APGENCO – Delegation of Powers & Purchase Management System Manual -Revised Orders -
Issued.
===============================================
G.O.O.No.129/J.S.(Per)/ 2016 Date:15.07.2016
Read the following :-
In the reference 4th read above, a committee was constituted with CE/C/Thermal,
CE/TPC, CE/HPC&HP, FA&CCA (Accounts & Resources) as a members and CE/Generation as
Member convener to submit consolidated recommendations for modifications/alterations to be
made to the “Delegation of Powers and Purchase Management System Manual”. The said
committee has submitted its report and same was placed before the Board.
02). In the 145th Board Meeting held on 01.03.2016, The Board of Directors of
APGENCO has approved the recommendations of the Committee with regard to the revision of
delegation of powers to various officers including the Chairman, Managing Director and whole
time Directors of the corporation on Works, Stocks, Stores, Finance and also purchase Management
System Manuals.
03). After careful consideration, APGENCO hereby communicate the revised manuals
as detailed below :-
04). All the Concerned officers are requested to take action accordingly.
05). These orders shall come into force with immediate effect.
K VIJAYANAND
MANAGING DIRECTOR
To
All Chief Engineers//Superintending Engineers
All FA&CCAs//Dy.CCAs
The Chief General Manager (Adm, IS & ERP)
The Joint Secretary (Per)
(Contd ., 02)
-: 02 :-
Copy to the :-
PS to Managing Director/APGENCO/VS/Hyd
SAO to Director (Finance)/APGENCO/VS/Hyd
DS/AS/PO/DE/ADE to Directors of APGENCO
Company Secretary/APGENCO/VS/Hyd
DE/MPP/VS/Hyd//Pay Officer//AO/CPR/VS/Hyd
PA to Chief of Vigilance and Security/VS/Hyd
All G.Ms/DGMs/SAOs/ DEs/EEs/Asst.Secys/D.Ms
S.F/Spare
C.No.JS(P)/DS(E)/AS(E)/PO.Reg/08/2015
// FORWARDED :: BY ORDER //
PERSONNE OFFICER
1
ANNEXURE – I
DELEGATION OF POWERS
1.12 To sanction Full Powers Upto 25% Upto 20% Upto 15% Upto 10% Can accept
cumulative excess subject to total subject to total subject to total subject to total minor technical
over authorization of estimate not estimate not estimate not estimate not deviations not
all capital works not exceeding exceeding exceeding exceeding having
involving material powers in (1.10) powers in (1.10) powers in (1.10) powers in financial affect
alteration in above above above (1.10) above in execution.
design/scope of the
project
1.13 Accord technical --- --- --- Full Powers Full Powers for Full Powers for Technical
Sanction to detailed the works the works Sanction of
estimates of works costing up to costing up to estimates may
be accorded
covered by 30 Lakhs 4 Lakhs.
only after
authorization administrative
approval.
2
Concerned CE/ CGM or SE/ GM or DE/EE/ DGM or
S.No. Nature of Power SPC MD Remarks
Director equivalent equivalent equivalent
1.14 Approval to extra or Full Powers Full Powers up to Up to 20% of the Up to 15% of the Up to 15% of Up to 10% of the Revised
deviated items 25% of the contract value or contract value or the contract contract value or estimate shall
Percentage cumulative contract value Rs.2Cr. Rs.1Cr. value or Rs. 4 Lakhs be got
(supplemental items) subject to a whichever is less whichever is less Rs. 30 Lakhs whichever is sanctioned
maximum limit of whichever is less wherever the
Rs.3 Cr. less actual exceed
10% of
contract
value.
