Академический Документы
Профессиональный Документы
Культура Документы
net/publication/267765195
CITATION READS
1 1,273
1 author:
Amund Bruland
Norwegian University of Science and Technology
63 PUBLICATIONS 728 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Amund Bruland on 05 November 2014.
Amund Bruland
Vol. 2 of 10
NTNU Trondheim
Norwegian University of
Science and Technology
Doctoral thesis
for the degree of doktor ingeniør
Faculty of Engineering Science
and Technology
Department of Civil and
Transport Engineering
PREFACE 1
0 GENERAL 3
1 TUNNEL DESIGN 6
2 RIGGING 22
2.0 Introduction 22
2.4 Water 28
3 TRANSPORT 30
3.0 Introduction 30
4 VENTILATION 52
4.0 Introduction 52
5.0 Introduction 68
APPENDICES 79
A. Previous Editions 79
B. Research Partners 80
C. List of Parameters 81
D. Estimation Forms 84
PREFACE
The report is one of six reports about hard rock tunnel boring:
Combined with the other reports in the Project Report Series from the Department of
Building and Construction Engineering at NTNU, the reports present an updated and
systematised material on rock excavation and tunnelling to be used for:
•= Economic dimensioning
•= Choice of alternative
•= Time planning
•= Cost estimates, tender, budgeting and cost control
•= Choice of excavation method and equipment.
A list of available Project Reports may be requested from the Department of Building
and Construction Engineering at NTNU.
The advance rate, cutter wear and excavation cost models also exist as a WINDOWS
programme.
The report is prepared by Amund Bruland and is part of his dr.ing thesis about
hard rock tunnel boring.
1
PREFACE
The reports listed above describe a comprehensive model developed at NTNU. The
model covers the complete tunnel boring process from the early planning stage
through preinvestigations, time and cost estimates, tunnel excavation and finally
acquisition and treatment of experience data. The models and data presented in the
reports are meant to be a practical tool for owners, consultants and contractors,
more than a theoretical analysis of the tunnel boring process.
The project has been granted financial support by our external research partners, see
list in Appendix.
Odd Johannessen
Professor
2
0. GENERAL 0.1 Project Reports about Hard Rock Tunnel Boring
1A-98
The report presents information and data for cross section design of various tunnel
types. Options and limitations of curve radius, tunnel length, tunnel inclination,
rock support, etc. are presented. Estimation models for transport capacity and ven-
tilation requirements are given.
Project Report 1A-98 is partly based on the project reports 1-76, 1-79, 1-83, 1-88 and
1-94, all published by the Department of Building and Construction Engineering at
NTNU. The report presents updated and revised information from the previous re-
ports as well as experience data from recent tunnelling projects.
Other Reports
The Project Report 1B-98 HARD ROCK TUNNEL BORING Advance Rate and
Cutter Wear provides methods and necessary data for estimation of time consump-
tion and cutter wear for tunnel boring. Geological parameters and machine factors of
significance for the penetration rate and the cutter wear are presented briefly.
The Project Report 1C-98 HARD ROCK TUNNEL BORING Costs presents
models and data for estimation of tunnel excavation costs and total construction costs.
The Project Report 1D-98 HARD ROCK TUNNEL BORING Geology and Pre-
investigations treats the rock mass parameters of the model in more detail. Preinves-
tigations and building of an engineering geological model adapted to the estimation
models for penetration rate and excavation costs are treated closely.
3
0. GENERAL 0.1 Project Reports about Hard Rock Tunnel Boring
The Project Report 1E-98 HARD ROCK TUNNEL BORING Performance Data
and Back-mapping covers follow-up procedures and collecting of performance data
from tunnel boring projects. Engineering geological back-mapping is treated in detail.
Project Report 1F-98 HARD ROCK TUNNEL BORING The Boring Process
covers rock breaking and chipping, machine factors affecting performance, boring in
fractured rock mass, and various types of cutter wear.
The estimation models are aimed at being used through several stages in a project:
The estimation models for Hard Rock Tunnel Boring should be used with care. Com-
bined with other estimation models in the Project Report Series from the Department
of Building and Construction Engineering, the Hard Rock Tunnel Boring reports pro-
vide a reliable and practical tool to be used for:
4
0. GENERAL 0.1 Project Reports about Hard Rock Tunnel Boring
Background
The estimation models are based on job site studies and statistics from tunnelling in
Norway and abroad, including more than 35 job sites and more than 250 km of tunnel.
The data have been systematised and normalised. The results are regarded as being
representative for well organised tunnelling.
A more detailed treatment of the background and the basis for the Hard Rock Tunnel
Boring estimation models is found in HARD ROCK TUNNEL BORING Back-
ground and Discussion.
5
1. TUNNEL DESIGN 1.1 Tunnel Boring Vs Drill and Blast Tunnelling
Planning and design of a tunnel system should at a very early stage evaluate the tun-
nel excavation method. A standard design approach is to plan the tunnel system for
drill and blast as the excavation method, all through to the bidding phase. This ap-
proach may exclude the most cost saving features of the tunnel boring method com-
pared to drill and blast excavation, e.g.:
When comparing drill and blast tunnelling to tunnel boring, the comparison must take
into account the total time consumption and the total costs, as well as topics like envi-
ronmental impact and third-party relations.
In addition to the direct tunnel excavation costs, the total costs include items like:
•= Rock support
•= Construction and operation of roads, communications, power supply, etc.
•= Labour housing
•= Auxiliary plants
•= Share of general costs
•= Interest during the construction period
See also the example in Project Report 2C-95 TUNNELLING Costs for Drill and
Blast.
Most of the items vary with the tunnelling method, either because of the method itself
(rock support) or because of different time consumption (operation of all auxiliary
functions, interest during the construction period).
Tunnels may be longer for tunnel boring than for drill and blast tunnelling, due to
increased advance rates and reduced ventilation requirements. This may facilitate a
more favourable tunnel system layout, e.g. with fewer adits.
6
1. TUNNEL DESIGN 1.1 Tunnel Boring Vs Drill and Blast Tunnelling
For geological reasons, it may be advantageous to choose a different route for a bored
tunnel than for a drill and blast tunnel.
It is highly important that tunnel boring is evaluated at an early phase in the planning
process to ensure full benefit of the possible advantages by the use of the method.
7
1. TUNNEL DESIGN 1.2 Tunnel Geometry
Tunnel boring gives a circular cross section with a smooth surface. TBMs with a
diameter from approximately 2 m to 12 m (3 m2 to 113 m2) have been developed for
boring in hard rock. New machines may be built to comply with any diameter
specification between 2 m and 12 m, or even larger.
When specifying the machine diameter, one must consider that the wear of the gage
cutters may reduce the tunnel diameter by as much as 40 mm from new cutters to
worn cutters (applicable for a cutter diameter of 483 mm).
Tunnel Gradient
Tunnel boring machines can be built for boring at virtually all tunnel gradients. The
gradient is limited by the muck transport system, which may be
•= Rail-bound transport
•= Truck transport
•= Conveyor belt transport
Truck transport is feasible for diameters larger than approximately 8 m if one wants to
avoid turning niches. A turning table may accommodate turning of the trucks. The
practical gradient limit is then ± 15 %, presupposing a roadway pavement of high
quality. Truck transport requires a minimum gradient of 0.25 % for good drainage.
8
1. TUNNEL DESIGN 1.2 Tunnel Geometry
A continuous conveyor belt is feasible for tunnel diameters larger than approximately
3 m. A standard conveyor belt may be used for tunnel gradients as steep as ± 20 %.
Since use of a conveyor belt must be combined with a different transport system for
personnel, cutters, etc., the tunnel gradient is limited by the auxiliary transport
method.
Shafts may be bored with an inclination from 25° to vertical. Scraping or flushing of
muck facilitates boring at even lower inclination.
Curve Radius
The minimum curve radius for tunnel boring depends on both the TBM and the
backup. Tunnel boring machines have a minimum curve radius of 40 - 80 m when
boring (without boring it is 15 - 25 m).
