Академический Документы
Профессиональный Документы
Культура Документы
Modern
Power r -
-I
I - -
Practice
Third Edition incorporating Modem Power System Practice
TURBINES,
ASSOCIATED PLANT
Pergamon Press
MODERN
POWER STATION PRACTICE
Third Edition
(in 12 volumesl
Authors
Chapters 1 8 2 G. F. Hunt. BSciEngt, CEng, MlEE
Series Production
Managing Editor P. M. Reynolds
PERGAMON PRESS
OXFORD . NEWYORK . SEOUL . TOKYO
U.K. Peigalnon Press pic., iieadtngion Hill iiali.
Oxford OX3 OBW. Erlgiaild
USA Pergamon Press, nc., (395, Saw Mill River iUoad.1
Elmsford. New York 10523, U S A ,
March 1990
Preface
'The increase in generating capacity of the Central Electricity Generating Board (CEGB)
during the last thirty years has invoived the introduction of new 500 M W and 660 MW
turbine-generator plant for a variety of operational duties from base load to that of flexible
two-shift operation. Thcse plants have been installed in nuclear, coai and oil fired power
stations.
The early operational experience of the 500 MW units provided important data for the
design developn~ent of the 660 MW turbine-generator plant. Thcsc latter machines
benefited from the high quality approach to the design of major components by UK
manufacturers using their developed analysis techniques in the areas of aerodynamics and
stress analysis. The soundness of this approach has been demonstrated by the improved
reliability and performancc of the iatcr plants.
The Third Edition of Modern Power Station Practice gives a detailed account of ex-
perience obtained in the development, design, manufacture, operation and testing of
large turbine-generators in the last twenty years. The practice of testing and evaluatioli of
modern plant has proceeded as before; the advance in analytical and computational
techniques has however meant that the application of this experience to future design and
operation of large turbine-generator plant is of greater benefit than ever before.
One of the major tasks of the Turbine-generator Plant Branch in the CEGB was to secure
the development of 'hrbine-generators a n d their associated Plants to meet the needs o f the
CEGB with due regard to economics, performance and reliability. As Head of the Branch
for some years I have felt privileged t o have been asked to edit Volume C.
T h e authors of this volume have wide experience of the plant engineering field and all
are authorities in their particular field of Technology. I would like to record my sincere
thanks to these colleagues who have produced Volume C . They have undertaken the task
with an enthusiasn~ derived from the knowledge that this work will be of the greatest
assistance to engineers in this field of technology woildwide.
P. HAMHL.INC
Advisory Edilor - Volume C
Contents of All Volumes
I I
John was an engineer, an inteliectual and a respected author
In his own right. It was this rare combination of talents that
he brought to Modern Power Station Practice as consuiting l$~iroductlon 4 E C D ~ D ~ ~of the
C S steam cycle
Editor of seven volumes and, in so doing, bequeathed a 1 l u r b i o e types 4.1 choice of exhaust oressure
legacy from which practising and future enaineerq
" - -- ,nriii
..,,, 1.1 Direction of flow 4.1.1 Thermodynamic dpiimisation
4.12 General economic aotimisation of nisnt
I continue to benefir for many years. I 1.2 Cylinder end exhaust arrangements
1.3 Speed of rotation 4.1.3 Economic optimisatibn of exhaust pressure, condenser
end CW svrtem
2 Ffficiency and output
2 1 Output limitations
21.1 Steam valve pressure drop
21.2 Swsliowing capacity 4.2.3 Feedwater be-aeration
2.2 Moving biades 42.4 LOW pressure feedwater heaters
22.1 impuise-type turbine 4.2.5 High pressure feedwater heaters
2.2.2 Reaction-type turbine 4.2.6 Summarv
2.2.3 Effect an turbine design 4.3 Choice of feed pump and drive system
2.2.4 Biade efficiency 4.3.1 Feed pump sire and number
22.5 Modern blading designs 4.3.2 Feed pump duty. margins, and the need for variable
22.6 LP turbine blading speed
2.3 he effect of clearances on reai designs 43.3 Economic comparison of steam turbine drives with