1.15 Acceptance of tenders
for works when
competitive tenders
are invited
A) If the acceptable
tender is the lowest
a. Open Tenders Upto Full Powers upto Full Powers upto Full Powers upto Full Powers Full Powers upto
Rs.25 Cr. Rs.6Cr. and Rs.2 Cr. and Rs.1 Cr. and up to Rs.30 Rs.4 Lakhs and
excess is not more excess is not excess is not Lakhs and excess is not
than 15% of the more than 15% of more than 10% of excess is not more than 5% of
sanctioned the sanctioned the sanctioned more than 10% the sanctioned
estimate. estimate. estimate. of the estimate.
sanctioned
estimate.
b) Limited Tenders Upto Full Powers upto Full Powers upto Upto Rs.30 Upto Rs.10 upto Rs.2 Lakhs Concrete
Rs.10 Cr. Rs.3 Cr. Rs.1 Cr. Lakhs Lakhs reasons are to
be recorded.
Powers are to
be used
sparingly in
case of
emergency
works only.
B) If the tender other than Upto Full Powers upto Full Powers upto Full Powers upto Full Powers upto -- Reasons to be
the lowest is to be Rs.10 Cr. Rs.3Cr. and Rs.1 Cr. and Rs.20 Lakhs and Rs.4 Lakhs and recorded, for
accepted. If necessary excess is not more excess is not excess is not excess is not approving other
more than 10% than the lowest
after conducting than 15% of the more than 15% of more than 10% of
of the sanctioned tender.
negotiations in case of sanctioned the sanctioned the sanctioned
urgency estimate estimate estimate. estimate.
3
Concerned CE/ CGM or SE/ GM or DE/EE/ DGM or
S.No. Nature of Power SPC MD Remarks
Director equivalent equivalent equivalent
C) If only one tender is Up to Full Powers upto Full Powers upto Full Powers up to Up to -- These powers
received and it is not Rs.5 Cr. Rs.1.4 Cr. and Rs.50 Lakhs and Rs.10 Lakhs and Rs.2 Lakhs shall be
considered necessary to excess is not more excess is not excess is not 5% excess exercised in
reinvite tenders and than 15% of the more than 15% of more than 10% of over with case of
follow up negotiations are sanctioned the sanctioned the sanctioned technically emergency
not considered necessary estimate. estimate. estimate. sanctioned only. The
estimate. monthly return on
such cases shall
be sent to the
next higher
authority with a
copy to the FA &
CCA (Audit)”
1.16 Awarding of contracts on Full Powers Full Power upto Full Power upto Full Power upto Full Powers upto
nomination if tenders are Up to upto Rs.1.4 Cr. Rs.50 Lakhs not Rs.20 Lakhs not Rs.10 Lakhs Rs.4 Lakhs not
not received even after Rs.5 Cr. not exceeding exceeding exceeding not exceeding exceeding
two calls. estimate rates estimate rates. estimate rates. estimate rates. estimate rates.
1.17 Awarding of contracts on Upto Upto Upto Upto Upto Reasons to be
nomination without Up to Rs.80 Lakhs not Rs.30 Lakhs Rs.10 Lakhs not Rs.4 Lakhs Rs.2 Lakhs recorded.
inviting tenders in case of Rs.2 Cr. exceeding not exceeding exceeding not exceeding not exceeding Powers to be
emergency both for estimate rates estimate rates. estimate rates. estimate rates. estimate rates. used sparingly.
original and repair works.
1.18 Annual maintenance and
repairs of Buildings/
Roads/ Station
Equipment/ Plant and
Machinery, and other
works.
Building and Roads: Full Upto Upto Upto Upto Upto
A) Residential, Non Powers Rs. 1.4 Cr. Rs. 50 Lakhs Rs. 20 Lakhs Rs.10 Lakhs Rs. 2 Lakhs
residential Buildings,
Roads, special repair,
additions and alterations
and ordinary repairs.
Maintenance, Repairs, Full Upto Upto Upto Upto Upto
B) Servicing of earth moving Powers Rs. 80 Lakhs Rs.20 Lakhs Rs. 10 Lakhs Rs. 6 Lakhs Rs. 2 Lakhs
and Heavy Haulage
equipment, like tractors,
cranes, locos, Fire
tenders, bull dozers etc.