The backup, i.e. the conveyor belt, determines the minimum curve radius. When using
a long backup (track-bound transport), the minimum curve radius is 250 - 450 m. Use
of a continuous conveyor for muck transport may increase the necessary curve radius
even more. The possible conflict between the backup and installed rock support also
affects the minimum curve radius.
Tunnel Length
The tunnel length that may be bored from one end is very long. The limiting factors
are:
9
1. TUNNEL DESIGN 1.2 Tunnel Geometry
Using the estimation models presented in the Project Report 17-91 TUNNELLING
Ventilation, a TBM of 3.5 m diameter may bore more than 25 km of tunnel from one
end. The basic assumptions are track-bound transport, tunnel gradient of 0.2 %, and
net penetration rate of 6 m/h. In general, the technical feasible tunnel length to be
bored from one end increases with the tunnel diameter. Use of a continuous conveyor
for muck transport will increase the possible tunnel length even more.
Hence, the total construction time and costs will be the decisive factors of the feasible
tunnel length to be bored from one end.
10
1. TUNNEL DESIGN 1.3 Water Tunnels
Loss of head in a bored tunnel is smaller than in a blasted tunnel with the same cross
section area because of the circular, smooth profile.
Figure 1.1 shows the relation between the cross section area of a blasted and a bored
tunnel with the same capacity (hydraulic equivalent cross section areas). The curves
are calculated on the basis of the assumptions shown in Table 1.1.
2 2 2
Cross Section Area 8m 20 m 50 m
Absolute roughness, mm - - -
Manning's Number 32.8 33.9 34.6
The marginal cost for bored tunnels increases with increasing cross section area,
whereas it decreases for drill and blast tunnels. Furthermore, the marginal cost for
bored tunnels is strongly dependent on the rock mass boreability. For economic
optimisation of the cross section area, a different relation between the blasted and the
bored cross section area than those shown in Figure 1.1 will most likely be obtained.
Such estimations must be carried out for each individual project.
The relation between the economic optimal cross section area for a specific project is
shown in Figure 1.2. The example is from the Project Report 6-81 PEAK POWER
AT RØSSÅGA The Tunnel System (Norwegian edition).
11
1. TUNNEL DESIGN 1.3 Water Tunnels
9
dtbm Schistose rock
m
8
Homogenous rock
7
6 1.8
5 Adb/Atbm
4 1.7
3
Homogenous rock
2 1.6
1 Schistose rock
1.5
20 40 60 80 100
Figure 1.1 Equivalent cross section area. Lower: Relation between blasted and
bored tunnels. Upper: TBM diameter of equivalent cross section area.
12
1. TUNNEL DESIGN 1.3 Water Tunnels
DRI=49
Adb/Atbm
1.8
DRI=65
1.6
DRI=49
DRI=56
DRI=65
1.4
10 20 30 40 50 60
Figure 1.2 Relation between economic optimal cross section area for tunnel boring
and drill and blast tunnelling. Example from Bleikvatn Hydro Power
Project 1981.
13
1. TUNNEL DESIGN 1.4 Sewage Tunnels
In bored tunnels, it is usually not necessary to concrete such a channel, because the
circular cross section is sufficiently self-cleaning when bored with accurate control of
the inclination. The TBM may be controlled and steered to achieve a maximum
deviation from the vertical alignment of a few centimetres.
14
1. TUNNEL DESIGN 1.5 Road and Railway Tunnels
The circular cross section is not optimal for road tunnels. Due to the required traffic
area and free clearance, the cross section area will be unnecessarily large if bored, see
Figure 1.4.
Cross section conditions for railway tunnels are similar to those for road tunnels, but
the cross section area may often be better utilised. Figure 1.5 shows relevant tunnel
profiles for single-track railroad tunnels, electric traction.
The cross section area will be better utilised if the lower part of the tunnel is enlarged
by blasting or other stoping methods, see Figure 1.4. However, the blasting will
introduce an undesired operation concerning time consumption and occupational
environment during the excavation.
Presumably, the best solution is to take advantage of the circular bored profile and the
more or less continuous excavation process. The circular profile is advantageous
concerning:
•= Better stability and less rock support than a corresponding drill and blast tunnel
•= Lighter and cheaper rock support methods than for a drill and blast tunnel
•= More systematic and mechanised installation of water and frost protection,
lighting, ventilation, communications, etc.
When using a continuous conveyor for muck transport, the tunnel behind the TBM
and backup is available to carry out the following operations while boring:
Road tunnels are discussed in more detail in the Project Report 8-88 ROAD
TUNNELS Drill and Blast or Tunnel Boring and the Project Report 2E-95
TUNNELLING Road Tunnels - Equipment and Installations (Norwegian editions
only).
15
1. TUNNEL DESIGN 1.5 Road and Railway Tunnels
Figure 1.5 Cross sections for railway tunnels. Minimum diameter for the bored
cross section is approximately 8.5 m.
16
1. TUNNEL DESIGN 1.6 Examples of Innovative Application
In the early 1980s several studies were done looking into the possibilities of using
tunnels from the shore to the oil and gas fields off the Norwegian coast. The Project
Report 2-81 TUNNELLING FOR THE OFFSHORE OIL FIELDS (Norwegian edi-
tion) presented the basic design solutions and models for estimation of time consump-
tion and total construction costs.
The design allows very long tunnels to be bored from one end. The only limiting fac-
tor is the construction time. The principle design for a 50 km long tunnel is shown in
Figure 1.6.
Gneiss Sediments
5.6k
m
1:8 18.0km 26.4km
6.5km 5.0km 5.0km 7.9km
D&B TBM
23m2 Fresh air supply dtbm=3.5m
45m2 dtbm=4.5m
Transport
Base station with crossover tunnels
Figure 1.6 Proposed design for a tunnel to an offshore oil and gas field.
17
1. TUNNEL DESIGN 1.6 Examples of Innovative Application
In 1994 a feasibility study of a deep tunnel for transport and storage of natural gas
between two onshore gas terminals and processing plants were conducted.
The total tunnel length was just above 375 km, at a depth of 1000 m below the sea
level. The rock is mostly Precambrian gneisses with low boreability, with an expected
net penetration rate of around 4 m/h. Due to the limitations in construction time, the
basic design was vertical shafts at approximately 50 km spacing, resulting in the need
of 9 shafts and 16 TBMs. The construction time was estimated at 3.5 years.
The study did not conclude with regard to the muck transport method for the tunnels
and shafts. The time and cost estimates were based on track-bound transport in the
tunnels and hoisting in the shafts. However, a combination of a continuous conveyor
in the tunnel and slurry pumping in the shaft seemed very promising.
18
1. TUNNEL DESIGN 1.6 Examples of Innovative Application
Vertical shaft
TBM startup Drill and blast 70m2 dtbm=3.5m Vertical shaft
area dtbm=3.5m
Figure 1.8 Arrangement at the bottom of each shaft of the proposed gas tunnel.
The planning of the tunnel system at Trollberget, a part of the Svartisen Hydropower
Project, started in the early 1970s. At that time, Norway had no experience with TBM
tunnelling, and the tunnel system was planned for drill and blast. Tunnel boring was
employed at several projects in Norway until the late 1980s when the final design of
the tunnel system at Trollberget was done.
Through several phases, the plans were adapted to TBM tunnelling as the know-how
and experience of TBM tunnelling increased, resulting in a tailor-made TBM project
of approximately 40 km of tunnel being bored from one adit by 4 TBMs.
The number of adits was reduced from 5 to 1, avoiding extensive environmental and
landscape impacts such as building of roads, power lines and other communications in
a barren and vulnerable region, close to the Svartisen glacier. All service functions
and housing of workers could be placed at Trollberget, ensuring safe and undisturbed
transport of people and equipment to and from the site.
