Вы находитесь на странице: 1из 302

British Electricity International

Modern
Power r -
-I

I - -

Practice
Third Edition incorporating Modem Power System Practice

TURBINES,
ASSOCIATED PLANT

Pergamon Press
MODERN
POWER STATION PRACTICE
Third Edition
(in 12 volumesl

Incorporating Modern Power System Practice


Main Editorial Panel
D. J. Littler, BSc, PhD, ARCS, CPhys, FinstP, CEng. FiEE (Chairman)

+ < E. J. Davies, DSc, PhD, CEng, FIEE


Professor
I
MODERN
H. E. Johnson POWER STATION PRACTICE
F. Kirkby, BSc, CEng, MIMechE, AMlEE
Third Edition
P. 8. Myerscough, CEng, FIMechE, FlNucE

W. Wright, MSc, ARCST, CEng, FIEE, FIMechE, FlnstE, FBIM


Incorporating Modern Power System Practice
Volume Consulting Editor
B Professor E. J. Davies, DSc, PhD, CEng, FIEE

Volume Advisory Editor British Electricity International, London


P. Hambling, CEng, MlMechE

Authors
Chapters 1 8 2 G. F. Hunt. BSciEngt, CEng, MlEE

Chapter 3 M . Douglass, CEng. MlMechE

Chapter 4 A. R. Woodward, BSciEng)


D. L. Howard, BSc, CEng, MlMechE
E. F. C. Andrews, CEng, MIMechE, ABTC Volume C
Chapter 5 B. J. Beecher. BSc, CEng, MlMechE
Turbines, Generators and Associated Plant
Chapter 6 J. J. Arnold, BSc, CEng, MlEE
J. I?. Capener, BSc, CEng, MlEE

Series Production
Managing Editor P. M. Reynolds

Production Editor H. E. Johnson

Resources and T. A. Dolling


Co-ordination J. R. Jackson

PERGAMON PRESS
OXFORD . NEWYORK . SEOUL . TOKYO
U.K. Peigalnon Press pic., iieadtngion Hill iiali.
Oxford OX3 OBW. Erlgiaild
USA Pergamon Press, nc., (395, Saw Mill River iUoad.1
Elmsford. New York 10523, U S A ,

SEOUL Peigamon Press Korea, KPO Box 315, Seoul 110-603,


Koraa
Contents
JAPAN Pergamon Press,8th Fioor, Matsuoka Central Building.
1.7~1Nishi-Shinjuku, Silinjuku-ku, Tokyo 160. Japan

Copyright a 1991 British Electrictty internaiionai Ltd


PLATES
COLOUR vi
All ~ i g h i sReserved. No pan of this poblicstion may be
reproduced, stored in a retrieval system or transmitted FOREWORD vii
;,I sny form or by any means: electronic, elecirosratic,
magneric rape, mechanical, photocopying, recording or
orhenvise, wirl~outpermission in writi,,g from the copy- PREFACE ix
rig/?t hoidei
First edition 1963 CON.IENTS
OF ALLVOLIJMES xi
Second edition 1971
Third edition 1991
Chapter 1 The steam turbine 1
Libraw of C o n g r e ~Cataloging
~ in Pubiication Data
Modern power station practice: incorporating modern
power system practicel8ritisi~ Eiectricity 1nternationai.- Chapter 2 Turbine plant systems 124
3rd ed, p. cm.
lnciudes index.
1. Electric power-planis, i . British Electricity inter- Chapter 3 Feedwater heating systems 241
national.
TK119lM49 1990
62.31'21 - dc20 90-43748 Chapter 4 Condensers, pumps and cooling water plant 323
writish ~ i b r a r ycataloguing in Publication Data
British Electricity international Chapter 5 Hydraulic turbines 422
~ o d e r npower station practice.-3rd. ed.
1. Eiectric power-plants. Design and construction
I. Title il. Central Electricity Generating Board Chapter 6 The generator 446
621.3121.
ISBN o-08-040510-X 112 Volume Seti
ISBN 0-08-040513-4 (Volume Ci 563
ISBN 068-04~43.8 (Fleximver)

pinred in the ~ e p u b ~ iof


c Singapore
by Singapore National Printers Lrd
Colour Plates Foreword
G . A. W. Blackman, CBE, FEng
Chairman, Central Electricity Generating Board
a n d Chairman, British Electricity International L fd
Fic. 4.24 Heysham 2 condenser - modular construction
Fic. 6.31 Flux test on completed core
Fic. 6.41 View of a 660 M W generator stator end-windings FOROVER .THIL.TY YEARS, Since its formation in 1958, the Central Electricity Generating
Board (CEGB) has becn at the forefront o f technological advances in the design,
Fic. 6.90 Condition monitor (NEI Parsons Ltd) construction, operation, and maintenance of power plant and transmission systems. During
Fic. 6.97 Dinorwig motor-generator during site winding this time capacity increased aimost fivefold, involving the introduction of thermal and
nuclear generating units of 500 MW and 660 MW, to supply one of the iargest integrated
power systems in the world. In fuliilling its statutoly responsibility to ensure continuity of a
safe and economic supply uf eiectricity, the CEGB built up a powerful engineering and
scientific capability, and accumulated a wealth of experience in the operation and
maintenance o f power plant and systems. With the privatisation of the CEGB this
experience and capability is being carried forward by its four successor companies -
National Power. PowerGen. Nuclear Electric and National Grid.
At the heart i f the CEGB~Ssuccess has been an awareness o f the need to sustain and
improve the skills and knowledge of its ennineering and technical staff. This was achicved
through formal and on-job training, aided by a series of textbooks covering the theory
and practice for the whole range of technology to be found on a modern power station. A
second edition of the series, known as Modern Power Station Practice, was ~ r o d u c e din
the early i970s, and it was sold throughout the world to provide electricity undertakings,
engineers and students with an account of the CEGB's practices and hard-won experience.
The edition had substantial worldwide sales and achicved recognition as the authoritative
reference work on power generation.
A completely revised and enlarged (third) edition has now been produced which updates
the relevant information in the earlier edition together with a comprehensive account o f
the solutions to the many engineering and environmental challenges encountered, and which
puts a n record the achievements of the CEGB during its lifetime as one of the world's
leading public electricity utilities.
In oroducine- this third edition, the oooortunitv
.. has been taken to restructure the
information in the original eight volumes i o provide a more logical and detailed exposition
of the technical content. The series has also been extended to include three new volumes on
'Station Commissionine'.- . 'EHV Transmission' and 'Svstem Ooeration'. Each of the eleven
subject volumes had an Advisory Editor for the technical validation of the many
contributions by individual authors, all of whom are recognised as authorities in their
particular field of technology.
All subject volumes carry their own index and a twelfth volume provides a consolidated
index for the series overail. Particular attention has been paid to the production of draft
material, with text refined through a number of technical and language editorial stages and
complemented by a large number of high quality illustrations. The result is a high standard
of presentation designed to appeal to a wide international readership.
It is with much pleasure therefore that I introduce this new series, which has been
attributed to British Electricity International on behalf of the CEGB and its successor
companies. I have becn closely associated with its production and have no doubt that it will
be invaluable to engineers worldwide who are engaged in the design, construction,
commissioning, operation and maintenance o f modern power stations and systems.

March 1990
Preface

'The increase in generating capacity of the Central Electricity Generating Board (CEGB)
during the last thirty years has invoived the introduction of new 500 M W and 660 MW
turbine-generator plant for a variety of operational duties from base load to that of flexible
two-shift operation. Thcse plants have been installed in nuclear, coai and oil fired power
stations.
The early operational experience of the 500 MW units provided important data for the
design developn~ent of the 660 MW turbine-generator plant. Thcsc latter machines
benefited from the high quality approach to the design of major components by UK
manufacturers using their developed analysis techniques in the areas of aerodynamics and
stress analysis. The soundness of this approach has been demonstrated by the improved
reliability and performancc of the iatcr plants.
The Third Edition of Modern Power Station Practice gives a detailed account of ex-
perience obtained in the development, design, manufacture, operation and testing of
large turbine-generators in the last twenty years. The practice of testing and evaluatioli of
modern plant has proceeded as before; the advance in analytical and computational
techniques has however meant that the application of this experience to future design and
operation of large turbine-generator plant is of greater benefit than ever before.
One of the major tasks of the Turbine-generator Plant Branch in the CEGB was to secure
the development of 'hrbine-generators a n d their associated Plants to meet the needs o f the
CEGB with due regard to economics, performance and reliability. As Head of the Branch
for some years I have felt privileged t o have been asked to edit Volume C.
T h e authors of this volume have wide experience of the plant engineering field and all
are authorities in their particular field of Technology. I would like to record my sincere
thanks to these colleagues who have produced Volume C . They have undertaken the task
with an enthusiasn~ derived from the knowledge that this work will be of the greatest
assistance to engineers in this field of technology woildwide.

P. HAMHL.INC
Advisory Edilor - Volume C
Contents of All Volumes

Volnrne A - Station Planning and Design


I'ower station siting and site layout
Sii~tiondesign and layout
<:ivil engineering and building works

\'oltnme B - Boilers and Ancillary Plant


I'ornace design, gas side characteristics and combustion equipment
Iloiler unit - thermal and pressure parts design
Ancillary plant and fittings
1111st extraction, draught systems and flue gas desulphurisalion

Volume C - Turbines, Generators and Associated Plant


'The steam turbine
'Turbine plant systems
I'eedwater heating systems
Condensers, pumps and cooling water plant
Hydraulic turbines
The generator

Volume D - Electrical Systems and Equipment


Electrical system design
Electrical system analysis
'Transformers
Generator main connections
Switchgear and control gear
Cabling
Motors
Telecommunications
Emergency supply equipment
Mechanical plant electrical services
Protection
Synchronising

Volume E - Chemistry and Metallurgy


Chemistry
Fuel and oil
Corrosion: feed and boiler water
Water treatment plant and cooling water systems
Plant cleaning and inspection
Metallurgy
Introduction to metallurgy
Materials behaviour
Non-ferrous metals and alloys
Non-metallic materials
Materials selection
Contents of All Volumes

Welding grocesscs ~,,I,,,IIcI 1, - System Operatioe


NOII-dest~ucliv~testing i,,.,,lrli, opclation in Englalld and Wales
Dcfcct analysis and lifc asscssnien; , I ~ ~-~ demand
o ~ , ~ ~ ;llian,lil~g ~ ~ I and generation
Environmental effects
r ~,,~t;&riouai plannilig - power system
Ol,rlil,i~,l,al p'.oceduxes - phi~osophy,i>~.inciplesand outline c o n t e ~ ~ t ~
Volnnle 1: - Control and Instrunlentation r 'i,ri!iol in rcal time
CoIhIc,,I COl,liol S;rUCtllle, supporting services and staffing
Introduction
Automatic control
Automation, protection and interlocks and manuai controls Velamu M - Index
Boiler and turbine instrumentation and actuators
(';,mplele contents of all voiumes
Electrical instruments and metering
t'.,lmt~lstive index
Central control rooms
On-line computer systems
Control and instrumentation system considerations

Volume G - Station Operation and Maintenance


Introduction
Power plant operation
Performance and operation of generators
The planning and management of work
Power plant maintenance
Safety
Plant performance and performance monitoring

Volume H - Station Commissioning


Introduction
Principles of commissioning
Common equipment and station plant commissioning
Boiler pre-steam to set commissioning
Turbine-generator/feedheatingsystems pre-steam to set commissioning
Unit commissioning and post-commissioning activities

Volume J - Nuclear Power Generation


Nuclear physics and basic technology
Nuclear power station design
Nuclear power station operation
Nuclear safety

Volume K - EHV Transmission


Transmission planning and development
Transmission network design
Overhead line design
Cable design
Switching station design and equipment
Transformer and reactor design
Reactive compensation plant
HVDC transmission plant design
Insulation co-ordination and surge protection
Interference
Power system protection and automatic switching
Telecommunications for power system management
Transmission operation and maintenance
C H A P T E R 1
Evan John Davies
Emeritus Professor of Electrical and Electronic Engineering
at Aston University in Birmingham. died on 14 April 1991. The steam turbine

I I
John was an engineer, an inteliectual and a respected author
In his own right. It was this rare combination of talents that
he brought to Modern Power Station Practice as consuiting l$~iroductlon 4 E C D ~ D ~ ~of the
C S steam cycle
Editor of seven volumes and, in so doing, bequeathed a 1 l u r b i o e types 4.1 choice of exhaust oressure
legacy from which practising and future enaineerq
" - -- ,nriii
..,,, 1.1 Direction of flow 4.1.1 Thermodynamic dpiimisation
4.12 General economic aotimisation of nisnt
I continue to benefir for many years. I 1.2 Cylinder end exhaust arrangements
1.3 Speed of rotation 4.1.3 Economic optimisatibn of exhaust pressure, condenser
end CW svrtem
2 Ffficiency and output
2 1 Output limitations
21.1 Steam valve pressure drop
21.2 Swsliowing capacity 4.2.3 Feedwater be-aeration
2.2 Moving biades 42.4 LOW pressure feedwater heaters
22.1 impuise-type turbine 4.2.5 High pressure feedwater heaters
2.2.2 Reaction-type turbine 4.2.6 Summarv
2.2.3 Effect an turbine design 4.3 Choice of feed pump and drive system
2.2.4 Biade efficiency 4.3.1 Feed pump sire and number
22.5 Modern blading designs 4.3.2 Feed pump duty. margins, and the need for variable
22.6 LP turbine blading speed
2.3 he effect of clearances on reai designs 43.3 Economic comparison of steam turbine drives with
2.3.1 Profiie loss electric motor drives
2.3.2 Secondaw ioss 4.3.4 Economic comparison of voriable-speed motor lVSMl
2.3.3 Tip leakage drive with induction motor plus fiuid-coupiing drive
2.3.4 Disc windage 43.5 Example of the resuits of an averaii comparison of the
2.3.5 L8CiW wires through-life costs of four feed pump system options.
2.3.6 Other iosres 4.4 Turbine by-paEl Sy518mS
2.3.7 Wetness loss 4.4.1 Superheat plant
2.3.8 Annuius loss 44.2 8"-oass caoacifv
2.4. Stage efficiency and the condition iine 4.4.4 s;&em
44.3 improvement
effectsof sfan-up capabiiity
24.1 Efficiency of stage
2.4.2 The condition iine 4.4.5 PWR wet steam piant
2.4.3 Cylinder efficiency 5 Turbine blading
2.4.4 Leaving loss
2.4.5 Hood loss 5.1 impulse stages
2.4.6 Wetness ioss 5.1.1 Moving blades - details and construction
24.7 Paniai admission 5.1.2 Fixed blades - detsiis and construction
51.3 Veiocity-compounded stage
3 Therrnodvnamics o f the steam cycie 5.2 Reaction stager
3.1 Development of the modern steam cycie 5.2.1 Fixed and moving blader - dstsiis and construction
3.1.1 The steam cycle 5.3 Low pressure stages
3.1.2 The Rankine cycle 5.3.1 Aerodynamic and mechanical constreinis
3.1.3 Practical cycie using superheat 5.3.2 Biade tip restraint
3.1.4 The rehsat cycle 5.33 Baumann exhaust
3.1.5 Regenerative feedheating 5.4 Moving blade root attachments
3.2 Cycle efficiency and heat rate 5.4.1 Fir-free 10015
3.2.1 Cylinder efficiency 5.4.2 Pinned roots
3.2.2 Heat rate 5.5 Diaphragm construction and support
3.3 Termins1 conditions 5.5.1 Kinematic support
3.3.1 Effect of steam inlet conditions 5.5.2 Radial ruppon pads
33.2 Effect of reheaf conditions 5.5.3 Diaphragm construction
3.3.3 Effect of pressure loss in pipework and valves 5.6 Blading materials
3.3.4 Effect of final feed temperatures 5.6.1 12% C i stseis
3.3.5 Effect of exhaust pressure 5.6.2 Titanium
3.4 Superheat cycle 5.7 Blade vibration control
3.4.1 Steam conditions 5.7.1 N ~ t u r afrequencies
l and excitation freq~encies
3.4.2 Reheat 5.7.2 Sources of vibration excitation
3.4.3 Double reheat 5.7.3 Verification of estimated natural frequencies and wheel
3.4.4 CEGB cycles chamber tests
3.4.5 Turbine desians
~ ~
5.7.4 Methods of "ibistion controi
3.5 Wet steam cycie 5.8 Erosion protection
3.5.1 The PWR steam cycle 58.1 Erosion mechanism
3.5.2 Cycie considerations 5.8.2 Erosion progression
3.5.3 Full-speed or hslf-speed machiner 5.8.3 Protection and erosion shieid msterisls
The steam turbine Chapter 1

6 Turbine cavings 7 3 . 4 Critical si,eeds


6.1 Forms of casing consiiuctioii 7.3.5 notor fast iracfi~rcr ~ s kassessment
6 1 . 1 High pressure casings 7.4 Cou"iinaS
6 1 . 2 Intermediate pressuls casings 7 . 4 1 Fiexibie coupiir,gs
6.1.3 Low pressure casings 7 4 . 2 Semiflexiblc couplings
6.2 Horizontal joints 7 4 . 3 Rigid couplings
6 2 . 1 Flsnge design 7.5 Rotor alignment
6.2.2 Bolting 7 5 . 1 Alignme,% teellnique
6.3 Exferoai connections 7 5 . 2 On-line monitoring
6 3 . 1 Steam inlets -- HP atid IP . .
6.3.2 HP exhausts 8.1 Journal bearings
6.3.3 IP exhausts (a)S8"gle #la*
8 1 . 1 Construction
6.3.4 Use of thermal skirts and piston rings
8.1.2 ln~fromcnfilfion
6 3 . 5 LP cvlinders 8.1.3 Bearing performance
6 3 . 6 ~ i e d i t e a mconnections 8.1.4 Factors affecting bearing life
6.4 Casing materials 8.2 Thrust bearings
6.5 Support and alignment 8.3 pedestals
6 5 . 1 HP and IP cylinder suppons 8.4 Oii sealing arrangements
6 5 . 2 LP cylinder supports 8.5 Turning gear
6.6 Casing and diephragm giends 8.5.1 Hand barring arrangement
6.7 Lagging 8 5 . 2 Electrical turning gear lETGl
7 Turbine rotors and oouplings 9 Turbine application5
7.1 Types of rotor construction 9.1 Power generation
7 1 . 1 Design for high fetnpeiature operefion 9.2 Mechanical drive
7 1 . 2 Cooling of IP rotors 9.3 Combined heat and power iCHPl
7.2 Rotor materials 9.4 Combined-cycie p1snt
7.2.1 HP and IP rotors
7.2.2 LP- rotors
~~~~

7.3 Rotor resting and balancing


7 3 . 1 Thermai stability
7 3 . 2 Ovenpeed testing
7.3.3 Rotor balancing

Introduction turbine have been presented by Traupel [I] and Harris


In order to function, a turbine requires a suitable PI.
working fluid, a source of high grade energy and a sink
for low grade energy. When the fluid flows through F I G . 1.3 ~ i i e c t i o of
~ i riow ror diiiele~itcaiesoiicr
of turbine
the turbine, part of the energy content is continuously
extracted and converted into useful mechanical work. 1. I Direction of flow
Steam and gas turbines use heat energy, while water Almost without exception, modern large steam turbines
turbines use pressure energy. The main objectives of are of the oxial-flow type (Fig 1.1). Even from the
(Fig 1.3 (b)), in which the steam is admitted at the
the turbine designer are to ensure that this process is early days in the late nineteenth centllry, this has been
centre of the cylinder and is divided to flow in op-
carried out with 'maximum efficiency' by means of the preferred solution for steam turbines of all ratings.
posite axial directions towards the ends of the rotor.
plant having 'maximum reliabilify' at 'minimum cost'. The principal exception to this rule has been the This arrangement is used to avoid the excessively
Second objectives are that the plant should require radial-flow turbine (Fig 1.2), originally introduced by long blades which would be incurred by a single-flow
'minimum supervision' and 'minimum starring time'. Ljungstrom, and developed to its most recent form arrangement. For turbines of large output, it is nor-
These five objectives conflict with each other and by Stal-Laval (now ASEA-Stall. In this design, steam mal to have several double-flow low pressure (LP)
the final outcome will be a n acceptable compromise is admitted to the centre o f the machine, expanding cylinders operating in parallel. The second benefit is
between them. outwards through two contra-rotating rotors to the that the double-flow cylinder effectively reduces to
Chapters I and 2 outline modern power station exhaust at the periphery. The concept was success- zero the axial thrust caused by the steam forces on
practice as implemented by UK turbine makers. The fully executed and has been applied at ratings up to the moving blading.
reasons behind every facet o f turbine development are about 60 MW. ASEA-Stal still offer the radial-flow according to the type o f blading used (see Section 5 One or both of these objectives are also the reasons
explained and, where necessary, technical terms are turbine for small industrial sets up to about 30 MW of this chapter), but in terms of direction of flow, for other arrangements of stage groups within a tur-
defined quantitatively and qualitatively to emphasise output. However, the design is not adaptable to large t i l e steam approaches a group of stages at one end, bine cylinder. Thrust reduction is the main target for
standard practice. outputs because o f the mass of the blades which would I'lows axially through the radially-mounted blading the reversed-flow cylinder (Fig 1.3 (c)), in which the
be mounted at the outer periphery. The largest ap- and exhausts at the other end of the group of stages. steam flows in one direction through one group Of
plication of the radial-flow turbine is for the high 'The simplest configuratior~of blading is in single-flow stages and is then ducted (internally o r externally) to
pressure (HP) cylinder of a 460 MW unit associated with (Fig 1.3 (a)). flow through a second group of stages in the opposite
a boiling water reactor at Oskarshamn in Sweden. Groups of stages within a turbine cylinder may be axial direction. In some cases, the second group o f
1 Turbine types Axial flow is therefore the characteristic feature of stages may have several sections in parallel to accom-
i~rranged for flow in opposing axial directions. The
Thorough reviews of the development of the steam modern steam turbines. These are often categorised inormal situation for this is the double-flow turbine modate the increasing volumetric flow rate.
2 3
The s t e a m turbine Chapter 1 Turbine tylx:!;

In axial till-bines, the stralii is adillitted to llic cyl- ~nombeio i L.1' cylinders being requiicd: the use of a
inder and cuhai~stciliioril it, by one or ino1.e circular rely long shaft can be avoidcd by the use a l a cross-
pipes in a radiai or near-radial orientation (see Section corn~oilndmachine. Further, the number of 1.P cylili..
6 of this chapter). A 1 thc L.1' t~irbineexbai~st,the deis can be reduced if thc 1.1' turbine shaft rotates at
connection fIaiige(s) to the condenser will however 1800 rimin, while llie H P shaft rotates at 3600 rimin.
llorlllally be rectangular, at an appropriate locatioli The arrangement of the L P turbine and its con-
and ol-ientation to matcll f h e condenser design. This nection l o the condelisei depends critically on the
always in\,olves radial flow in one or mare directions. location of the condenser, and the orientation of the
The steam is therefore required to turn through a condenser tubes with respect t o the turbine axis.
right angle to enter the axial-flow blading and to The condenser has traditionally been mounted below
exhaust from it, at the same time redistributing itself tbc turbine, with the condenser tubes either axial or
around the circumference. The inlet and exhaust areas transverse. During the 1960s and 1970s, many 500 MW
therefore require sufficient space t o allow an orderly and 660 MW turbines were built in the UK with side-
flow without undue pressure loss or flow separation. mounted condensers and axial tubes. Variants of this
In some cases, particularly low pressure turbine ex- design are called the pannier condenser (Fig 1.6 (a))
llausts, flow guides may be incorporated. and the ifrtegrul co,zdenser (Fig 1.6 ( b ) ) . The main
objective was to reduce the overall height of the
turbine, with a view to reducing the height and size
of the turbine hall. Because the tubes were axial, the
condenser steam space could be sectionalised, thus
1.2 Cylinder and exhaust arrangements
allowing a lower condenser pressure in the cold end.
For turbines driving electrical generators, the limit of This provided a small efficiency benefit.
a single-cylinder turbine is around 100 MW, d e ~ e n d i n g The main disadvantage of this design is that the
on the design concepts, the initial steam conditions conderlser becomes an important part of the turbine in
(pressure and temperature), whether or not a reheat terms of structural integrity, loading, foundations, etc.
cycle is used, fhc exhaust conditions and the specd This rnakes the condenser design dependent on the
Of rotation. number and size of LP turbines, thus inhibiting the
Frequently turbines o f this size are designed and
concept of modular design and complicating the de-
built o n a modular basis, with the inlet sections, biad-
sign interface between a turbine maker and a number
ing sections, and exhaust sections selected from a range
o f possible condenser makers. This design may also
of standard designs t o suit a range of output powers,
complicate access to the turbine for maintenance,
initial and exhaust conditions and special applications
for example, t o the bearing pedestals.
such as extraction steam for process heating or district
Later plant in British stations has therefore reverted
heating.
For larger machines, nrulti-cylinder designs are used to the use of undemlung condensers with transverse
(Fig 1.4). The numbel. of cylinders depends o n a simi- tubes (Fig 1.6 (c)), using a connecting duct between
the turbine outlet flange and the condenser inlet flange.
lar list of terminal conditions and design considerations.
Because the condenser tubes are normally much longer
A typical turbine of 500-900 MW output in a fossil-
than the width of the turbine casing, this duct is
fired power station (coal, oil, o r gas) or a gas-cooled
nuclear station would have one H P turbine, one inter- trapezoidal in shape.
mediate pressure (IP) turbine and two (LP) turbines, On some turbines built between 1920 and 1960, where
rotating at 3000 or 3600 rimin, depending on the grid the available last stage blading provided a limitation
frequency (see Section 1.3 o f this chapter). The I P and on turbine output or efficiency, the Buumann exhausf
L P turbines would probably be double-flow. turbine (Fig 1.7) has been used by certain manufac-
In a power station with a water-cooled reactor turers, particularly Metropolitan-Vickers in the UK.
(PWR, BWR, CANDU, etc.), the initial steam is at lower In this design, the penultimate turbine stage is divided:
pressure and temperature, so the steam mass flow rate the steam flow through the outer annular part of
and volumetric flow rate are likely to be much higher the stage is led directly t o the condenser, while that
flowing through the inner part flows through the final
for a given output. The turbine might then have one
double-flow H P turbine and two or three LP turbines. stage o n its way to the condenser. Because the two
The turbine with a number o f cylinders on a single parts o f the penultimate stage moving-blading have
shaft is described as a tandem-compound machine (Fig different duties, there is a discontinuity in the blade
1.5 (a)). The other main type is the cross-compound profile which makes it a difficult concept t o use in
machine (Fig 1.5 (b)), in which the turbine cylinders the most highly-rated turbines.
are mounted on two separate parallel shafts driving
two separate generators. The steam connections and
the auxiliary systems are arranged as for a single u
generating unit. This design of plant has been more 1.3 Speed o f rotation
widely used where the grid frequency is 60 Hz and In the normal case, steam turbines are directly w u -
the available L P turbine blading results in a large pled t o the electrical generator, n o gearbox being FIG. 1.4 ~ u l t i - c y l i n d e rturbine arransemenir
'a3e1s uo!lJear 'sapelq paxy aq1 u! pau!e3 L]!ao[ah aql J O UO!I a 4 1 'melsuos e s! )! pue sarnssa~disnaqxa pua lap!
e u! 1eq1 01 iualajj!p ieqmamos s! a3e1s aslndm! -lodoid e jo ssol aqi 01 anp Llalos alojalaql s! sape[q aql ale Ed pue Id 'ale1 MOU ssem aql s! mb alaqm
ue u! Laua!s!jja uo o!xer Ll!aojah aqi jo lsajja aql 3u!nom aql u! auop ylom jes!ueqsam aqL 'sapelq
'nadxa lq3!m auo s v '(3 = '3/n) LI!ao[aA alnlosqe 3u!nom aqi s s o ~ s edolp alnssald ou alojaiaql pue . '
meals aqi pun Lq~olahapa[q Bu!nom jo o!lei aql uodn doip Ieaq ou s! alaqL 'sapelq paxlj aql u! Ll!aolaA
iuapuadap L([e!iuassa s! slnaao sapejq Su!hom aql om! meals aqi u! leaq aql JO uo!)~odo~de sliahuoa
01 L31aua jo lajsuel1 aql qa!qm q l ! ~Laua!s!jja a q s au!qlnl aslndm! ue 'nealex ~ o s s a j o ~Lq d .pa)uahuI '[PI L Z ~ Iu! elopols Lq paanpord IS+J SEM
Axia(o!$$a a p e l a V'Z'Z au!qlnI edhl-aslndtul 1'2.1 au!qin~ aql ssoiae alnssald u! [lej aql pue moll ssem
uaamlaq d!qsuo!lelal v 'lndmo lamod aql aauaq pue
au!qini aqi q3norql MOU ssem aql sla!ilsai sapa(q
.ad61 uo!laeal l o aslndm! ue jo s! au!qlnl pax!j luanbasqns 11spue iaju! au!qJni aql jo salzzou
'JoroJu n i p e se u~nouyijeqs h\o[joq papuedxa L[iea13 aqi iaqlaqm uodn iuapuadap sk..sapelq 3u!~om aql u! aql ie paanpold doip alnssa~d a q s 'jlasq au!qlni
e Lq paaeldal ale s~s!p aqi 'pealsu~ ,a[qe!hun sas!p aql uo uo!la!rlsal e s! I! peol 3u!anpa~ JOJ sahjeh
saxem au!qIni uo!laeal aql j o sapelq 3u!nom aqj ssome aglorql u! [njasn s! doip alnssald jo jaajja aqi i s j ! q ~
doip alnssald e jo aJuasa~da q s 'sas!p aql ssorae loiaah Li!so[ah fea!dLl e smoqs 8.1 a1n3q (a[q!ssod Aqoedao fiU!MOllaMS 1'1.2
saaroj ainssald ou alojaiaq) pue sapelq aqi ssorse sa 008j 01 I E ~ U se s! paulnl s! mea~s<.a~ltl qq~!qm
dolp alnssa~dou s! alaql aau!s [(ems s! ~ o i aqi o ~ uo 'sapelq 8u!nuc11, A I I qznozqi ajBue aqi 'Ljleapl 'a3IOJ e 01 alojaraql pue urn
lsniql je!xe aqL ' ~ j e q sialame!p ljems e 01 paqseile u! meld sayel L31aua [ea!ueqaam 01 L81aua s!la\!ly 1" -"amom u! a3ueqa e 01 as!, sah!3 q~!qm meals aqi JO 'ayen aqi ssorae dolp
10 q i ! ~je.i3a1u! laqi!a ale qa!qm sas!p uo pa!i~ea ale iro!srahuoa ley1 .ia![rea passails iu!od sqi s~s!*!lijrllil,l uo!lom jo uo!lsal!p u! a3ueqa e saanpold sapelq aql a ~ n s s a ~aq1
d 3u!sea~su! pue ,nojj ssem ssal 3u!ll!mlad
sapelq 3u!nom au!qim-aslndml ,su3!sap au!qinl aq) u! s ! q ~ ,(I&) sapejq 3u!~om aqi 3u!ialua olrals , I ~ I 1" uo meals aqi jo iuama3u!dm! a q s ' ~ j e q sau!qrnl aql
sasua>ajj!p iue~!j!u3!s ale alaqi leqi sueam 3u!pe[q 0s 'eale anleh aql Bu!anpai Lq paqs s! peol slow 'pea[
Li!ao[an an!ie[al aql uegi ssa( s! ( 2 ~ sapnlq
) :I~I!,AIII!I uo xiom jE3!UEqJaW oiu! LB~auas!iau!y si! lrahuos pun paqs 01 pasn s! pue Su!y~ro~yr sa umouy s! s!qs 'dorp
uo!oeai pue asjndm! jo ss!ls!ialsereqs iua~sjj!p s q ~ aql 3u!hea! meals aql jo Ll!ao[ah ah!le[a.l at1.L. ' l i l ~ l i i l l ! l l ~
sapelq paxlj i o avzou e II! pa)eia(asae uaaq seq ]ern ainssard pue L ~ O I I U J u! asasmu! a31ej e jo asuadxa
ufi!sap au!qrn? uo i3a483 &'z'z LI!JO!~A 33elS adL~-as[n(im![e>!dLl e SMOL[S 6.1 : > t i ~ i I i [ meals an!aaar a3eis au!qlni e jo sapejq Bu!nour a q ~ aqi le inq 'anjen iaju! anjen agi ~e Ldjeqiua aqi 3u!
sapelq 6 u ! ~ o m Z'Z -n!eiu!em jo imjja aql seq s!qs 'ieaqai [eUO!lJ!lj 01
L ~ J ~ U~!IJU!Y
J p a i e ~ ~ u asi!
3 ~ j e3u!i~anuoa ' a ~ j e hsin
qSno.lr(l Bu!ssed ralje Ljp!del spuedxa meals aql aiaqm
'sah[en l o ~ l s h o 3autqlnl u! slnaao s!qi jo aldmexa u v
'sjanal lasuapuos d o ~ pa ~ n s s a l danleA w e a l s 1 ' 1 ' ~
lueisuoa le u!emal suo!l!puoa aql aiaqm pua isneqxa
aql molj Llan!ssassns paienlena aq uea i!un aql jo
a3e1s qaea la sarnssald aql ' ~ o [ pa~!nbal
j aqi 3u!mouy '(Lblaua J O 61!1!qej!eAe u! s o [ ) Ldoliua u!
pue 'au!qlm aqi r o j eiep ISJI 10 u3!sap raqira worj asealsu! pue alnssard u! ssol e inq 'Ldjeqiua awos jo
pau!elqo aq uea x luelsuoa ,riel asd![13 aqL 'p!n[J uo!luaial aql s! ijnsar a q s ' ~ e a q(euo!lgrj 01 pailanuos
Su!yiom aqi s! meals alaqm ( ~ ' 1 )uo!lenbx u! iiah!3 aq 01 ;\31aua ~!iau!y pai~raua3 aq1 jo auios sasna3
uo!srah xjr 3u!sn Lq pau!e]qo s! L s e l n ~ xiua!a!jjns a p o u aqi puodaq meals jo oo!suedxa aqL '(Ldlaqlua)
'L[je.iauat) 'ail!qlm B uo pea[ [e!lied jo s l x j j a a111 lea11 jo aslladra aql le L3iaua 3!1au!~ sa.i!nbae I! 'a12
3u![lapom uaqm [ooi jnjasn r! s! ,riel asd!l[x ail^ -7.011 ro S3!J!lO mo.lleil e i(3nolql sassed meals uaqm

suo!iei!ur!i indin0 L'Z


'a.1aq1doq) leaq aqi
J O a3uasa1d ail1 01 slip sapelq 3u!nom JL[I qsnolqi
Li!~o[~n n! aseaisu! aql jo asnessq s! s!ql :(I,%) s3pe(q
SU!AOUIaql 3u!ra1ua ruesls all1 jo Ll!aojan an!le[a.I lndlno pue A3ua!3!4)3 2
aqi ueql ia1ea.13 s! (ZM) sapulq ~U!AOUI aqr 3u!~es[
wears agl jo Ll!sojah an!le[ai aqL 'wer8e!p Ll!aojan
a8es adLi-i~o!)aear lea!dLi e smoqs 01'1 am8!d
Li!~olan ow! do.~pleaq 3u!iranuos Lq sapelq pax!j
au!q.inl as[ndm! agl se LaM awes aqi u! aheqaq sapelq 'Eal8UI![3 IS3UIIBM
pax!j a q .Li!~o[an
~ 11! dolp lau e asnes 01 lua!a!jjns aqi u! usna 'mnm!ido aql L[aier a.ie sanleh q3!q qans
1011 s! I! Inq molj ail1 jo ~ o ! ~ a a ~ J!Op aBueqa aql 01 :ieqr pamoqs oqm lreqm 06 ahoqe s! ~ l n s s ~ isneqxard mniu!>do aql alaqm
anp sapelq Su!~om aql u! s ~ n a s oosle aslndrn! a m o ~ [$I 1adne.t~Sq ush!S s! s!s,(jeue an!suaqa.ldmo> aiow V smalsLs z~ 09 u! uo!in(os pallajald aqi amosaq L[uo
,sspelq 3q1 3u!~e3(molj ail1 01 no!isar!p sl!soddo aqi .a.~nie.iadmaiainjosqe iaju! aql s! 'L araqm plnos ssu!q>sm u!iu/r 0 0 9 ~' I S ~ I I U OLE ~ 'sainieiadmai
u! uo!isesi i o isnlql e Sir!leai2 'sapalq Sil!houi sql la isiem 3u!(oo3 isamo( agl ql!m sa!.tliInos asoql u! '-a-!
Ll!so$a&weals o! as!. I? LI! S I ( I I S ~ I s ! q ~'sapti[q SO!AOU~ ' Y ~ I I I S S J JI ~ S ~ B mnm!ldo
~ X ~ lsa,noI aqi i o j [es!ruoiIosa
ar[i it! 3u!.~sn~so j[nq 3u!u!u~1a~aqi 'sspejq 1pax!j 3'11 II! ,(ai[.~'[E]
a.iour aq ,(ew iroiap[s)l
ssi~!il~em
plie s!i.ie~
u ! ~ ~ i / hq
i0051aparit
lei[l uaaq
ales!p11!
set(
s i n ~ s adosp lea,[ aYe~sagi jjerj ,([uo 5snr?xq pasn ?BM
uo!laear %OSuusi s i j san!qrrii
~ , i ~ o ! i e s%o~/as[ndro!,
~ :aioieiadmal lalo! jo lsajja sma~shsi . O< ~ I,! Sa:I!qJeK~ meals-paleriiles roj paads
p m m i aq ~ I I ! O L [ S S ' ~ L I !~~~. I IsI ~
n ~ u ~ ,([I~!>IS
y v ~ d s st11 ~pn[?u!01 pxj!pomi isle! sem d!qsuo!le[ai aij.~. J O 53!040 Jljl j O Ma!AS.I ~ A ! s u ~ L ~ ~ . ~ V
c ~ L'53p\.13S
U O ~ XI!
au!qlnl adAa-uo(aaeau 2'2.2 '.,ni?-lasd![[;[, aql re umooy s! rl~qs~~o!lejas 1131(1 1311!1[38111 183qi~tIn~ j)33tI~-j[lljJql 10J I I J A O I ~PUI?
Efficiency a n d oi~tiiill

* !,til Iiijt:<, l,l:i~~t\\iia being designed in the iatc


ti!il:. i,ii!l i.;iily I9hOs lhcrc were no analytical tools .. I . . : '~.r . . '
\hrork done by inoving blades t.5 ~ i I , i i ~ l1 i1 , i.~~iiliilcnily $predict the three-dimensional ...?. ', 4 , -
Biadc efficiency (7) = -. . : ,
Available energy i.tiiiii, ( $ 1 ilir llr,<v i n 1.1' cylinde1.s. Today, traverse
i i i r i * , I , 1iii.i.1. ~uliirlrines reveal the significant radial
siiii!,itii!i.itri (11 ,'elocitg in the highly divcl-gent flow.
For the simples1 case we wiil assume \hi, = W , and 13
= 8 (no friction present) as shown in Fig 1.9. i6ii1i111ji1~.: 111 i I ~ ~ ~ i ~ g lanalysis
~ - f / o now
~ employed
For the work done WD = mUAV, where m is the t i + i i i i l l 1111- vi~iri~li~tioii i n detail of tile flow around
c r * i i i t t ~ l i ~ l ~ l iblade, ~ ~ i l using modern computational
mass flow rate and AV = W,cos 8 + W2cos 0 =
2W, cos 0. Also, W , cos 8 = C,COSa - U. Therefore ic-;iiriiijirar, iund Ihavc enabled the complex flow fieid
iii 1 I+ iyllt~tlclslo hc analysed effectively. These methods TIP
WD = mUAV = 2mU (C,cos a - U).
li8rz: Ijrnt, rufincd and validated by input of data
The available energy to the rotor blades is that
f l i * r i i I'Itiw nlusscirement probes on model turbines in
delivered by the fixed blades = (mc,12/2.
Hence 7 = 2mU(C,cos a - U ) / [ ( m ~ , ) ~ / 2 1 iiiirli~iliirltrlcra' usorks and on full-scale machines in
i i i v l i r : 'lltc ilcctliacy o f prediction of flow is now
= (4U/C,)/(cos a - U / C , )
$..Pi.
,t, , C ~ I I C Ilhli!rling can be designed to obtain the de-
= 4<(cos a - 0 slir-ii Il!ri.r.ilixnrasi~~~~al flow pattern. Modeit1 finai MEAN
*ifi?i. liliiliv* iur iu,isted considerably, since the flow
Flii 1.1 l Ideal elliciency curves
1 G rii Itr 11io!.1coniplex at the exit plane. The cross-
This describes a parabola and is shown in Pig 1.11.
- c ~ i ! I i i i i i i l iircil i ~ tthu tip is only around 15% of that
The maxinium value of efficiency may be derived by
ilil l t , i > I (I.?? 1.12).
differentiating the above expression with respect to
U and equating to zero. In reality there are a number of factors that affect
blade efficiency and these wiil be discussed in section
2.3 of this chapter. T o achieve the best efficiency foi-
both designs, reaction turbines require twice the num-
ber of stages of an impulse turbine. This is because
Therefore qmri = cosZa when t = cos a / 2 . By the high velocity ratio (U/C,) for the reaction turbine
inspection of Fig l . I l , it can be seen this occurs means only a small heat drop can be accommodated
when the outlet velocity is axial ($ = 90'). at each stage.
FIG. 1.13 LP lait stage velocity profiles

Ideal reaclion-slage blade efficiency 2.2.5 Modern blading designs


For an ideal 50% reaction stage the velocity diagram Modern turbines are neither purely impulse or re-
to change the direction of the incident velocity o f
will appear as Fig I . 1 1 . Since the fixed and moving action but a combination of both, for the following
blades have the same shape, 0 = a and 0 = $, AV the steam relative to the moving blade, so the blade
reasons. lmpulsc turbines began ernplo)iing reaction
inlet angle would not line up with the direction of
= 2C,(cos a - U). Therefore, WD = mUAV = of up to 20% at the root of the moving blades in
the oncoming steam fiow. Furthermore, the leaving
mU(2Clcos n - U). order to counteract the poor efficiency incurred from
velocity would depart substantially from the axial
In a reaction stage, there is an enthalpy drop across zero or even negative reaction. On the other hand, I!( 1.1' last inovins blade
I I? stage direction, thus increasing the leaving loss and reduc-
the moving blade as well as the fixed; the available reaction at the root of reaction turbines has come
ing efficiency. This is overcome by changing the shape
energy is therefore: down to as little as 30-4090 resulting in the reduction
of the moving blade section. The outlet angle is re-
o f the number o f stages required and the sustaining
duced to restrict the flow area so that a pressure
of 50% reaction at the midpoint. Today it may be

.
'li! Ill~trlrit~ethe point let us assume, for the drop develops across the moving blades, and the
more accurate to describe the two designs as:
ritiiijralll, 111111 the final stage is designed to have a steam leaves the moving blades at a higher speed to
and since by symmetry W 2 = C , the available energy 'Disc and diaphragm' turbine, using low reaction isI11y low degree of reaction at the base diameter, offset the higher peripheral speed and arrive at a n
= m ( ~ -, Wi2)/2
~ furthermore W j 2 = C i 2 + U2 - blading. lioet lltr gcriphery of the rotor disc. The fixed and axial leaving velocity. This causes the pressure drop
2 C , U cos a , therefore, available energy = m / 2 ( ~ , ' - riliivitlK bllldc profiles are then as shown in Fig 1.13. across the fixed blading to fall in order to maintain
u2 + 2CiUcos a ) 'Drum-rotor' turbine, using high reaction blading [21. l , 118 ~ t!o\r2 move to the region half-way up the the same pressure drop over the stage as a whole.
ti~iiti~!ji lilttile, i.e., to the stage mean diameter. Typi- There is therefore a substantial degree of reaction at
and hence e?rlIv, ol! modern blading, the tip diameter is about the mean diameter. Figure 1.13 shows the effect that
2.2.6 LP t u r b i n e blading cii<iclilc ( l base ~ diameter so at the mean, the blade increasing reaction from root to tip has on the profile
7 = 2U(2Cicos a - u)/[(c,)' - U2 + 2CIUcos a1
Steam passing through the stages of an LP turbine ex- jriltli ( i . ~ ,lhc , circumferential distance between ad- and on the velocity vectors at root, mean and tip
= 2((2cosa - <)/(I - E2 + 2 t cos a ) pands rapidly and accelerates to a high velocity, often Jilt:r*l!l hl!irles) is about 1.5 times the pitch at the base sections.
and supersonic. Steam at exit from the cylinder can have rlii~~rtrrlor. 'l'l~eperipheral speed of the blading is also The effect o f these changes leads to a more order-
qmax= 2cos2s/l + cos 'a when € = cos a up to 10% moisture content. The flow then is complex I ,1 l l l t ~ t ' a tta prcal as at the base. If the same moving ly streamline flow with substantial increase in the
and the design a f LP blading reflects this. The blades lilsilt: uurllllt~ was used at the mean diameter as at efficiency of LP turbines. The pressure losses after
are long and have a highly-twisted profile so that the Ills i,itcr, lllr flow passage through the moving blading the last stage moving blades (proportional to the
Figure 1.11 shows the diagram efficiency of a reaction inlet and outlet angles conform to the three-dimensional ~"ctitldI ~ Pre~~dered incorrect by the increased pitch: velocity squared) have also been reduced by achieving
stage in comparison to the impulse stage. flow characteristics at all blade heights. wiillbl lhi. cl'fcct o f increased blade speed would be a reduced and substantially uniform velocity over the

10 11
The steam turbi~ie Chapter 1 Efficiency and o ~ i t l ~ ~ l i
-.

annuiai region i~ii~iicdiaieiydownstream o f tilc last ::l 4 l>ic+c; w i n d a g e 2.4 S t a g e eificiency a n d t h e condition line
stage biades. A further beneficiai effect o l reducing
iiii,, I ti,c iriclioii ioss due to the surface friction
crowding of fro\\' at the blade-tip is that tile excessive
i !, ~,iirii t,ti ~ i r ciliscs of an impulse turbine as the disc
steain leakage over the moving blade-tips, which did
~,,:,iic,; ii, tiic siezio~ atm0sphet.e. The result is the 2.4.1 Efficiency of s t a g e
no useful work, has bcen reduccd.
! , i i I ( . i ~ ~ ~01
i ~ si~afl power for an increase in killetic Thc efficiency a f a turbine stage will always be some-
,,itti i,<:iil cncrsy of i i ~ csteam. what iess than ideal because of the lasses discussed
in Section 2.2 of this chapter. Thc efficiency of a
weli dcsigned stage in a modern H P turbine is about
2.3 T h e e f f e c t o f clearances on real designs 8 , Lacing w i r e s 85-90%. This stage efficiency is obtained in the
Blade efficiencies arc far from ideal and the main ll,u ioug blades of the L P cylinder are stiffened foliowing way:
causes of this are aerodynamic factors. The three lii\rwiiila thc tip with iacing wires. Their purpose is
most important factors are profile loss, secondary i t , r i i ~ l i i i j vibrations and raise the resonant frequency Actuai stage heat drop or:
loss and tip leakage loss. These are of roughly the same ( $ 1 lile biade so that it does not coincide with any n =
Isentropic stagc heat drop
magnitude whilst other sources of aerodynamic ioss, i ; . i ' i l i ! ~ ) ~ frcquency present in the turbine. The pre-
such as windage and lacing wires, are much smallcr. ~:i.i~r.r o l these wires, however, produces losses in blade
(entlialpy at fixed biade inlet) -
iil~i.irncybecause of the passage area that they block.
(cnthalpy at moving blade outlet) x 100%
2.3.1 Profile l o s s (enthalpy at fixed blade inlet) -
:. , (cnthalpy at isentropic moving blade outiet)
This is due to the fol.mation of boundary layers on i 2 . 8 Other losses
the blade surfaces. The fluid in the boundary layer 1 liiir ;we further losses which, though not due t o
is subject to viscous forces which slow it down and i i i ~ . ~irsigii of the moving blades, do affect the biade 'This can be more eicarly envisaged through the
increase its entropy relative t o the flow in the main- i i iicici~cy.These iasses are Wetness loss and Annulus use of a rurbhie condition line.
stream. This results in the steam downstream of the 1li.i.L
moving blades having a higher entropy than the steam
upstream. At a given flow rate this would result in a 2.4.2 T h e condition line
larger pressure drop across the blades than there would 2.3.7 Wetness loss The condition line is the locus of the conditions of
be in isentropic flow. Since the pressures in a turbine
FIG. 1.14 Secondary flows 'illis is incurred by moisture entrained in the low the steam as it passes from the stop valve at the iniet
are fixed, the flow rate becomes less than isentropic
prcssore steam towards the exit plark of the L P tur- t o the H P cylinder, through all the turbine stages to
and the entropy of the exhaust steam greater than
itii~e. The loss is a combination of two effects; the the exit plane of the final moving blade of the L P
isentropic. This means the heat drop obtained across
firs1 is the reduction in efficiency due t o absorption cylinder (Fig 1.16). Ideally the expansion of steam
the stage is less than that for a n isentropic expansion
01 energy by the water droplets and the second is through the turbine will occur isentropically, that is,
and is therefore iess efficient. cumference of the moving blades, joining the tips.
Thc shroud is sealed against the casing by several liic erosion o f the final moving blades leading-edges. at constant entropy shown by the vertical dotted tine.
Profile loss is a boundary layer phenomenon and
knife edges.
lil-osion occurs because the water droplets travel In reality the friction effects, such as profile and sec-
is therefore subject to factors that influence bound-
i;ir slower than steam, consequently their velocity ondarv
. . ~ ~ , cause an increase in the heat and entropy
, loss.
ary layer devclopment. These factors are Reynolds The extent o f the leakage depends o n whether the ~

iclative t o the blades is significatltiy different in di- of the steam.


Number, Surface Roughness, Exit Mach Number and turbine is of an impulse or reaction type. Reaction
Trailing Edge Thickness. turbines suffer a pressure drop across the moving
~cctionas well as speed. The result is the impact of -
Figure 1.17 shows a section of the condition line
condensation droplets on the blades, in particular a t displaying one stage only.
blades, so encouraging flow through the clearances.
tllc tip where the blade rotational velocity is highest. H , - H, represents the isentropic hear drop and
Consequently, it is more important for a reaction
2.3.2 S e c o n d a r y l o s s turbine to have good tip sealing than it is for an
In the past, the leading edge has been protected H, -
H , the actual heat drop. Cylinder efficiency
either by a n edge-hardening process or by the brazing- then is obtained for H P , I P and L P turbines by
This is due t o friction on the casing wall and o n the impulse turbine (Fig 1.15).
oo of stellite, which is a very hard material. More considering the heat drop across ail the stages of the
biade root and tip. It is a boundary layer effect and recently, a better understanding of the mechanism of cylinder.
therefore dependent upon the same considerations as droplet erosion has produced means of alleviating
those for profile loss. Figure 1.14 shows how the o ~ u c hof the problem. Higher last-stage heat drops
interaction of the boundary layer phenomenon be- are employed, along with higher mass flow loading. 2.4.3 Cylinder efficiency
tween tip and casing and between root and shaft, 'The result is a higher pressure at the iniet t o the There are two commonly used cylinder efficiency
creates the secondarv flows A and B. moving blades leading to the reduction in the size definitions for H P and IP turbines. The first is the
of droplets. one described above and is known as the internal
efficiency. The second includes the effect of the pres-
2.3.3 Tip l e a k a g e sure drop through the stop and governor valves On
This leakage, as its name implies, arises from steam 2.3.8 A n n u l u s loss the H P turbine and intercept, stop and governor
passing through the small clearance required between This occurs when there is a significant amount of valves o n the IP turbine and is known as the external
the moving blade tip and the casing, or between the diffusion between two adjacent stages or where wall efficiency (Fig 1.18).
end of the fixed blades and the rotating shaft. The cavities occur between the fined and moving blades. It can be seen that, though the pressure drop across
problem is overcome to a certain extent through the The extent of the ioss is greatly reduced a t high an- the valves is at constant enthalpy, the change in
use o f inter-stage seals. At the biade tips there is a nulus area ratios (inlet/outlet) if the expansion o f entropy affects the moving blade-exit isentropic en-
shroud band which extends around the entire cir- FIG. 1.18 Reaction and impulse turbine interstage sealing the steam is controlled by a flared casing wall. thaipy so that:
12 13
The steam turbine Cliaoter 1 Efficiency and outl)ill

ma. 1.16 iilrbiiie candiiioct liixe I:i(i. 1.17 S ~ g ccondition line through the conversion of its kinetic energy to flow
friction losses. This is a constant enthalpy process
since the steam cannot do work on blades that it
has already left. Consequently the steam comes to
rest at the point X on Fig 1.19.
7 (internal) = H 1 - x 100% and Both exhaust conditions are displayed in Fig 1.19 > y derived
!idhi ~ ~ t l l ~ i , l l is from the measured powel The heat loss between the total conditions at blade
H , - H? from which the followine- LP efficiencies can be ci1iili111 iillcl lhc slatic isentropic enthalpy is normally exit (HZ)and the static pressure line (H,) is known as
obtained: tdLt81i 111 ~ . O I I ~ C I I S C Ipressure. TT/TT efficiencies are
H, - H2 the leaving loss. The significance leaving loss has on
7 (external) = x 100% liiit~i)~ii~lly dc~.ivedfrom wetness probe (traverse) tests. efficiency can be seen in the following example:
HI - H4 Total Static/Total Static efficiency (TS/TS) 'rt!i:I R F I I I I O P ~ C exhaust enthalpy in this case is at the
klaiJr still (Jene total pressure. Traverse tests measure Leaving loss = v 2 / 2 J/kg
-
- Hl - H, x 100% i$$i:w ~ l l i u h h ltnd other properties of the steam along
For H P and IP steam turbines, the kinetic energy H , - H, line IrcilQBt of a moving blade. The test is restricted where v, is the velocity of steam leaving the last row
effects at inlet and exhaust are small and usually $11 /lie 111011h11rement across L P turbine stages where of blades. For a 500 MW turbine, the velocity v , is
ignored. ~h~ kinetic energy at inlet to the LP turbine Total Total/Total Static efficiency (TT/TS) il~eirIR ~ ~ i l ' f l c i ~distance
nt between stages to permit typically 170 m/s:
is also negligible but a t the exhaust it is not. As lb6 Ilvr llllhhilge of the probe.
170'
a result LP efficiencies are derived by considering thus leaving loss = -2
= 14450 J/kg = 14.45 kJ/kg
either:

The total exhaust conditions - which includes Total Total/Total Total efficiency (TT/TT)
P:4.4 ibnvlng loss This would be responsible for a 2% reduction in LP
~ I C M I I IIVIIVCA the finalstage of an L P turbine with cylinder efficiency.
the steam kinetic energy and is measurable with a
correctly aligned pitot. - - X 100% b l l ~ i i l l ~energy
~ at the total pressure and enthalpy
HI - H i hlilivill 111 Ply 1.19. i f the steam could be slowed down
The static exhaust conditions - which represents iri?iiliitpiat~llylo zero kinetic energy, it would be at 2.4.5 Hood loss
conditions when the kinetic energy has been re- TT/TS efficiencies are usually obtained from heat ajnlli. (>trsxarc and cnthalpy. In practice the steam Another loss which occurs between the final stage
duced to zero and is measurable with pressure gauge. rate tests (see Section 3 of this chapter). The exhaust <Ittau xlll\r down after leaving the last blade, but and the condenser inlet is a pressure drop known as
The steam turbine

hood loss (1% 1.20). Norii~aily the condenser static 2.4.7 Partial admission
picssiire is less tllao that at blade exit, Tlic steam I'arrial adn~iasioiigives a loss In turbine crficiency il
expands ill the Ihood wllich joins the cxliaust of the thc stcan? sugpiy to the turbine is governed by thc
L.P cylinder to the condenser inlet. The cxpansiotr number o f inozzles in use. Thc alternative mcans o l
converts c n t h a l ~ ~ to
y kinetic energy which is theii steanl governing is tlirottle-control, where admission
converted back lo heat by flow friction losses. is over the con~pletccircumference o f the first stage,
In some cases tlie hood loss is negative and the and coiitiol is achieved by reducing the mail1 stcani
condenser pressure is higher than blade-exit static supply. Partial admission is tilerefore not experienced
conditions. This occurs when the steam kinetic enel.gy by throttle-controlled turbines.
is converted to pressure, a process known as dijfusiori. Thc problem with reducing steam flow by the use of
nozzie-controi is that when the blades are aligned with
a norzle group they run full of steam, but when they
pass into a blank arc, eddies are produced, so caus-
ing a loss. The first and last blades in line with the
nozzle group will only be partially full o f steam and
therefore the flow in them will be onsiderably dis-
tuibcd. Thls is often referred to as 'blade windage',
'blade ventilation' or 'vane action' loss.
There is also an additional factor to consider. As
the idle blades come under the influence of the noz-
zles, the steam in the blade passages has to bc ac-
celerated rapidly, so causing a loss In power. The
~nagnitudeo f this loss increases with the work done
per row, the heat drop, the blade speed, blade width
and height, and the number o f steam admissions. This
factor, known as the steam inertia loss, can account
for 15-20% of the total windage loss in a stage with
single arc admission.
In the UK, there are many interconnected units in
service so that each can be kept In efficient operation
at high load. System load reduction is achieved by
shutting down complete units, so that there is no <w
Fxc. 1.21 Simplified ilealii power plant cycle
benefit from the adoption of nozzle control for individual
units. Alternatively, load reduction is accomplished 8..
,f

8
by reducing the boiler pressure, so that the turbine 8
valves are maintained wide ope11 over most of the
!,i~,ii:iscs in a cyclic process. Figure 1.21 is a sim- The main steam, having been condensed in tlle
load range up to 100%. Part-load efficiencies obtained
l i l ~ l ~ r diagram
il of a modern steam plant, showing condenser, is now in a liquid state at a very low pressure
in this manner are comparable to nozzle-governed
iiio)~01' the essential elements. and approximately saturation temperature. This water
machines, whilst the full-load efficiency is better.
011r 11alCof the cycle consists of the boiler (or heat drains from the condenser, where it enters the hotwell.
,~liircu)and its auxiliaries; the other, the turbine The water in the hotwell is pumped by the condensate
ryclc, consists of turbine, generator, condenser, feed extraction pump through the low pressure feedheating
O I I I I I and
~ feedwater heaters. system to another pump, the boiler feed pump.
3 Thermodynamics of t h e steam cycle ('otlsider first the boiler plant involved In the cycle. In a modern regenerative cycle, some of the steam
FIO. 1.20 Hood loss I.r,:dwater is supplied to the boiler drum, where water passing through the turbine cylinders is bled from a
I!, boiled and converted Into dry saturated steam. series of extraction belts located after selected moving
'Illis dry steam is further superheated in the super- blade stages and fed to the condensate and feedwater
llvater and then fed to the H P cylinder of tlle tur- heaters. Thls steam is used to heat the condensate In
2.4.6 W e t n e s s loss
3.1 Development of the modern steam cycle
I~inc.The steam expands in the turbine giving up heat the L P heaters and the feedwater in the H P heaters,
Figure 1.16 shows how the condition line curves sub- This section will outline a modern steam cycle and energy, a high proportion of which is transferred which are o f a surface type.
stantially towards higher entropy values below the then discuss its development f r o ~ nthe basic thermo- inlo work energy on the turbine shaft. The shaft The boiler feed pump increases the water pressure
saturation line. The reason for this is the Increasing dynamic power cycle. Having developed a modern turns an electrical generator which produces electric to a level in excess of the drum pressure, to provide
wetness towards the exhaust in a n L P turbine, dis- steam cycle, the means o f assessing its efficiency and power. Steam leaving the H P cylinder returns to the for the pressure loss in the boiler circuit and H P
cussed in Section 2.2 of this chapter. If the efficiency economic implications will be introduced. boiler, where It is reheated. The reheated steam is feedheating train. The cycle Is now complete.
is adjusted to exclude the wetness loss, it is called the further expanded In the IP and L P cylinders, before
dry stage efficiency. It is common practice to assume passing into the condenser.
that the total wetness loss is proportional to the 3.1.1 The s t e a m cycle In the condenser, which is a large surface-type heat 3.1.2 T h e Rankine cycle
mean stage wetness. Baumann suggested that 1% total A power station operates using a closed steam power exchanger, the steam is condensed by transferring Its Having presented a modern practical steam power
wetness loss be assumed per 1% mean stage wetness. cycle, where water undergoes various thermodynamic latent heat of vaporisation to the cooling water (CW). cycle, attention will now be given to the development
-7:
The steam turbine .& Theifnodynamics of the steam cycle
&+
..-
V' , , . -
of such B cycle 110111 a basic vapour powcs cyclc - steam is expanded thraogli tire torbine iseiilrapicall)~, e No salniated steaill must enter the condenses, i.e.,
thc Rankine cyclc. i . c , u,itlroilt loss. This process (C-D) ~)ioduceswork point D must be within the vapoui boundary (Fig
For the purpose of illustraliiig the various power along liic turbine shaft. F'inally the wet steam issuing 1.23).
cycles, the Temperature-Entropy (T-S) and Entlialpy- from tile turbine gives up its heat in the condenser and
Entropy (H-S) diagrams will be used. An understand- returns lo watel. (process O-A). e The exhaust wetness in the last turbine stage must
ing of thermodynamic properties -- Entropy and The heat input t o the boiler or 'the energy paid not exceed 12%, i.e., DD' nlust be less than 12%

.
Enthalpy is assumed. However, in the context of for' is represented by the area EABCDP on the T-S of A D ' .
the following descriptio~lo f steam cycles, a review of diagram. The work done by the cycle is represented
Entropy will be beneficial. by the area within the polygon ABCD. The heat Material properties limit the maximum temperature
Entropy is an abstract property of steam which rejected to the condenser is represented by the rec- within the cycle.
increases when heat is added and decreases when tangle ADFE. In the context of power generation,
heat is rejected. Its magnitude is such that if the Thermal Efficiency q is defined as:
temperature at which heat is transferred is multiplied 3.1.3 Practical cycle using s u p e r h e a t
by the change in entropy that results in the pro- The first development o f the Rankine cycle into a
cess, then that product equals the amount of heat Work done = (Energy for geneiation)/Heat input
(i.e., energy paid for). Hence the Thermal Efficiency more practical steam cycle involves raising the pres-
transferred. sure and temperature of the steam entering the turbine.
Now consider the simple Rankine cycle for steam, Of the Rankine cycle, based upon Fig 1.23, 1.23 is q
(Rankine) = Area ABCD/Arca EABCDF. The superheated steam cycle is shown schematically
shown scheinatically in Fig 1.22 and on the T-S dia- l t i l , 121 K;$iikise cycle T-S diagram
in Fig 1.24, and on the T-S diagram in Fig 1.25.
gram in Fig 1.23. In the s u ~ e r h e acycle,
t the saturated dry steam leaving
Water is pumped into the boiler by the feed pump The economic implication of cycle efficiency is a ~,q
(process A-B). In the ideal Rankinc cycle, there is no %
.S!
the boiler drum is further heated before entering the
major factor behind the development o f the cycle, . ,...
.:.wlrs!ie lcr~~lil~iil conditions. The effect o f changing turbine. For the same quality of steam entering the
temperature rise across the pump and points A-B are wllil~t maintaining or reducing capital cost per elec- ,
condenser (i.e., same point D), the increase in work done
coincident. The water is then heated to produce dry
saturated steam (process B-C). The dry saturated
trical unit supplied. The other major consideration in *;
9
,E
ie$jir:iiei i-~i~~dltiorrs is dealt with thoroughly in Section
8 i nl i l i l i rltilplcr. However, it is useful to consider is shown o n Fig 1.25. The quantity of heat rejected to
the choice of cycle, is the engineering feasibility of the condenser is the same as for the Rankine cycle.
it!, li4li*wi11,&criteria when attempting to change
* . ; I I I I I ~ Icor~~iitions: Hence, there is an improvement in the cycle efficiency.
,~

FIG. 1.22 Simple Rankine cycle power FIG.1.24 Superheat cycle plant
18
The steam turbine C h a ~ t e r1 Thermodynamics of the steam cycle

The superheat efficiency is greater than the Rankine tlierrnel efficiency from the 7 - S diagram is q(lichia,,=~
efficiency as Area (P + Q)/(I' i- Q i R) is greater (Area ABCDEF)/(Area GABCDEFH).
than Q/(Q + R). "; The reheat cycle benefits from reduced wetness in
This superheat cycle was chosen to Ilave the same the turbine exhaust, but presents an increased capital
turbine exhaust conditions as the ~ r e v i o u s Rankine outlay in terms of reheater pipewoik to, from and within
- A S " , ' ~ , ~ ~ ' cycle. However, a major advantage of superheating the boiler. The turbine is usually split into H P and
$ L P cylinders t o avoid the high thermal gradients
which would be introduced between stages of reheat
o n a single-cylinder machine.
I'
3.1.4 T h e r e h e a t cycle
3.1.5 Regenerative f e e d h e a t i n g
The desire for further increases in cycle conditions and
T o complete the cycle development of the steam cycle
consequent increases in cycle efficiency, led to the
t o that of Fig 1.21, the inclusion of regenerative
addition of steam reheat during turbine expansion. The
ENTROPY, s feedheating must be discussed. Physically, a propor-
reheat cycle is shown schematically in Fig 1.26 and
tion of the steam is bled from various points on the
FIG. 1.25 Superheat cycle T-S diagram o n the T-S diagram in Fig 1.27. Fit. 1.27 Reheat cycle T-S diagram turbine, which is then condensed to heat feedwater
In the reheat cycle, steam at a given initial tem- o n its return to the boiler. Figure 1.28 illustrates
perature is partially expanded through the turbine
the improvement in thermal efficiency for a simple
Area ABC,D (process C-D) doing some work, and then is fed back
~ ( s u P c ~ ~=
Il,e reheat cycle incorporates an improvement in Rankine cycle (Fig 1.29), by virtue of the bled-steam
c ~ ~ )
Area EABC, DF t o the boiler, where it is reheated to about original
i l ~ o i n a l efficiency aver the superheat cycle. The releasing all of its heat to the feedwater, and little
temperature (process D-E). The heated steam is then fed
- Area ( P + Q) through the remainder of the turbine before being
Area (P + Q + R) condensed (process E-F).

flc. 1.26 Reheat cycle plant FIO.1.28 Rankine cycle with regenerative feedhealing
[
20
i1
i
T h e s t e a m turbine Chapter 1 Ther~nodynamicsof t h e s t e a m cycle

3.2 C y c l e e f f i c i e n c y and h e a t r a t e ii leal tul.binc erpaiision incorl>osates losses or ii- H, - H,


l?vcr,sibilitiescouesponding lo an inciease in entropy. HI' cyiindcr ,I =
lie last section dealt with tire theoretical aspects of H, - I(;
steaio cycles. An attempt is now made lo investigate I t can be seen from the Mollier diagram, that for
tile differences betwecn an ideal turbine expansion t i 1 1 expansion between two pressures, the gl.eater the H, -
i'illiopy rise (i.e., the greater number o f losses), tlie I P cylinder 7 =
(one which is isentropic) and an actual turbine ex- H3 - Hh
pansion, leading to expressions for turbine heat rate lusr energy there is available for wo1.k. Refinement
and efficiency. i l l turbine design aims to reduce the losses and in- H6 - H,
LP cylinder q =
The general cycle cfficiency was illustrated with the crease the available energy. Hd --
use o f the T-S diagram: for the turbine alone, eiii- Now consider tile whole turbine expansion process
ciency is best discussed using the Mollier or enthalpy- illlough H P , 1P and LP cylinders on a Mollier dia- In the case of the H P and IP cylinders, these are
entropy (H-S) diagram. A comparison of actual and ~!,i;im,as shown in Fig 1.32. external efficiencies because tlie throttling loss is
isentropic turbine expansions is illustrated in Fig 1.31. included.
The turbine expansion shown is that for an H P cylin- One small advantage of the irreversibilities in the
der, i.e., wholly in the superheat region. 1P and LP turbines is the reduction in exhaust steam
wetness, causing less erosion on the final stazes
. of
blading. The condition of the plant can be monitored
FIG. 1.29 T-S diagranl for the Kniikine cycic by measuring the temperature and pressure of the
will, feedlieating
steam at points between the cylinder, hence deriving
the steam enthalpy. It should then be possible to
compare cylinder efficiencies with the original design
or none to the condenser. There will bc a small values. Turbine blade erosion or steam leakage results
loss of work available from the bled-steam not ex- in a reduced cylinder efficiency. In practice, the L P
panding in the turbine; however, this loss is out- cylinder exhaust enthalpy is not direclly measurable
weighed by the gain in cycle efficiency. and it nus st be derived from an overall heat balance.
The greater the number of feedheaters installed,
the greater the improvement in thermal efficiency.
However. the incremental gain for each additional 3.2.2 H e a t r a t e
feedheater reduces as the number of heaters increases. The principles of stage and cylinder efficiency having
T h e methods of optimising the number of heaters for been introduced, consideration is now given to the
a particular size of plant are covered in Section 4.2. definition of turbine heat rate. The heat rate is deter-
of this chapter. mined by measurement of various plant operating
T h e cycle has now been developed to the modern parameters. These include:
plant cycle that was first considered. Before going
o n to discuss this in detail, the T-S diagram for a Flow rate, using a differential pressure device.
reheat cycle with regenerative feedheating is given in
Fig 1.30. Enthalpy, based on calibrated pressure and tem-
perature measurement.

Electric power, based o n calibrated voltage and


current measurements.

Consider a steam cycle with single reheat and re-


generative feedheating, shown in Fig 1.33.
I
ENTROPY
The heat rate is defined by:
FIG. 1.32 Mollier chart for aelllal turbine exllanrion
Heat input horn boiler (klih)
HEAT RATE =
FIG.1.31 Compaiison of isenfropic and Electrical output from generator (kW)
actual turbine expansions
Using measurements around the cycle from Fig 1.33
The actual turbine expansion line includes the ma-
3.2.1 Cylinder efficiency jor losses encountered: H P throttling loss through
In Section 2, the stage efficiency was defined. Re- llie governor valve and associated pipework; reheater HEAT RATE =
M I ( H I - HO + M I ( H I - H*)kl,kWh
ferring to Fig 1.31, the overall cylinder efficiency is ]pressure loss through pipework (to, within and from P,
given by: the boiler): the leaving and hood losses a t the last
The corresponding thermal efficiency is given by:
fitage of the L P turbine (see Section 2 of this chapter).
FIG.1.30 Rsnkine cycle with reheat and ?l(eylindar) =
HA-HC _- (Useful work done) From Fig 1.32 it is possible t o derive the following -
- 3600
x 100% -
(kW)
regenerative feedhesting H A - H, (Isentropic enthalpy change) cylinder efficiencies: HEAT RATE (klis)
22
'1-lie steam turbine Chapter 1 Tlier~nodyna~nics
of the steam cycle

1 i,. 1.35 Variation of Ileal raic with load for a typical


660 MI\' unit (tliroltle goveined) ENTROPY I

FIG. 1.33 Cycle used for derivation of lieat rate 11


' 4.1.36 Tlle cffccl or increasing temperalare
C: I2eicrioration of cylinder clearances on available energy
AS lclllperal~liei~ incieared from 7 ,to Tj tile available
cnergy increaser, as the slope o f rlle constant pressure line
r !li~lcrioration in feedheating efficiency is greater Ilia" the Condenser picsruie line, i.e..
A means of measuring cycle heat rate having been AIBI > A , ~ I
defined, consideration can now be given to varia- $ I'I!I>I
control of superheat and reheat temperature,
tions between the design heat rates auoted bv the Il~i~tliciilarly
in older designs).
turbine manufacturers a n d the heat iates achieved in entropy. As the temperature is increased from T ,
in operation.
1:~clors become more prevalent as the plant to T,, the available energy increases, since A,B, >
First, consider the variation of the hourly heat o iili,.~.
AtB,.
consumed by the turbine-generator with th; load
produced. This characteristic is known as Willans
line (Fig 1.34), and is based on turbine test runs at
8
$
so
1 iiyt;i
Now consider the effect of increasing the inlet steam
pressure at a constant temperature. The additional
available energy is shown on Fig 1.37. The increase in
100%. 80%, 60% and 40% load. It is British practice
to specify performance and test at these four loads,
$ available energy is less than that for temperature for
8 :$,3 'Terminal conditions the same entropy change. The significant advantage
A linear relationship exists and extrapolation to the 3
no-load output condition reveals a no-load heat con- !I! I I l i h tieclioll, the effects of certain terminal con- of increasing both temperature and pressure is illus-
/' d!ilblllh 01' the steam cycle are considered in detail. trated on Fig 1.38.
sumption of about 3% of the full-load value. The
/' l i l v illlplrcl on efficiency is evaluated and the con- There are limitations to the selection of inlet steam
variation in heat rate with load (Fig 1.35) shows the Po- /' SllsI!llx l'ttced by the designer are discussed. conditions. As mentioned in the previous section
high thermal cost of operating plant on part-load.
The optimum heat rate (i.e., the minimum condition)
/
/
'' there are criieria which affect the choice of inlet
conditions:
should correspond to the design output (100% load).
The major contributory loss comes from the throttling 7
NOLOAO HtATllCONSUMPiION 8.7 Effect of steam inlet conditions
20 10 80 80 100 Maximum turbine exhaust wetness 12%
loss across the turbine governor valves. The effects LOAQ UMCR I'llilly, consider the effect of steam inlet conditions
of throttling are discussed later in this chapter. l i t I l l ? turbine. The temperature of the steam supplied No dry steam to enter the condenser
Operating the unit at part-load is one of the 111 !llr lurbine stop valve is a major factor in the
'external' factors preventing the achievement of the PIG. 1.34 Willans line for a typical 660 MW unit r v c l i sl'l'iciency and the efficiency of the turbine in Metallurgical constraints on the choice of turbine
design heat rate. The other major external factor, r~iilvollinp available energy into work. The effect of and boiler materials.
which increases average heat rate, is the need to start l l l i i ! ~ l l ! ~ i t lthe
~ steam inlet temperature for a turbine
the unit as required by the operating regime. During Plant operating losses cause the other major in- u;t(%i~lidill[t between set pressures is shown on the
start-up, the unit is unloaded and additional works crease in design heat rate. In practice, turbine heat Ml~lllcr diagram (Fig 1.36). The expansion process The metallurgical limit on temperature is 565°C for
power is needed for start-up systems. rates increase due to: i.ll!iwti is 1'01 a single-cylinder turbine with no increase coal-fired plant brought into service with the CEGB
24
T h e steam turbine Chapter 1 Thennodynumics of t h e steam cyclr

lhas bcen mcntioocd in previous sections and is iniin


discussed in more detail. Simpiy, the effect of p s c .
sure ioss anywlicrc in the steam path causes a loss
in cycle efficiency by reducing the energy available for
conversion into work.
Vaivc gear at the inlet to the H P and 1P turbines
is used to control the inlet mass flow and hence the
load on tile machine by a throttling process. Figure
1.41 shows a Maiiier diagram comparing the condition
lines of a reheat turbine at fuil ioad with ail the
valves wide open and one at part load, where the ioad
has been reduced by 40% by throttling on the iniet
valves to the H P turbine. Other pressure losses are
neglected. The throttling effect is to reduce the inlet
pressure by a constant enthalpy process (represented
by horizontal line AB). The result is a ioss in en-
tropy and also a slight fall in temperature with some
reduction in the availabie heat drop. This accounts
for a small loss in efficiency. However, the major
flow reduction which results is the main reason for
the reduction of work done in the H P , IP and LP
cylinders. in this example, the condenser pressure is
assumed to remain constant and the pressure drop

FIG. 1.37 The effect of Inereasing presshire on ria i 38 The effect of


fempeiaiuic upon
mereasing borli prerniic and
avallabie energ)
?
available cneigy
A S P ~ ~ S S U T inere86e~
C from P I to P3 the available energy
increa~c~, a$ the slope of thc condenser pressere line is INleoP".S
greater than the temperature iine, i . c , AIB1>AiBI
I 4 1 1 'l'liu U I I C C ~ iif variation in relieat iempciatuie

over the years 1960 to 1986. This limit reflects <s


a compromise between ease of manufacture, creep d
z.*.
4li!iitil1lJi i,:dl!cin~ 1,P exhaust wetness is desirable,
strength and cost. The practice on CEGB 500 MW .$
and 660 MW sub-critical units has been to select a @
-4
(jrri i!i$di i t I~:!~lperaturecould iead to some diffi-
. r(rlline i+illi mi~lcrials.The common practice has been
pressure of 159 bar at the turbine stop valve.
!I;t~iirilt 10 I11c original superheat steam condition,
$.<, w*., ,
..*,. .11;(

3.3.2 Effect of r e h e a t conditions Allt!il!r~ important factor in the design of the re-
ti.-.- .
,nar~-i14llllc cffecl o f pressure losses in the pipework.
Now consider the selection of reheat conditions for
T
P/ fits jslwhllr~loss ~.esuItsfrom a throttling effect which
a single reheat cycle. Having established the steam
conditions at entry to the H P turbine, there are several , @$i!$v~h IIM ovi~ilableenergy for work (to be discussed
$$$elill lllih ~eclion).The oressure at which steam is
design com~romisesinvolved in the choice of reheat IN 11b0ut 25% o f ' t h e stop valve condition,
pressure and temperature. First, consider the boundary
conditions. The H P cylinder exhaust steam must be
sufficiently superheated to avoid any wetness in the
--.
WETNsESLlMi,
@
118 llpproximately a fourfold increase in
W@1811v. 'Thih necessitates the use of increased ~ i o e
ell are expensive and inflexible. The ;lait
cold reheat pipework, which would cause severe ero- IIIII~to weigh the merit of using larger pipes,
sion. As in the previous section, the exhaust steam
from the L P cylinder must be wet, but not greater fg
.?&
98 {Ape ~trtlsin parallel, versus the improvement in
@ p i # alflcicncy. The usual pressure drop is 7.5 to
than 12% wetness. These boundaries are illustrated, I@+% irl lhc HP cylinder exhaust pressure. Finally,
together with the effects of changing pressure, on ~4NrIliiinla will exist in the boiler on the range o f
the Moilier diagram (Fig 1.39). Now consider the
effect of changing reheat temperature for a constant
pressure drop in the H P cylinder (Fig 1.40). The
effect o f reducing the pressure or of raising the Eftact of pressure loss in pipework a n d
temperature of the reheat steam is to reduce L P Fia. 1.39 Boundary conditions for a rehcat line and the FiO. 1.41 LOPSof available energy due lo throttling
exhaust wetness. effect of changing pressure at constant ~empeiilture !cl o f pressure loss in pipework and valves the governor valve

26
The steain turbine Chapter 1 Thermodynamics of the stcaln cyclc

across the tiil-bioc cylinders is coiitroiled by liie Ellipse and its development to the current reheat cycic used
law relationship described in Section 2.1.2 of this 4 in CEGB fossil-fuel and AGR power stations.
chapter.
Pressure losses along pipe suns can bc caiculated
using equations and charts 161. Pressure loss is associated 3.4.1 S t e a m conditions
with pipe diameter, of surface roughness, steam flow rate The effects of increasing turbine stop valve pressure
and the pipe geometry (number of bends, expansions, and temperature and the effect of reheat have been
contractions). Simply reducing piping losses by re- discussed in regard to cycle efficiency in Section 3.3
designing pipe runs, or by adding to the number or of this chapter.
pipes, may increase the capital cost of the plant in It is also relevant to consider the major influences
excess of the benefit gained in running costs. on turbine efficiency. The most important factor in
t
turbine efficiency is blade length. Generally, an in-
crease in blade lengths implies reduccd leakage losses
3.3.4 Effect of final f e e d t e m p e r a t u r e s and secondary losses [5,7].
In the previous section, the concept of regenerative E/ A n increase in steam pressure at a given steam flow
reduces thc volumetric steam flow and hence reduces
blade length. Increased steam pressure also requires
thicker casing walls and larger horizontal joint flanges
and joint bolts. It also implies thicker steam pipe
walls which require additional length to obtain the
required flexibility. These difficulties are only partly
surface. In order to avoid a n increase in the stack I M~ATSUICTED I mitigated by the reduction in casing size and pipe
temperature, the air heater would have to be increased I i diameter made possibie by the smaller volume flow.
rNT"oP".S
in sire, and the cost o f this would exceed any sav- Another important effect of increased steam pres-
ing on the economiser. Consequently the ecollomic sure is the requirement of increased pumping power
F $ ( i 1.42 The effect of condenser saturation icmneraluic
optimum feed temperature is somewhat lower than on cycle work done
to raise the feedwater to the higher pressure.
the thermodynamic optimum. It follows that increases in steam pressure are only
Raising the final feed temveraturc also has imoli- ENTROPY S
a benefit in practice when associated with a n increase
cations for the design o f the'^^ turbine. Past prac- in unit size and/or an increase in steam temperature.
tice has been to use bled.steam from the HP turbine However, there arc several plant constraints affect- An increase in steam temperature has the effgct of
exhaust. The saturation temoerature o f the bled-steam ing the selection design exhaust pressure. Consider I,, clfeei of exhaust presmlre on turbine increasing the specific volume and hence blade length
the effect of lowering the exhaust pressure on the tur- expansion and therefore tends to increase turbine efficiency with-
controls the maximum feed temperature obtainable. %

To provide steam at a higher pressure with a higher bine condition line on the Mollier diagram (Fig 1.43). out any increase in unit size. There are vractical
saturation temmrature, rewires steam to be bled Expansion to a lower pressure results in increased disadvantages, which include the required increase in
from an intermediate point b n the H P cylinder. This wetness, and increased specific volume at the exhaust. 1 Ihr 1.1' turbine exhaust area affects casing size and pipe diameter, and increased thermal
is an additional complication and cost to the turbine The increase in exhaust wetness tends to increase I rii811 o f machine, in particular the ther- stresses especially when starting and loading.
plant. Despite the increases in capital cost, the benefit the erosion of the last-stage blades. However, more 11 01 lhc condenser (see Chapter 3). The
The influence of the combined effects of tem-
from improved cycle efficiency is such that the addi- significant is the effect of increased specific volume, I 1 0 plovide a certain volume flow rate perature and pressure changes and turbine efficiency
tional heater is worth including. implying the need for a higher volume flow rate. lit; ronfipufiltion of the L P cylinders since considerations on unit size can be illustrated by a
The design of the Advanced Gas-cooled Reactor The volume flow rate through the condenser is the 91 I ~ ~ C 4 I I double-flow L P cylinders may be
study of the 'standard' steam conditions specified by
(AGR) has resulted in limitations on the finai feed product o f the mean steam axial velocity and the 111 pi~rilllel to give the desired flow rate.
the BEA and CEGB from 1945 onwards.
temperature. The feed train is curtailed in order to annular exhaust area. The annular exhaust area is otid size of the chosen arrangement o f Table 1.1 has been simplified by the exclusion of
limit the final feed temperature to about 150°C. This limited by the maximum length of L P blade. At 3000 nl'lccts many other areas of design - the a number of units of close to the 'standard' 60 MW
limitation is imposed because of the allowable tem- r/min, the centrifugal forces o n the long blades be- lllicr; the plant arrangement; size of civil size, some of which employed reheat. It shows the
peratures in the gas cooling circuit. come very high and there is a limit to the mechani- general trend.
cal stress which blade roots can sustain. Hence, having rodoced all factors against decreasing There is a progressive increase in unit size accom-
established a maximum annular area, the increase in rrc, i l ~ edesign compromise is once more panied by a series of step increases of pressure and
3.3.5 Effect of e x h a u s t pressure volume flow rate must be accommodated by an in- ~pl'o~'cmentsin cycle efficiency versus the temperature, with a few notable exceptions. The main
The efficiency of the cycle is strongly influenced crease in exit velocity. Steam issuing from the last ity and therefore reliability exceptions are the two 375 MW supercritical units
by the L P turbine exhaust pressure. The back pres- stage o f the turbine with high residual velocity re- IIIIIY, a major factor affecting the choice for Drakelow C, commissioned in 1967-68 and the
sure of the condenser sets the saturation temperature presents a loss of kinetic energy. This kinetic energy p~r'ssure is the ambient temperature at two 550 MW cross-compound units for Thorpe Marsh,
at which the expanded steam rejects its latent heat performs no useful work on the turbine blades and ('\I1call reject heat. This factor seasonally commissioned in 1963-65. These units could be said
of vaporisation to the cooling water. Consequently, therefore is a loss of available energy, known as the tin Ihrraial efficiency of the plant. to have been ordered before their time and have not
changes in back pressure affect the temperature of 'leaving loss', and varies with the square of velocity. been followed by further development.
cycle heat rejection. The effect of a change in con- The other loss associated with the turbine exhaust is The steam temperatures can be seen to reach a
denser saturation temperature on the cycle work done the 'hood loss', which defines the hydraulic pressure plateau of 538°C and 565°C. The 538°C limit applies
is shown on a T-S diagram in Fig 1.42. Generally, loss between the last row of moving blades and the to oil-fired units to avoid the use of austenitic ma-
a low exhaust pressure is sought as it improves cycle condenser; this also varies with the square of the terials in the boiler. These suffer heavy corrosion due
efficiency. same velocity. @,'lion deals with the superheated steam cycle to the sodium and vanadium content o f the fuel oil.
29
T h e stearn turbine Chapter i Thermodynamics of the steam cycic

into superheated steani \+'itllout hoiling in the acccplcd


sensc. The latent iical of vaporisation is ~ . c i oand,
since the densities of the water and steam arc thc
same, there is no wcli defined water-to-steam rransi-
lion interface.
A brief explanation from physical data source may
be hclpful. Water at high temperature consists of
Bisckwall clusters of molecules held together by strong potential
P0illi
binding forces of short duration. Thesc clusters pci-
Uckaioutli
mil angular a r linear displacement which gives rise
Castle t o the liquid characteristics.
L)onnisg,on
Evaporation of a liquid into a gaseous space nor-
Feriyblidgc tl mally consists, at the molecular level, of a surface
Biytlie A molecule in a liquid cluster acquiring sufficient thermal
Higll Marnlla81l (and thus kinetic) energy to overcome the potential
Biyllle B binding forces of ils neighbouring inolecules to b x a k
Thorpe Marrll away clear of the cluster and leave the surface of the
U',,, Thuriock
iiquid to enter the gaseous space. The binding forces
between the surface molecuie and molecules well below
Tilbuiy B
the surface are not significant as potential forces drop
Drakelow C
off extremely rapidly with increasing distance. Liquids
Wcst Hllrlon subjected to high pressures logically require higher
Grain thermal energy, and therefore higher tempcratuie, for
the surface lnolccuic to break free of the molecular
cluster. At supercritical pressures, the potential forccs
exerted between molecules in a niolecular ciuster are
The 56SPC limit for coal-fired plant is to avoid a t the blading.
too large to bc overcome by increases in thermal
increasing costs due to the extended use o f austenitic The IP turbine casing has t o provide openings
materials t o avoid creep failure. Creep is the phe- energy and hence n o surface molecules escape from
large enough t o pass the exhaust steam on to the
nomenon o f slow progressive yielding which occurs the molecular clusters. However, as the supercritical
L P turbine at moderate velocities without unduly
at high temperature. In the turbine, it leads to re- reducing its stiffness. The casing inlet end must be pressure fluid undergoes a temperature rise, the aver-
duced clearances and increased stress levels over a carefully designed to reduce thermal stress. age size of its clusters diminishes. With further in-
period of time, and in the boiler (where temperatures The pipework to and from the reheater and in the creases in fluid temperature, the molecular clusters are
are higher) to time-dependent tube failures. reheatei section of the boiler represents a significant reduced to isoiated molecules and all traces of any
Current worldwide practice for modern large units storage volume. it is therefore necessary to supply form of crystalline structure has disappeared. Thus
is to limit steam temperatures to the 540°C level. additional valves to protect the turbine from over- the supercritical pressure fluid acquires its steam-like
speeding in the event of a sudden ioss of load. As in qualities not by evaporation of isolated surface mole-
the H P turbine, these valves must bc in serics-pairs cules, but rather by the gradual diminution in the
t o provide back-up in the event of one valve failing number of molecules contained within moiecuiar
3.4.2 Reheat
to close when required. They operate at the same high clusters.
Table i . i also shows the general adoption o f reheat A double-reheat supercritical cycle can show ap-
for all units over 100 MW. It has been shown earlier temperature but must be considerably larger than the
H P valves. T o handle the flow, up to four sets of proximately a 3.9% efficiency advantage over a single
in this chapter that reheat allows a closer approach
valves may be provided. reheat subcritical cycle (242 b a r / 5 4 O 0 ~ / 5 4 0 'compared
~
t o the ideal Carnot cycle. Its adoption has cost and
with 166 bar/540°C/540"C).
design significance. There is, of course, the require-
For single-reheat, the reheat pressure is commonly
ment of additional piping t o and from the boiler,
about 25% o f the initial pressure while for double-
the latter requiring high temperature with larger bore 3.4.3 Double reheat reheat the first reheat is usually at about 30% and the
size than the H P steam pipes. The higher volume
flow of the reheated steam requires the I P turbine A further approach t o the Rankine cycle can be made second 10% or less. There are no known proposals
to have a larger rotor diameter and longer blades by using additional stages of reheat. A second stage for triple-reheat, and it is most unlikely that the
than the H P turbine. Sometimes there is a choice of reheat involves similar additional cost and design additional cost could be justified. There is also the
between increased outlet blade angle and double flow considerations t o those already described for single difficulty of designing an LP turbine with the high
in the I P cylinder, resolved in the case o f CEGB 500 reheat. There are obviously greater difficulties in inlet temperature required. This is already about 370°C
matching steam and metal temperatures during start- for double-reheat machines.
and 660 M W units by using double flow.
T o reduce creep in the high temperature regions, ing and load changes.
it is common t o admit a supply o f lower temperature Figure 1.44 shows a simplified Mollier diagram for
cooling steam t o the space between the inlet fixed a single and double reheat supercritical cycle, and 3.4.4 CEGB c y c l e s
blades and rotor. This steam tends t o flow through Fig 1.45 shows the T-S diagram. In practice a second It is instructive t o consider some recent and current
the balance holes in the discs and the diaphragm stage o f reheat is only normally justifiable with a CEGB design cycles by comparing their Mollier diagrams
glands, thus shielding the rotor from the hotter steam supercritical cycle. (Fig 1.461, the selected cycles are:
30
The steam turbine Thermodynamics of the s t e a ~ ncycio
--
(b) 660 MW AGR 160 bar/530"C rclieating to heiow, the turbine ccntrcline, The 'above centl-cline'
37.4 bar (23.3% TSV) with 41 mbar lilt i:, ill ;i ci,:istal sitc with cold u8ater. arrangement reqiiiics i-cmoval of the pipework belore
pressure. the LP turbine can be opened (or inspection, The
'below centreline' location has sometimes been tliougl~t
(c) New subcritical coal-fired 176 bai/565'C reheatill to be responsible for some turbine misalignment, due
to 565°C at 50 bar (20.8% TSV) with 57 mb. to heal transmission to bearing pedestals and casings.
condenser pressure. qiirbi.(l to ronsider these cycles fro111the The IP exhaust is considered to be the most suit-
rltrl)i~lei,ylindei designs. T h e 660 MM1 abie point for connection to the de-aeratot.. This is a
(d) New supercritical coal-fired 240 bar/565'C r 11 llnc 660 MW AGR turbines are quite direct contact heater which is vented to the condenser
heating to 565-C at 60 bar (25.0% TSV) wi llltu 01' 11,c same steam conditions and and designed to remove air from the feedwater before
57 mbar condenser pressure. imelics this. In fact. the AGR machine it enters the main feed pumps. It is always combined
lcss i3P steam flow a n d 5 % more with a large capacity storage vessel and elevated to
w S17r similar power output due to its provide a static head to the main feed pump suction.
In this example, single-reheat has been selected f a
IrflniJ~~lircyoil-ement. 11 also has about The CEGB has used reheat cycles for all power
the supercritical cycle. The advantages and disadvan
of double-reheat require careful consideration. Ail C ' larhille inlet steam flow. station turbines above 100 MW rating. This is not
lncca UIK! accommodated by Small blade true worldwide. In some countries there is a need for
coal or oil-fired plant is designed to be capable o
'two-shifting' for a significant part of its life. level changes. In the Cases chosen, large units operating on a simple non-reheat cycle for
tlq)alcrlt contradiction in that LP inlet peak-load lopping duty. These machines run for only
clearly more difficult to achieve this kind of fle
; oll.firerl unit is lower, whiie its re- a few hours a year, so maximum efficiency is not
with double-reheat and the type o f plant eventual1
Is lhi~:ltei. This arises from the fact important, but they must be able to run-up to full-
built will need to take these factors into account. load quickly and be inexpensive.
IIC uscs A four-flow L P iurbine with
The two 660 MW cycles are typical of the lat
\rhilr the AGR uses six flows with For this class o f turbine, the feedheating cycle is
units in service, although the coal-fired 660 MW un kept as simple as possible and the expense and com-
use 565°C TSV and reheat temperatures. I' torbines are also rather different.
I I f ' crhanst/LP inlet pressure is en- plication of reheating is not economic. A typicai
Both the AGR and the oil-fired 660 MW unit
1111 thr tnrbine designer. It is the point machine o f this type would deliver 280 MW from a
a back pressure boiler feed pump turbine, sup
pil~ecr lrom the two flows of the IP singie-casing condensing turbine in doubie-flow.
with steam from the H P exhaust and returning I
i. 11111~ or six fiows o f the LP. A low
the IP/LP crossover point.
The oil-fired unit has bled-steam extractions at H 11. i n lnrgc crossover pipework and long
exhaust, at BFPT midpoint, at BFPT/IP turbine e I?litditng, while a high pressure results
haust and from three positions in the L P turbin ililel blading and higher L P inlet tem- 3.5 Wet steam cycle
I111 helecterl pressure represents a com-
The AGR requires cooler feedwater and takes ble The wet steam cycle is mainly associated with the
I I lllese considerations and must give
steam from the BFPT/IP exhaust and from four PO. evolution of nuclear power. Nuclear power has been
tions in the LP turbine. 1h1. 11' ilnd 1.P turbine appropriate to
developed mainly on conventional lines, by using the
The new large coal-fired units will use motor-drivel titgcs nnd tbc stage diameters required. nuclear fission reaction as a source of heat for the
feed pumps. They can take advantage of higher filla dcailtns, an effort is made to select
steam cycle. In this section, discussion will be con-
feed temperature and the economics justify bled-steal Ihu use of standard turbine mod-
centrated upon the thermodynamic and economic
extraction from the H P turbines at approximately 70- increased reliability and reduced
aspects of nuclear-powered ~ l a n t.s ,in .varticular those
and also reduces the number of
~ ~ ~

har.
..~~ Thev also have bled-steam extraction from H aspects relating to the steam cycle for a Pressurised
exhaust, I P exhaust and four stages from the notably spare rotors. Water Reactor (PWR).
turbine. trr the new coal-fired proposais, it
FIG. 1.46 Condition lines for current CEGB designs The diagram shows how much larger are the I Ibcrcil that, although the condition lines
and L P heat drops than those of the H P turbine 111oiclerbines will be very different from
1 Iunill. because they will be designed for
3.5.1 The PWR s t e a m cycle
It is also notable how close together are the I P a n
L P expansion lines for all four examples. The H Ihe order of 30% increase in power The PWR power plant features three principal heat
(a) 660 MW oil-fired with BFP turbine.
expansion line for the subcritical coal-fired machi ' I1 also embody the most recent blading transfer processes. In the primary circuit, fuel is
(b) 660 MW AGR with BFP turbine. is not very different from that for the two 660 M lfic of detail design improvements. irradiated, liberating heat which is transferred to a
units, although its higher pressures will mean redu le how little difference there appears secondary steam cycle. In a nuclear power station
(c) New subcritical coal-fired with motor-driven feed specific volumes throughout. The new supercritical U critical and supercritical condition the plant performing this function is known as the
pump. has larger H P and I P heat drop than the subcritic lnri LI' sections. It should be added Nuclear Steam Supply System (NSSS). In the second
machine. This implies additional available work b cr pressures quoted are approximate cycle, the steam generated is expanded to drive tur-
(d) New supercritical coal-fired with motor-driven feed this is bought at the price of increased feed pun1 Ily optniised values. bines which generate electrical power. Finally heat is
pump. power. t/l.I' inlet 'crossover' pipework merits rejected to the Cooling Water (CW) in the condenser
The feed pump power is a n important part o f t handles low pressure steam - this is the third heat transfer process. The PWR
cycle selection. to minimise pressure losses. general arrangement is shown in Fig 1.47.
The steam conditions for these cycles are summarised The NSSS consists of the reactor, the reactor coolant
The low back pressure of the AGR is clearly a ate branches where the 1P
below: system (RCS) and a number of auxiliary and safety
parent. This pressure is largely site-dependent and and where the LP inlet steam
a function of the mean year-round cooling Wat ed with a number o f flexible systems. The RCS consists of the reactor within its
(a) 660 MW oil-fired 160 bar/53S0C reheating to
temperature. The oil-fired 660 MW unit is locat pe/casing expansion differ- pressure vessel and three or four cooling loops con-
538% at 39 bar (24.4% TSV) with 61 mbar con-
on the Thames where the water temperature is qni Ircllnics installed above, and sometimes necting the reactor to the primary/secondary heat
denser pressure.
33
Chapter 1 Thermodynamics of the stearn cycle
,
The steam turbine
q,ii:I!t~ i,y iedi~cingwetncss. Thc iocarparation of a
r . l i ! ~ i . i i i ~ ~ i l l i surface
il~ would necessitate an unwarranted
iriiii~~Iii,titioii ill the design of the steam generator. The
i!i.risii ~pi:~cliceis to reduce the 'pinch point' to a
$ 1 1 1 1 1 I 1 i i i i r ~ (see
i Fig 1.48) whilst uptimising steam gen-
~iii!i)i cosl against improvements in overall cycle
~I~Iv~cIIL'?.
I~811iiiiiernow the cycle for the turbine-generator
Ll'!jl 1.47). The slightly wet steam leaves the steam
# @ l t ~ ~ ~ ' ~!)asses % l l ) lthrough
, governor valves and enters 2
f l i p lit' turbine. The steam is expanded through the
IIiV~orhinewhere its pressure reduces and its wetness
3
L l i r . ! o i i ~ ~ Tile ~. Wet steam then passes through a mois-
iiiir ncl~ilrntorwhich returns the steam to a near-dry
iai~liiilcd state. The steam is then reheated in two
*!ii!i~!,. 'I-he first reheat process uses steam bled from
e tiil~j>i~~g on the HP cylinder, the second uses live
ataitlli taken upstream of the governor valves. The
uti:iilli leaving the reheaters is in a superheated con-
~ l l i i i i r i 11erorc entering the LP turbine where it is
~ - i ~ ~ : ~ to ~ i ai l low
r d pressure. The low pressure steam
1,. ii~nilrmscdin the condenser, rejecting heat to the Fi(i. 1.49 Expansioll of slealii fcorn inilial colldiiioils
6 i V . I lhc condensate is pumped through several stages wiillout reheat or tnoisiure separation
i s ! i I; Ilcnlcrs to thc de-aerator.
I lic dc-aerator is a large direct contact feedheater
w l i ! i i , iprovides for oxygen removal, a buffer store
it! iccilrsilter and sufficient gravity head to overcome This expansion results in steam at the later stages
!lie I I I : ~ positive suction head of the boiler feed pump. with a moisture content of 25%. A high moisture
I l i i lrerlwater is pumped through several stages of content is intolerable as it results in blade erosion and
III' I,csters before return to the steam generator. stage efficiency losses. The undesirability of blade
erosion was discussed earlier in this c h a ~ t e r As
. steam
exchangers (steam generators) The reactor vessel and _------ ..,.~
: ,*Z,,S'#<,<..',
is expanded through the turbine it starts to condense
cooling loops arc filled with demineralised Water, which
is pumped around the primary circuit. In this system,
boiling within the reactor is suppressed by maintain-
I,

- / I
&.t\:> 'Cycle considarations
1 i,tirii!ul now the effects of the varrous nroceswr
in the wet region along the 'Wilson line' which
corresponds to a wetness factor of 3-4% (see Fig
.~~~
~ ~ ~ - 1.50).
- - Above the Wilson line, the steam behaves as
ing coolant water pressure in excess of the saturation 11ptitt 1111: thermodynamics and economics of the wet dry steam; below the line, wetness becomes apparent
corresponding to the coolant temperature at ils,&~,i ?yule. Earlier it was concluded that the inclu- in the turbine expansion. Water droplets entrained in
from the reactor. The pressure is controlled al!'ir 111' :I superheating surface within the steam gen- the steam flow only accelerate to a small proportion
system and a surge tank, known as the oiiiiir was economically impractical. However, it is of the dry steam velocity as they pass through the
by a
pressuriser, connected to one of the Cooling loops. rlnhi~sblcto reduce the steam wetness as far as possi- fixed blades. The resultant mist has a velocity which
he secondary circuit is of major interest to this tilr wilh the moisture separating equipment within does not suit the inlet velocity triangle of the moving
discussion, The fcedwater enters the steam generatpr, 1111; olrir!?~generator. The Westinghouse four-looo 3425 blade (Section 1.2.2 of this chapter), neither in mag-
its temperature increases up to its saturation -1 $:, kOW (Illermal) design, which ha; been adapted ;or the nitude nor direction. As the mist progresses through
temperature. AL the saturation temperature, the water 'II- I
I
I
,,.&
@ lIt('u first PWR station at Sizewell, provides steam to the turbine, the droplets migrate toward the blade
changes state to steam which leaves the steam genera- :$
e Ill* 111rbinewhose full load conditions are nominally: tips by virtue of centripetal inertia. The resultant effect
tor wet. The heat exchange process for both ! ! IS
-,
C V.C.I ~ S is shown on a Temperature-Enthal~~ (T-H) I I
U"151LDWXSPEcIFIczN~"a~~~
mx,'
I
$.d & l'rciisore = 66.6 bar
of the wet steam is a mechanical drag corresponding
to a 1% cylinder loss for every 1% wetness.
diagram (Fig 1.48). The effects of a high moisture content are un-
~h~ wet steam produced in the steam generator is Tempera,YIe ~ g a i n s i(mars x, "e'll~'erature = 282'C attractive from the viewpoints of turbine efficiency
of a lower quality than the superheated steam con- specific enthalpy, for the primary and secondary <"cutrS
ditions from both fossil-fired and AGR-powered plant. in *he $team generator of a PWR
is the pioducl of mass and
* Maximum wetness factor = 0.25%
and operational economics. The cycle described earlier
included a moisture separator reheater (MSR), which
ow^^^^, there are limitations to the steam, condltlons
attainable. On the primary side, the m ~ X m U m!em-
enthatpy of the two nutds. aqh must be the ,i' takes partially expanded steam, removes the moisture
Same for both piacerrer as it equals t h quanntY
g I IN' exhaust pressure in the condenser is of the order and reheats to a superheat temperature. The choice
~
perature is restricted by the desirability of avoldlng heat transferred
of reheat or crossover pressure is affected by various
boiling in the reactor core, as heat transfer 8 30 mbar. The expansion of the steam from the parameters for a machine rotating at 3000 r/min;
coefficients for steam are considerably !owe1 than ,j llllIi111 conditions to this pressure would result in an these are:
that for water. Consequently the primary clrcuit outlet conditions are designed factor in the final sages. ~h~
temperature, TI, is less than the saturation value for is heated and the resulting steam/water on a Mollier diagram ( ~ 1.49)
i ~ The maximum wetness in the LP turbine exhaust
that Having established the primary circuit through moisture separators, ~ h i c himprove the with 85% efficiency. (lo- IZrna).
conditions, the steam generator and secondary circuit
The sreain turbine Chapter 1 Thermodynamics of the steam cycie

MOISTURE
SEPARATOR

To LP
CYLlNOERS

I'lci. I S 0 The 'Wilcoo liiic' dividing llle ivcl and dry


ex"ilnii0"

. The maximum wetness in the H P turbine exhaust


(14-15%).
1'16. 1.51 Con~tiaiiirs03,crossover I ) T ~ S S U ( C ior MSK
Note that pierrurc P I is outside the 'wiiidos'
as it corresponds to an excessively-Pig11 value
of HP exhaust wetness
The temperature to which reheat steam can be
raised, limited by the maximum steam temperature
available at the turbine stop valve (TSV). The need for steam reheating has been addressed,
but the means of reheating has not been discussed in
Overail cycle efficiency. detail. The objective of the reheating process is to
Plant capital costs. produce the best steam conditions for the minimum
cycle and plant capital cost. The factors to be con-
sidered are:
The wetness in the H P turbine can be a little higher The choice of live steam (single-stage reheating) or

.
than that for the LP turbine as the blades are shorter live and bled-steam (double stage reheating).
and the tip velocities are considerably Less.
Considering these parameters on the Mollier chart The final terminal temperature difference achieved
(Fig 1.51) presents a 'window' within which the cross- between reheated steam and live steam.
over pressure can vary. The resultant LP condition
line is very similar to that of a conventional LP cyl- The pressure loss across the reheater
inder o n a fossil-fired or AGR plant. The option to
replicate the LP cylinder is attractive, as it presents TO LP
CYLINDERS
savings in terms of design and manufacture and of- Although all these factors are considered simui-
fers a utility, such as the CEGB, the option to ra- taneously in the design, consider the choice between
tionalise its national spares holding. The replication single and double-stage reheating. The plant arrange-
of the LP cylinder would, however, restrict the varia- ments for single and double-stage reheating are shown
tion in crossover pressure still further. in Fig 1.52. The variation in net cycle output against
The inclusion of steam reheating following mois- total reheater surface area (Fig 1.53), shows a con-
ture separation has obvious advantages in terms of sistent advantage over the single stage reheating.
improving the LP exhaust wetness. The more effective The thermodynamic benefit derives from using a
the moisture separator, the less reheating is required; higher proportion of the high quality, dry steam pass-
modern separators can produce steam with wetness ing through the turbine to do work. Hence the HP
factors of 0.25% or better. turbine efficiency is improved, since wetness reduces FIO.1.52 Single and double-stage reheating plant
The steam turbine Chapter 1
Thermodynamics of the steam cycle
--

1.4
IOiI i/liliii ,,l,i,il,~

5 I,, l~l,,,l< <~I,L,,,>, 1.42 = 1.96

z 2 . 0 ~ / 1 . 5 ~= 2.05
5 02 iilliil illlii I!,c~CIII of rotor 1.43 = 2.74
Z
5
$ <jolinnriniici wcigtli of 2.05 x 2.74 = 5.60
I

)%<,I illlit c x l i i ~ ~ i sarea


t
1.4
1.4
ii8td weii'iht of turbine 1.43 = 2.74
*PEX*hUS,PHESSUYF, 4011P,NiEiPiiFSS"R~

p i t i 1.54 Advastace of double-svage over single-

mc. 1.53 Comparison of output with reheater surface area


for siiiple and double.s,oge relieafiiig I I : I ? ~ I ~ C Itnornbci of turbine stages have to FIG. 1.55 Comparison of 1haIf.speed and full-meed
speed machine. Whilst small differences in efficiency Ilc ~'ollsll~~~clional differences between the HP cylinders
exist, they are much smaller than those arising in lllr~ely associated with the increased
the steam turbine area.

-f
I of rlle half-speed turbine. The dimen-
stage and cylinder efficiency. The other benefit of The principal factors involved in a comparison

.
unr lo the forgings of H P rotors of achievement of zero erosion is likely to be more
two stages over one concerns the efficiency improve- half and full-speed turbines are:
" furbine have resulted in a crossover difficult with a half-speed machine.
ment associated with dividing the temperature rise
across an increased number of heaters (in a similar xelative sizes and weights of the turbines and! ; @ ~ ~ 8 i ~ i i ~tlliI11 1 l s optimum.
i. These higher crossover The LP cylinder for the full-speed machine is si-
way, the increase in the number of feedheaters in- differences in their constructional features. bi 4,' ., ,li~qlllrr 1111 additional inner casing in the
$$%@$i.i '
milar to that of a fossil-fired plant. Consequently,
creases overall cycle efficiency). The benefits to op-
Relative exoectations of reliability, operational fleai. sS,
# :>?@ P i l h i l i . l 11) 11v0id excessive thermal gradients. In
Me&#+ibiaii. lllr lillgr size of the individual components
though there are few differences in blading erosion
problems, the experience of UK utilities is in the

.
erating efficiency must be judged against the increased
bility, and ease of maintenance. I t t i l l rpc,cd lilrbil~c,farces the designer to 'over
capital cost of the additional plant. The increased full-speed area. The design of half-speed LP rotors
i i i i l l i . u~~lislr~~clionalfeatures (see Fig 1.55). involves a shaft with various discs, shrink fitted; this
capital cost includes extra heating surface, a H P cylinder
Relative thermal efficiencies.
bled-steam tapping, extra pipework and increased pres- type of rotor presents poorer dynamic behaviour
sure loss in the reheater. ?WZ and is more susceptible to stress corrosion cracking
b Economic comparisons.
The effect of H P exhaust pressure upon the choice &?it#biiiir., o,~c'rlr,h,,lol flexibility and maintenance problems.
between single and double-stage reheating, is shown . ~ ~ # i i ! ? l i i ! l ol yl f1111 and half-speed turbines are just There are two disadvantages associated with the
in Fig 1.54. Size, weight ond construclion half-speed machine which are related to plant op-
@ $$ ~$fs*niliar~l In llle cho~ceof machine as efficiency
The ootimum pressure is shown, but there is little For equal stress levels in geometrically-similar turbi 111d need to be considered. eration. The larger diameter of the H P rotor leads
penalty associated with deviating from the optimum. rotating components, all linear dimensions should lillll 111 observe that there is no valid t o increased thermal stress. In addition, the rate of
However, this curve shows the general benefit of double- inversely proportional to the speed. Theoretical vs lllltion of experience to support any increase of steam temperature at the inlet to the LP
stage reheating over a range of exhaust pressures ollr design being more reliable than the cylinder may have to be restricted during start-up, to
the last-stage blades of a half-speed turbine could
made twice as long as those of a full-speed tur mmr be placed upon objective assess- avoid losing the shrink fit rotor.
and could be carried o n a rotor of twice the diamete I (including engineering) differences There is no reason to suggest that the frequency of
3.5.3 Full-speed or half-speed machines leading to an exhaust area of four times the. s i rccs of difficulty in various areas maintenance of the half-speed machine is significantly
However, practical half-speed turbines are limi nnd operation. different from that of the full-speed machine. However,
The final issue dealt with in this section involves a
by weight and physical size to be about 40% la I !iYslcmatic differences between the
there will be increased problems in lifting, handling,
comparison of half-speed (1500 r/min) and full-speed
than full speed turbines: Table 1.2 gives a compari transporting and machining components of the half-
(3000 r/min) machines. The study is limited to the 'ill1 re&ard to the H P blade and rotor
between realistic half and full-speed machines in te speed turbines, due to their weight and size.
steam turbine rather than the generator, as the tur- ltionary components of the H P cylinder
bine is more affected by the wet steam cycle. It is, of relative sizes and weights. hi pressarc differences with wet steam
however, pertinent to observe that generators at 3000 Note that the total relative volume and weight (ilucl,; if leakage flows are generated,
r/min and 1500 r/min are technically feasible up t o the rotors and casings per unit exhaust area for 1 IBcI of wire-drawing erosion. The in- Relative thermal efficiencies
the largest required outputs. There are substantial half-speed turbine is 2.85 times the full-speed turbin dii~~cnsions of the half-speed turbine Marginal differences exist between the two designs
differences in the weights and manufacturing costs The manufacturing costs associated with the larg k I~aditngsat the joints as great as with regard to the internal cylinder efficiences. They
of Lpole and 4-pole generators favouring the full- half-speed machine are higher as more materials a lhc flill-speed machine. Therefore the can be summarised as:
38
i i i e steam turbine Economics of the sleatn cycle

s 'The enforced i~igiicrossover pressure of the hail- w i l , k is iiol as iaigc as it could

speed machine resuils in higher leakage loss in tilc ti. v~~lIill~elsic flow rate, and tiierefore
last few stages of the L P cylinder-. r i l llir slrnm, increases as tile exhaust
ii~iillci.ri.Ail increase in velocity mcans
r The half-speed LP cylinder experiences higher tip i l i Ikiliclic ellcl-gy of the steam at thc
losses due to the increased radial clearances asso- i111d therefore a loss of power due
ciated with a more flexible rotor. Ica\,ing loss.

e The full-speed machine has marginally higher tip i l k 1 1)resSllre is reduced. the cor-
losses in the last stage L P blade due to aero- xirlilrlilion temperature is reduced.
dynamic effects. litole htearll is extracted from the tur-
lir iwni iIir iondcn3atc in the first feedwater..~
141 leas steam passes through the last
Economic comparisons flrrbine, giving a further loss in
It has already been shown that the half-speed turbine
is more expensive than the full-speed turbine of equal
output and exhaust area, with no advantage in effi-
ciencv or reliabilitv. Hence the full-meed turbine will s lilcan that there is an 'op-
be advantageous whenever its exhaust area can match ' where the greatest nct power
the value which is desirable for an economically achiev- when the effect of point (a)
able condenser pressure. Fit, 1.56 Regions of power outpui and coolins water 18, ,
ilnd (c). At exliaust pressures
In order to establish the regions of potential eco- temperature$ favouring econoinic application of 30W r/mili ll1111, ilie incl.ease in power due ta (a)
and ISW r/miil turbines, assuming current, iasr-stage blad? duc to (b) and (c), so a net
nomic application of the two types of turbine, it is lengths are used to give m exl~austarea of 65-70 mi also invoived in the choice of design exhaust pres-

.
necessary to consider:

The relationship of desirable exhaust areas to


different combinations of outputs and condenser The turbine comprises one H P cylinder and tllr
t
I (;cncri~tion and increase in heat
i r ~ l i ~ i u stn!.essure
l is lowered further.
rlra Ihigller than optimum, the op-
1 1 , 'l'ilis is shown graphically in
sure, resulting in the exhaust pressure being some-
what greater than tile thermodynamic optimum.

. pressures.

The economically achievable condenser pressures


L P cylinders on a single shaft. The six-flow exhai
provides a n area of 47 mZ, which is sufficient for
c pclccntage increase in heat rate
11~sillsl(exhaust pressure/optimum
4.1.2 General e c o n o m i c optimisation of plant
A central theme so far in this chapter, has been the

. available. rated output, whilst using seawater cooling. Howe improvement of cycle efficiency. The importance of
modern blading developments will enable the de lllc corresponding characteristic
efficiency in reducing the unit cost of electricity can
Available total turbine blade exhaust areas for full- of high speed machines with much larger exhai best be seen by examining its relation to other factors
areas, suitable for outputs in excess of 1000 MW. 191, nlrbiae heat rate with exhaust
speed turbines and the regions of outputs and ill I'il! 1.57, is obtained from the affecting cost. What matters most to the utility man-
condenser pressures where they are cconomically ager is the reduction of the total lifetime cost of the
11 iiilta relating to the turbine ex-
advantageous 111t%haflows and the heat rejected. plant (refer to Volume A for the full discussion).
The major concern of this chapter is the iifetime gen-
I' is tlscd liere with respect to the
4 Economics of the steam cycle i i l l i l 1hc::il rate. Economic factors are
eration costs of turbine-generator plant, which breaks
Half-speed turbines are economical only in circum-
stances where the largest outputs are combined with
very low condenser pressures, favouring the adoption
of larger exhaust areas than those which could be
4.1 Choice of exhaust pressure
The turbine efficiency depends, to a certain extet
.
down into:
Capital cost.
Fuel cost.
provided by currently available full-speed turbines
on the choice of turbine exhaust pressure. This ch
(see Fig 1.56). Even this region of economic appli- Operating and maintenance costs.
is based on both thermodynamic and economic groun
cation of the half-speed turbine is under threat from
the impending availability of full-speed machines with Following consideration of thermodynamic optimis
tion, the economic factors influencing the wh For a valid c o m ~ a r i s o n of new designs,
greater exhaust areas. - . all these
spectrum of turbine.generator plant optimisation cost elements musi be considered simultaneously at a
described. The form of economic study to per certain reference date, e.g., the commissioning date. The
Turbine-generator for the CEGB PWR selection of the turbine exhaust pressure, conden Capitai cost is conditioned by the timing of stage
The proposed station at Sizewell B will incorporate
a single 3425 MW (thermal) PWR of a four-loop
design. The NSSS will provide steam to two full-
speed turbine-generators, each with a gross output of
and cooling water parameters is then given.

4.1.1 T h e r m o d y n a m i c optimisation
/ payments and the interest rates predicted over the
construction period. Similar considerations a .. o ~.l vto
the Fuel cost and Operoting/Maintenance costs, with
interest rates being the determining factor. To enable a
The power developed by a steam turbine suppl'
622.5 MW. 6 7 8 9 1 0 comparison between plant of different ratings, these
with a constant mass flow rate varies on the exha
The current turbine design incorporates a means kXI4AUSI PRESSURE costs are expressed as a Capital cost factor, measured
pressure changes for the following reasons: l"P5lli)~ExHnusrrRsssunE
of isolation of the steam supply to enable main- in f/kW.
tenance work to be performed o n one machine whilst (a) As the exhaust pressure is reduced, the isentro The Capital cost comprises not only the cost of
continuing to operate the other. This means of iso- heat d r o ~across the last stage increases and the turbine-generator itself, but also the costs of the
lation will improve generating availability. additional work is done in the turbine. I,"! licul rate cllaiacieristic turbine hall to house it and the services required.
The steam turbine Chapter 1 Economics of the steain cyclc
.
?,.
\

The historicai trend has been to larger, higher output 4.1.3 Economic opt-imisation of exhaust -$
r $lit iiiliiiitil,, casts are: A sitc study is undertaken to obtain thc iempcra..
plant of compact design, which has had a considcr- pressure, c o n d e n s e r a n d CW s y s t e m ,$ t u x of Llie water sourcc over a !period of a year, so
u p to now we liave colisidered the design ,$ a !I". cils! oc additional pumping power (this will that an estimate o f tile average annual CW inlei
able impact on reducing the Capital cost factor. The
practical problems of transport and assembly indicale
diminishing returns in this trend, which suggest that
fhe turbine. The economic a~timisation is highly
~~~~ ~~

dependent upon the Cooling water (CW) systeln as


.g viily will1 CW flow). lemperaturc can be made. The specific heat and den-
sity o f the waler are also measured.
ti. cost of a small change in turbine efficiency.
plant with an output of about 1000 MW may be a well. The general economic considerations given ill Using these fixed parameters, the heat transfer cal-
maximum limit. the previous section will now be developed to examine culatiolls can be made. As well as the effect of the
The Fuel cost expended over the power station the combination of the turbine, condenser and CW exhaust pressure on output and heat rate, there are
operaling and maintenance costs are ignored
lifetime is of course directly influenced by the design system. other variabies needing optimisation, Increasing the
lilere are exceptional circumstances.
cycle efficiency, and the means of achieving this is Figure 1.60 shows a typical 'direct cooled system number o f tubes in the condenser, for a given CW flow
!z clear that there are many variables to be
the prime topic of this section. It has been shown that using sea water as a coolant. The system is called direct rate, results in a reduction in CW velocity, and hence
red and it is therefore necessary to fix certain
the cycle efficiency can be improved by increasing the cooled because the water is used once and then dis- a reduction in friction losses and pumping power
design Parameters (the number and area o f costs. However, low CW velocity needs a larger heat
provision and complexity of the plant, e.g., increasing charged. A circulating pump forces water througll exhausts) so that the characteristic relation-
the number of reheating stages. The designer carries screens, which removes any debris large enough t0 transfer surface, which could be achieved by increas-
veen the Power output and exhaust pressure ing the length o f the condenser tubes. This is not
out a cost-benefit analysis to reach a reasonable block the condenser. There are valves at inlet and aintained. With the turbine exhaust design
outlet to the condenser to ensure flexibility of op- possible because, as stated earlier, the length of the
compromise, to ensure that the benefits of improved constraints are automatically imposed on the
eration during changes in climatic conditions. Flexi.. tubes is usually constrained.
efficiency are not eclipsed by excessive capital costs, !he condenser.
bility is developed further by increasing the numbc Increasing condenser outlet temperature reduces
or by complication leading to reduced reliability. condenser surface can vary in two ways:
o f circulating pumps available. The CW system there the mass flow o f CW but increases the turbine ex-
In different parts of the world and in a rapidly
fore makes a significant contribution to the capital i l l ~ l ~ t t ~ the
i n g number of tubes (and adjusting the haust pressure, resulting in a rise in heat rate, a fall
changing economic environment, the cost of fuel can
of the plant. On inland stations, using indirect co Ilow lo give the same velocity). in power and therefore a drop in efficiency.
show wide variations. For new plant, it is desirable
with large cooling towers, the costs can be higher St1 . Figure 1.62 shows the results from the heat trans-
for the utility to present the designer with a cost S il~creasingthe length o f the tubes. fer calculations. Lines of constant CW velocity and
expressing the capitalised value of 1% improvement turbine exhaust pressure are displayed. If we consider
in the heat rate. This will enable him to identify the increasing the condensel- tube surface area by increas-
options best suited to the application. IIIC fixed the turbine design, for a typical trans- ing the number of tubes, then as discussed above,
Plant Operating and Maintenance Costs are reduced ~~adcrslung condenser, the maximum tube length at constant CW flow, both CW velocity and turbine
by improving the reliability of plant and by mini- o be fixed (Fig 1.61). The condenser tube sur- exhaust pressure decrease. The effect on output of the
mising the maintenance and overhaul outage times. area can only be changed by varying the number changing exhaust pressure, may be determined from
Increased plant automation permits a reduction in the !~l>csused up to limits imposed by the available the output/exhaust pressure characteristic (Fig 1.58).
manpower required per MW produced. I . Since these are basically heat transfer calcula-
Figure 1.59 depicts the typical breakdown of lifetime the condenser tube materials, diameter and
generation costs. Fuel costs form the largest element, icsses must all be fixed according to the prin-
such that a 1% improvement in efficiency of the 'el out in Chapter 4.
plant is equivalent to a saving of approximately 2%
o f the Capital cost.
I"BIIINGII<
9 .$om
FIG. 1.60 A once-through (coastal) CW system
# 6 r n
?
a 1,130
*
The task is to optimise the overall design so as ii rww
to minimise the lifetime generation costs. This means 3
minimising the capital and running costs over the
lifetime of the plant. The capital costs usually con- rww

sidered for a direct cooled system are: i J7IW

CML1NEWATlllrlWIUIW
The capital cost of the turbine and of the buil NUMBEllOlTUBES
VaRIAaLs
ing to house it (this will vary if longer last-stage
\ FUEL
COSTBIW
blades or a different number of turbine cylinders t
are chosen). FIG. 1.62 Relationship between hear transfer parameters

The capital cost o f the CW culvert system (this will


vary with CW flow).
The capital cost of the CW pump (rated to suit the It is customary t o consider a reference or nominal
CW flow). design having a given surface area and CW flow rate.
and to compute t h e change in cost from the reference:
The capital cost of the condenser surface (an indepen- The effect of the variables on the following economic
FIO.1.59 Lifetime costs of a rurbine-generator unit dent variable, subject to constraints). FIG. 1.61 Transverse underslung condenset data can now be considered:

42 43
The steain turbine Chapter 1 Economics of the steam cyc:iv

s Incieineots of CW l'iow wili affect CW puolp costs quite possible that these wiii not be used, becaosc \!I< lpioduce a range of CW iiilct temperature of bc shown by comparing lire lrcal laic (kJ/kWii) ot
there are Surtliei coiistiainls on the desigir yet to bc liriwecii 5-17"C, corresponding lo a variation fioni modern large capacity turbine-gcneialor planl, i n
s Increments of CU' fro\\, will afScct CU' systcni casts considered. i l i , . irleal turbine exhaust pressure of i 15 mbar. This volvirig seven stages of beating, with a hypothetical
r Increments of coridcnser surface wili affect con-
The most significa~~i consiiaints, after thc turbine i.<ii~idbe responsible for a change in turbine efficiency -
nlant of eauivalcnt electrical eelieratinc
. canacitv,
. . brii
exhaust area and condenser lcngth previously men- (11 around 0.7°/0. without feedheating plant. Thc comparison is made
de~isercosts.
tioned, arc the limits on CW velocity. There is a 11 cannot bc assumed, either, that all the condenser with the assuxnntions that the cyiindeis of a muiti-
0 Changes in output wili affect the running costs maximum velocity permissible to prevent tube erosion li$bcs will bc operational throughout the lifetime of cylinder tandem turbine have the capacity to pass
and a minimum velocity to avoid silting. Environ- 111c condenser. Material too small to be trapped by the total quantity of steam sul)plied by the boiler,
e Increments of CW flow and head will affect the mental considerations enforce a limit on the maximum Ihc screens may build up in the tubes, restrict the that the exhaust pressure is identical, that the 'leav-
consumed CW pump power and will therefore af- temperature of the C W discharge into the river or sea I'io\\, and eventually block it entirely (known as fouling). ing loss' is identical and that the condensate from
fect the running costs. so that fishing is not affected. 'The problem can be alleviated either by regular main- the turbine condensers is pumped, as feedwater t o
The exercise can be repeated with one of the fixed lcilance or through the provision of automatic cleaning the boiler, a t a typical condensate temperature o f
parameters changed t o a new value. In this way, the by circulating foam rubber balls that clean away the 35°C (for a temperate climate plant).
If the individual costs are calculated for the grid of change in costs using different exhaust annulus areas dIr.1 and scale formation. The effects of erosion at The difference in 'heat rate' of the two turbine
points on Fig 1.62 and then summatcd to give the can be found. A similar analysis can be undertaken for lllc higher velocities can be practically eliminated by plants is found t o be significant, the heat rate o f the
total cost at each point, wc can plot contours of a tower-cooled system, where CW is cycled between llir use of hard materials such as Titanium for the plant equipped with the seven-stage regenerative plant
constant cost, as shown in Fig 1.63. the condenser (where it receives heat from the steam), coi~denser tubes. Changes in tube material and in being only 0.86 of the hypothetical plant of equivalent
Computer programs have been devised which will and the cooling tower where it transfers the heat to loilling factor, arc evaluated during the design to capacity but without feedheating plant.
evaluate the best design combination of parameters the rising air. (For a full explanation of the 'indirect confirm the mosl economic choice for the full range A full treatment of the economic benefit of the
for minimum total cost and Fig 1.63 is a typical cooling' system see Chapter 4.) of operating conditions. turbine plant with feedheating would involve consi-
graphical output. From Fig 1.63 it can be seen that The economic optimisation calculations are based deration of a boilcr plant designed for a high feed-
the smaller the contour, the lower the total cost. The on a constant CW inlet temperature and the assump- water temperature and a hypothetical boiler design
most economic design parameters therefore exist at tion that all the condenser tubes will bc available. In suitable for feedwatcr delivered to it at condenser
the centre of the smallcst contour. It is, hawevcr, reality, the seasonal changes in temperature in the temperature, but the figure 0.86 provides a goad
4.2 Regenerative feedheating measure of the improvement wrought by bled-steam-
'llic principle of 'preheating' boiler feedwater before heated feedwater plant and of its benefit in terms
I l k admission t o a boiler was well established before of reduced fuel consumption.
t l ~ cturn of the century. The expression ‘regenerative'
Il~ipliesthat latent heat in steam, or sensible heat in
boiler flue gases, is captured, reclaimed and set to 4.2.1 Feedheating plant s t a g e s - s u p e r h e a t
work again in the fluid cycle. cycles
Ihrly examples of feedheating involved the dis-
The optimum number of feedheating stages, in strict
ullikige of exhaust steam into the tanks from which
terms of cycle efficiency, could be as high as the
llic feed pumps draw their water and the use of
number of steam expansion stages in the associated
'~~i:o~iomisers', which captured heat from flue gas and
turbine cylinders. But it is not practical, in cnginecr-
lrd lo economy in the use of fuel.
ing terms, to provide steam extraction points at each
'The practice of preheating the boiler feedwater has
stage in the cylinders, because of the casting/casing
ci$~itiibutedas much to efficiency improvements as
complexity that would arise and the additional and
itliy other single development in steam power plant.
excessive length of the complete turbine, with cor-
In this section 'regenerative' feedwater heating plant
respondingly long rotors.
iising steam extracted from the turbine is covered;
As with most engineering designs, a compromise
ieedheating plant involving the 'economiser' is dis-
between the academic optimum design and a design
cussed and described in Volume B.
which is practical; producible and commercially viable
From the early days of utilising latent heat from
is necessary.
lhe exhaust steam from steam eneines - and small tur- The type of power plant with which the turbine
bllles to preheat feedwater, the principle of feedwater
plant is associated also influences the number of feed-
heating has been progressively widened; modern ~ l a n t
heating stages because the steam-raising plant eco-
I b very sophisticated, involving multiple steam ex-
nomics interact with the turbine plant.
Iraclions from steam turbine cylinders, L P heaters,
For electricity generation in the UK, the following
combined heating/de-aerating plant, H P heaters, L P
steam-raising plant sources have featured in recent
rlrains pumps, H P drains pumps, pressure cascading
years:
111 drains and the incorporation of other plant, such
tua moisture separator/reheaters. which are used in
u'et steam cycles.
The academic treatment of regeneratve feedwater
CWI#NGW"llrlFLOl"PATIII9~S heating and its place within the cycle was covered
in Section 3.1 of this chapter and illustrated by Advanced gas-cooled reactors (AGRs).
Ikankine cycle diagrams. The impact of feedwater
RO. 1.63 Effect of cost Iheating plant upon the turbine cycle efficiency can Pressurised water reactors (PWRs)
The steam turbine Chapter 1 Economics of the steam CYL~C

Coal-fired and oi1:fired pla,ils yield similar numbcis slightly diffcrcnt systems, such as eithcr one or two
of fcedhcating stages as optimum, about three LP entiactioo poinis oil a boiler fecd pump turbinc, will?
stages, a heating/dc-aerating stage and two H P stages, a corresponding number of HP fcedwater ileaIel.s,
leading to a final fcedwater ternpclratol.e of about depending on their manufacturing costs and their
250°C. relationship to the then prevailing worih of cycle
An optimisatior~ technique is used to determine efficiency. The finai H P feedwater heater has, in every
the number of feedwater heaters, with practicalities case, used steam exhausted from the H P cylinder of
still dominating. the main turbine (i.c., the same point in the cycle as
In a world of changing economics in the field o f the supply to the feed pump turbine).
fuel supply, at1 upset in prices, upward or downward, For large capacity plant, HP feedwafer healers of
such as experienced with oil supply prices can lead the 'tubeplate' type (as illustrated later in Fig 1.691,
to a significant difference in turbine and turbine plant cannot be made sufficiently large to perform the
configuration. It is necessary at the inception of a entire feedheating plant stage duty because o f manu-
power station project to revalue cycle efficiency in facturing limitations. These limitations involve tube
the light of prevaiiing fuel prices and best predictions. plate diameter and thickness and tube hole drilling
AGR planrs are found to bc most economic with a length.
moderate final feedwater temperature of about 150". The provision of heaters in pairs has proved ne-
This is because the lower temperature produces a cessary at each heating stage to permit the stage duty
wider 'approach tcmpcratore' ta the reactor coolant to be performed. Each 'line' (or bank, or 'string')
gas, and a greater 'log mean temperature difference' o f heaters can be by-passed in the event of a fault
(LMTD) for the steam generators associated with the to permit continuity of feedwater flow to the boiler.
reactor. This wider LMTD, produced by the feed- The heat transfer surface area for heaters (of all
water temperature of 15O0C, is beneficial in that the types), and therefore the overall size of the heater,
steam generators, encompassed within the concrete is carefully optimised. The optimisation involves manu-
pressure vessel with the reactor, can be smaller, so facturing cost versus the lifetime value of efficiency
the pressure vessel is smaller and lower in capital based on fuel cost and the predicted utilisation for
cost. the type of plant.
The final feedwater temperature is 'optimised' - For relatively high fuel cost applications, an ad-
i.e., the value o f cycle efficiency, costed at a rate ditional heat transfer section is incorporated in heaters
appropriate to the use o f nuclear fuel over the life as a 'drains cooling' section. The condensate of the
of the plant, is related to the capital cost variations heating steam is cooled to a temperature lower than
of steam generators, etc. The lowest sum of lifetime saturation temperature by the ingoing feedwater, there-
operating cost and capital cost determines the op- by increasing the effectiveness of the heater in the
timum design, which includes the corresponding final cycle.
feedwater temperature as a design parameter. Further features of feedheating plant - and suitable
The outcome of this AGR plant optimisation is for any type of main plant - are those of 'pressure
that three LP feedwater heaters are used, in con- cascading' and 'drains pumping'. Heating steam, after
junction with a fourth combined heating and de- being condensed in a heater, is led, as drains, to a
aerating stage, to provide a final feedwater temperature lower pressure heater where it 'flashes-off' and sur-
of about 150°C to the complete exclusion o f H P renders part of its remaining heat to the lower pressure
feedwater heaters. The boiler feed pumps draw their heater. This principle can be applied to all heaters
supply of water from an elevated tank, forming the in a bank as a 'cascade'.
combined heating and de-aerating stage, and deliver Drains pumping involves collecting drains after
the water directly to the 'economiser' section o f the cascading and pumping them back into the condensate
reactor steam generators. feed system at a point that closely corresponds to
Economic systems evolved during the past two their temperature. Figure 1.65 illustrates both cascad-
decades for both fossil-fired and AGR plants involved ing and pumping for the two L P heaters.
'back-pressure furbines'(driving the boiler feed pump),
with one or two steam extraction ooints for H P feed-
water heaters.
4.2.2 Feedheating plant s t a g e s - wet s t e a m
The driving steam for the boiler feed pump turbine
cycle
is taken from the exhaust of the H P cilinder of the
main turbine, and is therefore steam which has been A PWR station is now under construction in the UK,
expanded and has lost part of its superheat (Fig 1.64). based upon a standard design for large capacity plant
Steam extracted from the boiler feed pump turbine (1200, 1300 MW). This design, designated 'Standard
is therefore relatively low in superheat and the heat Nuclear Unit Power Plant System' has a feedheating
to be surrendered to the feedwater is mainly the latent plant involving L P heaters, a de-aerator/heater and
heat which is beneficial to cycle efficiency. H P heaters but with certain variations arising from
Various main plant manufacturers have evolved the wet steam cycle of the PWR.
T h e steam turbine Chapter 1 Economics of tlie s t e a m cyciii
..

Steam admittcd to tlic H P cylinder of thc turbine is sccovcicd and introduced into thc H P fccdwalei lii, t,!c:lc inuolucs four stages of 1.P fcedheating, o f typically 5 pg (of oxygen) per kg (of water), i . c ,
is at a dry saturated condition, i.e., without superireat, heate1.s at appropsiatc temperature points in the cycle. riix i:i :ici:iioi/lieater and thl-ec stages o r I-1P feed- five parts per billion.
On expansion thrauglr tlie cylinder, tlie steam bc- The PWR steam generators liave a continuous I i i ~ ! ~ i i t i i i~i,i l i i ail ultiinatc heater utilising condensate Desigii piacticc has bcen lo iilslall lligli level plant
comes wet. The water fraction is removed in a passivc 'blowdown' system to limit the concentsation of slight liiiiii l i i v secondary reheatei to preheat thc feed to in an auxiliary plant annexe between the boiler house
'moisture separator' and the water and its heat is impurities in the steam generators. The 'blowdown' fi l i i i ~ i ~ r ~ iof ~ i 226°C
~ ~ r u before admission to the steam and tuibinc hall, at a level set by boiler house steel-
reclaimed and pumped into the fccdheating system at water, at a temperature approximating to boiler satura- ~ ~ V ~ ! W ~ , ~ I ~ ~ I S . work. l'ro\,ision of generous margins over the steady
the de-aerator (where separator water temperature tion temperature, is passed through a heat exchanger state NPSH iequiremeols of suction stage feed pumps
and de-aerator temperature coincide) for maximum incorporated in the LP fecdheating plant upstream of has oroved oossible.
efficiency (Fig. 1.65). Thc dried steam is then passed the de-aerator/heater, where the heat is recovered. 2 2 1,medwater de-aeration
~~
Typically, tanks have had a total volume equal to
through two-stage reheaters for superhcating, steam Condensate, formed from bled-steam extracted from about ten minutes feedwater flow rate, with an eight
jiiuitwlller chemistry requirements are stringent with
being the heating medium. Steam bled from the HP the LP turbines and supplied to LP feedwater heaters, minute store to provide a buffer for transients and time
Wpiiil lo lllc permissible level of dissolved oxygen.
cylinder is used in the primary reheatei- and live steam is collected in a drains receiver and pumped into the t o unload the plant should the condenser extraction
l'hc rrluill concern is that of minimising waterside
(i.e., at boiler conditions) is used in the secondary de-aerator/heater tank for recovery of both condensate pumps fail. The mass of water stored is about half a
Vi?l'iriiioii o i boiler tubes. Waterside corrosion and
reheatei. Condensate formed from the rehearing steam and heat. Iliailllc i:orl-osion lead to thinning of tube walls and tonne per megawatt of plant capacity (i.e., about
Iiir ~~t!hrvql~ent risk of rupture by the internal fluid 330 t for current 660 MW plant).
iilakiii! c In summary, this type o f combined plant, which
"".
A il,~lliflca,lt
% ' , ' feature of British designed is described in detail in Chapter 3, fulfils important
(iitilil bccn the combined 'feedheating/de-aerating/
liila
primary functions:
* f i l ? i hiorage plant'. This is illustrated in Fig 1.64
WI!ii'ii i~lhowsthe ~ o s i t i o nof the de-aeratine/feedheatine
j#lrit! wiiliin typical turbine plant and Fig 1.66 is a
alli!jili. lil~~stiation
f~~wlI~~:n~lit~,~, ..inlant,
of a typical high level de-aerating/
~~ ~~~~

. " Serves as a feedwater heater.


Feedwater is de-aeratcd down to the necessary low
gas content,
lbiiiiaater from LP feedheaters is admitted to the It acts as a 'buffer' to the fluctuations of condensate
iuiii lowers on the tank. Steam, typically bled either feedwater flow that occur in service.
i i i s i i t !!I? inain turbine or boiler feed pump turbine,
at 1iiI.ri1 from the feed pump turbine exhaust, is sup- The tank height provides a hydrostatic head to satisfy
p l i t ~ l i r , ~ heating and de-aerating the ingoing feed- the suction pressure requirements of the boiler feed
Qtillcl. I:eedwater, de-aerated t o a boiler quality standard pumps.

-
----Y*,Nn~WI"sPU

-e e ~ r m n~ mc ~
--- ~~~WY,e~ONIII*LT8
D%,WS

FIG. 1.65 Simplified feedwater heater arrangement for a PWR FIG. 1.66 Typical high level de-aeratoilfeedheatei
T h e s w a m turbine Chap Economics of the steam cycic

Keliable and effective service over sevcral decades has British practice l o r tlic stedin supply to the bn 11, 'rl'ill' iiilo tile crossover jpipe. If a for heating tire condensate, with consequentiai in)-
been obtained from plant of the designs described, fced pump turbine has been, as caplaioed earlier, 1 : I , I deficiency is supplied provement in cycle efficiency. Bled-steam valves are
but changing cconon~icsand competitiveness lrdve now use steam partly expanded through and exhausted I'l-0 I ' rlossovrr, at the same pressure but omitted - both the traditional isolating valve and
icd to a change in design. the H P cylinder of the main turbine (sometimes kno\ the non-return valve. It has been established by cx-
The design illustrated in Fig 1.67 invoives the as 'cold reheat deorn'). This steam, after furthei li11i1)il.~viieretlie heatei./de-aerator 'floats' periment and experience that steam refiux on turbine
direct injection of steam into the body of stored pansion thiough the boiler feed pump turbine, cont I p u m p turbine exhausi and the trip, when the stage pressure collapses to condenser
water through a series of vertical perforated tubes oniy a modest amount of superheat and this exlial literconnected piping, has proved pressure, is negligible and hence there is no significant
immersed in the waier, and the admission o f con- steam is used to supply the combined feedheatin feed pump turbine is unavail- contribution to rotor overspeed.
densate through self-regulating sprays. The condensate de-aerating plant. hy elcctric pumps are used, the heater/ With the heaters being almost completely within the
is heated almost t o saturation temperature; steam Because the steam requirement of the boiler fc supplied entirely from the I P / L P condenser 'neck', there is economy in turbine hall area
rises through the water and gases are liberated and pump turbine cannot be exactly matched to I lion can continue unimpaired. Such and in the elimination of supporting steelwork, access
conducted away through small vents adjacent t o the steam requirement of the feedheating/de-aerating 1118 ioo is advantageous and removes ladders and platforms.
sprays. throughout the load range, arrangements are necess o f one plant item upon another. The omission of an isolating steam valve prompted
The water passes at low velocity through the tank t o pass any excess steam, or t o supply any stc a steam turbine drive for the the development of improved methods of prevent-
at a rate corresponding to the plant load and is deficiency from another part of the cycle. Ilc economic benefits and the flexibiiity ing heater flooding. Neck heaters arc equipped with
almost at saturation temperature. The remaining dis- An effective means of accomplishing these reql iliril hyslcm are clear. If boiler feed pump valveless primary drains and a valveless secondary
solved gases arc liberated: they rise to the surface ments is to design the boiler feed pump t o exhaust ~lred,tllc system described above would drain, the latter being arranged physically a little higher
and steam space and are then conducted away through a pressure approximately equal t o the pressure of I i ~Ulll~ly from the main turbine only. than the primary drain outlet.
small vents, the water being brought up t o saturation main turbine IP cylinder exhaust. This exhaust sle External L P heaters, although still of the traditional
temperature by the injected steam. This design and is supplied to the L P cylinders and the boiler fc form, are now arranged in a horizontal attitude, elevated
pump turbine exhaust, the heater/de-aerator and t ~ r r r ~ u rfeedwater
e heaters
its function arc covered fully in Chapter 3. so that the bled-steam piping from the turbine falls
For thermodynamic economy, the bled-steam used main turbine IP/LP crossover pipes are connect (1.1') feedwater heaters are basically to the heaters, thus assuring drainage. This minimises
in the de-aerator should ideally be without superheat - together. ir!r'~ll.d 'tube and shell' heat exchangers, the risk of water entering the cylinder and the possi-
the use o f superheat is a wasteful way of heating water The steam pipcwork is arranged so that, du Ilailte I)assing through the tubes and bility of damage by impact o n rotating components.
when it could be more effectively used by being con- piant operation, the fced pump turbine exhaust stet Ibcinl! admitted t o the shell. This type The heaters are 'stacked', so that the ultimate
verted t o mechanical work in a turbinc. is preferentially used by the heater/de-aerator, w 111lpcdvcrlically, has been used for many L P heater can drain its bled-steam condellsate into
le'o ildvaaces worthy of note have been the next heater, and that heater can drain its con-
II ycllrs and are now treated as modern densate into the condenser above the working level
The steam turbine Chapter I Econoinics of the steam cycli:
,.
I\ b~;iriation on the traditionai design o f l i p lheater al.c;!s and increased tinit rating, serve la reduce capbiai
2
Q irlil; ils thick ihemisl,heiicai prcssul-e iiead, luheplate and operating costs arid arc therefore beneficial lo

".
@ b

E
0
8,
%L $
l i i , d sledni shell, is a design based o n boiler tech-
tiiili)l:!' in which inlcl/outlet headers and serpentine
lt~iics arc all contained within a steam shell, as il-
the consumers.

!iirlr;tted in Fie" 1.70.