4
i) Materials relevant to Full Upto Rs.6 Cr. Upto Rs2 Cr. Upto Rs.1 Cr. Upto Upto
construction/ Operation / Rs.30 Lakhs Rs.4 Lakhs
Plant & Machinery /
Electrical equipment
including spares, and
Telecom equipment &
computer related
equipment**
** Like purchase of (With the general approval of CGM/ERP/ Information Systems or through CGM/ERP/ In case of
a) Computers Information Systems after vetting by FA&CCA (Audit & Trust) printers/ Fax
b) Servers Machines
c) Printers/Fax Machines less than
d) Network equipment Rs.10,000/-
e) Computer related accessories value,
f) UPS station head
g) Telecom equipment can procure
h) Software, and
i) Software development intimation to
the CGM/IS/
ERP for
information
7
iv) Medical ,Hospital Stores and Medical Full Upto Upto Upto Upto Upto
lab Equipment Rs.1.4 Cr. Rs.40 Lakhs Rs.10 Lakhs Rs. 6 Lakhs Rs.2 Lakhs
v) Office equipment Including fax Full Upto Upto Rs.20 Upto Upto Upto
machine, Xerox machine etc, Rs.80 Lakhs Lakhs Rs.10 Lakhs Rs. 2 Lakhs Rs.50,000/-
Furniture and consumables.
vi) To Incur expenditure in respect of any Full Upto Upto Upto Upto Upto (Justification
matter for which no specific authority Rs.60 Lakhs Rs.10 Lakhs Rs.2 Lakhs Rs. 1 Lakh Rs.20,000/- shall be sent
has been provided. immediately to
the next higher
authority for
incurring the
expenditure).
8
Concerned CE/ CGM or SE/ GM or DE/EE/ DGM
S.No. Nature of Power SPC MD Remarks
Director equivalent equivalent or equivalent
2.11 Full Upto Upto Upto Upto Upto
a) To purchase on the basis of the rates Rs.3 Cr. Rs.1 Cr. Rs.50 Lakhs Rs.30 Lakhs Rs.2 Lakhs
approved under Rate Contract (s)
of DGS & D and APGENCO without
calling for tenders”
b) To purchase outs ide DGS&D rate Full Upto Upto Upto Upto Upto
contract in respect of the material Rs.6 Cr. Rs.2Crores Rs.1 Cr. Rs. 30 Lakhs Rs.4 Lakhs
available against APGENCO rate
contract items at the same or lower
rates than those prevailing under rates
contract on conditions which are more
favorable than those of DS&D rate
contract duly observing the tendering
procedures
2.12 A) Acceptance of tenders where more
than one valid tender is received
i) If the tender is lowest
a) Open Tenders Upto Upto Upto Upto Upto Upto
Rs.25 Cr. Rs.6 Cr. Rs.2 Cr. Rs.1 Cr Rs.30 Lakhs Rs.4 Lakhs
b) Limited Tenders Upto Upto Upto Upto Upto Upto
Rs.5 Cr. Rs.1.4Cr. Rs. 50 Lakhs Rs.20 Lakhs Rs.4 Lakhs Rs.1 Lakh
ii) If a tender other than the lowest is to For accepting
be accepted (Reasons to be other than the
recorded) lowest tender,
Open Tenders Upto Upto Upto Upto Upto Upto monthly return of
Rs.10 Cr Rs.3 Cr Rs.1 Cr. Rs. 50 Lakhs Rs.10 Lakhs Rs.1 Lakh such cases shall
be sent to next
higher authority
with a copy to
the FA & CCA
(Audit & Trust )
B) Purchase of Proprietary items
Upto Upto Upto Upto Upto Upto
a) Government & PSU Rs.20 Cr. Rs.6 Cr. Rs.1 Cr. Rs. 50 Lakhs Rs.20 Lakhs Rs.4 Lakhs
Upto Upto Upto Upto Upto Upto
b) OEM (Private) Rs.5 Cr. Rs.1.4Cr. Rs. 50 Lakhs Rs.15 Lakhs Rs.10 Lakhs Rs.2 Lakhs
C) Single tender (branded materials) Upto Upto Upto Upto Upto -- (Reasons to be
Rs.5 Cr. Rs. 1.4 Cr. Rs. 50 Lakhs Rs.10 Lakhs Rs.4 Lakhs recorded).
