Name of work :- Improvement to Tembhi Warodi Kasarbehal Hiwara Road MDR-55 Km.1/500 to 3/00 Under FDR-2013
by B.B.M., HMHL Carpet & Seal coat Tq.Mahagaon Distt.Yavatmal.

SN. Item of work Quantity. R A T E. Unit. Amount.


In Figure. In Words.

1 Providing and constructing 50mm.thick bituminous bound macadam


(BBM) road surface including supplying all materials, preparing the existing
road surface, spreading 40mm. stone layers metal 30% crusher broken
metal + 70% Hand broken metal (By breaking Rubble obtained by blasting) ,
heating and spraying the Bulk bitumen of 60/70(VG30) grade . @ 1.75 kg
/ sqm, spreading 12 mm.size chips compacting with power roller
etc.complete including applying tack coat at the rate of 50 Kg./100 Sqm.
on existing bitumen surface.
Km.2 2152.40 188.60 Rupees One Hundred One Square 405943.00
Eighty Eight and Paise metre
Sixty Only

Km.3 3687.80 189.30 Rupees One Hundred One Square 698101.00


Eighty Nine and Paise metre
Thirty Only

2 Providing, laying and rolling of open - graded premix surfacing ( Hot Mix
Hot Laid )of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates
using Bulk bitumen of 60/70(VG30) grade to required line, grade and level
to serve as wearing course on a previously prepared base, including mixing
in a suitable plant, laying and rolling with a smooth wheeled roller 8-10 tonne
capacity, finished to required level and grades. Including tack coat of Bulk
bitumen of 60/70(VG30) grade @ 5kg/10 sq.m etc complete. (On BBM
Surface )
SN. Item of work Quantity. R A T E. Unit. Amount.
In Figure. In Words.
Km.2 1875.00 175.90 Rupees One Hundred One Square 329813.00
Seventy Five and Paise metre
Ninety Only
Km.3 3750.00 176.10 Rupees One Hundred One Square 660375.00
Seventy Six and Paise metre
Ten Only

3 Providing and laying premix seal coat on Black topped surface by using
0.09cum per 10sqm of crusher aggregates passing through prescribed
sieves and 0.012 M.T.quantity of bitumen per 10sqm. Including supplying all
materials, preparing the existing road surface heating bitumen and
aggregates in hot mix plant, laying the mix seal surfacing by paver finisher
and compaction by powr roller etc.complete (Including transportation of all
materials) (Using 60/70 (VG) Bulk Bitumen)

Km.2 1875.00 82.70 Rupees Eighty Two and One Square 155063.00
Paise Seventy Only metre

Km.3 3750.00 82.80 Rupees Eighty Two and One Square 310500.00
Paise Eighty Only metre

4 Supplying murum having PI < 6 at the road side including conveying and 336.00 383.30 Rupees Three Hundred One Cubic 128789.00
stacking complete. Eighty Three and Paise metre
Thirty Only

5 Spreading gravel/sand/soft murum/available moorum over rubble 336.00 15.00 Rupees Fifteen and One Cubic 5040.00
soling/W.B.M.Surface,blanketing, berms etc. complete. Paise Nil Only metre
SN. Item of work Quantity. R A T E. Unit. Amount.
In Figure. In Words.
6 Compacting the hard murum side widths layerwise on each side with 1680.00 3.75 Rupees Three and Paise One Square 6300.00
static roller including necessary artificial watering complete . Seventy Five Only metre

7 Providing and fixing informatory sign boards in square or rectangular shape of any 0.90 4650.00 Rupees Four Thousand One Square 4185.00
size made out 16 guage (1.6 mm) thick mild steel sheet painted with one coat of zinc Six Hundred Fifty and metre
chromate-stoveing primer and two coats green stove enamel paint on front side and Paise Nil Only
grey stove enamel on back side and border / message / symbols etc. with cut out of
white retroreflective sheeting of engineering grade, including M.S. angle frame of 35
mm x 35 mm x 3 mm and two M.S. angle iron post of size 65 mm x 65 mm x 6mm,
3.65 m long properly cross braced with angle iron of size 50 mm x 50 mm x 5 mm
duly painted with alternate black and white bands of 25 cm width including G.I.
fixtures etc. and fixing the board in 1:4:8 concrete block of size 60 cm x 60 cm x 75
cm including transportation etc. complete. The nut bolts of board with angle iron
post/supporting structure after fixing at site has to be electrically
welded.Retroreflective sheeting should be with five years written warrenty from the
manufacture & authorised distributor/convertor,for satisfactory field
performance,durability & stipulatedretroreflectanceofretroreflective sheeting.

TOTAL RS. 2704109.00

( Rs.Twenty Seven Lakhs Four Thousand One Hundred Nine only. )

Sub-Divisional Officer Executive Engineer,


Public Works Sub-Division, Public Works Division,
Mahagaon Pusad.