'Thc pressure parts associated with such a design,
4.3 Choice of feed pump and drive system
1 ~ 1 1 i > \ +as
~ i , a 'header' type heater are smaller (relative to
li!i' thick walls of a hemi-head and tubcplate heater) A full description of feed pump design and devclop-
all11 are more amenable t o temperature changes as a ment is given in Chapter 3. In this section, feed
r~liisctiuenceof load change than the traditionai type pump size, number, duty, margins and the need for
of lheater. Furthermore, it can be made in larger variable-speed are discussed; comparisons on economic
eal,i~cilies than the traditional design. For large unit grounds are also made between steam turbine and
kirca, a single line o f 'header' type H P heaters could electric-motor drives, and between variable-speed motor
l i i iiscd instead of a double line of hemi-head/ tubeplate (VSM) and induction motor/fluid coupling drives.
IIPIIICIS, which may yield space and cost savings, The section is concluded with a typical example of
cli:l>oidiog on suppliers' specific designs and manu- an overall comparison of through-life costs of four
li8i:li~1~illg costs. feed-pump system options, that was performed for a
future 900 MW turbine-generator unit.
Boiler feed pumps now being designed for future
4.2.6 Summary large units are tandem arrangements, i.e., the slow-
11, silrnmary, in the field of feedwater 'heating, there speed booster pump (suction stage pump) is driven
l t n i ~ . been a number of changes in recent years but in tandem with the main plessurc stage pump, using
llir~clhavc been of an evolutionary, not a revolutionary, either a step-up gearbox (lo the high speed pressure
I I I ~ I I ~ I CThe
. first two stages of L P feedheating are stage) or a reduction gearbox (to the suction stage),
!i~oorl,orated in the 'neck' of the condenser, with the depending o n the speed of the driving motor or steam
~ ~ l r r i i aLl P stages being arranged in a horizontal turbine.
i~llil!lrle below the L P turbines.
The position of the feed pumps in the steam cycle
(Combined de-aerating/feedheating plant is now of
o f a modern turbine-generator unit was shown in
1111, 'steam-injection' type and more compact than
Fig 1.65 (in this case for a P W R unit) physically they
Illlherlo. H P feedwater heaters are arranged in a
are situated beneath the de-aerator, upstream of the
ilori?.ontal attitude below the turbine cylinders. The
friilxaler is now raised to a higher temperature by
HP heaters.
llic ~xtractionof steam from the H P cylinder. For
liili~ccapacity plants the use of 'header' type heaters 4.3.1 Feed pump sire and number
$!tit) permit space and cost savings t o be made which, The choice o f feed pump size and number is based
111 cat~junction with improvements in other plant upon the principle of ensuring that full turbine-

Fic. 1.70 Arra~~gemenl


of a header-type horizontat HP heater
The steam turbine Chapter 1 Economics of tlie steam cycic

generator unit output can be maintaincd with the As the powcr reqilii.e~lle~li
o f a boilex feed pump psouisioii necessary [or 50% eiectric fecd pumgs, wiiicll
loss of one main duty fccd piiml~. This ensures ti)! a typical 500 MW unii is approximately 10 MW, includes eqilivaie~ll bled-steam pipework for tiic HI'
inaxiillum plant availability. i t can be seen that the clioicc of an economic and beater alone, 11lus elcct~icmotors (including reinforce-
For the majority of 500 and 660 MW units, thc leci~nicallyacceptable variable-speed boiler feed pump ment of tlie station electrical system to cope with thc
most economic solution has been a 100% duty steam iliive is a decision of major importance. The possible high motor-starting currents). Also, the first option
tuibine-driven feed pump with two x 50% electric lyiies of boiler feed pump val-iable-speed drives which usually includes a live steam connection direct from
motor-driven start/standby sets (higher capital costs ii;ii,c been considered by the CEGB for use on large the boiler to the feed pump turbine for operational
but lower running costs than ail-electric pumps). puneraling units arc: flexibility, even though the electric pumps are aften
The situation is now changing for units over 660 used for starting. The live steam pipework is expensive,
e I'ixed-speed electric motor with variable-speed
MW in that the saving in capital costs of having due to its high pressure duty.
150% (three x 50%) feed pump capacity compared coupling.
There is usually no extra capital cost attributable
with ZOO%, begins to outweigh the increased com- D Converter-fed variable-speed (electric) motor (VSM). to the required increase in rating of the main IP/LP
plication o f having two pumps running in parallel turbines and the generator needed to supply the extra
for full-load operation. Other advantages of having e Back pressure steam turbine power for electric motor-driven feed pumps, since it
three idcnticai 50% duty pumps include reduced requires only a marginal increase in steam flaw (3%)
spares holdings, quicker maintenance, modular con- r ('ondensing steam turbine of the main unit.
struction with a more compact layout occupying less With all-electric feed pumps, the system is more
station floorspace, and less complex and expensive compact (less floorspacc) and simpler, needing fewer
pipework. I I I addition to these choices, the option of slipring spares holdings. Because the pumps are frecd from
Feed pump size has more recentiy been influenced ilidtiction motor, regulated by resistance in the rotor
tile constraints of steam pipework they can be placed

.by two other factors: cllcuit, has been considered and used in the past.
in the ideal position for NPSH considerations, on
lliis relatively cheap and simple solution, using large
the basement floor (instead o f a few metres above
international market appeal - 50% duty pumps llitiiiil rheostats with mechanically-movable tapping
I,oiiirs, has proved unreliable in practice, with a high it to accommodate the steam inlet pipework below
for large (over 660 MW) units have the greatest
l~~iiiiitenance burden. tile pumps) directly beneath the de-aerator (NPSH is
worldwide market potential, whereas 100% duty
defined in Chapter 4 and de-aerator height, etc., is
pumps would require new pumps to be designed that the boiler is designed, and also to allow for a & i'ariable-speed electric motors and condensing steam
discussed in Chapter 3). These factors can lead to

. that have very little export potential.

The choice o f feed pump driver influeilces, to a


certain extent, the pump size - for example, the
current international trend to electric motors and
deterioration o f plant capability in service. In addi- L
tion to the effect of the boiler margin, the boiler f
feed pump is designed to produce a rather higher
feedwater flow than that needed by the normal boiler 8,
design condition. This is intended to cope with pump 13
Illrbines have only recently become viable options
l l o i future units over 900 MW) due to the trend to
8ll)wel- (6000 r/min or less) 'International Class' boiler
kc11 pumps, to limit erosion and cavitation in the
Ipllmp, to the NPSH required and de-aerator height,
savings in capital costs for the de-aerator and its
civil engineering costs and the feed pump suction
pipework between the de-aerator and the pump.

50% duty pumps means that no variable-speed wear and transient conditions, and to act as an op- fj Flu. These two types of drive are not feasible for
motors or couplings large enough for 100% duty erational margin. 8 IIPr with the higher speed 'Advanced Class' pumps Running costs
have yet been developed. At the value of fecd flow corresponding to the $ Ilacd on 500 and 660 MW units so far, due to con- A steady state model of the thermal performance of
turbine design quantity, the head produced by the g \'CIIPI size limitations and blade vibration and stressing tile turbine and fecdheating/pumping plant can be
pump is in excess of that required to pump the water ~llil'ici~ltics. incorporated in a computer simulation program. Such
to the boiler. This excess pressure can be minimised f
4.3.2 Feed p u m p duty, margins, a n d t h e need
f o r variable s p e e d
The duty of the boiler feed pump as determined by
if the pump can bc driven at reduced speed: if this
is not possible the excess pressure has to be broken E,
1, /\ technical description of electric motor drives
h'r~iinble-speed,induction, synchronous, etc.) for feed
I~Iltili)sis given in Volume D. A description of the
a program can then be used to compare overall cy-
cle efficiencies (it calculates the cycle heat rate) for
different input data and can be used to compare the
the boiler and turbine pressure flow conditions, is down across the feedwater regulating valve. As can E II*V o f steam turbines for driving feed pumps can thermodynamic effects on the overall cycle of steam
given by Fig 1.71. Shown on the diagram are the be seen from Fig 1.71, at low values of feed flow, 'g I!,, found in Section 9 of this chapter. turbine-driven and electric motor-driven feed pumps.
boiler feed-pump characteristics, i s . , the relation-
ships between the head produced by the boiler feed
pump corresponding to the particular value o f feed
the excess of head produced by the pump over the %
system resistance head is considerable. On typical
British sets of 500 MW and over, variable-speed drive -$
1 d,9.9 Economic comparison of s t e a m turbine
Figure 1.72 illustrates these thermodynamic effects
graphically for a fixed 900 MW sent-out (SO) unit
with a fixed main turbine exhaust area and pressure,
flow pumped, and the boiler feed pump speed. Various is always adopted because the cost of providing it is dllvus w i t h electric m o t o r drives for 50% feed pumps. Also shown, is an example
head/flow characteristics corresponding to the operat- much less than the operational and financial losses calculation to determine the additional work done
ing range o f pump speeds are indicated. The curve that would be incurred by this breakdown of pres- in the main turbine due to changing from a back-
sure. In addition to this, all conventional plant is I%/,i,iro/ costs
denoted as 'system resistance' is the relationship pressure feed-pump-turbine drive to a n electric-motor
between feedwater flow and the head that has to required to be capable of two-shift operation, i.e., i)ll the majority of 500 and 660 MW units, a variable- drive. This calculation is continued in Fig 1.73, where
be produced by the boiler feed pump to pump the to be shutdown overnight and started in the morning. ~pcl'ddrive to the 100% duty feed pump is provided the additional work done in the main turbine due to
feedwater into the boiler. Also shown in the dia- During an overnight shutdown the boiler pressure Iby ti back pressure steam turbine, using bled-steam nor having steam turbine driven pumps is compared
gram are the design values of feedwater flow for the falls significantly, such that during the start-up period Iloni tile main turbine H P cylinder exhaust and ex- with the electrical power used (and associated gen-
turbine plant, boiler plant and the feed pump itself. next morning, the boiler feed pump is only required Ilnllhling to the main IP/LP crossover. Bled-steam erator, transformer, cabling, motor, gears and converter
It is normal practice to design the boiler to pro- to deliver some 100-2043 bar instead of the approxi- li~ppingson the feed pump turbine itself have been or fluid-coupling losses) to drive the motor-driven
duce a higher rate of steam generation than that mate 230 bar closed-valve full-speed pressure o f the tlkerl in the past to supply steam to one or more pumps. It can be seen that in this case, which is for
appropriate to the value used in the turbine-generator pump. For this reason, the pump that is used during klaDcr of H P feedheaters. a back-pressure feed pump turbine with no bled-
design. This margin is normally about 5 % and is the start-up period should have a speed range down !,ti, large modern units (over 660 MW), the capital steam tappings to H P heaters (for a future 900 MW
intended to cover application variations (e.g., site to approximately 70% full speed to avoid excessive k'tlata of the extra bled-steam pipework and the boiler unit), there is a unit heat rate improvement with
conditions such as available cooling water) at the time IBGd PUIIIP turbine are significantly greater than the electric motor-driven feed pumps.

55
Tile steam turbine Chapter 1 Economics of the stealri i:yclr:
..

B/iCl< PRESSURE 13Fl~iURBlNl:. MOTO:? ILRIVEN i:€liD i,UMlii.S


2~50% FEED PUMPS %r50*/oFEE:) I'IJMI'S -
.
I
CHANGCSUUE TOUSEOFfrlOTOR OiilVt
lexl>!eirodi r u oiunt(scn8 ovooutputortotai n c i i r u p p t i e ~ )
FiGURFS FOHVAHHBIE SPEED MOTORS IN BRACKETS WHERE DI:I:EHENI
,50vo DUTY PUMPS)

ADOIIIONAI HEAT SUPPLIE0:NREHEATeR - 16996 AOUITIONAI.WORKDONE N i i ' i U R B N t - 4 280:0

ii001TiONAL POWER REQUIRED


8 Y FEE0 PUMP
= 2MB ADOiiiONhi WORK DONE iN LP TURBINE
OUETODiVERGENiCONSIANTPRtSSURE LlNES
DUETOLOWER WETNESSLOSS
O.~Uvo
= 0228
-
LOSSESASSOCIAT-TEDWTWMOiORDRlVE.
ADDITIONAL GENERATOR LOSS
TRANSFORMER
CABLlNG
-
= 004"0(004"/.]
001""10.01"%~
= 005% (005%)
MOIOR I& INVERTER) = 00996 (013%1
GEARBOXIFLUIDCOUPLlNG = 0 20%. (0.00%)
= 03Sah<O230/r)
DEIERIORATIIION IN HEAT RATE - 44B0laI4.320/ol iMPROVEMENlIN HEATRATE - 6 We)o

NET HEiirRiiiEiMPROVEMENi 7 499 - 4 4 8 = OSl~b(lN0UCIIONMOIORS)


499 - 632 = a 6 ~ o m l v a n i a a i e s ~ ~ ~ ~ ~ 0 1 0 ~ ~ ,

I'lCi. 1.73 Collll~lrisoi)OI iilrbille-drives and motor-driven feed pc~rnps

Ill' exhaust, and is therefore a lower grade o f speed, has a soft-start capability (oniy 1.5 times against
r l than that used for the back pressure turbine, 4.5 times full-load current) which salves the station
lllc steam is exhausted to the feed pump turbine's electrical system problems.
condenser o r to the main condenser. This has
'vantage of reducing the steam flow (and hence
loss) through the main LP turbine, or of Running rosrs
18 its required exhaust area.
In addition to the flow and head margins applied
SPECIFIC ENTROPY, ~JI~QK ;I3 operating data demonstrates that feed pumps
to the feed pu,np (and hence to the drive, that
licilicve the same availability figure regardless of
been described, clcaric motor drives are cur.
A ADDITIONAL HEAT SUPPLiED IN REHEATER (if dl.iver. Hence the savings in overall CEGB
=62.g (3588.2-31232) = 2924MW = 1 49°/0TOTAL HEAT SUPPLIED to be able to give their rated
. I I I rlilming costs froin the higher feed pump system
output at a eicctrical system frequency of
(3 ADDITIONALWORK DONE IN IP TURBINE i i i l i l i l i i ~of a 100% steam and two x 50% electric
=62g (3588.2 .29735) = 38.65MW = 4,29°10 TOTAL POWEROUTPUT 49,5 Hz so, at the operating condition of
i l>llws, colnpared with three x 50% electric
C ADDITIONAL WORK DONE IN LPTURBINE Hz, is again a margin to be
Iiilln~s,are not significant. (Typical feed pump
(DUETO DIVERGENTCONSTANT PRESSURE LINES) for, in this case by VSM converter or by cou.
=62.g (785.4 .689.8) 0.852 = 4 . 4 4 ~= 0.48NTOTAL
~ POWER OUTPUT 1 availabilities would be 99.96% compared with
(DUETO REDUCED WETNESS LOSS) = 0.22% TOTAL POWER OUTPUT piing slip, Hence, the normal duty point for the feed
pump drive has significantly less power output than
MW TOTAL
HEAT SUPPLIED its 100% rated output. Figure 1.74 compares the
MW GENERATED MW SENTOUT (BOILER 8 REHEATER) kgbTSV overall efficiencies of VSM and motors with fluid
BASIS: Economic c o m p a r i s o n of variable-speed couplings, for decreasing pump outputs. Even at the
1 BACK PRESSURE BFPT 900 900 1962.4 772.0
2 INDUCTION MOTOR 925 900 1954.2 757.5 r &%MI drive with induction m o t o r plus normai duty point, the advantage of VSM drive can
3 VARIABLE SPEED MOTOR 923.5 900 195j.o 756.3 clearly be seen, and the difference in efficiency affects
station lifetime costs signficantly. This difference at
the duty point is mainly due to two factors:
F,C. 3.72 ~ h ~ ~ ~ ~ o d y effects e the change to inotor-driven feed PulnPs
n a m i of
Fluid coupling slip - it is an inherent feature
lllc presently preferred auxiliary electrical system
of fluid.drive designs that there is still some slip
illlie of 1'1 kV, the direct on-line starting of squirrel-
'''duction the input and output turbine,
for 50Vo duty feed pumps On
even at their rated output, which creates losses in
=he back pressure turbine option considered above problems have occurred with this type o f ~iiodernunits (900 MW and over) would involve
form of heat in the working fluid (removed

.
has no bled.steam tappings for HP heaters because Overseas electricity utilities have tended to use c0 cvelopment o f quick-switching techniques not by coolers),
it has bee,, found [hat, in practice, the improvement densing turbines with their slower 'International fly available. The squirrel-cage motor and geared
they give to the overall cycle efficiency can be offset pumps because they can give a better overall lllic coupling gives the minimum first cost, but Gearbox losses - VSMs have the same advantage
by the effect of the main boiler feed pump availability cycle efficiency (heat rate). Steam is usually extracted lirect drive high speed synchronous motor (about as steam turbine drives in that they can drive
on ~p heater ALSO, feed system stability from the main turbine IP cylinder exhaust instead Of r/min), fed from a converter to give variable the high speed (high power) pressure stage pump
T h e sream turbine Ciiapter 1 Economics of the stearn cvcli.

the four feed pump oplions that were the subjecl


of detailed invesligation fox a typical future large
coal-fired turbine-generator unit. This histogram sum-
marises the effects of the factors already discussed
in this section, the main points of which are repeated
below.
From this study, the three x 50% feed pump
option became the only viable one for many reasons,
but mainly because it is the best compromise between
feed pump system availability (no interruption to
full-load outout with one feed Dump unavailable)
and capital cost. Operations data ~ ; O ~ ? E G B sources
suggests the same level of pumpset availability regard-
less of the type of drive, so for these four options
(all three x 50%) the iloss of availability' costs shown
on the histogram are all the same.

due to not having three identical pumps (increased


maintenance trmes and spares holdings), and the fact
that operating data shows that repair and maintenance
costs are directly related to capital costs, which ale
higher for the steam ootions.
Capital costs reflect the higher cost of steam turbines
and their associated bled-steam pipework, valves, ctc.,
compared to electric motors, with the condensing steam
turbine (option 3) being the most expensive, due to
the larger steam volume and the design problems COST OF LOSS OFAVAILA~ILITY
FIG. 1.74 Variation of electric motor drive efficiency involved with the last-stage blade. The VSM and con- L=l REPAIRS A N 0 MAiNTENANCECOSTs
with outpiit, for boiler feed pumps verter equipment (option 1) is more expensive than C3 CAPITALCOST
the simple induction motor with fluid coupling (option
RUNNING COSTS RELAiiVE TOOPTION (31
2), but there is more uncertainty in the latter cost due
to the development costs of equipment to cater for the
directly, so that the gearbox (reduction) only has high starting current with existing 11 kV station electrical FCC;.1.75 Ranking of feed pump opcioiis
to transmit the suction stage power, which is about systems.
20% or less of the total feed pump power. For the Running costs are presented in Fig 1.75 relative to
same gearbox efficiency the actual power lost in the the condensing steam turbine-driven pumps (3) which
gearbox will therefore be up to four times as much was found to be the most efficient option. For turbine- si~r!ilicantly lower load than its rated output. Since 4.4 Turbine by-pass systems
for a n induction motor/fluid coupling pump, where driven pumps, the differential heat rates, calculated tllr efficiency of the induction motor with fluid This comprises a pipework system with valves and
the slow-speed motor has to transmit over 80% o f by computer program using data from CEGB refer- caoi~iingfalls off with decreasing load much quicker pressure dropping devices to enable live steam from
its power to the pressure stage pump through a ence designs, have been used to obtain the equivalent Illan the VSM efficiency (due to coupling slip losses - the steam raising plant to by-pass the turbine complete-
step-up gearbox (usually incorporated in the fluid lifetime running costs between the turbine and elec- IDC Fig 1.74). the through-life running costs of this ly and be dumped into the condenser. The associated
coupling). trically-driven options. The back Dressure turbine option el~lion(2) are greater than for the VSM option (I). control system will open the by-pass according to
is based on the most efficien; designs but without An example of how an electric motor-driven feed the specific needs of the plant. The need for a by-pass
bled-steam tappings for H P heaters, to avoid possible pUlnp system can give a better overall steam cycle system and the purposes to which it may be put are
Rapidly increasing slip losses in the fluid coupling feed system stability problems and loss of heater qfl'iciency, i.e., a better heat rate, than a back pressure discussed in this section. The details of its physical
lead to a much sharper decrease in drive efficiency Itlrbine-driven system is shown in Figs 1.72 and 1.73, implementation are discussed in Chapter 2.
availability.
than the VSM, for decreasing pump speed (output). which are largely self explanatory. This efficiency The requirement for, and configuration o f , by-pass
For the motor-driven pumps, the lifetime running
Lifetime running costs will increase even further, costs take account of the power input required at the yalli can lead to the improvement in through-life systems are mainly governed by the boiler arrange-
relative to the VSM, if the fixed-speed motor and Illnning costs that can be seen on the histogram if ment. The general considerations applicable to fossil-
pump couplings (calculated for all pumps, whatever
fluid-coupling feed pump has to be run at part-loads l!(*lions ( 1 ) and (2) are compared with option (4). fired and AOR superheat cycles are discussed first.
the type of driver, using pump efficiencies consistent
for any significant periods o f time. with what might be expected for international stand- l ' l ~ eabove conclusions relate to a specific set of The special considerations for PWR wet steam plant,
ard machines), augmented by efficiency losses in the C'Lonomic circumstances. Different applications, studied using steam reheat, follow.
d r ~ v epackage, associated cabhng, and transformer. The U~ilinsta scenario of changing fuel prices, capital costs
4.3,5 Example Of the results Of a n overall tradltlonal pump head and flow marglns (3%/5%) nsd operating costs may result in different conclusions. 4.4.1 S u p e r h e a t plant
parison Of the through-1ife costs Of four feed and the reoulrement to be able to oroduce full out- Mc\,crtheless, these considerations exemplify the need The superheater and reheaters are an integral part o f
p u m p system options lu ilnalyse not only the capital cost, but also the other the boiler. The basic system for a single reheat turbine
put with a'minimum electrical system frequency of 'f
Figure 1.75 shows the capital and running costs of 49.5 Hz ensure that the pump duty point is at a
8 Ouslponents of lifetime cost in arriving at a solution. is shown in Fig 1.76.
The sreain ti~rbine Chapter 1

heales and lhe main sleain ~>ipework.A tnorc iaipid


boiler run-ill, may he possible, thus saving fuel.

c Water loss during start-up is mioimised since, if'


no by-pass is fitted, supcrheatcr vents are used
lo discharge steam to provide a flaw o f steam
I l ~ r o u g ltile
~ sugerhealer.

61 Independent operation o f the boiler is more readi-


ly achieved with the fuli capability of de-aeration
and condensate poiishing.

4.4.2 BY-pass capacity


y SO.

/
Sizing of the by-pass system is based on the most
$
iiidilous duty, in this case the abilily to run-thiougl~ ,.
8 ti trip to house load. The H P by-pass size is usually
8 i.spressed as a percentage of the H P stop valve flow m-
@ at rated full-load conditions. T o cater for a load
f,
c t i o to h o s e l o a d the size of the b. . m will
t i
lii. given by:

pic. 1.76 ~ a s i ctuibliie by-pass iysiexn Ill' by-pass capacity


Wliei) oil iilii by-pars, tile governor i,alue and interceptorvalve are ~losed.the sicam parses iron, the supcilieatei
lo the HP by-pars valve, tiicn titrougli ihe lelieatcr and LP by-pass valve. The rlenm is fully atlcmpeiaied by house load
spray water before parriog to the condenser. ~ l l inon-renwn
e valve in the H P turbine crllausr pre'enrs a ieveisc
110\s- into the turbine, In praeiicc. ~ulierca ungle vaive is rhowi>. tlicre are usually two or more parailel
values pcifoilnlng each duty
= 100% -
( full load ) loo] -
1'14. 1.77 Typical lleai load on col>denrei
[inherent boiler ioad rejection capacity]
= 70% (typically)
The additional throughput of condensate flow must
can be slowly reduced in load to a low level, ready also be taken into account in the design of the LP
The system depicted permits completely independ-
for reioading when required. If the boiler load is 'i'lic L P by-pass size is generally expressed as a heaters.
ent boiler operation. Although the system operation
seems quite straightforward, the function of reducing maintained and the system fault cleared, the unit llcicentage of the interceptor valve flow at rated full-
the steam pressure from turbine inlet conditions down may be reloaded to a generator ioad corresponding Ihad conditions. For a trip to house load, rapid closure
to exhaust conditions invalvcs a major change in the to the capacity of the by-pass within a fcw minutes. 01' the interceptor valves causes a pressure rise and 4.4.3 System effects
energy available which imposes a heavy duty on the Subsequent loading to full load is then accomplished lliu LP by-pass opens to contain this. The LP by- In operation, other problems arise from the intro-
components involved. The need to supply a by-pass at the normal rate. ~)ilssis ilsually sized at well beiow the 100% capa- duction of the by-pass systems. Followit>g a load
system must therefore be carefully evaluated against If provided for this basic reason, the turbine by- ibilily since, under the worst case of rejection from rejection, the H P governor valves close fully and once
the benefits. pass system may also provide other benefits, although filli-load, any excessive pressure rise is accommodated the by-pass is operating, the non-return valves in the
The prime reason why UK manufacturers have these are not always significant. A full list of the Iry lifting of reheater safety valves for a feu, minutes. H P turbine exhaust prevent reverse flow into the HP
sunplied by-pass systems for certain applications is other possible benefits are summarised as follows: A by-pass system sized on the basis of load rejec- turbine. However, the steam already in the turbine
to-permit continued operation o f the boiler and turbine 1lo11 capability can readily accommodate the duties cylinder is effectively 'bottled up' and the continuing
For hot starts, following less than a I 11 shutdown, Iaiposed for start-up and independent boiler operation.
following a large load reduction or a circuit-breaker rotation o f the turbine causes rapid overheating of
the boiler flow through the by-pass can be adjusted To reduce the enthalpy of the steam, it is neces-
trip to the house load. In a weakly-connected supply the blading due to turbulence and frictional heating
to raise the main and reheat steam temperatures Nury to inject spraywater, derived from the condensate
network, this may be an overriding consideration, of the contained steam.
l o the values required by the turbine. When the hyslem, after both H P and LP by-pass valves. The
since the abiiity to run-through such a transient would A similar problem arises during start-up. Without a
turbine valves are opened, the thermal stresses in rpraywater flow adds to the H P by-pass flow to give
allow iapid reconnection of the unit following fault by-pass, the H P turbine exhaust pressure prior to
turbine components is minimal. The subsequent Ihe mass flow rate through the L P by-pass system;
clearance. Without a by-pass, the power mismatch synchronisation is at a very low value, controlled by
run-up and loading may then be selected t o mini- lliis is therefore used in sizing calculations.
following opening of the circuit-breaker causes the the flow through the I P and LP turbines. With a by-
mise either the time to load or the thermal stress, The supply o f a by-pass system reflects on the

.
turbine governing and interceptor valves to close pass, there will be a much higher flow through the
or some compromise between the two. tlcsign of other plant in a major way. To cater for
r a.~ i d i y . T o accommodate the reduction in steam
~
by-pass and the turbine exhaust pressure is consider-
flow. the boiler firing rate must be rapidly reduced 0,
. ~~
starts. the by-pass
.. may be used to bring the supply of spraywater on top of the maximum ably higher. Normally this value of exhaust pressure
to a minimum. On most boilers, with the possible the main and reheat steam temperatures to a posi- U P by-pass flow, it is necessary to increase the rat- would only be attained with a much higher flow
exce~tionof some oil-fired units, this involves a firing tive ,,,ismatch in order to minimise the time to In); of the condensate extraction pumps. through the turbine. The H P turbine is therefore
trin which necessitates a ourgine
- ~ - ? ~~~~ . operation for several inad ~. . i t .h i.navailable
~ ~ ~ stress
~.~~~~ ~ -
mareins The increased flow and high enthalpy of the by- operating with its efficiency considerably reduced and
hours prior to reloading. If a by-pass is supplied, a purs steam increases the size and cost of the con- in addition is producing some rotation'loss heating.
large proportion of the excess steam can be diverted In general, the by-pass provides for a smooth deliser significantly. Figure 1.77 shows how the A typical condition line for the H P turbine is shown
through the by-pass system. If necessary, the boiler warm-up of boiler components, including the re- iudditional heat load relates to the H P by-pass size. on the Mollier diagram in Fig 1.78.
F&ri
%(
*r g
$,+ The steam turbine Cliapler 1 Economics of the steam cyclc
..,,
&
up of the boiler and tu~.bine,11s economic impact is
most readily appreciated by considering the effect on
hot starts following an overnight shutdown. This is
the duty normally seen by a unit allocated to two-
shifting. Figures 1.79 (a) and (b) depict tlie diffei-
ences in unit start-up with and without the by-pass
in operation. The start-up time is roughly 15 minutes
less if the by-pass is used. The saving may be coil-
siderably more if the boiler/turbine is not a flexible
unit designed for two-shifting.
Depending on the intended duty of the plant, this
may represent a significant saving to lifetime costs.
There is also a small saving because, without a by-
pass, water would be lost through the superheated
vents as part of the standard start-up procedure. A
further advantage of the by-pass system for start-up
is that inexperienced operators are more easily able
to bring the steam conditions to appropriate values
before rolling-off the turbine. Against these advantages
must be set tlie cost and maintenance burden asso-
ciated with the supply of a by-pass system. In general,
a small capacity (35%) by-pass system is unlikely to be
iustified on the erounds of im~rovementof start-ur,
capability.
One notable exception is the once-through boiler,
where a substantial bypass flow is required for a
lengthy period during start-up. The CEGB AGR ma-
chines, which use a superheat steam cycle, are examples
of this. The AGR also needs to use the by-pass for a
lengthy period during shutdowns, particularly if the
reactor is to bc maintained at temperature in readiness
for the next start-up.

F ~ c . 1.78 HP turbine condilion line 4.4.5 PWR w e t s t e a m plant


The reheater is not part of the boiler. This function
is carried out by live steam from the reactor and
bled-steam from the H P turbine in vessels mounted
These problems arc effectively dealt with by pro- adjacent to the turbine. There is therefore no require-
viding a connection from the H P turbine exhaust to ment for separate H P and L P by-passes to permit
the condenser, sized to take approximately the H P independent operation of the reactor and steam gen-
flow that obtains prior to synchronisation and ar- erators. A single by-pass circuit to dump H P stop
ranged to open only when the by-pass is in operation. valve inlet steam to the condenser is employed. Warm-
During by-pass operation, there is a transient loss through of the reheater is accomplished as part of
in the water stored in the de-aerator due to the re- the turbine start-up. Rapid starting and utilisation for
circulation of spraywater. An assessment o f the worst two-shifting is not the role of PWR plant.
case transient is normally made to ensure that feed The reasons for the supply of by-pass systems on
system stability is maintained. PWR plant are therefore:
The remaining problems concern the malfunction
of the by-pass system and associated plant. T o pro- (a) To enable the nuclear plant to accept transients
tect the L P turbine, it is necessary to trip the by- without tripping or actuating safety valves.
pass valves closed in the event that loss o f conden-
ser cooling water causes a high L P turbine exhaust (b) T o remove stored energy and residual heat follow-
pressure. Failure of spraywater valves and other as- ing a turbine and reactor trip to bring the plant
pects are covered in more detail in Chapter 2. to equilibrium.

(c) TO permit a manually controlled cooldown of the


4.4.4 I m p r o v e m e n t of s t a n - u p capability plant to the point where the residual heat removal
The provision of a by-pass system improves start- system can be put into operation.
The steam turbine Chapter 1 Turbine blading

(d) I~ollawiiiga turbine trip or sliutdowo, lo maintain only i-eqilircs a by-pass capacity of 40% and is ac- Ii Turbine b l a d i n g mid blades need to be very robust, Tlie diapliragnl
the reactor and steam generators in a hot-standby complished williout discharge lo atmosphere. lhas the atlvantagc of a i-clatively S ~ R I I diameter a!
condition, ready for turbine restarting. Both condenscr and atmospheric sets of valves are llle stcam seal between diapliragin and rotor, hiit
required to open fast, particola!-ly for duties (b) and this labyrinth scal niusl be as good as possible to
(d). The opening time of approximately three seconds
L1 Impulse stages deal with ibc high pressure drop. Tlrc radial iabyrintll
A diagram of a typical by-pass system configuration
is shown in Fig 1.80. The main by-pass is through permits containment of tile steam pressure rise witll- seal ensures adequate insensitivity to axial dispiace-
six parallel sets of control valves into the three con- in the settings of the atmospheric valves for the 6.1.1 Moving b l a d e s - details a n d c o n s t r u c t i o n rnent between the rotor and the casing. A typical
denser sections. Valves I, 3 and 5 are niodulating reactor trip case. The valve closing rates are designed lli !lie impulse stage, invented by Professor Rateau, impulse stagc arrangement is shown in Fig 1.81.
valves used for all three functions but sized to be to protect the turbine and condenser in the event llic imajority of the lieat drop occurs in the station-
capable of performing the cooldown duty (c) on their of a system failure. A closure time of 5 seconds is itry blading and the driving force on the stagc arises
own. Valves 2, 4 and 6 are capable of being switched provided to protect against high condenser/turbine from the change in momentum o f the stcam across
open or closed and arc only used for duties (a), (b) exhaust pressures in the event of a condenser cooling llic tiloving blades. The impulse design possesses the
and (d). An additional dump t o atmosphere is also water failure. The effects o n other plant are similar itdvi~ntages o f compactness and comparative inscn-
provided for duty (d), sincc infrequent discharges t o those discussed for superheat plant and are taken hllivity t o blading clearance since little pressure drop
to atmosphere are permissible for short durations. into account In the design. Itikcs place over the moving blading. However, the
This reduces the duty on the condenser, permitting The provision of sufficient by-pass capacity t o liioving blades are subject to disturbances from the
considerable economies to be made. Thus, in the avoid tripping the reactor in the event of a turbine- Ilur/.le wakes, so resonance must be avoided and
evcnt of a turbine-generator trip, valves 1, 3 and 5 generator trip justifies the by-pass on economic grounds. rie;iln bending stresses must be kept low; also, sincc
are opened first, followed by valves 2, 4 and 6 and If the reactor were allowed to trip for a turbine l l ~ u~nomentunichange is relatively high, the moving
finally, if necessary, the atmospheric dump valve. problem lasting for perhaps only 30 minutes, there Irliides have t o be robust and tend to be heavy. It
For one reactor, the total capacity is arranged to be would be a severe availability penalty. I,. ihcl-efore regular practice to attacll the iadivid-
approximately 70% of the full MCR steam flow with The problems of implementing a by-pass system ll~llly manufactured blades to a wheel disc, often by
about 10% being accommodated by the atmospheric are addressed in Chapter 2. Thcse matters are proper- ,IlsildIe roots which engage with corresponding axial
dump valve. In association with further relief valve ly dealt with at the design stage and result in systems i l ~ ~ ~ o l d machined
ers on the whecl rim.
capacity in the reactor system, this permits a trip of which provide economic benefits by achieving better One or more protrusions arc left at the outer end
the total turbine-generator capacity. A reactor trip co-ordination between the turbine and boiler systems. 111 i l i ~ . moving blade. These pass through holes in a
ri,\,rrband which may in turn fit into a slot machined
Ill tlic outside of the blade: when these protrusions
nl tenons are formed into rivets, they keep the cover-
btisd in place. The coverband acts as a seal and braces
lllc blading t o reduce vibration. Each length of coves-
I)tlnd ties a short length of blades together and may
l i l t i t , tip to the next length or overlap, so that an
retleniely robust construction is created. Since a cer-
li3i11degree of reaction builds up towards the outer
!ll~i~iieterof all impulse blades, axial scaling fins arc
lur~iicd integral with the moving blade shroud or
~,o\'erband.

8.1.2 Fixed b l a d e s - details a n d c o n s t r u c t i o n


'l'llerc are two methods of constructing the stationary
Iloszlc blading. Built-up blades, machined from the
mlid, are used for nozzle plates and steel diaphragms, nc. 1.81 Modern impulse stage with labyrinth seating
Whilst cast-in blades, formed from steel plates em-
lredded into cast iron diaphragms, are used where
loeperatures are below 230'C. On some of the latest
tlinchines, HP blades have been electrochemically ma- 5.1.3 Velocity-compounded s t a g e
~lllned.An impulse stage is frequently used for the The first HP stage of a turbine, where it is desired
I'lrhl s a g e of the H P turbine. The fixed blades may t o give a large pressure drop t o the first row of noz-
1llc11be incorporated in an integral nozzle box, there- zles, sometimes incorporates two impulse stages on
Ily obviating the problem of pressure sealing at the the same wheel. This is done to protect the casing
inaldc of the blade ring. By absorbing a high heat and rotor from higher pressure and temperature con-
drop, the nozzle box arrangement also reduces the ditions. As a velocity-compounded stage uses ap-
IVessure and temperature of the steam impinging o n proximately the same heat drop as four impulse
llie 14P rotor and inner casing. stages, it is used t o provide a shorter and cheaper
Since impulse stage diaphragms have t o withstand turbine, although with some sacrifice in efficiency.
FIG.1.80 Turbine by-pass system for a wet stcam machine llie bulk o f the stage pressure drop, both diaphragm It is no ionger used in large base-load turbines.

64
Tl?e sreain turbine Chapter i

Figure 1.82 shows the arrangcrneill of such a 'This type of blading was designed and developed b)
stage. 'The iiazzlcs, of the convergent-diverge~~t
type, Sir Charles Parsons and lends itself lo ecoi~omiczil
produce "cry high stearn kinetic cncigy, sonic of production of blades from standard rolled sections.
which is absorbed by the first raw of blades, the Only a sinall heat drop can be accommodated pci
remainder being deflected back by the slationa~y blade row, due to the comparatively high velocity
guide blades and used in the second row. Both moving ratio required for good efficiency; this means that a
blades and nozzles are machined froin tlie solid and large number of expansions are required. Steam ap-
are nccessaiily very robust. proaches the moving blades with a velocity that is
low and substantially axial in direction. Consequently,
the driving force applied to the moving blades arises
almost entirely from the reaction force of the steam
as it accelerates through the moving blades. The force
applied to the moving blades is thus fairly steady, witli
very little disturbance arising from the nozzle wakes
of the fixed blades, so fairly high bending stresses
can be employed in the moving blades without risk
of fatigue failure due to vibration.
Since the pressure drop across the fixed blades is
small, diaphragms are not required, but small tip
clearances are needed throughout the turbine to pre-
vent excessive leakage losses. This was achieved iii
earlier turbines by axial sealing and end-tightening.
With solidly-coupled shafts which expand either
side of a single thrust bearing and with multi-casing
arrangements, end-tightening is not feasible and a
compromise has to be reached between fine clearances
sure drop develops across the moving blades and
to reduce leakage and large clearances to accom-
the steam leaves the moving blades at a higher speed
modate differential exvansion when starting. - to offset the higher peripheral speed, enabling the
Modern reaction turbines generally employ a com-
steam to leave the blades with the minimum of swirl.
bination of axial and radial sealing at the stators and
The stage is designed to have a fairly low degree of
rotors, and for this purpose, the rotor blades are
reaction at the base and, since the pressure drop
provided at their outer edge with shrouds formed
across the fixed blades decreases in response to the
of sections integral with the blade (see Fig 1.83).
These mate with replaceable finned sealing segments
I Aerodynamic a n d mechanical c o n s t r a i n t s increasing pressure drop across the moving blades,
lti i.;iily machines, the last few low pressure moving reaction increases with blade hcight. The radial tcn-
in tlie casing. Fins formed on the inner diameter of
lilii~lc~ were of constant cross-section. Thc stl.ess in sion duc to centrifugal force and the aerodynamic
the fixed blades provide sealing at the rotor.
l l i i i l y p c o f biade increased quadratically from the effect o f change of steam flow resiilts in a highly-
Small reaction-type blades can be manufactured
!ip lo the base and attained its rnaxiinum ijaiue in twisted moving blade, having a robust low reaction
by cutting from rolled bar of the requisite profile
Iri~asitionfrom blade to root: this placed a re- section at the root and a slim high reaction sectioit
or machining from bar, while larger blades may be
ii:lio~l on the length of blade that could be used at at the tip, see Fig 1.85.
separately cold-rolled after which the root portion is
heated and forged. Blades may also be machined from iionous speed. Modern last-stage blades have a
envelope forgings o r produced by precision forging, so section which reduces exponentially with the
that the profile requires no further machining; this of the radius. The tensile stress due to centri- 5.3.2 Blade t i p restraint
is valuable where tough materials make machining ss is then virtually constant over the gl.eater The use of long blades and large blade chords in-
difficult. Final machining can also be awkward where I of the blade length and this has enabled blades volves an increase in pitch and this creates compli-
integral shrouds and root fixings interfere with the lo 940 mm long to be used on 3000 r/min cations in the various devices used to stiffen the
machine tool. T o facilitate manufacture, modern prac- blade assembly and dampen vibration. A coverband o r
FIG. 1.82 Velocity-coinpounded (Curtis) stage O n modern blading, the tip diameter is typically
tice is to braze together short groups of blades before lacing wire must behave as a beam spanning the blade
machining the circumferential serrations on the sides Iloul double the base diameter, so that at the mean, pitch in resisting centrifugal loading, and must also
of the roots, see Fig 1.84. The brazing also permits Ill? blade pitch, i.e., the circumferential distance be- accommodate the substantial circumferential strains
easier assembly. Groups of blades are fitted in the lwrcli adjacent blades, is about 1.5 times the pitch due to radial elastic extension of the blades and the
5.2 Reaction stages rotor or casing in circumferential grooves which have UI liiu base diameter. The peripheral speed is also tendency of the blade to untwist at speed.
corresponding circumferential serrations machined in 1.5 ti~nesas great as at the base and the effect of When lacing wires are used, they are usually of
their walls. The blades arc secured in the grooves lI11h increased blade speed is to change the direction the 'loose' type with circumferential restraint on only
5.2.1 Fixed a n d moving blades - details a n d by similarly serrated side-locking pieces cut from rolled at' 1!1c incident velocity of the steam relative to the one blade in each group,
- ~
and are free to move
ConstruCtion strip. A suitable stop plate at the half joint locates fr~<~\'iiig blade. The moving blade inlet angle is there- circumferentially in adjacent blades, centrifugal forces
Although called 'reaction', these stages in fact employ the fixed blades in the circumferential groove and l b t c set to line up with the direction of the incoming providing the necessary damving
. .throurh friction. Thc
equal degrees of impulse and reaction, resulting in prevents the blade segments from rotating due to iilci~ni flow and the moving blade section is also gaps between adjacent lacing wires can introduce
the fixed and moving blades being of identical section. torque reaction. c l ~ ~ ~ n g This
e d . reduces the outlet angle so that a pres- complications in vibration patterns on long blades
66 67
Turbi~tchiadin(>

5.4.1 Fir-free roots


Fir-lice serrations lliay be in line with tlie axis ol
the macliinc, inclined to the axis. or curved, see
Fig 1.88. Curved fir-tree roots follow the blade chord
at the root section. Tire straight root, in iine with
the axis, is used for slightly-twisted end blades. Botl,
the iiiclincd and the cwved fir-trec roots are used
for iliglily-twisted blades t o achieve a closer blade
pitch at the inner steam patli. Optimum selection
of tlie dimensions and number of serrations of the
fir-tree root has been made possible by finite ele-
ment calculations o f stresses in the shaft and root.
Because o f unavoidable inaccuiacies in manufacture,
the pit between the supporting planks of the ilidividual
fi~.-treetips varies. This is also taken into account
in the calculations. Pull-out tests on fir-tree roots
have confirmed their reliability. In view of their high
strength and close packing capability, side entry fir-
tree roots arc gene~ally used for fixing last stage
liable. Some tliicketting of the bladc is required, how- L P blading.
ever, in the region of the tip tie to accommodate tlie 111 earlier turbine stages, fir-tree serrations are $ma-
ball-joint sockets. chitied circu~nfercntiallyin grooves in the rotor, and
A few manufactui.e~.shave dispensed with all forms groups of biades are secured in the grooves by simi-
o f stiffening, relying on the stiffening effect of cen- larly-serrated side locking pieces cut from rolled strip.
trifugal forces, which can be very substantial on Tile blades of the first row of the H P turbine are
freely-cantilevered blades. This type of blading tends axially attached to a short wheel disc o n the rotor
- t o be wider and heavier than blading with stiffening
and introduces difficulties in manufacture and rotor
by straddle roots, which engage with corresponding
shoulders machined circumferentially on the wheel
design. Freely-cantilevered blades are most suitable rim. The straddle fixing therefore acts as an inverted
I:IG 1.85 i:>nal blade envelopes
for the last stages of very small high speed turbines, fir-tree, the tree shape, usually with only one or two
where it is not bossible t o intioduck complicated stif- branches, being formed on the rotor disc.
fening devices and where the increased bladc width
is not an embarrassment.
and overlapping lacing wires are sometimes used to
give some measure of continuity around the annulus. 5.4.2 Pinned roots
A coverband of conventional design is not feasible Multifork pinned roots are generally easier to maoil-
5.3.3 B a u m a n n e x h a u s t facture than fir-tree roots, since the machined faces
for slim sections and where the peripheral speed may
bc approaching Mach 2, but a continuous ring o f A special type of exhaust blading, invented by Dr are plain with no undercuttitlg, and the pin or rivet
stiffening devices of sufficient elasticity may be used Baumann, has been used by one manufacturer in holes are simply drilled and reamed. The enormous
t o accommodate circumferential strains. The elastic order to achieve greater exhaust area without undue force o n moving blade roots, particularly in the LP
arch banding, shown in Fig 1.86, braces the blade lengthening of the blades of the last moving row.
tip and provides some resistance t o blade untwist as Known as the 'multi-exhaust', it used two-tier blades
well as largely permitting circumferential strain. for the penultimate stage, steam from the outer tier

2F--F
Zigzag spool rods shown in Fig 1.87 are frequently exhausting directly to vacuum. The net result was
incorporated in the tips of the last-stage L P blades that, without lengthening the blades of the last row,
of modern turbines. The spool rods provide no re- but by lengthening those of the previous row, the
leaving loss was appreciably reduced.
-
straint against circumferential exoansion or centri-

xK
fugaal untwist, but the reduced sections at the ends
of the rods are forced against the holes in the blades
by centrifugal action and the sliding friction provides
effective damping, minimising blade vibration and 5.4 Moving blade root attachments
high frequency flutter at the blade tip. The last-stage blades of large turbines develop centri-
fugal forces of hundreds of tonnes when running, tbilncllned
A recent variant to the spool rod is the ball-
jointed tip tie. The dumb-bell-shaped tie rod fits into
a fixed ball-shaped socket in one blade and into a
very efficient methods of attachment are therefore
needed.
Systems in use at present include rhombus fixings
I'IG. 1.67 Zigzag rpool roc1 lip-tier
i~
iclCurved
sliding ball socket in the next blade. In common with
the spool rods, centrifugal strains are not restrained in a peripheral slot, finger-shaped pinned fixing and close staggering o f the blade cascade and the
but the ball-joints provide more controlled damping straight or curved fir-tree roots. Fir-tree roots provide
and the evaluation of tie rod stressing is more re- a n excellent method of attachment, since they permit lhc shaft teeth. FIG. 1.88 Types of fir-tree roo,
A

l l i c stcai-ii tiiihine Chapter 1 Turbine i,li~iiiin;i


0
,,

stages ellsiil.es rigidity i n any typc of root fixing at to take into account the torque ieactioli 0x1 t l l c
$
synchronous speed but, contrary to thc fir-lrec root, rliapl~ragin.
tlic multifol-k pinned root provides a rigid fixing Ail keys have provision for adjustmcnt, so thal
when the macl~ine is statiannry. This enabics the correct aiignmeot of the diapliragms can bc achieved.
zero speed vibl-atioii characteristic of the blades t o A typical arrangemcnt of diaphragm support and
be confi~.medwith confidence and ensures a smooth location keys is shown in Fig 1.89.
unstepped spectrum of characteristics, as tile machine
is r u n up. Replacement of multiforked blades, how-
ever, involves further reaming of the securing pin 5.5.2 Radial s u p p o r t p a d s
holes. This is awkward in-siru and can only be carried
The provision of this system of kinematic support
out a limited number of times.
becomes progressively more difficult as the diameter of
the diaphragm increases. As the size of turbine has
increased, the basic concept of kinematic support has
been modified t o suit the circumstances.
5.5 D i a p h r a g m c o n s t r u c t i o n and support One alternative has been t o fit keys in both half-
diaphragms so that each is supported independently
at the horizontal joint. This arrangement requires that
5.5.1 Kinematic s u p p o r t there is a gap between the half-diaphragms for ex-
pansion, resulting in a steam leakage across the half
AIi diaphragms are dividcd at thc horizonlai joint
joint: it also requires more machining and fitting.
into two scmicircuiar halves l a permit assembly.
Thc difficulty in proxaiding kitiematic support for
Iliaphragms arc located in the turbine cylinder as
large diaphvagms occurs inainly in LP turbines, where
close as practical to the horizontal and vertical axes
the outer ring diameter is large. In the LP turbine,
of the machine, in order to reduce to a rninilnum
the differential temperature between diaphragm and
the effects of differential expansion. Particularly when
cylinder that has to be accommodated is much reduced.
the machine is small, the ioss in output arising from
This, together with the need t o provide some form
the internal ciearances can bc significant. It is for
of stop-plate for the top half-diaphragms, led to an
this reason that the practice developed of supporting
alternative arrangement where, in the running condition,
and guiding the diaphragms in the inner cylinder by
the top half-diaphragm is supported on the bottom
keys in each half. This method of iocation, which
half-diaphragm, which itself just rests in the recess
is known as kinematic support, is generally used on
in the cylinder. The clearance for differential expan-
current H P and IP turbines o f the disc and diaphragm
sion is achievcd by exact machining of the outer
type, and o n the early stages of L P turbincs.
diameter of the diaphragm.
The details of a kinematic support systenl are in-
A more practical arrangement is to machine a
flt~cnccd by the method of manufacture. As the
generous radial clearance between cylinder and dia-
adjacent surfaces of the cylinder and diaphragm are
phragm and to fit the haif-diaphragm with a nuinber The first four L P diaphragms are usually a welded
circular, the diaphragm has t o be supported on keys hli~iids fitted into grooves machined in half rings,
of radial support pads which are then dressed to construction, similar t o the H P and IP, with stainless
fitted into milled recesses in both cylinder and dia- wllirh may be machined from plate or may also be
obtain the required location of the half-diaphragm. steel blades, rims and centres. Later stages may have
phragm, as close to tile horizontal joint as practical. ci~st.The diaphragm half rings are then built up by
Differential steam pressure forces the diaphragm pre-machined biades cast into cast-iron inner and
Transverse location of the diaphragm is achieved by weirling the nozzles to the inner and outer half rings
outer rings against the downstream axial face of the outer rings. Cast iron enables optimum shapes of
keys o n tile verticai centreline fitted into milled key- lhc axial faces of the half rings. Castings in stain-
circumferential recess in the inner cylinder. T o prevent
ways. Adequate clearances are provided o n fitting the steel suffer from the formation of regions of steam passages t o be formed. These diaphragms may
the diaphragms seizing in this recess, and to permit
keys t o ensure freedom of movemetlt for differential n ferrite, particularly near the trailing edges o f also be cast as complete halves in stainless steei.
adjustment, small crushing pegs are fitted in the up. Very large modern last-stage L P diaphragms have
expansion. T o avoid steam leakage between the two (1 blades, and cracking near changes in section
stream face of the locating spigot. massive sections for the rims and centres and can be
halves o f the diaphragm, the top half sits o n the .ss cooling rates are very carefully controlkd. Also,
Temporary support pads may be fitted and adjusted
bottom half, and keys at the half-joint are arranged 81cc the welds penetrate only part way into the inner extremely heavy if made from solid castings. The rims
t o achieve the correct positioning of the diaphragm and centres are therefore sometimes fabricated from
in line with, and transverse to, the machine centreline. d outer half rings, a circumferential crack exists
in the cylinder. The packing bush radiai clearances
This iocates the top half-diaphragm axially and ra- fbe middle of the rings. Radial cracks also exist plate into semicircular hollow box sections. Weided
are bored to a charted size and checked with the
dially with the bottom half-diaphragm, and provides Iween each nozzle section where they butt against constructions are always heat treated t o remove iocked-
rotor in position. If necessary, the temporary pads in stresses and allowance must be made for distortion.
an effective steam seal. The keys o n the bottom half c another. These cracks weaken the assembly and
are adjusted t o optimise radial ciearances. When the
horizontal joint have to be sized t o take the weight II provide initiation points for fatigue crack propaga-
desired alignment has been obtained, the thickness
of the complete diaphragm. rn. Investigations are being carried out t o develop
of the temporary support pads is gauged and the final
T o enable the top half-diaphragm t o be retained sided diaphragms, using full-penetration electron
in the top half cylinder when it is raised, stopplates support pads ground t o size.
welding. This will largely avoid the problems 5.6 Blading m a t e r i a l s
are ~ r o v i d e d at the horizontal ioint o n e a c h ~ s i d e . tcrnal cracks or voids.
The diaphragm is located axially against a machined A more modern method of construction is to
recess in the cylinder which offers frictional resistance 5.5.3 Diaphragm c o n s t r u c t i o n ~ctrochemicaiiy machine each complete half ring 5.6.1 12% Cr s t e e l s
to the expansion of the diaphragm relative t o the H P and I P diaphragm nozzles may be individually I of a solid stainless steei blank, thus obviating Turbine blading alloys are chosen for their ability to
cylinder. When sizing the support keys, it is usual machined or cast and the inner and outer blade up- l e problems of welding and casting. provide properties particular t o the mechanical and
The steam turbine

ca\~irnnmental service u,liicli tlky must cndorc. One gcsatuic bladcs. Aii siccis of lliis type ieqiiive tlic irhiliancc but in01 as good as Sleiliic 6 , whicli is 'Tlic vibiaiioii clr;iiacteiistics of t u ~ b i n e iniicl~iix
o i thc first considerations of 1.i' biading, for exampic, addition of an nustcnite-forming clement to pl-eveol cc>i~iinoniy!ired as an erasion shicld on steci I,[' blades, as lnicasiised n,,clci- opciating condiliol~s, ;air
is the ability to rcsist cosiosion and scaling in fast.. the fol.m;itioo of ?ones o f delta ferrite in thc material. lilii<ii~ig. usually found to be cxtiemely complox and oiici,
flowing wct steam. This generally roles out low alioy Nickel is employed for this purpose but its conlenl 'i'lic yield sticrrgth o f a typical titanium alloy in quite different from tl~eoretical predictions. There
steel and blades are made froin either stainless steel is limited in ltigli temperature blades becaiisc liighci l11r anncaled condition is approxirnatcly 50% bettel~ are several reasons for this.
or titanium alloys. A sccond icqiiiicmenl Is adequatc percentage additions reduce creep strcngtli. T11e addi. l11ii11 standard 12% chromium stainless steel material, First, in spite of tlte advances in finite element
tensile strength to resist steady centrifugal and bcnd- lion of niobium to the 12% Cr Ma V steels increases sil<leven slightly superior to the Super 12% C r steels: computatio~i in recent years, the intricate geometry
ing stresses. Sucngth without ductility Is not desirabie; stress rupture strength and creep strength in the short I l l ? ductility is somewhat lcss, The fatigue strength of a blade, whlcli is denlanded for aerodynamic pes-
ductility is needed to accommodate stress peaks and term, but the strengthening effect falls off with time 01 iilanium alloy is, however, generally higher than farmance, makes it a very difficult component to
concentrations. Ductility aiso is needed to resist rub- so that the long term properties are no better than tltr 12% Cr stecls. analyse theoretically. Consequently, predictions for
bing, and, in the case of shrouded blades, t o permit those of the 12% Cs Mo V steels without niobium. 'Titanium alloy is not as readily forgeable as 12% the modes and freooencies of a sinale cantilevered
the peening of tenons to secure the shroud. Impact Typical British steels for high temperature blad- VI inaterials. The titanium alloy has to be forged at biade may not always be very accurate. Then, a second
strength is also necessary, since contact with foreign ing include FV 507, a ferritic casting alloy with good a lower temperature which means that more energy factor which compounds the problem, is the existence
objects is sudden. Water slugs can produce impact tensile and crecp properties combined with low thermal i b re~iuiredto forge a certain amount. Also, since all of muitiple interactions between each blade and all
loading. expansion, and Esshcte CKM 12 from British Steel, tlililliilln alloys are very activc chemically at high the other blades in the same stage due to coupling
Since most blade failures are due to fatigue, ade- a heat tieatabic martensitic 12% C i steel alloyed with I~~liipcratures, surface contamination is another pro- through the disc and shrouds or lacing wires linking
quate fatigue strength is a crucial property. The blades molybdenum and vanadium. Both tltese alloys havc I,Iclii encountered when forging. adjacent blades. These interactions lcad to the predic-
are under steady centrifugal stress while operating, good long term creep strength at temperatrives up hlnchining is possible, if slow speeds are used, tion of a muitiplicity of modes in the working fre-
and this must be incorporated into the fatigue strength t o 650°C. 1 ~ 1 1 1 :I propensity for cmbrittlement by contamination quency range, where for a single blade there are only
considerations. Since L P turbines can see wet 'aggres- The intermediate blades, wlticll are neither highly clld lack of heat penetration make welding difficult. two or three. Thc vibration of a fully-bladcd disc is
si\,e environments', the fatigue strengths upon which stressed nor very hot, can be made from 12% C r steels I I I L , ~gasI welding is the normal solutio!~ but this is therefore much Inlore complicated than is suggested
- are based must account for environmental
designs with leaner alloying content and lieat-tl-eatcd to the lltiie consuming and costly. by the characteristics of a single cantilever blade.
degradation. appropriate hardness. A typical steel is FV 448, an 'l'llc main problems of titanium are high cost and An individual blade, cantilevered at its root, has a
Material damping is also considered of high im- 11% Cr, 0.6% Mo, 0.25% V, 0 . 3 % Nb steel with good I!I,O~ vibration characteristics. The cost of titanium set of natural frequencies in the operating range which
portance. The vibratory stress devclopcd in a turbine creep resistance up to 550°C. ~ l l l l y is several times that of standard 12% C r blade arc classified in three groups: 'flap' modes, 'edgewise'
blade is inversely proportional to the damping. One The corrosion and scaling resistances of the latest I~li~lcl-ial and a row of titanium blades normally costs modes and torsion modes. The disc carrying a set of
of the reasons 12% Cr stalniess steels are so widely so-called 'Super 12% Cr' steeis are at least equal to l\so la three times that of a steel row. all factors such blades itself possesses several natural frequencies
used in blades is due t o their superior marcrial those of the simple 12% Cr steels and In many cases within the same range, each one of these being associated
damping. significantly better. General corrosion resistance In , material damping of titanium is very poor, with a mode mode shape having n nodal diameters
Notch sensitivity also affects fatigue response and, steam is better than the grades containing less than g from 10% t o 40% of that of 12% Cr blade (and possibly one or two nodal circles as well). The
since Stress concentrations are unavoidable, parti- 12% chromium: the ferritic grades are much lcss ' I. Thus there is a potential for higher vibratory complete bladed disc has a very large number of
culariy near the root, a low notch sensitivity is very prone to stress corrosion cracking than the austenitlc when opera tin^ the titanium blade a t o r near modes of vibration in the same frequency range, and
desirable for good blade life. Unfortunately, whereas steels. tarl~ilance.Also Young's Modulus of titanium is low each of thesc will constitute a unique mix of the
high tensile strength desirably Increases fatigue strength, Welding is considered the mast complicated fabri- brill, since the flexibility is relatively high, natural individual blade and disc modes. Some of thesc as-
it also increases notch sensitivity. cation process lor the Supcr 12% Cr steels because 111':iiirncies arc depressed and harmonics are more sembly modes will be identified as being 'prcdo-
The short blades in the H P turbine work at tem- of their high hardenability. The martensite formed t'ln\i'iIed in the running range. minantly disc' modes, while others will be Immediately
peratures near to the maximum steam temperature, in the weld metal and heat affected zone (HAZ) is 111 view o f the lower cost and imoroved ~ r o n e r t i e s associated with one of the biade cantilever modes,
so creep strcngth is vitally important in this region, hard and brittle and must be tempered. However, ril llir Super 12% Cr steels, it is'unlikel; that ti- in both cases by virtue of the iespectivc natural
with the amount of permissible creep usually restricted when temperature recommendations outlined by the iilli~ltiialloys will supersede tltese steels for L P mov- frequencies.
t o 0.2% deformation in 100 000 h. various producers of Super 12% C r steels are fol- blading on UK steam turbines in the near future. Other modes exist which are associated with tlrc
The conventional 12% C r steels have an ideal set lowed, welding does not present any unusuai problems. waver, because of its hlgh strength/weight ratio, fully-bladed wheel assembly and arc quite distinct from
of properties for turbine blading as long as the Information concerning production, constituents, ' Irn is used extensively for lacing wire and for disc or blade modes. When there is additional inter-
temperature does not exceed about 480°C. Austenitic properties and application of the Super 12% C r steels landing and shrouding. blade coupling provided by some form of shrouding
steels have been tried but, in general, have not been is given In [81. either at the tip or part-span, then most of the modcs
satisfactory, except for the short blades in the HP of the complete structure will tend t o be wheel modcs,
turbine where damping capacity is not as crucial as and small modifications to the shrouding or lacing
it is for the longer blades in the later stages of the 5.6.2 Titanium can result In significant changes in the pattern of
L P turbine. Austenitic steels, however, have relatively Because of its hlgh strength/weight ratio and excellent Blade vibration control wheel natural freauencies.
high coefficients of expansion and tend t o be avoided corrosion resistance, titanium has been considered as
because of this. Ferritic steels of the FV 520 type a n alternative t o 12% Cr steel for low pressure lur-
have been used for last-stage LP blading but have bine blading. Since the density of titanium is aboul
Natural f r e q u e n c i e s a n d excitation 5.7.2 S o u r c e s of vibration excitation
now been generally superseded by steels such as FV 60% of that of steel, a titanium blade nearly 40%
566, which were designed for applications where good longer than a steel blade can be substituted, assuming Vibration excitation can arise from a variety of sources
impact properties are required at medium-to-high comparable stress levels in the blade root. of the large number of blades in any turbine but principally involves the following categories:
strength levels. Mechanical properties have been im- T h e corrosion resistance of titanium makes the nc, the existence of unavoidable sources of
proved by the addition of molybdenum and vana- material highly attractive for blading subject t o pit- ilion excitation and the serious consequences of (a) Non-uniform pressures, velocity or changes in the
dium, and suitable heat treatments t o give adequate ting, stress corrosion and corrosion fatigue. Laboratory l'itiiure of just one blade, an intimate knowledge angle of steam flow resulting in a periodic fluc-
creep resistance in the short hlgh temperature blades, tests have also shown that certain titanium alloys are Iri~dcrstandingof the vibration characteristics of tuating force on the rotating blades. This may be
and adequate proof strength in the long low tem- superior t o 12% chrome stainless steel in erosion Iblitdes in their operating environment is essential. caused by:
Tlie stearn Turbine Chapter 1 Turbi~icl~laiiiii(i
..

slcan1 soiati,,g ia,,s or.ci o,iiy 3 1 1 1 ~stationa~yS i o \ ~passages, tliese call incItIdC: 8 iiI:iil~,ii or inaliiial Srcqoencie can be clicckcd. IPio-
par~ioilof its circolal- path (liariial admissioll). viili'il ilia! cantileuci vihi-atioii tcsts confirm that tlic
cxis,;,, of some e Acoustic resonances in inlct \>assages, erlractio~l
lines or other cavilies, excited by the fio\l past
..lii,:lc-blade rrequincies are in accordance a,itl~ re-
~(ili!cinents,a complete bladed disc is manufactu~erl.
l i p turbines but not in LP stages.
thein. I l l i . bladed disc is thcn tested by fitting piezo- VI~HFIIIt i ~ ~ o <or
i r ~,,<!~C,,,OI$IC
t
c A change in the direction of' flo\v, partico- (.lcl.l~iccrystals at selected positions on the wheel and
larly from axial t o radial a1 exit from moving
r Voiler-shedding fr,om stay bars, etc. icruiding the modal shapes and natural frequencies.
blades. Good aerodynamic design shouid mini- e unsteady flaw separation from stationary bladcs, etc. Siilce the natural frequencies o f all blade rows,
mise the magnitude of this non-uniformity t~ircilt llie last few L P stages, arc generally above 9
m Unstcady shocks in choked stationary blade pass-
and ensure that multil,le I~armonics o f the e i ~ l l t h engine order (400 Hz for a 3000 i/min 2
. synchronous speed are not produced.
Flow
of extraction
by the prcse,lce
passages for feedheatel
ages.

e Surface p~.essurciluctuatioos, due to impingement


of turbulent flow out0 rotating blade shrouds, discs,
lrliine), static testing is usually sufficient to confirm
ssible resonances will bc well removed from
11s which the blades will experience in service.
3
8
tappings. etc.
onal frequency below the eighth order. Also,
(b) Periodic effects due to manufacturing colistrainfs 1, the blades then~selves, flow instability, flexibility of longer twisted blades changes
or structural feattires. These can include:

e Incxact matching of stationary blade geometry


at horizontal joints. Blade-pitching at diaphragm
ltorizontal joints be ,,,,iform and {],is
.
and hence excitation, can arise from:
Boundary layer pressure fluctuations.

e Vortex-shedding from blade trailing edges, causing


1)' with speed, the bladed discs must bc tested
running range to ensure that natural frc-

can to excitation at even multiples unsteady aerodynamic force. Also windage, particularly near the blade I'l~i. 1.90 1'1,~icnl'Carnpbcii Diaginsi' fo, a
of rotationai frequency. r Recil.culating fla%', particularly in last-stage LP xiid cause overheating and make tlic results loir' pressare blade

.
l i l l lo interpret. For thesc reasons, the complete
Leakage through gaps in stationary blade ti disc is run in a vacuum wheel chamber, whcrc
shrouds and diaphragm discs at llorizontal unsteady condensation shocks, caused by SUperSatUra- i~il;~)'of magnets is used to stimulate impulses
joints. The current arrangement o f diaphragm in diverging passages, I f a wheel mode and a harmonic of rotatiollal
1~ 011 each blade as it Passes. The disc is r u n U P
support precludes this effect. fl.equeitcy coincide below the engine order,
('yo synchronous speed and the blade vibration selected modes may be 'tuned out, by adjusting the
lcctcd by strain gauges or crystals. Signals are blade mass,
Eccentricity of diaphragms and other station- * necessary condition for high resonant "ibratory 11 o ~ either
t through slipi-ings on the shaft or,
near the tip. ~h~ geometry
of tip ties ol. coverbands can be altered, or material
ary elements with respect to the rotating blade is the coincidence between the frequency of a reccntl),, by telemetry and the frequency and added to/removed from material
assembly. Again, current design practice should harmonic component (of significantly high magnitude)
minimise this. and tile natural frequency o f a mode of vibration of o f these components may be changed. Altering the
i. rr'ilmining particular resonances, it is possibie position of shrouding change
a blade, or a blade group, or bladed disc assembly. modes over the speed range.

.
0 Ellipticity of stationary parts, such as end With a continuously-connected blade row, a resonance frequency of modes and it may eve,l be pas.
lilt drawl1 011 a 'Campbell Diagram' similar to ~ i b kin certain
walls, seals, etc. condition is associated with a multinodal standing to adjust the blade
''$1 in Fig 1.90. Radial order lines througi~ profile. Experience has shown that a continuous lacing
in the gauge tl,ickness of wave pattern around the circumference. This, how- 1 rellresent events that occur a fixed number
ever, is not always a sufficient condition. It is also or tip tie arrangement is less likely to form complex
stationary blades, Modern quality and inodes of vibration than blades connected in groups
this effect necessary that the distribution of vibratory deforma- or packets, and is more predictable. Complex modes
tions and the distribution o f exciting forces have a resonance occurring dur- are likely to be excited by high frequencies and are
Moisture removal slots. relationship that permits a net input of energy into the It is usual t o confine attention to within almost impossible to 'tune outx,
vibration. speed (i.e., 2820 t o 3180 r/min).
For example, consider a long blade vibrating in a The damping afforded by 'loose' pins, tip ties,
tllis speed range, the specified requirement is lacing wire, etc. and the choice of blade material,
All the above sources give rise to excitation fre- mode with one displacement node (point of zero dis-
n o resonances up t o the eighth engine order. minimises the effect o f random or broadband exci-
quencies a t the rotational frequency or low multi- placement). The upper portion of the blade deflects
tation which is difficult to quantify. Damping re-
ples (harmonics) of that frequency. in one direction when the lower portion deflects in
duces the response to resonances as erosion or impact
the opposite direction. If the distribution of exciting damage changes the natural frequencies of particular
(c) Nozzle wake excitation caused by the aerodynamic force along the height o f the blade is essentially
modes and bring these natural frequencies into closer
force.fluctuations seen by the rotating blade as uniform, then the upper portion of the blade wants
coincidence with harmonics o f rotational speed.
it passes each stationary blade or traverses each t o respond a t a phase angle 180' different from that
stationary blade pitch. hi^ is seen by the rotating of the lower portion. The net response of the blade M e t h o d s of vibration control
blades as excitation at the nozzle passing ire. to this exciting force would therefore be very low. 1111 lacti tical to 'tune' blades to avoid reso-
quency (rotational frequency x number of stationary ill~o\'cthe eighth engine order. The harmonics 5.8 ~~~~i~~
protection
blades) and its multiples. 'lorc together and natural frequencies cannot
5.7.3 Verification of estimated natural frequencies lli~lcd or controlled to sufficient accuracy.
a n d w h e e l c h a m b e r tests luly, excitation forces at these high frequen- 5.8.1 Erosion m e c h a n i s m
A number of sources can also give rise t o excitation After a prototype blade has been designed on paper, illill and are incapable o f exciting complex The last stages of large condensing turbines operate
having n o direct relationship t o rotational speed. In a single blade is made in mild steel so that the cal- in the wet steam region, where the steam contains

74 75
Tlie steam liitbine Turbine casiogs
--
5 iZO1O ioi\arel. 'l'iirbiiie biade eiosion is initiated by there foliows a tcstiary period during W I I I C ~ ) l i i i ., r ~ ~ ~ ~ ~ l > l ib!c! ; t111e
! c ~need
i f o r intcrna sliell at tlie capciise of the ouler sheli, it also perinits
a reiativcly stuaii proportion of the water dropiets lerial ion by erosion falis logaritillllicaliy nil\. iilp lhciiili splil along their liarizolll;iI siniplc blcd-stcaln tapping ;it !he iotcr-shell conditio~li
in tlic steain separating olit and coiiecting o n tlic arid after about a year iniay almost ceasc, 'it! i i t i j ~tlic lolor to he inserted as a colil- and reduces the net tliri~slon l11c 1-11' rotor.
concave prcssure facc of thc diaphragm biades, where babie explanation fur this is that thc poirr t $1-. Sul~sii~iitialfianges and bolting arc Tiipic casings have bcen used on some modern
a film is formed which is drawn towards the trailing surface ai' the blade where erosion has 2 wllliiti~~iti the ~liessuscforces at llie lioii- toshines to fuillicr reduce the stresses on the hot
edge by the drag of the steam. Here the filni grows are partly-filled with water. This cushions llic ii111 'I Ill. ~clalivelyniassive flanges respond inncr casing, and hence reduce therillai distortion.
and passes around the trailing cdgc an to the convex o f the drops sti.iking thc blade and the impacl 11s ielnl,urature cilangcs Illail thc rest The inner casing is enclosed in a ba~.rel-iike sleeve
facc wilere, usually in a region of strong secondary are only transfericd to the material in a t i l t , resulting in different rates o f expao- wiiicli has no lhoiizontal joint. The inner casing is only
flow, droplets move back and forth increasing in form. hcilinjpog of temperature stresses and lightly stressed and can be relatively thin with light
sire until they are torn away by the shearing action of Itl~oi~yh rliese are minimised by the ap- flanges, whilst the barrel casing which encloses it is
the main steam flow. Relatively iargc drops (50-200 litingr warming steam. Further stress more highly stressed. 'The barrel casing, however, having
pm in diameter) are produced and have t o be acce- 5.8.3 Protection a n d erosion shield materlo Ir sct up by the gland housing and steam no flanges and bcing of uniform thickness, can easily
lerated fro111 rest by tlie steam. These laigc drops be designed to accornmodatc the strcsses whilst also
Methods have been investigated for collecting
arrive at thc inlet plane of the moving blade row at c i ~ s i n gare of cast construction and are remaining iciativciy thin. The pressure between the
from thc stationary blade passage, including rein
only a fraction of the absolute velocity of the stcam i i,rirrs-section to minimise non-membrane inner casing and the bal-iei is controlled by small
and arc subsequently struck by the convex surfaces by suction through slots near the outer edge
inl,)rr!,, bolting, steam penetrations and other radial passages tlirough tlie inner cylinder wails and
of the moving blade r o u ~ ,This causes the abrasion low fixed blades or by bled-steam belts
8th l i ~ ras possible symmetrically arranged piston ring seals between the innei and barrel casings.
on the leading edge of the blade known as erosion before tlie last stages. These methods have 11,
ir11ni~1 asymmetry and hence distortion. One disadvantage o f this form of triple casing is
Fig 1.91. advantage that they autoinatically reduce perfoiln
ti~tly be fabricated or a combination of the dilficuity in assembling and dismantling tlle HP
The adoption of higher heat drops in the iasl
I,! li~brications. cyiieder. On assembiy, the rotor has t o be fitted into
together with higher mass flow loading and i
t i t it11 ipiessurc vessels, the integrity o f the tlie inner and outer lower half, the inner casing boited
pressure at inlet to the moving blades, can lea<
SIATIONRRY DIAPWRAOM cukeil after manufacture with a hydraulic up, and then the rotor and innei- casing lifted and
smaller droplets whose velocities more rapidly t
o 150% of the highest working pressure. mounted in a special jig to allow the barrel to bc
proach that of the entraining steam. This can icr~t
threaded over them. Thc assembly can then be lowered
in reduced imnact velocitv and erosion effect.
back into the bottom half of the outer casing, and the
It bas been the practice for inany years to pro1 Nigh pressure c a s i n g s top-half outer casing added.
tlle leading edge and part of the convex surfa
oilctti 1~1l-bines,with steam pressures over 100 The steam inlet pipes pass througli the outer casing
the last-stage moving blades by surface harde
i!~licigsgreater than 100 MW, have H P casings and deliver the steam into the inlet belt o f the inner

a
IMPACTVELOCITY or by the attacliment (by silver soldering, or $11
J i'.ahcll design (Figs 1.92 and 1.93). This has casing. The inlet belt is formed by a n extension to
-----(--===*----
-----------&--DROPLET VECTOR
recently by electron beam welding) of a shield m
plcrl because of the difficulty of designing a the main casing which ensures that the inlet steam
TRIANGLE from a hard material such as tungsten, chromium t
STEAM VECTOR !;it18 lo withstand the thermal and pressure cannot come directly into contact with the rotor but
TRIANGLE steel or Stellite 6 0 .
IKI yct be capable of flexible operation. With must first pass out through the nozzlcs and the first
Attachment is always followed by the most stringet ili,rliell casing, the space between the shells is raw of moving blades. T h e inlet belt is often blanked
non-destructive examination of the joints. Erosion v,illi sleani at exhaust conditions, allowing each at the casing joint t o reduce the pressure on the joint
thc original biade material around thc shield ci
to bc designed for smaller tcmperature and face, although care must be taken that the admission
lead to undercutting of the shield material and eventi1
1. ililfcrentials. A baffle is farmed between thc o f stcam to the first stage is not interrupted.
shield detachment. Coverbands, blade upstands $31
ii..in>:s near the exhaust end as part of the innei- With steam temperatures at inlet in excess of
tip ties can also suffer from droplet erosion. It
i.;isiii~g.The baffle extends almost to the outer 538"C, separate nozzle boxes of heat-resistant steel
therefore considered prudent to inspect the blad
docs not seal against it. The turbulent cr- are sometimes used t o protect the casing from the
I'lci. 1.91 Relative inipacf relociiy onto iari-stage during overhauls. Even if tlie erosion shield do
is directed by the baffle to the exhaust full temperature. These take the place of the inlet belt,
lnovilis blades not become detached, the shields wili erode in tin1 nd prevented from cooling the inner casing; delivering steam from the inlet penetrations t o the
and will probably need t o be replaced at least oil uces the tcmperature differentials and hence first stage nozzles.
during the life of the machine.
,!I the inlet end of the inner casing. Steam leaking Some overseas units have nozzle governing instead
tl?e gland between the inner casing and the rotor of the throttle governing employed on all large CEGB
5.8.2 Erosion progression
nlet end is piped away to the exhaust connec- machines. With nozzle governing, the inlet belt is
When a drop impinges on t o the blade surface, a the space between the casings contains divided into sections, each controlled by a separate
very high pressure shock is generated for a short xhaust conditions with a gentle flow being valve opening in sequence, resulting in a more com-
period. The pressure wave causes plastic deformation 6 Turbine casings ~ l i ~ i n eby d leakage through the outer casing giand. plicated casting and the need for stronger first-stage
of the material and repeated plastic deformation rriialier Dressure differential oermits a thinner moving blades.
leads t o an increase in the internal stress. After a ~\,liich,combined with the larger surface area of The stationary blading is carried in diaphragms
certain time, the stress concentrations in some areas \hiecasing, allows quicker warming of the turbine which are supported and guided in the inner cylinder
exceed the tensile strength of the material, a n d cracks 6.1 Forms of casing construction iirt-up. Thinner shelis are also easier t o cast and by keys near the horizontal joint and vertical centre-
form. During this incubation, o r primary period of A turbine cylinder is essentially a pressure vessel wit kcly to have fewer defects. line, permitting concentric expansion. O n modern
erosion, there is little or no weight loss. When the its weight sunnorted at each end on the llorizonta 11 sornc machines. reversed flow blading has been machines the tip seals and shrouding for the moving
cracks spread and join, however, the result is material centreline. l t i s designed to withstand hoop stresses , where the steam is diverted b a c i between blades are usually carried on an extension of the
breakdown. Tiny pieces of surface material are re- in the transverse plane, and t o be very stiff in the ngs part way through its expansion, continuing adjacent diaphragm. Earlier designs had separate
leased and, during this secondary period, erosion rate longitudinal direction in order t o maintain accurate the final stages in the opposite direction. sealing strips supported between the diaphragms.
increases t o a maximum. cieatances between t h e stationary and rotating parts rangement gives a higher inter-shell pressure H P cylinders o n wet steam machines, such as those
After the surface has become uniformly pitted, of the turbine. temperature, reducing the stress on the hot inner on PWR stations, are different in design, being more
76 77
constrilctioli wiili a n iniicl casing containing d i ; i ~
piiragrn siipporis, blcd-steam and water cntraclio~,
beits, and a n oilier casing directing the exhaust la
thc condensers and providing sui~ctuialsupport for
the inller casing (Fig 1.96). This is not always so,
Ihoweves, particularly with pannio condensers where
a single casing may bc employed. The large size of
LP outer casings combined with their low pressure
loading favours a fabricated rather than cast con-
struction, Inner casings which are more complex can
be fabricated or cast depending on economic consi-
derations. All casings have boited horirontai joints.
L P cylinders are virtually all of double-flow design
but vary greatly in layout due to the different can-
denser configurations. The latest practice for con-
densers is similar to early 'undcrslung' designs with
separate condensers underneath each cylinder, tubed
transversely, allowing easy access t o both condenser
and LP cylinder. Foundation columns, bearing and
cylinder supports are located between condensers.
However, during the development of 500 MW ma-
chines, variations of thc turbine and condenser ar-
rangement were tried, both to simplify the L P casing
support arrangcmenls, to increase the area and shorten
the exhaust connections. The four arrangements used

.
were:

The oxiol condenser, which permits the L P turbines


t o be supported o n two parallel walls. Space has
t o be allowed beneath the generator for tube
withdrawal.

The bridge condenser, which bridges the gap be-


tween the I P turbine block and the generator. It
is constructed in the form of two deep girders,
which carry two parallel rigid solepiates for the
LP turbille support. The condenser tubes are
mounted transversely. This construction uses a lot
of stccl.

The pannier condenser; here the tubes are mounted


axially with the condensers themselves mounted
on either side of the turbine, so that the steam
is exhausted horizontally into the condensers. The
advantage of this arrangement is that the exhaust
steam flow from the turbines is facilitated, which
cuts down the hood loss; in addition, construction
savings are made by having a reduced basement
depth.

8 The integral condenser, which is a development of


. the pannier type; the condensers and L P turbine
altllcr end; this keeps the outside of the casing and outer casings are combined in a single structure
like standard IP cylinders. Further details are given for IP cylinders are similar t o those for H P cylinders, !llC bolts cooler, allowing smaller diameter bolts to containing internal ribs t o give it adequate stiffness.
in Chapter 2. the steam being a t a similar temperature but lower Irr tlsed. Access t o the bearings is obtained via wells, and
pressure, which allows 1P casings t o be thinner. In access t o the turbine inner shells is obtained by
general, machines over 300 MW rating have at least removing the top cover plates. Here again, the
6.1.2 I n t e r m e d i a t e p r e s s u r e c a s i n g s a partial double-casing covering the first few stages, 8.1.3 Low p r e s s u r e c a s i n g s basement depth is small and there is direct support
In modern reheat machines, the design considerations subsequent stages being supported by carrier rings 1'1' cylinders (Fig 1.96) are often of double-casing beneath the bearings.
18
puelsql!m 01 pue Su!ses a q ~ JO slauloa l o 'sap!s 'SpUa Lew Zu!sea ialno aq) jo amnlon a q u a a111 'lasuap
.ruaqt uaamlaq Ll[euoZe!p pa[l!~p saaessed Su!laauuos roj [e!luassa ale sSu!sea au!qlm u! slu!ol leluo
aql l e slu!od iloddns aql 01 iqZ!a~ aql lajsuall 01 -uoa aql 01 molj aql u! sass01 aql as!w!u!m OJ.
-.ialu! [leuis ~ I ! M 's!ql i o j pasn aq Leu sahlaswaql siu!o! le$uoz!loH siaomam !e~msnils su!eluoa au!sea ralno a q 'alq!s ~ 'lasuapuoa aql u! leql ueql IaMol
saloq lloq aqJ, 'au!sea aql JO lsal aql 01 lel!m!s LllqZ!ls s! snlnuue isneqxa Zu!pelq aql IE alnssa~d
-sod se l ~ o q sse sSu!~eaq uaamlaq q18ual lo101 aql
ale1 s le dn may] 2u!rulem 'saSue1j aql u! pall!lp aql i e q ~os (asualajj!p alnssald e aanpoid 01 meals
daay 01 raplo u! '8u!sea ~ a l n oaql j o pua aql le ssaaal
saloq l o sLem aSessed qSnolql meals sassed qa!qh\ e u! palesol lelsapad e 110 palloddns aq Lem Zu!leaq aql j o L81aua a!lsu!y aql jo asn ayem uea Laql "a'!)
malsLs Bu!mlem aauelj e Lq pas!ru!u!m aq uea asaqL ,~u!sesaql jo do! .1
aql uaql 'IOU j! :sBu!~eaqd l aql IOJ lloddns sap!hold U O ! I ~ ~U!SOJJ!P e aneq 01 apem aq uea asaql 'ilqsap
.uo!l~ols!p pue sassans ~ e m l a q ldn %u!ilas 'Su!ssa aql jnjaiea Lq 'pue padoldma aie saueh panlna ',Su!qaunq,
ralno d l aqt jo uo!les!lnssardlano tuanard o s p Zu!sea ialno aql iapu!lSa d l jo su8!sap Luem ul
30 isai aql ueqi Llys!nb ssal dn UleM saBuel3 aql Inoql!m .orj qanolql meals jo amnloh a%nq aql ulm
.Zu!uunl mnnaen rood l o peal lq%!l 30 s .u%!sap lasuapuoa Bunlslapun
'ssauqa!qI enxa aq? j o asnesaa '(16'1 Z!d) slnu aql o~ .mnm!u!m e 01 ]day s! dorp a~nssaldaqi ieql 0s
paZuo[o~d Zu!~np slsneqxa aql 100s 01 s9u!sl!. ue u! %u!sea raMo[ aq] j o alluaa aql u! lasuapuoa aql
~ o saaejms
j 8u!leaq pue slloq aqi JOJ iuool moll8 'meae lsneqxa aqi i o j MOD jo eaie alq!ssod mnm!xeru
J O vale isneqxa sql u! pap!no~d ale sLeidslaie, 01 Zu!l!xa pue au!sea aql 30 ap!s aql llmop %u!ssed
01 Su!sea aql jo lsal aql ueql iay3!ql AllE!luUlS9nS
.suolllpuoa mnnaeh lasuapuos l e S[a~!iuas! nl! slsneqxa aql j o suo!lsas do1 aqi morj meals 'pasn aq sqi an!% 01 pauZ!sap ale sSu!saa isneqxa d l aqL
aq 01 aheq sasuelj aqL 'smalqold [elanas asnea inq
'sau!qinl aql jo aaueualu!eru pue uo!l~n1lsuoa aql

-sjamop uo!ie~olijpii!lh ~ a s u !aql j o a i l u ~aqi~ qanoiq, parsed uaJq .IOIOWpue y u ! s e ~i a n o u a a , ~ ~rpusla


q ' Y U ! E ~lalno
J j o ipua illoq ia r L a ~ap!nY !e~!llan 'ra!zzou ~Yeir-isi!~ .(9
JhBii q5!ilh, E~~~~~ WBJIE YU!!OO> IJEI!Ea,!, pue '4u!se3 iauu! JIO wou .(!l'a!p pal'oddnn a e ! ~r o l 3 a ~ vaql :apn!~u!rail,l!li.l paiioddi~sJOIOI j o ailus3 u ~ i o i d01 a"!, io~m!jap's,d!d ialu! tueals aql uo EII!YE ! B W J J 'ulolloq
~I 5q1 uo ~ a ~ ! d d eurealr-palq
l
13d!d lalu! WeaiE 1!Ynoii(l 1JpU!!63 )U!qlnl dl ili! J O U0!1331-isOJ3 $6'1 'OI:! On,l pun au!sas iaino ail, )o do, aqi so rlmsqxa inoj 'ap!r iaq~!adu!r >a!i>e, ql!m Yu!sna iauu! lellua3 3l!l :apn!>u! ralniead
>,,!q>",<,I ,,8 S" ,,"#,>as ID!Y" V 6 , ',,,:I
,apt#!\,(>
The steam turbine Chaplet 1 Turbine
-.

l.'lci. 1.96 Axial sectioo 01 an Ll' iurbiiie cyli8lder


Fealuies include: fabricated inner and outel cylinders. bled.sleam bclis i n ille intier cylinder, turning vanes ar iilc exllaust.
and glands rupporied by bearings wit11 a bellows connection lo the olrfei casing.

6.2.1 Flange design after a period in service, they are often found to
The forces taken into account in flange design are have distorted so that they no longer fit, typically
illustrated in Fig 1.98. The flange is assumed to seal leaving a gap between the fianges on the inside face.
at the inside edge, with the faces subject to a contact Thls is due to temperature differences through the
pressure greater than the internal cylinder pressure. casing on-load causing thermal stresses which relax
T o minimise bending stress on the flanges, the bolt by creep. When off-load, opposite stresses are then
centreline is arranged tangential to the siieli as can induced which distort the casing. This is generally
be seen in Figs 1.93 and 1195; this produces the typi- confined to inner casings as there is very little tem-
cal thick narrow flange seen on H P and 1P cyiinders, perature differential through a n outer casing on-load
! I .7 \\ rb < . . < , . o l ! . I I I I ~ : . : , l P . : . ~ : . . ~ : r ~f.a~.. \l\<'~.rt,#fu: 1 . h ~ I > h ~ r ? t l.IN>.
! :<>J: L . : ~
The seal is obtained by simple metal-lo-metal contact due to the external lagging. i n addition, distortion . > : r... 1 I . . I .:I! ,1>...1,::., < "<.J. ! : , c ] 1,: ,,.:L">b~.ol<~8r
of the flange faces, after careful bedding on initial
assembly.
can occur due to relaxation of residual casting stresses.
If distortion causes a small flange leak on an inner
A .

L,,. ,,..;,.>..,1;r,.,\.,,: .,.; rc , : . , , , , 3 ' , .,."C, . Il:,, V ! . "j.,. <,E<'I.,,>.#,<be,.:,*!,,. 1c:

When flanges on H P and IP cylinders are unbolted casing, it may not be noticed unless large enough to
The steam) turbine Turbine casin(j!:

lhead of the inill or enlircly ciicolai nuti a,itii siii;iIi riaiiii I>ul ihas uic ;adi,antagc of alloa~ingimmediate by lhc barrel casing, i t is lpossiblc lo lhavc exiiaiistr
holes diilicd in tllerii, aliowing then, lo be lurned by r l ~ i - c l . i of
~ , ~the bolt lellsioil ~ ~ ~ i l h owaiting
ot for ten^ ;it ail four bolla,n corners of liic lawel- casing.
tommy bars. Bccarlsc of f~.iction,ihc iiecessal.y bnlt ~ w ~ ~ : ~ l ~stabilise,
t w s t o agaili by measuring the cxteosion
tension could not be achieved in the large diaincic~ iiiici cylinders are assembled with the lower i~alf
casing baits simply by turning the nuts, even if lolgc 11,c casing rcsting in its final position insidc tile 6.3.3 IP e x h a u s t s
flogging spanners could be used. Instead, the i i l t l s ili:i czising. It is thtis awkward lo usc norniai bolls
11' cylinders gcnel-ally have two or four inlets ar-
are first tightei~cdby hand; the bolts are then heaicil llii! inner casing and studs are often used instead,
ranged in a similar manner to the H P . The IP exhaust
t o expand them, and the nuts again tighteocd thy : screwed into the lower casiing and then tight-
positions are detcrmilied by the positions of the
hand tilrough an angle calcuiated t o give the correcl in the normal manner. Alternatively, a square
crossover pipes to the LI' inlets. With underslung
bolt-tension after the bolt coois down. By measurin on the bolt a t the horizontal joint a l l o ~ , sthe
condensers, the LP itlieis and crossovers are usually
nut t o be assembled and tigittened before the
o n the top half, hence I P exhausts are also at the
top. However, arranging IP exhaust and LP inlet
pipes in the lowcr half casing reduces the amount
rod into a thin hale drilled down the centre of ea lernal flange, but L P casings may also be bolted
af pipework to be disconnected when cylinders arc
bolt, thus heating the bolt without sig~tificantlywar8 IIP some of the internal webs if access through
opened, and is thus easier if thc condenser arrange-
ing the flanges (Fig 1.99). Tlic same method can i ~ilioiesis possible. Thc bolts used on L P casings,
ment allows it.
used for undoing or retightening the bolts. ~ l iof smail diameter, are tightened by spanner
An alternative method of tightening the bolts ilic conventional manner to a controlled torque.

6.3.4 Use of thermal s k i r t s and piston rings


To allow for differences in temperature where the
the fiange or adjacent bolts, instead of by therm steam at the joint, typically after 30 000 11 inlet lpipes enter the cylinder, the H P and 11' pipes arc
expansion. Thc hydraulic equipment is more cumbe attached to the outer casing through flanged thermal
skirts (Figs 1.92 and 1.94). Thc skirt, which is bolted
lo the outer casing, reduces the conduction o f heat
bolt iailurc. A record of the history of all high from the inlct .~ i. o cto the casinc.and accommodates
the differential expansion between the hot pipe and
the cooler casing by elastic deformation. It also carries
the pipe forces into the outer casing: minimising the
the creep ductility of the material; this often load on the inner. The outer casing is reinforced t o
is changing steam chest cover bolts, hut this is minimise stresses and thermal discontinuities at the
,I!, necessary for turbine casing bolts. joint. Piston rings are used t o seal the joint between
the pipe and the inner casing; these allow for differ-
FIG. 1.98 Diagra811 oi forces 0s casing flallgei
The reaction at Ole nangei is lligher at ihe oulside oi tile ential expansion in the radial direction between the
caiins ilian the insidc. The pressure betweexi the naiiges a1 casings and a srnall degree of transverse movement.
~ i l eiliride jniurt exceed llic inleriial cyiindel piersure lo The piston rings may be of tiic conventional split
prcvcnt steam leaking between the joint racer.
0.3 External connections type, housed in a groove, or unsplit rings in the
'stacked' ring design. The split type may be 'outspring-
ing', housed in grooves in the pipe and springing out
against the casijlg; or 'inspringing', which are housed
have a n effect on the measured efficiency of thc between spacers in the casing and spring in to seal
turbine, unless it is a wet steam turbine, when rapid against the pipe. The 'stacked' design uses unsplit
erosion of the joint face at the leak may occur. rings stacked in the gap between the pipe and the
L P inner casings may also distort substantially due casing. They are not sprung against either surface
1 in order to minimise inlet losses. Usually either
t o their complicated design of webs, bled-steam belts, but are a close tolerance against the pipe and the
or four inlets are used; with two, the pipes are
etc., and to the substantial temperature differences casing alternately (Fig 1.100). Several rings are used
icai, making it easy t o wilhdiaw the inlet pipe
between different parts of the casing. This can lead in series to reduce the pressure drop across each,
11 the casing; with four, all the pipes enter a t an
t o crushing of the webs and distortion of horizontal and hence reduce steam leakage; however, there should
joints, though leakage can be minimised by incor- no1 be too many rings, as a lightly loaded ring can
porating spring sealing-strips in the half-joint faces. vibrate and wear excessively. The split rings are made
of a high temperature creep-resistant material, such
8,3.2 HP e x h a u s t s as Stellite or a Nimonic alloy, in order t o retain their
141' exhausts are arranged in such a way as t o keep springiness; the unsplit rings are made from a low
6.2.2 Bolting Il~ccold exhaust steam away from the hot inner cas- alloy steel. Stellite-coated bearing surfaces or Stellite
The design of bolting on HP and 1P cylinders is Ill0 lo reduce temperature differentials and stresses. inserts in the casings reduce wear.
complicated by the need to place the bolts close to- Fo.1 9 g Thermal-lightening of nange baits Hcnce, o n double-casing machines, a baffle is used The exhaust steam connections are attached directly
gether to get the necessary distribution of stress in The heating element is inserted into the lhollow boil and all the exhausts are a t one end. They are usually
to oxpand il. The nut is then hand-tightened by a prc-
t o the outer casing. When attached to the lower cas-
the flange. Special nuts are used to allow close spac- determined amount and the bolt is allowed to cool, taking In the bottom half t o facilitate dismantling. On triple- ing, where they are unlikely t o need disconnecting,
ing, either cap nuts with faces cut o n the reduced up its full lension as it contracts. raring machines, where the inner casing is protected they are simply welded t o stubs o n the casing.
85
systems

Viscorily, hiacala~ica< 4n°C, eill?/r ("$1) rili8, 28.R 41.4


~rax 35.2 50.6
Viscoilii i~,dex lllili 70 70
1:lasll~oiei. closed. 'C. I'cnskv-Maricnr ox,,3 16s VAR

Pour point, 'C


Total acidify, nig KOH/g ~ ~

Coppui corrorios, classiricaiio~~ (3 houvs at 1 0 0 ~ ~ ) mah 2 2 2 2 ,$


:$,a
llull-preventing ~llaiacieri$~icr rusliilg vusting rusting ttwi810 4

Foain, mi, a 24'C >mar 450 450 600


at 93.S°C
211 24'C ariei icst rl 9 3 . 5 ' ~ ma* 450 450 600 6011
Foam rlabilif), after 303 s
Toan,. ini. ai 24OC mar Nil Nil 100 ill0
ai 935°C nlax Nil Nil 25 25
at 24'C after terl a, 93.S°C rnax Nil Nil 100 I011
A i l ieleasc propercier, imitiutei to 0.2% air content a, 5nDc 6 7 I0
Oxidation ciinracterisiicr:
Total oxidation products (TOP) will? sludge lirnited ,a
40% of the derer8niiied TOP
N o catalyst. % max 0.1 0. I 0. I 0.1
Solid copper catalyst. % duration or tests 164 iiours niax 1.0 1.0 1.0 1.0
Solubie metal catalysts, oh max 1.0 1.0 1.0 1.0

The oil pressure used to lift the rotors is around


300 bar and with the use of mineral oil in close pion-
imity to high temgerature comoonents. this reoreseots
a fire hazard unless special precautions are taken.
Older units used a single pump with long pipelines
..
components include:

pedestals'baseplatea.
Steam valve gear pivots.
to feed each bearing and with this arrangement oil
leakage does occur. On modern units, the high pres- Previously, attempts were made to provide autom;,.
sure pumps are mounted in or on the bearing pedestals tic greasing systems, using a motor-driven multi-
(see Fig 2.66). Details of the pumps used are given piston pump with long pipelines conveying the grease
in Section 6.2 of this chapter. A pressure relief valve to the various components. Unfortunately, separation
is fitted in the discharge line from each pump in order and hardening of the grease constituents in the pipe-
to prevent over pressurisation and overload damage. lines resulted in frequent blockages and inadequate
lacking oil is also provided to the turning gear journal lubrication.
bearings during start-up and shutdown. Modern plant uses bearings consisting of a sintered-
The pipework systems use Class 1 welded pipe joints bronze matrix, impregnated with PTFE, on a steel
and all the high pressure pipework is contained within backing strip. These bearings are now used under the
the pedestal. Figure 2.67 shows the arrangement used main pedestals and are provided with manual greasing
for the turning-gear jacking oil pump, but is typical of points. The greasing channels are provided with suffi-
these installations. cient area so that the total grease pressure can over-
come the deadweight and allow the grease to spread
over the bearing surfaces. Grease leakage 'tell tales'
are provided so that the effectiveness o f the greasing
operation can be checked. In order to prevent the ingress
6.10 Greasing systems of grit and foreign matter, the pedestals are provided
Various components require greasing in operation to with dust shields.
ensure smooth linear or rotational movement between Examples of the greasing points provided on the
components; oil lubrication is not appropriate. These main steam valve gear pivots are shown on Fig 2.68.
Turbine plant svsteins Gland sealing system
-
7iiis priocipie can bc extended to a greater iiumbcr
oC iaise diameter fins, bu! !he iiombev of effeciivc
restrictions pel. i i r r l t o f axial Ieiigth becomes progres-
sively less and it beconies preferable to adopt a simpler
form of seal, such as those shown in Fig 2.69 (a), where
the larger number of restrictions compensate for the
decreased efficiency compared with the stepped gland.
Another design of giand that is independent o f
differential expansion is the vernier gland shown in
Fig 2.69 (d). Both the shaft and seal ring are finned,
the pitch of the fins being slightly different on the
two seal components. This has the advantage that some
of the fins will always be directly opposite, providing
a -areater restriction.
Figure 2.70 (a) shows a form of labyrinth gland with
axial as well as radial fins which increases the number
o f restrictions in a given length of gland.
The tip thickness of labyrinth glands is made as
i:l(i. 2.67 Sllatl luvriirig gear, jacking oii pump
thin as piacticabie so that if a n accidental rub occurs
between thc shaft and the gland, the fins will rub away
with little heating of the shaft. A heavy rub would
quickly generate so much heat that the shaft would
7 Gland sealing system
bend and become unbalanced.

7.1 Function and system layout


Giands and seals are used o n turbines t o prevent or
reduce the leakage of steam or air between rotating
and stationary components that have a pressure
difference across them, for example, where the turbine
shaft is extended through the cylinder endwalls t o
the atmosphere. When the cylinder pressure is higher
than atmospheric, there will be a general steam leakage
outwards: if the cylinder contains steam below atmos-
pheric pressure, the tendency is for air to leak inwards
and the sealing system is designed t o prevent the air
from entering the cylinder and the condenser.
As most of the steam leakage from glands does not
pass through the turbine stages, a loss of power output of grease poilils
is invoived and every effort is made to reduce this ICl Double stepped Iabyi8nlh
power loss by an efficient arrangement of seais and
glands.
In the more recent larger steam-turbines, the labyrinth of pressure energy; ideally, when the steam enters the
gland is in general use, although the carbon ring gland expansion chamber, the kinetic energy is converted
and the water seal gland may be found in old& tur- by turbulence into heat with n o recovery of pressure
bines. The labyrinth gland acts as a restrictor to both energy. In practice, as the steam is throttled a t suc-
steam and air leakage. cessive restrictions a t approximately constant enthalpy
the pressure is progressively reduced.
T o ensure that the maximum kinetic energy is con-
7.1.1 Labyrinth glands verted in the expansion chambers, the finned ring and
The labyrintli gland has superseded the carbon ring the shaft are usually stepped as shown in Fig 2.69 (b).
gland o n large steam turbines because it can withstand This type of gland can only be used where the axiai
higher steam conditions. The labyrinth gland consists differential expansions between the rotor and casing
of a ring with a series o f machined fins that form a are small. Stepped labyrinth glands may have an alter-
number of fine annular restrictions, every restriction native arrangement with two o r more large diameter
being followed by an expansion chamber. A simple form id) Vernier labyrinth {b) Spr~ng-backabyrinlh
fins as shown in Fig 2.69 (c). This arrangement is able
of labyrinth seal is shown in Fig 2.69 (a). to accept a larger change in relative axial dimensions
As steam enters the restriction, the velocity in- since, under all conditions, a t least two of the three
creases and kinetic energy is developed at the expense fins per pitch form effective restrictions. Fic. 2.69 Plain, stepped and vernier labyrinth glands nc. 2.70 Axial radial and labyiililh glands

198
Gland sealing system
Turbine plant systems

The radial clearance and diameter 01' thc labyrinth leading slcain back lo iu, appropriate stage iii
gland is made as slnall as possible, since the leakage turbinc or to a feedheater after each sectio~,.
f l o , ~tiirough the gland is directiy proportional to the result, heat is returned lo the cycle.
leakage area. In praclice, the niinimuni radial clear- The arrangement of the final glands section l t i i

four or nlore segments.

velocity through the final restriction cannot exceed glands is connected to the gland steam cond

mass flow will occur. Thus for a gland with a given through the outboard gland section.
number of restrictions, there is an associated pressure At low loads, live steam enters the system thic
ratio that produces the maximum leakage through a motorised isolating valve and a pressure redu
valve to the U P dcsupc~hcater.Here the steam is m i
Tlie gland sealing system is designed to supply to a temperature suitable for the H P / l P glands. I
steam to seal the turbine shaft glands at all operating then passes through a inotorised isolating valve to 111
conditions and to extract leak-off steam from thc HP/IP glands or, via a separate ~notorisedvalve, lo $11
LP desuperheater which further cools the stcam to

7.1.2 S y s t e m layout
A typical gland sealing system is shown in Fig. 2.71. LP desuperheater and is used to seal the LP glan

ATMOSPHERE

leak-off steam produces a useful thermal gain over desuperheater,


the permanent use of live steam. The changeover from CLEAN
one source of sealing steam to the other is entirely DRAIN

T o ensure that the steam is supplied to the glands F,G. 2.71 ~ ~ ~ igland
c a tsealing rsrtem
at a suitable temperature, it is cooled by desuper- 7.2 Temperature and pressure control
heaters. An H P desuperheater regulates the tempera-
ture of the steam of the HP/IP glands and an LP
desuperheater regulates the temperature of the steam 7.2.1 Temperature control
to the LP glands. Some systems also employ a third The temperature of the steam supplied to the glands
desuperheater to cool the steam which is bled to an is controlled by two desuperheaters; one for the HP/II'
LP heater during on-load operation. system and the other for the LP system. The waterspray
In order to reduce the loss of energy in external type of desuperheater is generally used although thr
glands at the ends of the H P and I P cylinders, and tube and shell type of heat exchanger may be in usc
to promote a gradual temperature gradient along a on some smaller units. A typical desuperheater is shown
shaft, it is usual to divide such glands into sections, in Fig 2.73.
201
Gland sealing system

WATER

COYER PLATE
PACKINGILEAK-OFF
STMM
NOZZLE

BAFFLE TUBE--

BOTTOM DOOR

(bl LPgiandi
FIG. 2.73 Gland steam desupeihcatei
FIG. 2.72 Final gland arrangementr

drain connections on the desuperheaters glands progressively reduces and eventually reverses,
allow ,drainage to pass to the clean drains tank as leak-off steam becomes available. Consequently,
The dnuperhieaters cooling water which
is the reserve feedwater tank through heater is cornpenate. by tb automatic or ing valve, a strainer and a drain trap, the rise in pressure at the glands causes the live steam
a motOrised closing of the valve to admit the amount of wale,, pressure regulating valve to close progressively, thus
valve. The water supply is then necessary to maintain the maintaining a constant supply pressure at the glands
controlled by regulating valves. Each valve is ad. outlet
perature, -up and shutdown, when live steam is and eventually closing completely. The L P glands are
justea by a on receipt of a signal from a
The steam temperatures are in the con, the pressure at the glands is controlled by the now sealed by steam leaking from the H P and I P
?"'Or in the desuperheater outlei. ~ n y t r o ~
Increase Or and locally; high and low temperature re reducing valve in the live steam supply line. glands, and the pressure at the glands is controlled by
in temperature at the desuper- alarms are included to indicate a fault condition, creases, the steam flow to the H P / I P a leak-off valve which dumps steam to a n L P heater.
203
Turbine ~ l a n svstems
t Flange heating system

l'ilis arsaligelnenl cllsuies ilia1 oiily able icgulat-


iog valve is in control a1 any one tiine and tlrat the
clraiigeover from livc steam lo leak-olf steuni is fully slcaili is i)rwenlcd from cscaping inla tile (1
automatic. by o1)erating the vent rails.
The steam lplessure i11 tile sealing line is indicated
in the control room and locally; a f ~ u l tcondition is
indicated by low pi-essu1.e alarms
8 Flange heating system

7.3 Gland steam c o n d e n s e r


The function of the gland steam condenser is t o main- 8.1 F u n c t i o n and system l a y o u t
tain a sub-atmospheric pressure at the outermost leak-
off belt of the glands and thereby prevent the leakage Xr 6 1 1 A N OISCHlRCIL
I ,,OM FLANGES
o f steam from the glands into the turbine hall, where
it would condense on the walls and plant. of each casing arc bolted loge the^. at the hoii?o
The condenser is vented to the atmosphere via a flange (see Fig 2.75).
blowc~.. The small vacuum cl.eated by the blower is During turbine starting, the relatively thin , cl,Niiiol SIONAL

sufficient to draw air into the glands where it mixes the H P and IP casings tend to heat up more
with steam leaking from the cylinder; the air is se- thali the large masses of metal in the horizonta
parated in the gland condenser and passed back to the flanges. The function of the flange heating systci~j
atmosphere via the vent fans. The steam is condeiised t o pvovide steam heating (at app~.opl.iatecondilit~j
and the condensate passes to the main condenser. A 10 the HP and IP outer cylinder flanges, theichy I
IPRSSSUREIRhNSM171IR
typical gland steam condenser is shown in Fig 2.74. ducing the difference in 1emperatul.e between eacii
Thc condenser typicaily consists o f a steel shell the cylinder casings and their associated flange
closed by a dished-end warerbon cover incorporating a boits. This prevents excessive thermal stressin
tubeplate into which are expanded U-tubes. Cooling cylinder distortions.
water, provided by local river water or seawater, is
F ~ C .2.76 T ~ HP alld
~ I P ~tulbiile~ nangc
~ ileatins
I system

function and layout and a typical flange heating syslcl~


is shown in Fig 2.76.
WATER WATER
OUT IN The flanges on the HP cylinder arc supplied ,,.ill
Steam from after the H P governing valves and I
IP flanges are supplied with steam from after the
1i;lii;ite top and bottom cross-drillings which provide or, alternatively, when the cylinder barrel and flanges
imsages enabling the hot steam t o flow freely tlirough are heated to about 250°C.
1111. flange. This is shown diagrammatically in Fig 2.77. The flow of steam is controlled by preset regulat-
'l'he heating steam enters and leaves the flanges a t ing valves and orifices. These valves, in each cylinder
irveial points by way of drillings from the flange outer supply line, are sized in conjunction with their corre-
STEAM D I I I ~ R Cinto
~ the bolt holes, the inlets and exits being sponding flange outlet orifice plates to give maximum
nlilably spaced t o give even heating throughout the pressure in the flanges. This pressure is approximately
Nzingcs. The annular spaces between the bolts and equal t o the pressures o n the inner surface of the re-
s are swept throughout their length by the hot spective outer cylinder under full-load conditions. As

Steam leaves each flange from outlet pipes which steam pressure has a corresponding effect on both
converge into one pipe, fitted with a flow regulating flange and cylinder steam pressures. As a result, rapid
heating due t o condensation heating is maintained at
Subsequently, the combined flows from each side the same relative levels, thus enabling the difference
of Ole turbine are joined and led either to a suitable in temperature between the casing and the flange to
reedwater keater or t o a drains receiver. be maintained within acceptable limits.
Suitable steam distribution is achieved using bal-
ancing orifices installed and set during commissioning.
Once the correct orifice size has been determined, it
CASING remains unaltered.
'The HP and IP flange heating systems are brought With the system as described above, the flange
into operation by the remote manual opening, from heating steam temperature is always higher than that
PIC. 2.74 Gland Elearn condcnser Fie. 2.75 Turbine half-carings joined at horizontal flanges the central control room, of the motorised isolating o f the steam within the cylinder casing. In some de-
204
EMEROENCYSPRAY
WATER PUMP

signs, however, the steam supply is taken from inside the possibility of excessive casing distortion. T F ~ G .2.78 LP eriiausi pray cooling syiteii,
tile rekvant casing and hence its temperature is always done by spraying cooling water into the exhaust space,
equal to that of the steam within the casing. whenever necessary, downstream of the exhaust giii
vanes. The exhaust steam is cooled and then re xhaust guide vanes. Initially, a number Of these keep the L P exhaust steam temperature within accep-
cuiated to cool the casing. A typicai L P exhaust coolinl, may be blanked off, to be used as additional table operational limits during no-load or light load
system is shown in Fig 2.78. iozzles if extra spraywater is found to be ne- operation. A temperature detector, incorporating
9 LP exhaust spray cooling system During normai running o f the turbine, the coildcii. during the subsequent running of the turbine. theimocoupies, is situated in one exhaust flow of each
sate extraction pump supplies the spraywater to lllc ,r liangement of the spraywater nozzles is shown LP cylinder and this measures the exhaust temperature.
system. The condensate supply, before reaching tilr In operation, a signal is passed to thc temperature
spray nozzles in each end o f the L P turbine cyinder 11 nozzle is designed t o provide a spray of atomis- controller, via a n amplitude selector (this ensures that
9.1 Function and system layout
exhaust, normally passes through a manuai isoiatit~g les which will evaporate quickly, thus promoting the LP exhaust with the highest temperature is selected),
During the low-load running o f a turbine-generator valve, a pressure reducing valve, a strainer to remoup ]>id cooling of the exhaust steam. which operates the spraywater control valve.
unit, tlle volume of steam flowing through the last row dirt particles, a flow indicating switch (~neasurin~watcr Suitable safety measures are built into the system to When any individual sensing element detects a pre-
o f the L P turbine blades is reduced considerably and flow to sprays) and a pneumatic flow control valve, ctly maintain spraywater supplies so that a n effec- set low exhaust steam temperature, the controller will
the smooth aerodynamic flow of steam through these with manual inlet and outlet isolating valves. A pres. 1 , atomised
~ ~ spray is available when required. This is open the spray control valve to pass a minimum quan-
blades is lost. The L P exhaust steam is recirculated sure switch is usuaiiy fitted across the strainer to mea. ,orlnally achieved by installing an automatic valve in tity of water. Further increases in temperature will
and, as a result, ellergy is transferred from the blades sure any difference in pressure, thus indicating whethe lit supply system to ensure that the spraywater flow is allow proportionally-greater quantities of water, rising
to the steam, resulting in a significant temperature rise blocking has occurred. A by-pass, with a manual iso ove a ~ e minimum
t level. This valve is arranged t o t o a maximum water flow at a preset high exhaust
o f the circulating steam. In addition, if the condenser lating valve, is usually provided round the spray contro ,en or close rapidly near this minimum set point. The steam temperature.
back pressure is high, a smaller volume of steam will valve and its associated isolating valves. ninimum flow requirement may result in a slow cycle The temperature detectors can have an inherent
flow through the system, causing a significant worsen- An emergency spraywater pump driven from a DC
ing of the situation, of valve opening and closing during low load, but this time lag and, under certain circumstances, an overriding
Protected power supply will cut in automatically in control is necessary to produce a two-minute burst of
The excessive temperature rise caused by these ef- the event of a failure o f the normal spraywater sup- A temperature detector is located in the path Of the spraywater at maximum flow.
fects can result in an undesirable restriction on the ply. The emergency pump draws its water from an
length of time that the turbine can run with no load, exhaust steam downstream o f the spray nozzles to In the event of the condensate extraction pumps
auxiliary water tank and discharges into the spray- the signal for the automatic start and control failing, the emergency spraywater pump is brought
and possible uneven heating of the exhaust casings water line upstream of the strainer. The emergency of the spraywater quantity. into operation automatically, provided that the turbine
leading to serious distortion and adverse effects on supply line normally contains a manual isolating valve,
turbine alignment. gland steam isolating vaive is open. This condition is
a n emergency spraywater pump and a self-activated detected by a limit switch situated on the isolating
The L P spray cooling system is provided to ensure isoiatine valve.-
that exhaust temperatures under these conditions are
~~u
valve. Loss of supply from the extraction pumps is
maintained within defined limits, thereby minimising
Each L P turbine exhaust flow incorporates a split 9.2 Control indicated by a pressure switch located on the supply
ring of spray nozzles, the ring being located outboard A" automatic temverature control system is fitted to line from the pumps, which is able to detect low water
802
.oh01 Les j o anlen e molaq s l p j peol aql alesuapuoa aqi jo asodsip 01 pap!hoid ale s a y II
uaqm Zu!uado a!lewolne l o j uo!s!noid aq Lew alaql 10
uMoplnqs ialje pauado Lllensn ale sahlen iLliem pue
~ a l s e waqL '[eu8!s aimeladwal 10 peol e w o i j Llles!l SJiZZOU iaiemr(eJds j o lualuasuei~y ~ L . T.ora
-ewo$ne pasola aq uea aqeh a q ~'Lfah!)eurallv 'pasola
aq ues sahle.4 iLiiew pas!lolom aqz pue su!elp aql
q a n o ~ q l%u!ssed aq ~I!M weals Lip itluo ley1 awnsse
01 alqeuoseal s! i! 'alnssaid au![ aql 01 Su!puodsailoa 3011VH3SIO dWnd N0113VillX3
WOM3 0333 t131VM AVildS
arnleradwal uo!ieinles aql ahoqe 3 0 0 Llalew!xoldde ~
ON3ISnVHX3M3H1001
jo a ~ r n e ~ a d w ea llv 'a81188 ainleiadwal e pue aainos 0333 M31VM AVildS
u!elp aql le (arnleiadwal uo!;elnies ~ o q 01 s palelq![ea)
a8ne8 a~nssarde q l ! ~pap!noid s! au!l u!eip qaea
'uo!lelos! l q s ! ~ap!nord ol alqe
sLe(emleuaql s! anlen ialsew a q j 'aAlEA iLllem aql 01 paU!j
-uoa s! lalem su!eip aql 8u!lnoiq1 w o i j spas anleh aqi
jo uo!leio!ralap alq!ssod 'LeM s!ql U I 'ahleh ~ L l i e w
aql Lq pamOllOj lSl!j suado ahlen latsew aql 'dn-llels
IV 'sanlan iLllew pue lalsew aql bq pa11o~luosLlle 'alesuapuoa aql l o j lallno ue saprnord malsLs
-nsn s! 'lueld aql jo uo!lerado 8u!rnp pasop Lllew~ou agJ 'sarnie~adwal[claw pun weals uaamla
ale q ~ ! qSU!BIP
~ J S O ~ I U! ~ a i e mSU!BIP j o MOD aqL -j!p e u! silnsal suo!i!puoa weals so peol u
lOJlU03 Z'01 e uaqM uo!isrado jeurlou 8o!1np s l u ~ o osle
j I

lSnVHX3
'lassan sn!elp sqi u! 15~51 3 0 3015 M3HlO 01
0333 1131VM AVildS
aql jo uo!leJ!pu! jeJo1 san!8 ssa[%iq%!s v '1~suapuos 's.iapu!lL~ ao!qim ail1 ii!ql!~ alesuapuos jo il
aqi 01 .!an!aaal su!e~p aql w o q ajesuapuos ayi IJ!I aql u! sllnsal slelaw laloo2 q1F.n IJeluos oio
01 p a q n b a ~ale sdwnd 'sl!un awos u g .IssuapuoJ sql meals aq1 'au!q~nl e J O po!rad dn-lle?s a[(
jo wolloq aql 01 su!erp axesuapuos Su!u!ema.l aqL
'sLelds aql 01 pailddns lalem jo
lnohel walshs pue uo!$Dunj
lunowe aql sajeln3al rosuas ainleladwal e pue dwnd
uogaerlxa alesuapuos aql Lq paqddns s! iteids aql
IOJ luelooa a q j 'sLelds Su!leaq~adnsap ql!m palllj ale swa$sAs s u ! % ~ g
STUJA aql saw!iawoS 'rasuapuoa =!em aql oi paluah s!
qqqm weals oiu! saqselj rap* su!eip aqi jo awos
lassah s!ql Su!ialua u g 'lasuapuoa aql reau p a i e ~ o l I N 3 W 3 1 3 DNISN3S
'sran!asar su!erp aql 01 peal s a y iqerp neals IIV 38niVii3dW31
'as!j!'o aqi 01 uo!l!ppe u!
ssed-itq panjen e sale~od~oso! an!$ aqi 'rln-irels 8u!.1np e ~ 0 1 a qsjlej peal ail1 .so [anal s!in spaaaxa arn~i
alesuapuoa jo uo!oallos s51-el e aq 01 .(jay![ s! alaqr
amqM saseld u1 'molj aql Ia!rlsa.I 01 sa~ejda3!J!IO aherj
saw1 qJnS 'a8eu!elp snonu!]uos ap!ho~d 01 ,(mss53
-su ale sauq u!erp 'uo!lelado [awron Su!inp laM s!
weals aql alaqM 'sapu![La sql se q3ns sam!Sar u~
su!elp snonu!iuo3 2'1'01

0s p a s u e ~ ~s!a pue alnssald meallsdn ail1 60


.seala s ~ n s s a ~q8!q
d u! palnonej 1011
ale asaql inq 'sanleh litiiem aql jo amid u! pasn
are sderl weals 'smalsits raqlo u g .pea[ uo s! au!qsem
sql U J ~ M it[jenuem 1 0 itl[es!lemolne .Iaql!a pasols
I S B I U aql pue aleld aa!j!lo ua Lq paselda.1
s! 5 . y ~I ~~ Su!uo!ss!rumos je!l!u! So!rnp las s! sdwnd
ase sanlen r.(lr~maql 'swalsbs swos rrl ,sir!e.Ip dil-1.1eis
aql .soj 10.111103 alenbape sap!~\old 'TUO!I!~UOJ SU!
-lersdo 1nw.rou Zu!.tnp 'piie pas!roloui s! anjeh r.<lieur b!ddns ialem.iesds ai[i u!elu!euI oi loleiarlo ril
aq.1, .pa.c!nba.c s! uo!le!os! usi[,\i ,(11unueu~1pasols sq
ues jnq 'usdo bllewiou s! 'ulaarlsdn palesol 'snleh
isiseu~aqL 'sa!.las il! sshleh .ai).mili pile iaisulu aioior!
-.co~u! ,iei~csti!eij> 5 ~ 1 .d~n - i i e ~ sSu!.<nps13a1103 L~D!IIM
Turbine plant systems

facilities to mdil-ect steam frolli


tulbine. Thew are several reasons why
~ ~ c d eandd thcy differ, depending uPOo
pli,nt is fossil-fired or nuclear. The one
(and the most important) is
arge loss o f turbine load. For a more UULIISTEP
INTERNAL
n of the reasons for by-Pass systems FRiCiiON DEViCF

COND~NSER , clear and fossil-fired by-pass systems


uallat in design, their fundamental modes
are They both redirect steam from
lilct and pass it to the condenser via a series
,ii valves, pressure control valves and dump

CONVENTiONhl
SlNGLt ORiFCE
VhlVE

I'ressure control valves


,,IVCS are designed to greatiy reduce the Pressure
c,t stcam so that its conditions correspolld
those inside the condenser.
I , P I ~ S I way of creating a iaige pressure drop
is by the conversion of heat energy to
(kinetic energy) by passing the steam through
I.
ENTROPY -
ice. Downstream from the orifice, tur- I:IG 2.81 i'reriure coiliroi valve cl>arreieiiiiics
mpanied by shock waves reconverts the
ange in energy for a
TIC. 2.80 Typical turbine HP drains system
drop, the shock waves created produce a large
I of undesirable throttling noise. Consequentl~,
llavc been developed that produce the same
i drop but with considerably iess noise, Fig 2.82

es a complicated flow path which results in the


,ation of energy through a high loss of head rather
I tlirough shockwaves (Fig 2.81). The flow area
rc8idethe stack is gradually increased towards the
ownstream end. This helps maintain a n almost con-
Of water but limits steam flow. 1 l l n t steam velocity over the expansion caused by the
o r wet steam will pass through to the drains vesse ressure drop. Generally, these valves are capable of
In other cases, the valves are opened automatically As soon as steam at saturation temperature (or abov
On reducing load or steam traps are used in place
~~,,i,,~from fully-closed to fully-open within three
enters the trap, the ball valve is held tightly on its c,:conds and from fully-open to fully-closed in five
Of the valves. The steam trap is designed to seat, thus preventing the escape of live to tl,e
allow water to escape. but not steam. There are various drains vessel. The temperature can
types Of such as ball float, inverted-bucket and constant, or can be varied depending on conditions i,, Isolating valves are not required to create a large
thermostatic traps. The traps are similar in operation the steam system. pressure drop and their design is simpler than that of
21.1.2 Isolating valves
and construction, although detailed differences are Most steam trap installations incorporate a by.pass, the pressure control valve. A typical isolating valve is
,l'hese are usually situated either side Of a
needed to meet the various operating conditions. s o that the traps can be isolated for inspection anrl shown in Fig 2.83. The valve is a parallel-slide type,
I,ressure control valve for two reasons. First, 10 en-
As an example, the thermostatic trap consists of maintenance. This by-pass permits the blowdown of the total isolation o f the control valve if it so called because it does not rely on a wedge action.
a forged-stee1 body with a removable cover. Inlet debris or contaminated condensate during commis. requires maintenance whilst the turbine is running: Instead, the discs slide over the seat faces when the
and outlet Ports are divided by a vertical wall. A sioning o r subsequent run.ups, and prevents ,,,,due valve is being opened or closed, resulting in a minimum
second, to provide a back-up should the control valve
ball valve situated on the downstream side of the contamination of the trap strainer, pressure drop.
210 211
B y p a s s sysletiis

tlic tube section diverges hcrc to act


associated exgansioo o f tlic steam. T

lion known as the dispenser.

11.2 By-pass systems for nuclear plant


A b w a s s system is important in a nuciear phiit
the following reasons:

gellerator safety valves. (The reactor control


Fit; 2.64 1)smp cube

ill the need for system by-pass.)

Stored energy and residual heat can be remc


following a turbine or reactor trip. This ill b nd [he progra,nlned rcactoi-coolant tem- their last held position and control is regained by using
. The controller subsequentiy closes the valves remote lnanual operation. The pressure control valves
the plant to no-load conditions without the ac
tion of the steam generator safety valves.
The plant can be maintained at hot standby coil

Manually-controlled cooldown of the plant can


achieved to the point when the 'residual heat rcmai
system' can be operated. 11.3 By-pass systems for fossil-fired plant

Figure 2.85 shows the arrangement of the by


System for a nuclear plant.

FIG. 2.81 Typical irolaiing valve


lines branching off it to the three condenser she
via the isolation/controi/isolation valve arrangeme
and the dump tubes. For each pair o f lines, one [ill condition. It is also used to maintain steady
The isolating valve downstream from the pressure is designated 'Bank alld is used in a modulating mod
control valve has a back-seating arrangement on the that the required conditions can be regulated,
spindle to prevent the ingress of air to the condenser other line is designated 'Bank 2, and is either open or
under normal running conditions. closed.
There is another bank on a separate line from
manifold (not shown in Fig 2.85) which exhausts
rectly to atmosphere. This 'Bank 3' is used when th
hlcam by-pass control valve is not closed. Thereafter The by-pass scheme comprises two systems - an HP
(lie spraywater flow is arranged to be directly pro- system and a n LP system. A schematic representation
,xw[ional to the steam pressure measured in the dump of the HP system can be seen in Fig 2.86.
[t~he,after the control valve downstream isolating The HP steam is taken from each of the main
villvc and before the first orifice piate. As the flow steam lines after the main steam stop valves. The steam
through the dump tube is critical, the spraywater passes into the cold reheat inlet via four pressure
Slow is proportional to the steam flow. control valves and their associated isolating valves.
In the event of a loss in electrical power or air The correct temperature to the cold reheat is achieved

212 213
lliiough the employment of desuperheater spraywater.
'Tlic spraywater supply to the pressure control valve is
. If condenser pressure is too high.

litken from the main feed pumps and has its own set Unlike the nuclear by-pass system, the pressure control
c11 !pressure control and isolating valves. The presence valves will fail locked in their last-held position if
(11 warming piping and drains in Fig 2.86 will be dis- there is a loss in electrical power. The spraywater
LA7ikli
iiivt c~issedlater in this section. pressure control valves also fail locked in their last-
Iluring start-up the pressure control valves are held position.
xned manually until the valves are more than 10% The LP by-pass system consists of four lines taken
,en, at which point the system is controlled auto- from the four hot reheat pipes (upstream of the IP
atically. When the boiler steam pressure reaches a turbine control valves). These four lines are then con-
xcified value, the by-pass system automatically keeps verged into two. The steam in each line flows through
ie boiler at that value. In the event of a turbine trip, a n isolating valve, a pressure control valve and then
ii signal is sent to the control valves to open rapidly. into the condenser dumo tube. The LP by-pass system,
CONDENSER Alternatively, in order to protect the cold reheat piping therefore, is very similar to the by-pass system on a
system, the pressure control valves can be ordered to nuclear plant: it behaves in the same way as the HP
close rapidly under the following conditions: system, the pressure control valves opening or closing
under exactly the same circumstances.
o When the spraywater pressure 1s low

D If any spraywater valve falls to open wlthzn three


FIG. 2.85 B Y - P ~ Econfiguration
S for a nuclear piasi seconds of its assoc~atedpressure control valve. 11.4 Problems with by-pass systems
The presence of by-pass systems, as has been seen,

.
If the steam enterlng the cold reheat plpes is at too
can greatly benefit the plant. Their addition, however,
hlgh a temperature
does result in a few oroblems such as noise, water
If the pressure m the cold reheat system is too hlgh Ingress and thermal shock.
214
Turbine plant systerrls Operationai flexibiiity

11.4.1 Noise O i l tile conti0l v;ilvcs that exil lo almospheie (1i;iii itilili~iooto loadfoilowing cyclcs, This ici]uiiemeot iinoccessasily. Stcani coirditioris at tile stop valves
li usas discussed earlier liow iargc pressure drolis across on nuclcai plant) by includirig n sileilcer. l,,,l>ii,ued ficxibiliiy has resulted i t ? all 500 M\h' and sliorild alloiv for tlie temperatucc drop due to Ilirol-
valves induce co~isiderablc i~oise. Figure 2.87 slio\~~s \.lW t u r b i n e - g e n e r a unils on the U1< system tling at steam adn~issiolilo the turbine (sec Section
ho\v !lie proportion of energy loss converted to noise esigned to be capable of operating a two-shifting 1.3 of this chapter), It is pal~ticulal~ly
importali1 wIleI1
(acoustic efficiency) increases with the sizc in pressure 11.4.2 Water i n g r e s s i n addition t o thc requirement for high effi- carrying out hot starts, that thc late of roll-lip to
drop. This effect is reduced dramatically by using valves With the pressure conual valves shut, a large hoiii1.1 ase-load operation during early life. Typical speed and initial block loading is sufficient to pre\,eol
that employ adiabatic flow with friction, as discussed o f condensation wili occur in the steam lines. 11 11 ooal requirements for modern high merit tur- a reduction in turbine tcmpcratuie. The range of tcnl-
eariier. Noise can be reduced further by increasing tlie condensation were allowed to remain, water wa plant are shown in Table 2.2. pcratuie cycling should be controlled as far as possible
thickness o f the downstream piping and covering it passed through the system when the valves are ai t o minimise the risk o f thermal fatigue.
with acoustic insulation. Figure 2.88 shows the ratios resulting in damage t o the valves and conden Figures 2.91 and 2.92 show typical run-up curves
Tnai.s 2.2
o f pipe thickness to pipe length used to create further avoid this build-up, drains are located at strate for a warm start (after a weekend shutdown) and a
noisc attenuation. Even rno1.e attenuation is achieved tions, for example, in the busmain and upstreiini T j p i c n l opernrionnl requiie,8ir8ilr hot start (after an overnight shutdown) respectively.
each control valve shown in Fig 2.85. Drains arc ill The rapid loading shown during the hot start i~idicates
present on the HP system o f the fossil-fired plant silo\ the importance o f maintaining a steady rate of rise
in Fig 2.86 t o prevent ingress of water from 111 of temperature. Run-up procedures must be adhered
Spraywater system. g) viti? iu~>-up lo full-load 5000 to in order to minimise cyclic thermal stresses in the
iii 30 niiiiutes turbine and thus prevent thermal fatigue problems
1000 during the life of the turbine.
11.4.3 Thermal s h o c k 8 ii;,r~s starts ioiio~isg> 120 lhoi~s
200
The drain lines at the upstream section of the colit pvoionged r l l u t d o w ~ ~
valves serve a duai function. As well as maintaininlr 11 12.1.3 Load cycling
pipework free from water, the)' also maintain the viil
I ,,,li~.io~~owi~ip
Clia,>geiof loud iii 50.- iOO0lo 4000 The amount of load cycling that a turbine is expected
load range. Asruining
bodics at a temperature wllicll will avoid any large l i of 3
~liiniintn~r hours belwccn
t o carry out (i.e., defined as cycling between 50%
ma1 shock t o the valves when the by-pass comes i i i l c cyciei. and 100% load) needs to be controlled. In addition
operation. to specifying tlie number of load-following cycles
required during the life of the plant, thc time taken
t o carry out ioad changes should be such as to mini-
11.4.4 Leakage f l o w s 2.1.1 B a s e load mise cyclic thermal stress. This means avoiding rapid
An almost inevitable problem with by-pass systems, ider normal conditions, all high merit plant would bc cooling or heating of the turbine when inlet steam
with most steam systems, is leakage flaws. Leaks fr ~pectedt o operate in a base load regime. This involves throttling is applied or removed to achieve the desired
valves reduce the efficiency of the plant, so valve ng periods o f continuous operation, with infrequent load change.
designed t o be as secure from leaks as possible. Du )i+,ti times' to facilitate statutory testing, inspection
the life of the plant, leaks are likely t o occur, but ,nil overhaul/maintenance periods. Base ioad units
kept in check with regular maintenance. Taking all t l ~ In inot normally accumulate a high number of hot or 12.2 I n f l u e n c e on m a c h i n e design
considerations into account ensures a safe, ef iviixln start cycles or load-following cycles. Figure 2.89 The need for flexibility has brought with it inherent
and reliable system which provides flexibility bet\r,ecli ows typical run-up curves for a cold start on a problems which have needed to he redressed at the
the boiler/reactoi and turbine conditions. MW turbine-gcncrator. In this particular example, design stage of the turbine, with the knowledge of
-load is achieved after nearly six hours, excluding future operational requirements. The main probleni
1111. time taken t o achieve satisfactorv steam conditions is the effect of thermal cycling with respect to thermal
iil the turbine stop valves. This long run-up time is fatigue damage. The flexible mode of operation in-
12 Operational flexibility 11111 only to limit differential expansion rates and rotor volves some degree of temperature cycling of com-
eccentricities, but also t o limit thermal stresses within ponents, leading t o strain cycling of inaterial in the
tlic turbine, critical regions. The damaging cumulative effects o f
12.1 T y p i c a l o p e r a t i o n a l regimes thermal cycling (i.e., stress-strain cycling) must be
Power station output, and therefore generation, need assessed over the turbine life t o ensure that sufficient
to be regulated constantly t o match consumer demands, 12.1.2 Two-shifting margin exists in the design for the effects of steady state
Economics demand that the base load should be pr Onc of the most important factors when considering creep.
vided by the most efficient plant, which mainly includ two-shifting operation is t o keep the turbine tempera- Figure 2.93 shows a typical stress-strain cycle as
nuclear and large-capacity coalfield-sited coal-fired st;$- illies as high as possible during shutdown. This means experienced by the surface of a large HP rotor. The
tions. More expensive, or less efficient, generating plant Illat the machine needs to be deloaded as rapidly as cycle shows the effects of two-shifting using a typical
(small-capacity coal and oil-burning stations) arc possible. Figure 2.90 shows typical shutdown curves 'warm' start where the temperature gradients cause
therefore needed t o vary output t o match demand. The lor a 660 MW turbine-generator, in which the machine thermal strain. O n heating with steam at 565°C the
plant that is required t o run intermittently to matcli is shut down within 20 minutes, with the last 50% surface attempts t o expand but is compressed by
demand operates what is known as a two-shiff regime, of load being shed in approximately 2 minutes. Main- restraint from the underlying material. This compres-
so called because o f the requirement t o run during the taining the turbine temperatures in such a way ensures sion, represented by line A-B in the figure, may cause
two daytime shifts but t o shut down during the nigh1 o faster run-up and reduces thermal cycling of the the surface t o go into compressive yield, represented
shift. Such plant may also be called upon t o shut down turbine components. When starting, it is imporlant t o by line B-C, in areas of high stress concentration.
over the weekend. It is now common for 5W MW and ensure that the steam inlet temperature is matched to Subsequent heating and expansion of the underlying
FIG. 2.88 Ideal pipe dirnensiolls 660 MW machines t o carry out two-shifting operations tile metal temperatures t o avoid cooling the turbine material then causes tensile stressing of the surface
216 217
iiME.rn,"

FIG.2.90 Typical 660 M W turbine-generator rhufdo>vn curves


Operational flexibility

iiME.m#n

FCC. 2.91 Typical 660 MW turbine.geneiator run-up curves for a


FIG. 2.92 Typical 660 MW turbine-generator run-up curves for a 1\01 start
. ..