19
1. TUNNEL DESIGN 1.6 Examples of Innovative Application
Vegdalen
Chainage 12537
TBM 220
3.5m diameter
Storglomvatn
Chainage 13630 Chainage 5766
Rebuild of TBM 251
TBM 251
5.0m diameter
Adit
Trollberget TBM 257
1000m 3.5m diameter
Chainage 4034
TBM 252
4.3m diameter
Bogvasselv
Chainage 12218
Figure 1.9 The tunnel system at Trollberget. Courtesy of Statkraft Anlegg AS.
20
1. TUNNEL DESIGN 1.6 Examples of Innovative Application
Start boring
Assembly
area
22 Workshop
5m
Warehouse
Drainage and
ventilation
shaft
Dump station
and muck silo
3 draw points
Adit
21
2. RIGGING 2.0 Introduction
2.0 INTRODUCTION
The chapter gives a brief treatment of rigging and auxiliary installations that provide
the necessary service functions to achieve high productivity in the tunnel excavation.
When designing the rig area and the support functions, one should try to incorporate
the following aspects in the plans:
Each project has its own features, and the items above do not cover all situations.
Muck transport and ventilation are treated in Chapter 3 and Chapter 4 respectively.
For long tunnels, it is very important that the design criteria and assumptions are valid
when the tunnel excavation is in progress. One should do systematic measurements
and tests of e.g. the ventilation system and the transport system as the excavation pro-
gresses, to confirm that the systems will be capable to serve their functions through-
out the tunnel length.
22
2. RIGGING 2.1 Dump Station
Track-Bound Transport
•= Bottom dump
•= Side dump
•= Rotational dump (e.g. Rotadump and forklift).
Bottom and side dump systems have proved to be very efficient with regard to time
consumption and necessary number of muck-car trains (see Table 3.1).
Selection of location and type of dump station should at least be based on the follow-
ing aspects:
In some cases, the dump station may be located at a muck disposal site close to the
tunnel, facilitating the use of a wheel or LHD loader to place and compact the muck.
But in most cases, the distance between the tunnel and the muck disposal site requires
truck transport of the muck.
If possible, one should avoid reloading the muck with a wheel loader onto the trucks
for transport to the permanent muck disposal site. A silo system with draw points at
the bottom is an economically favourable solution even for shorter tunnels. The silo
system provides buffer capacity and may be adapted to all dumping methods. Figure
2.1 shows a possible layout of an underground silo system.
23
2. RIGGING 2.1 Dump Station
Figure 2.1 Layout of an underground silo system for bottom dump muck-cars.
An underground silo system gives a high degree of freedom with regard to the design
of the adit and the start-up area.
For the same reason as above, one must avoid water flowing into the muck silo.
Drainage water from the tunnel should be conveyed carefully past the silo. Ground-
water inflow to the silo should be sealed by pregrouting.
Truck Transport
Using truck transport in the tunnel should imply direct transport to the muck disposal
site. Public roads have regulations with regard to truck size and weight, which may
require reloading of the muck at the tunnel site before entering the public road sys-
tem. Reloading the muck may be done similar to that of track-bound transport.
24
2. RIGGING 2.1 Dump Station
Continuous Conveyor
In principle, a continuous conveyor in the tunnel should include a conveyor belt sys-
tem for muck transport all the way to the muck disposal site. When this is not appli-
cable, the reloading of the muck should be handled similar to that of track-bound
transport.
25
2. RIGGING 2.2 Muck Disposal Site
The design and the filling plan of the disposal site should be available when the muck
transport system is selected. The filling plan must ensure compaction, slope stability
and erosion protection.
The TBM muck may be described as a well-graded material with larger prismatic and
flaky chips.
Older Machines
80
Standard Machines
60
40
20
HP Machines
Grain size d, mm
The muck must be compacted during placement of the fill to avoid large settlements
later. If the muck is placed in layers of 1.5 - 2 m, the trucks or the wheel loader driv-
ing on top of the layer may be able to compact the muck to a volume expansion factor
of 1.55 - 1.6 from in situ rock to fill volume. The compaction is best achieved by a
predetermined driving pattern when the muck is placed in the fill.
The final surface of the muck fill should have a maximum slope of 1 : 3. Furthermore,
the fill must be protected by a drainage system along the perimeter and at the surface
of the fill to avoid erosion from precipitation.
For more information on use and disposal of TBM muck, see the Project Report
16-91 TBM MUCK Properties and Use (Norwegian edition).
26
2. RIGGING 2.3 Electricity Supply
The cutterhead rotation during boring is by far the most power consuming operation
in the tunnel excavation process. Installed cutterhead power as a function of TBM
diameter and cutter diameter is shown in Figure 2.3.
Ptbm dc=483mm
kW
3000
dc=432mm
2000
dc=394mm
1000 dc=356mm
TBM diameter, m
Additional power consumption at the TBM and backup normally adds up to less than
10 % of the installed cutterhead power. The capacity of the power supply (transform-
ers and cable) into the tunnel should be at least 20 % higher than the installed cutter-
head power to ensure stability in the supply system.
At the adit, the required power supply to the ventilation fan(s), water supply pumps,
continuous conveyor, etc. normally adds up to less than 30 % of the installed cutter-
head power. Hence, the capacity of the power supply to the adit should be at least 1.5
times the installed cutterhead power.
27
2. RIGGING 2.4 Water
2.4 WATER
Water Supply
The water is needed for spraying, cooling and cleaning, and should in principle be
clean freshwater. The water supply capacity must be dimensioned with regard to the
instantaneous consumption, see Figure 2.4.
l/min
600
500
4 5 6 7 8 9
TBM diameter, m
The water pipeline should be designed for an internal pressure of 20 - 25 bar and the
water pumps should deliver a pressure of at least 10 - 15 bar for a horizontal tunnel.
Drainage Water
When the tunnel has an incline of 0.15 % or more, the drainage water will flow easily
by gravity in normal rock conditions. If high water inflow is expected, the tunnel in-
clination should be 0.25 % or more. At low inclination, it is necessary to pump the
drainage water from the cutterhead and TBM area to the outer end of the backup.
28
2. RIGGING 2.4 Water
The drainage water contains suspended fines from the TBM muck and oil from the
hydraulic and lubrication system. The drainage water should be treated in sedimenta-
tion and oil separation basins before it is discharged.
The amount of fines in the drainage water is best reduced by keeping the bucket lips
on the cutterhead in a good condition.
29
3. TRANSPORT 3.0 Introduction
3.0 INTRODUCTION
The trend towards machines with higher maximum gross thrust resulting in higher net
penetration rate sets greater demands to the performance of the transport equipment
and the transport system.
The aim of this chapter is to design the transport system to achieve continuous boring
that is not disturbed by insufficient transport capacity.
Capacity estimation models for track-bound transport and for transport with trucks are
presented. The models estimate the necessary number of transport units, i.e. muck-car
trains or trucks, to be able to continuously transport a muck volume corresponding to
a predetermined dimensioning net penetration rate. A brief treatment of conveyor belt
capacity is also given.
The decisive dimensioning parameter of the transport system is the dimensioning net
penetration rate. The estimated net penetration rate (see Project Report 1B-98
HARD ROCK TUNNEL BORING Advance Rate and Cutter Wear) should be
interpreted as a dimensioning average for longer tunnel sections, to be used for the
estimation of time consumption and excavation costs. The dimensioning net penetra-
tion rate for the transport capacity should be at least 50 % higher than the estimated
net penetration rate.
30
3. TRANSPORT 3.1 Track-Bound Transport
Tracks
Track transport operations must therefore be planned carefully. The backup, muck
cars, locomotives, shunting and dumping arrangements, tracks and the system for
installing tracks, must be rational and functional.
Installation of the track takes place in the area between the TBM and the backup. A
crane mounted on a monorail system under the bridge conveyor is used.
•= Pre-made track sections with steel sleepers and special blocks of wood or steel
as support
•= Single rails mounted on wood or steel sleepers
•= Single rails bolted to the invert with special fastening brackets (suitable in hard
rock only, bolts are prone to loosen in medium to soft rock).
