Академический Документы
Профессиональный Документы
Культура Документы
STATEMENT OF METHOD
140
DATE 21/10/2010
SIGNATURE
TABLE OF CONTENTS
1.0 Title
2.0 Methodology
2.1 General Description
2.2 Equipment
2.3 Materials
2.4 Preparation
2.5 Work & Methodology
5.0 References
6.0 Figures
7.0 Attachments
7.1 Heater Specifications
7.2 Thermocouple Specifications
7.3 Forms
1.0 TITLE
This document outlines the procedure for Thermal and Water Curing of PC Units
for Ma’aden Aluminum Smelter Plant Project in Jubail, Kingdom of Saudi Arabia. Bechtel
Overseas, Inc. is the Main Contractor and Al Kifah Precast Company is the sub-contractor
sub
forr manufacture and delivery of required Precast Concrete Units and responsible for
compliance with this procedure.
2.2 EQUIPMENT
List of Equipment:
Equipment
2.3 MATERIALS
No materials required.
2.4 PREPARATION
Prior application of heat for thermal curing, ensure that the concrete had
achieved the required initial setting time as per Bechtel Specification No. 25457-0000-
25457
0001 “Furnishing & Delivering Ready Mix Concrete” Sec. 3.3 – Initial Setting
3PS-DB01-0001
Time,, which should not be in any case less than 1 hour and as determined by the time
Concrete Compressive Strength achieved 3.4 MPa (500 psi).
1. After ensuring that the concrete has achieved the initial set, the heaters
are placed and arranged in such a way that all areas will be heated
uniformly (see Section 6.0, Fig. 1 & 2).
2. Rubberized Tarpaulin and Expanded Polystyrene to be installed in such a
way that the units are thoroughly covered and minimal heat escapes from
the contraption. Moisture is maintained using a cover of moist
burlap/hessian cloth. Double the thickness at corners and edges for a
distance of 300mm.
3. Cube Samples for Compressive Tests
Tests should be cured the same way as the
parent concrete.
4. Monitor the interior and surface temperature of the unit using embedded
B. Water Curing
4. Water used for curing must be the same water used for the production of
concrete.
5. Water is manually sprinkled until the hessian cloth and the precast unit is
thoroughly wet. Water curing will be considered satisfactory if at any time
the concrete
concr surface is damp to touch.
6. No curing compound should be used.
7. Water curing should be for seven (7) consecutive days.
8. Inspect curing minimum twice at daytime and once at night for signs of
drying. Replenish water as required.
9. If drying is discovered, re-wet
re wet and increase the inspection frequency.
3.2 RESPONSIBILITY
The following personnel are responsible for the conduct of this Operational
Procedure:
1. Frequency
Frequency of measurement within the unit must cover all units at
intervals specified in the Work Methodology.
2. Equipment
All measuring equipment must be thoroughly inspected prior to
use:
3. Records
The following Forms must be used on each specified Quality Control
Points:
KPC QA/QC Department copy is kept for minimum of two (2) years.
1. Hard Hat
H
2. Safety Shoes
3. Cotton Gloves
Not Applicable
Not Applicable
5.0 REFERENCES
Concrete Work”
Bechtel Specification No. 25457-0000-3PS-DB00-0001 “Concrete Work
Revision 000,
000 07 May 2010
Manual for Quality Control for Plants and Production of Structural Precast Concrete
“Manual
Products, 3rd Edition”
Edition PCI Manual MNL-116,
Precast/Prestressed Concrete Institute (PCI)
175 West Jackson Blvd., Chicago, Illinois 60604
6.0 FIGURES
HEATER
Fig. 1:: Heater and Mould Assembly
For Drain Channels (mayay be modified
as per actual conditions).. Note the
movement of air through direct
heater blower throw (10m) and
subsequent heat movement through
convection.
DIRECT HEAT
THROW
HEATED AIR
MOVEMENT
THROUGH
CONVECTION
(SAME AS ON
UPPER PORTION)
HEATER
DIRECT HEAT
HEATER THROW
BED HEATING
PIPES
Fig. 2:: Heater and Mould Assembly for Cover Slabs. Bed Heating Pipes are used to ensure uniform
heating and temperature controlled at the Boiler Room.
50
40
20
10
°C Initial Setting Time
0
Pre-Heat @ Sustained Cooling
Water Curing Stage (7 Days min.)
+27°C/hr Heating @ -28°C/hr
Fig. 3: Thermal Curing Temperature and Concrete Compressive Strength Relationship (Note: for
illustrative
llustrative purposes only; actual conditions may vary but must not exceed the limits set in this
document)
7.0 ATTACHMENTS
7.1 HEAT BLOWERS
8.0 FORMS
8.1 CONCRETE POUR CARD
8.2 POST-POUR
POUR INSPECTION REPORT
8.3 CALIBRATION OF EQUIPMENT
8.4 NC AND CAPA LOG SHEET