1.

Temporary Utility – Sea Water Intake System


No. Description Total Install W-1 W-2 W-3 W-4 W-5 Remark
(M) (M) Desember 2017

1 Sea Water Intake Line 12” 590 Waitting Preparation Area

2 Hydrotest

________ : Completed Install : Duration of Work


________ : Remaining Install : Schedule of Work

Note :

• Baharu Cannot Performed for the installation.


Waitting finish the Preparation area by
See detail Drawing for PT. Leighton
the connection

• From SWI to RO
• HDPE Line 12” Above ground 590 M

See detail Drawing for


the connection

• Road Crossing Area


• 1 Road Crossing
2. Temporary Utility – Potable Water System (RO-Pioneer Camp)
No. Description Total Install W-1 W-2 W-3 W-4 W-5 Remark
(M) (M) Desember 2017

1 Potable Water Line 6” From RO to Camp 4.770 3.434 Continue

2 Potable Water Line 3” From RO to 2.650 1.500 Continue


Batching Plant & TR-3
3 Hydrotest Partial Hydrotest

P/W Line 3”
Crossing Road (3 Point)
See detail Drawing for
the connection
Crossing Road (3 Point) P/W Line 6” Crossing Road (1 Point)

Crossing Road (1 Point)


Crossing Road (3 Point)

Crossing Road (1 Point)

________ : Completed Install : Duration of Work Crossing Road (1 Point)


________ : Remaining Install : Schedule Work

Note :

• P/W line 3” still waiting fro fixed Route the pipe


continue to TR-3
• Remaining Material HDPE 6”
• Remaining Road Crossing 2 Point-at AMP Laydown See detail Drawing for
the connection
3. Temporary Utility – Potable Water System (Inside Pioneer Camp)
No. Description Total Install W-1 W-2 W-3 W-4 W-5 Remark
(M) (M)

1 Potable Water Line 3” Inside Pioneer 1.013 1.013 Finish


Camp
2 Hydrotest Finish

See detail Drawing for


the connection Crossing Road (1 Point)

• HDPE Line 3” Potable Water System-


Underground Pipe

________ : Completed Install : Duration of Work


________ : Remaining Install : Schedule of Work

Note :

• Remaining Install Pressure Switch 1 Ea


4. Temporary Utility – Waste Water System (Inside Pioneer Camp)
No. Description Total Install W-1 W-2 W-3 W-4 W-5 Remark
(M) (M)

1 Potable Water Line 4” Inside Pioneer 92 114 Finish


Camp
2 Potable Water Line 6” Inside Pioneer 550 713 Finish
Camp
3 Potable Water Line 8” Inside Pioneer 106 108 Finish
Camp
4 Potable Water Line 10” Inside Pioneer 22 28 Finish
Camp

Crossing Road (1 Point)

________ : Completed Install : Duration of Work


________ : Remaining Install : Schedule of Work

Note :
5. Temporary Utility – Fire Water System (Inside Pioneer Camp)
No. Description Total Install W-1 W-2 W-3 W-4 W-5 Remark
(M) (M)

1 Fire Water Line 6” Inside Pioneer Camp 485 579 Finish

2 Hydrotest Finish

________ : Completed Install : Duration of Work


________ : Remaining Install : Schedule of Work

Note :
Hydrant 3
• Waiting Foundation Hose Reel Box Fire Hydrant
Action by Buma
• Waiting Valve 3” Fire Hydrant

Hydrant 2

Hydrant 1
9. Matoa Facility to Pioneer Camp– Potable Water Line 3”
No. Description Total Install W-1 W-2 W-3 W-4 W-5 Remark
(M) (M)

1 Potable Water Line 3” From Matoa 1.340 1.340 Finish


Facility to Pioneer Camp
2 Potable Water Line 3” From Matoa 1.340 1.340 Finish
Facility to Pioneer Camp
3 Hydrotest Finish

See Detail Connection For TIE-IN


to Tank

Potable Water Line 3” x 2

See Detail Connection For TIE-IN


to Tank

________ : Completed Install : Duration of Work


________ : Remaining Install : Schedule of Work

Note :
10. Waste Water System-From Pioneer to STP-C
No. Description Total Install W-1 W-2 W-3 W-4 W-5 Remark
(M) (M)

1 Potable Water Line 3” From Matoa 1.400 1.400 Waiting Installation


Facility to Pioneer Camp Summersible Pump
2 Hydrotest Partial Hydrotest

See Detail Connection For TIE-IN


to Tank

________ : Completed Install : Duration of Work


________ : Remaining Install : Schedule of Work

Note :

• Remaining Connection Pipe HDPE 3” to


Summersible Pump at Treated Sump PIT
• Install PVC Line 2.5” STP to Sump PIT

See Detail Connection For TIE-IN


to Tank
11. Temporary Utility – Treated and Brine Water System (Camp-RO to Jetty Outfall)-PHASE I
No. Description Total Install W-1 W-2 W-3 W-4 W-5 W-6 W-7 W-8 W-9 W-10 Remark
(M) (M) Desember 2017 January 2018
1 Treated Water Line 8” from Early camp to 446 302
TR-3

2 Treated Water Line 10” from Early camp to 1.825 1.856 Finish
TR-3

3 Treated Water Line 10” Inside to TR-3 1.280 616 Finish

4 Brine and Treated Water Line 14” to-6LAT 1.978 Double Joint/Flange to
Flange Connection
5 Brine Water Line 10” from RO to Jetty 1 2.340 2.008 On Progress

6 Hydrotest Partial Hydrotest

________ : Completed Install : Duration of Work


Treated Water & Brine ________ : Remaining Install : Schedule of Work
________ : Completed Install Water Line 10” x 2 Treated Water & Brine
________ : Remaining Install Water 14” Note :
See Detail Drawing
Note : Connection • In Progress Laying Line Pipe 10” at TR-2 Area
Treated Water & Brine Water Line 14” to Jetty Outfall