•= Rails mounted on concrete segments.
Choice of track must be adapted to the backup equipment and the transport volumes.
Experience shows that pre-made track sections with steel sleepers as shown in Figure
3.1 will give a good track for high transport capacity.
The track gauge should be at least 900 mm. The rail weight should be at least 35
kg/m.
•= Blasted niches
•= Build-up of invert to sufficient bypass width
•= California Switch - a movable bypass station running on the permanent track.
31
3. TRANSPORT 3.1 Track-Bound Transport
Steel sleeper
Steel sleeper
Estimation Model
The model is based on muck transport from a double-track backup with a minimum of
2 muck-car sets and 1 locomotive. The transport capacity for a TBM with a single-
track backup and a California Switch directly behind the backup may also be
estimated by the model.
The model designs the loading and transport capacity so that continuous TBM
production can be obtained. In other words, the cycle time for one train must be less
than the loading time at the backup for one set of muck-cars.
32
3. TRANSPORT 3.1 Track-Bound Transport
Loading time
Normally, a muck-car set with a capacity corresponding to the muck production from
at least one TBM stroke is chosen.
l s ⋅ 60
t stroke = (min) [3.2]
In
When a muck-car set is fully loaded, it must be changed with an empty set in the
backup. This causes a time loss on a backup where loading can not be carried out
during changing of sets. Time for changing of sets is observed as tset ≤ 1 minute.
When the set has a capacity of 1 or 2 strokes, the changing of sets can take place
during the regripping of the TBM. As a rule, the regripping time exceeds the set
changing time, so that changing of sets will not be a part of the loading time.
The regrip time depends on the TBM's hydraulic system. Boring in curves, alignment
requirements, etc. will influence the regrip time. The observed average is tregrip = 4.5
minutes.
33
3. TRANSPORT 3.1 Track-Bound Transport
Vcar ⋅ n set
V set = (sm 3 ) [3.3]
k swell
2
d tbm ⋅ π ⋅ ls
V stroke = (sm 3 ) [3.4]
4
The actual number of TBM boring strokes per muck-car set is:
V set
k set = [3.5]
Vstroke
34
3. TRANSPORT 3.1 Track-Bound Transport
The cycle time is defined as the time it takes to drive a fully loaded muck-car set from
the backup and return with an empty set to the backup, see Figure 3.2.
TBM
Backup Equipment
tloco
t100
tout = tin
tdump
tadit tshunt
Adit
Dump Station
Figure 3.2 Transport model without bypass, 2 muck-car sets and 1 locomotive.
t cycle = t100 + t out + t adit + t shunt + t dump + t shunt + t adit + t in + t100 + t loco
[3.7]
= 2 ⋅ ( t100 + t out + t adit + t shunt ) + t dump + t loco (min)
35
3. TRANSPORT 3.1 Track-Bound Transport
tadit = driving in the adit and from the adit to the dump station
tshunt = shunting at the dump station before dumping
= shunting at the dump station after dumping
tdump = discharging the muck-cars
tloco = shunting of the locomotive at the backup
(l back − 100) ⋅ 60
t out = t in = (min) [3.9]
v out ⋅ 1000
(l adit + l dump ) ⋅ 60
t adit = (min) [3.10]
v adit ⋅ 1000
When the cycle time exceeds the loading time, bypasses in the tunnel and extra muck-
car sets and locomotives are needed. The transport system is shown in principle in
Figure 3.3.
36
3. TRANSPORT 3.1 Track-Bound Transport
It is assumed that the cycle time of each cycle (outer, middle, inner) must be less or
equal to the loading time to obtain continuous TBM production. Optimal locations of
the bypasses are found when:
TBM
A new bypass is installed when the time for the inner cycle is larger than the loading
time. The demand for locomotives is then:
37
3. TRANSPORT 3.1 Track-Bound Transport
A model for transport with 1 bypass, 3 muck-car sets and 2 locomotives is shown in
Figure 3.4.
TBM
tloco
t100
tinner
tout-i=tin-i Inner loop
tbypass
tadit tshunt
tdump
touter
Adit
Dump Station
Figure 3.4 Transport model for 1 bypass, 3 muck-car sets and 2 locomotives.
Since the bypass is located as far into the tunnel as possible, without the time of the
outer cycle exceeding the loading time, the cycle time will be defined by the outer
cycle.
38
3. TRANSPORT 3.1 Track-Bound Transport
tbypass = time for meeting at and driving past the bypass (the outbound train waits
for the inbound train)
tout-o = driving from the bypass to the adit
In addition, the time for the inner cycle must not exceed the loading time.
If the time for the inner cycle exceeds the loading time, another bypass is needed.
To avoid later moving, the first bypass should be placed at an optimal point found by:
l bypass ⋅ 60
t out −o = (min) [3.18]
v out ⋅ 1000
lbypass = distance between the adit and the first bypass (m)
39
3. TRANSPORT 3.1 Track-Bound Transport
When more than one bypass is necessary, the optimal placement is found by:
(l bypass − 2 − l bypass −1 ) ⋅ 60
t out − m = (min) [3.22]
v out ⋅ 1000
The transport speed and unit times vary with the type of locomotive, backup and
dump system. It is therefore important to carry out time studies of the transport
system to obtain an optimal use of the transport equipment. Table 3.1 lists some
average values for tunnel inclination of 0.15 - 0.4 %.
Figure 3.5 illustrates the need for bypass installation as a function of the tunnel length
and the net penetration rate. The estimations are based on the following assumptions:
40
3. TRANSPORT 3.1 Track-Bound Transport
In, m/h
6.0
5.0 3 California
Switches
4.0 2 California
Switches
3.0
1 California
Switch
2.0
No meeting
1.0
2 4 6 8 10 12 14 16 18 20
Tunnel length, km
Figure 3.5 Demand for bypasses for 35 kg/m rails and 22 ton locomotives.
41
3. TRANSPORT 3.2 Truck Transport
For tunnel diameters less than approximately 8 m, bypasses must be established by:
•= Excavating niches
•= Filling up the invert until the required width is established.
Figure 3.6 Roadway. Sorted muck may be used if the rock quality is suitable.
The bypasses may also be utilised as a turning place before the dump trucks backs
into the backup. For tunnel diameter larger than 8 m, the trucks may be turned by a
turning table, see Figure 3.7.
42
3. TRANSPORT 3.2 Truck Transport
Estimation Model
The transport capacity depends on the number of trucks, cycle time and volume per
truck. To maintain continuous boring, the transport capacity must exceed the muck
volume to be transported at the dimensioning net penetration rate.
The cycle time is defined as the time it takes to drive a fully loaded truck from the
backup hopper to the dumping station, dumping, return to the backup and load the
truck.
t cycle = t to + t meet + t in + t turn + t man + t load + t man + t out + t to + t dump (min) [3.26]
tto = driving from the dump station to the tunnel portal and vice versa
tmeet = meeting in the tunnel
tin = driving from the tunnel portal to the turning point, including the adit
tturn = turning the truck in the tunnel
tman = backing from the turning point to the backup loading point
= driving from the backup loading point to the turning point
tload = loading the truck at the backup
tout = driving from the turning table to the tunnel portal, including the adit
tdump = turning the truck and dumping the load
The time for driving from the dump station to the tunnel portal is:
l dump ⋅ 60
t to = (min) [3.27]
v to ⋅ 1000
ldump = distance from the dump station to the tunnel portal (m)
vto = average speed for the distance ldump (km/h)
When the trucks meet in the tunnel, the empty truck driving in has to wait. Maximum
total meeting time is:
44
3. TRANSPORT 3.2 Truck Transport
tm = unit time for one meeting of one in-bound and one out-bound truck
ntruck = total number of trucks in the transport system
TBM
tload
2 tman
tturn
tout = tin
tmeet
tdump
2 tto
Dump Station
Time for driving from the tunnel portal to the turning table is:
l turn ⋅ 60
t in = (min) [3.29]
v in ⋅ 1000
lturn = distance from the tunnel portal to the turning point, including adit (m)
vin = average speed of the in-bound empty trucks (km/h)
45
3. TRANSPORT 3.2 Truck Transport
Normally, a turning table is placed 50 – 100 m behind the backup. The empty truck is
turned at the table, backs from the table to the backup silo, loads and drives outwards
and past the turning table.