Turbine plant systems Operatio~ialtlexihility

ciaiioii lhas inilucnced the desilin of iiil-bines in scx~t~ial


areas

12.2.1 Turbine cylinders


Probably the most significant change in turbine desi(tii
has been the adoption of multisliell cylinders, I'lic
advantage of this type of construction is that piessiirr
difference and temperature gradients across each SIII:II
is reduced compared with single-shell construction. 11 i$
now normal practice in one form or another, in lhigl~
temperature machines, for HP and most IP cylindrrr,
and is usual for most LP cylinders. Low pressorc
cylinders sometimes have a larger temperature ranpc
from inlet to exhaust than any other cylinder, and rlie
inner casing may itself be of double-shell canstructio~,
to reduce thermal stresses and distortion. As ratinpi
have increased, component size has increased and wiil!
it the problem of transient temperature gradients witlli!,
a component and thus thermal stress. The use ol'
multishell cylinders has allowed temperature distribution
and gradients to be controlled, thus minimising cyclic
thermal stresses. 111addition, this design allows the heavy
flanges which were necessary on single-shell designs lo
be reduced in size. In some cases, the use o f one-piece
shells, with no horizontal split, obviates the need fol
flanges, thus removing the problem of axiai thermal
stresses due to uneven heating of flanges and cylindcr
walls. The use of flange heating has also contributed to
matching the rate-of-rise o f temperature of the flanges
and cylinders more closely.
The adoption of multishell casings and the separation
of steam chests from the turbine cylinder, has allowed
PIG. 2.93 Typical sfreir-slraiil loop for 1r.o-sliifiisga
large, iiigii temperature rotor simplification of the geometry o f each component. This
means that the design has fewer changes in section ant1
more attention is paid to radii to avoid high stresses in
areas where a change in section is unavoidable. Figure
as full power is attained (line C-D). Stress relaxation 2.94 shows a triple-shell H P cylinder with an unsplii
(line D - 4 can then occur at the maximum operating intermediate sleeve. To further reduce tempeiaturc
temperature, during which elastic strain is converted gradients, particularl~ in the first staee - of the H-~P ~lietrical rubbing, which bends the rotor even more, requirements of steady and cyclic operation. One
to creep strain and may cause microstructural damage. turbine, pure throttling of the governor valves has been cnn cause so much heating that the heated area of the example of this is the rotor bore sire. A large rotor
Shutdown causes a drop in temperature at the surface, adopted for load control. Although this type of control rotor, expanding and constrained by the surrounding bore, often with a diameter of half the external dia-
the thermal contraction being constrained by under- reduces efficiency at part-load, this can be tolerated in unheated material, yields in compression. As a result, meter, gives improved performance for transient or
lying material, resulting in further tensile stressing. two-shifting operation, where the machine tends to be when it is allowed to cool, local tension is applied cyclic operation, as the temperature gradients and
However, this straining takes place outside the creep operating at rated load or is shut down. The practice leading to a permanent bend. Such 'rubs' are usually thus thermal fatigue is reduced. However, large dia-
range of CrMoV steels used in rotor construction. Details of using nozzle control to maintain part-load efficiency caused by distortion of gland seal positions from their meter bores cause an increase in the hoop stress which
o f rotor materials and their properties with reference has the disadvantage of reduced efficiency at full-load normal concentric location due to rapid thermal cycl- will accelerate creep at steady load. In large modern
to creep resistance are given in Chapter 1. The stress- and leads to temperature gradients because of the ing. The adoption o f spring-back gland seals allows machines, the requirement to reduce the hoop stress
strain cycle of Fig 2.93 is similar to that experienced circumferential non-uniformity o f steam admission. retraction of the seal should contact with the rotor dictates that the bore diameter should be kept to a
by the inner surface of a high temperature casing This reduces the rate at which load can be changed occur. This limits the damage caused by a rub and practical minimum. The main requirement for rotors
under severe starting transients. without inducing thermal stresses. Rapid starting and seduces the.risk of a shaft bend. is to reduce thermal fatigue by ensuring that all stress-
The magnitude o f thermal stresses produced during loading, which are essential requirements for modern Cylinder expansion and contraction during run-up concentrating features are controlled so as to mini-
two-shifting or cycling, depends on the amount of tem- machines, are therefore achieved more securely with and run-down, requires that cylinder/pedestal sliding mise the stress levels.
perature change imposed in a given time in relation to throttle control. surfaces are well maintained, to prevent unnecessary A fracture mechanics approach is adopted to assess
the sizes of components involved; for example, casing During run-ups and r a d d loading, -. the turbine is
~ ~
external forces on the cylinders due to sticking. the growth of any initial inherent forging defects. The
thickness or rotor diameter. Stress concentrations in most at risk from a 'rub' between stationary and rotating repeated application of stress during cycling could cause
casings and rotors must be reduced to a practical components. Apart from localised damage at the area the defect to propagate to the stage where fast fracture
minimum by the avoidance of rapid changes of section of contact, the resulting heat generated by the 'rub' 12.2.2 Turbine rotors of the forging would occur. With knowledge o f the
and by proper fillet radii. T h e need for flexible op- can cause a bend in the rotor shaft. Continuous asym- Rotor design is influenced by the often conflicting operational requirements of the turbine and assuming
pallolluos aq lsnw mou l!e aqJ 's~uauoduroaSleuo!iels s1010i dl Due d~ U! Sarsahs t*ru,aql %u!lo>!uom
pue Bu!leIoi uaamlaq lsemoa jo uo!lea!pu! an@ plnoa ~q aqoid Su!lsjnru[s lolo1 alqeaJe!dax $6'2 .old
I[J!~M ' t u a ~ n aIOIOUI Bu!i~eq aqt pue salnwiadlual
lelalu dl pue d ~ !suo!suedxa le!luaiajJ!p d 7 pue
' d !sa!i!a!lluaa3a
~ lolol au!qlnl d l pus d ~ 01 p!ed s!
uo!lualle asola ieql le!luassa s! I! '8u!looa Bu!ln= c
"

'meld iaqlo 03 l o lauuosiad

r---
.laql!a 01 plezeq ou luasa~d01 se Sem e clans u! pa81eq~
I131VM -s!p aq lsnm I!e paleaq aq& 'sadrd iahossola
ON11003
aq1 urolj swan B!A s~sneqxaau!qlni 41 aql urolj I!-+

-
'SaAleA dwnp laleaqal aql e!h alaqdsoluie 01 Bu!)sneqxa
l e a ~ p pue
i sad!d leaqar ploa a q 01
~ suo!laanp qloq u!
1131711
i3iNl siw awis-2 OW aurqlnl d ~ aql JO anaalr m u ! aql pue lapuysa
no aql naam~aq9u11ama I!V 'sau!qml pue d ~
111 i o j mou i!e JO uo!mal!p aql smoqs s ! q ~'96.7. a!d JO
Iuama9uelie a!leluwerse!p aql u! u ~ o q sS! lo)e1aua9 NOIL~SO ~
H3V3

SiiNn t13HIO 01 - I N N 099 e IOJ uralsKs 8u!loo~ i!e-paa~oj [ea!dLl v


IVS3ld003OWIJ3HI
1IVUVd3S OM1
uivo33no~

S3IVld 331di80
11 '!lo!suedxa le!luarajj!p aql jo loliuos laaaq Su!n\olle
'inill 'iorol aq3 $0 leql ueql laq%!q s! slooa Bu!sea aqi
tq>!q~le ale1 aql leql sarnsua s ! q ~'ssu!ses ralno pue
raou! aql UasMlaq aaeduaiu! ail1 olu! i!e a111 Bu!)3alu!
q paha!qae s! 8u!iooa 'uo!suedxa le!loarajj!p ah!l!sod

1003 .10101 310 luanald OL 'Jnsao IOU s ~ o psluauod


12 iaqlo l o iapu!lLs aql jo Su!1l!qa jeaol alqeidasse
11 laql ainsua 01 slu!od uoya/u! aqr 1e pap!nord
~r!iolou ale slasnjj!a 's~apu![Sa aql punom paleaor
n!od uo!laaju! le!aads e!n slapu!lSJ d l pue d ~ aql
n! l!e 3~![003JO u0!13alu! IOJ a[qel!ns aq 01 pau8!sap
aIt!qlm aql 'paLoldwa aq 01 anb!uqJai s!ql iod
au!qlnt lo 6u!1oo3 L'PZL
3A7m DNW301
NOliVlOSl aienoa

. . . . ..
1003 i!e-PaJ.iOJ J o asn aql ql!M 'ilT~3!dLl:S~LU!I
~.
I~~loloa lalJW~q!SSOd se uoos se In0 pa!Ue3 aq 01
! ,~sueualo!euBo!lqeua snql 'aw!, Jlq!ssod isal.loqs
-!dLl sMO1ls 56'2 s J n 9 ! ~'iolOl aql J O uo!nas [e3!1!12
ti! ;rll!lleq Jjo eayel aq 01 au!qaew aql ,qle ol '4' salefnu!S li3!qM a102 IBllUa3 8 q l ! ~saqoid sin)
-e'admal J0 asn aql PaAa!li3e s! Su!iol!uom ~ I I J
."
I I I I iiretu aul 10 a u.. , ,~
r i o o ~rie-nJJ.,oI
~ $ < . asod,nd 2 , ,<&r
'palles sam!laruos a.le
6u!loo3 r ! e - p a 3 i o j &'ZL Laqi se 'SIOI!UONI a.lnl!p~tadxaa j , ro s t o ~ ~ u o ussa.,rs
,
JO lualudojanap sql inoqe 1qSnolq luaura.r!nba.I Su!rol
-!uom s!qL 'au!qinl aql jo aj!~jeuo!lelado agl u! Insso
IOU II!M a8eurep an8!lej e~eur~aq~ 1eq1 a.insua plnorls
' ~ o i o i541 J O seaie !ea!~!.rs u!ql!n ssarls s ! q ~' p a p a a m IOU ale slahal ssalrs jeutxaql a1qeMoile
I sill arenleha 01 mo pa!rlea s! s!sAjeue ssalln wnm!xeur aql leql 0s paiol!uou ale 'sro1o.i d l pue d ~
I a.lsgM ' i a ~ n d u o ae olu! p q uaqi s! elep s ! q ~ "9.a 'scuauodmo3 je~!r!is U!~I!M S15ASj SS311S [BU1.13ql
ill! aqold qloq IOJ awes aql s! q3leurs!w ainlerad leql le!a!Jauaq s! I! dll-sun1 9u!.lna 'papaaaxa lo" lnq
lii.>iu/rneals leql sueam S!IIJ '21e.1 a u a s aql re 'paqaear s! lrws qma 01 pale1a.1 pna[ sss.11~ie[na!l.led
i i i l i l a,n j o seare l e q i 3 pcre aqo.id ail1 '9u!joo~ e ieqi uo!lduInss-e aql pun nc!aual!nba.I leuo!is.la
11 i i ~ l n pteqr os pauo!l!sod are saqord sq) 'uo!reI -do sl! no paseq s! ~ole1aua8-a11!qinlaql jo sf![ arfL
I! i.'.,i.ios rod '.rolo.i aq1 01 pai~!mpe se meals st11 s~o%!uoru$sails E ' Z ' Z ~
Turbine plant systems Wet stearn turbine pi

to give a cooling rate which allows eccenlricilics and flow at the entry lo the L.P cylindeis, and th
differential exgarisions l o be maintained within the adequately lhigh cfficicncy of blading. Higher I
manulactuicr's specified limits. ~ I C S S U I C S help to miilimise the sire of the or
segarator/rehcaler, and tlie mean diameter and lriigll
of the H P cylinder exhaust blading.
12.3.2 Cooling s y s t e m Thc inlet steam conditions also dictate the scai~tl
The cooling air is provided by a sysreni consisting of of the 1-IP stop and governor valves, which a
oil-free compresscrs or blowers, distribution and ex- similar in arrangement, size and thickness to
haust pipework, supports, valves and control gear, and valves on a conventional unit. A typical back-I(
fillers or air conditionine- olant.
. The svstem shown in arrangement is shown in Fig 2.98. Because $11
Fig 2.96 employs a single multistage compresser. It is temperature (about 280°C) and pressure do n
normal to install sufficient capacity to meet the cooling a material with high temperature strength and, sine
requirements of one turbine only, with pipework pro- steam at inlet is insufficiently wet to cause er
vided to enable cooling air to be supplied to any of a low carbon steel is used fox the valve chest
the units in the station. loop pipes supplying steam fro111 the chests l o I I
It is important that the air supply is filtered to ensure H P cylinder may also be made from carbon steel
the removal of small particles and also that it is free the same reason. The loop pipes are generally ariai!
of any corrosive gases, such as sulphur dioxide and to be as short as possible to limit the quantity
chlorides, as emitted from the stack of fossil-fuelled steam which might overspecd the machine in the i.!,cl
stations. Moisture separators should also be installed, of load rejection.
along with suitable pipework drains to ensure llial the The H P turbines of large wet steam machines t
air supply is dry. usually of double-flow design, similar in appeal;$
Fieurc 2.96 also shows lockinn double-isolatine valves to tile IP turbines of conventional units. As ma)
seven stages of moving blades in each flow are ca
by a rotor which, in tlie UK, is nonnaliy of a mona I
from the turbine when not in use construction. Diaphragms or fixed reaction bladitr
are supported by carrier rings bolted to the outer cissill
at the horizontal joint as in conventional macliitl
This effectively forms a double-shell construction
permits moderate casing thickness, flange and bolt
13 Wet steam turbine plant to be employed.
For impulse blading and an adopted rotational.
of 3000 r/min, the bladed wheel diameters tend i r
13.1 Influence of steam on components relatively small and, with the high specific steam .
The steam produced by a modern light-water reactor, sumption, the blade lengths become relatively I
such as a PWR or BWR, is of poor thermodynamic The double-flow arrangement serves to keep the . ,
quality. The pressure is typically in the range of 65-70 lengths, and hence the blade stresses, to conservat
bar and since thc steam is around 3% wet, the tem- values.
perature corresponds to saturation conditions. It there- Care must be taken in the design of the H P c ~ s i
fore follows that the steam mass flow per unit of to eliminate crevices and pockets where water 11
generation is about 80% higher than in fossil-fired or collect, otherwise, during sudden load reduction, 110
AGR power stations. of standing water could flash-off and overspeed I
The very modest steam conditions at the turbine turbine.
stop valves results in a very large volumetric flow. It is normal practice to pack the shaft end glan
The turbines consist of one high pressure and two or with live steam which has been throttled and 11
three low pressure cylinders, with the steam exhausted therefore acouired a small amount of suverheat. TI
from the H P cylinder being dried and reheated in also removes the possibility o f erosion damage to II
external moisture separators and reheaters before be- rotor and other components in a n area of high mol
ing readmitted to the L P cylinders. A typical turbine ture content at the end of the H P expansion.
arrangement is shown in Fig 2.97. Unlike high tem- The steam leaves the H P turbine with a well1
perature reheat turbines for fossil-fuelled power stations, of between 10% and 15% dependent upon tl
where reheat pressure affects boiler design and is lected crossover pressure. If the steam were then p
therefore not a free choice of the turbine designer, the directly into the LP cylinder without any form
reheat pressure in turbines for light-water reactors is mechanical drvine . - or reheat. the terminal wetness
chosen by the turbine builder to suit the turbine and condenser pressure would exceed 20%. This would cao
moisture separator/reheater design, performance and unacceotable LP movina.blade erosion, oarticularly
economics. Due to the very large mass flow of steam, the last stages, and turbine efficiency would bc i t
it is not necessary to select a low reheat pressure paired. Reheating is therefore always employed
in order to preserve a n adequately high volumetric saturated steam cycles.
226
Turbine plant systems Chapter ? f Wet steam turbine plant

:ill lileir stages to stcaill ptessllics ant1 1empcratiil.e~ HI' cylinder into b l c d s t e a o ~pipes and into the caid
!irtually i d e ~ ~ l i c alol those 1'01 fossil-Coellcd stations. rchcat pilics, whicir are drained at a11 times to llrc
it is therefore $possible and desirable to use LP cvl- drains icceivcr; the Ll' cylinders into bled-sleam pipes
intieis of identical design to those used in turbines for and lhe condenser. if gockets at each end of the H P
ii~ssil-fuelledstations. However, enhausl volume fiow cylinder arc formed in the casting between the coid
ii 60-70% greater than for a fossii-fired unit of the reheat branches, these are drained cootinuousiy into
m n e rating. If, therefore, exhaust losses are to be the coid reheat pipes.
Ikcpt to a minimum, either the exhaust annulus of each Intcrstage drainage introduces considerable quanti-
1.1' turbine must be increased or the number of LP ties of water to the feedheater system and the provi-
llirbines must be increased. sion of exlra laree drain arrangements in the design of
In the USA, half-speed machines have been adopted this system requires careful consideration. In common
l'cv use with iarge output light-water reactors. Power with conventional machines, every effort is normally
g r ~ ~ e r a t i ois
n at 60 Hz, which limits the choice o f made ta ensure that there is no oossibiliti' of water
rotational speed t o 3600 r/min or 1800 r/min. The refluxing to the turbine. Present specifications require
ilrcsses in the exhaust blades impose a limit l o their individual routing of drains t o thc turbine drains re-
lul~glh in full-speed machines and hence a limit in ceiver and prohibit the commoning of drains from
Ihc cxhaust area ner turbine. This. ~,toeether
~ . " with
~~
thr
........ sources at different potentiais.
FROM
STEAM GENERATOR
TO HP TURBiNL w,idcspread use of 1800 r/min LP turbine elements in
ci,~iventionai power plants, has led naturally t o 1800
I : , ~ , 2.98 ~ ~ ~ k . t ~ alrailgemoi~i
. b ~ ~ i , or H13slop a#?dgovernor valves ~/iiiin as the design speed for PWR turbines in the
hO IHz system. 13.3 Erosion protection
111 a 50 Hz system the position is entirely different.
Steam enleis the H P turbines slightly wet and i t be-
h41icb larger turbine exhaust blade annulus areas are comes progressively wetter with each stage of expan-
In order t o avoid the complication o f additional t~vi~iiable and still longer blades are being deveioped; sion, but the moisture droplets are very small and
ISWP nrnrtrntions into the reactor. steam is oassed tr~eking3000 r/min turbines economical for large out- are so well entrained in the bulk steam flow that the
purs and different condenser pressures. Half-spccd velocities of droplets and main steam do not differ
turbine hail where the wet steam is dried mechanically 'hines are invariably more expensive than full-speed
significantly. Blade path erosion is not therefore a
before entering a reheater, also situated in the turbine ines. The design of the LP turbine elements can
significant problem and the biades can be made from
hall. Here the steam is superheated by the use of live sed upon extensive experience of identical oroven
12% chrome stainless iron coupled t o a NiCr MoV
steam which results in a performance improvement of llponents for conventional power stations. Howevcr, forged rotor, as in conventional machines.
about 1.5%. The thermal efficiency can be increased clear power generation leads in itself to increases
Centrifugal stresses are generally low and, since the
rlic size of generating units, and it may be necessary
-,a further 0.3-0.5% bv two-stage superheating, i.c.,
hv steam temperature is far below that at which creen has
I i'aiisider half-speed machines for future very large
by using b~ed-steamfro; the HP t u A n e as heating t o be taken into account, only medium-strength ferritic
I I ~ I ' . requiring large annulus areas, particularly in
steam in the first stage and live steam in the second
---.-- The
stage. - .
efficiencv imorovement
. ~ a i n e dby bled- -----.-- nbination with the low cooling wale,. temperatures
lii;riy in UK plants.
stainless iron need be used for the blading.
Where changes in flow directioli are induced in the
steam reheating has t o be balanced against the in- casings or pipework, or where pressure differences exist
creased capital cost, and is dependent o n the cross- across joint surfaces or pressure seals, water droplets
over pressure, bled-steam pressure and the rcheater can combine and there is considerable potential for
terminal temperature differences. The bled-steam rc- F ~ G .2.99 %utterfly type low nreiruie i>xerccntoi valve
Water extraction devices erosion. The H P casings, fixed biadc carriers and cold
heater improves the cycle efficiency by reducing the reheat pipes must therefore be made from a chromium
steam demand of the live steam section, but it also the steam enters the turbines wet and becomes
essively wetter as it expands through the H P alloy steel such as 2.25%Cr 190Mo. Such alloys resist
incurs a n additional pressure drop of the reheated
shedding to zero load, the interceptor valves cl ~ g arrangements
, are usually made for internal the formation of the surface oxide layers, which would
steam through the tube bundle and requires additional be continuously removed and reformed by an erosion-
drainaee facilities. Despite these factors, bied-steam rapidly, preventing the steam present in the SeParato tlre extraction at each stage. Where appropriate,
and reheater, together with any water which migh aeitls fitted t o stationary components are slotted corrosion mechanism. It is also essential to protect joint
rr.lle311ng 1% bccdmin& increaslngl) c;ansmrally \iable
.ind i s normally dircred on prescnl rlcanl n~a:h~nr,. evaporate off hot walls and pipework, from overspeed ennit extraction of water collecting o n the outer faces subject to a pressure drop against cutting by wire-
ing the turbine t o unacceptable limits. The valves oundary. This water is either removed with steam drawing erosion, and to protect surfaces which might
- \ulumc.lr(; flon at LP c)llndcr
Bcc;luie o f rnc larac
designed so that steam forces assist closure as soon from extraction points between the fixed blade be subjected to impact from water droplets flung o f f
inlet, the interceptor valves tend to be very large.
a small degree of rotation is imparted. The valves or, in stages which have no bled-steam tap- the shrouding of the rotating blades. This requires
This precludes the use of normal plug valves; instead,
butterfly valves similar t o that shown in Fig 2.99 are fitted with bearings which are capable o f operatin8 rained through the casing via pipes, drillings the use of very erosion-resistant alloys, such as 13%Cr
normally used for this application. Since there are no relatively high temperatures and have shock absorbi ces t o a stage at lower pressure. or 18%Cr stainless steel. Austenitic steel facing can be
right angle bends and n o restriction t o the flow, they characteristics. 'Illel extraction grooves may also be incorporated provided by weld deposition and 13%Cr inserts may
have the advantage of providing very low pressure The thermodynamically optimum choice of the cro m necessary to assist the feedheating belts in ex- be located by seal welding.
drop in the normal operating fully-open position. over pressure between HP and L P cylinders, and I Iiig additional moisture. These consist of a n annular T o minimise the possibility o f joint jacking by cor-
Butterfly valves are used for both stop and governing universal application of steam reheat, result in i ' c in the cylinder wail at the trailing edge of the rosion products, horizontal joint bolting must be ar-
valves, the two valves being arranged in a single chest conditions t o the L P cylinders which are closely . lli biades connected to a series of nozzles which ranged to ensure that water penetration is restricted.
weided into each hot reheat pipe. ilar t o those encountered in a high temperature irirge water and a small quantity of steam into It may be necessary to protect certain joints by placing
The valves may be used in a reheat governing mode, heat fossil-fuelled cycle. As a result, L P cylind between blade rings and outer cylinder. short stainless steel sleeves around them and incor-
for water-cooled reactors are subjected througliol 111: turbine cylinders should be self-draining; the porating stainless steel barrier keys.
as in conventional machines, but in the event of load-
229
Turbine plant systems Wet steam turbine

Sevcic erosion Ihzii lbecn cxpciieoced by conliiicilial noiinally lbori?.onlal ioicl pips Lliriiilgll a i1ivei.ging c l i l , I1ii.h ive/oci(,) g'ciotie Se,io~atoi
~nanofactoiers or, loa, alloy axid cal.bon slecl casings ical channel la a io\r of supirier bladcs. The s w i ~l r ~ 'I lit' major ~pl-obleol \$,it11 cyclonc or ccntrifogal sc-
and pipework in wet stcan1 macliines. 'Alstboin' ori- blade ring imparts tangei~tialvciocily, or swirl, to i l ~ i jiiii:iiors is the uressuie drop produced by swirling the
ginally niade 131' casings in f CrMoV hut, in view of s t ~ a t nand helps to agglon~eiatethe watei- dl-oplcts. 'I'ilr iiti.;iiii in a relatively large diametec drurri and then
cnpeiience gained at Muhlcbcrg, Beznau and Oskar- watei- films forming on tile aerofoil surfaccs o f tlic i;l!;iigl~teningthc flow at exit iron1 tlic scpaiatol. One
sliamm and in Germany, intend using a steel with at swirlel blader are subseqiiently detached as coarsr iorihod of reducing the pressure drol) through tllc
least 11% chrome lo luture to give satisfactory erosion droplers by the main steam flow. The droplets are then h~i>;iiatol. is by swirling the wct stem tli1.oug11a nitmbei
protection. They curl.ently make pillework bends in centrifuged by the stcam flow and deposited onto tlic 01' ielativcly small diameter tubcs or cells arranged in
2 i % chrome steel and apply a high-chrome cladding inner surfaces o f a loui,red liner which reinoves and it bundle in an enlarged section of cold reheat pipe. A
protection on interceptor valves. CEM (Asca Brown partitions the free water from thc main steam flow. typical separating cell and vertical assembly arrange-
Roveri) protected low alloy diaphragm groove facings The louvred liner is provided with a series o f narrow Inciii used in the Stein lndusliie design . is shown iii
and similar facings for gland groovcs with 13% chrome axial apertures uniformly distributed around its pcii.. I:i$ 2.101.
cladding but, having found the cost of achieving a phei-y lo entrain the water droplets. Separated watch. I n colnmon with the NEI-Parsons design o f cyclone
satisfac1ol.y 13% chl.ome deposit prohibitive, now supply films then cascade around tile outer surfaccs of tllc ruparator, a set of turning vanes at the cell inlet im-
13% chrome castings for wet steam HP inner and outer louvred liner. To encourage the separated water lo litisls a swirling motion to the steanl/watei mixture.
casings. flow over to the louvrcs, steam is extracted from tlir Inslead of a louvrcd drum, an annular skimmer slot
separator vessel and passed to a heater in the fecrl I!,cinployed t o collect tllc watei and a small flow of
train. The separated water is also passed from tlil, ~xlractionsteam is allowed through the slot to improve
vessel, via drain pipes, to a convenient point in tiit. liioisture removal. Another sct of guide vanes at the
13.4 Moisture s e p a r a t o r r e h e a t e r s ( M S R s ) regenerative feed train. crli outlet straibhtens the flow and helps recover rota-
Separators and relieateis fall into two main types. In order to ensure that steam leaves the separator tional kinetic energy. Since the flow does' not depart
Manufacturers such as Westingl~ouse, Asea Brown with the minimum o f swirl, anti-swirl vanes arc fitted hif:~iificantIyfrom the axial direction tlirougllout the
Boveri, GEC, etc., combine the two units into a single into the outlet nozzle. These vanes ensure that a low hcparation process, pressure drops a1.e generally small.
vessel or MSR; whereas Parsons, Stein Industrie, etc., energy axial flow of steam enters tlle rebeater, mini- hlso, because the cell bundle is not mllcli larger than
favour individual vessels connected by large bore mising the risk of disturbancc to the reheater tube IIIC diameter of the pipe on which it is fitted, tlle
pipework. bundlcs. separator may be retrofitted into existing installations
The performance of cyclone separators is very de- s'ith the minimum of disturbancc.
pcndenc o n the droplet size of the water entering thc In tests carried out a t Bugey I1 power station, the
13.4.1 S e p a r a t o r s vessel. Very high efficiencies (of the order of 98%) l>ressuredrop for an inlet velocity of 50 m/s was about
can be achieved with a wetness of, say, 12% if thc 150 mbar and the moisture content at outlet from the
Cyclone seprrralors
droplets are relatively coarse, but efficiency falls con- separator was 0.3% compared with 11.4% at inlet.
siderably if the separator is presented with steam o f Ifowever, 10% of the main steam flow was extracted
In the. NEI-Parsons design o f separator, shown in the same wetness with droplets in the sub-micro metre lo assist water rcmoval.
Fig 2.100, water droplets are recovered from the steam range. Tests t o determine separator efficiency, using Stein lndustrie have also developed a horizontal
by centrifugal action. The vessels are conveniently located superheated steam artificially wetted in a spray-type liigh velocity separator, in which a portion of the
in the cold reheat pipes from the H P turbines, generally desuperheater, generally give optimistic efficiencies aleam from the bleed-off is passed into the central tube
one vessel pel- pipe. The wet steam is passed from a since the large water drops produced by the desuper- ill the separating cell and recirculates through slots
heater arc easily separated from the steam. Measure- i i l this tube just downstream of the inlet vanes. The
ments taken o n site on practical installations have ,net leak-off flow is thereby reduced and good sepa-
confirmed separation efficiencies in excess of 95% liition efficiencies have been reported from rig tests.
SWIRLER BLADES
EYTRACTlON STEAM BAANCII
/
for an inlet wetness of 12%, and 93% at very high 'The performance of this type of separator has not
moisture contents above 20%. lhowever been repeated o n site, possibly because the
ISWIRLVANES
A major f a d o r in achieving these high efficiencies drainage systems are less than adequate on site and
is the growth in droplet size from a mean diameter of also because of the difficulty, expressed above, o f
about 10 microns at HP turbine exhaust to about 120 reproducing an a n HP turbine exhaust water droplet
microns in the transfer pipe t o the separator. Further size distribution in a test rig.
agglomeration of water films o n the surface o f the
COLD
REHEAT STEAM
swirler blades results in droplets o f about 240 micron
STEM diameter being centrifuged to the louvred drum. Wire mesh separalors
iNLEi OUllET
Erosion and corrosion are minimised by employing The early designs of combined moisture separator/
suitably resistant materials in areas subject to im- rehcater supplied by GEC, Asea Brown Boveri and
pingement. At the separator inlet, where moderate Westinghouse incorporated a wire mesh separator.
steam velocities and water droplet sizes generally prevail, The water separation characteristics had been sub-
2.25%Cr I%Mo steel is used for the inlet pipe and ject t o theoretical and experimental investigation and
cone pieces. In the main steam space, where velocities was established in a number o f industrial applications.
and droplet sizes are greater, the swirler blades, louvres Brodie [41, who studied the extraction properties of
and internal cladding o n the pressure vessel are of wire mesh in an atmospheric air/water flow, had de-
12% Cr low carbon steel. The basic pressure vessel monstrated that a residual steam wetness of 0.1-0.2%
PIG. 2.IW Cyclone separator Is manufactured from carbon steel. could be obtained but only over a narrow range of nc. 2.101 High velocity cycione separator

230
Turbine plant systems W e t s t e a ~ nturbine plant

\,cry lo\+! ilcam velocities of the oldel o f 1 - 2 m/s. is collecled on llic sloping bas? of each tray aii(l i~lenicnts do not lhave a clear uppcr limiting velocity
I'iirthes tests carried oul by GEC coniiroied that good drained to she base of tlie vessel tliroulih funnels ail<l :ind are tlierefoie moi-c tolerant af possiblc excessive
separation performaocc could be cblaincd for cross- pipcwoik. Irlcal velocities. Chevron separator performance also
over conditions in w a stcam turbines and gavc good A scheme devised by GEC is shown in Fig 2.103. leilds to be as good as wire mesli performance at
correlation with thc previously predicted upper limit- Steam enters froin tile base o f the vessel and is dii i~ricetile steam velocity. Modern designs of chevron
ing velocity. These, and other investigations, showcd tributed along the length of the vessel by a series ni aeparator regularly extract 98% of the watei from
that wltcr is cxlracted when the approach velocity is perforated plates which also act as water collectols, 12% wet H P exhaust stearn. Because chevron sepa-
siifficient t o cause inertia lmpactio~i of droplets o n Each hole in the distribution plates is provided with $1 rators are able t o give satisfactory performance at
the wires o f tlle mesh. After deposition, the droplets raised lip on the upper surface o f the plate t o prevelil lhigher steam velocities, they require a smaller frontal
coalesce and run along the surface o f the wire under the separated water draining into the steam flow a110 iiica for the same steam flow, giving a more compact
the Influence o f gravity until they reach a point where becoming re-entrained. The holes are o f such a sizc ;lirangement.
two wires cross. This point soon becomes overloaded and pitch that they ensure diffusion and downstreain Chevron separating elements are produced in various
with water and large drops fall from the mesh against mixing of the steam. Water is collected in drainage fol.rns. Basically, the elements are parallel corrugated
the direction of the steam flow. troughs set into the perforated distribution plates and ~)ialeswhich induce separation of the water droplets
The wire-mesh mats must be disposed as near hori- is led to the bottom of the vessel. From there, tlic by inertia and impaction. Earlier types incorporated
zontally as possible and, in view of the necessary low separated water is piped to a heater i n the feed train. Iiooks or stops in the corrugations to induce even
velocity, the mats have to be very large (80 m2 for !inore sudden changes in the steam flow. Thcse elements
a 300 MW machine). This, in turn, requires a steam were complex t o make and the slight performance
Chevron or corrugated-plate separators
distribution system capable of coilecting and draining in~provementdid riot warrant the additional complex-
the separated water falling from tile mesh without Although mesli separators arc most effective in re. ily and expense. Current designs employ simple cor-
causing re-entrainment, or impairing the uniforrnity moving moisture, their major limitation is the massivc rugated plates, sometimes with curved sides or, more
of the steam flow. Different manufacturers achieve size imposed by the low iimiting velocity. A mesli recently, with flat plates in a zigzag pattern.
this using different ingenious methods. Figure 2.102 separator which is almost 100% efficient at 1.5 m/s The droplets captured on the corrugated platcs
shows a cross-section through an Asea Brown Boveri may only be 60% efficient at 1.7 m/s, since the steam coalesce to form a film of water which drains down
arrangement. In comnlon with all mesh separator velocity is then just sufficient t o prevent the watel Iiie corrugations. If this film is allowed to accrlmulatc
designs, the wire-mesh mats are conveniently incor- falling, and re-entrainment occurs. Chevron s e p a r a t i n ~ over a large depth of plate it could grow to a thickness
porated in the same vessel as the reheater tube banks. which would result in re-entrainment of water by the
Steam is channelled along the lower side of the vessel sleam flow. Hence, the chevron plates must be either CHEVRON
o f a limited depth or the corrugations must be fitted SEPARATORS
(the left-hand side in the figure) and directed dia- REHEATED STEAM
gonally through three mesh trays in parallel. Water REHEdiER with water-collecting channels shielded from the steam
TUBENEST
Ilow. The design of the final drain-collecting device, at
the bottom of the vane, also requires detailed atten- FIG. 2.104 Cross-section of rwo-stage MSR with
lion to ensure that it does not induce re-entrainment. ellevion separators
A typical MSR design using chevron separators is
shown in Fig 2.104. After general steam distributioi~
within the vessel, the flow through the separators is structure is supported a n two integral tubular sup-
controlled by perforated plates located in front of ports which penetrate the shell and provide support for
tach packet of chevrons. the tube elements and integral framework. The tube
In order to avoid any problems from wet steam elements are therefore allowed to expand vertically from
erosion and off-load corrosion, components used in this tubular support near the base inside a sliding
tlle construction are normally stainless steel. Separator linkage arrangement. The tube elements are also posi-
plates, for example, may be in austenitic stainless steel tioned centrally within a support frame which locates
and the distribution plates in 13% chrome ferritic the elements inside the shell and ensures that the shell-
steel. Internal supports for these elements are designed side steam does not by-pass the tube elements. A full
l o avoid resonant vibration and lo allow for differ- diameter bolted joint is provided near the top of the
cntial thermal expansions. shell t o allow the upper dished end to be removed for
access t o the tube elements.
Each identical tube element contains a number of
13.4.2 Steam-to-steam reheaters straight externally-finned tubes welded into similar up-
per and lowei headers. Welding is done with an auto-
matic TIG welding system, using a two-pass technique
Vertical reheaters
followed by full NDT. The headers are rectangular in
Vertical reheaters have been developed in recent years section and trough-like in shape, the side opposite
by NEl-Parsons for Canadian machines and by Deutsche the tube sheet being in the form of a coverplate or
Babcock and Wilcox for machines in Europe, parti- lid. The covers are bolted t o the headers and a soft
cularly in Germany. metal gasket is incorporated between the cover and
A typical NEl-Parsons deam-to-steam reheater is the trough section to ensure a leak-tight seal.
Flc. 2103 Croro-seaion of an eariy single-stage MSR
shown in Fig 2.105. The shell consists of a large ver- The tubes in each element are arranged in a narrow
FIG. 2.102 Wire mesh separator with mesh seDararors tical cylinder with dished ends top and bottom. The rectangular pattern with the long span being perpen-

232 233
Titrhine uiant svstelns Chapter 2 \Met steam turbine plant

rather tiiaii the heal transfer coefiicico1 o f the exiendcil ii1:lles most bc Silted w'illi carc la ensure lhai no floor. Shell-side relief is normally accornlllodalcd oil
tube surface. ll;linage occurs to the lube fins on assembly. By ad- vcsiical schcaters by a coinbinatioii of burstillg dia-
On recent wet steanl machines, economic factoii .iiisiing the sPacill'2 01' these plates, the vibraiionai phiagins and pressure vali,cs i n the blot le],cat
dictate two stages of reheat. The exhaust steam from ~:ll:~~acteristics of the tube can be arranged to be lines between tiie re~,eate,.a,ld tl,c interceptor
the external separators is directed across the outsidc clcay o f damaging vibrations, w~hether rnccl~anicall~
o f tile tubes in a single pass in a manner which is very r18 Slow-induced.
close to pure crossflow. The reheating steam is supplied Oil-load detectioi~ o f tube leakage be deter. I I ~ ~ I separaror rehealers
~ ~ o I ' ~ z omoislure
t o the upper header of each tube eiement and condenses milied by isolatitlg each tube element and comparing The overail size of the MSR vessels incorporating wire
on the inside o f thc tube. The condensate is piped fro111 lllr internal 'settle-out' pressure with the prevailing mesh separators was originally governed by the Ilro-
the bottom header and passed to the feed train. The i;l~cll-sidepressure. vision of sufficient area of horizontal mesh. It was
heating steam supply t o the elements through which the l1 Canadian units, in the event of any tube leak- most convenient to dispose the vessels horizontally
separator exhaust steam first passes, is obtained from the particuiar tube element is isolated until it and position the heater elements above the mesh. The
iiEhTED
STEAM
a tapping o n the H P cylinder. The shell-side steam, then be replaced by a spare element at a convenient steam distribution system was beiow the mesb and the
INLETS passes through fiirthci elements, which derive their i!;ige: the leaking element tubes are then plugged. steam inlets were therefore positioned in the bottom
heating steam from the live steam pipework upstream 1 1 ) ~ elements are removed by taking off the shell of the vessel. The hot reheat connections were posi-
o f the H P stop valves. The healing elements impart a ~'r\'ei, cutting the tube-side stealn supply and drain tioned on the top the vessel.
small degree o f superheat t o the shell-side steam, whicli l>il)rs (jive or bled), and iifting out the tube element. With one vessel located each side of the L P cylinders
then enters the LP cylinders through the LP inter^ I l l c i.cplacetncnt o f a tube eiement is sitnpiy the re- at engine room floor level, the cold reheat pipework was
ceptor valves in a condition almost identicai to LI' rcrrc o f element removal. routed from the H P turbine exhaust to the bottom o f
inlet conditions in a fossil-fired plant. A tnrobienl wit11 vertical reheaters is tiiat the maxi- the MSR and the llot reheat pipework from top of
Occasionaily a smail percentage of inlet steam from !!Iliili height of the crane hook has to bc sufficient the vessel t o the ~p cylinders.
the separator exhaust is allowed to pass on either side, it1 tile heating elements out vertically. TO reduce With the adoption of inciined separators,
and also around the top and bottom, o f the tube hailk 1111: ;llnount of cutting during dismantling, the live it was no longer necessary to limit the stealn distl.i-
and finally exits with the superheated outlet steam. iitlii i'lcd-steam pipework normally enters the shell butio,, system to the lower section of vessel. A
This by-pass steam cools the reheater outer slleli and :Ir lhe side wall rather than through tile shell typical schematic of a two.stagc MSR is
minimiscs the vessel deformation which can be caused This pipework from the sheli wail to the ele- shown in Fig 2.106. he steam is introduced into $he
-u by the temperature rise in the sheli-side steam as i t
BLED
STEAM
LiVt
SIEANI
passes from one side of the vessel to the other.
DRllNS DRAWS On NEI-Parsons reheaters in Canadian machines,
all components, with the exception of the tube elemen
FIG.2.105 Vertical type relleater header-gaskets, are made from carbon steel. In orde
t o protect the heat transfci surfaces on the inside
and outside of the tubes from rusting during pro-
longed shutdown periods, heated air is blown througll
dicuiar t o the direction of the shell-side steam fiow. the reheater elements on the sheil side to keep tilc 'led on its own foundation from the basement and the separator eiements, TO op.
This results in the minimum shell diameter, and faci- ambient internal temperature above the dew poinl
litates element interchangeability and ease of nlanu- This prevents rust forming on the outside o f the tubes
facture, erection, leak detection and replacement o f and the shell internals. The tube bores are protected
L ~ VINLET
ESTEAM
elements, if necessary. during shutdown periods by nitrogen blanketing. Ex-
Steam condenses as it passes down the tubes and ternal erosion-corrosion of the tubes, tubeplates and HOT REHEAT

the vertical tube arrangement obviates problems o f vessel at full and part-load is minimised by limiting
slug-water flow that can occur with horizontal con- the venting and flow velocities. Wet steam erosion of
figurations. Complete drainage during shut down or thc tube bores is minimised by using low reheating
eiement isolation is also ensured by the vertical steam velocities o f the order of I m/s and a downward
arrangement. flow direction which results in a steady annular flow
The heat transfer coefficients are very different o n pattern.
the inside and the outside of the reheater tubes. On The tube length or support has to be arranged to
the inside, where the heating steam is condensing, the ensure that the natural frequency of the tube bundl
heat transfer coefficient is much higher than o n the is clear o f machine frequency, low harmonics of m
outside which is in contact with the nominally dry chine frequency, flow-induced Karman vortex sheddi~
steam at low pressure. Externally-finned tubing is frequencies and acoustic standing wave frequencie
therefore used to enhance the heat transfer capability Tube diameters are normally chosen t o ensure th
on the shell-side and hence reduce the total number the tube natural frequencies are clear of aeroelast
of tubes, reheater size and shell-side pressure loss, frequencies, but tube first-mode natural frequenci
compared with an unfinned tube arrangement. The have been found close t o acoustic standing wave f r
length and number of tubes and the fin profile are quencies. In a n attempt t o avoid this, horizontal su
chosen o n the basis of a cost optimisation. The critical oort olates adjacent t o and within the tube element ar
variabie in this cost optimisation procedure has been
found t o be the pressure drop across the reheater, FIG. 2.106 Typical horizontal two-stage rnoisluic separaiorrelleatci
Turbine plant sysrems Wer sreain .turbine plant

elation, i t is ncccssary la segregate llle incoining caul sidcs o l tiie ii~bcs. The relatively l o x iatc piiatc tubes, to balance the plessilic drop lliiougli
steain from tiic reheated steaol. A close-fitting slil-oiid translei between superheatcd sleanr and the tii1,c ti i llic vessel to perinit lubenes! replacement: thc incst to the extent tilat, wilir a slllall veot flow, llic
is theieforc often provided to guide the stcan) from the el.aIly dictates llic use o f extci,lally-finned tnhe!,. i i l ~ l hc a rare occu1,rencc and might not be titbe temperatiisc diffcreirtials are maintained at an
relieatel to the outlet connections. Where the hot shroud Early designs of MSR were based on p~ii,li ili the life o f the plant. Leaking lubes de- acceptable level and thermal st~.ainsare minimised.
is in close proximity to tile outel. shell, it lmay require predictions of the ircat transfer and prcssure d l rncleased lheating stearn flow woi~ldnormally Vent lines are normaliy ied to healers in tiie feed
a thernlal shield t o prevent local heating and distortion flo\$, across tubes. However, the condensation j i oiit of service by plugging. trains for thermodynamic recovery, but on start-up
o f the shell. T o cater for temperature differentials, which inside tile tubc produces a two-phase flow wli obes are suppoitcd by drilled plates spaced so and low-loads it is sometimes necessary to provide
could cause unacceptable distortion, the earlier shroud the time was not fully understood. The con ,ithe most cxtrcme conditions of operation a slightly enhanced vent flow. An additional line is
designs were divided into a number of panels held in were therefore simulated in tests which showcil I >noharmful vibrations. The distance between then provided which is usually routed to the condenser.
place by clamps, which permitted relative movement the flow was initially stratified and progressed lhv jpiiits is such as to limit any vibrationaliy- It is possible for conditions to arise which cause
without significant leakage. In a Swedish unit, a com- wave-flow and slug-flow to plug-flow a t the tube .tresses and the effect of the gas flow across a pressure rise in the H P turbine and consequently in
bination of pressure differential, thermal distortion and
discontinuity of shape was sufficient to cause a section
of shroud to collapse away from the clamps. The
section then vibrated in the steam flow and failed by
Eaiiy designs of reheater in the UK, using I
tubes in carbon steei, suffered extensively from e
of the inside of the tubes, particularly at the I
bends, and the impact of high velocity steanl
to acceptable levels.
llural frequency and mode shape of the tube,
ilcd in the nest, are caiculated to avoid the
nodes. It Is not possibie t o eliminate all forms
.
the MSR, these are:

A turbine trip from full-load, resulting in the entrained


steam between the stop vaives and the interceptor
valves settling at a pressure ievel between normal
fatigue. Shrouds are now designed t o avoid similar leaks in these tubes caused consequential darnaiic \sibration, as successively higher modes occur
failures.
Current designs of MSR lhave an outer shell welded
together from cylindrical plate sections and dished
adjacent tubes. Major retublng with erosion resisl
material was necessary in certain reheaters, w
strictions on internal steam flow and hence perf0
I frequency intervals and the actual frequency
icnced by factors such as alignment of the tube
plates and the amount of clearance in the . pressure and the H P cylinder inlet pressure.

Operating with H P feedheaters by-passed and MSR


ends, designed and constructed in accordance with
pressure vesscl codes, The vessels are generally mounted
o n two supports, one o f which is anchored to the
foundations. The other support is free to expand
Some rehcaters had to bc scrapped completely.
Some early American MSR designs used
nickel tubes but, at elevated operating temp
this material produced high levels of coppe
]plate holes, both of which are variabie over
.wtional life o f the unit. In order t o avoid
of the tubes in their support plates, which
tube failure in some MSR designs, it is es-
. reheating tubenests isolated.

Leaking tubes in a live steam reheater tubenest


allowing steam to by-pass the turbine stop valves.
longitudinally but is restrained from moving in a reactor feedwater. Since carbon steel tubes si that the plates maintain their alignment when Leakage across the turbine stop valves in excess
transverse direction by means of a longitudinal key. from crasion and had to be protected against rusl Ihenest is subjected to operational temperature of corresponding leakage through the LP turbine
MSR vessels are always provided with manholes during shutdown periods, 18/8 stainless steels \ valves.
for access and inspection, and penetrations through provided in some continental units. This optioi~ temperature difference between the cold and
the shell for connections to the tubenest headers are expensive, particularly when compared to carb i steam, as it flows across the hot tubes of the Closure of all six LP turbine interceptor valves, whilst
normally provided with devices to allow for relative and occasionally suffered from cracking caused , produces temperature differentials which are an HP turbine stop valve and governing valve remain
thermal expansion. The number of reheated steam which leaked out of the condenser. Seawater cou imes greater in the first tube row than in the open.
outlet connections from the vessel is governed by ex- carried around the feed circuit and since the reheat ube row at full-load, with even greater differ-
ternal layout considerations and the number of L P the only significant drying unit in a wet steam 11 part-load. By arranging the heating steam flow
turbines. sodium chloride was ultimately deposited in the reh hairpin tubenest such that one leg has a low The MSR is, therefore, fitted with a relief capacity
With precautions taken to avoid high velocity wet The reheater tubing in present machines is densation and the corresponding leg a high sufficient for the full reactor steam output. Relief
steam, especially at the steam inlet, mild steel is a 18% ferritic stainless steel. This has a greater tole possible t o achieve a reasonable balance in valve capacity is pl.ovided t o cater for a nominal
satisfactory material for the containing vessel and the both t o the deposition of salts and t o general cors condensed per tube. Even so, a sufficient number of burst tubes, with a setpoint above the
internal support frames. It is obviously desirable to and erosive conditions. Since tubeplates contin tial exists to induce the steam, which has not maximum normal operating pressure, and bursting
limit the need for erosion protection and therefore it be made from carbon steel, the tubeplate sur condensed by the inner hairpin, to flow via the diaphragms to cater for the total steam flow at a suit-
is necessary t o avoid high velocities within the sheli. normally clad with a layer of Inconel to fa section of the header into the lower leg of the able higher pressure.
Any areas of the shell and main support frame which weiding of the tubes t o the tubeplate. Both the t i hairpin. Obviously, whilst operating in such a
are exposed to wet steam erosion are always protected plate cladding process and tube welding are foilo ,I, the outer tubes are not adequately drained
by stainless steel. by full NDT procedures. 11ed and a section of tube is intermittently de-
An internal support provides a framework for weld- Present designs of reheater are sized using of heating steam. This section would then be 13.5 Steam supply and drains systems
ing the separator sub-assemblies and a support for transfer and pressure drop data obtained from I ltly cooled by the external steam until the The heating steam for the majority of modern re-
the tubenests and steam shroud. Longitudinal mem- o n existing units for both the internal and exte g steam flow is re-established. Such a cyclic heaters is bled from the H P turbine t o the first-stage
bers which add stiffness t o the frame often serve as surfaces of reheater tubes under operational conditi i~tionhas been shown t o be capable of causing reheat and supplied from the live steam pipework for
runners for rollers which assist in the insertion of These tests have enabled higher operating veloc ile failure o n MSR tubes. the second-stage reheat. Reheater steam temperature
tubenests into the frame. These rollers also allow the to be used without impairing the integrity of the arly designs, this mode of operation was avoided control is designed t o be completely automatic and
tubenests t o expand longitudinally during operation. wall. Higher velocities lead t o enhanced heat trans iting sufficient steam from the drain section of requires n o intervention from the operator. A typical
The costs of the separator and reheater are governed coefficients and consequently permit a more compac leader t o ensure a continuous flow through ali diagrammatic arrangement of the live and bled-steam
mainly by the reheater bundle, in other words by the and economic MSR design. lobes. T o vent such a flow external t o the reheater supply and drains system for a combined separator/
size o f the heating surface serving the heat exchange. Current reheater tube banks are based on hair uld result in large thermal losses, so the reheaters reheater is shown in Fig 2.107.
The residual water after the separator must be eva- tubes arranged in rectangular-shaped nests as in earl fitted with a vent element. This comprised a
porated before reheating. This requires additional designs. In earlier machines, the limited length of lob el of tubes, located prior t o the main tubenest, which
heating surfaces and both live and bled-steam re- available from the manufacturers resulted in multl iilensed the necessary flow of steam. The vent was 13.5.1 First-stage reheat
heating. ple-nest arrangements and central headers. Since tub ependently vented and drained. The bled-steam t o each reheater is conveniently sup-
T o determine the type and the size of the reheater manufacturers can now provide longer tubes, hea 'urrent designs incorporate the simpler solution of plied from a bleed-off (usually the first) from one of
heat-transfer surface, it is necessary to establish the can be placed a t the ends of the vessel, making m 11l-olling the distribution o f steam into the tubes. the flows of the H P turbine. Since the bled-steam is
heat transfer and pressure drop correlations for both tenance and withdrawal of tubenests more convenient table restrictions are placed at the inlet t o appro- wet, the supply lines usually incorporate some form
236
Turbine plant systems Chaptei ? Wet steam turbine plant

'1.0 prevent excessive 11


.' turbine kick-cod tempcra- Separated wales from each scpaiatoi vcssel, or from
tiiicr during lrrw-load operation when the hot ~.eheat each MSll shell, and from the cold reheat pipes is
t.li.iiill flow is low, tlie live steam reheat supply is drained by gravity into tlic separator drains tank.
~.'t)~iirolledby a valve which icgrilates the live steam flow Carnmoning of drains pipes before the drains tank is
iii:~:ol-dingto the temperature of the hat reheat stcam. not acceptable, since pressure differences between
l i t certain designs, this control valve does not open individual pipes and vessels can cause water to back-up
11i11il the machine has reached a particular load. At in the pipework. Water levels can become unstable and
fiill-load, tlie valve is fully open and could be subject oscillation or hunting can occur in the drains system
tci wear. A by-pass valve is therefore sometimes pro- leading to vibration and sotnetin~esfailure, particularly
vidcd so that the temperature control valve is not of the pipework supports. It is normal practice there-
iii use during full-load operation. At a hot reheat fore to provide an individual separator drains tank
tclriperalure slightly below the normal full load tcm- and drains control system for each vessel containing a
lrcrature the control valve closes as the by-pass valve Sevarator.
opens. A small warming connection may also be Horizontal drains tanks are often chosen for economy
plovided to enable the pipework to be pre-warmed but vertical tanks have the advantage of a constant
to reduce the degrce of thermal shock to the rcheatcr surface area and have greater hydraulic stability in
iil~il pipework when the temperature control valve level control. The layout of the drains pipcwork to the
,~I,C,,S. drains tanks should be chosen with care, particularly
In common with the bled-steam supply, isolating where loop seals are included. The lowcst point of
!'kiives are always included in the live steam pipework, the loop must be far enough below the floor of the
l i t i t non-return valves arc generally not fitted. vessel to permit free drainage during any tank transient
pressure rise. Any transition in the bore of the drains
pipework should also be well below the floor of the
13.5.3 Performance monitoring vessel to inhibit any tendency to flashing at this point
'The most satisfactory method of detecting tube leaks o f sudden pressure reduction. Drains tanks are nor-
ill steam-to-steam reheaters is by monitoring the live mally fitted with vent pipework, level indicators, high
ilnd bied-steam flow rates. Both live and bled-steam level switches and pressure indicators.
slipply lines to the reheaters are therefore usually fitted Water from the drains tanks may be discharged to
\\,ith flow measuring devices, such as orifice plates a heater in the feed train via a flashbox, or pumped
or pitot tubes. Tube leaks are identified by a sudden to the de-aerator, in which case the pump flow is
increase in the heating steam flow rate. Thermocouples regulated by a level controller on the drains tank. A
are sometimes fitted to tubenest headers to ensure recirculation valve is then necessary to satisfy the mini-
liiat start-up procedures produce acceptable thermal mum flow requirements of the pump and to guard
stresses; and thermocouples are also sometimes fitted against cavitation. Forward flow may be prevented
lo reheater tubes to confirm that the tubenest is not completely in the event of high level in the de-aerator
aiibject to unacceptable thermal cycling. by a motor-operated isolating valve in the pump
discharge line. In this case, drains are routed to the
condenser. Drains are also normally routed to the
WLVE I\ lSOLhiiNG VALVE CLOSED BY HlCiH WATER LEVEL SIGNAL
13.5.4 S y s t e m drains condenser during start-up to prevent contamination
IN ASSOCIATE0 HEATER 130th the live steani and blcd-steam supply lines must of the de-aerator inventory. Pump discharge lines are
VhiYt B NOAMALDRiiiNTO HEATER FLASHBOX bc adequately drained at all times. Drain lines usually always provided with isolating valves and non-return
VALVE C ALTEnNATlVt DRAlN TO CONDENSER include a dirt trap at the take-off tapping and some valves.
-
---
STEAM iiNE
ORltiN LINE
form of steam trap arrangement. Under normal con-
ilitions, water is drained away via the steam trap to a
CONTROL SiGNAl drain vessel. However, steam traps have a history of 13.5.6 Reheater drains
poor reliability and, in the case of the bled-steam sup- The location of the drains receivers, control valves
ply line, are often inadequate to cope with the water and the routing of the drain pipes, requires careful
FIG.2.107 Steam supply and drains system far a combined senaratoi/ietieaIer
flow at low-loads. Water traps are therefore always consideration to ensure stable and safe operation o f
provided with vaived by-passes, sized to pass the the system.
maximum possible flow under all oberating conditions. Condensate from each bled-steam tubenest header
of water separation device, close to the H P turbine: are rarely fitted with safety valves, but motor-operated is drained by gravity to a bled-steam reheater drains
to safeguard the H P turbine from any possible ingress isolating valves are always included which close if tank. One tank per vessel is the usual arrangement.
of large slugs of this water, non-return valves are the water in the reheater drains tank rises to the extra 13.5.5 Separator drains In the case o f multiple headers, as in NEl-Parsons
normally included. On the most recent machines, these high water level. 130th cyclone separators and MSR internal separators type vertical reheaters, drains pipes are not commoned
non-return valves are often power-assisted and close ale normally situated close to engine room floor level. but individual pipes lead the condensate from the
in the event of a turbine trip or a load rejection. 13.5.2 S e c o n d - s t a g e r e h e a t 'This provides sufficient height to accommodate the headers to the drains tank, thus avoiding the problems
They may also be triggered to close from a signal The live steam supply to the second-stage reheater drains tank, sufficient net positive suction head for a o f instability mentioned above. Similarly, drainage
initiated by an extra high water level in the associated tube banks is obtained direct from the main steam separator drains pump (if fitted) and a falling drain from from the tubenests in the MSR vessels are kept quite
reheater drains tank. Bled-steam lines to the reheater pipework immediately upstream of the H P stop valves. the drains tank to the condenser. separate and are not cross-connected.
1-urbins plant systeins Chaptr!! %

Conderisalc froin the drains ianks is normally routed 'The a i r a n g e m c n i and control of thc livc steam diiii,r
to a heater Slash vessei or drains cooler Sor tiie1.- is ver)' si~iiilar to the bled-steaai drains exccpl 11i;ii
inodynamic gain. If liowcvei the heater bank is aul of rile condensate i s finally r o i l l e d l o a ihealeu flash v c ~ . i l
scivice, either a three-way valve routes the drains to further along llre fccd traio.
rhc condenser Slashbox, or a motoiised valve in the
Iilie to the heaters closes and ail emergency drain
valve in the line to the condenser flashbox opens in
response to a high level signal from the level controller A P T E R 3
in the drains tank. This emergency drain valve also
14 References
opens in response to a high water level in rlie heaters. ill Heilbrone. F. S.: Lffeeis of noscd steslii and ~ a l e upo,,
i ii~i
All valves and drain pipework must be sired to pass
ovenpeed or lavge siealii luibiiies alter sitddell loss of io;$ii:
P r o c 1Meci1C. Volume 180. Pall 3J: 1965-66
Feedwater heating systems
the bled-steam drains at maximum turbine capacity.
I21 Kcailon, W. I.: Srealli Iltrbirie llleory and piactice: Pitman
Drains tanks are sized such that the time taken to fill
131 Nel~oil.W. (i. and Walennai?. A. \\'.: Advances i ~eomirci.
?
the volume bounded by tlie tankwalls, and the upper cia1 aeroplane 1i)~drauiicfluidr: SAE Camniiilce A6, Aerosjiarr Ililrodu~tio" 64.1 Length of U-tubes
and lower limits of the control band, will be several I'iuid Power and Control Tcclinologies. Uostoii: 1974
1 Feed system design 6.4.2 Tube siipport plates
times the control valve stroking time. 141 Urodie. J. K.: Ealrainmeiii studies Phi) ~heiis: Herio~-W;,li 6 5 Bled-steam inlet
Non-return valves are usually provided in the line Usiversiiy: 1969 I.' Introduction 6.6 Ti>cirnal design
1.2 Functional needs of the system 66.1 Desuperheafing section
t o the heater flashbox to prevent possible refluxing 1.3 System configuration 6.6.2 Condensino section
of water during transient opc~.ation, or backflow to 1.4 Component design parameters
the condenser flash vessel from the heaters in the 1.5 Compon~nflevels
1.6 Maintenance 01 system water content
event of valve malfunction. Since MSR vessels are 15 Additional references
situated at or near engine room floor level, sufficient
1.7
1.8
Protection against usc of contalninaled feedwater
Protection against ingress of waterlateam to
- , ~~~~ ~

Uergscxarrer. G.:Reii~ioicerlconcrete Soi~ndacioiisroi sican? tarbil~c. 6.9 Alternative designs of heater construction
height is available underneath tlie vessel to accommo- Elekt: ib,irir, Volt~nie59 pp 805-809: Nove#l~bei1960 turbine$
1.9 Summary 7 De-aerating feedheafers
date adequately-sized drain tanks and pi.ovide a falling 1:iiiI~eibcrl. W. A and Barncil, J. H.: Causes oS movcnlenf i8, 7.1 Introduction
drain to all possible destinations. The base o f a vertical reiniorcetl concrete turbo-blocks and dei,elopme~>rill turbo-bloc!. 7 HP feed svstem 7.2 TiieimaIIhydraulic design
reheater, however, may be low in the turbine hall design and coiirirudio81: P ~ OIhlecLE.
C VOI~IIII~ 181. Par, I No 22, 7.3 De-aeietor construction
and a positive static head may not be possible for all pp 589-614: 1966-67 8 LOW pressure heaters
2.3 system configuration
operating conditions. In this case, it might be necessary 1:iinl. I.J.: Plasl arpccir o f lurbine generator rouiidniiooc: Pror. 8.1 lntrodu~tion
2.4 HP heater drains system
IMechE, Volurile 181, Par, I No 22, pp 567-578: 1966-61 2.5 Pipewoik arrangement 8.2 Surface type low pressure heaters
to provide a pump which would have to be sited in the 8.3 Construction of iow pressure heaters
basement, or even in a pit, in order t o provide the itaupi. L. and Frobs1 P. H.: Civil engineering and vibratioa aspect, 3 De.aeratof System 8.4 Water header, tube bundle and sheli
or steam iuibinegeneiaioi foundations in Germany: Proc. IMechE. 8.4.1 Tube thickness
appropriate net positive suction head. Otherwise par- Volume 181. Par1 I No.22, pp 579-588: 1966-67 3.1 Introduction
3.2 De-aerator heater 8.4.2 Fiow srea thickness
8.4.3 Tubeplate
ticular drains might have to drive against an adverse
Piaefckc, R. 0.: Steel foundations for tile suppoi, o f high-speed 3.3 De-aerator storage tank
static head. snachinery: i'rac. IMecliE, Paper C7: 1983 3.4 De-aerator elevation 84.4 Wafer header wall thickness
3.5 Piotecfion systems 8.4.5 Wafer header branch thickness
3.6 Protection valves 84.6 Compensations for openings in the waterbox
,a 3 7 Plpework 8.4.7 Shell and dished end thickness
8.5 Heater tube lenglll and fube supports
i 3 8 Boller feed pump sucfton f~lters
85.1 Tube support plates
2 4 LOW
41
pleESUre feed system
Inilod~~ilon
8.6 Bled-steam inlets and drain outlets
8.7 Thermal design
42 Low pressure system configurat8on 8.8 External drain coolers
43 Plpework and valves 8.8.1 Thermallhydraulic design of a fiashing drain cooler
88.2 Thermallhydrsulic design 01 a water-to-water drain
5 D B S ~ S o~f Sfeedheafers Coder
6 Hlgh PIBJSUrB feedwafer heater* 8.9 Direct contact low pressure heaters
6 1 Functronal needs 9 EvaporafOrS and other means d water treatment
6.2 Con~trucfionof high pressure heaters 9.1 lnirodu~tion
6.3 Wafer header, tube bundle and rheii 9.2 Types of bied-steam evaporator
63.1 To find tube thickness 9.3 Sulface type evaporator
6.3.2 Area required for flaw through the tube bundie 9.4 Flash type evaporators
6.3.3 Tubeplafe thickness
6.3.4 Water header wall thickness 10 Future developments
6.3.5 Hesder branch thickness 10.1 HP feed system
6.3.6 Compensation for openings in the water header 10.2 Ds-aerator syslem
6.3.7 Shell and dished end thickness 10.3 LP feed system
6.4 Heater tube length and tube supports 11 References
Feedwater lieatirig s y s t e m s Introduction

Introduction 1:oi all slationi, tllc SVI' is 160 bar; thc ill ' I I' llcalci syslellis a,hicli weie 1iiL.n current!? route was pruvidcd for tlie B1:P'T enhaus1 to tlle coo..
llcgeoerativc fccdl~calinglhas long beco iccogilised as 565°C for coalfired hoilers and 538°C for oil 1 dcnsci, llie BI:I"I' wiild also be itin-up will1 llie alaiii
a means of improving turbine-generator plant effi- boilci-s. 'The cold rclieat pressure vai-ics b c l ~ v r i ~ ~ i concluded from the review, tllat r u b ~ ~ i asui-
r unit. 0'1 irrcreasc cycle efficiency, lhcalcr bleed poillts
ciency and the first practical installation was on a atid 44 bar. As all feed systems for these onil, I I P lheatei feed systems weie more cost on the BI:I37 are provided. However, more Illail onc
3 b1W set in a British gower slatioii at Rlaydoii Bul.ii cold reheat ( H P turbine exhaust) to stlpp lnd they have been used for all subsequent healer attached lo the BFPT can cause difficulties
near Newcastle-upon-'Tyne in 1916. tlle final licater, the final feed tenipeiatiire ( in the fccdlieaters downstreani of the heaters from the
From this modest beginning the modern fcedheating only vary by a small amount doc t o the c f i il size increases, so does the power needed BFPT. The manner in which the BFPT bas been
systeni has evolved, a typical feed system consisting of small variations in cold reheat pressure and I llle boiler feed pump (BFP), which is about integrated into the various feed systems is show11 in
sin to eight heat exchangers, each bleeding steam from ininal temperature difference (TTD) o f the fin;il I 01 main unit output. Multiple electrically- Figs 3.1 t o 3.6.
the appropriate turbine cylinder. heater. 1ll;l's could have been used but a more cost Cooling of the generator by condensate is not
T h e economic justification for the use of a parti- Because of the economics of the advanccd I,C solution at the time was to provide a tur- employed for the latest units. The complex and costly
cular configuration of feedheaters is given in Chaptcr cooled reactor (AGR) cycle, a lower final feed Iiiving a full-duty feed pump. From Figs 3.1 arrangements needed to ensure maintenance o f prime
i of this volume, in which it is explained how the perature o f about 156°C was specified (see Chal~t ii is seen that each system uses a back pres- and freedom from boiling o f stagnant condensate in
theory of regenerative feedheating is combined with which has resulted in a feed system having thi. ltithine as the BFP drive. Steam is taken from generator coolers on cessation of condensate system
the economic information the purchaser makes avail- aerator as the final heater. I l l cnlraust, expanded through the turbine and flaw was the reesan why a simple cooling package,
able to the manufacturers to determine the most Thc relevant cycle details for the feed system I to the main turbit~eor t o a heater. A live with indirect coolers using condenser cooling water
appropriate number and disposition of feed stages. pressurised water reactor (PWK) are also shoi\il ru,ply from the main boiler is provided on (CW), was developed and is now used. Thc loss in
When the ideal cycle has been evolved, it is tho] used Fig 3.6. ation o f boiler feed pump turbines efficiency is accepted in return for increased opera-
as a basis for tlie determination of a practical design. The steam caaditions for the 660 MW PM'I' to enable the turbine to drive the feed pump tional integrity and simplification, with consequent
The economic need to replicate proven turbine and 67 bar, 0.25% wet, result in the stop valve flow I, dl conditions of unit load. As an alternative reduced maintenance costs for the condensate system.
feed system components, whenever practical, places approximately twice that of a convention
restraints o n the manufacturer. Usually these are o f a unit and, in consequeiice, all flow c o m ~ o n e n t sini
minor nature and will only changc the ideal blccd be approximately 1.5 times tlicir normal size I
point pressures by a few tenths of a bar. Thc minor coinmodate thc doubled flow. The I'WR feed
loss in efficiency is accepted in return for the use o f is also more complicated than conventional f
proven plant and the lower cost resulting from the fired units as provision has to be made to a
replication of existing designs. reheater a n d separator drains into the feed system
The main parameters for the feedheating systems all conditions of operation, as shown in Fig 3.6.
of a range of typical modern 500 and 660 MW units Table 3.1 shows that the latest stations, such
are shown in Table 3.1. T h c corresponding heater Littlebrook D and Heysham 2 , are provided witli
arrangements are shown o n Figs 3.1 to 3.6. bular surface type heaters t o the exclusion o f
The turbine/boiler main cycle parameters of stop 'direct contact' (DC) heaters (i.e., feedwater and h
valve pressure (SVP) and stop valve temperature (SVT) steam in direct contact within the heater shell).
have been standardised for all modern fossil-fired 500 changc in design philosophy was the result of a
and 660 MW units. view, in the early 1970s, of the cost effectiveness

-
Sl01, Final Number of Tyne o f Fig ref
Sil" valve feed stages 1.P
pressure lenip heater
(bar) (OC)

Oil DC
Grain Oil DC
Oil Surface
Drax
Coal Surface
Heysham 2 660 Nuclear 159.6 538 45.2 156.4 0 4 Surface 3.5
Projected
PWR unils 660 Nuelear 66.77 + 5.86 226.7 3 4 Surface 3.6

De-aeralor not iticluded in number given


+ 0.25% wet a1 stop valve
Feedwater heating systems Chai
.... Introduction
Feedwater heating systems Chaptai :I
Feedwater heating systems

1 F e e d system d e s i g n 'y,e al>aucioiiciio~isare llie principal ainis of feed iy!,lciii


'lesigii: lhow they have beeti achievcd b y llre s y s i r l l ~ ' .
innailed in rnodeiil CF.GI5 powcr statioiis is dewii1,viI
in the following seclions.
1.1 I n t r o d u c t i o n
'Thc feedheating systciii associated with a turbine pro-
vides tile means by which the steam condensed in tlic
main condenser is fed lo the boiler, It must also heat
1.3 S y s t e m c o n f i g u r a t i o n
the feedwater by use of a series o f heal exchangers as The riiunbcr of ieediieaters is determined by the applic!~.
demanded by cycle dcsign. T o provide both these ser- tion of the relevanl economic factors, as explained i l l
vices requires a complex arrangement of heat exchangers Chapter 1. However, the theoretical bleed point pits.
and pumps, with hundreds of valves interconnected by surcs are seldom obtainable because of constrainls i l l
many kilometres of pipework. blading design. Thc actual points used are determinetl
Such a network of valves, pipes and heat exchangers by what is possible with current designs of blades aild,
1laS many possible flow paths. The determination o f flow ill some cases, by standard cylinder modules. On sill
paths and eliminatior~of unwanted routes is critical for modern large reheat units, final feed temperatore i r
the design of a successful system. In this respect, tlie determined by cold reheat pressure as in all prcirill
fossil-fired plant the ultimate H P heaters are fed frilin
system design is analogous to electrical circuit design.
The configurations which have beelr developed ovcs the HP cylinder exhaust (i.e., at cold reheat pressoic).
the last fifteen years to mcet the functional needs of feed A typical tubular surface type L P and H P feed systrnl
system design in the most cost effective manner are is shown in Fig 3.7.
described in this section. 1,) this system, the Condensate formed in tlie condeiisi'~
is pumped by the condenser extraction pump thro~lg!~
the gland steam condenser (GSC) and the L P healcli
to the high level de-acralor. The elevated positioii 01
the de-aerator provides the net positive suction lhe;id
1.2 F u n c t i o n a l needs o f t h e s y s t e m (NPSH) needs of the BFPs. In this context, the NPSII
T o play its part in the boiier/tuibine-generator cycle, needs of the BFP are defined as tlie head equivalcol to
the feedheating system has to perform the following the pressure necessary, over and above the temperat11
functions: dependent saturation pressure at the inlet to the pulnp,
to prevent the feedwater from flashing into steam witlii
Provide the required amount o f feedwater t o the the pump. The capacity of
boiler at a temperature dictated by cycle design. to meet any flucluations i
pumps draw from the de-aerator and discharge throupl~
Maintain a stable suction regime for the boiler feed
the feed regulating valves and thc H F heaters lo tllc
pumps.
boiler.
An alternative system with DC L P beaters and tubiiizil
* Contain a buffer store for water to allow for a short
surface H P heaters is illustrated in Fig 3.8. 'The coli.
term mismatch between boiler demand and available
densate is extiacted fiom the condenser and pumpcil
feedwater.
through the GSC and the generator coolers up to t l
first LP DC heater. The condensate cascades from 1.PI
In the longer term, t o keep the water content con-
stant. t o LP3 DC heater via LP2. A DC heater extractio\
pump, pumps the water from LP3 heater up t o the hi
Supply water t o the boiler with a n acceptable oxygen level de-aerator. The BFP draws from the de-aerator 1.
content. and discharges to the boiler via the feed regulating val
and the H P heaters.
8 Automatically cut off the supply of contaminated
feedwater to the de-aerator, and hence to the boiler,
in the event of ingress of chlorides due to inleakage
o f the condenser cooling water o r chemicals fiom the I .4 Component design p a r a m e t e r s
polishing plant. T o determine the physical sizes of the various col
ponents used in the feed system the flows, pressures and
In the event of a turbine trip or sudden reduction of temperatures must be known. These are provided by t l l C
unit load, the stored energy within the feed system turbine manufacturer in the form of a series of hcsl
must not overspeed the turbine-generator. balances which cover the whole o f the range of expected
cycle operation. As the de
Be so engineered as to protect the turbine from may be other than consta
possible reflux of water or water/steam mixture from conditions, it is i m ~ o r t a n tthat the whole spectrum a
the feed system under all conditions of operation.
IFeedwatei heating systems Feed system design

component is designed. Pronl the heat bal-


llii: heater drains can cascade by gravity to the condenser,
most appropriate design conditioiis for each
le as denicted in Rr 3.11.
system are determined, and thc value and Gravity drainage allows opeialion at low unit load and
S special provisions to maintain unit output unit start-up without alternative drainage arrangements,
bnormal conditions is evaluated. Tlie physical
I of the individual components is discussed in
". .
"sine ournus or snecial ooeratiollal nrocedures.
On those stations which use direct contact LP heaters,
in Section 5 of this chapter. the method of fixing the heights of the heaters is more
complex. A typical DC heater level diagram is shown
in Fig 3.12.
The elevation between two adjacent DC heaters is
Component levels arranged to accommodate a column of condensate which
eration must also be given to the elevations at forms a seal between adjacent heaters. The seal is
the various feed system components are placed. provided in the form of a loop. The condensate column
lative elevations are of prime importance as they counter balances heater differential steam pressures,
ce the ability of components to meel the func- pipework and waterbox/spray losses.
41 needs of the system. The levels at which the various The height of the condensate column at full-load is
ponents are installed for a feed system using sur- about half the vertical separation between heaters. Thc
type heaters are shown in Fig 3.9. loop seal must be of sufficient depth to withstand the
liking the L P turbine horizontal centre line as the most severe turbine load changes envisaged; for if it
n i , the vertical height of the condenser and its were ruptured by a temporary reversal o f condensate
sition piece, between condenser and turbine, com- flow, two turbine stages would become directly connected
a with the NPSH needs of the condensate ex- and there would be the possibility of steam and water
on pump, determine the basement depth needed being transferred to the lower stage.
,\, the machine. The water level in the condenser Further information on the detailed dynamic be-
well is fixed by the individual condenser design. liaviour of DC feed systems is to be found in the paper
inling a transverse condenser for each turbine LP by Dartnell [I] and the hydrodynamic aspects are
~nder,the water level is set at a convenient height examined by Kubie, Rowe and Jones 121.
the condenser bottom. As the traditional split- The height of the de-aerator relative to the boiler feed
g design of extraction pump usually stands on the pump is important as this provides the static head on
lent floor, the basement depth has to be set to the BFP suction to satisfy its NPSH needs under all
vide the head of condensate needed to satisfy the conditions of operation. Tlie other considerations which
traction pumps NPSH. However, current practice can influence de-aerator tank height are discussed in
lo use a vertical multistage condensate extraction detail in Section 3 of this c h a ~ t e r .
11npo f the 'caisson' type, whicli is sunk into a local
I in the basement floor. Use of this pump design
~ w the s basement floor to be set just below condenser
lorn-plate level as the pump impellers can be placed 1.6 Maintenance of system water content
below floor level as needed. The principles in- The de-aerator tank provides a reservoir o f water on
d are illustrated in Fig 3.10. It is evident that the which the feed pump can draw should there be a
f a caisson type of extraction pump reduces the mismatch between the feed requirements of the boiler
ent depth and thereby reduces station cost. A and the condensate flowing into the de-aerator tank.
d description of the various types of extraction There is typically 7-10 minutes' worth of constant
smps used in CEGB power stations is given in maximum rating (CMR) feed waterflow stored in the
tank. To allow for normal gains and losses to the
n the latest stations with all surface-type heaters de-aerator tank content, insurge and outsurge systems
ding the de-aerator), a horizontal heater attitude are ~ r o v i d e dto maintain the tank content as near to a
opted as opposed to the traditional vertical posi- constant value as is operationally necessary. As illustrated
allows the heaters to be placed below the in Fig 3.13, the insurae and outsurge connections to
)!torn of the turbine cylinders but above the con- and from the reserve feedwater tanks-(RFTS) are made
nser water level. The heater levels are set with suffi- to the L P feed system to allow adjustment of the
cicnt static head for them to cascade by gravity from total cycle water content. During normal operation,
Ihc highest pressure H P heater to the lowest pressure, the large content of the tank smooths out any sudden
lund then to the condenser. Even when set at these levels, small changes in demand and so allows the insurge/
Ily using horizontal heaters it is possible to arrange the outsurge valves to respond in a controlled manner to
bled-steam pipework to have a continuous slope from restore the tank level to normal.
llte bleed point on the turbine down to the heater. The I n the event of a low level in the de-aerator tank, the
hnnie arrangement is also possible with horizontal L P insurge group feeds into the condenser from where
hcaters. This has the important advantage that the it is pumped forward to the de-aerator tank by the
bled-steam lines can drain towards the heaters and the condensate extraction pumps. This continues until the
253
IZeedwaler healing systems C i l a ~ l ~3 ? ~ Fuel system) desigii

I:IG 3.10 Delcrminaiion of basement dcplli


(a) uircancc fio#?iceiiireiine of LP (urbine lo bouoir of caring - deiern~ined by ~niai>iifacfaierto aiiow room for casing, etc.
(b) Depth of condei?se~>neck - deie~milledby tile ,need lo uniforrniy distribute steaiu from rile LP fi8rbi~ieexhaust l o llle
iubepiate ends of the condenrei. Angle of narc is fixed lo give mir~iinuixilheig1,i conducive witti unifornl $lean, distribution.
(c) TI~~CIICSId e ~ l l iib dcsigi>cd i o B C ~ ~ ~ Coplin\im
YE il~ermalpcrfoimacice by tile tubenest colluniensuiate \uith tlie distance
beliveen 1.1' cyliiiders.
Id) Sufficielil space must exist a, the boiionl of the tubenest lo allow slenm access lo ihc bollosn lubes.

water level in the tank is restored to its normal work- caused to turbines by the ingress of water or a water/
ing level. If the dc-aerator tank level is higher than the steam mixture from the feed system have been reported
setpoint, the outsurge valve is opened and the excess [3,4,51.
- from the svstem to the RFTs until
water is dischaired There are scvcral potential sources of water within
normal working level is restorcd. The method by which the feed system which can flow or be induced into the
lilese systems are integrated into the L P feed system is turbine. The potential sources are as follows:
iiescribed in Section 4 of this chapter (a) High water level in an H P or L P feedheater. The
high water level could be caused by a tube leak o i
failure of the drainage arrangements.
1.7 Protection against use of contaminated (b) High water lcvel in a de-aerator. If there is a
feedwater mismatch between inflow and outflow the vessei
Siiould there be an inleakage of cooling water into can flood.
the condenser, the feedwater to the boiler could be (c) Undrained bled-steam lines. When the bled-steam
contaminated. Contamination of feedwater can also is wet, tlie water in the steam is deposited on the
result from the inadvertent release of chemicals from a pipework walls or is separated when a valve or
polishing plant. bend is encountered. Condensate is also formed
Modern boilers can sustain severe damage from on start-up, while the lines are being warmed to
contaminated feedwater. T o prevent feedwater of an operating temperatures.
unsuitable quality beinp fed to the de-aerator storare
tank and f'om there to
the boilers, or outsurged t o
In the case of items (a) and (b), if the rising level is
the reserve feedwater tanks, protection valves which
are tripped shut on high conductivity levels are placed allowed to continue unchecked, then it could flood
upstream of the outsurge connection and downstream into the bled-steam line and back to the turbine.
of the polishing plant (if provided), as illustrated in With regard to item (c), if there is continual fall from
Fig 3.14. The hardware and detail design is discussed the points where the water is accumulating towards
in Section 4 of this chapter. the extraction point on the turbine, it will most cer-
tainly flow against tlie steam flow towards the turbine.
The other means bv which water o r a water/steam
mlxture can be induced into the turbine is by a pres-
against ingress of water/steam sure reversal between the feed heaters and the turblne
FIG.3.9 Piclorial iepresenlation of the relalive levels of heaters and feed pumps for a po>vei station using horimnfal to turbines bleed ooints. A oressure reversal is caused bv a unit t r i ~
HF and L P tubular surface type feedheaters
Many well documented instances of damage being or a sudden load reduction.
254
Feedwater lheating systems

"aL"e8 A,#oPeN#%
SPI1INTCLOS,MG

-- "AL"clo"AINT*IY
~ C O W ~ A W , ~ " ~ . ~ ~
LlYlilNCONDiNSliiB

,
, f
~~Cm~~~, ,
To9IULO(ooPrNT#m

nc. 3.14 Devices installed ar nrotection against the use of caniarninalcd feedwater
~*~S"UlilYALI1.

~-
~-

Ir1SULGI"ALYE
((1) A non-return valve is placed in the bled-steam line cuits to close the protection valves.
as close to the turbine bleed point as practicable.
For the de-aerator and H P heaters, these are In some instances the pumps which discharge to
a particular heater are tripped.
power-assisted non-return valves. For the LP heater
bleed points, free-acting valves are normally pro- (f) All bled-steam lines have an adequate fall towards
vided. On very low pressure heaters, the omission a drainage point. Each drainage point is capable
of the non-return valve is permissible if the con- of draining by gravity t o the drain receiver vessel,
FIG. 3.13 Typical ilisurge and outsurge system ditions given in (g) have been satisfied. which is at condenser vacuum. Any pockets of
(b) Power-operated bled-steam isolating valves are water which can be formed by the closure of valves
provided on each line between the turbine and a have drains,
return valve, the bled-steam isolating valve is also Flow in both normal and reverse direction must heater, as close to the heater as is practicable. Again,
arranged to be shut on unit trip. (g) In the case of very low pressure heaters such as
be considered and, where provision to prevent flow on very low pressure heaters the isolating valves turbine moisture extraction condensers (which ex-
Reverse steam flow can also carry quantities of in one direction is provided, care must be taken to can be oinitted provided the conditions given in (g) tract a steam/water mixture before the last blade
water from heaters and undrained low points in the ensure that there are no 'sneak' paths to bypass thc have been satisfied.
bled-steam lines into the turbine and cause damage, in the LP turbine), the pressure drop caused by
protection. It is evident that the protection system the isolating and non-return valves as specified
particularly to the large LP turbine blades. These must contain flooding and also prevent back flow of (c) Feed or condensate isolating valves are provided,
'back flows'can induce cooler steam into hot cylinders, where appropriate, to shut off the supply of water in (a) and (b) may be unacceptable so, instead,
steam. duplicate unvalved drains (which can drain the
with the consequent risk of thermal distortion. The following provisions (illustrated in Fig 3.15) to a heater or group of heaters.
heater by gravity alone) are provided between the
This is an example of how a system must be have been made on all 500 and 660 MW units withi,, (d) Duplicate level sensing devices are provided on heater and the condenser. The feedwater flow to
designed to allow for all conditions of operation. the CEGB to prevent these possibilities: each heater, either of which will actuate trip cir- the heater is also isolated in the event of a high
UP feed syslenl

FIO.3.16 Diaillaee airanaemenrs for very low oresrure l>eaters without valves in bled-seam lines

b%, these principles are expressed in terms of detailed 2.2 System parameters
stem design, the feed system description has been The final feed temperature (FFT) out of the ultimate
,lit into three sections, viz: HP heater is fixed within a few degrees by the bleed
pressure and steam temperature available to the heater.
HP feed system. On all current 660 and 500 MW units, the bleed point
is the HP exhaust or 'cold reheat' pressure.
De-aerator system and associated plant. The feed temperature out of a heater is conditional
on several factors. First, a bled-steam pipework tem-
LP feed system. perature loss, usually l.l°C, which is subtracted from
the saturation temperature equivalent of the bleed
FIO.3.15 A typical feedheating plant - rhowing proteetion eauipment point pressure. The resultant temperature is the sat-
uration temperature equivalent to the pressure of the
HP feed system steam entering the heater shell. The heater thermal
performance and hence its heat transfer surface is
water level in the heater. The protection provided of protection relay and associated tripping circuils determined by the values of the temperature terminal
is illustrated in Fig 3.16. are described in Volume F, which deals with control differences (TTDs) on the steam and drain sides.
and instrumentation. 2.1 Introduction The steam TTD is defined as the temperature dif-
The HP feed system is defined as the group of heaters ference between the saturated steam temperature at
Recause of the short tlme scale in whlch the com-
~
and associated equipment whlch is situated in the feed entry to the heater shell and the feed water leaving the
mencement of water feed back to the turbine can pipework between the boiler feed pump (BFP) dis- heater. The drain TTD is the temperature difference
occur, all protection measures are automatic and the 1.9 Summary charge and the boiler. Their function is to accept water between the feedwater entering the heater and the
~-~each tvne The ~revious sections give an outline of the maill from the boiler feed pumps and raise the feedwater drains leaving the heater. To achieve optimum HP
hmrlwnre nrnviaiona
r.......... for , of heater is detailed
-~~~~~
~
r

in the appropriate section of this chapter. The types principles for overall feed system design: to explain temperature to the final feed temperature heater performance, it is usually necessary to partition
B
~- ....

Feedwater heating systems IHP feed system


-
Considering the functions of Llie feedwater isolating
lii:;~dess are subjected, tliey are placed dowo- \,aivcs under naimai conditions of operation, water
01' the feed regulating valves. As thew arc no flows from the boiler feed pumps through the heaters
is fully explained in Section 6 of this chapter. surface. i,alves between the HP heaters and the boiler lo the boiler. The by-pass is in the closed position, as
By applying tile line temperature drops to all NP lhcaters in this position, the maximum pressure the spiing-loaded valve is set such that it does no1
heater bled-steam extraction pressures and the steam commence to open until a heatcr bank is isolated on
TTDs, the feed temperature out of each o f the H P the water side. Assuming that the feed flow is to be
heaters is determined. Once the temperatures out of 2.3 systemconfjguratjon proportioned so that 60% flows through the remain-
which results in a typical 50% heater water ing active bank and 40% through the by-pass, the
ell thickness of about I20 mm and a typical redistribution for a typical pair of H P heaters is
c thickness of 350 mm. shown in Fig 3.20. Representative friction losses for
each heater are used to d ~ m o n s t r a t ehow the head
n drilling the holes through the tubeplatc. loss across the spring-loaded by-pass valve is deter-
mined. Sllould the pressure loss across the by-pass
valve be larger than needed, the flow through the
active bank will increase to balance the pressure loss,
which leads t o excessive steam flows. The larger steam
flows could lead t o damage of the external tube sur-
face from greater than design steam velocities within
the heater. The topic of steam-flow-induced damage
to lheater tubes is discussed in Section 6.3 of this
ilcd by reference to Spence, Ryall and Mc- chapter. There is also the possibility of erosion damage
[GI. T o date, even using the gun drilling to the internal surface o f the tubes from high velocity
steam T T D is larger than that of the ultimate heater diameter, the feed flow is divided between two 1 , tubeplate thickness bas been limited to about feedwater due t o the excesslvc flow through the active
which has more superheat in the bled-steam. banks of heaters. bank.
The spring-loaded by-pass system is the simplest
by-pass system in current use; but in the past, diffi-
culties in setting and maintenance of the by-pass
ssuming a typical feed system, where each line valves led t o the use of alternative designs of by-pass
system. Systems using motorised parallel slide valves
9 ~ BARA8S for both H P heater isolation and by-pass have been
7 " TcuPeRAT"me
~ ST"RAT,ON ,EuPEnAT"*E
provided. This requires a complicated control sequence
a 8. s~rosrinuriNe~i~P~nXumiDmoP to be provided, using many electrical relays and valve
$Ti0 " ITI*YlrUPE"A."ilTinhlN*LOIIIR~NCE
OTTO. L8,i i"lNCL
L)IIINII*~e~~,"illi"UN*0 limit switches. A typical isolation sequence would be:

n accept both of these conditions, there is Open by-pass valve


uent loss in cycle efficiency for the lower
When by-pass valve is fully open, allow sequence
to start closing the isolating valves. (A system which
allows by-pass and heater isolating valves to act in
antiphase has also been used.)

Close isolating valves

Opening the isolating valves is the reverse of the


*..>UATHEA,ER
,as* - ,> .,n<,<
11 -1132. i, "ZIilC w
P . <,.e5AT"s&,Es closing sequence:

Open Isolating valves.

When isolating valves are fully open, allow sequence


t o start closing the by-pass valve.

Shut by-pass valve.

e bled-steam isolating valves close o n all heaters In the event of sequence malfunction, it is possible to
have both isolating and by-pass valves shut a t the
~ ~

same time. T o allow an alternative path t o the boiler,


c feedwater isolating valves for the bank are an emergency by-pass spring-loaded valve is sometimes
FIO. 3.17 Application of temperature terminal differences to heaters to find the temperature of feedwater and drains provided to act if all normal routes t o the boiler are
262
Feedwater heating systems
-

"lGIIW"TERLEYELTR,P
HIOHWATLIIICVEL ALARM

N O W L L WORKINCIIEVEL

- IROMFEEDPUMP

1 BLEDSTEAMNONREIUI~NVAIVEHP"IISPRINGASS~ST~DCLOSINC.I
2 B L L D ~ E l M N O N R E i U i l N Y A V E H P W SPRNGbSSiSTEOCLOStNCi]
3 BLLO~EAMISOLATINC-VALVEnnA(M&noPmATaa,
1 BLEDSTEA~ISOlA-IIN(.V*IV~~P~lMOPilROPERmEo
6.
I BhNYNLEIIELDWATERISOLAT<MOVhLYE
BANKNLLTIECOWA~ERISOWT<NOV~LVE~IPN~VALVE MO/OROPER~~~~)
MOTOIIoPEbATLD
I WNKOUTLEIFEBDWAICR1SOLhitNCiVALVE(MOIIIROPEkATECI
8 SPRINGLOADEDBIPbSSVALVES

Tic;. 3.19 i l i e A bank of heaters at Drax Co$npleiion powcr slaliorl


18) l h c even1 of a liish water level i n either lhealer being delecfed by the duplicated sensing devices (float switches), air i r
ii.lr;lsed f i o m tlie non-return valves I , 2 and the rpiings asrirl valve ciosure. Feedwater and bled-itearn isolnting valves, 3, 4,
>, 7 C I O Sand ~ water flows forward lo llie boiler via the by-pass valves 8. Tile lieaters are lhus isolated on the bled-steam and
feedwater rides and tlie turbine is proreeled against reflux of water from the HP hearers.

11 118 the spring-loaded by-pass valves. rate of flooding, the time for the water to rise from
Another principle in current use is to utilise the the normal working level (NWL) to the bottom of
n the high pressure feedwater to close the the bled-steam connection is about 8 s. T o provide a
olating valves. The use of feedwater energy margin, a factor of 2 is used to allow for the valve
a1 When fop healer bypassed Ieedramr
temperelure to mils, -mvc bl One ban@bypa$reddue
IOfBYIlon lop hsafer
in bank-
€0 x2517 + 40 x 185.4 asons why medium-actuated valves were con- meet these needs, valves with a closure time of about
= 2,5ec
1w : reliability and speed of actuation. 4 s are required; however, the flooding time of vertical
Pic. 3.18 Configuration! single
lor-operated parallel slide valves o f the size HP heaters can be extended by making the steam
double hanks o f HP heaters
ircd for HP heater isolation duty have a mini- pipework loop vertically to a suitable level before
265
Feedwater heating s y s t e m s

~pioduccwhatevel- closing force is nceded to cloic


val\,e as swifliy as lhe sysiem hydraulics will ;illin
However, lhe svslenr is comniicared and costiv. iii~il

The bled-stcam lines to the 11earei.s are isalaivil


motoiised parallel slide valves. T h e power-assisic~llit
r~tu1.11valves are given the signal to close but u'iii
main open until the closing spring can overconic
reducing steam flow tending to keep the valvc opc
When the heater bank is isolated o n the steacii i
feedwater sides, small heater shell drains are opcrit
which discharge to the condenser. Due to the
of the hearer vents, assisted by the shell drains,
pressurc in heaters and the associated steam and drs
pipework within the isolation valves will fall to
denser vacuum.
The duplicate water level sensing devices \ ~ I I
initiate a bank trip due to a H W L are float switi:
manufactured by Mobrey t o meet the plant man
factul-ers' and CEGB needs (see Fig 3.23). Also ilht
trated arc the methods used for testing the duplictt
float switches with the beaters in operation.
The overall electrical control scheme is descsii
in Volume F. This gives full details of the duplicii
electrical supplies from the 110 V DC system wl,
powers the duplicate high integrity master tripp
relays. The master tripping relays initiate all protect
valve closures except for the autonomous action o
bled-steam non-return valve due t o a pressure revc
In the event of a turbine trip, a separate signal
the master tripping relays which shut all the prote
valves o n both banks

FIG.3.22 Dei$,rance medium-acluated valve. 2.4 HP heater drains system


ouilec valve shown The combined H P heater drains should be disch
U'heii feedwaler ir reieased froiil thc tinderside of
fiie piston. the fuii feed pressure causer the piston t o the de-aerator under all possible conditions
10 move down l o close ti,? valve. As tile roindle movcr simplest method to achieve this is to use the pr
dawn, tiie flow is restricted by the increasing sire of
,he tapered portion of tile spindle eilreiing the cylinder differential between the lowest pressure HP heat
iinei exit poi$ which is concentric with the spindle. This and t h e de-aerator t o overcome the static head an
progressively siows the valve head as il appioaelies the friction between the H P heaters and the de-aerat
seat, 50 allowing swift closure without seat impact damage
This feaiure also helps prevent hydraulic shock caused by tank.
swift valve ciosure. Figure 3.24 illustrates a typical drains system, show
FIG.3.23 Mobiey float switches and 011-ioad test facilities for heaters
ing the control valves and relative levels of equipme,
A system with the HP heaters in a horizontal attitu
is shown. As the unit load decreases, the p r e s s
(a) Mobiey float swilcli
The rising water ievel lifts the noaf i and causer ihc
permanent magnet 2 la repel the other pcrrnanenf magnet 3
. .
CLeck ILat test lamps indicate that float switch
actuates correcliy
Open valve o
from Figs 3.21 a n d 3.22 are the provision for the
system t o fail safe (i.e., t o isolate the feedwater side
differential between the H P heater and the de-aerator
decreases to a point where there is insufficient pr
on the srvitdl-actuating mechanism. The repulrion force
moves magnet 3 in the direetotl of the arrow causing the
switcli-aetjatian rods 4 to open and close the contacts. The .
Cheek that rest lamps indicate that water level is now
belo\%,trip level
Switch C O I U ~ and
~ S iepea~procedure

.
of the heaters), a n d the slowing down of the closing sure head t o raise the drains t o the de-aerator stora contacts are houred in 5 and 6 in the terminal block. The (c) Mobrey float switch arrangement using condensation
stroke over the last few millimetres to ensure that tank. The drains are then diverted t o the condens switch assembly is mounted in a waterproof housing 9 method. To on-load-tesc column 3:
n o hydraulic shock can occur due to sudden valve
closure. As the feedwater isolating valves have a
T h e converse applies o n increasing unit load. In this in
stance, the level in the heater is used t o determin
which b attached to the "on-magnetic siainless steel
diaphragm nange 7. The whole assembly is ciamped to the
standpipe or flosf switch chanlber by the back flange 8. . Switch ~olumn3 to IICSL' state
Ciose valve g
Wait untii the rcrt lamps indicate that float switch
protective function, high integrity is important. T h e
use of the feedwater as a medium to close these valves,
ensures that a pressure source to actuate the valves
is always available and the actuator can be made t o
t h e destination of t h e drain water. A rising water level
in No. 6 heater opens the control valve to the No. 5
heater flashbox or t o the de-aerator storage tank. Th
destination chosen is under the manual control o
(b) Mobrw float switch arrangement using vaeuim to

. .
lift the water to on-load-test the switches. To on-load-test
eoluinn 1:
Switch column I to 'lest' state
Close vaive a
. . ~CIUBICS correctly, typically up to 30 minutes.
Open vaive g
Check that test lamp indicates char water level ir liaw
below trip level
Switch columni and repeat prac~duie
268
OLZ
Llwa!uahuoa aq 01 voMad!d aql smolle lnoLer ialeaq s! qlomad!d meals-palq marua%ue~~e
JO n a u o a ar!,L a1no1 ale!idoidde aql !lassan qseu lasuapuos aql 01 30 sanu!luos [anal IaIeM aql 'lolaiae-ap aql 01 pa%~eqa
~e~uoz!ioq a q 'la~eaq
~ lea!llan e 103 LZ'E 8!d pue i n o ~ e l luawa6uelle y ~ o ~ a d ! ds.1 [assah qseu aql 01 su!erp ialeaq lsai!p 01 aseqd!~ue u! -s!p aq louues lam* aql uaqm 'peal i!un %u!glej u o
laleaq d~ leluoz!loq e l o j luawa%uslle yiomad!d S u ! y l o ~'p pue g sanpn uo!laalas alnol su!elp j o asn 'iasuapuos aql 01 au!l aql u! aqeh l o i ~ u o su!eip aql
aql smoqs 92's ain%!d 'anleh uo!lelos! ue jo %u!uado Lq palaalas s! atno1 sukeip ~ a l e a qd~ 8 'ON a q ~ suado uaql laha] l a l e ~4u!s!l aql 'yuel io~erae-apaql
uo ylomad!d aql %uole l d a ~ sBu!aq ~ a l e mJO slaysod ',8u!?unq, luanaid 01 01 su!elp iaieaq d~ aql IJ!I 01 ~ua!s~jjnsu!s! ~e!lua
SWa~alds ! q ~'pau!elp ale pasola aq plnoa qa!qm sah~en palunow saqal!ms leou Lq 'papaau se 'pa?le)s piia peal %u!s!l pue %u!llej uaamlaq ohor lnoqe Lq lasjjo -laJJ!P alnssaid aql j! !yuel lolelae-ap aql 01 ahleh
uaamlaq suo!laas leql alnsua 01 uayel s! ales fe!sads paddoas ale sdmnd aqL 'Ilamloq lasuapuoa aql o i ~ l sle Laql :lu!od lahoaZusq:, aql au!rulalap 01 pasn ale ~ o i l u o asu!e~paqi suado ISXJ ialsaq d~ s .ON aql u!
.yiomad!d aql u! lu!od sdwnd su!eip Lq padwnd ale lassah qseu lasuapuon Sa!pl!MS alnssaid OMJ, .au!qin$ u!em aql uo saqs~!ms laha1 lalem 8u!s!1 v 'lasuapuoa aql l o ~ u e al % e ~ oaql
s
uo!laallos le~nleuqaea le pap!noid are sdeil u!eip l o aql 01 pa%mqas!p su!erp aqL .rua~sLs10116oa [anal 3111 asnssald Lq pallonuoa s! 'esian as!n l o 'lassan qselj ale su!elp a q ~lo3 a[qel!ehe srro!leu!aap aql 'ialeaq
sas!J!lo Lq p a ~ ~ o n u osau!!
s u!ev ql!m slod u!elp 'pua sa!J![dm!s qs!qm 'sanlen [olauos aql 01 sleu%!s qs~!.,~ asuapuo9 aql 01 a%leqas!p i o j role~ae-apaql 01 pas!el d~ ainssald lsamol aql s! s!q~ asnesaq 'Inq aid!:,
s!ql 01'dn pawlem %u!aq s! pup plea s! y ~ o m a d ~ d 01 paau ou s! a ~ a qsahlen~ uo!lsa[as a l n o ~su!elp at{ aq w o i j qs~!ms su!erp qqqm l e IU!O~ aq& 'SZ'E -u!id iel!w!s e uo YIOM su!elp laleaq d~ JaqwnN
aql u a q ~luasaid aq Kluo plnoqs atesuapuoa ' y i o ~ Kq pau!m~a~aps! qled MOU su!e~p aql s v .y pus u! umoqs s! s ~ a ~ e ad~
q lea!lian ~I!M pala!sosse '51 AXN a41 Lq pamahaid s! ~ o ~ e ~ a e -aql ap w o l ~
-ad!d d~ aql u~ 'WOJ Lew qs!qm a~esuapuosLue JO S ~ A I E A Lq S! laleaq d~ L .ON 103 leql pue 'Z pun ISLS 1011uoa SU!E-IP ialeaq d~ a~!~euratyeu v I anleh qanoiql mouysea .iasuapuoa aql 01 a8ieqs
pau!eip Llalaldwos ale Laql leql osle pue papaasxa IOU sahleh Lq s! laleaq d~ 8 .ON U! l a ~ a 1aq1 JO forit1 ' ~ o ~ e r a e - aaql
p 01 sliaha, -s!p su!erp aql pue uado 01 papuewmo9 s! iasuapuos
ale saaueu au!qlnl aqi pue ialeaq aql uo swamow aqL 'anoqe paq!lssap saqsi!ms ainssald aql J O I noi a%leqss!p y e l p aql prle sllej [anal l a ~ e maql aql 01 au!l aql u! g anlen aql ' y u e ~io~elae-apaql
Pue slsnlql alqemolle aql leql arnsua 01 iueliodru! aql Lq pale!l!u! aauanbas anleh e Kq pau!mjalap am!] qans l!lun iasuapuoa aql 01 pa8ieqss!p uaql 01 Su!elp aql IJ!I 01 alnssald le!~uaiajj!p lUa!3!JJnSU!
su!erp a q l 'lasuapuoa aql 01 ahpn loquoa aql s! aiaql asnesaq asp 01 sanu!luos laha[ aql 31 'spaau
lo 01 leu%!s e spuas ia]lolluos lanal SI! [!lun as!, 01 UalSLS 01 %u!ploJse paqst!ms s! pue ~ o ~ e l a daql o
SJaleail !eJ!lisn lo) UalsLn ru!elp laleaq d~ uv ST( .OPJ
FIG. 3.27 ~rrangerncntof HP heater bled-swam pipework for vertical heaters at Drar Cornpietion power station
3.3 De-aerator storage tank
3.2 De-aerator heater The main function of the de-aerator storage tank is
A cross-section through a typical de-aerator heater to provide a reservoir of feedwater whicj,
272 273
PIO.3.28 Section f l ~ r o i i g l la iypicai de-aerator lhcntel

can be drawn upon by the boiler feed pumps when The highest ievel to which the condensate can
needed. is determined by the manufacturer, such that t
The capacity of the tank and the quantities o f feed- maximum velocity o f the steam flowing across t
water stored at the various Levels within the tank are surface of the water will not cause water pick-up
determined by the following functional needs: 'sloshing' of the tank content. In this context, w
pick-up is defined as water which is stripped fi
(a) To store sufficient feedwater to meet the re-
the tank surface and transported to the de-aer
quirements for flexible operation.
head by the action of heating steam. Damage to
(b) T o provide control levels for the operation of the de-aerator head internais can be caused by the iml PIG. 3.29 'Tyi>iciil de-aerator lank lei'els
insurge and outsurge systems without exceeding of the water which has been carried over. The lien
the hieh water level. can also become flooded due to the drains being II
able to cope with the extra water burden.
(c) Even when working at the top of the normal i, allow the insurgc and outsurge system to operate during a transient, the water travelling down the suc-
'Sloshing' of the tank content is caused by tl
operating level control band, to accept the con- formation of waves in the tank which close the stea niiel~eiidently without hunting. tion pipework must gain sufficient static head to pre.
tents of the condenser hotwell in the event o f the pathway and are then propelled the length of t h e t a vent boiling. The important factors are the rate at
condenser level control valve failing to the open by the force created by the heating steam bei which tank pressure reduces o r decays and the rate o f
position, without exceeding the high water ievel. tracted to the head. For a more complete expla flow down the suction pipework. The limiting case
(dl From the same initial working level as in (c), to o f the mechanism, reference should be made De-aerator elevation found for CEGB plant is a hot restart of a feed pump.
accept half-a-minute's-worth of CMR flow without paper on the subject o f de-aerator tank inst elevation of the de-aerator must be such that In this case the extraction pump is lost, the standby
exceeding the high water level. by Cranfield and Wilkinson [7]. On the latest ction head requirements of the feed pumps can fails to start and the feed pumps draw down the de-
of de-aerator, only a fraction o f the steam is isfied under all credible modes of operation. aerator tank until the unit trips or is shut down. On
(e) From the level indicated in (c), to accept water over the tank surface, the majority being introduc cal de-aerator tank and suction pipework con- unit restart, the water in the condenser which has ac-
accumulated in the condenser hotweil after a unit local t o the head. The small flow across the tank ji~urationis.shown in Fig 3.30, the tank content, pipe cumulated after the extraction pump trip, has to be
trip when the extraction pumps are restarted with- retained to scavenge any oxygen within the tank and lcngths and component elevations being indicated. pumped forward to refill the depleted de-aerator.
out exceeding the high water level. transport it to the head. The head is vented to remov la addition to the static head indicated, there is Assuming that the tank is at full-load conditions but
any accumulation of non-condensable gases. +Is0 the pressure head within the vessel. Under steady only partially full, the 100% cold condensate inflow
The rest of the working levels in the tank are dete f a t e conditions, the water within the feed pump suc- into a hot depleted tank produces a rapid pressure
Figure 3.29 shows a cross-section through a typical mined applying rules (a) to (e), above. From Fig 3. ion pipework is at the saturation temperature equi- drop within the tank. The feed pump is started on
de-aerator tank for a modern 660 MW unit. Indicated it will be seen that the insurge and outsurge valv valent to the pressure within the de-aerator. T o ensure leak-off, so the feed velocity is at its slowest and
are the various levels and the resultant actions which have been provided with separate control bands. hat boiling within the pipework cannot occur when hence the time for the column of hot water in the
are initiated. dead band is placed between the two control ban 8 sudden pressure reduction in the tank takes place suction pipework to gain static head is at its greatest.
274 275
F e e d w a t e ~hearing systems D e ~ a e r a t o rsysten?

provided in the bled-steam line between [lie dc-aclator


and the bleed point on tlrc luibiiic. As t11c amount of
steam evoivcd would overspeed the tuibirie, tile 3.6 Protection valves
return valve is o f a high intcgi.ity type specially dc- The bled-steam non-return valve is 1) 1st thc full differeiitial between heater at each natural drainage point, witli a side take-off
3nd turbine condensei pressure to keep it which is led with a continuous fall to a suitable iow
a is needed as the IP/LP turbine pressure pressure disposai point. The drainage is controlled by
~ ~ j ~ ~ d e back
n s e r pressure in approximately one orifices or traps, wit11 by-passes t o allow for cold start
u.Iiell the interceptor wives close due t o a unit conditions when drainage requirements are at their
bled-steam isolating valve is tripped so that it also non-return valve. ir 11eater pressure remains constant for seconds maximum. The steam traps, if used, are set so tllal
closes. In the evelit of an NWL in the tank, the blcd- The actuator is there primarily t o give tha vll according l o circumstances, and then re- they discharge a few degrees above saturation tem-
steam and power-assisted non-return valves are shut. positive closing fovce t o overcome any stiffo wly, hence the isolating valvc must close perature to prevent condensate build-up. Attention is
In addition, a high integrity valve in the condensate the bearings, etc., when the valve is comalsn e full differential pressure. also given to those sections of pipe which arc isolated
line to the de-acratoi is also shut. The route to tile shut. 'The valve is shut by dumping the air iroi

isolation on a high watci level is no1 needed arc the forward steam flow falls to a low value. This is I
HP heater drains and the feed pump leak-offs. This cause the steam fio\v on the underside of 1111. 11
is because the feed pump leak-offs are purely circulatory creates an opening force w l ~ i c l is
~ greater tl~itli I
flows between the tank and the boiler feed pump, and spring-closing force. The hied-steam isolating

AIR OPENING SPRlNG RETURN ACTUATOR. IMAXSEALI


.VALVE CLOSES ON LOSSOF AIR SUPPLY
SOLENOIDVALVE

FIG. 3.32 A ~ower-a~~i~ted


"an-return valve m ~ 3.33
. A bled-steam isolating valve ~ i t hair-opening, spring-closing acluator
187.
082
.uo!leiado paq2!amlno seM i(aua!a!jja a1sLJ u! u p 2 aql leql pue lall!J uo!l~nndmnd paaj e j o luama8uelle auo P ( . ~.31d
~ ! u nu! suo!lqilsal luanbasuos q l ! ~'yuel i o l e ~ a e paydde 1a8uol ou sos61 ~ I P Iaql u! uo!ldope i!aql
-ap aql u! Lesap ainssald sasnes io~eiae-apaq, u! pallnsai qs!qm siolsej aql leql papnpuos sem I!
01 alssuapuoa plos jo MOU aql 'pap!ho~d s! ssed qs!qm m o ~ 'S
j OL61 L ~ e aaql u! uayeliapun SeM malsLs
-Lq e j! uana 'anuanal 30 ssol %uellnsalql!m peol lareaq a~nssaldM O ~3a aql JO ssauat.!lsajja lsos a q ~
jjo uaqej aq 01 seq Lllensn i!un aql 'u!eig pue I JO Lpms e 'uo!lsnpoaul a q ~u! pauo!~uam Lua!lq s v
lilXEMOllo"
meqsLaH '[OodallleH 'g p!od Lalyu!H l e se pap!^ HO"OI(XI
~?"SVMY~I~LIII~IO
-old s! sseddq e ssalun 'aauanbasuos e s v 'ialeaq
'as!oqs [es!So[ aql pamaas
3a (ainssald isamol) lsllj a41 01 i o p d lsnl paseld uo!~snilsuos laas-lie jo w e a q 3a e os 's[e!JaIem
anlen au!ln[os! alesuapuoa aql jo ainsop jo asnesaq
3u!ieaq-,add03 u!eluos IOU lsnm lueld au!qs!lod
l o ~ e ~ a e - aaqt
p 01 paaj j o ssol U! sllnsai u!ei) ialeaq
aql j o meai~sumops i a l a a ~'lueld (Su!qs!lod) luam
3a e u! slaleaq arfl j o Lue u! lana~lalem q8!q v -leal1 rawm O ~ Wau!l-u!T ue jo asn a q ~palel!ssasau
'sraleaq aql w o l j ssal3u! lalem s ' ~ t ) v aq] IOJ Sluamal!nbai lalempaaj ial!oq aqL e
JO L1!1!q!ssod aq) ~su!eae uo!lsaloid au!qinl aql JO
.~alzaqd ? paqni e u e q ~ssal Llqe~ap!s
Su!pezlldn aql pue sleas doof aql j o qldap aql 3u!
-uoa s! 'malsLs uo!lnq!qs!p J ~ I ~leuialu!
M ue q~!m
-seanu! papnlsu! asaqL 'Llqeldaaae wiojlad maql
yuel e ~lles!seq s! qyqm 'ialeaq >a e j o s o ? aqL
ayem 01 suo!lexj!pom alqelap!suos papaau sualsap
jeu!3!ro aql ley1 umoqs seq asua!ladxa leuo!~elado 'ohsz'o 01 5.0 lnoqe j o ale1
leaq a q ~u! uo!r~npa~luanbasuos e q l ! ~pat.a!qse
ale sasualajj!p ainleladmal u!elp pue weals oraz
cpax!m ale a ~ e s u a p u o ~pue w e a ~ s a q ~asnessu

:suoseal 8u!molloj aql roj siali!al


d 7 azmj~nspaqnl [ ~ ~ ! I J J[euo!l!pen
A aql 01 asuai~,
-a.Id u! pajdopa Slleu!3!1o alaM sraleaq d 7 3(1
.sllem aqm aq] Lq paleledas ale alesuapuo~aql
wea~s-palqaql alaqm 'ualeaq d l aaejins paqm (1
ulalsLs jo u3!sap fsuo!l!peil aql 01 pasoddo se 'iaq
-01 plemioj padmnd ale pue laleaq aql u! x!w WUY U S V M I ~ Y B A ~
OlktEIMYl""3YA
-uapuos aql pue weals-palq aql 'sa!ldm! ameu arll S O I ~ O~S 3 ~ ~ ~ n ~ ~ ~ ~ ~

morj lajlno aq? u a a ~ l a q~uamd!nba aql pue SIJI


aql Se paurjap S! UalSLS paaJ ( 4 7 ) a~nssaidMO! :
Nl3lt3SOBINmDIS
uo!mnpo~$ul 1' a,diilnlv

walsAs paaj alnssald MO-1

'sa!l!l!seJ 8u!qsnuyaeq ~ ! ~ e w o l nql!,e,


uanbas 3U!UsnlJXJeq Wl J O uo!le!l!u! u o .uo!l qaea 'suo!ge~s par!~-l!ssoj u~ nsS3 aql tq pap!nord
I! PUB aaueualu!sw loJ Llqwasse qsnlJXaeq aql
uaaq seq jalleled u! SJa)l!J ~ ~ %ooi
n p
~aqlazola l q e ~ o m L~Il! P ~ ~ Js! W ! ~ M '~aqseqqsaw -a3uelic uv .~ue[dmea,lsuMop .lo sdwnd paad aql
1 lJals ssa!u!els JO s~s!suos iuawala J~II!J a q ~
raqva ssemep plnoa qa!rl~ Jalempaaj aql luorJ ,a,lew
-paJ!nbal J! 'sjeA~a~u! a w l pax!~18 8u!qsnuyaeq U~!~.IO Lue
J anomai 01 pap!hold ale SIall!J uo!13,iS
at1 01 PaP!noid OSiB ale Sa!1!/!3eJ .I~UI!L,req p.0 01
.lali!J aql S S O I ~ B doip alnssald J ~ UOLIM
I slle3!1 sjal1!4 uo!l3ns dwnd paa4 ral!og 8.E
-a.xraumo~sq) le rnsao ue3 Al!l!qelsu! >!I olne alelado 01 pa8ue~i-es! Su!qsnljy3ea ,.ieq I.0
i [aleaia ou jo suo!r!puo3 ueals aql u! dolp
?!lqap palejnun3m sill ~ [ erjsnij 01 SMOIJ
Feedwater lleati~igsystems

s Uecaiise of tile vertical sepal-ation ieqiiiied bctwecn


1lC Iicatcrs, aiicady iliostrated i i i Section I or tliis
chapter, long coiidensale and bled-steanl liiics were
ineeded. lixlensive steelwork was also necdcd to
soppo1.1 the lheaters at the reqoii-ed ievcls. 'Thesc
cxtl-a costs were foulld to outweigh the cast differ-
eiice betwecn VC and surface type LF lieaters.

As it was evident that a revision of traditional prac-


tice was cost effective, a complete review of previous
practice was undertaken by the manufacturers. A new
conceis evolved which followed international practice
o f using surface LP heaters in the horlzontai attitude.
Figure 3.36 shows the position finally adopted, which
ailowed easy bled-steam pipcwork drainage and makes
use of the entire beater shell to contain condensate in
a flooding situation. Another important factor is the
compact layout, which allows the heaters to be factory
built, complete with pipework fittings, etc., and ship-
ped to site as a onit. The only site work necessary is
to connect to the system on the steam and water sides
and to provide air and electl-icitv to tltc valves anti
~ ~~~~

instruments as needed, with consequent savings in


erection costs.
The cost o f modificatioii and upgrading of plant
after or during construction has vindicated the de-
cision to change to surface L P heaters for future
units: however, there are forty-nine 500 and 660 MW
units in operation with DC heaters. T o complete
the picture o f current plant, Fig 3.37 shows a typical
D C three-heater cascade a s employed at Hartlepool
and Heysham I, both AGR stations.
Water is pumped from the condenser hotwell via
the condensate system up to DC 1 heater. From this
heater, it cascades into DC 2 and then cascades into
D C 3 heater, from wheic it is pumped by the D C
heater cxtractior~ pump to the de-aeratol. heater. A
60% capacity by-pass is provided to prevent the unit
tripping on low de-aerator water level in the event
of a D C heater train trip.

4.2 L o w pressure s y s t e m configuration


Figure 3.38 shows the L P feed system for Littlebrook
D which uses tubed LP heaters in a horizontal atti-
tude. The heaters are by-passed in two banks, the
first group being LP1 and L P 2 heaters and the second
LP3 heater. Steam is supplied t o each of the three the malfunction of associated equipment d o e s n o l
L P heaters from the L P turbines. Each bled-steam result in the forced isolation of the heaters which iirc
line contains a free-acting non-return valve and a drained by the drain pump because of lack of as F , 1~. 3 6 A typical of horizontal-aiiiiude LP heaters
lo lhC
bled-steam isolating valve. Pic,orial view ofhorizonta~.afliiude LP heaterr showing tl~eprinciple$ adopted to determine their position
alternative destination for the drains. T h e short teinl level in condenser. The bled-seam pipework is sria.8ed lo from
T h e drains formed in LP3 heater are cascaded to loss of efficiency is accepted until the drain pump is bled.rteam ex,raclio,, poiets and
ellraction to heaterr cascadeby gravity from L P to ~ LPI heater and thence lo the flash dram cooler.
LPZ drains flashbox, from where they are drained returned to service. m e drains illen cascade la the condenser.
into L P I drains flashbox. The combined drains from Distribution of bleed point pressures and hence en.
L P 2 and LPI flashboxes cascade to the condenser thalpy rises over the heaters, determines the gair ill
fiash vessel. The drains from L P I heater are also cas- efficiency by forward pumping of the drains of each
caded to the condenser flash vessel.
Feedwater lheatiiig systems Low pressure feed sysleni

ihe roalriil \ral\rc is dcieiinii~edbp lhc sigoal i ' i < i t v I I,,imp Svoiii the disc1,;irgc of tlle dilly l ~ t ~ m l ) .
Icvei conisoilel- oil ilic dc-aclatoi, l l i c rnaxii~~iiii: O n all 500 h4W iinils and 111rcarliei 660 M W iilllls
will1 DC lhealcl-s, cooling o f tlic gcnclalai by con-
densate was incol~poralcd in !be reed rrain immc-
cliatcly after the extraction pump, as illustrated in
Fig 3.41.
The ieason for placing it in thc feed system was lo
reclaim lbe generatar losses as heat input lo thc reed.
by the opcrator as needed. lo practice, it was round tllar for large rnodern power
T o supply the de-aeratoi- with feed from the I
under emergency conditions a 30% make-up pi
may also be provided. The pump can also be used I
fill the de-aerator, avoiding ihc use of the extractio
.
stations the following difficulties were experienced:

On extraction pump trip, the residual heat in the


generator could boil the condensate in tile system and
cause theimally-induced hydraulic shock 1101.
pumpr for this duty wben initialiy filling the la,
Upstream of the make-up pump and outsurge coi
~lectiolls is a sectionalising valve, wllicli is useci I e To provide an acceptably modest condensate pres-
isolate the coadcnsate systcm during system flus1,iiili sore within the coolers on the generator, two pres-
and clean lip. sure stages arc needed. Two pumps are used and
Ali o f the systcm components upstream of 1111. the condensate is discharged from the first pump
isolating valve arc primarily concerned with c o n ~ ~ o l . through the generator coolers and tben into the
ling the flow through the condensate system to rn;iiw turbine moisture extraction condenser (TMEC) with
tain a constant water level in the condenser. consequent cornplicatcd pipework ariangcment. The
The prescribed level is required to give surge iiiiil TMEC extraction pump then discharges t o the lo%,est
cavitation-free extraction pump performance anti it
inaintained by tl~l.ottlingthe extraction pump flow,
A level control device on the condenses, typically it!,
manufactured by Fisher and sold vindci the tvailc
. pressure DC heater.

Ta Drevcnt limitations on unit output during tile


summer when condensate temperatures may be too
high to cool the generator adequately, coolers to
name 'Level-Trol', is used to give an air signal wliicl,
reduce the conde~lsatetemperature before it passes
heaters will result in isolation on both steam and through the generator may be required in the feed
condensate sides, with the condensate by-pass valve system. The introduction of raw water coolers in
opening to supply water to LP3. the condensate system carries the risk of leakage
control signal, thus preventing a unit trip due t o I
Also shown in Fig 3.38 is the portion of the LP of the cooling water into the system.
feed system which connects the condenser to the L P
loss of feed t o the boiler.
feedhcaters. Part o f this system is the insurge group,
The position o f the controi valve is immediately Whilst these problems can be overcome, the resultant
by which means feedwater is admitted lo the con-
upstream of sectiollalising valve. Its functiotl in triii,. plant is expensive and needs special care to operate.
denser. Water is Fed into the condenser from the
ming the pump discharge head to suit tlie systeiii Consequently an auxiliary CW system using indirect
reserve feedwater tanks (RFT) under the control of
resistance is sho\%,nin Fig 3.40. T o protect the extrac. coolers has been developed by the main manufacturers
the illsurge group.
tion pump from damage due to low flows, the pump and is fully described in Chapter 6 .
There are three routes by which feed can be ad-
manufacturcl. specifies a flow belous which the ex. O n all modern feed systems, protection against the
mitted via the insurge group:
traction pumps should not be operated. T o meet tills use of contaminated feedwater is provided. On some
A fixed orifice which allows I % CMR flow on a need a recirculation connection and a control valvc units, this takes the form of visual alarms t o alert
continuous basis. Any small leakages and water is provided and is commanded t o onen as the maill the operator of high conductivity levels in the feed
losses are made up by this quantity. control valve goes below the 25% flow position. Thc leaving the extraction pumps. In this case, the opcra-
way In which the recirculation valve operates in ant). tor has to use his judgement as to the subsequent
Via the control valve which receives its signal from phase to maintain a minimum flow through the ex- i:l(l.3.40 LP feed rysicrn rcninrance curve and function or actions. for enamole. to close sectionalising valves
iecirculalion loop at tow flows
de-aerator level. T h e capacity of the valve is usual- traction pump is also illustrated in Fig 3.40. valve A , condenser levei control valve - maintains a and unload the unit.
ly about 2 - 3 % and varies according to the static Between the condenser level controi valve and the ~011~tanl levet in fhc condenser and hence NPSH on For AGR feed systems, as illustrated in Flg 3.5, a
the extrnccioii .oumn. bv throfttinc nos to lnialch inno,!,
head available from the RFT (especially relevant sectionalising valve, a dump connection is provided, to ibc condciser.
full-duty polishing piant is provided t o ensure high
for a low level tank). which is used t o discharge contaminated condensate Valve B,recirculation toon coiiiiot valve - when valve A quality water for boiler feed. As their boilers need
from the system during system clean up. is passing leas than 40%, cl~envalve B opens io antiphase special protection against chloride ingress, valves are
A manually-operated by-pass valve which can pass T h e non-return valve upstream of the control valve such tiia?the combined discharge from A and D is a
constant 40% ar illiistraled by curve in (b). provided upstream of the polishing plant but down-
an)thing from 5-770 and is only used for start-up prevents accidental discharge o f water from the de- stream of the outsurge connection.
o r in a n emergency. aerator tank into the condenser in the event of an In the event o f a condenser tube leak, the conduc-
extraction pump trip with a faulty discharge non-return tivity sensors close the protection valves and trip the
valve. provided with isolating valves o n both suction and extraction pumps; should there be a n accidental re-
The outsurge valve and associated equipment is con- T h e gland steam condenser is placed upstream of ~lischarge to allow isolation for maintenance. Non- lease of chemicals from the polishing plant, the sec-
nected to the condensate system downstream of the the recirculation connection to ensure a cooling con- teulrn valves are provided o n the discharge of the ond line conductivity sensors also close the protection
sectionalising valve. The rate of discharge through densate flow a t all times. The extraction pumps are pumps t o prevent backflow of water tl~roughan idle valves. The valves used for this duty are butterfly
286
Fit. 3.42 Arrangemenl of LP heaten, showing bicd-steam pipeu,ork

iiiisisted-closing devices as these are not manda- average overall heat transfer coefficient has to be
101 LP heaters. found and used to determine the heat transfer surface
area needed. From the tube size and feedwater flow,
the tubenest diameter is found. With the tubenest
diameter known, the heater diameter and the main
structural details of the shell and water heater can be
ibim of feedheater design is to provide a heat determined by use of the appropriate design standard.
liigel- that will raise the temperature of the in- The length of the heater is a function of the heat
IV feedwater t o a specified outlet temperature, transfer surface needed. A detailed explanation of
I d~.awinga predetermined amount of steam from thermal/hydraulic design is given in Section 6 of this
,bine cycle. There are four groups of heat ex- chapter.
used in the feed system to fulfil this function: De-aerator head and DC heater sizes are deter-
mined by the need to accommodate the sprays or
Ir pressure feedwater heaters. trays used to create sufficient water surface area to
transfer the heat from the steam to the water, as
erator heaters. needed by the cycle. The vessel diameter and length
is determined by the need to contain the requisite
w pressure feedwater tubed heaters. number of sprays or trays.
FIO. 3.41 Diagrammatic arrangement of generator coolers is an LP feed system There are long established British Standards for the
R, pressure feedwater direct contact heaters.
structural design of feedheaters and these are used by
the CEGB to specify a uniform design standard for all
valves of the spring closing/air opening type similar pipework is shown in Fig 3.42 and shows cle lcsign of each type of heat exchanger is deter- components, materials, welding and testing.
to those used for bled-steam isolating valves. the principle of the heaters being below the cylin i by the thermal, hydraulic and structural needs Until 1976, the standard used was BSlSW 'Fusion
bottom level and above the condenser Level.

In 1976 BSlSW was replaced by BSSSW 'Unfired


4.3 Pipework and valves used in the de-aerator bled-steam pipework. The tubular heat exchanger to raise the tem-
I Fusion Welded Pressure Vessels' Ill], which conso-
The general arrangement of LP heater bled-steam return valves are also similar but are not prov 11.e of the feedwater by a defined amount, the lidated and expanded the previous standard. BSSSW

288 289
Feedwater liealilig systelns liigli pressure feedwater lieafers

)has bee11 used for ;ill liealeis ordered since 1976 and nicans by !+iricll lllc cooseqiielll lheiil liailsfcr su1'f;iCi.
will be used for all iiitoie piaot, I-'or a specific heal areas are foiiiid is shown in Seciioii 6 of this chaptel.
<WX"",,., ,mALe:,r, -,,or STCAL,
cxcbanger size, the standard is used to determine thr Figure 3.41 iilust~atesthe way in which the kcri " " ~ " ~ D L I U Y L i 3 i l i i i l r riiC:lO\

lhichness of all giessuic )parts sricli as shell, lubegiaie temperalore increases as i t passes through a t!'l~ic~il
and Naatcr header, branches, etc. 'The materials, weld two-pass horizontal heater of the U-lobc lype. 'i'lir
details and procedures, as well as relief valve capacity heater has both integral drain cooling and d e s o l ~ i ~ .
and vessel pressure testing, are also defined. heating sections as shown (Fig 3.44).
In certain specialist areas, such as heater internal The desuperheating section is placed on the oullcl
design, the 'Standards of Tubular Exchanger Manu- end o f the U-tubes in order that the incoming super.
factol-ers Association (TEMA) 1978' [I21 can also be heatei steam can raise the feedwater near to or abovc
applied. the satiiraiion temperature of the body piessuie be..
The lieat transfer cocfficients are determined by a fore it leaves the heater. 'The drain cooling section
manufacturer's experience with a particular design of is placed at the inlet end of the tubes to allow lllc
fecdheater. However, a good approximation to the outgoing drains to be cooled t o as near to the ill.
coming feedwater temperature as needed. Steam entelr FIG. 3.44 Steam axid water Flow nalhs iii u typical lhaiizo~~tal
H P lheatei
design values for surface type heaters can be obtained
by reference to the 'Guide t o the Design o f Feed the desuperheating section and is reduced in tenl.
Waler Heating Plant (BEMA) 1968' [I31 or 'TEMA perature by transferring its heat to the feedwater l(1
1978' [12]. within 27OC o f the temperature of saturation of ill?
condensing scction pressure. The steam then flows lo
the condensing section, where it leaves as water at sal.
"ration temperature to enter the drain cooling sectio~i. lining cost due to the loss of cycle cfficiency, !heaters Z CONRT S
~ R ~T L~O. ,~S ~T S
, S
~ SR~OT ,~O ~ O ~ C

6 High pressure feedwater heaters A watec seal is niaintained at the inlet to the drziin II be constructed without drain cooling sections or _,DE~UPLR~~E~INGS~OO~

cooling section by a level control system lo preveirl !parate desuperheating sections.


loss of prime in the section. Vertical H P heaters employ the same basic layout
in the drain cooiing section, the condensate ir ,it11 regard to disposition of the dcsupcrheating and
6.1 Functional needs 1':lin cooling sections. However, there are some poinrs
cooled to the drain outlet temperature and then dis.
The structural design of high pressure (HP) feedwater to the next lowest pressure heatci, difference in construction which are highlighted

.
heaters is determined by two main needs:

T o contain the steam and H P feedwater at the ap-


propriate cycle conditions.
Each section within the heater is provided with
baffles to ensure flow across the outside of the tub
by the heating medium.
As the heating steam is condensed in the heate
n the following section on construction of specific

Figure 3.45 shows a typical arrangement of a ver-


I H P heater. T h e desuperheating section is below
T o provide the heat transfer surface to raise the feed. "on-condensable gases are released. unless corre lhc working water level in the heater. T o prevent water
water temperature by the specified amount. vented these would rapidly blanket the heat tran olrakage, seals are provided between the tubes and
surface and would impair the heater thermal perf01 Ill? e n d plates of the desuperheating section, trunking
I5 :hlso needcd t o carry the steam from the dcsupei-
lieater t o the condensing section if needed. These
~vovisions can be avoided by placing the desuper-
Ihcating section in thc dotted position shown in Fig .~
X~RI(AIIv~I191rYtl

3.45 but, as it is not now adjacent to the tubeplate, ,~,,,o,,,,_


?s%?&~'NCoo''Nr
llir fccdwater must travel through tubes immersed

o be cooled back down t o saturation temperature.


lie horizontal design of heater does not suffer from
his problem as the desuperheating section is above
hc water level by virtue of the heater attitude.
The reduction in the complication of heater internal
ilstruction is another point in the favour of hori-
%ontal attitude H P heaters.
As the high pressure feedwater heaters are on the

Y/UBE /<nmn >contain this high pressure, various designs of water

F ~ G .3.43 ~enlpciat~re
rise of feed water as it passes ~ i ~ o u ganh HP healer nto the back of the tubeplate by the 'Foster Wheeler method of tube attachment has been used for many
Feedwater heating systems Iiigh pressure feedwater hearers

where c = minimum thickness of suaight tube, mm


p := calculation pressure, ~ / m m ~
f = allowable dcsign stress, i\'/mm2
TIIEPANNED SPIGOT
D = outside diameter of tube, mm

For a typical 660 M W unit


I = 217.2 bar or 21.72 i\'/mm2
D = 19.05 mm outside diameter

The heater tubes are manufactured to conform to


ESI Standard 23-4 82 [I51 (which supersedes GDCD
STEAM SiOEOr Standard 56-80 1161).
TUBEPLATE The tube material conforms to the 'Type 400' which
ARGON
FLOW
appears in the allowable design stress Table 2.3 (k) in
BSSS00 [ I l l , giving 96 N/mm2 at 300°C and 88 N/mm2
at 350°C for this material.
If the temperatures used to determine the allowable
I'IC 3.46 Foster-UJl?eelermelhod of but,-weldisg HI, theatel tuber to iubcplale stress in the tubes are taken as that experienced by the
ultimate heater, then the worst case is considered.

Steam temperature (assumed) 370°C


Outlet feed temperature 253'C
method o f tube attachment. Average temperature 312°C
By interpolation f at 31ZPC = 97.8 N/mm2
welded joints wherever practicable, as bolted joints plates with a forged steel or cast stcel hemis
Then tube wall thickness: t = (21.72 x 19.05)/
[(2 x 97.8) + 21.721
maintain heater internals, the heater shell has to be alternative which has been used in the past
= 1.90 mm
cut off and likewise any defective valves, etc., have to piece forged low carbon steel water header 7 Typical casl and Forged HP iheatei water tieaders
o f the hemispherical t),pe
be cut from the pipework. The subsequent re-welding 'bottle' type with welded-on feedwater branches.
of the heater shell has proved to be less difficult than cal examples of these methods o f constructi From BS1113 Clause 3.7.3, the thickness (eb) allowing
the reassembly of complicated bolted joints, which shown in Figs 3.47 and 3.48. The tubes used for bends is given by e b = 1.125 e, so e b = 1.90 x
require special techniques to ensure precise bolt ten- carbon manganese steel suitable for fusion 1.125 = 2.14 mm.

Using the nearest standard tube thickness of 203 mm,


In the following section, examples of current H P plate. tube bore = 19.05 - 4.06 = 14.99 mm, say IS mm.
heater construction are given for the two main con- The following sections outline how the design ci Having determined the tube thickness and hence the
tractors who have supplied heaters for 500 and 660 are used to determine the physical size of a typ bore, tlie area for flow per tube is known and so the
MW units, which shows how their designs meet the H P feedwater heater. number of tubes required for a specified H P feed flow
feed system needs. can now be calculated.

6.3 Water header, tube bundle and she 6.3.2 Area required f o r f l o w t h r o u g h t h e t u b e
6.2 C O n ~ t r ~ ~ t iof
O nhigh pressure heaters The dominant influence in determining the thick bundle
The construction o f the pressure envelope o f vertical of various parts of a water header for an H P heatel As all H P heaters employ U-tubes, the number of holes
and horizontal H P heaters is very similar and the a given pressure on the feed side is the tube bu 1'1G 3.48 Typical forged H P Ihealer 'bottle' water to give the flow area needed is equal to the number of
only differences are the arrangement o f the heater diameter, which is governed by the liumber of t Iti.iider - monobloc consiriiefion wirh we1ded.o" branches Us. Taking a typical 660 MW feed flow and two-
internals, support feet, etc. needed to provide the flow area for the feedwate bank heater configuration:

Tube thickness is found from application o f Flow/heater = 273.5 kg/s


desuperheating sections. In all cases, BSSSOO [ l l ] is and flows. Heater feed inlet temperature = 19IPC
Clause 3.7.1.1 but using the same notation Internal tube diameter = 15 mm
used to determine the thickness of the water header,
tubeplate, shell, etc. The U-tube wall thickness can 6.3.1 To find t u b e t h i c k n e s s Average feed temperature = 22ZDC
be found by application of BS1113: 'Design and manu- All modern CEGB H P feedheaters use 19.05 From ERA 1967 Steam Table, = 1.17 x l~-~m)/kg
facture of water tube steam generating plant' [14], (0.75 in) outside diameter low carbon manganese e = pD/(2f + p) specific volume
292
Feedwater lieating systems . f e e d w ter heaters

Tile missing parainelei i o rind the flow arca is ihc


velocity of the feedwater in the tubes.
For tile pul.pase of this spccimcn calcolatiorr, a ivalei
velocily 01 2 m/s is taken, but the actual value va1.i"~
with individual maoiifacturer's practice; lhawevei,
the 'Standards for Closed lieedwaler Healers (HEI)
1979' [I71 recommend not more than 2.4 m/s (8 ft/s)
at maximum flow conditions.
If, lor inslance, one bank of H P heaters is by-
passed in a two-bank system and the feed split is
60/40, with 60% through the active bank, the feed-
water vclocity will increase to 1.2 times normal ve-
locity, which would give (1.2 x 2) = 2.4 m/s (i.e.,
the HE1 maximum recommended feedwater velocity).