2.3.1 Profiie loss electric motor drives
2.3.2 Secondaw ioss 4.3.4 Economic comparison of voriable-speed motor lVSMl
2.3.3 Tip leakage drive with induction motor plus fiuid-coupiing drive
2.3.4 Disc windage 43.5 Example of the resuits of an averaii comparison of the
2.3.5 L8CiW wires through-life costs of four feed pump system options.
2.3.6 Other iosres 4.4 Turbine by-paEl Sy518mS
2.3.7 Wetness loss 4.4.1 Superheat plant
2.3.8 Annuius loss 44.2 8"-oass caoacifv
2.4. Stage efficiency and the condition iine 4.4.4 s;&em
44.3 improvement
effectsof sfan-up capabiiity
24.1 Efficiency of stage
2.4.2 The condition iine 4.4.5 PWR wet steam piant
2.4.3 Cylinder efficiency 5 Turbine blading
2.4.4 Leaving loss
2.4.5 Hood loss 5.1 impulse stages
2.4.6 Wetness ioss 5.1.1 Moving blades - details and construction
24.7 Paniai admission 5.1.2 Fixed blades - detsiis and construction
51.3 Veiocity-compounded stage
3 Therrnodvnamics o f the steam cycie 5.2 Reaction stager
3.1 Development of the modern steam cycie 5.2.1 Fixed and moving blader - dstsiis and construction
3.1.1 The steam cycle 5.3 Low pressure stages
3.1.2 The Rankine cycle 5.3.1 Aerodynamic and mechanical constreinis
3.1.3 Practical cycie using superheat 5.3.2 Biade tip restraint
3.1.4 The rehsat cycle 5.33 Baumann exhaust
3.1.5 Regenerative feedheating 5.4 Moving blade root attachments
3.2 Cycle efficiency and heat rate 5.4.1 Fir-free 10015
3.2.1 Cylinder efficiency 5.4.2 Pinned roots
3.2.2 Heat rate 5.5 Diaphragm construction and support
3.3 Termins1 conditions 5.5.1 Kinematic support
3.3.1 Effect of steam inlet conditions 5.5.2 Radial ruppon pads
33.2 Effect of reheaf conditions 5.5.3 Diaphragm construction
3.3.3 Effect of pressure loss in pipework and valves 5.6 Blading materials
3.3.4 Effect of final feed temperatures 5.6.1 12% C i stseis
3.3.5 Effect of exhaust pressure 5.6.2 Titanium
3.4 Superheat cycle 5.7 Blade vibration control
3.4.1 Steam conditions 5.7.1 N ~ t u r afrequencies
l and excitation freq~encies
3.4.2 Reheat 5.7.2 Sources of vibration excitation
3.4.3 Double reheat 5.7.3 Verification of estimated natural frequencies and wheel
3.4.4 CEGB cycles chamber tests
3.4.5 Turbine desians
~ ~
5.7.4 Methods of "ibistion controi
3.5 Wet steam cycie 5.8 Erosion protection
3.5.1 The PWR steam cycle 58.1 Erosion mechanism
3.5.2 Cycie considerations 5.8.2 Erosion progression
3.5.3 Full-speed or hslf-speed machiner 5.8.3 Protection and erosion shieid msterisls
The steam turbine Chapter 1
In axial till-bines, the stralii is adillitted to llic cyl- ~nombeio i L.1' cylinders being requiicd: the use of a
inder and cuhai~stciliioril it, by one or ino1.e circular rely long shaft can be avoidcd by the use a l a cross-
pipes in a radiai or near-radial orientation (see Section corn~oilndmachine. Further, the number of 1.P cylili..
6 of this chapter). A 1 thc L.1' t~irbineexbai~st,the deis can be reduced if thc 1.1' turbine shaft rotates at
connection fIaiige(s) to the condenser will however 1800 rimin, while llie H P shaft rotates at 3600 rimin.
llorlllally be rectangular, at an appropriate locatioli The arrangement of the L P turbine and its con-
and ol-ientation to matcll f h e condenser design. This nection l o the condelisei depends critically on the
always in\,olves radial flow in one or mare directions. location of the condenser, and the orientation of the
The steam is therefore required to turn through a condenser tubes with respect t o the turbine axis.
right angle to enter the axial-flow blading and to The condenser has traditionally been mounted below
exhaust from it, at the same time redistributing itself tbc turbine, with the condenser tubes either axial or
around the circumference. The inlet and exhaust areas transverse. During the 1960s and 1970s, many 500 MW
therefore require sufficient space t o allow an orderly and 660 MW turbines were built in the UK with side-
flow without undue pressure loss or flow separation. mounted condensers and axial tubes. Variants of this
In some cases, particularly low pressure turbine ex- design are called the pannier condenser (Fig 1.6 (a))
llausts, flow guides may be incorporated. and the ifrtegrul co,zdenser (Fig 1.6 ( b ) ) . The main
objective was to reduce the overall height of the
turbine, with a view to reducing the height and size
of the turbine hall. Because the tubes were axial, the
condenser steam space could be sectionalised, thus
1.2 Cylinder and exhaust arrangements
allowing a lower condenser pressure in the cold end.