Driving time from the turning point to the tunnel portal is:
l turn ⋅ 60
t out = (min) [3.30]
v out ⋅ 1000
The transport speed and unit times vary with the type of truck, backup and dump
system. It is therefore important to carry out time studies of the transport system to
obtain an optimal use of the transport equipment. Table 3.2 lists some average values
for tunnel inclination of 0.25 - 4 %.
Table 3.2 Transport speed and unit time for truck transport.
46
3. TRANSPORT 3.2 Truck Transport
Transport Volume
The roadway may be built by using some of the muck from the TBM (preferably
sorted muck, using the largest fraction for the roadway). Later, this muck must be
removed, and therefore as little muck as possible should be used for the roadway
construction. The recommended thickness of the roadway is hroad = 0.9 m due to
drainage pipes placed on the invert of the tunnel (see Figures 3.9 and 3.10).
The production volume from the TBM depends on the TBM diameter and the net
penetration rate.
2
d tbm ⋅π ⋅ In
Qtbm = (sm 3 / h ) [3.32]
4
The muck volume used for the roadway depends on the cross section area of the road
and the net penetration rate.
Aroad ⋅ I n
Qroad = (sm 3 / h ) [3.33]
k road
Aroad = cross section area of the roadway, see Figure 3.9 (m2)
kroad = swell factor from solid to compacted roadway, measured to 1.5
47
3. TRANSPORT 3.2 Truck Transport
The muck volume required for the roadway construction may be estimated from the
tunnel diameter and the roadway height, see Figure 3.9. Figure 3.10 shows the
roadway cross section area as a function of tunnel diameter for varying hroad.
hroad
ϕ = 2 ⋅ arccos(1 − ) (°) [3.35]
d tbm / 2
2
d tbm π ⋅ϕ
Aroad = ⋅( − sin ϕ ) (m 2 ) [3.36]
8 180
48
3. TRANSPORT 3.2 Truck Transport
hroad=1.5m
Aroad 8
m2
7
6 1.2m
4 0.9m
2 0.6m
8 9 10 11 12
TBM diameter, m
Figure 3.10 Cross section area of the roadway for hroad = 0.9 m.
Waiting Time
The waiting time per truck at the backup hopper before loading begins depends on the
transport capacity, the muck volume to be transported and the cycle time.
æ Q ö
t wait = çç1 − out ⋅ t cycle (min ) [3.37]
è Qtrans
When the waiting time is > 0, it means that the trucks are waiting at the backup to be
loaded. When the waiting time is < 0, the TBM must wait for trucks, i.e. more trucks
are needed.
49
3. TRANSPORT 3.3 Continuous Conveyor
The capacity of the continuous conveyor must be dimensioned on the basis of the
muck volume corresponding to the dimensioning net penetration rate. Figure 3.11
shows produced muck volume as a function of TBM diameter and net penetration
rate.
sm3/h
6m/h 5m/h
300
In=10m/h
4m/h
8m/h
200
3m/h
2m/h
100
1m/h
4 5 6 7 8 9
TBM diameter, m
50
3. TRANSPORT 3.3 Continuous Conveyor
•= Horizontal tunnel
•= The swell factor from solid rock to loose material is 2.0
•= 60 % of the maximum belt capacity is utilised.
The belt speed should be low to avoid release of dust to the tunnel air. The release of
dust from the TBM muck on the belt starts at a belt speed below 1 m/s.
vb=3.5m/s 3.0m/s
3
sm /h
2.5m/s
600
2.0m/s
400 1.5m/s
1.0m/s
200
Belt width, mm
51
4. VENTILATION 4.0 Introduction
4.0 INTRODUCTION
The occupational environment and the design and dimensioning of the ventilation
system for tunnelling is described in more detail in the Project Report 17-91
TUNNELLING Ventilation (Norwegian edition).
In TBM tunnelling, part of the rock is crushed to fine particles. The smallest particles
may become airborne, called Suspended Particulate Matter. Table 4.1 shows the time
one quartz particle will use to settle 1 m in stagnant air. These very fine particles are
easily suspended in turbulent air.
The Threshold Limit Values for dust and quartz dust are shown in Table 4.2.
52
4. VENTILATION 4.0 Introduction
Table 4.2 Threshold Limit Values for dust in the tunnel air.
The rock type itself does seldom consist of 100 % quartz. Hence, the Threshold Limit
Values should be adjusted for the quartz content of the rock type.
cTLV − q ⋅ 100
cTLV − d = ( mg/m3 ) [4.1]
pQ − q
The value of cTLV-d to be used for dimensioning and similar must be less or equal the
Threshold Limit Value of General Dust.
If more than one type of quartz is present, the Threshold Limit Value is estimated
according to additive effect.
53
4. VENTILATION 4.0 Introduction
cQ −1 cQ − 2 cQ − q
+ + ⋅⋅⋅⋅⋅ + ≤1 ( mg/m 3 ) [4.2]
cTLV −1 cTLV − 2 cTLV − q
54
4. VENTILATION 4.1 Dust Sources
The dust is produced through the boring process in front of the cutterhead. The
greater part of the dust is included in the TBM muck that is transported out of the
tunnel. However, some of the dust enters the tunnel air.
Cutterhead
The air in front of the cutterhead contains a large amount of dust, resulting in a higher
specific gravity than the surrounding air. Without closed air suction from the cutter-
head, the heavy air will flow out under the cutterhead, see Figure 4.1. The rotation of
the cutterhead will press some of the dust-filled air outwards along the periphery of
the cutterhead. The front of the cutterhead is exposed to negative pressure by means
of an air suction system to avoid the dust-filled air to enter the tunnel air.
The suction should be from the upper third of the cutterhead to avoid coarse particles
to enter the system. The capacity of the suction fan depends on the TBM diameter and
how efficient the dust seal around the cutterhead is. The suction capacity may be re-
duced somewhat if the dust seal functions well.
55
4. VENTILATION 4.1 Dust Sources
In rock of low boreability (frequently combined with high quartz content), the boring
will produce extra fines, including quartz fines. This should be considered when di-
mensioning the suction capacity.
To estimate the suction capacity, we have adopted the empirical model developed by
the Norwegian contractor Statkraft anlegg AS. Recommended suction capacity is:
krock is found in Table 4.3 based on the rock drillability index DRI and the seal proper-
ties. For low drillability and no dust seal, the high krock value will include a safety fac-
tor to avoid dust to flow below the cutterhead and into the tunnel air.
Tunnel Walls
The tunnel roof and walls right behind the cutterhead will be covered with fine parti-
cles and dust. The roof and walls should be washed continuously by a spray system
mounted close to the cutterhead. Leaving the fines on the walls will increase the dust
problem at the backup and in the tunnel.
56
4. VENTILATION 4.1 Dust Sources
Conveyor Belts
The muck on the conveyors will release dust to the tunnel air. The main source is the
reloading points where the drop height should be as low as possible. In difficult con-
ditions, the reloading points may be encapsulated with a suction system, but water
spraying will help in most cases.
The belt speed affects the dust release. According to experience, the belt speed should
be 1 m/s or lower.
Water must be used with caution. Too much water, sprayed either in front of the cut-
terhead or on the conveyor belt, may cause the muck to set in the muck-cars and com-
plicate the discharge of the muck at the dump station.
A lot of dust is released when the muck is dumped from the cutterhead scopes to the
machine conveyor. Encapsulating the forward part of the machine conveyor will
cause most of the released dust to be sucked back to the front of the cutterhead.
Use of a continuous conveyor must be given special notice with regard dust release
along the tunnel. Possible booster stations must be treated as reloading points.
