ID Task Name Qtr 2, 2011 Duration Start Finish Predecessors Successors Resource Names

May June
S M T W T F S S M T W T F S S M T W
0 Construction Schedule2007 406 days Tue 5/17/11 Mon 6/25/12
1 1 SUB-STRUCTURE 107 days Tue 5/17/11 Wed 8/31/11
2 1.1 Driving Piles 15 days Tue 5/17/11 Tue 5/31/11 3SS+13 days Labor[20],Machine,Mason Labor[20],
3 1.2 Excavation 10 days Mon 5/30/11 Wed 6/8/11 2SS+13 days 4FF+2 days,9SS+20 days Labor[32]
4 1.3 Breaking Piles upto cut-off level 2 days Thu 6/9/11 Fri 6/10/11 3FF+2 days 5FS+2 days Labor[12]
5 1.4 PCC 15 days Mon 6/13/11 Mon 6/27/11 4FS+2 days 6SF+20 days Labor[32],Bhisti[15],Mason[2],Machine[3] Labo
6 1.5 Formwork for foundation 5 days Tue 6/28/11 Sat 7/2/11 5SF+20 days 7 Carpenter[14],Labor[14]
7 1.6 Reinforcement for pile cap 3 days Sun 7/3/11 Tue 7/5/11 6 8 Labor[5],Fitter[5]
8 1.7 Casting of pile cap 7 days Wed 7/6/11 Tue 7/12/11 7 12 Labor[15],Bhisti[8],Machine,Mason[2]
9 1.8 Formwork for individual or combined footing 9 days Sun 6/19/11 Mon 6/27/11 3SS+20 days 10 Carpenter[8],Labor[8]
10 1.9 Reinforcement for individual or combined footing 11 days Tue 6/28/11 Fri 7/8/11 9 11SS+4 days Fitter[11],Labor[11]
11 1.10 Casting of individual or combined footing 28 days Sat 7/2/11 Fri 7/29/11 10SS+4 days 12 Labor[35],Bhisti[18],Mason[4]
12 1.11 Backfilling, Compacting the filled earth 10 days Sat 7/30/11 Mon 8/8/11 11,8 13,17SS+21 days Labor[32]
13 1.12 PCC below plinth beam 2 days Tue 8/9/11 Wed 8/10/11 12 14 Labor[10],Bhisti[4],Mason,Machine
14 1.13 Formwork for plinth beam 10 days Thu 8/11/11 Sat 8/20/11 13 15 Carpenter[9],Labor[9]
15 1.14 Reinforcement for plinth beam 5 days Sun 8/21/11 Thu 8/25/11 14 16 Fitter[9],Labor[9]
16 1.15 Casting of plinth beam 6 days Fri 8/26/11 Wed 8/31/11 15 19,46 Labor[7],Bhisti[4],Mason
17 1.16 Anti-Termite treatment 4 days Sat 8/20/11 Tue 8/23/11 12SS+21 days 19 Labor[7]
18 2 SUPER-STRUCTURE 191 days Thu 9/1/11 Fri 3/9/12
19 2.1 Formwork for column upto first floor 3 days Thu 9/1/11 Sat 9/3/11 16,17 20SS+4 days,25 Carpenter[42],Labor[42]
20 2.2 Reinforcement for column 5 days Mon 9/5/11 Fri 9/9/11 19SS+4 days 21SS+6 days Fitter[13],Labor[13]
21 2.3 Erecting the column upto first floor 5 days Sun 9/11/11 Thu 9/15/11 20SS+6 days 22FS+7 days Labor[15],Bhisti[8],Mason[2],Machine
22 2.4 Formwork for slab and beam 12 days Fri 9/23/11 Tue 10/4/11 21FS+7 days 23 Carpenter[59],Labor[52]
23 2.5 Reinforcement for slab and beam 6 days Wed 10/5/11 Mon 10/10/11 22 24 Fitter[20],Labor[20]
24 2.6 Casting the first floor slab and beam monolithically 3 days Mon 10/10/11 Thu 10/13/11 23 46SS+90 days,28SS+13 days Labor[164],Bhisti[66],Mason[20],Machine[6]
25 2.7 Formwork for staircase upto first floor 9 days Sun 9/4/11 Mon 9/12/11 19 26 Carpenter[19],Labor[14]
26 2.8 Reinforcement for staircase 1 day Tue 9/13/11 Tue 9/13/11 25 27 Fitter[5],Labor[5]
27 2.9 Staircase upto first floor 3 days Wed 9/14/11 Fri 9/16/11 26 28 Bhisti[5],Labor[25],Mason[2]