Area per tube = (a/4)(14.77/1000)~


= 1.713 x I O W ' rn2

Volumetric flow = 273.5 x (1.17 x


= 0.32 m3/s thickness c = pD,/(?f - g )

Required area = 0.32/2 'Tile bore of the branch must be found first: if a
= 0.16 m2 city of 3 m/s is assumed, the cross-sectional a )
0.32/3.0 = 0.107 m2, giving a 0.37 m bore. Thcr
Number of holeslflow = 0.16/(1.713 x 10.') !
= 934

The thickness calculated is that needed for pressit


The heater needs 934 U-tubes and the tubeplate has considerations alone. In practice, the branch wali tlii
1868 holes. If a tube pitch o f 25.4 mm is taken with a ness is increased to compensate for the opening nee
60" triangular pattern, then allowing for a typical (see Clause 3.5.4 of BSSSOO [ I l l ) and also to ensu
minimum U-tube bend and gaps for internal fittings, that it is adequate to withstand the forces imposed (
etc., the tube bundle can be assumed to have a n it by the pipework to which it is attached. The eirrl
ovcrall diameter of 1300 mm. o f the branch is reduced to a thickness suitable SOB
weiding to the H P feed pipework, which has a typical bC*h*P"NO,oNoll
;*,,,,i,>> " N D E I O I I T U B . S " . ~ ~ ~ . * ~ D ~ , , F ~ " " ~ " " ~ ~ " ~ E ~ ~ ~ ~ L " ~ ~ ~ ~ ~ ~ ~
.<,.I, :~rn*,,orr*a"i"srsniir
~ ~ U ~ L " S U P ~ ~ ~ E O
wall thickness of 32 mm (see Figs 3.47 and 3.48).
6.3.3 Tubeplate t h i c k n e s s
'The tubeplate thickness is found bv. ao~lication
.. of I',c. 3.49 Suggested working form for "-tube iubeshect design froin MIIW, rllowing worked exaspie for cypicai NP beater
BS5500, the calculation being shown in Fig 3.49, using 6.3.6 C o m p e n s a t i o n f o r o p e n i n g s in t h e w a t e r
- .
the suggested working form for U-tube tubesheet desien. header
page 3/96. The thickness calculated for the hemispherical par1
The values of the coefficients, which are given in of the water head is based on a vessel wall without
,.1 Heater tube length and tube supports AvelaEe Umbe length between tubeplates
Table 3.9 of BSSSOO, are also shown in graphical openings. Any openings, such as the branches a = 1450/(0.06 X 934)
form to demonstrate how they are obtained during access door, have to be allowed for by thickening he thermal performance needed from the heater fixes
lic heater surface in accordance with the methods = 25.9 m
the course of the calculation. If a single bank o f H P walls adjacent to the openings (Figs 3.47 and 3.4
feedwater heaters is considered in place of the double later in Section 6 of this chapter. Aueiaselube bundle length = 12.94 m , which deter-
The amount o f the compensation is found by
bank, for the same velocity of water in the tubes, the Assuming a heater surface o f 1450 m2 as typical
plication of Clause 3.5.4 of BS5500 [ I l l . Since t shell length,
flow area would have to be doubled. of the highest pressure heater for a 660 MW unit, the
amount of compensation will vary with individ
If it is assumed the area required to accommodate I~~.atcrlength and tube bundle support-plate pitch is
manufacturer's designs, a specific example is not give11
the doubled number of tubes is twice that previously I'ousd as follows.
here. 6.4.2 Tube s u p p o r t plates
needed, then the tube bundle diameter will be J2 times
the original diameter, with a consequent increase o f
!& The lubes are supported by a series of tube support
6.4.1 Length of U-tubes plata in the form of mild steel drilled with the same
tubeplate thickness to 550 mm. 6.3.7 Shell a n d dished e n d t h i c k n e s s pattern of holes as the tubeplate. The hole size is a
Number of U-tubes = 934 (as calculated previously)
The shell thickness is calculated from the formulae close fit over the outside diameter of the tubes. The
used to determine branch thickness. The dished end 'The tubes are 19.05 mm outside diameter so the ciearance between tube and tubeplate varies according
6.3.4 Water h e a d e r wall t h i c k n e s s thickness is found using the method detailed in [ I l l surface area per metre length is a x 0.01905 to the manufacturer's practice, but general guidance
For the purpose of finding the wall thickness of a Clause 3.5.2 'Domed Ends'. = 0.06 m2/m is given in TEMA 1978 [IZ).
294
liigh pressure feedwater heaters

6.6 T h e r m a l design
Earlies in this section i t was explained how thc tem-
' guide the
Ol- water across the lubes to
'The drains water is guided tiiioiil,
section by anotiler
perato1.e of tile high pressure feedwater varies as it
bai.,.l,~s,
1)rovide efficient heat transfer.
,,
1)ermissibIe values of baffle l)itcil ; , , r
passes ti~rouglian HP heater. Tlic heater temperature
limits, coiilbined with the physical size of tube bundle
from a design code, such as TEMA I);'/, diameter, shell diameter, tube size, etc., are the factors
which determine tile heat transfer surface area of a
wllich is used to predict if coilision heater.
Figure 3.51 (a) shows typical heat balance informa-
tion for the ultimate stages of feedheating for a 660
desuperheating section.
MX' unit. Also shown, is the associated temperature
orofile for the ultimate stage of feedheating (Fig 3.51
(c)). The basic equation used to find the surface area
(A) for each section is A = (q,,,h)/K(LMTD):
and desuperheating flow area and therefore increases tile
the tube
The sketch illustrates
plates act as baffles to dis-
because tubes are long
certain conditions be
objects, t i , i. i n turn influences thermal design. For where A = heat transfer area, m2
by randoll, q,, = mass flow rate, kg/s
h = specific enthalpy change through zone,
J/kg
K = oveiali heat transfer coefficient, W/m2K
LMTD = log mean temperature difference, as
tubular spacers at appropriate illter- defined in Fig 3.51 (d)
~ e i d i n gthem t o a structure within the
,ich is anchored t o the heater tubepiate. Figure 3.51 (a) and (b) illustrate how the heat
e close together in the desuperheating balance information is used to find the enthalpy rise
ling sections, but wider apart in the through each section in turn and the resultant tem-
perature profile.
From this information, the surface area for each
section is calculated in the manner described below.
I aspects o f the thermal design are found
11 6 of this chapter. 6.6.1 Desuperheating s e c t i o n
The bled-steam has a high degree of superheat which
allows the feedwater at the exit of the desuperheating
section t o approach very near to, or to be slightly
above, the saturation temperature equivalent of the
pressure at inlet t o the desuperheating section.
must also be given t o ensuring that local T o prevent erosion due to wet steam flowing through
e ~ ~ c i t i eare
s not present at the steam inlet t o the exit of the desuperheating section it is established
eater. There must be ample area to ailow the practice to retain about 28OC of superheat at the end
of the desuperheating section, so T 2 is made equal
t o the saturation temperature equivalent t o the pres-
sure in the condensing section plus 28'C. Figure 3.51
~,is based on this assumvtion.
(c)
The temperatures in the desuperheating section are
used t o evaluate the LMTD as shown in Fig 3.51 (dl,
so the only unknown in the equation to find the
or baffle to protect the tubes in terms of the surface area is the heat transfer coefficient.
lilllitingvalues o f e(v,,)2 where e is the steam density The methods of calculating the heat transfer co-
(kslm3) and ,v,, is the velocity o f dry steam (m/s), as efficient for a particular tube bundle are given in
detail in BEAMA 1968 [131 or T E M A 1978 1121: for a
typical desuperheater in the last stage HP heater its
v,,(max) = J(2250/e) m/s
value is about 500-600 w / m 2 K .
The heat transfer coefficient increases with the in-
If a velocity greater than this value is t o be en- creased velocity across the tube bundle. The higher
countered, even for short periods of operation (e.g., the velocity, the greater the pressure drop across the
Fa' Typicai arran&!emenr of tube supporl Plater in the desuller~eaiing, and cooling seclionr desuperheating section, which in turn reduces the sat-
of an HP heater
previous heater by-passed), the provision of a larger
branch or some form of impingement plate is needed. uration temperature within the condensing section.
296
297
Feedwater heating systems High pressure feedwater heaters

t exchanger dcsignex lras to reach a cosl as the nieair effective lcngtli of a U-tobc i n dctei-
i-ornise between increased condensing ~i~inirig ihe lheater siieli length.
rainst decreased desupei-heating surface The baffles within the lheater shell, which forol lire
ve ocity being dependent on the pitch of tbc compal.tmcnts tlixougii which thc steain or condensate
i ilic desoperheating section lo]. a given tube flow, have windows so that the fiuid can pass longi-
. Once an acceptable compromise liar been tudinally, Tiie area used is equal lo, or greater than,
that available for cross-flow.
From the ieferences given to find the lieat transfer
coefficients 1141, it will be seen that the theoretical
i\ ilcscribed earlier in this section). values arc modified to allow for leakage through the
aiirface area can now be calculated. From the tube/bafflc plate clearances, lack of true cross-flow and
iu~nberof tubes and surfacc area/metre iength the stagnant areas in the corners of the compartments
I,?, ihe length o f the desuperheating section is formed by the baffles.
'The baffle pitch may need slight readjustment The lieat transfer coefficients obtained by using
tile overall length requirement. these references, assume that the condensing section
within the healer is adequately vented to the condenser
t o avoid the accumulation of air or non-condensable
'ondensing s e c t i o n gases withi,? the section. The lieat transfer coefficient
used to determine surface area is significantly infiu-
SI<" 001,100:
enced by "on-condensables which tend to form a
gaseous muff around the condensate film on the out-
~rgsection. The effect of thc 28°C of supcr- side diameter of the tube. The slowing of the diffusion
o f vapour into tile condensate by the non-conden-
sables, significantly affects the condensing section per-
formance. This is a most imporlant factor in heater
I lbo found by reference to BEAMA 1968 1131 performance, and an unexpectedly poor performance
l A 1978 1121. The baffle pitch is determined from a new heater can be usually traced to incorrect
iecd lo distribute the steam throughout the air venting. The usual vent rate is about 0.5% of the
, ~ , ~ ~ m m , ~ , u , e p ~ o ~ , 9 ~ ~ o ~ ~ ~ , , m ~ , ~ ~ c ~ t ~ t I I section
~ and is usually about the maximum bled-sleam flow t o the heater.
,ic without the risk of tube vibration. The Accumulation of air can also occur in the drain
cooling section and cause pockets in the corners local
to the baffle plates. This reduces the available heat
hc per unit length and the number of tubes. transfer surface which again reduces heater performance.
N I ~ ~ ~ ~ L ~ ~ ~ U ~ ~ ~ ~ ~ ~ ~ I N ~ ~ t ~ l ~ l : ii '~\\~o-flowU-tube heater, as illustrated in Fig For an overview of the complete thermal/mechanical
llic condensing section inciudes the return bend design of HP heaters, reference should be made to
C o ~ ~ I O E P I s , ~ T 5 ~ . T , o l Y ~ , T ~ , ~ ~ ~ ~ ~ ~ ~ , L o ~ ~ ~ ~ ~ ~ ~ E ~ T ~ N ~ ~ , ~ ~ ~ ~ ~ ~ ~ r 'ti' and p a n of the bottom return leg. the Heat Exchanger Design Handbook 1984 [19].
CoollN9SL",OnS
Should cycle economics dictate a low first-cost feed
system, then H P heaters can be used with n o drain
I N I ~ ~ ~ ~ L ~ ~ l l N ~ ~ ~ L 1 ~ ~ ~ ~ ~ ~ i o ~ Drain cooling s e c t i o n cooling section and/or no desuperheating section. Where
11s section the condensate formed in the con- no desuoerheatine section is orovided, a small section
section has further heat removed by transfer local t o i h e steaminlet is baffled to help t o absorb the
~coniingfeedwater. The equation for the calcula- superheat, but is not allowed for in the calculation of
the surface area is as before. The LMTD is the surface area.
using the temperatures shown in Fig 3.51 (c). The omission of the drain cooling section means
lent transfer coefficient is found by the methods that the drains are discharged from the heater a t sat-
1 BEAMA 1968 1131 o r TEMA 1978 [12]. The uration temperature and there is n o need for a fixed
f the drains condensate across the tubes is im- water level in the heater shell t o protect the drain
n determining the heat transfer coefficient, so cooling section from erosion. The design procedures
fflc pitch is important and the subject of an to determine the surface area o f each section is the
'c iwocess during- the design." same whatever combination of sections is used.
,dlOaioim,"r,m*iMTD
~icalfigure for the lieat transfer coefficient in Vertical-attitude heaters differ slightly in the inter-
n cooling section will be about 19W W/m2 K. nal arrangement of components but use the same
Ill, tube length is found from the drain cooling design principles for mechanical and thermal design.
FIG. 3.51 Thermal design
as explained above

Other f a c t o r s a f f e c t i n g t h e r m a l d e s i g n 6.7 Horizontal high pressure heaters


,181 length o f the heater U-tube is the sum of An HP heater, as manufactured by GEC for the
lyills of the three sections. This length is taken Littlebrook D 660 MW units, is shown in Fig 3.52.
299
Feedwater iheating systems Chr?l Iiigli pressure fecdwater heaters
-
laths for feedwater, hied-steam and drain and thc holes tlil-ougb which thc tubes pass.
ndicated. 'The lheater illustrated has a steel Figure 3.52 (c) and (d) shows how the 'dip tubes',
al water head with mild steel iJ-tubes weid- which forin tlie seal between the condensing and drain
tubeplate by the Fostei-Wheeler method. Tlic cooling sections, arc welded to the drain cooler shroud.
es, etc., are all made froin mild steel. The The dip tubes and the bellows piece which seals the
of all-welded construction, except for itenis drain cooler outlct are welded in position after tlie
spection doors, etc., which need regular shell has bccn placed over the tubenest.
The heater has desuperheating, condensing The space below the tube bundle in the condensing
cooling sections provided in the form of section is used to maintain a fixed water level above
.- affled compartments. T o provide a steam the drain cooling section dip-tubes by means o f the
all1 in the condensing section above the top drain water level control system.
ubenest and also a space below the tubenest The drains from the bottom of the condensing sec-
11 flow, a segment at the tap and the co1.- tion flow via the two dip-tubes into the drain cooling
rig segment at the bottom of the tubeplate section, from where they flow to the centre and are
uld be used for tubes is left blank. This discharged by the central drain branch
a 'flat' on the top and bottom o f the gen- The venting arrangements arc illustrated in Fig 3.53
lar tubenest. A dividing baffle is placed which shows the vent paths within the heater. The air
ater head to pro\,ide the two-pass flow path and non-condensables in the condensing section are
vented by the hollow tubes incorporated in the lhori-
Ilorizontal dividing plate which runs the full zontal centre baffle. The drain cooling section also has
f the tubenest is used to support the baffle air vents just above the drain cooler outlet.
~d also to carry the air extraction ducts. The heater has a single relief valve sized in accord-
lesuperhcating section is in the form of a ance with BS5500 Appendix J [ I l l .
lui over the return half of the water flow adjacent Support feet are provided at each end of the heater;
Ilc tubeplate encompassing nine baffles. A platc the fixed foot is at the water header end, with the
idcd to seal the bottom to form a steam-tight other foot being free to slide to allow for thermal
nent. The steam inlet is at the top centre of expansion.
uilerheating section. A diffuser is provided to A water header manhole door is provided to allow
l t direct impingement of steam on the desuper- access to the feed side of the tubeplate for inspection
ction tubes. The steam flows in both di- and tube plugging. The heater internals are not in-
'om the central entry point, the baffles having tended to be maintained in sifu, but to have the whole
lustrated in Fig 3.52 (b)) to provide as heater cut out o f the pipework and moved to some
flow o f the heating steam as attainable. convenient maintenance area for the shell to be cut
fles have no cut-outs and form the end adjacent to tubeplate and removed. This is oltly ne-
n. The end baffles are also thicker than cessary if a heater has to be retubed.
have combined sealing and anti-
i c ips fitted in the clearance between the
LI the holes through which the tubes pass. A
I>le bellows piece connects the steam inlet of 6.8 Vertical high pressure heaters
:iIlcr and the stub branch on the desuperheating A 500 M W unit vertical HP heater, as manufactured
piece being welded in place after by NEIP for Ince B power station, is illustrated in
is in position over the tubenest. The steam Fig 3.54. Because of the economic factors prevailing
c desuperheating section by four windows cut when the overall turbine/feed system was evaluated,
o u d as shown in Fig 3.52 (b). The condensing it was found that the provision of drain cooling sec-
affles have no cut-outs but take advantage tions was not cost effective. The heater does, however,
ace between the tube bundle and the shell have a desuperheating section. The water header is o f
te the steam over the length of the con- the all-forged 'bottle' construction, with the inlet and
ction where it is condensed, the condensate outlet branches and the support feet welded to the
Ilp to the bottom of the shell. A drain water main forging. The desuperheating section is at the
Is !maintained in the shell by the external drain bottom of the heater surrounding the tubes on the
outlet side of the U-tube bundle. As the desuperheat-
Ilr iIl.;lin cooling section occupies the space directly ing section wrapper plate and end section will be in
Ihe desuperheating section. It comprises 13 contact with the drains water, a double-skin con-
11 cut-outs suitable to promote cross-flow of struction is used to prevent direct contact between
, all enclosed by a semicircular shroud, with metal at steam superheat temperature on one side
affles at each end forming the end of the and condensate at saturation temperature on the
ing section. A plate is provided to seal the other (see Fig 3.54 (a)).
11s section. The end baffles have combined A baffle plate is provided at the bled-steam inlet
and antivibration clips fitted between the tubes to prevent tube erosion/vibration and, as a further
301
Feedwater heating syslelms De-aorating feedheaters

toll1 of tile heater to accoaliilalc in tllat half of the HP lieatei is tlie watci header, '1'0 i-ediicc ;illou, a sn~aiicrnumber of artachments lo lo lhc de-aerator tank is used. Cllaptci 4, Section
shell nut occiipied by tile desupcrlieating sectioii. A and aiso its tlievmal inertia, designs incorlrili to the header to gain access for tile attachment 14.7 of this voiurnc describes the system and lloiv
ware) icvci is ~iiainlainedin thc buttonl of rile heater, drum-type !water header have becn constiiicti, lo tlie headers. i t functions.
tllc i)Ul.pose being to sedi tltc drain outlct to prevent Figure 3.55 (a) and (b) shows two diffu~c~it lieaters suffer from some tube erosion in the
erosion due lo two-phase flow adjacent to thc drains lions for constructing ail H P beater witho~u r i I' the bifurcations but, in general, have been a s Accept the H P lieate? drains,
oiitiet. The air vcnls are placed at the top o f the shell i'entional water head. The heater shown o n 11 design. Because of the high cost o f con-
as all inon-coildensable gases and air wili rise to that e Heat tile tank content from cold t o provide hot
was constructed for Thorpe Marsh power ,I,, the development of this design was not
point. employed a central header with the mild stccl de-aerated water for unit start-up.
These two short descriptions of current H P hcaters radially disposed, the tubes being welded to tlir
illustrate how the design principles, explained earlier by the Foster-Witeeier method. T h e length 01' t i
in this section, are implemented in practice. The following examples of different manufacturers'
was such that they had to be constructed frorii de-aerators show how they achieve these objectives
lengths o f pipe butt-welded together. This ICI by different design philosophies.
tube was difficuit to handle and adequate pr( @-aeratingfeedheaters
had to be made within the shell to support t o t
6.9 Alternative designs of h e a t e r c o n s t r u c t i o n The only drawback to this design was its higli
A brief description o f older heater designs is inciuded canstructioo. 7.2 T h e r m a l l h y d r a u l i c design
to indicate how othei- approaciies to provide cost ef- The heater illustrated in Fig 3.55 (b) was co~,. Figure 3.56 shows a typical de-aerator and feedwater
fective H P heaters have been tried. liom the condenser (condensate) which has
by GEC and used mild steel tubes manually-weld storage tank, the head of which heals and de-aerates
The most expensive cornpotient in the construction calcd by the 1.P feedheaters is supplied t o the
bifurcation pieces which were, in turn, weld the incoming condensate before it drains by gravity
of a conventional hemispherical water headei- type o f tior to be further heated and de-aerated
superltcate~type headers. Tile bifurcation into the storage tank. The design uses spray nozzles
itory to being fed to the boilers by the boiler
to produce a fine film/spray t o maximise the surface
urn],, via the H P feed train. De-aeraton on
area of the water available to the steam for heat
i large units are designed to provide feedwater
transfer and to minimise the distance that the oxygen
- .~~ .. ~...
~ liom the storage tank with not more than 5
FEE0 WATER .,-. has t o travel t o be released. Any residual oxygen is
11s per kilogram &/kg) of oxygen.
released while the water is further heated as it passes
o n is achieved by the application of Henry's
over a series of perforated trays, which causes the
llicli states that the quantity of gas dissolved in
condensate t o fall as a continuous 'rainfall' from tray
CONNECTlON EYE 1 quantity of solution is proportional to the
t o tray.
ssure of that gas over the solution. When
The heat transfer coefficient in the fine film/spray
-JACKING SCREW applied t o the removal of oxygen from feed
zone is about five to ten times the value for the drop
phere above and around the
phase of approximately 14 k w / m 2 ~ As
. nearly 90% of
ate contains no oxygen, then the dissolved
the temverature rise occurs in the film uhase, the
'I1 escape t o that atmosphere in an attempt
temperature difference between the water drops cas-
cading from the iower trays and the steam is small. The
nstruct a de-aerating heatei to release the
additional trays, however, arc needed to allow time
amount
~iil~ii of oxygen from the incoming con-
for the residual oxygen to escape and also to heat the
Ir, the following factors have to be considered:
water to the saturation temperature equivalent to the
lime for the dissolved oxygen to travel to the prevailing pressure.
The steam flow path is shown by the arrows in
cc of the water.
Fig 3.56. A small flow of steam, along with the oxy-
clwtll time is needed for the steam to heat the gen and non-condensable gases, is extracted by vents
ate and so Increase the equilibrium pressure o n the top of the head. The mixture of steam and
en in order to release it. oxygen, if vented directly to the condenser, would
constitute a heat loss. T o save this heat, a vent con-
~ r f a c etension of the water. denser is provided t o heat the incoming feed by con-
densing the vapour and extracting the heat irom the
lime taken for the diffusion of the oxygen
.. .- and non-condensable -gases.
oxveen
the water into the steam atmosphere. The oxygen and non-condensable gases are extracted
from the vent condenser by venting it to the conden-
ser, from where the gases are discharged by the main
rlorage tank associated with de-aeration has t o
air extraction pumps.
DRAINOUTLET 1 lhc following needs:
The storage tank associated with the de.aerating
xpproximately 7-10 minutes' worth of CMR function stores about 300 tonnes of feedwater in a
tts defined in Section 3.3 of this chapter. tank o f approximately 4.5 m diameter by 32 m long:
it is accommodated o n an elevated floor in an annexe
>I the leak-off flows from the boiler feed between the boiler house and turbine hall.
>s, when needed. At low loads, when the flow Diffusers are provided to discharge the leak-offs
yli the feed pump would be less than about and the H P drains into the tank, as indicated o n Fig
FIG. 3.55 HP feedheaters with cylindrical headers a special leak-off system which discharges 3.56.
Chapti.! :4
Feedwater heating systems
i i 1ic;ited by a large vcnt condensci ~i,l~icli
cootribiites sllows a section through a typical Stork iie-aerator,
it11 iir~irl-eciableproportion of the ternjlel.ature rise over with the steam and watci paths indicated.
!It,: ticater. This reduces tlic heating requi1,ed during There is no de-aerating head as such, but in tlie
li;iiisit through the trays. space above thc working water levei in the lop of the
'I'iie condensate is directed onto the top tray from storage tank there is a series of speciallp designed
w11ere it cascades through tlie rest o f the trays to flow sprayers, which spray the incoming feedwater onto a
I,) gravity into the storage tank. The steam/water flow ring of plates which further breaks up the water.
pslhs are indicated on the figure. The sprayers are designed to create sufficient spray
' ' steam flaw to the vent condenser is about area and water droplets to provide the necessary heat
"10 of the bled-steam flow: any oxygen and transfer surface t o heat the incoming feed to as near
in-condensable gases are swept away in this vent to the saturation temperature (corresponding to the
)w. The vent condenser is vented to the main con- pressure within the de-aerator) as practicable. In prac-
er, as indicated, and the gases are discharged tice, the temperature of the feedwater in the tank has
the main condenser by the air extraction pumps. been measured t o b e within 1-Z°C of the saturation
'The feedwater storage tank associated with the temperature. T h e stored water in the tank is therefore
lc-aerating heater on Fig 3.57 is similar in size and heated t o the saturation temperature of the incoming
; provisions for leak-offs, HP drains, etc., to heating steam as it enters the fank through the sprays.
described for Fig 3.56. The other features de- A steam distribution system in the form of a 'rake'
ed for the first de-aerator storage tank are also is provided, the teeth of which arc vertical tubes per-

v
forated at their ends. Thc end which is oerforated is
I .0, k~W0

S//A,A1,JPJINB/UB/NL5/SY
\
0,SI"IOulmY ,.,PIS
7a
PUUPIUCTtON I,/
S,E*,IRI~,,NO,"I6XESI
\
510"AGET"N*
A design of de-aerator currentiy intended for use
a,illiin a CEGB power station is the 'Stork' de-aerator.
positioned to be always below the lowest working
feedwater level. The heating steam introduced into
lOlNS"tlrN8XiND
O@TAN<COWTEN. 'Illis type of de-aerator employs a different approach the tank content via the steam 'rake' is nearly at the
lo llle task of extracting the oxygen and other non- same saturation temperature as the tank content and
i~>ndensabIegases from the condensate. Figure 3.58 is therefore not condensed, but bubbles through the
I:!<;. 3.56 Sectio#>illlougl~ a typical ~pra)./truyl y l x dc-acrrcoi niid associaled aiora8e iank

The steam coiis used t o boil and thereby de-aerate Vertical baffles are also needed t o prevent possib
the tank content prior to unit start-up are also shown 'sloshing' of the tank content from end t o end und
in Fig 3.56. conditions of abnormal steam flows across the tal
Unless provision is made to induce movement o f surface. The transfer pipes between the tank and I1
the tank contents, stagnant areas o f subcooled water de-aerator head arc of generous size t o ailow flow
will resuit. A distribution system is provided to pre- vapour to the head when the tank content boils ill1
vent direct discharge of the incoming heated and de- to a i.eduction in de-aerator tank pressure.
aerated feedwater from the boiler feed pump suctioll The de-aerating head shown in Fig 3.57 employs 11
pipe connection. By use of a distribution system, ade- different design phiiosophy, using trays only to obtait~
quate mixing of the tank content is ensured. the de-aeration of the feedwater. The incoming feed

Em. 3.58 Section through a tygkal 'Stork' de-aerator


Low Pressure lieatel!,

oscd for LP heaters, nccd a tube wall thick- do no1 allow for the effects of openings in the vesscl
ai ieast 1.2 om to g~.cverit the tube wail walls. Tlie compensations needed around the various
openings to conipeiisate for the penetration arc
calculated, as fox HP headers, by the application ol
,ifecdwates pressure requirements, it nevei- Clausc 3.5.4 of BS5500 [ I l l .
iows for corrosion damage and aiso makes
8.4.7 Shell and dished e n d thickness
The pressure range over which LP heaters operate
blCr,ONl""O"B*
ITSAMNLeT is from maximum bleed point pressure to full vacuum.
i f the shell thicknesses were determined by differen-
FIG. 3.60 Seciion ibrougil s lypical lhorironlal LP liearci, Heysham 2 po>!,el riac,oll t of the depth of the tubeplate. The light tial pressure alone, the thickness of the lower pressure
is to close the gap between the tube and heater shelis would be insufficient to withstand loads
le, where water could penetrate and possibly from pipework or being lifted into piace during the
,revice corrosion. The mechanism of rolier- course of plant erection. In practice, shell thickness
iig tubes into tubeplates is described in depth is not made iess than about 12 mm but this again
depends on individual manufacturer's practice. Ex-
ternal stiffening rings are sometimes aiso used to
permit the use of slightly thinner shells. The dished end
thickness is chosen to suit the shell thickness.

iiation to find the flow area is the same as

8.5 Heater tube length and tube supports


The procedure used is again similar to that already
described for H P heaters. However, for LP heaters,
660 MW unit, a typical LP heater has about this usually only involves consideration of a condensing
-tubes with a tube bundle diameter of abour section. If integral drain coolers were to be used,
the procedure would be the same as that used for HP
heater drains coolers. An average U-tube length between
Tubeplate thickness tubeplates o n a n LP heater for a modern 660 MW unit
is about 18 m, giving an average tube bundie length
Ie suggested working form for U-tube tube- of 9 m.
,sign o n Page 3/96.
calculation is very similar to that shown on 8.5.1 Tube s u p p o r t plates
2.49, the only difference being that allowance
From Figs 3.60 and 3.61, it will be seen that there is
;idc for the stiffening effect of the tubes where
a divergence of design philosophy in the method of
xiss through the tubepiate. Using this method of providing support for the tube bundles. The heater
Ition, a typical 660 MW LP heater tubeplate
in Fig 3.60 has a vertically-disposed structure extend-
ii lube bundle diameter of 1.4 m has a thickness
ing the length of the tube bundle, made of plate
FIG- 3.61 Sceiion tl~rougba typical horizontal LP heacei, LirLlebiook D power ststion eliout 200 mm. and hollow square-section tube which carries the tube
support plates. Attached to lugs on the periphery of
Water header wall thickness the tube support plates are radial side support bars,
which locate the tube bundle in the shell. The support
full flow polishing plant is needed, copper-bearing 8.4 Water header, tube bundle and shell formula from BS55M) Clause 3.5.1.2 (a) 'Cylin-
plates also take the weight of the tube bundle while
materials should not be employed downstream of the A significant factor in determining the thickness I Shells' [li], is used to find the wall thickness
it is being inserted or withdrawn from the shell.
polishing plant: so stainless steel is used for ail L P the various parts of the heater is the tube bull IC water headers illustrated in Figs 3.60 and 3.61.
heater tubes, including the drain cooler and TMEC. corrosion and other allowances, a typical wall The heater shown in Fig 3.61 uses six stays, over
diameter. To find this the number of U-tubes need which fit hollow cylindrical spacers to maintain the
Until 1976, LP heaters were designed to comply with to pass the feed flow has to be found. Each LP fe ncss is 32 mm.
BS15OO; heaters specified since that date have been intended distance between baffle plates. The baffle
heater passes full feed flow.
constructed to BSSSOO. The heaters shown in Figs 3.60 plates are cropped at top and bottom, as shown in
and 3.61 are constructed to comply with BS55M) [Ill. w a t e r header branch thickness the section through the heater, to allow steam to flow
The methods used to determine the physical size of 8.4.1 T u b e thickness ame formula as that quoted above for water transversely along the top of the shell and drains to
an L P heater to fulfil a particular duty, as defined cr wall thickness is used to determine the branch flow along the bottom of the heater. The main steam
As the LP heater U-tubes are roller-expanded in
by feed cycle needs, is very similar to that illustrated and drain flow paths are indicated on the figure. Two
the tubeplate, the tube wail thickness is determi
for H P heaters in Section 6 of this chapter. Using guide rails are provided inside the shell to take the
by the need to have a long term leak-free joint
the same order of calculation as for H P heaters, the tube bundle weight via the baffle plates. They also
tween the tube and the tubepiate. Experience .G Compensations f o r openings in t h e waterbox
details are shown in the next section. support the tube bundle when it is inserted or with-
shown that tubes expanded into a mild steel to
thickness calculated for the various components drawn from the shell.
311
aql IoJ palOu8! s! I! 'meals-palq aql u! leaqladns
amos aheq slaleaq d? alnssald raq8!q aqz q 8 n o q i l ~
1p11nq aqm aql ssolse ~ o l su!erp j aql Su!yem kq 'uojlsas Bu!suapuoa ialeaq d~ aql jo u8!sap lemraql
~napuosSu!mo~u! aq? leaq 01 J ~ I E Mu!e~p aql u! aql 01 slajal qa!qm 'laldeqs s!ql jo g uo!lsaS u! pawl
I aql sasn laloos u!slp jo adkl ah!?eulal[e aqJ -in0 kpea~lepoqtam aql 01 lel!m!s s! raleaq 47 ad61
'(8) z g ' ~ U! pales!pu! S! l a l e ~pus weals aql Su!suapuoa e jo vale asejins ayl jo uo!leu!mlalap aqL
clayel q1ed ayL 'aaemep uo!sola 8u!snes pue saqnl ufi!sap l e t u l a y l ~ ' 8
[laqs aql uo 8u!8u!dm! laleM pup meals 8u:qseU
111 iuahard 01 pap!hold ale saljjeq l e u ~ a ~ u'uo!1anns
]
[pals pi!ru paplam-118 j o s! [laqs aql pue aleld
nl pals pl!m e o ~ u !papuedxa-rallo~a16 saqnl-n 'suo!l!puos
'58181 aq II!M arunloh 'alnssald M O ~aql j o asnesaq Su!lelado pall!mrad aql lapun laha1 au!yloM mnm!xem
kl!luanb 8u!mo~u! aql j o O&OPol O& lnoqe aq aql uo luapuadap os[e s! 13s aq plnoqs saqs$!ms [aha1
meals aq.L 'slaleaq aql jo asueunojrad lem~aqzat11 i a l e ~q8!q aql q q q ~ le [aha[ aqJ 'is01 aq il!m asejlns
pau!mralap alnssald aql le IaleM pua meals olu! lajsuell leaq ayi 10 saqnl molloq aql Molaq aq ~ s n l u
llj ue3 Su!elp aq1 anqM laqmBq3 qselj e ap!ho~d laha1 law* aqL 'luel~odui?s! qldap w e m f e ~ n l e uaql
papualxa s! llaqs aqL 'raieaq ue se awes aql s! j o uo!leu!mlalap aqL 'raleaq aql u! J ~ I ~joM qldap
100su!wp Su!qseU e J O uo!lsnosuos le~aua8aqJ arn uo aneq s ~ a ~ a m e ~sno!leh
ed leql asuanuu! aql J O
'anlRh uo!leueidxa llnj B ~ o [IZ] j p1a!jue.13 pue [z] sauof
!,!!,ads aql le ainieladwai ~ a l ~ nraloos
o u!e~p aql pue aMo8 'a!qnx '[oz] ~ 0 1 pue 3 iaupJe9 01 apelu aq
plnoqs asuarajai pue xaldmos s! d!qsuo!ielal aqJ 'lassah
p aql IV 'rsleaq aql jo az!s aql sau!mralap leql [eluoz!.loq a q ~jo sn!pei aql pue lassah ail) jo ]no ales
no suielp aqi pue iaieapaal 8u!luosu! ayi uaamisq -uapiloa jo MOIJjo aiel 'ialawa!p iaflno uodn luapuad
il.>lajj!p slnleradma, aql s! 11 'a~nleiadmaisu!erp -ap s! L I J ! ~ M paqs!fqelsa s! [?"a1 .ralem [ernleu v
I 01 iuale.\!nba alossald uo!iernles aql 01 lenba 'ilaqs aql jo moiloq aql uo io!od Seu!eip
[ ~ ~ aql
q s u! ainssald ail1 '(3) 2 9 ' ~8 ! ~molj uaas e 01 .lalaaq 541 J O pua qaea w o l j Bu!h\o[j ralem aqi
w3ueqsxa l e ~ qe j o saqnl-n aql uo pasuapuoa s[ uodn sprladap slaleaq [aluoz!loq jo a?.eu!elp aqL
P paqseij aql jo uo!lse.ij weals aql se '.laleaq d 7 'Ilaqs laleati aql J O wonoq aqi u o ~ j
1 iel!ru!s s! a d 4 8u!qseU aqJ .ialoos u!mp jo pau!erp s! I! 'lalea[[ aql u! pawloj s! apsuapuoa s v
1 om1 aql LIlea!lemmei%e!p smoqs ~ y c a~n?.!j 'uo!lelnlunsse ialeM luanald 01 llaq iaju!
'sralearl d l at11 jo su!e~ppau!qmo> aql morj meals aqi jo monoq aql uo papyold s! y e l p v .sag!>
ail jo lunowe mnm!xem aql l ~ e ~ l x a ~1~100s
01 o!e.ip -ofan ~ I U !MOI ~uanbasuospun Bare MOU a2.1~1e ap!h
riralxa se pasn aq ues ia8ueqsxa laaq jo sadhi oh^^ -old 01 1jaqs aql jo a>ualajrnnsI!s aql punole paseld
slrod q l ! ~sljaq la["! meals ap!~o.ld 01 uasoqs seq
'Isnamoq 'raleaq laqio aql jo lalnlsejnilem a q '~0 9 ' ~
B!J u! pslerlsnl[! iaieaq aql uo saqsualq IajlI! luesir
-palq all, ispun psp!nold ale saleid ji1~wa9u!dml
leq aql l l a s ~ i a qpaddell aq ues r!e jo slaysod on 'saqnl 01 a8ewep
slnsua 01 qi8nai Ilnj sl! roj rsau aql jo a.llua> iuana.ld 01 pap!one sq isnu slalu! weals-palq aql 01
I illorj palJerixa s! I!e aql ' 1 9 ' ~pue 09's s9!j n! luase/pe sa!l!solan lwol qS!q 'slalearl d~ ql!" s v
ia!.iisnll! slalearl arjl .JOJ '~aleaqsql 01 1~301.tnxo slallno u!eip pue slaluj ueals-pala 9'8
ru i[s!qm a8eyealu! .&!aiqi?![s due ~ I ! M adas 01 shoq
liiavl",r>Oid*, D,iurr,,,r,
la,! aqi pun ulnnseh rapun yroM Slaieaq amos se
1 ~ 3 qd~ q)!m ueqi rases ailios o! i~n,!jj!p siom
938ni n . C L
,ism s!r[l :pawah klalenbap~~aleay d7 aql aheq 'dlay!lun s! a8emep uo!l
iiiallodm! se IS"/ s! 11 'sralaaq d~ i o j passnss!p -e.iq!n paonpu!-n\o[j leql qsns s! saijjeq u a a ~ l a qaauei
kpeaile seg sase8 alqesuapuos-uou jo asussa.id -s!p aql j! su!wlalap 01 pasn ,Lf[emrou ale sraqlunu
01 anp Lsua!s!jja u! pasnpsi 8u!aq S S J J O I ~ I ~ J S U B J I asewep [a[] uaISu.loq& aqJ 'slaleaq 1 0 j Jaideqs
[ 3111 iuanaid 01 slaleaq aqi lrian oi paau aqJ s!q~ jo p'g uo!isas n! uah!8 asoql se awes aql s!
papaat! saijjeq uaamlaq asuels!p au!wlalap 01 pasn sajn.1 aq*
tl,)~fls 5\13 pue saqnl jo raqlunu 'qi8ual arisru/eare
l!liriLraiilo aqm u ~ o i punojj s! i[lgua[ aqni-n ail^
<,!il?.lq!npa3npu!-.no[j oi anp saqni aqi 01 azsuiep jo
I iiloql!m alqeh\ol[e rilnuijreru 3ql ol ssols .(ljensn

*OO?AlOAl nv31s
'paii!aiiaiap s! ssej.lns
1leati si(i 'ralileilJ sjijl jo 9 uo!isai. u! iia,\!$
)s sill 81i!s(l (i.i.flV1a q l 8iI!lu[n~[i.?.lo ssodind
Feedwater heating systems Evaporators and other lneans of water rreatmenr

described far 1iP !heaters. The lhcal balance to detci- of the Incoming condensate for presentation
mine the rise ovci the drain cooler is shown in Fig healing steam, 'The rnaximun~heal transfer coc S P R A Y TUBE
3.62 (0 and the resultant temperature gradient is
illustrated by inset (e) of the figure. Again, U-tubes droplet flow.
are. roller-expanded into a mild steel tubeplate. The The slielis and dished ends are constructed o i ill1
shell is of all-welded steel construction. steel. As the last station to be constructed wit
The baffle arrangement, however, is different as heaters was ordered before 1976, all the D C h
the baffles are required to guide the water across
the tubes and to prevent leakage between the shell
and baffle. The baffles are semicircular and a close mined by the need to accommodate the spra
fit in the shell. The path needed to be taken by the
drain water is shown in Fig 3.62 (d). to heater. Figure 3.63 shows a typical horizontal a1
tude DC heater of NEIP manufacture, employiny
system of jets which impinge on plates to produ
8.8.1 Thermallhydraulic design of a flashing a fan-shaped film. The feedwater from the previo
drain cooler heater is introduced into the channels which run aloi
The temperature of the feedwatei leaving the heatel the axis of the vessel. These distribution chaiin
for a specified temperature difference is found by are bridged by pipes across the inside of the si
performing a heat balance over the drain cooler (Fig
3.62 (c)).
The temperatures required to complete the diagram
shown In Fig 3.62 (b) are now available. Assuming water t o the saturation tempeiature coriespon
that all the condensate flows through the drain cooler
tubenest, then the tubenest will have the same number
of tubes as the LP heaters in the feed system. The
overall diameter will also be the same. The LMTD is extracted. The heater is continuously vented
calculation is shown in Fig 3.62 (b). The heat transfer condenser. The steam inlet has a baffle which
surface is then found using the same method as for a the steam along the axis of the shell.
normal L P heater. The drain outlet is at the centre of the heater ail
is fitted with an antivortex device. As discussed earl1
in this section for horizontal LP heaters, a nalor
drainage level in the heater exists dependent on 111
8.8.2 Thermallhydraulic design of a warer-to-
flow rate into the heater, the heater shell diametei
w a t e r drain cooler
etc.
The temperature out of the drain cooler is found by The DC heater illustrated in Fig 3.64 was milti
a heat balance over the drain cooler as shown in factured by GEC. The design philosophy is slnlil
Fig 3.62 (0: however, in this case the drains flow is to the de-aerator head shown in Fig 3.57, but will
treated as hot water. minor differences to adapt the principles for 1)
The heat transfer coefficient is calculated as for an FXG.3.63 Tynieal arrangement of a lhorizon~aldirect contact LP Iheater, lncc B power station
heater service.
H P or L P internal drain cooler, using the temperatures
A water distribution header directs the inconii
indicated in Fig 3.62 (e). condensate through perforated windows in its "nil
The tubenest will have the same number of tubes Evaporators and other means of water Current practice is to use a chemical raw water
as the first LP heater for full condensate flow, and will treatment plant followed by filters and mixed-bed
have the same shell diameter as the L P heaters. deionisation plant. For the AGRs and for the pro-
The baffle pitch is determined by the need to main- jected PWR, a full-flow polishing plant in the feed
pressure.
tain the velocity of the water across the tubes to give The illustration shows the provision made to all train is provided to ensure the high quality of boiler
the needed heat transfer coefficient. feedwater.
the steam free access to the water cascading
The drain cooler actually used depends on the traditional method of producing high quality A full description of the raw water treatment plant,
the trays. Steam flow is directed to the lower
manufacturer's assessment of the most cost effective for boiler feed was to distil water by the eva- filters and mixed-bed deionisatlon plant, and a full-
of the heater t o ensure that water cascading f I
type for a particular installation. ration o f treated raw water. Treated water is boiled flow condensate polishing plant is given in Volume E.
lie evaporators by the application of heat in the However, to provide a complete description of modern
nest of trays from just below the cold water entry n of L P bled-steam from the turbine or a steam plant, the following section gives details of typical
point. ply from the auxiliary boiler. The resultant vapour steam evaporating equipment which is currently in
8.9 Direct contact low pressure heaters Double drain outlets are provided to ensure a ndensed and can be used to replenish the reserve use in large CEGB power stations.
In both thermal and mechanical design, direct contact quate drainage, taking into account the princip
(DC) L P heaters are very similar to a de-aerator heater discussed earlier in this section for horizontal I
head. They are cylindrical vessels arranged in either heaters. tment by the deionisation method has made it with a daily output of about 3% CMR steam flow.
the horizontal or vertical attitude, equipped internally The trays and perforated distribution inlet window conomic to install bled-steam evaporators for the The water treatment plant has also to provide water
with a means to maximise the heat transfer surface are made o f stainless steel to prevent eroslon/corrosioii. to meet the additional losses of two-shift operation.
Future developrne~ils

of the evapoiatoc plant u,Iiich ~pl-o\,idesthe necessary


tempri-aiiil-c variation tllioiigll llle evaporator for cffi-
cicnt heat transfel..
The vapour charnbei a l thc evaporator is connected
to a blo\vdown system which allows a calibrated floiv
of B,ater to be pumped out oftirc vapoul- chamber. This
fixed flow rate maintains the correct body concentra-
tion wileri the evaporator is on-load.
The purified water vapour from the evaporator is
condensed in the condenser by heat exchange wit11
condensate from the turbine. It is then drawn from the
condenser by a distillate pump and pumped through
a cooler/heater to the system discharge point. The
iii. 1.66 Sclieii~aiicdiagram of a L$I.O-SLB~C 'fiasll'
eVIIpolatOl distillate raises the temperature of the incoming feed-
water as already described. After leaving the heater/
cooler the temperature, presswe and conductivity of
the distillate arc checked.

9.4 Flash t y p e e v a p o r a t o r s
Flash evaporators have been available for inany years.
They have only emerged within the last two decades
I:i(i. 1.64 Typical airnllgernezil of a lioiizo~~rl
direct cori<aci 1.1' Ihcalci. Herrhs8r i lioi\'ez riatioil
li ensures circulation to the heating cham- as a viable proposition for large scale distiliation,
us heat exchangers are also added to increase due to thc fact that multiple-effect or multistage
I efficiency of the process. plant can now be built in the very large sizes required
the filling of boilers and the feed system after main- stage and is finally removed by means of an e feedwater is pumped successively through for potable water in arid countries. Thanks to modern
tenance, and the special needs of chemical cleaning pump. s/cooiers, a preheat and a vent vessel to methods of raw water pre-treatment they can also
and commissioning. tor. After vaporisation in the evaporator, operate continuously for long periods.
nsed into distillate and delivered to the Large multistage evaporators can be built econo-
harge point by a distiliate pump. mically on the 'egg crate' principle, each stage con-
sisting of a narrow vertical compartment in the crate
9.2 T y p e s o f bled-steam e v a p o r a t o r with raw water on its way to the heat input section
Two types of evaporator have been used by the CEGB traversing each compartment in straight tubes. Figure
(discounting the horizontal submerged coil type as 3.69 illustrates the construction of an experimental
inappropriate for large modern power station feed- 10-stage flash evaporator which has been in service
water treatment). with the CEGB.
The first is the surface 'Vertical-tube' type invented Since heat consumption varies inversely with the
by Kestner in 1909. Figure 3.65 shows the arrange- I, evaporator and condenser. number of stages, the flash evapoiator can compete
mcnt of a typical vertical-tube evaporator. The water re vented from the feedwater in a vent successfully with other forms of evaporation plant
inside the tubes is boiled by the heating action of by having multiple compartments or stages in a single
the bled-steam o n the outside of the tubes and a vessel. However, even this economic form of water
mixture of vapour and water is expelled from the lporator. It is then circulated to the heating treatment plant is not as cost effective as a modern
top of the tubes. The water spills into the central polishing plant for the production of boiler feedwater
downcomer and the process continues by natural cir- and no further installations are planned.
culation. The rising vapour passes through baffling
to reduce the quantity of entrained droplets thrown
up by ebullition and is then condensed in an external or vapour condenser.
vapour condenser. Any non-condensable gases carried MAxE,up,wLE,+
team condensate from the heating chamber, 10 Future developments

-
out with the vapour are vented. ludes that from the preheater, passes through The development of feed system design and its asso-
The second type is the 'Flash' evaporator. A sche- ciated components is dependent upon the cycle steam
matic diagram of a two-stage flash evaporator is conditions and the turbine-generator unit capacity
shown in Fig 3.66. The raw water is heated near to
saturation temperature of the heating steam and is
then cascaded through the evaporator in series, which
is at a lower pressure than the water. A proportion
-
;.:'.:,
.
WLIINCISIEW
IPY~POY~
IlEDWAIIR
CONTINUOUS
8LOWOOWN
chosen for the next generation of power stations to
be constructed by the CEGB. Present indications are
that non-nuclear stations will be coal-fired, with sub-
critical or supercritical steam conditions and a unit
of the hot raw water flashes in each stage and is capacity o f about 1.5 times the current 660 MW units.
condensed by the raw water on its way to the heat FIG. 3.65 ~ y p i c a larrangement of a 'vertical-tiibe' 1 lhese vessels and discharges to atmosphere. The need for the development of systems and com-
input section. The distillate cascades from stage to evanorator IC system maintains a vacuum at the hack end ponents for a number of specific plant areas has been
316
Feedwater hearing systems Future developments

PIO. 3.69 Diagrammatic arrangement of a lo-stage narh evaporator


identified l o tnicci the increased llo!\,s and ipscssoies Altl~ailgh thevninl traosieois can be redilci: lhavc l o bc deteiii,incd for each case. Iiowcver, in
t o be used for llic jprojectcd plant. ininimoin by i~idiviiliiaihy-passing of jprcccdin!! 1, gciiccal, i t is expccicd thal lank size c a n be reduced
studies indicalr that a decieasetl tank ca- t o aboill 5 miniitcs' IYO~III o r C M l l flow at normal
xsorking level, with thc tank placed at a significantly
reduced elevation.
plant \\.oilld bc utiliscd. the extra equipn~entio\,alved as well as imposiii

and LP fecd system: consider each in tiira. 10.3 LP feed system


typc o l heater can be oveicomc by using a 111 te of pressure decay (and hence the ability of It is expected that future large coal-fired units will
version o f the header type of healer similar i i i t i de-aerator system t o avoid boiling in the feed use a n LP feed system similar t o that already illus-
ciple t o that illustrated in Fig 3.55. T h e use n soction pipework during transients) depends trated i n Fig 3.6 for the PWR cycle (i.e., forward
10.1 HP feed system latest manufacturing techniques l o r a similar , amount of stored heat (i.e., hot water) in the pumping of higher pressure 1.P hcater drains with
~h~ increase i n unit size and possible use of has resulted in heaters which are currently gi\,i!l illd the rate of introduction of cold feed t o the the lower pressure heaters mounted in the condenser
critical steam conditions will increase the H P heater factory service in Europe and ~ m e r i c aas s neck). These will therefore bc n o significant changes
hcmi-head diameter and thickness. wit11 cuirent ~p R E 3.70. T o increase throughput of feed' in existing system design or components.
n has l o be m a d e t o prevent c o m m o n m o d e

lheating steam t o the LP heaters, as this intl-o-


11 References
Ill Durlseil, L.: 'A review oi the operaiioi)ai bchz~viosia81d
y. Diversity of operation o r the provision of deiign of direct colllacl iced w a l c i lhealiilg plar>ir for iarge
ergy local t o the valves would be a suitable Ihcrlllll poi<'cl slaliosr': Proc. IMecliL.. \?ol 187: 1973.
1.5 times that used when steam conditions are sub. of 1.5 times does not rcsult in a header wall 1 I21 Kiibie, J . , Koiue, M , and Jolles. E. \v.: 'Hydrodyiiamicaspec~i
critical, r h e increased tubeplate tl,ickness wi!l also which imposes operational restrictions d u e t o I or it,c deiigii or reed heateis aiirt rie-aera~or stalsse tailks.:
transients inducing unacceptable stress ievels i iiil techniques a n d suitable sequences t o avoid l'ai~ei CI40179 'Steam Tuibincs for 1980s. IMechE Sym-
need further development of. present techniques for l,osium': 1979
deep-hole (gun) drilling. O n e disadvantage o f thicker the header. T h e use of header type heaters i h 11scold condensate into a hot depleted tank.
sidered t o bc a n option for future stations as ail II I ;!Iternalive solution is t o provide a '!)egging' [31 Downs, J. E.: 'Forced outages of large steam lurbinos-an
tubeplates and hemi.llead walls is the increased sus. atiaiysis of causes': Vol 32, Proceedings o f the Amciican
ceptibility to damage caused by thermal transients native t o conventional hemi-head HP heaters. sllpply which would maintain the de-aerator Power Conference: 1970
inducing high stress levels. [dl Dickin~on, J . D, and McKiiiiey, u. E.: 'Turbine crfeclr
T h e perforated a r e a o f the tubeplate responds al- from steam and water ablloinlal cooling': Proceedings of the
most immediately t o the feedwater temperature change American Power Conference: 1970
caused when preceding heaters a1.e by-passed. T h e un- 10.2 De-aerator system i51 Reinhard. K. G. and Schalzsanii, G. P.: 'Teibine watel dam-
tors being supplied by UK manufactureis age pieventioil': t'iaceedinw or tile Amciicali Power Coa-
rs o\,erseas, require less suction head t h a n feiel,ce: 1972
ntly installed in CEGB power stations. T h e 161 SPence, J . R. Ilyall. M . L. and MeCoiinell, A,: 'Tlte develop-
11 which the de-aerator tank must be placed men1 md produciioil or lhigli pierssie feed heaters ray moderrl
with the potential of creating high local stress levels. size, it becomes increasingly costly t o accomlll central poivei $cations': Pioc. IMecilE, volume. 182: 1967/68
l o each boiler feed p u m p depends upon the
(71 Craiifield, R. K. and wilkmrun, D. H.: 'Analysis or poivei
plant de-aerator storage lank inriabililies': Proc. IMechE,
Vol. 195: 1981
181 Darfneil, L. M . : 'The liiennal-liydiaaiicdesign of main feed water
I1 in tank elevation. T h e elevation a t which pump suction systems for large lherrnai power plant': Pioc.
IMechE. Vol. 199: I985
191 Wilkinson. D. H. and Darlnell, L. M . : 'Ware' hammer
phenomena in thermal power station fwd water rystemr':
Proc. IMechE. Vol. 194: 1980
I101 Dailnell, L. M.: 'Hydraulic and thermal hydraulic iiisiability
ili condcnrate feed systems far large thermal power stations':
Proe IMecliE. Vol. 186: 1972
ion heads, then the combination of a small-
IIII BS55W: 'Splfieation for unfired fusion welded pressure vessels':
1985
1121 'Slandards of tubular exchanger nlaoufactureis assochion', Sixth
Edition: Addenda Address, Tubuiar Exchanger Manufacluiers
Asrociation, Inc.. 25, N. Broadway, Tariytovn, New Yolk,
30591: 1978 and 1982.
OWtM
0"TLeT
3 'Guide io the design of feed water heating plant': Publication
No. 226, the Brilish Eleciiieal and Allied Manufacturers'
AIsOeiation Limited, 8 Leicerlei Street. London: 1968
II4I BSlll3: 'Derign and mafiuiaelure a i water-tube stcam gen-
erating plant (including superlieaten, rehesuers and steel tube
Tic. 3.70 Ariangemcnt o f HP header-type lheafcr economiserig: 1985
320 321
. .

Feedwater heating systems


~~-

j IS] 12S1 S,n,~d;ivd 21-4: 'Scaiiilcri steel reed wale, lheaiel iiibcs carbon i ~ l o c e s s i ~Prac
~ ~ . 129: Al3ril 1970
lot lhigli prcsaiire a~,i~lratioss':Llcct~icitySapply I#~dusli?: 'lieu,
erd,anger desigl~ lhal?dbook': Hemispbclr I
Mavci, 1982 Corporation: 1984
l i b ) CEGB Standard 234102; GDCD St.psduid 56. lssae 2: 'Carboll e r .C, elid Crow, I. Ci.: 'Onrei o i I
~ ~ ~ . d i iG.
axid Allor Stocl Feed Watcr tieater Tuber': Dcceillbci 1980 supernate8~fFluid is Surge Tasks': Clieiiiicai
. . ,.,.,,,. . <. ,,,\.: ..,' i::i, ,,: .. science, Voli~me26, I'agec 211 lo 219: 1971
.. , , .. I I.. . ,I,. I ,. ,>,>
% ! ' ~ ' , . . , .?> h t
crasrieid, R R.: ' ~ r a i sdischarge chaiacterislics
I,. 1, ,,;. . .
. :: I .I: '.?: j ~ u i n a oi
i Mecl,allicd Engineering Scic C H A P T E R 4
[18j 'Sl~oisgren,I. T.: 'Predict exchanger lube damage': Hydro 23, No. 2: 1981

Condensers, pumps and cooling water


plant

8 Plant testing
8.1 Introduction
8.11 Test codes and practices
9 Future devslopment~
COnden~eisurface area. turbine exhaust pressure and
9.1 Aims and objectives
9.2 Resesrch end development
9.2.1 Tubenest layout
9.2.2 Thermal performance properties of tubing
PUMPS
10 Air e x t r s ~ f i o nsquipmenf
10.1 lotioduction
10.2 Determination of sir extraction quantity
vironmenfsi can~iderstions
10.2.1 The mechanism of air extraction
,1 Cooling weler quality 10.2.2 The condenser air cooling section
Corrosion prevention 10.3 Revisw of air extrsction equipment
Other copper-slloy tube failure mechanisms 10.3.1 Hydraulic air pumps
Matetlal seiection 10.3.2 Liquid-ring type air pump
10.3.3 Air ejectoripump Eystems
10.3.4 Steam eiactoripump systems
10.4 Quick-start plant requirements
10.4.1 Type of plant
10.4.2 Starting times
11 H Y ~ ~ B Y BI S
I cP B C ~ Sof centrifugal pumps
BEAMA design recommendations 11.1 Specific speed
CEGB specifications 11.2 Net positive suction head
nfluence of tubeplate and tubenest geometry on thermal 11.3 Suction specific speed
li.l.1 Subjective design evaluation 12 Circulating wafer pumps
li.3.2 Computer assisted design evsiuaiion 12.1 lntr~ductlon
12.2 Horizontal split-=sing pumps
12.3 Vertical pumps
12.3.1 Veriicai metal-casing pumps
Con~tr~cfionald~veloprnent 12.3.2 Concrele volute pumps
Construction mafarials 12.4 Gearboxes
Design forces and stresses 12.5 Shaft seals
Methods of manufacture and oonstiuclion 12.6 Pump testing
12.7 Materials
1 3 Condenser extramion pumps
Condenser tube cleaning system
Special consider~flon~ 1 4 Boiler feed pumps
14.1 inttoduction
Ollerationsl life limiting constraints
14.2 Feed pump developments
7.1 Condenser sir inleakage 14.3 Advanced clsss feed pump construction
14.4 Axial thrust
14.5 Gland sealing
14.6 Pump layout and drive
14.7 light load protection
14.8 Testing
7.2.3 Bubbler devices 14.9 PWR feed pumpsets
'1.24 Tracer g ~ methods
s 14.10 Future trends
7.2.5 Flame and smoke methods
7.2.6 Uitrasonic method 15 Miacslianeous pumps
1.3 Condenser fouling and 15.1 Sewice water pumps
7.3.1 Condenser fouling 15.2 Chemical injection pumps
7.3.2 On-load condenser cleaning 15.3 Fire pumps
7.3.3 Off-load condenser cleaning 1 6 Reference$
Condensers, pumps and cooling water plant Econoinics

CONDEINSERS iigurc 4.2 indicates thc componeni termill<,li


fur thc two iypicai arrangemcnis of thc ei,a)>o,oll
1 Introduction cooled and heated wale, systenis wl~icliwili hc ii
The ultimate heat sink for a Iargc thermal powcr tl~iougl~oul this chapter, and i t is intended to
station is the atmosphere. Ther; arc various options
avaiiabie, using different processes to achieve tlie
far reference purposes. I l i c follo\\,ing p
briefly describe the functional requirements
4 ATMOSPHERIC
AIRFLOW

mast effective heal sink, and therefore meet the rc.. of the plant components.
The screening pirrrii must i-emovc any debris l'rot STEAM
quirements of the condensing plant and cooling water CONDENSER
(CW) system. the cooling water which is large enough to block 11
Typical atmospheric heat dissipation systems are condenser or auxiliary cooler tubes. It must b ,
illustrated in Pig 4.1. Those most commonly used are: to keep clean, even during periods of excessive d ( 8 ) EvainidlVD EOD"S

The cooling ulaler (CW) pumps must circula


Process (a) evaporative cooling, associated with water against system resistance, o i pumping
closed systems (cooling towers) for heat dissipation. under all conditions encountered at a particula
To ensure efficient and flexible CW pump opera
e Process (b) heated water discharges, associated with
valves are usually provided to aiiow any combinzit (
direct cooled systems (rivcr or seawater) for heat
of pumps, condensers and cooling towers to opcit~
dissipation. SEAM
together. CONDENSER
In the healed >voterdischarge dixcl-cooled sysl
When considering a new site for a power station, it the cooling water (rivcr or seawater) is used oncc $11
is important at the planning stages to ensure that then discharged. In the evoporative-cooled closed cur
it has adequate cooling water faciiities. With increas- ing lower and mixed cooling systems, the coal'
ingly high station output and unit rating, the choice towers transfer heat from the plant to the atmospl
of location is narrowed by the necessity to match and the cooled water is recirculated. In this casc
available water resources. This along with equally water requirements are for make-up and purge pi
important factors, such as type o f fuel and selection poses only.
o f steam conditions, are the major features con- In addition to the condenser satisfying the prima
sidered when assessing the suitability of any site. functions, its design must also be capable o f meetit
In order for a steam power station to operate ail the failowing objectives:
efficient closed cycle, the condensing plant, CW sys-
tem, and associated pumps must extract the maximum T o provide the turbine with the most econon
quantity of heat from the exhaust steam o f the LP back pressure consistent with the seasonal variatio
turbines. in CW temperature or the heat sink temperntlr
The primary functions of the condensing plant are: of tlie CW system.
To provide the lowest economic heat rejection T o effectively prevent chemical contaniinatiot~ n
temperature for the steam cycle. the condensate either from CN' ieakage or (toe
T o convert the exhaust steam to water for reuse inadequate steam space gas removal and condenssfit
STEAM
in the fced cycle. de-aeration. CONUENStR

T o collect the useful residual heat from the drains The aim of the designs is to ensure that these ob
of the turbine feedheating plant, and other aux- rives are met within the framework of the followi PUMP
iliaries. practical considerations:

The aim of the C W system Is to maintain a supply Econon~iesof size, space and pumping power.
o f cooling medium to extract the necessary heat, in
order that the condensing plant can meet its objec- Ease o f maintenance and construction.
tives. It achieves this by the use of effective screen-
ing equipment, circulating water pumps, valves, and
.. cooline- towers.
(where necessarvl
The economics, design, construction and functional 2 Economics
requirements of the above systems and associated The detailed design of the condenser and its a
plant components are discussed in detail in the sec- ciated CW system requires careful optimisation
tions which follow. parameters which include material selection, coolin
Since many pumps of different types and duties water flowrate, condenser surface areas, and turhin
feature in the above systems, aspects of their design exhaust pressure, etc., in order to harmonise 111
are collectively considered in later sections o f this
chapter. These include condensate extraction pumps,
performance inter-relationships between all t
ferent plant components, and to produce a
14
cooling water pumps, circulating water pumps and offering maximum efficiency and reliability, and
feed pumps. mum running and maintenance costs. Flc. 4.1 Typical atmospheric heal dissipation systems
Condeiisers, pumps and cooling water piant Econolnics

lar attention must bc paid to direct-cooled a Cooling water fiowiate


e Number and size of condenser tubes - lhclice tube
length and Slow velocity in the tubes.
r Basement height.
e Scai pit wcir height.

and lake cooled stations (of which thcrc is


ne large example in Britain) take a n intcrme-
.
e Culvcrt flow velocity - hence cuivert size
Culvert length - usually fixed by external con-
siderations, e.&., avoiding recirculation between
inlet and outlet.
position as far as water quality is concerned.
iving identified these technical inconsistencies,
basis of an optimisation study is to achieve a From the culvert velocity and length, and other para-
iilicc between capital costs and operating costs, meters, the CW pumping requii-ements can be detei-
I!, the lowest overall lifetime cost. mined. A typical assessment procedure is illustrated
in Fig 4.3.

Condenser surface area, turbine exhaust 2.1.1 Input d a t a


Referring to Fig 4.3, headings 1 to 6 represent the
('1 Heale* aa,sr dlrcllsigo systam different items of input data which should be as
representative as possible. Listed under each beading
lnccessary to optimise the desigu of the various are the different parameters which collectively con-
stitute the item o f innut data. Relevant information
or cstimatcs should be available on parameters such
as station load factor and seasonal variations in sea-
riling to its own set of design rules, using 'fixed' water temperature, and values must be decided for
ce parameters based on a combination of pre- parameters such as auxiliary power consumption, and
experience and engineering judgement. However, the capital costs of different plant items. Finally,
of these 'sub-optimisations' are in fact inter- pump characteristics and system resistances are re-
dent, for example, variations in the civil costs quired, from which pumping costs can be input.

2.1.2 Computation
The problems to be solved can be classified into thrcc

eally to calculation by computer. .


basic types:
The first type of calculation is based on a single
set of parameters to determine the predicted per-
formance of the system. This can be used to com-
pare the overall costs of a small number of discrete
options.
It creates a mathematical model of the system,
The second type of calculation is a frue opfimisafion.
The single calculation described above is repeated
many times for a grid of values defining possible
CW flows and configurations of condensing surface
,b, Evaporative maad *"Yf*f
(i.e., number and length of tubes). The program
identifies the lowest overall (capital and operating)
cost at each stage and, after a number of iterations,
1. FOREBAY AND GATE AREA (3. ! N E T E N 0 WATERBOX homes in on the optimum within the applied con-
2 CWIINOWA'IER tCW1 SCREENS 11. OUTLETEND WATERBOX straints. This type of calculation is important for
3, DRAFIIUBE 16. I I I B E P M E ASSEMBLY
4. CWPUMP
5. CW PUMPDISCHARGEVALVES > I . W&TERBOXACCESSDWR
16. TUBESUPPORTPLATES determining the most appropriate CW flow and
6. CWCULVERTS
7. CONDENSER iNLEi ISOWTING VALVE
78. TUBES
19. CONDENSATE OUTLET
condenser size for a new site. Figure 4.4 shows
8. CONDENSERSHELL 20. EXPWSION BELLOWS procedure involved in achieving a realistic typical graphical presentation of the results.
9. CONDENSER OUTLETISOLATING "&LYE 27. AIR EXIRACTION BAFFLE
70SURGECHI\MBER 22. AiR EXTRACTION
in parameters to be optimised are: The third type of calculation is the sensirivify study.
This involves r e ~ e a t i n g the optimisation process
~ndensersurface area - hence the vacuum, assum- for a range o f values of one particular parameters,
FIG.4.2 Terminology for major plant comnonenls g that a n efficient tube layout is adopted. such as power cost, to examine how this affects

326 327
Condensers, pumps and cooling water piaiit liistorical developinent viid layout
..
sullcd in consislenr concepts of condcnsiog plaiil mcnls were niade in sevciai other aspecli.
iayout. feature of these coridcnsers was that they a
Tlie costs incurred in exterisivc design work, and singlc-shell design; otherwise they differed cai
the development of special manufacturing techniques, Tlie most obvious differences relate to thr
have becn spread over a large number of units which arrangemenr. Figure 4.5 (a) illust~.ates e
have progressively benefited from minimised commis- arrangement, and Fig 4.5 (b) an axial a i .
sioning problems, and increases in service reliability Each o f these has advantages, as will be
and maintainability. During this "criod the size of latel. sections. When considering thernlal p
generating plant bas also progressively increased from the transverse design is simpler and easier i
120 MW to units of 660 MW. A difficulty with the axial condenser is thsr t i
Standardisation of approximately fifty machines tubes naturally result in a rather large dificrclt
was achieved in two stages: first at a unit sire of 120 thermal performance between inlet and ooilel
MW, and later at a unit size of 500 MW. The latest so making the effective extraction o f non-con'
machines a f 660 MW sire represent an evolutionary more difficult.
development: at present, there are some 23 machines The axial arrangement, however, has a c;lpiii~l <a,Am,," ude'nung
at this rating either in service or under construction advantage because o f the smaller number of (I
in the CEGB. rubes involved. This results in a saving in $11
Certain features associated with 660 MW turbines of manufacture of the expensive tube piarcs.
have had a major influence on the development of allows a simple turbine-generator foundation i
condenser design and iayout. In order to appreciate ment in which the LP turbines are suppoi
the significance of these features, a slight digression parallel foundation walls, one along each sic
to highlight the development of their design is worth- process of tubing the condenser can use ti1
while. under the electrical generator, which is kept
Single shaft turbines running at speeds of 3000 major plant items for this purpose.
r/min have become increasingly compiex, as set rat- Again, due to the length o f tubing involvc~l
ings have increased by increasing the steam mass an axial design, it becomes necessary to
flow. Increasing the steam mass flow has demanded sures to avoid large scale axial migration o
a need for multiple L P exhausts with last row turbine towards the cold end, which may invoive ado
blades approximately 914 mm long, and a n exhaust opposed cooling water flow. This can be don
area of approximately 6.7 ma. having two separate water passes with the Fi<
While the turbine n~anufacturers (each of which opposite direction, as illustrated in Fig 4.6. Sc
has developed its own blading design) have made arrangement can complicate the culvert layout, r
improvements to details such as aerodynamic pcr- water pipework and valve layout, and result i>
formance, erosion shield vibration characteristics and ditionai costs. Desienine the condenser as ;I

exhaust blading has increased the operating capability tion and is now standard British practice for: ;ax
to very much higher specific steam loadings. condensers.
Economic considerations have also favoured substan-
tially increased turbine exhaust specific loadings. This
is reflected in the 660 MW machines at Littlebrook D,
where a four LP turbine exhaust design - .(of aooroximate-
., 3.2 Phase 2
I! 7 . 3 ni2 annulu, area per r \ l ~ a u , t )h3s becn adopted This phase covers the remaining 500 MW units 1,
S t r ~ c t u r arela~ioltchtp~
. bctueen turb~neand ~ ~ u d c n c r r . all excevt the most recent 660 MW units. Conlnilt
~ ~

and the method of overall support, have also developed with phase 1, it is characterised by a radical
as unit ratings have increased. ferent design: the axially-tubed side-mounted coil
Three main phases of design exist within a period o f ser. The develooment of the side-mounted cond
development which covers early 120 MW plant right coincided with a general move towards the us
through t o the present 660 MW plant design. Justifica- steel foundations.
tion for these various changes are now discussed. In some arrangements, this becomes a 'pan~i'
design as shown in Fig 4.5 (c), in which conde
and turbine are seoarated and connened
~. ~ ~ to .~
. . . ~ ~
other by short ducts (either rigid or with fl
3.1 Phase 1 bellows, deoendina. upon. the details o f the tur
In this phase, which covers about half the total num- and condenser support arrangements). In other case (dl """I" P'""8e'
,E,And,iy ,nlBgrBl
bet o f 500 MW turbines, the underslung condenser the condenser and turbine are combined to form ti
arrangement used on previous 120 MW and 200 MW 'integral' condenser design (Fig 4.5 (d)) in which 11
units was retained. The reinforced concrete turbine- condenser shell encloses both the condenser tubes art
generator foundation block was kept, but develop- the low pressure turbines. FIG.4.5 Condenrcr eonfiguratianr for recent British 5W and 6W MW units

330
Coi~densers,pumps and coolihg w a l e , platv
Enviroritncntal considerations

aries or major sivcrs. Corrently, o\iei 40% of opcrational


statioiis are placed in silcli locations and are therefoi-c
Illc turbinc hall, and tlic question of acces- subjected la a wide variety of cooling water conditions.
ti llle LP turbine for maintenance. A typical water analysis can coiuain abrasive sand
particles and marinc life. Debris and cyclic tidal var-
iations affect tube velocity and promote two-phase
flow under syphonic conditions: this is particularly
damaging to condenser lubes and CW system ma-
lhcildy mentioned, economic considerations have terials. It is against this background o f operating
111s led to a preference for increased turbine ex- experience that a broad knowledge of materials has
been accumolated.
Fortunately, the position is less severe with the
tionship between condenser and turbine. Othcr operation of inland power stations, where cooling
have also promoted a move away from the water quality is generally satisfactory. There arc, how-
,tinted condenser towards an arrangement in ever, instances of condenser tube corrosion due to
BOILER I~OUSE i i each low pressure turbine is combined with its products of biological decomposition and operation
1i;insversely-tubed underslung condenser. This ill polluted waters.
llic advantage that it allows the development of It is important to secu1.e information concerning
xliilar LP turbine/condenser design so that one, C:W quality as early on in the planning stage of a
three modules can be combined to cover a power station as possible, since it forms the basis
SINGLE PASS UNI OIRLCT~ONOL,:LOW ingc of possible ratings, for example, 200 MW upon which material selection will be made later. A
IC module, and 600 MW or more with three survey o f other industries using the same water sup-
ply, along with the local water authorities, is o f
tremendous value in identifying the history of CW
quality. Meanwhile, systematic monitoring and dis-
CW PUMPS
cussions with Local authoritics yield information on
the current situation, and on possible future develop-
thcse few remarks, it is clear that the choice of ments which may influence water quality.
nser for future large turbine-generator plant Lack of attention to this type o f detail often leads
to favour the transversely-tubed underslung con- to the wrong choice of materials. In condenser tubes,
his seems unlikely to be reversed in the for example, tube perforations and condensate con-
tamination levels exceeding the boiler water chemical
requirements [I] can have serious economic conse-
quences. If leakage of CW into the condensate per-
sists, costs can be incurred from tube replacement,
Environmental considerations loss of availability and consequential damage to other
sections of the plant, such as boiler tube failure from
)ndenser relative to the turbine, another very feedwater chloride contamination.
These problems can be avoided and the associated
costs minimised by combining the detailed knowledge
accumulated on CW quality with that associated with
tlle known corrosion performance o f condenser tube
BOILER HOUSE
BOILER HOUSE materials, which forms the basis o f material selection
to prevent premature corrosion and erosion of strategy discussed later.
components, due to dissolved and suspended
4.1.1 Corrosion prevention
SlNGLE PASSP-DIRECTIONAL FLOW Copper alloys form the basis o f traditional condenser
tube and tubeplate materials, typical chemical composi-
1 Cooling water quality tions of which are given in Tables 4.1 and 4.2.
PIG. 4.6 The effcci of undirectionai and iwo-directional condenser cooling water now an syrtcm layout
Copper-based condenser tube alloys rely for their
corrosion resistance on the passivating action of a
protective film of corrosion product which forms when
The side-mounted and integral design styles have chine and condenser can be reduced quite significa~~ e and erosive effects of the cooling water. These the tubes enter service. Under conditions of turbulence
several advantages. Compared with the equivalent (typically the condenser tubes are about 20 m 10s
ects are discussed in more detail in the subsections and excessive water velocity, this protective film can be
underslung condenser, the steam flow path between The turbine centreline height above basement, and he, corroded/eroded from the tube surface, exposing the
the turbine exhaust and the condenser inlet is wider, the crane height and overall turbine house height, c The demand for substantial quantities of cooling bare unprotected surface and thus promoting further
and the losses smaller. Because of the reduction in also be reduced by, typically, 4 m. However, 111 lter leads to an increasing tendency for large power attack. Such unfavourable conditions can occur in
exhaust casing length, the overall length of the ma- advantages are partly offset by other factors. 7'11 lions to be located on the coast and on the estu- condensers operating with high water velocities or
332
Condensers, puinps and cooling water
Environmeiital considerations

ions wbicli lead to air relcase (e) IlTirroi)uni~debrir.


i!lcatly increased local ivater velocities due to
cilce. For each material, tliel-e is a threshold if) M"sseiJouling.
velocity above wlriclr attack of this type will
( a ) General in?pinge,ricrir allack Inrpinge~nent attack
le breakdown velacitics for the
is characterised by an overall surface roughening
film O n brass and 70/30 cupso- slid horseslloe.sllaped undercut [he extent o f
5 re 2.5 m/s and 4 m/s respectively, compared
-
S 'i
G
z sign water velocities o f the order of 1.5 m/s.
which depends upon the extent of local turbulence
(Fig 4.7). The attack is aggravated by water con-
most common tube failure event is corrosion/ taining a high suspended.solid burden, as is the
5 ement attack, which develops case with condensers operating in con.
'Z0 'I v ses. These are dealt with under ditions ,,,llere lligh tidal rates are experienced, r h e
0 a lollowing headings:
i resistance t o impingement attack of conventional
(i<,neral irnpingemenl ulrack.
copper materials is illustrated in Fig 4.8. They all
Y exhibit a threshold water velocity value, and are
c
e$ c.,mz: liable to suffer from attack under conditions of
2 high water velocity.
(b) Inier end impingement urrack Inlet end attack is
Iron oxide scale.
s -5
a localised form of impingement attack associated
- - $
2
:..?
2 -
F9$2
.e z
.$ -
O O O Z : :

LOCAL IMPiNGEMENi ATTACK ON


ALUMINIUMBRASSIUBES

FIG.4.7 Condenser tube impingement attack


INCRChSING PROBP*IILI1Y
OF PRFMATURC FAILURE i N
SEAWATER (MP4NCIEMENI
ATTACH

NORMAI. W h i t " VELOCITY m - s

Fit. 4.8 ~'robabiibiyo r ii~ipinperneritattack in seawasel

with high inlet water velocities and air release. If impingement attack cannot be controlled EXAMPLESOF TUBE
PLUGGiNG
The attack has the same characteristics as general ventive maintenance, consideration can be g

suspended-solid burden. It has been suggested throat inserts (Fig 4.9). These are nylon inserts 1

lance of the material to impingement attack. the insert initially absorbs water and effectively
itself into the tube.
(c) Impingement arrack af iodgcddebris General debris Thelc is a 0,24 m,n feather on the
causes 11artial blockage of the condenser tubes
edge of the closely to the tu
and gives rise to high local water velocities of thc
to pl.event significant disturbance to the waleilio
Order Of m/s. This the threshold value Tests confirm that erosion problems from debris loci
for conventional copper alloys and causes severe
in these inserts are contained and cause no dama!?c !
highly localised impingement attack.
the tubes.
Tube failures caused by general debris can be
minimised by concentrating attention on removing
the source of the problem.
4.1.2 O t h e r copper-alloy t u b e failure mechanis
(d) Iron oxide scale This is produced from the cor- Other types o f copper-alloy tube failures can oc
rosion of carbon steel waterbox and CW pipe- and these are briefly reviewed under each of the
work components and is prevented by applying lowing headings:
cathodic protection or by protective coatings (see
Section 6.2.3 of this chapter). The oxide scale (a) Deposil nflock.
which forms as easily dislodged 'plate-like' sheets,
becomes lodged in the tubes and causes failures (b) corrosion.
due to highly localised impingement attack. (c) Stress corrosion cracking.
(e) General wolerborne debris This is produced from Corrosion ,ofigue, FIG.4.9 Condenser tube reduced lhioal inserts and rubc piugr
ineffective screening plant allowing shells, wood
and marine debris to pass, in addition to debris (e) Steamside ommonia corrosion.
from the culverts in the form of concrete spoil.
(f) Mussel fouling This is caused by ineffective (a) Deposit attack Deposit attack on condenser tuba
use of low level CW chlorination or bio-fouling occurs under conditions of stagnant or low watc
equipment. velocities, generally less than I m/s. Depositio~
Condensers, p u m p s a n d cooling water plant

o f iocil materials, such as sand and sill i,articics, conditions (Fig 4.10).
causes oxygen depiction at the particle-to-tube ma-
No1 spar co,7osiu,i 'l'liis rorm o f locali
teriai interface, leading to diffeicntial aeration and
Colrosiol7 occurs at 'hot spots' a n lllc
anodic dissoiution of the tube material. The pre- tube wall which can occur because of i
sence of decomposing biological materials and pol- velocity and/or high heat fluxes. Thesc coil
luted water, particularly sulphide-containing water, can be caused by paor stcam distribinioii
accelerates this type of attack. Deposit attack call absence of water on the cooling water sid (2,) 1.OCill Iligl, l",l,pela,,,les 01, i l l C ",,,side of iilbes
be experienced in both inland and coastal power can lead 10 abl>or~iialirrapid currosioi?al coiieipondilip
tube. The cupro-nickel alloys are less resisl ipositi081~081 i l ~ eillside (cooliiig water ride) of tile tubes.
stations, particularly in Iocatiol~swhere polluted aluminium brass t o this typc of attack. !lo! Hot S I > O ~ ~oirobioiitakes the form o f a highly locatiscd
waters are used. this form of attack is rarely experienced ' ~ i t t i i l gattack, a eliaracieristic feature being 11,;ti t l ~ cpiii
By maintaining the cooling water velociiy in often coniain meialiie copper. he iilosiiatioii shows a
steam condensers as the steam side tern arclion illlougha pit filled witti s,elallic eopilez produced
the tube above I m/s and avoiding stagnant con- are not high enough (Fig 4.11 (a)). by a iiol sliof attack in a copperf100lo >nickel alloy tube.
ditions in aggressive media by flushing and peri- Problems can be exoerienced in the dullll~al#&im@$%j.
odically refilling the condenser with town water sections of the condenser or in sepalxic
during shut down, major deposit attack may be steam condensers with high superheat, where
prevented. However, a permanent solution can be steal11 impingement o n the tubes occurs. l:el
achieved only by the selection of a more resistant in titanium tubing can provide a satisfacl<
material. Such materials are the 70/30 and 90/10 tion or, alternatively, an engineering sol
cupro-nickels (of which the 90/10 is claimed to avoid direct steam impingement such as re
have the better iesistance) and titanium. Titanium of steam flow can be found: the introduciio
offers the best solution, as it is immune to this effective steam desuperheating is also con
type of attack under normal condenser operating t o be a satisfactory option.

(E) Failure of rubes by cracking can occur as a roruit of


the combined action stress and corrosion. In coriosion

FIG.4.10 Pitting resistance of titanium corro~ioncracking and ~orrosianfatigue cracking in tubes


339
Condensers, gumps a n d cooling water piant Tliertriai design

(c) S1res.s corrosion oockiiig Failure of colbdeiises the iemperalilre diffei-encc between the turbinc ex-
tribcs by cracking ondci the combined action or ei'fecls. isuiating against galvanic action. haust steam arid the cooling watci is as low as pos-
tensile stress and corrosion has occurred in !he construction, tubeplates manilfaciiired sible if the bcnefils o f the Rankine cyclc ate to bc
pas1 owing to high residual tensile stresses inad- e Compatibility with other CW sysrein mateli;ilr, realised, providing tlial the ~neclianics used are con-
iilotninium bronzes ASTM-BI71 Alloy D, and
vertently remaining from the tube making process. M.lil7l Alloy E, have couple potentials with ti- sistent with previously discussed economics o f platit
However, with modern coadense~.tube production Experience has indicared lilal studies of 11 bes of -215 IIIV (SCE) and -133 mV (SCE), optimisation.
practice, such failures are now uncommon (Fig yield materiais which initially appear to bc an ly. The co~.rosioilrates of aluminium bronzc
4.11 (b)). sivc choice, hut because of their inherent11 I tes are therefore low enough to allow their use
Cracking can result from stress corrosion at corrosion-resistant properties show a higher ccoi,<i~ IOIXI any protective coating. The waterboxes, how-
the tube-to-tubeplate expansion joints. The cracks return when plant availability and retubing cosls tile still protected with suitable coatings as in a
initiate at the edges of the expanded regions on taken into consideration.
5.1 Theory
the CW side of the tube and propagate into the The condenser is the beat sink for steam power plant.
vice trials have been carried out at a number
tube wall under the influence of residual stresses The condensation process is accomplished by the
Copper-based malerials r stations, listed in Table 4.3, under various
remaining from the 'rolling-in' operation. The cor- transfer of heal from the steam exhausting from the
conditions ranging from the particularly
rosive medium is suggested to be ammonia, formed As previously illustrated in Fig 4.9, the copper-b turbine to the water used for cooling. Steam is con-
sand-laden waters of Bristal Channel power
from the decarnposition of oiganic slime, and con- tube materials are liable to varying degrees densed at substantially constant pressure and its heat
centrated by evaporation during outages. Effective lo the pollutcd environment experienced by
pingement attack, depending upon the operatin content (enthalpy), which is given up, raises the tem-
media control such as washing with cleaih water de power stations.
ditions. Thcse matel.ials, however, can be o perature of the cooling water as it flows through the
before prolonged outages or fitting protective sleeves, lowing the satisfactory performance of the ti-
employed providing that a good margin of tubes (Fig 4.12). Referring to Fig 4.13, which illus-
1111 tubes in these trials, two condensers were
appears to provide a solution to this problem. is maintained between operating conditions aoil trates a basic heat flow diagram, there are three factors
impingement attack threshold, and providin~!, I I rllcil with titanium; one with seamless tubing and
which determine the enthalpy of the steam at the
- can occur ill, seam-welded tubing. Results from these

.
(d) Corrvsion .fati,eue
. Coirosion fatiaue steamside corrosion conditions are satisfied. M'll turbine exhaust:
in any tube material and is caused by steam buf- freedom from erosion or steamside corrosion ctizii onfirmed that the tube installation procedures
feting, or structure-borne vibrations, in association be assured, it is necessary to use a matcrial s~lclt sequent service has been satisfactory.
The conditions and heat content of the steam leaving
with inadequate tube support. Generally, failure 11years ago, titanium was considered extremely
titanium. the boiler.
occurs at midspan where tube thinning occurs due c and unlikely to become economic.
to excessive movement and contact with adjacent st constraint on the use of titanium tubing The efficiency of the turbine in converting this heat

.
tubes (Fig 4.11 (c)). Additional support plates or Titonium bu minimised by a reduction in the required energy into work.
the fitting of antivibration damping equipment Over the past twenty years, work has progressed wall thickness, This, coupled with savings ex-
solves this problem. tile development of titanium for use as a condcn I lrom leak-free operation, establishes the use The selected heat sink temperature
tube material. Its major attribute is a tenacious o anium as a n economic material for power sta-
(e) Stearnside ammonia corrosion Aminonia corrosion film, which rapidly repassivates if ruptured under z >ere aggressive attack is either experienced or

usually attacks brass alloy air cooler tubes in the ma1 condenser operating conditions. Jet impingem 5.1.1 Heat rejected
form of pits on the external tube surface, with tests on both welded and seamless titanium tubing result of the favourable in-service trials and Equating the total heat per kilogram o f steam leav-
grooving at points adjacent to tubeplates and sup- water velocities of 10 m/s for 60 days have slio ~g economic competitiveness, titanium tubing ing the boiler 11, wit11 subsequent heat losses 11,. h b ,
port plates [2]. Titanium and the capper-nickel the material to be immune to attack. Under tb h,, and the heat equivalent of turbine-generator work
alloy tubes are highly resistant to this form of conditions, aluminium-brass and cupro-nickel tub I tittack of the condenser is considered possible. output h,v, then the heat at the turbine exhaust 11,
attack and the problem can be solved by retubing failed rapidly. Titanium tubing manufacturers (Imp tests, which are carried out at new power can be represented by the equation:
in an appropriate material. Metal Industries Ltd. [3)) quote impingement at oil sites prior to the ordering of titanium, confirm
threshold values of 20 m/s in clear seawater ar I in all cases the corrosion resistance is good, and
m/s in water with a high sand content. Thus, even 1 no operating problems arc envisaged.
4.1.3 Material selection localised tube blockages where water velocities
The need for a materials selection strategy has been rise to 6 m/s, the tubing retains its resistan The heat flow rate rejected to the cooling water @,
touched upon briefly in the consideration of CW qua- impingement attack, whereas this velocity woul is found from the equation:
lity. The objectives of such a strategy are to ensure beyond the reliable range of the copper-based mat
that the costs associated with leaking condenser tubes (Fig 4.8). Thermal design
are minimised throughout the life of the plant. This The use of titanium tubing in condensers desigl c preceding sections outline the functional require-
can be established by studying the following technical for conventional copper-based tubing materials, 11 of condensing and C W systems, and illustrate
and economic considerations: ever, poses a problem of incompatibility between tu ciivironmental studies into cooling water quality where q, = CW flowrate, kg/s
tubeplate materials. tiiken into consideration when choosing the geo-
The estimated life of candidate tube materials from Couples of titanium and naval brass, and titanium a1 lhical location of a new power station, and how
test rig trials, manufacturer's literature, experience, iron/steel have junction potentials of -288 mV nt Added to this is any heat rejected by drains from
aspects, in turn, affect the economics of plant
etc. -660 mV respectively, in relation to a saturated cal feedheaters, etc., which may be discharged within the
me1 electrode (SCE) [41. This creates the potential p 4 ,hasis has been placed on the importance of condenser.
The predicted number o f outages and associated
costs. blem o f anodic attack of the tubcplate material wh selection of materials in order to avoid un-
could lead to penetration of the tubeplate within bly high availability a n d maintenance costs.
The number of retubes required. design life of 30 years. Where naval brass tubeplat eration has also been given to the choice o f 5.1.2 H e a t t r a n s f e r
have to be used, such as in retubing situations, 111 le and condensing plant arrangements. The heat is transferred to the cooling water across
The capital costs of materials and retubing costs. practice has been to coat the tubeplate and waterbo Ihc objective of thermal design is to ensure that the condenser tubes (Fig 4.14).
340
Condensers, pumps and cooling water plant

FIG. 4.12 Typical steam now pattern in a condenser

~nyheating or cooling process, the resistance to the outlet.


transfer determines the relative temperature of Wet steam enters the condenser and condenses
nted and cooled fluids. completely at a constant temperature t,K, as it passes
total resistance of the tube to heat transfer is over the condenser tubes. These processes are re-
ned by the sum of: presented in Fig 4.16.
Consider an element of tube length dP where the
cooling water is at t, and the condensing fluid is at
. [he resistance of the condensate film on the t,. The temperature difference is (t, - 1,) = 8, and
steamside of the condenser tube, m2 K/W a small amount of heat, dm, is transferred across
the element. From Newton's Law of cooling,
lhc tube metal resistance, m2 K/W

the waterside film resistance, m2 K/W


a = UA (t, - t,) (4.1)

and therefore
al resistance to heat transfer RT of the tube
d.P = (aD dP)U0 (4.2)

RT = R, + R, + R, m2 K/W
where D = mean diameter of tube.

overall heal transfer coefficient U, is inversely


The coolant increases in temperature dB, along element
ortional to RT therefore:
dl, and the heat received is

U = l / R T w/m2K
d+ = q,,c, dB, (4.3)

hmic mean femperature difference (LMTDJ


where q, = mass flow rate of coolant, kg/s
msider Fig 4.15 which represents a condenser. The
oiing water enters the condenser tubes at tempera- c, = specific heat of coolant, kJ/kgK
re t W l K ,and its temperature is raised to tW2K at do, = temperature increase of coolant, K
343
-
I herinal design

B,, .. (L2 I )/Iiog,,(i\ I \$,i)/(I, iu2)1 (4.9)


TOTAL IIESISIANCL $3.
.....-.----4
O,,, is kno\!,n as lire Iogaiitl~mic mean tempeiatlll'e
differcncc (LMTD).

Finally, tire total surface area o f the tubes can be


capressed by

A = 4,/UO,,, (4.10)

where A = total mean surface aiea o f the tubes, n12


4, = rate of flow of heat, kW
U = overall heat transfer coefficient, w / m 2 K
O,,, := LMTD, K

5.2 Design codes. standards and


,:Our ,NcMlaiE nS,oE specifications
Dacunlents exist which are based a n the design theory
outlined above. They arc generally used as a guide in
CWI.ING WATER
establishing condenser size and design, Tile validity
of these documents is sufficient to ensure that coo-
CONDENSATE
EXTRACTION PUMP denser selections will meet specified performance. They
include:

The Heat Exchanger Institute (I-1EI) Standards for


- TOTAL HEAT OI STBAM LEAVING THE BOIiER

.
I>
-THE RADIAT~ONHEAT LOSS Steam Surface Condellsers [ 5 ] .
-THE BEARING HEAT LOSS AND MECHANICAL LOSSES
b, "4EGtNER"IORClASAND LiOUIOC001.FR HEAT LOSSES
nh,, H E A T ~ TTURBINE ix~nusr
T O T A L HEAT OF THE CONOENSATE FIG. 4.14 Ilea! tlal3riei reiisiancei vlld fillni The Brilisil Eiectricai and Aliied Manufacturers
n, .- ~ ~ a r ~ a u v a ~ t i r i o i r u nGsEi Nr Er R~~ O H ~ Y O R K O U T P U T
Association (BEAMA) publication 011 the Recom-
mended Practice for 1be Design of Surface Type
I'iC 4.13 Basic heal flow diagram Steam Condensing Plant [ 6 ] .
1/q,,c, = - O*)/Q.

These documents provide a comprehensive treatment


rce substituting into Equation (4.7), o f surface condenser perforlnance and describe levels
Let the incremental increase in fluid A temperature Substituting this in Equation (4.2),
of performance which can be obtained from well de-
dt, = dB, then substituting into Equation (4.3,
signed condensers.
dO/(l/q,,c,) = (aDdP)UO log, = aDPU(Ol - 82)/Q The objectives of thermal design procedures will
be reviewed in relation to the relevant codes and
dB = dQ/q,,,,c, (4.4) standards.
therefore d8/8 = a D U ( I / q , , , c , ) d P
icrefore 4, = aDPU (el - 82)/Yn(%i/82) (4.8)
Integrating Equation (4.4) between sections 1 and 2
5.2.1 HE1 Standards
(Fig 4.16), Integrating Equation (4.6) between sections I and 2
'3 = These standards [5] use four basic equations in sizing
rature condensers:
02 - 8 1 = @(i/qmwc,v) (4.5) log, O 1 / O 2 = sDPU (I/q,,c,) erence, Om, is given by
Mean temperature dgference The logarithmic mean
temperature difference is expressed as follows:
Also from Equation (4.4), (where P is the total length of the tube) 8, = (el - @2)/logn(@l/82)
t2 - t l - 8, (4.11)
8, =
d* = dO/(i/q,,c,) From Equation (4.5), nce O l = (I, - t w 1 )and 82 = (1, - t,",) 0 t -I -t log, (81102)
344 345
Condenseis, pumps and cooling water p l s i ~ t (
- ..
o.f/feot trc,,zsj>r'I'hc coefficicnl of ikal
>il%iniendedby l i l l is cnprcssed by rhr
6 Cooling water i~elocilythrough lobcs

U = F , F 2 F, C (I1)'? (4.12) 7 Effective ileal transfer surfacc, which is a hinc


tion oi:
C = correction factor for tubc diameler, e Number of tubes.
e Tube length.
\J = tube water velocity, m/s
a Tube diameter.

9 Tube thickness.
,,trier Equarion The Fourier equation for
tional heat transfer is used lo express the 0 Tube material.
lieai flow in terms of heat transfer surface e Number of cooling waler passes.
cacfficient of heal transfer and meari teni-
lii. difference and is written as follows:
8 Service conditions:
r Tube cleanliness
q,,,L = AUO,,, (4.13)
r Air inleakage.
CONDENSATE
OUT
=
11,,>~ mass flow rate of condensed steam,
5.2.2 BEAMA design r e c o m m e n d a t i o n s
1. = specific latent heat, kJ/kg The thermal design procedures set down in the BEAMA
design recommendations (61 are very similar to tilose
followed by the HEI, except differences occur in the
linionce Equation This equation is usually statements regarding tube cleanliness, and the correction
factor for cooling water temperature as applied to the
overall heat iransfer coefficient (Fig 4.11).
The curves for the BEAMA heat transfer coefficients
qmsL = q,,,,cor (4.14) are based on tubes in the brushed-clean condition and
include an allowance for the normai oxide film coat-
ings which are an inherent feature of any tube during
<I,,,,, = mass flow rate of cooling water, kg/s its operational iife, whereas the HE1 curves relate to
c = specific heat of cooling water kJ/kgK tubes in the clean, as-new condition. In addition, the
BEAMA curves for cooling water temperature cor-
rection are based on a mean temperature, and not on
tube inlet temperature as in the HE1 curves.
Taken collectively, these departures have very little
In can be established for a given performance
effect on any design, providing due recognition of
ed on eight principal variables, which are:
these differences is made.

111 heat transferred, which is a function of:


5.2.3 CEGB specifications
\4'cigi1t of steam to be considered. Specifications for plant include a requirement for the
contractor to guarantee the thermal performance of
i(i1tllalpy of steam less enthalpy of condensate.
the condenser. The contractor is expected to guarantee
lilili~aipyloss or gain of drains and make-up. an absolute pressure at the turbine exhaust under the
conditions of design steam flow, minimum cooling water
quantity at the design cooling water inlet temperature
li$,oil1lestatic Steam pressure. and with the tubes in the brushed-clean condition.
The temperature of condensate leaving the condenser
,111ing water flow rate. and the air suction temperature, with the design air
loading, are also guaranteed.
As a way of comparing how the design standards
Fio. 4.16 Graph of steanllwater cemperatuie vaiialion againsl lube Ienglh ,ling water inlet temperaturc. produced by the HE1 and BEAMA reflect the level of
347
HEATTRANSFER
COEFFICIENIkWlm'K 30

---- HEI RECOMMENDED


40- 0 HEAT TRANSFER
COEIIICIENI- IF3. 0.85)

- BEAMA RECOMMENDED
HEAT TRANSFER
COEFFICIENT-(BRUSHED
0 A TUBES1
0
BEST FIT CURVE

DES~ONCORRECT~ON
FACIOR

0
A
A
0 v
A
8.8..

I
20
VELOCITY THROVGW IUBES -mb

.GI' 4.17 Graphs indicating differences in assum~tionnmadc by HE, 151 and BE^^^ ,61 design documents
FIG. 4.18 Typical condenser test results or ])eat transfer coefficient plotted vetocity in

349
Co~?densew,piimps atid cooling water plant

h4oi-c ieccntly, hovievci. caicuialed v;il,ies of heal


translei- coefficieni, based oii laboratol-y measuremalts side-mounled and underslu~igcondenser dis~lohi
or sleaoi and waterside coeiiicieo!~, iodicatc that con- which depcnds lnainly a11 turbine design aiicl ii
denser performances bclter Illan those prcdictcd by l ~ y o u tlacion. Other factors which are also ipcji
present design codes, i.e., liE1 151 or REAMA (61. fixed at an early stage, without special i
sllould be possiblc ivitli carcfol attention lo the tube- tubenest arrangement, include the condenser
nesl geometry. interaction with the turbine support structore, < I,
ing floor height above basement, overall turI>ili
dimensions, CW flow direction, number oi 1111
and the condenser alignment (i.e., axial or trans"
5.3 Influence of t u b e p l a t e and t u b e n e s t In addition, before the tubenest arrangcnm
g e o m e t r y on t h e r m a l p e r f o r m a n c e developed in detail, the main performance ciitwn
It has been shown that the HE1 and BEAMA docu- islics of the condenser must be agreed, folio
ments give recomtneitdaiions for the design of water- optinlisation studies as mentioned in Sectioii
cooled surface type condensing plant, and describe the this chapter. The main parameters settled at tl,i
levels of performance which can be achieved. However, are:
ooiissioos on the separate treatment of tubcplate
geometry and tubenest ventilation arrangements make Design heat load.
it difficult to use this data when calculating new designs
Design CW inlet temperature.
which have tubenests and venting systems differing
from those for which the empirical dependence was Design CW flow.
obtained.
Two methods of design evaluation can be applied Desigrr condenser pressure.
in the assessment of tubeplate geometries; there is Total surface area.
thc general subjective treatment, which involves cval-
ualing the total pressure within the steam space and Tube length.
tubenest, and there is more recently the rigorous
mathematical analysis using computer-aided numerical Tube outside diameters, wall thickness, and m
EXHhUST STEAM
solutions whicl~solve the heat and mass transfer equa- Number of tubes. CONDENSER
tions for individual tubenests.
Each method is discussed in turn, the general prin- CW velocity in tubes
ciples Of tubenest arrangement are outlined, and their
practical application illustrated by reference to large
condensers designed over the last IS years. Apart from the performance parameters, the lyii
tube/tubeplate fixing will have been decided, i\I,
. . . . .
In tuln aetermlnes the mnurnurn pltch o f the IlllrM
~

-p
5.3.1 Subjective design evaluation (Section 6 of this chapter), and also design val
'The tubenest geometry and its dispositioi~relative to the amount of air entering the coltdenser in th
the turbine exhaust have a considerable effect on will have been established.
the distribution of steam over individual groups of
tubes which, in turn, influences local heat transfer
Preliminary considerafions of fubenesl arrungn?irrrf
rates, and tubenest ventilation. More perhaps than
any other feature of large condensers, tubeplate and A number of decisions relevant to tubenest arrangcnr
tubenest arrangements may differ considerably between can be taken at this stage:
one design and another. This can be seen from the
many arrangements employed on the 500 MW series,
Fig 4.19. Each manufacturer of condensing plant ar-
extent to which the total number of tubes may
rives at his own solution independently. This high-
subdivided into separate banks, each associated u
lights a point which emerges from exoerience. that
its own tubeplates and waterboxes, air extract
tubenest arrangements which are apparently quite dif-
points and cooling waterside isolation. It is coniln
ferent can be of equally good performance, orovidina
nowadays t o restrlct the number of tubes supplld $@
that proper attention is paid t i a number df general
from any waterbox t o around SGQO, which has b
principles.
found through experience t o be a number which d
not inconvenience on-load Leak searching or I U
External conslrainls cleaning. Flo. 4.19 Typical lubenesl eonfibuialionr for 5W M W condensing plant
In designing the tubenest arrangement, a number of
external influences and constraints have to be taken Subdivision of banks Consideration may also
into account. The main external constraint has already given to subdividing the individual banks into 1,s
Condensers, pumps and cooling water plant Thermal design

or lilorc sub-banks, eacll wit11 its own air extractialr


point (Fig 4.19 (b)). tive usc of the incidcnt velocity of the apli
steam.
Cor~zparrme~~tal~sirriow of the condenser. Steani fl.om c Air blanketing and slognation in the tiib,~iir~ii,
each LP turbine can be condensed in two or three
separate compartments, which are baffled from each Inundation of tubes by condensate, and (18
other on the steamside and operate at different back ing of condensate.
pressul.es, the lowest being at the end corresponding
to the CW inlet. An alternative to this arrangement Three-di,nensiorlal efjccts.
is tlie 'opposed flow' concept whereby the CW flow
is in one direction in half the banks, and in the op-
posite direction in the remainder. This avoids the The main options open to the designer will iio
need for large-scale axial redistributiori of steam within discussed briefly in relation to the various c;iil
the condenser, towards the CW inlet end. poor performancc listed above:

Detailed corrsiderations of tubenest arrorrgernent High pressure drop in the tubenest This is i n
As a first stage in tubenest design, it is necessary to concerned with tlie pressure drop in the main
choose a basic concept. The two main features by densing section of the tubenest. Once the incoi
which the various possible concepts can be mast easily sable gases and residual steam have reached 111
characterised are the steam flow approach pattern cooling section, it might be assumed that tlic
to the tubenest and the disposition of the air cooling metric flow is small, and that the pressure illal
s~ction: therefore no longer a significant problem. This
ever can be a dangerous assumption (Fig 4.19 (I

The steam flow approach pattern to the rubenest The


steam may enter the tubenest from just one direction, High pressure drop before the tubenest Th
i.e., from the turbine exhaust, or it may be allowed of large condenser design originally tended to
to pass around the nest and enter it from all sides. little attention, though its significance is nowz
Figure 4.19 (c) clearly indicates that, for side-mounted recognised. If high velocity steam entering the
condensers, a unidirectional steam approach has al- denser is not travelling naturally in the direcliot
E X H W S T STEAM
ways been the natural choice, since the face area of which the designer would like it to go, the ef
the tubenest is fairly large. However, Fig 4.19 (b) pressure drop caused by forcing it to turn in ti
indicates how underslung condensers have a small face ferent direction may be substantial. Figure 4.20 ah
area to a unidirectional steam approach, and a more how one condenser designer has developed his i r
common arrangement is for a substantial percentage nest layout to improve the use of the incident vela
of the steam to be allowed to pass round one or both in the steam. This problem is more apparcui
sides of the nest, thereby increasing the face area over underslung condensers than side-mounted or into
which the steam finally enters. condensers. Conversely, due to irregularities
velocity profile of the approaching steam, the p
drop through the condensing section of the tubet~
The disposition of the air cooling section In most should not be too low. A moderate pressure
condensers.the air cooling section is a block of tubes helps to redistribute the steam flow beneficially
located between the main condensing section and the prevent high velocity jets of steam penetrating stra
air extraction point (or points), representing some through into the air cooling section.
10% of the total number of tubes (Fig 4.19 (a)). In
other condensers, however, the air cooling section is
arranged adjacent t o the CW inlet tubeplate, and con- Air blanketing and stagnation in the tubenest S
sists not of separate tubes. but of the cold ends of all air is a poor conductor of heat, it is essentia
the tubes. The steam must travel axially along the con- ventilate the tubenest adequately if a thermal
denser to reach the air cooling section, and this type of formance, close to theoretical, is going to be achie
condenser requires design in three dimensions. Some air blanketing in the air cooling section is
ceptable, but good ventilation will ensure that blan
ing is minimised within the main condensing secti
Causes of poor condenser performance Briefly, the main function of the air cooling sect
There are a number of possible reasons for poor con- apart from cooling the vapour/air mixture passing
denser performance, the main parameters being: the air extraction equipment, is to ensure that 11
condensing section is properly ventilated. Therefo
High pressure drop in the tubenest. the total pressure drop between the turbine exha FIG. 4.20 Compari~onof rubencsi designs lo improve use of the incident velo~ityof ,he steam

352
Condensers, pumps a n d cooling wale1 ~18111

anrl the condenser air eatractioii poiiii caii bc envi- lemperaioie. I'liis jnicaiis 111e diSScvclice
liiili coiifigui-ation, arid coaling water flow, togetllei with tiit.
saged as being divided inlo lw'o pails; one across the tl~eoiclicaicold and 1101 end perSor.m- CW inlei lemperaturc.
tlic main condensing seclio~l,ilir othci ;!cross the air For a more detailed understanding of llic c o w
cooling section. Tliis C O I I C ~ I )is
~ ~ ~ i i ~ l ~ l i c by
a t e1111.cc..
d therefore inherently small. poiei lcchniques currently being iesearched, the reader
dimeitsional effects whicl? ate discussed later, but arc should refer to a paper presented at tile International
llle basis of I\vo imgo~.taiil gelieral principles (see Symposiuni on Condensen: Theory and Practice 181.
Fig 4.21): 1 liiiellv mentioned, this is a variation where thc
iidcnser is divided up into two or three corn-
a The resistance l o steam flou, along all actual flow tnxnts, one corresponding to cach double-flow
paths between the turbine exhaust and the entry turbine, the total C\?' temperature rise is, 6 Mechanical design
to the air cooling section should be equal. Wig11 eicfore, divided into a number of separate steps.
resistance paths tend to cause stagnation, resulting s compartments operate at different
in the poor thermal performance of associated to achieve balance in tlte air extraction
tubes. usual to connect the air pumps directly 6.1 Introduction
end compartment, and then allow the
Present day power station steam turbines require very
e There should be no major routes whereby steam can artments to vent into the ail. suction
large condensers: the basic problems are those asso-
reach the air cooling section directly, without first II~.via restriction orifices.
ciated with translating conceptual ideas into func-
passing through the main condensing section. If tional mechanical designs. As already discussed in
this occurs, it may become impossible to maintail1 of iiiree-di,nmsioria/ design Figure 4.22 shows
previous sections, the disposition o f condensers has
a satisfactory pressure difference across the con- i examole of the use of three-dimensional air
largely been influenced by the generic development
densing section and it will tend to stagnate as a >lingsections.
of turbines. This has made it impractical to specify
whole. Also the air cooling section will become 1, addition, 'disc' baffles can be installed in the
AIR COOLING a unique set of design rules which will complelelp
overloaded with steam, and will itself manifest a PLATE SECTlON - (li1i1, i lrai axial passage. Steam which is flowing axial-
cover thc diversity in constructional desians.
. How-
high plessui-e drop. f~.om the hot end of the condenser is forced
ti-li into the tubebank, thereby increasing the
ever, there arc many features common to all designs,
la)eeforemodlllcaton and thcse will bc discussed in detail with reference,
ce o f the steam flow path froin the ho;end,
lping to achieve correct balance of pressure where applicable, to relevant design codes, standards
Inundorion of lubes This is a problem which is and specifications.
directly related to the number of tubes in the tube-
TUBES REMOVED TO FORM n 10 of this chapter, looks at the position
nest. Reduce the number of tubes in each bank NEW AIR SUCTION PASSAGES
TUBES REMWBO TO FORM (ORIGINAL SUCTlON PASSAGLA nctional requirements of the air cooling sec-
(particularly in the vertical plane) and inundation NEWSTEMLANE BLANK50 OFF)
1011 in more detail, and describes its influence on
is reduced. 6.2 Constructional development
lii: design of the air extraction equipment.
An alternative is to place collecting trays at key The main areas of mechanical design are discussed
positions within the tubenest which will catch the under three main headings, these are:
condensate and divert it directly into the bottom of
the condenser (condenser hotwell) through a system C o m p u t e r a s s i s t e d design evaluation Construction materials
of gutters. nd and more recent design evaluation meth-
Condensate drainage can cause ondersooling. AI- computer techniques to assess the perform- r Design forces and stresses
though this is not generally a serious problem, it can steam condensers. The computer program
be avoided by allowing a small amount o f steam to $tl;ites the fluid flow, heat transfer and air con- Methods of manufacture and construction
enter below tlte tubenest to reheat the condensate lion processes locally through the condenser.
before it finally falls into the condenser hotwell. the interaction of these processes is very com-
Ihe program begins by representing the con- 6.2.1 Construction materials
s a series o f parallel slices perpendicular to The constructiotl materials may be conveniently di-
'Three-dimensional' eflecrs These effects have a sig- flow. Each slice is divided Into a number o f vided into those used in contact with the steam, and
nificant detrimental effect on the performance of fro1 volumes so as to represent both the tubenest those used in contact with the cooling water. Gen-
large condensers. The problem arises from the fact I i11c steam access lanes. The program first finds erally, plate materials, hollows and bars comply with
that, theoretically, the amount of steam which con- cam flow pattern, and calculates the local con- BS4360: 1972 [9] and BSISOI: 1964 [IO].
denses at the cold end of the condenser is greater lion rates starting at the CW inlet. T h e laws Details of materials for components, such as con-
than the amount which condenses at the hot end. ,PI Alter modillml,m servation of mass, momentum and energy are denser tubes and tubeplates which are in contact with
However, in practice this frequently cannot exist, be- to each cot~trolvolume to produce a large the cooling water, are thoroughly discussed in Section
cause it requires that the pressure drop through the I- o f , simultaneous equations for each slice. 4 o f this chapter. In addition, a n interface clearly
tubenest should be greater at the cold end than at program also calculates whether air pockets exist exists between selection of tube material and struc-
the hot end, and this is not possible if the air ex- FIG. 4.21 Ailernalivearrangements roi
steam-nor/iiii. ic tubenest, and identifies where they will form. tural design. It is important, therefore, to select these
suction in undcnlung condensers
traction point pressures are the same at both the sizes of the air pockets are determined by the materials early in the design stage in order that tube
cold end and the hot end. at the air vent points - the higher the vent support arrangements and the effects on structural
Although this phenomenon is sometimes accepted re, the larger the air pockets. From the solu- stiffness may be finalised.
as a fundamental factor in condenser performance, Use of a /ow CW temperalure rise, and avo1 1 the condenser vacuum can be predicted for given On conventional power stations, condensing plant
various measures can be taken to minimise its effect: of close approach between CW outlet tempt :a of steam flow, air leakage, condenser surface components which are in contact with steam are nor-
354 355
Mechanical design
-.
iii;iliy co!lstriiclctl froin eitlici reirrous or inon-Scrious sideration. These include Forces resuitirig fzom \,ariaus
,ii;iiel-isis. Recent specification:, for a Prcssulised Water connections, such as CW cannectionr to the water-
ilractor (I'W11) power statioll have indicated tliat boxes, and operational loads of the condenser struc-
~ioi~-ferrousinictals sliould not be useri, since the ture which must be considered when designing the
Iwild-up of deposits fro111 con-osionlerosioo effects LP turbine inountings and supi?ort foundations. Thesc
ii~sociatedwith non-ferrous materials, could be passed latter loads are of particular importance in the design
ihiough the feedheating plant, and jeopai-dise thc of integral and side-mounted condensers, where struc-
iilvel-ted tube bundle of the stearn generator, The tural stability is necessary to secure turbine alignn~ent.
atearn generator, unlike conventional boilers, has much Design stresses for the structures a1.e given in BS1501:
Eleater restrictions on the frequency of biowdown 1964 [lo]. In practice, however, these stress levels are
rarely realised, since the plate thicknesses are usually
optimised well within the limits OF stress to satisfy
minimum deflection criteria, and to conlply with the
Design forces and s t r e s s e s economics of manufacture.
main forces acting on condensers are shown in
.23 for vatious condenser configurations.
6.2.3 Methods of manufacture and construction
The methods used in the manufacture and assembly
of large condensers arc outlined, and the factors
influencing the extent of manufacture carried out at
works and site are discussed.
Traditionally, condensers for British turbines of
i 120 MW rating and above have always been shop
d I \, = force due to coohng watei static load~ng,N manufactured as a multitude of components which
are transported to site for final assembly and tubing.
1.1 = reaction force on turbine exhaust flange, N As already highlighted in Section 3 of this chapter,
however, economic considerations have recently led t o
a preferred arrangement in which each LP turbine is
= Sc = reaction force on condenser foundation
combined with its own transversely-tubed underslung
steelwork, N
condenser. This has allowed the development of a
modular condenser design so that one, two or three
I.$\\ = reaction force due to static and dynamic modules can be combined to cover a large range of
loadings from flawing cooling water, N possible turbinc ratings. This modular concept has
a high attraction for turbine manufacturers, parti.
I = Stc = reaction force on titl.bine/condenser cularly where they are competing in world markets.
foundation steeiwoi.k, N Now, before dispatch from the works, the condenser
shell sections, tubeplates, Support plates, baffles and
waterboxes are temporarily assembled and carefully
1: = reaction force due to springs, N
aligned so that final welding of the shell sections can
proceed rapidly and efficiently in the power station
= force on waterbox support, N prior to tubing.
There are a number of advantages to be gained
c = mass of condenser, N from maximum fabrication and assembly of condensers
at the manufacturer's works:
I = mass of LP turbine, N
8 It enables fabrication and erection to be carried
out in favourable environmental conditions, with
to = combined mass of LP turbine/condenser ready access to specialised machinery, welding, fitting,
inspection and test facilities.
w = mass of waterboxes
It provides a location where there is a high density
o i skilled labour and supervision in the various
disciplines.
n be seen from Fig 4.23, the largest single force
ultimately affects the design of the condenser Conflicting requirements between contractors for
is that which results from the vacuum, Fv. Ln space, access, cranage, etc., d o not exist. These can
on to the forces illustrated in Fig 4.23, there lead to reduced productivity which is detrimental to
external loads which are also taken into coil- the overall station construction programme.
P,Ci 4 22 ,,,,derlluns condenser for 660 MW unlt ehowing three-dimenclonal ax cooltng secuons
'uo!lea!.rqe~ j o sa!mouosa
pue 1113ua~lsJOJ Pas!iu!ldo a l e rla!qM sq!s pua saleid
3u!sn p ~ o lUnnseA a111 1su!e3e pauaJj!ls s! ljsqs aqL
'sauuol oOZZ s p a a m a r n l ~ n l l sa%p!lq le13a)il! aqi j o
1r18!a~ ieuo!le~ado J ~ L .s!xe au!q.rm a q ~01 as.lansue.1,
a l e saqnl aql leql 0s pa9uelia st rsauaon, , ~~~~~
,... 9--*
rrr
'la!liea Pals!! s3u!peaq a q ~.lapun p;>r
.IU!O/ isneqxa u!ew s q l ~ u i p j a f ialoJaq s11oq aq MOU !I!M .iasuaprro3 Sun!s.rapun 1 S I J A S
3~!!!3~alLq UO!I!SO~ Bu!lerado jemiou i!arll 01 palsnl -1EIOJ B iUlOJ q ~ ! i ls ~ u a u o d r n oJ O ~/ B U [en
-pe s3u!ids aql pue raiefi rn!M pall!^ sri: ssqnl pue .to Llqrnasse pua arniaejnueiu aql [I! pas"
5axoqlalEM aql '3rr!ses lsneqxa ao!qlnl ail) 01 pall!m
-?tier1 Su!aq s i u a ~ u o as1! 1 0 IJSUJp1105 JO lq3!aM
all1 p!oAe 01 pui: 's3o!ids [!o3 uodn palloddn? s! issuap - ~ .lasirapiloa
p j o ids>~ros.ie/npocu srli 5.1311,
-110s arlL 'Plea .Iaql!a ie s.ra!d uo!lepnnoJ sql oi s3p!rq r a LIE S M O ~ I SPZ'P ~ . l n 9 ! ~ ! oi t r o d s ~
2111 pa!.I.lea 911!aq r113!JIn aii!q.lni 5111 ' S ~ U ! . I B LIB
S~ -1los suralqoril auioarano oslv sni.i! ~ n q'a.
<13Ilil!!i(J 47 aqi 3u!tu1od1oso! ainisnirs a3p!iq J.J!IS j o poqisar ielnpoiii E ps~s!.i~saraxio L[J!LI,-
I: ~ t i l !13Suapl103 3111J O j[eg do1 aiji srirni ( s z ' ~ 8 ~ 1 ) -El!"'!! ~ ~ o l i s y i o m
I ~ ~ I J #([lie
!! loll a,\eq s.~ain~,,!l
a.
Condensrrs. ~puiiipsand cool~tigwarpi plant Clidp~~
4 2 Mechanical des~gri
- 4 -
Condensers, gumps and cooling warer plant Mechanical design

Wo'orerho.x~c 1'aclnrc o i condenscl.s, hui also oil kiioivlcdgc i is puuely onc of cconomy; porting striictiiic for the plate. Leak-tight slidiilg
1)cpending on tlic nii11,bcr 01' lpasses, Iransversc iioni inodci tests and fso,ii tests on otliei 1:iiy lready mentiained, it is a icquireolent joiilts are used to compensate for expansion. Vaiiolis
ii~lde~sluog colldcilrers ma). have inlet, ootlet and re.. denseis ill Britain, and oreiseas. us makeiiais arc noi to be used for tlle inethods may be used in combinatiori to providc
tuiii waterboxn. In every case the waterbox dio~ensions Clean conditions arc established within the coiiili design. Boll hole drilling ai' cl~al-acteristicsconsistent with tlie design requiremenls
ate sufficiem lo allow easy access for. ins;~ection via ser shell prior to cominalcemeri! of tubing. ate is carried out either by a jig or template and specific service conditions. Details of configura-
bolted and hingcd maniioie covers. The major design is u s ~ a l i )started
~ at lhc bottom rows, worki iuc ~niatchingwith the %,aterbon and shell flange tions commonly used on large condensers are shown
objectiucs to be realised in their construction, in ad- giessively upwa1.d~.When the bottoni io\vs on Fig 4.27. Figure 4.27 (a) sllows a typical double
dition lo acccss, are those of pressure and vacuum plele, it is ~~ossible to remove personnel as tl inner stecl tubeplate and lubeplate arrangement, using a combination of the
loading, and support. tlleil act as supporting &"ides when inserling suhvtji~, ndensei- shell is crucial and requires t articular lined and sliding joint, the inner and ourer tubeplates
The static and dynamic forces generated by tile rows of tubes. Guide bullets in tlie leading end 01' I it cannot be easily renewed once tubing is being of the same material. This design was extensively
flowing cooling water are taken by the waterbox struc- tube greatly assist the tubing operation. Figure 4.26 shows a typical detail of a used on the 500 MW condensing plant.
ture (Fig. 4.23), which is shaped to promote a smooth d flange joint. This joint is sealed with a Figure 4.27 (b) shows another typical double tobe-
flow of water through the tubcplate and tubes, and roofed fibre cloth and cord-filled dumb-bell plate arrangement, using rolled fixings at each joint;
Tubeplaies
prevent erosion at the inlet. Flange rotation is pre- ch is manufactured in one piece. The bolt the tubeplates arc o f dissimilar metals, hence the need
vented by selecting plate sizes of adequate stiffness The provision for double tubeplates has been mandti jointed up with a water test for the wide interspace gap to accommodate bending
or, alternatively, the pidtes are stiffened by external for UK power station contracts over the past ye81 id a drilling from the hydraulic connection niovements and to reduce shear stress in the tubes.
reinforcement, usually in the fornl of ribs. eliminate any possibility of cooling water enterinp I lbeplate periphery breaks into this groove, This is the method proposed for the PWR design.
The waterhox flanges are jig or template drilled to steam space of the condenser. Each tubepiate in1 the joint to be hydraulically tested prior lo Figure 4.27 (c) shows a double tubeplatc arrange-
ensure matching with tile tubeplate and shell flange. space is drained to a low level drain vessel ivhicli Access for tubeplate inspection may be gained ment of similar design t o Fig 4.27 (b), but here tlle
Earlier waterboxes were generally protected against niaintained at the condenser absolute press, ilic waterbox, which is fitted after all tube fixillgs tubeplates are of similar materials and the need for
corrosion in service by cathodic protection, with pro- means of a connection to the ail- pump suction lin ~npiete.Aftzr completc erection, when all tube the wide interspace gap is eased.
tectlon bosses provided to receive anodes. It is now equalisation of pressure on either side of thc it11 invc been expanded and packed, tile space be- Figure 4.27 (d) shows a typical doublc tubeplate ar-
normal practice to offer protection against iron oxide tubeplate ensures that no leakagc occurs across. i ilie tubeplates is filled with a fluorescent solution rangement, using a combination of fixed and sliding
scale by means of a rubberised coat, applied to grit- Therefore, any leakage into the interspace will I l~ressure,and the tubeplates examined from both joints, with dissimilar tnetals for the inner and outer
blasted surfaces pi;or to dispatch ta site. ~inilerultraviolet light to prove the absence of plates, as used on the more recent Heysham 2 and
interspace can be hydvaulically tested to a pr Tortless power station designs.
of 0.7 bar during maintenance overhaul via 2 Each of the above arrangements has been employed
Condenser shell water connections on the tubeplate periphery. A successfully. Typical tube sizes are 25.4 mm OD and
The condenser shell forms the boundary of the steam is fitted at the top of the tubepiate interspaw 1.2 mm wall thickness; tubeplatc materials are mild
envelope. The structure comprises a flool, two side- ensure that it is full of water. iclhod selected for securing tubes to the tube- steel and rolled naval brass, Muntr metal or aluminum
wails, and end plates with provision for expansion The formulae and rules governing tbe sizing l,l-ovides leak-tightness and strength as a sup- bronze for the outer plates (see Table 4.2). Titanium
and location of tubeplates. The build-up of a con- tubeplates have been based on the following stantlar
denser sllell varies between manufacturers. British and codes which have been progressively amended I
experience has shown, however, that the various line with tubeplate developments:
manufacturing practices produce end products which EXPANSION
SINGLE BELLOWS
CONVOLUTION
are compa~ablein quality, cost and construction time.
The sections making up the condenser shell are
BSI500 [Ill.
,
BS1515 Parts I and 2 (12).
invariably built up from steel plates welded together,
the only exception to this being the tubeplate attach- TEMA Standards: Tubular Exchanger Manufaot
ment, which is arranged for bolting or studding to Association Standards, Fourth Edition 1959,
shell and flanges. The shell is sometimes stiffelled for Edition 1968 (131.
vacuum and structural loadit~gby separate stiffening
members, but more generally the necessary support ASME VIIl Standards: American Society of
is provided by welding the intermediate tube support chanical Engineers - Boiler and Pressure V
Code Section 8, Divisions 1 and 2 (141.
plates direct to the shell. After welding, all shell
envelope and major structural welds are crack-detected.
using magnetic particle non-destructive testing or an The wider use of computer techniques in the desi
equivalent clleck. of tubeplates is presently being researched. An
ample which has been used is a beam element prog
which is based on the theory of beams o n elasti
Tubenests
foundations, and analyses the effects of pressu
The design and layout of tubenests is extensively edge loading from the waterboxes.
covered in Section 5 of this chapter, which empha- The methods of manufacturing of the tube
sises how the disposition of the tubes within the shell vary. The steel (inner) tubeplate is often drille
is the heart of any condenser design. The present and used as the jig for drilling the non-ferrous (outer
tubenest arrangement consists of an upper and lower tubeplate. Sometimes, however, inner and outer tuba
tubenest, each taking the form of a 'folded band' plates are drilled together, even where they are o
of tubes (Fig 4.20 (b)). This design draws not only dissimilar materials, to ensure accurate tube-1101
on the experience gained during many years of manu- matching between the two tubeplates. The reasott f o Fio. 4.26 Dmaiis of beliars and flange joinis
362
Cli Mechanical desigi~
Condensers, pumps and coolinil water llialll

liirs of 25.4 null 01) acd 0.7 mni ivall tliickncss


k e n fixcd successfully into a sii~iilaiconfigurn-
lo that sho~rsnin Fit 4.27 lril r-l
I I . ' , I... .. I . . i l ' r ;)I.i51... I . . . . . I . . ill.?,,,
(I,, :1c.,2,1 :'.:c'..t : . , , I . .\,r. I . , . , ! I :,:: .:
. . I : . I : 1 . 1 ,>IJln< \ ' : . : ~ ; t l .
II 8 > : ' n . ~ u ( 1 8 . lc..tll~.t, : ,I ,.I),: , I.!,!
.... e I.,,,, ' 1 ) ~.a!. ~ I). I C ....~ ) , I I . I ~ I . \ . x L ?1,.. . .
1 ,' I J l 11). 1 1 1 ! ) ~ ( 1 I ~ x l (ill[:\\
~ \,!..: L>II.c> I J : i l . >:
- t,.,! ~.lll:r. l ~ , > S C ~ !~l . !Cl C~! ~ l . ~ ,,,.I l , ~ , , , ; , , , , 2,

:I I I , .<a,. L h ..,J\>I>Ic.'
l 4 ~ l ~ ' ~ ~1, ~:d'tlcJ ~ ~ nJu' ~ l3, Jrl,?~ ),..I:,. <.lJ l!,t:c[
. u I , . l 1 t l ~ !:rat, u > l n d . I ~ : t l l . h l . ~ . : ~ ~llc,!
~ ~ ~1 >!I:! .\
ta,v$,l l',~r:~:-l.~c a v \ \ :?.ken 11. ~ c I I ! ~ . ~ ! '.!.
1-1. I: eil.olr. '11;' o \ ~ I . < ~ A P : , o , .IJ.),)I
.I. s ! . J rhe
MlLDSTEEi MILO STEEL
$ 4 ' l..l~:~,l,tc ) < > L > 0 < 2 , . o:.", 0,. ..,".,,l~l,.~,,
BRhSSOUIER INNER iNNER BRASS OUTLR 8 8 I .I t u l ~ c p l ~ l :: (~
I . , l l l ! < l .,.d ,,-,L, ,,l$.,,.d'~
'(I ~'.~.t.cd.>r c\t'.,nJvd d ~ i db:llc! . I , ;$pl,t>
. , . 8 1 1 . 1 :.J:L~,,:< i J < ,.!k,>,,~Ic~ v,,c ., >,,,.,la,
, . ' 111. I . I > L ~ 3 r c 11:I h.ll~tl I U I . I I I ~ I : I U I C I ~
'.I . . I. . . t V ~x:>.~rluir..~! ~>dttc!r:,I , : ,.:I: ~111.1 ? I . ~ (
I ~ ~ . l l ~ ~ . l ?~t~cr!2n:c,
".~l c,o,, :\<,, 6 \ , , C I < ' . L ,
. , I .r.:: :< ,~l!,':l)\ <%d,)~ltcJ I ~ O
I I J Lt ~~ , Ij : I I : . I I H , .
Fit; 4.28 Turbine l a condcascr joint (for underslung
coiidesseirl
, . . .I . , ! : ,. .XI 'I. c ,l,'l., c,,a

8 . , t \,,,,:< ,,,, l
purposes. They support the tubes in order to control
. . I ,.,..I !uhc I I I ' ~ I ~ I I ~ III:~,I:~I
I ~ . x t ~ 3 1 . \ 1 d :+
n vibration, and provide means for bowing the tubes
". ~ v ..,I~ ~ oc InjdrkcJl! d ~ i t e r c n t . :\:cpl ~ I L W to assist drainage. Also, they provide a convenient
. . .1*t0.881 I I arc I C~llc:tl\el). ,u:rlcr rn,rmJl method of reinforcing the sheli against the external
8 -1818 . . I ! ~ I IL ,C 1 u l a 1 I ! 5111 pressure forces.
. ,,1 . : I c r a l o t . S I C 1511 The spacing of support plates is controlled by the
1
.,I.,. td~lurcd! thc Iul>c 1.21n1.'Tw ~ : I I ~ . I -criteria governing tube vibration, but usually the maxi-
a . , > I lb:r~%ecn41ell JLICI ! L ~ C *<I!. I . I ! & ~ mum dimension does not exceed 60 tube diameters.
1 I 1 .l:,l~:, .at1 I>: <>< Ih,&l, LC 22 .#.,,. \ With the intl.oduction of titanium tubing, tilt spacing
. ., ').at; t:\ir.; ilTllllldCII~C111\itnilsl I., 111. 4 2 - can be as low as 35 lube diameters which satisfies
8 m. ,, 11 \ ~,:x:kcJ gl.it~d J , > L , I I , , 3lm; U . I O the criteria of freedom from fundamental frequency
I . < . I . c~;,nllneJa, i ( , o s , ~ b . ~ j~lrri,t,n I., vibration from both machine and steam-flow-induced
' ust, t.11:;111 prdb1''m. bt.1 lans bccll .ibalidonc2 sources.
. I . , ' . t!n!clihbilil>. l h u praai:ai s o l u t ~ d , ~ Where support plates are used as inherent stiffness
,5( .. 1 . . t '11) o $ r the uac of ehpan,t,r b c l l o , ~ ~ members for sheli reinforcement, the plate strength
,$.
;
' iti
j. 1.8
8
.-I1.
. t 1,s.,~I.I.~~t~tl.ln
tttb:plate 1 1 r i ~ rat one cnJ. ~u,ilsll)
typci . <l-iL; 4.26,. and attachments receive consideration as edge-loaded
MlLOSTEEL MlLO STEEL BRASSOUTER s, perforated diaphragms and are stiffened to avoid
BRASSOUTER iNNER
buckline, if required. The plate thicknesses can vary
from 16 mm to 38 mm, depending on the design cri-
PACKEOGUNDS
PACKED GLANIIS
/ I ,,,,,,,< 101, ,I
teria. The tube hole drilling is carried out by multi-
, J I I I I . I C I ~ ~ I . I I L ?: ~ n d c ~ ~ r ci,' r atta:llcd 13 the spindle numerically-controlled drilling machines, and
.*., - '\84,,!, 1,
: *.
, e
,,l,l.t,& it is common practice to 'stack drill' up to seven
, .'. w..! ~ c t d i a sl~ostni n Pii! J . 2 ; l h h is support plates at a time.
.*;, B .:~vrt, .% 3
1.1 . Ir.,tl ucld. srslded t r o n l [he insldc, \ r l t l l
'*?.
...I.., s. ,.'.IN,. m,.,., In$ ,lril'. Aflcr .'Jnlpletion, the aeld I,
. ,**!:11. , # * . I . . ..111, .~;l;k-dcrcaed for soundrlel,. Branches, connections and reinforcetner~f
,.'$
.. '.', 112.8. I. I . O I I , ~ V I I > C ~ >3rc b o l t e d 10 tne turbine Ordinarily, reinforcement may be dispensed with be-
'".s . . I I , ! $ . I llc\~blc~ C I I J W S j ~ ~ n l , . cause plate thicknesses are in excess of those that
;j2$ require compensation. Details of any opening or branch
,.,.
I a
connection to the shell which requires compensation
and reinforcement must comply with the standards
Pm. 4.27 Tubc.to.tubeplate fixing arrangements for large condensers set out in BS1500 [Ill.
Condensers, pumps and cooling water plani Operational life limiting constraint$

Nydr-uuiic zests Siolll the filtei ranges from 3 lo 10% of lllc i


Theit arc mandatory requirements far hydraulic tests CW flaw, over a riiising period of 5 to 10 tnliinii
on the components of tlie condensing piant, and these
are suinmaiised in Table 4.4.
6.3.2 Condenser tube cleaning system
SPONCIE RUBZEli
Figure 4.29 shows how oversized rubber ball,, /ani.LsnisinisurEo
(NCIRCULflING WhlER
continilously pressed through the condenser lii1,rh
the water flow. Screens located downstream al
condenser waterboxes extract the bails from thc it
CW discha1,ge flow. They are then drawn oSl'
pumped through a collector to be subsequently
I Waterboxes / 4.1 (liydrauiic) i charged into the CW inlet to the condenser.
SCREENS FOR
ilnu RECOVERY
otherwise lower the neat transfer charact

I Pumps, gipci.orli
a i d ralvcr
1.5 times ma*. woiking
pressare
the tubes, with a resulting loss in condenser ef

6.4 Special considerations


in addition to the normal function of cond
the steam which is discharged from the LP i ~ i r
condensers on ntlciear power stations are design,
6.3 Protection and cleanliness of condensers provide a heat sink for the removal of heat fron
During plant manufacture, storage, transport to site reactors. These condensers are fitted with steam
and site erection, special precautions are taken to water dumping facilities of the pressure breakd
ensure that all plant items remain clean and reasonably type. The condenser structures are suitably rcinl
protected. To achieve this, condenser internal surfaces
are usually grit-blasted at the works and a temporary
protective coating applied, i.e., a type of coating which
does not require to be removed prior to the unit enter-
ing service. Tube holes are protected by a lacquer account of the steam and water dumping requirrl F ~ G4.29
. On-load condenser cleaning system
which is removed immediately prior to condenser on nuclear power stations is covered in Chapters I
tubing. External ferrous surfaces are either grit-blasted 2 o l this volume.
or wire-brushed and degreased, and a suitable primer
is applied to the cleaned surface.
In the post-erection period, until commissioning, reasons why it is desirable to minimise air 7.1.1 Locating air leaks
deterioration of internal surfaces is minimised by 7 Operational life l i m i t i n g constraint Air leakage can occur in any part of the condensing
keeping the condenser surfaces dry. If the condenser The main constraints which limit the operatiottal system which operates near or below atmospheric
is used and has to be put into storage again before of a condenser are summarised under the follo loprove condenser heat transfer performance. pressure, and is often caused by failure o f joints, at
commissioning, steps are taken to ensure that all water headings: flanges, and also by weld and material failures. Whet;
is removed from the condenser. ]educe the capital tost of the air extraction the turbine is off-load, detection of air leakage is
In order to operate a condenser at its optimum Condenser air inleakage. ~iipmentrequired. made in some parts of the system by flooding with
level, on-load cleaning methods are used which ensure water. Water seepage from sections normally under
Cooling water inleakage. reduce air extraction plant running costs.
the high availability of condensing plant (Fig 4.29). vacuum indicate leakage areas.
Condenser fouling and cleaning. When the turbine is on-load, however, different

6.3.1 Debris filter


An awareness of these problems at the design stage
Coastal power station condensers are more vulnerable
significantly reduce lifetime running costs I
to the intake of debris such as mussels, fish, wood, plas-
maintenance costs. Operational experience of thc
tic and fibrous materials, than inland power station
ious techniques employed for each of the thre
condensers. One solution to prevent the blockage of
straints listed are now discussed.
condenser tubes is the installation of a debris filter in
the CW inlet side of the condenser. traction equipment. The last method is the most
Ail particles in the cooling water larger than 10 mm tional levels of air inleakage, however, vary common technique employed today.
are kept in the filter and rinsed away through the 7.1 Condenser air inleak
debris discharge. Throttling of the filter inlet isolating
valve causes a change in flow direction near the screen, and methods for measuring the rate of air inleaka
creating a rinsing effect. The discharge water quantity condensers are described. scrs and direct-contact feedheating plant. are capable of detecting low concentrations of halo-
366 367
Condensers, pumps atid cooling wator planT Operational life limiting constraints

genaled compoonds in ;in air stl.ealn, 1'0s iiiiiiimuin ge is oot usilig coiidoctivity )probes s i'lamc and siuokc techniques; the flil~nc from a
toxicity and maxirniln sensitivity thc lialoge~iatedconi- lion lo make divcct measuicments of air leaha il oil-load. l.11~ tubenest causing tile pro- taper (or smoke) is uscd to indicate a flow of air
poonds cl~iorofluorocarbon and dichloiofloaro- a i)eriociic basis, or i\,iien a condenser peiioit identified by an increase in condensate coli- into a leaking tobe.
inethane (trade narlles Freon 12, lsceon 12 or Arcto,? problcm exists, The metliods employed ilicl~iiii: his is si~nplificd in transversc underslune
12) are itsed. e Ultrasonics; the 11oisegenerated by air !lassin&tll~ough
use of Pitot tubes, anemometess, lhot wire 8811 , wilere multi-seclioning local
Of the leak detectors mentioned above, only the i n condensate conductivity will be signifi- a leak is detected'
meters, rotameters and orifice plate assernhii
LEYBOLD equipment tias a detectol. probe which can Measurements are made both a n the air 11 the location of the leak, and therefore easily
be immersed in the gas to be tested. This equipment pipe and at the air extraction plant discharge. The sensitivity and application of these techniques
is used by irlstalling the probe in the air extraction necded at bath locations. The assumption nlad ~ i n gidentified which condenser tubenest is at are discussed below.
pipe from the condenser, whereas the other detectors measuring in the condenser air suction pipe is I tiic second stage is to determine the level of
sample from the air extraction system discharge. water vapour present is satura:ed. When lneast~r iikage in that nest. This can be found either by
Most leakage points are found at flanges and joints, ,g the cooling water level in the waterbox and 7.2.1 Ffuorescein
the air extraction plant, if more than one piis
and are usually small cracks or holes. These can nor- opcrating, the flow between the pumps is no1 iii ring the condensate conductivity or by intro. The steam side of the condense1 is flooded to above
mally be sealed with any of a number of proprietary evenly distributed. trace,. gas the waterbox, dropping the the tubcnest with a 10 mg/kg solution of the sodium
metallic resin or rubber-based sealing compounds. water level, and monitoring at the air extrac. salt of fluorescein. A search is carried out in the
n l For the appearance of the gas as the leak is
waterban using ultra-violet light to detect traces of
fluorescein. The tube which is leaking is therefore
7.1.2 Measurement of air leakage rate 7.2 Cooling water leakage in condens. [Cresting are identified. There are, however, disadvantages of this

.
that these two
Apart from the air extraction system (see Section 10 The methods employed in British power statioi I , ble for all power stations, e.g., the former
of this chapter), air leakage measuring equipment is the detection of leakage of cooling uaater inl s satisfactory at sea-cooled stations, but, it is I~ is restricted to underslullg off-load.
generally not insrailed as permanent instrumentation condenser, and of the conseque~~t pollution of lble for freshwater-cooled stations wilere the
on British power stations. As in locating the air leaks, condensate are: ,thod is adopted. The reverse action of water pressure on the tubes
there are several techniques available to measure the procedures are adequate for narrowing the c o n ~ p a ~ cwith
d normal operation is known to close
I.ate of air leakage. r Condensate conductivity. search to within two or three rows of tubes, up the leak in some cases.
Operational techniques are used to determine whether !* ingc three provides techniques which will precise-
a reduction in condenser performance is due to con- * Sodium contamination. T ~ I Cthe source of the leak. The water pressure is low at the top of the condenser
and small leaks may escape detection.
denser fouling, or air inleakage overloading the air techniques used include:
extraction equipment. The operations carried out, which Location of condenser leakage is influenced bg Residual fluorescein can affect feedwater and boiler
only require measurement of condenser back pressure, ,rescein metllod; the side of the colldenser
following factors: looded with a fluorescein solution. water analysis, and impair judgement as to whether
are: repair of the leak was successful.
CW supply, i.e., fresh, estuarine or seawate I or film methods; the condenser tubeplates
Isolation of the air extraction equipment from the overed with a foam or thin film material whilst This method requires an operator to carry it out.
condenser on-load, and monitoring the subsequent Condenser design, i.e., underslung or pannier. vacuum is maintained o n the steam side.
rate of vacuum decay.
~bbiecdevices; air bubbling through a jar of water 7'2'2 Or methods
Changing the number of vacuum pumps in senice, Experience bas shown that the techniques us. The principle of this method (Fig 4.30) relies on the
used to detect a tube leak.
and establishing the effect of this on the vacuum. locate the region of leakage in fresh water cond development of a vacuum in a leaking tube. If the
a1.e not sufficiently sensitive to locate leakap gas methods; a halogen gas detector is tube is then sealed at each end, the vacuum draws in
Seawater condensers. Also, the introduction of p 11icd at the air extraction equipment and the a foam blanket or a film of polythene or paper, and
Typical unacceptable vacuum decay rates are 4 mbar/ type condensers for the 500 MW units mean] I xct tubes sprayed with gas. thus identifies the location of the leak.
min and above, as compared with expected rates of flooding the steamside with fluorescein solutioli,
approximately 1 mbar/min. most popular method of off-load detection
Wllere these techniques are not either favoured underslung types, was no longer possible. Undersit
or practical, other diagnostic techniques are often transverse condensers, however, have an advanta
employed which require measurement of: that they can have up to six separate sections w
M

can be isolated and monitored using condensate c


Air temperature in the air extraction line from the ductivity probes. This means that on-load location
WATERBOX
condenser; increase in air quantity handled reduces elimination of leaks is considerably simplified,
the mixture temperature because of low water vapour without output loss.
partial pressure. The method of locating condenser CW leakage !r
a unit on-load has three separate stages:
Undercooling of the condensate outlet from the
condenser; high air partial pressures give increased
Location of the affected tubenest by condens
undercooling in some conddnsers.
conductivity measurement (desirable conductivity 6
Differential pressure between LP cylinder exhaust condensate approximately 0.1 pS/cm).
and air extraction plant; low differential pressures
indicate that the air extraction plant is controlling Location of the physical level of the leakage with1
the waterbox.
the vacuum and not the condenser heat transfer
performance. Location of the leaking tube or joint. FIG.4.30 Tube leak deteclion by foam/filrn method
Condensers, punips and cooling water plarii Operalional life lirniling consfrainls

Generally two ogeralois, each with a ihilni generator, metiiods of on-load and off-load cleaiiini! iil
arc required. Pill-hole leaks wilh a leakage rate of densei's are now described.
400 mi/h can be located, and 5000 tubes/lioiii can bc
tested.
The success of ibis method relies on being able lo 7.3.1 Condenser fouling
establish a vacuum of 330 mbar. Various forms of fouling havc already beel! i
in detail in Section 4 of this chapter, wl~icii
at the erosion/corrosion of condenser tubi!s
7.2.3 Bubbler devices impingement attack.
Figure 4.31 shows the two different types of bubbler Basically there are three aspects o f fouli
which are used for tube leak detection. arc beyond the scope of the CW scree,,
Figure 4.31 (a), the conventional bubbler, monitors installed:
the flow of air through a hole when the leaking tube
is under vacuum. The method will detect leaks down Blockage by debris.
to 175 ml/h, and an arrangement is adopted where Biological siimcs.
I0 tubes are monitored simultaneously, enabling 700
tubes/hour to be checked. Two operators are required 0 Scaling.
for this method which is suitable for off-load use
providing a vacuum of 330 mbar can be obtained.
Figure 4.31 (b), the MEL bubbler, is similar in prin- Blockage by debris of tube and tubeplates \
ciple to the conventional bubbler except that the tensively covered in Section 4 o f this chapter.
suspect tube is evacuated with atmospheric pressure Biological fouling refers to marine life wi~icli
on the outside of the tube. 'This method can iocate tribute to the formation of the slimy deposits
leakage races of only 35 ml/h, the test iate being up heat transfer surfaces of condensers. These
to 200 tubes/hour. bacteria, fungi and algae. The slimes formed !by I
micro-organisms adhere to the metallic surface, I
heat flow and form a laver to which other sust,e
7.2.4 Tracer g a s m e t h o d s matter can adhere to reduce condenser perforill
further. Some forms of marine life, such as ti1 ATMOSPHERIC PRESSURE
Detectors for halogen organic gases are extensively
and barnacles, can cause by restrictin
used for both air and cooling water leakage loca-
tion; Section 7.1 of this chapter gives details of the and blocking tubes,
method. Scale formation is caused by the depositio
reaction of inorganic material on heat tiansfi'r
Generally leakage rates of around 1000 ml/h can
faces. It usually occurs at inland river-cooled stal
be detected with the unit on-load or off-load, as long
using cooling tower systems. The scales are lirtl
as a vacuum can be obtained. One operator can carry
calcium carbonate or calcium phosphate, or niix
our a search using a transmitterldetector, although
of both, and arise from variations in their solil
lnore normally two operators arc employed.
products with temperature and p H changes (Fig 4
The temperature effect is due to the inverse solub
cllaracteristics of calcium salts. The pH changes tt LiUM
7.2.5 Flame a n d s m o k e m e t h o d s I'
by carbon dioxide stripping in the cooling tow
These methods are fairly insensitive and involve the
use of lighted tapers o r smoke tubes. Due to their
insensitivity, these are generally used as primary meth- 7.3.2 on-load condenser
ods of detection when massive leaks are suspected. T~~ methods of on.load fouling preven
are employed to avoid unnecessary costly shuld
of condenser plant, in order that efficient thro
7.2.6 Ultrasonic m e t h o d costs are realised:
Again, this is a fairly insensitive method which is
not generally used. It involves the use of ultrasonic Chlorination of the cooling water.
detectors to pick up turbulence effects of the air TUBE PLATE
near a pin-hole. Owing to the noise from the steam Fine filtration, plus tube cleaning using rubber b~
flow, and to a n extent tube vibration, only leaks ibi M E L. bubmr
close to the ends of the tube can be detected. Intermiltenr chlorinalion of the cooling water enlel
the condenser is carried out on all British 110
stations, and forms the accepted on-load foil
preventive technique. It is effective in controlling F ~ G 4.31
. n b e teak detection using bubblers
7.3 Condenser fouling and cleaning growth of mussels in seawater systems, and the for
The types of fouling encountered in condensers, and tion of slime in freshwater systems.
Coiidensers, i?umps and cooling water plarit Plant testing

8 Plant testing

8.1 Introduction
Condenser thermal performance tests are carried out
when the unit is recommissioned. for two reasons:
tions have experienced stress-corrosion crack-
e As acceptance lesfs to establish that a condenser
anded tube ends from acid cleaning.
meets its specified Performance, and is capable
of producing the desired condenser steam inlet pres-
sure when operating under specified conditions.

As routine operalionol fesfs to monitor the con-


grit blasting; it involves blasting graded denser performance periodically, and to verify that
ineral grit through the condenser tubes. station thermal efficiency is not being adversely
.it blasting nozzle incorporates a venturi affected by a deterioration in the condensing plant
heat transfer coefficient.

ncss in cleaning tubes, and requires a charge In both acceptance tests and routine tests, a high
I approximateiy 1 tnls. standard of instrumentation is required, particularly
in the measurement of the condenser steam inlet . ares-
sure, and the cooling water temperatures. Routine
tests generally use less instrumentation than acceptance
irlhod uses either high or low water PressuIe, tests, but only when it is certain that this is not
,dine a n the application. detrimental to accuracv.
1'10. 4.32 Graph or soiUbiiili ot caicium phosphate with cilangei iil ~cinpcial!iie and pH

8.1.1 T e s t codes and practices


Condensing plant is the only major item of power
At coastal sites, marine fouling is significantly which becomes irrecoverable when the plant plant which is at Presellt not covered by a British
reduced by continuous chlorination of the cooling commissioned. Standard code for thermal performance testing.
U'ater. The degree of chlorination required is in- Late filling of the fine debris filters imme For this reason, the CEGB has compiled its own
md is therefore generally not used. test code, entitled 'Performance of surface-type steam
pressure water washing is effectively used to condensers' - Site Test Code No. 3, 1981 (151.
loose sludge and sediment deposits prior to
At inland sites, slime control is maintained by Except in a few exceptional circumstances,
intermittent dosing of chlorine (a few minutes every load condenser cleaning is done during outages. Scope
four to eight hours) at a level which leaves a resi- techniques used are now discussed. This Code covers requirements for acceptance, routine
dual of chlorine of 2 mg/kg at the condenser CW pressure of 7 bar. and diagnostic testing Of water-cooled surface-type
steam condensing plant, including multi-pressure de-
signs. It specifies procedures for testing condensers,
and for calculating and reporting the results, so that
the condenser performance may be checked against
contractual obligations. In addition, the performance
cs by drying internal deposits prior to flushing of different condensers may be readily compared, and
the operational performance of condensing plant may
Ile former application controls marine fouling by be assessed.
ng the temperature to 40% for one hour every Within this Code, reference is made in particular
veeks. This reslricts mussel growth to sizes which to the BEAMA design code 161 and to ES752: 1974
lot lodge in condenser tubes. The heating is Test Code for Acceptance of Steam Turbines' (161.

7.3.3 Off-load c o n d e n s e r cleaning


Acid General outline
Although improvements in the on-load techniques
continue to be made, off-load cleaning is frequently This method is restricted to condensers sufferill The assessment as to whether a condenser meets its
required for various reasons. guaranteed performance is based on comparison of
the condenser inlet pressure measured on the accept-
ance test (corrected to specified conditions of CW
Plant teslitiy
Condet?sars. pumps atid cooling water platit Clini~ic
--
iiilet tenlpeialui-e and flow, Ileal load, tube cleanliness bc deterillioed, as this is lhc ~mostpiacticiil 11
and tube sii~iaccarca) wit11 tile guaranteed coridcilse~ of obtaining thc Pall in temperature throiigi
pressure. tilbenest, and also the air extraction pressliwi'r.
When the test condition& differ fl.om tllose speci-
fied, the Code describes a correction procedure which (b) T e m ~ e ) . o t ~ ~I.Ie~ C ~ S U I . C I ? I ~Temperatuic\
II~
relies on validated curves or formi~laeand imposes quired are those of CK' inlet, CW outlci. i
closc limits for permitted deviations when these are densation outlet, steam and air suction, All
not available. The corrections are applied to the rest measured directly except that of steam, fo, utlti
logarithmic mean temperature difference (LMTD) and it is preferable to assume saturation and to der
allowance is made for variation in steam temperature the steam temperature from tbc correspoinli
through the tubenest. pressure.
A method is also given for the routine assessment The accuracy of the CW inlet ternpei;
of condenser performance, in which the actual con- measurement equipment is specified as + O
denser inlet pressure is compared with that recorded Cooling water inlet temperature to the con
during the acceptance test and corrected for lhe is gelteraily constant across the pipe section
changes from acceptance test conditions to those the temperature measurement is made eithe,
obtaining at the time of the routine test. thermometer in a pocket or by extracting a
A section dealing with test accuracy is included. tinuous flow of water tllrough a vessel contain1
The assesstncnt of accuracy is based on tile effect a thermometer.
of systematic errors only, the random errors being At the entry to the condenser CW outlet
effectively eliminated by the proposed frequency of however, the temperature of the water is $11
readings. tified. To allow mixing to occur, t l ~ etempernti
measurement point is sited as far as po~sil
8-----7 v 'A'
downstream
Acceptance test procedures
Temperature sampling probes on two diairi
Before testing, a meeting is held between ali parties
involved to discuss the testing programme, and to
are used in each condenser outlet. The pro!
either thertnopiles or multi-hole probes tlir
a IEMPERATVRE

make arrangements for any necessary preliminary work. which water is drawn into a mixing vessel. @ DIFfERENItkI PRESSURE
For example, discussions include reaching agreement boles or thermocouples are situated at cetl
with the manufacturer on: of equal areas, one hole or thermocouple to c
0.2 mZ of pipe area.
Interpretation of contractual guarantees
(C) Flow measurement The flowrates of cooling \vi I:xc. 4.33 Points of ntearuvcslent for condenser test
Location, type, and calibration of test instruments
(Fig 4.33). condensate and extracted air may be requ
when assessing condenser performance. Mrtl~
Means of obtaining the desired operating conditions. of determining the CW fiowrate include: ( oridcnser heat load deterf~~inationSite Test Code milar to that o n the rest of the condenser. The
No. 3 recommends that condenser heat load should common inlet temperature and individual tubc out-
Isolation of the plant for test purposes. Condenser heat balance
bc iierived from a calculation of the heat rejected let temperatures and flowrates are measured, from
The procedures to be followed for calculating results. Velocity/area methods. by the turbine-generator, preferably using heat rate which the cleanliness factor of each sample fouled
dnta obtained concurrently with the condenser test. tube is calculated according to Site Test Code
Differential pressure methods. No. 3 [IS], Appendices A and B.
BY agreement, the official report of an acceptance 7idDe cleanliness and air blanketing Both on-load The off.laad method reauires s a m ~ l etubes to
test may be produced by either party to the test, or Tracer methods. imd off-load methods for the determination of be withdrawn from the condenser. In a laboratory,
by representatives of the parties working together. condenser tube cleanliness are required, and also the cleanliness factor is determined by measuring
(he occurrence and location of air blanketing need the thermal resistance of the fouled tubes and
These are listed in descending order of preferel
lo be identified. comparing this with the thermal resistance of some
Test measurements and the Site Test Code No. 3 [IS] shouid
Figure 4.35 illustrates the on-load method for of the tubes after acid cleaning.
consulted for qualifications.
(a) Pressure meosuremenr The test pressure mea- iictermining condenser tube cleanliness. Briefly, Air leaking into an inadequately vented con-
Several methods are available for measul
sample tubes in groups of three or four are se- denser will blanket the tubes, impede condensation
suring system must give the mean static pressure the rate of air leakage into the condenser, n
lected such .that operating conditions throughout and increase the condenser pressure. The position
at the condenser inlet from each individual LP reference should be made to Section 7 of I
!lie condenser are represented. Separate supplies of air blanketing can often be inferred from mea-
turbine cylinder to within $0.3 mbar, Fig 4.33. chapter which covered these aspects. General
of CW are provided for each sample tube by surement of the CW outlet temperature distri-
It usually consists Of separate sets of pressure the preferred position for measurement is
tneans of insulated pipes passing through the bution at the tubeplate.
sensing holes linked by manifolds to which the air pump discharge (Fig 4.33), because me
\r,aterboxes, and one tube in each group is selected An abnormally low temperature rise indicates
test manometers or transducers are connected. ments at the air pump suction require detert
21s a clean tube which is acid-cleaned before the probability of air blanketing somewhere along
The same plane should be used for measuring tion of the steam/air ratio, and are made diffic
commencement of the test. the condenser. A more precise indication of the
both the condenser pressure and the turbine LP by the low density of the steam/air mixture. Cooling water is pumped fhrouglt the clean position of the air blanketing can be made by
cylinder exhaust pressure, fig 4.34. The measurement of condensate flowra
tind corresponding fouled tubes at a flowrate si- inserting a small probe into the steam space to
In addition, the steamside pressure drop should described in CEGB Site Test Code No. 2 [I
375
374
LLE 9LE
.sa!lleuad jeuo!lelado Zu!lln3u! l n o q l ! ~'pasnp sfe!ll aql 30 ssaaans aql 30 ljnsal B s v 'E'P a1qe.L lonls J O a s u e u l o j ~ a dlemraql aql j o 8u!puelslapun :Ol ale lueld %o!suapuos 30
-a1 aq o) az!s alsldaqm pue ql8ual aqnl llelano a q ~ 'suo!l!puos Bu!lalado 8u!Llen Japun suo!le~s~ a ~ a d IIJq e aAa!qse 01 In0 Pa!llel 8u!aq S! IroM luam su8!sap almnj 103 sah!lsalqo pue sm!e aql '!e~auaZ u~
SMOlle u%!sap aql 'asuemloj~adaqnl ~u!s!m~xem~8 laqmnu e 18 ]no pa!rres alaM sle!iI 8u;qni urn!li [wap pue qsleasal 'sua!sap auqd a w n 3 30 (,m/Q)
'pasea131q ~ ~ ! A J ~ S - U'uo!sola/uo!so~Ioa
I 30 slaajja aql isii! atldes 8u!suapuos s!j!sads aq) asealsu! 01 lapro u~
sa~!ma!qopue sur!t/ L.6
luawdola~appue qaeasau 2.6
anoqe O ~ O EL[a~m!xo"dde aq 01 pa~em!lsa s! lua!s -em aqnl lasuapuos sranoa laldeqa s!ql 30 p u
-!jjaos sajsueq ieaq llesaho u! asearsu! lei01 aqJ w u a l u d o l a ~ a pa ~ n ~ n6 j
'a8eu!elp alesuapuos
8u!ls!sse lua?!~~aosl a ~ s u e l lleaq ap!smea)s aqi 6u!q,,a 'Q!l!qel!ehe pus Ll!l!qe!lal alnsas (s)
sa!uado,d a3uaw,o,lad ;sw18qL l.Z
sluaur8ne osle 11 'leaq 30 ~ a j s u e ~aq) l ~!q!qu! pue auspuo3 a q l j o asuemlojrad [ernraq~aql as!m!mK (q)
[fern aqn) aq? Buole dn pl!nq iou op ssaitel Llepunoq
'9E'P 8!d u! u ~ o q sse 'sisauaqnl
'lasuapuos aql 30 az!S aql aS!m!U!K (el aql u!ql!~ arnssald pue am~eladma]aq) amseam

sap!s lalem pue meals qzoq uo a8plr les!laq pall01 e uo!iaas u! pau!llno ale luaudolanap Japun 4 1 1
seq 11 .8u!qnl pado, 30 aldmaxa ue s! L E ' ~adn8!d awmelSold ilo!les!m!ldo lasuapuos a 30 sl!ei3 siaruapuo~Bunlsiapun lo] tuaiua~nrearu a~nrraldlo Ju.id .9,d
'raldeqs s!ql J O 1.6 '4sua!a{j~a3!u1eui(pou1laql u! sluaman
uo!laaS u! uah!8 san!naCqo PUP. SUI!~ 30 IS!^ aql u! as!lea 01 .raplo u! 'sanb!uqaal s!sAlme ralndiu 'aNBp"r?B"n,5rs~"n , r a ~ / q ,
(q) pue (e) smai! Ljs!les 01 'Su!qnl (padol) 41iamoa8 sinoKei isauaqni rasuapuoa jo uS!sap aql as!ul!i
pasuenpe j o asn aql s! panZ!gsanu! Su!aq tqluallns paau aqi as!uSosal s ~ a i n ~ s e ~ n ulasuapuos
e~u )((I
s! q ~ ! r lFJu!qni
~ rasuapuoa u! luamdofa~aplaqloov anohel l s a u a q n ~
8u!qn) i(rlauioa8 PaJIlflApV

ir$ii!lileaIa j o uo!ieu!umop pool-uo c6.p '~li


.~o~ae)

@
-
31VHMOld

3t(niV83dVi31Y i V 3 l l i W301 3 0
?I+"lWldVHI
0
SINlOd lNalY4HnSV3N
N O I I Y Y I W t l 3 l 3 0 "09 U3lV-M DNiLV7I73133ii

U3iY,i\\ 3N11003 -

'""aD"o2 ""nliioy"" arlo"runii,8l

NI M3
1110
3iVSN30N03

weld ialeM 6u!joo3 p u s sduind 'siasuapuo3


I.$(, 4 36 Air blaeiei>~,g
aunveyr by inrerun& a 1,tobe into tiie conden\ci tubmest
i
Optimisation studies have been carried out on a A comparison of the mechanical behaviour betwccn
transverse underslung condenser, using 25 mm OD roped and plain tubing is given in reference [181.
roped titanium tubing, and 22 mm OD plain tita- As far as reliability and availability are concerned,
nium tubing. Water velocities varied from 1.2 m/s research continues in the following areas:
Fio. 4.37 Photograp1 of plain and roped lubilie

.
to 2.2 m/s, and tube lengths varied from 12 m to
18 m. Tube maintenance.
Table 4.5 shows the minimum cost, optimum CW ~~b~ cleanliness,
quantity and condenser parameters possible within
the constraints imposed o n the system being studied, Modular construction. TABLE
4.5
i.e., a CW flowrate of not less than 1.68 m/s and Oj~li,,$i$alionsludy resultsfor plain ond roped lilonium rubing
a CW temperature rise of less than 12'C. In particular, the maintenance of condenser t
Total Hcai ~ube CW nowrate
This suggests, for the two optima in Table 4.5, without access t o the waterbox is being investiga CW
Tube Tube optimum cost transfer veiociry, per set
savings of £200 000 by using roped tubes, however, ienglll (3 sets), areaiscl. m/r kp/s *PC
design
when compared to the existing condenser using conven- m C ~niliion mi
tional tubing materials, savings in the order of £2.6 PUMPS
million are calculated. Plain 15.1 43.2 29590 1.68 17790 11.0
An itnprovement in the overall heat transfer co- 10 f,ir extractionequipment 12.2 43.0 21786 1.68 16379 12.0
Roped
.
efficient of roved tubes is clearlv illustrated bv the
defined reducion in tube length and CW quantity,
and hence the size of tubevlate reauired to achieve lo.' Introduction
these savlngs The objectzves of the alr extraction plant are.
...~~. "-

Condensers. ~ u m mand cooiinq water plant Air extractior~cqiiiji!,ii,i;l

s 'TO icniove air ivhicli has ieaked into the condenscl' 'The desigii air lcakngc i;itc\ ~,ici?liliii i ! i of how this is achieved arc described, and the Lions oS vacuunl niaint.aining and vacuulri l i t i , . i m / 8 ,
via flanges and glands effectiveh. 4.4 are known to be lhiglhei I!I~U! I I I O ! , ~ l ~ c i c ~ quipment types are reviewed. either in full or in pa1.1, depending upon the v c i l i ~ i i i i .
some othcr countries and, iii ~ n l l m y ill!,il#l to be evacuated and the time specified for syiiciii,i
e To remove other iiicondensabie gases that are pre- cousidcrably in excess or niv Ic~lk.l$?!.<% l % \ v L < ni~iiigthe machine.
sent in tlle steam exhausting froin the L P turbines. on British plan1 in practice. The c o n d e n s e r air cooling s e c t i o n It is interesting to note that the last-row bli~ir,,
However, experience has sllowll l i l i i l . O i i I' lci for the air cooling section to perform ef- o f a 660 MW turbine will overheat if they run ;ii
the adoption of these ratings lhna 1hui:n oc,rllc 1 I?, its position within tile condenser and the speed and at iow load in a poor vacuum. Therefor',,
It is important that both are removed from the con- justified as a means of countel;irlilI)i lilc i'i,illl Il)d of venting must be optimised, and the trans- a vacuum o f 677 mbar(a) must be obtained befoir
denser, as their presence in any quantity impairs the 01' incondensable gases from the condensing zone steam is admitted to the turbine, and a vacuum of
heat transfer performance of the condenser. Con- I
High air leakage, duc to val\'e pt~ckii~l> 880 mbar(a) for full speed. It is important that the
versely, excessive air extraction capacity should be joint leaks, etc. nsures that the air cooling process is achieved time taken to bring boiler and turbine plant on-
avoided, and reasons for this are discussed later. inirnum pressure loss through the condenser, load shall not be increased by insufficient extraction
The air extraction plant must be capable of func- Higher than design pressure loss tl~rollal~
Ill withoul creating stagnation regions within the capacity.
tioning under two cegimcs: one during normal opera-
tion, the other when raising vacuum on the turbine-
generator unit. . denser and air extraction pipework.

Excessive steam penetration through lilc


ond den sing zone or introducing excessive steam
ution into the air cooling section.
I different air cooling section designs have been . The main systems in use today are:

.
Rotary pumps (e.g., Le Blanc), which use water
When raising vacuum, the air extraction equipment system.
is faced with a large quantity of air which must be

.
from the cooling water inlet end of the with separate booster pumps for vacuum raising.
removed, and must therefore have the capacity for Adverse effects of part-load operalion I
the other uses multi-point extraction from
reducing the pressure in the condenser quickly to a cooling water temperature conditions.
points along the condenser lengt,h; these are Hydraulic pumps, which work on the water-jet
level which aliows the turbine to be started. lled for a pannier condenser in Fig 4.38. principle, for vacuum maintaining. Pumps of this
The considerable experience gailled, ptllliclil I' cooling sections designed on the first principle type have reasonable vacuum raising cliaracteristics,
from 500 MW turbine condensers, h;~slerl 1 0 I! lllc basic features of a redistribution passage but usually require to be supplemented by liquid-
greater understanding o f the factors iafil~c~~i:i! lic steam and incondensable gas mixture in the ring pumps for vacuum raising duties.
10.2 D e t e r m i n a t i o n o f air e x t r a c t i o n q u a n t i t y inleakage and its effective removal from Iinpo ~rxialdirection, together with a baffling arrangc-
T o ensure adequate removal capacity under operating densers. )wards the cold end of the condenser to force A system which consists o f an ejector and a pump.
conditions, the capacity of the air extraction plant The limiting difference between lh ' tiire across the tubemst before final extraction. The ejector provides the first stage of compression,
must be greatex than the maximum amount of air temperature and the cooling water d i-point extraction condensers, the steam and and a liquid-ring pump provides the final stage of
and non-condensable gases expected to be removed able gas mixture usually make one trans- compression to atmospheric pressure. This system
from the condensate. , of the air cooling section tubes, and no uses both the ejector and the pump for vacuum
The main parameters which determine the quantity performance. Most large condensers in opernl es are provided for reintroduction of the mix- tnaintaining duties, but the pump is used in iso-
of air to be extracted from the condenser and, hence, temperature differences in excess of this figuic: lo the air cooling section tubenest. lation for vacuum raising.
the design of the condenser air cooling system and air thinking suggests that a temperature differen i$icnsers with single and multiple water passes,
removal equipment are: to 5OC Is desirable if pressure loss on 11 will, single and multiple vacuum arrangements
and/or excessive steam carryover to the nllopted both types of air cooling section, and A summary of the development of air extraction

.
r The design air leakage into the condenser.
The degree of sub-cooling of the air/steam mixture
leaving the air cooling section.
equipment is not to become a critical fact<
mining condenser performance.
erally operated satisfactorily.
ingle-point air extraction concept generally
higher pressure drop in the condenser to
lisfactory flow through the air cooling section
equipment is given in Table 4.7, wilicll indicates the
number of installations of each type of equipment
associated with 500-660 MW turbines in the UK.
It is quite clear from Table 4.7 that the use of
multi-point arrangment, but it reduces the rotary and hydraulic air pumps has virtually been
r The limiting approach temperature difference 10.2.1 T h e m e c h a n i s m of air extraction
I? o f excessive steam carryover t o the air phased out in the 660 M W designs. The reasons for
between the saturation temperature B P , T cor- The mechanism by which non-condensable Bl this change in policy are discussed below.
responding to the absolute pressure p, in the transported between the points of entry to I h the introduction of air extraction equipment In the initial stages of the 500 MW programme,
condenser, and the CW outlet temperature. denser shell and the discharge to atmosphrrc incorporates a direct contact pre-condenser, orders were placed for two air pump systems on
subdivided into three stages: over o f steam is not such a critical factor which there was previous British experience; these
Table 4.6 indicates recommended values for typical 'rmining the air extraction capacity. being Le Blanc pumps and hydraulic air pumps. Both
Transfer of incondensable gases from the systems, however, could only offer a small contri-
fossil-fired power stations of varying size. condensing zone to the air cooling sectioll bution during vacuum raising, and relied on supple-
condenser. mentary equipment to enable units to be loaded within
TABLE 4.6 R e v i e w o f air extraction equipment 20 minutes.
Cooling o f the incondensable gases and as
Design oir ieokagc roles for typic01 fossil-,ired siorions lia development of air extraction equipment The 'ejector plus pump' extraction systenl was
steam in the air cooling section.
condensers has evolved through the use of introduced into Britain during the early 1960s. Initially
Turbine size. MW Extraction and compression of the incondc clion pumps. Steam-jet air ejectors were in this system only used atmospheric air as the motive
11 use, but, for the higher pressure and fluid in the ejector stage, and incorporated a liquid-
gases from condenser vacuum to atmosphert!.
Design air leakage rating, kg/h tilrc cycles adopted today, these have proved ring pump for second stage compression. This gave
Design air suction lcss economic than air pumps, both in capital better vacuum raising characteristics than the hy-
ienipcrafure at oiltlet. C
' In order to meet the objectives outlined earli draulic air pump, which offset the slightly higher
Limiting CW outlei temperature is important that all three stages in the procc Iv different air extraction equipment designs operating costs of the system for vacuum maintain-
carried out efficiently. en developed, all of which combine the func- ing duties.
381
Air extraction equipment

ba~.ometiicloop in the air suction line as a ful-tiler


safeguard.
As aiready mentioned, thc requirement of a 660
M W turbine to reach full speed at no-load withi11
20 minutes of sta1.t of vacuum raising is beyond the
capability of hydrauiic air pumps alone; the inslalla-
tion of supplementary vacuum raising booster pumps
overcomes this problem. On their own, hydraulic air
pumps wiil take in excess of 40 minutes to achieve
desired vacuum levels. In same cases the booster
pumps are supplied on a unit basis, but it has become
increasingly popular to adopt common booster equip-
ment for two or more turbines, therefore reducing
capital costs.
Separate electrical control systems are provided for
the hydraulic air pumps and booster pumps. The op-
eration of the pumps and their ancillary equipment
is semi-automatic and sequence controlled to ensure
that start-up and shutdown procedures are correctly
implemented. When common booster pumps are in-
stalled, the system is interlocked to prevent the pumps
being connected to a running turbine. Booster pumps
are generally arranged to sliut down automatically
when the condenser vacuum reaches a predetermined
level.