For turbines driving electrical generators, the limit of This provided a small efficiency benefit.
a single-cylinder turbine is around 100 MW, d e ~ e n d i n g The main disadvantage of this design is that the
on the design concepts, the initial steam conditions conderlser becomes an important part of the turbine in
(pressure and temperature), whether or not a reheat terms of structural integrity, loading, foundations, etc.
cycle is used, fhc exhaust conditions and the specd This rnakes the condenser design dependent on the
Of rotation. number and size of LP turbines, thus inhibiting the
Frequently turbines o f this size are designed and
concept of modular design and complicating the de-
built o n a modular basis, with the inlet sections, biad-
sign interface between a turbine maker and a number
ing sections, and exhaust sections selected from a range
o f possible condenser makers. This design may also
of standard designs t o suit a range of output powers,
complicate access to the turbine for maintenance,
initial and exhaust conditions and special applications
for example, t o the bearing pedestals.
such as extraction steam for process heating or district
Later plant in British stations has therefore reverted
heating.
For larger machines, nrulti-cylinder designs are used to the use of undemlung condensers with transverse
(Fig 1.4). The numbel. of cylinders depends o n a simi- tubes (Fig 1.6 (c)), using a connecting duct between
the turbine outlet flange and the condenser inlet flange.
lar list of terminal conditions and design considerations.
Because the condenser tubes are normally much longer
A typical turbine of 500-900 MW output in a fossil-
than the width of the turbine casing, this duct is
fired power station (coal, oil, o r gas) or a gas-cooled
nuclear station would have one H P turbine, one inter- trapezoidal in shape.
mediate pressure (IP) turbine and two (LP) turbines, On some turbines built between 1920 and 1960, where
rotating at 3000 or 3600 rimin, depending on the grid the available last stage blading provided a limitation
frequency (see Section 1.3 o f this chapter). The I P and on turbine output or efficiency, the Buumann exhausf
L P turbines would probably be double-flow. turbine (Fig 1.7) has been used by certain manufac-
In a power station with a water-cooled reactor turers, particularly Metropolitan-Vickers in the UK.
(PWR, BWR, CANDU, etc.), the initial steam is at lower In this design, the penultimate turbine stage is divided:
pressure and temperature, so the steam mass flow rate the steam flow through the outer annular part of
and volumetric flow rate are likely to be much higher the stage is led directly t o the condenser, while that
flowing through the inner part flows through the final
for a given output. The turbine might then have one
double-flow H P turbine and two or three LP turbines. stage o n its way to the condenser. Because the two
The turbine with a number o f cylinders on a single parts o f the penultimate stage moving-blading have
shaft is described as a tandem-compound machine (Fig different duties, there is a discontinuity in the blade
1.5 (a)). The other main type is the cross-compound profile which makes it a difficult concept t o use in
machine (Fig 1.5 (b)), in which the turbine cylinders the most highly-rated turbines.
are mounted on two separate parallel shafts driving
two separate generators. The steam connections and
the auxiliary systems are arranged as for a single u
generating unit. This design of plant has been more 1.3 Speed o f rotation
widely used where the grid frequency is 60 Hz and In the normal case, steam turbines are directly w u -
the available L P turbine blading results in a large pled t o the electrical generator, n o gearbox being FIG. 1.4 ~ u l t i - c y l i n d e rturbine arransemenir
'a3e1s uo!lJear 'sapelq paxy aq1 u! pau!e3 L]!ao[ah aql J O UO!I a 4 1 'melsuos e s! )! pue sarnssa~disnaqxa pua lap!
