Академический Документы
Профессиональный Документы
Культура Документы
4
l
i u Initial repair; stub end screwed in.
1\11 t
>;5Wz ”
Y I
’;;::mW7///&7AQ/f,
I
ROTOR
[I.Mech.E., 19511
Mr. C. W. PRATT, B.Sc. (Eng.), M.I.Mech.E., said that a bad ,/ (EN. I4 STEEL)
type of tube failure had been prevalent during the last ten
years in highly-rated high-pressure boilers. In two samples of
tubes taken from a high-pressure boiler (Fig. 3, Plate l), one
showed internal corrosion and a crack which was filled with
copper. The copfler could be considered to be incidental. The
tubes’ insides were covered with calcium phosphate, and also
with some copper and a small quantity of iron oxide. The “scab”
itself was 100 per cent magnetic iron oxide. He believed that the
copper had been washed into the crack when the water escaped
from the tube. The other tube was bulged owing to overheating COPPER RING-
caused by the insulating effect of the scab. ;’THICK
Corrosion scab seemed to form in layers; it probably started
as a “pin-point” and gradually grew in area. A n illustration by
-
Hankinson and Baker (1945, Fig. 2)* showed a typical formation.
Fig. 4, Plate 2, showed two samples of tube which had been
acid-etched with hot hydrochloric acid to show the decarburized
areas of the tube which occurred directly under the scab.
u
The decarburized areas showed black. The material was about
0.13 per cent carbon, but drillings taken from the decarburized /’ I t4
‘KLINGERITE’ JOINT’
zone showed only 0.03 per cent carbon. Decarburization was
said to arise from the liberation of hydrogen which could occur
when water seeped through corrosion scab. As the metal of the
tube was hot, owing to the insulating effect of the scab the water
dissociated and liberated the hydrogen, which then diffused into Fig. 5. Form of Original Joint
the tube metal. The hydrogen combined with the carbide and
subsequently escaped, leaving the material devoid of carbon. In the new head the flange thickness of the forging was
Cracking which occurred in the decarburized areas (Fig. 4b, 7+ inches, whereas the original forged &nge thickness was
Plate 2) was said to result from the high pressure set up between 3 inches-the basic change which gave rise to joint leakage.
the grains, as a result of the formation of methane. Apparently Fig. 5 showed the spigot form of the original joint having a
the methane escaped when the g a i n s were forced apart. -1 .
,-inch thick copper ring.
In the opinion of many experienced observers embrittlement Off-load tests (“throwing” 30 megawatts off the machine)
could be avoided by the avoidance of feed water contamination, caused the joint to leak. The explanation of that leakage was
and particularly anything likely to cause a sludge, and certainly by that the flange cooled at a greater rate than the bolts and calm-
the complete elimination of oxygen. lations showed that the contraction of the flange due to the
temperature reduction was about 0.013 inch. The loading on
Discussion. A speaker asked for the range of pressure covered the bolts gave a stress of nearly 11 tons per sq. in. and the strain
by the troubles. He had experienced similar trouble due to scabs, on the bolts corresponding to that stress was about 0.006 inch.
in a boiler working at 600 lb. per sq. in., owing to minute traces With the bolts lagging behind in contraction, there was con-
of magnesium salts in the water, which had led to the formation sequently a loss of contact pressure at the joint.
of hydrochloric acid on the hot tube surfaces. One alternative (Fig. 6)which involved making contact beyond
Mr. Pratt replied that the troubles had been found mainly the bolt circle had been tried and had proved effective with
in boilers of 1,000 lb. per sq. in. working pressure and over. further off-load tests. Three other alternative joints had been
They had also, however, been found %I boilers working at lower considered but had not yet been tried, One comprised an
pressures-down to 500 lb. per sq. in. Apparently one of the assembly of Belleville washers to counteract the differential
factors was the tube metal temperature; that being dependent contraction, previously mentioned, by giving a strain of about
on the boiler pressure, the boiler rating, and the heat trans- 0.010 inch; another utilized a super-sealed packing of shredded
mission rate. The most important factor, however, was the metal which was caulked between each bolt and flange to
deposit inside the tube, so that if tubes were kept free of deposit, obtain, as far as possible, homogeneous conditions between the
even with high metal temperature associated with high-pressure bolt and the flange; the third involved an effort to return to the
boilers, avoidance of the trouble was probable. 3-inch bolt length as used in the original design of head.