X
10.3.2 Licluid-rintt- tvne
.. air numn
. .
: 0 . I I Hydraulic air p u m p s This is essentially a centrifugal displacement pump.
A multi-blade impeller revolves within a n offset casins
. \ I,,) ..$I Il!draui\i XLI putnp arraopcmrn: !r \i>;\srl which is partially full of water. The rotating impeller
$ .?t I . . .I 39. I'll: l , ) . l r , ~ u lpump
~~ unit 1, a !%a.cr-
throws the liquid outwards, resulting in a solid ring
of liquid revolving in the casing at the same speed
r. rccirculating lift pump, and a covered water
as the rotol, but following the shape of the casing.
ld air separation tank. Figure 4.40 shows how this alternately causes the
watcr tank serves the dual function of acting liquid to enter and recede iron] the interblade spaces
___)
il:;it sink for the air and vapaui drawn from the on the impeller. The provision of inlet and outlet
and providing a suction supply for the lift ports enables this pump action to be used for eva-
cw ~ N L E T recirculate the sealing water. cuation of air from the condenser. The advantages
up water is introduced t o the tank at the of this type of pump are that it is simple and reliable,
I11 to replace any losses, and maintain the tank at with large clearances on rotating parts, and no valves
iy temperature. The tank overflow is controlled or pistons.
weir, and is discharged to waste.
in8 water from the tank is circulated to the
'
ONE PANNIERSHOWNONLY air pump where it is fed into a series of 10.3.3 Air e j e c t o r l p u m p s y s t e m s
Streams of water leaving the nozzles pass Figure 4.41 shows a typical arrangement, using air
blades of a spinner which is mounted on as the motive to the ejector. The system comprises
11 of a shaft, and is free to rotate. The blades a n ejector stage and a liquid-ring pump stage, which
led so that the sealing water propels the combines to give two stages of compressio~~ of the
and, in doing so, is broken into slugs. The condenser a i r h a p o u r mixture.
(hi ~ ~ i t , - p oaiiexlra~lon
i~i u'hich ,discharges from the spinner seals poc- Figure 4.41 (a) illustrates the system when operating
Ol' air in the diffuser, pressurises them, and to maintain vacuum in the condenser. The a i r h a p o u r
illges the mixture into the tank. The tank is suit- mixture from the condenser is first drawn through
FIG. 4.38 Single and multi-point air eriraciion vcnted, and the sealing water is recirculated to the vapour cooler. This is a direct condenser which
receives recirculated seal water, of towns water qua-
nir suction line t o the water-operated ejector lity. This cooler reduces the vapour quantity of the
[,rates an electrically-operated isolation valve mixture before compression by the ejector stage. The
C-type non-return valve t o prevent backflow ejector uses atmospheric air as the motive fluid and
llnd water to the condenser in the event of compresses the a i r h a p o u r mixture to a pressure of
failure. Some arrangements also include a about 135-170 mbar.
383
..

Condensers, pumps and cooiing water plant Air extraction equipment

INIERNALINLEIPORI
(NTERNIIL DlSCHIHCit PORT

lllihiE PUMP OISCHARG LTERNAiE PUMP DISCHARGE No 2

--
.-
--.
-
=--- WATER

FIG. 4.40 Tyjlical 1iquid.ring lype air jpuillp

~c condensate from the vapour cooier and the 10.3.4 Steam ejectorlpump systems

-
- CWLINGAND MOTIVE

&tR "&POUR IQIXTURC


WATER

USUAL NUMBER OF UNITS 3 x 50% OR 4 x 33%%

last vacuum raising, booster Pump arrangements is pumped to waste by a cooling water extractor
PIG. 4.39 Typical hydraulic aii pump airangment
'iar to those described for hydraulic air pump pump.
ms) are incorporated, these booster pumps are The motivating steam for the ejector is vent stekrl>
iged t o shut down automatically at about 50 from the de-aerator which would otherwise be dumped
to the main condenser. Since de-aerator pressure varies
385
----....---

-
-
-
COOL1NG WATER
USUAL NUMBER OF "NILS2 x 700%

-
TOWNWATER OR CONOENSATE
SIEAM
AIR VAPOUR MIXTURE

Fic. 4.42 Steam ejector and liquid-ring pump air airaecio~lmainlainins system

-
- CWLINCI WATER

---- T O W N M T t R OR CONDENSME

-
-
ELECIRICAL
AiR
4iA YAPOUR MIXTURE
I° vacvvm ralrno DPsral,o"

Flo. 4.41 Air ejector and liquid-ring pump vacuum systems

387
Condensers, pumps and cooling watel plant liydraulic aspects of centrifugal pumps

148 5W
DATUM

roi.er pci two puliipi, kW 298.4


I'ower reduction, LU' DATUM
cost saving at IISW/LW DATUM

space occupied, mi DATUM


Cost saving at f12601n1~ DATUM

Cost ~aviiigsin terms of pump


siw. po.iei and space (I), I DATUM

Quick start times, nlin 13


Additioiiai times. !win DATUM

For internal aeeoaiiling


10% DCE is used, i.e.,
XI0 3881min

DATUM

Overail cost saving,


(1) - (2). I I DATUM /
I
64 794 1 134 164

nc. 4.45 rum,, efficiency vers US specific speed and punlp size

is not exceeded. These costs could offset the apparent in pump design - head, flow and speed. All
cost savings of £134 764. metrically similar pumps have the same specific
It would appear that the intermediate vacuum which is calculated in non-dimensional units r, pumps, optimum efficiency when using low 11.2 Net positive suction head
pump size (pump B) can meet the traditional vacuum the following formula: i prime movers necessitates a large number of The net positive suction head (NPSH) is an im-
raising time of 20 minutes, and offers some cost portant concept in judging the suction behaviour of
saving, aithough not as significant as pump C. n, = 2 ~ n ( q , , ) ~ ' / 6 0 ( g ~ ) ~ ~ ~ !s comparison, efficiency optimisation could be
a centrifugal pump. A distinction needs to be made
The extra pumping capacity of the option would llieved by using single-stage high speed machines.
between the NPSH available to the pump and the
be more tolerant to any increases in air inleakage where n = pump speed, r/min 11 these extreme options, however, can have their
NPSH required by the pump.
above 40 kg/h, and therefore less emphasis would I potential disadvantages. The high speed ma-
q, = flowrate per impeller eye, m3/s The NPSH available is the difference between the
need to be placed on achieving and sustaining low ' can lead to excessive impeller tip speeds and
H = generated head per impeller, m equential erosion problems, while the slow speed iniet head to the pump and the saturation pressure
air inleakage rates from the associated plant.
g = acceleration due to gravity, m/s2 Ingernent results in a flexible shaft design unable of the liquid being handled. As the available NPSH
'ater for transient operational requirements. Thus is reduced, cavitation commences, first at flowrates
pump hydraulic design is usually a compromise away from best efficiency and eventually over the
There is no firm demarcation between the \ complete operating range. This is a result of the local
pump types. Each merges into the next, so take account of all relevant factors, including
11 Hydraulic aspects of centrifugal ,hanical limitations and suction head considerations. pressure falling to the vapour pressure of the liquid
a given specific speed there can be two p
pumps le effect of moving away from best efficiency can at the particular temperature condition. Operation
differing construction. However, specific sp
en in Fig 4.46. A specific speed below optimum in a cavitating mode for extended periods results in
be defined as falling into the following catego
the peak level of efficiency, but there is a erosion damage, regardless of impeller material. Feed
uential improvement in the spread of higher pumps with a high head per stage are most liable to
11.1 Specific speed Type of pump Specific speed rang? cy. This can be of use when plant is required cavitation damage because of the higher energy input
(IS0 notation) perate frequently over a large flow range. to the fluid.
Centrifugal pumps are traditionally divided into three
basic types: radial flow, mixed flow and axial flow. Radial flow 0.2 to 1.8 oving to high specific speeds is seen to produce Cavitation performance breakdown has been shown
The names indicate the direction of flow of liquid Mixed flow 1.8 to 3.0 eeper head/flow characteristic. This can be ad- t o be directly proportional to (shaft speed12 for a
through the impeller. The term specific speed (n,) lnlageous when operating pumps in parallel as it centrifugal impeller. It has also been shown that the
Axial flow 2.8 to 8.0
can be used as an aid to the classification of the oiinises the risk of unstable operation. One dis- head drop at which unacceptable cavitation damage
pump type and is indicative of the shape of the im- vantage of the high specific speed designs is the in pump impellers occurs, increases with pump speed.
peller and the pump hydraulic characteristics (Figs It is evident from Fig 4.45 that to optimise the npe of the power/flow characteristic which can be From these findings, it is evident that the suction
4.45 and 4.46), which are taken from Steponoff [19]. draulic selection on an efficiency basis, a spe lest at closed valve. This results in excessive motor head levels needed for high speed pumps are signi-
The expression involves the three fundamental factors speed around 0.8 is necessary. For high-head I ngs to cater for start-up requirements. ficantly greater than those for lower speed machines.
391
Cotidensers, pumps and cooliiia water alant Circulating water pumps

Suction specific speed CCGB experience baa beeti gencsaliy based oil
cinr siiclioir syccific speed (n,,) cxpl-csscs the lhydieuiic designs wliel-e tlic specific speed bas been
3 1 capability of the piimp iiiipcllcl- and is defined limited to 1.6. This iediices the risk of both head/
iiow clial-actcl-istic instability and high gowe~.sat low
- a -cood efficiencv. sol-ead
flows. I t also ri\,cs . over
n,, = 2nn(q,)oS/6~(g~~~~)0.75 thc range of operating flowratcs. 'The head/fIou~rate
and absorbed power characteristics are now controlled
EFFICIENCY %
OF NORMAL
n = pump speed, i./min
q,. = fiowratc per impeller eye, m3/s
NPSH = net positive suction head, m
.
by the following specification:

Pumps are designed so that the discharge head


falls continuously as the flowratc is increased from
zero to rated capacity by a minimum of 1% for any
g = acceleration due to gravity, m/s2
15% increase in discharge flow.

The p u n ~ p sarc capable of sustained running at


n,, are associated with large
any point on their hcad/flow curve from 25% to

.
CAPACITY % OF NORMAL CAPACIIY % OF NORMAL diameters and improved suction capabilities the maximum ~ ~ u n o ucondition.
t
EFPlClENCY HEADCAPACITY
llnd pump best efficiency (BEP). The large eye
lead to problems of inlet The input power rises continuously as the flow
off-duty conditions, with is increased from zero to the rated flowratc.
hcquential pulsations in the pump and adjacent
()?work. At flowrates away from BEP, incidence
scs flow separation within the impeller. This se- Circulating water pump speeds arc normally in the
inled flow is then directed backwards out of the range 150-300 i/min. Low spccd motors, suitable
'l'lic larger the impeller eye, the nearer to the for direct coupling to the pumps, are expensive and
is the flow at which this recirculation occurs. it is usually economically justifiable to include a
BRAKE 1 Prevent the damaging effects of inlet flow re- stcp-down gearbox between the pump and motor.
$HORSEPOWER% lation, leak-off flowrates need to be sized so as The combined efficiency of a I000 r/min high speed
OF NORMAL
cllsurc that pump throughput is always in excess motor and associated gearbox can bc similar to the
ille amount at which recirculation commences. low speed multi-pole motor. When comparing capital
a applies particularly to both feed pumps and costs of the two ootions. the costs of extra cranaee -
equipment and the additional civil work to support
111 the absence of detailed information of pump the heavier motor have to be added to the direct drive
0 21 50 7S >OD 125 550
liability at the tender stage, the CEGB normally pumpset costs. The two main advantages of the dircct
CAPACITY % OF NORMAL iliiires that the suction specific speed bascd on the drive option are its simplicity, which can lead to higher
Sli available to the pump should be limited to availability, and the elimination of any noise control
BRAKE-HORSEPOWER
requirements arising from the high speed motor/
gearbox combination.
For fiowrates over 10 n?/s, main cooling water
pumps arc now bascd on the concrete volute type.
Circulating w a t e r pumps Below around 6 m3/s, it is impractical to consider
concrete volutes because of physicai access limitations
in the mechanical seal area, and metal casing designs
The minimum NPSH required can be defined as that to avoid cavitation problems [ZO]. have been used. Between 6 and 10 m v s the CEGB
value of NPSH needed by the pump under long term Visual cavitation tests are carried out on a sp ,I Introduction have so far installed only metal casing pumps, al-
load conditions to prevent the occurrence of harmful test facility, where, for example, a perspex wind ructural design of main circulating water pumps though concrete volutes have been successfully used
cavitation effects, in particular that required to avoid allows an uninterrupted view o f the impeller eye, EGB has changed over the last 20 years from elsewhere.
cavitation damage and ensure satisfactory operation. enables visual observations t o be m a d e uni tal split casing double-entry designs to the
Normal practice for determining the NPSH re- stroboscopic lighting. This is a n important to spindle bottom inlet single-entry type. The
quired to limit cavitation damage to a n acceptable allowing the exact cavitation inception point to tal pumps, while easy to maintain, require a
level is based on head drop tests. For high duty feed determined, which effectively defines the zero cav floor space, and the weight problems on the 12.2 Horizontal split-casing pumps
pumps, the assessment of visual test data is now also tation damage line. Although observations o f I units necessitated the use of multiple casing Double-entry horizontal split-casing type pumps (Fig
used as a n additional means o f assessing the adequacy pressure face o f the blade are difficult, this pr s. The alternative vertical spindle pumps, now 4.47) have been installed on CEGB stations to cover
o f NPSH margins. can be overcome by using acoustic inception ly specified, have been developed for both a wide range of duties up to 18 m3/s and 24 m gen-
The NPSH head d r o p test can be included as niques to establish the onset of cavitation. I casing and concrete volute applications, with erated head. This design of pump has the major
a standard proof o f performance test, with mea- checking NPSH adequacy using the visual techniq~i clloicc depending on the overall economics o f advantage that the top section of casing and the
surements being taken to establish the NPSH a t current practice requires the available NPSH to Ihtl\ installation. They have significant advantages rotating element can be removed without breaking
which a 3% drop in generated head occurs. From a margin over the visual appearance NPSH, wh >pared with the horizontal designs in terms of thc either the pipe joints or disturbing the alignment.
data available, it is considered prudent to provide itself is associated with bubble cavities having n apactness and cost of mechanical, electrical and While this feature gives good accessibility for both
for feed pumps at least 3 x 3% head drop NPSH agreed maximum length. I engineering work. overhaul and maintenance work, the horizontal design
392
:ondenscrs, piimps a n d cooling water 111ont chiii,li: Circulatilig water pumps

i nomher uf disadvantages apart from the large duct. Tiic asseinbly then acts as both a sealing ring
area i-cqilired. In ipariicular, the preference for for [lie top covci and also as a ccntral location
ling llic uilit with thc iiiipeiler cyc beiow mini- araunrl which the precision-made voiute sllutleiirlg
water level, to eiiminale the need for com- framework is assembled piior to concrete pouring.
prilliing equipment, results in expensive civil The volute shotteiing is iiorrnally provided by the
ivations. The physical size of thc large metal civil contractor to thc pump manufacturer's dimen-
has also brought about both manufacturing sions, and can be re-used on all pumps on the same
lties and fiexing problems with the complicated contract. Figure 4.49 shows the various stages of
construction of the volute. From experience, it has
been found that no special protective coating is re-
quired on the concrete to guard against the effects
o f the water being pumped. Both wear and life
Vertical pumps expectancy of the concrcte are excellent and no pro-
blems have been reported on CEGB pumps at inland
3 . 1 Vertical metal-casing p u m p s or coastal stations over a 20 year operating period.
lute casing designs have been used by the CEGB A fabricated steel bearing bracket is mounted on
iIilmping duties up to around 8 mi/s. On low head top of the pump cover and bolted down and dowelled
a1 applications, standard gear-driven units have into position to secure correct alignment. The speed-
lstailed, while on the higher liead inland cooling reducing gsarbon is !mounted on top of the bearing
applications, it has been possible to use a direct bracket, with the unit incorporating the pumpset
I- drive while still retaining the same equivalent forced lubrication system. The rotating assembly is
,cific speed a s the equivalent gear-driven units. supported by a combined thrust and journal bearing
llernative bowl pump designs have been used which can be located within the gearbox. Access to
iisivciy on overseas applications. With this design, the bottom bearing and mechanical seal is gained
l u m p forms part of the piping and its intake is from within the tubing.
rn a relatively unsophisticated suction chamber;
~nerallyhas a smaller civil engineering cost than
equivalent concrete volute design. There is no
nplicated volute to construct, and as the pump has 12.4 Gearboxes
nalier overall diameter than the concrete voiute, Gearboxes, when included on vertical pump units,
pumphouse floor area is smaller. On thc debit must be of the coaxial type with the pump, motor
and gearbox centreiines positioned vertically above
each other to ensure an equal load distribution on
the support ring.
c normally has to bc sized to take the total Coaxial gearboxes may be either of the muiti-
I 11111 weight for installation and overhaul. As the layshaft or epicyclic designs. With recent epicyciic
111111) is withdrawn vertically for major overhaul designs, it has been possible to combine the gearbox
a suction isolating valve is not required. This and the pump by mounting the impeller on the low
er leads to a relatively long pump to facilitate speed output shaft of the gear unit (Pig 4.50). This
I isolation. One major technical disadvantage arrangement eliminates the need for one journal
the bowl pump is the need for submerged shaft bearing, which in turn reduces the overall height of
iring bushes. These are not readily accessible and the pumpset leading to a more compact arrangement.
lave a relatively short life in silt-laden water. A further reduction in pumpset length is achieved
sting problems have tended to limit the size of by combining the thrust coliar into the coupling hub,
as shown in Fig 4.50.
of cast iron necessitates the inclusion of sub- The gearbox is equipped with a complete forced-
ntiai allowances on coastal units to allow for lubricating oil system to provide a continuous flow
rosion/erosion effects over the life of the station. Of oil to the gear internals and the thrust and journal
bearings throughout the pumpset. The oil system
includes both gear-driven and standby motor-driven
C o n c r e t e volute p u m p s oil pumps, and the piping and non-return valve iayout
re 4.48 shows the sectional arrangement of a allows delivery of oil to the bearings and gears,
1 concrete voiute pump, which follows the whichever direction the pump is rotating.
e hydraulic principles as the conventional metal
lg designs except for the volute which is formed
F ~ O .4.67 ~orizon~ai
split-caring extraction pump at Dunsenerr B Power station ite on the concrete foundations. The pump casing
ists of permanently-embedded top and bottom 12.5 Shaft seals
'ng rings separated by the cutwater and stay Mechanical seals are included to prevent water es-
cs. These are carefully positioned over the inlet caping from the casing along the pump shaft. Split
TACHOGENERATOR C0NCIIEII;INIO

F i N A l i Y POSiiiONFD BUT 'IAGE


ONLY IF VOLUTi BASE iS FLAT

MOTOR srooi
1:iG 4.49 ConstrucLion or concrete voiuie

I designs are used (Fig 4.51). All the com- performance of the full sire pump and the cost of
OlL "RAIN

Ipollcnts to be carried out witllout any major itself. Model tests enable the hydraulic characteristics
of the full size pump to be accurately predicted. This

m the pump discharge o r a separate towns Scale models are also used to verify design pro-
ply. Figure 4.52 shows a typical seal flushing posals for the suction intake to the pumps. The model
nt on a coastal station, where the filtered normally comprises the forebay, intake screen cham-
normally taken from the pump discharge ber, draft tube, volute and discharge pipework. Com-
ng purposes while the pump is running. A prehensive tests are carried out to demonstrate the

is also available as a back-up supply during in suction water levels.


PUMP CASING COY8 i l

laws are applied to demonstrate that the guarantees


'l'lic seal assembly also includes an additional in- on head and efficiency at the rated flowrate, and the
h i e static seal. This is operated by air and forms shape of the headiflow and poweriflow character-

T o overcome any contractual problems in determining


Any water which leaks into the access well of the head losses at suction and discharge, the pump is
lcrete volute pumps is removed to the drainage deemed to be that part of the system from the open
np by either a small submersible pump or an air- water level at draft tube inlet to the discharge mea-
crated ejector system. These can be controlled surement point.
111 float switches o r a n adjustable timer. Flow measurement is considered the most difficult
aspect of circulating water pump site testing, and
various methods are currently employed. On stations
with long straight open culverts, the current meter-
FIG. 4.48 Bottom inlet sinde-entry impeiier concrete voiute pump .6 Pump testing traversing technique has been found to give satis-

f any large new circulating water pump design. use. For other stations where there are no suitable
an economic method of evaluating the likely open channels, the isotope dilution method is widely

397
MAINOIL PUMP

INFLATABLE SEAL

ANNULUSRINGS MOUNTING RiNG-

PLANET WHEEL
LOW SPEED Hli<i

Flci. 4.11 Puo)p $11811 seal

while grey cast iron can be used for inland fresh-


water sites, austenitic ni-resist cast iron is required
for seawater applications.
Circulating water pump impellers are supplied in
stainless steel with renewable eye rings to cater for

FIG.4.80 CW pump gearbox

used. This involves the injection of a tracer of work, and yields highly accurate results. The prir
known concentration at a constant rate upstream o f disadvantage arises from the strict safety precaul
the pump and measurement of the concentration at necessary when using radioactive tracers and thc the waterways. Special attention is required at the
a point downstream of the injection point where sulting inflexibility of the test programme. c use of austenitic ni-resist cast irons for the sleeve/sleeve and sleeve/impelier joints to prevent
adequate mixing will have taken place. The dilution An alternative flow measurement technique 18 material of cooling water pumps where severe ingress o f water onto the shaft surface, which can
technique is completely independent o f the velocity developed is the use of ultrasonic flowmeters, lilions exist is now increasing rapidly. This ma- cause corrosion fatigue. On horizontal pump designs,
of the pumped fluid, or the dimensions of the pipe- multiple transmission paths being included to I, particularly in its spheroidal graphite form, overlapping sleeves and radial O-rings have been
399
FIG.4.53 Horizontal split-casing extraction pump
Condensers, pumps a n d cooliiig water plant
Railer teed pumps
-

impeller inlet, the first stage impeller eye of a hori- which can occui on the a l t ~ r n a t i \ ~aliangeillr
e
zontal extraction pump should be vented back to the the punlps are operated significantly awa)' f~-oil3Ill
vapoui space in the condenser, with the vent piping duty points.
having an upward slope to the condenser. I'umps are specified with a requirement thar
In recent CEGB stations, where surface tubular tion erosion does no1 produce mechanical fail

COIlPilNG L D C K N U i
large split-casing pumps, particularly in sealing the is limited to 2.4 (ISO). COUPLING KEY
main joint and withstanding impeller radial loads.
VEHIICALIHRUSTANO
An alternative caisson type pump (Fig 4.54) has now JOURNAIGUlDEULARINC.
been adopted. The multi-stage vertical pump design
has several attractions over the horizontal split casing 14 Boiler feed pumps SPINOLESFIIING
PUMPDELIVCRI
pump: ARRLNGMENIAND
LE*K.OFT SISIEM
COFDELIYERV
The NPSH available is increased by installing the
pump in a pit, thereby reducing the risk of cavita. 14.1 Introduction
tion crosion.

An increase in the NPSH available allows the 1, determining the arrangement o f I

same NPSH margin.

is need take static shaft deflections


effects of loss o f availability. Other constraints n
into account on the vertical pump. Radial stresses are:
should be

. are reduced allowing a slimmer shaft to be used.

Only a single mechanical seal is required which


operates under pressure, providing less danger of
the oxygen ingress that was sometimes encountered
The need to ensure that failure o f a single purl
does not impair the start-up of the main 1111
affect output capability. Standby capacity equ
lent to the largest duty pumpset is indicatet
with the older traditional pumpsets. To prevent
a rapid start-up capability, sufficient to I>
oxygell ingress while the pump is on standby, the EOI s ~ ~ ~ , ~ ~
inner seal chamber is filled at all tinies with pies- the loss Of boiler drum level and cOnseque'
surised water supplied either from the common
discharge manifold or from a back-up reserve feed- .
.
to ensure that the plant is able lo
water supply when both pumps are stopped. erate satisfactorily during and after a large I >
There is a facility for a cartridge-type repair which rejection by the turbine-generator unit. This
improves pumpset availability. ~h~ pumps are quires that the drives for the duty pumps and t
designed so that, by disconnecting the pipework power supplies must be suitable for this opera
at the discharge branch, the pump element can condition. Alternatively, a suitable rapid $1
be readily removed from the caisson in one piece $landby pumpset is necessary.

. following removal of the electric motor.

A more compact layout can be achieved with the


vertical pumps which take less space than the hori.
zontal designs.
The need to provide adequate NPSH margi
taking into account that the Pumps are ~ U P P ~
from a direct contact heater (de-aerator), which
be subject to pressure decay following a redticti
in turbine load.

To ensure that the extraction pumps have stable There should be at least two pumpsets capable
head/flow characteristics and are capable o f operating starting the unit. If a turbine drive is to fulfil t LWSE BELLMOUItI
in parallel over the complete operating range, the function, then a steam supply independent of
BEARING BUSH
pumps are now designed so that the generated head main boiler (i.e., an auxiliary boiler) is requir
rises by at least 1 % for every 15% reduction in
flowrate between the rated duty point and 25% rated If two o r more pumps are required to op
flowrate. in parallel, then the pumpsets should be able
Extraction pumps on CEGB stations have been accommodate run-out duties following 10% of
operated on either free suction or recirculation control. operating pump. FIG. 4.54 Vertical caisson extraction pump
402
Boiler feed pumps
Condensers, pumps and cooiing water plant

r TIi? pio\,ision of sufficient l>iirnying to were typically a sliou,n iri Fig 4.55; tile!' illcli ?/mill) to aciiicve tlie necessary lhigir licad pel- stage.
fro,,, ,.equire,,,ents ol)cl-ationai ~ i ~ long
. flcxibie shaft witli about sin stages and i l l i Slow speed boostcr pumps arc therefore required to
cumstanccs. It is lioililal practice to include a flow dual t111.ust from the impellers taken by ;I pravidc sufficient NPSH to linlil cavitation problems
rnaigio to accommodate additional demand by the tional balaiice disc arrangement. The bearin I>III damage, and having s cartridge co~istructiorl on the main pump.
turbine above its design rating during transient mounted o n separate pedestals which had I < With regard to NPSH, a conservative design ap-
flow disuirbances. A margin on pump generated moved before the $main pomp internals could i)i' V proach was adopted. De-aerator storagc tank height
head is also appropriate to cover for deterioration drawn. Glands were of the fixed labyrintli Or i i ~ ~ l l and suction pipewark layout were arranged to pro-
from intcrnal wear during periods between ring type, and the main bolted casing joint I specification, means that the pump nlust be vide a substantial margin of NPSH over the measured
overhaul. In the interests of keeping pumpset sizes jected t o full discharge pressure. pump 3% head drop NPSH, even under the worst
transient situation.

for replacement of the pump internals. iibstanlial head. After this the pump is enpccted 14.3 Advanced class feed pump construction
The pump casing consists of a forged steel barlei to
flexible shaft design of feed pump, and which are welded the suction and discharge branches.
awareness of overall economic considerations, :i I Extensive areas have stainless steel cladding to give
14.2 Feed pump developments concept was developed with the emphasis on ac ' " protection against erosion. Supporting feel are ar-
Boiler feed pumps installed on early 500 MW units maximum availability coupled with a dcsig~l ranged at the centreline t o give positive restraint to
movement upwards and downwards and yet ailow-
ing for free thermal expansion. Sliding keys control
thermal movement and maintain alignment with the
drive.
The pumps have all their bearings, both thrust
and journal, in housings supported off the pump
!!.I. requirements have been met by the develop- casing or internal cartridge. This makes the pump
NIISWIRLVANE more immune to the effects of pipework ioads and
SUCilONSiOPPERASSEMBLY
minimises the effects of shaft misalignment.
ORhYLOC SEALING RING The 'cartridge' inner pump assembly, complete with
substantially stiffened shaft with the number of integral bearings, is designed so that it can readily
MECHANICALSEAL
COYER PUiiE be transported to a suitable maintenance area as a
package unit. The cartridge components are pre-
assembled on a manufacturing jig so that no subse-
quent adjustment is necessary to ensure component
Illrrnai clearances enlarged to ensure that the concentricity, and minimal adjustment is required to
liiaip is capable of dry running without damage. achieve the necessary degree of coupling alignment
after the cartridge is installed in the pump barrel.
MECHANICAL SE lplacement of the heavy externally-bolted dis- O n ilisertion into the barrel, the suction and dis-
Irge cover by a n internal self-sealing high pressure charge ends are slid apart and located at their res-
pective ends of the barrel. Three joints are made
during this operation; the suction ring section and
main cover joints. Although different designs of
pump have been adopted (Figs 4.56 and 4.571, car-
11 external oii-lubricated thrust bearing. tridge replacement follows the same strict methodical
procedure.
dge' design, permitting rapid replacement of T o ensure rapid cartridge changeover, the normally
mp internals with a spare element (an alter- heavy externally-bolted discharge cover arrangement
design was also developed using the concept has been replaced by an internal self-sealing high
11' removal and replacement of the complete pump pressure joint system. Rapid replacement of the car-
lllit, having a special bolted arrangement o n the tridge necessitates the use of specially designed with-
iiijacent suction and discharge pipework). drawal gear as illustrated in Fig 4.58.
CoOLlNG WATER CONNECTiONS
The impellers are o f high quality precision-cast
stainless steel, with the castings subject to extensive
. result of the stiff shaft is that, even with the radiographic inspection and stringent dimensional
xlnil~m permitted worn internal clearances, the control to ensure repeatable cavitation performance.
r transverse critical speeds in water are well above The first stage impellers are designed to have a ca-
mating speed range. This permits relatively high vitation life of 45 000 hours when operated in the
FIG. 4.55 500 MW main boiler feed pump oilal speeds (typically in the range 6500-8700 range 80-100% of the rated flow.

405
"--
<~
"si-
8
.

R
Condensers, pumps and cooling water plant Chaotei 4 i
Boiler feed pumps
Boiler feed pumps

SlhllOSIILL Siihl
C""FI1

SHAFT SLEEVE

IIYURO GLAND
BUSH
--- SEALFLANGE

W A i W THROWER

ROiAliNG FACE

SIAIIONARY FACE

4.60 Labyiinfll gland and siaiidsiill real


F~G.

taken from the condenser extraction pump discharge of these long slender shaft designs, in additic SPRING HOLDER
and fed direct to the feed pump glands. The injection minimising running and standby leakage. As a
pressure would be controlled at approximately one of the early satisfactory performance of mech;
bar above the gland unloading pressure. T o cater for seals, there has been a progressive developmrlil
start-up conditions and interruptions in the supply mechanical seal systems up to the high speed viil,i FLANGE

1'lG. 4.61 Meel~aocalacal

tanks. feed pumps, while retaining labyrinth arrangcnic


Since the leakages through labyrinth seals are on the main feed pumps. For a 3 x 50% pumi)
relatively high, it can be desirable to reduce the rangement, mechanical seals are accepted whei~: I ;any magnetic particles, which could abrade the feed pumps has resulted in the need for an NPSH
leakage flow when the pumps are stationary. This can be demonstrated that the seals have a design ll laces, are removed. well in excess of that available, even from high level
is particularly relevant to standby feed pumps. There- of at least I5 000 h. , face materials used on early feed pump seals de-aerators. This can be provided by slow speed boost-
fore standby seals are included which operate when A typical hish duty mechanical seal arrangem lungsten carbide rotating against a stationary er pumps, driven either separately or in tandem with
the pumps come to rest. The standby seals consist of is shown in Fig 4.61. The 'cartridge' design enill 11 face. While this combination proved very sat- the pressure stage pump.
three segments which are held together on the shaft it to be assembled as a complete unit into the puin ry on low speed applications, on certain high Separately-driven booster pumps necessitate the
to form a closed seal when the pump is stationary. thus minimising installation errors. A pumping rll
They are opened by centrifugal force at a predeter- is incorporated into the rotating part of the sco
mined speed to minimise rubbing contact during pump which circulates water around a closed loop, throu
operation. For base-load feed pumps, it is possible a heat exchanger and returning to the seal face nlr rcmature failure. The reliability of feed pump prevent vapour locking in the event of failure of
to replace the centrifugal seal arrangement with a n This recirculation enables the correct seal face
extended labyrinth. This reduces on-load leakage losses peratures and stable face conditions to be achie
at the expense of higher leakage while the pump is The heat exchangers are normally positioned abi
stationary. A labyrinth bush outboard of the injection the seals in order to obtain a good thermal sypl additives, use o f this material eliminates this sure stage pump leak-off valves to be closed when the
point controls leakage of water t o a clean drains effect during hot standby conditions. An inner co pump is standing to prevent recirculation back to the
vessel, from where it can be recovered to the system. ing jacket is also included to reduce the heat de-aerator.
Problems with labyrinth glands on some earlier into the seal chamber. In certain designs, the e Tandem sets (Fig 4.63) require less complex pipe-
work arrangements, less complex feed systems and
to mechanical seals. These reduced the risk of tem- thermal syphoning. A simple magnetic separator Pump layout and drive take up less turbine hall space. Being dependent on
perature stratification problems in the labyrinth area also installed into the seal pumping loop t o enso increasing head per stage in the high head boiler a single drive, they are also more reliable than the
Condensers, pumps and cooling water plant Railer feed pumps

'The overail unit (Fig 4.54) cooil~iiscs, witiiiii tile lion. lo #lie boiler and the lcalc-off i?o\v. Aisc,,
casing, a nuid coupling and step-og gears. For tile prcssore diffeicntiai tappings are not reqoiie<l i t , I
high oulput speeds required on advanced clasi gomps, position.
stcp-ug gearing is included on boti, the input and Eiectiically-operated valve actuators have b c i i i I I
output sides of tiic coupling. on many stations bill as failure of the e1cctric;iI i.
The fiilid coupling incorporates two separate oil plies woi~ld rendel. then1 inoperative and pomji
systems drawing from a common sump. One system tection would be lost, the electrical supply
provides lubricating oil to thc fluid coupling and to valve is taken fvom separate station switchh

and the driving motor. The oil is drawn from the electropncunmatic systems lhave resulted in a pref

the second system, oil used as the working fluid is of the pneumatic system is that the spccd of i
circulated by the dynamic head generated at the scoop tion is readily adjustable.
tip in a closed loop. Make-up for this closed loop is To provide maximum protection to the pun111
provided by a gear-driven centrifugal pump dwing piping system under all foreseen operating COLI
normal operatioll and a motor-driven gear type pump the valves lihust be capable of opening r a p i
for startilmg and standby duties. Both circuits include the other hand, very fast opening can lead
oil coolers. acceptable shock loadings on the feed systenl
experience, valve opening times of up to IS
been found acceptable, dependent on the feai

14.7 Light load protection


The telnpcrature rise across a pump is caused by times after installation, to suit local conditionr
two separate phenomena; the isentropic co~npression operating practices.
temperature rise and the rise generated by the in- T o pcrnmit on-load maintenance of the I
efficiency o f the pump. As throughput diminishes, system, sufficient manual isolating valves are il
efficiency falls and the temperature rises. If a pump and any parts subject to in-service wear, for ex,

this, a leak-off system is provided which opens auto- avoid malfunction.


matically at the minimum safe flow and allows the
pump to discharge to the de-aerator. Pressure in the
leak-off piping is broken down through a pressure
reducing vessel, uahich consists of a series o f orifice 14.8 Testing
plates, and finally with an orifice plate positioned at CEGU specifications require that the 100@li 8x11
the inlet to the de-aerator and sized to avoid flashing boiler feed pump is tested at a load corieslioi,dl
in the leak-off pipework. to turbine MCR to prove conformity with the R I I I
Low throughput can also lead to random pressure antee, and also at part-load to confirm thal I
pulsations being generated by the pump. These can pump performance characteristics are satisfaciol
excite low frequency resonances in the adjacent feed Site tests, however, are of necessity late in the sliill
system pipework, leading to unacceptable pipework construction programme, so that any shortfalls

commenced.
The configuration commonly used on CEGB stations For steam turbine driven pumps, it is not pracll
(Fig 4.62) consists o f 2 x 100% parallel slide leak-off to specify full works testing and instead part-spc
Valves, arranged in parallel, with a separate pressure interim hydraulic performance tests are carried oul
reducing vessel downstream of the valves. T h e ini- the manufacturer's works to d e m o ~ ~ s t r a tthal
e I
tiation signal for leak-off valve operation is taken pumps have reasonable prospects of achieving 111
from an orifice plate located in either the suction specified requirements on site In terms of rated di
or discharge pipework. Installation in the suction and hydraulic characteristics. These interim tests I
pipework is preferred since this location senses total followed by full-load acceptance tests on site wit11 I
pump throughput, i.e., the summation of forward plant in service.
Condensers, pumps and coolitig water plant

Manofactul-cl-s works test facilities arc gnlcrally


suitable far full-load acceptance testing of electrically-
driven feed pumps. Tire suction and picssuic stage
pumps are first tested individually to canfirin tlic incccssary NPSH, is in line wilh overseas p
head/efficiency guarantees, the 3% bead drop cavila- use of fixed-speed motors and fluid coull
tion performance guarantees, and the shape of their within the experience of plant already o
hydraulic characteristics. These are followed by testing
of thc complete pumpset, including the motor and Double-entry feed pumps (Fig 4.65) can lei;
gearbox/fluid coupling assembly. In each case, hydraulic the features of advanced class construction,
performance tests are undertaken using the method stiff shaft, 'cartridge' design, with vapour lo
of measurement laid down in BS5316 [21]. thermal shock capability. The provision of 111
Hydraulic output control tests are included on
electrically-driven pumpsets t o determine the thres-
hold response, repeatability and input/output char- pumpset reliability. The seals themselves are ii
acteristics of the fluid coupling arrangement. For t o have a minimum life o f I5 000 h betu'eu
starting/standby feed pumps, tests may also be re- haul. A 'cartridge' seal assembly reduces do\i,l
quired to demonstrate compliance with run-up time for any seal maintenance and minimises instal it^
guarantees. Thcsc would include the time from test type faults.
to full-speed and also acceleration from part-speed T o prevent any axial shuttling of the shaft, !\,I
conditions. could damage the mechanical seals, a delibefiilr
For new pump designs, supporting tests are required pcllei wear-ring diameter differential is intl-oil1
to demonstrate that the plant offered will satisfactorily to create a known unbalanced unidirectional I
accommodate any possible thermal shock, vapour lock which is taken by an external thrust bearing. 7'0
or axial thrust condition that can arise during op- for radial loadings acting on the pump, the
eration. In addition, a visual cavitation test is carried designs can either include radial diffusers or ale
out on the pressure stage first-stage impeller to de- the double volute type.
P","P
monstrate compliance with NPSH visual cavitation CA88"G
,M*SLLS" Ss,,hrl
LSWF

guarantees.
The thermodynamic method of determining pump
efficiency has now been successfully applied t o CEGB 14.10 Future trends TIC. 4.65 PWR feed pump
feed pumps. This method compares the isentropic
enthalpy rise across the pump with the measured
enthalpy rise, and has the advantage over the con-
ventional torquemeter method in that it is suitable with 100% standby capacity and substantial sp
for continuous on-line monitoring o f plant perform-
ance. Accurate measurements of the temperature and
pressure parameters at pump suction and discharge
are required, and suitable equipment is now installed necessitated very tight internal running clearallces till
o n new plant. In calculating the thermodynamic
efficiency, losses resulting from gland sealing, balance
water, bearing friction and heat transfer have all to inability t o withstand vapour lock or thermal trar will be continued, but with a limitation on
be taken into account. These secondary losses can conditions. ller speed t o minimise risks of impeller erosion
be derived at the initial commissioning test by com- A comparison of operating experience has den11 g off-duty operating conditions. A likely eco- 15 ~ i ~pumps~ ~ l
paring the conventional torquemeter acceptance test strated the effectiveness of providing rugged relia c solution is a three-stage machine with booster
results with those obtained from the thermodynamic feed pumps and highlighted the strong financial
method. centives of installing spare capacity to maximise f
pump availability. It is now evident that overs
ultilities are moving towards CEGB practice.
When determining standby requirements, the cu
14.9 PWR feed pumpsets rent trend is t o provide 3 x 50% pumpsets. TI1
The feed pump generated head requirement o n a arrangement meets the basic objectives listed in II
water reactor unit is in the region of 900 m. This is introduction to this section and achieves them tor with consequent reductions in station civil parate categories, pipeline-mounted pumps and sump
considerably lower than that necessary o n a fossil- larger fossil-fired plant without any excessive extr
fired station and allows the use of a single-stage polations of existing technology, by taking maxim11
double-entry pump. Changing t o the simpler double- advantage of UK manufacturer's international e
entry design, eliminates the need for any balance perience to produce reliable plant.
drum to rcdcl against large ~mpellzr lw.rdinp, This A 3 x 50% configuration with quick-start variab
Ic3ds to an tnlpro\.emcnr in pump hldraulic effalen. speed motor-driven units represents a low capital a
cy compared with the equivalent multi-stage pump through life cost option for a practical plant arrang

41 6
Condensers, pumps and cooling water Illant

FIG. 4.67 Verlicnl in-line pump cons~ii~ctio~i

tiracy over long periods and po-


F ~ G 4.66
. mod err^ recd jpunlp constiuctior~

I I sililable corrosion-resistant materials. 15.3 ~i~~


pumps
'"'
'peration of a meteri'lg
Fire pumps are of simple robust construction to
" i'lunger a certain ensure high reliability when called upon to operate
assists maintenance activities with no disturbance of In the past, sump pumps h ~ c l stroke.
"IgI1 a
l Liquid is drawn into the
and
in ,, emergency. =he pumpsets are usually self.
contained packages driven by diesel engines with the
ings eliminates the need for removal of the motor from columns, the impeller be in^ nO'l-return valve. The gear drawing start-up motors supplied from a local battery pack.
during work on the pump. level motor through a long nlull ; a mechanism for altering the stroke water for engine is taren from the pump
a "ariation in Pump delivery, there- discharge. Shaft leakage is controlled by traditional
All pumpsets in this range are close-coupled, with failure occurred, particularly th Control of the amount of chemical soft-packed glands rather than the more sophisticated
the pump impeller mounted directly onto an extended which is difficult and often very nosilive displacement action results in mechanical seals. This eliminates any risk of enforced
motor shaft (Fig 4.67). This arrangement requires a Increasing use is now being mil llsations of flow rather than a steady shutdown which could arise from failure of a me-
b? smoothed out, if necessary, by the chanical seal.
bearings to carry the pump hydraulic forces. Although dium power outputs. Ease of wit
there is an initial cost penalty compared with the ment are good and reliability
equivalent end suction designs, the vertical pumpsets the arduous conditions often 11
take up less floor space and experience indicates drainage work.
they are more reliable and require significantly less
maintenance. This is attributed to several factors,
including the elimination of coupling alignment pro-
blems which can result in a reduced seal life.
Larger pipeline pumps are of the horizontal split- These are used to pump a me
418
Condenset.~, pumps arid coalirig wale? p l u ~ i ~

,t!lii I'iesaii~e Yeircl Codc, Seczlo~i8, 13irisio8,r I and 2 of Specific Sp~ctl':'riiil)s ASMII: 1943
c 1:GB: 1'erf~)linasceor Sulfsce-lipc Steam Colideiiserr: Site 1201 <;rirc. E.: ,Nett liosiiive suction lhehd ieqiiiieo~e~?fs for a\,oid-
ierl Code No. 3: 1981 ~ ~ I CofC u ~ ? a c c e ~ l a bal ic- i i ~ t i o terosion
i it, ceni>i(ugaipurni,~':
lJS752: 'Test Code for Acceplaiicr. of S~eairi'siirbiilei': 1974 IMecllI Ci63: 1974
('liG8: 'Steam Torbi~?e-Geseiaioineat ~~i~ T C S ~ ? ' :site I211 US5316: 'Speciiicalioi~ for Accci,rance 'Tests for Ce~?lvirugal.
( o d e No. 2: 1978 Mixed Plow and Axial Pumj>s'
hlnericaa Sooery of Mecllar$ical ~ n e i n e e r s(ASME): 'stvaciurai 1221 855257: 'Specifieatios for End-suction Cenil.ifuga1 13umpr
I'l~nrucleiiriicsof Hclicnl-Corrueated Heat Excliangcx n b e s (16 bar)': 1975
I,? ASME': 1975
1231 BS4082: 'Spccificalian for External Vimciisionr for Vertical
ELECTRICAL TERMINALS StcPanoff, A. 1.: 'Cenoiiugai P u m p Perfoiniancc as Function In-line Ccnrrifugal Pumps'

COOLING JACKET

OIL RESERVOIR

FIG. 4.68 Sublnersible pumjl construction

16 References I71 Steel, T . F. (CEGB): 'The Thermal Design of Condcl


I11 CEGB:'Chemieal control of boiler feedwater, boiler water and From rlle users point of view': taken from a report of a I
saiurated steam for drum-type and once-throilgh boilers': Genera- ing at NEL on the Thermal Derisn of Condensers: Jan
lion operation mcmoranduni ( 0 0 M ) 7 2 Issue 4: 1975 1966
121 Poppl~welland Barer: 'Corrosion Performance of some Copper 181 International Symposiuni on Condenrers, Theory and Pruc
Alloy Condenser Tube Materials in Ammoniated Condensate': UMIST Maneliestei: March 1983.
National Association of Corrosion Enginecrr. Paper 102. Cor- 191 894360: ~ ~ ~ ~ i for
f i weldable
~ ~ ~ ~~~~~~~~~l
i ~ , , steels:
rosion: 1974
131 'Titanium Information Bulletin': Imperial Metal lndustrior
(Kynoch) Ltd.: 1974
.
1101 BS1501: Specification for steeis for fired and usifired pr
ves~cl6.Par1 1 Csrbon and Carbon Manganese SLeelr:
1 1 1 1 B S l s w (Withdrawn), now BSSSOO: Specification For liii
I41 Han~on, C . F.: 'Malerials in Power Plant': lnniituie o r Fusion Welded Pressure Vessels: 1976
Metalluigirla, 98-103: April 1975
[I21 BSl515 (withdrawn), now BS5SW: Specification for lii!
IS1 Standards for Sieem Surfsee Condensen': The Heal Exchanger Fusion Welded Prosnure Yesrein: 1976
lnsiitilie (HEI)
[61 ‘Publiestion on the ror rhc of 1131 TubuiaiExchangerManufaclurersAsrociaIion(TEMA)SI~~~
ardr: Fourth Edition 1959, Fifth Edition 1968
surface-type steam condenring plant': The British Electrical
and Allied Manufaciarerr Association (BEAMA) 4 American Society of Mechanical Engineers (ASME) llul

420
Types of ti~rbine

Ipiessuie ins!, bc alicctcd b r suilablc locaiioii o l the


turbine in rclaiiali to tlie lailwalei levci. This Iheighi
i i called ihc suction ihead (14,) anrl is govcrocd by lhc
rclatian I i , r 13 - OH.

where B = diffcrencc in head bctween barometer


and water saturation vapoor pressure, m
T E R 5
o = Thoma's cavitation parameter

Hydraulic turbines H, is positive when the tailwater level is below the


pump runner as shown in Fig 5.1 and negative when
above. An indication of bow o varies with 11, is given
in Fig 5.3.
1 Definitions and conceprn ~ From the information given in Figs 5.2 and 5.3 it
1.1 output 3.1 Ffesfiniog power station is evident that for a given n,, the type of turbine
1.2 Specific speed 3.2 The reversible puinp~rurbine employed can be influenced by tlie ability of the ap-
1.3 Cavitation 3.3 Dinorwig power station
1.4 Running speed 3.3.1 The site plication to accommodate the suction head require-
3.3.2 Runner submergence ments. These iiifluences may result from physical,
2 Types of turbine 3.3.3 Operational requirements
3.3.4 Design life performance or cost considerations.
2.1 he Pelton turbine
2.2 The Francis turbine 3.3.5 Machine iayout
2.3 The Kaplan turbine 3.3.6 Vaives
2.4 Tubular turbines 33.7 Testi~lg
2.4.1 The bulb turbine 3.3.8 Some delailr of lhc Dinoiwig pumped-storage ~ f i # i i o , t 1.4 Running speed
2.4.2 The tube turbine 4 References
'This should be as high as possible for economical
24.3 The rim generator design 5 Additional references turbinc design and the generator is the dominant
influence in its selection. In tlie event of disconnec-
'igure 5.2 shows how specific speed and head are tion of electrical load, the acceleration of the com-
plete turbine-generator rotor system is extremely rapid
. led for turbines o f good efficiency. Superimposed
n indication of the range of application of each
the types of turbine i n use. It will be noted that,
and stabilises at a maximum called the runaway speed.
Since water hammer effects would, in most cases,
Illlough there is a consistent trend in the application preclude shut-off of the water supply in sufficient
of these various types, there is considerable overlap. time to prevent the rotor reaching runaway, this speed
1 Definitions and concepts 1.2 Specific speed must therefore be acceptable to the generator which
Turbines vary widely in form and a~nlicatioii, A is the most vulnerable component.
..
one extreme is the pure irf~puise,noclzine (sucli it The ratio of runaway speed to normal speed varies
the Pelton turbine), where the flow is generally lo 1.3 Cavitation between different turbine types as follows:
1.1 Output
The wafer turbine is a device which transforms the
but the head is large.- Reaction turbines. in wllii: I'81uitation is a very complicated physical phenome-
i ~ i ~resulting
~ i from the water flow in the passages Reversibie pump turbines: 1.35 to 1.45
the prcssu1.e drop takes place in both fixed and I
potential energy of a head of water into mechanical taring parts of the machine, cover the remail~i I r l 3 turbine. It can occur whenever the local fluid Francis turbines: 1.7 to 2.0
work in accordance with the relationship: types. These range from rodial flow turbines (so pressure falls below a value corresponding t o the
a,nler vapour pressure at the prevailing temperature. Kaplan turbines: 2.0 to 2.2 (guide bladcs/runner
as the Francis turbine), for medium heads and floi
~ d e rthese conditions, boiling and steam bubble blades linked)
t o axial orpropeller fypes (such as the Kaplan turbirr
for low head, high flow application such as rivers. nrlnation may occur. When these vapour bubbles 2.4 to 3.0 (guide blades inde-
The turbine operating parameters of head, ilo ira\~ctravelled t o some other point in the fluid path pendent of runner
where P = turbine output, kW
e the pressure is higher, violent collapse of the blades)
and rotational speed thus cover a wide range of con
q, = water flow rate, kg/s binations. In order to characterise them for c ubbles can take place. In such circumstances, severe
H = head difference between upper and tail parison and selection purposes, the concept of spe n and loss of metal in pump components and Hence the normal running speed of the turbine can
water levels, m (see Fig 5.1) speed (n,) is used. This is defined as: s can occur, even though materials such as stain- be determined. The final turbine runaway speed is
lcsa steel are employed which are resistant t o cavita- usually determined from model tests.
h = hydraulic losses in pipes, m lioii attack. Cavitation is often responsible also for
- np0.5/~l.21
e = turbine efficiency 5 - isy operation and vibration within the set, and
iy be associated with a reduction of output and
2 Types of turbine
where n P = turbine rotational speed, r/min
Avoidance of erosion damage is the aim of the
design and may require restricting the range of
This quantity is o f great importance in turbil lurbine operation. It is also important t o ensure that 2.1 The Pelton turbine
The efficiency varies considerably between various selection as it is found that, by its use, many o f t lile water pressure is sufficiently above saturation. T h e Pelton turbine (Fig 5.4) is generally used in
turbine types and sizes but is in the range 0.9 to turbine's design and operating parameters can particularly so at the turbine outlet where applications where there is a relatively small rate-
0.94 for large machines. correlated. pressure is lowest. Adjustment of this of-flow at a large head, typically above 250 m.
422
Hydraulic turbines

PELTON TURBINES

SPEClFlC SPEED n,

It is an example of the pure impulse machine in shaped lobes; the central ridge which divides them
'hich the whole of the pressure head is converted splits the water jet and guides each of the two flows
1 velocity in one or more nozzles in parallel, the through an angle of about 165'. Ideally, for maxi-
1s from them impinging on buckets mounted on mum momentum transfer, the jet would be turned
Ie runner. Each bucket consists of a pair Of spoon- 180" but this is precluded by the need to direct the

425
liydraulic turbilies Types of turlline

HlGW PRESSURE +
WATER INLET

FIG. 1.4 I'elloe wlleel turbine RUNNBRBUDE

discharged water away from the runner and from disposed around the full circumference. The ant
the path of the following bucket. For similar reasons, these vanes can be varied to control machine i,
the central ridge is scalloped at the tip to give a clear and the water is uniformly distributed to theni I
path to the jet impinging on the working bucket. spiral casing.
Theoretically the maximum efficiency of this type After being directed onto the runner, the
Of turbine occurs when the bucket peripheral speed flows radially inwards, being turned by the I
is one half that of the impinging jet. This is im- blades so that it discharges axially into the i
D R A R CONE
AND D R A R TUBE

required. In practice, the ratio of blade-to-jet speed lies maximum efficiency of Francis turbines is 9 4 9
between 0.46 and 0.47. Both horizontal and vertical shaft mounting c;in
I:~c,$ 5 i7raseisiurbine for leu. head applications
The efficiency o f the Pelton turbine can be o f the employed.
order o f 92%. Control of end thrust is important. This
Water is directed onto the buckets by means of largely from the different pressures between th
nozzles, the flow of water, and hence the output, being and rear shrouds and their respective casings.
controlled by a central needle, or spear, whose bulbed rear shroud, the source of pressurisation is so
head varies the flow area as it moves axially within high pressure at guide vane exit, whereas th

and this water is ducted away by the drain system.

quired after loss o f load from the driven machine, As well as this varying pressure distributioo,
cannot be effected by rapid closure of the spear front face o f the impeller also experiences draft 11
due to the water hammer effects referred to earlier. pressure over the whole eye (i.e., the area o f
Shutdown is therefore effected by inserting into the impeller facing the draft tube).
jet either a cut-off to destroy its kinetic energy o r a Since the areas involved are often large, the t11re
deflector to direct the jet away from the bucket. The resulting from even small pressure differences ca
jet of water is then shut off at suitably safe rate. considerable. It is usually reduced by control o
pressures on the top and bottom shrouds, thro

bearings are therefore provided on the spindles pro-


2.2 The Francis turbine inboard of this latter seal is maintained at d
In this type of machine (Fig 5,5), the water is fed tube pressure by the use of balance pipes connect , must accommodate shaft axial movement. These Movement of the guide vanes is effected by a
radially to the runner from guide vanes which are these two regions and/or holes drilled in the ro re either conventional packed glands or ~ r o p r i e - crank attached to the end of one of the spindles,
427
liydraulic turbines Types of turbine

tire oilier end o f t l ~ ccrank bciiig located in a icgu- 2.4 Tubular rurbines
laling ring. Rotation of lhc rcpiiialing ring movcs The Kaliiaii turbinc has been uzideiy wscii iii I
t l ~ ccranks, and ileiice ilic guide vanes, in syochronism and tidal power sciiernes, iuhere a coinpaiaitivlr
GUIDE VANE
OPERATING
throi~gb the required angle. This rotation is lpio- lhcad o r wafer is available. Howcver, tlicic : i i i MECHANISM

duced by one or, rno1.c usilaily, 1\1,0 hydrai~iicrams advaniagcs:


or servomotors acting at eacll end o f a diamctei of
the regulating ring. Some form of slipping device is r The submersion of the runner to avoid c
normally incorporated in the crank/goide vane con- rcqiiires excavation fol. the draft trubc, i
nection so that if a foreign body (such as a log) sequent increased civil costs.
g a s jammed between two vanes, the remainder can
be closed normally. A warning device is often fitted Several changes of direction occur in thi. i
to indicate that the slipping device has operated. and draft tube system which raises hydrauiic i

This led to the development of the t u b u h 1111


in which the Kaplan type of runner is osril,
2.3 The Kaplan turbine
fixed or variable blades, and installed will1 i r h
The essential featore of the Kaplan turbine (Fig 5.6)
more or less horizontal. T h e water path IIIIO,
is that the water fiow through the runner is in an
viates froin the axial direction as iittie as po*%lb
axial direction. The inlet spiral casing and the guide The efficiency of the tubular turbine is siiii
vanes are similar in layout and operation to thc that of the Kaplan machine.
Francis turbine. After leaving the guide iiancs, how- The principal subdivisioxls of the tubular ~ i l i t
ever, the water turns into the axial direction before
meeting the runner.
The runner resembles a ship's propeller whosc
blades (typically four to six in number) are adjustable
in pitch to present the optimum angle of attack to
.
are as follows:

The bulb wrbine.

Tlle tube turbine.


the water flow. It is this ability to optimise the
runner performance that enables the Kapian turbine The rim generator.
t o maintain its efficiency over a much greater range
of speeds and power outputs than the Francis type.
A peak efficiency of about 94% is achieved in iargc 2.4.1 The bulb turbine
machines. This derives its name from the 'bulb' in 111
The biades are most conveniently adjusted by means path which contains the electrical generator (I
of a lever arm within the hub. Axial movement of Normally the bulb is placed upstream of thc I
a cross-head connecting with each of the lever arms and is supnorted in the water path by struls \ TURBINE W A F 1

rotates the blades. The servomotor system which op- since they arc hallow and large enough to gal
erates the cross-head can be within the hub o r outside to the generator for maintenance, must be <
the machine, connecting with the cross-head by hy- designed if unnecessary hydraulic losses a,
draulic means (Fig 5.6) or through a control rod disturbances are t o be avoided.
within the holiow shaft. The optimum relationship Guide vanes, sometimes called wicket galcr,
between runner blades and guide vane angle is con- located in the annulus between bulb and carin&
trolled by a cam system in the operating mechanism. control the fiow of water t o the runner.
lnstallation is usually as a vertical shaft machine. Several combinations of guide vane/runne~ b
This configuration has the following advantages: control are possible:
Bearing and lubrication system layout is simple.
Variable guide vanes and runner blades
Electrical generator installation. access a n d
maintenance is made easier. This combination provides the best efficiency
the load range. It also allows a useful variaal
s Turbine support and secure embedding of parts, tidal power schemes. Thus, as well as operatin]!
such as the inlet volute, in a heavy concrete mass turbine in either the ebb o r flow direction, tllc~
are facilitated. the capability for pumping in either direclion
Equipment can be mounted o n the top cover and improve the head availabie for the next geneml
is easily accessible for maintenance. cycle. u
Submersion o f the runner below the tailwater level
t o obviate cavitation is achieved with minimum Variable guide vanes, fixed runner blades WC. 5.6 Kanlan turbine with delail of the hub mechasisn, far varying llle blade angle shown on tbe insel
civil costs, compared with submersion of the com- Load is satisfactorily controlled over the camp
piete set. operating range by varying the guide vane 1111
428
Hydraulic turbines

creatc shall whirling and bearing arrangement


ditions and vibration.
s Using fixed ronnei blades, tile cost of these units is
extremely with other types. 'The narrow
2.4.3 The rim generator design

--- methods, does however, detract from the financial

his design is marketed by Escher Wyss under thc


e 'Straflo'. The efficiency of these units is com- Pumped-storage
ble with other tubular turbines. pumped-storage offers a means of storing electricity
he concept has the following features: in the form of the potential energy of water held at
high level. The main advantages and reasons for its
e Generator accessibility is very good and the large installation can be stated as f0llowS:
diameter ensures high inertia, and hence stability.
Its design is, however, dictated by turbine
than electrical considerations and balancing must
be rigidly controlled o n these large diameters.
. For electrical generation in the 'peak lopping' role.
~~i~~ comparatively simple, it can provide a rapid
start for peak lopping or emergency reserve, with a
higher reliability than thermal plant such as gas
6 Seals a1.e required between the rotating shroud ring
turbines or diesel engines,
of the turbine and the static casing of the water
passage to prevent ingress o f water to the electrical On a system containing thermal generating plant
generator. These seals have been the subject of it reduces the requirement for Sets on 'hot standby'
intense development t o enable them to perform or 'spinning reserve'.

I:!<;. 5.7 U ~ i l bturbine

The low inertia of the rotating parts (small diamel


Fixed guide vane, variable runner blades

gates, must therefore be provided.

optimised. Access t o the generator and gearbox


2.4.2 The tube t u r b i n e considerably improved over the bulb design. Vari
There are two major disadvantages o f the bulb turbine: arrangements have bee11 constructed: one such FIG.5.8 Tube turbine
431
Hydraulic turbines
Pumped-storage
~:

ivil to thc till-bines froin !lie lop lakc, discharging I'uolp casings iirc in casl steel welded lo a lplale sicel
lii ilie iower. l'hc scts can be r u n in this mode "Oillt~.
i t demand is met or otiici plant can be starled. Whilst pumping, the drive imust take lpiacc from the
oil-peak lxriods the water is pumped up from motoi- through the turbine, wilicli is filled with air to
lower inlo $he upgei lake ready to meet the next rcducc pumping Iosscs. The pump is disengaged whilst
the turbine is in opcsatiori in tile generating mode
i e requirements of the set for both a tol-binc and a coupling is provided for this purpose. Syatem
pumping role can be met in lwo ways; either by iequirernents did not justify the expense of a coupiing
1',separate pumps and turbines or by a singie capable of cngagement/disengage~ncnt at full spccd
~l~ii)-turbinewhich combines both duties in one and so tliesc operations are conducted whilst the ma-
lo!, and which reverses direction between roles. chine is stationary. A toothed gear, sliding-muff type
o f coupling is used, engagement being actuated by oil
pressure and a positive mechanical lock inserted during
periods o f rotation.
F f e s t i n i o g p o w e r station
tation, part of the CEGB system in England
'ales, is an example of the separate pump and
,i!,c system and was completed in the 1960s. The 3.2 T h e reversible p u m p - t u r b i n e
~ i i j iand turbine are mounted in tandem o n coaxial Such a machine enables both pumping and turbining
iil\s, at one end o f which is a unidirectional motor- to be performed by the same runner or runners. It is
effectiveiy a Francis turbine whose runner geometry is
'1'1,~ upper reservoir operates between extreme levels a compromise between the optimum for pumping and
,1113 and 502 m abovc sea level and encloses a generation. During generation, the turbine output is
11iige volume of 1.7 million cubic metres giving a absorbed by tile generator; whilst ptlmping, the geo-
Ili'iation time of sonlc 4.5 hours. The lower reser- eralor acts as a motor, driving the runner in the
lcvel correspondingly fluctuates between 182 and opposite direction.
A desirablc featurc of this design is that it is
e cross-sectional arrangement of the sets and considerably cheaper than a type employing a se-
relationship to the lower lake arc shown in Fig parate pump and turbine and the necessity for a
). Pour pump-turbines, each of 90 MW maximum clutch between the two is also eliminated. Also. since
Inciatins capacity, are arranged in an overground the same runner is employed in both the turbining and
reduce civil costs and t o facilitate flood pumping directions, the need for separate suction and
disposal in the remote event of a burst. discharge piping for the two components with the
h pump-turbine is arranged in a vertical con- associated mechanical and civil costs is similarly un-
on with the pump mounted below the turbine necessary. Thc efficiency of such a unit as a pump or
liar it may have maximum submergence for mini- turbine is usually some 1 % lower than a corresponding
ion of cavitation. The piping system, connecting optimally designed machine of similar size. Typical
r lake, bifurcates, as shown in Fig 5.10. maximum vaiues for very iargc machines might be
upper branch connects l o the turbine inlet via 92-93% when pumping, and 93-94% when turbining.
I~yilraulically-operatedinlet valve and the lower to Subsequent to the construction of Ffestiniog power
, pump outlet through a similar valve. station, considerabie worldwide experience had been
I:nclt single-stage Francis turbine runs a t 428 r/min obtained with single-stage reversible pump-turbines.
111 a maximum efficiency of over 93%. The high- Therefore, for their pumped-storage station at Dinor-
ilc steel spiral casings are constructed in halves wig, the CEGB decided to install such machines. The
111 site-bolted flanged joints. The variable guide first sets were commissioned in 1982 and, since it
st stainless steel are operated through a represents one of the world's major pumped-storage
and link system which is auto~naticallygrease- schemes in terms of both unit capacity and operat-
icated. The runner is in 13% chromium steel and ing head, it is used as an example of modern practice
in this field.
a maximum diameter of 1.93 m.
Ihe vertical two-stage pump is of double-entry
FIG. 5.9 Rim generator ('Srraflo') t~lrbine
. Thus the second-stage impellers are disposed
o-back as a sinale rotor and the first staees
be mounted outboard of it (see Fig 5.11). Suc-
-~~ 3.3 Dinorwig p o w e r station
It provides a convenient form of system frequen- pumping at periods of low system deman on from the lower lake is therefore via a breeches
cy regulation especially during periods of rapidly coroliary of this is that margins o n system capa 3.3.1 The site
ipe which conveys water to the suction of each of
changing demand. can be reduced. lr first-stage impellers. Each o f the two 2.5 m This station is Located near Lianberis in Wales, in the
meter first-stage impellers and the 2.6 m diameter Snowdonia National Park; an area renowned for its
It facilitates load curve smoothing by using con- Operation of the system requires two lakes or we nble-entry second stage are manufactured in 13% natural beauty. This fact dictated some of the design
ventional or nuclear plant to provide power for storage reservoirs. During generation, water is romium steel and are keyed to the pump shaft. features of the station.
432
liydraulic turbines

lo i-cfili the upl,el reservoir by i)uml,iog froiii the lowel 111 order to nlcel sucli sirol-t loading times,
in a six-lioui- period. ccssary for the machine la be kept for ion
A schcnlatic plan and elevation of lllc site is shown at synclironous spced. In the generation
in Fig 5.12 whilst a section tirroug:1 the underground this could be effected by allowing a sinali thrr,\ii! 11
station itself is shown in Fig 5.13. of water to generate sufficient power to o v v i r i i
macllinc losses. This is unattractive since:

3.3.2 Runner s u b m e r g e n c e e It wastes water and its corresponding piiinl'


As referred to in Section 1.4 of this chapter, the power.
economics of turbine design improve with increase
At low flows, the water strikes the runner biai
o f speed. Since the runaway/normal speed ratio is
smallest for pump-turbines, the running speed be- off-design angles, promoting erosion and wcil,,
comes higher for a pump-turbine than for any other There is the fear that, in a closed systcn>,
type operating at similar output and head. power losses could raise reservoir temperaliili
In the pumping mode, the increased speed coupled the long term.
with the high head, requires considerable submergence
o f the impeller below tail water level to avoid cavi-
tation. Similarly, submersion was also required in Similarly, in the pumping mode, the churnint:
the turbining mode to obviate column separation - a erated by running against closed guide vanes cil
condition in which inertia effects can cause cavities a loss o f power of about 70 MW.
within the water flow with severe water hammer on The problem has been overcome, in both rixi
recombination. For these reasons, a runner submei- by filling the runner space with air at tailwatci 8
gence of some 60 m was required. This was obtained sure: the windage losses are then reduced to
by placing the machines in a machine hail below 2 MW. With the main inlet valve (MIV) on I l l ?
ground and within thc mountain itself; As well as pressure side of the pump-turbine and the guide \,,I
being environmentally desirable, it was found that the closed, air from air bottles is blown into thc rill
small increase in civil costs was Inore than compen- space through a connectioll in the t o p covc, I
sated for by the lower machine costs througli using automatically maintained by a level control valvt
reversible pump-turbines. the draft tube. The machine can then be held all
ning at synchronous sueed indefinitely in eithei
pumpiilg or turbining direction (known as s p i n / p ~ ~
3.3.3 Operational requirements and spin/generation modes respeclively). Whilst
In order to meet CEGB system needs the pump- runner is spinning in air, a small supply of cool
turbine has a load regime which involves: water is supplied to the seals at the top and boll
shrouds, the centrifuged water being led away to d
Generating in the range of zero to a full-load of 317 from a connection at the runner periphery. Rev,
MW with up to five hours of continuous, constant to pump or turbine operation is initiated by
output generation. opening the MIV and guide vanes, and the air
is quickly dispersed by the water flow.
Pumping, using one or more units at full-load
Emergency reserve. This provides 1320 MW to the
system in the event that two of the largest units of 3.3.4 Design life
660 MW each are simultaneously lost to the grid. Each machine is designed to undergo a n u m b e ~$
Frequency regulation, which involves operation mode changes per year, viz:
over the range o f zero to full-load to correct for Routine pumping starts and stops, up to three
system frequency deviations as they occur. per day.

Associated with the above is a requirement to meet Routine generation starts and stops, up to four
these system needs within certain time scales. Whilst per day.
it was never envisaged that there would be any de- Change from spin-generation to generation and
mand for rapid adoption of the pumping role it is versa, up to 13 times per day.
essential that the machine is capable of changing
modes within very short time scales as follows: Emergency loading and change from pumping I
generation.
Standstill to no-load generation 90 s
Pump and turbine trips.
No-load synchronised to 1320 MW output 10 s
Emergency pumping to spinning-in-air (both In total, this represents 7500 loading/unloading c)
in the pumping direction) 10 s per annum. A fundamental consideration is the
Pumped-storage

during each of tliese cycles tbc MIV shuts, Illus sllaft and thc upper sllioud seal u,llici> ariinil blo\i-
~.isingthe penstock and turbine casing to [he down air into the s)atern, togettier wit11 the peripheral
oressure of some 6 bar, then re-onens to drain pipes which arc opened under these conditions to
uriseihem again to 50 bar. Over its 40-yea; design discharge the cooling water supplied to the ogpct and
:, (lie machine is thus subjected to 300 000 cycies lower seals.
Figurc 5.15 shows the guide vane apparatus, in-
' ' e requiremelit to design for a fatigue life is un- dicating the substantial bearings employed and also
in water turbines. In this instance, consequently, the manner in which the reguiating ring rotates the
.
s thought necessary to use a fracture mechanics
plr~oachto the design, adopting the ASME standards
vane through the lever and locking assembly, which
incorporates a friction clutch. Seals are fitted on the
licable to nuclear pressure vesseis. Essentially this end faces of the guide vane blade to miriimise water
lnes that defects present in the steel, which are leakage and both these and the guide vane bearings
ller than those detected by non-destructive test are equipped with an automatic greasing systein.
lhods and cansequently repaired during manufac- In the turbining direction, the guide vanes are
will grow under the varying stress field. Over infinitely variable between fully closed and about 32"
llant life, these initial defects must not grow to o f opening rotation to achieve the required output.
approaching the critical defect size, where the In the pumping direction, however, the guide vanes
can grow in an uncontrolled manner. Due to are opened to a notninally fixed postion, although
herent uncertainties of crack detection during pump performance can be optimised for varying speed
lofacture, the design allows for inspection o f cri- and head by minor variations in the angle between
I areas during the life o r the piant. As shown in 20' and 30" o w n .
14, one such area is the spiral casing, which

--",
c
.-0 11 t been invested in concrete over critical welds
i as occur between the spiral casing and the 3.3.6 Valves
"L
'ilg. In turn, this has necessitated placing a rub- The valves piaced either side of the pump-turbine
0
n iiiembrane between spiral casing and concrete to are similar to those used in many types of turbine.
.-an3 b panting and flexure of the spiral casing dur- Those. used at Dinorwig will be described in detail
i
i: pressure cycle whilst still providing adequate as an example of modern practice.
6 nt of the spiral by the concrete. Provision is
made in the design for grout injection should
B0 ,ap develop with time.
The main inlet value (MIV)
5 the pump casing and inlet spiral are com- Each MIV is a 2.5 m bore rotary valve, interposed
c
.- structures, the stresses in them were deter- between the main and intermediate penstocks, which
" 0th by finite element methods and photoelastic isoiates the turbine from high pressure water at each
5:
-
w
rn
iilysis of a plastic model. shutdown (see Fig 5.16). Tile vaive rotor rotates
within the valve body on two trunnions to which are
P
UI
attached the operating lever arms and closing weights.
6 Machine lavout The valve is held open by the upward thrust on the
nine-bladed runnpr in cast stainless steel has a lever arms from two servomotors (or rams) filled with
Ilum diameter of 3.8 m and an eye diameter of oil under pressure. The system is thus 'fail-safe' since
ti see Fig 5.14). The vertical drive shaft is mounted the valve closes under the action of the weight alone.
ingle guide bearing of tilting-pad design. Lu- The rate of closing is controlled by restrictors in the
n of the bearing is by a self-contained system with oil discharge line.
>il reservoir and integral water-cooled oil coolers The MIV is closed each time the machine shuts
osed within the bearing housing. Oil circulation down and, in this condition, leakage between the
ugh the coolers is maintained by the head gen- near-spherical valve rotor and body is prevented by
I by shaft rotation. The thrust from the p u m p a service seal. This is in the form of a stepped ring
le runner and motor-generator to which it is which slides axially in its stainless steel housing to
t y coupled is taken by a tilting pad thrust bearing seat against a ring attached to the rotor on its inter-
~nted in the motor casing. It must be sized to mediate penstock face. The seal is operated, as well
the widely vdrying thrusts achieved during pump as being held on and off, by penstock water pressure
turbine operation and, in particular, those tran- acting on the appropriate face of the stepped ring.
t i which occur during mode changes. Leakage of The seals between stepped ring and valve body are
I jlressure water from the upper shroud of the D-shaped to prevent rotation within their grooves:
ley along the clearance between the shaft and they were the subject of considerable testing t o ensure
pump inner top-cover is minimised by a balanced that they met the six-year life required of them.
of the type referred t o in Sectiun 2.2 of this A similar seal is provided on the penstock face of
the valve rotor but it is only operated to provide
lhnwn also in Fig 5.14 are the pipes between the additional safety during maintenance. Under these
Hydraulic turbines Additional references

T/IPdrNJ) I u D ~r,oiee 3.3.7 Testing 10 enable ipeiformance deferioiatioll to be monitored Stotio,, "Ut,,,,I
The d r a h lube vaive (1)TV) (see Fig 5.18), is piaccd I'oli-size testing of tiic installed p o m p t i i ~ l i ' tiring service, eacli machine is equipped with tap- Average generated station output 1680 MW
011 the tailwater side of the p ~ r n p - t ~ ~ ~ aiid
b i ~is l ~ verify efficiency guaiantees, sequircs rneasurell ' points in the intermediate and lower penstocks Generating period at coilstant output 5 11
d isoiate the machine froill tile lower re-
~ ~ i o v i d c to power, net head and watei flow as devailed i ~ i ling thermodynamic testing o f the machine ef-
Average individual pump power input 283 MW
sei-voir during maintenance, and to close in the event 1.1 of this chapter. Difficulties and costs y to be undertaken.
of a major burst to prevent station flooding. It is ing for tile accurate measurement of the lar?, 11s method does not require any flow measure- Pumping period 6.3 lr
normally left open and does not form part of any involved make such an undertaking unattraciiuv l i i i I r m It measilres tllc internal efficiency of the ma-
automatic operating sequence. both practicai and contractual considerations. Ihii~e by comparing the actuai enthalpy change of
(six ofn
Pu,~~p-T~o.Dincs
Each DTV is a 3.75 m diameter buttesfiy valve, For this reason the comprehensive tests c a r ~ i i , ~ i Ir water due to the work done in passing through
the rotor being of the lattice type. Integral eccentric by the manufacturer on the one-eighth scaie ~ I I machine, with that which wouid be experienced Type Reversible Francis
tronnions ensure that should it be inadvertently left logous model of the pump-turbine and cor lile water experienced an isentropic change from
shut during turbining, it will flip open under the tur- full-sized machine values by established means 1 1 1 I to final pressure 01. head. The ratio of these Turbining (Generating)
bine flow. Opening and closing is performed by a accepted by the CEGB as evidence of the , , iles gives the machine The main probiem
servomotor and lever and weight system, in a similar liie method is that of accurate measurement of Maximum output/net head U p t o 317 MWl535.8 m
ability to meet efficiency guarantees. Howeve
manner to the MIV. firmation of this and to cstablisb a referel small temperature difference (typically 1 t o 2'C) Minimum output/net head U p t o 280 MW/487.9 m
111 which cnthaipy changes depend but for this, Maximum flow 70 m3/5
I olher details of the method, see [21. Synchronous speed 500 r/min
Maximum transient
BWDE
runaway speed

/ S o m e d e t a i l s of t h e D i n o r w i g p u m p e d -
SIIDINGAOINT
800"
I
Pumping
Rated discharge/head 50 m3/523 m
6.7 million m3 Maximum power input 318 MW
634 m Synchronous speed 500 r/min
600 m Min/max frequency 49/51 Hz

4 References
iII 'lnfeiiiational Code for Model Acceptance Tcrrr of Hydraulic
Turbines': iEC Ptkblicalion No. 193
12) Thom. A . S.: 'Tl?eriiiodyi?aaucTesting or'l'urbiner and l'ul,ipi'
IMecllE \'"I. 7 No. 3: 1965

5 Additional references
Gutl~rie.Biown, J. (Ed): 'Hydro-Eieetrie Engin~eiiiig Practice':
Biackie & Son
Headland. H.: 'Blaenao Fferriniogand other Medium-Head Pumped
Storage Scllemei in Oreat Biilain': lMechE Proc. Volume 175
No. 6: 1961
'The Dinorwig Power Station': Papers presented at a major achieve-
ment symposium: iMechE: 1985
nerator
Introduction
,

130th the pace o f development and the rate of Other parameters, such as hvdraulic vressure and
,]case in unit output has slowed markedly in re- dielectric loss test values, are specified in various
il years, as greater emphasis iias been placed on CEGB Standards.
reliability achieved by proven designs, and on Specific requirements for a new generator are con-
. advantages of interchangeability of major plant tained within its own specification, which covers items
peculiar to its location or duty, for example, tem-
perature of cooling water, power factor and reactances.
Where necessary, these requirements may differ from
those in the appropriate Standard. The expected op-
Standards and specifications erational life is quoted in the specification; this is
British Standard covering generators is BSS000, currently 200 000 hours, with 104 start/stop cycles.
i refers to many parts o f BS4999. The corre-
These values are used in design calculations, e.g., crack
roading international standard is IEC 34. Standards
growth rate by fatigue.
)ccific for turbine-generators are BSSOOO Part 2 and The following Standards are relevant:
!(' 34 Part 3. These standards specify acceptable
aracteristics, values o f temperature, vibration, noise,
unbalance, harmonic content, excitation control i E C 34- I : Rolaling electrical maellines - rating and perforisance.
and tolerances, and test conditions, e.g., high I E C 34-2: Rotating eleciri~almachines - methods for determining
IOSI~S and efficiency from tests.
Syiicliro~iousgeneratoi i1iiii:i:
..

frequencies are used for special purposes; those whosc

-
- i~ S E ~ ~ V I C C

SUPLRCONUUCTlNG
the rotor rotates inside the stator bore, a con-
c i o r fixed in the stator will be subjected to an
lproximately sinusoidally varying magnetic flux den-
output is rectified for use as an excitation supply
conlinoiliy operate at 150 Hz or 400 Hz.

y, and ujill have an approximately sinusoidal \'oltage


lerated along its length (Fig 6.4). The magnitude
the flux density, which determines the magnitude 2,3 Load, rating and power factor
the geneiatcd voltage, can be changed by varying Root-mean-square (RMS) values of altcrnatillg volt-

voltage/current relationship dictated by the nature of


that load. For any load which is not purely resistive,
OlRLCT G4S OR LiOUiO CWLjNC.
OF STATOR AND O,RECTRO~ORCOOL~NG the sinusoidal voltage and current will not be in
05-
LiOUiO C0011NCi OF SFNOR AND ROiOR

the product of its rated voltage and its rated current,


expressed in volt-amps, kVA or M V A . The rated
f = pri power is the rated output times the rated power factor,
MY# RAI~NO expressed in watts, kW or MW.
\viiere f = frequency, Hz The rated power of a three-phase geuerator is three
n = rotational speed, r/s times rated phase voltage times rated phase current
I'iG. 6.3 D e v e l o ~ a i e ~of
u genierator sire, weight asid ariasgemcnts times power factor. Virtually all CEGB generators
12 = number of pole-pairs
have their three phases connected in star, so that:

drical rotor 50 Hz generators have two poles line voltage = J 3 x phase voltage
34- 3: Ratings and characierirlies of )-phase 50 wr turbine 2 Synchronous generator theory peratc at 3000 r/min, or less commonly four and line current = phase current.
type macPiner.
Some basic principles of theory and desigll
IEC 34-4: Metliodr ioi derermi,,ing sy,lcl,ronoui ,nac,,ine qua,,. tablislled in this section in order that the de
tities from tesci. matter in later sections ma). be more easily land

IEC 3 4 - 6 : Melliok or cooling ,otnti,,g muel,ineiy.

Bs4999: General reguiicziienls for rotating eiccirica~mac~iii>es. 2.1 ~ l ~ ~induction


t ~ ~ ~ ~ ~ ~ ~ t i ~
BS4999 I'Rrl 106: C1B~~ificatioil
of methods of cooling.

BS4999 I'ari 101: Specification for rating and p e r r ~ ~ r n ~ ~ ~ ~ ~ .

BS4999 Pair 142: Meclianiesl percom,ance - vibration.


BS4999 Part 109: Noise levels.

B S S W Specification for rotating electrical inachine~of panicu~al.


Iypei or for particular a ~ p t i c a t i o ~ s .

BSSOOO Part 2: Turbiae type n ~ a c h i ~ e s .

892787: Clarsificatiolr o i insulating macerials for electdeal

BS55OO: Specification for llnfired f u i o n welded prcrsure vessels.


= length of conductor exposed to the fI(ix,
BSW: Steel sheets for magnetic circuits o i power electrical appaiatur.
k = constant
851433: Copper for eleetrieal purposes: rod and ber.

BS3906: Electiolytic coq~presredhydrosell. In order to operate synchronously with the in[


connected A C transmission system, the geno.u{
Terdns the ilrsuiation system 01 baa.
ESI Standard 4-1: voltage is requited to vary sinusoidally. The rnaailc[
T h e generator

'Thc MVA sating is tilcrr: whicir proijidc a source of magneto-i,l<,iiti. I


J3 x rated line voilage x sated iiiie current x iO.." (MMF); the 'driving foscc' beiiind the niei:iii.iii
The vaiue of MMF depends on the rni~xiiiiii~ii INSTANTANEOUS
VOLTAGE
density required at the stator conductors to iuii
The MW rating is then: rated MWA x w e d power
factor.
the required voltage and on the rciucta~ici. ill v . "sin (PWO ,
magnetic ciicuit. The magnetic circuit coi\~i!.t+
paths of low reiucldnce in the iron of thc r i > i t u
The present CEGB rating for iarge turbine-generators is:
660 MW, 0.85 power factor lagging, 23 500 V, 3- but that of the iron paths increases a t lhiyli
phase, 50 Hz of magnetic flux density, when the iron b
magnetically saturated.
The MVA rating is therefore 660/0.85 = 776 MVA
and the rated line current is:

2.5 R o t a t i n g p h a s o r s
A sinusoidaily-varying voltage has an instantiif
value v at time t expressed by:
The output is specified as a maximum conlhuous
rating (MCR), which implies no guaranteed sustained v = V sin (2af)t
overioad capacity. Tile standards specify very short
term overcurrent capability, and acceptable variations where V = maximum vaiuc of v
in voltage and frequency. Samc sustained overload
f = frequency in Hz 17i~i. 6.6 ~oiatingphasois
capability may be possible by operating at a hydrogen
pressure greater than the rated value, by agreement.
Although operation at 0.85 power factor (lagging) T h e same relationship can be derived by rotatiti
is specified, generators on the CEGB network gen- phasor of constant magnitude V at a constant sl
erally operate at power factors of 0.9 or higher, and (Fig 6.6). At time t, when the phasor is at an
this allows operation at higher than rated M W if 0 t o the horizontal axis, v = V sin 8, i.e., ti1
this is available from the turbine, u p to the limit of jection of V o n t o the vertical axis.
rated MVA (see Fig 6.5).
In a synchronous machine, all tile sinusoiilal
varying quantities (voltage, current, etc.) can hr
presented by phasors rotating together a t synchroiiintt:
speed. The rotating phasoi diagram can be tho~ii:I~l
2.4 M M F , flux and magnetic c i r c u i t of as a snapshot of a set of phasors which ail i<ititls
Direct current circulating in coils wound into the together while maintaining the reiationships to r;irll
rotor poles, causes them to act as electromagnets, other.
In a three-phase machine, with balanced ciectricul
output, conditions in one phase are repeated exnclly
OPBR~TIONABOYtRATED MW in the other two, with time delays of 1/(3fJ an
PERMlSSiBLE IN THESE AREAS
(30. For clarity, one phase is chosen, a n d its ph

2.6 Phasor diagrams

2.6.1 R a t e d voltage. n o s t a t o r c u r r e n t , open.


circuit c o n d i t i o n s
Let a phase voltage be represented by the phasol
V (Fig 6.7). Since it is the rate of change of fiua FIG. 6.7 Pharors for open-circuit eondilions
density which produces V, the phasor for flux den,
sity, B, is drawn 90' out-of-phase with V. The
MMF, F , producing this flux density is in phase
FIG. 6.5 Operation at liigh M W and power factor with B.
452
Synchronous generator theory

2.6.2 Rated voltage, rated stator current a n d reactance. r l i c ierni syrichronolic reoclnnce (X'I ; Xi-)
rated power f a c t o r is used io express this cffect, the IXd drop lbi.irfp
If llic poivcr i a c t o ~is expressed as cos $, y', is thc added lo the IX, drop in the diagrams.
angle betwecii the voltage and current phasors, as As the lagging power factor of the load i8~,i,.rlir:
shown in Fig 6.8 Sol a lagging power factor. i.e., cos y', is smaller and 4 larger, the required I\Ihll ,
Current circulating in the stator winding rcsults in F, increases, i.e., more current is required i!, l l i i
vollage drops: IR due to the winding resistance R, in rotor winding (Fig 6.9 (a)). Conversely, if the lit(q!Jiifi
phase with I, and IX, due to the winding 'leakage power factor increases or goes beyond unity i l l l r i llir
reactance', X,, lagging i by 90". R is negligibly sinall, leading regime, the rotor current must be re<llir~il
and the resistive voltage drop is neglected henceforth. (Fig 6.9 (b)).
An 'internal' voltage E must be generated in the
winding such that after subtracting (phasorialiy) the
Ieakage-reactance drop, the rated voltage V is pro-
duced at the terminals.
2.7 Torque
In order to generate E, fiux density Be and MMF
Fe arc required, such that the voltage, flux and MMF The mechanical torque provided by the prime nrnrat
phasor triangles are ail similar. Tile pbysicai meaning is balanced by a n electl.omagnetic torque causcil lij
o f this is discussed later. the interaction o f the magnetic fiux and the ckillrni
Current in the three-phase stator winding produces fiowing in the stator windings.
its own MMF, Fd, which acts in tile same direction The rotor shaft must be designed to transmit li11t.d
as F,,. An MMF, F, must be provided, such that, torque, and the stator must be abic to withsl;il,ti t i
when the Fd component is subtracted vectorially, similar torque reaction. In practice, the design i i i 1 1 6 1
the resultant is Pe. This is achieved by increasing the cope with the very much higher torques proiiiscuil
rotor winding current and by the rotor moving ahead during certain fault conditions.
o f its open-circuit aiignment, by the 'load angle', S,
as silown.
This demagnetising effect of the stator winding
current is known as artnolure reaction, and can be 2.8 Three-phase windings
seen from the diagram to be similar in effect (though The voltages and currents produced in each ~ p i i FIG. 6.9 Pliasor diagiaiiis for lagging and leading loads
much larger in magnitude) to that o f the leakage must be identical, apart from their phase displ

inents, in order to axaoid the damaging effects of profile which cannot be shaped to produce a sin-
tinbalance. usoidai fiux density variation (as can, approximately,
In this and the next section, a complete two-pole a salient pole on a multi-polar slow speed generator).
$:enerator is considered, for simplicity. In a machine The flux density variation in a turbine-generator is
\ ~ i t l l2n poles, a two-pole segment is exactly repeated of a stepped rectangular form (Fig 6.11), which con-
11 times, and can be considered as elect~omagnetically tains a fundamental with odd harmonica of significant
cquivalent to a two-pole machine. amplitude. The voltage induced in a single stator con-
An economic design of stator winding has many ductor would contain similar unacceptable harmonic
conductors connected in series, so the individual con- components.
liuctor voltages are additive. Each 'go' conductor is In a series-connected winding occupying several
connected to a 'return' conductor, acted on by the adjacent slots in the stator, the voltage induced in
pole of opposite polarity, and thence to a third con- one conductor will be displaced from that induced
ductor adjacent to the first, and so on through the in Its nelghbour by the electrical angle subtended
phase. The 'return' conductors are disposed in a layer by the two slots, a in Fig 6.12. The sum of n such
displaced radially from the 'go' conductor, both in voltages is V + 2Vcos ol + 2Vcos 2 r ~+ ... 2Vcos +
the slots and in the end region. (n - + ) a if n is odd, or, 2Vcos a / 2 + 2Vcos 3a/2
The usual and most economic arrangement Is for + ... 2V cos (2" - +)a,if n is even. The ratio of
the winding.of one phase to occupy one-sixth of the this to nV is the distribution foclor Kd ( < 1).
circumference, with a parallel section of the same The effect of distribution on the third harmonic
phase occupying the position diametrically opposite voltage is to triple the effective angle, so that the
(see Fig 6.10). surnmated voltage is:

MMF PHkS:SORSROTTEOBACK
THRoUGH SOI TO SNOW
SiMlLARiTY Of TRIANGLE 10
V3 + ZV, cos 3 a + 2V3 cos 6 a + etc.
VOLTAGE PHASORS

2.9 distributed and chorded and the resultant third harmonic voltage is very much
winding reduced. A similar argument applies even more effec-
FIG. 6.8 Phasor diagram Eor load conditions A cylindrical rotor generator has a circular rotor tively to harmonics of higher order.
T h e generator h
Cl~i.lllir~ Turhine-genera~orcomponents: the rotor
. .<
3 Turbine-generator components: the8
rotor
The rotor milst carry the excitation winding, l'i,,
a iow reluctancc path for the magnetic flux,
transfer the rated torque from the turbinc 1 0
electromagnetic reaction at the air gap. Steei i.
only material which meets these r e q u i r i : ~ ~ MMF DUE
TO COlL
econotnica1ly. A single steel forging is uscd.
which the centrai cylindrical body and its s u p l ~ o ~ t i
shafts are machined.

3.1 Rotor body and shaft


The high rotational speed produces large centrill
forces in the rotor body, and a high-strengtlt st
necessary. Typical alloying constituents are:

2.5% nickel 0.25% carbon


1.2% chrome 0.2% siiicon
0.6% manganese 0.1% vanadium
0.5% molybdenum

The steel is vacuum-degassed, which minimisei I


possibility of hydrogen-initiated cracking, and 111
forging is hardened by reheating and quenching U I I C
closely controlled conditions. Rough machininp
followed by a stress-relieving heat treatment.
Mechanical properties as high as 800 MN/m2 at iI.Z~/
proof stress, with 940 M N / ultimate
~ ~ tensile stl.eligIll
are obtained in forgings f o r t h e la~gch FUNDAMENTAL

ratings. A reduction in area of 40%. elongation lSci<n, \


Charpy V-notch impact level of 40 Joules, atirl it
fracture-appearance transition temperature o f 20"(',
are typical of this material, though specified tpni
perties are allowed to differ at different parts oi 1111:
forging and in different test piece orientations. S t r c i r t , ~
in a rotor at 3000 r/min limit the practicabk dian~ctp!
to about 1150 mm.
The rotor is examined ultrasonically from the
face at various stages, and any significant d
are reported. These are most likely to occur near I
cylindrical axis, and may be cleared by machining DEVELOPEDVlEW
A somewhat similar effect is produced by the central axial hole, not usually larger than 100 111 SHOWING STEPPE0 MMF WAVE
AND FUNDAMENTAL SINE WAVE
common practice of chording, or short-pitching. Here diameter, through all or part of the rotor. The critic
the return conductor is at a n angle less than 180" defect size is established from considerations of
from its connected conductors. If 0 is the angle by growth by fatigue, recognising that there will be I!
which this falls short of 180' (Fig 6.13): FIG. 6.11 The sleppcd magneto motive force wave
small, but significant, once-per-revolution alternalllt,
bending stress superimposed on the steady stress.
the ratio (1 - cos0)/2 is the pitch factor, K, (< 1) Magnetic permeability tests are carried out at rill
densities up to 2.2 tesla, i.e., well into magricll The shape and size of the winding slots are deter- keeping a low current density to minimise the loss
saturation. lnined by a n optmisation process, taking into account and temperature, as much of the area as possible
Hence, in the usual distributed short-pitched winding, The rough-turned forging is further turned by 111 Ole following factors, and considering a radial cir- must be allocated to the winding copper.
the generated voltage is nVKdK,, the harmonic con- generator manufacturer. The winding slots are tlic cumferential section:
tent is acceptably small, and the stepped rectangular cut, using accurately indexed milling cutters workin The winding insulation must be mechanically strong
flux density wave generates a substantially siuusoidal at a controlled cut rate to minimise residual surf1 c The more ampere-turns the rotor can carry, the to withstand centrifugal and bending stresses, and
voltage of fundamental frequency. stresses (see Fig 6.14). smaller the generator. Together with the need for stable to withstand load cycling. Adequate electrical
T h e generator rtirhinr.yi?nei-aro; componer~ls: liie r o l o ~
-

/---\ EI:liECION
IUNONdEMIbt. WLl"rl(

THE E F i i C i O N i i , !
FUNOAMENIAI V<il I,,, ,, I. EiitClON
THIRDHARMONIC
VOLTAGE

EFrECl ON
SIIIINHARMONIC
VOLTAGE

"5

PIC. 6.13 The effect of shoil.piiclliC>g Llle slator wilidiiig


THE EFFECT0
THIRD HARI4ONIC

PIC. 6.12 Tlie errcc~of disiributing the rlalor winding over rcvcral dois i:l~cumfereniial plane, at intervals axially along the Because the rotor winding slots are cut radially,
i t is not possible to fit a preformed coil into the slots
Iluring a three-pliasc sudden short-circut at the since the span o r a coil is smallev the iower down
,:rzieratoi terminals, torque peaks of Sour to five the slot it is, and considerable distortion would be
litiies full-load torque are experienced between the required to get the coils in. Each turn is therefore
tracking distances from the winding to the rotor 0 The whole centrifugal force of the slot conteots, I
I I' turbine and generator shafts. The generator rotor assembled separately, either as half-turns or in more
ali;iSt and coupling at the turbine end must be designed pieces, with joints either at the centres of the end-

insulation must therefore be more substantial than between the maximum tooth stress at overspecrl
the Operating voltage of about 600 V would require the proof stress of the steel.

.
proportion of the coupling bolts are fitted, the content to improve its creep properties, is used for
in other applications. the coils. Depending on the method of ventilation,
irers have a clearance to the coupling holes.
Passages for a n appropriate flow of cooling gas The optimisation of these conflicting require! lournal and journal-type shaft seal surfaces are rectangular sections with grooves and/or slots, or
must be provided in the winding copper section, has led, in the latest designs, to a departure ound and polished to a high degree of circularity. tubular rectangular sections are used. When a trape-
and also in the steel body section in some designs, parallel-sided slots to slots o f trapezoidal section verall, good surface finishes and absence of sharp zoidal slot is used, the sections may be o f several
to ensure that the specified temperature rise is 6.'s). >Itmishes are called for. Radii are made as large as different sizes. One or two turns in the width of the
not exceeded. The winding slots are cut in diametrically opl?i ~v;~cticable
to minimise stress concentrations. slot are normally used. Radialiy-aligned slots provide
gas exit passages (see Fig 6.17).
T h e coils are not individually wrapped with insuia-
tion. Instead, slot liners of moulded glassfibre, or a
no loss due to magnetic hysteresis or eddy currents, pendicular axes would produce a twice-per-rev01 .2 Rotor winding composite of glassfibre and a more flexible insulating

458 459
Turbine-generator components: the rotor

URRENTCARRYING
CONDUCTORS

I:l(i. 6.14 Cutting wiliding rloti in a rotor


MACiNCilC
FLUX

(Fig 6.18). Thick layers of insulation niaterial on the Fans mounted on the rotor, primarily to circi
inside surfaces of the end ring and end disc insulate hydrogen through the stator, assist the natural PiO. 6.15 Optimi~ationor a rotor seetioii
thein from the end windings. The spaces between through the rotor (see Fig 6.19).
turns in the end windings are partially filled with The ends of the winding are connected to flexil
insulating blocks, which ensure that the coils do not leads, made from many thin copper strips, which r,
distort, and which contain holes and passages for radially inwards onto the shaft a t the exciter ell because of the coarse grain structure, particularly
ilgal force. For electromagnetic reasons, these rings
the transfer of ventilating gas. These leads are housed in two shallow slots in tnve traditionally been made from nonmagnetic steel, where the shape is complex.
Because direct current circulates in the winding, shaft and are retained by wedges. At a point axi pically a 18% Mn, 4 % Cr austenitic steel. A 0.2% An austenitic steel, containing 18% Mn 18% Cr,
there are n o eddy current or other frequency related beyond the end windings, the leads connect oof stress of IMK) M N / ~is available
~ to cope with has recently been developed which has shown virtual im-
losses in the rotor winding. The resistance ( 1 ' ~ ) loss, radial copper studs and thence to D-shaped col lie high operating stresses. A ring is machined from munity to stress-corrosion cracking in exhaustive
amounting to 2 MW at rated load, together with the bars housed in the shaft bore. Seals against hydr single forging, and is attached to the end of the tests, while maintaining other properties at least as
rotational (windage) loss, must be dissipated, and the leakage are provided on the radial studs. Fronl tor body with a shrink fit designed to provide a good as the older material. This alloy is being used in
average winding temperature must not be allowed D-leads, connections are taken either to slipri, iall residual interference at 20% overspeed. The new machines and for replacement rings, eliminating
to exceed 115°C. A cooling system is used, in which or to the shaft-mounted exciter connections in the need for periodic inspection.
aterial has proved to be liable to stress-corrosion
hydrogen is in direct contact with the copper con- brushless machine (see Fig 6.17). The end ring is re vented from moving axially
cracking at the stresses invoived, and all the surfaces ex-
ductors, for optimum heat transfer. The high ro. ept the shrink fit are given a protective finish t o either by means of lugs mating with similar lugs on
tational speed produces a pressure head through the
risure that hydrogen, water vapour, etc., does not the rotor body, or by small spring-loaded plungers
rot01 Slots which causes hydrogen to flow from both
iave access to the surfaces. Even so, it is recom- locating into grooves (see Fig 6.20). In both these
ends, under the end windings and axially through sub- 3.3 Rotor end rings ,,ended that rings are removed occasionally for de- designs, the ring must be rotated through a small
slots in the rotor and channels in the coils, whence Thick end rings are used to restrain the rotor clld ailed surface crack detection using a fluorescent angle, when fully home axially, in order to lock. In
it emerges radially through the wedges into the airgap. windings from flying out under the action of cen~rlc dye. Ultrasonic scanning is not entirely satisfactory, a different design, a screwed ring is used t o pull the
The generator clhi%,ll,:,
ti
....,
*8
g
components: the rotor
Tiiibii~e-geneiato~.

4. -
$

s,.,,31,,14,
TERMIN,,, :,I,,,,
END BELL
i

FIG. 6.16 Stiffness eonlpenration


Tho generator Cl~a~!t*!@
---..,
a small taper lo facililatc asscrnblv and reniov;il, I!
~, -
Turbine-geileiaior components: the rotOi

is insitlatcd from the end winding with cittiri B


moulded-ii, glass-bdscd liner or a loose cyliiiii~iiiil
sleeve.
The outboard end of an end ring is partiall)
by a siiri~nk-onannular steel disc which enc
EPOXIDE GLASS STRII'S
end wnding. Clearance between the end win
the shaft allows hydrogen to pass into entry
in the winding copper. No contact between llrc
board end of tlie ring and the shaft is perniirhl
since the shaft flexure could promote fati
fretting damage at the interfaces. The end d
monly contains facilities for adjusting the m
balance of the rotor.
DOUBLE STRAP
COPPtR COlL TURNS

3.4. W e d g e s and d a m p e r s
- INSULATIONSTRIPS
NYLON PAPER
BETWEENTURNS The winding slot contents are retained by a u'iilgc,
which must be designed to withstand the crl~,liii~i
stress on its lands and the bending stress acroar 116
width, bearing in mind that it contains holes at al,!li
through which hydrogen passes. It must also br I,I,II
magnetic in order to minimise flux leakage aro11n11
OUieoARD
the rotor circumference, and to ensure a reasonable ~cili, END

EPOXIDEGLASS
tance value.
Extruded aluminium section is generally used,
chined in the regions of high stress. If shorl
lengths are used, the potentiality for localised
initiation in the rotor teeth exists. One c o n t i a i ~ a ~
wedge per slot is therefore commonly used, alli~ollelj
these are more difficult to fit.
During conditions of rapidly changing flux, fw c h
ample, during system faults, or when an altcit!i~l
ing flux links the rotor during unbalanced elcci~ii:iil
loading, when negative phase sequence currents it1111
fluxes occur, current is induced in the surfacr i r l
the rotor. Because the 'skin depth' of the magnrllr
rotor steel is about I mm whereas that of the ino,~
magnetic wedges is an order of magnitude grcalol
current flows preferentially in the wedges, whi
form a 'damper winding' analogous to the rot0 Ihc slits, and prevent hot spots at the ends of the several brushes and holders o n one of several
of an induction motor. The wedges are of slits. movable brackets, each of which can be withdrawn
cient cross-sectional area to carry the curren for brush replacement while running on-load, if SPe-
responding to the expected unbalanced load, wi cial precautions are observed (see Fig 6.22 inset).
FIG. 6.18 Rotor slot damage due to overheating, but the areas of cu Brush pressure is maintained by constant Pressure
transfer into the end rings (which act as the s I 3.5 Sliprings, b r u s h g e a r a n d s h a h earthing springs. A brush life of at least six months
circuiting rings) have to be carefully designed. Thin Connections are taken from the D-leads in the bore, be obtained.
per sheets with 'tongues' fitting under the en ll~rough radial copper connectors (which may have The brushgear is housed in a separate coflPartment
ring through its final few millimetres, and this also of the wedges form an interleaved ring under tli back-up hydrogen seals) and flexible connections, onto of the excitation housing, separately ventilated by a
locks it circumferentially. inboard end of the end ring, and assist in the avoid. the sliprings (Fig 6.21). For a 660 MW generator, shaft-mounted fall so that brush dust is n o t distri-
The ring must be heated to about 3W°C to expand ance of localised areas of preferential current transfc~ tlie rated excitation current is about 5000 A, and buted into other excitation components. mall leakages
it sufficiently for the shrink surface to pass over its and hot spots. sliprings must have a large surface area and run cool of hydrogen past the connection seals which might
mating area on the rotor. The heat is applied by a In pole faces having axial compensating slols, o in order to transfer this current satisfactorily. One accumulate in the brushgear compartments during pro-
special cylindrical electrical heater. If a gas heater is similar arrangement is provided. In those with croaa.. design uses two sliprings of the same polarity in longed shutdown periods, are safely diluted by the
used, the ring surface is protected from the direct pole slits, a few very shallow axial slots are cut lo parallel. The ring surface is grooved and drilled to im- fan on start-up before excitation current is applied. Win-
flame by a thin metal cover. accommodate copper damper strips, which are rc. prove its surface cooling. dows in the cover permit easy inspection Of the
The inner diameter of the ring is machined with tained by wedges, t o transfer the surface current acroh!, The brushgear shown in Fig 6.22 is arranged with brushgear.
i l l c generator
- Turbinegenerator c o ~ n p o n e n l s : t h e rotor

FlO. 6.20 Roloi end ring

Monitoring o f excitation current and voltage and It is normal for a large generator t o prodo
rotor winding temperature by resistance measurement, on-load voltage o f 10-50 V between its two
is simply achieved in a generator with sliprings, using ends, due to magnetic dissymmetry and other cat
a current shunt and voltage connections in one of This voltage would drivc current axially througl~
the excitation cubicles. Rotor earth fault detection, rotor body, returning through bearings and joorlli
and tile application o f tests such as the recurrent causing damage t o their surfaces, and insulatioil bii
surge method for shorted-turn detection, are also riers are provided t o prevent such current circu1;ttio~
simply arranged. These need only be at one end, the exciter end,
Where no main excitation sliprings are fitted (Fig must be present wherever the shaft would otherwise
6.231, signal may be transmitted from the shaft, via tact earthed metal, for example, at bearings, seals,
telemetry. Alternatively, a set o f light current sliprings scrapers, oil pipes and gear-driven pumps.
and brushgear may be provided for signal monitoring some designs, two layers of insulation are provi
and protection purposes.
with a 'floating' metallic component between 111 ,
466
F
& ~ " ~ b i n e - g e n e r a t ocomponellts:
r the rotor
T h e generator Cl,iiliiiii ti 2
.,., !F' -.
D

1 IiUUBLRGLOVE

INSlllhlCD HANDLE

so that a simpie resistance measurement between the It is important that the shaft at the turbine end
fioating component and earth confirms the integrity of the generator is maintained at earth potential,
of the insulation. and a pair of shaft-riding brushes connected to earth
While all the insulation remains clean and intact, through a resistor achieves this. Because carbon
ii voltage will exist between the shaft at the exciter brushes develop a high resistance glaze when OP-
end and earth, and this provides another method erated for long periods without current flow, a spe-
of confirming the integrity of the insulation. A shaft- cial circuit passes a 'wetting' current into and out
riding brpsh enables this shaft voltage to be moni- of the shaft through the brushes; this circuit also
tored, and an alarm is initiated when this falls below detects when brush contact is lost (Fig 6.24). A
;i predetermined value. different scheme, in which a current carrying contact

468
FIG.6.22 Slipring brushgear and brushes
JUNCTlON BOX

RESISTORS
--.-

-+
4
BRUSH
VOLTAGE MONITOR BRUSil

LlNK
JUNCTiON BOX

FUSE HOLDER
-_iJ

FIO.6.24 Shaft earthing and monitorins


STCTiON
EARTH
The generam Chsl,ii.i ir Turbine-generator components: the rotor
.... ..,.
or sub aiiy\r,Iiel.e along the tui-binc-generator shaft slings lhi.o~igii0111tile operation. 'The use of a siij>jiiiii
system can be detected, lhas aiso been used. t~oliey running on whcels of insulation rnaicii:;~ i i ,
the bore is depl-ecaled because of the co3.e d;ttr,:i!zi l i
can cause. Adequate space for rotor inseitioii t i l i t 1
removal must be provided.
3.6 Fans The whole turbine-generator line of rotors is I,C,I,
Fans circulate hydrogen through the stator and coolers. flexibly coupled together and must be allowv,l i i i
Identical fans are mounted at each end o f the shaft, attain its natural catenary shape if the bearinf:, ltitrtl
each ventilating half the axial length o f the generator. ings are to be satisfactory. The supports fol !lit.
Fans are either of the centrifugal type, with many generator (and exciter) rotors must be set up sc tllal
vanes in one annular assembly, or of the axial-flow these rotors form part of the catenary. Cooplln~i
type in which tile propeller vanes may be separate alignments are accurately set by the use of liiiil~l;
bolted-on components (Fig 6.25). The diametes over gauges and concentricity checks, and the stator i* rei
the blade tips may exceed that of the stator bore, up so that the radial airgap is approximately coristi~tl~.
necessitating the fitting of one fan after the rotor The axial position of tlie rotor train is fiar~lIly
has been threaded through the stator. Inlet and outlet
conditions are far from ideal, and though stationary
guide vanes are used to reduce swirl, the fan effi-
the thrust bearing, which is located in the I U ~ ~ I I I I . ,
Axial expansion o f tlie turbine rotors downstreit~tiiil
the thrust face, and of the generatol. rotor, 411,. lli
I,.h.,.
, ,. . . : .:ti-rz:b:
. . . . . . . . . . . . . . . . . . . . . . . ......
I.'
ciency is low. Noise reduction is not a major concern, temperature changes, may amount to 25 mm or V ~ I O I G : , b p ' i-J f
since the massive stator casing is an effective acoustic and this must be acconimodated in bearings, avr~l!., STAGE 2
barrier. fan baffles, oil scrapers, etc.

3.7 Rotor threading and alignment 3.8 Vibration


The rotor must be inserted into the stator bore, which Rotors for generators of 500 and 660 M W operalili~
is about 250 mm larger than the rotor diameter. This at 3000 r/min are relatively flexible, and pass throt~lih
is accomplished by supporting the inserted end of two main critical speeds (natural resonances in bendii
the rotor body on a thick steel skidplate which slides during run-up to rated speed. Simple two-plane b
in the stator bore, while supporting the outboard end ancing techniques are not usually adequate to atta
from a crane (Fig 6.26). The skidplate spreads the the high degree o f balance demanded at speed and
load over its area and prevents high iocal pressures to maintain reasonable vibration levels during ruli.~rp
being applied to the stator core laminations. The and run-down. Facilities for balancing are therciirld
rotor and skidplate are pulled in using jacking ar- provided along the length of the rotor in the (ovn~
rangements until tlie inboard end emerges and can of tapped holes in the cyiindrical surface, as wrll
aiso be supported in a sling. as in the closing discs of the end rings, and in oi1,el
Other methods are also in use: short lengths of locations at the ends.
extension shaft which are successiveiy bolted onto The rotor is balanced at speeds up to 3WO r/nbIl~
the inboard end enable the rotor to be supported by in the manufacturer's works. The winding is Illon

Tic. 6.26 Rotor insertion and withdrawal

lieated and the rotor is run at 20% overspeed. This ally be partially offset by balancing, so that conditions
subjects the rotor to stresses greater than it would at operating temperature are optimised (see Fig 6.27).
experience in service, and also causes the winding Imperfect equalisation of the stiffnesses (see Section
and end rings to settle into their final positions. 3.1 of this chapter) will cause 100 Hz vibration to
Trim balancing is then carried out, if found to be occur, superimposed on the normal 50 Hz. It is im-
necessary. portant to distinguish between these components when
Some rotors exhibit a relationship between vibra- presenting or analysing vibration amplitude readings.
tion amplitude and temperature. A few degrees dif- A significant crack in the rotor will have a com-
ference in temperature between one pole and the paratively greater effect on the double frequency vibra-
other, due to inequalities in ventilation, for example, tion component; 'run-down' traces are recorded and
FIG. 6.25 Axial flow fans on rotor can cause this. If the effect is consistent, it can usu- analysed, to provide assurance that no significant
471
The generator C I 1; 8.,
88
. . . ,
OILOEFLECIOH OIAPHHhllMOUIEA NSUlhllNG i i N G S
RETAINING RiNG

SECOND
CRITICAL

lA LoA@
i i N l \ i HOT
OPERNINGPOINT ORIG41"!,i

CHIIICAI.
INCREASL W I I H
TEMPERATURE
INCRIA!il(
,,,,,,,,,,,

OROiNRL COLD BALANCE

AFTER O F i S E i B A W N C E C O i C
SPEEU. llm#n

VECTORS RtPRESENTAMPLITUDE*ND PHASE ANCILI < i


SHAFT DISPLACEMENT OR SINUSUIDAL VELOCiTY

6
~ I U 27 R O , O ~ vlbrailon a
change has occurred since the previous run down. and are connected to the same lubricating oil systv~~i
Oil whirl in bearings can cause vibration at 25 Hz. Seals are provided in both endshields to prcvclt!
Vibration amplitude and phase are recorded at the escape of hydrogen along the shahs. Mosl ir
generator and exciter bearings by accelerometers these seals are like small thrust bearings, in wlr
mounted on the bearing supports and by proximity a non-rotating white-metalled ring bears against FIG.6.28 Thrust-type sllaff real
probes which respond to the shaft movements. Var- collar on the shaft (Fig 6.28). Oil fed to an an!,\
ious degrees of sophistication, up to complete Fourier groove in the ring flows radially inwards acros. II,I;
analysis, are available. face into a collection space at frame gas pl.cssiito,
The torsional resonance of the generator rotor while the radially outward flow is collected i n rti absorbent.' If left inside an open stator, dry air must be transported. The completed core and core
coupled t o the turbine rotors is of the order of atmospheric air compartment. The seal ring niuri I>? be circulated. assembiy was inserted into a substantlai Outer casing
13 Hz. It is important that this is significantly dif- held against the rotating collar, and must thrlrltr~,- Protection applied to journals, sliprings, etc., must for in-works testing and finally at site.
ferent from the frequency of torsional exciting in- be able to move axially to accommodate the thc~iriiti be removed before operation. Blanking tape and one-piece stators for 660 MW generators can
fluences, of which the excitation and steam governor expansion of the shaft. collars, designed to prevent ingress of foreign ma- be transported, the two.piece concept has been con-
control (I - 2 Hz), and transmission system resonances Some machines have seals which resemble terial into the winding, must also be removed before tinued (see Fig 6.1).
are the most important. journal bearings (Fig 6.291, in which oil is appl operation
Transient oscillations in torque occur during elec- centrally and flows axially inboard to encounlet 11
trical disturbances, e.g., during switching operations, hydrogen pressure and axially outboard into ail
lightning strikes, imperfect synchronising events, etc. mospheric compartment. Such a seal does not I 4.1 Stator core
Some of the torque cycles may be large enough to to move axially, since the shaft can move freely in 4 Turbine-generator components: the The core provides paths for tile magnetic flux from
cause plastic deformation in the turbine-end shaft it. Details of the seal oil system are given in Sec stator one rotor pole around the outside o f the stator wind-
and at the generator/exciter coupling. 5.3 of this chapter. The stator must carry the output winding, provide a ing and back into the other pole.
low reluctance path for the magnetic flux, and with- As the rotor rotates, carrying its flux distribution
stand the torque produced, both at rated load and with it, all points in the stator core experience a
during faults. sinusoidally-varying 50 flux density. This would
3.9 Bearings and seals 3.10 Size and weight When generators rated 300 MW and above were induce a 50 Hz voltage of 700 V mially in a
The turbine-end bearing is located in a common ped- A rotor for a 660 MW generator is up to 16.5 ili first specified,'it was found that the smallest prac- solid core, and to prevent large circulating currents
estal with the LP turbine outboard bearing. The ex- long and weighs up to 75 tonnes. It is provided I!~III ticable stator core, assembled into the lightest pos- with their associated losses, the core is made ,of thin
citer-end bearing is either located in the endshield a cradle for transport. The rotor must never bc 11. sible casing was too heavy for transport by road steel plates coated with an insulating material; the
or in a separate pedestal. The white-metalled bearings lowed to be supported on its end rings; the weigkl in the UK, within the statutory limitation of that voltage induced axially in plate 1 s about 50 mV.
are spherically seated for ease of alignment, are pres- must be taken by the body surface leaving the old time. Since it is not practical to design a core in The sheet steel from ~ h i c hcore plates are cut
sure lubricated and are provided with jacking oil tap- rings free. Lifting slings must only be used ovcr tlr. sections for on-site assembly, and complete core conforms to ~ ~ 6 0 which
1, specifies dimensional lim-
pings. They are similar to the turbine bearings (see body length. It must be protected from water con. building and winding on site has disadvantages, a its, magnetic properties, silicon content (normally 3%)
Chapter I), except that the outboard and exciter bear- tamination, while in transit or storage, by the use ol design evolved in which the core and windings were and state of annealing, and test m e t h o d s Sheet thick-
ings are insulated (see Section 3.5 of this chapter), a weatherproof container with an effective moisti\tr assembled into a skeletal core frame, which could nesses used are 0.35 and 0.5 m m , with a specific
The generator
Cl~z%!b!t'$
$, Turi>inegeneratoi colnpoiicnts: tile stator
...

A n infra-red camera is used to scan the stator bore The net axial length of magnetic steel presented to
total loss value at 1.5 tesla and 50 Hz of 3.55 W/kg, where required, for the passage of cooling gas, l i y Idi areas of higher than normal temperature during the flux is less than the measured stacked length by
or better. building in a ring of thicker piates to which sni;ill ,iich a test. a factor between 0.9 and 0.95, known as the stacking
Core plates are cut to form segments of an annular steel bars have been welded. These bars are aligi~cil Some designs include a bonding agent between Jocror. This is because of the varnish iayers (and
ring, twelve segments per ring being common. Wind- in a mainly radial orientation, and serve to distribtltc layers of core plates to ensure that individual plates, adhesive if present), and the air spaces between core
ing slots, iocation notches and holes for ventilation the gas througil the ducts. Holes in the plates ;nc ;and particularly the teeth, do not vibrate independ- plate layers due to uneven plate thickness and im-
(if required) are cut in one pressing operation. The arranged to be in axial alignment and thus form axirll catly. Any wavyness in core build-up is corrected by perfect consolidation.
use of dedicated dies is justified, since nearly a quar- ventilation ducts in some designs. At intervals durine 111e use of suitable packing material. Slots for the stator winding conductors (bars) extend
ter of a million core piates are used in each 660 MW core building, heavy pressure is applied to consolidalc Grain-oriented sheet steel, whose magnetic pro- radially from the bore. These slots have parallel sides,
generator. The punched plates are ground to remove the assembly of plates. perties are deliberately made different in the two so that the deep bars can be inserted radially, the
edge burrs, and are then coated all over with one or When the build is almost complete, and with prch. perpendicular axes, is used in some designs (Fig 6.32). teeth between them therefore increase in section with
more thin layers of a baked-on insulating varnish. sure applied at the top end, the core is subjected ti, increasing radial disrance. The flux density in the
];lux in a circumferential direction behind the winding
With the core frame axis vertical, and one core a peripheral 50 Hz magnetic flux, which causes t l ~ r slots is arranged to coincide with the low loss orienta- teeth is therefore preatea at the bore, at the tooth
end plate in position at the lower end of the frame, plates t o shake down further, following which llio tion, which enabbs the back of the core to be op- tips, and is usually about 2 tesia for an acceptable
a ring of core plates is assembled, located on dove- space created is filled with more core plates and thr crated at a higher flux density than with non-oriented specific loss in the teeth. Since the slots and teeth
tail-shaped keys on the inside periphery of the frame. top end plate is assembled and pulled down. Core core steel, for the same specific loss. The opposite is are roughly equally wide at the gap, the mean peak
The radii1 butt joint between plates has as small flux tests are also carried out on the completed corc, true for the teeth, where the flux is radial and the flux density in the air gap is typically 1 tesla. The
a gap as possible to minimise magnetic flux distor- with a flux density in the back of the core 90-100010 specific loss is higher than normai. A reduction in peak flux density in the core back is typically 1.5
tion. The next ring of core plates is assembled so of the rated value, in order to demonstrate free do,^^ outside diameter should be possible from magnetic tesia. Some leakage flux in the end winding regions
that its butt joints do not coincide with those of from significant faults (Fig 6.31). If sufficient acoi- considerations, but the mechanical properties are ad- penetrates into the ends of the core. The axial com-
adjacent rings (see Fig 6.30). dental contacts between adjacent plates occur, il is .ersely affected. Core piates of grain-oriented steel ponent of this flux induces alternating voltages in the
Gaps in the build-up of core plates are created, possible for current to flow, causing local hot spots. ,nust be specially annealed after punching. teeth, and current flows around the teeth, as shown
Turbine-generator components: the stator

reiicved, thcsc additional weids are not.


Even thoogli the axial framc members arc outsidc
the core diameter, they link with the low level of
leakage flux existing in this area, and voltages are in-
duced axially along them. Near to the ends, elec-
tromagnetic end-effects tend to force the resulting
currents into the core and, if the assembly bars arc
not insulated, core back burning and welding can oc-
cur. T o prevent this, copper short-circuiting conncc-
tions are fitted between assembly bars at the core
ends. Where the bars are insulated, the currents flow
into and around the core end plate.
The outer surfaces of the core end plates are
covered by conducting screens of copper or alumi-
nium, about 10 mm thick (see Fig 6.37, end plate flux
shield). Leakage flux impinging onto these screens
sets up circulating currents within them which prevent
the penetration o f an unacceptable amount of flux
into the core end plate or the ends of the core. The
high conductivity and good surface exposure to
cooling hydrogen ensures that screen temperatures arc
not excessive. The leakage flux is produced by a
DlACRPMMI'ICREPRESENThiiONOi MAONLIICSLUX combination of stator and rotor MMFs, and there-
IN STATOR CORE, 0PLNClilCUICONL)lllONS
fore varies with load angie, or, roughly, with power
factor, the effect on the screens bcing most intense
at leading power factors.
1:10. 6.31 Flux test on eoznplelerl care AREAOF The core end plate assembly carries the end winding
MOOERATE
(see also coloui pllolograpll between pp 482 and 483) FiUXOENSilY ROLLING OIRECIION support structure, and the design must ensure that
axial forces due to differential thermal expansion be-
tween core and winding do not force the end plates
into a position where core pressure is significantly
in Fig 6.33, causing unacceptable additional losses. perature at the bore, as well as the final sl?,iil) reduced.
To reduce this effect, one or more radial slots are tcmneratu1.e. The completed core and core frame assembly must
punched in the teeth for a few centimetres at the As noted earlier, if accidental contacts occl!, li!i
ends of the core, referred to as Pistoye slots. be jacked into position inside the casing, where it is
the tooth tips or due to burrs at, or damage ti), llii. supported on fee: with resilient mountings, or by flat
The rotating magnetic field results in a rotating slot surfaces), a circuit may possibly exist for ;! iril vertical support plates, either of which provide some
radially-inward force being applied to the core across culating current. The current lcvei depends, intcr ; i l i t t , attenuation o f vibration. The holding down bolts must
a diameter, causing an ovalising distortion moving
on the contact resistances between the back 01 lltr be designed to withstand the overturning torque pro-
synchronously. The strength of the core and core core plates and the core frame bars on whicii 1111
frame assembly must be able to resist this force with duced during a sudden thiee-phase fault at the ter-
plates are assembled. In some designs, all these I ~ I I I ~ ORIIN.ORIENTtD minals, which may be four to six times the full-load
minimum strain, which is transmitted to the windings (except one which earths the core) are covered \\,ill1
CORE SEOMENT
torque.
and the outer casing as a 100 Hz vibration. It is also insulating material, minimising the chance of c u r r c ~ ~ l
important that the assembly has no resonances near circulation (Fig 6.35). In others, there is no itia~i. FCC.6.32 Flux in stator core
to the exciting frequency. lation, and the contact resistance is not only randoai,
Hysteresis and eddy current losses in the core form but may vary with load as the torque reactioti I$ 4.3 Stator winding
a significant proportion o f the total loss. In UK transferred, causing a hot spot in the core to 'swilch' The stator winding must be able to carry the rated
designs, the heat produced by these losses is removed passing through the core would have high voltages
on and off. induced in them, the only permissible axial members current without exceeding specified temperatures and
by hydrogen circulating radially in the ducts and be able to withstand the voltage to earth induced in
axially through holes, where these are provided (Fig are located outside the core back: these include the
6.34). Thermocouples are built into the core, parti- core plate assembly bars. In order to apply pressure it. The currents and voltages in the three phases
cularly in regions expected to be hotter than average, uniformly over the core ends with such a n arrange- must be exactly the same, but with a 2s/3 time dis-
4.2 Core frame placement for balanced conditions, and so the wind-
to ensure that the maximum detected core temperature ment, the e n d plates are machined with tapered inner
The fabricated steel core frame is designed to be ;I!, ings associated with each phase must be identical
does not exceed the specified value. If a hot spot faces, so that when they are pulled towards each
light as possible consistent with its required functions, other they distort until they present a truly plane but separated by 2s/3 around the stator circumfer-
exists, or develops in service, it is unlikely that there as previously explained. As well as the function;
will be a thermocouple sufficiently close to it to surface to the core, at which point the design pressure ence. It is convenient in large two-pole generators
already noted, it must be able to resist elastically thc is being applied to the core (Fig 6.36). to arrange each phase winding in two identical paral-
provide an unambiguous alarm. An occasional flux axial pressure applied to the core.
test, when opportunity occurs, offers a better chance The core plate assembly bars are loose as the lel circuits, located diametrically opposite each other,
A core end plate assembly consists of a thick disc core is assembled, and are progressively welded to and, because they are influenced by rotor poles of
o f hot spot detection. A deep-seated hot spot may of non-magnetic steel, with (usually) separate no,).
be detectable by observing the rate of rise o f tem- the frame as core building proceeds, using location opposite senses, connected back-to-back with each
magnetic 'fingers' to support the teeth. Because boiia other (see Fig 6.10).
plates. Thus, although the core frame may be stress-
477
Turbine-generator components: uie
.
8- li,e radial conductor dimension becomes about 40 mm, effect is not quite nullified since leakage fluxes occur
g with the o<erall radial bar dimension about 80 mm. in the end winding areas also, and some designs use
3 . - conductor embcdded in a nar-
A current carrvine a transoosition of greater than 360" in order that these
low slot in a magnetic material drives magnetic flux end efiects shall not be additive.
CMMPjNG POSITION
svound itself, mainly confined to the magnetic teeth, A differential eddy current voltage still exists bet-
hot completing its circuit by crossing the 'aiigap' ween the top and bottom of each strip, and current
represented by the slot width, further up the slot than will flow around it. The loss due to this current varies
file conductor (Fig 6.38). If the conductor is viewed as the fourth power of the radial dimension of the
EARIHINO POSlTiON
8s an assembly of separate strips, it can be seen that strip, so the incentive is to make the strip very thin.
lhe leakage flux density experienced by each strip However, the space required for insulation then
increases linearly with distance from the bottom strip. becomes excessive and compromise is needed. Water
'This alternating leakage flux induces alternating volt- is circulated in rectangular section tube, which must
CORE FRAME
ages along the lengths of the strips, in quadrature with have a considerable depth, and in some designs an op-
Ihe main voltage, and varying as the square of the timised mixture of tubes and thinner solid strips is
CORE distance of the strip from the slot bottom. If a solid used (see Fig 6.40).
conductor were used, or if the strips were connected Conductors are made of high conductivity hard-
together at the core ends, these unequal voltages drawn copper. Each strip or tube has a thin coating
would circulate current around the bar, causing un- of glassfibre insulation, and is cranked to enable
acceptable eddy current losses and heating. all the strips in a bar to be assembled with the
In order to minimise this effect, the conductor Roebel transpositions correctly made. The bar ends
is divided into strips, which are lightly insulated, are bent using formers to give the required shape of
DETAIL SHOWING CLAMPING AND EARTHINO POSlTlONS
VlEWEDFROMiURBlNE E N D O F M R E arranged in two or four stacks in the bar width. The end winding. The strips are bound together and the
strips are transposed along the length of the bar by main insulation is applied: a tape of mica powder
the Roebel method (Fig 6.39). in which each strip oc- loaded with a synthetic resin, with a glassfibre back-
Pic. 6.35 Insulated core frame bars cupies every position in .the stack for an equal axial ing, is wound without breaks along the length of
length, so that the eddy current voltages are equalised the bar. The straight part of the bar is pressed In
and no eddy currents circulate between strips. The a heated mould to cure the resin and obtain the
The generator

Ways restraint. Packers o f i


parators and drive strips, slid
thermo-setting dougll are a i s ~ ,
(see Fig 6.40). Support of tile r
arrangement of connectiol~s ;til.

1-i<i. 6.37 C08c end-place and icieci? are included components due to: Fio. 4.24 ~eyshaln2 condenser - modular construction

AC resistance being greatel


design dimensions, while thc curved ends are con- (skin effect).
solidated using heat-shrinkable tape. Tests are carried
out to ensure that the insulation is properly conso- 0 Eddy currents, as already 11,

OISIkNCE FROM
SLOT BOllOM, X

SLOT la1 FLUX LINKAGE AT X


CONTAINING lbl EDOYVOITAGEI" X
IDENTICAL
CoNDUCiORS

FIG. 6.38 L I I u s ~ I B ~ ~ z ~ $,lie variation o I eddy currents in stator


482 Fzo. 6.31 Flux test on comple<edcore
Fro. 6.90 Condition monitor (NEI Parsons Ltd)
Turbinegenerator components: tlie stato,

FIG. 6.39 Rocbel fiai~rnosiliolli

e Currents induced in core end plates, screens, and forces are produced, both at rated load and parti-
end teeth. cularly when large current peaks occur duringfault
conditions. The end turns must be strongly braced
Harmonic currents induced in the rotor and end to resist the peak forces and also to

F8o 6 97 Dlnoiw~gmotor-gonoralor during rlio w r n d l n ~ #"


. ring surfaces.
Currents induced in frame, casing, endshields, fan
baffles, etc.
100 H
~
7
.. . .- .- ...
.vihratinn ...
The MMF produced in the end winding legion by
the combined effect of the stator and rotor end wind-
ings produces a considerable magnetic flux in the
end regions. Paramagnetic material would tend to
These individual losses have to be assessed so that concentrate the flux into itself, and electrically-con-
the appropriate cooling medium is directed to their ducting material would have eddy currents induced
sources, in order to avoid unacceptable localised hot in it, causing both additional loss and potential hot
spots. Spots. Metallic inserts and fastening devices can be
caused to vibrate and loosen, or wear away their
surrounding medium. Consequently non-metallic com-
ponents are used, mainly moulded glassfibre.
4.4 End winding support Substantial support brackets are bolted to tlie core
In the end windings, bands of conductors are arranged end plate and provide a support for a massive glass-
side-by-side, all carrying the same current although fibre conical support ring. The outer layer of end
not all in phase, and considerable electromagnetic turns is pulled onto a bedding of thermosetting con-
The generator CI~;~jiiiai
l3 Turbine-generator components: the stator
,,,..
",..

lrable material between it and the support cone, nals are housed on the external stems of the biishings.
packers between the bars arcli-bind the structure The connections from the genciatoi terminals to thc
EACH DAR COMPRiSFS mfcrcntiaily. The inner layer is treated similarly, generator transformer are described in Volu~iie D.
P GROUPSOF BOTTOM INSULATION
2 STACKS OI STRAPS
4 /PACKING STRIP AND
CONrORMRBLE DOUGH
Phase isolated connections are always adopted, so
,y through-bolts, completing the very rigid structure. that an electrical fault at the connections must start
'ome designs use sheets of insulation material to as a line-to-earth fault, which is much less damaging
lose any spaces and prevent the accidental ingress to the generator than a line-to-line fault.
CROSSOYEH INSULATION

rly unwelcome, since it can be caused to vibrate


brade, or be heated by eddy currents and de-
the adjacent insulation (see Fig 6.33). Vibration 4.6 Stator winding cooling components
e end windings must be minimised, since it can Water is the best of the commonly available media
for cooling the stator winding, and imposes only one
ALTERNkTE SOLID condition that would not also apply to other fluids: it
ANDHOLLOW
COPPERCoNDUCioRS - ROUP BINDING iAPE
lube, since hydrogen will leak into the water circuit. must be pure enough to be effectively non-conducting
Resonances close to 100 Hz must be avoided, since (electrically). It is continuously degassed and treated
both the core ovalising and the winding exciting force in an ion exchanger, with the following target values
occur at this frequency. Accelerometers in the end being aimed for:
RlPPLE SPRiNG
winding structure allow any increase in vibration due
to support slackening to be monitored. Vibration am- Conductivity: 100 pS/m
plitude is highly current dependent. Any looseness
developing after a period in operation can be cor- Dissolved oxygen: 200 pgllitre lnax (in some
cted by tightening the bolts, by inserting or tighten- systems 22000 is acceptable)
g wedges, and/or by pumping a thermosetting resin Total copper: 150 pg/litre max.
to rubber bags located between conductor bars.
Figure 6.41 shows the stator core and end windings pH value: 9 max

At these levels, no aggressive attack on the winding

1
GROUPVERTiCAL
SEPARATOR copper has been noticed after very many years' ex-
perience. Any erosion of copper is detected by the
4.5 Electrical connections and terminals monitoring equipment.
13ectrical connections between one conductor bar and Water is passed into one or more inlet manifolds,
ALL HOLLOW
COPPERCONDUCTORS - MAIN INSULATION WRAP
$he next in series are made differently in different
iicsigns. In one, a common electrical and water con-
which are copper or stainless steel pipes running cir-
cumferentially around the core end plate. From the

1 STRAP INSULATION
iiector is formed by a copper tube bent into a U-shape,
;mid brazed onto small copper waterboxes into which
till the bar subconductors are brazed. In another, the
electrical joint is made by a solid copper bolted joint,
with the water connections separate. It is common
practice to insulate the joint or to enclose it in a
rubber housing.
The conductor bars at the high voltage end (line
manifolds, flexible PTFE hoses are connected lo all
the water inlet ports on the stator conductor joints.
In a two-pass design, water passes through both bars
in parallel and is transferred to the two connected
bars at the other end, returning through similar hoses
to the outlet manifold which adjoins the inlet mani-
fold. This design minimises the number of hoses,
but requires a larger pressure head of water across
end) and the low voltage end (neutral end) of a phase the winding (see Fig 6.43). In a single-pass arrange-
band are electrically connected t o tubular connectors ment, hoses connect both ends of a bar to the
I, PROTECTlVE DRiYiNG SiRlP which run circumferentially behind the end windings manifolds, which are located at opposite ends.
at the exciter end, to the outgoing terminals, usually Thin metallic-sleeved components are crimped in-
with line terminals at the bottom and neutral ter- side and outside the ends of the PTFE hoses, and
minals at the top, although other arrangements do these are then attached to bosses on the manifolds
exist. These connectors are internally water cooled, and winding connectors, using screwed-up olives,
and must be insulated for line voltage. O-rings or brazed joints. The casing hydrogen pressure
Terminal bushings (Fig 6.42) are proprietary paper- is everywhere greater than the water pressure in the
insulated items, with internal water cooling from the winding circuit, so that any leakage is of hydrogen
stator winding water system. Their insulation must into water, rather than the reverse, which would be
be capable of withstanding the hydrogen pressure in damaging to the winding insulation.
the casing, with no perceptible leakage. It is common The loss input into the water circuit at rated load
practice to flange-mount the terminals on a plate of is designed to raise the water temperature by less
nonmagnetic material, and to arrange for a terminal than 30°C. With an inlet temperature of 40°C, there
lo be withdrawable from outside the casing. Current is plenty of margin before theitemperature at which
transformers for instrumentation and protection sig- boiling would occur, 115-120°C at the working pres-
%
.

Tlie generator g
-- Clhi$i)r,, 0
........, @ - li~rbirie~generatoi
cornpo~~er~ts:
tlie slator
d,
@
&

RING SEALS

OUTER STATOR
FRAME

AiUMlNlUM
TERMtNAL
PLATE

TUliULhRCOPPER
ICONDUCTOR

PiFE HOSE
,CONNECTIONS

CONNECTION PALM

AIR SiOE

FD.6.42 Gcneiaior terminals


Turbine-generator components: the stator

circulated for a lcngthy l,eriotl, to waini the winding runners lo accornrnodatc the hydrogen coolers. At
bcforc thc generator is excited. the ends, thick r i n g provide facings for ihc separalc
end shields. Internai supports for the core frame, in
the forni of horizontal footplates or spring plate fix-
ings, arc provided, and external feet support the
4.8 Stator casing complete assembly. Lifting trunnions are usually made
The casing contains the stator core and core frame, detachable.
and must resist the load and fault torques. It must The design of the welded joints is carefully con-
also provide a pressure-tight e~lclosurc for the hy- trolled to avoid the presence of unfused lands wherever
drogen. Historically, casings have been made strong possible. The main welds have to be leak-tight against
enough to withstand the pressure developed by a n hydrogen at 4 bar, which is a very exacting require-
ignition of the most explosive mixture of hydrogen ment. The complete casing may be too large to be
and air, without catastrophic failurc. stress-relieved in a n annealing oven, in which case
Because any mixture of hydrogen and air within it must be assumed that stresses up to yield stress
the explosive range is not allowed to occur, attain- exist in the welds. In one design, the casing is con-
ment of explosion pressure is not a credible condition, structed in two halves, which are stress-relieved before
and to specify the casing on the basis of withstanding being welded together.
such a pressure without leaks, as would be required Thc end shields are thick circular fabricated steel
by BS5500, is unrealistic. Consequently, the full re- plates, ribbed to withstand the casing pressure with
quirements of the pressure vessel code are not invoked, minimal axial deflection. They house the shaft seal
though some o f them are applied. This pragmatic stationary components and, in some designs, the out-
approach has been justified by worldwide experience over board bearing. Leak-free sealing o f the end shield/
fifty years. casing joints against the hydrogen pressure, as with
Casings are fabricated steel cylinders o f up to all other casing joints, is effected by gaskets, O-rings
25 mm thickness, reinforced internally with annular rings and sealing compounds injected into grooves.
and axial members which strengthen the structure and The Completed casing assembly is hydraulically pres-
form passages for t h e flow of hydrogen (see sure tested, and finally must be demonstrated to be
Figs 6.44 and 6.45). Internal spaces are provided with leak-tight to a level corresponding to a fall from

FiO. 6.43 Stator wiinding waler cooling syrtcrn components

sure. Monitoring the temperature of each bar by horizontally inside the casing; they consist of banks
thermocouples, either in the slots or in the water o f finned o r wire-wound tubes through which waccl
outlets, enables a reduction o r stoppage o f water flow flows in one or two passes while hydrogen flows ovrt
in a bar to be detected. them. The coolers are arranged so that their headers
are accessible (for tube cleaning) without degassing
the casing. The tubes and the cooler frame must be
supported so as to avoid resonances close to tllc
4.7 Hydrogen cooling components principal exciting frequencies of 50 Hz and 100 Hz.
The advantages of hydrogen cooling, and its para- It is most important that moisture does not con-
meters, are described in Section 5 of this chapter. dense on the stator end windings, since electrical
Hydrogen enters the generator casing through a n breakdown may then occur. The dewpoint of the hy.
axially-oriented distribution pipe at the top, carbon drogen (at casing pressure) must be at least 2 0 ~ 1
dioxide for scavenging being admitted through a simi- lower than the temperature o f the cooled hydrogcil
lar pipe at the bottom. emerging from the coolers, and this is continuously
The rotor fans circulate hydrogen over the end monitored by a hygrometer. In normal on-load op-
windings and through the stator core, while a parallel eration, the stator winding water maintains the wind..
flow passes through the rotor. At rated load, the ing temperature above 40°C; if condensation occurrctl
hydrogen temperature increases by about 25'C during it would be on the hydrogen coolers first. Durinp
the few seconds taken to complete this circuit. Two run-up, however, the stator winding water is likely
or four hydrogen coolers are located vertically or to be cold, and it is either pre-heated electrically, or FIG.6.44 Outer stator caring
4
The genelator
CI??I,~<',I ,
.
.
*$ Cooling systems
*
2

@ rated hydrogen pressure o f not niare than 0.035 bar ductivity and specific heat of hydrogen, thc effect
k5 in24h. is that heat removal from heated surfaces is up
a Some of the core vibration is transmitted to the to ten times more effective. icsultine- in iower tem-
casing, and rotor vibration is transmitted through the peratures. Coolers can also be considerabiy smaller.
end shield and the foundations, The casing assembly
iiiust be designed to avoid resonances in the range e The use of hydrogen imposes the need fox hcime-
of these exciting frequencies. tic seaiing and condition control, which helps to
Drains arc arranged so that any oil or water col- ensure that the original electrical clearances are
lecting in the bottom of the casing is piped to liquid maintained.
leakage detectors, which initiate an alarm. Distri-
MOW imnporfanfly: the degradation of insulation
bution pipes for hydrogen and CO, are built-in; a by oxidation processes cannot occur in a hydrogen
temperature sensor at the CO, inlet initiates an alarm
atmosphere.
if the incoming gas has not been adequately heated
and could chill the fabricated casing locally. Electrical
iheaters are fitted in the lower half of the casing to The disadvantages are:
maintain dry conditions during outages. Since concet~trationsof from 4 % to 76% of hy-
The casing is bolted down to the supporting steel- drogen in air are explosive, hydrogen must not be
work on packing plates which are machined after aliowed to escape from the stator casing and its
triai erection to provide the correct alignment. Axial associated pipework in significant quantities and
and transverse keys prevent subsequent movement. become trapped in potentially explosive pockets.
The weight of the casing, complete with core frame, The casing and end shields have to be o f rugged
coolers and water, is up to 450 tonnes. construction and leak proof, demanding meticuious
welding techniques. Penetrations such as the rotor
shafts, and all outgoing connections, must be posi-
tively sealed, the former requiring a sophisticated
5 Cooling systems sealing system.
A generator of this type has an efficiency o f about
98.5%. Even though the losses are low in terms of A comprehensive gas control system is required.
the ootput, tiley amount to some LO MW, ail of For generators rated much above LOO MW, air cool-
which must be removed by the cooling systems; the ing is not practical; more than half the total loss
heat lost by convection and radiation from the casing would be due to fan and rotor windage. At 500
is not significant. and 660 MW, hydrogen pressures of 4 or 5 bar are
In some stations, most of the generator (and exciter) economic; higher pressures than this have little or
losses are transferred into the boiler feedwatcr system no advantage. The only practical alternative at
- condensate in the heat exchaneen.
bv usine, - Whiie these ratings is complete water cooling including
such an arrangement can be economic, there is a the rotor, which has not been adopted in the UK,
Penalty in the form of added complication, and the and only rarely elsewhere, because of leakage pro-
most modern stations do not have this feature. blems at the very high water pressures produced
by the rotation.