e u! 1eq1 01 iualajj!p ieqmamos s! a3e1s aslndm! -lodoid e jo ssol aqi 01 anp Llalos alojalaql s! sape[q aql ale Ed pue Id 'ale1 MOU ssem aql s! mb alaqm
ue u! Laua!s!jja uo o!xer Ll!aojah aqi jo lsajja aql 3u!nom aql u! auop ylom jes!ueqsam aqL 'sapelq
'nadxa lq3!m auo s v '(3 = '3/n) LI!ao[aA alnlosqe 3u!nom aqi s s o ~ s edolp alnssald ou alojaiaql pue . '
meals aqi pun Lq~olahapa[q Bu!nom jo o!lei aql uodn doip Ieaq ou s! alaqL 'sapelq paxlj aql u! Ll!aolaA
iuapuadap L([e!iuassa s! slnaao sapejq Su!hom aql om! meals aqi u! leaq aql JO uo!)~odo~de sliahuoa
01 L31aua jo lajsuel1 aql qa!qm q l ! ~Laua!s!jja a q s au!qlnl aslndm! ue 'nealex ~ o s s a j o ~Lq d .pa)uahuI '[PI L Z ~ Iu! elopols Lq paanpord IS+J SEM
Axia(o!$$a a p e l a V'Z'Z au!qlnI edhl-aslndtul 1'2.1 au!qin~ aql ssoiae alnssald u! [lej aql pue moll ssem
uaamlaq d!qsuo!lelal v 'lndmo lamod aql aauaq pue
au!qini aqi q3norql MOU ssem aql sla!ilsai sapa(q
.ad61 uo!laeal l o aslndm! ue jo s! au!qlnl pax!j luanbasqns 11spue iaju! au!qJni aql jo salzzou
'JoroJu n i p e se u~nouyijeqs h\o[joq papuedxa L[iea13 aqi iaqlaqm uodn iuapuadap sk..sapelq 3u!~om aql u! aql ie paanpold doip alnssa~d a q s 'jlasq au!qlni
e Lq paaeldal ale s~s!p aqi 'pealsu~ ,a[qe!hun sas!p aql uo uo!la!rlsal e s! I! peol 3u!anpa~ JOJ sahjeh
saxem au!qIni uo!laeal aql j o sapelq 3u!nom aqj ssome aglorql u! [njasn s! doip alnssald jo jaajja aqi i s j ! q ~
doip alnssald e jo aJuasa~da q s 'sas!p aql ssorae loiaah Li!so[ah fea!dLl e smoqs 8.1 a1n3q (a[q!ssod Aqoedao fiU!MOllaMS 1'1.2
saaroj ainssald ou alojaiaq) pue sapelq aqi ssorse sa 008j 01 I E ~ U se s! paulnl s! mea~s<.a~ltl qq~!qm
dolp alnssa~dou s! alaql aau!s [(ems s! ~ o i aqi o ~ uo 'sapelq 8u!nuc11, A I I qznozqi ajBue aqi 'Ljleapl 'a3IOJ e 01 alojaraql pue urn
lsniql je!xe aqL ' ~ j e q sialame!p ljems e 01 paqseile u! meld sayel L31aua [ea!ueqaam 01 L81aua s!la\!ly 1" -"amom u! a3ueqa e 01 as!, sah!3 q~!qm meals aqi JO 'ayen aqi ssorae dolp
10 q i ! ~je.i3a1u! laqi!a ale qa!qm sas!p uo pa!i~ea ale iro!srahuoa ley1 .ia![rea passails iu!od sqi s~s!*!lijrllil,l uo!lom jo uo!lsal!p u! a3ueqa e saanpold sapelq aql a ~ n s s a ~aq1
d 3u!sea~su! pue ,nojj ssem ssal 3u!ll!mlad
sapelq 3u!nom au!qim-aslndml ,su3!sap au!qinl aq) u! s ! q ~ ,(I&) sapejq 3u!~om aqi 3u!ialua olrals , I ~ I 1" uo meals aqi jo iuama3u!dm! a q s ' ~ j e q sau!qrnl aql
sasua>ajj!p iue~!j!u3!s ale alaqi leqi sueam 3u!pe[q 0s 'eale anleh aql Bu!anpai Lq paqs s! peol slow 'pea[
Li!ao[an an!ie[al aql uegi ssa( s! ( 2 ~ sapnlq
) :I~I!,AIII!I uo xiom jE3!UEqJaW oiu! LB~auas!iau!y si! lrahuos pun paqs 01 pasn s! pue Su!y~ro~yr sa umouy s! s!qs 'dorp
uo!oeai pue asjndm! jo ss!ls!ialsereqs iua~sjj!p s q ~ aql 3u!hea! meals aql jo Ll!ao[ah ah!le[a.l at1.L. ' l i l ~ l i i l l ! l l ~
sapelq paxlj i o avzou e II! pa)eia(asae uaaq seq ]ern ainssard pue L ~ O I I U J u! asasmu! a31ej e jo asuadxa
ufi!sap au!qrn? uo i3a483 &'z'z LI!JO!~A 33elS adL~-as[n(im![e>!dLl e SMOL[S 6.1 : > t i ~ i I i [ meals an!aaar a3eis au!qlni e jo sapejq Bu!nour a q ~ aqi le inq 'anjen iaju! anjen agi ~e Ldjeqiua aqi 3u!
sapelq 6 u ! ~ o m Z'Z -n!eiu!em jo imjja aql seq s!qs 'ieaqai [eUO!lJ!lj 01
L ~ J ~ U~!IJU!Y
J p a i e ~ ~ u asi!
