Вы находитесь на странице: 1из 2

PEKERJAAN TANAH PROYEK JALAN TOL CENGKARENG

STA 30 REST AREA


HARGA KONTRAK MODAL RAPP
No Pekerjaan VOLUME satuan H/SATUAN H/TOTAL %SUSUT H/CURAH NILAI SUSUT T/HARGA

PEMBERSIHAN TEMPAT KERJA


1 LAND CLEARING 57,768.48 M2 Rp 4,250.00 Rp 245,516,040.00

PEKERJAAN TIMBUNAN TANAH


2 GALIAN BIASA UNTUK TIMBUNAN 2,858.24 M3 Rp 22,525.00 Rp 64,381,856.00
3 GALIAN BIASA UNTUK DIBUANG 14,035.56 M3 Rp 34,000.00 Rp 477,209,040.00
4 BORROW MATERIAL 92,820.42 M3 Rp 115,000.00 Rp 10,674,348,300.00 30% Rp 72,000.00 Rp 21,600.00 Rp 6,683,091,840.00
5 URUGAN MATERIAL BERBUTIR ( GRANULAR BACK FILL ) 1,096.48 M3 Rp 225,250.00 Rp 246,982,120.00 30% Rp 145,000.00 Rp 43,500.00 Rp 159,033,100.00
6 URUGAN REMBESAN ( PERMEBLE BACK FILL ) 540.54 M3 Rp 233,750.00 Rp 126,351,225.00 30% Rp 155,000.00 Rp 46,500.00 Rp 83,830,200.00

PEKERJAAN GALIAN STRUKTUR DAN PEMBONGKARAN


7 PENGGALIAN STRUKTUR SAMPAI KEDALAMAN TIDAK LEBIH DARI 2 METER 12,395.46 M3 Rp 22,100.00 Rp 273,939,666.00
8 PENGGALIAN STRUKTUR SAMPAI KEDALAMAN LEBIH DARI 2 METER 994.84 M3 Rp 29,750.00 Rp 29,596,490.00

TIMBUNAN PILIHAN SEBAGAI LAPISAN PENAMPANG


9 LIMSTONE 19,250.00 M3 Rp 210,000.00 Rp 4,042,500,000.00 30% Rp 145,000.00 Rp 43,500.00 Rp 2,791,293,500.00

SUBGRADE
10 PERSIAPAN TANAH DASAR 57,768.48 M3 Rp 4,000.00 Rp 231,073,920.00

PEKERJAAN LAPIS PONDASI AGREGAT


11 BASE A 10,780.00 M2 Rp 258,000.00 Rp 2,781,240,000.00 15% Rp 152,000.00 Rp 22,800.00 Rp 1,638,582,800.00
12 BASE B 7,700.00 M2 Rp 242,000.00 Rp 1,863,400,000.00 15% Rp 142,000.00 Rp 21,300.00 Rp 1,093,421,300.00

A JUMLAH HARGA PAGU Rp 21,056,538,657.00 RAPP Rp 12,449,252,740.00


B PPN 10% Rp 2,105,653,865.70
C TOTAL KONTRAK SETELAH PPN Rp 23,162,192,522.70

1 PROFITE KOTOR Rp 8,607,285,917.00


2 PROFITE KOTOR

PROSENTASE PROFITE TERHADAP NILAI KONTRAK 41% Rp 8,633,180,849.37


POTONGAN POTONGAN

A ALAT BERAT C/W BBM & OPERATOR

1 ECSA / BEKO PC 200 2 UNIT 400 JAM Rp 291,600,000.00


2 DOSSER 1 UNIT 400 JAM Rp 145,800,000.00
3 VIBRO 1 UNIT 200 JAM Rp 95,910,000.00
4 DT LANSIR INDEX 24 4 UNIT 2 BLN Rp 408,800,000.00

SUB TOTAL A Rp 942,110,000.00

B OFFICE \ KOORDINASI \ RISK CUACA \ KEAMANAN

1 OFFICE ( BUGED WIKA ) 3 BLN 1 LOT Rp 71,000,000.00 Rp 213,000,000.00


2 KOORDINASI LINGKUNGAN 3 BLN 1 LOT Rp 30,000,000.00 Rp 90,000,000.00
3 KEAMANAN PROYEK 90 HARI 6 PERSON Rp 120,000.00 Rp 64,800,000.00
4 RISK CUACA 3 BLN 1 LOT Rp 75,000,000.00 Rp 225,000,000.00

SUB TOTAL B Rp 592,800,000.00

C PAJAK & FEE MARKET

1 DISCONTO SCF 4.7% Rp 989,657,316.88


2 FEE MARKET 3% Rp 631,696,159.71
3 PPH 2% Rp 421,130,773.14

SUB TOTAL C Rp 2,042,484,249.73

GRAND TOTAL Rp 3,577,394,249.73


FROFITE BERSIH Rp 5,029,891,667.27

BAGI HASIL

A PELAKSANA 20% Rp 1,005,978,333.45


B PEMODAL 80% Rp 4,023,913,333.82

ESTIMATOR AZIS TEAM

Вам также может понравиться