In reply to a question regarding the desirability of maintaining Although this was really a simple case of stress and strain, it
su5cient residual sodium sulphite to ensure that oxygen would emphasized the necessity of taking into account strain as well as
not cause trouble, even at very high pressures, Mr. Pratt said stress in component assemblies.
that it was desirable, if possible, to have sulphite; general
experience indicated that it was possible to keep about 5 or 6 parts
per million in a boiler working up to about 1,500 lb. per sq. in., GENERAL F A I L U R E S
but in the 2,000 lb. per sq. in. pressure region it was not possible, Mr. F. W. SKELCHER, A.M.I.Mech.E., said that he would
so that it was necessary to improve de-aeration by other means. review his experiences of central power-station plant and some
HANKISON, L. E., and BAKER, M. D. 1945Trans. A.S.M.E,, vol. 67, incidents of other steam plant which had been brought to his
p. 317. “History of Potassium Boiler-water Treatment at Spnngdale”. notice.
r
had occurred probably owing to operational conditions. The
failure was thought to have been due to vibration produced by
rapid loading of the machine. Owing to an electrical disturbance
on the outside system approximately full load had been thrown
on to the machine within a few minutes of synchronizing. Two
of the wheels were completely stripped and the last row of
blading was badly damaged. Some of the diaphragms had turned
and locked the top and bottom halves of the machine, making
dismantling laborious. Practically all the condenser tubes were
cut, and turbine blades were twisted round the condenser stay
rods. The cylinders were undamaged, however, and the spindle
had been re-bladed, the machine re-lined and put into service.
(3) Thrust Failure. Thrust failure in ’a 12+-megawatt
machine, running at 3,000 r.p.m., steam conditions 250 Ib. per
sq. in., 650 deg. F., had resulted in the wheels and diaphragms
making rubbing contact. The wheels were dished, presumably
owing to heat generation.
Patches of fused metal and closure of the lifting holes were
noted on one of the wheels.
( 4 ) Failure of End Bells or Caps or Rings of Electrical Rotor.
I The machine concerned was a 12+-megawatt, two-cylinder
turbo-alternator, running at 3,000 r.p.m., with a steam pressure
I of 200 lb. per sq. in. It had been installed in 1928.
-I---- The rotor was a solid forging, the windings being retained in
slots by dove-tail keys. The end-bell locating disks, to which the
ventilating fan impellers were bolted, were mounted on the shaft
at each end of the rotor.
The rotor end-windings were retained by end bells or rings
hollow cylindrical steel forgings approximately 24 inches thick.
The end bells bore on the extremities of the rotor teeth at the
opposite end of the coned portion of the end disks.
Failure of the end cap had resulted in the end shields dis-
integrating and completely tearing away from the top securing
bolts. The end bell of the rotor had disintegrated and the rotor
end-turns had sheared off.
The alternator cast-pin bed-plate had fractured and the stator
dowel pins had sheared. The stator end windings had been
wrenched from their bracing rings and the insulation stripped.
(5) Boiler Drum Failure. A boiler drum had been scrapped
after sixteen years’ service owing to cracks in the butt straps and
shell plates. This was a fatigue failure.
The boiler operating conditions were: 220,000 Ib. per hr.;
420 Ib. per sq. in. working pressure; 760 deg. F.
Fig. 6. Alternative Joint
(6) Failure of Boiler Domncomer Pipe. The boiler concerned
( 1 ) Sheared Alternator Shaft. A 25-megawatt, twin-cylinder had a twin-grate stoker. The operating conditions were: 150,000
turbine, running at 3,000 r.p.m., had been installed in July 1931 Ib. per hr.; 710 Ib. per sq. in. working pressure.
and had broken down in February 1945. The machine had been The end of the front downcomer pipe, which was expanded
completely overhauled fifteen months prior to the accident. At into the furnace left-hand side water-wall bottom header, had
the time of the failure the machine was being overspeeded to been blown out of the header, .and boiler water had been
check the operation of the emergency governor, after having discharged at full-bore on to the firing floor of the boiler house.
been on load continuously for one week. Before the overspeed The explosion had been caused by constraint imposed on the
tripping value was reached, coupling failure occurred. downcomer pipe by the furnace-casing side plates. The clearance
Despite extensive damage, the high-pressure casing of the cut into the plates at the pipe hole had been insufficient to
turbine w2s intact, and also the centre of the low-pressure casing. permit the pipe to conform freely to the normal thermal move-
Both turbine rotors were free and had continued to run for ment of the header. The joint between the pipe and the header
some 10 minutes after the accident. The top half of the exhaust had been consequently subjected to abnormal stresses which had
casing on the alternator side was almost completely broken off, eventually loosened the expanded part and also the end of the
together with the bearing cradle. Other damaged parts were the pipe at the bell-mouthing, until the joint was unable to with-
bottom half of the exhaust casing, the turbine coupling star, the stand the working pressure of the boiler.
coupling sleeve embracing the coupling stars, and the alternator
coupling bush. ( 7 ) Wastage of Main Rear Supporting Beam An unusual
A thorough investigation, including physical tests, chemical failure of a main rear supporting beam had been caused by
tests, microphotographs, and macro- and sulphur-prints, had oxidization from the combustion chamber side. The boiler
been made. operating conditions were: 220,000 Ib. per hr.; 420 lb. per sq.
The general conclusion was that the first cause of failure could in. j 750 deg. F.