3 ~ j e3u!i~anuoa ' a ~ j e hsin
qSno.lr(l Bu!ssed ralje Ljp!del spuedxa meals aql aiaqm
'sah[en l o ~ l s h o 3autqlnl u! slnaao s!qi jo aldmexa u v
'sjanal lasuapuos d o ~ pa ~ n s s a l danleA w e a l s 1 ' 1 ' ~
lueisuoa le u!emal suo!l!puoa aql aiaqm pua isneqxa
aql molj Llan!ssassns paienlena aq uea i!un aql jo
a3e1s qaea la sarnssald aql ' ~ o [ pa~!nbal
j aqi 3u!mouy '(Lblaua J O 61!1!qej!eAe u! s o [ ) Ldoliua u!
pue 'au!qlm aqi r o j eiep ISJI 10 u3!sap raqira worj asealsu! pue alnssard u! ssol e inq 'Ldjeqiua awos jo
pau!elqo aq uea x luelsuoa ,riel asd![13 aqL 'p!n[J uo!luaial aql s! ijnsar a q s ' ~ e a q(euo!lgrj 01 pailanuos
Su!yiom aqi s! meals alaqm ( ~ ' 1 )uo!lenbx u! iiah!3 aq 01 ;\31aua ~!iau!y pai~raua3 aq1 jo auios sasna3
uo!srah xjr 3u!sn Lq pau!e]qo s! L s e l n ~ xiua!a!jjns a p o u aqi puodaq meals jo oo!suedxa aqL '(Ldlaqlua)
'L[je.iauat) 'ail!qlm B uo pea[ [e!lied jo s l x j j a a111 lea11 jo aslladra aql le L3iaua 3!1au!~ sa.i!nbae I! 'a12
3u![lapom uaqm [ooi jnjasn r! s! ,riel asd!l[x ail^ -7.011 ro S3!J!lO mo.lleil e i(3nolql sassed meals uaqm
.
'li! Ill~trlrit~ethe point let us assume, for the drop develops across the moving blades, and the
more accurate to describe the two designs as:
ritiiijralll, 111111 the final stage is designed to have a steam leaves the moving blades at a higher speed to
and since by symmetry W 2 = C , the available energy 'Disc and diaphragm' turbine, using low reaction isI11y low degree of reaction at the base diameter, offset the higher peripheral speed and arrive at a n
= m ( ~ -, Wi2)/2
~ furthermore W j 2 = C i 2 + U2 - blading. lioet lltr gcriphery of the rotor disc. The fixed and axial leaving velocity. This causes the pressure drop
2 C , U cos a , therefore, available energy = m / 2 ( ~ , ' - riliivitlK bllldc profiles are then as shown in Fig 1.13. across the fixed blading to fall in order to maintain
u2 + 2CiUcos a ) 'Drum-rotor' turbine, using high reaction blading [21. l , 118 ~ t!o\r2 move to the region half-way up the the same pressure drop over the stage as a whole.
ti~iiti~!ji lilttile, i.e., to the stage mean diameter. Typi- There is therefore a substantial degree of reaction at
and hence e?rlIv, ol! modern blading, the tip diameter is about the mean diameter. Figure 1.13 shows the effect that
2.2.6 LP t u r b i n e blading cii<iclilc ( l base ~ diameter so at the mean, the blade increasing reaction from root to tip has on the profile
7 = 2U(2Cicos a - u)/[(c,)' - U2 + 2CIUcos a1
Steam passing through the stages of an LP turbine ex- jriltli ( i . ~ ,lhc , circumferential distance between ad- and on the velocity vectors at root, mean and tip
= 2((2cosa - <)/(I - E2 + 2 t cos a ) pands rapidly and accelerates to a high velocity, often Jilt:r*l!l hl!irles) is about 1.5 times the pitch at the base sections.
and supersonic. Steam at exit from the cylinder can have rlii~~rtrrlor. 'l'l~eperipheral speed of the blading is also The effect o f these changes leads to a more order-
qmax= 2cos2s/l + cos 'a when € = cos a up to 10% moisture content. The flow then is complex I ,1 l l l t ~ t ' a tta prcal as at the base. If the same moving ly streamline flow with substantial increase in the
and the design a f LP blading reflects this. The blades lilsilt: uurllllt~ was used at the mean diameter as at efficiency of LP turbines. The pressure losses after
are long and have a highly-twisted profile so that the Ills i,itcr, lllr flow passage through the moving blading the last stage moving blades (proportional to the
Figure 1.11 shows the diagram efficiency of a reaction inlet and outlet angles conform to the three-dimensional ~"ctitldI ~ Pre~~dered incorrect by the increased pitch: velocity squared) have also been reduced by achieving
stage in comparison to the impulse stage. flow characteristics at all blade heights. wiillbl lhi. cl'fcct o f increased blade speed would be a reduced and substantially uniform velocity over the
10 11
The steam turbi~ie Chapter 1 Efficiency and o ~ i t l ~ ~ l i
-.