9
DE/EE/
Concerned CE/ CGM or SE/ GM or
S.No. Nature of Power SPC MD DGM or Remarks
Director equivalent equivalent
equivalent
2.13 To place repeat order provided there is Upto 50% of Upto 50% of Upto 50% of Upto 50% of Upto 50% of Upto 50% of Where the
not downward trend in prices subject the original the original the original the original the original the original quantity cannot
to budgetary provision and over all order order order order order order be broken in to
powers vested with the purchase approved by approved by approved by approved by approved by approved by half, then
authority. itself him/her self him/her self him/her self him/her self him/her self minimum
possible
quantity can be
ordered even
exceeding 50%
of the original
order
2.14 a) Emergency Purchases (reasons to Full Upto Upto Upto Reasons to be
be recorded) Rs. 40,000/- Rs. 20,000/- Rs. 10,000/- recorded).
b) Short term lending / borrowing and Upto Upto Upto Upto Upto Upto
emergency / purchase of materials and Rs.5 Cr. Rs. 1.4 Cr. Rs. 50 Lakhs Rs.30 Lakhs Rs.10 Lakhs Rs. 2 Lakhs
equipment with centre / State Govt. &
Govt. controlled organizations
2.15.A) To declare stores as surplus / Full Upto Upto Upto Upto Upto (Salvage
unserviceable to fix resale , reserve Rs. 80 Lakhs Rs.20 Lakhs Rs.10 Lakhs Rs. 4 Lakhs Rs. 2 Lakhs committee to
price for them and order disposal by be appointed
open Tender or other-wise difficult to at every
dispose off at book value. station
B) To declare stores as surplus / Full Upto Upto Upto Upto Upto consisting of
unserviceable to fix resale, reserve Rs. 30 Lakhs Rs.10 Lakhs Rs.6 Lakhs Rs.4 Lakhs Rs.2 Lakhs SE (user
price for them and order disposal by dept.), SAO,
open tender or otherwise difficult to Divisional
dispose off at book value for T&P Engineer /
articles. Stores & other
C) Sanction of sale of stores other than Full Upto Upto SE to be co-
tools and plant and controlled articles Rs.2 Lakhs Rs. 50,000/- opted)
at issue rates plus storage, supervision
and handling charges or at market
rates which ever is higher without
detrimental to works (against payment)
10
DE/EE/
Concerned CE/ CGM or SE/ GM or
S.No. Nature of Power SPC MD DGM or Remarks
Director equivalent equivalent
equivalent
2.16 To sanction expenditure on transport
of materials by the
i) Cheapest mode shortest route; Upto Upto Upto Upto Upto
Full
Rs.2 Cr. Rs.80 Lakhs Rs.40 Lakhs Rs. 20 lakhs Rs. 4 Lakhs
ii) Other than the cheapest mode/ Upto Upto Upto Upto Upto
shortest route for reasons to be Full Rs.1.40 Cr. Rs.40 Lakhs Rs. 20 lakhs Rs. 10 lakhs Rs. 2 Lakhs
recorded.
2.17 To award contract for loading Upto Upto Upto Upto Upto Upto
,unloading, transport and handling of Rs.10 Cr. Rs.3 Cr. Rs.80 Lakhs Rs. 40 Lakhs Rs. 20 Lakhs Rs. 4 Lakhs
materials based on tenders
2.18 Purchase of stationery, drawing Full Upto Upto Rs. 15
materials, printed forms, printed book, Rs. 25 lakhs lakhs
logbook, charts for recorder etc. per annum per annum
except computer stationary.
2.19 A) Authorizing expenditure of
demurrages or wharfage charges
a) Railways Full -- --
b) Other than Railways Upto Upto Upto Rs. --
Full
Rs.10 Lakhs Rs. 1 Lakh 10,000/-
B) Authorizing Waiver of demurrages /
wharfage charges
Upto Upto Upto
a) Railways Full
Rs.2 Cr. Rs. 1 Cr Rs. 50 Lakhs
Upto Upto Upto --
b) Other than Railways Full
Rs.2 Lakhs Rs.1 Lakh Rs.10,000/-
2.20 Sale of scrap Upto Upto Rs.6.00 Upto Upto This item to be
Rs.20 Cr. Crores Rs.2 Cr. Rs.1 Cr. dealt by head
quarters.
