Project : PBMSJ - JAMBI

Title of Work : FIELD ERETED TANK Date 27-Sep-17


Name of Customer : PT. RECON Rev. 1
MAIN EQUIPMENT SCHEDULE
TOTAL
NO. EQUIPMENT DESCRIPTION Unit EQUIPT. REMARKS
WEEK
WEEKS
1 2 3 4 5 6 7 8 9 10 11 12
Main Equipment Schedule
1 Welding Traffo LCF-1200 Unit 0
2 Welding Rectifier RC-500 (500 Amprer)DC Unit 0
3 Gouging Machine 800 Amp to 1000AmpreDC Unit 0
4 Air Compressor for Gouging Machine (125CFM) Unit 0
5 Welding Trafo ARC-400 Unit 3 3 3 3 3 3 18
6 Welding Engine 500-700 Amp Unit 4 4 4 4 4 4 24
7 Grinding Machine dia (4"/5"/6"/7") Unit 7 7 7 7 7 7 42
8 FCAW Welding Regulator Unit 4 4 4 4 4 4 24
9 Crane 25 Ton (Telescopic) Unit 1 1 1 1 1 1 6
10 Crane 50 Ton (Telescopic) Unit 0
11 Truck Crane (5 Ton. Cap.) Unit 1 1
12 Fork Lift (2.5-3Ton) Unit 0
13 Fork Lift (5-7 Ton) Unit 0
14 Genset (250 KVA) Unit 0
15 Genset (125 KVA~ 200KVA) Unit 0
16 Genset (63~100 KVA) Unit 1 1 1 1 1 1 6
17 Light Truck Unit 1 1 1 1 1 1 6
18 Trailler / Heavy truck Unit 0
19 Bushing for Transportation of manpower Unit 1 1 1 1 1 1 6
20 Light Vehicle Unit 1 1 1 1 1 1 6
21 Compressor for 750CFM for Blasting Unit 1 1 1 1 1 1 6
22 Painting Aparatus Set 1 1 1 1 1 1 6
23 Electrical Compressor (for painting) Unit 1 1 1 1 1 1 6
24 Hydro test Pump (6"x5") Unit 1 1 2
25 Tube Scaffolding @ 6 mtr Joint 300 300 300 300 300 300 1800
26 Scaffolding Clamp Pcs 900 900 900 900 900 900 5400
27 Metal Deck @ 2.5 mtr to 4 mtr Unit 100 100 100 100 100 100 600
Monthly subtotal Direct Labour - Manmonths 3 3 1 0 1323 1323 1326 1326 1327 1327 7,959
Cumulative Total Direct Labour - Manmonths 3 6 7 7 1330 2653 3979 5305 6632 7959 7,959