annuiai region i~ii~iicdiaieiydownstream o f tilc last ::l 4 l>ic+c; w i n d a g e 2.4 S t a g e eificiency a n d t h e condition line
stage biades. A further beneficiai effect o l reducing
iiii,, I ti,c iriclioii ioss due to the surface friction
crowding of fro\\' at the blade-tip is that tile excessive
i !, ~,iirii t,ti ~ i r ciliscs of an impulse turbine as the disc
steain leakage over the moving blade-tips, which did
~,,:,iic,; ii, tiic siezio~ atm0sphet.e. The result is the 2.4.1 Efficiency of s t a g e
no useful work, has bcen reduccd.
! , i i I ( . i ~ ~ ~01
i ~ si~afl power for an increase in killetic Thc efficiency a f a turbine stage will always be some-
,,itti i,<:iil cncrsy of i i ~ csteam. what iess than ideal because of the lasses discussed
in Section 2.2 of this chapter. Thc efficiency of a
weli dcsigned stage in a modern H P turbine is about
2.3 T h e e f f e c t o f clearances on real designs 8 , Lacing w i r e s 85-90%. This stage efficiency is obtained in the
Blade efficiencies arc far from ideal and the main ll,u ioug blades of the L P cylinder are stiffened foliowing way:
causes of this are aerodynamic factors. The three lii\rwiiila thc tip with iacing wires. Their purpose is
most important factors are profile loss, secondary i t , r i i ~ l i i i j vibrations and raise the resonant frequency Actuai stage heat drop or:
loss and tip leakage loss. These are of roughly the same ( $ 1 lile biade so that it does not coincide with any n =
Isentropic stagc heat drop
magnitude whilst other sources of aerodynamic ioss, i ; . i ' i l i ! ~ ) ~ frcquency present in the turbine. The pre-
such as windage and lacing wires, are much smallcr. ~:i.i~r.r o l these wires, however, produces losses in blade
(entlialpy at fixed biade inlet) -
iil~i.irncybecause of the passage area that they block.
(cnthalpy at moving blade outlet) x 100%
2.3.1 Profile l o s s (enthalpy at fixed blade inlet) -
:. , (cnthalpy at isentropic moving blade outiet)
This is due to the fol.mation of boundary layers on i 2 . 8 Other losses
the blade surfaces. The fluid in the boundary layer 1 liiir ;we further losses which, though not due t o
is subject to viscous forces which slow it down and i i i ~ . ~irsigii of the moving blades, do affect the biade 'This can be more eicarly envisaged through the
increase its entropy relative t o the flow in the main- i i iicici~cy.These iasses are Wetness loss and Annulus use of a rurbhie condition line.
stream. This results in the steam downstream of the 1li.i.L
moving blades having a higher entropy than the steam
upstream. At a given flow rate this would result in a 2.4.2 T h e condition line
larger pressure drop across the blades than there would 2.3.7 Wetness loss The condition line is the locus of the conditions of
be in isentropic flow. Since the pressures in a turbine
FIG. 1.14 Secondary flows 'illis is incurred by moisture entrained in the low the steam as it passes from the stop valve at the iniet
are fixed, the flow rate becomes less than isentropic
prcssore steam towards the exit plark of the L P tur- t o the H P cylinder, through all the turbine stages to
and the entropy of the exhaust steam greater than
itii~e. The loss is a combination of two effects; the the exit plane of the final moving blade of the L P
isentropic. This means the heat drop obtained across
firs1 is the reduction in efficiency due t o absorption cylinder (Fig 1.16). Ideally the expansion of steam
the stage is less than that for a n isentropic expansion
01 energy by the water droplets and the second is through the turbine will occur isentropically, that is,
and is therefore iess efficient. cumference of the moving blades, joining the tips.
Thc shroud is sealed against the casing by several liic erosion o f the final moving blades leading-edges. at constant entropy shown by the vertical dotted tine.
Profile loss is a boundary layer phenomenon and
knife edges.
lil-osion occurs because the water droplets travel In reality the friction effects, such as profile and sec-
is therefore subject to factors that influence bound-
i;ir slower than steam, consequently their velocity ondarv
. . ~ ~ , cause an increase in the heat and entropy
, loss.
ary layer devclopment. These factors are Reynolds The extent o f the leakage depends o n whether the ~
ma. 1.16 iilrbiiie candiiioct liixe I:i(i. 1.17 S ~ g ccondition line through the conversion of its kinetic energy to flow
friction losses. This is a constant enthalpy process
since the steam cannot do work on blades that it
has already left. Consequently the steam comes to
rest at the point X on Fig 1.19.