28 2.10 Formwork for column upto second floor 3 days Mon 10/24/11 Wed 10/26/11 27,24SS+13 days 29SS+4 days,34 Carpenter[42],Labor[42]
29 2.11 Reinforcement for column 5 days Fri 10/28/11 Tue 11/1/1128SS+4 days 30SS+6 days Fitter[13],Labor[13]
30 2.12 Erecting the column upto second floor 5 days Thu 11/3/11 Mon 11/7/1129SS+6 days 31FS+7 days Labor[15],Bhisti[8],Mason[2],Machine
31 2.13 Formwork for slab and beam 12 days Tue 11/15/11 Sat 11/26/1130FS+7 days 32 Carpenter[59],Labor[52]
32 2.14 Reinforcement for slab and beam 6 days Sun 11/27/11 Fri 12/2/11 31 33,37SS+13 days Fitter[20],Labor[20]
33 2.15 Casting the second floor slab and beam monolithically 3 days Fri 12/2/11 Mon 12/5/11 32 34 Labor[164],Bhisti[66],Mason[20],Machine[6]
34 2.16 Formwork for staircase upto second floor 9 days Tue 12/6/11 Wed 12/14/11 28,33 35 Carpenter[19],Labor[14]
35 2.17 Reinforcement for staircase 1 day Thu 12/15/11 Thu 12/15/11 34 36 Fitter[5],Labor[5]
36 2.18 Staircase upto second floor 3 days Fri 12/16/11 Sun 12/18/11 35 37 Bhisti[5],Labor[25],Mason[2]
37 2.19 Formwork for column upto third floor 3 days Mon 12/19/11 Wed 12/21/11 32SS+13 days,36 38SS+4 days,43 Carpenter[42],Labor[42]
38 2.20 Reinforcement for column 5 days Fri 12/23/11 Tue 12/27/11 37SS+4 days 39SS+6 days Fitter[13],Labor[13]
39 2.21 Erecting the column upto third floor 5 days Thu 12/29/11 Mon 1/2/12 38SS+6 days 40SS+7 days Labor[15],Bhisti[8],Mason[2],Machine
40 2.22 Formwork for slab and beam 12 days Thu 1/5/12 Mon 1/16/12 39SS+7 days 41 Carpenter[59],Labor[52]
41 2.23 Reinforcement for slab and beam 6 days Tue 1/17/12 Sun 1/22/12 40 42 Fitter[20],Labor[20]
42 2.24 Casting the third floor slab and beam monolithically 3 days Sun 1/22/12 Wed 1/25/12 41 43 Labor[164],Bhisti[66],Mason[20],Machine[6]
43 2.25 Formwork for staircase upto third floor 9 days Thu 1/26/12 Fri 2/3/12 37,42 44 Carpenter[19],Labor[14]
44 2.26 Reinforcement for staircase 1 day Sat 2/4/12 Sat 2/4/12 43 45 Fitter[5],Labor[5]
45 2.27 Staircase upto third floor 3 days Sun 2/5/12 Tue 2/7/12 44 46 Bhisti[5],Labor[25],Mason[2]
46 2.28 Constructing brick walls 28 days Wed 2/8/12 Tue 3/6/12 16,24SS+90 days,45 47,49,50,51,52,53,54,61 Labor[48],Bhisti[5],Mason[24]
47 2.29 Fixing doors and windows frames 3 days Wed 3/7/12 Fri 3/9/12 46 49 Carpenter[9],Labor[2]
48 3 PLUMBING WORK 9 days Wed 3/7/12 Thu 3/15/12
49 3.1 Completing the pipeline work and connecting it to municipal chambers
6 days Sat 3/10/12 Thu 3/15/12 46,47 58 Fitter,Labor[16]
50 3.2 Plumbing work in lab 2 days Wed 3/7/12 Thu 3/8/12 46 58 Labor[24],Bhisti[11],Mason[18]
51 3.3 Plumbing work in WC 1 day Wed 3/7/12 Wed 3/7/12 46 58 Labor[18],Bhisti[14],Mason[17]
52 3.4 Plumbing work in Bathrooms 1 day Wed 3/7/12 Wed 3/7/12 46 58 Labor[15],Bhisti[7],Mason[11]
53 3.5 Wash-Hand basins 1 day Wed 3/7/12 Wed 3/7/12 46 58 Labor[15],Bhisti[7],Mason[11]
54 3.6 Connecting pipes from electric motor to elevated tank 2 days Wed 3/7/12 Thu 3/8/12 46 56 Labor[15],Bhisti[7],Mason[11]
55 4 FINISH WORK 111 days Wed 3/7/12 Mon 6/25/12