5.1 Hydrogen cooling


Hydrogen has several advantages over air as a means 5.2 Hydrogen cooling system
of removing heat from turbine-generators: It is necessary to ensure that potentially explosive
mixtures of air and hydrogen do not occur when filling
The density of hydrogen is the lowest of all gases the casing with hydrogen, or when emptying it.
and is one-fourteenth that of air. Even at the rated The usual method is to use carbon dioxide as a
pressure (4 or 5 bar) and with the allowable level buffer between the two other gases, in a process known
o f gaseous impurities, it is still only half as dense as scavenging, or simply gassing-up and degassing.
as air at normal temperature and pressure (NTP). Carbon dioxide, stored as a liquid under pressure,
The large losi due to the gas being churned by is expanded to a suitably low pressure above atmos-
the rotor, and to its circulation through the fans pheric. It is also heated, because the expansion causes
and cooling passages, is minimised by the use of it to cool and it would otherwise freeze. With the
hydrogen as a coolant. rotor stationary, COz is fed into the bottom of the
@ stator casing through a long perforated pipe, and
The heat transfer capability o f hydrogen is up to because it is more dense than air it displaces air from
twice that of air in similar conditions, though, as the top via the hydrogen inlet distribution pipe t o
with all gases, it increases with increasing pressure. atmosphere outside the station. Some mixing of gases
PIC. 6.45 Core frame being inserted into casing
Together with the several times higher thermal con- occurs at the interface. A gas analyser is used to
8@, 491
.e gelrelator Cooling system5

inonitoi the pl.opoi-lioil of C O , in the gas passing lo iored by several thermocouples, wliosc readings s l i ~ ~ i i l i l
atmosphere; when this is sufficiently high, lhe C O , be averaged, at the inlets to and outlets fl-olii 111i

TE:cq
~~ .... ~
~

inlet i s closed (see Fig 6.46). hydrogen coolers. Typically, hydrogen is ciucill;itvil --,-.--"I-

1-ligh purity hydrogen from a central storage tank at 30 m"s which, with a full-load loss input af ;$l>i!iit
GENERATOR STATOR CASING END
or electi.olytic process is then fed through a bus nrain 5000 kW, results in a temperature rise of the olrlvi ($1
a1 about 10 bar to the gas control panel, where its 30°C. The cooled gas should nor be hotter than lO"1 ,
pressure is reduced before being fed to the casing so the temperature of the gas entering the cooirih
through the top admission pipe (Fig 6.47). Being very should not exceed 70°C.
much lighter, it displaces the C 0 2 from the bottom Water cannot normally leak into the casing fi-OIII 1111-
of the casings via the C 0 2 pipe to atmosphere, again stator winding water circuit or the hydrogen coolc~!~,
with some degree of mixing. When the proportion since the water pressure is lower than the gas pressilir
of C 0 2 in the vent is low enough, the proportion in both circuits. It can be released from the slinS!
of air left in the casing will be very low, and if the seal oil, particularly if the oil is untreated turl>i~ir
casing is then pressurised with hydrogen t o its op- lubricating oil which has picked up water froril t110
erating pressure (say 4 bar), the proportion of air turbine steam glands. It is imponant that the ~moie
will be reduced to a quarter of this low value. The ture content of tllc casing hydrogen be kepi lor),
complete process normally occupies a few hours. enough to prevent condensation occurring on l l i u
Separate procedures are followed t o ensure that coldest component, which may be the water coolcd
other components, such as tanks, are properly scav- winding. The differential pressure is used to circlllutc
enged, so that dangerous mixtures do not occur. The a flow of hydrogen continuously through a dryri,
reverse of the foregoing procednrc, using C 0 2 and typically of the twin-tower type, using activatetl I ~ I I I
tllen dry compressed air, is followed t o remove mina, with automatic changeover and regeneratiol~,A
hydrogen from the machine for inspection or for a inotor-driven blower maintains the flow througi, 1111
prolonged outage. rotor when the rotor is not running at speed (scc ].if:
In one design of 500 MW generator, air is removed 6.49).
from the casing by drawing a vacuum, using the Continuous monitoring of the humidity of the r l l r .
pump normally used to degas the seal oil. The shaft in& gas is provided by means of a hygrometer. i l i i
seals are arranged to seal effectively under this unusual maximum permissible dewpoint is not less than 20°C
operating condition. When the vacuum is as low as below the cold gas temperature, measured at cusion
can be achieved, hydrogen is admitted, the resulting pressure. It is i m ~ g r t a n tthat this caveat is observed,
purity when pressurised being sufficiently high. particularly if the dewpoint is being compared with
Normally, hydrogen purity remains high, since air that of a sample drawn from the casing and measulcil
cannot leak into the pressurised system. Some air at atmospheric pressure.
may, however, be released from the shaft seal oil Hydrogen is circulated by the fans through tlic
flowing into the casing hydrogen space. Replacenlent stator core and end windings, the precise paths biiiii:
hydrogen to make up for leakage is usually sufficient different in different designs. The rotor acts virtuzill?
to maintain the required purity. as its own fan, hydrogen being drawn through liii.
The differential pressure developed across the windings and exhausted into the airgap, again tiil
rotor fans is used to circulate a sample of casing ferently in different designs. The hydrogen removr,.
hydrogen continuousiy through a katharometer-type the electrical loss in the rotor winding, the 'iron lirv,'
purity monitor, which initiates an alarm if the purity in the stator core, the windage loss produced by llic
falls below a preset value, typically 97%. The purity rotor and fans, and most of the electrical losses gcn.
monitor (and the gas analyser) can he calibrated with erated in the frame and end winding structures.
pure gases from the piped supplies. A check on the Because it is impractical to ensure that potentially
purity is also possible by monitoring the differential explosive mixtures of hydrogen and air never occur
pressure developed by the fans, which responds in the small bore instrumentation pipework, thosu
markedly to the change in density produced by air instruments and devices containing electrical circuil~.
impurity. in contact with the gas, such as katharometers, mu*;!
A Pressure sensitive valve admits hydrogen from be intrinsically safe in such mixtures. This means thsl
the bus main if the casing pressure falls below a pre- a sudden break in an electrical circuit must not br
determined level, while a spring-loaded relief valve capable of providing enough spark energy to ignitr
is set to release hydrogen to the outside atmosphere the gas.
if the pressure becomes excessive. It is important It is impossible to ensure complete freedom f r o r ~
that these two pressures are not set so close that Leakage of hydrogen over the lifetime of the plan:,
:t,.
s.>
wastage occurs, particularly as the gas temperature and the areas near to potential leakage sources arc ----
p,,,.:.
F,,', ,

kz
.
,, and pressure changes when on-load cycling. Monitoring
of the hydrosen
. - cansumotion is a reeentlv introduced
classified into zones of differing degrees of hazanl,
described in detail in CEGB Code of Practice 098/311:
- AIR
CO*
b;izi
~,.
feature on some units (see Fig 6.48). .
The temperature of the hydrogen is normally moni-
'Code of Practice for the Design Principles relating
FIG.6.46 Generator gas system - displacing air with CO?
<:,+
$< to the use of Hydrogen in Large Generators'. Zones 0
Cooling systems
.-

-?@ PERFORATE" AOMiSSlON PIPE


GENERATORSTATORCASlNG
?@ * EXCITER
END
1

FIG. 647 Oeneialor gas systenl - displacing co2 with H, FIG.6.48 Gcneralor gas ryrtem in normal operation
The generatoi Chap11 8 i Cooling systems

station, and to admit C 0 2 to the casing, duplicated in the white-oietalled ring, and fIou,s along the clear-
valves are provided, one set being located remcte from ances between the shaft and the bore of the seal,
where any fire is conceivable (see Fig 6.50). both outwards to tlie drain and inwards to the hy-
Hydrogen has been used universally for 50 years drogen pressurised space. The inward flow rate is
for high speed generator cooling, and incidents such much greater than that for the thrust type, because
as this have been very rare. The meticulous attention it is not inhibited by centrifugal force, and it would
to safely precautions both in design and operation be capable of contaminating the hydrogen purity to
lhave been largely responsible for this good record. an unacceptable extent. T o prevent this, all the oil
fed to the seals is subjected to vacuum treatment, in
which much of the air and water is removed. Against
this disadvantage, it is claimed that the journal type
5.3 Shaft seals and seal oil system seal is inherently better able to withstand disturbances
Seals prevent the escape of hydrogen where the rotor of the shaft by expanding to provide a larger clear-
shafts emerge through the casing end shields. What- ance for oil flow if it is heated by excessive shaft
ever their design, they are located in the end shields, movement
and are inboard of the bearings. Two types of seal More sophisticated versions o f tlie journal type seal,
have been commonly used: the thrust seal and the one of which has two separate oil supplies for inward
journal seal. and outward flow, have been developed to avoid the
need for vacuum treatment (see Fig 6.29). It is also
possible to keep the oil supplies separate from the
5.3.1 Thrust t y p e s e a l main turbine lubricating oil supply, which is the source
In the thrust type seal (Fig 6.281, the seal ring acts of most of the entrained water.
like a thrust face, bearing onto a collar on the shaft.
Turbine lubricating oil is fed to a central circum-
ferential groove in the white-metalled face of the 5.3.3 Seal oil s y s t e m
seal ring, at a pressure controlled to be greater than In the conventional seal oil system (see Fig 6.51), the
that of the casing hydrogen. Most of the oil flows main seal oil supply is taken from the shaft-driven
outwards over the thrust face and drains into a %ell. lubricating oil pump, with its pressure suitably re-
A small proportion flows inwards, against centrifu- duced. The pressure is further controlled by diaphragm
gal force and with only the oil/hydrogen differential valve which maintains a constant differential pressure
pressure behind it, into a drainage compartment which above casing gas pressure at the seals. The oil is cooled
is at casing hydrogen pressure. This oil can release in a water-cooled heat exchanger, and finely filtered
entrained air and water at this point, thus contami- to prevent metallic particles gaining access to the small
nating the casing hydrogen, as noted earlier, and it clearances at the seal faces.
is therefore important that the inward oil flow is Because it is necessary to maintain the shah sealing
small. oil at standstill, to prevent hydrogen escape, motor-
The seal ring is attached to a housing which must driven seal oil pumps are also provided; these act as a
lhe free to move axially to accom~nodatethe 30 mm back-up in emergencies, and are initiated by falling
or so of axial movement imposed on the shaft by seal oil pressure. They are commonly vertical pump-
tliermal expansion o f all the coupled rotors down- motor units mounted on the top o f the lubricating
stream from the turbine thrust bearing, as they pass oil settling tank with the pumps submerged. A battery
F10. 6.49 Oas dryer and blower from cold to hot conditions. The housing is arranged fed DC motor-driven pump may be provided as a
lo move inside a stationary member, using rubber back-up in case o f supply failure, but this would
sealing rings to contain the oil and to create a n axial be expected to operate only a few hours while the
pressure at the seal face. hydrogen is scavenged.
and 1, in which explosive mixtures exist continuously virtually impossible to eliminate some potential ignl. In some designs, an additional chamber between The oil flowing to the casing side of the seal is
o r occur in normal operation, should not be present tion sources, such as the rotating shaft rubbing a n oil fixed and sliding components is fed with oil at a in a pressurised hydrogen environment and must be
if the principles outlined above are followed. Zone 2, scraper ring, or sparking at brushgear. separately controllable pressure so that the overall collected in a 'break pressure' tank, which releases it
in which explosive mixtures are unlikely to occur Another potential source of ignition occurs wheir pressure at the seal face can be varied. In another through a float controlled valve and enables it to be
and, if they do will only exist for a short time, covers currents are induced in pipework loops, as may irr. variation, additional pressure is provided by springs. returned to the drain tank. The possibility of hydrogen
instrumentation as previously noted; the hydrogen the case when pipes are routed near to main con. entering the drain tank is recognised; low level alarms
dryer and blower, the detraining tanks, and the in- nections. Here, flanged joints are insulated to break give a first warning (some form of pressure loop is
terior of the control cubicle to which hydrogen is the possible current path. 6.3.2 J o u r n a l t y p e s e a l usually provided) and a blower exhausts the gas above
piped. Also classified as Zone 2 are the areas into If a serious rupture occurs, e.g., the break-up ol llere the seal resembles a short journal bearing float- the oil in the 'hydrogen section' of the tank to at-
which hydrogen may leak, through gaskets, seals, etc., a shaft seal, hydrogen may escape very rapidly, and ing on the shaft. In this case the shaft can freely mosphere. This blower also serves to reduce the
knowing the normal pressure behind the gas and its if it encounters a source of ignition, say the shall Inlove axially through the seal, and it therefore does pressure in the bearing housings (communicated via
propensity for rapid upward movement. Sources of rubbing, it will burn intensely in the ambient air. 111 not have to accommodate the thermal expansion of the half empty drain pipes) below atmospheric, thus
ignition are not located in such areas. It is, however, order to vent the casing to atmosphere outside tlir. tile shaft. Again, oil is fed to a central annular groove reducing egress o f oil vapour at the bearings.
497
The generator
Cha1,ii.l 1.
.

498
FIG 6 50 Generator gas system - emergency scavenging

i
,!
#
FIG 6 51 Seal oil system
F- E* ;.=>=.* - -
2 ='.E -
>
? c ;Z2>z g
.?Eo*.- " . O " O
psJ
$$?S$"
"?G$ a3 g2-2 2
gbfZ.5 .-.-?E
-" g g -$: 3 - ge *gz:.z
-" 2 ~ " ~ C8 a. Sg - :J m
2 : O z
cm

2.EGk.= E c . - m
-e s o 5 s g i K.G
5.5 o z = . E C l 0s
03.2; 2- "P- 8

=.
h:g;scos
5 2 0 1m "m c:z % E
2, 0
o
".CC5 ".Z$
g ,c .C ,? " " F .O :
'0 %
E 9 5.22
z3m5%;~tk::
3
" o z
g.gpgg a " " a
,= " = a "
-
m $ g a0 0a s" sG:g 2z . ,E
42
-2 + = :25 8 m gE g3'a"a-
2
2
o o m m ~
m
8
TI?@generator
~ l i a p i i .(.~ f Cooli!?g systems
Y

DRhlN VALVE \& STRAINER


As noted earlier, it is important that condensation
does not occur o n the windings. Some machines have
a n electrical heating element, or an automatic cooler
bypassing system, to prevent water that is too cold
from circulating in the windings during start-up and
early loading.
It is not easy to measure the insulation resistance
(IR) o f a winding which has multiple high resistance
paths to earth through the water-Xlled hoses, and even
epoxy resin insulation systems d o not absorb mois-
ture, and a low IR is usually indicative of surface
contamination, which can be removed by warmed air
circulation.

5.5 Other cooling systems


Casing hydrogen is cooled by passing it through water-
cooled heat exchangers arranged horizontally or ver-
draining out the water does not ensure that the inside
surfaces of the hoses are dry. Attempts have been made tically in the casing. The heat exchangers consist of
to use a specially designed resistance measuring device many tubes of non-ferrous metal with either metallic
which uses the water manifolds as 'guard rings', but strip fins or wire loops brazed to their outside sur-
this is not always satisfactory. Fortunately, modern faces (Fig 6.55). These coolers have a double-pass
T h e generator Chapter (i

water circiilatioii, so ilia1 ililct and oiitlct asater con- 6 Excitation


~ieclioiisare at the sainc end. They arc equipped wiih
sealing devices so that acccss to the header box can
be gained for inspection, even though the casing is
p~.essuiised.Some form of ail. venting system is also 6.1 Exciters
provided. Tile coolers can be withdrawn from the
casing when it has been scavenged. 6.1.1 Historical review
Water for tiiese coolers (and other auxiliary coolers)
When the first AC generators were introduced ii
may be condensate or distilled water in a self-contained
natural cholce for the supply o f the field systems was
system, or both; it is undesirable to use raw cool-
the DC exciter. These direct current commutator ma-
ing water because o f the danger of corrosion. The
chines were not only used as main and pilot exciters
water pressure is arranged t o be less than the rated but later also as a control amplifier, known as a
pressure of hydrogen in the casing, so that in the rotating amplifier or amplidyne.
event of leakage, hydrogen will leak into the water The DC exciter suffered from commutation and
circuit. In the latest machines, hydrogen detectors are brushgear problems but also offered certain advan-
provided in the water circuit (Fig 6.56). Operation tages; in particular, a capability for equal voltagr
is usually possible with one hydrogen cooler valved- output Of either polarity, which was used to improvc
off; this provides some redundancy. Loss of primary generator transient performance. The main exciter ar-
water is detected by rise of Ilydiogen temperature, mature also provided a path for the commutatioo
which may be so rapid that the protection is arranged of induced currents, regardless of polarity, which ap-
to trip the unit. pear in the generator field winding during poie-slipping
Air cooling systems are provided for the rotating and other severe system disturbances, thereby limiting
exciters, and for the slipring/brusbgear or rotating the induced voltage.
rectifier chambers. The rotating exciter components Gear-driven exciters were introduced to extend thc
llave a closed air circuit with a water-cooled heat application of these machines, however, increased
exchanger; the sliprings usually have open air venti- demand for higher excitation currents paralleled by
lation. advances in semiconductor technology brought about

STATOR EN0 CORNERMEMBER


WALL

,h,, c7 "h,nm,,,, =,
\ HORIZONTALFRAME
ENOMR i
COVER
PLATE

!~%&,TuBEdihiE StCURtNO
INLETAWL) OUTLET /- * SCREW
WATERBOX DOOR

LARCE HOLE FIX

FIG 6 55 Hydrogen cooler FIG. 6.56 Didlilled water cooling system

504
i i i e generator CI,?i~~lcv
I,

tlie introdoction oi' thc rectified AC excitcr. I'iicsc iixciler icsponsc ratio :~

!i8crc either stalic semiconductor diodc icctifieis sup-


plying ilic generator fieid winding via siipiings, or Tlrr avci-age rate of increase in excilaliol,
bri~slilesr systems \\.hicli carry llle diode rectifier on oi~en-circuitvoltage (V/s)
the shaft. l>cveiopmcnts iiavc continued and excita-
Nominal excitation voitage
lion powers now range from 70 kW for 20 MW gas
turbine-generators to 3500 kW for the 660 MMJsteam
Typically, exciters are required to incrcasc oulpul roli
tul-bine-generators. age from 100% to 200% in iess than 0.3 s c c a ~ ~ i i ~ , ,
Where generators are connected to tlie main
corresponding to a rcsponsc ratio of 3.5.
transmissioii system ovei long transmission links, it
The average rate of increase o f the excitation opc>t
is necessary to p~.ovide a high response excitation
circuit voltage is given by the slope of AC in Fig 6.51G.
system capable o f satisfying system transient stability
requirements. In these circumstances, a static thyris-
tor excitation system capable o f step changes in field Slope of AC = BC/AB but AB = 0.5 seconds.
voltage is generally specified. Hence AC = 2BC (average rate of increase of c i .
citer voltage) and the nominal exciter response r;iiiii
is given by 2BC/OA.
6.1.2 AC excitation s y s t e m s
The excitation requirements o f all CEGB 500 and 660
6.1.4 T h e pilot exciter
MW turbine-generators are provided by AC cxcitatioti
systems. A typical AC encitation scheme, showing the A shaft-driven excitation system consists of a maii,
shaft-mounted main and pilot exciters together with and pilot exciter, the pilot exciter providing the inp~li
associated brushgear is shown in Fig 6.57. power to the AVR. A number o f different types h a w
The CEGB currently operates 660 MW turbine- been developed including salient pole, inductor type
gencl.ators with either static or rotating excitation homopolar and heresopolar designs. System requiic.
equipment. Detailed descriptions of these are given lnents for complete indcpelidence from external sujl.
in Sections 6.2 and 6.3 of this chapter respectively, plies during 'black start' conditions have led to a trend
while this section concentrates on exciter plant which in favour of the permanent magnet generator (Ph4<il
is common to both. pilot exciter design. The salient pole design has gained
T o maximise plant availability under 'black start' favour on all recent 660 MW units and forms the
conditions, reliance on external electrical supplies is basis of the following discussion.
kept to a minimum by using direct-driven perma- The salient pole PMG is a three-phase mediunl
nent magnet pilot exciters. For many years, DC pilot frequency machine, providing an essentially constani
exciters were used, but the low currents involved voltage supply to the thyristor converter and AVR
introduced commutation problems due to brushgear control circuits. A typical salient pole PMG is shown
glazing and, as a consequence, they were supe~.seded on Fig 6.59.
by A C machines. The permanent magnet poles of the generator are
The pilot exciter provides power for the excitation manufactured from high energy material, such as
AVR control equipment which, on present 660 MW Alcomax. The permanent magnet pieces are bolted
plant, is of a salient pole design with ratings approach- to a steel hub and held in place by pole shoes. The
ing 100 kW. bolts are generally made from non-magnetic steel to
Both the main and pilot exciters are air cooled prevent the formation of a magnetic shunt. In some
machines, cooling air being drawn through the ma- designs of PMG, the pole shoes are also skewed one
chine by shaft-mounted fans. Temperature measure- pole pitch over the stator length to improve the
ments are taken at the inlet and outlet of the cooling waveform o f the output voltage and reduce electrical
circuit to monitor performance. noise.
The stator core is constructed from a stack o f low
loss sheet steel laminations, assembled within a fabri-
6.1.3 Exciter transient p e r f o r m a n c e cated steel frame. Radial and axial cooling ducts are
Exciters must operate over a wide voltage and current provided at intervals along the core length to allow
range as ceiling requirements are considerably in excess cooling of the core and windings. T o facilitate re-
of rated full-load conditions. The exciter is required moval, certain designs of pilot exciter can be split along
to respond quickly to changes in excitation at its own the horizontal centre line.
rotor terminals. This requirement for a fast response T h e stator winding is a two-layer design, each
characteristic is achieved by the use of a short air stator conductor comprising a number of small dia-
gap and a laminated rotor body. meter copper wires insulated with polyester enamel.
Exciter transient performance is characterised bv The coils are connected together to give the raced
the exciter response ratio defined in BSSOOO Part 2, three-phase voltage output, and insulated with Class
as follows: F (BS5000 Part 2) epoxy glass material.
The generator Excitation
.- ..,..,
layel' of gunchiogs in ihc core is ,made from a ln~il,i>ti
of tiiesc scgmeiils, coated with insulating varnisl, i i i l i i
iaid side-by-side to form a circle, Ail ihe joiiil~ i i ~ i
adjacent layers arc staggered.
The statoi- winding is of a lhrcc-phase, foiit oi
six-pole design, formed by copper coils whicli :I,,
contained in co~iductorslots io the corc, and rei;ii~ivci
in position by insulating slot wedges. Each coil i a
made from individually-insulated copper strips, coii
tained within a moulded insulating tube. To reslliii
eddy currents in the coil, the copper strips in each coil
are transposed.
The rotor consists of a hollow-bored alloy sruvl
forged shaft whicli carries the silicon steel iaminaiioitb
forming the rotor core. The rotor body is gencrzill)
laminated to reduce polefacc losses in the exciici
The reduction of this loss is important, as in the r i
citer, the ratio of stator slot opening/gap lengtli i,.
comparatively large, a short airgap length being i i i ,
cessary to lighten the burden on the main excites t i
citation system. The stator slots form indentations i i ~
the airgap boundary; therefore, as the rotor flux mar't,i
across the stator teeth, the changing permeance diii.
FIG. 6.58 Concept of rllc exciter iesposce ratio
to the sloi openings introduces medium frequeiiiy
pulsations. These pulsations induce harlno~iicvoltiir:ci
in the surface of the stator teeth but due to iiir
A steel enclosure is fitted over the PMG stator, laminated construction, the resultant losses are kcpi
whicli provides mechanical protection and serves to to a minimum.
reduce the medium frequency noise emitted from the The rotor windings are retained in position by cylin.
PMG to an acceptable level, as defined in 854999 drical rotor endcaps. A fan is mounted on a seatin!!
Part 51. machined in the balance ring to circulate cooling ail
Cooling of the PMG is achieved by drawing air At the exciter outboard end, two slipring units aic
through mesh-covered apertures in the enclosure; the connected to the endwinding, via radial connectio~r!.
air is then circulated by the rotor or shaft-mounted and upshaft leads.
fans.

6.1.6 Exciter performance testing


6.1.5 The main exciter Exciters are required to undergo a number of tea!,
i
li(R SCOOP
The main AC exciter is generally of a four or six- within the manufacturer's works to ensure that iiii
pole revolving field construction. The exception is the of the functional requirements are fulfilled. Thesr
FIG. 6.59 Salient-pole perlnanenf magnet generator
revolving armature main exciter used in a rotating include open- and short-circuit tests, overspeed bsi.
rectifier scheme, which is described in detail in Sec- ancing and HV testing. PMG exciters are stabilised
tion 6.2 of this chapter. by applying short-circuits across the stator terminals
The exciter magnetic circuit is designed to operate to ensure that there is no appreciable loss of outpiit
o n or near the unsaturated part of its characteristic. current for a pre-set time, after which the current is The rated current is well below maximum current;
voltage over the plant life.
This preserves a linear relationship between the con- The full exciter test requirements are contained witli- ramped back to a safe value. therefore, for reasons similar to those given for the
trolled excitation of the main exciter and the gen- The result of these measures is a pilot exciter having pilot exciter, no additional protection is provided.
in BS5000 which covers routine and type testing.
erator slipring voltage. The armature is designed for a considerable design margin for normal duties. It is
low voltage operation, with comparatively high current not, therefore, CEGB practice to provide additional
levels. A typical rotating field main exciter arrange- 6.1.7 Pilot exciter protection pilot exciter protection.
ment is shown on Fig 6.60. The pilot exciter is now invariably a permanent m a t 6.2 Brushless excitation systems
The stator core and windings are air cooled, the net generator with windings only on the stator. These
ventilation circuit being formed by the end cover windings are insulated to 1.1 kV and tested at 3.2 kV, 6.1.8 Main exciter protection
and ducting in the stator casing. Thermometers are 50 Hz for 1 minute, which is well in excess of the The main exciter, like the pilot exciter, has con- 6.2.1
fitted to the casing to measure inlet and outlet air normal operating voltage of 220 V. siderable inbuilt margin compared with its normal The development of the solid state silicon diode, with
temperatures. The pilot exciter is only ever called upon to deliver duties, the AC windings being insulated for 3.3 kV, its inherent robustness and reliability, made possible
The core is constructed from a large number of its full current output during field forcing. Modern even though normal working voltages are around 500 the design of a compact rectifier system that can be
segmented plates stamped from core plate material of AVR equipment is fitted with a time/current limiter V. During ceiling conditions, this rises t o approxi- rotated at rated generator speed. This alternative to
high magnetic quality and low electrical loss. Each which allows the pilot exciter to deliver maximuni mately 1000 V. the conventional slipring excitation system eliminates
508
The yeneratot b Excitatiori
~:l,,,l~,,.i
. . ,.,
,
-
poncnts. T i l a ied la a airnplified inechanical radiai veiitiiation ducts.
COiiii K t " arrangement. The armatore windings arc hcid in place by wedgcs
driven into dovetail slots formed when the wi~lding
slots are punclied. The arrnaturc winding overhang is
6.2.2 The rotating a r m a t u r e main exciter cooled by axial vents in the teeth in each end packet.
The main exciter is a brushless machine which, in The three-phase two-layer winding is secured in placc
conjunction with the other units of the biusllless ex- by wedges made from epoxy glass mat. In order to
citation system, supplies power to the main geilcrator minimise iosses caused by eddy currents, the conduc-
rotor. By dispensing with commutators, sliprings and tor is made from braided strips in parallel. A Roebel
brushgear, the brushless machine requires less main- transposition is used in the slot portion to reduce
tenance than the conventional machine and there are eddy current losses.
no sliding o r rubbing electrical contacts to cause Each of the phase ends of the three-phase winding
sparking or carbon dust. is connected to the appropriate phase conductor in
The machine is a three-phase rotating armature AC the AC shaft connection assembly by six laminated
generator driven dircctly from the main generator copper connecting straps. A copper ring under the
through a solid coupling. The DC field system is outboard endwinding forms the neutral point.
mounted in the stator and the AC winding is on tile The AC shaft connections between the exciter and
rotor. A laminated pole construction is used, giving a rectifier consist essentially o f three cylindrical con-
field circuit with a short time constant to produce a centric conductor assemblies which pass through the
fast response. wall of the shaft. Thc conductol. bars are insulated
The AC output from tlie main cxcitei is rectified from each other and from the shaft.
by diodes on the shaft and, in order to reduce diode Figure 6.62 shows the rotating rectifier unit of a
commutation reactance, a fully interconnected damper 660 MW generator which is mounted outboard of the
windine- is fitted to the exciter palefaces. Ficurc 6.61 main AC exciter, Three-phase A C power is supplied
shows a typical rotating armature main exciter. to the silicon diode rectifier from the main exciter
The stator consists essentially of a fabricated support by conductors taken axially along the surface of the
structure which carries the laminated magnet frame shaft. The components within the rectifier arc con-
and the associated field windings. The support frame tained against the high centrifugal forces by a steel
is formed from two steel end plates connected by retaining ring.
rectangular steel axial tie bars. The tie bars are equally The diode modules are accommodated within the
spaced around the bore to form a cage into which retaining ring in two circular rows, the complete
PIG. 6.60 Main exciter the magnet frame laminations are assembled. rectifier being a '3-2- 1-9' connection of 54 diodes.
The stator core consists of a laminated magnet The notation signifies three A C connections, two
frame with the latninated field poles boited into the DC connections, one diode in series per arm, and the
bore o f the frame. The magnet frame is built up from last number indicates that there arc nine paths per
the need for brushgear maintenance and reduces the segmental laminations of sheet steel. Each ring of phase.
the bridge operates normally. In the unlikely c\,i,~tl
overall unit size. laminations is made up of six segments; the segments The rotating rectifier includes a 20% standby ca-
of two diodes failing in the same bridge arm, a in~oili
Basically, the brushless scheme consists of a re- in adjacent rings are half overlapped so that the pacity, this ensures continued unrestricted operation
toring circuit in the field of the main exciter dutccis
radial joints d o not coincide. Ventilation spacers are in the unlikely event of diode failure. Anode-based
the fault and trips the machine. diodes are used in the positive arm and cathode-based
inserted during manufacture to form radial ventilation
Because of the high excitation power requirelnen~r diodes in the negative arm o f the bridge. The diodes
coupled to the main generator shaft. ducts.
of a 660 MW generator, a number of diodes are con. The field poles are laminated and assembled onto are of a compression bonded construction.
The rotating excitation system does not use field nected in parallel in each rectifier bridge arm. A fiiau key bars which allow the bolting of the poles onto Individual diodes are protected by two HRC (high
suppression switches and discharge resistors. The main is connected in series with each diode to isolatc i f the bore of the magnet frame. The poles are built rupturing capacity) fuses, connected in parallel, which
generator field is de-energised by suppress in^ the ex- if it fails. Present CEGB requirements include buiil., up from T-shaped laminations clamped between end- isolate the diode should it become faulty, leaving the
citer field which can be done rapidly by inverting the in redundancy of rectifier components so that, should plates by axial rivets. remaining healthy diodes to carry the full excitation
thyristor bridge which supplies it. The exciter time two of the parallel paths in each arm fail, full MCI( The exciter armature is formed from laminations current. Each diode moduje has a resistance-capaci-
constants are short; therefore the time taken to sup- excitation requirements can still be supplied. This of low loss electrical sheet steel, shrunk onto a shaft tance spike voltage suppression circuit and an indi-
press the generator field is only slightly longer than increase in components has meant the use of largcl cator fuse. The indicator fuse, in conjunction with the
forged from annealed carbon steel. Each segment is
in a conventional system. diameter diode wheels. Diodes and their associalcd thinly insulated on both sides with a varnish, baked blown fuse detector equipment, is designed to detect
All modern gas turbine units are fitted with brushless components have therefore to be designed to witit. the operation of the main diode protection fuses.
on to give a durable insulation. The shrink-fit is such
excitation systems, where the pilot exciter, main exciter stand centrifugal forces in the region of 60W g. that the stampings are always in contact with the The rectifier retaining ring is shrunk onto the out-
and diode wheel are overhung; this arrangement means Measurements o f essential quantities, such as lo. shaft. The laminations are clamped between heavy side of the hub. A thick cylinder of insulation is
the equipment is readily accessible for inspection. The tor earth fault indication, field voltage and current endplates of nonmagnetic steel with strong finger moulded onto the inside bore of the retaining ring,
complete rotating system is balanced as a unit. The are obtained via a telemetry link o r instrument slil).. supports for the armature teeth. and the circular rows of diodes are attached to it via
rotating diodes are connected in a three-phase bridge rings. Radial ventilation ducts are formed by spacer plates the diode module heat sinks.
arrangement, the bridge arm consisting of two diodes Recent designs o f rotating diode wheel have taken at intervals along the rotor body. Cooling air from The anode-based diode modules, situated at the
in series, so that if one fails by going short-circuit, advantage of continued developments in semiconduc. both ends flows axially along slots machined in the hub end o f the retaining ring each consist o f a heat
the other diode will continue to operate and hence tor diode technology to reduce the number o f cam. shaft to feed air into the interpolar gap through the sink, diode, capacitor, capacitor fuse and main fuse.
511
The generator Cllaiiti~,I ,

SUPPLY TERMINALS
CWLlNGWAiER INSULATED CLAMPING
INLET YENTIMION
ROC( HOLES
EXCITER STEELCOUPLING
BEOPMIE SUSHliND BOLT

FIG. 6.61 Rotating armaturc main exciter

Flc. 6.62 Rotating rectifier


The cathode-based diode modules are situated at bushes. Laminated copper straps connect the positive
the open end of the retaining ring, and in addition and negative rings to insulated radial studs in the
to the anode based components have two indicator shaft. These studs are screwed into the shaft bore
fuses mounted on the heat sink. Figure 6.63 shows a insulated D-leads. fuse detector performs this function; it consists of taining the three photoelectric cells associated with
typical cathode-based module. With a rotating rectifier system, diode condition two main units, an optical detector head and a ter- three separate light sources, two on the bottom face
The DC output from the rectifier is connected to monitoring is not as simple as it is on the equivalent minal unit containing the detection equipment, shown and one (the datum) on the top face. The light beams
copper alloy rings shrunk onto bushes on the shaft, static rectifier scheme. A method of indirect measure- diagrammatically in Fig 6.64. on the bottom face pass over the path traversed by
with insulation between the connection rings and the ment is required to indicate a diode failure. The blown The optical detector head consists of a unit con- the tips of the diode failure indicator fuses as the
513
p
The generator $;
Chii~?ii.ii, 5 Exi;it;ntoc~
.

FUSE PIN

IUNGSTFN HRLOGFN
LlOiiTSOLiRCF

BLOWN
REMOii
OETFCiOR ALARM
CiRCUli CIRCUITS

i."C*iAi*RM
NDICAICJR
LAMP

i TIC 6 64 Blown fuse deceilor sysienl


!6
z
tinuously scanned by the third photoelectric cell. Current measrrrrrxetit A current shunt is built into
The datum detector output is compared with the the rotor winding, giiaing a mV outi~utcoriespond-
blown fuse detector signal and the relationship be- ing to the 0-5000 A flowing in the field winding.
tween the two cstabiisl~es the position of the failed
diode. Earth leakage A DC supply is produced in tlie
Generators fitted with brushless exciters employ telc- rotating electronic equipment, the positive supply
metry systems to provide measurement o f generator o f which is connected to the negative end of the
rotor winding quantities, including rotor current, volt- field winding via a resistor R3. The negative is con-
age, temperature and most importantly earth fault nected to the rotor shaft through a high value
indication. resistor 114. Leakage to earth will result in current
The equipment uses solid state electronics, some flouing through these resistors which is measured
o f which are shaft-mounted and the remainder rack- by the voltage drop across R3.
mounted within the AVR. The rotating units are com-
FIG. 6.63 Negative DC diode module
pletely encapsulated and accommodated in transverse The output from the current channel is fed to a volt-
holes in the exciter shaft. Plugs and sockets are used age controlled oscillator that oroduces a freauencv
. .
for connections. The power supply for the rotating modulated (FM) signal, which is then conveyed to
rectifier rotates. Under normal operating conditions, electronics is supplied from the stationary unit at me- the stationary unit by the aerial assembly. Voltage
detector circuit, where an alarm signal is generated. dium frequelicy via windings on the aerial assembly. and earth leakage signals are treated similarly. Values
these light beams remain unbroken and the light shines T o distinguish between the two rows (positive and
continuously on the photoelectric cell immediately op- T h e overall schematic of the telemetry system is shown o f winding resistance and average winding temperature
negative) of indicator fuses, the light beams from thc o n Fig 6.65: are derived from the voltage and current signals.
posite, thus maintaining a constant signal. However, two probes are offset by an amount equal to half thc
should a diode fail, the associated indicator fuse op- The signal from the field voltage demodulator is
circumferential distance between fuses. Without this Voltage measurement The field voltage is obtained
erates and ejects a striker pin which interrupts the also fed to an active filter tuned to the exciter funda-
arrangement, signals from the two rows of fuses would from a voltage divider circuit connected across the
appropriate beam of light on each revolution. This mental frequency. Should a complete rectifier bridge
be coincident and therefore unidentifiable. field winding. This comprises resistors R1 and R2 arm fail, signals at this frequency appear in the field
interruption produces a pulsed DC signal at the output To establish the angular position of a failed diode
o f the photoelectric cell which is fed to the blown fuse which have a voltage output of 0.6 V corresponding winding causing the filter output to increase, initiating
on the rotating rectifier, a fixed datum point is con- to the generator field voltage. a n alarm.
FIG. 6.65 Rot~tionallclcilielly - overall rcnenlalic diagram

An alternative brushless exciter design consisting The need for the two diodes in series was deter-
o f a rectifier witii a 3 - 2 - 2 - 8 arrangement o f connec- mined from consideration of two diodes failing simul-
tions tolaiiing 96 diodes is also in common use. The taneously in the same phase of the rectifier. If the
notation signifies three AC connections, two D C con- series diodes u,ere not present, tlle resuit would be a
nections with two diodes in series and eight parailel short-circuiting of the generator rotor.
paths per bridge aim. The rectifier is designed to Indicator fuses are connected in parallel with the D Fla. 6.66 Rectifier nlodule (anode)
maintain rated output following the failure of up to main fuses as a secondary method of determining 9
two paths in any bridge arm. diode failures. When the generator is shut down, in- Q
A circular row of fuse modules and two circular spection of the indicator fuses readily identifies failed
rows of diode modules are contained against the cen- diodes. indication and phase location of up to three blown fier is fed via the mixer unit 4 to the transmitter
trifugal forces by a steel retaining ring. The diode For cooling purposes, air is circuiated in a closed fuses per phase, making a total indicating capacity 10 to give direct frequency modulation of the trans-
modules consist of anode and cathode units, which are ventilation system which contains a water cooled heat o f nine blown fuses. The other changes are the use mitted carrier frequency.
used in the positive and negative arm of the bridge. In exchanger. Air from the outlet side of the cooler cir- of a single transmitter, directly modulated by the The transmitter output is transferred via the aerial
contrast to the mark 1 systems, the mark 2 is fused on culates within the main enclosure. The self-fanning field voltage, to which are added sub-carriers contaie- to a carrier amplifier 16 and demodulator 17 to give a
the AC side of the rectifier and advantage has been action of the fuse and diode modules draws air from ing the rotor current, blown fuse and earth leakage mean output voltage proportional to the carrier fre-
taken of the improved peak inverse voltage capability the main enclosure througll the rectifier. information. quency. The output is then smoothed and scaled to
of modern diodes to eliminate the capacitor fuse cir- produce a n output corresponding to the DC field
cuits. A typical mark 2 diode module is shown on voltage.
Fig 6.66. 6.2.3 Telemetry system Voltage
Fusing on the AC side means a reduction in fuse T h e telemetry system employed on this design of The field voltage measurement is taken differentially
size, as tlle elements are no longer subjected to the rectifier makes use of the principle of frequency di- at each end of the shaft. as shown on Fie 6.67. Ear'" leakage de'ec'ion
high induced generator field voltages which occur vision multiplexing and includes a number of addi- Voltage measurement is made via a voltage "divider Rotor earth leakage is detected as a voltage devel-
during system faults and pole slipping incidents. tional features. The most significant of these is the and differential amplifier 1. The output of this ampli- oped across a resistor R6 which produces a frequency
8
change nt the ootpot o f a voitagc-to-frequency coil- of these sliprings.
vcster 3 , This oolpot is added to the voltage signal Thc hi-ushes arc designcd to opciatc contiotlolisiy i l l
in tlie t~ansmittcl-input inlirer 4. TIlc eartii lcakage order to acilievc ~lniotei-iuptcdrotor earti? Paul1 ilro-
signal is isolated from tlle carrier denioduiatoi 17 out- tcctian. This airaagcmenr is lightly loaded and \ ~ o u l d ,
put by a band-pass filler 22 and pioccsscti t o provide after a sliort period of operatior at iow current.
an earth leakage alarm signal. develop a high iesistancc contact film, resulting in
incorrect iwadings. T o oveicomc this difficulty, a
constant current is circulated through the two brushes
Field currenr ,neasure,iie~il ('brush-wetting'). This continuous flow of current
Field curreilt is measured by means o f eight series- maintains the interface resistance constant at normal
connected current transformers ( T I - T 8 ) in phase A levels.
of the main exciter output. Since each current trans- A signal propartional to generator rotor current
former (CT) surrounds a conductor between the fuses is obtained from a search coil mounted in tile
and the associated rectifier in one phase, the total quadrature axis of tlie exciter field coils. The output
output from the current transformers corresponds to signal is filtered and converted fronl a voltage to a
the total phase current. The C T output modulates the standard 4-20 mA current signal suitable for use
voltage-to-frequency converter 5 over a range of field with the station central logging computer. The field
currents from 0-6000 A DC. The signal carrying the voltage signal is similarly conditioned and buffered
current information is selected by a band-pass fiiter to protect the instrumentation from tile high voltages
20, dcmadulated and rectified to give field current induced in the rotor field following incidents, such
indication. as pole siipping. The currcnt and voltage signals are
subsequently processed to providc an average rotor
winding temperature measurement.
Blown fuse indicafio!! Continuous monitoring of the rotating diode equip-
Eight CTs (T9-T16) in each phase, identical lo those ment is considered unnecessary, given the proven
used for current measurement, are each loaded by a operational reliability of the equipment. This is the
transistor switch (TRSI-TRS8), shunted by a resistor simplest and most robust o f the described schemes
(K17-R24). The resistors are connected in series but t o monitor essential rotor quantities. It has the added
under normal operating conditions each one is shorted advantage that generator rotor RSO (recurrent surge
out by its associated transistor switch. The resistance oscilloscope) testing can bc carried out, a facility not
of the circuit is therefore low. If a fuse operates, available with equivalent telemetry schemes.
the associated transistor switches off and the circuit
resistance increases; further fuse failures result in fur-
ther increases in resistance. This arrangement is re- 6.2.5 Rotating rectifier p r o t e c t i o n
peated on each of the three phases and connected t o The main exciter is protected against the effect of
the summing unit 40 which, by supplying a current diode failure by the provision o f fusing, either on the
to each of the circuits, provides an output voltage AC or DC side of the rectifier. When a diode fails, it
proportional to tile number of blown fuses in each usually fails to s i ~ o i rcircuit, blowing the high rupture
phase. The output of the summing unit controls the capacity (HRC) fuse, which in tuin blows an ejector
output of the voltage-to-frequency converter. pin indicator fuse t o initiate an alarm. On the mark I
The blown fuse information is selected from the system, the pin is detected by a pllotoelcctric cell,
receiver carrier demodulator 17 by a band-pass filter and an alarm is raised in the control room. In contrast,
21. The signal is then recovered by the demodulator the mark 2 system can identify u p to nine individual
24. T h e output waveform for the circuit corresponds diode failures.
t o the number of blown fuses so the waveform is On the basis of the proven high operational reiia-
analysed to give the number of fuse failures. Phase bility of the rotating diodes, it is not now considered
identification is carried out by a strobe generator 30 necessary to continuously monitor the rotating system
which produces three separate pulses that coincide for failure. Present practice is t o examine the indica-
with tile centres of each positive phase current period. tor fuses o n an opportunity basis and during planned
maintenance overhauls.
Should a major fault occur, such that a complete
6.2.4 I n s t r u m e n t sliprings bridge arm is either short- or open-circuited, major
An alternative scheme is shown diagrammatically o n damage can be caused to the excitation system. T o
Fig 6.68 and uses shaft-mounted sliprings. Connec- protect the unit in the event of such a failure, it is
tions are taken from the exciter upshaft leads through CEGB practice to provide bridge arm failure prolec-
the shaft bore t o instrument sliprings mounted o n tion. This device initiates a turbine trir, o n detection
the permanent magnet generator shaft. These slip- of a failure.
rings permit direct measurement of field voltage. The The detector monitors the amount of ripple induced
rotor earth fault indicator relay is connected t o one in the main exciter field, which in a healthy rectifier
Tlie generator Chaptii~1 l.xcilation

ciatcrl \ ~ ~ i ttlic
h cxcilcr is ihc lpiincij>al cause of dciay, voitages iippeai across the ,cciiSiei in tlic l e i e i h c
its removal greatly improves the speed of cncilalion diseclioil, i t is CECH lpsaciicc lo use diodes with ;i
system response, enhaticirig generator transient stability peak invnse capability of 3 . 4 ~ 4 . k\',
2 illus providin~
margins. ample margin.
A feature o f all static excitation eqilipment is tlle T o protect the diodes against voilage spikes (caused
need for sliprings and brushgear which require regular by diodc commutalion effects and external s\+~itcbing),
maintenance. As this is cair-icd out on-load, an inter- each diode is provided wiih a dV/di suppression cir-
lock system is normally proi'ided so that access to cuit, consisting of a capacitor and series resistor. In
the slipring enclosure is prevented, unless a safety addition, each rectifier section has a resistor-capacitor
procedure has been followed. No further mention of suppression network connected across the DC output
sliprings or brushgear will be made here, as a detaiied to limit voltage transients coming from ihc DC side
account of the equipment is given in Section 3 of this o f the rectifier to within the peak transient voltage
chapter. rating of the diodes.
The rectifier diodes are easily damaged by ovcr-
currents and arc thcrcforc individually protected by
6.3.2 General description of s t a t i c diode rectifier high speed, high rupturing capacity fuses, with micro-
equipment switches for fuse failure indication. These fuses op-
A static rectifier system is an assembly o f diodes and erate for an internal fault ro isolate the faulty diodc
diode protective equipment. Typical 660 MW rectifiei- and allow conti~iuedoperation o f the ~.emainingdiodes
units consist of up to four self-contained, three-phase, in the arm. The ,nost severe fault experienced by the
full wave bridges. The number o f diodes per section are diode is a short-circuit on the DC side of the icctifier;
selected so that MCR requirements can be niet with one this is cleared by HRC fuse operation.
section out of commission. Each section is provided Overcurrents due to system faults or slipring fiash-
with AC and DC isolators, and an interlock system overs are ciearcd by DC cir,cuit-breaker operation.
ensures that, during on-load operation, access can be
gained to one section only.
Diode rating is based on the continuous and peak 6.3.4 S t a t i c thyristor rectifier s c h e m e s
inverse voltages, together with the current/time rating T h e thyristor has radically changed the role of static
on overload. A typical rectifier bridge has a number rectifier equipment, as it no longer plays a passive
of parallel paths per arm (the diodes being specially but an active role in tlle control o f generator excita-
selected to ensure satisfactory current sharing) with tion. One of the principal features o f this form of
one diode in each parallel path. excitatioll control is its very fast rate of response
To dissipate the heat generated during rectifica- due to the elimination of a main exciter. A typical
tion, the diodes are mounted on heat sinks. Cooling thyristor excitation scheme is shown on Fig 6.69.
is provided by either forced or natural air circula- Excitation power is generally taken from an excita-
tion and alarms are generally provided to warn op- tion transformer which is connected to the generator
erators of high temperature conditions which require output terminals. With this arrangement, the trans-
investigation. former primary voitage follows the generatoi terminal
is the sixtll harmonic of the exciter fundamental frc- excitation system. Early equipment contained diodes Busbars are used for the AC connections from the voltage during normal and fault conditions. Under
quency. This ripple is associated with the normal o f relatively low rating, where up to three diodes weir main exciter, and for the DC rectifier output to the fault conditions the excitation power transformer must
three-phase full wave rectification of the exciter ai- required in series to meet reverse voltage requiremenls generator field winding. The busbar system, like the be capable of meeting the field forcing requirements
mature voltage. Should a bridge arm fail (to either during pole slipping. This, together with a cautious exciters, is rated for 110% MCR and is capable o f at reduced terminal voltage, and of withstanding the
open- or short-circuit), a component of ripple at the design approach, resulted in high spare capacity. withstanding the mechanical forces arising from the overvoltage experienced following a load rejection.
exciter fundamental frequency appears in the exciter The rapid development o f semiconductor techno- worst overcurrent fault conditions. An alternative scheme, which is not subject to
field. This is detected by a band-pass filter tuned to logy has resulted in a reduced number of simpler, All rectifier equipments supplied to the CEGB must system voltage variations, is the compound source
the exciter fundamental frequency. Once the input is more compact devices, capable of operating at high meet the requirements of ~ ~ 4 4 1which7 covers both rectifier system. These static systems use both current
o f sufficient magnitude to overcome an internal bias voltage and current levels. Equipment of this type routine and type testing. and voltage sources (generator terminal quantities) to
signal, which is set to prevent spurious operation, a has a record of high reliability on the CEGB system, make up the excitation power source.
relay is energised which initiates a Category B unit and is currently in use on a number of 660 MW units. T o ensure integrity under 'black start' conditions,
trip. With the introduction o f the thyristor, the role o f 6.3.3 Rectifier protection however, a scheme based on shaft-mounted exciters is
the static rectifier has radically changed. The thyristor Diodes are susceptible to overcurrent, which causes a n attractive alternative. The exciter runs continuously
rectifier plays a n active role in the control of excita- excessive heating of the element, and to overvoltages at ceiling output with low power factor, providing
tion power t o the generator field. Like the diode, which can pierce the rectifying element and cause com- the thyristor converter with a constant voltage source
6.3 Static rectifier excitation equipment the thyristor conducts current in one direction only; plete breakdown. It is therefore essential for system o f excitation power.
however, unlike the diode, the point at which con- integrity that both the operating and ceiling voltages The thyristor rectifier unit is arranged in several
duction takes place can be controlled. are within the capacity of the diodes. isolatable sections so that any one section can be ser-
6.3.1 Introduction Excitation power modulation is achieved by con- During generator pole slipping o r asynchronous op- viced wllile the remaining sections provide full MCR
Excitation systems based on the static semiconductor trolling the thyristor firing angle, eliminating the need eration, the peak voltages appearing at the slipring excitation requirements. Thyristor free-wheel and pole-
diode bridge were the first alternatives to the DC for a main AC exciter. As the time constant asso- are about ZMX) V on a 660 MW machine. Since these slip crowbar circuits are generally included to protect
Excitatiori

GENERATOR F L U
VOLTAGE V,"