57
4. VENTILATION 4.2 Air Cleaning
The TBM has a cleaning device for the air from the suction system. The air is cleaned
before it is released further back from the cutterhead. However, the dust cleaning sys-
tem is not able to remove all respirable dust from the air, and the tunnelling process
should be focused on producing and releasing as little dust as possible. There are ba-
sically three principles of cleaning being used.
In a dry filter, the dust is deposited in a chamber with several filter bags through
which the suction air is filtered. The recommended air speed through the filter bags is
0.7 - 0.8 m/s, corresponds to 0.072-0.075 m3/s air per m2 filter area. The filter is self-
cleaning. After the air has been filtered, it is released in the backup area.
The filter principle functions well under favourable conditions, but the self-cleaning
effect is substantially reduced if the air is humid.
Wet-Washers
The separation of the dust is based on contact between the dust particles and water.
Small nozzles spray water into the air coming from the cutterhead and the dust is
bound to the water. After the dust has been moistened, a centrifugal separator re-
moves the moist dust from the air by negative pressure.
Electrostatic Filter
The method is best suited for additional cleaning. First, the air is ionised and then
passing between electrically charged plates. The ionised particle is drawn to the plate
with the opposite polarity of the particle. The plates are cleaned by water.
58
4. VENTILATION 4.3 Fresh Air Supply
It is necessary to supply fresh air to the TBM and backup to ensure that the air from
the cutterhead will be forced out of the tunnel. When the fresh air supply to the
backup area is too low, the released air from the dust cleaning system will flow to-
wards the cutterhead again.
For electric driven muck transport, the suction volume from the cutterhead will be
dimensioning for the ventilation duct size and the capacity of the fan(s). For diesel
driven muck transport it is necessary to dilute the exhaust gases from the locomotives
or trucks. Sufficient air must be supplied to the backup area or along the tunnel to
ensure good working conditions along the whole tunnel.
Leakage in the ventilation duct may be a problem in TBM tunnels. Often, the tunnels
are long, but of small diameter with little space for the ventilation duct. The air pres-
sure in the duct is generally high, and the duct must frequently be inspected and re-
paired.
Figure 4.2 shows the ventilation principle of the TBM and backup.
Figure 4.2 The ventilation system at the TBM and the backup.
59
4. VENTILATION 4.3 Fresh Air Supply
The fresh air supply to the TBM must be larger than the suction capacity of the dust
cleaning system (Q0 > Qa). The fresh air discharge must be closer to the cutterhead
than the air discharge of the dust cleaning system. Hence, the effect of the cleaning
device will not influence the conditions at the TBM, only the conditions in the tunnel
behind the discharge of the dust cleaning system (i.e. the locomotive or truck drivers).
The air supply to the backup should not be unnecessarily high, since this will result in
high air speed and extra release of dust from the walls. Figure 4.2 indicates fresh air
ducts directly to the permanent working places.
In general, the discharge air velocity should be kept low to avoid dust to be sus-
pended.
The fresh air supply must always be at least 20 % larger than the volume being re-
moved from the cutterhead, but not more than 30 - 40 % larger than the volume from
the cutterhead.
A main cause of dust problems in a TBM tunnel is that the principles described above
are not followed. As the tunnel gets longer, the pressure drop in the ventilation duct
increases and leakage from the duct increases, resulting in less fresh air supply to the
TBM.
The airborne dust follows the air movement. Hence, it is very important to avoid high
air velocity in the work area. If the leakage from the ventilation duct is high, the leak-
age must be repaired instead of increasing the overall air supply to the tunnel.
60
4. VENTILATION 4.3 Fresh Air Supply
The necessary transport work must be estimated for track-bound and truck transport.
The forces acting against the movement of the vehicle must be calculated. These are:
•= Rolling resistance
•= Air resistance
•= Tunnel gradient.
The dimensioning principles and basis are given in Project Report 17-91
TUNNELLING Ventilation (Norwegian edition). Only the resulting equations are
shown here.
61
4. VENTILATION 4.3 Fresh Air Supply
Wvehicle
k load = [4.5]
Wload
Table 4.5 Relative load weight for various transport vehicles. Truck 6x4 means a
truck with 3 axles, and traction on 2 axles.
2
d tbm ⋅π ⋅ In
Qtrans = (m 3 / h ) [4.6]
4
The necessary fresh air supply per metre of tunnel is estimated for 3 different cases.
Qtrans ⋅ (2 ⋅ f r + k load ⋅ ( f r − f s ))
q trans = ( m 3 / s ⋅ m) [4.7]
k load ⋅ 1180
62
4. VENTILATION 4.3 Fresh Air Supply
Track-bound transport is in general under Case 1 since the tunnel incline most often is
from 0.2 to 0.5 %.
Qtrans ⋅ ( f r + f s )
q trans = (m 3 / s ⋅ m) [4.8]
k load ⋅ 1180
Qtrans ⋅ (1 + k load ) ⋅ ( f r − f s )
q trans = ( m 3 / s ⋅ m) [4.9]
k load ⋅ 1180
If qtrans is less than the duct leakage, use [4.11] to estimate Qfan.
The total fresh air supply for electric driven muck transport is estimated on the basis
of the fresh air supply to the TBM and the ventilation duct leakage.
Q0
Q fan = ( m 3 / s) [4.11]
100 − pleakage Ld
( )
100
63
4. VENTILATION 4.3 Fresh Air Supply
To select the fan (or fans), the total pressure drop along the ventilation duct must be
estimated in addition to the air delivery from the fan. A rough estimation model is
presented in the following. A more complete model is given in the Project Report
17-91 TUNNELLING Ventilation (Norwegian edition).
When selecting the ventilation duct size, the maximum air velocity in the duct should
be 20 - 25 m/s.
64
4. VENTILATION 4.3 Fresh Air Supply
Friction
The friction loss in the duct is by far the largest contribution to the total pressure drop
for long tunnels. The friction loss in the ventilation duct for duct section i may be es-
timated as:
1.85
Qduct
pduct −i = 0.017 ⋅ 4.96−i ⋅ l duct −i ( Pa ) [4.12]
d duct
The Figures 4.3 and 4.4 show the dimensioning airflow in the duct as a function of the
tunnel length.
Qfan
Qx = Qo + qtrans (lt - x)
Qo
lt
0 x (m)
Figure 4.3 Airflow in the ventilation duct for diesel driven transport.
65
4. VENTILATION 4.3 Fresh Air Supply
Qfan
Qo
Qx =
100 - pleakage Ld-x
( ) Qo
100
Ld
0 x (km)
When the total duct length is divided into n sections of length lduct-n, the air volume at
the end if section i is for diesel driven transport:
Q0
Qi = (m 3 / s) [4.14]
100 − p leakage Ld i
( )
100
66
4. VENTILATION 4.3 Fresh Air Supply
n
p total = p intake + p fan + p bend + p outlet + p duct − i (Pa ) [4.15]
i =1
The fan is selected on the basis of the performance diagram of the fan, which is
shown in principle in Figure 4.5. The estimated total pressure drop combined with the
estimated fan capacity must plot below the curve of the actual fan type.
ptotal
Pa
1 Fan type 1
2 Fan type 2
2
1
When more than one fan is needed because of the size of total pressure drop, there
should be a rest pressure in the ventilation duct of at least 500 Pa at the point where
the new fan is installed.
67
5. ROCK SUPPORT 5.0 Introduction
5.0 INTRODUCTION
Tunnel boring as excavation method affects the remaining rock mass less than drill
and blast excavation, with considerably improved stability as a result. In medium or
good rock conditions, rock support is not needed or reduced to a minimum.
However, tunnel boring is less flexible than drill and blast tunnelling in handling sta-
bility problems at the face. Unforeseen problems may therefore cause long delays and
additional costs.
The TBM should not be equipped for all the conceivable stability problems and sup-
port methods, but be focused on the more or less systematic rock support needed. Ex-
pected single events (e.g. large crushed zones or concentrated water inflow) may be
handled through predetermined procedures with auxiliary or stand-by equipment.