Task Project Summary Inactive Milestone Manual Summary Rollup Progress

Project: Construction Schedule2007 Split External Tasks Inactive Summary Manual Summary Deadline
Date: Thu 3/20/14 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 1
ID Task Name Qtr 2, 2011 Duration Start Finish Predecessors Successors Resource Names
May June
S M T W T F S S M T W T F S S M T W
56 4.1 External plastering first coat 7 days Fri 3/9/12 Thu 3/15/12 54 57 Labor[24],Bhisti[11],Mason[18]
57 4.2 External plastering second coat 5 days Fri 3/16/12 Tue 3/20/12 56 69 Labor[18],Bhisti[14],Mason[17]
58 4.3 Internal plastering first floor 12 days Fri 3/16/12 Tue 3/27/12 49,50,51,52,53 59 Bhisti[7],Labor[15],Mason[11]
59 4.4 Internal plastering second floor 12 days Wed 3/28/12 Sun 4/8/12 58 60 Bhisti[7],Labor[15],Mason[11]
60 4.5 Internal plastering third floor 12 days Mon 4/9/12 Fri 4/20/12 59 64 Bhisti[7],Labor[15],Mason[11]
61 4.6 Floorings of first floor 17 days Wed 3/7/12 Fri 3/23/12 46 62 Labor[7],Mason[11],Machine[5]
62 4.7 Flooring of second floor 17 days Sat 3/24/12 Mon 4/9/12 61 63 Labor[7],Mason[11],Machine[5]
63 4.8 Flooring of Third floor 17 days Tue 4/10/12 Thu 4/26/12 62 64 Labor[7],Mason[11],Machine[5]
64 4.9 Fittings of wall tiles in lab, water closet and bathroom 9 days Fri 4/27/12 Sat 5/5/12 60,63 65 Labor[19],Mason[19]
65 4.10 Applying Putty in two coats 19 days Sun 5/6/12 Thu 5/24/12 64 66 Labor[83],Painter[83]
66 4.11 Internal painting first floor 6 days Fri 5/25/12 Wed 5/30/12 65 67 Labor[8],Bhisti,Painter[17]
67 4.12 Internal painting second floor 6 days Thu 5/31/12 Tue 6/5/12 66 68 Labor[8],Bhisti,Painter[17]
68 4.13 Internal painting third floor 6 days Wed 6/6/12 Mon 6/11/12 67 69 Labor[8],Bhisti,Painter[17]
69 4.14 External painting 14 days Tue 6/12/12 Mon 6/25/12 57,68 Labor[12],Bhisti[2],Painter[23]

Task Project Summary Inactive Milestone Manual Summary Rollup Progress

Project: Construction Schedule2007 Split External Tasks Inactive Summary Manual Summary Deadline
Date: Thu 3/20/14 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 2
Qtr 3, 2011
June July August
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Labor[20],Machine,Mason
Labor[32]
Labor[12]
Labor[32],Bhisti[15],Mason[2],Machine[3]
Carpenter[14],Labor[14]
Labor[5],Fitter[5]
Labor[15],Bhisti[8],Machine,Mason[2]
Carpenter[8],Labor[8]
Fitter[11],Labor[11]
Labor[35],Bhisti[18],Mason[4]

Labo

Task Project Summary Inactive Milestone Manual Summary Rollup Progress

Project: Construction Schedule2007 Split External Tasks Inactive Summary Manual Summary Deadline
Date: Thu 3/20/14 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 3
Qtr 3, 2011
June July August
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Task Project Summary Inactive Milestone Manual Summary Rollup Progress

Project: Construction Schedule2007 Split External Tasks Inactive Summary Manual Summary Deadline
Date: Thu 3/20/14 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 4
Qtr 4, 2011
September October
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T

son[4]
Labor[32]
Labor[10],Bhisti[4],Mason,Machine
Carpenter[9],Labor[9]
Fitter[9],Labor[9]
Labor[7],Bhisti[4],Mason
Labor[7]

Carpenter[42],Labor[42]
Fitter[13],Labor[13]
Labor[15],Bhisti[8],Mason[2],Machine
Carpenter[59],Labor[52]
Fitter[20],Labor[2
Labo
Carpenter[19],Labor[14]
Fitter[5],Labor[5]
Bhisti[5],Labor[25],Mason[2]

