Proposed Installation of 2No.

Passenger Lifts for 5-Storey Social Science Building Complex for Faculty of Social Sciences, KNUST-KUMASI
ID Name Duration Start Finish Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019
Mar Apr May Jun Jul Aug Sep Oct Nov
1 Installation of Lift 1 & 2 150 days Mon 4/1/19 Fri 10/25/19

2 PURCHASING 66 days Mon 4/1/19 Mon 7/1/19

3 Purchasing and shipping customer 66 days Mon 4/1/19 Mon 7/1/19


service elevator
4 CONSTRUCTION 79 days Tue 7/9/19 Fri 10/25/19

5 Temporary facilities establishment 15 days Tue 7/9/19 Mon 7/29/19

6 Inspection and handing over of shaft 3 days Tue 7/30/19 Thu 8/1/19

7 Installation of guide rails for cabin 6 days Fri 8/2/19 Fri 8/9/19
cage
8 Installation of guide rails for 6 days Mon 8/12/19 Mon 8/19/19
counterweight
9 Installation of traction machine 3 days Tue 8/20/19 Thu 8/22/19

10 Installation of distribution board and 3 days Fri 8/16/19 Tue 8/20/19


control panel
11 Installation of buffer 1 day Fri 8/23/19 Fri 8/23/19

12 Assembly cabin cage 6 days Mon 8/26/19 Mon 9/2/19

13 Installation of landing doors and 12 days Tue 9/3/19 Wed 9/18/19


limit switch
14 Test and commissioning 10 days Thu 9/19/19 Wed 10/2/19

15 Installation of guide rails for cabin 6 days Fri 8/16/19 Fri 8/23/19
cage
16 Installation of guide rails for 6 days Mon 8/26/19 Mon 9/2/19
counterweight
17 Installation of traction machine 3 days Tue 9/3/19 Thu 9/5/19

18 Installation of distribution board and 3 days Fri 8/30/19 Tue 9/3/19


control panel
19 Installation of buffer 1 day Fri 9/6/19 Fri 9/6/19

20 Assembly cabin cage 6 days Mon 9/9/19 Mon 9/16/19

21 Installation of landing doors and 12 days Tue 9/17/19 Wed 10/2/19


limit switch
22 Test and commissioning 10 days Thu 10/3/19 Wed 10/16/19

23 Handing over 7 days Thu 10/17/19 Fri 10/25/19