Crossing Road (2 Point)


Treated Water Inside
Crossing Road (1 Point) TR-3 Line 10”
Brine Water Line 10” From RO to Jetty 1
Brine Water Line 10” Treated Water Line 10” Inside TR-3
from RO to Jetty 1
Crossing Road (2 Point)
Crossing Road (1 Point) Treated Water Line 10” from camp
To TR-3
Crossing Road (1 Point)

Treated Water Line 10


“ from camp to TR-3 See Detail Drawing
See Detail Drawing Connection
Connection Treated Water Line 8” from camp
To TR-3
Treated Water Line 8”
From camp to TR-3
15. Divertion Line 6”-Existing Potable Water Line
No. Description Total Install W-1 W-2 W-3 W-4 W-5 Remark
(M) (M) January 2018

1 Potable Water-Existing Line 6” 845 612 Waiting Material 6”

2 Potable Water-Existing Line 6” 845 612 Waiting Material 6”

3 Hydrotest 1 Lot

See Detail Connection For TIE-IN


to Existing Line

New Potable Water Line 6”-


Divertion Line New Potable Water Line 6”-
Divertion Line

See Detail Connection For TIE-IN


to Existing Line

________ : Completed Install : Duration of Work


________ : Remaining Install : Schedule of Work

Note :

• Waitting Material HDPE 6”


17. Fuel Diesel Line System-Tie-In To Tank Existing
No. Description Total Install W-1 W-2 W-3 W-4 W-5 Remark
(M) (M) February 2018

1 Fuel Disel Line 4” Carbon Steel 282

2 Hydrotest

See Detail Connection For TIE-IN


to TANK Existing

See Detail Drawing for


Crossing Road

________ : Completed Install : Duration of Work


________ : Remaining Install : Schedule of Work
See Detail Connection to Fuel
Station
Note :

• Waiting e-MOC Permit


18. Raw Water HDPE Line 6”-Existing RO to New RO
No. Description Total Install W-1 W-2 W-3 W-4 W-5 W-6 W-7 W-8 W-9 Remark
(M) (M) Desember 2017 January 2018

1 Raw Water Line 6”-Existing RO 1300 336 Continue  Waiting Material 6”


to New RO
2 Installation PVC Connection at 1 Lot
Existing RO
3 Hydrotest 1 Lot

________ : Completed Install : Duration of Work


________ : Remaining Install : Schedule of Work

Note :

• Remaining Material HDPE Line 6”

See Detail Connection For TIE-IN


to Existing RO-PVC Pipe

HDPE Line 6”-Lenght- : 1300M


(Above Ground)

See Detail Connection For TIE-IN


to Tank
19. Temporary Utility – Treated Water System (Demolize Existing CS Galv.)
No. Description Total Install W-1 W-2 W-3 W-4 W-5 Remark
(M) (M) January 2018

1 Traated Water Line 8”-Demolize CS Galv. 700 Waiting HDPE Line 8”


Exisiting
2 Hydrotest

Crossing Road (1 Point)

Treated Water Line 8”-Demolize


CS Galv. Existing 8”
________ : Completed Install : Duration of Work
________ : Remaining Install : Schedule of Work

Note :
________ : Completed Install : Duration of Work Detail Connection
________ : Remaining Install : Schedule of Work
• Remaining Install By Pass 6” : Waitting tanky
Empty
Note :

• Remaining Material HDPE Line 8”


20. Potable Water Line 3” from RO Existing to Batching Plant
No. Description Total Install W-1 W-2 W-3 W-4 W-5 Remark
(M) (M)

1 Potable Water Line 3” From RO Existing 850 850 Finish


to Batching Plant
2 Hydrotest Finish

________ : Completed Install : Duration of Work


________ : Remaining Install : Schedule of Work

Note :

• Remaining Connection Pipe HDPE 3” to


Summersible Pump at Treated Sump PIT
14. Treated Water Line 3” from WWT Existing to Batching Plant
No. Description Total Install W-1 W-2 W-3 W-4 W-5 Remark
(M) (M)

1 Treated Water Line 3” From WWT 450 450 Finish


Existing to Batching Plant
2 Hydrotest Finish

________ : Completed Install : Duration of Work


________ : Remaining Install : Schedule of Work

Note :

• Remaining Connection Pipe HDPE 3” to


Summersible Pump at Treated Sump PIT
21. Temporary Utility – Treated and Brine Water System (Camp-RO to Jetty Outfall)-PHASE II
No. Description Total Install W-1 W-2 W-3 W-4 W-5 W-6 W-7 W-8 W-9 W-10 Remark
(M) (M) Desember 2017 January 2018
1 Treated Water Line 10” from RO to Jetty 4465 340 Phase-II
LNG 1 Hold Laying Pipe

2 Hydrotest 1 Lot

Treated Water & Brine Crossing Road (2 Point)


Water Line 10”
________ : Completed Install : Duration of Work
________ : Remaining Install : Schedule of Work
________ : Completed Install
________ : Remaining Install Note :
See Detail Drawing
Note : Connection • In Progress Laying Line Pipe 10” at TR-2 Area
• Remaining HDPE Pipe 10”
Treated Water & Brine Water Line 14” to Jetty Outfall
Brine Water Line 10”
from RO to Jetty 1

Brine Water Line 10” From RO to Jetty 1


Treated Water Line 10” Inside TR-3

Treated Water Line 10” from camp


Crossing Road (1 Point)
To TR-3

See Detail Drawing


Connection

Treated Water Line 8” from camp


To TR-3