2.21 Material Inspection by 3rd party
agencies
a) Governments / Full Powers Full Powers Full powers with in Full powers with in Full powers with in
Statutory Local his/her jurisdiction his/her jurisdiction his/her jurisdiction
bodies as per
statutory
requirements
b) Other Agencies Full Powers Upto Rs. 1 Lakh ------ ------ ------
3.17
a) To accept Full Powers Upto Rs. 2 Lakhs Upto Rs.50,000/-
certificate of
payment in lieu of
missing voucher
where payment
was made by
crossed
cheque/D.D.
b) To accept Upto Rs. 40,000/- Upto Rs. 20,000/- Upto Rs. 10,000 /-
certificate of in each case
payments in the
time of missing
voucher where
payments was
made by cash
13
Concerned
S.No Nature of Power MD CE/FA&CCA SE\Dy.CCA DE/EE/SAO Remarks
Director
3.18 Write of powers
A) Due to obsolescence Upto Rs.30 lakhs p.a Upto Rs.10 lakhs Upto Rs.4 Lakhs p.a Upto Rs. 10,000/-
Rs. 2 Lakh in each p.a Rs. 1 Lakh in Rs. 40,000/- in each
case each case case
B) Due to theft, fraud or Upto Rs.30lakhs p.a Upto Rs.4 lakhs Upto Rs.1 Lakh p.a Upto Rs.20,000/- p.a
negligence Rs. 2 Lakh in each p.a Rs. 50,000/- in Rs. 20,000/- in each Rs. 5,000/- in each
case each case case case
C) Due to irrecoverable Upto Rs.12 lakhs p.a Upto Rs.2 Lakhs Upto Rs.50,000/- p.a Upto Rs.10,000/- p.a
rents / hire charges / Rs. 1 Lakh in each p.a Rs. 10,000/- in Rs.5000/- in each case Rs.1,000/- in each
debts / loans / advances case each case case
D) Any amount due to the Upto Rs.20 Lakhs Upto Rs.4 Lakhs Upto Rs.2 lakhs p.a Upto Rs.10,000/- p.a
APGENCO such as bills p.a Rs. 1 Lakh in p.a Rs. 10,000/- in Rs. 5,000/- in each case Rs. 1,000/- in each
receivable from supplier, each case each case case
rent, hospital dues etc.,
becoming irrecoverable
E) Irrecoverable amounts Upto Rs.12 lakhs Upto Rs.4 lakhs Upto Rs.2 Lakhs p.a Upto Rs.10,000/- p.a
dues from employees p.a Rs. 1 Lakh in p.a Rs. 10,000/- in Rs. 5,000/- in each case Rs. 1,000/- in each
and ex-employees each case each case case
F) Small irrecoverable Rs. 1 Lakh in each Upto 40,000/- in Upto Rs.20,000/- in each Upto Rs.10,000/- p.a
amounts from the case each case case Rs. 1,000/- in each
accounts of contractors case
G) Transit/ Windage More than 1.5% More than 0.8% & Upto 0.8%
Losses of Coal upto 1.5%
3.19 Settlement of claims Upto Rs.12 Lakhs
against the APGENCO
from any cause not
specifically provided for
in the powers delegated
3.20 Mode of payments
Operating of Letter of Full powers with
A) Credits (L/C) concurrence of
JMD/Director(F)
B) Negotiation of documents Full Powers
through Banks for
indigenous supplies and
services
14
S.No Nature of Power MD Concerned Director CE/FA&CCA SE\Dy.CCA DE/EE/SAO Remarks
3.21 Appointment of Tax Consultants / Upto Upto Rs. 20,000/-
internal / Tax auditors / and experts Rs.12 Director (F) upto
in accountancy company law, Lakhs Rs. 2 Lakhs
costing and financial management
etc., for consultancy services and
approval of their fees
3.22 All types of administrative and Upto Rs. Upto Rs. 75,000/- Upto Rs. 30,000/- Upto Rs.15,000/-
general expenses of relevant 1,80,000/-
nature not covered under other
items (Contingencies )
3.23 Liveries, Uniforms, safety items Full powers for Full powers for
purchases with in purchases with in
his/her jurisdiction his/her jurisdiction