CURRENT IHYRISlOl(
CONTRO~. CONiROl
SIGNAI

SIGNAL
I

I,-F l E l D I I M t CCMSTANT
i,- SUPPRESSlON ?$MEFORAIHYRISTOR EXCITER
the thyristors from excessive overvoltages. Direct cur- to connect a number of thyristors in parallel. This I>-SLlPPRESSlON iiMC FOR AN AC RECIIFIER EXCITER
rent voltage transformers (DCVTs) trigger the crow- presents difficulties, since individual thyristors havt
bar into operatioll on detection of an oveivoitagc different forward path characteristics, causing one io
condition. Free-wheel thyristors provide a path for cotlducl the majority of current; if allowed to cori.
stored energy in the rotor during thyristor commu- tinue, this would cause breakdown. Forced curre,,!
tation and system fault conditions. The pole-slip crowbar sharing, by the addition of a low value resistance 01
provides a path for the induced reverse direction poie- inductance in series with each anode, is llor~nallyuscd 6.4 The v o l t a g e r e g u l a t o r erators and continue to provide reliable operation.
slip current, so avoiding excessive pole-slip voltage to obviate this. The rapid developments in the field of semiconduc-
developing across the rotor terminals. Thyristor cooling is provided by a natural or forced tor technology brought about the introduction of the
The DC output Of the thyristor rectifier is provided air scheme. Temperature detectors mounted within the 6.4.1 Historical review transistor amplifier and the thyristor output ampli-
with voltage and current surge suppression circuits air circuit provide early warning of high temperature fier, which have increased the speed of response and
Early designs . of voltage regulator equipment had a
which are designed to protect the thyristor from volt- conditions, aliowing appropriate operator action to be improved the overall system performance. Subsequent-
large deadband, were slow to respond to system changes
age spikes generated during thyristor commutation or taken. On future large plant, the higher current ratings ly, the discrete compone~ttaperational amplifier has
and required regular maintenance. This was due main-
field circuit-breaker operation. In addition, individual and associated losses may make it necessary to use been replaced by integrated circuit equivalents. A
ly to the use of moving mechanical components within
thyristors are protected against dV/dt breakdown by water cooled thyristor equipment. typical modern dual channel arrangement is shown
the automatic voltage regulator (AVR). T o eliminate
a capacitor-resistor suppression circuit connected in Thyristor excitation systems can improve the steady on Fig 6.71.
these difficulties, AVR systems were developed which
parallel (identical to the circuit used to protect diodes). state and transient stability limits considerably because Future developments in the field of AVR design will
made use of the cross-field generator or amplidyne.
Overcurrent protection is provided by a series-connected of their ability to change the generator field voltage centre around the use of digital microprocessor tech-
The amplidyne was used as the regulator output stage
HRC fuse. In the event of an individual thyristor almost instantaneously. They are therefore finding gen- niques. These discrete time controllers offer a number
and controlled the field of the DC exciter.
drawing excessive current the series fuse will rupture, eral application on generating plant which is connected of potential advantages, most notably the introduction
The amplidyni and DC exciter were, in turn, super-
electing a striker pin which initiates an alarm. Over- to the periphery of the main transmission system, of adaptive control strategies.
seded by the magnetic amplifier and AC exciter. In
current excursions are normally controlled by the AVR
to within tile rotor heating limit; however, in the
where the inversion mode of operation, in which the
field current is rapidly reduced by the reversal of
....- - -....~
+hi? ., the
~~~. ~ -
magnetic am~lifierwas used as the
regulator output stage controlling the main exciter
event of a prolonged overcurrent condition, the ex- energy flow, is exploited to the full. The rapid field 6.4.2 S y s t e m description
field. The output from the exciter was rectified by a
citation is tripped through the field circuit-breaker. suppression achieved following isolation from the sys- The AVR is an essential part of the operation of a
diode bridge and taken, via slipring connections, to
To meet the high current requirements of large tem under load rejection or fault conditions is illus- modern electrical power system. It is at the heart of
the generator field winding. Schemes of this type were
turbine-generator excitation systems, it is necessary trated on Fig 6.70. the excitation control systems around which the re-
successfully employed on all the CEGB 500 MW gen-
The generator (;l?a~>~t.t
I,
-. .... .

being coii~paiedusill, thc i-cfercocc voltage. Piovisioll iiiiiial voltage and, if it exceeds a sale lcvci (nari~lail?
is made foi tl,e operalor to change tire iefeieirce 1.3 pu), the thyristor coii\,ertes is imn~ediatelyswilchcd
\,oltafe in iesilo1ise lo syslem reqilirements. into the inverting rnadc, which reduces llie lield ciiw
1x1 addition lo llic basic voltage co~itrai require- rent in minimum timc. This relay is oillp active dori~i~!
mcnt, the AVR includes control loops which perform unsynchionised operation.
other vital tasks. These controllers, which include the The ovel.fluxing relay is also only active during oil.
MVAr limiter and overfluxing limiter. are discussed synchronised operation, when there is a chance that
in detail in Section 6.5 of this chapter. the geoel.ator transformei. could be overfluxed if the
safe voltage/frequency ratio is exceeded. A special
relay detects this condition and initiates an alarm.
6.4.4 A u t o follow-up circuit Control loops within the AVR will act to reduce this
With a dual channel design, both regulator channels to a safe level but, if the condition persists, the thy-
can be active at the same time, each providing half ristor converter is switched to the inverting mode and
the total generator excitation requirements. An alter- the excitation is tripped.
native arrangement allows for one channel to be active, Most faults within the regulator loop give rise to
whilst the other follows passively. Should a channel cithei an over or under excitation condition. There-
trip in either scheme, then the other picks up the fore comparator circuits are used to monitor reglllator
full excitation requirement of the generator in a and converter bridge input and output levels. Alter-
'bumpless' manner. This is achieved using follow-up natively, a singlc comparator monitors the thyristor
circuits which track the primary (or active) channel output current and compares it with maximum and
and drive the standby channel output while a dif- minimum field current limits allowed. Transiently, these
ference exists between the two. limits are exceeded during system faults, but the chan-
nel is tripped if thc condition persists beyond a few
seconds.
6.4.5 Manual follow-up
This is similar to the auto follow-up but is used to
adjust the manual control system in response to 6.4.8 Thyristor converter protection
automatic channel changes. In the event of an AVR In addition to the above, AVR channels are tripped
1 . EXCITAT8ON
OYSRFLUX
failure, the manual control takes over in a smooth if any of the indicator fuses protecting the converter
TRIP8 ALARM
TOTAL CURRENT bumpless manner. thyristors rupture. The thyristor converter is further
protected by a temperature sensing device which Op-
erates in the event of excessive heating.
PIC. 6.71 Dual clialliicl AVR 6.4.6 Balance m e t e r
A balanCe meter is provided in the power station
control room and in the AVR cubicle. This monitors 6.4.9 Fuse failure detection unit
the difference between the automatic and manual The regulator relies upon a signal from the generator
maining equipment operates. The central function of terminal voltage also changes, increasing the error sij, control output settings. During automatic control, the voltage transformers for its controlling action. Loss
the AVR is to maintain constant generator terminal nai. The error is amplified by the regulator and osr.,i follow-up circuits ensure this error is minimal, whereas o f the signal is due in general to failure of the fuses
voltage under conditions of changing load. There are, to increase or reduce excitation, as necessary, to brini during manual control no such facility exists to adjust in the voltage transformers. A fuse failure detector
however, a number of other functions which are the voltage back to its original value. The need for ;i the AVR, and a large discrepancy can therefore exist. unit monitors the input to each channel and compares
required from the AVR, if a large generator is to rapid, stable response following such changes is ol During manual operation and prior to selection of it with that of a check or reference transformer. If
operate satisfactorily under all operational conditions. paramount importance and, since control systems i l k . AVR control, the balance meter is consulted and an a fuse fails in the voltage transformer supplying the
The CEGB currently specifies dual channel AVR ing such high steady state gains would rapidly becotnr adjustment is made so as to avoid large MVAr dis- reset voltage, the channel is tripped; a fuse failure
equipment complying fully with EES 1980 together with unstable, special signal conditioning networks are in. turbances following control changeover. in the reference transformer initiates a n alarm.
manual back-up control on all 660 MW plant. This cluded. These consist of phase advance and phasc
provides maximum reliability as the loss of one chan- lag circuits which have adjustable time constants a!.
nel does not inhibit operational performance. Facilities lowing accurate tuning of the voltage response. To. 6.4.7 AVR protection 6.4.10 T h e digital AVR
are provided to repair the faulty channel while the gether, these circuits act as a notched filter, reducinf: The AVR plays a vital role in the unit overall pro- The rapid development o f the microprocessor has
generator remains in service. On small gas turbine gain at generator electromechanical oscillation frequer).. tection scheme, as it controls suppression o f the gen- brought about the increased use of digital electronic
plant, single channel AVR equipment is specified. cies, whilst permitting the high gains necessary foi erator field after faults. In addition, it is necessary techniques in a number of industrial control appli-
accurate voltage control. The setting of the time c o n to protect against AVK component failure which would cations. While the present generation of solid state
stants is of great importance, as transmission systern otherwise jeopardise generator operation. AVRs meet all existing CEGB functional requirements,
6.4.3 T h e regulator dynamic stability is sensitive to AVR settings. For The field suppression circuit accepts signals from there are advantages to be gained if microprocessor
The AVR is a closed loop controller which uses a this reason, sophisticated analytical techniques (sec the main unit overall protection scheme, in addition schemes are considered.
signal proportional to the generator terminal voltage Section 6.7 of this chapter) have been developed and to signals from the overvoltage and transformer over- High reliability, which has been a feature of pre-
and compares it with a steady voltage reference. The applied in order to obtain optimal performance. fluxing relays. The circuit switches the AVR thyristor sent AVR equipment, can be expected to improve
difference or error voltage obtained is then used to The AVR accepts the generator terminal voltage converters to their inversion mode of operation and still further due to the reduction in the number of
control the exciter output. signal via its own interposing voltage transformer. then trips the excitation. components, since much of the control logic, at pre-
If the load on the generator changes, the generator The voltage signal is then rectified and filtered before The overvoltage relay monitors the generator ter- sent carried out by electromechanical relays, will be
T h e generator Excitatioti
Cl~ailti!t i
.
software s~)ecificd.Cosl advantages are also envisaged 6.5 Excitation control llii~.iagsysleiu lauli conditions, the AVll reacts to at one end or a tsanso~issionlinc osciilate willi iesilect
us standard memory circi~itsreplace the present cus- In addition to tlic basic voltage contrili loop, ~ ~ I o c I ~ I , ! boos1 excitation; normaily this siloation lasts only to ti~oscat the olilei end. TIlese oscillalions, knowti
tomised printed circuit boa1.d~.I-lowevei, the principai exciiation eqoi~)rnenlincludes a number of ail<Iiixi,!ijii ~nilliseconds beforc cil.cuit-breaker operation clears as power s.vste,,i osci//aiioris, are load dependent and,
moti\~ationlies i n tile iangc of sophisticated control- ii~iiitel.circuits. Tilesc li~nitersopcrste as parallel i , i i t the fauit. I-lowever, it is necessary to ailow for tile if not prevented, severely linlit the MW transfer across
ler designs tliat lhc iuicroprocessor makes physicaliy trollcis, in that their signals replace the genci:it~li longest back-up protection clearance times and hence a the transmission system, To obtain a solution to this
realisable. One class of controller is the adaptive voitagc as the controlled variable whenever tliosi ill dciay of up to 5 s is specified. After this delay, the problem, an understanding o f ihc basic lmachine lor-
regulator, which (as the naine suggests) is capable of pill signals exceed predefined limits. que relationships is necessary.
rotor currciit iimit ci~.cuit generates a signal which
adjusting its structure to take account of changing For a generator to remain in synclironism following
opposes that from the AVR and ramps excitation
plant conditions. This type of regulator, shown sche- system faults, it must produce a braking torque to
6.5.1 Rotor c u r r e n t limiter current back to a safe value.
matically on Fig 6.72, consists of a recursive real- balance the accelerating torques introduced by changes
time parameter estimator (based on s form of least All exciters are capable of supplying generator lirkl
current well in excess of that I.equired for noriiti,i to the eiectrical transmission system. The braking tor-
squares structure) which is used to identify the con- 6.5.2 MVAr limiter que can be separated into two components:
trolled plant. The estimated plant model is then used MCR opeiation. This field forcing capability or 111;ii
gin is necessary during system fault conditions, ~ , I , r i , , Modern AVR equipment is capable of controliing
by the regillator to form the control law. A wide generator operation at rotor angles of 130' to 140'. e The synchronous lurque, which is in-phase with
the additional reactive power provides the much aeedril rotor angie changes and is necessary to ensure res-
choice of regulator/control law designs exists; typicai This mode of operation is not, however, tenable when
boost of synchronous torque. However, this ciirrr~~t toration of rotor angle following displacements.
strategies include poie placement and minimum var- transient stability criteria are taken into account; it is
must be restricted in duration because o f the diinfrr!
iance. Botll have a very flexible structure, making it therefore customary to limit the generator operation
of overheating the generator rotor which would c;!tisi The damping torque component, which is in-phase
a simple matter to include additional input signals, to a rotor angle of 75'.
insulation system degradation. To prevent overhr,it with rotor speed changes and provides damping of
such as machine accelerating power (which has been in&, the exciter field current signal is applied to i l l < The permissible leading MVAr varies with the square
demonstrated to enhance transmission system dyna- rotor oscillations.
rotor current limit circuit which detects values ( , I of the generator terminal voltage, the limit line being
mic performance), and post-fault recovcry. field current in excess of 110% MCR. defined by the following equation:
Where generating units are connected to the grid over
MVAr .+ MW = V2 high reactance tie lines, fast response excitation sys-
tems are vital to maintain system transient stability.
This has the effect, however, of reducing the inherent
CONVENTIONAL
SPEEDGOVERNOR generator damping torque; consequently, under cer-
The in-phase and quadrature components of stator tain load conditions, generator rotor swings following
current are obtained from a form of phase sensitive system changes will have little damping.
rectifier. Tile signals are then compared with the As the component of torque in question is strongiy
generator terminal voltage bias and, if the iimit set- associated with rotor speed, a logical starting point
GOVERNOR
VALVE REF
I t POWER
ting is exceeded, an output is generated which acts to
boost excitation and reduce rotor angle.
for investigation is the generator torque speed loop
shown in Fig 6.73 (a).
The introduction of a n AVR, while enhancing syn-
iURBiNE
GENERATOR
GENERATOR
OUTPUT
chronising torque, has a deleterious effect on the small
6.5.3 Overfluxing limit inherent generator damping torque (the latter is ob-
VOLTAGE
In addition to the overfluxing protection circuit, mod- tained by means of poleface windings or induced eddy
ern AVR equipment includes overfluxing limiter cir- current effects). This presents some difficulty, as from
cuits. This is a closed loop controller which monitors considerations of transient stabiiity a fast response
the voltage/frequency ratio during unsynchronised op- high gain excitation system is necessary, however, its
implementation could result in reduced power system

I ANALOGUE To
DIGiiAi
CONVERTER I eration. Should a predefined ratio be exceeded, the
limiter generates a signal which acts to reduce ex-
citation and thereby prevent generator transformer
damping and a consequential reduction in load trans-
fer capability.
T o counteract this, a device known as a power
overfluxing.
system stabiliser (PSS) has been developed. Figure
6.73 (b) shows the addition of such a device to the
RECURSlYE 6.5.4 S p e e d reference controller torque dpeed loop. A signal derived (in this case) from
PARAMETER shaft speed is used as the input to the stabiliser; this
ESTlMAIiOR COMPARaTOR In accordance with current CEGB functional require-
ments, this feature controls the application of excita- is then orocessed and conditioned to provide sufficient
tion during the turbine run-up sequence. This limiter phase lead to compensate for the phase lags inherent

I PARAMETER

CONTROLLER
unit ensures that voltage is brought up to nominal and
the unit synchronised with the minimum delay.
in the generator plant and transmission system. The
output of the stabiliser is superimposed onto the AVR
demand signal in order that an increased damping
torque component is produced.
OPTjMkL WITH ADAPTIVE A comprehensive linearised generator and power sys-
CONiROL
SBNAI. 6.6 The power system stabiliser tem stabliser representation is shown on Fig 6.73 (c),
where it can be seen that the PSS signal is fed to the
block denoted as GEP. This represents the generator,
6.6.1 Basic c o n c e p t s exciter and power system, detailed knowledge of which
FIG. 6.72 Block diasram or adaptive exci~ationcontroller
Situations have occurred where groups of generators is vital if the PSS is to compensate for the phase
526 527
Excitation

lag within <;El' arid piodocc a component of geo- if uncoriecled, will result in prolonged rotor swings
clator tosquc in phase with speed changes. This in- in lllc region Of 0 . 9 - i . 6 14%.
formation can be obtained in a variety of ways, nota-
bly by on-load frequency response analysis, using puise Infra-plant ~iiodes
injection techniques and by computer simulatioil tecli- Intra-plant modes of oscillation occur between units
oiqoes based on representative system models. within the same power station. Unlike the above,
these are not power transfer dependent but rcsult from
interaction between generator excitation systems. If
6.6.2 Characteristics of GEP
action is not taken, intra-plant interactions will limit
Extensive system investigations are used to establish the available PSS gain and hence its effectiveness.
the characteristics of GEP. Ail operating modes o f
the plant arc examined to identify the conditions
under which stability is marginal. In general, operation 6.6.4 Principles of PSS operation
at leading power factor during times of low system PSS action is inhibited during steady state trans-
AND demand are the most critical. However, in the case of mission system conditions, as it has a detrimental
EXC1TER
pumped-storage plant, which will generally be opeiat- effect on voltage control. A steady state voltage offset
7 ing in the pumping mode during these periods, the is prevented by the use o f a washout circuit at the
situation can bc more critical because of the large PSS input. The washout circuit, shown on the PSS
machine rotor angle with respect to the rest of the block diagram on Fig 6.74, is essentially a differen-
system. tiating circuit which attenuates low frequency changes.
A series of simulation studies is then conducted, The time constant of the circuit, Tw, is chosen to
using detailed plant representation (including the AVR washout low frequencies but not to interfere with
. ....,
. .. and PSS), the results being assessed by the analytical the signal conditioning networks at system electro-
- .... . , ,. , . . . ,
.- ....
. . I > I . .
~,.,..,
.. . - ,. . e.:., , . ...,, . . ,,.."..'.
., techniques described in Section 6.7 of this chapter. mechanical frequencies.
I. I .
.I,
/ ;
. F
(..
/
, ,..
9
,-,<
:
'
I,..
,.',..,,*
.,.,,,
;-,,
The model PSS settings are adjusted until optimum The signal conditioning network provides the phase
excitation performance is achieved at all critical op- compensation, so that a torque is produced it, phase
erating conditions. These settings are then used as a
basis for plant commissioning tests, thereby reducing
with sneed changes.- This network essentially shapes
the PSS characteristic to provide the best damping
expensive on-site testing. oerformance at all electromechanical modes. Generally
this is achieved by maximising stabiliser gain (within
the constraints imposed by the power system control
6.6.3 S y s t e m m o d e s of oscillation
loop) and shaping the phase characteristic so that it
Examination of the basic torque-speed-angle loop in has a slightly lagging value at the particular inter-
Fig 6.73 'yields W,, (natural frequency o f electro- area oscillation frequencies o f concern. T o prevent the
mechanical oscillations) = \/(u,Ki,/M) rad/s. For intra-plant interaction, tuning should ensure that the
typical values of machine inertia (M) and synchron- overall phasc characteristic is not greater than 90"
ising torque coefficients (Ki,), the frequency range of lagging at frequencies up to 4.0 Hz.
interest is 0.2-4.0 Hz. Within this frequency range, It is important to ernphasisc that PSS action is
the oscillatory modes can be broadly divided into intended to improve the system damping following
three main components. small disturbances. PSS action following system faults
will degrade AVR performance, and hence system
Infer-area or infer-lie osciliafions recovery; therefore, the stabiliser output is limited, so
Inter-area oscillations range typically from 0.2-0.6 Hz that AVR action is dominant during the first post-
and occur where two generation groups are connected fault cycles.
by a weak tie line; they tend to be power transfer
dependent. Inadequate damping of these modes will 6.6.5 T h e c h o i c e of stabiliser signal
result in operational difficulties, since power transfer
A n obvious choice for the stabiliser input signal is
capability is reduced. These low frequency inter-tie
rotor shaft speed, measurements being generally made
oscillations have been initiated by random events oc-
at the H P turbine pedestal. The drawback with this
2urrLng d ~ r w gperlod5 of h ~ g h\I\\' trdn,icr o\cr ae3L
form of signal is its inherent susceptibility to shaft
trxlilnlrrlun l i u k i and or unu,oal load d~btribution.
torsional frequencies. This term refers to the reso-

.-------
i
iC1
OErEf-A'OeEXc~TER
COMPREHENSlYE LINEARISE0
SYSTEM iGEPl_ _ _ _ _ - 2

GENERATORiiND POWER SYSTEM STABIIISBR


II Local mode oscillafions
These occur where a single generator is exporting
power over a high reactance transmission link. In
nance conditions on the shaft line which cause one
section of shaft to oscillate with respect to another
with little natural damping. These frequences act
through the PSS and excitation system to set up elec-
these situations the need for static thyristor excitation tromechanical torques which tend to aggravate the
FIG.6.73 Simplified torque-speed loop diagrams systems (because of transient stability requirements) situation and, in the extreme, to cause shaft damage.
aggravates the problem of steady state stability which, T o eliminate this potential problem, detailed infor-
528
529
Tile generator Chai>t<:gI , Excitation
...

craloi- to the systeor increases, the synchronous tor- oscillatory respoiise. It is possible lo simplif), llie
que component is reduced. Under these circumstaoccs, inteiprctation of the roo1 locus diagram by considei-
thc AVR bucks and/or boosts lhc generator field ing those poles which lic furtliest to llie right as
current in such a way that the generator itself develops dominating the syslenl res1)onse.
the additional synchranising torque. 'This approach is extended to rile n>ultivasiablc situ-
A properly tuned AVR tlierefoie performs a vital ation by making use of modern state variable theory.
role in the maintcnancc of stable system operation The system considered is first linearised about the
under all operating conditions, and this section is operating point of interest and the equations o f stale
concerned with the methods developed and employed formed.
to analyse AVR performance, and hence to arrive at
tuned settings. X = AX + CV Input equation
Y = DX + FV Output equation
6.7.1 Frequency r e s p o n s e analysis
Frequency response analysis is based on the injection where X is the vector of stare variables, Y is the
of a sinusoidal signal at the input to the AVR and vector of output variables, A is the state matrix and
thc corresponding measurement of generator terminal C,D,F arc the feedback, input and output matrices,
voltagc magnitude and phase shift. This procedure is respectively.
repeated over the range of frequencies necessary to A series of simulations is conducted over the com-
identify the plant, which in the case of the generator plete generatox operating regime, using a detailed
ERROR excitation system is 0.2-4.0 Hz. Results are plotted model of tlie turbine-generator and excitation sys-
in the form o f inverse Nyquist or Bode diagrams, from tem. The dominant poles (or equation solutions) are
which information on system stability and damping plotted for a range of control settings, and those idcn-
can be obtained. These tests call be repeated for a tified as providing optimal damping at the most critical
REFERENCE VOLTAGE
range of AVR settings until an acceptable system operating condition are selected for commissioning
response is established. Performance indices used in purposes. This method of analysis therefore provides
GENEHATOR TERMINAL
VOlTACIE this form of analysis are system gain and phase mar- advanced information regarding equipment settings
gins, both of which are measures of relative stability. and plant performance, thus reducing expensive com-
In general, a phase margin of 40' or more, and a missioning time.
gain margin of 6 decibels is considered good design
FIG.6.74 Power syslern rtabiliser - black diagram practice for most feedback control systems.
An alternative approach is the injection into the 6.7.3 Large signal performance investigations
AVR summing junction o f a short duration iectan- The foregoing methods are based on the response of
gular pulse. The corresponding machine terminal volt- the excitation system l o small signals; hence non-
mation is required of the shaft torsional conditions 6.7 Excitation system analysis age response is measured and harmonically analysed linearities can be ignored and the system assumed to
so that, if possible, speed probes can be mounted at Trends in modern generator design, with the cmpha- by a computer, using a fast Fourier transform pack- bc linear.
a torsional node and suitable torsional filtering can sis on large thermally-efficient but electrically-remote age. The results are then plotted in the form of an It is equally important, however, to investigate the
be applied.
centres o f generation, have combined to reduce trans- inverse Nyquist diagram from which measurements perforinancc of the turbine-generator plant following
Because of these considerations, use is made Of a
mission system stability margins. As a consequence, can be made of relative stability and damping. This substantial changes in operating conditions. In these
signal derived from generator electrical power which the primary responsiblity for power system dynamic approach has a number of distinct advantages, par- situations the non-linear characteristics of the plant
is related to shaft speed by the following relationship: and transient stability rests with the generator excita- ticularly during on-load testing as, unlike variable must be taken into account to obtain realistic results.
tion system. frequency techniques, pulse injection testing can be These large signal performance investigations pro-
1
Au = -
M
j (P, - P,)dt (6.1) oscillations. without the risk of exciting power system
undertaken vide a means of evaluating excitation system response
following a major transmission system disruption (gen-
Dynamic sfabilify refers to the system performance
following small load changes which, under conditions erally a three-phase fault at the generator transformer
where w is shaft speed change, P., is mechanical of high MW transfer over long distances, can result in high voltage terminals is used for standard studies
input power, P, is machine electrical Power and M is sustained oscillations in the region of 0.5 Hz. If these 6.7.2 S t a t e variable analysis -
and investiaations), . which could jeopardise system
~

the angular momentum. If the mechanical Power is oscillations are not rapidly attenuated, severe limits A common method used to assess the performance transient stability.
assumed to remain constant, Equation (6.1) is sim- and stability of feedback control systems is to track Transient stability analysis is primarily concerned
will be imposed on transmission system operation.
plifled to: the path taken by the roots or poles of the closed with the effect of transmission line faults on genera-
loop transfer function. Changes in system parameters, tor synchronism. While certain simplistic approaches
Transient sfabilily is concerned with the ability o f a
A* = - -I Pcdt (6.2) generator o r group of generators to maintain syn-
such as gain and time constants, cause these poles exist dealing with the case of a single machine operating
M to move. The path taken by the poles in response onto an infinite bus (such as the equal area stability
chronous operation following system faults. Under to control system changes can be plotted and are criteria), a full multi-machine solution is generally
such operating conditions, the generator requires a known as a roof locus. Referring to Fig 6.75 any necessary requiring the use of digital computer slmula-
The major advantage of this form of stabilising signal boost of synchronous torque. This is provided by the roots appearing on the right hand side of the S-plane tion techniques. These simulation packages represent
Is its insensitivity to torsional oscillations and the transmission system in the form of a synchronous imply an unstable system. Roots on the real axis in- in detail the generator, transmission and excitation
simplicity of measurement. Its adoption, therefore,
has both technical and cost advantages.
comDonent of the oost-fault infeed. However. as
~ ~~.~~-the
.~~. dicate a n exponential o r overdamped response, and systems, and solve the governing non-linear differen-
reactance of the transmission line connecting the gen- roots containing a n imaginary component imply a n tial equations by numerical integration.
levels ;arc monitored at all liic beai.ing ihoosings and
at ,he shiifis adjacent to lbc generator bearings duti~i?,
iliii-tip.

7.2 Open-circuit conditions and


synchronising
Generators are usually operated at or near their fated
voltage, any departure demanded by the translnission
system being accommodated by the tiansforlncr tap-
changer. A generatol- voltage range of i S % is speci-
fied. For the same MVA output, a higher voltage
results in greater losses and temperatures in the cove
but lower current in the stator winding, so the overall
thermal conditions are not much changed.
Since these ia1.g~generators are invariably connected
to the grid through generatoi transformers, the rated

@
voltage of the generator can be deteinlined by the
manufacturer to give the most economic design. Once
FULI.
MAGNITUDE the first of a new rating has been decided, a degree LOAD
of standardisation is imposed to allow generator trans-
former units to be made interchangeable, 22 kV being ROTORCURRENT

standard for 5W M W units and 23.5 kV for 660 MW


units, on the CEGB's system.
The electrical phasor diagram for this excited, open-
... circuit condition is shown in Fig 6.7, though, at this
stage, the machine is not running synchronously with
the transmission system. ference voltage would cause a large current to circulate
I'ic. 6.75 S-plane stlowing porrible root iocaiions with corresponding time response The open-circuit characteristic wili have been es- from the system through the stator windings, causing
tablished during running tests in the manufacturer's high forces in the windings. If the frequencies were
works. The rotor currents for several values of stator significantly different, the sudden pulling into syn-
voltage are measured and plotted (Pig 6.76). The chronism would impose a large torque on the rotors.
The ability to simuiate these situations is essential the windings arc not colder than their ambient by^ relationship is virtually linear (the ai~aop/in?) ,up to A back-up check synchronising device inhibits tile
to tlle CPGB, because generator excitation system drogen. Cooiirig water to the hydrogen, distilled watcr, cilcuit-breaker from closing if the voltages, angular
about 75% rated voltage, demonstrating that the air-
performar~ceunder system fault conditions cannot be winding water, seal oil and excitation heat excilangel* positions and speeds do not match within predeter-
gap reluctance is constant, whereas the iron circuits
demonstrated by test methods, due to tlie potential is established. The lubricating oil system (commojl mined tolerances.
depart markedly from constant reluctance as the flux
risk Lo syitem stability. with the turbine) must also be operating, and also ti,? Once synchronised, the speed is effectively con-
density increases above the point at which saturation
jacking oil systeln if the shaft is at standstill. starts to occur. After a long shutdowll, it is reas- trolled by the transmission system and the steam ad-
The run-up cycle is primarily determined by the suring to check a few points on tile open-circuit mitted to the turbine produces just sufficient power
requirements of the steam turbine, and may be under characteristic with the unit on manual excitation. Note to overcome the mechanical and magnetisation losses.
7 Generator operation the control of an automatic run-up system. 11 is ad- that direct measurement of rotor current is not possi-
In this section, the operation of the generator under visable to pass through the first and second criticai ble on brushiess machines.
aii common conditions is considered. Elect2ical and speeds of the generator rotor (roughly, 800 and 2200 Synchronising is effected either manually or by
other Parameters are introduced as necessary in order r/min) quickly to avoid subjecting the bearings to means of an automatic synchroniser. The speed of 7.3 The application of load
to describe the condition. the increased vibration amvlitudes which mav ~~~.~occnl. If the voltages and angular positions match exactly,
~~
the unit is adjusted by controlling the speed governor
at these speeds (see Fig 6 . 2 j ) . -
until the generated frequency
.
~
closely matches the no current flows in the windings and no electrical
As the rated speed is approached, excitation may be system frequency. The generator voltage is adjusted torque is produced. In order to generate load, an
automatically applied by the voltage regulator (or this by the setpoint of the voltage regulator until it closely imbalance in the phasors must be created.
7.1 Running-up to speed may be manually applied) by closing the exciter and The turbine steam inlet valves are therefore gradu-
equals the v ~ i t a g eo f the system, as monitored by a
Before running-up to speed, the casing and other main field switches. The resulting voltage will be pre- ally opened further; the extra torque thus produced
voltage transformer with the same ratio as the
components wili have been scavenged o f air and filled vented, by a voitage/frequency control device, from starts to accelerate the rotors so that they move for-
generator transformer, or directly where a low voit-
with hydrogen to a pressure approaching tile rated. being greater than would maintain rated voltage/fre- ward relative to their no-load (direct axis) position,
age switch is used. The main circuit-breaker is closed
Hgdrogen pressure increases with increasing tempera- quency, s o as to prevent overfluxirlg o f the generator though still in synchronism with the system. The volt-
when the two voltage phasors are almost coincident,
ture and tlle objective is to achieve rated pressure transformer. At rated speed, rated voltage should be and the generator will then pull into and remain in aye phasor difference created by this angular change
when on steady load. The seal oil system must be generated, with the machine on open-circuit, unless results in current circulating from the system through
synchronism with the system. If the voltage phasors
operating in order to contain the hydrogen. The stator some other voltage condition is required. Speed is the stator windings, producing an electrical torque
were significantly different in magnitude or angular
winding water system is established, taking care that under the control of the turbine governor. Vibration which balances the increased mechanical torque, re-
position when the clrcuit-breaker Is closed, the dif-
533
The gellerator
--
suiting in a i l c w state o f sy~icliioooiiscquiiib~iiimat scale of ;i i,ecloi inrtct, across wllicll cliisois ti-ai'ei
/Xd (or sliicliy llated I\I\'A/Xq u,l,el-c X q is
h 'load aiigle' (scc aiso S C C ~ ~2.6 O I Iof this cl~apier). uadrature axis synclironaus reactance), determines parallcl to ilie ;lacs, rejiicseiitiiig p.eiiciatcd M\4' and
U e c a ~ i etlie pciicrated ioltiigc cSSectivciy dcpaids MVAr, the apciating point beiiig where tiic cuisors
ilicoretical limit of stability. The practical values
on the sytcnr voltage and thc load being gcneiated, SX;,,~, ,< inlei-sect. I'ei-missible o"crating arcas arc indicated
1c;idiiig reactive outputs, allou,ing a margin for
aclion by thc voltage ieguiatol' caiunot changc tlic ,P?
with diffeienl typcs of excitation control on the instiurnenl
geneidled voilage directly. Ilowevcr, if ihc rotor cur- n 5 of this chapter), can be plotted on a It can be seen that tile capability ciiart is ailother
8,:
rent is cha~igcd,the phase relation between the gen- s diagram. The exanlple shown in Fig 6.78 manifestation o f the generator pbasor diagrain. Op-
erated voltage and ciirrenl is changed, and tile required instantaneous increases in MW of 4% at eration at rated load and about 0.95 power factor
power factor can be maintained by voltage iegulaior ii~ledload and 10% at zero load. leading is possible, thoogb rarely required.
action. These processes o f conrl-oi of gcneiated load
and power factor continue to meet the requirements
of the transmission system, as long as the unit remains
synchronised. Phasol. diagrams for various on-load
conditions are showii in Figs 6.8 and 6.9. lu &, 6s

1.i ur!ia~81eill~~squ,,b,,un,
lit
Capability chart
capability chart is a MW-MVAr diagram, for
Iiicl, the limits of leading MVAi were discussed
7.6 Steady short-circuit conditions, short-
circuit ratio
Anothcr relationship that is established during works
testing, is between the field current and the stator
A constant MW limit can bc drawn at the rated current with the three stator line terminals short-
7.4 Steady state stability "2 ~!o!r,cl- output of the turbine, though the maximum circuited (Fig 6.79). In this condition, the voltage re-
The power produced by a synchronised generatol. can Ixtnvcl. capability of the steam system may be signi- quired to ci~.culate,say, rated current through the wind-
be expressed as (VE sin b)/(Xd). For a given machine, lil.;$nlly greater than this. The circular locus of rated ings is very low ( = XE, say 0.15 per unit) and there-
operating at a terlllinal voltage V, the syncllronous rt;ilor current cuts the rated MW line at the rated fore the flux is also very low and conditions are lin-
reactance Xd is a conslant parameter, and if tbc hd\'A and powcr factor point, but does not in prac- ear, since there is no magnetic saturation. Most of the
'internal voltage' E, or rotor current, is kept constant, 1ii.i. impose a limit. The rated rotor current, also a considerable magneto motive force (MMF) produced
power varies as sin 6. At rated conditions, 6 is about ciicolai locus but with its origin at the 0 M'h', by the rotor is required t o counteract the armature
45-55O. liiitcd MVA/Xq MVAr point, imposes a limit at con- reaction MMF produccd by the stator winding.
From this position, a sudden increase in steam clilions of MW and laeginp.- . .power factor both lower Kunning under these conditions in order to cir-

\
throughput, or (more likely) a sudden demand for 111an rated. Such a capability chart is used as the culate current through the windings to dry out the
more power into the system, perhaps because of a
fault on the lines, results in a n increase in 6 and in
generated power until a new equilibrium position is
RATED STATOR
reached (Fig 6.77 (a)). CURRENT
This is valid if b is less than 90' before the sudden
change. Once 6 is greater than YO", a demand fol.
more power cannot be met by an increase in load
angle, and the generator rotors cannot attain a posi-
tlon o f equilibrium (Fig 6.77 (b)). The rotor then
accelerates to just above synchronous speed and 01)-
erates in a non-synchronous mode ('pole slipping'),
with large power and voltage oscillations which are
unacceptable to either the transmission system or the
boiler controls. The situation may be relrievable il.
the voltage regulator can initiate a rapid increase in
the field current, increasing E in the equation, to
prevent instability (Fig 6.77 (c)).
Load angles approaching 90' are associated with
operation at leading power factor, which is not a
normal requirement in the UK. However, studies of
the transmission system under ail credible conditions AOTOIIANGLE 8
of loading, line outages and faults are carried out to iiiMsinlalning rlsbibYinrcoas#ngoic~~aiol,

ensure that the system will not fall into instability,


and the required values of synchronous reactance
and excitation response are based on these studies, FIG. 6.77 Steady state stability
which may recommend different values in different ....-... @.
4
~ ~~ ~~~

locations. In practice, because of magnetic saturation, *s I--RilNoEoFMvARFoRS~NcHRoNouscoMPENsm~oN


Xd is reduced as the load angle moves towards 90°, unit in the quadrature axis. MMR
the 'quadrature axis' position, so that the limiting Operation at leading power factors reqi
condition is ameliorated slightly. Values for CEGB duced rotor current. Operation with zero rotor
machines are about 1.8 per unit, falling to 1.7 per at zero MW, and a leading reactive outpul = KISI Flc. 6.78 Capability chart
Geiieiaroi operation
C l ~ a p i i !I .

(Note Ilia1 diileici~tconsiderations apply to 21 s : i i i ~ ~ ~ ; 'Tlic lolal loss is typically 9300 hW, and Ibc cffi- nents oScoi~ccri,a r c the i,egativr sequcnce components.
golc inacliinc, where ihc geonletry of tiic rnol;i,r:i, cicncy is 98.6010, The efficiency is sliglilly lhighes a: I n order to cit.coIatc nega~i\;c seqtielicc cu~renls
IPallls is very differen1 when ol)eratiiig near tbc qii;,<i about 80% than at 100% MW load, and also im- ihl-oilgli the generator stator and tiaiisfosmci wind-
iature axis frnm tliat ill the direcl axis, and Xd ;tzi,i proves as the power factor incl.edses lowarils uniry. ings, a system of negative seqiieocc voltages must be
Xq have dissin~ilarva1ucs.i The losses shown in tne list are renioved by tlic v a r ~ producerl by negative sequence flux, i.r., (lux rotating
ious cooling systems described in Section 5 o f this at synchronous speed but in the opposite direction of
chapter. The total loss removed by each system is rotation to the main flux. This tilts the rotor at twice
therefore known, and the flow rates are designed to the rotational speed, and indoccs a 100 1-17 voltage in
7.7 Synchronous compensation maintain an appropriate tempeuatul-e. In thc llydro- the rotol surface. 100 I-iz current flows in the outside
While operation in this mode is not foreseer i i i i gen system, 30 m3/s of hydrogen is circulated, being 'skin' of the rotor body, in the wedges and in the
generators o f this rating in the UK, a note here i s cooled to about 40°C by the heat exchangers, and top winding conductors, as if these components were
included for completeness. A generator, synchronisril reaching about 65°C on entry to thc coolers. The part of the squirrel cage of an inductiotl motor.
to the system, ma? be used to generate o r absoll stator core will attain about 75'C, except at the ends, Additional heating therefore occurs in these regions;
reactive MVA, while drawing its loss power froni ~ l i i which are likely to be hot, but within the BS limit in particular, in positions where current transfers
system. By varying its excitation, it can be 0per;ilciI o f 120°C. The rotor winding will reach an average from one componen? to another, sucli as at the wedge
over tlle range shown on Fig 6.78, to meet thc rv temperature of 105°C with local hot spots perhaps ends, and at the endring shrink faces.
quirements of thc system. It is not normally possibl~ 20°C higher than this, which poses insignificant ther- Because of the potentially damaging effect of this
to drive the turbine at rated speed with no steam flou, mal stresses on thc insulation and creep conditions on extra heating, limits on the extent of unbalance have
and s~nallergenerators operated in this way are <li. the copper and aluminium components. to be established. These are conservatively set to ini-
coupled from their turbines. At large values of leadilii, In the stator winding water system, conditions differ tiate alarms when the negative sequence component
FIG.6.79 Opeii- and slioil-cimuii cliaiacierisiicr reactive generation, stator core end temperatures mziy exceeds 5% of the rated current and to trip at abovc
between single and double pass arrangements, but
be high, because the axial components of MMF frojii with inlet water cooled Lo 40-C, the outlet water will 10%. The component is detected by a three-phase cir-
both stator and rotor windings become more in ph;,s,., not exceed 70°C. Hence the winding copper will bare- cuit designed to respond to negative seqllence current.
insulation is not a normal requirement for these large resulting in higher values of axial leakage flux. ly exceed 70°C, and then only at the water outlet In some designs, copper shims are placed in the
generators. It may, however, be necessary to demon. end, and the winding insulation will nowhere exceed ends of the rotor slots, below the wedges, and cxtend-
strate the capability of the connections between gen- iOO°C. CEGB specifies Class F insulation with Class ing outboard of the rotor body to form a colltitluous
erator and transformer, in which case the short. B rises, which are very comfortably met in these ring, in order to assist circumfcrential currcnt flow
circuit would be applied at the transformer terminals. 7.8 Losses, efficiency and temperature designs. and to minimise the small intense hot spots where
Manual control o f excitation is essential. Many separate components of loss can be identified, A considerable advantage of water cooled windings current transfer is concentrated. Where circtlmfer-
The open- and short-circuit characteristics enable some of which are substantially constant irrespective is that the temperatures arc inherently constrained to ential slots are cut into the pole faces (Section 3 of
certain parameters to be established. Short-circuit ra- of load; others can, for simplicity, be assumed i i , be very low, thus maximising the intrinsic life o f tlle this chapter), means for transferring surface current
tio (SCR) vary approximately as (stator c u ~ r e n t ) ~These
. col~i. insulation. Also, since the temperature rises of the across the slots are provided, usually in the form of
Ponents are listed below, with kW values given for ;I core and windings are similar, problems associated copper strips retained by wedges in shallow 'pole
typical 660 MW generator at rated conditions: with differential thermal expansion arc minimised, face slots', to avoid overheating at positions of currcnt
- Rotor current for rated voltage on open-circuit
and it has not been found necessary to incorporate concentration.
Rotor currcnt for rated currcnt on short-circuit
Consranr Iossa Coolonr loss, k i l features in the end windings to accommodate axial The shallow surface current paths must also handle
Fan ioss Hydrogen 600 movement. the very much larger, short duration currents imposed
Rotor windage loss by unbalanced conditions during transient faults. A
Hydrogen 350
Othel. windage loss rough criterion of acceptability is provided by assuming
Hydrogen 150 that the heating is proportional to ~ ( l ~ ) where ~ t ,
This rough measure of steady state stability is nearly Open-circuit core (iron) loss Hydrogen 950 I, is the negative sequence stator current (per unit)
the reciprocal of Xd; minimum values of 0.4 and Bearing loss Lub ail 600 7.9 Electrically unbalanced conditions and t the time (in seconds) for which the condition
0.5 are specified for the 500 and 660 MW units, re- Shaft seal loss Seal oil 100 The amplitudes and phase displacements of the three- persists. This is only approximately valid for times
spectively. Rotating exciter constant loss Exciter air 100 phase voltages and currents in the transmission system short enough for heat dissipation to be ignored. Per-
Auxiliary system losses, e.g., motors - 100 are usually symmetrical t o within about I % , which missible values of of about 3 are usual for
Synchronous reactance Xd may be quoted as the does not impose any significant difficulties in the 500/660 MW generators, and 'instantaneous' irip-
reciprocal o f short-circuit ratio, in which case it is Variable losses Coolant loss, kM' generator. However, it is possible for much larger ping is initiated if this value is exceeded (see Fig
the value corresponding to the degree of saturation Stator copper loss Stator winding water 1600 unbalances to exist, for example, if one phase o f a 6.81).
at rated voltage on open-circuit (which is not the same circuit-breaker remains closed while the others are The surface current paths are also involved in any
Eddy current ioss in
as that at rated load). It is of interest when discussing windings Stator winding water 600 open for considerable lengths of time, then the ability condition in which the generator is connected to the
operation close to the stability limit, in which case of the generqtor to withstand such conditions must system but is not operating synchronously. This may
its unsaturated value is appropriate and given by: Additional core loss,
due to higher flux and) be established. happen on total or partial loss of excitation, and
can usually be tolerated by the generator for a short
Rotor current for rated current on short-circuit
end loss
Lass in core end olates I Hydrogen 1600
The well known method o f resolution of unbal-
anced phasors into systems of symmetrical components
is used in the analysis shown in Fig 6.80. Because
time, although slip frequency surges will occur on
the system. Because the induced currents are at slip
Rotor current for rated voltage on airgap line and frame
Loss ill rotor surface
Rotor copper loss
J Hydrogen 2400
generators are invariably connected to transformers
whose LV windings are arranged in delta, which there-
fore d o not have a neutral connection, zero sequence
frequency, they are able to penetrate further into the
rotor, wedges and winding, and the thermal conditions
are not as critical as with the 100 Hz currents pro-
Variable excitation loss Exciter air IS0 voltages and currents cannot exist. The only compo- duced by unbalanced operation.
537
Tlie generator
Chapt(ii I:

$'!-11111591111F i ' A i l i i C L 1 I I I I I N i
1 W i S MCR CUiiRiiNi

10

70

UNBALANCED VOLTAGE SEl

ANUNBALANCED VOLTAGE SETCAN BE


RESOLVED INTO THE FOLLOWING

20 30 50 60 70

embracing the stator winding slots, the airgap and change of flux induces currents in the rotor surface
the rotor slots, with a small component associated paths, and for the first few cycles, say up to 200 ms,
with the end windings, and is affected by the degree conditions depend more on a reactance linking these
Fic. 6.80 Unbalanced pliase eonditionr of magnetic saturation. The normal value for un- surface flux paths with the stator winding. This is
saturated transient reactance is of the order of 0.3 referred to as the sub-transienl reactance, X d " , with a
per unit. value of about 0.2 per unit. It is this reactance which
7.10 Transient conditions It is this reactance which controls the initial rise- limits the current in the first few peaks after a fault.
vious position, i.e., 6 changes, so that the electrical For a three-phase fault at the generator terminals from
of-voltage when load is suddenly tripped off; typi-
Changes in the load demand, system operation con- power generated changes to restore equilibrium. The
cally the voltage rises instantaneously to 1.3 per unit rated voltage open-circuit, the RMS value of the initial
ditions and the response of other generating units, combined effect o f similar load changes occurring in and finally reaches a value determined by the pre- current peak will be V/X,", i.e., 1/(0.2) = 5 per unit.
mean that conditions at the unit transformer terminals many units acts to restore the system frequency to its vailing value of rotor current. Also, transient reactance The peak value is J 2 times this, and, if the par-
are constantly changing. Increase in overall demand original value. is used in calculations involving the stability o f the ticular phase experiences full asymmetry (depending
causes a fall in frequency to which the speed gover- Coincident with the change of load will be a change unit with the system during a transient fault situation. on the instant at which the fault occurred), it is pos-
nors of all the connected turbines respond. Their rate in system voltage, which causes the voltage regulator Such studies require accurate representation of gen- sible for the first peak to reach 2 4 2 x 5 = 14.14
o f response depends on the settings of the individual to adjust the excitation to restore the original voltage erator parameters, and in this context it is important times rated current. In practice, flux decay results in
governors, some units being deliberately arranged to value. (A large voltage change may require a trans- that its specified value has been met (see Fig 6.82). the maximum current being about 90% of this value,
act more responsively than others. former tapchanging operation to maintain the gen- During conditions of massive change, such as those but if the short-circuit is applied from a condition of
A highly responsive unit varies its steam inlet valve erator terminal voltage near its rated value.) that occur during a close-up fault, when the terminal load, i.e., with increased flux and a higher 'internal'
position frequently, causing the steam throughput to Flux cannot change in the machine instantaneously, voltage may be suddenly reduced to half its rated voltage, the peak current could be greater.
change and altering the torque equilibrium. The ro- and the rate-of-change is influenced by the transient value (or even to zero for a fault at the generator or Such peaks o f current result in enormous forces
tors move forward or backward relative to their pre- reaclance X d . . This depends largely on the flux paths transformer low voltage connections), the very rapid on the stator windings in the slots and end windings
538
Tlie generator CI7apti.i t. Meciialnicai considerations
.
~hioogli a ncuisal eariliing device, designed to linlil
the fault current in tlie event oC B s t a t ~ wiiiding
i Pail11
to earti,.
The neutral earthing device of eailicr generators
consisted of a wales rcsistoi, designed lo limit tlle cur-
rent in a line lo earth fault to a maxirnunl of 300 A.
Morc recent machines use a small single-llhasc dis-
tribution type transformer with its primary connected
between the generator star paint and earth, and its
secondary loaded onto a resistor. This arrangement
limits the fault current to about 15 A, and was ori-
ginally intended to allow a n internal fault to be sus-
tained while load was reduced, rather than requiring
an instantaneous trip. Modern practice is to trip in-
stantaneously oil fault detection, even with this form
o f earthing. In both cases the sensitivity of protection
is such that a fault at less than 10% from the neutral
point is not detectable, and could persist, though the
low voltage to earth in this part of the winding makes
OPENCiRCUii CIIARACTERISTIC ASSUMES NO VOLTAGE R B G U L A I O R A C ~ ~ O N
fault initiation less likely and fault current compara-
tively low.
FIG.6.82 Voltage lire oil rated toad ibrou,-oll

7.12 Shutting down


(since force varies as current squared), and in the between two phases. Here, the phasors become highly The process of load reduction is the reverse of that for
connections, which would result in considerable move- unbalanced, and the 'negative sequence ieactancr'. load increase except that, when the load has reached
ment if the components were not adequately sup- Xz, helps to determine the peak current, which may a low value, the main circuit-breaker (or the LV
ported to resist them. It is therefore vital to establish attain a maximum of 2 4 2 x J3(v/Xd- X2) whicli + S T A T ~ ~ A N D PWITH
O ~ OIOO%ASYMMEIRY
RS~~OR~CRCU~TCIIPIIICTCRIS~~CS
switcli, if fitted) is opened, and with it the turbine
the value of sub-transient reactance. (It should be is of a similar magnitude to that in the three-phasc steam valve and the excitation crcuit-breakers, The
noted that the thermal effects are not troublesome case. TIO.6.83 ~hree-nl?aic rtioit-circuit current ct~aracleiistics unit runs down in a time determined by the inertia
because of the rapid rate-of-decay of current.) In a line to earth fault, the 'zero sequence reactance', of the rotors and the windage and friction losses. At
Another reason is to ensure that the main circuit- X,, is involved, and the peak current may be 2 J 2 Y some stage, the motor-driven lubrication pump is
breaker (and low voltage switch, if fitted) is able to J3 (V/Xp + X 2 i- X,) usually considerably lowri switched in to take over from tlle shaft-driven pump.
withstand these very large through-currents and that than the three-phase value, depending very much oil The turbine must usually be barred for some hours
it can, if necessary, break them although, in practice, the neutral carthing arrangement. on shutdown, and lubricating oil must be maintained
it rarely breaks on the first peak of current. Works tests for X, and X, are not normally carried to all the beaiings during this process.
T o measure the transient and sub-transient re- out, even on prototype designs, since X 2 is easily It is usual to leave the hydrogen in the generator
actances and their associated time constants, a three- derived from the positive sequence reactances, anil casing, unless a prolonged shutdown is envisaged Or
phase short-circuit is suddenly applied to the prototype the value of X, is not as critical as the others. access to the casing is required in order to avoid
generator running at speed during the in-works tests, Another factor involved in transient stability repl-r. wastage of gas. The pressure will fall as the tem-
while excited to one o r more agreed voltage values, and sentations is the inertia o f the rotating masses, usually perature drops, but it is not usual for the pressure to
the resulting three-phase currents recorded. Figure quoted as the 'inertia constant' H, with units of MW be maintained exactly at rated value, nor for water to
6.83 shows a typical trace and how the Xd' and X," seconds/MVA (or simply seconds). For these ratings, be circulated in the coolers and windings. It is essential
values are deduced, while Fig 6.84 shows how the H will be of the order of 3.0, of which the generator that the shaft seais are supplied with oil both during
reactances vary with initial voltage due to saturation. contributes only about 0.8. The higher the inertia, barring and when stationary, t o prevent hydrogen leak-
A generator terminal fault, though physically vir- the longer the time taken to accelerate the rotors age, and, because of the possibility of moisture ingress
tually impossible, imposes the most severe of the into instability, allowing more time for corrective from the seal oil, the blower may be run in order to
three-phase conditions, with the effective voltage 1.0 action and hence a bigger margin. circulate hydrogen through the dryer.
per unit, or higher. More likely is a fault on the
system which, because of the interposed reactance
of the generator transformer, imposes short-circuit
currents similar to those from a terminal fault at a 7.11 Neutral earthing
voltage equal to Xd"/(Xd8' + Xe). where X, is the T h e neutral ends of the three phases of the stator wind- 8 Mechanical considerations
reactance o f the transformer and that part of the ing are connected together, outside the casing, by the Some aspects of torque, stresses, vibration, etc., were
system between it and the fault. 'star-bar', which may be located underneath the cas- mentioned in Sections 3 and 4 of this chapter, and
A type of fault more likely to occur, particularly ing alongside the line connections, o r above it in a these and other mechanical aspects are considered in
inside the generator, is one involving a short-circuit special enclosure. The star point is connected to earth FiO. 6.84 Transient and sub-transient reactances more detail in this section.
540 541
The generator Mechanical considorations
ChapIei 1,

8.1 R o t o r t o r q u e lifc. Kesilits fvom inodeis do not scale accurately i i l t c i to take the creep beliaviour of aiu~niniulninto con- solational hoop strcss due to the rataiioll o f the
At a constant ioad (eicctricai output and generator at llic most exireme (anrl ti~c~.cfoie inust dan~agi,,!.) sideration at teinpeiatuies in excess of iOO"C, but ring. At rated speed and ovcispecd, tile strcss al
loisesi of P kM', tile torque (Nm) cxpericriccd at the stress, the lhiglily non-linear erfects or inalcrial daiiii, it is not usual for wedge temperatures to exceed this the shrink-fits may be less than tliat in the centre.
lol-bine-generator coul)iing is 95451' divided by (i/iain). ing ntust be considered. valuc (see Fif 6.85). Thcri- is also an axial stress due to the higher thermai
The coupling ii~iist be capable of tl-ansmitling the In tile UK, where ltigh speed rcclosurc is not ( l i ; ~ i . Pole
~.face wedees
~ - are much less stressed, and are expansion o f the copper in the end winding relative
to that o f the steel ring. As noted in Section 3.3 o f
torque associated with rated output continuously wit11- tised, sub-synchronoos resonance due to the use oi conimonly made of steel.
out deformation. Tliese couplings commonly have series capacitolr is nor a piobiern and the operaii~,~: The most inboard of the field lead wedges may this chapter, direct contact of the end disc onto the
four o f their bolts closely fitted into both coupling of the tranmiission system is under close conlrr>i. be unusually highly stressed because of thc extra CF shaft is not normal, since the flexure of the shaft
flanges, while the other bolts have smaller diameter it is tl~oughtthat the combination of very ltigh stresscs loading imposed on it by the section of connector would transmit a small alternating stress onto the
and a clearance in the coupling holes. The torque is and very low probability of occurrence results in ;nii leading into the winding. highly stressed ring which could promote crack pro-
transmitted partly through the fitted bolts and partly acceptable risk for rotors designed to conventioniil The shrink-fits of the end ring onto its seatings pagation by high cycle fatigue. Again, it is important
through friction between the flange faces. The full specifications, and that iifetilne monitoring is iloi on the rotor body and end disc reduce as speed that the stresses under all conditions are attalysed in
torque must also be transmitted tlirough the shaft justified. increases, and are greatest at standstill. There are detail, and this may necessitate a three-dimensional
end at the turbitie end, which must therefore be de- The exercise llas highlighted the need to avoid therefore large circumferential strains at the ends of finite elemeltt computation in order to ensure free-
signed to witl~slandit. stress raisers such as unnecessarily small radii, and t i , the rings, and carrespondingly high stresses, at stand- dom from high stress concentrations, particularly at
In the very much larger section of the rotor body, ensure a high quality surface finish. It has also drawl) still. As speed increases, the centrifugal force of the the sudden changes of section involved (see Fig 6.86).
shear stress due lo torque is very lnucll less than in attention to the need to design the generator to C A . rotor end windiilgs imposes a load and stress in the In the rotor conductor nearest the wedge, it is the
the shaft ends and is not of significant magnitude. citer coupling t o withstand torques of the order ol central part of the ring, which combine with the compressive stress produced by the centrifugal force
Also, the transmitted torque reduces in a linear man- the rated generator torque, since it has been sbowll
ner along the length of the rotor body, so that at tliat these can exist during tl.ansient conditions.
the exciter end, only the small torque required to The requirement for torque transnlission places :r
drive the rotating exciters (and any other coupled cquip- limit on the minimum diameter of the shaft and therefoi-r
ment) has to be transmitted, o f the journal. An acceptable compromise belwec,,
As ~notcdpreviously, during electrical faults, stator the higher loss associated with a large diameter and
currents of many times rated value occur, and these adequate hydrodynamic stability results in a bearlny
cause electrontagnetic torques of a similar magnitude. somewhat shorter than its diameter for these ratings.
The torque reaction at the turbine to generator cou- Bearing performance is described in Chapter 1.
pling and in the associated shafts depends, among
other things, on the ratio of inertias of the turbine
and generator rotors, but can also be several times
rated torque. The specification requiles that the shaft 8.2 S t r e s s due to c e n t r i f u g a l f o r c e
and coupling shall be designed to withstand stipulated All rotating components are subjected to stresses due
fault conditions, without failure, though not neces- to centrifugal forces, and are designed so that thc
sarily without permanent distortion of coinponetits yield stress o f the material exceeds the stress at over-
such as coupling bolts. It is not unknown for the speed by an adequate safety factor. Usually the com-
fitted coupling bolts to exhibit distortion after a severe ponents closest to the limit are the rotor teeth, rotoi
electrical fault. wedges, end rings and outermost winding conductors.
Materials subjected to repeated high stresses ea- The tensile stress in the rotor teeth was considered
hibit a lifefirne, during which damage is accumulated, as part of the rotor optimisation in Section 3 of this
and at the end of which failure occurs fairly rapidly. chapter. It is greatest at the tooth root, but will have
Much effort has been devoted to establishing models local concentrations at the wedge dovetail. There will
of turbine-generator shaft systems in order to be able also be a high local stress where the wedge transfers
ta predict their remaining 'life' (i.e., ability to with- the centrifugal force (CF) load of the slot into the
stand further faults), knowing the history of the faults tooth. Detailed finite element analysis is carried out
t o which they have already been subjected. This has to ensure that unacceptable stress concentrations are
been done analytically, knowing the torsional char- avoided. These stresses ate constant at constant speed,
acteristics of the rotor system, and computing the so that the only cyclic factor is the number of stop-
shaft torques due to postulated electrical transients. start cycles, which is relatively few ( < 10') over the
It was found that in the case of rapid reclosure of a lifetime of the machine. Thus crack propagation by
circuit-breaker following clearance of a faulty line, high cycle fatigue from this mechanism alone is not
the magnitude o f the peak of torque depends very of concern.

-
critically on the timing o f the instant of reclosure. Similar considerations apply to the slot wedges, in
This has also been demonstrated, during transient which the loading pattern is similar to that in a short
conditions, using values of stress obtained from strain beam in bending, uniformly loaded on its underside,
gauges fixed to the shafts. Devices which calculate and with built-in ends. Aluminium alloy wedges are
shaft torques from electrical inputs have also been commonly made from extruded sections, but have
used. the outermost layer (1 mm, or so) machined away
It is difficult t o relate measured or calculated torque where stresses are high, so that the properties of the
peaks accurately to damage caused, o r to remaining parent metal are fully realised. It would be necessary Fia. 6.85 Finite element mesh for tootli.wedge slier$ calculations
The generator Electrical a n d eieclromugnetic aspects
--
8.3 Alternatirig s t r e s s e s , i r e t t i n g t t n ~ i1;riiiji;is
One feature of this is ti~arthe rotor must usoaily he second increases the rcquiscd Siiix magnitude; both
A stationary color sags under its o w n \+'rif:i,~,i j r i i - i ~ ! ~
run down in speed before the changed vibratioii dis- increase saturation, the effects of whicli arc highiy
a compressive stress in tile ootermost i l i ~ c >( i i i i i , appears, wi~ent i l ~cycle can he repeated. non-linear (see Fig 6.87). Oric result o i this is that
top and at tile axial centrr of about 15 k4l';i. i + ; i t , Oncc the rotor is at speed and tempcratilre, it does overall iron losses will be higher than those calculated
a corresporiditig Lerisile stress at thc bottain i i l i l i i not tend to suffer froin high cycle effects. It is more for no-load conditions, and their distribution u'iil dif..
same magnitude. As the rotor rotates, eaoli l ' i i i ~ i I.,+ vulnerable to effects promoted by reiative mo\,ement, fcr. Anoti~eris that the calculation of the required
periences a coInpTessive/zero/tcnsilc~~er~~/cc~~i~~~t~~~, such as abrasion, when running at lower speeds and MMF (rotor current) required for any load condition
sive Stress cycle once per revolution. Sincr IS ~ t i i i i , ~jhile barring, when the cei~trifugai locking-up is cannot be accurately based on the simple phasoi-
operating at 3000 r/min accunlulates 1.5 x i(i" vyvlc; absent. diagram. Since the rotor is necessarily designed with
in a year, alternating stress due to bending l t t ~ , 1,. little margin, accurate calculation of the rotor current
be considered in the design. Tilough its msgliiltl,lt; needed for rated conditions is essential.
is small, it is superimposed otl the high steady sti.t.s.rcu
in the rotor and wedges identified above, and c;ul 8.5 N o i s e
mote the growth of cracks by high cycie fatig,itr. The generator rotor, with its fans, generates very
One source o f crack initiation may be frcttini:, l i
high noise energy at speed. The spectrum is wide, but
a once per cycie movement can occur, say at the ~:,,l,
contains peaks at frequencies related to the number
between two short slot wedges, the resultant loc;ilisi.d
of fan blades and siots.
damage may bc sufficient to intensify the local srii.;..
The other main sourcc of noise is generated by
field at a minute 'crack-tip', from wiiich the ; ~ i i i i
the stator corc when magnetically excited. As pre-
nating bending stress can propagate. Such featusus ;sir viously noted, the magnetic forces 'ovalisc' the stator
avoided wherever possible, and particularly oe;il i i i , core, causing vibration and noise at 100 Hz and niul-
axial centre uahere alternating bending stresses ;,$,. tiples. The main component of magnetic noise, how-
highest. The concepts of fracture mechanics arc iiri-,i ever, arises from distortions on a much smaller scale,
to study such crack tip stress intensification. that o f the magnetised iron crystals, in the pheno-
menon known as magneloslricrion, at 50 Hz and
multiples thereof.
The robust stator casing acts as an effective sound
8.4 'Slip-stick' o f rotor windings attenuator, and little can be achieved to reduce the
One effect not mentioned in Section 3.8 of this ciiap transmitted noise further, for example, by the acoustic
ter is the behaviour of the rotor winding during i t treatment of the inside surfaces. In practice, the major
loading cycle. The rotor is run up from cold, anti sources of high noise intensity tend to Occur in the
though the windings and rotor body are warmed thy driven components such as exciters, wldcli have fans
gas friction, there is iittle differential in thermal effect operating in air and no heavy steel surround. Some- t:ic 6.87 I'tux diitiibutioi~on load
at this stage. At speed, the winding conductors aic times the complete line of driven units is housed under
iocked together and to the wedge by the centrifug;li an acoustic cover to attenuate these sources. Access
force, unless an axiai force can overcame the frictioi, doors and windows must be provided, and these can
between them. reduce the effectiveness of the covers. A method previously used took as its basis the
When current is applied to the rotor winding, i t A sound power level o f 93 dBA is specified at simple no-load unsaturated phasor diagram, and de-
reaches a higher temperature than the rotor body, 1 m distant from the plant. Legislation map require fined a n imaginary reactance, the 'Potier' reactance,
and as the coefficient of thermal expansion of copper this to be reduced for new plant in the future. empirically derived, which was used to define a 'Potier'
is nearly twice that of steel, the conductors experience voltage drop, IX,, for the given ioad conditions. An
an axial force directed outwards from the axial centre. internal voltage required to overcome this voltage
As the differential temperature increases, the axial drop, the 'Polier voltage' was thus established. The
forces increase, until slippage occurs at a point where 9 Electrical and electromagnetic aspects MMF difference between the airgap and open-circuit
the build-up of axial force is able to overcome the characteristics at the 'Potier voltage' was then pha-
Some electrical and magnetic aspects of generators,
friction. Because the 'bottom' conductor experiences not previously considered, are dealt with in this section. sorially added to the unsaturated MMF phasor. In this
the least centrifugal load, it is most easily able to way, the increasing and non-linear effects o f sat-
overcome friction, and a shorter length of it remains uration were taken into consideration (see Fig 6.88).
FIG.6.86 End ring lug area - finite eiement mesh and frictionally-locked than those o f coils further up the Present methods use finite element calculations,
s1iess CO"1OUrS slot. Slippage in most windings appears to occur in 9.1 Flux distribution on load which can be reduced to two dimensions for the
small steps, apparently randomly, though possibly re- central part of the machine. Even so, the detailed
When, in previous sections, magnetic flux densities
peatably, so that the release o f the axial forces does geometry and non-linear magnetic characteristic make
have been mentioned, operation at rated voltage,
not result in sudden changes in vibration of sufficent the calculation complex.
of all the other conductors in the slot which is of no-load has been assumed, where the load angle is
magnitude to be significant. In some rotors, however, In the end regions, a three-dimensional approach
concern, particularly where the copper area is reduced zero and the rotor operates in the 'direct axis'. In
due to higher frictional restraints having to be over- practical load situations, the ioad angle is 40-50' is almost essential, although various schemes have
by ventilation grooves and slots. Some creeo of the....
copper may be observed at such slots after many years
. ~ ~
come, the release of much larger axial forces appears and the effective flux level must be large enough to been devised in which simplifications can be made.
to cause the bending moment to change significantly, overcome the leakage reactance voltage drop. The In addition to the difficulties already noted, the thick
in operation. resulting in a noticeable sudden change in vibration. first effect distorts the flux pattern markedly; the conducting plates in which non-linear eddy currents
545
I-llc geiicraror TIectri~aland electromaclnetic aspects
Chaptiif ti

content than that specified in BSS000, in \+,l,ich ccr- soiii-cc impedance, and can ciiculale significanl cur-
rain langes o f frequency arc more highly weighted rent through bearings, seals, erc., causing eventual
than others because of their cflcct (in the lransmission brcak-up of white-metalled surfaces.
system) on communications lines. This now rather oul- Voltages of the same frequency as the shaft-driven
dated concept is still accepted as an agreed and useful excitation lnacllines can be measured on the generator
crite~.ioti,since high harmonic levels can induce high shaft, but these arc capacitively coupled, have a high
local losses in parts of the generator, e.g., the rotor source impedance and will not sustain a large current.
surface. The steam turbine rotors may develop a voltage
In practice, harmonics arc generated by the con- due to the electrostatic action o f steam and water
nected loads, a recent trend being the even-order droplets on the blades, and one function of the shaft
harmonic requirements of equipment using thyristors. earthing brushes is to cnsure that this is discharged.
This must be supplied by the generators and must A phenomenon which has occurred (rarely) on tur-
therefore appear in the flux wave, causing rotor surface bines is that, where a rotor or rotors have a degree of
losses similar to those produced by unbalanced load oermanent magnetism and there are contacts of low
conditions. resistance between shaft and earth at suitable axially-
Rotor windings occasionally develop short-circuits separated locations, the small generated voltage can
between adjacent turns in a coil, and while this is not circulate a small current through the turbine casing,
usually of great concern, the difference in flux pat- which, in certain designs, can act as a partial 'turn'
tern from the two poles is detectable, using a small of a winding encircling the shaft. This then produces
flux coil mounted in the airgap. When the signal from an MMF and therefore a higher shaft voltage, the
one pole is offset against the signal from the other, whoie process building up until many thousands of
differences reveal any abnormality. Ailother method amocres circulate, causing damage at the contacts. It
which has been suggested uses the presence of second is therefore important to cnsure that deliberate con-
harmonics in the stator current, as noted above, but tacts, such as eartlnng brushes, have a resistance (say,
PIG. 6.88 l'oliei coiisiructioli foi on-toad excitation current
this has to be able to reject those imposed by the load 1 ohm) deliberately included in series, and that heavily
requircmcnts. magnetised shafts are de-magnetiscd (see Fig 6.24).
The residual magnetism of a generator rotor will
normally produce a voltage of several hundred volts
are induced, and other conducting components, must tance. If higher values are required than the 'natural' at speed, even without external excitation; and access
be included in the modelling. It has reached the design produces, the leakage reluctance can be re-
9.4 Magnetic pull to terminals, connections, etc., must not be allowed.
stage of refinement where detailed changes, say, in the duced by making the Slots narrower, and/or sinking
thickness of magnetic screens, can be modelled in them deeper into the core. Again, this is extravagant If the rotor is exactly centred in the bore of the sta-
order to optimise the design, and to indicate where and results in a larger design. tor, the magnetic pull between one pole of the rotor
potential llot spots may occur due to unwanted flux If lower values are required, it is not usually suf- and the stator will be exactly balanced by that o f
collcentrations. the other: If not centred, there will he an unbalanced 9.6 Field suppression
ficient to manipulate the slot geometry, and a mow
pull acting as an attractive force on the pole with If an eiectrical fault occurs in the generator, the
basic change to the design might be needed.
the smaller air gap. However, the air gap of these connections, or on the generator transformer, the
Using computer programs similar to those men- protection will act to trip the main circuit-breaker.
tioned in the previous section, more accurate repre- large machines is so large (80 to 130 mm), in order
9.2 Control and calculation of reactances to achieve the required synchronous reactance, that This will extinguish the stator current within one
sentation o f the reactances can be made, over the cycle of circuit-breaker operation but the flux cannot
The reactance of an inductive circuit determines its range of load conditions, than is possible by simple centring the rotor to a readily achievable accuracy
does not impose a magnetic pull at all comparable be reduced so quickly. In all except brushless ma-
voltage/current relationship. In a generator, different calculation.
with the gravitational force on the rotor. chines, a field circuit-breaker is connected in circuit
reactances are identified in order to model or de-
between the excitation source and the rotor winding.
scribe voltage (or flux)/current relationships under Similarly, the net axial magnetic force on the rotor
If this were to be opened, the instantaneous reduc-
different circumstances. is zero if it is axially centred in the stator, and this
tion in current would induce a large (several kV)
The synchronous reactance, Xd, relates the arma- 9.3 The cause and effect of harmonics is the condition normally achieved at rated load with
voltage in the rotor winding, with the risk of insulation
ture reaction MMF (proportional to stator current) to As explained earlier, stator winding distribution is the rotors at their normal temperatures. With the breakdown.
the MMF needed for rated flux in the air gap. For a designed to minimise the generation of harmonic volt- usual axial offset which occurs with the rotors cold, Instead, a field suppression resistor is inserted in
given design of machine, increasing the radial length ages and currents. the axial magnetic pull is only of the order of a few series with the rotor winding, the excitation source
o f the air gap proportionately reduces Xd and im- The stator winding is invariably star connected, so thousand Newtons and is not a significant additional circuit being opened subsequently. The resistor has
proves steady state stability. This results in a larger that triple harmonics cannot occur in the line voltage load on the thrust bearing. a n ohmic value o f 1 to 3 times that o f the winding,
outside diameter, and a higher rotor current at full o r current. Since one pole of the rotor is identical and reduces the current (and flux) rapidly, without
load. with the other, it cannot produce second-order flux imposing an excessive voltage. Thus the ability of the
The stator leakage reactance, X,, is not a specified harmonics, which would make the two halves of the flux to prolong the current in the fault is safely
quantity, and its value is a matter of economic design. flux wave dissimilar. The only harmonics of signi- 9.5 Shaft voltage and residual magnetism minimised.
The transient and sub-transient reactances, Xd' and ficant magnitude which will appear are those of order In brushless machines, direct suppression o f the
The production of a voltage (predominantly at 50 Hz)
Xd", are specified. They describe the flux/current rela- 5, 7, 11, 13, etc., with diminishing amplitudes, and from one end of the generator rotor to the other oc- rotor winding current is not possible. The exciter field
tionships during transient changes, and under these cir- those near to the rotor slot pitch, e.g., 41 and 43 current is rapidly reduced by the operation of the
curs because o f some asymmetry, either of the position
cumstances, the amount of flux encircling the sta- for a 42-pitch rotor slotting. The no-load rated volt- exciter field switch (this also applies in a non-brush-
of the rotor in the stator, or some difference in mag-
tor slots, rotor slots and end windings are of impor- age wave must not contain a greater total harmonic less machine), or by inversion of the thyristors, but
netic properties. This mechanism has a low effective
547
Operatiotial measurement, control, monitoring and prolecriol?

tile rotor clllreiit ihas an efrcctiveiy zcro Iesistaitcc ing, a iarge fault current a,ouid flow,, with dangel i l l 10 O p e r a t i o n a l m e a s u r e m e n t , c o n t r o i ,
wiriding surfaces, ,nay occur, particula~.iy whel.e the
llalli through the rotating diodes, and decays with thc maintenance opei.alor. It is considered prctrl m o n i t o r i n g and p r o t e c t i o n
seoii-conducting surface tieat~neiit layers becomc bro-
the rraloi-a1 time constant of llie ivinding (src Fig 6.89).
able not to apply ao earth, but to elislire that I I , , ken or damaged, but again this does not norlnalls M~~~ of these sirbjects have becli mentioned in pass-
operator is properiy clothed and is using special 1,; lead to breakdonan. Mucii more likely is ~nechaiiical i,,g. I,, this s e c t i ~ i i ,each group is consideied as a
sulated equipment. damage to the insulation by pieces of core pu11chi11g co.ol.dinated
9.7 V o l t a g e in t h e r o t o r winding which become delaciled, magnetic debris (which call
At rated load, the voltage required to circulate rated cut 'wormholes' into the end winding insuiation un-
rotor current is of the order of 500 V. During field der electromagnetic forces), and abrasion of packing
9.8 Stator winding i n s u l a t i o n blocks into insulation. For these reasons, insulation 10.1 R o u t i n e i n ~ t l ~ m e n t a t i ~ n
forcing, this may rise to almost twice this value for In normal operation, the highest voitage to eaitii
a few seconds. The rapid decay of current during field thicknesses have not been reduced to take advantage provisions vary between manufacturers and have chang-
occurs in the winding bar (and connection) at the hi(.li o f the superior electrical properties available with ed over thc but the following is representative.
suppression may possibly induce 1500 V briefly in voltage ('line') end o f each phasc. This amounts to
tile winding. During transient fault conditions, the modern insulation systems.
23.5/\13 = 13.5 kV (RMS) for the 660 MW uniis.
requirement o f maintaining the previous flux level may Considerable effort has been devoted to devising
Voltage to earth on the other conductor bars is i c . means of detecting signs o f insulation deterioration, 10.1.1 Temperature
cause large currents to be induced into the winding, duced through the winding to effectively zero at ti,?
with correspondingly high voltagcs (1500 V or so). for instance, by observing discharge activit)' in a ~ h ~ ~ , , , ~ c o u are
p l e sused to detect the temperature
neutral end. The eiectrical stress in the insulation
~~.~~~~~ i.
oermanently installed, capacitively coupled device, or in:
The highest voltages are likely to be appiied during riot high even on the line-end bars; all the bars arv
asynchronous operation, during which the induced by radio frequency aerials inside the casing; both
similarly insulated. Stator core - in teeth, back of teeth, core ends
alternating rotor current (at slip frequency) seeks to methods are still being developed. Discharge energy is
The system of insulation has to undergo searchin!: nrcdominantlv in the I MHz range, whereas corona and axial Cetltle.
reverse. This possibility is blocked by the excitation type tests before it is approved for general use, aaci ,~
~

diodes and high voltage peaks occur ( 2 2 0 0 0 V) at discharge, which also occurs, is predominantly at a 8 Core end plates and end plate screen - these are
even then, quality control tests on production bays
the sudden changes in current. higiiei frequency. Occasional 'fingerprint' measure- permitted to attain higher temperatures than the
include the destructive cutting up of two sacrificial

.
The winding insulation of a new rotor is finally ments can show, whether either activity is increasing core if not in contact with insulation.
bars per machine to ensure freedom from cavities i l i
tested at 3500 V, having withstood higher test voltages the insulation, among other quality checks. with time.
during manufacture. However, the arduous operating In operation, electromagnetic forces cause tile bars Similarly, an overall measure o f the insulation ~~d~~~~~ inlet to and outlet from coolers -
conditions may cause insulation to become physicaily to vibrate at 100 Hz in the slots and end windings, integrity of a whole phase can be gained by mo- to ailow averaging.
damaged, displaced, or just oily or dirty from con- nitoring the capacitative component of currcnt at
to an extent Limited by their restraining devices. 11' Stator winding, either one per slot or in water outlet
tamination, and such high voltages are less easily bars becomc loose in their slots due to relaxatioii various voltage levels, usually expressed as 'tan delta'
withstood in an older rotor. values.~~,i.e.., a measure o f (very
. . low) Dower factor. hose - basically to monitor water flow in in-
of ripple springs or wedges, the layers o f insulation ~ ~

When brushes are being changed with the generator Breakdown, however, is most likely to occur from dividual bars,
tape may become locally de-laminated, in spite of
on-load, it is common practice to ensure that the one local area of damage, as already noted, and the
the bonding resin. Electrical discharges can occur at Hydrogen seal faces - to detect rubbing, or oil

.
excitation control is on 'manual', so that the rotor such sites which might eventually lead to electrical poor results from this local area are swamped by the
starvation.
cannot be subjected to field forcing voltages, and to breakdown of the bar to earth. Fortunately, in a hy- better measurements of the rest, so that such methods
disconnect the earth fauit indication biasing voltage. drogen atmosphere, carbo~lisatianof the surfaces does are relatively insensitive. Stator frame, at C 0 2 inlet - to detect freezing.
It may be thought to be advantageous to earth the not occur as readily as it wouid in air, and brcak- Stator insulation withstands more than twice its
slipring being worked on deliberately, but if this were downs from this cause are uncommon. Discharge on rated line voltage, i.e., >2[J3 x maximum (phase)
Resislortce eleme,lls or other thennometers are used

.
done and an earth fault developed in the rotor wind- the bar surface, either in the slot, or across the end ooerati,te- .. and an insulation sample
stand at least twice this again, so there is a huge for:
safety margin on intact insulation, Even so, testing Water inlet and outlet temperat,lres in all water.
at high voltage is destructive, and repeat testing in cooling systems.
service is deprecated.
If an earth fault occurred at one of the phase o i l outlets from hearings and seals
ends, the voltage at the neutral would be elevated,
and that at the other ohase ends could rise to 43 x Seal oil at outlet from Cooler.
normal. This condition would persist for only a few
seconds, at most, before the protection acted to trip
r Hydrogen to and from cooler, as back-up to ther-
mocouples.
the unit and suppress the flux. In normal operation,
the maximum voltage a winding can attain is limited r An ohmmeter is used to display rotor winding
to about 35% above rated, for example, if rated temperature.
load were tripped, but again this would quickly be
suppressed. Temperatures are monitored during works tests
Surges arising from switching or other operations and during on-load commissioning, to ensure that
o n the system are greatly attenuated in the generator the specified limits have not been exceeded. The
transformer, and d o not pose a significant hazard to alarm level would normally be set above the high-
the generator winding. These large machines do not est temperature attained at rated load with the
have multi-turn coils, which are more at risk from warmest ambient conditions, but recent thoughts
surges. The surge withstand voltage is quoted at about are that this practice may miss early warnings of
85-90 kV, but surge withstand tests are never carried developing abnormalities. If a measured tempera-
FIG. 6.89 Field suppression circuits ture is related to other parameters, such as current
out.
548
lil olhei similar sigliali to scc tliiil its imaguili~tlc
i n llic cstal~lislicdscatlci paltcl-n is correct, by oiing s IExciialion voltage, cilirelit
a dcdicuted mici-o~)ioccssoi,a moie inlorinalive @ AVR indicalions (locally, on AVI: ganel).
indication can be lpiovided lo ihc opcratoi.
0 Diode faiiure.

10.1.2 Pressure b Slinrt voltage.

I'ressuics are monitored as foilow~s:


10.1.6 Vibration
e Hydrogen in supply bus.
e Bearing and shaft movement
e Hydrogen in casing.
0 End winding vibration, using accelel-ometers o n sul,.
e Carbon dioxide in supply line. port beams.
e Stator winding water.

e Seal oil (and thrust oil, if separate). 10.2 Logging and display
0 Vacuum in seal oil treatment lplartt (if used). Transducer outguts arc received as inputs to the com-
puter at intervals determined by consideration of what
event could have czused a signal different from nor-
Differential pressures are monitored between: mal, and in what time scale tllis could cause damage.
e llydrogen and stator winding water. Readings may be logged oniy when outside ihc normal
range or, alternatively, readings within the range may
0 Hydrogen and seal oil. be logged at intervals.
The most moderr1 stations display only the essen-
e Fan inlet and outiei. tial information coritinuousiy to the control room
operator. Some systems display 'by exception', i.e.,
when a parameter falls outside its expected range.
10.1.3 Flow
All information is available on demand, on VDU
Flow rates of the following are measured: screens or printc1.s.

Stator winding water, by fiowmetcr or by diffeien-


rial pressure across either an orifice ai the winding.
10.3 Control
8 Make-up hydrogen (in some machines). The load and excitation control systems have already
e liydiogen through katharometer been described. The following quamities are common-
ly controlled automatically:

10.1.4 Condition monitoring * Hydrogen pressure, by spring-loaded valve, backed


up by spring-loaded overpressure valve.
Purity of hydrogen (katharometer).
Seal oil pressure, by pump pressure control and
s Humidity of hydrogen (hygrometer). differential control valve.

Humidity of exciter air (hygrometer). Stator winding water pressure, by spring-loaded


bypass valve.
Conductivity of stator winding water.
Cooling water temperature, by heaters and bypass
Composition of scavenging gases (katharometer). valve.
Quantity of particulate matter in hydrogen (condi- Gas-in-water detection, by timed operation of
tion monitor). solenoid valve.
Regeneration of dryer, by timer and automatic
Fig 6.90 shows a typical condition monitor console. valves.

10.1.5 Electrical Other parameters, such as water temperature, are I'


:3
commonly controlled manually, adjustments t o valves ?.
MW, MVAr, voltage, current, power factor (in being made as necessary when indicated values exceed i nc.6.90 condiiion monitor (NEI Parsons Ltd)
control room). given limits. (see also colour pllorograh
between PP 482 and 483)
I hi? generato,
Cl7;~1~1,~#
!,
-- - - -
i, and pioiectioil
Opeiarioiial lmeasureniei>t, c o ~ ~ t r omr?nitijrini~
70.4 Oil-load Illolliioiilig, deiectiol? ai?d otic iv m o r e toins ili a coil becoming siii>ii
diagnosis ciicilileii. (In solirc ~ililchincs,tliis condition ini;iy I>,.
Iletectioii aS abiioimal ci:iidiiioiii is divided bcrw,ecii coiiti~~ilousli inaiiitored.) Tile condition iiai.n,:ill!
two sections: oil-ioad delcction techtiiquei, desciibcd iiuiies ~eincdiaiaaioll hill i l is prodent to check ili:,!
hcie, and lecll~liqocs a'hicil air ai?l,iietl off-load. a( tile sililalioll is stablr.
stailclstill, or during inainienance, whici~are gl-oul,eil
witii Tests under Section l l of illis chaplei-.
Some equillment is i)iovideci so thal on-load cllecks 10.4.2 Core or condition monitor
cali be carried oil1 ipe~iodically on a ioolinc basis ill in this device (Fig 6.90), hydrogen is drawn iiiw
order to ensure that pi-evioi~slyestablished co>idilions the casing through a chamber in which a radioaclivr
Ihave no1 cllanaed. source emits a liormally constant rate of eiectl.olis.
lonised particles in the hydrogen stream, due to d~ihi
or iiquid aerosol dropiets, cause the collected currciii
10.4.1 Air g a p flux coil
to fall, and initiates an alarm at a given level. It is, i ~ i
A search coil monitors the rate of change of leakage effect, a sophisticated smoke detector. Tbc particle\
flux in tlle ail. gap as tlie rotor rotates (Fig 6.91). may be from areas of overheating stator core (hei~cr
The signai from one pole is subtracted froin tlie sigoai tile name) or from insuiation; they cali be trapped i t ,
from the other; significant diffcielrces are indicative
a filter and analysed.

I'ic 6.91 (coald ) Airgap searcl, coil aiir: i\,a,,efoiiaS

10.4.3 Insulation discharge and the condition investigated. If it is decided that


~l~~~~ techniques were discussed in section 9 of this a calculated risk can be taken to enable generation
o he continued.. a .
i.. orotection device developed in
chapter. ~~ ~~~

1987 can be installed. This will initiate a Class 1 trip


on the occurrence of a second rotor earth fault, and
10.4.4 Rotor winding earth fault indication minimise the damage from the high circulating current
and its connected excitation circuits that this would otherwise cause (see Fig 6.93).
The rotor
..-.earthed.
are not ...... ~.~ In order lo detect a low value of
insulation resistance while on-load, a biasing voltage
10.4.5 S h a f t current insulation integrity
of 30 v DC is applied to the 'positive! end
of the winding through a current relay, causing the In a machine with 'islanded' insulation (see Section 3
entire circuit to have a negative voltage to earth (Fig of this chapter), the integrity of its insulation can be
- 97>
h .-, l.f the o ~ e r a l iinsulation resistance to earth falis checked with a rnegger.
below 100 000 ohm (the actual value depends on
the position of the 'fault' in the circuit), the relay
operates to initiate an alarm. Operation of the rotor 10.4.6 Stator winding w a t e r analysis
FIG. 6.91 Airgal) search coil and ivavefoiins may be continued but it is recommended that the This water must be checked for oxygen and copper Con-
unit should be taken off-load as soon as convenient tent at recommended intervals.
552
a.
8
3 T h e generator Cliaptci I ; Maintenance, testirig and diagnosis
'@i
g amination is made. llefects greater t h a l ~2 mm shouid be pcrfoimed on the rotor winding, with siigrin&
be ground out, blending in the ground area so that brushes lifted.
there are no discontinuities. Finally, the ring must If any hot spots in the Stator coi'e are suspected,
be i-e-treated with its protective finish before being or as a reassurance exercise, a care flux test can be
refitted. Thc whole operation i.equires great skill and carried out. This may take the foim of an hour loll&
experience, and though it can be c a r i e d out at site, test with about lated flux in the core, using about
it is better done at the manofacturer's works, fol- 10 turns of I1 kV cable wrapped around the core
lowing which the rotor can be subjected to overspeed and fed from a suitable I I kV source, and using
and balancing runs. Thcsc comments also apply to an infia-red camera to scan the bore to lnonitor its
exciter end rings.
~ ~ ~~ " temperature. Easier, but less positive, is a low flux test
Examination of the stator core can be carried out using one turn of light current cable and a magnetic
by inspecting the bore for loose areas, u'hich can impcrfcction detector.
be tightened by insertions of hard insulation, or by It is not easy to ensure that the stator winding
treating with an epoxy-based liquid having low sur- is dry enough to make an insulation resistance test
face tension which will penetrate between the la- meaningful, though a technique of applying a vacuum
minations. Ventilation ducts should be inspected for to the winding has been used. A 2 or 2.5 kV motor-
debris, blockages and broken spacer bars. The back ised megger should be used, monitoring one phase at
of the core will reveal excessive welding of core to a time, and maintaining the test for 10 minutes so
core bars, or damaged co1.e bar insulation, where that the polarisation index can be obtained. It is
this is fitted. Some core back burning, and some not normal to apply a high voltage test, the only ex-
fretting products (e.g., 'cocoa dust') seems to be ception being after some damage has occurred, possi-
innocuous. The core liamc can be inspected for ob- bly with partial icplacement of the winding, when an
vious signs of damage, and patches of overheated agreed HV test on the remaining bars gives some
paint or metal should be investigated. reassurance.
Every stator slot wedge should be checked for tight-
ness along its whole length, using a tightness tester
developed in 1985, or by rapping with a coin or simi-
lar object to observe the expected 'ringing', indicative 11.5 Reassembly
of a tight slot. Airgap flux coils can be fitted or With the rotor reassembled, mechanical checks such
renewed at this stage. as alignment, axial clearances and concentricity of cou-
Stator end windings can be more thoroughly checked plings, and of the rotor in the stator, are carried out,
than as described in the previous section. Signs of and that all lolocng plates and other devices arc pro-
looseness o f packings, fretting, slack fastenings, etc., perly assembled. All jointing materials, such as gaskets,
are all indicative of movement. If there are unfilled O-rings, jointing compound, etc., should be renewed,
bans between coils, these can be filled with epoxy and the appropriate leakage tests carried out.
All such examinations of the interior must be sub- resin at this stage. The surfaces should be cleaned using It is SO important that small metallic items d o not
stator is possible. Inspection of the rotor surface,
ject to the rigorous enforcelnent of rules concerning a proprietary cleaner suitable for electrical windings, fall into, or get left inside, the generator, where they
particularly where crack initiation sites are suspected,
tools, the wearing of overshoes, etc., to ensure that but it is not recommended that repainting is under- could be drawn into the windings, that a strict ac-
such as the gaps between short wedges, should be counting system for such items is recommended.
foreign materials are not left inside. The statol. casing taken without the manufacturer's advice. If a 'worm-
carried out. Inspection down the radial ventilation
heaters should be kept on once degassing has been hole' (made by small conducting particles) is found, Several expensive failures have occurred a short time
holes to check that insulation packing has not moved
completed the particle should be removed and the insulation after a major maintenance outage, due to this cause.
to block the gas cooling passages, is recommended,
At these outages, seals and bearings may be dis- patched rather than left in, possibly to break through
following which the holes should be sealed with a
mantled for inspection, both for signs of wear and into the copper.
continuous strip o f adhesive tape, to prevent the
damage, and of electrical discharges due to the Dass- ingress of rlehri?
The state of the hoses and their connecting joints
age of shaft current. The inside of exciters can also
" ~

should be checked. A leakage test on the stator wind- 11.6 Diagnosis


Limited inspection o f the end winding is also pos- ing, using vacuum o r pressurised air with a tracer If the reading of any instrument has been outside its
be inspected, as can components in the various aux- sible, and signs of fretting, looseness, distortion of
iliary systems. gas, will reveal any significant leaks. It may be expected limit, o r caused concern in other ways, it is
coils, or movement o f insulation, blades or coils considered prudent to renew all the rubber O-rings, sensible to investigate its possible causes during an
A limited amount of testing can be carried out, e.g., should be looked for. If the pole-to-pole crossover
the insulation resistance of the rotor winding, using a both in these locations and elsewhere, if they have outage. It may be tempting to extend the operating
is visible, it is advisable to examine it for signs of regime beyond its normal level, before such an out-
500 o r 1000 V megger, and the IR of the shaft current been in service for several years. Care must be taken
fatigue cracking. age, in order to observe the effects, but this is not
insulation if islanded. to follow the .assembly instructions meticulously, as
End rings should be examined for surface crackine recommended, since a 'stable' fault has been known
overtightening may damage the joints.
and, by using ultrasonic techniques, for embedded to become 'unstable' during such operation, causing
The opportunity should be taken to clean the sta-
defects. The CEGB guidelines recommend that those problems when the unit is recommissioned.
tor casing, particularly at the bottom, noting if water
end rings which are not of 18/18 material should be Specialised techniques, some in their development
Maintenance and tests with the has collected, and checking that the flow to the leak-
removed after about 80-90000 h in operation, and phase, may be available to assist in suspected fault
machine dismantled age detector is unobstructed.
skimmed to a depth o f about 0.25 mm over the cyl- Insulation resistance tests should be carried out location, and up t o date advice should be sought.
If the outage is to be long enough for the rotor to indrical surfaces (but not the shrink face), following
be withdrawn, much better access to both rotor and on the rotor winding, using a 500 or 1000 V megger, Sometimes readings of more than one type may
which a fluorescent dye ('Zyglo' or equivalent) en- and on excitation windings. An RSO test could also be high, though not so high as to be alarming in
The geneiator Cli~![>l,.l
c,
"*.

iliemsel\,es. Wlien judgcd jointly, clues inay bc ob- wiiicli tile pliimbiiip atid insulated co~iocctioii<l i t i t ,
iaiiicd wliicii ii~dividualreatiiligs o~ighi inat have re- to witi~stsiid wit11 no detectable leakage. Siax~~Ir.,~.
/:
LAMINAill> RON COW
vealed. stecl ]pipes, with soine welds iiavilig Lo he n,:iciv i t , CONCRCii SiATOii
siiu, %,ere found to be necessary in the U1< expciieiwr
STATOR WtNDING
Neveilheless, watcl- cooling Lhc rotor windin: ; m i l t
other parts, for example, the stator core, may he ;ti! OUTER ROTOR

12 Future developments answer if unit ratings much above 1300 M W arc rii INNER ROTOR Wi'lii
SUPERCONDUCTING WiNDiNG
visaged. One difficulty, that of aqueous stress c o ~ VACUUM
rosion of rotor end rings, has been removed witli
12.1 Extension of present designs the advent o f 18/18 rings. A major advantage I\
that in an ail-water-cooled generator, hydrogen i \
The choice o f 3000 or 1500 r/min for future tuibioe- 1x0 longer necessary, and the casing cat1 be of rnucli
generators is made almost entirely from considerations lighter construction. The rotor can operate in a pariii~i
of the steam turbine and its steam cycle. In general, vacuum to reduce windage losses.
if a two-])ole generator can be designed and manu-
factured at a particular rating, then so can a four-
pole generator, its overall dimensions will be a little
larger. 12.3 Slotless generators
The present UK designs with water cooled stator
The very large radial dimension of the air gap in the
windings and llydroge~icooled stator core and rotor
660 MW design appears to be a waste of space, and
can be extended to at least 1300 MW by extrapola-
prompted much activity in the 1970s into the design
tion. Increases of the order o f 10% to the rotor and
o f generators with slotless stators and even slotless
casing diameters, electrical loading (ampere conductors rotors. lo s siotless stator, winding conductors oc-
per metre of circu~nference),magnetic densities and cupied a radial dimension of about half the stator slot
voltage, and pe~.haps25% on length over the pie-
depth, and since there were no teeth, could occupy
sent designs, would be envisaged (see Fig 6.3). The chines from a n established design acllieve a settled
twice the circumferential distance. This is economical At the higher flux densities envisaged, an iron core
increased diameter and length of the rotor result in reliability of better than 99%, and operate at an
on outer core diameter, and because the conductoi- offers no advantages and the disadvantage of the
the critical speeds and alternating bending stesses efficiency of better than 98.5%. Those breakdowns
bars are not embedded in iron slots, a more eco- magnetic core loss, so a cast 'concrete' core is en-
being similar to those of the present machines. A visaged. Some form of outer environmental screen which d o occur are generally due to lapses in qualit?
nomical design of insulation should be possible.
judgement would have to be made about the number around the core is necessary to prevent leakage flux control, or if in old machines, to practices long since
The idea has not been pursued, largely because
of parallel paths in the stator winding of a two-pole from inducing currents in support steelwork, etc., overtaken. Thus the impetus for embracing new ma-
it was overtakei~ by the superconducting generator
machine. If only two paths are used, the number terials and technologies is not great.
concept, which promised greater economies of size, this . . take
..... can ~~~ ~ the form of a n annular magnetic o r
of slots and bars is low, but the bar forces become conducting copper screen.
better efficiency and the prospect of much larger unit
very large; if four are used the circuits cannot be Many problems remain to be solved, and develop-
ratings than any other design.
exactly balanced, and circulating currents and losses ment is ongoing in several countries. If the technique
are generated. Parameters, such as reactances and cffi- reaches the stagc where reliability is as good as for 13 Other types of generator
ciencies, would not be very different from those of conventional machines, it offers the possibility of up Generators, other than the 500 and 660 MW turbine-
the present machines. generators and direct coupled AC exciters for tur-
12.4 Superconducting generators to 5000 MW in one generating unit, a prospect not
T h e phenomenon of superconductivity can be applied available through any other known technology. bine-generators, described in the ~ r e v i o u ssections, ill
to DC circuits, but cannot sensibly be used with the operation by the CEGB include:

.
12.2 Extension of water cooling rapidly changing fluxes and currents involved with
Turbine-generators of lower rating.
50 Hz (see Fig 6.95). It is therefore used only in the
Since water cooling has been used so effectively for 12.5 Auxiliary systems
rotor windings, where it has two advantages: Water turbine driven salient-pole synchronous
the stator winding, it may be wondered why it is not The most likely other areas for new developments
used in the rotor winding where space is at such generators.
The rotor I*R loss is reduced to zero are those o f instrumentation, control and diagnosis.
a premium. Water cooled rotor windings have been New tecllniques are continually being investigated Diesel engine driven salient-pole generators.
successfully operated; in the UK in a 500 MW unit The rotor current and MMF can be very large, so for instrumentation, and in the environment of a gen-
with a n experimental rotor for a few months, and that higher levels of flux density can be used than erator, the means of communicating the signal non- Induction generators.
internationally in a few units commercially. are permitted by iron saturation. electrically in order to avoid the pick-up of spurious
The more intensive cooling provided by water means electromagnetic signals and noise are very well worth
that smaller winding copper sections can be used, but A very brief survey of these groups follows
pursuing. Here, fibre optics are expected to be pro-
this increases the resistance and therefore the I ~ R The need to maintain the rotor winding at a tem- minent. Also, the use of microprocessors to relate one
loss. In a hydrogen cooled 660 MW rotor, this loss perature of 10 K means that only that amount of parameter to others, as previously noted, will become
is about 2.5 MW at rated load, so a worthwhile heat which can be removed by the refrigerant can more common. Perhaps automatic diagnostic tech- 13.1 Turbine-type generators of lower rating
reduction in section brings an expensive loss penalty. be allowed to pass into the rotor, so that elaborate niques will reach a stage where they can be used with Virtually all the steam turbine driven turbine-generators
There are difficult problems to be solved in feeding heat shields are necessary. Liquid helium is used as confidence, and selective recording of non-standard now in operation are hydrogen cooled. At the lower
the water into and out of the rotating rotor, but the the refrigerant, the windings being made of a ni- signals will be introduced more widely. end of the range, machines of 60 MW have a rated
major concern is that the centrifugal force imposes obium-tin alloy embedded in a copper matrix. The It should be recognised that generator design and pressure of 0.1 bar, i.e., just above atmospheric.
very high pressures (20 MPa) in the water circuit, rotor body is made from a stainless steel forging. manufacturing techniques are old-established. Ma- Above 200 MW, water cooled stator windings are used,
Otiiei types of generator
The aene!.stor cl>;?)>?,>l
1,
---
..
tbougli there are soiur onits i n irliicir l~iglier!pi-ersoic i'he coinpaiatively low speed incant large ditiiiictr! ...
lhydi-ogcn is biowt~thiongli the lhoiloa* candiictors aT and 081-silt asseinbly of tile slalois was es~c~iti;iI(w
the itator u,indiog. 1;ig 6.97). Air cooling was adopted, mainly S o ic;i
ill olllei respects, tbc geliciatois are \,cry silnilai sons of iciiabiiity. Paitl!, on account of illis. III,.
to tile larger, morc moderr, units, except tiiat tiicy aye stator ~rindingbars were unusually deep, \villi :I 1;iip
iess intensively rated. I n some cases, a degree of nuiuber of subconduclors, necessitaling a 540' l l o ~ ~ l ~ v l
refurbishment bas been carried out to extend their transposition. The core was stacked iri situ, being c o l i ~
operating lires beyond the 25 years or so already pressed with hydraulic jacks at intervals, and b a i ~ l c < l
achieved. logether for meciianicai stability
There are aiso a number o f gas turbine driven A fabricated steel spider surrounds the forged slrrl
generators intended for peak load arid synchronous shaft and carries the keyed-on laminated rim and polus.
compensation duty. These have ratings up to 70 MW, Great care was taken to ensure the integrity of liic
and are usually air cooled. The single-piece stators are welds, which are subjcct to a n uilusual amount 01'
o f lighter constriiction than is necessary in hydrogen cyclic stressing.
cooled units, and the auxiliary systems are minimal. Ventilation is provided by motor-driven fans blow-
In some cases they were designed for unmanned sta- ing cooled air onto the stator end windings top and
tions, so manual monitoring equipment and sophis- bottont, with some booster fans for thc centre of tlic
ticated logging is minimal. Brusl~less excitation is core. Water cooled beat exchangers are nlounted a1
universal, for reasons of minitnum maintenance, and the outside diameter of the core.
even the fuses protecting the excitation diodes have The thrust bearing has an arduous duty, having
been omitted. a load o f 510 tonnes and requiring larger thrusl
A noteworthy feature of the most recent of these pads, at the specific ioading, [ball had previously
units is the facility to disengage the prime mover, been used at the specific loading and speed. Each
or, in the case o f the Quad-Olympus units (Fig 6.96) pad rests 011 a 'mattress' of coiled springs, and is
ill which the generator is dl.iven at both ends, both arranged to pivot centrally to allow for rotation in
prime movers. Then, after a period of peak load gen- both directions. Lubrication is by oil bath and natu-
eration, the synchronous clutches are disengaged, leav- ral oil circulation, with an immersed water cooled
ing tile generators operating as synchronous compen- heat exchanger.
sators, with excitation controlled to suit the require-
ments of the system. When peak load or emergency
generation is next required, the gas turbines are run- 13.2.1 Excitation and control
up to speed and the clutches moved into engagement. Two variable-frequency starting equipments are pro-
vided for the station, each rated at 14.8 MVA, consist-
ing o f air cooled thyristor rectifier/AC connector/
inverter banks.
13.2 W a t e r t u r b i n e driven salient-pole s y n - On starling as a puinp, the stator winding is fed
c h r o n o u s generators with low frequency AC from the starter, using forced
Tilere are only a few of these on the CEGB system, commutation at speeds below 10% and natural con]-
but the most recent, the pumped-storage units at lnutation thereafter. It is run to just above 500 r/min
Dinorwig, rate a brief description to campienlent the and is synchronised as it runs down through syn-
water turbine section in Chapter 5. chronous speed. There are also arrangements for start-
The six generators are each rated at 330 MW, 0.95 ing one unit as a pump from another, being driven
power factor, 18 kV, 500 r/min, and have a motor up to speed by its turbine.
rating sligl~tlylower when operating in the reverse Excitation power is taken from the generator ter-
direction. minals, through a transformer to a thyristor bridge,
The very onerous requirements included: whose output is controlled by the AVR, and then to
the sliprings which are located at the top end of the
Full speed, no-load to full-load, in 10 s. rotor shaft.
From rest to full-load in 100 s. The synchronous operation of such machines fol-
lows very closely that of steam-driven turbine-gen-
From full-load pumping to full-load generating in erators. The electromagnetic Loading is considerably
90 s. less, leading to a smaller radial air gap. The very
different magnetic path presented by a pole centre
5000 stop/start cycles per year. line and an inter-pole gap results in marked differ-
hlultiple load cycling from 50% t o 100% for system ences in direct axis and quadrature axis synchronous
frequency regulation. reactances, compared t o a turbine-generator in which
they are almost identical; this is the 'saliency' effect.
Availability of 98% and mode change reliability of By applying excitation in the reverse direction t o
99%. normal, an increase in the steady state stability can
SUBJECT INDEX

Acceleration
leedbaek
aoverr~on.130
~ c c e p l i n c ecesir
cosdenscm.373
pm~edures.374
Acidcicaning
candeasers.372
AClUalOrpiStolls
governor valve ielnys, 145
Adiabntic now Wiih iric,io,,
pressure canlrol vr1vcs
noise. 21 1.216
Advanced gas-tooled rcacloli run-up, 134
iccdwatei Auxiliary sysieinr
fempcralaie. 46 generators. 559
sieanl luibirles i,,s,iumen,a,io,,. 174
sires, i22
Aii
inieakage
~ o ~ ~ d c ~ ~366
sers.
icskage lecdwaicliiesfers
mearuresies1.368 uenicnl. 301
leaks Baffles
locaion.367 d e - a c r ~ i i n g f c ~ d h c a 308
~e~~,
Air blailkeling lcedwaler lhcaiers. 297
co8ldcnSCrs.375 BRlancemeien
lubcncsls nittomatic voltage regulators, 525
colidessers, 352 Balelicing
rotors, 96.470
muili-olanc.97
dynamic. 97

Bars
Stators. 475.482
vibration
stator windings.548
Base level govcmois. 141
Rc.6.97 Dirlorwig ~nloroi-generatorduring site winding ~ icxtractjnn
r pumps Base load
(rce also colour piioiograpii between 1pp 482 and 483) condei,rers.378-390 neain iurbil,es. 217
A i r g r p flux coiis Baumann C X ~ ~ U S ~
gC""8,"'" binding. 68
moni,oring.552 Baumannexhausttuibines. 4

be gained, i.e., operation further into the leading


Aiinulnnr
, .
liq"id-""g
Beatingpedeslais
on-lincmonitating, I01
stalled in a few stations for emergency duty. The vibratians
reactive regime becomes possible. condensen. 383.388
generators are standard industrial units with proven Air nagna,ion instrumentation, 173
high reliability. The need for sudden run-up after long Beating suppons
periods at standstill means that brushless excitation foundations
Alarms 1IBVDU"ilS. 175
13.2.2 Other features and casing heaters are essential. governing systems. 134 Beatingr (rer also Journal bearings: Thrua bearings)
Other features peculiar to these machines include the Sicam iemperatures. 174 boilc~feedpumps. 405
Alignmen, forced lubricadon, 181
continuing integrity of stator bar insulation in a n air rnlan. 106.472
mtois. 103
environment, the continuing stability of the bonded Icchniaue.
, . 101
~leamturbincr.105-112
stator core and the built-up rotors, the vacuum ex- 13.4 Induction generators Ainmonia Blades
~Lea$ntidCc~m~i~n ciearnnccs
traction of dust from the shaft brakes, and the very These machines, rated usually at less than 1 MW, oificicncy, 12
condensers. 340
high overspeeds possible; e.g., a transient value o f 1.5 are used in remotely controlled run-of-the-river hydro officionev. 9
for Dinorwig. plants, and in wind generators on an experimental omrion, 5s
fixed
basis. Such machines d o not operate synchronously, conaiuciion, 65,66
but have a characteristic similar to induction motors i d a i impulse-~lsge
except that they run at above synchronous speed. A efficiency. 10
ideal ieaciion-sage
greater input from the prime mover increases the
13.3 Diesel engine driven salient-pole power output. Like all induction machines, they draw
efficiency, 10
lcnph
generators their magnetising current from the system and there- turbine efficiency. 29
Arcto" 12
These machines, with ratings o f a few MW, are in, fore d o not require a n excitation supply. air leak d~lcclion moving
condenscn. 368 construcBon. 65.66
Subject Index
-
101pICsSUc~
s l e a l ~erblne
i casings, 86
CC011011iiCb.44 riea~miurbincr. 4
Cooli81g wntcr plant. 321~421 siipponr. 87
C~l~peralioys Cylind"c1 nrlor gescraiois. 447
Colldenrcrs. 333,340
lubc faiiuie, 336 Dalnpcm
Core end nlaies 1010rs. 464
statok.482
Cure frnme ham steam lclrhiner
SlalOi' cfficiescy, 13
insulaiion.480 Display units
cicaning sysienis, 366 core frames
iiiundation.354 generatom
salon, 476.481 innruinentarion.550
lubeplaic joints. 363 easincs.490
llibing Di5,""lion f~clor.455
lhcnnai perionai>cc,37i ~ ~ " ~ t r ~ ~ t i o n Dislncl heating
lurbiaejoints. 365 fedwater lhcaiingsys&mr, 308 steam tiirbincs. 118
Cosdi,ioii lines clcvnlion, 275 Doublc rcheal
seam turbines. 13 feedhcnlen. 305308 Rankine cycle. 30
Condition lmonifol.ing graiil-orieiiied slecl. 475 feedwater hcating sy~cms.250.27238i Dran tube valves
Cormrion (sac also Firesidc con, water level. 253 pump-iurbiscs. 444
gescrstors. 550, 552
Wa~c~idccomosio~) healers, 272.274 Drain "al"es.210
inslrumcniation, 551 cm1inc water
ixl~irumentatioii,174 pipework. 279 Drains (see "IS" systeni diailis)
pEve!llios. 333 pmtection systems, 277 ~olin"0iis.2m
Conducion
eyclonesepararois stornge lank. 272 feedwater
low pre~suie lhealing
fccdwaterheains
syslems, 268
siaton, 481
Colllaminntion wetsccam turbines.230 tnnks
inhibition sloshisg.274 forward pumping. 282
chemical
lubricaiingoils. 193 waienprayislca~niitjectian-lypc, 50 stan-itp. 2 m
hydr8ulicnuids. 153 journal bearings. 108
water Debris slalon. 491
C ~ r n s i o lfatigue
l condcnsen. 370 waicrflow
ihydrauiic fluids. 153 Col>dcn$~r$. 340
Coiami unit iypc I filters con,rol. 2 m
Canorion fatigue crac&ing condensen, 366 Drains cmling. 46
governor valvereiayr. 145. 146 condensen.339
Control unit type 2 Dininr pumpills
Cormsiorl resista~~cc feedhealing. 46
governor valveiclays, 147, I48 chromium slceis D,a.ssys,ems, 2m-210
..
Control unit lvne 3 blading. 72 wet steam turbines, 237
governorvaivc relays, 149 litsnium
Control valves Drax Coinpleiion power station
fccdwater heating systems Couplings
hladisg. 72
"~
DeiolliSBliOn
". . feedhcalen, 247
fcedwarcr heaters
tow PrOSSYTC f w d sysiems, 285 bols. 102
Coolers feedwater hcating syssms. 315 pipework.273
iloxiblc. 101 D~mincrali~ers Drmpadjusunenl
hydraulicnuids hag( 102
govemingsysteil~r,15i spced imp. 128
rigid, I01 stator winding cmling rynems. 502 Drum rotor. 9
Cooling (see also Aircmling; Porccd-aircwiing) scmi-nexible. 101
roton Deruperliealers Dry SlSgeeffiCiienc."
shah leiieth. I W gland sealing syrfcmr sicam turbines. 16
inlennedialc pressure. 93 rrrist-on, 102
sfcam fuibiner. 224 cooling water 202 Ductility
steam tarbi,as.Y&~os glmd seam. 203 biading
chromium steels. 72
thyrision.522 Cover rcsls
Cooling ryslen~s(sarnlsoE~hni~slspiay tooling sysless) gland ieinpcracun coniml. 2 W
slcain chests. 158 Deleigesir Dun~ppistonn
healed water discharge dirccl-cooled. 324 Covcrb~nds
lurbilicgciierators. 491-5M iuhricotisgoiis. 194 govcrnorvaluerelnyi. 145
arc), Diapllraplnr Dump tubessysfenls.212
hy-pars
cooiing ,owem blades. 68
ccollomi"~.44 connn,c,ion.70
blades cyliadcn. 87 Duplex
lubricating
filters oil. 190
heat dissipation, 324
Stearn Lurbinci, 65 kiilenieic suppon. 70
Cooling watt, creep
culv~nS"stem radial supponpads, 70 Dynamic stability
mion, 92.94 stvam turbines excitation systems. 530
Creepstrength gland$. 87
blading suppan, 70 Eanh le&age
chmmium aeeis. 72 Dichlomnuoromethane dctecfion
C"ics1 speed band8 air leak detection excitation systems. 517
steam turbines eondensen. 368 excitation systems.515
foundation movcmcnt
sovemingsyslcms. 133 Diesclengines Eccenfticily
monitoring, 175 C"iic*l speeds
hirroricai devclopmens 329533 salica-polegcncrafon. 562 shafts
instmm~ntalion.173
mron, 97 Diffcnsislcxpansion
iniet tCmmrntUre Currentmeasunmeiil
cconomie oplimisalion.44 swam turbines sfcam turbines
excitation system. 515 run-up. 133 protection, iM
economier.43 Cyclone separator^
layout, 329-333 Diffus$m mn-up, 133
high velocity boiler f w d pumps. 407 Economics
leakate
wet steam arbiner. 231 Dinonvig powcr stallon urndenscrs. 3211-329
condensers, 368 WE1 Steam turbines. 230
pumping faligue life. 439 Econ0miy.n
Cvlindan feedhcating, 45
costs, 43 guide VMC8.443
boiling. 84 machine 1ayaa1, 439 ~ d d current
y losses
pumps. 324 efficiency, 13
capital casts. 42 main inlet valves, 442.443 stator cons. 476
steam eveic. 22 pump-rurbincs.440 Eddystator conducton. 482
currents
qualily
cnvironmcm. 333 pumped starago. 433
LempeTBLUR sation. 438 inswmcnta$ion. 173
Efficiency
gcnoraton. 550 site plan. 437
statistics. 445 Elccrricmolon
Subject Index

n,,,,,i,,g C"lli. 55
valiablo-speed-n?olo~.ddiiiii
~ * ~ i l costs.
R l 57
economics. 51
eificiilcy ">",lint COSIS, 57 ~ ~ ~ i - f ipianl.
r e d 46
Electrical cmsian ~ e suction
d Ivmps oii-iired piant. 46
i o u r , ~ bcnrisgi.
l 108 b ~ i l c r f e c dpumps. 412 ~rgen~r~!iuC. 242
Eleclricili lrijiping Feedwater ~c0no,"ic1.45
LUrbillc1~101cClioll,167 ~~n,al,,ina/i"l> Rnnkinecycic.?l
Eicciricii" dislribiiiinn
AC v; DC. 447
ccor1omics.41
Rsnki8iecycie. 28
pmiectio#~,
do-aeration.49
255,259,281 ua ~ .
. .. seam cvcic. 46
Fecdwacr hcnling cycle
Ele~lioinagnclicinductioil. 450 Steam cycle tcinperaluie CEGB, 33
Elli~)seiaw economics. 40 d rcacton. 46
a d u a ~ m gas ~ ~ ~ dlbeaiing
~ e plalil
e r
oufpul, 8 noain ,urbi,,es F~edwalelheaderS p~Oieciion qnipment. 260
Emergency siog heat ram.41 10," plCSBure ~ ~ ~ dlh~ating~ ~ systems.
t e r241-322
turbinepioteciios. 172 pmtcction, 164 flow area.311 design parameters. 250
Emergency ,tip valves ttips, 165 t~bcthicknessos.310.311 camnoncni loucls, 251
on-load resling, 166 unloaders. 137 ~Ii~lls
turbine prulcctioi~,166 unloadinggcai. 130 constmaion. 310
Elid " g r Exhaust rprny cwiing syscernr
mrara. 460 low presstire. 206-2W
End wi,,dings ~empeis~uree~r~cml
SlillOTS
suppon1,483
aucomsfic.207
Exhaust $team .~
...- .
parameters.26i
Enthaipy-entropy lliagrarns low pressure bled-neamin~cir,297 iiigh pmsruic feed system. 320
Rankinc cycle. 18 iernperature control. 207 %tiah Standards, 289 iow pi0SEUrC, 321
Blliopy. 18 Exiiausis c~ndenringsectionr,299 low feed s y s l m
Environment steam iurbitlc casings. 85 de.e-aoraling.305-308 iubulnisrlai-etype HP henlcrr.252
condelnseis.333-341 stesnl turbines, 4 de-aoraton, 289 water COnlOni
Eroriol~ Extenlal eificicncy mrimcnance. 253
biadcs. 75 cyiinders. 13 ~ ~ " i t si~iniess
ic imn
progression.76 E~llra"lionp","~s de;dopmeas;s3 bladillg
shieid nlatetials. 76 condensers. 4CU402 direct contact LP w ~ ~ n e aibincs,
an 229
CYCID~C SCpsralOrs con~ponentlove! diagram. 251 Ffe~fi,,iogpWCisladon
wet ~lcainturbines. 230 Fans drain cooling sections. 299.301 ,,~~pedslorage.433.414
hydraulic mrbines. 423 mt015.465.470 drains. 210 F ~ D~ I ~~ r r cmcasvrcnlclil
nt
pr0,ection
welstean Lurhines. 229
Fatigue nrrrc-~ .
~ m ,n l e t i o noowcr siriion. 241 ~ ~ e i ~ a tsystems.
ion 519
mlon eievstion, 254 Ficld lead wedges
Es~heleCRM12 generaton, 544 final feed tempoiaturer. 28 m,on
hiading.12 Fatiguecracking flooding. 51 generaton. 543
EVBIKIT~~O~S journal beatings. 108 flow-induced vibration, 296 ~ i o l suppression
d
bled-steam Fatigue strength ciain power station. 245 generators. 547
fccdwaler heaiingsystemr, 316 blading ~~~~h~~ 2 AGR power nation. 248 Filrni
nash.316
venicsl-Iktype. 316
ehrorniu~?l
Fault cunents
steels, 72 hi-h .
...- orosnuie. 46.51.289-305
con~t~eiion.292
icedwaier henling sysccins. 315-3 17 generalon. 539 hotizonLal. 299
aswmbly.319 Fced pumps t h ~ m ~dcsgn.
al 291
nasii back-pre~~urc lube thickness. 292
fecdu,;iler healing syrass. 319 Steam iisbiiies. 115 venieai.3Ol cooling water
nasiltype condensing-type I , , ~Rc power station. 244 ~ondenscm.372
lcedwarcr healing sysicnis. 317 sieall turbines. 116 ~ i t i l e b m o k Dpower nuion. 246 hyd*"iic nuids
singie-stage low pres~ure,51.308-314 governing systems. 151
feedwalci hcnlingsys$cms.318 bled-$team i"ltIS, 3 n ~ i n afeed
i temperamre
rurfnce cype cons~ruefion.3W reedwater huliinz sysccms. 250.261
feedwater heating systems. 317
Excilalion
. "
economies. 57
dircct mnuc1.314
dished ends, 314
AC turbine goncralon. 506 induction-mocoi-drivenm drain ou~lers.312.314
adaplivecontmllcn. 526 capita1FOSIS. 57 cxtemsl drain cmlcrs. 312
conuoi. 526 e&nomics, 5 1 hotizornal-at~itudemmgoment. 283
future dcvelapmenis, 560 runningcosts, 57 shellr.314
turbine gelicraion. 5 W 5 3 2 margins. 54 SUM type. 308
Excitationequipmcnr moio~dtiv~n thermal design, 312
stsic rceiificrs. 520 thermodynamic effeea. 56 lube lengths. 31 1
Excitation System$ number <ubesupponplatcs.311
analyiir.530 economic%.53 lube suppons, 31 1
brushless size low pressare direct conlacl, 289
turbine generators. 5W economics. 53 low pressure abed. 289
EXC~LCT field S W ~ L C ~ C S steam turbines, 115 on-~osdtest facilities. 269
field suppression, 547 lhmugh-iifccosts. 58 pipework. 273
Excilcrs (see air0 Main exciron: Pilot cxcifers) lurbinogovemon. 156 prOstu"red water reacton. 48.249
A C voltage regulation. 523 lurbincs shclls.292
DC lurbino gcnmors, 5 M exhaust mute. 156 t h t m a l efficioney. 22
DC veilage regulation. 523 power rating. 157 cube lengths, 295
gear driver steam supply. 156 tube suppons. 295
lurbino-genera~on.504 vatiahlc spcod,54 akplate-typc hatizonlal high prcnsurc. 52
porfomancc testing. 508 variable.spnddrives tubular surface type. 254
transiencperformancc capital costs, 55 component leveldiagram. 256
turbine-gcnoiarars.506 eloettic moton. 55 wat~~to-~~te~drain~~I~n
t
! Subject Index
i --- ---
Coiiilo1. 205
i'1asgei Furca
*,aceiiil~bilie dri\,cii saiie81i-jrrlc rysciwonour. 560
slcaii cu~biziccnrii~pr.82 blows
G i n ~ ~reiling
rl systems, 200. 201
1:1as1iil8 draill C W ~ ~ ~ s detector syi~enl.515. 516,519 ~ p r c s u coii!iol,
z 2W. 203
lo>%'I""6airC feedwaicilicnieri. 306, 312 fnilille
$lean, lurbiiici. 19820.1
Illcrmai Ihydiviilicdeiig~i.314 deiecliozi ii~,ic,52~ ,e,llper"luie Control, 200
Fl~xibilily TV 44R
Gland steam eondeaseli. 204
stcna,iuibi~?cs binding. 72
G i a n d ~(see also Labyiyiill gliindr)
dssigr~217 FV 507
boilci feed pv8llps
cfficicncy, 39 bladisg.72 realing.408
noiv slea~nfuibincr,i98
corldcnsen Governillg
n,eilsurcn,est. 374 eloeimnic. 134
gencratoir highprcrsure. 128
insirumentatioi~.550 higll pressurn plus intermedinie pressure. 128
nlCilSUmmCn, parallel. 128
cirnuialillg i$,siei puxaps, 397 Govemingrysiems. 125-157
curbir>cs combined-cyclcpla~>l.118 digilalpmcerring. 140
dircclian.2 Gassing-up
functioss. 125
Piuidcouplingsiilr hydrogen coalii8g systems inecllasicai
reed pumps turbine generators. 491 reliability. 134
Gearboxes
vaiivble spccd driver, 57 Steamturbines
Fluoie~cein air extraction pumps. 395 o u e i ~ p e dpmfecBo8i. 164
cooliiig wii,ei ciict~la~inp water pumps. 398 Govcrn~ivnlverelays.142
ieakngc. 369 iced pumps conlml aniciype I , 145. 146
Flux variable s p c d drives. 57 conlml unit i y p 2. 147. 148
S Y ~ C ~ ~ ~gencmtois.452
~ O Y S
Ocnersloi phnsoidiagrams, 535 colitml unittype 3, 149
Flux dislnbulion Generalom, 446-562
20MW Gov0n10rvalves. 160. 162
GCIIOTRIOrS ~~~~

forcer. 145
on ioad. 545 aircwled. 449 guidcdnow lypc. 161
Foaillisg 6MiMW.448
high preasurc
i"ilibifi0" Cescmlars (sea alsnQuad-Olympur gentraton: Synchronour on-load leriing. 132
labricarisgoils. 193 geocrators: Turbine-geserutors: W i r ~ dgenerators) ii,,crmedialeprers"rc
F0:oan,s condition monitoring. 550 on-load ssiing, 132
conim1.549-555
coaling water
fulvie dcvelopmcntr. 560 .
muslliwin ivoc. . 163
leakage. 369 pressure dm],. 8
Fo~ced-ai~cwli"~ DC, 114
revene now. 163
diagnosis. 555-558
main turbines. 224 throttling
Forging eEciency, 536
flenibiliry.222
,itanium elecl"c1 aspcct~,545-549 Oovemon (see also Basc levol govcrnorsj
blading, 73 ~ l e c ~ r mcasuremenl.
i~sl 550 acceleration feedback. 130
F o s ~ i l d i c dplan, cleeltically unbalanced co!~dlfions,537
characleristics. 126
by-pars ayslen>~.213 electmmagnclic aspmu. 545-549
failure
Fouling exciter and power systems, 527
pm,ection, l M
biolo~icsl charaelcrixics. 529 iilicr-valv~monilorin~. 137
cosdcnsers.370 fixed speed AC. 114 speed rnfercnee. 131
condensen, 370 fu~uredevelopmcnts.558-559
s p e d reipoinir, 129
Foundations induction.562
stcam ,"rhinos
CDDCrele. 177
iotscs. 536
nl~dulaia"angement, 157
iIexiblc.l76 mainici,ance, 555.558
turbincs
resonaiicer. 176 mccllanical c ~ ~ l ~ i d e r a f i o541.545
nr,
feedpumpr, 156
spring. 180 nlonitorinp, 549-555 ~ r a i power
n station
Steamarbiacs, 175...181 on-load mosiioring. 552 fcedheaten. 245
movcmcili. 175 Open-circuit eondilions. 533 Gmses(srenlsoLilhium-bascdgieascs: Silicolie-barad
operalion.532-541 ficcasesi
operational measurement, 549-555 types. 154 . -
lunisg. 176 ourages purity
Greasingsyslems
Fourier equation mainlcnance. 555 steam lrbines. 196 monitoring. 492
hcai transfer nmleciion.549JSs Gril cleaning safety. 497
ieassembly. 557 temneraturc
condensen.347 condensen. 373
Fracture appearance transillon temperature running up 10 speed. 532 Guidcvanes monitoting.492
saliea.poie Hydmgen c w l i n g
mion, 96 Dinowigpowei station. 443
Francis turbines. 422.426 diesel engines, 562 pumped storage.441 Slalors
end thrust. 426 shuuing down. 541 vriable windings,488
Freon 12 slollcs~.558 tempraturn
tabular turbines, 428
sir leak detection speclfiesions, 449 trips. 554
Gundrilling
~landards.449 turbine-genoraton.447.491
condensers, 368 water headen
Frequency responseanalysis SlOsdy shon-circuit eonditlons. 535 tubcplaos.263 Hydmgen embriltlement
exCilslion systems. 531 Steady slale stability, 534 mton. 94
Fretting superconducling. 558 Half-sped machines, 229 Hydmgen pressure
mton Synchmnising.533 goncraton
instrumenlaion. 550
Halagen lcak detectors
lemperature.536
air leaks
IcsIing.555-558 Hydmgen seals
condensem. 367
transformers generaton
Hand baring
winding fault^, 554 turning gcar, 1II lubricalingoii. 183
arbine-tvoe lubricatingoil, 188
Harmonics
lowoikting, 559 chorded windings. 455 HysLern~i~
lYpoS.447A50 dislribula windings.455 stator cores. 476
unbalanced load faults. 554
generaton. 546
Subject llidex
3 Index

S'C"tII iuibincr, 198


slewed, 199 Magllciic ainplifcri Oil COillesceiJ
t i i ~ 8 1 ~ i c 199
k~~~~~, c~ciiationisysleiiis. 523 hibricsiisgoil, 191
vcnlier, 199 MagnClic circiiiB s,a,ic. 193
i~~tb"ti,,ti,se*,* ~ y n c h i o ~ ~gcneraoii.
ot~r 452 Oil co01ers
iubricaiii~goil.189
Magnelicpuil
genCmio15.547 oil fiiiers
1ubricari1,'oii. 189
FCncraiOrs. 549 Magncfostrietion.545
Main cxcitem. 510 Oil-fired plane
jolimal kanllgs. 105 tip iefirninc. 61
stealn v ~ r b i ~ a r pmtec,ion.509 fecdhcating
Bosl-incident records. 175 ?numberolnagcr. 46
efficiency. 13 rotating nmaiure. 512
Profeclion alld control equipse~ii,17s Oil pumps
arbines. 112.175 Lappin'?
~. . turbine genoraiors. 51 I
Stcam turbine casings. 90 luibinc gcneratom, 508 lubrication
e l a ~ ~ i f i ~ a t i 171
oti. main. 184. 185
Leading power factor Main inlet V B ~ Y C S
generators. 534 D i n a n v i g p w e i stsfion. 442,443 main bearings. 183
Leakage nows pump-,urbi,ios,439 ~teamturbiacs,184
generaton
by-passsy%cms. 216 Maintenance mafor-driven auxiiiaw. 185
>~~aintenance.557 Oil purineis
Leaving iosscs steam iurbinos
monilotiiig. 553 lubncaiingoil, I91
Rankine cycle, 28 efficiency.39
mior windings, 459 static. 193
mtom $lean>turbines, IS turbine-~.~."cmiors
Life cxpendilure mol,iton cost1 42 Oil scnlirlg
windings,548 nedeslais, ill
stator windings.548 stcan, iurbin~e,224 Majority voting circuits. 137
Lighl-water reacion Master iosd mnlmllcn
dctenoration,s49 bdlcm. 129
lntegr~lcondensers, 4 half-spmd machine$. 229
Lithium-based greaser steam turbines Oii tanks
Inler-vaiu~m~~i~~~~,~
SlCBni turbines, 194 boilerprcssurcconirol. 129 l u b r i ~ ~ i i n ~ o187
il.
govcmon. 137
llilemai efieioncy LilllcbrnokDpowers(ati~~ Materiai damping
cyliildcn. 13 feedhoaccn. 246 biading
imli oxide Load chmmium steels. 72
condcnsen.336 awlication titanium
isceo>i 12 sencrators. 533 blading, 73 orciilarions (we niso Power r y r ~ e mosciliaiioiir)
b a d angles Maximuniconrinuousmting isrei-area. 529
air ieak deteciioli inlei-tie. 529
generaron. 514 syi~chronou~g~cralois. 452
COndcnscrs. 368 inirn-pianimodes.529
lsoialingvalve~ hadcyciiiig Mean teinpeiaturcdiffcrences
stearn turbines, 217 cOndenScrS local iiiodcs, 529
by-pass sysiems. 21 I ~yslcinmodes, 529
Laad rejection cor~troilcn Standards.345
feedwafer heating systems, 266, 267 Outases
by-pars systems Mineral fibrcs
low pressure fwd systems. 28s lagging
nuclear piant, 212
Jacking oil pumps. 18s Load shedding steam turbine casings. 90
Jacking oil systems lhmfiiing, 8 M i n ~ r aoils
l OU,~"~
Losding~ystem~ stcam turbines. 194 sLoamiurbines
s l a m lurbincs. 194. 197 iimifaions. 8
Join* governing systems. 132 Mobrey float switches
iasatithmic mean tenaperamre differences fe~dwalcihcaling systems, 269 overnuxing
condensem, 343 Moisture separator rehealen avlomalic voltage regularon, 527
Logging ho"n0lal Oven&
SCllelalOTS wet rieam lurbines. 235 p i w f test
instrumallation. 550 wet stcam turbincs. 230 lurbinc proleaios, 170
LooppiBos, 157.162 Moliierdiagrams prOleclion
i o o p pipewol*. 160 CEGB eycies. 31 steam turbines. 164
luhinccasingi. 81 Multi-exhausts protection systems
ilonranlal bollilig pressure feul sysmms
feedwaleriicafingsysicms, 281.289 blading, 68 govcming systems. 132
~ ~ I s l e aturbines.
tn 229 MUSSCIS fe~ling
govcniing~yst~ms. 132
welded confipuration.281-2x9
contmi valves. 283 cmdcnscrs
Stalorcilsing~.489 Ovenpecd
govemingsyslemr.
itipn 125
Journal bearin*" isolating valves. 283 conlml. 373
". c w i i n g water. 336
consruetioq, 105 Lubricatingoii~
acidity. 194 sicam turbines
perfomancc, 105
Steam turbines, 105 fai1uci . .
Network freaucnev
power generalton
governing Jynems. 165
turbine pmiecrion, 170
life. 108 tripping. 165
governing systems, 125 Oxida,ion
Journal type seas 1%" pre$iUre ",ps
turbine pmfeedon. 170 Neufralearthlng inhibifion
Iubricalingoils, 193
hYdmsen cooling systems
purification. I92 generators. 540
'Urbino generaton. 497 Noise lubri~alingoils.
Oxidation inhibiton193
regeneration, 195
Kaplan turbines, 422 steam turbines genenitom
hlailrr pmleeiion, IM roton.54s Oxygcn
rquircmens. 196 p r e ~ ~control
~ r e vaives fcedwaier
tYpcS. 193 by-pas$ sYEICmS.211 cormsion.49
Lubrication fossil-fired pianl, 216
Steam turbines Non-return valver Pannier condensers. 4
arrangements. 181 de-aeralom steam turbinceasings. 79
rquirerncnts, 181 bicd-scam pwer.assisled, 278 Panial admission
Lub"~tion~y~tem~ Notch sen~ilivity steam turbines
Labyrinth gland$
steamturbinos. 181.198 blading efficiency. 16
axial-radial. 199
diamelem. 2cq chmmium steels. 72 Pedcsfals
now. zw Machine levels Nuclear plant beaings. 108
plain, 199 instmmc~a~ion. 174 by-pBBr SySlemS. 212 oil m l i n g . II 1
Nuclear slcam rupply system. 33 steam turbines. 105-1 12
radial clearan~o,zw Machining
timnium Pciton turbines. 422,423
spring-back. 199
blading. 73 Oil bOOSsr pump8 Phasoidiagrarns, 452
turbine.driven. 184 Phosphareesten
Subject Index
-.
-- -- Subject Index

rllrfis.456
shrink-on.91
sires. 472
1Prolecii081.508 ~ t e a n iiiibiner.
l 90105
tt~rbinegenciaiors,s06 rei,ea,e,s, 149
Reliability flexibiliCy.223
Seclio". 507 "oilagCS.547
Pillrlcdimtr PtlrliPa(rrea1soAiicxliaclion jpum~ls:Aiipuinps; Boiler feed govenlitigsystcms
deR81ition. 134 teetii
blader, 69 ipumi>s:Caisson enlraclin#?jptimps: Centrifugal
pumps: Cilemical irUeciion pumps: Circulaciilg steam lurbincr lensiieslrers.542
Piixwork Oer oiro hp pipeiuo,k) ihermai 96.456
icslisg. nnbilily.96
cmsrover. 163 wateii,umpr; Coiicreievoluic punips; coxidenrate eriiciency. 39
de-acraiors, 279 exiinclio~ipunins: Extiaciion pumb>s:~ c e punips;:
d Rclicivalvcs
rehcnlcis, 149 threading.470
feedwalei hcaiers. 273 Feed suction pumps: Fire pusps: llydravlic pumps:
Jnckizig oii pumps; Oil bwsrerpumps: Oil pasps; Residual inarnciism torque
fced~agrhealillgsyslem~, 271 g ~ n ~ ~ a t542
on.
govemingsys~ems Ptiming pumps; Rotary pumps): 323-421 shafts
C",,rlrnsrrr ?"P-?"n geneia,on, 547 turbine-generalois.456
sl~inlesss~ccI, 154 vibralion.470
Rerisiance elements
tow pressure feedwaicilieatiiig ryscems, 288 weight.472
leh~alers Icin~ialremOssuiemCni
gencra,ors. 549 windings.
welded disc,
459.463
91
pressure loss, 27
Piping Re~ollance~
foundations. 176 ~0il~.459
lubricatinpoii. 188 can18 faull indiealion. 553
Piston iinqs Revemible pilmp-iurbines. 433
Rigidity slip-stick. 5 M
sleamiurbir~ccnsiilgs, 85 lempcrntvremearurcmeni, 466
Pisloycs$ts foundalioss, 176
Rim generator turbines, 432 vollagc. 548
stators. 476.478
Radial ruppan padr dcsign.431 Routille operational tcsis
Pilch factor, 456
diaphmgms.70 R W I imus condensers. 373
Plantoperaiion
turbine-geneintors Rnnkiaecyclc, 17 cxcitation systems. 531
cosls, 42 finai feed t e i ~ l p c r a c ~28
,~~, Rotary pumps
Plan1trip c o n i r o l l ~ ~ superheat. 19 ilirexlracli~n
~ Y B B S ES Y S ~ S Reaciancer condcnscn. 381
generators Roiafmgan,plifcrr governing syslems. 125
nuclear plnni. 213 Runaway speed
Poie face wedger calcuiaiion. 546 OXCilCm
conlmi.546 lurbinc-geaorarors. 504 hydraulic lurbinas. 423
genoi~lon,543 Rvnncrbiadcs
Post-incident records ReeriSerequipnienr Rolalingdiodeiles
saiicdiodc~ excitation rystcmr tubularfurbiner.428
insImmcnta,ion. 17.5 Ru~liiihibifors
lubricafing0ils. I93
Powcigei~einfion exciinlion equipment, 521 moniforing.519
mechanicaldti~~ Reclificrs (reeniso Rolali~lgreciifien; ~ , ~ ~ i ~ RoLalingphs~~r~
SlOBln IUrbincs, 114 Thytislorieerifiers) 1yn~hmno~sgcncralors.452
cicilation systcms.516.517 Roiarins rectifiers Safety
network frequency hydmgcneooling. 497
pmieciion.52i exciladon
€ovcmingsysrems, 125 turbine-gonora~on.513 Scale
seain turbines. 112 SIali~lhy~~~~rs
excitation sysicms, 521 excitation systems condensers. 370
Power system osciliations, 527 cleanine 372
Power S Y S ~ slabiliscn.
C ~ 527 Rchcaf pmtecion, 519
Camotcyclc. 30 Rotom scavenging
operation. 529
COlidili~,,~ alignment, 103.470 hydmgen cwling Sysccms
Pre~suie
slcamcycie, 26 R~iaipasiii"" turbinc-genernloir.49 1
colidcnscm
dllllble inr,mmen,a,ion, 173 Scieeniogpianr
acceplance ~css.374 coolillg waicr, 324
generators Rankineeycie, 30 balancing. 96
fin,-stage body.456
insirumeniaiion. 550
Picsrure cascading wcl Steam lurbises, 237 bmshlers
second-siaec conncciions.469 Seal oil prcrrurc
feedheating.46 gcncrstom
Pie~~umcOntmi wetrteam turbincs. 238 buill.up. 91
Reheat cyclc. 20.26 eonstiuerion.90 inammcnta,ios, 550
hiiers. 129
CEOB, 33 cw1i,,g,93 Seal oil rvsems
Presnuie control valvcr .
r., ir,g:n :u np <,-,r, l.
Reheaters criIiealrpeds, 97
~ Y - P ~ Ssystems.
S 21 I l L n l c c )cn:rl.lr' $97
draills current iimilers. 526
nuclearplant. 212 S:A .e* ' 1 . L > b ) o n m % ? ~ l .
spraywater wet sleam turbines, 239 dmm type, 91
eCollDmic1.59 ondrings, 464 mechanicai
fossil-fired plant, 215 h i l e r feed pumps. 41 l
Pres~u"~ed waterreae~o~ governing vaives. 128 fans. 465
pipework fast fraaure mfon.472
feed pumpsets. 416 ~ ~

steatntuaines, 198
feed SySIemS PrCSSUrelols.27 tisk assessment. 98
Pressure loss. 27 gcnerafors seasans
cycledotails, 242 cooling water
feedhealors. 249 reliCf V B ~ O S 149
. maintenance. 556
s t e m Supply residual magnetism. 547 temperaarc. 44
hedwatcr hesten. 48 Secondary ioss
seam cyclcn. 33 we1 sleam turbines, 237 high presSU'e
Stcam-to-steal,, ma~erials.94 blader
turbine-gencnton.40 efficiency. I 2
we, s t e m cycle. 46 peifamance monitoring. 239 ~ l r c ~ s m n t m129
i.
high tcmperarure operation. 92 Sclf-shifting Synchmnouscl~l~he~
w c l s l e m plant. 62 wet steam turbines. 233
valve$ inlcgral. 99 cuming gear
Ptimingpumps Steam turbines
lubrication. 185 PTDSEure IOSS. 27 inlemedialcoreseure
venics1 Semicondu~ton
Proflie 109s
wet steam turbincs, 233 static recliiicn
blader
Rchcaiing cxcitationcquipmont.520
efficiency, 12 Se~aralon(see also Cvelane seDaralon)
Roleciion steam tuaines
candoasen.366 effrcioncy. 114
Pmtcction and conlml equipment Rohcafingplant
double-scage, 37 cormgated-piarc
inrmmentation, 175 wet steam turbines. 232
single-stage. 37
drains
t
I -
Subject Index
Strbjed Index

main excitem. 508 cioscd-loo~~coi~lr01.


131
\\~iiiCiCooliilgsysl~l,,s, 488 exllaus, area
SLCIIdY LllOn-CirC~ilC"lltiili,l,lS ~cononlics,44
genemtorr. 535 exilBUsipieiSUre
conmi unit type i.145 Steady state siahiiily ccono~nics.40
eieclrohydm~li~ gercra,ors. 534 crhausls. 4
eiectronicso~emi~,~, 142 steal,, cxiraclion. 116
Shalt end glands cfiicai prcss*x, 3 i fcedback-prerrureboilers.
pumps 115
livestenm, 226 ingrCIS
Shaft Seal$ sleain turbines, 255 condensing-lypc, Ii 6
aiiexlraclion punlps, 395 strair~cn.158 variable-sweddtivcs. 55
hydmgen cooling systelllr SUPPIY now
turbine gentraton, 497 wet steam lilrbincs. 237 direclion.2
Shafts foundations. 175-181
boiler fwd pumps. 405 full-speed
eircuiafirlg w ~ t e i p , , ~ ~ ~ efficiency, 38
malcrials, 399 matingfaees. 158 g~vemingsyslems
CYrnilC i n ~ ~ l a l i o n spindles. 158 ovcrspccd protection. 164
inlmmontation. 553 s t e m lurbincs. 13 Sleamcherts. 157-164 hail-speed
eccentricity Si~ndsidnuclear unit power plant system. 46 colislruciioii. 157 cconamics.40
instmmenlalioa, 173 Standards (see also Heal Exchanger lnsiii~tecta, maletinis, 158 cfficiency.38
length feedheaten. 2x9 Steam cycle Ilea, rate
couplings. I W Standstill scais cCononlicS,4a-(rl exiinusl pressure. 41
mton boilcrfecd pumps. 410 efficiency,22 impuisc-type.8
eanhing, 465.469 S,l".,,"", pre~suti~cd waleirenaon.33 inai~>tenancc
monitoting. 469 by-pas systems. 61-63 lemlinai coi?dilions. 25 cmciency.39
SP" OmC-through boilem. 62 tilermodynssics. 16-40 mes,ci ioad coniroller~
~nswmenation.173 Statevanabicanaiyris Stea~nc j e c t i r i p u ~ nsysteliir
~~ boiler pressureeon,ioI
vibration excitation systems. 531 condensers. 385 inuiti-cylinder, 5
insrumenmiion. 174 Slalicdiode~ SleGm heldCreOnlmiiers operational noxibiiity
voi,agc rcclificrequipmcnt hy-ga$ssy~~~mi effieienev. 39
gcneraton, 547 excitation equipr,ies~,521 nuclenrplant. 2 i 3
Shon-timuitratio Staticrcctifien steain inleis
generalon. 535 sfcam lurbine casings. 85
Shon-pitching steam-jet air ejectors
harmonic~.456 condonren, 381
Shuitinndown Seam prorsurc rcsction-type.9
gonGraron. 541 exeilalion systems, 521 blade lenalh. 29 rciativc thermal efficiencies. 39
Siiicone.based masei Slatorcorer in~lrumentation
efficiency, 174 reliability
SLeam tulbine~,194 emling. 508 officicncy.39
Sinusoidal grit blasting Stator leakageroactance Steam~rbinen.122 reversed-now. 3
condensen genenlom. 546 S f c m icmpeiatuie mlors. 90.105
eieaning.373 Slarorslo~s.484 blade ienglh. 29 singlc-now.3
Slipstick Stator willdingconducton, 475 Steam iemperafurcs 5izc
mtom Stator windings ih~Wm~"t~li0ll cfficicncy, 38
windings.544 wafer pressure efficiency. 174 speed o f roiat>os.4
Slipring induction motor generators. 550 Sceam turbines. 1-123 siageefficicncy. 13
feed pu.mps statom appiications. 112-120 stcam ingress
vanable-speed drives, 55 casings. 489 axiai-now. 2.3 protection. 255
Sliptings maintcnance.557 backprcrsure. 116 tandem-compouiid,4,6
generators mnduclor~ blading thonnodynamicoplimisadoa
exhaust pmnrure. 40
mainrenance.555 eddy euiients. 482 doueiopmenls. 123
in~tmmcnt core framc ban iow pressure. 10 types. 2-8
excitation systems, 519. 520 in~ui~tion.480 boilerfeed pumps variable-rpeed.7
mton, 465 cares. 473 cycle diagran.47 wateringres~
brushe~,468 nux. 477 by-pass sysiemr. 59 proleetian. 255
hmshgenr. 468 maintonanco.5~7 capiisicost~ weigh,
~nlltCtions.467 8leCL"~i COnntCtions, 485 eeonamic oplimiaaiion.42 efficiency. 38
Slot wedges end windings casings. 76-90 Steam valvcrplays
mton maintenanee.5~7 hotilantal joints. 81 pumpingsystems, 149
gcnerston. 542 in~ulation combinedi.yclepIani. 119 Stcamvalves. 157-164
Smoke dete"o~tion,54~ condcnser~ ci~singlimc
cwiing water Pistoye s101s.478 joints. 365 governor valve relays. 142
les*age. 369.370 sbt Wedees condition linw. 13 oiecrmnic govcming. 134
Speific s p e d mai&nmce, 557 constmction govemingsystems. 125
h~draulic~urhin~~ tcm*inal bushings. 485 eEcioncy, 38 g ~ ~ ~ m o ~ v a i v e r o 142
layr,
terminals, 485 +mling, 224 pasepoinls, 198
tulbinD-genemton,473+gi critical sped bands linearisalion C~BTBCLC~~EIICE. 140
sensing vcntiladon, 479 g o ~ ~ m i n g ~ y ~133
~em~, positions
governon. 138 winding EmPE-U)mpOUnd. 4.6 instrumomation, 173
Pmximateir~nsducc~, 139 walei analysis. 553 cylinden.4 pie~suredmp,8
SPeed reference eonmllen windings. 471 ileribilily.222 relays, 126
BU10maIic voltage r e g ~ i a t o 527
~, 669 MW. 486 design tripping. 165
SpeM of mtation CMling. 485 cfficiency. 9 Steel (see also Ausrenific steels: Chmmium alloy steels;
s l a m lurbiner. 4 L a d l fsuils, 554 rfcamcyeles, 33 Chmmium molybdenumvanadium srezl:
SWdselpoints senemion. 546 double now.3 Chmmiumssds: Super 1 2 8 0 steel$)
inrula~ion,548 cfficiency. b i 6 foundations, 179
electtical loads grainurienledsheei
Subject Index Subjecl Index
--
SYIIC~IIOII~~~S reac,a,,ce cosdci~sci~. 327
gcnemlols. 536. 546 Turlliilc-gciield,m 447
Syridilasous torque. 527 capital costs. 41
Syslclli drains 'T"r1,lc coniponcnls.456-173
wet rievili m t i n c r , 239 gcncmion.454 fuel costs. 41
Torque-speed i m p diagralrs, 528 liistoncal bsckgioaitd. 447
r$ slopY.~ve ic~sys
esergc~lcy.145 Traccrga~deieclois iifciimc casts. 41
Slol~VaIVCtel~ral,~," a i l ICBkS
slandaidiraiion. 242 condeieen. 367
it Stopvaives cwiing water
ieakap. 369,370
control uni~typeI, 145
E emergency. I61 Transduccn
high pn~sure on.londfesling, 170
i on-load testing, 132 trip-initia~lng
illicnnediate piersure lurbinc protection, 167
Traii~ientiearianco steam iurbmes
on-loadlenliag. 132 lun.up. 133
on-load testing. 160 generatoo. 538
Trnnsienl slabilily Turbine valves
ttipping. 165
excitadon sylems. 530 gavemon. 128
Sloik dc-aeiaron mcasuieincni. 374 'nrbinos erbiner;
aiso~sck-pressure
Francis turbines:
turbines:
Gas iurbincs;
Bausnan Hydrsulic
oxhnun
feedllealeo. 307 Trallsient srabiiily analysis
gesemtors exciiaiion systems. 531
s r ~ & n ~ a r 431.432
bi~~~. inslrumescation. 549 n c ~ e n iKaplail
rurbinc~; bpump-rurbi~les;
l ~ turbines: Pump
Rim gcnerniorturbinei:
iuihiner:
Strain gauger Transistor amplifien
'Terminals exeliatian syswms
alignmeni generators, 487 Sceam curbinen: Sfrailo lurbiner: Tubular lurbinor)
voltage regulatioii. 523
mtors, IM Thennal cycling govemoo
StTCsr Tnpping (riealro Electrical ,tipping)
Sfcam iurbincr.217 govemaivaiveiclayr. 145 fcedpumps, 156
cenlnfugal rocc Thcnnal fatiguc high pressure
generalon.542 operatorfacilifier
mtom. 92 iurbicicproleciios. 171 wet neani, 226
ln~ilii~n Thomalshocks Trips (rrealso Category A trips: Caicgorl wet steam. 226-240
instrumelirafion. 172-175
ncxibilily.224 by-passsyslems.216
S ~ ~ ~ S S E Oerncking
~OS~~,, t"pr)
Tllcrmal skins mechanically operaled 'runiing gear
condeilsen. 339,340 seanl turbine casings, 8s elecltisl
S,~CSIC$ t~rbin~prolection,170
Tliermsl ~ t r e s s c ~ Tube bundles slealn arbiner. III
rotors $teain turbines fcedwaler healers jackingoilpumps. 186
genoralors. 544 two-sliiflieg. 222 sreatn turbioos, 105-1 12
Subsoils now, 293
Thermal tightening high prenrure feedwater lieaters. 292 Two-shift reginle
elasticity. 176 nange hlcr. 84 low pressure feedwatcr heaten. 310 steam turbinoa. 216
Sucdon filters mennocoupler ~ u b suppan
e plates s l a m tu6incs. 217
Two-shifting
boiler fced pumps, 280 genoramrs.549
Suction s w i l i c s@ fcedwateihealers.295
Thermodynamie~ Tube iurbincr 430
airoxtracloipumps. 393 ~tenmcycle.16-40
s u p , 12% C i $ l e i s Thermon,etcn c o ~Ic&age.
l i x ~ g w369,370
~ter
blading. 72 gCnCralOR, 549
Supercanduclivify nlrottling Unbalanced ohasecondilioni
generaton. 558 loadsliedding, 8
Supercritical plant Thrust bearings
Sltamiurbines, 122 bollcr feed pumps. 408
Supeihe~l failure
Rankinccycle. 19 fhcm~al wrformance. 350
Pmleciion, 164 gometry I~fur~proSpecIS. 120
Superhca! cycles. 29 steam turbines. 108 unit sires
fculhealing.45 condonacidcrign evaluation, 350
tilling-pad, I W Tubeolafcs IIOBmfulurc
turbines
prospects. I 2 0
Sllperhc~fen WCBr
econoinien. 59 cbndenreishells
instiilmcnt~cion.173 join,$. 363 Unlosdinggear, 130
Suppenplates Thlus, pads exhauihressuro. 130
condeosers.365 condensen.362
war manufacture. 362 Upper wntrol level
Surface cuncntpathr measurement, 110 governon. 141
gcnerstan.537 thermal performance. 350
Thlurr type roals iubojoints. 363
Surgepads hydmgencooling sysems wsfor headers Vacuum dcgssslng
thru~~beatings, 108 lurbinc generaton. 497 roton
Swallowingcapaeity thickness, 263
~y~slorconveners Tubes materials. 94
steam turbines protection. 525 Valve actuators
condensen
Thyrisiaroutpu~amplifiers cleanlinesr.375 boi!cr fepd pumps
exeilalion s~slems ~ e ~ .
llsht ~lnadnmtection.414
~ ~ ~ ~ - - 7 ~ ~

vo~tagc>ogu~atian, 523 Valve soivosmplificn. 137


govemars lhyrisloirecrifien Valves (see o l ~ Batterfly
o valves: By-pass valves; Conln>l
speedrefcrence. 131 excitation systems. 521 vakes; ~ ~ a f l t valves:
uk Drain valvcr: Emcrge<~cy
steam turbines nivtisron tnp values; Govemorvalvcs: Isolating unlvca: Main
governingsyrrems. 125 unling.522 inlei valves: Non-return valuer; Pnrsun: c<u,liin,l
Synchmnou~compensafion coidenren
Tigl~cening advanepd gcomclry, 377
generaton.536 hyhlie
Synehmnousgeneraton ropcd.377
n a n g bolts,
~ 84 !llcrmal performance. 371
frquoncy.451 thermal govcming sys,ems
1OSd. 451 litanium.379
nange bolts. 84 'Tubular turbines. 428 on-losdteaing. 132
pole-pain.451 T ~ leaLane
D low pmrrurefepdweter headngsyncms.288
Power factor. 451 blader ~umo-turbinos.439
rating. 451 efficiency. I 2 rehoalen
speed.451 Titanium picsauro loss. 27
lhcov.450456 blsding.72 spurious opening, 135
Subject Index

dished end ii>icbiesrer,I 1 i


~ 1 ~tiiicksesses.
~11 i ii
wali tiiick~iesser.11 i
Walci lheaierr
drunl-typ
SoYneE, 73 fecdwalcr ihcalillg sysics?~.304
emcigciiey stop Waleriliessure
rurbinc pmteccioit. 172 inst~~n~cnlsl~ozl
flow-induced efficicncy. 174
fcedwaler heaten. 296 Waleifornperatuier
genemtors in~lruln~niation
insirumesraiion.50 efficieilcy, 174
journal bearings. 107 Waiertrcatment
pmfection. I64 feedwaier hcatiilg systems. 315.317
mlors.470 Waterwasbinn
alignment, 103
balancing. 97
Shnffs
in~liyme~itation, 174 low preESUie fcedwillcr hcatcis
Sfcam lurbine~ openings, compensafioss. 31 1
NII-up, 131 1lanSVOrSC undeislung condensers. 362
ViSeosiiy index inlprovols Walersidc~~rio~io~~
iub"c8iigoiLiis. 194 boiler lubes
V0ita.e measuremcat feedwater de-aeration, 49
Warcnprays
casings
steam turbines, 81
Wedges
mtors. 464
Welding
blading
chromivnl slecls, 72
Welsleam cycle, 33
deminorali~ed feedhesting. 46
stator winding ewiing sysccnls. 5 W Wet steam ~ i a n i
ingress by-pass sysmmr. 64
by-pass sysmms.216 press~riscdwaiorre~c~ors. 62
Steam turbines, 255 Wetness loss
turbine luhricalingoils. $94 Steam turbines. 16
SIBlor winding cmling. 485
Steam turbines, 165
Walti-mdedreactom
steam l~rbillcs vihrslion, 74
sizes. 122 wi1ians tinc
watercmiing 660 M W uiiil. 24
generaton. 558 Wind gcneralors. 562
SlSfO,$ Windings
windings. SW. 501 rolors. 459,463
W a i e r ~ w l i nsysteni~
l earth fault indiaatioii. 553
msin cxcilon. 508
slip-~ti~k,JM
temperaturcmeasuremeni. 466
voltagc. 548
arbines. 229 stators. 477
Wafer headers 660MW.486
mnv~ntionalhemirphencal cwling.485
manufac~ure.262 earth faula. 554
feedwafer heaters generators. 546
branch thicknerr, 294 insularion.548
dished end ihickness. 294 msin exciters. 508
openings, Ulickmssmmpensation. 294 water analysis. 553
shell ihickness. 294 walercmlingsystems.488.5W. 501
wall thickness. 294 thm-phase. 454
high pre~surefeedwater hoa~ers,292
low pressure feedwater hoalen, 310 zig7~g spool mds
branch Ulickne~se~. 31 i blados. 68
British Eiectrieity ianfiernretionali "" "-

Power Station
Practice
Third Edition incorporating Modern Power System Practice

The electricity generation and distribution industry has undergone


far-reaching development during the last 20 years, and the informa-
tion needs of its policymakers, managers and power engineers are
no longer served by any one pubiication. With this in mind, British
Electricity Internationaland Pergamon Press are pleased to present
a completely revised and eniarged Third Edition of Modern Power
Station Practice, incorporating Modern Power Sysfem Practice.

Ail volumes are devoted to specific subject areas, and have been
written by authors who are recognized authorities in their speciality
fields. Since the pubiication of the previous edition in 1971, much
experience has been gained by the Central Electricity Generating
Board throughthecommissioningof its large modern power stations;
in addition, the wider issues of power transmission and system
operation had not been previously addressed. The scope oflhis new
eoll on nastncrefore been cons ocrab ) enhancba b) rnree aod11onal
i o .mes Srar,on Commrss on no. EHV Transm seon ang Svsrem
Operation. A completely up-to&te treatment of theoretical and
practical aspects is compiemented by thousands of illustrations:
innovative fiow diagrams, coiour and black-and.white plates, and
detailed cut-away drawings.The coverage throughout is comprehen-
sive and clear, ensuring that engineers and technicians will gain
maximum benefit from the wealth of information provided.
1-he steam turhino Chapter 1 1-urbine casings

and additio~~allyfioiii either tlic i P turbine or the ;ti law tcrnpcratores) and casiel- la weld Casings in reaction froin tile rotor into the foundations. In some
boiler fced pump turbine, lo current practice, steal11 tliese materaais arc cast rather than fabiicatcd be- cases, the paws are part of the lower half casing as
is not hied from the H P turbine except at the ex- c;iose of the difficuli), oI quality control and like- illustrated, alternatively they may be part of the upper
haust, although iutuie designs with higher final feed Iiiiood ol' thermal distortion in the thick sections half, simplifying the casting but necessitating tem-
teinperatuies ma), blecd steam from the later HI' ii,volved. I..P cylinder casings arc generally fabiicatcd porary supports for the lowci half casing when the
cylinder stages. I i o m carbon steel, although the inner cylinder may be halves are unbolted. Vertical guides on the vertical
In L P cylinders (Fig 1.96), the steam is bled-off ctist from spheroidal graphite iron. Large defects in centreline of the rotor act in conjunction with sliding
into annular belts within the fabricated inner casing ofistings are ground out and repaired by welding, but at the paw faces to ensure that the outer casing re-
from which it is piped to the feedhcaters, bellows iicvertheless the materials are chosen to have a high mains concentric with the bearing pedestal and rotor
being used to take up differential expansions between tolerance to the presence of defects u,hich may grow during expansion. Similar arrangements support the
inner and outer cylinders. The connection to the hled- diiring service. inner casing inside the outer, with paw supports on
steam belt is usually made at the bottom; if made High temperature bolts are either made from low either side to take the weight and torque reaction,
elsewhere, a drain connection must be provided at itlloy steels designed specially for creep-resistant bolt- radial keys in the plane of the steam inlets permitting
the bottom. The bled-steam connections are identical ing, for example, Durehete 1055, or from nickel alloys concentric expansion only, and axial keys at the ex-
in each half of the double-flow L P cylinder so that hiicli as Nimonic 80A. The nickel alloys are more haust end allowing for differential axial expansions.
changes in steam flow to the heater do not affect <creep-resistail1and stronger, allowing a tiore compact The paw supports o f the outer casings contain trans-
the thrust forces on the rotor. However, the connec- $ fiange with better thermal properties; however, they verse keys so that the H P and I P casings and bearing
tions may not be the same on all L P cylinders on 8 ilic cub~ectto stress corrosion crackme. .~ . a r t ~ c u l a r lifv blocks expand axially as one unit away from a fixed
a unit. If, for instance, bled-steam is required at wct or contaminated with sulphur compounds. Nickel point between IP and L P cylinders. The axial location
stage 2, stage 3 and stage 4 conditions, it may be alloy bolts are thus used mainly on inner cylinders between the rotor and the casings is at the thrust
taken from each stage on each cylinder, or it may \!,Itere the compact flange is most advantagcaus. bearing between H P and I P cylinders: this arrangement
be taken from stage 2 on one cylinder, stagc 3 on ).ow temperature bolts on L P casings are made ensures that the close clearances between fixed and
another and stage 4 on the third (for a three L P S ~ o ~normal
ii high tensile bolting steels. moving blades in these cylinders are affected as little
cylinder machine). The latter method involves sim- Iligh temperature wet steam is considerably more as possible by differential axial expansion between
pler pipework but has the pcnalty of less interchange- crosive than dry steam, consequently H P casings for rotor and casing on start-up and shutdown.
ability of spares bet\\,een the cylinders. Usual practice wet steam machines are either made from 2.25Cr
is to favour the arrangement requiring minimum spares iMo steel with stainless steel cladding at the joint
holdings. laces or entirely from a higher alloy steel. 6.5.2 LP cylinder s u p p o r t s
I P cylinders usually only have one stage of bled-
steam from within the cylinder, although it may also The L P cylinder casings are supported on feet in
be taken from the IP exhaust. a similar manner to the H P and I P casings, but
On double-casing cylinders, the steam may be bled because o f their relationship with the condenser they
are limited in axial movement. Consequently they are
between the inner casing and a carrier ring, o r be-
FIG. I I W Inlet pipe piston rings
Tile piston rings shown iiere, real between the inlet pipe tween carrier rings, into a belt between the ring and
pr I'ri achieve maximum efficiency in a steam turbine, either joined together and fixed axially to the foun-
and t l ~ eHP barrei and the itil>ci casings in a triple-caiilig the outer casing. On single-casing IP turbines thc tlttly small clearances are permitted between fixed and dation at the centre or each fixed individually at one
H P turbine 'Outspringing' rings are riiowl~between tile end. This causes larger differential axial expansion
bled-steam belt is cast into the casing, with slots cut choving parts at casing and diaphragm glands, and at
nine and !lie barrel casing, and ,stacked' rings belwceo
to allow the steam to bleed from the main steam i
# lili~ilutip seals. These clearances must be maintained
between rotor and casing than in the other cylinders,
file pipe and iliner caring.
ilndcr all operating conditions, so the inner and outer so the axial clearances are greater.
path into the belt. The bled-steam pipcwork can then
Diaphragms and carrier rings are located axially
simply be bolted to the outer casing. Many 1P cyl- . n ctirii~gsmust be supported in such a way as to main-
within cylinders by circumferential grooves in the
6.3.5 LP cylinders
inders have no bled-steam tappings, as steam is taken . .
ciiiii concentricitv with the rotor as thev exnand and
casings. They are maintained concentric with the cas-
from the boiler feed pump turbine instead; however, ~o~ltiact.
ing by radial keys at the horizontal and vertical
Steam connections to L P casings are made with bel- latest practice with development of variable-speed 'Ihe total axral exnanslon o f a 500 MW turbine
centrelines.
lows pieces to accommodate differential expansions. electric drives, is for electric boiler feed pumps and lor between cold and hot conditions is about 50
The bellows are short sections of pipe with thin hence bled-steam is taken from the 1P cylinder. ~ n ,occurring mainly in the H P and IP cylinders, - are all aliened
The casings - bv reference to the
re the temperature change is greatest. The casings horizontal and vertical centrelines of the rotor at each
corrugated walls, allowing relative movements of the Steam bled from H P turbines in the future is likely
supported to allow axial expansion and yet main- bearing. The alignment of the rotor itself is discussed
ends in both longitudinal and transverse directions. to be via a belt cast into the inner cylinder wall, with
I the axial clearances between fixed and moving in section 7.5 of this chapter.
With underslung condensers, a rigid bolted joint can connections similar to the H P inlet connections.
be used between the L P outer casing and the con- rles which may be only a few millimetres. Main-
denser, the condenser being mounted on springs to ,ling both concentricity and correct axial expansion
support its weight but allowing the required flexi- to a complicated system o f sliding supports and
bility. Bellows can be used on the exhausts with a 6.6 Casing and diaphragm glands
floor-mounted condenser but are inconvenient because 6.4 Casing materials Glands are used to provide a steam seal between
o f the large area o f the exhausts and because the H P and IP casings, where temperatures over 350'C fixed and rotating parts of the turbine: in particular,
bellows, being flexible, transfer the vacuum forces to are encountered, are made from creep-resistant ma- .I HP a n d IP cylinder s u p p o r t s between the rotor and the diaphragms and between
the cylinder and condenser foundations. terials. Two different low alloy steels are used; 2.25C1' alld IP cylinders are fitted with 'paw' supports the rotor and the cylinder casing. The glands are of
IMo for temperatures up to 538'C and 0.5Cr 0.5Mo rilcll end which rest on the bearing pedestals (Fig the labyrinth type, consisting of a series of fins on
0.25V for temperatures up to 565'C. The 2.25Cr 02). The paws are horizontal with the palms aligned the inside of the diaphragm o r casing in close proxi-
6.3.6 Bled-steam c o n n e c t i o n s material is slightly weaker and more ductile in creep, 11 lhe horizontal joint; they are well spaced towards mity to the rotor surface. Steam trying to escape
Steam for feedheating is bled from the L P turbines but it is also tougher (i.e., less prone to fast fracture ollter edges of the casing, as they carry the torque between the fins and the rotor suffers a series of
The stearn turbine Chapter I
*8: Turbine c s s i ~ l $ j n
:.s
? ~,

,b r $ ,.,..
'
v,.
s
g

RRACKET

1I ExHliusi
WE,.
HALF 8 HRLI'
CKER
LINER
I FOllNDAilON '
STEELWORK

NO i BEliRlNG PEDESTAL , (hl LP frame supports


(Cl HP Cylinder centre guide key
(a1 Pedestal guade key
(uwrerl
(11 LP Cyltndet anchor

.. KEY

(bl HP Cylinder centre


guide key (lower1

/I BEARING KEEP

( k l LP frame centre gulde key (I1 IP Cylrnder centre gulde key t o LP frame
I
BEARING KEEP

(dl HP Cylinder centre guide key (IP end)


(el IP Cylinder centre guide key (HP end) RFARlNG PLATE

LOCATCON BLOCK

ANTI-FRICTION
PLATE

LOCKING
PLATE
SQUARE KEY ANTI-FRICI3ON
BEARING PLATE
LOCATiON BLOCK
REARING

BEARING KEEP (91 IP Cylinder palm (LP end) ( m l HP and IP Cylinder palms ("1 HP Cylinder palm

( f ) IP Cylinder centre guide key (LP end)

I'iC. 1.101 S~pportand alignment keys for outcr HP. IP and LP casings Fic. 1.101 (eonr'd) Support and alignment keys for outer HP, IP and LP casings
88
The steam turbine Turbine rotors and couplings

l'lie insulation consists of up to 150 Illin tl m Dru,?, ty/)e rolor inanufactured from solid or hollo\r
of mineral fibrc which is applied either a s forgings (Fig 1.104 (c) and 1.104 (d)).
'mattresses' or sprayed on as loose fibres, !
s The welded disc l a l o r (Fig 1.104 (e)). These rotors
I y dependent oil thc temperature of the sl are not too common in the UK, where they have
be covered, enough insulation being used to been applied to LP turbine rotors. Overseas ap-
thc outside temperature to about 50°C. Asbesloa \ plications have included H P and IP turbine rotors.
used extensively for sprayed insulation in the
but all modern insulation is asbestos-free, becai
the health risk of inhaled asbestos fibres. For various reasons, monobloc forgings are preferred
The mineral fibre is held in position by wire 1110 but where the size has exceeded the forging capa-
which covers it and is attached to studs welded bility, the built-up disc construction has been used.
the outer casine and vassing out through the mini31 The current 660 MW UK designs all have monobloc
rotor forgings.
TIC, 1.102 Derail of support for HP and IF ouicr casilis Built-up rotors required very careful attention to
wire mesh support between them. The outsidc wit shrink fit and location geometries to avoid problems
mesh is then covered with 6-8 mm of cemenl in running and with fatigue cracking. While the discs
lowed by a thin coat of oilproof and watl may have facilitated non-destructive testing (NDT),
expansions which reduces its pressure in stages and sealant. A glass reinforced plastic may be uscii the NDT capability on monobloc rotors has been
restricts the flow through the gland. A detailed ex- the sealant to provide suitable mechanical slrclr developed to meet all the needs. With the monobloc
planation of the %,orking of glands and the different and life. method of construction, the L P rotors are more rigid,
types is given in Chapter 2. The insulation extends over the horizontal resulting in better dynamic behaviour. 660 MW plant
The H P cylinder has glands at both ends of the covering the bolt heads and has to be chippe employs rotors o f this construction almost enclusively,
outer casing and the inlet end of the inner casing before the casings can be separated: the joint rci andexperience has been good.
(Fig 1.92). They are housed in gland carriers, which on reassembly. It was the practice to provide test material from a
are supported either on keys to allow differential ex- It is essential that oil is not allowed to en1 bore-hole down the forging axis but, as confidence
pansion or simply on spigots in machined recesses in forging practice and material properties has in-
in the casing. -- - creased, the central bore has been omitted on some
The H P glands are longer than those in other severe turbine fires.
current designs. The benefit of reduced stress levels
cylinders because of the higher pressure drop required gives enhanced confidence in the longer-term fatigue
across the gland, and are often divided into several integrity of the rotor.
sections. The IP glands are similarly supported (Fig Welded rotor construction has the advantage of
1.94), but the L P glands may differ; if the bearings 7 Turbine rotors and couplings smaller forging components at the expense of high
are separate from the L P outer casing, then the L P integrity welding. The welded design, having been
gland carriers may be supported from the bearings adopted by countries lacking an intrinsic large forging
and connected to the rest of the casing by a bellows 7.1 Types of rotor construction capability, has been successfully applied by them to
piece (Fig 1.96). Four different types of rotor construction havc H P , I P and LP rotors. There are a limited number
The LP glands prevent air entering the cylinder, used on large turbine-generator units on the of welded L P rotors in service in the UK.
>.3;z
unlike the H P and I P glands which prevent steam system: ,$ High temperature drum-type rotors, manufactured
escaping. Thus the L P glands need a continuous sup- from hollow cylinders bolted to stub shafts, have
ply o f higher pressure steam, whereas the H P and 1P The monobloc or integral rotor, in which the WIIUP@
been prone to differential creep and have been re-
glands need additional steam only at start-up. This and shaft are formed from a single-piece f o r y i d
placed by monobloc drum rotors in current designs.
is explained in detail in Chapter 2. (Fig 1.104 (a)). &. ..fg Where constraints on last-stage blading design dic-
The gland carriers are split, like casings, along the tate, double-flow cylinders replace the single-flow
horizontal centreline and bolted together. TUR8INECYLIN design as used in the H P turbine. Double-flow I P
and L P turbines are standard for 660 MW designs.
With the single-flow H P turbine, the axial thrust has
to be balanced to some extent by a 'balance piston'
6.7 Lagging SELFSETT~NGCEMENT
RE~NFORCEDWITH
to reduce thrust bearing loads: for reaction turbines
The hot external surfaces of the cylinders are lagged, particularly (with a high pressure drop across the
INSULA7ION RETENTION moving blades) the balance piston is of substantial
i.e., covered with a thick layer of thermal insulation.
There are several reasons for this: proportions, as shown on Fig 1.105.
In contrast, a n H P turbine rotor with impulse blad-
ing is illustrated on Fig 1.106. This arrangement is
The loss of heat from the steam is reduced.
characterised by the reduced number of blading stages
The thermal stresses in the outer casing are sub- and larger blading pitch diameter compared with the
stantially reduced. reaction design. In addition, a very much reduced
balance piston is necessary, as the axial thrusts are
Danger to personnel is reduced TIG 1 103 Thermal lnsulatlon on tuiblne caslns 4 lower.

91
The steam turbine

FXG, l l O S Sectioli <!>roughu monobloc HP turbine with reaction blading

1 3 , due to creep. The shutdown or load reduc- same steam temperature at the inlet as HP rotors
$1'111 Sillill follows, causes cooling of the rotor surface and, because o f their larger diameters, are subject to
equently tensile thermafstress in the surface larger centrifugal stresses. The bore of an 1P rotor
7.1.1 Design f o r high t e m p e r a t u r e operation operation, due to the cyclic reversals of thermal stre
1e stress-strain condition at the concentration under tile first few stages is therefore a criticai region
The increase in size of large turbines over recent resulting from the transient temperature gradients
Ows the line 3 - 4 with possibly some further for creep.
years, together with the higher steam inlet conditions tabiished during tlle heating and cooling periods. tension, at 4. As the rotor temperature On large machines operating with reheat steam at
often used, has made the design of turbine components thermal fatigue problem is accentuated by the incre llius more uniform at the part-load or shutdown 565'C, forced cooling of the rotor by cooler steam
in contact with high temperature steam more critical. scantlings on larger machines which result in high ilioll, the material stress-strain moves along the is employed. This method is particularly effective in
Fundamental considerations include creeu and thermal thermal stresses occurring within components durin 4 5 to point 5. At this point, the rotor tem- cooling the bore under the first wheel (Fig 1.109);
fatigue, both requiring control of the temperature transient conditions. Illre will generally be too low for significant creep with further increases in turbine size, additional cool-
distribution in components during steady and transient The inlet sections of H P and 1P rotors are t1 or and there is no stress relaxation, such as ing is needed to cool the bore o f the second wheel.
operation. At the design stage of high temperature critical areas for thermal fatigue, demanding caref d between 2 and 3. This can be effectively provided by introducing a sec-
turbine components, temperatures and thermal stresses attention to design detail and operational practices en the material at the point of strain concen- ond cooling steam flow between the first two stages,
are assessed to ensure that creep, which occurs as a A typical cycle of events undergone by material 1 is held at reasonably high stress (point 3), SO that gland leakage steam is replaced by cooler
function of time, temperature and stress levels d o the critical region of a turbine rotor is illustrated is a damaging effect o f the hold-time due to steam.
not exceed specified values and that thermal stresses Fig 1.107. The material undergoes plastic strain col rsibie creep strain. The effect of this is shown
due to cyclic operation are not of sufficient magni- pression during the heating period to point 1 on t
tude to cause thermal fatigue during the life of the diagram, at which point the thermal stress has reached lermal fatigue, which shows as surface cracks,
turbine. its maximum value. The stress then falls as the tern. occur when there is a net amount of plastic strain
Creep can be limited by close attention to detailed uerature o f the rotor interior increases towards that - . .
llic thermal cycle. Material wooertv curves are ~ ~ ~
7.2 Rotor materials
geometry in critical areas, such as blade fastenings, of the surface, causing the stress and strain at tlle Ived for combinations of plastic strain range, num- Developments in the field o f steam turbine design
in order that stress-concentrating features are con- stress concentration to move along the line 1-2. At of thermal cycles and hoid-time at the peak o f would not have been possible without corresponding
trolled. Rotor stresses generally are kept low in re- point 2, the nominal thermal stress is virtually z Icnsile part of the cycle. materials developments. The development of alloys
lation to the high temperature mechanical properties and stress at the concentration is the residual stre with properties which provide good creep-resistance
of the creep-resisting steels employed. arising from the plasticity which occurred at 1. Durin at high temperature and o f other alloys with good
Thermal fatigue is associated with changes in op- the period of full-load running, the temperature Cooling o f IP rotors mechanical and high fracture toughness has been one
erating conditions, such as occur during two-shift the rotor is such that this residual stress relaxes t IP rotors o f reheat turbines are subject to the area of considerable metallurgical accomplishment.
a
:t
f:

1
The steam turbine

I)/
IWIELIT~MEI

- - .- - - ... - - -.

!
I
I
I
I
I
i
sTc,A,,4""",,,<;
"NiOhOlNG
wlicrc E = creep strain

Typical
steel,
rupture
o = stress, ~ / r n m ~
t = time, 7
T

Typically,
on a creep
and
-

are
absolute temperature, K
n , m and B are materiai constants

curves
high
strain
show
shown
of
temperature
of
the
time
on
0.2%
powerful
Fig
to during
1.110
produce
turbine
effect
for

temperature in controlling creep strain.


10S0.2%
design
Cr
h of
Chapter I

ofMo
stress
strain
operation.

steam temperature is encountered on discs at the IP


inlet stages, which have larger diameters and blades
than equivalent stages on the H P rotor exposed to
steam at thc same temperature. Both at the rim and
isV based

While the best possible creep properties are required


on both H P and IP rotor forgings, the HP problem
is simplified by modest dimensions of HP rotors. The
1P rotor poses a much more serious problem, es-
pecially in turbines employing a reheat cycle. Full

the bore, the stresses are sucll that steam cooling may
rotor
and
8g

g
%

!i.
.. .,.

0,
10

I'l(i. 1.108 T ~ ~ , i c astrain


i
10' 10'
CYCLESTOCRACK N I I I A I I O N
Turbirie rotors and coullli~iys

10.

range plotted against a number of iiicimai cycles to crack iniiiaiiori at 540-C


sliosine illc effect of dvell iiine

I he necessary, even with steels having the best creep


0
/
properties.
The reduced temperatures encountered at the last
s
spection of the axial bore with ultrasonic examina-

kI
two stages of the IP turbine are offset by increased tion was the accepted approach to non-destructive
STRA1NOURINCI
bore stress due to the longer blade length, which examination of the rotor forging whose simple geo-
demands an adequately high proof strength. metry, in the rough machined state, permits accurate
The requirement for good creep strength and the location and diagnosis of any internal defects pro-
mi*csrannaC~Y~ necessary proof strength in conjunction with a rotor ducing ultrasonic indications. Ultrasonic techniques allow
forging of heavy section is achieved on current rotors the material in the vicinity of the bore hole,
~ic.1.107 Typical stress-strain cycle at romr surface
by the use of 1Cr 1Mo 0.25V steel alloy. -
which is subjected to the hiehest taneentiai stresses
iluring overspeed, to be examined critically. This pro-
vides reassurance of integrity in circumstances where
7.2.2 LP rotors the compiex geometry of tile machined rotor prohibits
Also, the ability to produce components for use both For low temperature rotors, the main requirements the use of external examination.
at high and low temperatures, having large physical are relatively high tensile strength combined with high The purpose of the bore was to permit internal
size and uniform material properties which meet ri- toughness. inspection, but it also removed some of the central
gorous inherent defect acceptance requirements, testi- The 3.5Ni Cr Mo V monobloc rotor forging is Part of the forging which is where defects or segre-
fies to the improvements in steel-making techniques. currently used as it avoids the complication of shrink gation in the original ingot might be located and
fits in the case of built-up rotors. The manufactur- Provided the opportunity to obtain fracture appear-
ing facilities and forging technology required for the ance transition temperature measurements.
7.2.1 HP and IP rotors manufacture of monobloc rotor forgings of very large Inspection techniques have now developed to the
size and weight are fully able to meet the designers extent where external ultrasonics can replace the former
High temverature rotors are required to have a com- bore inspection. This is very significant as the LP
bination of creep strength, rupture strength and duc- requirements. No limitations are identified for the
forgings of 2-pole 900 MW units currently under rotor is subjected to high centrifugal stresses, the
tility. This is conferred by rotors manufactured from
consideration. last-stage disc being the most heavily stressed part of
forged Chromium Molybdenum Vanadium steel (Cr the turbine. The centrifugal load of the large rotating
Mo V), a ferritic material which provides the best The use of vacuum degassed ingots, single and l i ( i 1.109 .The effccr of coolill8 steam lemperatuie on !he
double upsetting procedures and the use of larger lnaximum 1P roloi bore temperature under the first disc blades sets up a tensile stress in the rim of the disc,
posaible creep properties. Creep is a high temperature and this stress increases with decreasing radius, its
phenomenon and traditional design methods involve presses capable of such forging operations, have all
contributed to a marked improvement in quality of maximum value being at the hub. The larger the bore
the selection of materials which provide the required Of the hub, the larger the maximum stress. If the
creep strength and creep rupture ductility during the large L P rotor forgings. Rotor forging for 660 MW
$uod fracture toughness. Ultrasonic inspection techni- bore is small, the hoop stresses are iessened.
designs of 100 tonne forged weight, produced from
required design life. 11um enense freedom from any internal discontinuities Ni Cr Mo V steel containing up to 3.5% Ni has
ingots twice this size, are provided for LP rotors.
&rc;itcr than 5 mm effective diameter. been used for both shafts and discs for built-up LP rotors
Vacuum degassing has eradicated the former pro-
The parallel application of visual and magnetic in- and is the first choice to achieve the tensile properties
The equation for creep is of the form E = o"t"'~-'/~ blems of hydrogen embrittlement cracking and gives
94
The steam turbine Chapter 1 .# . ., .,.
Turbine rotors and c u u ~ l l i n i ~ s
- fj
provides tile necessary f i a m c ~ ~ ~foi.
o f 1.P turbines.
o i hthc safe operati<>ri 8 ,sr,,tii.
jirwii
h ~ i l c nincaris
~ ~ tliat the u,cight is cvcnly dis..
;i~r,tiodthc axis o f the shaft. It cart bc checked
rotors via access Iholcs in eaclt gland housing. 1:igllic
1.111 shows ihe balance planes and site trim balance
bs
3.5% Ni Ci Mo V slccl has a lox,, value o f F ~ 1 ' l . ii, i,,Iiiiil: ihc rotor on liorizontal knife-cdgc supports. arrangements for a typical 660 M W LP rotor.
In tile water.-qoenciled and tcmpered condition, alld i',,jii,rric boirr~ice means Ilia1 tlle mom cot^ of the
with careful cont~.oiof composition, higil tcnsilc p r o i i ~ l !i~i.l~;~l;ince weights aiong the axis about either
pcrties can be matched with a FATT weli below iii.siifii: add up to zero. This is checked by spinning MOVING BLRDE SIAGES
ambient temperature and a consequential high fiacti~re tolor oil resiiient bearings, detecting the vibration, REAR
toughness. #,,,I itdiling or subtracting weights until the vibl.ation
lb twgiigiblc.
A nrodcrn balancing machine enables balancing t o
d out with a high degree of accuracy and
i1,sles to a large extent the trial and error pro-
7.3 Rotor testing and balancing used in the ~ a s t .
lors are normaliy balanced at low speed (400 r/min)
wi:igl~t adjustment made in two convenient planes,
7.3.1 Thermal stability
jut each end of the rotor. This adjustment may
During the manufacture o f turbine shafts, great efforts arying screwed plugs in tapped holes, or by
are made to ensure that the physical properties o l balance weights at specific circumferential po-
the forging d o not change in service. Thcre are thre Tee-slots are )machined circumferentially in
types of instability: lpllery of the rotor front and rear half-coupling
Permanent, due to asymmnrical coefficients o l r!.t:s to permit the weights to be positioned and
expansion across the diameter. This is avoided by ,cd
i. aim of balancing is to reduce the amplitude
close metallurgical control o f the for.ging process.
rll~ri~iion to a tolerable levei. which can he taken
8 Temporary, due to residual stresses in the rot ;!bout 25 prn at the bearing pedestals.
This is eliminated by stress relieving the rotor, bo rotors become larger and more flexible, it is
before and after machining, in a special furnace lngly important to understand their modal be- ROTOR BALliNCE
WEIGHT ACCESS PORT
in which the shaft is rotated. so that balancing can ensure smooth running COYER PLATE

8 Transient, due to differences in conductivity an larger L P rotors and generator rotors having
emissivity. The use of ferritic materials throughox speeds below running speed are overspeeded
has obviated the difficulties that occur. necessary, balanced in the fully-bladed con-
,
ill a vacuum chamber, where they can be run
IIIOI~Ibeing overheated due to windage.
An unstable shaft is likely to develop a 'bow' 111 11icvacuum chamber and the high speed pit, rotors
service, producing out-of-balance forces and cons ii,c 11,n in bearing bushes and pedestals as nearly as
quentiai vibration.
~$!ih~.ll,lv simulating site conditions. Facilities are avail-
alllr l,,r #measuring journal or pedestal vibration and
trii.iii! can be carried out at closely controlled
7.3.2 Overspeed testing lnywl~eiein the range required. Standards of
A 20% proof overspeed test is specified on all larg obtained during the factory testing must pro-
turbine-generator rotors at the time o f manufacture ficient vibration margin to take account of
FIO,i.110 Typical 0.2% strain and rupture propertie$ of
C, MO V $teeis for rotor forgings This allows the rotor balance to be satisfactoril ditions. Balance on-site is likely to be affected
(bj site trim balance arrangements
($
established throughout its operational speed range i;~.iirtionsin the stiffness of the bearing, possible
thereby providing sufficient margin over normal op inisalignment and the coupling of the indi-
erational overspeeds caused by electrical grid syste ally balanced rotors to form the complete shaft
necessary for large monobloc rotors. Welding tech- disturbances, and the regular 10% overspeeds expe FIG. 1.111 L1' rotor balancing iacililiei
niques are established for the design o f fabricated enced during overspeed bolt testing. Overspeeding the 11i-plane balancing is carried out at speeds
L P rotors employing a series of solid discs. Alloy rotor also proof tests the forging, as it applies cent, Icd with each critical within the running range.
steels for this application are subject to the conflicting fugal stress in excess of that experienced during norma weights are attached ta correct imbalance in
demands for tensile strength and weldability. operation, thereby providing a quantifiable measure ~c modes related to these criticals, as well 7.3.4 Critical speeds
Since L P turbine rotors may run at temperatures o f the margin against spontaneous fast fracture. balance in the modes of up to two criticals A stationary shaft supported between bearings has
not much in excess of ambient, the provision of running speed. Typical H P and 1P turbines a natural frequency of vibration, depending on its
safeguards against the danger of brittle fracture is ovidcd with two balance planes. The L P rotors diameter in relation to the distance between bearings.
important. The use of materials for discs, shafts and 7.3.3 Rotor balancing lllree balance planes and generators have faci- If its speed of rotation corresponds to its natural
monobloc rotors of the lowest possible fracture ap- When assembled with blades, the rotor is balanced to attach balance weights in almost any axial vibration frequency, the residual out-of-balance forces
pearance transition temperalure (FATT) and subject both statically and dynamically. For built-up rotors, are amplified, and can build up to a dangerous extent.
to stringent non-destructive testing and fracture me- each bladed disc is balanced individually prior t o lid site vibration levels exceed those specified, This critical speed is either above o r below running
chanics assessment (see Section 7.3 of this chapter) assembly. 11 is made for site trim balancing on the L P speed, depending on rotor construction. If below, the
96
T h e steam turbine Turbine rotors and coulilirig!;
.,...,,
, -
shaft is regarded as flexible, and care niiisi bc cxei- criticai speeds of a complclc line a1.e shown as fun p ~ ~ i a ~ n not ~ ~significantly
~ r ' e below the tcmpcralure liigir teml>eialilre steani iilrhine rotors opclaie lli
cised during run-up to ensure that the critical is lions of bearing flexibility, cxpressed as the deflection lsiirc rapcrieoced in ol,elation. The l~ossibilityof ;i ihc creep range and cracks within them couid lllerc.
passed as quickly as possibie. o f aii equivalent spring u n d e ~the static load ul3oil r $ i l i , l lirililc fiaclul-e cannot bc disinissed withoot a fore grow under steady loading. Rates of growill
Critical speeds decrease with increased rotor length the bearing. under cieep can be correlated with the linear elastic
and with reduction in rotor diameter. On current large eter K , via an equation of
units, the trend is to provide a rigid rotor (criticals
above running speed). Because of the increased rotor 7.3.5 Rotor f a s t fracture risk a s s e s s m e n t
length (necessary t o accommodate the required num- There have been major advances in the quality or by the requirement that it shall introduce
bel. of moving blade stages) on large units, rigidity monobloc rotor forgings (see Section 7.2 of this chapt rotor brittle fracture in service. The initial
has been accomplished by an increase in diameter. and in understanding the problems of brittle fractu
The rotors of large machines are joined by solid Rotor forgings can now be produced with grea

X 550.C
0 5254:
?d3. (i OSiC

id '.

10 20 30 40 50 50 70 80
lio. 1.133 Typical fatigue crack growth data for various K. M N I ~ ' ' ~
turbine steels between iW and 550DC

FIG. 1.114Tile cffcct of temperature on creep crack


da/dN = CAKm growth re~i~tance of a turbine rotor forging

lore a = crack length


A K = cyclic stress intensily range da
C, m = constants
- = AK"
dl

B E ~ R I N GOEFLECTION mm 'I'llr operational duty of large generating plant is where A, n = constants


blrcll that upper bounds can be reliably established K = stress intensity
lul slress cycles. In actual service, the stresses during t = time
%Illri-up are limited by established operational pro-
Plo. 1.112 Critical speeds of a campiere line of rotors, calculated as a function of bearing flexibility O P ~ I I I ~ C S(see Chapter 2) t o protect the plant against
Each curve is arroeiated with a particular span in whieh the maximum amplitude occurs. The black curves (a and h) refer to lilpli sirain fatigue. The total fatigue growth can then The design criteria normally adopted for high tem-
the modes in whieh the maximum amplitude occurs within the generator span and are called the first and second criricals of
the generator. Similarly, curve (g) refers to the exciter span, curve (b) to the HP span, curve (e) to the LP span and curves kc ciilcuiated o n the basis of the upper bound stress cycles perature turbine rotors limits the maximum rotor
(d, c, n to the associated LP span. nl!il colnbined centrifugal and thermal stress. stress in relation t o the 101 hour creep rupture stress
98 99
The weam turbine Turbine iotois a11d caupIi!t(i.:

and lio~ita ihe accilrnulatcd creep strain to 0.2% in giowtl\ during thc sl>eciiied lifctimc service, s iiiici construction of large iii~~bii~egenciaiors
! 0 5 hours, ensuring that tlie stress in critical higli without fsiiilre caused by instantaneous fast frac ICS i l ~ euse o f a coupled sliah system.
temjleratoie regions is acceptably small. Calculated This will depend on whether the extended defect I l i i r i ;,re essentially deijices ioi tiansmittiiig
cieep crack growth is therefore small and iniay be longer or snlaller illan lhe critical defect size cai i t i l tl~cynray also have to allon, relative angular
simply added lo calcuiated fatigue crack extensions. latcd foi the otost adverse contbi~~ation of eve1 ii~iciil, iraosmit axial thrust and ensure axial
The region of maxiinum combined centrifugal and T o furtllei complicate the assessment, variations 0 l i t c i s allow relative axial movemenl. They mag

thermal stress, near the rotor centreline, coincides with rotor tenlperature diiring machine start-up prod11 h!,il'icd as flexible, semiflexible or rigid. On
the region where, for I.easons of ingot cooling and a corresponding variation in rotor forging fracui I lushine-generators (LC., up to 120 MW) semi-
heal treatment, the material fracture toughness is toughiiess properties which influence tlte instanta i, ;tnd flexible couplings were commonly used,
lowest. Valid plane strain fracture toughness specimens eaus critical crack size. Assessments must therefor ,I 1;trge turbine-generators it is now common
cannot be obtained without removing an unacceptably be undertaken at each critical operating conditio Iru to use iigid couplings.
large diameter core and samples taken elsewhere may for complete confidence.
not provide a reliable basis from which t o estimate
centreline properties. Consequently it is most common
t o measure toughness indirectly by using Charpy FATT
specimen results. Established correlations between F A T ~iignment,as well as axial movement. Double
and fracture toughness (see Fig 1.115) are used to 7.4
determine a Klc for the rotor material. The need for couplings arises from the limited lengtl
lo all cases, the crucial judgement to be made is of shaft which it is possible t o forge in onc piece an(
whether the rotor f o ~ g i n gcan, given the longest fea- from the frequent need t o use different materials So
siblc initial crack and maximum fatigue and creep the various conditions o f temperature and stress. TI1

.. and provides (in addition t o the other


im -

180 -
I external gear teeth of involute form, which
$50-
I lo accommodate angular misalignment.
3'b NCMV ROTORS
X 1 CMVROTORS

lr recess, from which it is fed centrifugally to


til,ling teeth through drilled passage-ways.

120-

110 - . Gerniflexible couplings


l y l x of couplings will allow angular bending
'I lhcy require no lubrication and consist of a
w a lpicce having one or more convolutions. Figure
-E
:so- aliaws a semiflexible coupling.

80 -

Ihe use o f flexible couplings impracticable.


quently, it is now normal practice for rigid
ngs to be employed between the turbine cyl-
SO - so that the turbine shaft behaves as one con-

30 -

means that the shaft alignment must be set


that the coupling bending moment forces
TESTTEMPERATUREIFPilTIPC

F ~ c .I . l l S Relationship between KIC and FATI for rotor materials F~o.1.116 Flexible couplings
The steam turbilic Tiiibi~ierotors anii coili,iir,g!,
----
lHalS coiq>Iinga, which are foigcd scpalalely flolli
tlic siiaft, arc assembled by heatiiig and shrinkin?,
them on io the shaft. Dowcls arc then insertetl hr- o ~:IIJEC
i
POIN; ~OIK

tween thc bore of the coilpiing and thc dianleter of


the shaft. For additional security against axial illovc.
lnent of the coupling, a sciewcd ring, secured by a
locking screu~,is fitted to the shaft end outboard oi
the fLange. An oil injection point may be provided
on the coupiing through which oil can be supplied
under pressure to one or two annular grooves in the
coupling. This allows the coupling to be 'floated' to
ensure that it is seated correctly following the shrink-
o n procedure and also assists removal. Figure 1.11'1
shows a typical arrangement of a shrunk-on type
half coupling with oil injection facility, bolted to a
monobloc half coupling.
Earlier designs of shrink-on couplings ernplayed $1
tapered seat, with a corresponding s h a h taper. Witll
this type, an oil injection system was used to remo\,e
the coupling from the shaft.
been used on turbines and still arc used on the gcn- A forged steel spacer plate is normally fitted i s
erator. They allow thc couplings to be iaken off for each coupling to provide a tneans of axial adjustment
the removal of turbine rotor discs, or the generator of the rotor relative to the cylinder. This ensures that
rotor endwinding retaining rings (end bells). T o miiii- operational design clearances between the stage dia-
mise stress concentration in the coupling region, the lihragms and the rotor blades are always
manobloc design of half coupling lhas a large transi- and also facilitates rotor interchangeability. The spac
tional fillet radius. Figure l . l l 8 shows a typical plate is annular in shape and dowelled to one ha
monobloc coupling. coupling and secured by screws with countersu
heads. The spacer plates must be sufficiently robus
to avoid distortion.
SPACER PLATE The couplings are connected by fitted bolts wh'
I arc arranged so that torque is transmitted
bination of axial clamp load (resulting in
the coupling faces) and radial grip (resulting in sheai
load on the cross-scctionai area of the bolt). Th
bolts are tightened in a controlled manner t o a pre-
determined extension. The use of fitted bolts means
that some final on-site reaming of the bolt holes
necessary at the assembly stage, which can make t
a prolonged operation. In an attempt t o reduce
sembly time, it is now normal practice only to 'fil' ng is normally surrounded loading and hence alter the shaft vibration behaviour.
sufficient bolts to enable system fault torques 1 stationary steel guard to reduce windage heat. A long shaft beiids natuiaily under its own weight
be transmitted without damage to the bolts. The re f the adjacent pedestal and the creation o f oil t o form a catenary, but nevertheless revolves around
maining bolts are installed with larger its curved centreline during rotation. The alignment
permit speedier assembly. is arranged so that the shaft system has minimum
Couplings should be designed t o withstand a close bending moments at the shaft couplings. The catenary
up three-phase fault or out-of-phase depends solely o n the mass and stiffness o f the shaft
without damage. The highest torque under these eon system. Figure 1.120 shows a typical shaft catenary
ditions (typically 4-5 times full load torque) occur alaill objective in setting and maintaining rotor for a large turbine-generator.
a t the generator/turbine coupling and would almost ll3lellt is t o achieve satisfactory dynamic behaviour During initial erection, bearings are set at appro-
certainly cause 'stepping' of the fitted bolts. priate heights relative to one another to form the
T o further reduce the assembly time of couplings e misalignment can affect the vibration catenary shape.
hydraulic bolt fitting techniques have been develope of the multi-bearing shaft line. It imposes The final bearing height must ensure that adjacent
These have the advantage that bolts can be fitte ctive bending moment at the couplings which coupling faces are square and true to one another, so
quickly and also removed quickly witho f-balance. Changes between that there is no transmission of bending moment
the bolt hole or the bolt. *nd Cold running vibratioll behaviour may be through the coupling. Final adjustment o f bearings
The standard coupling bolts have cylindrical heads. live o f misalignment, with the effect showing must be made with all the cylinders fully assembled
with a n internal hexagon for tightening, and are rc- ,lice-per-revolution vibration. Very drastic and all pipes, which may exert a strain o n any turbine
FIG. 1.138 Rigid monobloe coupiing cessed into the coupling t o cut down windage losses lltll~ntmay have the capacity t o cause bearing un. cylinder, fully assembled and attached to that cylinder.
102
The steam turbine ~ h a p t e l1
,
4
'B .-
13earings, pedestals and tuiiii~iggoat
ii
f iliiiilt'cs iliiring sei\'icc. A dcsci-iptioi, of such ;I wi- hc rather ioiiger, >uitii I./]) ratios o f 0.6 lo 1 . 0
I!I,I i:, given in Cliaptei 2. take account of ttic ireavics genciator rotor i n sclalioii
lo ille weigh1 of individoal tiiibiiie rotors. In this
way, a typical load on projected beari~lgarea is kept
belon' about IS kPa.
'Two main whitc mctal profiles are i n cotmrnon use
8 B e a r i n g s , pedestals a n d t u r n i n g g e a r in modes,, UI< tol.biiie D~arii: t~iese are known as
el/i/~licn/and ih,pe-ln,id respectively.
Thc e//i~,lico/ bore is produced by first ,machining
a circular bore \\'it11 shims in the bearing horizontal
1 Journal bearings
half joint and then assembling the bearing without the
)Illpose of a turbine bcaring is to retain the rotor shims. This results in typical clearance ratios (diametral
11 in its correct radial position, relative to the clearance/diarnctcr) of 0.001 vertically and 0.0015
icrs, and t o provide a low friction support u,hich lhorizantally. Oil is fed into the hearing via lcad-in
<\.iill~stand
the static and dynamic loads o f shaft ports at two diametrically opposite points on the
111,1i, together u,ith the frictional and condrictcd iloriz~ntalcentreline.
, and to remain free from maintenance except The lhree-land design lhas three separatc bearing
surfaces, or lands, of coual ~ , i d t lbut~ of different
arc lengths; one land in the bottom half and two in
thc tap half.
I' Construction There is an oil s o.~. ~. l l.
eroove
v with lead-in at the
44469mm
-1 Ilearings noi~nally support each section o f the beginning of each land, and a drain gl.oove at the
end. Recirculation of oil is limitcd by an axial strip
ir shaft, although, with solid coilpii~igs, some
~ i c I. ,120 ~ y n i ~ ri~aic
a t catenary 10, a large la~bini~gelleluLoi only use one bearing between cylinders iii o f bearing surface bclwccn each drain groove and
lo save length and bearing losses. Plain whitc- the following supply gI.oove. The three-land bearing
111 ie~ijournal bearings are invariably used because
is generally of circular bore %,it11a deal-ancc ratio of
1lli:ii )high loading capacity, reliability and absence about 0.0013. This design is more resistant to low
7.5.1 Alignment t e c h n i q u e wave output as the shaft is rotated. T o use this tecl 1' due to hydrodynan~icallygenerated films of
frequency whirl (see later).
nique fully, it would be necessary t o establish a datul ling oil. These films are formed automatically, Oil is supplied, to cool and lubricate the bearings,
The basic intention is to have zero shear and bending
at each coupling for a properly aligned machine, an nning, by a high pressure wedge of oil between at about I bar and 30-40"C, from the main turbine
momellt at the couplings, so that drivng torque is lubricating-oil pump. Each bearing also has a separate
t o carry out a calibratio~iexercise t o see how bendi the shaft - the maintenance of
the only force transmitted, This means that the shaft
"IeSS is affected by shaft high pressure (300 bar maximum) jacking oil supply
centrelines must be coincident at the point where the I:llsures that no metal-to-metal contact is made.
LOW power laser-based optical alignment techlliqll which is injected at the bottom of the bcaring. This
coupling faces meet, and tllat the axes of the two 11 is continuously fed into the wedge by frictional
Can also be used the shaft fully Th lifts the journal in the bearing when starting from
s ~ ~ a f must
ts be parallel at tile same point. Using one nil leaks away axially towards the edges o f
are suitable for initially setting up thc pedestals rest, thereby preventing wear and reducing the starting
rotor as a datum, it is possible to set the
the required catenary. These techniques have the torque requircd from the turning-gear drive motor.
reiativc to the datum coupling gap a,ld 11' \s'llite metal surface is either cast into a mild
advantage that, when adjacent turbines are operatin
periphery measurements, and so on do,,,n the line, the resulting atmospheric disturbances and structl liilcl 10 form a bearing shell, whicli is supported
T O carry out gap measurements, it is necessary 11, lhc;~ringbody, or cast directly into the bearing
borne vibratioih lnay "leir use' 8.1.2 instrumentation
t o separate the couplings slightly. The gap between ilsclf. Both types are in use in modern U K
Aiignmcnt of the shaft necessitates the outer be Instrumentation specific to the performance of the
the coupling faces is then measured at a number o f ings being raised. On large turbine-generaton, t
points around the rotor, for a number of bearing normally comprises white-metal temperature
outer bearings could be up t o 25 mm above the leve Ijrnling assemblies are split in halves on the
rotor positions. If the coupling is correctly aligned, lI11I Centreline and held together by bolts, the and oil inlet pressure, indicated both locally and in
of the central bearings. the Control Room. Bearing oil outlet temperature is
the gap should be uniform all the way round. If l i c i ~dowelled together to assure precise lo-
It is often necessary t o deliberately misalign P normally indicated locally, with remote alarm facili-
this is not so, the bearing positions can be modified ticulai bearings when cold so that a n acceptable 11
by the appropriate amount and the gap remeasured. enrings are normally spherically seated in their ties. Provision is also made at the bearing housing
alignment is achieved. T~~~makes allawance for sup to monitor vertical and horizontal vibration modes.
The concentricity of the two rotors is checked by 5 On four pads under which shims are placed
structure expansions when the turbine is at oper Jacking oil pressure is monitored local t o each bear-
measuring, using dial gauges, the radial difference llltc precise horizontal and vertical alignment
temperature. The required offsets are included eiti ing, with alarm indication in the Control Room.
between the periphery of one coupling and the peri- lilft line. The spherical seating feature assures
by removing/adding shims from/to the bearings
phery of the other coupling while rotating the separate I1 assembly, the bearing will automatically align
be adjusted, or by deliberately allowing a known e
rotors. Any errors can be corrected by bearing ad- Ol'reCt axial tilt; this is necessary because, when
in a coupling. The amount of offset can be deci
justments, as for gap errors. ~ I I R laces are set and bolted flat together, the 8.1.3 Bearing p e r f o r m a n c e
by measurements taken from a multilimb-manom
Other methods of alignment, based o n strain gauges t~carillgon each shaft needs to be higher than The first step towards understanding the performance
system, or derived from operational experience.
and optical techniques, have been developed. llPl bearing due to the natural bending catenary of a bearing under dynamic conditions is t o know
The strain gauge technique is not widely applied I each shaft under its self weight (for further the condition of the bearing oil film in vibration; as
but can be used o n the coupled shaft at a suitable )I' illignment refer to Section 7 of this chapter). described by Smith 191, this is different from the
point near the coupling t o be checked. It measures 7.5.2 On-line monitoring ul.ical seat Is restrained in normal operation. steady state hydrodynamically-generated oil film noted
the bending stress of the shaft at that point by the Manometric systems are used for on-line monito 11 large turbine bearings are up t o 530 mm earlier.
application of strain gauges. The presence o f bending of the bearing pedestal positions. Connection Cl. and have length/diameter (L/D) ratios in When a sufficiently large journal vibration is super-
stress is indicated by the strain gauge giving a sine each pedestal provide information o n the relative lev of 0.5 to 0.7. Generator bearings tend to imposed o n the steady state running condition, changes

104
Bearings, pedestals iind t i ~ ~ t i i ~ (i )(~,? I I I

with the \x~l~iii.The pressure-bcaring filiu ilicli ti;~vrli


round m'itii the journal and the operating c<,ii<liti<,~i
is lno longer closely reiated lo the sleady i i ~ r > ~ ! i i i f ~ ,
condition.
In a journal whirl of sustained magnitude ;it C O I I ~
stanl eccentricity, the ideaiised bearing is in a conditii>n
of stcady running relative to axes rotating with thc
whirl. There is an effective speed o f rotation, relative
to these axes, of (N-ZF), where N is the speed of
rotation o f the journal and F is the frequency of
whi1.l measured in the same direction. The position
of formation o f the pressure-bearing film depends
on the direction of the mean ~eripheial speed of
beaiing and journal relative to the rotating axes, that
is on whether N is greater or smaller than 2F.
When the frequency o f whirl is iess than half the
jouinai speed, the piessul.e-bearing film is built up
on the trailing side of the minimum film thickness,
as in Fig 1.122 (c). When the frequency of whirl is
greater than half tile journal speed, the gressure-
bearing film is built up on the leading side o f the
minimum film thickness, as in Fig 1.122 (d). The
diagrams show, for each case, the direction of the
reaction applied by the journal to the bearing.
When a rotating load is superimposed, on a much
smaller stcady load, the1.e is a variation of eccentri-
city during each whirl rotation, but the film regimes
obtained resemble those given by whiri of constant
eccentricity.
With rotating trailine film the reaction of the bear-
ing on the journal (opposite to the reaction just
mentioned) has a component normal to the attitude
radius in the direction of the whirl. This component
tends to increase the whirl. An explanation is thus
offered of why a rotating trailing filtn is associated
with tendency to instability. As reaction force in-
creases and minimum fiim thickness decreases, the
direction o f the reaction swings closer to the attitude
radius, so that if there is damping elsewhere in the
system, a steady condition o f whirl may be attained.
With rotating leading film the corresponding com-
ponent tends to damp the whirl. A bearing in this
regime does not excite instability.
The transition between these last two conditions
is o f importance, because it may exhibit a sharply
resonant tendency to maintain rotor whirl when there
is a natural frequency close to half running speed.
Figure 1.122 (d) gives a diagrammatic representation of
this film condition: the angular extent of the pressure-
bearing film is not known.
Prediction of rotor dynamic behaviour depends
on an adequate understanding of the bearing per-
formance, for which full-size bearing test rigs are
commonly used. Dynamic behaviour can also be in-
fluenced by the stiffness of the support structure and
the effectiveness o f the connection between bearing
pedestals and the turbine foundations. In this latter
respect, bolting to steel foundations is more predict-
able than bolting to soleplates grouted into mass
concrete foundation blocks.

107
The steam turbine Chapter 1
- Bearings, pedestals and turning gr?a

8.1.4 Factors affecting bearing life


Wear of journal bearings mainly occill-s with an oii
rliiving ioad seductioii and following a Isrbiae i i i i , .
ln opc~.alion,the pad faces are slightly iiicliiied lo
a
: 1i,.noim 10'1 IHRUSI I.UBRIChTINGOILOHhlN
film of very sillail minimum thickness and mild local !lie facc of the thrust coilas and the wcrlge-sbaped -: ,11N COLLAR ANNULUS

wear, especially as new bearings 'bed-in', is to be cavity thus formed fills \r,it11 oil. As thrust jpicssose I
expected. I-lowevei, severe wear is a symptom of
trouble and can be caused by:

e Contacling asperities on substandard joul.i~ai and


bearing surfaces.
Scoring by oil-borne solid particles.
8 Excessive iocai pressure or temperature.
b Electrical pitting.

Fatigue cracking a f the white rnetai siirface can be


caused by heavy vibration or cavitation within the
oil film; the latter is usually caused by a restricted
supply of oil.
Corrosion rarely occurs, due to the control by
treatment plant of moisture in the turbine lubricating-
oil system (see Chapter 2).
Electrical erosion of bearings and journais has oc-
casionally given trouble. Small shaft voltages are set
up by eiectromagnetic induction in the generator
rotor. Higher voitaaes sometimes occur in the turbine.
produced electrostatically. Bearing erosion is prevented
by effective insulation of the generator bearings from
earth and the application of an earthing brush to
a suitable point on the turbine rotor system. Both
insulation and earthing brushgear require good main-
tenance as well as good design to assure their correct
functioning.

8.2 Thrust b e a r i n g s
The purpose of the turbine thrust bearing is to pio-
vide a positive axial iocation far the turbine rotors
relative to the cylinders. To achieve this, it must be
able to withstand the unbalanced thrusts due to blade
reaction and steam pressure acting on unbalanced
areas. It must be free from maintenance, except at
major outages. Since it is universal practice to use
solid couplings between rotors, only one thrust bear-
ing is required in each complete shaft line. It is
normally located close to the areas where blade/
cylinder clearances are minimum and operating tem-
peratures are highest and is split on the horizontal
centreline for ease of asssembly and maintenance.
All large UK steam turbines use the Michell tilting-
pad thrust bearing (Fig 1.123).
Although the net thrust on the white-metalled pads
in the on-load condition is always in one direction,
i.e., typically towards the generator, a second set of
pads, termed surge pads, are incorporated on the
opposite side of the integral shaft collar to take ac-
count of transient reversals of thrust which occur
108
The sreani rurbil7e CI7aptel. I' .f Bearings, pedestais und turning geiii
.,,..,.
g
@ I'cilviliils in tlie l l ' arca o l tire tuibiiic arc troi-mall\, - inside the line o l tlre liall.
all round tiic ioiot flange
i ~ ~ i i i l lbollcd
y and dowelled to the foundations, It joint bolts; any seepage from the ends of tliese gioovca
ADAPTOR FLANGE RXIAINOICATOH
BODY ,
TI+RUSTC3Al> T H R U S I ?All SO,' l i , li<lnri,ei, common praclicc at the high tempciatore
i 3 , i i l 01' liie ti~rbincto make provision either lor the
is collected and ]piped away lo a dirty-oil drains lank.

iyiiiniris lo expand at sliding mounting points on top


r i i l l l i i i Pedestals or for tlic pedestal to slide i.elative
l i ! tlie foundations. For details o f cylinder support
8.5 T u r n i n g gear
N I I ~cxl)arlsion arrangcnlents refer to Section 6 of
The turbine rotors must be turned continuously
througiiout the process of waiming-through the unit
Iir lpcdestals incorporate facilities for the attacli-
p~.iorto start-up and, in addition, during the cooling
11 of lubricating and jacking oil supply pipework
process following a shutdown. Rotor and cylinder dis-
Ilc ilssociated bearing oil drain pipework. Mounted
tortion could occur as a result of uneven heating oi-
11 (or on) the enclosure are all necessary instru-
cooling if the facility for turning the rotors weye not
il~lliot~ connections, c.g., bearing temperature, dif-
available to provide circulation within the cylinders.
Illial expansion pick-ups, togethel. with eccentricity
Cylinder metal temperatures, specified by the manu-
n dctectors. A manometric level system
facturer, are the normal criteria for allowing a warm
o thc pedestals adjacent to each bearing
turbine to cease barring.
i l l liclccl lnisalignment due to support structure scttle-
TWOindependent turning gear facilities are usually
izirlil, for details of this system rcfer to Chapter 2.
i'i~rlicular care is taken to ventilate around the
(ii~tlrrlals,keeping them cool so that any yertical thci-
r l l i ~ li'xpsosion cffects, which might disturb the overall
aillical alignment of the turbine, are minimised. For
.
provided:

Hand barring arrangement.

Electrical turning gear (ETG),


~itllll)lc,many pcdcstals contain couplings which are
OlL SUPPLY PIPE THRUSTBLOCK i i i ~ ~ o ~ ~ nby d e dcoupling goal.ds; these guards are
ili?~!lseivescooled by oil sprays tapped-off the lubri- 8.5.1 Hand barring a r r a n g e m e n t
ilili oil supply to remove windage heat generated
Should the ETG be unavailable, provision is made
~Oillllingrotation.
to turn the rotors manually by mounting a lever and
I l l addition, those uedestals adiaccnt to the high . fulcrum apparatus at a prearranged point on the cover
rature components of the turbine are frequently
.. of a bearing pedestal. This lever operates on a per-
cted by thermal radiation shields, with provision
manent toolhed-wheel between two turbine rotors
NOZZLE $(!I I U I I circulatlori in the snace between the sh~cld
. , (Fig 1.125). This is usually an operational feature
irliil lhc pedestal structure, also to minimise thermal
DETAILOFTHRUST ANDSURGE to protect the turbine in a heat-soaked condition.
PAD NOZZLE SETTINGS Bki)ibIlaion effects.
Further hand barring, for maintenance purposes
only, can often be carried out by using a simple
crowbar against a toothed barring ring, replacing the
normal spacing ring between rotor couplings, and lever-
Oil sealing a r r a n g e m e n t s ing against a simple fulcrum plate secured to the ped-
OlLSUPPLY FROM
ends of the pedestals where the turbine rotors estal horizontal joint face (Fig 1.126).
MlliNOlLPVMP CHOKETUBES
are fitted with oil catchers. The baffle fins
I'm oil catchers, in conjunction with oil throwers
111c shaft, prevent egress of bearing lubricating 8.5.2 Electrical turning g e a r IETGI
'rom the pedestal. The rotors are turned slowly, typically less than

I
CON laving regard for the speed and size o f the bearing
CONTROLROOM 30 r/min, during start-up and shutdown by the ETG.
/._.._........ ..... i:oupling assemblies within the pedestals, the pro- An electric drive motor turns the rotors through a
I I I lo11 of oil mist is inevitable. The escaoe of this wormshaft and wormwheel, thereby providing a re-
..-A is prevented by the main oil tank vapour ex-
lors which, since the bearing drain lines d o not
duction gear. A jacking oil pump supplies high pres-
sure lubricating oil to the reduction gear.
LOCAL INDIC#TlON
AND ALARM 111 11111, maintain the inside of the pedestal at a Manual control of the motor is provided in the
air pressure than the turbine hall. There Control Room, and automatic stop and start faci-
I1 flow of air through the baffle ring and lities are also included in the motor switchgear. The
the surface of the shaft; this purges the oil motor overload trip is set at a value which prevents
NO 1 NOZZLE ack into the pedestal and via the bearina drains excessive torque being applied to a seized rotor. Elec-
Ihr main oil tank, whence it is discharged at a safe trical interlocking prevents the motor being started
iiotl. For details of the lubricating oil system see until jacking oil pressure is established.
A self-shifling synchronous (SSS) clutch is installed
TIC. 1,124 ~ h i u t tpad wear n~asuiemenrsysrern, reiying upon decreasing gap a: the naaale head causing a r i x in
leakage from the horizontal joint of the ped- between the drive motor and the turbine shaft and
indicated discharge oil pressure a a is commonly prevented by machining a groove provides a simple mechanical means of automatically
111
T h e steam turbine Chapter I' Turbine applicalio~,.;

FiG. 1.126 Vicn on ihc enid of a luibine coupiiilg.


ihoiviilg provision for iinnd barrilig during oalages ior
niaiilleliallce

pawls 'bite' and reactive torque is applied to thc


helically-splined sleeve which moves axially and slides
the clutch teeth into engagement.
The positions of the pawls and ratchet teeth en.
sure that the clutch teeth pass between each other
exactly, without making contact until full engagement
is reached; at this point the pawls leave the ratchet
teeth, and the flanks of the clutch teeth meet to take
up the drive.
It is important to note that the pawls merely sensc
zero relative speed and angular location, they do no1
carry the main torque. To prevent ratcheting and
consequent wear when the relative speed is high, rhc
i.'10.1.125 Asreiilbly or hand b a i l i n g cquipnlesc; lliir is an pawls are designed to disengage centrifugally.
operational alternative i n the event of tile main electrical The only load imposed on the pawls is the forcc
iinrning geni being unavaiiabic required to engage the clutch. In a very large clutch,
this could overload the pawls and so a relay clutch
is used. Here the primary mechanism is exactly as
described above, but the helically-splined sleeve, in
connecting or disconnecting the turning gear drive. moving forward, engages teeth to move a much heav-
The SSS clutch is a positive tooth-type overrunning ier helically-splined sleeve o n which the clutch teeth
clutch which is self-engaging when passing through are cut. A further refinement is an oil dashpot, which
synchronism, that is, immediately the speed of the cushions the engaging action, and prevents disengage-
input shaft exceeds that of the output shaft. The
ment as a result of rapid transient torque reversal.
clutch disengages automatically when the torque re-
verses, that is, when the speed of the output shaft
exceeds that of the input shaft (Fig 1.127).
At standstill, when the driving shaft begins to pro-
vide torque, the clutch will engage; if after this the 9 Turbine applications
torque ceases, the clutch will disengage. It will re-
engage if the speed of the driving shaft exceeds that
of the driven shaft, whether at full barring speed o r
at any lesser speed. 9.1 Power generation
Spring-loaded pawls, acting on a ratchet, sense the The main concern of this volume is turbines for the
relative speeds of the input and output shafts; when generation of electric power via a constant speed
the input shaft is about to overtake the other, the generator. In this area of technology, as applied in
112
1-ile stcain turbine 1-urllinc applii:alioii!;

l4Aia iiias~EiN~ti
<.OIOIIOI.VXLVE

1'14. 1.129 A 4-fiow exll~~ns$Lurbine cycle wills back pressure BFFT

BULK THANSMiSSlONP<PELINE
would otherwise ,~eed to be fed from tappings on domestic and industrial use. It is the purpose of
the main turbine IP cylinder. It is generally simpler C H P schemes to exploit this potential.
to arrange this with shorter pipe runs from the feed The condenser pressure in a typical turbine fo

1 : ~ . 1.130 Diiciici !heating supl>ly scheme irilil special tilrbine desigli

pursued for future plant. the saturation temperature corresponding to the steanl
Condensing-type boiler feed pump turbines are also pressure, i.e., at 33-45°C to 49.5% for pressur
o f single-cylinder single-flow design and, because they 50-120 mbar. Unfortunately, temperatures as lo
exhaust into the condenser, their inlet steam conditions these would be unacceptable for transmission t 1.131. More than two pressures could be used of ach~evingcontrolled extraction pressures, since con-
I tile advantage o f liigher thermal efficiencies but trol valves can readily be supplied in the ii~tcr-cylindel-
ill^ expense o f greater com~iication.The extraction crossover piping downstream o f the 1P exhausts. The
Ill is i~assedto two district water heaters, so that asymmetry is provided by designing for a different
c i l ~ a l temperature rise is obtained across each number of stages in each flow of the turbine.
Figure 1.131 depicts three large existing turbines

higher pressure. The former is know11 as a n exlraclio


o r pass-oul turbine whereas the latter is called a bac
pressure turbine.
9.3 Combined heat and power (CHP) Many plant configurations exist to suit the pa
The inherently poor efficiency of the turbine-generator cular requirements of each specific application. T
in power generation applications has always been re- examples are given here to illustrate the range
garded with concern by turbine designers. The reasons plant and some of the possibilities. The first exampl
for this are discussed in Section 3 of this chapter, is o f a condensing turbine designed at the outset fo
where it will be seen that the major part of the heat a domestic heating installation with electrical powe
produced by the burning o f fuel in the boiler is generation as well. The second example illustrate
rejected as low grade energy in the condenser cooling how a n existing large power station might be con
water. It has long been appreciated that there is a verted for a similar heat load. lrical Power is also generated by means of a All the plant shown in ~i~ 1.131 would normally
major thermal advantage to be obtained if such low i n both cases, steam is extracted from the turbin tional shaft-driven generator. The asymmetric be installed at the existing power station. ~h~ only
grade energy can be employed to provide heating for at two different pressures, as shown in Figs 1.13 lindcr provides a neat solution to the problem modification to the existing turbine-generators would
117
7-urbitie a p p l i c a i i o ~ ~ s

STEAMTURBINE

BULXTFINSNISSoNIPLLNE

FIG. 1.131 CHP conversion lor a district iieaiing supply rcl>erne

be the provision of bleed and condensate return tap- the economics o f such schemes are likely to
pings, with control valves as shown. The district water increasing favour.
system would include the heaters, pumps and pro-
vision for make-up and heat storage so that the
operating periods of the auxiliary turbine generator
and its loading schedule can be controlled with a 9.4 Combined-c~cieplant
degree of independence from the heat demand.
Such a scheme could provide heat as well as power producing process where the prime movers empl
FIG.1.132 Simple 'combined cycle' plant, employing one gas turbine and one steam turbine
to a large city located many kilometres away from more than one working fluid in a combination
the power station. turbines. The most common and practical form

which makes it attractive for countries with cold with variants of this basic theme.
winters. One difficulty which has prevented a more Figure 1.132 shows a combined-cycle plant i lliry steam turbine is able to make use o f this applicable to countries having an abundant supply
widespread use of such schemes is the cost and com- simplest form with the heat from the gas-tu llhe of the low temperature exhaust made possible of oil or natural gas where there is a need to rapidly
plication of distributing the heat thus provided to exhaust utiiised to generate steam in a heat-reco l o condenser. The condensate is returned to the extend the utilisation of these resources to meet the
hundreds of domestic premises. The most successful steam generator. This cycle makes use of the inh li generator, via a single combined feedheater populations' demands for electrical power. A phased
schemes have been applied to new developments of ent characteristics of the gas turbine process, wh de-aerator, followed by a pump. Typically the development could be implemented, the first stage
large apartment blocks. With ever increasing fuel combustion takes place and, following expansion 1, lilrbine output will be about 50% o f the gas being the installation of gas-turbine generators to
costs and the need to conserve valuable fossil fuels, the turbine, heat is rejected at a relatively high te meet the immediate needs for electrical power, thus

118 119
1-lie steam itirbine

cxl~loitingthe potciitial short dclivcry tiines and simplr depends on:


izistailation 01' packaged units associated irritli gas t u i -
binc tcchiiology. 'The scconil stage wortid be the iii- i'lic economies oS scale; i.e., lhc generally lob
stallation of the stcam gcnesatvrs, steaiii turbine and ca1)ilal cost per unit oull,ut given by larger oolj
auxiliaiies, illus providing a Surlliei increase in power 1)lanl.
output at a lhigli overall therlnal efficiency of about
45%. e The steal" cycle arid conditions associated with t i
A tliird stage might be considered if a furtlicr selected steam generation system.
increase In output for sliort pel.iods during load peaks
is desired. Supplementary firing would be fitted to 8 The availability of plant designs for the steani
the boiler to generate more steam to meet the full generator and the turbine-generator.
capability of the steam turbine in respect of steam
inlet temperature. Because gas turbines are normally b The size of thc grid system and the individual
operated with a high excess air factor, there would generating units o n it.
be sufficieiit air in the gas turbine exhaust to support
The size of the organisation owning the plant, and
the combustion of the additional fuel.
its economic environment.
Plant using a high proportion of supplementaiy
firing is someti~iies co~istructed making use of the e The available construction time.
gas turbine primarily as an air supply for the main
combustion process. In this type of plant, the steam The available site area.
turbine may generate as much as eight times the
power o f thc gas turbine and employ a multistage
feedhearing system to maxiinise efficiency. This may
be more rliermally efficient tliatl a steam turbine on era! period of consolidation worldwide, with relativ
its own, but is prone to giving a lower a\,ailability
few new stations being ordered. Those that w
unless a means o f cliangeovcr from gas turbine t o
ordered were generally established design, or part
forced-draught fan is provided.
a deliberate series ordering o f plants. In the larg
A Inore common vaiiant is t o use one or more
industrial countries, tandem-compound turbine siz
gas tu~.bincsin a dual-pressure heat-recovery steam
have stabilised in the range 600-800 MW for sup?
generator. This permits more heat extraction from the
heat plant, and 900-1300 MW for saturated ste
gas turbine exhaust since the low pressure circuit heat
plant. There have, however, been a few individ
transfer can take place at a lower temperature than
in the high pressure circuit. A typical arrangement is
shown in Fig 1.133. If more than one gas turbine is
uscd, additional flexibility of steam turbine operation cross-compound units in the USA. Saturated steant
is possible, since shutdown o f one gas tt~rbine will plant has included a 1500 MW tandem-compoui,d
not prevent steam turbine operation. More efficient
part-load operation can be obtained in this way.
Combined-cycle plant developments are likely to turbine manufacturer can offer a range of outpu
follow the development of the gas turbine. Higher
combustion and exhaust temperatures will lead t o
higher overall efficiencies. As the practicability of
burning a wider range of fuels (Including coal) in will preclude the larger plants, and the 250-350 MW
the gas turbine improves, the application of combined- range is often favoured.
cycle plant will become more widespread. With the Looking to the future, it appears that the selectioi
current state of the art, there are no limitations t o o f the unit size will be increasingly determined b
such further development in respect of the steam the system size, the plant ownership and the ratin
turbine. A wide range of outputs is generally offered by of nuclear steam supply systems. In the USA, wher
manufacturers, using various numbers and size-ranges there arc a number of relatively small utilities, t11
of standard gas turbines in combination with steam preferred unit sizes for fossil-fired piant are like11
turbines of modular design. to be around 350 MW and 700 MW. If new nucleat

reactors. In France, with a large utility (EDF), th


10 Future outlook
FIG. 1.133 Dual pressure 'combined W e ' plan1
more likely. In Japan, there is a committed plan
10.1 Unit size and rating development towards fossil-fired units rated a t up to
The selection of unit size for a particular application 1000 MW, and nuclear plant up to about 1200 MW.
120
Tlie sleani tuvbitie

T11c ijiiilcd l<ingdoin 11as also gone t l ~ s o u g l ~a 10.2 Supercritical plant As mosl modcin toibine blading in lHIJ and 11'
period of consolidation in the 1970s and 1980s. After Onc effective way of achieving increased thcrmal i. ,,ti51 c,lI,cr have ail m t i a cyiindo or it must tuibincs airzady has an internal eificiency in the range
a relatively rapid increase in unit size from 30 MW in ciency Is to increase stearn pressiiie. The limits il I>ii,c<lcylinder for the first two expansions. 90°/0 to 95%, ilic potential inipl-ovemcnt is 1101 iargc.
1945 lo 500 MM' In 1970, this lhas only increased to natural circulation boilci are around 180 bar, i i ~ y l i ~ ~increases
~ies rnaciriire iengtll and cost, Turbine makers h a w developed standard blading fa-
660 MW subsequently. Thc carliest 660 MW unit was ailhough assisted circulatioil may be used at i1ip.h co~nbii~cd cylindci may give tlic possibility inlilies of lhigli efficiency wliicli are tolelalit t o the
ordered in 1966 and was in se~wice by 1974. This ~ICSSUTES, an overall imp~~ovemeot in station efficiel~ ealing between the two e x ~ ~ a r i - range o f stcam flow incidence angles, which arise in
inodest rate of development has ixoduced piant of is not achieved unless the pressure is advanced r $ 8 , i l t i i : to lhc close proximity of sections at different applicalions aiid different conditions of op-
excellent thermal efficiency and reliabilitv... and UK about 240 bar, i.e., above tllc cl.itica1 prcssurc i!ii i i j l i l reheat temperatures. Combined H P / eration. Root and tip clearances are as small as
manufacturers' designs have becn progressively devel- water/steam (221.2 bar). Although the use of sup i i c ~ s iiave, however, been wideiy used by practicable, with as many flow constrictions as tile
oped and refined to take advantage of new technology, critical pressure requires special consideration in 111 ratrrpanies and their associates in machines design permits. The detailed geometry of these restric-
design methods, and manufacturing rnetllods in the design of the boilcr, the iniplications for the turbin tions can aliaw some reduction of the flow discharge
intervening years. only concern the higher pressure as sucli. 01' ll~ese developments prescnts technical coefficient, so that steam leakage through these clcar-
In the late 1980s, it has been judged that the time A further improvement may be obtained by in (~ivcnsufficient time and resources. Their ances Is minimised.
is right for a further increase in unit sire for super- creasing steam temperature. Most of the supercritica in practice depends o n potential customers The development of L P turbine modules is a costly
heat plant to 904 MW, in order to meet both domestic plant in service worldwide operates at 538"C, altho "cd that the potential return in improved and lengthy process, yet there is always an incentive
and overseas requirements. For the domestic UK needs, some 565°C plant exists, and there are some pion ot accompanied by additional risk either t o increase the cni~austaica of each flow seaion t o
ing units with temperatures as high as 650°C. At operational flexibility, or availability. seduce the exhaust kinetic cncrgy (the leaving loss).
this offers substantial benefits from the economies
higher temperatures, the efficiency is often boosle , tile development programmes embody This development may aisa permit, for particular unit
o f scale - typified by the physical dimensions of
still further by using double reheat. Apart from 111 I;itlge of research, design, rig testing, and sires and steam cycles, a reduction in the number of
tile turblne-generator being only marginally increased
efficiency benefit, this has the $merit of reducing 111 ~ p ucom~,onent testing, which, coupled with the LP cylinders: this is a wortliwliile objective to save
from tlie 660 MW units. The initial steam conditions
turbine exhaust wetness from thc high level that sucl ll k i i C prototype unit, will give the necessary cost and reduce the size o f turbine liall requiied. The
have bccn advanced from 160 bar, 565°C to 176 bar, lasr-stage and penultimate stage blading is always
advanced initial conditions would otherwise entail.
565°C thus providing an increase in thermal efficiency The use of supercritical plant has varied consid btc XI which such plant will be i~ltroduccdis the limiting area of design; in terms oT the stearn
without sacrificing operational flexibility. ably through the world. In both the USA and Japati depending as it does on factors
I ii~~cer.tain, bending stresses on the blades and the large mass of
For nuclear plant, the choice will be determined it has been used t o a considerable degree for lail lcclricity demand, fuel costs, the economic the blades which imposes a large centrifugal stress
mainly by the reactor type and size. For advanced gas- units for base-load operation, typically up to 700 M : 11,lhc extent of alternative energy sources, on the blade fastening to the disc. Lasl-stage blades
cooled reactor plant (AGR), the preferred reactor size tandem-compound and 1300 MW cross-compoun irbishment of existing plant for extended for 3000 r/min turbines have been developed up Lo
is in the 660-750 MW range. Being a superheat cycle, The initial steam conditions have normally been aroux 1200 mm long: this is believed to be about the limit
this requires a steam turbine almost identical to that 240 bar, 538°C. In Germany, supercritical plant 11 for conventional 12% Cr blade materials. Indeed,
for a fossil-fired unit o f similar output. Any turbines been in the smaller range, up t o about 200 MW. the 1200 mm blades in scrvicc in the USSR are made
required can therefore be derived from the existing the United Kingdom, two prototype units were bu from titanium alloy, and this is likely t o be the pre-
families of modules covering plant up to 900 MW at Drakelow C with steam condltions of 240 b ferred material for longer blades. In particular, the
''. rbine blading development
01 more. 593°C. introduction of longer last-stage blades is likely to
For water-cooled reactors, the reactor sizes are up At temperatures up t o 5 6 5 T C , low-alloy creel) r)llinent of turbine blading can be expected permit the use of 3000 r/min machines with the lar-
to 1200-1300 MW, although some enhancement of resistant stccls such as 0.5%Cr Mo V and 2.25 illlsc to mecl three objectives: gest nuclear reators in 50 Hz systems, althougli the
this may be expected. For the first UK PWR at Mo are used foi- the high temperature components 3600 r/min equivalents are much further away.
Sizewell B , the decision was made in 1979 t o employ The pressure determines the thickness of pressm lcril inanufacturing cost.
two 630 MW turbine-generators with the 1260 MW(e) containing sections such as steam chests and pi1
reactor, as these made substantial use of modules work. The combination of steam conditions. mate
developed and proven for the 660 MW fossii-fired thickness, and operating regime determines the pl
life in terms of creep and thermal fatigue. At pr ' il efficiency, including new L P blading of 11 References
plant, in particular the LP turbines and the generator.
sures of 240 bar and above. and narticularlv a t t le I exhaust area.
Those elements specific to the saturated steam cycle, [I) Tiaupel, W.: Steam turbines, yesterday, today and tomorrow:
such as the H P turbine, moisture separator, and higher temperatures o r where reasonable operation Pioc, IMechE 193 No 38. 391-4W: 1979
steam/steam reheater (see Chapter 2), had been de- flexibility is required, other high temperature material 121 Harris, 1. R.: The Parsons Centenary - a hundred yeais of
are used, such as high-Chromium (9-12%) ferritic I of blade manufacture can be minimised steam turbines: Proc. IMecliE 198 No. 53. 1-42: 1984
veloped and proven in plant supplied to overseas
by UK manufacturers at ratings up t o 110 MW. It alloys, or austenitic alloys. Austenltic alloys have sonic application of computer-aided design and 1' I . I h 2 : I . , 4 I) 1": :4..< .,l
Jv*!: s;le.J I
adverse properties, such as poor thermal conductivity Ire, in which the optimised geometry from P\<h . . r b n e , lo: % 11, ,,c~.:~aL.#., ~ s , # ~ , ln\ l%t . l k C I#.~::cI..v
is expected that, if there is a series o f PWR stations
and high thermal expansion, so the current trend is rnnce, vibration, and stress considerations is *;,,I Plllll ,, P,.,\",.<C, \\a';, Red.,,,, t$h?
in the UK, the decision will be made at some stage 141 Stodola, A , : Steam and Gas Turbines, Volume I p 316: Peter
to develop the ferritic alloys for use in the large cast d directly to the numerically-controlled
to select a single turblne-generator per reactor, thus Smith. New York: 1945
and forged components. Development programmes ar
taking advantage o f recognised savings in capital cost, (51 Traupel, W.: Thcrmische Turbo Manchinen, Volume I p 491:
under way in the USA, Europe, and Japan for d \loved, integrity blading can be obtained by at-
construction time and operational costs. In line with Springer-Verlag: 1966
signs and materials for the so-called 'ultra-supercrltica 011 to detailed design t o reduce stress concen-
developments elsewhere, it is not expected that reactor 161 Miller, D. S.: Internal Flow Syrtemi. Volume5: Biitish Hydraulics
piants of 350-1000 MW with steam conditions su y controlling the vibration characteristics to Research Asrocation: 1978
size, and hence turbine-generator size, will advance as 310 bar 590°C, and later up to 350 bar 650" nances near running speed, and by reducing
beyond 1500 MW in the foreseeable future. 171 Craig, H. R. M, and Cox. H . J. A , : Performance Estimation
all with double-reheat cycles. These plants are not, or improving the quality) of attachments such of Axial Flow Turbines: Proc, IMeellE 185. 32-71: 1970-71
There is therefore no perceived need for unit sizes to however, likely t o be in service until after the year uding lacing wires, and erosion shields. There
advance substantially in the next ten or twenty years, 181 Biiggs, 3. 2. and Parker, T. D.: The Super 120ia Cr Steels -
20W. nliince to be made between robust blading with aii update: Climax Molybdellum Company
beyond about 1000 MW for superheat plant o r 1500 The use of the double-reheat cycle introduces cctions and efficient blading which favouis a 191 Smith, D. M.: Journal Bearings in Turbo machinery: Chapman
MW for saturated steam plant. additional complexity. First, additional boiler contro sl)cci ratio (length/chord). and Hall: 1969
122
Governiiig system:.
- ..
13.4 Mo8stuie separator rel>c.itc~sIMSHsi
134.1 Separators
13.42 Stcanl~o-sicamreilearers
ii8rliinc totors 13.5 Stealn suppiy and drains systems
!%11(,3s nioilitors 13.51 First-siagc reilcat
<m<:<><I.t,i,
~oolir,g 135.2 Secandsfage reheat
cc,oii,,g at turbine 13.5.3 Performance ino~>itoring
(:ooli#,gsysfetn 135.4 System drains
C H A P T E R 2 135.5 Separator drains
135.6 Rehearer drains
it~lltro8~aeof steam on components
N,,,lol cxiiaciion devices 14 R e f e r e n ~ e ~
ib10tioil ipioteclion
Turbine plant systems 1 5 Additional references

1 Governing systems
1.1 Introduction 6.1 Lubrication requirements and typical ariangemenls
6.2 Oil Dumps
1.2 Governor characteristics
62.1 Main lubricating oil pump
Verning s y s t e m s system. T h e initiai transient speed rise following s u c i ~
12.1 Simple scheme - boilcr on pressure control
6.2.2 ~urbine-drivenail booster pump a ioad rejection, contaitled by t h e governor, is pri-
1.2.2 Turbi~iemaster load controller with boiler on pressure
6.2.3 AC and DC motor-driven auxiliary oil pumps marily d u e t o t w o factors:
controi
12.3 Boiier master ioad controller 62.4 Jackino-oii DumDs and "riming Pumps
1.3 Subsidiary functions 6.2.5 Other liumps Tile stored energy o f steam within tlie turbine a n d
1.3.1 Acceleiation feedback
fi 8 Oil tanks n i n g system o f a large
6.4 Piping used f o r electricity production via
it"ssociated pipework.
1.3.2 Unloading gear
6 5 Oil coolers
1.3.3 Gaveinor speed reference
1.3.4 Closed-loor, controi of turbine electrical load 6.6 Oii strainers and filters
6.7 oil purifiers and cosiescers
)power netwo1.k are:
* T h e time taken by the turbine vaives t o ciosc in
1.3.5 Overspeed testing
1.3.6 On-ioad testing
6.7.1 centrifugal separation systems
6.7.2 static oil purifieraicoalescers
$8 B 'I!% iiii)i;iin
liil
the speed rise within accentable limits
ihu ilnit becotne disconnected f r o m t h e l o a d .
t o t h e sensed overspeed

1.3.7 Automatic run-up and loading syrtemr 6.8 Oils end 4reases
1.4 Electronic governing 6.8.1 Oils It is aiways well inside t h e overspeed trip setting a n d a
- .orocessina
1.4.1 Dioital 6.8.2 Greases
illrol t h e steam valve positions (and hence
full analysis is given in Heilbronn [ I ) .
1.5 Goveinor valve relays 6.9 Jacking oil systems ,lt<i gcneratedj in response to signals f r o m t h e
1.5.1 Governor vslve relay and contioi unit Type 1 A n electrical governing system f o r a typical turbine-
6.10 Greasing systems lilr, o r f r o m a separate station automatic control
1.5.2 Governor valve relay and control unit Type 2 generator with multiple steam admission paths comprises
1.5.3 Governor valve relay and control unit Type 3 7 Gland sealing system
m a n y elements, a s depicted in F i g 2.1. Since it includes
1.54 Rehesfer relief valves 7.1 function and system layout
1.6 Hydrsulic fluid system a t least one closed-loop control function, t h e machine
71.1 Labvrinfh alandr llrvl t h e initial run-up a n d synchionisation o f
16.1 Filtration 7.1.2 sysiem lahut and network characteristics f o r m an integral part of t h e
1.7 ~oiierfeed pump turbine governors 7 2- Temosisfure
~,~ and Diessure contioi system. T h e orimarv feedback is o f turbine shaft m e e d
7.2.1 Temperature control
2 Steam chests. vaives and loop pipes i s in matching t h e power generated to which is usuaiiy measured by a toothed-wheel a n d probes
7.2.2 Pierrure control
2.1 Steam chest arrangements and construction 7.3 Gland steam condenser !I ~ l r i ~ i ~ i n dby
e dresponding t o network frequency at t h e HP end o f t h e machine. T h i s signal
. is orocessed
2.2 Steam chest materials by a m o d u l a r electronic system, o f t e n mounted in a
2.3 Cover seals 8 Flange heating system
2.4 Steam strainers 8.1 Function and system layout cubicle quite r e m o t e f r o m t h e turbine, t o f o r m o u t p u t
2.5 Stop valves 8.2 Control signals which are directed back t o each steam valve o n
2.6 Governor vaives I <,f these functions is a vitai o n e f o r t h e safety
9 LP e x h a u ~ f*pray coaling system t h e turbine. T h e processing is complex a n d is subject to
2.7 Loop pipework
2.8 Crossover pipework 9.1 Function and system layout detailed variations for each application; it generally
9.2 Control includes t h e following:
3 Turbine proteotive devices f these connections are opened, either by a
3 1 PosSibie hazards 10 Drains svstsmr
tern fault o r by t h e unit's o w n protection 8 T h e speed/ioad characteristics o f t h e machine when
3.2 Protection scheme 10.1 Function and svstem iavout
' s t e a m flow a t t h e instant o f disconnection synchronised.
3.3 Electrically-signaiied trips 101.1 Stait-up drains
3.4 Overspeed trip 10.1.2 Continuous drains le sleam flow necessary f o r steady state opera-
3.5 Mechani~ally-operatedtrips 10.2 Control 132 (3000 r/min) by t h e a m o u n t necessary t o A predetermined relationship between the high
3.6 Operator tripping facilities illl-load. T h e excess energy input m u s t h e pressure ( H P j a n d interceptor valve position.
11 By-pass Systems
4 Turbine instrumentation 11.1 Configuration rapidly i f an unacceptable overspeed is t o be
11.1.1 Pressure control valves Facilities f o r o p e r a t o r control.
4.1 classification of instrumentation I . Tile governor performs this function by re-
4.1.1 S u p e r ~ i ~ oinstrumentation
w 111.2 Isolating valves
lij! l o t h e initial change in speed t o close t h e
4.1.2 Efticien~yinstrumentation 11.1.3 Dump tube Features t o limit t h e m a x i m u m speed o f t h e machine.
41.3 Auxiliary system instrumentation 11.2 By-pass systems for nuclear plant
4.1.4 Condition monitoring instrulnentation 11.3 By-pass systems for fossil-tlred plant lilc oversoeed trios (described in Section 3.5 Features t o limit the o u t p u t in t h e event o f abnormal
4.1.5 instrumentation associated with protection and control 11.4 Problem9 with by-pass systems
11.4.1 Noise operating conditions.
equipment
4.1.6 ln~trumenfationto provide posl.incident records 11.4.2 Water ingress
114.3 Theimsi shock onnei is always maintained. T h e governor Features t o permit routine proving and testing o f t h e
5 Turbine foundations 11.4.4 Leakage flows
111s this safety function and, since it maintains system.
5.1 Tuning
1 2 Operational flexibility ii lilt r u n n i n g speed, ensures t h e continuity
5.2 Concrete foundations
5.3 Steel foundations 12.1 ~ypicaloperational regimes rilpplies f r o m its o w n generator a s weil a s T h e a b o v e functions are described i n detail i n Sections
5.4 Spring foundations 12.1.1 Base ioad
5.5 Sub-foundation 12.1.2 Two-shifting lily l o reconnect t h e generator t o t h e power 1.2 and 1.3 o f this chapter.
Turbine Governing s y s t e ~ ~ ~ s

6 P
g 9
WHEEL 8 PROBE
i i oil and off at will. On a large power system,
$ 9 :$
A
g units, similar consumer demands may apply >OD.
iciuations may be a significant percentage

an, these power system requirements imply a 50.-

,itlistand a full-load rejection safely and to


ilppropriate contributions to system frequency
GOVERNOR EOUlPMENi CUBICLE
iliain characteristic of a governing system is
,li- Illc relationship between the generated load of
iiliollcd machine and speed, which is the prime

0 e
48 49 10 51 12
FREQUENCY, H i
1
2880 3000 3120
SPEED, d m n

FIG. 2.2 Governor iieqiiesc)' reguiaiio,i ciiaractelistic

1 Nl, = rated speed


N,,,, = speed at full-load
I = speed at no load

FIG.2.1 Eie~tricaigoverning system applied to a i5'ei rtealll turbine

>vratoi to adjust the load contribution made


lachine relative to the others on the system.
Fitted to each steam valve is a relay, whose function unit characteristics are described later in this sectioll shows how the droop characteristic is varied
is to convert the low power electrical signal formed One o f the features of a n electrical governing sysl g the speed setpoint. If the machine is at
by the processing equipment into the movement of is that since the conversion to mechanical movement and unsynchronised, point a , on the diagram,
the steam valve. Since the mechanical forces involved made at the steam valve relay, all other interfaces c setpoint is raised, the frequency will change
are substantial (150 kN) and the time for full stroke electrical. This facilitates connections to sta I 10 a2 and then to a,. If, however, the machine
may be less than 2W ms in the case of a load rejec- automatic control systems, alarm systems, data proc hronised to an infinite system running at constant
tion, several stages of hydraulic amplification may be ing systems, switches and indicators both on llcy a , , an increase in speed setpoint will cause
necessary. Conversely, in order to obtain fine control operator's desk and at the governor cubicle. All th ld to be raised to b2 and eventually to b3. It
over load (or speed when unsynchronised), the gov- other systems are closely associated with either the ope 1 be noted that the linear characteristics drawn
erning system needs to be very sensitive and capable of tion or maintenance of governing systems. dcalised; in practice they may be non-linear.
moving the valves to within about 0.2% of the required cless, the degree of adjustment of the speed
position. The needs of high resolution and the ability
to amplify small electrical signals, necessitates the use
of precision hydraulic components with fine clearances. 1.2 Governor characteristics normal frequency, with a margin. Typically the
Although earlier mechanical/hydraulic governing systems In normal operation the turbine-generator is syncll of 0l)eration is '~6% o f nominal system frequen-
shared the lubricating oil supply, adequate reliability nised with and connected into a n electrical power S 01 the turbine unsynchronised at no-load.
of the precision systems is only assured by the use tem, comprising other generating units and an extens Illel feature to be noted from Fig 2.3 is the
of a separate high quality fluid supply unit. Various network for distributing power to the consumer. Typ
configurations of valve relay and typical fluid supply cally, in the UK, the power supplied at any instant PIC. 2.3 Eficct o i varialion of specd selpoini

126 127
Turbitie lati tit systetns

qilency f by adjusting the sjleerl sclpoinl to give char- beioiv tlie overspccd trip setpoint 0x1 a Ihigh dioop go cii:liacIeristics described so far in this sectioii iue
nos. On it low droop govciiior (say 4% or less), 111 Ilitil soit the jparallcl connection of turbine-
acteristic a,b,, then a fali in frequency by a i l ainoont
overspeed niay be contained by tllc normal droati 1015 onto rlic p o ~ c systcm.
i However, same o f
a T wili give a inotional load o f value c 3 , However, ibis
value of ioad Will not be attained, as tlie tul-binc valves cliaiacteiistic witliout any oecd ibr thr special overs~>eid tolcs o f a governing system aiisc frolii a considera-
OEMAhl"iii> ion0
are aiready fully open at point b i . Tire speed selljoint limiting facilities. 01 llir types of plant being contraiicd and the way
TO INCREASE OR
In eitiier case, to lnieet the requirement of containillp li the control of the scparate boiler and turbine
is said to be 'avcrwound'. The disadvantage of this condi- OLCREASE
SPEED SETPUN,
tion is that, if asked to reduce load on the unit, the thc overspeed within the trig setl>oint,it will be necessary
operator is unable to d o so immediately until lie has t o closc all the turbine valves withiii a fraction of 11 e purpose of this description is to note the
reduced the speed setpoint to the line given by c2a2. second. When the speed error reduces, the goverl~ol lres affecting the governor. Three basic options
Normal practice is either t o draw the operator's atten- reopens the valves to the amount necessary to maintain cd, each of which may include enhancements
the speed at the reduced value of load. scribed) t o improve the response to particular
tion to the overwound condition by an alarm or to
provide an automatic reduction at the sctpoint so O n reheat machines such as that depicted in Fig 2 llional circumstances. i:io 2.5 Sci,elralic of a silnple ioad frequeilc), cosi~olici
that an immediate response is possible, if required. it is necessary to control nor only the H P govcrnillg
Facilities for droop adjustment are often provided. valves but also the interceptor governing valves folio\
Typically a high value of droop, like 25070, may be ing the rehealer. if the H P valves only were closed rapidly 1 Simple s c h e m e - boiler o n p r e s s u r e
beneficial in reducing transient steam pressure varia- on a full-load rejection, the amount of stored steam ill speed setpoint, which changes the load o n the turbine
tions if the system frequency fluctuates to a marked the reheater and associated pipcwol-k would be sufficient clne the governor speed setpoint is controlled to reduce thc error. This form of slow-acting integral
degree. The droop may be adjustabie within a range to ovcrspeed the machine to destruction. Thel-efolr, ollcrdtor t o load the machine by means of the error correction gives accurate droop characteristics
or alternatively switched from a selection of two or similar rapid response to close the interceptor governilig droop characteristics. Options for droop adjust- or controi to a fined load (infinite droop), if selected.
more values. Droop adjustment, or switching, on-ioad valves is provided. iic often incorporated. T h e master ioad controller may be included as part of
generally implies a ioad change uniess carried out at Most large turbine-generators employ rehealing cil~llmi~sioning purpascs it may also be an ad- the governing systcm or may be provided separately in
the pivot point of the characteiistic or uniess coupled intermediate pressure (IP) stcam to improve th a unit control scheine. Apart from providing accurate
with a simultaneous change in speed setpoint. Many efficiency. Thermal efficiency is reduced if thro I . 'l'l~esewould either prevent thc turbine valves linear droop cllaracteristics, the performance of this
governors incorporate facilities for a 'bumpless' change takes place in the interceptor valves, so these vaives a ,l?ening above a certain proportion of their travel scheme is very similar to the scheme described in the
in this fashion. usually fully open over the normai load range o f tl load measurement, would prevent further valve previous subscction.
Fieure 2.4 is a develovment of Fir 2.3, showing the machine. This operating regime is referred to as HI' I' above a certain load setpoint. Thc main dis-
"
characteristics of additianai overspeed limiting facilities governing and is achieved by applying a fixed bias to Ilulie of the overall scheme is that a ioad rejection
that have t o be built into the design so that the speed the interceptor governing valves, thus giving them 11 Id cause the turbine steam valves t o close rapidly, 1.2.3 Boiler m a s t e r load controller
rise on a ioad rejection can be adequately contained same speed/load characteristics as the H P gove sing all flow through the boiler, possibly with In this scheme, the output of the master load controller
valves but more open by the amount of the fixed om firing rate applied. Although the boiler safety described in the previous case is used t o set the boiler
(typically 50%). In the event of an overspccd, these valv would lift a few secolids later, there is some firing rate. The governor speed setpoint is controlled by
will close, albeit at a greater speed-error than the HI' ~ o o dof thermal damage to superheater tubes. a boiler pressure error signal, so that the turbine valves
iob OilOOP 21- DROOP governor valves. tt~vl~ioe by-pass system (described in Section 11 increase or decrease steam consumption in a sense to
h ltls chapter) is one option which could ameliorate
Another possibie mode of operation (often provider reduce the error. This responds very satisfactorily to load
as a switched option) is to allow the interceptor goverlr changes demanded by the operator as the boiler firing
ing vaives to operate in a throttled condition. Altliougll otllei disadvantage is that any load increase,
rate correction is made first and, subsequently, the rapid
the thermai efficiency is reduced, 'thc spinlling spare iri allplied t o the turbine manually by the opeia-
response of the turbine can easily control any pressure
capability' of the plant is enhanced: the capability o f fluctuations.
the machine to increase load rapidly iii response t ly matched by the boiler. Because the flow
However, rapid changes in frequency, particularly
either a reduction in the power system frequency 0 the pressure will fall to a degree dependent
the increase arising on ioad rejection, still produce
a demand by the operator t o increase load. This may the necessary governor safely response and abrupt
be important in power systems where there are iarge lls, the droop characteristics provided in the
changes in firing which cause large boiler pressure
fluctuations in network frequency, or where there at' overn nor are usually derived by measurement
fluctuations.
insufficient machines with good regulating characte~ position rather than electrical load. This may
istics. This mode of control is referred t o as HP PI i n Incremental droop deviations at any operating
IP governing or sometimes as parallel governing. In th due to the imperfection of valve linearisation
HP governing mode, the reheater pressure is normali uleristics (see Section 1.4 of this chapter).
proportional to the ioad o n the machine, but in the H
1.3 Subsidiary functions
plus IP governing mode, the aim is for a constant re- This section describes additional functions of gov-
heater pressure, at least over the load range of 50- 100%. Turbine m a s t e r load controller w i t h boiler ernors, giving typical characteristics of these features.
This means that at 50% load, instead of the pressure ressure control Not all governors include all these features; in some
MiNiMUM SPEEDER GEAR RANOE AT N O LOAD
FREoUENCY HI in the reheater being say 20 bar, it will be at the t~scrcomethe previous point about non-linear droop cases they may not be essential to the plant being
..-e
R ' C..rii,;.. : I.. :.I-c: L . .. c:3'il"
fuli-load value of 40 bar and the 'spinning spare'
capability will be improved by the additional thermal
llilcleristics, a separate load/frequency controller is
Ill having the features shown in Fig 2.5. Far any
controlled, or they may be carried out in other equip-
ment but operating through the governor. Equipment
C".l:..)F:,,i4.(
.:,s!; .,,a -,,,,, s u e . , :, ,.,:;,s.;..<:
li.. ? ? ' I , . , ,,-I-.,.C,PCD:1.. .i':iaR:
<.C.T.C>$>>
I-,.
storage available through having reheater steam a t the titlg frequency, depending o n the characteristics, for HP rotor stress control during run-up and load-
I . O.O.li.sTli: lR.,..C. . A :
fuli-load pressure. Thus the I P and L P cylinders will be u'ill be a demanded load determined by this ing is a typical example of the latter. It can be
able t o provide their full-load torque almost immedi- teristic which is compared with the measured performed by an external computer modulating the speed
ately, although there may iater be some decay until the " I load in the master load controller. The result- setpoint of the governor or it can be a n intrinsic part
boiler firing rate has picked u p to its full-load value. ?r signal provides the input to the governor of the governor.
Turbine plant sysrelns C

1.3.1 Acceleration f e e d b a c k of \+'liicli wo~iltl ~nosiiiaily c a ~ s ca toibiric tril?. coi-l,oiatcs an invelne Cunctio~rso tiiat all ogstreaiii gob'ci
Acceleratioli feedback is commonly used to provide a iiicoi-oorated so that the colldition likelv to cat i b < r o i 120 mhas, as slrowir on 1:ig 2.7). nor processing lhas an almost linear cffect on the steiiill
secondary stabilising term to inipravc the damping oS tiil) is sensed early and thc turbine load is de demand at one nominal set of steam inout coiidilioni.
the governor and to assist tlie prim? safcty fiinction of to rcdiice the prababiiity of tripping. If a tr I-lowever, if tiie conditions vary, the significant non-
occur, then the ttansicnt effect an thc plant is redii ernor speed reference lioearities \\'ill aive rise to i~nperfections.Closed-loop load
thc governor in preventing overspeed due to a load
rejection. because it occus.s at a lower load. in#speed reference is the prime input by control ouercomes these imperfections by superimpos-
With a disconnection froni the power system, thc Low exhaust oressure unloadina-aear is norarali ilii. t~iibinecan bc conuolleti, either by the ing a trio~mingsignal onto the governor speed reference.
response of a governor without acceleiatioii feedback :,I J... $ 1 . ~,I..,II. 1. 1.1.tIl ..I..:I . I :.t111'1'; !' : I i . I . : I '1. I: I : . ., 11 .,. I...).. A block diagram of the load ioop is shown iii Fig 2.8
would be controlled by the speed error leim as modified I . . I . ! I I . I . ' I :1.11 I . , ' I 1. 1 3 1 1 . '.111,: . ~ p ~ . .)\:I
; ,A!,#.1 .+. arid the characteristic i t produces in Fig 2.9.
by the droop law. If the speed droop is set to 470, the
valves u,ould have fully closed by the time the speed was iscd or unsynchronised. Prior t o synchronisa-
peed reference range will extend from the

,
- -
4 % above nominal. A typical value of the initial accelera-
tion rate is 12% oer second, so it would be at least 0.33 rollable speed (typically 3 % of nominal) up
seconds before the valves had been signalled to the fully- cst spccd at which the turbine-generator
DEMANDED 1 0 A 0
closed state. In addition, inherent delays in tlie hydraulic ])able of synchronisation (104%). Once ERROR SIONAL
system mean that the valves do not achieve the signalled istic is shown in Fig 2.7. The purpose o f unlo I, the speed refercncc will be limited to thc TO INCREASe OR
DECREASE
closure response. Taking a linear acceleration rate o f is to reduce the effects or prohahilit)' o f a trip. SPEED SEXPOINT

12% per second, the time to reach an overspeed of 10% reason for providing a trip is discussed separate I maximum rates of increase or decrease of
VOLTAGE
would be 10/12 = 0.833 seconds. Because of the Section 3.1 of this chapter. T h e degree of unlo ANALOGUE
OF FREOUENCY
expansion of steam entrained between the steam valves FUNCTION GENERATOR
and the turbine, the turbine will continue to accelerate sibility of motoi.ing. The rate of unloading is ge uite rapid fixed rate which is compatible LOAO LOOP i R L o U E N N
CHARACTERISTIC
after the steam valves arc closed. T o contain the consistent usit11 the rate of incrcase in exhaust pr lium conceivable rate at which the turbine
o v e r s x e d within the trill setting of l o % , it is generally However, if the initiating cause o f unloading is ,e increased if warmed through and all
I usere at an optimunl. In this latter case, tile
necessary to incorporate an acceleration tern?.
A govcrnor incorporating acceieration detection can \ r ~ ) u / either
d be ~nanuallyraised by the operator
sense the need to close the steam valves as soon as its
measurement circuits are able to respond. The valves can the load. This is achieved by resetting the govern
be instructed to close a t maximum rate within 30 ms of speed setpoiot which has been independently reduc usually a single fixed rate.
the load rejection and should be fully closed 1W ms later. the tuibine-generatol- comes under control
Figure 2.6 shows a typical response t o a load rejection. to-synchroniser, o r if manual synchronisation
T o ensure that this form o f acceleration feedback only t o veto the operation of the loading gear until performed, another rate-of-change of speed
comes into play during a significant load rejection, a exhaust pressure has reduced to a value such that '$1 apply. This must be compatible with the
threshold is preset into the sensing system below which unlikely t o restrict the initial loading up to full-loa nising unit and is usually designed to give
lain synchronisation.
there is no outout. The acceleration sienal - must also be T h e veto is normally removed by the operator but,
forgotten, the veto will be automaticaily removed wli ~nchronisedand under operator control, the
present for a preset time before it takes effect.
lige is conventionally set to give full travel
u to + 6 % of nominal speed in 2 minutes.
1.3.2 Unloading g e a r lnor speed reference now acts as a load
Unloading gear may take several different forms, depcn- nd, if a 4% droop is applicable, this means
ding o n the plant being controlled. It is usually
complementary t o a protective function, the operation

if a prolonged increase or decrease is

omatic unit controller is generally used to raise


>lo
OVERSPEED TRIP SETTINO LEVEL the governor speed setpoint in preference t o
to^.. In this case a specific rate, usually slower
10 load per second, will apply.

FIG. 2.9 Load loop frequency 'box' characteiiicici


Closed-loop control of turbine electrical load
oo > control o f turbine electrical load is added
overning system to give accurate load droop
s and facilitate the provison of variable- The frequency range over which the load loop is
ngs. The basic governor incorporates a speed operative is limited so that, even when the load loop
m where the trimming signal is derived from droop is set to high or infinite values, the unit responds
e position. Because the steam flow/position t o any large frequency errors in a manner matched
FIG.2.6 Turbine response lo load rejection FIG. 2.7 Turbine exhaust pressure unloading characteristic lip is non-linear, the basic speed governor in- t o the characteristics of the normal 4% droop of the
130
Turbine piant sysretns Governing systems

basic speed governor. By liniiliiig thc load range over then tlic HP stog, 11' govcining and Ii'stog valves t i i i i i l
wliich the load loop is operative, the magnitude of the u~halegroup is closed. Valvcs arc opened in tiic
sudden load clianges on the boiler systern is limited if a reverse sequence and tlicl-c is also tlie cayability hi revcl
lox, speed droop is used. For obvious reasons (Fig 2.91, sing the sequence at any point \i,lIell llie glolill tesl is
spccd and load variations over which variable-droop only partially complete.
is pcimitted a1.e known as the box chal-actel-istics. On a typical wet steam (PWR) torbine, there will b
Consider a sudden fall in network frequency or1 a four H P inlet and six LP inlets so a group cannot b
nuinber of machines operating in parallel with different defined in the above manner.
droops but similar box size. Bccause the load loop is A vital part of the on-load test equipment is the pro
slow-actinp, through the governor speed reference, all sion of some means for the operator to monitor 111
machines initially cantiibute an increase in demanded performance of the valves. This may be done b
load. Then those machines with high or infinite load loop automatic initiation o f a chart recorder, giving a tin1
droops will slowly reduce in load, returning to a value base against which the opening and closing times
at or near theii original load. This allows the other valves ,nay be judged for conformity to the spe NO"

machines with low droop to pick-up load at a rate tion. Another method is to use an XY plotter wi
compatible with their boilers. The advantage of this actual valve position being plotted against the deman
arrangement is that some units can bc designated for ed position. This can be arranged to give a well-define(
rapid load pick-up, whilst those unable lo sustain such characteristic for a correct test, so that an incorrect tcst
a transient can still contribute usefully t o the control of is readily identified. A third method, likely to be
falling frequency. employed in the future, is t o make use of the VDIJs
provided in the control room for data processing. A
similar type of record to that described for the XY plotlcr
1.3.5 Overspeed t e s t i n g may be obtained, using a temporarily enhaoccd scann.
Overspeed testing to prove the actual value of trip ing rate for the valve position signal of tlie valve undet
setpoint of ovcrspccd protection systcms is an essential test.
subsidiarv function of EOVcining .systems.
. The testing is
carried out on an unsynchronised turbine. Initially, the t..i(i. 2.10 A ~ l ~ r n i l i iIUII-"8)
c and lovdi~~g
equip81~ciit
oneiator has to operate a key-locked test switch which 1.3.7 A u t o m a t i c run-up a n d loading s y s t e m s
permits a higher than normal governor speed range Automatic run-up and loading systems are provided f
up to + 13% rather than + 6 % . The normal governor two main reasons:
raise button is used t o increase speed t o the trip set- lilse o f the large number of plant-mounted trans- and load. The method of controlling these is dependellt
points. The full method of testing is described in T o assist the operator in making the complex sequenc providing inputs, careful consideration is given

.
o n tlle type and size of the turbine and the steam condi-
Section 3.5 of this chapter. of checks necessary prior to and during start-up. design stage to provide enough redundancy to tions for which it is designed. Thus large turbines
The abilitv to test the correct functioning.of cach i t fully automatic run-up and loading with high working at high main and reheat temperatures, w h e , ~
T o run-up and subscquently load the turbine in
turbine steam valve is necessary for both on-load opera- ~ilily.Most inputs are either dupiicated by 'master' specified for two-shifting duty, require tlle most
safe and consistent manner. Sophisticated schem
tion and also nrior to run-un. The latter is described as ~ck'transducersat the same measuring point, or sophistication if optimum run-up and loading rates are
can be provided whcrc the rate o f run-up or loadillg
valve exercising, the requirement being to stroke cach functional duplication built into the system to be achieved. A large wet-steam turbine for base load
is faster and less stressful for the machine than a
\,alve open and closed individually, t o test valve freedom of measurements made at entirely different operation requires control of stress in the H P chests and
human operator could reasonably achieve.
o f movement. As far as the operator is concerned this ng points (e.g., separate measurement of inlet rotor, but the L P chests and rotors do oat need any
uses the same controls as on-load testing, with the excep- I IPressure in left-hand and rigbt-hand steam chests), separate control a t all. Direct measurement of stress, by
tion that selecting 'exercise' ensures that the valves can The primary output of a typical system is t o the ba. i f one o f the minor input signals is lost, fully thermocouples measuring the difference between inner
only be opened if the boiler stop valves are closed. speed governor, either to increment the speeder ge lllltic operation may still be possible. The failed and midwall metal temperatures at suitable measuring
or t o the governor in such a way that failure of t llcers are identified t o the operator. points, provides a means ofcontrolling run-up or load
output signal gives a similarly rate-limited change ral minor input signals are lost or one of a changes t o the optimum values. Control is of a ciosed-
1.3.6 On-load t e s t i n g demand. Some outputs of digital state signals provid pair of major signals, automatic control may loop proportional form, acting into the governor as
On-load testing can only be carried out on groups o f interlock or initiation signals t o the governor and aut led such that there is only a fixed safe accelera- shown in Fig 2.10, so that stress is held constant at the
valves in turn. Thus, o n a four-inlet turbine, one group synchroniser, whilst others provide indications t o (if in run-up mode) o r fixed safe loading rate reference value throughout most of the run-up.
o f valves comprises the left-hand front H P governing, operator. The inputs and outputs are shown on One exception to this concerns the critical speed bands
H P stoo.. . I P "eovernine- and I P stoo valves. The on-load 2.10. The inputs to system depend on the degree further signals fail, only manual control may be of the turbine, which are determined by rotor dynamics.
test system includes facilities for checking the operation sophistication, in the most comprehensive case the ble. The turbine governor will provide a limitation Here the strategy is to ensure that there is a large stress
o f all the valve relay inputs. O n H P and I P governing
~ ~
would be as shown. rate-of-change of speed or load, but this will not margin before entering the critical speed band and then
valves the ability to close in response to governor signals The scope of the system described here assumes tha y be safe, particularly if a cold start is in to provide a rapid acceleration through it. Any 'hold'
is checked and also the means of tripping tlle valve in separate operator actions o r sequencing systems bri The operator must then decide whether there signals from the operator (or any other source) are vetoed
response t o the action of the protection system. O n H P all the auxiliary systems necessary for the safe opes ent desk indications t o permit progress, or to whilst within the band.
and 1P stop valves, the normal tripping and resetting tion of the turbine t o a satisfactory state of readin ill a safe condition whilst a repair is effected, or Provision is often made to 'hold' run-up and loading
action from the protection system is checked and also Thus lubricating oil, main and auxiliary CW syste ltt down the turbne. by vibration, eccentricity or differential expansion signals
the facilities provided as back-up for emergency closure. etc., will have previously been brought into servi Itc main requirement o f the automatic run-up and sensed by the separate Turbine Supervisory Equipment
Testing of a group of valves is carried out sequentially, A digital state signal will indicate that each of th 111 system is to limit the thermal stresses within the (TSE). These will also be vetoed within critical speed
starting with the closure o f the H P governing valve, conditions o r prestart interlocks has been satisfied. lc rotor and valve chests during changes of speed bands o r during block loading; outside these bands

133
Governing systems

liniil. l'lic 'bold' wili be released i f the contioliing not effective in tlla stearly state but comes i
l~araillctcrreduces to 80% of the application level, i f crtation transiently \\,lien required. Unloading g
the TSE signal continues to increase above thc 'hold' reduce the steam delnand \+,hen r e q i ~ i ~ e dOtlrci
.
limit, a second Limit is reached at which tlic operator puts, soch as the overspeed test spccd demand or val
is advised to trip the machinc. testing controls, are su,itchcd into service by t h ,
When the turbine reaches syochionoos speed, a num- esafor whcn required. Auto run-up and loading
ber of pre-synchi-ooising checks are ln~ade(e.g., the apply the demands of operator or thc unit colii
Autotnatic Voltage Regulator must be on 'Auto') and system for a change in turbine output to the speeder
then a signal is given to the autosynchronising systcm in the optimum manner. Note that the governor
tllat the turbine is ready and in a safe state to accept be split into two parts - a common processing syst
load. The governor speed demand is then increased or and a number o f individual valve controllers.
decreased automatically by pulses from the autosyn-
chroniser until synchronism is achieved, the circuit-
breaker being automatically closed by the synchroniser
following the operator's command to autosynchronise. ,4 Electronicgoverning
Alternatively, tile synchronisation and circuit-breakei-
Traditionally, the early mechanical and lnecha

I:i(i. 2.1 i Governor overall block diagram

I be made to close the valve by a closing spring ning systems.


eset electrical null bias.
In a wider context than auto run-up and loading 0fSUCCeSS in this must be of such a high order that failu
I t will be seen from the block schematic diagram set o f circuit components, whose sole task is to perform
I) that single faults in a valve channel can cause that function by converting input signals into output
of unloading gear or any governor fault which is causing, terns, using different hardware and different techniqu
ise to close, giving a partial loss of load. A signals whose amplitude (in voltage or current terms) is
Or likely to cause, a load reduction if not rectified. for speed sensing, operating by different routes to th directly proportional to the required transfer function.
ctc loss of load would require a failure in the
Typically an 'unloading gear operated' alarm and a two Series-connected sets of valve gear. Obviously, th
'governor fault'alarm would be provided. If a governor reliability of the speed governor should be as high a
fault developed into a situation where the governor could possible to achieve this and may be defined as th
no longer control the machine, a further alarm 'gover- probability of not exceeding the overspeed trip setpoil les. These are described later in this section. The and the output (or outputs) passed on to following
nor tripped' would be generated concurrently with the However, in any general governing system, the valv modules. This permits a simple approach to fault finding
hility of not achieving a complete loss o f load is
signal to trip the turbine. position output has three failure modes. A valve can clos another important governor characteristic. by monitoring signal levels.
The component parts of governing systems have down, open up or stick in its current position. It e redundancy or monitoring is normally em- A three-channel system can be made to satisfy the
now been discussed fully in functional terms. The only when either of the last two occurs and is followe reliability requirements established for governing systems.
I, when faults occur in the common processing
subsidiary functions described may be provided in total by an event leading to a sudden unloading o f ti f the governor, they u,ill be annunciated to the If a failure occurs in one channel, it causes the output
or in part for any particular application. Irrespective turbine, for example, the opening of the circuit-break
of the method o f implementation, it is necessary to on a turbine driving a generator, that the overspe
understand how the subsidiary functions are connected trip is brought into operation. There is also the p
into the main governor. Figure 2.11 shows the most sibility, in an uncoupled turbine, that a failure w and to disconnect them before they can contribute an
n-line without interfering with operation or
complex scheme, incorporating all the described func- occur through an excessive speed demand. g in any of the previous definitions of re- erroneous output. Because the detection circuits deter-
134
135
Turbine plant systems

speed co~iespondingto llic naminai network fl-cqncncy.


'The deleciol- circuit provides a iinear frcqucocy to
voitagc conversion over a iirnited range only. The rea- dose operator supervisioii of macliioc pai;!lli
so11 for providing a separate narrow range signal is
tiiat, by using such techniques, better iong-term accu- Therefore, as in the case of the narrow i-angc I
racy can be obtained. I-lowever, neither technique will thcsc reqoii-cmeots arc conveniently caiiieil olt
function correctly when there is a substantial deviation lnotorised potentiometer suitably controlieil I DEMANDED
(e.g., > 10%) iionl the reference frequency. In the
tuned circuit, this is because of a loss of iinearity away
from the nuli point t o the extent that gross errors in
operator. More recent practice empioys the
RUN-DOWN
8.81~
REVERSIBLE
COUNTER
- D~GITAL
TO ANALOGUE t-
CONVERTER
SPEED
o-10" OC

the sense of the output will occur at sub-harmonic


frequencies. Thc timing circuit measures the time for vides an input to two signal comparators C i
a number of teeth o n a speed-sensing wheel t o pass whose other input is equivaient to the demand
tile detector and compares this with a fixed accurate If there is no difference between these I
time reference. The number of teeth passing in one demands, neither oscillator is activated and ti,
revolution of the wheel and the number o f teeth taken retains its existing count, giving the define< FIG.2.14 uigital speed setnoin, - block diagram
for measuring purposes are determined to provide a
compromise between accuracy of tneasurement (the
Inore teeth the better) and adequate transient response,
particularly of the derived acceieration signal (the more I, iilc wheel is opposite the pole piece, the ever, a spare probe is often fitted, wliicli can be sub-
measurements per second the better). Tile accuracy with output reaches the terminal speed selected by
which the teeth are cut o n the wheei and the combina-
tion of speed detectol. and trigger circuitry fol. register-
ing the passage of teetll are also considered carefully
in the design.
Some of the latest governors employ a pulse timing desk. Although typically there is a choice of
technique for speed sensing with auto-ranging to deter- up rates, the 'lower' oscillatoi- is normally
mine the optimum number o f teeth which are t o be give a single fast rate-of-speed decrease.
timed. This gives a n adequate range of the speed signal The demanded speed is compared with the mc
over the whole operating regime of the turbine from speed in the speed error amplifier, the gain
approximately barring speed to the overspeed range. is set such that a 10% change in valve po
For turbines where there is a narrow range detector, achieved for about 1% change in turbine spe
a separate wide range speed-sensing circuit must be
provided. Typically, this comprises a diode pump cir- ~g system requires three probes; how- electromagnetic field is intercepted by the toothed wheel,
cuit, giving a linear conversion of frequency to voltage stability margin. The speed error amplifier acts lliri eddy currents arc generated in the material and dcpcn-
over a required range from barring speed up t o the either the stop or governing valve controilers 10 ding o n whether or not a tooth is present, a varying
maximum synchronous speed. Wide range governing energy loss occurs in the strength of the return signal
systems may operate t o control the run-up by means selccted by the operator. Since the turbine-g which is sensed by the demodulator.
of either the governing valves or the H P stop valves. remains unsynchronised during run-up, the A characteristic feature of most electronic governors
Run-up o n the governor valves has the advantage is light and with near normai steam pressures is that they exercise individual control over each steam
that the H P steam chest can be 'warmed through' small proportion of the full valve opening is ne control valve in the turbine in response to an overall
prior t o steam admission t o the turbine, but this to achieve run-up t o speed. Often a steam d steam demand signal. This permits on-load testing of
arrangement requires very sensitive control at small limit is applied during run-up and if this I individual valves and also fault monitoring with the
valve openings in order t o provide a smooth increase exceeded the operator is alerted t o a possible capability to close a valve in the event of a failure.
in speed. Control of the HP stop valves permits the Two types of speed-sensing device are in con1 Particular mention is made here of the characteristics
use of a built-in pilot valve for steam control of o f the valve position loop and its significance in achiev-
the run-up phase. Since this has a lower-gain valve ing the desired control of turbine load.
position/steam flow characteristic, the required sensi- Given constant steam inlet conditions, the power
tivity of the valve position co~ltrolleris less critical. mounted a t the H P end of the machine so that in I output of a turbine is a linear function of steam flow
The typical facilities required by the operator are: passing through the no-load point at a small percentage
of maximum steam flow. This characteristic is known
The ability t o preset the terminal speed. ing of the H P end of the machine and the gavert as the Willans line and is shown in Fig 2.16 (a). In the
would act t o close all the turbine steam valves. conventional condensing turbine used for driving a power
A 'hold' button so that the speed can be held a t the generator, the pressure drop across the turbine is also
current value. The first type o f speed-sensing device is the m
netic pick-up shown in Fig 2.15. The sensing col directly proportional to the steam flow through it.
A 'release' button to allow the run-up to continue. wound round the pole-piece which directs the magn The desired characteristic is therefore that the steam
demand input to the valve position controller should have
The ability t o preselect speed ramp rates to any one a linear relationship with steam flow. However, inherent
of several values (usually five). I !I,, l . l S Magnetic piek-up speed sensing device features of valve design are non-linear so that a valve

138 139
Turbine plant systems Governing systi+~n:.

linearising filnction lhas to be intrutli~cctlioio tllc g o t . A. i\'ilh the anaioguc govciirar, individual valve 11icR1.G. are processed by tlic UCi.. Output c a i n o r a ~ ~ d s
errini lo restore the required iinearity. In ~ ~ a i i i c u i aillc
r, i:~iii)!ii'icrsa c c e ~ tllc
t t1ll.e~tiiglex slpeed channel outpots fsonl the UCL to alter the speed, load or operatint?

i.
moqh
valve arca/steam flow irlatiansl~ipis rion-linear ior v;ai- ti, iiiiil!ogue form and jpiaccss tlicm lo drive 111c s e i v o ~ o ~ o d etake eficcl through the HI.<?, but only iS thcy
lies of pressure ratio (across the valve) leis than l l i u viilvc coils oil each stearn valve. meet thc accelxability criteria stared at base level. This
criticai value. Refer lo Kearlon, gage 628 121 and llie 'Iiir sccond type of governor employing digital forni o f digital governor is shown diagrammaticallp
typical characteristic is sliown in Fig 2.16 (b). Depend. jili~rvssi~ig uscs a completely different configuration. A in Fig 2.17.
ing on the valvc shape, there will also bc a noir-1ioc;ii rrl!!wnlc single-channel, basic speed governor is pro- The BLG haidwareand software are totally standard
SIEA~.I FLOW iclationship between valve lift and valve area, giviii Vlilril lor each steam valvc. At this level, termed the base for all applications whereas, at the UCL, the hardware
WII.I.ANS llNE
the characteristic sllown in Fig 2.16 (c). T o iiiiearis ivcl governor (BLG), there is Ihigh integrity due to the is a standard niinicompulei but the software incor-
these two effects, the steam demand is shaped I> llliplc redundancy and built-in error checks which porates all functions and parameters special to the
linearising circuits t o give a characteristic of the far) liirle closure of the related steam valve in the event application. A particular feature of the design is the
in)
shown in Fig 2.16 (d). Additional versinc effects arisillg valve channel fault. ability of the UCL to provide communications to the
from the lever arrangement driving the valve position A1 tile upper control level (UCL), a single Unit Pro- operator via a multi-character dispiay panel. This permits
pick-off may also be included in the conipensatio~ provides all the other functions required in a the iuteractive prompting of the operator far every mode
LOAD 700% Each individual valve controller has thiee-channcl
in& system. All interfaces t o the operator and of operation and enables him to see the response t o
PRESSURE R A P S~~ P , valve stcam demand signals as input. its function i
,m"a , except the basic signals connected directly to his actions. Additionally, precise details arc given of

1 > CRITjCAI
#-
I
I
I X C A i
t o take a majority vote of these signals to form a s
nal demand, t o provide iinearisation and t o provide
position control of the turbine steam valve, using tile

in the event of loss of accurale valve position control. .;#


1.4.1 Digital p r o c e s s i n g
Two types of digital processing are employed on the late.

precise functions, such as steam valve llneartsatlon %


character~stics,res~dentin the software for accuracy and
ease of settlng-up I
One tvoe . .
uses the ntoicx , modulal redundanl I' I CONTROL
,
configuration very similar to that previously
Fig 2.13. Each sinele channel uses a combined
and memory module whlch is an independent speed 3
I
1
i!liillAT0R'S

'>A'41 '.
PLANT
HIOHWAY

(TRIPLEX) -___
lNTER.
computing element in its own right. The module also FACE
"Mi,
includes all the built-in features to ocrmit its use in the

. .

4ii3
provide interchannel communication for channcl

'1/
harmonisation and fault detection purposes. DUMP
SOiENOiD
As with a n analogue governor, '2 out of 3' majority
voting is carried out at key points in the system. Control
variables are entered bv means of setoolnts whlch can @ 8
BI'LED WHEEL
7
be ramped u p or down by the user. High priority d PROBES

STEAM DEMAND -- LINEARISING setpoints such as the speed and load setpoints are avai
CHARACXERISIIC able to the operator by direct access to the process0
Lower priority setpoints, which alter the control cha MODULE

(dl I
acteristics (e.g., droop variation), are accessed via a serial /xunmrl
communications link to the interface processor. Contro

!
modifiers, such as vacuum unloading, are sent t o th
channels from the interface processor via serial link
The system timing, the synchronisation between channe
--------------------------.
U6LLEYELLlOYERNOR 10 OiHER VAiVE MODULES I
VALVE LIFT 100% and the fault monitorine,. orocess
. are chosen t o suit the

FIG. 2.16 Typical $team now/load/valve characteristics


1lrcd3 Idr adcquate trallilr.rl1 rr,ponse and lu ailou l r r
f FIG. 2.17 Microgoveinor - block diagram
140
liirbinr plant systems Chaplet 2

:illy poveiiioi iaiill alarnr \vl~iclimight occur. I'hc ap- spool is slio\zn ill the ccntsal position \uith llic contrcil
erator may also seiect particular foons of disglay, for ports blanhcd-oll. This is referred lo as lhc 'null poi)-
example, to faciiitalc turbine run-"1,. tioii'. When llie spool moves, one control goit is opencd
'The Bl,G clianriel includes ail tlie iiard\rare and t o the supply port and tlie other opcns lo the drain goil.
signal routcs froin the speed probe sigrral-bus t o the Thc flow rate is proporiional t o ihc spool dcllectioii.
electrohydraolic scivo-valve o f its associated stcam When connected as a position controller, as showii
valve relay. As well as validating data inputs from the diagrammatically, the null position of the spoiil
\ / / DEMAND POSliiON

UCI., the B1.G incorporates extensive self-checking corresnands t o the condition of eauai 'demainded' aiiii
facilities, i n the event of a fault, the steam valve is 'actual' positions. An)' discrepancy with the positioi,
closed by an independent $means through its own measured by the LVDT causes a current to flow, resulting
faiisafe watchdog hardware. in a hydraulic fluid flow t o the power piston until the
required position is achieved.
T o avoid stiction of the valve it is usual practice
t o superimpose a 'dither' current o n the servo-valvc
1.5 G o v e r n o r valve r e l a y s amplifier output. This is a medit~nifrequency (1 kHz)
The output of the electronic speed governor requires low amplitude current which plays no part in the overall
conversion from a current signal to a mechanical force position control, but keeps the servo-valve spool in a
of sufficient power t o actuate the steam valves. It is tile 'live' condition, the effect being t o vibrate it by a negli-
function of the governor relays to perform this duty. gible amplitude at the 'dither' frequency.
The hydraulic relay has no competitor as a force The null is adjusted by altering the spring bias applicil
amplifier for steam valve actuation. it has the capabili- t o the armature. In the event of a loss of the electrical
ty to develop the high power needed for rapid valve signal driving the scrvo-valve, it is essential that the valvr
opening or closing, without a significant deadband or relay and hence the power piston is driven t o a closccl
hysteresis. position, so a 'null bias' is set t o give a small offset in
The usual arrangement for electronic governing is to this direction. The control characteristic of the servo.
employ a single separate relay for eacll stcarn valve, the valve in this condition is shown in Fig 2.19 (a). Also
conversion being carried o u t by a proprietary plotted (in Fig 2.20) is the corresponding valve internal
electrohydraulic servo-valve. There are many different leakage which reaches a peak at the normal controlling
forms of valve relay, of which three are used o n CEGB point of the valve. The servo-valve is likely to be the
turbines with electronic governing. These will be refer- most sensitive item in the hydraulic system owing to the
red to as Types 1, 2 and 3 in the descriptions which small clearances, especially in the nozzles, and the align-
foilow. Types 1 and 2 use the same proprietary servo- ment of the control edges of the spool with the ports
valve which will be described first. The servo-valve used in the valve body. The hydraulic fluid must be kept iii III3IYE ARM
with the Type 3 relay is inciuded in tlie description o r a pure condition with a low contamination level, othei- PORT
the relay. wise the control edges will become eroded and the inter-
Figure 2.18 shows a servo-valve in cross-section, nal leakare will increase substantiallv. If this leakarc
together with a diagrammatic rep~esentation of how persists, it will result in an excessive fluid cotisumption
it is connected in a simple position-loop controlling and a reduction in tlie fluid pressure, eventually resulting
a primary ram. The feedback t o the amplifier in the in the need to shut dawn the turbine and replace all the
governing system is provided by a linear variable worn componelus.
differential transformer (LVDT). The needs for the control of the fluid characteristics
The function of the servo-valve is to provide a n are described in the section on the fluid pumping system.
output flow rate of hydraulic fluid proportional to the However, a t this point, it should be noted that CEGB
input current. The input current, derived by the gover- standard practice is to provide a test rig in the laboratory
nor servo-amplifier is applied to the coils of a force for checking the characteristics of servo-valves removed
motor thereby deflecting the armature and drive arm from the turbine.
mounted in a flexure tube. The high pressure supply is Before going o n to describe the details of the valve
filtered and supplied via orifices to the boost chambers relays following the servo-valves, it is necessary to sel
and at either end OF the spool. The fluid from each out the requirements of the final drive t o the steam valve.
boost chamber is cross-connected via porting to the re- In the event of a failure of the hydraulic system, the
verse ends of the servo-spool. It travels down the centre steam valve must be capable of closing in less than 200
of the spool and returns to low pressure via the drain ms against any force acting to open the valve. The flow
port. The deflection of the drive arm will block one o r of steam through the valve usually generates a n opening
other of the nozzles and create a high pressure in one force over some part of the travel. Figure 2.21 shows FIO. 2.18 Basic servo-loon
boost chamber and a low pressure in the other, thus a typical case where the steam force acts to open thc
creating a force to move the servo-spool until the pres- valve over the last 70% of the valve lift. A substantial
sures are equalised. The spool deflection is thus pro- spring (or even a nest of springs) is provided t o give
portional to the drive arm deflection which is itself the closing force with a large margin over the steam
proportional t o the current. In the diagram, the servo- valve opening force t o overcome frictional effects. The
142
Turbiiie plant systems Governing systciii:;
1.5.1 Governor valve relay and control unit Type 1
Having covc~.edthc rcquircments, tlic Type I syste~rrwill
i-
be examined in detail. This is used on large reheai
o turbine-generators having four steam inlets to both HI'
4 and IP cylinders, each inlet being fitted with series-
i connected elnergency stop and governor valves. Since
ail control for both the run-up and loading phases is
T O ~ FORCE
L CLOSING VALVE carried out by the govcrnor valves, the stop valves must
PR~NGFORCE *STEAM FORCE)
be fully open whenever the turbine is needed for opera-
tion. The simple form of open/closed control required
for the stop valves will be described separately.
WPUI CURRENT
+ Figure 2.22 shows a diagram of the governor valve
reiay and control unit. The input stage, comprising the
servo-valve and actuator piston controlled by the
INPUT CURRENT. i r n ~
electronic system, is identical to Fig 2.18. The heart o f
ia) ~ ~ , ~ data
, b ~ ~ ~ ~ x the unit is the relay plunger, rigidly connected to the
actuator piston and sliding in the relay plunger sleeve.
In the normal position o f the sleeve, as shown it, the
diagram, the relay plunger is moved upwards by the
actuator piston when the steam valve is required to open.
-
This admits power fluid above the relay power piston
,el ~ ~ , ~ t - b ~data
po,n~ to move it do~,nwardsagainst the force of the valve
spring (not shown), and hence open the valve until such
time as the sweep-resolver position signal is in balance
with the valve position demand. This returns the servo-
amplifier output to zero with the actuator piston and
its transducer restored to the null position. Closing is
effected in a similar manner, with the relay plunger being
17xti. 2.21 Typical govertior valve forces moved downwards to allow fluid to be drained out of
the upper power piston chamber.
INPUT CURRFNi 2 mll Tripping is accomplished by the relay plunger sleeve
L ~ N ~ A R I TSYMMETRY
Y (UI ~ o n ~ ~ n u odea
vr
which, in the running condition, is held dowiiwards (in
B HYSTERSIS ENVELOPE the position shown) against Its internal spring by the
in presence of high pressure tripping fluid in chamber F.
PIG. 2.20 lnicrnat ieakage tiow cbaincicrisfics to meet closing demands. T o assist in this, parti-
~NPUTCURRENT ~f a trip occurs, fluid pressure is lost and the
lily where fast opening is required, hydraulic ac- ,,lay ,,lungel- moves upwards due to spring
111111atoi-s
are often provided adjacent to each steam force. F~~any position of the actuator piston, this will
These requirements are best met by a single-acting cause the power piston to be drained.
A secondary means of closing the valve relays o f ~i~~~~ 2.23 shows a diagram of the emergency stop
power piston opened by hydraulic fluid pressure and
llliliiiturbine unit from the unit protection system valve relay ,,,,it, Examining the operation of the relay
closed by the closing spring. Once the steam force and
,t also be provided. This will be described in detail in the tripped condition, this is held on
spring force are known, it is a straightforward design
later section, but from the valve relay point of view, its bottom stop so that power fluid entering chamber
task to calculate the size of power piston required. Again,
a large margin is provided to allow for friction and, B through port A is prevented from gaining access to
- where appropriate, the weight of the valve and linkage. I- &h'en high pressure tripping fluid is applied
(b, Conlinvovr data
The valve closing rate of 200 ms for full stroke (typical h through port C to chamber D,the relay plunger will lift,
superheat unit) is set by the need to control overspeed thereby allowing high pressure power fluid through port
in the event of a load rejection. The capability of opening S F to lift the relay power piston,
FIO. 2.19 ~o.laadflow characteristics
at the same rate is designed into the valve, as it is needed The dump piston acts as a parallel means of ensuring
in some applications to improve the transient stability that the valve is closed if tripping pressure is lost. IR
of power system networks. However, this facility is the normal running condition it will be held against its
figure shows a typical spring force characteristic and not provided on turbines supplied to the CEGB and the top seat by high pressure tripping fluid in chamber E,
the net force closing the valve. Frictional forces are opening of the steam valve is rate-limited to give a time thus the power piston fluid from port H apart
for full stroke of about 5 s. T o achieve fast opening and from a small warming flow,
kept to a minimum by designing the valve so that side
loads on the valve spindles are minimised. To open the closing, the servo stages which feed the power piston he orifice arrangement permits warming flows to the
must be designed with the appropriate size of porting ality, emergency stop valve relays (and sometimes lower end of the dump piston. In the event of a loss
"alve, it is necessary for the valve relay to supply a
to provide the required flow into and out of the power lor valve relays as well) are provided with a dump of tripping pressure, the dump piston will unseat and
force sufficient to overcome the spring force and any
piston. As well as the porting, there must be pipework having generous clearances and operated by the allow fluid to be drained rapidly from the power piston
steam closing force, such as that occurring over the
first 30% of movement shown in Fig 2.21. o f adequate size t o supply the fluid flow from the high liping system so that safety is assured. into chamber H.

144 145
Turbine plant systems Governing systems

SIGNAL FROM ELECTRONIC GOVERNOR i ! l;!,:;:?:~

dump piston has clearances one order higher than Figure 2.24 shows the control arrangements for a
ISOLATING 8 ay plunger and other servo components. The governing valve. Again, the input stage, comprising a
RELAY SHOWN IN VALVE OPENING POSITION FLUSHING
BLOCK 'lity of its seizure in the event of widespread fluid servo-valve and primary ram, is positioned by a servo-
ination is therefore remote. valve amplifier using the LVDT connected to the primary
orifices fitted to the systems of both the gover- ram as feedback. In this case, however, the positioning
and stop valves ensure appropriate rates of valve of the main ram is accomplished by mechanical and

-
DRAIN TRIPPING POWER ACCUMULATOR el in normal operation and prevent excessive rates hydraulic means without a further electronic feedback
7 1
TRIPPING FLUID FI UID IN FLUID IN TEST iilve travel when on-load testing. loop. The primary ram provides the input onto a
c arrangements of trip and test valves shown permit feedback linkage, the other end being connected to
POWER FLUID
oad testing of the valves in all their functioning measure main ram position. A pilot valve is connected
DRAIN FLUID to the linkage so that, with the spool aligned with its
ports, the main ram will be in equilibrium with the
ELECTRICAL CONNECTIONS
primary ram. A dump valve is interposed in the outlet
(2 Governor valve relay a n d control unit Type 2 port o f the pilot valve supplying the main ram. In the
c 2 control units are fitted to similar machines to normal operating condition, if the primary ram lifts, it
PLG.2.22 Governor valve relay and control unit (Type I) c 1 , but in this case run-up is carried out on the H P will lift the pilot valve, allowing fluid to flow at high
alves, with the governor valves partially open. The pressure to open the main ram. This will move
ol units for H P stop and H P and IP governor valves downwards to open until the main ram position
t lerefore similar. The IP stop valves require simple corresponds to the primary ram input and the pilot valve
tr/closed control only. is restored to the null condition.
Governing systems
Turbine plant systeins
arc of a sgiing-loaded type, set lo ope,, at a defincd
io\i,il itgainst its seat against ilic opening spring. IprCsSIIIP.
1: piutcciion fluid presstire is lost, tlie dunljr valve in addition, on sonle machines, there is a need to
VaLvE SPiWDLE FORK END
ti~,~.iii!e~l by its spring and relesses thc fluid supply supply relatively small release valves to release steam in
Iiic niiiin ram to drain, thereby closing the valve rapid- the rehealer system to atmosohere when the governor
'I iii. il11111pvalve iowcr seat is also closed by the spring valves and iiiteicegtor valves close soddenly in an emer-
liit~scuuing off the higii pl-cssure suppiy f r o n ~tbc gency. Allhougil the steam may not be at a sufficiently
111lu1o~ adjacent to the valve reiay. The dump valve high pressure to cause the relief valves to open, any
iolao be operated by an electrical signal to the residual steam trapped in tlie H P cylinder and reheater
' alve in the piotectio~i fluid line, thereby could give rise to overheating of H P blading due to
back-up means of tripping individual valves. churning in the relatively high density steam. The release
., the solenoid valve maintains thc tripping val\,es, located in the connecting steam piping between
to the remainder of the valves, but locally the reheater and the interceptor valves, are signalled to
the high pressure fluid above the dump valve open under the appropriate conditions to prevent this
in, causing the valve to trip. from happening.
'The relcasc valves may be hydraulically or pneu-
matically operated. Where an electronic governor is
Governor valve relay a n d control unit Type 3 fitted, they arc opened by energising a solenoid. Condi-
ys are similar to Type 2 but employ a different tions which signal their opening are:
nd servo-valve, known as a
. The primary ram displacementis directly 0 Loss of tripping pressure.
rniil ta the input current to the servo-valve. The
e High acceleration detected by governor.
I\,c employs a similar principle and configura-
!hat described in Fig 2.18, but feedback of ram Closure of ail interceptor steam valve relays.
$11 is introduced magnetically onto the force motor
llil~actsfrom the armature deflection pl.oduced by
n coils. The primary ram is used to drive the These conditions cover circumstances of machine tripp-
I I I I I I via a feedback linkage and pilot valve as in ing or turbine load rejection without tripping, where
relay, but there is also feedback of main ram churning could occur either during rundown of the
a the servo-valve amplifier by means of an machine after a trip or during the period of interceptor
Itis ensures accurate fine control over the full valve ciosure on load rejection.

3 relay is now superseding the Type 2 relay


it and some retrofit applications, with the
i u that it has reduced dependency on the LVDT 1.6 Hydraulic fluid system
rate without it. Additionaily, Universai use is made o n large turbine-generators of
Ive has generally larger clcaranccs than the hydiaulic fluid at high pressure to provide the large
Iri is less susceptible t o the effects of wear and opening- forces and rauid strokina times. This section
~

deals with the design of the pumping system for supply-


~d 2 relays have seen many thousands of ing fluid at high pressure to the steam valve relays and
on large turbine-generators and have been t o the protection system.
~ : i lto provide a high degree of reliability and The design and construction of tile system is close-
from problems. Nevertheless it is essential that ly related t o the choice of operating fluid and to the
o f valve relay, and indeed all hydraulic use of small-clearance components in the valve relay
11% are treated with care and that maintenance operating systems. System pressure is chosen t o allow
d Out in a clean environment by experienced the use of an economically-sized relay capable of meet-
'I. If plant is shut down o r awaiting commis- ing the required opening forces. For small turbines
1'01.more than three months, then fluid should (<500 MW), system pressures may be 35 bar or less.
led round the system periodically to maintain For larger turbines, system pressures of 70- 150 bar are
vc coating on components and prevent corro- needed.
ns. Components kept in store must also be These high pressures represent a significant fire risk,
r n dirt and corrosion. The manufacturer will as a small leakage can result in a jet of oil being sprayed
CONTROL VALVES MANIFOLD BLOCK lo provide further information to cover specific over a considerable distance. The vroximitv of steam
pipes at high temperatures (typically'565"~0; coal-fired
plant) makes it necessary either t o provide for double
rta. 2.24 Governor valve relay and control unit (Type 2) enclosure of the pipework and components or t o use
heater relief valves a fire-resistant fluid (FRF). All CEGB systems falling
relief valves are supplied on all machines into the latter category use phosphate ester fire-resistant
I over pressurisation of the reheater. These fluids. These systems are completely separate from
Governing systems

i t ! !ilIo\i8any entrained air to be rclcased. Should variable-delivery cal~abililyniakes the use o f a spill-type
li:ial I ~ c allowed to detcrioratc for any reason or prcssu1.e control valve unnecessary. A cross-section of
boiier feed pump Lurbine is associated with the nyain described as tlie needs of the basic component. i lliere he a fault causing excess air lo be entrained a variable-swashplatc pump is shown in Fig 2.28. It will
unit, its control and protection systems are powered by considered. I'liiid returned to the reservoir, the air release be imnicdiateiy apparent that this is a much rnoic
the same supply unit for convenience. Screw-type pumps may be of the subxnersibic k i l l lllay be affected and excess air could be supplied complex device than the screw-pump shown in Fig 2.25.
Phosphate-ester fluids are used because o f their mounted on the reservoir top piatc, or they ma) However, since the flow can be made to exacriv match
superior thermal stability compared with water-based sel~arateiymounted. Axial-piston pumps and screw-ty the system requirements, the reservoir, pipework, coolers
fire-resistant fluids which would be unsuitabie for the pumps require that the pump suction pressure is adeqii~ and system filters can be scaled down accordingly. From
high temperatures norinally found in thevicinity o f steam to provide a lengthy service life. Failure to meei I Fig 2.28 it can be seen that the axiai-pistons are forced
valves. They also have the advantage that their viscosity suction pressure requirements will result in cavitation to reciprocate in their cylinders by rotation of the pump
and lubricating characteristics are similar to lubricating erosion of the pump components and eventual break-il barrel at constant speed and the movement of the slippers
oil, so that conversion o f earlier units running on high of the pump, with the release of numerous metalll against the fixed angle of the swashplate. The piston
pressure oil is possible with some care, subject to the particles. This would necessitate shutdown of the wliol displacement and hence the pump output can be varied
fitting of compatible sealing maleriais. These fluids also turbine-generator to replace the faulty pump and t o llur by tilting the swashpiate. Fixed inlet and outiet ports
have the necessary fire resistance and provide for a long the entire hydraulic system. supply and deliver the hydraulic fluid. The fluid is
service life from the system components. They can be The phenomenon of cavitation results from the cli~ pumped against the system resistance and a pressure
maintained in good condition for an indefinite period acteristics Of air in the fluid. Tlic solubility of controller senses the outlet pressure and modulates the
without the need for replacement. proportional to the fluid pressure, so that air b swashplate to regulate it to the desired value. Some
The fluid system is designed to permit either on-line present in the fluid at low pressure become dissoiv pressure oscillation is produced at a frequency equal to
when driven at constant speed. In these rotation frequency times number o f pistons, but this is
damped out by a local accumulator.

1.6.1 Filtration
lil? control valve and the excess flow is returned Filtration is an essential part of any fluid supply system
c r~servoir.Again, a separate pressure relief valve a n d the standards required are set by the smallest
investigated promptly, otherwise coinponent life will be atmospheric pressure, to colne out of solution in lhc ihr provided as an overall protection. A non-return clearances in the system - usually the servo-valve. The
very seriously affected. suction pipe and form bubbles. At some point within is fitted in the outlet flow of the pump line, so purpose of the filters is to reinovedebris from the system.
In basic form, the fluid supply system comprises a the pump, the pressure increases to the extent that 1 Iwo pumping lines can be coupled together. I t is quite normal for debris to be continuously generated
fiuid reservoir and a pump to deliver high pressure air returns into solution with a n abruptness which cau. lougll only one line is needed for operation, the within the system, some from wear processes by the
fluid. To ensure high availability two pumping lines collapse of the bubble and damage to any metal in 111 Iby line can be brought into operation either man- pumps and other moving components, some introduced
are needed, one being the duty line and the other on vicinity. Although such cavitation is usually avoided I> or automatically by sensing loss of pressure in externally via air entering through the reservoir breather
standby. Pumps are either of the screw-type (for use in good design, the user must be aware that blockage o r in the valve relays. Debris will be in the form of small
systems up to 80 bar) or of the axial piston variable- any suction filters could lead to a similar effect. Also,
delivery type (for use up to 150 bar). Additional system the reservoir is provided to give a definite fluid dwell
- in
uarticles susuended in the fluid and will be irreeular
size, shape and chemical composition. Filters are usual-
further rise in fluid temperature. Phosphate- ly given 'nominal' and 'absoiute' ratings, suggesting
~. that
ds have a high temperature gradient o f visco- n o particles larger than the absolute rating are passed.
1 40°C,the fluid has optimum conditions for tlie In fact this is not the case. Because of lack of uniformi-
mp. At higher temperatures, the viscosity will ty i n the size of passages in filters, a whole spectrum
o f particles will be passed, although the general
characteristics ensure that there is an increasing probabili-
ty that the larger the particle, the more likely it is to
ufes, the fluid starts out as extremely viscous b e 'captured' by the filter.
If a sample of fluid from the filter outlet is ex-
amined, its contamination level is described by the
number o f particles greater than a given size encountered
these reasons, coolers are necessary in all systems in 100 ml of fluid. With a 5 micron absolute filter in
, insome systems where cold-starting is essential, circuit, typical sizes of interest would be 1 micron, 5
ers may also be required. Coolers are o f the cross- microns, 10 microns, 15 microns, 25 microns and 100

-TO SYSTEM
double-pass shell and tube type, using demin- tnicrons. The total number of particies greater than each
o f these sizes would be recorded and if plotted on a
iog/(log)' plot (as shown in Fig 2.29), would give a
nearly linear form. Using these techniques, various con-
/ \ i~timers~on type, fltted either m the reservoir or m a tamination classes can be defined. A number of standards
SUCTION FILTER PUV.P SUCTlMi PUMP OISCHkRGC
PORT PORT -line. A schematic diagram of a typical pumping a r e in existence; the one gaining some international
111 is shown in Fig 2.27. recognition is the American NAS 1638 Standard, based
ems employing axial-piston variable-swashplate o n measurements taken with a n electronic particle de-
have similar arrangements for boost pumps, tector, using a iight-blocking principle. Another standard
Fio. 2.25 Pump suction arrangement for a separalely.moun1ed Pump I' filters, coolers and pressure relief valves, but their in widespread use in the UK is one published by a
151
SCREW PUMP AND M ~ A R
S S E ~ ~ ~ ~
AUXILIARY SCREWS
I
INSERT
I

organisation, Thermal Control Company Ltd Differential pressure drops across such filters are normal-
.hlo~~ England.
, This standard is based on extrac- ly alarmed and provision is made for on-line filter
100 ml sample of fluid from the system, passing replacement. Prompt maintenance in these circumstances
,ugh a filter membrane, and then comparing the enables the fluid cleanliness to be maintained and helps
c under a microscope with a series of reference to ensure trouble-free service from the system
representing different classes. components.
ause of the different measurement techniques and As well as particulate contamination, which is readily
f defining the 'size' of a n irregularly-shaped parti- visible - albeit under a microscope, contamination by
lie standards lay down different acceptability criteria water or chemical means is also possible. The former
ernis of numbers of particles) for systems incor- is likely to cause a n increase in fluid acidity and possible
CONE I
MRiN
orating fine clearance servo-valves. The system user is
i~ilvisedto opt for one of the available techniques and
formation of gels or salts, which cause components to
stick. Chemical contamination can result in severe
SCREW lihc il on a regular basis. Results taken from a normal electrokinetic erosion of fine clearances, especially if a
system then provide a reference point for what is abnor- source of free chlorine ions is introduced to the system.
2.26 Typical sere, pump IIIIII, which therefore requires investigation. For further information on these effects refer to Nelson
In a system incorporating components with clearances and Waterman (31.
01' 2 microns it would be normal practice to fit 0.5 The likely effects on turbine-generator operation,
iniicron nominal filters in the system to give typically if contamination is allowed to persist, would be high
NAS Class 7 or Thermal Controls Class 3 conditions. leakage flows through the hydraulic system - even-
Turbine plan? systems

TIUINCI SI'VASIII3L%T1E CAM P l A i F


\ REAR OF PUMil I

AXIAL PlSXlNS

FRONT

MG. 2.28 Variable swrslipiate pump

tually giving a low system pressure and a unit trip.


Those associated with maintaining and operating such
systems should avoid any possible introduction of
water, especially seawater. Chlorinated solvents should
never be used for cleaning reservoirs, pipework or
components. Nevertheless, some water will be present
in the system due to contact o f the fluid with air in the
reservoir and in the valve relays and drain lines. To
maintain it at a n acceptably low level (<2000 PPM),
a vacuum dehydration unit is normally incorporated in
the FRF pumping system. This usually works on a
separate sub-loop, taking fluid from the reservoir and
then returning the conditioned fluid to the reservoir
(Fig 2.30). The main features o f the pumping unit have now
Fluid is pumped from the main reservoir into the been described. All these features are combined into a
FIG.2.30 Fire.ieristant fluid conditioner
conditioner reservoir, where it is heated to 80°C and single baseplate-mounted unit which is factory assembl-
then passed through a coalescer unit into a vacuum ed and shipped to site as a complete package. Pipework
chamber where the water is drawn off. The processed joints are kept to a minimum and are welded wherever
fluid is then often passed through a fuller's earth possible. All pipework is fabricated in stainless steel
filter which further reduces the water content and also t o avoid long-term problems of corrosion and the
reduces its acidity. A trap filter normally follows the generation Of rust particles. A typical packaged unit
Turbiiie plant systeivs
(:l>;,~,~,tt ;, Steam chests, valves and loop pipes
~ -... .,
lsslioiun ill 1:ig 2.31. 'I'lie sysian also incliides local rangc~iie~~tsfov zicl~ie~si~~g
feccl iio%,c o ~ ~ i r Zu l ~o~;I,,,I,
I ~
Insrriillieiitalio~i and racililies for the ca~lnectioli of tlic ii+,o.Nornrally, wiioii the iliain turbine is on-load,
thc scope of illis cbaptcr, but tllc part i,layfi1 131 l i l t
r(-liioie iiistri~riicrilsanti lhc 1110101. slarte~.unit. I I I ~ C I ~ O C ~ S i l l i . ieci~nd-stageblading of llie 13i'l''l' is snpplied ivitll
boiler iecd p i ~ m pL~>rbiric
(BI7P'T) is to (IrivP # t i C /iliilill
are built inlo thc sgsicm to rliilt dow11 a pumping iioc .,~i.;tii>from the liiain turbinc HP exiraust via bled-steallt
at a speed sncb as to niail~taiiia coiistailt pfri,ii!,
in the ei,eiit o f lob+!pnmg si~ctioilor oullct tcmpeiat~>re, viiicigcncy and governing valves. Either one pair, or two
drop across the feed regulating valvcs wiiicb icilla~itiii.
and alarms of abiiormal conditions arc giveii. ]>:sirsin parallel, of these valves are fitted. Because of
gump. The feed flow may then be controlled lhv.. \i.liiiii
~ .. ... . iioli-availability o r steam froill the nlaiii lol-bioe HP
the feed valve positioi~.This requires a variablc~jic~~il
~xl12iustprior to start-up and when the main turbine is
turbine whose speed or steam valve position dem;giiil in;,)
i~jiriatingat low loads, the first-stage blading o f tlic

'" 'Oiler feed pump turbine


On CEGB 660 M W turbine-generator systems, it is
be set by the feed control svstem.
The normal exhaust route for the BFPT is l o 11,c
IP/LP crossover pipe of the main turbine, altlla~ll:li,,I
I1I:Iyr may be supplied with boiler steam through a sillglc
lviir of live steam emergency and governing valves. 111
i l i r . event of non-availability of the bled-steam supply
low loads it be routed through to the co,,~r,,se,,
nol'mai Practice t o use ail auxiliary back-pressure turbinc i l l hill-load on the main turbine, the live steam valves
autolnatic changeover from one exllausl to the oll,cl
t o drive tile main feed pump. The feed pump is required will supply sufficient steam t o enable full-load to be
being sensed by a load-dependent palalnetel of the ,llilil,
t o nlaintain the boiler drum level during steam raising turbine - usually crossover
prior t o start-up of the main turbine, and also over the 'I'lie nominal maximum power rating of such a boiler
The steam supply to tlie BFPT ma), be derived f l a i i i
full load range of thc main turbine. The precise ar- lrril pump turbine is about I5 M W and the possibility
one or oilier of two sources, or from a mixtulr ,,f
iil a Load rejection leading t o a potential overspeed
ili~lsibe considered. The loss o f load could occur as a
~u*illlof loss af feed pump suction. If this occurred with
Ilir li~rbincspeed and power output close to the fuli-
li)iltl value, a11 entiemely rapid acceleration would result
11111. 10 the low rotor inertia, In the unlikely event that
l l i i llirbine did oveispced to dcstl.uction, the strengtb
$ 8 1 the casing would contain the disaster and protect
~ ~ c i s o ~ mHowever,
cl. it is normal practice t o follow
11i;iin turbine practice and fit the BFPT with a three-
inei electronic governor, coupled with separate over-

''lie turbine governor is a modular arrangement using


~nyof the same elements applied t o the main turbine.
is, speed-sensing and on-load testing facilities will
ir similar in principle. The emergency valves upstream NOMINAL BLED S E A N PRESSURE
AS PERCENTAGE OF MlXlMUM RATE"
I,! lhe governing valves provide protection shutdowns
1'1 llic BFPT in the event of failure of more than one
(b) Died 9,uin,ra imn, reqroncmQ
(.ourriior channel or in the event of a mechanical trip
iozidilion (e.g., loss of lubricating oil) being sensed.
'I hi. valve relay systems use similar servo-valves to FIG. 2.32 Valre and piessule sequencilig diagiains
for ,lie UFP'T
lliori fitted lo the mail1 turbine and the following stages
i!l lhydraulic operation are often similar in principle to
(li,rsc of the main turbine. It has sometimes been passi-
to omit the pilot stage associated with the main until the H P exhaust pressure has risen t o the value
bine valve relays and t o drive the power piston direct at which it can sustain the feed flow demand via the
11 the servo-valve. Referring back t o Fig 2.24, this BFPT.
id be equivalent to considering the relay to comprise These features and others, engineered by techniques
the servo-valve and primary ram. I n all cases, the similar t o those of the main turbine governor, enable
lraulic fluid is supplied from the main turbine system. convenient interfaces to be provided for autotnatic feed
.ive and bled-steam governing valves are controlled control systems and automatic run-up.
~purallel,with an offset being applied t o the live steam
j lvcs so that they only begin t o open when the bled-
inn1 valves are fully open o n a speed loop droop of
>ill 5%. Any additional speed error, requiring further
2 Steam chests. valves and loop pipes
iini supply, progressively opens the live steam valves
il they are also fully open.
I>uring start-up of the main turbine, the steam is
niil,lllied via the live steam valve. A common means of 2.1 Steam chest arrangements and
*asitring this automatically is t o superimpose o n the
am channel a limited maximum opening char-
construction
c as a function of bled-steam pressure, as shown Steam is admitted t o a turbine from the superheater
FIG.2.31 Pice-resistant nuid packaged unit
will keep the bled-steam valves ciosed outlets, via the high pressure steam mains, to the
156
Steam chests, valves and loog (Jipes
Turbine piant systems

emergency stop valvcs and the associated govciriing tllerc ~vouldbe gl.obiems of crcep vatchcting.
valves wliicir arc housed in steam ciiests. In order 'The iaaivcs clasc onlo i-enlovable-plate typ
lo reduce the lliermai stresses and lheilce ihc risk of which can be replaced when worn or damaged.
thermal fatigue, these sleani chests are of simple shapes scats are secured in place either by tnealis of a sc
and are manufactured either from closed-dic alloy steel ring or by screws tllat are locked in piace, and s o m a
forgings welded together, or from alloy steel castings. the seats are additionally prevented from rotating \ui
Similar steam chests containing emergency stop valves radial dowels. A diffuser is generally provided; ti
and interceptor valves are used in the hot reheat pipes either integral with the valve seat or machined as
from the reheater to the intermediate pressure cylinder of the valve chest.
o f the turbine. These steam chests are invariably The mating faces of the valves and their seats are faccll
manufactured from alloy steel castings, which are thinner with Stdlite in order to resist wear, mainly due to erosio
but larger than the I I P steam chests because of the much by steam. Such wear is most likely to occur when 111
lower steam pressure conditions. valve is cracked open: a jet of steam is then propelle
The steam chests are usually mounted alongside the at liigh velocity by the large pressure differential throuplr
turbine: on 660 MW machines they are either o n swing the narrow port opening. The Stellire facing also protects
links or on springs to accommodate movement due to against impact damage when the valves shut normally,
thermal expansion and flexibility of tlie H P steam mains. or during frequent liigh speed test closures. Cushioning
Tlie steam chests on 500 MW machines were keyed to devices in the relay system or slow motion testing can
be used to alleviate this.
The valve spindles are supported and guided by means
freely witli the steam piping. of specially treated alloy steel sleeves in the valve covers,
On modern large machines, the usual practice is to the materials of the spindles and the sleeves being selected
have four steam mains together with four emergency stop both to avoid excessive oxide build-up between 30 000
valves and four governor valves, two on each side of I1 overhauls and to ensure the minimum wear of thr
tlie turbine. On some of the early 660 MW nuclear components when subjected to the forces imposed 011
turbine-generators, however, the two stearn mains on the valve from steam, vibration and the operating gear.
each side join into one large steam chest, so that there Tlie bushes are securely locked in place, the clearancc
are only two steam chests in total. These steam chests. between spindle and bush being suitable for the operating
conditions of the valves. In order to prevent steam
leakage to atmosphere, there is a gland steam leak-off
used for the reheat steanl chests at the 1P cvlinder. sub-atmospheric connection from a chamber between the
On some current 660 MW machines, the stiam chest spindle and the bush to the turbine gland steam system.
arrangement is such that there is one steam chest on each Steam leakage from emergency stop \,alves is also
side o f the machine, which has an emergency stop valve prevented by means of a stellite back seat o n the back
at each end and the two governor valves are co~lnected of the valve head against the lower valve spindle bush.
to the common chamber between the stop valves. A
typical arrangement is shown in Fig 2.33.
Another steam chest arrangement employs the reverse
flow type of governor valve (see Section 2.6 o f this
2.3 Cover seals
chapter), permitting a more compact arrangement of stop
and governor valves. This requires two steam chests each On large modern H P valve chests, it is difficult to
side of the machine, which have sometimes been inter- provide an adequate bolted joint between the valve
chest and its cover. Current practice on these chests
connected before the emergency stop valve.
generally is to utilise pressure-assisted seal joints si-
milar to that shown in Fig 2.34. On reheat steam
chests, bolted flanged joints are used. These joints
usually have gaskets that are either of the Metaflex
2.2 Steam chest materials type backed up by a metal-to-metal joint face, o r they
employ an lnconel ring. All such bolted joints are
As stated in Section 2.1 of this chapter, the chests are
designed not to require retightening for at least 30 000
manufactured from alloy steel. On current 660 MW
machines operating at 565'C, the material is usually hours of operation.
0.5Cr Mo V steel, and on some recent machines operating
at 53e°C,the chest material is 2.25Cr steel. However.
011 larger unlrr operar~ngat 165'C'. it nin) be ncressar) B
to utl11.c highcr-<hrunir. f s r r i t i ~,tech xirh impro\ed 2.4 Steam strainers B
creep resl,tatl;c in order lo avoid clndul) r11i.k :hc,t ualls In order to prevent solid particles of foreign matter from 8
s hi;h wuuld prej~diceuprrational flr.xib~lit).Auctdnitic being carried into the turbine by the incoming steam and
sterlc would proside s gredrct impro\emml in crecp causing damage to the blading, each stop valve is
resistance but experience with these has shown that surrounded by a cylindrical strainer which has many
158
i
stearn
chests, valves and loop PiPC"
Turbine plant systems
. i i w L PIN

"&LYE SPRING

M A ' N E E L T governor
T ~ ~ VBIYCS provide accurate control nl I
steam flow rate entering the turbine, thus controlliii~iI
generator load when the machine is synchroniscd I < ,
grid. The present practice for the control of the st
flow rate during turbine run-up to speed is also I <
the governor valves; however, on earlier 660
machines and also on 500 MW units, run-up is can!
HALF COUPLING
ed by use of the emergency stop valve pilot-valv
conjunction with the governor valves. O n 660
I:,<;.2.34 i ~ r e i s ~ ~ r e ~ i l ~seal i ~ t ~valve c o r c ~jumi
8 1 ~type machines, the interceptor valves can also be used
governing mode, if required, to use the stored en
in the rcheatei to provide a quick response Lo frequ
variations
Small diamctei hoies, ranging frolll 5 - 2 mI11 depending ~h~ diameters valve opening are gei~erally EAM LEAK-OFF *
011 the o~anufacturer. Even particles of this size call culated to give maximum steam velocities o f about
cause serious blading damage, it is tflelcfore esserltial m ~ for
s ,lie valve head designs are such I I ~ Z
that a thorough steam blow o f all P ~ P C U ' O is~ ~carried they are to steam-induced vibration duii~ri!

STEAM CHEST

paEssuaE TAPPING *
As with the stop valves, it is essential that these v
close in an emergency; they are therefore similarly o WER SPINDLE BUSH

25 Stop valves load tested.


slop valves are to cut Figure 2.38 shows the 'mushroom' type o f govern01
TI,^ purposes of the
periods of s,,utdowll and valve which has a profiled head l o give a more lineal
off the supply
flow in a,, flow/lift relationship. A 'guided flow' t),pc of valve head BOTTOM BUSH
to Provide interruption of the
has also been developed in order to control the flow
emergency trip.
downstream of the seat so as to mini~nisenoise and vibra.
In order to ensure that the valves will close in an
emergency, it is a requirement that they are tested on- see Fig 2.39.
load regularly, at least once a month. During such testing
there is a load reduction, which can be minimised by
a Suitable interconnection downstream of the valves. The
On-load testing is carried out in sequence so that only 2.7 Loop pipework
One valve is tested at a time. The steam chests are connected to the turbine through
Single-seated unbalanced plug type valves are normally loop pipes. On present machines these are arranged to
used, with an internal pilot valve that opens first. The be relatively short, in order to reduce the quantity of STEAM CHEST
Pilot valve is small so that it may be opened against main entrained steam between the governing valves and the
s e a m pressure. It also provides initial fine control and turbine when the valves are shut. On earlier (500 MW)
reduces the loads required to operate the valve. Normal- machines, where the chests are firmly anchored to the
[Y, Once the machine has run-up to speed, the governor supporting steelwork or the concrete foundations, the
which have been open, close in. It is then possi- loop pipes are long and flexible in order to allow the
ble t o open the main stop valves as the Pressures turbine and the pipes to expand freely without undue
upstream and downstream of the valve are equalised. forces/moments on the turbine cylinder.
A typical emergency stop valve is shown in Fig 2.35. AII loop pipe joints with the steam chests are welded, % SHOWN OUT OF POSITION
O n some 500 MW units and On some early 660 M W as are all other loop pipe joints, except where dis-
machines, flap valves were used for reheat emergency mantling flanges (see below) are provided. The loop pIC, 2.35 ~ypieaiemergency slop valve
valves, where the steam pressures were moderate and pipes enter the cylinders, preferably radially, at the
Turbine plalit systems
Char,io Steam chests, valves and ioop pipes

STEAM INLET

DOWEL FOR
.--VALVE SEA7

V A L V E STEAM CHEST
BUSH RETAINING-
SLEEVE

I'ia. 2.39 'Guided now' iypc goveruor valve


SPIRAL WOUND GASKET

o f the loop pipes is made, to ensure that there is


no risk of water entering the turbine during start-up.
Where the pipes or the tee-pieces enter the double-
PRESSURE TAPP~NG V A L V E CHEST COYER
shell cylinder, provision is made on the pipe connecting
to the cylinder for a thermal sleeve which secures the
pipe to the outer cylinder. The loov~vine. .vasses
. to the
inner cylinder and the expansion between the pipe and
cylinder is allowed for by a sliding joint on the outside
o f the pipe, using either stacked continuous rings or split
piston rings. A more detailed description of this type
of joint is given in Chapter 1, Section 3.
BOTTOM HAIF COUPLING
SPRING CARRIER

2.8 Crossover pipework


The steam from the intermediate pressure cylinder oasses
to the low pressure cylinders through large diameter
FIG.2.38 'Mushroom'type governor valve
IP/LP crossover pipes, which have to accommodate the
thermal expansion between cylinders by a combination
of various designs o f bellows which allow either bending
o r axial movement. The bellows arrangements either
P and bottom of the cylinders. On many current incorporate hinge links or have tie rods in order to
chines, the'loop pipes from each side combine to form transmit the pressure forces in the pipe, thus protecting
'nlet into each half of the cylinder by means of a the bellows convolutions from the tendency to open out.
CONNECT~NGROD SPRING LOCATING RING
,.piece connection. The loop pipes into the top half Any bellows units at the horizontal ends of the crossover
nder are provided with dismantling flanges for pipes are usually of the balanced type, incorporating tie
ntcnance purposes, used when the cylinder is opened rods. A typical arrangement of this piping which includes
I>. These flanges have a gasket-type joint that has a both types of bellows is shown in Fig 2.40.
no. 2.36 Goverrmr valve tsign life of 30 000 h between replacements. On some designs of 500 MW machine, these pipes
11 is important that adequate provision for drainage are run along the sides or underneath the machine.
Turbine plant systems Turbine protective devices

PRESSURE BALANO
ilkloicc is provided by separate ove!.speed trips. The .oine.
. The turbine is then triotlcd
. . on low iobricating-ail
i l l $ ijiur cannot overspeed when the generator is connected DSCSSIIIF.
~ i i i i i in synchronism with the electrical power syslenl in thc event of a compicte failure of the turbine gover-
iiri\:ork. The turbine is at risk during rurl-up and also ning system, i.e., failure of inlorc than one channel or
wiici, a disconnection occurs ori-load. Since disconiiec- a failure whicii renders the governol. opci-ative, the gover-
PRESSUREBALANCE
tioil can occur as a result of another tritl function, - to send trin-initiating signals lo the protec-
nor is desiened
tion scheme.
Water ingress to the turbine can occur due to tnalfunc-
circuit-breaker and the closure of the steam lion of boiler or feed controls, especially during a change
in load. In this case, wet steam or even slugs of water
could be introduced through the HP steam line. The
degree of hazard and the type of protection required
first close the turbine steam valves. Whcn the depends on the boiler type and steam conditions at the
flow has reduced nearly to the no-load value, the inlet to the turbine. When a drum boiler is used to supply
Itor may be disconnecred from the power system superheated steam, turbine protection may not be
ol-k without risk of overspeed. This is known as a necessary, providing loss of boiler firing is adequately
LPZ CYLINDiO
ry B trip and is particularly important in the detected and alarmed so that the operator can take the
f water-ingress trips or a manual trip follou,ing necessary corrective action. In the case of a once-through
an incident. if the event caused distortion of the boiler supplying superheated steam, it is necessary to trip
I valves and they failed to close, simultaneous the turbine on low steam temperature before saturated
LPI CYLINDER nection of the generator would promptly lead steam conditions reach the turbine. The dangci is that,
if not tripped, severe distortion could occur, causing
sits connection, the unit can bc safety shut down seizure of the turbine steam valves or fracture of the
turbine blading. Once-through boilers supplying dry
saturated steam represent less of a hazard due to chill-
FIG. 2.40 IP/LI' crossover pipework ,y B trips. These include governor failure and ing. However, the sudden ingress of wet stcaln could
ring oil failure as well as overspeed, watcr-ingress result in severe thrust loadings on the turbine and
nd the operator's emergency stop button. blading, so the plant must be designed to accept this or
be protected against it. Water ingress ,nay also occur
Some early 660 MW machines with pannier condensers Excessive temperature differentials.
used both crossover pipes and cross-under pipes. Similar from feedheating plant via hack-flow to the tapping
bellows arrangements were used to accommodate thermal Excessive eccentricity. points on the main turbine. The arrangements to protect
aaainst this are discussed in C h a ~ t e r3 on feedheating
plant.
If the plant is manned by responsible operating staff 011
a continuous basis, the last four items can be monitored
by supervisory equipment having preset alarm levels. Thir
to as Cotegory A trips.
3 Turbine protective devices allows the operator freedom to n~anoeuvrethe operatino 3.2 Protection scheme
conditions to reduce the dangerous condition. If unablr
The trip-initiating devices as described in the previous

.
to do this, the operator must trip the plant manually.
paragraph will be of two types:
3.1 Possible hazards The other dangers have more immediate effects
the plant and are generally detected by special trip g is excessive, the last-stage 1.P turbine blading
Devices where an electrical changeover contact
Abnormal operating conditions, including those where W I I ~ Creleases
~ the protection system hydraulic press omc overheated and damaged. Since the prime
operates.
the turbine and its systems are not working as designed, and thus closes all the steam valves and disconn of poor exhaust-pressure is likely to be loss of
ow, it is usual practice to provide high exhaust Devices capable of direct tripping of the hydraulic
re unloading gear as part of the governing system fluid system.
encountered are: effort to reduce turbine load and avoid tripping.
The result of a trip initiation will be to close the turbine
Overspeeding.
steam valves and trip the generator circuit-breaker,
Lubricating oil failure. having regard to the division into Categories A ond B.
from these devices, which are described in the re1 clow a predetermined value. Note that there is a The tripping system includes redundancy, so that the
failure of any one element in the system does not prevent
tripping, and is also designed to avoid spurious tripping
as far as possible. Figure 2.41 shows schematically the
Governor failure. Overspeed would have serious consequences for main functions of the hydraulic tripping system much
both plant and personnel, therefare the protective simplified. The interfaces with the electrical tripping
Water ingress to blading.
arrangements have been designed to eliminate any system and the stop and governor valve relays are also
Thrust bearing failure. possibility of a dangerous overspeed. shown. The diagram does not show the redundancy
The turbine governing system provides the first lirie associated with the electrical tripping system, which is
Excessive vibration. of defence against overspeed and t h e second line 01' described later in this section.
165
Turbine plant systetris 1-urbine protective devices
CIiapt<:$ 9
-...., ..
iii'i.iqic:cd trig, latcb levcr and t 1 . i ~lpii~iigerare in ihc contact5 ojlciatiog ihc siixi1ial.y relay 01'. Individual
I t i i i i t pedestal of necessity, liowcuc~,ail llic otlicr iinils sets o i contac~si l l tliis iclay theii encvgise llie solenoid
ing the emergency lrip i,alves, lest inter.lock, diio~ovalvcs of each stcao~ijalve relay. these being o f
11sand reset faciiities are impletnented by means Type 2.
piieiary co,npoi~ei~ts mounteil on a largc manifold Circuit I shows a typical CalezolyA tripping function,
, iji. i outside the ti~ihinecasing. Ihigl, LP turbine exhaust pressure, sensed by pressure
s\\~ircliesPS6 and 7. Tliesc are shown in the norn~al
running position; ivlien there is a trip conditioii, PS6
closcs and energiscs flag i-clay AXRI.1. Providing I'S7
3 Electrically-signalled trips also closes, TR3 is energiscd through contacts AXRI.l
ectrical tripping scheme is also shown in outline and AXR1.2. If the 'front' system is being tcsted, the
2.41. Any electrical trip function is signalled test switch will be in the T1 posilian and, instead of a
front and rear trip solenoids via duplicated trip initiation, lamp LPI will illuminate when PS6 and
rcli,!, contact systems. These relays are segregated into PS7 close. Test facilities, interlocked with the test switch,
('ulegory A and Category B trips. Separate contact sets enable atmospheric pressure to be supplied to pressure
r , l l tllc same relays trip the cil.cuit-breakers directly in switches PS6 and PS7, thus comprehensively testing the
1l1r case of the Calegory A trips and via low forward- functioning of all components through to the lamp.
Imwcr relays in the case of Category B. To enable Circuit 4 is very similar, in this case PSI and PS2
IIIP mechanically-signailed trips, e.g., the overspecd provide the Category B low rclay fluid pressure trip
Irii,, to signal opening of the circuit-breakers, loss of shown in Fig 2.41. Auxiliary relay TPR2.I is used t o
nlotection fluid oressure is sensed bv setsof Dressure nrovide other interlocks as well as trips. One contact,
p a\ritches that provide further inputs to initiate Catego,)' ?PKZ.I is connected it1 parallel with other Calegory B
:$,
I? isit~svia the low foiward-power relays. The uressure trip contacts to energise trip relay TR7. In torn, contacts
,.itjitches may also be used to trip the boiler and auxiliary on this relay, which are not shown, initiate ciicuit-breaker
, I I1 (lcvices, e.g., bled-steam non-return vaives, dependent lripping via the low forward-powcr rclay.
INTERLOCK "NIT
t oil the applicatioii. The 'I out of 2' tripping concept is provided by the
FROM F R I
SUPPLY UNll The low forward-power relays use power sensing via duplication in the rcar channel circuit, where complete-
voltage and current transformers to determine when the ly independent sets of transducers initiate tripping.
NOTES
power generated is less than about 1%. This ensures that Because o f the configuration of the turbine hydraulic
i SHOWN INTHE NORMAL RUNNING UNiRiPPEO CONOiTioN Ihe steam valves are very nearly closed and that an tripping system, a trip occurs as soon as any one of the
2 ISOLalNGAND HESET P A C I I i i E S NOT SHOWN
ovcrspeed cannot result when the circuit-breakers are turbine trip solenoids is energised.
opened, even if no further steam valve closure occurs. The examples chosen to illustrate typical Category A
FIG. 2.41 Hydraulic trip anil - simplified block diagraiii The above general principles may be implemented in and B trips have each used two pressure switches in each
iiifferent ways with either 'I out of 2' or '2 out of 3' channel. For other tripping funcctions some other forin
ii:ilundancy. Although the hydiaulic tripping system of redundancy may be appropriate. Thus, in some
previously described is a 'I out of 2' system, it will be au~lications,
.. hinh L P exhaust temperature is used for
The heart of the unit comprises two sets o f emernen- ditional hydraulic units before the subsequent turbine secn that compatibility with a three-channel electrical tripping, the sensing being carried out in each flow of
.!IrlP \ 3 1 \ ~ i,l l 1 Illr l ~ l l 1 1 1 ~ : 1 ~C.i.:. C l \ . l ; ~ i l < ~ l1 3 l t i l . run-up. For clarity, these have not been shown on the system is still possible. Each of the two systems is each exhaust. For a six-exhaust machine, 12 transducers
ill .,I . , ! ~ . r q > e : J t r ~bolt,
p ri~(,t~ntc.I
I:, ihc LIIYIII! ~ ~ i ~ L l . r . i diagram. ]now described in detail. wouid be used, six in each channel combined in three
. h a i ~ .l.lujd .XI !I.&IIprr,>brc L~ ~!LI)I,II:.I to rlw dn,cri::n. - T o exercise the system and ensure that any faults in The redundancy of the 'I out of 2' system is more pairs to provide immunity from spurious tripping.
cy trip valves so that if either is caused to trip, i.e., move the tripping system are identified and rectified without complex than a simple interpretation of this title suggests. Figure 2.43 shows the second method of implemen-
to the left, protection fluid is connected to drain via pipe delay, regular on-load testing is recommended. To test Additional transducers are incorporated in each of the ting the turbine-generator electrical tripping scheme using
A or pipe B and closure of all the turbine steam valves the front emergency trip valve, the interlock unit is two channels so that at least two transducers per channel, a '2 out of 3' majority voting system. Using this techni-
results. Control fluid pressure is maintained to avoid shifted so that the left-hand ends of the trip cylinders or four transducers in total, are employed. Series- que, it is virtually impossible for any single component
excess fluid consumption from the FRF supply unit. are isolated from each other. T h e same operator action connection of the two trip-initiating contacts in each or transducer failure to cause a spurious trip. Likewise,
The emergency trip valves are operated by spring- also blocks port A on the front emergency trip valves. channel permits any single transducer to fail without a single failure will not prevent a trip from occurring.
loaded trip plungers. When in normal operation, the While in this condition, any solenoid, manual or over- causing a turbine trip. However, no single failure of an Auxiliary contacts, not shown in the figure, give the
spring is held compressed by a spigot held in place by speed trip acting on the front trip valve will cause the electrical component will prevent a genuine trip from operator an alarm if there is a failure and inhibits on-
the Y-shaped trip arm and latch. Initiation of the emergency trip valve to move to the tripped position. occurring. Identification of faulty components is picked load testing until the fault is rectified.
overspeed trip, the manual trip or the solenoid trip causes Due to the isolation, protection fluid pressure is not lost up either by supervision circuits or by routine on-load The circuit is very simple, with the main functional
the spring-loaded latch to be released. H i g l ~pressure
protection fluid in the chamber at the left-hand end of
-
and the unit will run undisturbed throuehout the test.
A genuine trlp occurring during the test period will be
lesting of the trip-initiating transducers of the 'front'
and 'rcar' systems in turn. Figure 2.42 shows a simplified
blocks being.triulicated
. or duplicated as necessary. The
transducers are connected in three similar auxiliary tripp-
the emergency trip valve is thus released to drain and initiated by the rear trip valve and will result in the unit trip circuit for one Calegory A trip, one Category B trip ing circuits. In auxiliary tripping circuit 1, PS7 provides
tripping in the normal way. and the operator's emergency pushbuttons. The 'front' a typical Category A tripping function such as high L P
The detailed implementation of the hydraulic tripp- and 'rear' circuits are completely independent being turbine exhaust pressure. It operates auxiliary relay RL7
mid-position, operation of any one overspeed trip will ing system by each turbine manufacturer will vary. GEC powered by two different DC battery supplies. It is through a flag relay. The equivalent auxiliary relays
cause both emergency trip valves to move to the tripped Turbine Generators, mounts the complete unit in the necessary to energise the turbine trip solenoid SOL to in channels 2 and 3 are relays RL8 and RL9. On the
condition. front pedestal, with a short direct connection to the initiate a turbine trip via the emergency trip valve (circuit right-hand side of the diagram there are four circuits
The trip plungers and latches must be reset by ad- overspeed trip units. In the case of NEI Parsons, the 2). As a back-up, circuit 3 shows a duplicate set of each using a set of contacts from relays RL7, RL8
166
Turh~nepldnl systems

TRIP

-- CATEGORY h
TRIPRELAY
TR3

TEST SViTCH
LPI
I
I /

AUXILIARY RELAY

TRiP
CiHCUlTl EMERGENCYSTOP
PUSHBUiiONS

TRlP
CIRCUlla . TO OTHER
CATEGORY 8

r__

CATEGORY B
TRIP RELAYTR7

NO.2.42 Sinlplified trip circuit employing ,I out of 2' redundancy,


168
~ ~ , protective
b i ~ devices
~
Turbine plant svstems
-.-
aiid R1.9 co~~rrecled in a '2 otlt o f 3' vutii~g fasliiol~.
'The l'irsl two sets o1,eralr tltc Sraot and rear. ttrbine lhave simiiar requirclnents for. tlicii , i i ; , ~ i ~ ~ , i i ,
trip solenoids, wbiic the sccond two sets operate trip rates. The overspeed trip is set in tiie ran(,,c O I I
relays TR3 a i d TR4 to give a direct trip of the circuit- speed. This rccognises norlnal govcrrioi ;ictt<,i
breaker. t 1% speed range.
A feature of this system is that on-load testing can
be carried out on each transducer in turn and circuit
operation checked sight through to the operation of the
turbine trip solenoid. Thos, if the front solenoid is arrangement is shown in Fig 2.44. Oiie trii
hydraulically isolated and test switch contacts T F arc
closed, t~.ansducerPS7 can be vented to atmosphere so
that it gives contact closure, energising RL7 and the front
turbine trip solenoid. axis of rotation and, at low speeds, is held
Actual operation of this can be indicated to the a spring. At 109u overspced, tlic out of hi $01
operator via a relay fluid pressure switch monitoring the overcomes the spring force, causing the bolt I
protection fiuid pressure at an appropriate point on the beyond the shaft where it trips the static trip I
front eniergeltcy trip valve. Durine- testinr. -. the rear
~ ~~

turbine trip solenoids provide protection in the event of


a genuine trip. Similar test facilities are provided for most
of the transducers, the test inputs being applied by a
soienoid valve adjacent to each transducer. This enahles
all on-load testing to be cairied out from the trip gear selecting either the 'front' or 'rear' system for
cubicles, with a full set of indications to the tester so thus autotnatically isolating the associated en
that faults can readily be traced and rectified. trip valve. An interlocked movement of the
The Coregory B circuit is vecy similar to that descrih-
ed for Category A . Here the tripping contacts from all
the tripping parameters are connected in parallel. Thus shaft, through porting wliich directs it to tile o\
several similar sets in channel 1 are in parallel with PSI speed bolt under test. This then fiies out and trips
and RLll and they all operate relay RLI, which is one emergency trip valve via the lever and trip plonl
of the auxiliary tripping relays forming the ' 2 out of 3' ~ o l l o w i n grelease of the test pressure, these items
contact sets to operate the turbine trip solenoids and the reset and the second bolt selected for test.
Category B tripping relays TR7 and TR8.

3.5 Mechanically-operated trips


3.4 Overspeed trip Included under this heading are any trips which may
The overspeed trip is the final protectido against catas- be implemented by means of a direct mechanical ai
trophic failure of the turbine following a load rejection, hydraulic action onto the latching trip lever.
causing the unit to become disconnected from the power The low lubricating-oil pressure trip Is sometimes
system. Additionally, an oversoeed mav be caused hv implemented in this manner (Fig 2.45). Lubricating oii
under pressure is supplied to a single-acting spring-loaded
.. -
would cause a rapid acceleration of over 10% speed per
trip cylinder. The oil is supplied via a deadweighl
aCCUmUlat01 common to front and rear channels. This
second. In documented cases where this has occurred, smooths out fluctuations in oil pressure and, in the event rlc. 2.44 Overspeed ~WeInor
the centrifugal Stress limits of the rotating parts have of a sudden loss of oil pressure, will maintain the pressure
been exceeded and a major rupture has taken place with to the trip cylinder for several seconds, thus allowing
components penetrating the casing. Speeds as high as possible recovery by starting of the emergency pumps. the front protection system is isolated. its two ass'.
180% have been recorded.
The manufacturer normally carries out a works
Similarly, a direct high exhaust-pressure trip is often As the condenser pressure rises, a point Is
is counter.balan~ed
ciated exhaust pressure detectors can be tested ln turn
valve adm'.t-
implemented using the same spring-loaded trip cylinder leached where the spring by s ~ o w raising
i~ the pressure by a needie
overspeed proof test at 120%, well below the design limit a furiher pressure increase causes the leak-eff,valve Of the trip
as shown in the upper part of pig 2.45. For the front the ting atmospheric a i r This permits
at which failure could occur. The setpoint of the is lost
tripping System, there are two sets of detectors Labelled to iubricatinF.oil poirIt if desired'
overspeed trip is such that this speed would never be vacuum trip unit, B is moved downwards by
1 and 2. Lubricating oil is supplied to the detectors via
exceeded even at the maximum acceleration rate of the an orifice plate. The downstream pressure is controlled spring form and the pressure in the short length
turbine. Because of the delay time associated with the by a leak-off Valve, actuated by a bellows unit. The top pipe C is lost. If detector 2 also trips. lubricating 01'
drain,
mechanisms, the finite response time of the valve relays half of the bellows Is evacuated and sealed at a reference Supplying the front trip cylinder is connected 3.6 Operator tripping facilities
and the stored energy in the form of steam and water Pressure close to zero mbar absolute. The lower half of thus releasing the trip latch. A similar pair of, exhaust l t is normal practice 10 provide direct
within the turbine, it is logical to split the 20% range the bellows is connected to the condenser. The leak-off p_sun detectors the trip cgInder of the front pedestal'
by a me- means of tripping the turbine
of 'available' overspeed equally between the governor a i d valve is normally fully seated, since the force supplied the rear system, On-load is Originai1y2this was an
safeguard 'Or persOnnel
that when
the overspeed trip. The stop valves (operated by the by spring A the condenser j chanicd inlenoc~on the trip test lever, r 171
'Turbine insrrumentatioil

e Slmfl ~icreniriciiy Thc peak-to-peak radial escursio~r


or lhe rotor reiative to the non-rotating parts is
iricasuied oil each rotor lo oionitol. qualitati\,e cllanges
I ili this chaptcr, need to be controlled and any in the bchavioor of the rotor whicii may indicate
,#ti conditions drawn to the operatol"~attelltion. abnormal or unsafe conditions.
~ i l : requirements
~i for instrumentatioo are dealt
I! tlte appropriate subsection. Specific transducer e Shofl speed A single measurement of sliaft spced is
iit~d icchniques of measurement are described required, independent of the turbine governor, for
SPRING A--_.I..-
l ~ ~ r r F,
l r Chapter 4. The purpose of this section operator ~efel.ence,particularly during turbine run-up.
REFERENCE---_I_~
PRESSURE loscribe, in broad terms, the different categories
e Steom valve positions An analogue ineasurement
~rinn,entation that are supplied and the part they
of the position o f each steam valve is useful to
the opeiatoi- foi- general reference, to check the
capability for carrying more load or for assistance

!icy instrumentation. . in fault finding.


Metal 2emperolure meusurcments These provide a
knowledge of the thermal state o f the turbine during
both transient and steady state operation. Measuring
Allxiliary system instrumentation.
points are located in the walls of the HP and intercep-
LU~R~CAT~NG i~,iidilionmonitoring instrumentation. tor steam valve chests, and in the HP and IP cylinders.
OIL SUPPLY

li~:.l\umentation associated with protection and e Tlirust bearing ,*'ear This measurement ensures that
cc>tiivolequipment. thrust pads wear is maintained within safc design
limits.
a i\i!,tiiimentation to p ~ o v i d cpost-incident records.

All of these parameters are displayed to the operator


either on continuous, direct-reading instruments o r on
Classification of instrumentation a VDU format associated with a computer-based data
processing system. If a VDU display is used, it is se-
lectable for continuous access and scanned at intervals
Supervisory instrumentation of less than 10 s to ensure that the operator is kept
informed of the current value. Certain parameters, such
as steam valve positions and speed, can change substan-
tially in a fraction of a second. It is essential that the
h r t l ~ operation within the defined limits and (b), to operator has available a true value of the present reading,
~ : i v v advance warning of deterioration or change ill the therefore direct reading is always employed.
hiiiin turbine-generator behaviour, which may require Because of their close association with the running
rillicl- maintenance attention or a temporary restriction machine, generally using transducers mounted in a
ORlFiCE PLATE COP)
11) lile operating role. severe environment, highly specialised and tlioroughly
'The parameters measured are: proven equipment is essential. This aspect is described
OlL FROM
LUBOlL in Volume F. The processing equipment is cubicle-
l<otor oxial position In conjunction with cylinder mounted and includes, where necessary, alarm outputs
expansion measurements, this enables the relative SO that the operator's attention can rapidly be drawn
Flo. 2.45 Mechanicaiiy-operated trips (front tiipping system only) axial movement to be measured so that adequate to parameter excursions requiring corrective action.
clearance margins are maintained under all conditions Where computer processing is involved, the whole
of operation. Typically this measurement is provided scheme is subject to careful review to ensure that
on each cylinder of the machine. if the computer fails, the operator still has sufficient
information to continue running at a steady load o r
r Cylinder expansions In addition to its use in deter- to permit safe shutdown.
mining clearance margins between the rotor and
All of the turbine supervisory parameters are used
cylinders, differential measurement systems are pro-
provides a n independent and very direct means of load. to provide post-incident records. Some are also used
vided to monitor the expansion and movement of
shutting down the turbine-generator, should a plant in the control equipment for turbine run-up.
cylinders relative to each other and their support struc-
attendant observe local conditions which are hazardous tures. Measurements are provided on each cylinder
t o men or the machine. For the same reason a n
of the machine.
electrically-signalled pushbutton trip is provided near 4 Turbine instrumentation 4.1.2 Efficiency instrumentation
the generator-end of the machine. A large modern turbine-generator comprises a num- a Bearing pedestal vibrations These are measured at These are instruments required to determine o r infer
A remote emergency stop pushbutton is also pro- ber of cylinders coupled together to form a rotating each bearing to continuously monitor the dynamic the operating efficiency of the plant, both for short
vided in the control room, where the operator has shaft line, Chapter 1 has described this arrangement behaviour of the machine. term monitoring and the detection of long term trends.
Turbins plarlt systems r i ~ r h i n efoundations

I'hc teo~l~eratures and pressures of steam and water in llritish Standard 752. Sincc many ol thc transdiicers I Instrumentation associated with protection Acconimodate the thermal capansiorr of tllc stsuctilre
are o~casuredlo confirm tliat the plant coinponcnts are have to be ixecalibsaled, UK practice requires that l l i t *md control e q u i p m e n t conditions.
and stalic parts of tiic platit under all ollerating
aperatiiig efficiently and in the intended manner. For illant is built with piovisioii for fitting the instrumei,ts
exampic, measiirclnellt of the steam and water condi- 'I i i i , comprises imtrumenlatioii used in conjunction
when a test is required, Thus thc manufacturer sup"lies
tions at the inlet and outlet of a feedwater heater enables
~ ~

ivilli ;i control loop, either locally or for tlic )nail1 plant Raise thc plan1 above the ~ u r b i n chouse floor to
pockets for insertion of tliermocouplcs and pressule
an operator lo confirm its satisfactory operation. ,.iiiituoI systems. The turbine governing system (de- provide access for electrical connections and pipe-
tapping points up to and including the primary isolatinji it.tibed in Section I of this chapter) is an exaniplc o f
Unsatisiactory operation is unlikely to prejudice the valve. Where possible, stcam and coniensate flaws ale work, Bottom connection of the main stcam pipe-
continued running o f the planl but does affect its ef- l l b ~latter, whilst any local control loops not covered work is particularly desirable to avoid dismantling
measured by differential pressure devices and so tlic
ficiency. This category of instrumentation therefore Iby Auxiliary Systems form part of tlie former. These pipcwork during maintenance and to prevent the
provision made on the plant as-built can again be confil~.
Ioriil controls are used to onerate plant prior to a unit
draws attention to maintenance activities which are
efficiency-related.
..~ .
ed to fixed orifices with suitable tannine ooints. The mail,
condensate flow measurement is one o f the most critical.
aluii-ul~or following maintenance, where operator action
pipework draining into tlie turbine. The height o f
the turbine abovc the basement floor level is partly
Alarms are derived from some parameters in this Srolrl the control room is not necessary. Also, some plant determined by thc need to accomnlodate the con-
Provision is generally made to insert the calibrated orificc
category, for example, steam temperatures upstream of tcijiiires controls which may not be immediately con- denser and condenser neck, when an underslung
plates in sections of condelisate pipework parallel to the
the H P stop valves. These alarms are less critical than rlcotcd with the minute-by-minute operation of the unit. condenser is used, and partly by consideration o f
main path. When tests are to be performed, the maiii
those derived froin supervisory instrumentation and I'iirtlier local controls are sometimes needed to permit condensate drainage iequiretnents. The bled-steam
path is isolated and ail the flow passes through the orifice
i t detailed fault analysis to be carried out following
thcrcfore the alarm processing may be carried out plates. Provision is also made for the connection of ;i piping should drain away from the turbine and the
exclusively in the data processing computer. Steam iili:l~tificationof a problem in the central control room. drains from L P heaters must be returned to the
transmission-type dynamometer to messure the power
temperatures upstream of the turbine H P stop valves are supplied by the boiler feed pump turbine (if fitted). condenser. For this to be achieved with gravity
used to provide data for the long term history. In some plants, a more limited range o f parameters drainage requires a certain minimum height differ-
Some o f the parameters in the efficiency insfrwnoi- 8.1.6 Instrumentation t o provide post-Incident ence between turbine and condenser hotwell.
is measured on a permanent basis to provide a routine
ration category are used for the heat rate test instl-umeri- tocords For inain turbine-generator plant, these require-
on-line efficiency monitoring scheme, usually combined
tation identified in the condirion nioniioring category. with boiler plant. Such schemes inevitably provide 'ilic detectors required to provide these records are ments have been satisfied by eithcr reinforced concrete
The rcquil.ement for accurate, calibrated instruti~entsfar less-accurate illformation than would be obtained from ileiived from other categories of instrumentation, mainly or steel support structures, which are described in
a heat rate test often pl.ecludes the use of the same plant acceptance tests, using recently calibrated trans- liilin the supervisory instrumentation. These records more detail in later sections.
transducers as tliose used for efficiency instrumentation. ducers. The value of on-line monitoring is that it enables )xovide critical plant data for desisnated periods be- It is also necasary to monitor the movement of
trends to be identified and appropriate maintenance work l u r c and after a n incident to enable the cause to be Uhe foundations througliout the life of the station.
scheduled. Where alternative plant operating strategies ii~vestigated. Thc recording is initiated by a unit or Settlement of the whole foundation in service is
4.1.3 Auxiliary s y s t e m instrumentation pI23nt trip (for example, the trip of a feed pump), or not very serious, provided that it is not large enough
are possible, for e x a m ~ l c ,selection of a standbv feed
These instruments confirm the satisfactory operation cliicctly by the operator on demand. These records are to affect electrical and steam connections, but dif-
pump instead o f a fauliy duty pump, then the opirator
of plant auxiliary systems. The description of thesc can take measures to improve the efficiency of the plant l>r~duced by data processing computers and, since con- ferential movement between bearing supports must
systems forms the content of this section and more linoous scanning of all the input parameters is necessary, be avoided if the alignment of the plant is to be
on-line. The scheme is implemented by a series of
systems are described in Chapters 3 to 6. All these some compromises have to be made in the scanning maintained within reasonable limits. Multi-limb mano-
algorithms processed by a dedicated computing system
systems require instrumentation for local operation or spccd. Thus, assuming a minimum scanning interval metric level measuiing systems are therefore installed
and is capable of displaying trends in overall performance
fault finding. Wherever their operation is essential of 3 s and depending on their relative positions in the on tlie bearing supports to monitor relative level
given by changes in heat rate, as well as the performance
to the main turbine-generator unit, facilities for re- of individual components. scnoning cycle, a parameter might respond up to 3 s chanees. A schematic diagram . of such a system is
"
mote alarms and indications in the control room are liefare or 3 s after the recording shows the trip to have shown in Fig 2.46.
necessary. operated. In specifying the requirements of the data 'Slave' units are fitted to each bearing support, with
Machine level insfrumenrarion
logging system, the turbine plant designer considers these a master reference unit at one point and the whole
This comprises equipment for automatically measuring limitations to provide a compromise which is both cost system is filled with water. A uniform level is thus
4.1.4 Condition monitoring instrumentation and recordinc- c h a n-~ e sin the relative levels of the turbine-
~ ~ ~ ~~~~~
cffcctive and valuable to operators. established by the water surface and movement of
This defined list o f instruments is used on a periodic generator bearing pedestals. Primarily used for fault
basis to confirm the absence of long term trends which the bearing support relative to the fixed water level
diagnosis, this equipment is sometimes sunplied .. built-in can be detected by suitable sensors fitted on each
might lead to unplanned outages and to define acti- by the turbine manufacturer. A n alternative approach
vities for future outages. T o this extent, some of the slave unit. Sensors using micrometer adjustment of
is to provide facings and connection points on the
a n electrical contact probe, and floats with LVDT
instrumentation in this category is of a diagnostic pedestals so that portable equipment can be used to make 6 Turbine foundations
nature. position measurement have been used in the past,
the checks during maintenance outages. 'The turbine-generator
. foundations consist of the support but both systems have disadvantages. Present day
The defined subcategories are: structure, the sub-foundation and the subsoil; they systems use a n ultrasonic sensor fitted in the base
Heat rate test intrumentation Shafl vibration insfrumenfafion perform the following functions: of each slave unit which measures the position of
The scope of the measuring points required for this the water surface by sound reflection technique.
Machine level instrumentation. Support the static load of the turbine-generator and
is more complex than the provision made for turbine Accuracy of measurement is typically k0.05 mm, with
associated pipe loads, and transmit these forces to
Shaft vibration instrumentation supervisory purposes. At each bearing, two transducers a minimum measurement range of +2.5 mm about
the subsoil.
measure vibration in the same plane but displaced at nominal level.
The purpose and scope of each of these subcategories 90' to each other. This facilitates the recording of shaft e Restrain the plant from undue movement due to Cooling water is circulated around jackets on each
is described below. vibration signatures on run-down and also orbit plots dynamic forces resulting from the load torque, slave unit to eliminate errors due to manometer water
may he taken on-load so that a complete picture of unbalance forces, electrical faults, etc., by trans- temperature variations. Air pressure variations are
changes in shaft dynamics can be formulated by an expert mitting and absorbing the associated energy. nullified by connecting the air spaces of each slave
Hear rare fesr instrumentofion
o r a n expert computing system. Such a n analysis can unit together in an 'air balance box' (not shown in
This comprises all the equipment necessary to conduct lead to improvements in the "rediction of maintenance Maintain the alignment of the plant under all op- figure). The balance box is then vented to atmos-
a thermal performance test on the plant as described routlnes
I erating conditions. phere at a single point.
Turbine plant systems Turbine fout?dations

5.2 Concrete foundations


SlhVL UNiiS 'The traditional foundatiori used in the CEGB lor
turbine-geneiator units up to 500 M W was reinforced
concrete. For small units, the support stiucture was a
rigid monolithic block on a substantial sub-foundatioo.
with openings to accommodate plant arid pipework.
This type of foundation was invariably high-tuiled and
moveinent at the bearings was restricted at the expense
of high bearing forces. The dynamic energy associated
with machine vibration was transmitted through the
LXCITAllON UNIT
support structure and sub-foundation and absorbed
by these structures and the subsoil.
As unit size increased, the problems of designing a
high-tuned foundation with adequate access for pipes,
conimctions and ancillary plant became more severe, and
the larger units now in service with concrete support
structures generally use a low-tuned design. Examples
; ,,, 2.47 ~ e l ~ i e i e n ~ a t iofo na li1rbii,c-8eneiaiorarid in of low-tuned rcinforccd concrete supDort structures are
iouiidalion urcd for analysis shown in Figs 2.48 and 2.49. The structure is generally
DISPLAY
I,, ,,,i,clicc, the com~icieturbine and supper1 sIrueiure arc
l,,l~,r\cilicdby a full three-dimessional assembly of nlasres. in the form of a series of portal frames, linked with
~,vl,,,,, illid ~prinp,~.'fhc efieci of the subsoil is inof rigtliii- horizontal beams at the top to form the platform on
c,,,,I i,, ciicun?itanccs and can tllen be i88iored. which the turbine and generator are mounted. The struc-
ture is designed to limit the differential settlement o f
1'10 2.46 Sclleiiinlic diagram of a iurbillc mnnomclric level iridicnlloii riid ineusuri#~p,
eqtiip8llent bearing supports to about 0.5 mm, although for bearings
close together differential movement of half this value
is more appropriate.
When designing a concrete foundation, margins on
T o allow any relationship between bearing support Analysis during the design process and before con calculated natural frequency have to be allowed because
level changes and foundation structure temperatures struction to establish design values of natural frequei of the wide range of values of Young's modulus for
t o be studied, temperature sensors are buried in the cy (and harmoriics o f that frequency) well remove concrete which can be met in practice. Concrete also
foundations during construction or attached during from runni~lgfxequency and its harmonics. shrinks during curing and this can continue for a long
erection. time after construction. Most of the shrinkaae occurs
Incorporation within the support structure of a means during the first six months, so turbine-generator erection
for adjusting the natural frequency after erection and on the support structure is normally programmed to
commissioning to remove o r control unwantcd occur nine months after construction.. Further shiitlka~e
~ .
5.1 Tuning resonances and forced vibrations. continues to a lesser extent for some time and minor
The foundations need to combine rigidity, to avoid changes to machine alignment may be necessary for up
excessive movement, and flexibility, to prevent excessive Analysis methods used at the design stage model to four gears. Concrete also creeps under stress and this
forces being Present at the bearings. Dangerous re- plant and its foundations mathematically as a series continues throughout the life of the support structure.
sonances at all speeds must be avoided and the natural o f masses, beams and springs as shown in ~i~ 2.47. In fact creep is one of the mechanisms by which the
frequencies o f the foundation as a whole must not be Because of the complexity of the model and the num- stresses resulting from shrinkage are relieved. Special
close to running speed. ber Of possible modes and frequencies of vibration, concrete mixes have been developed for minimum
Two methods of avoiding resonant conditions and computer programs are used to assess the forces and shrinkage to alleviate this problem but these are some-
unacceptable vibrations are possible: deflections in the structure in response to a variety of times difficult to pour and compact.
static, transient and oscillatory forces. The design studies ation, it becomes necessary to tune the structure Thermal expansion of concrete is significant and,
Overtuned Or high-tuned, the natural frequency of . TWO basic methods are available for this:
also consider the response of the foundation to the together with its poor thermal conductivity, can give rise
vibration Of lhe foundation structure is above the to alignment changes between hot and cold conditions
running speed of the machine and away from any effects of shaft misalignment, out.of.balancc forces, and
load and electrical fault torques, hdding massto columns or panels at selected locations due to differential expansion. Thermal shielding of parts
harmonics of this speed. This is referred to as a
The subsoil elasticity is important at some sites but to reduce vibration amplitude. of the concrete support structure is therefore employed
sfiff foundation.
the effects vary with subsoil type and foundation type. to reduce these effects and one UK power station has
Undertuned or low-tuned, the natural frequency of These can be ignored. * ~ d d i n g(or removing) structural strength to (from) been fitted with cooling pipes embedded in the concrete
vibration o f all or some of the foundation structure Rigidity is achieved by establishing the mass of thc lilt foundation structure to change its stiffness and to control temperatures directly.
is below the operating speed of the machine, hi^ is Support Structureand sub-foundation at about ten times move the natural frequency away from a plant ex-
sometimes referred to as a /lexible foundation. the mass of the rotating shafts. With flexible support citation frequency.
structures, the foundation mass can sometimes be re- . .~ ~~

duced as the elasticity o f support reduces the dynamic tion might be expected to be greater than with other
In designing turbine-generator foundations it is therefore forces transmitted to the sub-foundation and subsoil. )lot11 methods have been used, separately 01 in corn- types of support structure. This has not been the case
necessary to consider 'tuning' the foundations and there in calculating the loads on the structure, account \,ination, on occasions, although post-commissioning in practice, and post-construction tuning of reinforced
are two aspects to this: concrete support structures is rarely necessary. If tun-
must be taken o f pipework loads (both hot and cold) tuning is generally not necessary.
Turbine fou~idations

A steci sui)port SII.LICIIII.C is liiore flexible liiiiri the


ctjnivalenl rcinforccd concrete structure and is alw,ays
low-tuncd. Tiie flexibility o f t h c support colu~rinsisolates
the dynamic forces produced by the rotating shafts from
the sub-foundation to some degree and may ailow a
reduction in sub-foundation mass. This isolation also
Ireips thc causes of unusual vibration bchaviour of
the plant to be determined as the effects are more lo-
calised than with stiffer support structures. Any attacli-
ments necessary 011 the ~upp01.tcolumns arc strictly
controiled to ensure that the structure characteristics
and integrity are maintained.
With a steel foundation, the responsibility for de-
signing and supplying the support structure usualiy rests
with the turbine-generator contractor, rather than with
the civil engineering contractor, l'his is generally regarded
as a n advantage, as tile same contractor is responsible
both for the plant whicil generates the dynamic forces
and the structure which must respond to, and partially
absorb them. Shrinkage is not a problem with a steel
structure and working support structure temperatures are
below those liable to give creep in the steel. The use of
good-quality weldabie steel is very important to accom-
modate the static and dynamic loads, and the steel inust
have good impact properties. Steel to BS4360 grade C
is typical of the types used. Thorough non-destructive
testing (NDT) is used on a random check basis for all
!) 3 Steel foundat~ons weids, with particular emphasis o n critical and site welds,
nG. 2.48 'i'lie use of a welded steel support structure for the to ensure freedom from defects.
support rtrueture for a SW MW turbine-generator sitti underslung condenser
This is a low-luned design. turbine-generator has several advantages: The thermal expansion coefficient of steel is less
than that of concrete and, together with the good
B A Steel support structure is lighter than one of thermal conductivity, reduces problems of differential
reinforced concrete, reducing the static load on the thermal expansion upsetting shaft alignment in the
sub-Foundation. vertical direction. In the axiai and transverse direc-
r Steel is a uniform material with accurately known and tions, the thermal expansion characteristics of the
dependable properties, giving greater accuracy in support structure arc almost the same as those of the
analysis. static parts o f the plant which it supports: this ex-
pansion is readily accommodated by flexing of the
e Offsite fabrication is possible, independent o f the support columns. Attachment of bearing pedestais to
weather, and site erection time is reduced. A site the support structure is quite simple for there is no
erection programme time of three montlls would be need to use grouted-in fixing plates, as on a concrete
typical for this type of support structure. structure.
The design analysis includes for the effects o f ro-
Plant erection can be done immediately the support tating out-of-balance loads and considers the fatigue
structure is complete, as it is not necessary t o wait conditions at welded joints to ensure the long term
for curing or shrinkage. This has obvious advantages integrity of the structure.
for the construction programme. The accuracy of analysis possible with a steel struc-
ture gives confidence in the performance of the struc-
A steel support structure gives improved access for
ture in service and post-commissioning problems have
pipework and generator connections.
only rarely been experienced. If problems do occur, the
structure can be 'tuned' more easily than a reinforced
Steel support structures are fabricated as a 'table concrete structure by three methods:
top' of cellular construction supported from the sub-
foundation o n box construction columns. The 'table Adding steel struts t o the structure.
F'O. 2.49 Concrete suPPOrfltiueture for a 500 MW turbine-generator with side-mounted condensers inreaial top' is designed to provide support
. to the bearing Adding weight external t o the columns.
I
~

with the LP cylinders pedestals, turbine cylinders, generator and exciter.


The HP eld of the slructure is similar to that of Fig 2.48, but the structure is lower and is not required to provide LP
cylinder support. The mass of concrete used is about 60% that of the structure in Fig 2.48. This is also Examples of steel support structures are shown in r Adding weight inside the sections of a box construc-
a low-tuned design. Figs 2.50 and 2.51. tion column.
179
Turbine plant systems Chapti') 2 Lubrication systems
...-

TURBiNE
NO. 2 i . P
LOCATlON

No 1 L.P. TURBINE

H P TURBINE
LOCATION '\
,

F~o.2.51 Steel support structurefor a t o 1.P


a 5W MW t ~ r b i n e - ~ ~ ~ ~ ~ihree ~ and pannier condensers
H.P. STEAM CHEST The condenser support columnr are not shown.
SUPPORT
BEAMSUPPORT
COLUMNS

ilic load only, or even to dispense with a mass The thickness of the sub-foundation should not be
FIG.2.50 Steel suppoil structure for a 660 M W ioibinc-generator with two LI' cyliiideis and aii underslung condcnsci
licrele sub-foundation and install individual foun- less than one tenth of its length. The need for piling is
lions for each support column. The precise design, determined by the nature of the subsoil at a particular
I course, depends on subsoil conditions at the par- site. Discontinuity between the sub-foundation, the
Springs mounted in rows on structural concrete walih basement floor of the station and the foundations of
Differential settlement can also be corrected by jacking-
up each of the affected columns and inserting packing or in groups at the top of support columns have bee11 'Tlle spring support, concrete deck and support other plant is attempted to prevent transmission of vibra-
used and viscous dampers are sometimes employed i n Itrmns are no cheaper than other support structure tions to other plant and the building structure.
between the column base and the sub-foundation.
conjunction with the springs. Natural frequencies of x s : the economic advantagc claimed for spring
about 3 Hz for movement in the vertical direction arc andations lies in the possible reduction in mass of the
claimed for these systems. A hydraulic locking system I1.foundation. Cost reductions of 25% are claimed in
5.4 Spring foundations is used to pre-load the springs to a set deflection for vourable circumstances. 6 Lubrication systems
As the natural frequency of a low-tuned foundation construction and plant erection purposes. The sanie
support structure decreases, the isolation between the locking system can be used to allow the insertion of
support structure and the sub-foundation increases, packers, above a spring or spring-group, to correct for 6.1 Lubrication requirements and typical
and the sub-foundation is called upon to absorb less foundation column settlement: this also allows sprin 6 Sub-foundation arrangements
of the energy resulting from dynamic and transient to be changed after erection for others having a different ?art from any special designs associated with spring Forced lubrication of the turbine bearings is essential
forces generated in the shaft line and static sections springrate, if it is necessary to change the characteristics undations, the sub-foundation must be a massive in order to prevent damage due to wear or excessive
of the plant. of any part of the spring support system. 11 rigid concrete base designed to transmit and dis-
Such low natural frequencies are accompanied b white metal bearing temperature. Before starting to
The closest practical approach to complete dynamic the static and dynamic loads of the support
the possibility of greater plant deflection under tra turn the main rotating elements, it is necessary to lift
isolation results from mounting the turbine-generator e and plant above it to the subsoil. Rigidity is
sient conditions. Under generator load rejection or the rotors clear of the bearing surface: the jacking oil
plant on springs and this approach has been used ry to limit differential settlement of the bases system used to achieve this is described later in Section
successfully overseas. In the UK, condensers of the short-circuit conditions, torsional rocking of the plan1 support columns to a value acceptable to the
can impose vertical movements of 1-1.5 mm at the
6.9 of this chapter.
underslung type have been spring-mounted, as have 111.line-generator, and the sub-foundation mass is es-
The purposes of the forced lubrication of the main
smaller items of plant, but spring mounting has not yet springs, so pipe and electrical connections must be blished from design analysis to limit plant vibration.
bearings are:
been used for main turbine-generators. designed to accommodate this. he sub-foundation of a modern turbine-generator
Established overseas practice uses springs of the Because the sub-foundation is well isolated from CEGB station, the mass is typically (a) T o provide a hydrodynamic oil wedge between
helical-coil or plate type supporting a reinforced con- dynamic loads, it is possible to reduce the mass of the ombined mass of the plant and struc- the bearing surface and the journal bearing of
crete deck on which the turbine-generator is mounted. sub-foundation towards that necessary to support the sufficient thickness so that the particles of debris
Turbine plant systems Chapti:i 2

normally jpiese~it in tile oil will 1101 damage the ex~~eriencc has sliowr~that lin~itingtllc oii tempeiariili
bearing surfaces. leaving a bearing to 71CC, gives satisCac1ol.y heiliiiljr
~ ~

ilf~.
(b) To provide a fiow of cooling fiuid sufficient to On older units. the lubricating oii system !i;ri
maintain the bearing white metal temperature be- integrated with tile turbine control and protectio~, oil
low ilOeC, dissipating the heat at the bearing system, with the lubricating oil being supplied throiiirl~
due to: a pressure control valve. A typical arrangement is shoiu18
@ Thermal conduction. on Fig 2.52.
On modern units, the control system (see Sectioii 1.6
0 Friction between tlie journal, oil film and white of this chapter) normally requires a fire-resistant fliiiil
metal. (FRF) system with a pressure between 70 and 175 bar.
Turbulelice with the oil itself. The lubricating oil system on these units (Fig 2.53)
is provided using a directly-driven centrifugal punip
delivering oil at around I1 bar. The oil from the pump
The majority of the oil fiow is needed to cool the passes through an oil turbine which drops the oil
bearing. Because o f the problems of accurately mca- pressure to around 3 bar; the oil turbine drives a
suring the white metal temperature at the point of booster pump which supplies oil from the main oil
maximum hydrodynamic pressure in the oil wedge, tank to the centrifugal oil pump suction. This arraotc.

I'ii;. 2.53 1.ubricaliiip oil syarczn lor modern turbine-generator platit

Inrbll allows the oii tank iocation to be optimised with seal-oil system (see Chapter 6 , Section 5) is provided to
fci:ard to oil drainage under gravity, whilst meeting the prevent hydrogen transfer to the main oil system; on
centrifugal pump suction-head requirements. T o protect these units, the supply from tlie main lubricating oil
lhc System against overpressurisation, a connection is system is used as a back-up.
Inken from the bearing oil supply line to a relief valve On modern units, the lubricating oil system supplies:
lounted on the oil tank.
' he directly-driven main oil pump provides a n Each journal bearing on the turbine/generator/exciter
cmeiy secure source o f lubricating oil under normal rotating line.
ing conditions. For normal start-up and shutdown,
11 AC auxiliary oil pump provides the lubricating oil The main thrust/surge bearing.
rpply. For emergency shutdown, when the AC supplies
arc not available or the AC pump fails to start when The generator hydrogen seals, either as the sole supply

AUXillARY
O i l PUMP
required, a DC auxiliary oil .

ullit can be brought


~
oumo . is .vrovided. Auto-
malic sequefitial starting of these pumps is arranged
llpon falling lubricating oil pressure to ensure that the
- to a standstill without damaee
~~~~ ~