7 (internal) = H 1 - x 100% and Both exhaust conditions are displayed in Fig 1.19 > y derived
!idhi ~ ~ t l l ~ i , l l is from the measured powel The heat loss between the total conditions at blade
H , - H? from which the followine- LP efficiencies can be ci1iili111 iillcl lhc slatic isentropic enthalpy is normally exit (HZ)and the static pressure line (H,) is known as
obtained: tdLt81i 111 ~ . O I I ~ C I I S C Ipressure. TT/TT efficiencies are
H, - H2 the leaving loss. The significance leaving loss has on
7 (external) = x 100% liiit~i)~ii~lly dc~.ivedfrom wetness probe (traverse) tests. efficiency can be seen in the following example:
HI - H4 Total Static/Total Static efficiency (TS/TS) 'rt!i:I R F I I I I O P ~ C exhaust enthalpy in this case is at the
klaiJr still (Jene total pressure. Traverse tests measure Leaving loss = v 2 / 2 J/kg
-
- Hl - H, x 100% i$$i:w ~ l l i u h h ltnd other properties of the steam along
For H P and IP steam turbines, the kinetic energy H , - H, line IrcilQBt of a moving blade. The test is restricted where v, is the velocity of steam leaving the last row
effects at inlet and exhaust are small and usually $11 /lie 111011h11rement across L P turbine stages where of blades. For a 500 MW turbine, the velocity v , is
ignored. ~h~ kinetic energy at inlet to the LP turbine Total Total/Total Static efficiency (TT/TS) il~eirIR ~ ~ i l ' f l c i ~distance
nt between stages to permit typically 170 m/s:
is also negligible but a t the exhaust it is not. As lb6 Ilvr llllhhilge of the probe.
170'
a result LP efficiencies are derived by considering thus leaving loss = -2
= 14450 J/kg = 14.45 kJ/kg
either:
The total exhaust conditions - which includes Total Total/Total Total efficiency (TT/TT)
P:4.4 ibnvlng loss This would be responsible for a 2% reduction in LP
~ I C M I I IIVIIVCA the finalstage of an L P turbine with cylinder efficiency.
the steam kinetic energy and is measurable with a
correctly aligned pitot. - - X 100% b l l ~ i i l l ~energy
~ at the total pressure and enthalpy
HI - H i hlilivill 111 Ply 1.19. i f the steam could be slowed down
The static exhaust conditions - which represents iri?iiliitpiat~llylo zero kinetic energy, it would be at 2.4.5 Hood loss
conditions when the kinetic energy has been re- TT/TS efficiencies are usually obtained from heat ajnlli. (>trsxarc and cnthalpy. In practice the steam Another loss which occurs between the final stage
duced to zero and is measurable with pressure gauge. rate tests (see Section 3 of this chapter). The exhaust <Ittau xlll\r down after leaving the last blade, but and the condenser inlet is a pressure drop known as
The steam turbine
hood loss (1% 1.20). Norii~aily the condenser static 2.4.7 Partial admission
picssiire is less tllao that at blade exit, Tlic steam I'arrial adn~iasioiigives a loss In turbine crficiency il
expands ill the Ihood wllich joins the cxliaust of the thc stcan? sugpiy to the turbine is governed by thc
L.P cylinder to the condenser inlet. The cxpansiotr number o f inozzles in use. Thc alternative mcans o l
converts c n t h a l ~ ~ to
y kinetic energy which is theii steanl governing is tlirottle-control, where admission
converted back lo heat by flow friction losses. is over the con~pletccircumference o f the first stage,
In some cases tlie hood loss is negative and the and coiitiol is achieved by reducing the mail1 stcani
condenser pressure is higher than blade-exit static supply. Partial admission is tilerefore not experienced
conditions. This occurs when the steam kinetic enel.gy by throttle-controlled turbines.
is converted to pressure, a process known as dijfusiori. Thc problem with reducing steam flow by the use of
nozzie-controi is that when the blades are aligned with
a norzle group they run full of steam, but when they
pass into a blank arc, eddies are produced, so caus-
ing a loss. The first and last blades in line with the
nozzle group will only be partially full o f steam and
therefore the flow in them will be onsiderably dis-
tuibcd. Thls is often referred to as 'blade windage',
'blade ventilation' or 'vane action' loss.
There is also an additional factor to consider. As
the idle blades come under the influence of the noz-
zles, the steam in the blade passages has to bc ac-
celerated rapidly, so causing a loss In power. The
~nagnitudeo f this loss increases with the work done
per row, the heat drop, the blade speed, blade width
and height, and the number o f steam admissions. This
factor, known as the steam inertia loss, can account
for 15-20% of the total windage loss in a stage with
single arc admission.