3.24 a) Sanction of imprest Full Full powers . Full Powers with in Full Powers with in Full Powers Vide G.O.O
powers can sanction imprest to his/her jurisdiction as his/her jurisdiction with in No. 165/GM(
Non- imprest holders . per rules as per rules his/her HR) / 2002,
jurisdiction DATED
as per rules 04/07/2002
3.25 Sanction of Legal charges Full powers Full Powers for payment up to Rs. 50,000/- per
of legal fee as per Govt. annum
approved scales to legal
councils
3.26 Sanction of expenditure on Tender Full Powers a) Upto Rs. 1 Lakh p.a. Upto Rs.20,000/- Upto
notices / Advertisement / publicity / for photograph works p.a. for photograph Rs.10,000/-
Photographs works p.a. for
photograph
b) Upto Rs. 1 Lakh p.a. works
for publicity.
Concerned
S.No Nature of Power MD CE/FA&CCA SE\Dy.CCA DE/EE/SAO Remarks
Director
3.28 a) Sanction of postage, freight, Full powers Full Powers upto 1 Lakh in Upto Rs.20,000/- upto Rs.4,000/-
demurrage, wharfage, loading, each case in each except in each case
unloading and other contigent demurrage and except
charges other than coal. wharfage. insurance
b) Insurance Full powers CE / head Full Powers Full Powers
quarters will deal with main
plant & machinery
c) Custom duty Full Powers Full Powers Full Powers
3.29 Purchase of Office equipment like Full Powers Upto Rs. 2 Lakhs p.a. Upto Rs. 50,000/-
Clocks Time Pieces, Rubber p.a.
stamps and Other Articles of
Office equipment based on
quotations wherever feasible
3.30 Articles and equipment for Guest Full Powers a) Initial expenses Upto a) Upto Rs.4 Lakhs
Houses, Project Hostels, Rs.10 Lakhs in each case p.a.
Inspection Bungalow etc., based b) Replacement and b) upto Rs.40,000/-
on quotations wherever feasible. renewals upto Rs.2 Lakhs p.a.
p.a. per building
3.31 Retention of quarters in the
project beyond stipulated period
a) Transferred employee Full Powers Full powers in respect of Full powers in
employees working under respect of employees
their control till the end of working under their
control till the end of
academic year
academic year where
SE is head of the
station
b) Deceased employee 3 months from the date of
death extendable to 6 months
in special cases.
3.32 Passing bills Full Powers Full Powers Full Pow ers A.O. may
AO Upto exercise full
Rs.2 Lakhs powers in
AAO Upto case of estt.
Rs: 1.0 Lakh Bills.
3.33 Cheque drawing Full Powers Full Powers Full Pow ers
AO Upto Rs.3
Lakhs
AAO Upto
Rs.1.5Lakh
16
Concerned
S.No Nature of Power MD CE/FA&CCA SE\Dy.CCA DE/EE/SAO Remarks
Director
3.34 Approval of Journal Entries Full powers Full powers SAO Full Entries for
Pow ers
accounting,
AO Upto
Rs.2 Lakhs rectification etc.
AAO Upto without involving
Rs.50,000/- any financial
3.35 Refreshments or office expenses. Full powers Full powers Upto Rs.10,000/- at a Upto Rs. commitment
time Rs.1000/- at
time
3.36 Authorization and approval of Tour
Programme
a) Within his/her jurisdiction Full powers Full powers Full powers AO may exercise full
pow ers wherever the AO
is the head of the
Accounts Wing
b) Within the state Full powers Full pow ers where SE is the
head of the station
c) Within the India Full powers
d) Abroad Full
powers
3.37 Authorizing staff and executives under Full powers
them to travel on official tours by a
higher class / mode to which they are
not entitled under TA rules.