-- tn
~

--
. o r as a back-up system.

The bearings on the turbine.driven boiler


where this plant is provided,
pump,

flit bearings, and to ensure that the bearings d o not


overheat due to conducted heat. Oil filters and strainers, oil cooler, tank vents and
Lubricating oil is also used for the generator hydrogen oil purifier connections are provided o n the lubricat-
hcals and the supply is taken from the 70-170 bar oil ing oil system. Details of these features are described
FIG. 2.52 Lubricating and relay oil system for older turbine.generatar plant piessure manifold. On some modern units, a separate below.
Lubrication systems

station cleall and dirty oil tanka, and also to the ,ii in pig 2.54.
l~urificaliotl system, with the pipework and JOURNAL BEARING

necessary to permit the transfer of oil:


THRUST BEARING
0 From the station clean-oil tank to the unit oil tank.* 6.2 oil pumps O I L DISCHARGE

e From the station used-oii tank to the oil ta,,k,* Details of the various oil pumps used arc dcic,ii
JOURNAL BEARING
in the paragraphs that foilow.
To drain the whole of the oii inventory from the
LOCKlNG PLATE
unit oil system into the unit oil tank, and from the
unit oil tank into the station used-oil tank. 6.2.1 Main lubricating oil p u m p

JOURNAL BEARING. -VENTILATION HOLE


TO EXPANSION
in the unit tank or the oil in the station ~ l e a n - ~ i l COUPLING
tank. The pump is not self-priming and requires a su
oil pressure of around 3 - 4 bar. COUPLlNG FLANGE
Through a portable unit oil purifier to process TURB~NE E L E C T R ~ C A L TO DRWE SHAFT
IIIRNING GEAR END
the 0ii in either the unit tank o r the station c ~ e a ~ . ~ i l
tank. 6.2.2 Turbine-driven oil b o a s t e r p u m p
In order to ensure the security o f lubricating oii siii,.
ply, oil from the main oil pump discharge is passvil
* These transfers are made using the oil purification through a n oil turbine. ~h~ turbine is mou,,,cil IOOITOM HALF
PUMP SHAFT
unit. on top o f the oil tank and drives a submerged ocn. NECK R l N C

BOTTOM HALF
WEAR RiNClS
JOURNAL BEARING
OIL OUTLET

-.~.~ TEST PRESSURE


GAUGE CONNECTiON
OIL LNLET FLANGE

--._01L DISCHARGE
FLANGE

FIG. 2.55 Main iubricating oil pump

-
.--. LUBIliUiiNrOii
rn"PASS
- U#*CriU"lO"I
- URA,WS system as the A C pump, or the pipework which feeds
vEMr 6.2.3 AC a n d DC motor-driven auxiliary oil oil directly to the bearings at around 1.5 har. Each pump
M NoM.~~un.vALv. has a capacity o f around 70-120 litres/s.
The AC and DC auxiliary oil pumps which supply oil
to bearings under start-up and normal shutdown, or
under emergency shutdown respectively, are centri- 6.2.4 Jacking-oil P u m p s a n d priming P u m p s
fugal pumps with a submerged suction. They are also The jacking oil pumps deliver oil at around 300 bar
suspended from the tank top and their arrangement to the individual bearings. The pumps used are motor-
FIG. 2.54 Lubricating oil transfer and conditioning system is very similar to Fig 2.56, hut with an AC or DC driven positive displacement and either multi-plunger
Turbine plant systems

P V M P BODY

SEALING RiNG

TURBINE C I \ S $ N G

DISCHARGE PIPE---
TURBINE TOP

JOURNAL BEARIN0

TAXE-OFF

PEDESTAL

LOW PRESSURE
MEASUREMENT
OUTLET PLUG
TAKE-OFF

PlSTON SPRING
PVMP COVER W i L E T Poll7

YAPOUR BLEED------- OUTLET V I \ I V L


ASSEMBLY

1:lc. 2.57 Mulfi.piunger jacking oil pump


DISCHARGE BEND
P U M P BOD"

l i ~ cdischarge pressure is the same as for the other Pump duty Type Drive
jacking oil pumps. Purifier/oil conditioner Gear Electric motor
- oil
6.2.5 Other pumps Purifier/oil conditioner Electric motor
Various other pumps are used on the lubricating oil - water
PIG. 2.56 Turbinc-driven o i l booster pump system and oil transfer systems as follows:

pumps Or
Oil tank water/oil Centrifugal Electric motor 6.3 Oil tanks
gear Pumps, see Figs 2.57 and lubricating oil manifold and the gear pumps have vapour extraction On modern units, the main oil tank has a capacity of
2.58. around 75 m3 for the lubricating oil system oil inven-
a motor-driven positive displacement two-shaft gear
The arrangement utilises either one gear pump per Oil tank hydrogen/ Centrifugal Electric motor tory, with a normal working level volume of 50 m3:
pump.
bearing or one motor/pump unit for either one or oil vapour extraction a typical arrangement is shown on Fig 2.59. The tank
On some designs the turning gear is provided with
two bearings. The pumps require a positive suction a separate jacking oil pump. hi^ pump is a motor. Clean and used Gear or Electric motor, is designed with the oil return and the pump suction
pressure. The multi-Plunger Pumps are fed from the driven, positive displacement, two.shaft gear pump; separated by baffle plates, to assist in de-aeration and
oil transfer diaphragm or air
186
I 1urbtne piatit systems Chdlill i Lubrication systems
--

A C MOiORORlVLN A C MOIORDR8YEN
LU6HICATlNCIOIL PUMP

-
'
OILFLOW
' MPOIII1

8001 SEAL
O-RING ' 1
0 4 L SEAL

kt6 2 58 Gear i)pe jackmg o#l/primlng pump

settlement and also to prevent the formation of stag- valves, two vapour extraction pumps are also mounted.
nant pockets of oil. The quantity of oil in the tank One to remove water and oil vapour from the tank and
and the internal design of the tank provide around the other to extract hydrogen and oil vapour from thc
seven minutes oil transit time from return to suction, detraining tank.
with the normal time limits being between five to
ten minutes.
The trend on modern systems is to provide a self-
contained section of the overall oil tank for the hy- 6.4 Piping
F ~ G2.59
. Main oil lank - general ariangenleni
drogen seal-oil system, the objective being to eliminate Pressure oil piping for both jacking ail systems and
the risk of hydrogen gas passing into the main lubri- lubricating oil systems on modern units is subject to
cating oil system. Where a self-contained system is special design precautions against oil leakage and fire
used, a back-up supply of oil to the hydrogen seals risk. The oil piping is sized so that the oil velocity is 6.5 Oil coolers dissipation requirements are around 2 MW per cooler.
is provided. Where the lubricating oil system provides between 1-5 m/s. Oil piping from the pump discharge 'The function of the oil coolers is to ensure that the oil On some designs, the oil coolers have the main
the hydrogen gas-side seal-oil, special precautions are is contained within an enclnsure/duct and the pipe- fcmperature leaving the bearings is below the permitted lubricating oil filters integral with the cooler shell. A
taken to ensure that any entrained hydrogen is released runs between pipe joints are as long as is possible. limit by removing the heat absorbed by the oil within typical example of a n oil cooler, which also shows the
and vented to atmosphere. A separate seal-oil loop All pipe joints are o f Class I welded construction. (lie pumps and the bearings. Redundant coolers are integral oil filters, is shown on Fig 2.60.
detraining chamber is used to ensure that all hydrogen At the exit from the ducted area, the pressure oil pipe provided in order to enable repairs and tube cleaning Arrangements are made for automatic by-pass of
is removed before the oil is mixed with the main oil is contained within a protective pipe, so that any oil lo be carried out whilst the unit is on-load. Normally, the oil coolers upon excessive pressure drop across the
system. leakage would be contained and would be detected at three 50% duty coolers are provided, but two 100% units coolers. Automatic control of the oil outlet temperature
Coarse-mesh strainers are provided on all oil returns 'tell-tale' drains. Pipe material up to the filters is mild nre sometimes used. is provided.
t o the tank to assist de-aeration and to catch any large steel; on some designs, the pipe-runs after the filters 'The oil coolers are mounted vertically with a two-pass
foreign material. Problems have arisen in the past with are in stainless steel to minimise the risk of corrosion water flow through the tubes and a single-pass oil flow
corrosion at the air/oil interface in the main oil tank products damaging the bearings. Automatic air venting through a series of baffles, to ensure even cooling. The
due to the presence of water/water vapour in the oil. of the pipework system from its highest points to the cooler shells are of mild steel and modern practice 6.6 Oil strainers and filters
The main oil tank is now fabricated either in stainless oil tank is provided where the air is not vented through is for the tubes to be made of titanium. The tube The oil strainers are coarse wire-mesh basket type
steel or mild steel with a special phenolic paint protec- the bearings. Oil filters are also provided with air vents nest has a fixed and a floating tubeplate to contain assemblies which are designed to catch large foreign
tion against corrosion. to the oil tank; these ensure that any air accumulation, lllermal expansion. The coolers are provided with re- material from the oil drains into the main oil tank.
O n the top of the oil tank, in addition to the sus- either in service o r as a result of servicing or inspection, movable end plates so that cleaning can be carried thus ensuring that material reaching the centrifugal
pended oil pumps and the bearing oil pressure relief is vented to the oil tank. nut without dismantling the water pipes. The heat pump suction will not cause pump damage. They can
188
Tiirhine plant systems Chapii'i 1 Lubiication systeins
.

C "llii, i .,: ,.,


__
-.
iioss i O i i
iiiFRNO I'OI:KFI VIIRBOXAIII
LlDSS FOR R T i i h S E CONNECIIONS
OiSlANCE
IIIFRMOMFIER -.
C W <>"TIE? -- COOiFRUODYhiii
RFLFASE CONNSCilONS
VIAISRBOX COV

IWICT,O"llli .-

TOI'TUBFPLAT
Oil. OUTLET-

BOSS FOR DlSiANCE


THERMOMFTEA

BAFFLE PLATES

i l L l E i l CHAMBER
C O O l l H BODY ACCESSCOVERS i

-IILIERCIIAMBFR
OIL ,Nlil---..
FLIERCHAtIIIEH AIR
RELEASE CONNFCIION

04l'ltREN1IAI PRESSURL
GAUGE CONNLCTiONS

FlOWDiAGRAM

FIG. 2.60 Oil cooler with iniegral f i l m

be lifted out of the tank to remove and inspect any of one compartment whilst the unit is on-load.
debris collected. Facilities are provided to enable a filter to bc
Two main systems of filtration of the lubricating primed and pressurised after service, before ~ u t .
oil are used: tillg a filter cimparllnent back into service. The filtej
norinally provides a capacity of around 106 litres/s
(a) Curlridge fillers fitted into the oil cooler casing under a pressure drop of 0.3 bar with both com-
which are designed to filter 13 litres/s of hot oil partments in service. Normal filter cleaning is
Fit. 2.61 Plate lyne oil filter
per cartridge, to a nominal particle size of 10 carried out automatically when a rising pressure
microns. Each cooler can have up to four dispos- differential reaches 0.45 bar across the filter. Ro-
able cartridges giving a total filtration capacity of tation of each plate filter assembly then occurs
around 52 litres/s, with two coolers required for against a scraper bar; the debris off each filter falls 'The oil for these duties is taken from the filtered oil housing and the cold lubricating oil, which results in
into a sump at the bottom of the filter irousing and supply to the bearings and passed through a duplex condensate being dispersed through the oil. The oil
100% duty.
is cleaned out on a regular basis. A typical arrange- plate-type filter system similar to that described above also collects wear particles, oxides, soluble acids and
(b) Duplex filters fitted after the oil coolers. These ment of a plate-type filter is shown on Fig 2.61. and shown o n Fig 2.61. This additional filter has only sludge. These need to be removed from the oil to
four plate filter assemblies in each compartment and ensure its long life and efficient lubrication. There
can be either multiple disposable filters, with facilities
lhas only manual filter cleaning. The filter provides are two main systems used o n continuous by-pass duty
for on-load replacement, or a duplex plate filter Where a plate-type filter is used in the main oil supply
which can be cleaned on-load. The plate-type filter a capacity of 16 litres/s under a pressure drop of whilst the unit is in operation, and an oil regeneration
t o the bearings, additional filtration is required for 0.2 bar with'both compartments in service. system is also used in the station oil system. The on.line
consists of two compartments, each with five filter the oil supply to: systems are described in the sections which follow.
assemblies. Each assembly consists of a series of
plates and spacers, which give the required degree
of filtration of 15 micron. Each compartment
normally passes 50% of the oil: facilities exist to
pass LOO% flow through one compartment in order
. The main thrust and surge bearings.
The shaft turning gear, jacking oil pump, gearing
and clutch,
6.7 Oil purifiers and coalescers
The main source of contamination of lubricating oil
is the leakage of steam from the rotor gland seals.
6.7.1 Centrifugal separation systems
This type of system has been used for many years but
requires careful adjustment for maximum efficiency,
as well as considerable maintenance. A schematic ar-
to allow replacement, maintenance or inspection The main oil pump, thrust bearing and cooling sprays. This steam condenses upon contact with the bearing rangement of the system is shown on Fig 2.62.
190
Tuibii?c plaiit systems
Lubiicatioii systems
~=:+=:z:-~
-1 1 Oil is taken froin tile inain oil tank at a rate of 17010
of the oil i~lventoiyper hour. Thc oil initially passes
lliir)ilgi~ a scrics arrangement of fine-nlesli sloping
screens. Thc water coalesces on the screens in water
droplets which iilil down to the bottom of each screen
and are led to drain. The oil then passcs through a series
o f polyolefinic bags which filter out the particulate
matter. Finally, the ail is pumped through a 5 micron
pressure filter and delivered back into the main oil tank.
The oil passes through the purifier at its operating
temperature and because it is not heated the risk of
bacterial/fungal growth may be greater (see Section
6.8 of this chapter).
Provision is made for the regeneration of used oil
within the station oil transfer system. Oil for regen-
eration is taken from the unit oil tank or the station
dirty-oil tank at around 1.1 m3 per hour and processed
in the plant shown schematically on Fig 2.65.
The oil is healed to 54.4"C and is then sprayed into
a chamber with a vacuum maintained at 913 mbar
below atmospheric. Under tiiese conditions the water
boils o f f , is removed by the vacuum pump and con-
densed. The dry oil is then pumped out of the vacuum
chamber and through a filter. The filter comprises a
pack of nylon-backed filter papers clamped between
perforated steel plates, and filters the oil to 10 microns.
From the filter, the oil is taken into the clean oil tank
prior to being pumped back into the unit oil tank after
it has been cleaned.

6.8 Oils and greases

6.8.1 Oils
The oils used in steam turbines must provide ciean,
stable and efficient iubrication whilst exposed to the
severe operational conditions. They are also required
to be efficient at absorbing the heat generated in the
bearing. These conditions require the use of oils in-
corporating additives, particularly for the inhibition
of corrosion and oxidation.
The basic turbine lubricating oils are to British
Standard 489: 1983: CEGB Standard 207001 covers
lubricants for use by the CEGB and Table 2.1 is a n
extract which covers turbine lubricating oils. The spe-
cific grade used on the modern 3000 r/min tandem
turbine-generator is TO-32.
Additives are now used to inhibit oxidation, corro-
sion and foaming. An oxidation inhibitor is added to
stabilise the oil against oxidation and to passivate the
metals which act catalytically to increase oxidation. These
inhibitors maintain a low neutralisation value (acidity)
of an oil over many years of service. A rust inhibitor
in the oil protects carbon-steel surfaces from rusting
when in contact with water or moist air entrained within
192 5 nc 2 63 011 purifier bowl operat~on the oil circulating system.
f
193
Turbiiie plant systems Lublication systems

PEHTORATEO UEAEHKIING
PLATES IN VACUUM DRUM

FIG. 2.64 Static oil purifier

Detergeni additives arc used to inhibit high [em- 6.8.2 Greases


peralure oxidation, the formation of low temperature ~ l t l the ~ ~ hof many manufactu
~ ~products
sludge and the deposition of contaminants. utiliscd, there are three basic greases used for tul-
Viscosity index improvers reduce the fall in viscosity
with temperature rise. Pour-poilit dqressents have
the opposite effect and reduce the temperature at which Silicone-based grease containing tnolybdellii
the oil becomes immobile. disulphide. This has a working range of - 50°C 1
Anli-foaming agenis are added to suppress the ten-
dency of aerated oil to foam and assist in the release
of air from the oil.
The acidity (total) of new oils is normally within the
. 300°C.
Mineral oil with this grease
slightly lower temperature limit of 260°C.
range 0.02 to 0.10 mg of KOH/g, or slightly higher in Lithium-based grease. These greases are used foi 81
additive-conditioned new oil. In service, oils tend to wide range of lubricating duties including ball a,
oxidise to organic acids and this is accompanied by an roller bearings. The requirements for the testing
increase in total acidity. The acidity levcl of the oil this type of grease are laid down in CEGB Stand;irl
is therefore a useful guide to the condition of the oil No. 207001.
and the need for purification or conditioning.
Water ingress into the turbine oil is the most com- The first two greases listed are for the lubricatiox> ol
mon problem with oil systems. The Presence of excess high temperature sliding surfaces, such as turbirl
water in oil, particularly if stationary for any length palms and steam valve pivots.
of time, may result in bacterial and fungal contamina-
tion of the oil systems. This can reveal itself as a
yellow/black stringy grease-like material. This growth
can take place in sediment in oil tanks or other plant 6.9 Jacking oil systems
items. It can be particularly difficult to clear from

.
When a turbine-generator shaft is rotating very slowiy, TANK ORAIN
tube nests. The basic precautions are: the normal lubricating oil supply cannot ensure that
ensure that the water of the oil in a hydrodynamic oil wedge will be maintained. Also
-I OIRIY OIL (WITH WATER1
operation is kept low by regular use of [he oil puri. additional lubrication measures are required to preven

. fier; the water content should not exceed 0.05qo. bearing damage and to minimise breakaway torqil "..- . DiRiY OIL (WATER FRtEl
when starting a turbine-generator from standstill. In b
To remove sludge deposits from the oil system circumstances the jacking oil system provides h . CLEANOIL
plant-sumps on a regular basis. pressure oil to the base of the bearing and floats

If bacteriai/fungal growth becomes a problem, the is capable of sustaining an adequate bearing oil wed
--- VACUUM

addition of the correct biocide to the oil will kill the (above 200 r/min), the jacking oil system and the no
bacterial/fungal growth. ma1 lubricating oil system are run in parallel. FIG.2.65 Oil regeneration plant - flow diagram

194

Вам также может понравиться