68
5. ROCK SUPPORT 5.1 Stability Problems
Crushed Zones
Steep and dry crushed zones containing clay seldom represent any acute danger. Fall-
outs do seldom occur until 1/2 - 2 days after boring into the zone. The time span en-
ables rock support work to be carried out efficiently in the area behind the TBM.
However, this requires a predetermined strategy to handle stability problems with
regard to time and method - to avoid unnecessary loss of time due to ad hoc solutions
from zone to zone.
Fall-outs begin almost immediately when boring into zones of "water-sick" clay,
loose material such as "sugar-lump" jointed rock or clay-infected, medium to heavily
jointed and blocky rock. This requires ground support right behind the cutterhead.
The most difficult zones to handle are zones with low dip angle in the tunnel direc-
tion. Zone material and unsupported rock have a tendency to fall on the machine
without any warning when boring into the zone.
The most extensive ground support work carried out in bored Norwegian tunnels has
been related to altered mineral zones.
Gripper hold may disappear in fairly large crushed or altered zones. Sandbags, bags
with ready-made concrete mix, railway sleepers, etc., may be used for packing to get a
provisional gripper hold. It is difficult to maintain the tunnel alignment in wide zones.
Reboring into good rock is also difficult when the gripper hold is poor.
Rock with low strength combined with rock stress results in squeezing ground. The
whole tunnel must be supported with systematic bolting, ring beams or concrete seg-
ments to maintain the tunnel profile.
69
5. ROCK SUPPORT 5.1 Stability Problems
Rock Burst
Required support work in moderate rock burst conditions is considerably less in bored
than in drill and blast tunnels. This is due to the favourable cross section with an even
and undamaged rock surface. Rock support is only necessary at higher stress levels,
and for a smaller part of the circumference. Furthermore, shorter bolts are required.
Less scaling is also required in a rock burst situation.
Under very high rock stress compared to the rock strength, the necessary support may
be of the same extent for the two excavation methods.
Rock burst appears first as stress loosening of blocks along joints and fissures. High
rock stress appears as bending along the schistosity planes in weak and schistose
rocks.
Scaling and spot bolting is extensively reduced in bored tunnels compared to drill and
blast tunnels. The rock mass must be heavily fractured or have clay-infected fractures
before systematic bolting is required. Horizontal joints may cause unexpected fall-
outs of blocks.
Water Inflow
Large water inflow into bored tunnels requires as extensive measures as for drill and
blast tunnelling. Small water inflows rarely represent any problem. An exception is
projects where lowering of the ground water table must be avoided. This requires ex-
tensive probe drilling and pregrouting or the use of continuous lining. Where possi-
ble, the tunnel system should be designed with an incline of at least 0.15 % to ensure
gravitational draining.
70
5. ROCK SUPPORT 5.1 Stability Problems
Figure 5.1 Rock burst in the roof due to horizontal tectonic stress. The fissure in the
foreground initiated the burst. The rock type is granitic gneiss.
Figure 5.2 Rock support against moderate rock burst. The rock type is granitic
gneiss.
71
5. ROCK SUPPORT 5.1 Stability Problems
Figure 5.3 Fall-out in limestone along horizontal bedding and vertical joints.
Figure 5.4 Bolting in a drill and blast branch-off tunnel. The large amount of rock
support is due to the disturbance of the stress concentration around the
bored tunnel. Stress and rock conditions as in Figure 5.1.
72
5. ROCK SUPPORT 5.1 Stability Problems
The risk of inflow of toxic or explosive gases into tunnel must be assessed. Where
there is any risk of such inflow, adequate systems for detection and treatment of the
gases must be installed.
Heat due to high rock temperature or hot water inflow demands air-cooling. The cool-
ing may be individual (e.g. of the operator's cabin, the cutterhead area, the track lay-
ing area, the locomotives, etc.) or more general (e.g. the TBM and backup area as a
whole). In rock temperatures of 35 - 40 °C, the best cooling is achieved by a system
based on general cooling using pre-cooled water from the surface.
Heat and gas may seriously disrupt the tunnel boring process, and must be addressed
properly if they are expected to occur.
73
5. ROCK SUPPORT 5.2 Support Methods
Alertness
The net penetration rate and the torque increase when boring into crushed or altered
zones. This is a warning to the operator of possible poor rock mass quality ahead.
Limit values for the combination of high net penetration rate, high torque and low
thrust should be predetermined. When the limits are approached, the operator must
stop the boring and inspect the rock mass at the face. When boring through zones, the
stability of the exposed roof must be carefully assessed, especially when cutters are
being changed.
When boring through zones of difficult rock conditions, continuous monitoring of the
muck on the machine conveyor may give valuable information as a supplement to
repeated inspections of the face. The inspections should be done at intervals shorter
than the length of the cutterhead and the cutterhead support. Usually a machine can
only be retracted a few stroke lengths before it butts into the backup.
One must also ensure that the results and interpretations of the engineering geological
preinvestigations are available to the TBM operators.
Scaling
Scaling is required after boring through heavily fractured or altered zones. Scaling is
often a sufficient rock support method.
Bolting
Drilling of the boltholes is carried out with pusher leg or carriage mounted pneumatic
or hydraulic drills at or behind the TBM. The TBM should be designed to carry out
the bolting while boring to get a best possible machine utilisation. When continuous
bolting over a longer part of the tunnel has to be applied, the tunnel crew should be
increased by 1 or 2 persons.
Bolting may be combined with straps, mesh or similar. Some types of mesh are unfa-
vourable in water tunnels due to corrosion, and must be shotcreted.
74
5. ROCK SUPPORT 5.2 Support Methods
Shotcreting
Shotcrete alone (with or without steel fibres), or combined with bolts or steel ring-
beams, is a good rock support method. Track transport in small diameter tunnels may
make the use of wet-mix shotcrete inconvenient because of the transport. Dry-mix
shotcrete may be more practical for small volumes.
Shotcreting from the TBM or the backup always involves additional cleanup work.
Special care should be taken when designing the shotcreting system.
Concrete Lining
Continuous concrete lining is used as permanent ground support, and should be in-
stalled as a separate operation after the boring is finished.
Pumping concrete in front of the cutterhead to fill up larger cave-ins is also a form of
concrete lining. The concrete may then provide a stable roof and walls when boring
starts again. This method may also be used in situations of cave-ins with water inflow
if sufficient draining of the water from the zone and into the tunnel behind the TBM is
provided (e.g. by boreholes with casing).
Concrete segments are used with shield machines in mechanically weak rock. Where
weak rock is expected or where lowering of the ground water table must be avoided
for long tunnel sections, the segmental lining is a well-suited support method. A dou-
ble shield machine with segmental lining will be able to obtain a weekly penetration
rate of approximately two times that of an open TBM with continuous probe drilling
and pregrouting.
75
5. ROCK SUPPORT 5.2 Support Methods
Ring-beams
Ring-beams of all types and sizes (U-, I- and H-profiles) may be used as continuous
rock support in fractured or weak to medium strong rock mass. Ring-beams are also
well suited to be used in singular situations to be able to bore through crushed zones
or blocky ground and install the final rock support behind the TBM or even behind
the backup. The ring-beams may be installed rapidly right behind the cutterhead, and
may be combined with weld-mesh or liner plates as rock support. The ring-beams
should be shotcreted in water tunnels.
Probe drilling is used to detect possible water inflow or unfavourable rock conditions
ahead of the tunnel face. Pregrouting the rock mass in front of the face is primarily
used to avoid water inflow, but may also be used to stabilise crushed zones or blocky
ground before boring through possible unstable rock mass.
For small diameter TBMs, the available space for the probe drilling equipment is lim-
ited, causing a risk of blind zones for the probe drilling and grouting holes. The avail-
able space also limits the drilling capacity for the probe and grouting bore holes. For
the larger TBMs, the available space close to the cutterhead is sufficient to perform
the probe drilling and pregrouting efficiently. However, for continuous pregrouting,
the time consumption of the grouting process will in most cases be larger than that of
the tunnel boring.