Carpe

Task Project Summary Inactive Milestone Manual Summary Rollup Progress

Project: Construction Schedule2007 Split External Tasks Inactive Summary Manual Summary Deadline
Date: Thu 3/20/14 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 5
Qtr 4, 2011
September October
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T

Task Project Summary Inactive Milestone Manual Summary Rollup Progress

Project: Construction Schedule2007 Split External Tasks Inactive Summary Manual Summary Deadline
Date: Thu 3/20/14 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 6
November December
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M

]
Fitter[20],Labor[20]
Labor[164],Bhisti[66],Mason[20],Machine[6]

Carpenter[42],Labor[42]
Fitter[13],Labor[13]
Labor[15],Bhisti[8],Mason[2],Machine
Carpenter[59],Labor[52]
Fitter[20],Labor[20]
Labor[164],Bhisti[66],Mason[20],Machine[6]
Carpenter[19],Labor[14]
Fitter[5],Labor[5]
Bhisti[5],

Labo

Task Project Summary Inactive Milestone Manual Summary Rollup Progress

Project: Construction Schedule2007 Split External Tasks Inactive Summary Manual Summary Deadline
Date: Thu 3/20/14 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 7
November December
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M

Task Project Summary Inactive Milestone Manual Summary Rollup Progress

Project: Construction Schedule2007 Split External Tasks Inactive Summary Manual Summary Deadline
Date: Thu 3/20/14 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 8
Qtr 1, 2012
January February
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

enter[19],Labor[14]
itter[5],Labor[5]
Bhisti[5],Labor[25],Mason[2]
Carpenter[42],Labor[42]
Fitter[13],Labor[13]
Labor[15],Bhisti[8],Mason[2],Machine
Carpenter[59],Labor[52]
Fitter[20],Labor[20]
Labor[164],Bhisti[66],Mason[20],Machine[6]
Carpenter[19],Labor[14]
Fitter[5],Labor[5]
Bhisti[5],Labor[25],Mason[2]

Task Project Summary Inactive Milestone Manual Summary Rollup Progress

Project: Construction Schedule2007 Split External Tasks Inactive Summary Manual Summary Deadline
Date: Thu 3/20/14 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 9
Qtr 1, 2012
January February
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

Labo

Task Project Summary Inactive Milestone Manual Summary Rollup Progress

Project: Construction Schedule2007 Split External Tasks Inactive Summary Manual Summary Deadline
Date: Thu 3/20/14 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 10
Qtr 2, 2012
March April May
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T

Labor[48],Bhisti[5],Mason[24]
Carpenter[9],Labor[2]

Fitter,Labor[16]
Labor[24],Bhisti[11],Mason[18]
Labor[18],Bhisti[14],Mason[17]
Labor[15],Bhisti[7],Mason[11]
Labor[15],Bhisti[7],Mason[11]
Labor[15],Bhisti[7],Mason[11]

Task Project Summary Inactive Milestone Manual Summary Rollup Progress

Project: Construction Schedule2007 Split External Tasks Inactive Summary Manual Summary Deadline
Date: Thu 3/20/14 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 11
Qtr 2, 2012
March April May
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
Labor[24],Bhisti[11],Mason[18]
Labor[18],Bhisti[14],Mason[17]
Bhisti[7],Labor[15],Mason[11]
Bhisti[7],Labor[15],Mason[11]
Bhisti[7],Labor[15],Mason[11]
Labor[7],Mason[11],Machine[5]
Labor[7],Mason[11],Machine[5]
Labor[7],Mason[11],Machi

Task Project Summary Inactive Milestone Manual Summary Rollup Progress

Project: Construction Schedule2007 Split External Tasks Inactive Summary Manual Summary Deadline
Date: Thu 3/20/14 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 12
Qtr 3, 2012
May June July
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S

Task Project Summary Inactive Milestone Manual Summary Rollup Progress

Project: Construction Schedule2007 Split External Tasks Inactive Summary Manual Summary Deadline
Date: Thu 3/20/14 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 13
Qtr 3, 2012
May June July
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S

r[7],Mason[11],Machine[5]
Labor[19],Mason[19]
Labor[83],Painter[83]
Labor[8],Bhisti,Painter[17]
Labor[8],Bhisti,Painter[17]
Labor[8],Bhisti,Painter[17]
Labor[12],Bhisti[2],Painter[23]

Task Project Summary Inactive Milestone Manual Summary Rollup Progress

Project: Construction Schedule2007 Split External Tasks Inactive Summary Manual Summary Deadline
Date: Thu 3/20/14 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 14