 1698.39 2296.75 2595.33
18 280 7.471 11.455 16.328 24.713 1867.75 2110.56 2863.75 3236.04
19 315 9.416 14.508 20.695 31.239 2354.00 2660.02 3627.00 4098.51
20 355 11.957 18.382 26.245 39.643 2989.25 3377.85 4595.50 5192.92
21 400 15.221 23.343 33.311 50.353 3805.25 4299.93 5835.75 6594.40
22 450 19.162 29.485 42.067 63.609 4790.50 5413.27 7371.25 8329.51
23 500 23.835 36.406 51.903 78.749 5958.75 6733.39 9101.50 10284.70
cal Development
nt Committee
L OFFICE

PIPES
Fiscal Year:- 2073/074
Rate per meter
6 kg/cm2 10 kg/cm2 Remarks
Without VAT With VAT Without VAT With VAT
23.00 25.99
33.75 38.14 ½"
50.50 57.07 ¾"
56.50 63.85 83.75 94.64 1"
87.50 98.88 128.50 145.21 1¼"
135.50 153.12 199.25 225.15 1½"
212.75 240.41 317.50 358.78 2"
297.75 336.46 445.75 503.70 2½"
429.25 485.05 642.25 725.74 3"
636.25 718.96 972.75 1099.21 4"
823.25 930.27 1240.75 1402.05 4½"
1025.00 1158.25 1552.50 1754.33 5"
1338.75 1512.79 2020.00 2282.60 6"
1700.25 1921.28 2564.50 2897.89 7"
2098.00 2370.74 3155.75 3566.00 8"
2636.00 2978.68 4004.25 4524.80 9"
3260.25 3684.08 4940.25 5582.48 10"
4082.00 4612.66 6178.25 6981.42 11"
5173.75 5846.34 7809.75 8825.02 12"
6561.25 7414.21 9910.75 11199.15 14"
8327.75 9410.36 12588.25 14224.72
10516.75 11883.93 15902.25 17969.54
12975.75 14662.60 19687.25 22246.59