The type and amount of rock support expected should decide the design of the rock
support equipment. In tunnels where only insignificant amounts of rock support is
needed, the rock support equipment may be based on the use of pusher leg drills for
spot bolting and ring-beams to handle crushed zones and similar. The final rock sup-
port (e.g. shotcreting) may be carried out when the boring is finished or as single
events behind the backup.
76
5. ROCK SUPPORT 5.2 Support Methods
When more or less systematic rock support is expected, the TBM should be equipped
with equipment and working platforms as close to the cutterhead as possible. For the
larger TBM diameters, working platforms, drilling machines, ring-beam erector, shot-
creting equipment, etc., may be mounted directly on the TBM.
For the smaller TBM diameters, use of a dedicated rock support platform between the
TBM and the backup may be a good solution. Still, the TBM must be equipped to
install preliminary rock support right behind the cutterhead.
Figure 5.5 Rock support platform between the TBM and the backup. Courtesy of
Statkraft Anlegg AS.
Figure 5.6 Rock support equipment for a large diameter TBM. After the Robbins
Company.
77
5. ROCK SUPPORT 5.2 Support Methods
Summary
The total cost and quality of the tunnel will benefit from engineering geological pre-
investigations adapted to the tunnelling method, and not only transferred from inves-
tigations aimed at drill and blast excavation.
78
APPENDIX A. Previous Editions
A. PREVIOUS EDITIONS
Previous editions of the Hard Rock Tunnel Boring Report including project group
members:
79
APPENDIX B. Research Partners
B. RESEARCH PARTNERS
•= Statkraft anlegg as
•= Norwegian Public Roads Administration
•= Statsbygg
•= Scandinavian Rock Group AS
•= NCC Eeg-Henriksen Anlegg AS
•= Veidekke ASA
•= Andersen Mek. Verksted AS
•= DYNO Nobel
•= Atlas Copco Rock Drills AB
•= Tamrock OY
•= The Research Council of Norway
80
APPENDIX C. List of Parameters
C. List of Parameters
The parameters used in the report are listed in the following. The list is according to
when the parameter first is explained or treated.
81
APPENDIX C. List of Parameters
M Manning's Number 11
nbypass number of bypasses in the tunnel 37
nloco number of locomotives in the transport system 37
nset number of muck-cars in a set 34
ntrain number of muck-car sets in the transport system 37
ntruck number of trucks in the transport system 43
pbend singular pressure loss at the ventilation duct curves Pa 64
pduct pressure loss (friction) in the ventilation duct Pa 65
pfan singular pressure loss through the ventilation fan(s) Pa 64
pintake singular pressure loss at the ventilation fan intake Pa 64
pleakage ventilation duct leakage %/km 63
poutlet singular pressure loss at the ventilation duct outlet Pa 64
pQ-q rock content of quartz type q % 53
Ptbm installed cutterhead power kW 27
ptotal total pressure loss in the ventilation system Pa 67
3
qtrans fresh air supply for diesel driven transport m /s·m 62
Q0 fresh air volume delivered to the TBM and the backup m3/s 60
Qa air volume sucked from the cutterhead m3/s 56
Qduct air volume flowing in the ventilation duct m3/s 65
Qfan air volume delivered from the ventilation fan(s) m3/s 63
Qout muck volume to be transported sm3/h 43
Qroad muck volume used to build the roadway sm3/h 47
Qtbm muck volume excavated by the TBM sm3/h 47
Qtrans capacity of the transport system sm3/h 43
Qtruck transport capacity of one truck sm3/h 43
Qx air volume flowing in the ventilation duct at chainage x m3/s 65
t100 driving the 100 m close to the backup min 35
tadit driving in the adit and from the adit to the dump station min 35
tbypass train waiting time at and driving past the bypass min 40
tcar discharging one muck-car at the dump station min 36
tcycle train cycle time min 32
truck cycle time min 43
tdump discharging the muck-train at the dump station min 35
turning the truck and dumping the load min 44
tin drive the train from the adit to 100 m behind the backup min 35
82
APPENDIX C. List of Parameters
83
APPENDIX D. Estimation Forms
Solid volume per set Vset = Vcar ⋅ nset / kswell sm3 [3.3]
l s ⋅ 60
Time per stroke t stroke = min [3.2]
In
Driving the 100 m close to the backup t100 min Table 3.1
l out ⋅ 60
Driving time in tunnel t out = min [3.9]
v out ⋅ 1000
Average speed in adit and to dump station vadit km/h Table 3.1
Dumping time per muck-car set tdump = tcar ⋅ nset min [3.8]
Cycle time
t cycle = 2 ⋅ (t100 + t out + t adit + t shunt ) + t dump + t loco min [3.7]
Stop time TBM for change of muck-car sets tset min Page 33
Loading time one set t load = (t stroke + t regrip + t set ) ⋅ k set min [3.6]
If tcycle is larger than tload, a bypass has to be installed and one new muck-car set and
one new locomotive have to be added to the transport equipment. Use Appendix D.2
to find the optimum placement of bypass no. 1.
Solid volume per set Vset = Vcar ⋅ nset / kswell sm3 [3.3]
l s ⋅ 60
Time per stroke t stroke = min [3.2]
In
Stop time TBM for change of muck-car sets tset min Page 33
Average speed in adit and to dump station vadit km/h Table 3.1
Dumping time per muck-car set tdump = tcar ⋅ nset min [3.8]
Driving the 100 m close to the backup t100 min Table 3.1
l inner ⋅ 60
Driving time in tunnel t out −i = min [3.18]
v out ⋅ 1000
If tinner is larger than tload, a new bypass has to be installed, and one new muck-car set
and one new locomotive have to be added to the transport equipment. Use Appendix
D.3 to find the optimum placement of bypass no. 2.
l s ⋅ 60
Time per stroke t stroke = min [3.2]
In
Stop time TBM for change of muck-car sets tset min Page 33
l inner ⋅ 60
Driving time in tunnel t out −i = min [3.18]
v out ⋅ 1000
If tinner is larger than tload, a new bypass has to be installed, and one new muck-car set
and one new locomotive have to be added to the transport equipment. Bypass no. 3
should be placed a distance equal to lbypass-2 - lbypass-1 from bypass no. 2.
Aroad ⋅ I n
Muck volume in roadway Qroad = sm3/h [3.33]
k road
2
d tbm ⋅π ⋅ In
Muck volume from TBM Qtbm = sm3/h [3.32]
4
Driving speed from dump station to adit vto km/h Table 3.2
l dump ⋅ 60
Driving time dump station to adit t to = min [3.27]
vto ⋅ 1000
l turn ⋅ 60
Driving time in-bound t in = min [3.29]
vin ⋅ 1000
lturn ⋅ 60
Driving time outbound t out = min [3.30]
vout ⋅ 1000
Cycle time
t cycle = 2 ⋅ t to + t meet + t in + t turn + 2 ⋅ t man + t load + t out + t dump min [3.26]
2
d tbm ⋅π ⋅ In
Dimensioning transport volume Qtrans = m3/h [4.6]
4
n
Pressure loss duct p duct = p duct −i Pa D.7
i =1
2
d tbm ⋅π ⋅ I n
Excavated volume TBM Qtbm = m3/h [4.6]
4
Air flow end of section i, duct leakage < qtrans See next
Qi = Q0 + (lt − l duct −n ⋅ i ) ⋅ q trans page [4.11]
100
Qi + Qi −1 See next
Average air flow section i Qduct − i =
2 page
1.85
Qduct See next
Pressure loss section i p duct −i = 0.017 ⋅ 4.96
−i
⋅ l duct −i [4.10]
d duct page
0 lt = Q0 = Not applicable
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
n
Pressure loss in the ventilation duct p duct −i Pa
i =1