Вы находитесь на странице: 1из 2

Hilbert Garlando

From: Alfredo Fernandez


Sent: Sunday, June 11, 2017 12:54 PM
To: Hilbert Garlando
Subject: FW: MG/QG - Train-3 Temporary Pipe Bridge - Meeting between QG/MG/TPD

From: Anoop Nair. A [mailto:anoopnair@medgulfconstruction.com]


Sent: Sunday, June 04, 2017 8:27 AM
To: Sanjeev Kumar Sharma <sksharma@technip.com>
Cc: Hilbert Garlando <hgarlando@technip.com>; Alfredo Fernandez <anfernandez@technip.com>; Muthukumaran
Angamuthu <muthu@medgulfconstruction.com>; Ronaldo Reyes <rreyes@technip.com>; Giriraj Agarwal
<gagarwal@technip.com>; Sridhar Dowlra <sridhar.d@medgulfconstruction.com>; Sivaram Ramamoorthy
<sivaram@medgulfconstruction.com>
Subject: RE: MG/QG - Train-3 Temporary Pipe Bridge - Meeting between QG/MG/TPD

Dear sir,

This is to inform you that, all the structural materials which we got from the market is S275JR.
Please revise the spec in the drawing on next revision submission time, as per below screenshot.

1
Thanks & Regards,

From: Sanjeev Kumar Sharma [mailto:sanjeevkumar.sharma@technipfmc.com]


Sent: Wednesday, May 17, 2017 10:51 AM
To: Sridhar Dowlra; DMistry@qatargas.com.qa
Cc: Hilbert Garlando; Alfredo Fernandez; Anoop Nair. A; Muthukumaran Angamuthu; Ronaldo Reyes; Giriraj Agarwal
Subject: RE: MG/QG - Train-3 Temporary Pipe Bridge - Meeting between QG/MG/TPD

Dear Sridhar / Deepak,

Please find attached following advance copy of the drawings for Temporary Bridge for review/approval by QG.
03-87-CI-DR-DT-0001, Rev B1 – Foundation – Plan sections and Details.
03-87-CI-DR-PL-0001, Rev-B1 – Foundation Layout Drawing
03-87-ST-DR-DT-0001, Rev-B1 – Steel Frame – Plan sections and Details.