Background 6. Lack of understanding that geotechnics


In Indonesia, only top-class mining companies is a component in mining operational
have realized and implemented geotechnical safety.
modeling and supervision systems as part of 7. Insufficient understanding of the
their operations. Whereas, only a few of mid-low consequences of the risk of geotechnical
range companies who implement good hazards that can cause a greater cost
geotechnical practice in their mining. Most of loss if it has already occurred.
this occurred because of the lack of awareness
Effects of Ignoring Geotechnical Aspects
that geotechnical is one of the works, health &
Landslides in mines are actually a fairly common
environment safety component. On the other
occurrence, but if from the beginning the
hand, there are still many companies that are
companies have had complete geotechnical
more focused on their production compared to
investigations & data in a specific site, the
work safely in accordance with government
impact and risk of landslides to mining
regulations.
operations can be minimized. This can be started
Mid-low range companies will become aware of with a geotechnical investigation, followed by
the importance of geotechnics in mining making the specific geotechnical modeling,
operations when there has been a landslide or a designing the “right” geometry of the
failure in their mine pit that is detrimental to the excavation, to make a hazard area based on the
company's operations. What they do not know is consequences of failures.
that by investing in geotechnical aspects &
Some of the losses obtained when ignoring
investigations earlier, they can reduce risk from
geotechnics in mining operations are as follows:
the beginning.
1. Loss of life or disability.
These are some commonly used excuses by
2. Loss of income for workers.
mining companies in not doing investigation
3. Loss of employee confidence in
and monitoring works on geotechnical aspects
operational activities.
of mining:
4. Loss of company credibility.
1. The company is prioritizing production.
5. Safety & social factors.
2. Geotechnics is considered as law
6. Blocking operational activities.
enforcer which disrupts production.
7. Loss of resources / resources (ore, coal).
3. Maintaining a safe open pit slope
8. Loss of equipment & equipment.
stability is considered to make greater
9. Increase the stripping ratio due to
stripping ratio and smaller reserve
landslide material that must be cleaned.
recovery.
4. Geotechnical research takes a lot of time Mining Geotechnical Modeling
and costs money. Conducting geotechnical modeling from the
5. There are no funds to invest in software very beginning is a very good preventative step,
or man power for geotechnical work. and also indicates that the company is
concerned about good safety in mining

LENUSA CONSULTING by
PT. LERENG NUSANTARA KONSULTAN © 2019
Figure 1. Example of Landsides on Mining,
source: https://www.reddit.com/r/newzealand/duplicates/4jw6ei/massive_landslide_this_week_at_the_martha_mine/

practices. The making of geotechnical models factor and the level of confidence in the
can be adjusted in quantity by the area of the analysis made.
research site and budget, but for the quality of 4. Get a more detailed description of the
the data collected there should be no geotechnical conditions and
compromise. Some input data or basic characteristics at the site.
information needed to make a geotechnical
KEPMEN 1827 K/30/MEM 2018
model are:
In the past few years the Government of
1. Data of model geometry.
Indonesia has contributed to the curbing of
2. Data on subsurface geological
mining geotechnical data collection for all
information.
mining companies in Indonesia. In 2018, the
3. Material properties of rock/soil.
Ministry of Energy and Mineral Resources issued
4. Groundwater conditions.
Ministerial Decree 1827 K / 30 / MEM 2018, in
5. Additional data such as rainfall
which there was a new regulation that every
conditions, static and dynamic load
mining company must carry out geotechnical
conditions, etc.
data collection at least:
Some of the benefits that can be obtained from
1. Geometry modeling of mine slopes.
geotechnical modeling are:
2. Dynamic safety factor of open pit slope.
1. Inventory of existing geological data 3. Probability analysis.
information. 4. Recommended service life for mine
2. Cross check the complete data available slopes.
at the site. 5. The consequences of failures.
3. Get a more detailed description of the 6. Mine slope monitoring required.
completeness of the data, uncertainity

LENUSA CONSULTING by
PT. LERENG NUSANTARA KONSULTAN © 2019
Figure 2. Example of open pit slope modelling.
Source : GEOSLOPE Internasional Ltd.

With this new regulation, it is expected that all In conducting geotechnical modeling, qualified
mining companies in Indonesia will slowly begin human resources and sophisticated tools are
to apply the geotechnical aspects of mining in needed in carrying out the modeling. One tool
their operations.
that can be used is a software called GeoStudio
2019, which is able to help geotechnical
Conclusions
Geotechnical modeling in mining operations is engineers to do modeling easily. Whether or not
very important, because it is a component in the modeling that is made is influenced by
work safety and good mining practice. Many existing human resources, training and
mining companies in Indonesia still do not apply experience are needed enough to be able to do
the geotechnical aspects of mining in their geotechnical modeling correctly. LENUSA
mining activities, therefore the Ministry of Consulting is working with GEO-SLOPE
Energy and Mineral Resources issues KEPMEN International Ltd and EDP Media to hold a public
1827 K / 30 / MEM 2018 which contains the training entitled "International Geotechnical
obligation to collect geotechnical fields in every Modeling" which will be held on March 26-29,
mining operation. The hope is that all mining 2019 in Yogyakarta, Indonesia. In this training,
companies from small to large companies have participants will learn to do the stages of
begun to slowly realize how important mining geotechnical modeling using SLOPE / W, SEEP /
geotechnics are W and SIGMA / W.

LENUSA CONSULTING by
PT. LERENG NUSANTARA KONSULTAN © 2019
References
[1] Abramson LW, Lee TS, Sharma S, Boyce
GM (2002) Slope Stability and
Stabilization Methods. John Wiley &
Sons, New York, NY.
[2] Hawley Mark, Cunning John (2017)
Guidelines for Mine Waste Dump and
Stockpile Design. CSIRO Publishing,
Australia.
[3] Read John, Stacey Peter (2009) Guidelines
for Open Pit Slope Design. CSIRO
Publishing, Australia.
[4] GEO-SLOPE International Ltd (2018) Pit
Slope Design Using Multiple
Geometries. Canada

LENUSA CONSULTING by
PT. LERENG NUSANTARA KONSULTAN © 2019
LENUSA CONSULTING by
PT. LERENG NUSANTARA KONSULTAN © 2019

Вам также может понравиться