3.38 Counter signatures of T.A. Bills / Full powers Full powers Full powers A.O. & A.A.0 can
Medicals and other bills counter sign T.A. bills
and other bills subject
to approval of tour
diaries etc., by
competent authority
3.39 Sanction of local conveyance charges Full powers Up to Rs.1000/- in each Up to
case per day Rs.500/- in A.O. can exercise
each case per similar powers.
day
3.40 Sanction of purchase of books, Full powers Up to Rs.10,000/- p.a. Up to Rs.4000/-
journals, periodicals, magazines etc., per annum
3.41 To execute promissory notes, hundies, Full powers With the approval of
bills of exchange, bill of lading and the competent
other negotiable instruments authority
17
DE/EE/ DGM
Concerned CE/ CGM or SE/ GM or
S.No. Nature of Power SPC MD or Remarks
Director equivalent equivalent
equivalent
4.0 Administrative approvals of Above Rs.2 Cr. From Rs.1 Cr. to Up to Rs.1 Cr.
Technical specifications, pre- Rs.2 Cr.
qualification criteria & technical
bids
5.0 Sanction of hired vehicles Full Powers
6.0 Sanction for payment of excess Full powers
KMs run in respect of hired
vehicles
7.0 Deviation (s) in the commercial Full powers Next higher level Next higher Next higher Next higher
terms and conditions after committee level level level
placement of the order (s)/ committee committee committee
awarding of work (s)
8.0 Engagement of the Data entry Full powers
operators, Technical and
Non-technical staff and Drivers
through outsourcing
9.0 Approval of billing breakups Full powers
10.0 Approval of short closure/ Full powers Full powers Full powers
cancellation/ reduction of face pertaining to pertaining to
value of the purchase order(s) / director level CE level and
agreement(s)/contract(s) committee lower level
committees
11.0 Adoption of orders issued by the Full powers
government towards revision of
minimum wages and VDA, etc.
ANNEXURE – II(A)
TENDER COMMITTEES
8. BOARD: The Chairman, the Managing Director and all Full Time and Non Whole Time
Directors
Note:
i) The proposals beyond the powers delegated to the SPC and having impact on policy
of the APGENCO shall be placed before the Board.
iii) The date and time of the Tender Committee Meeting shall be fixed by the competent
authority and in case if it is not held for any reason on that date, the same has to be
held within next two days with the requisite quorum of three Members.
ANNEXURE – II(B)
NEGOTIATION COMMITTEES
( ii ) The delegation shall effectively utilize the organizational structure for realization
of the purpose set out in (i) above.
( iii ) The delegation shall be commensurate with the responsib ilities and the status of
the executives to whom the delegation has been accorded.
( iv ) The delegates shall be accountable for their decisions under the delegation.
(v) The delegates shall be subject to such controls/instructions as are conveyed from
time to time to the delegates in general or in particular.
( vi ) As the delegation is meant for smooth execution of the work and expeditious
realization of corporate goals, any constraint or impediment in this direction shall
promptly be brought up the concerned and reviewed by the Competent Authority
to remedy the same.
( vii ) An interpretation placed on the delegation shall take into account the intent,
purpose and concept behind the delegation,viz, to execute the work in a manner
which is smooth(i.e. not causing any disturbance or dislocation in the course of
execution), effective (i.e cost effective, being the best possible alternate at least
possible cost) and expeditious (i.e ensure timely quickest possible realization of
the objective without any hindrance or impediment).
( viii ) The delegation is also based on the concept of centralized policymaking and
decentralized execution.
(x) The financial powers shall always be exercised with due observance of canons of
financial property, which are enumerated in the Annexure IV. Care may be taken
to ensure that awards are not split only for the purpose of bringing the same
within the powers of a particular Executive.
ANNEXURE-IV
( iv ) Public money should not be utilized for the benefit of a particular person or
section of the community, unless.