In the UK, there are many interconnected units in
service so that each can be kept In efficient operation
at high load. System load reduction is achieved by
shutting down complete units, so that there is no <w
Fxc. 1.21 Simplified ilealii power plant cycle
benefit from the adoption of nozzle control for individual
units. Alternatively, load reduction is accomplished 8..
,f
8
by reducing the boiler pressure, so that the turbine 8
valves are maintained wide ope11 over most of the
!,i~,ii:iscs in a cyclic process. Figure 1.21 is a sim- The main steam, having been condensed in tlle
load range up to 100%. Part-load efficiencies obtained
l i l ~ l ~ r diagram
il of a modern steam plant, showing condenser, is now in a liquid state at a very low pressure
in this manner are comparable to nozzle-governed
iiio)~01' the essential elements. and approximately saturation temperature. This water
machines, whilst the full-load efficiency is better.
011r 11alCof the cycle consists of the boiler (or heat drains from the condenser, where it enters the hotwell.
,~liircu)and its auxiliaries; the other, the turbine The water in the hotwell is pumped by the condensate
ryclc, consists of turbine, generator, condenser, feed extraction pump through the low pressure feedheating
O I I I I I and
~ feedwater heaters. system to another pump, the boiler feed pump.
3 Thermodynamics of t h e steam cycle ('otlsider first the boiler plant involved In the cycle. In a modern regenerative cycle, some of the steam
FIO. 1.20 Hood loss I.r,:dwater is supplied to the boiler drum, where water passing through the turbine cylinders is bled from a
I!, boiled and converted Into dry saturated steam. series of extraction belts located after selected moving
'Illis dry steam is further superheated in the super- blade stages and fed to the condensate and feedwater
llvater and then fed to the H P cylinder of tlle tur- heaters. Thls steam is used to heat the condensate In
2.4.6 W e t n e s s loss
3.1 Development of the modern steam cycle
I~inc.The steam expands in the turbine giving up heat the L P heaters and the feedwater in the H P heaters,
Figure 1.16 shows how the condition line curves sub- This section will outline a modern steam cycle and energy, a high proportion of which is transferred which are o f a surface type.
stantially towards higher entropy values below the then discuss its development f r o ~ nthe basic thermo- inlo work energy on the turbine shaft. The shaft The boiler feed pump increases the water pressure
saturation line. The reason for this is the Increasing dynamic power cycle. Having developed a modern turns an electrical generator which produces electric to a level in excess of the drum pressure, to provide
wetness towards the exhaust in a n L P turbine, dis- steam cycle, the means o f assessing its efficiency and power. Steam leaving the H P cylinder returns to the for the pressure loss in the boiler circuit and H P
cussed in Section 2.2 of this chapter. If the efficiency economic implications will be introduced. boiler, where It is reheated. The reheated steam is feedheating train. The cycle Is now complete.
is adjusted to exclude the wetness loss, it is called the further expanded In the IP and L P cylinders, before
dry stage efficiency. It is common practice to assume passing into the condenser.
that the total wetness loss is proportional to the 3.1.1 The s t e a m cycle In the condenser, which is a large surface-type heat 3.1.2 T h e Rankine cycle
mean stage wetness. Baumann suggested that 1% total A power station operates using a closed steam power exchanger, the steam is condensed by transferring Its Having presented a modern practical steam power
wetness loss be assumed per 1% mean stage wetness. cycle, where water undergoes various thermodynamic latent heat of vaporisation to the cooling water (CW). cycle, attention will now be given to the development
-7:
The steam turbine .& Theifnodynamics of the steam cycle
&+
..-
V' , , . -
of such B cycle 110111 a basic vapour powcs cyclc - steam is expanded thraogli tire torbine iseiilrapicall)~, e No salniated steaill must enter the condenses, i.e.,
thc Rankine cyclc. i . c , u,itlroilt loss. This process (C-D) ~)ioduceswork point D must be within the vapoui boundary (Fig
For the purpose of illustraliiig the various power along liic turbine shaft. F'inally the wet steam issuing 1.23).
cycles, the Temperature-Entropy (T-S) and Entlialpy- from tile turbine gives up its heat in the condenser and
Entropy (H-S) diagrams will be used. An understand- returns lo watel. (process O-A). e The exhaust wetness in the last turbine stage must
ing of thermodynamic properties -- Entropy and The heat input t o the boiler or 'the energy paid not exceed 12%, i.e., DD' nlust be less than 12%
.
Enthalpy is assumed. However, in the context of for' is represented by the area EABCDP on the T-S of A D ' .
the following descriptio~lo f steam cycles, a review of diagram. The work done by the cycle is represented
Entropy will be beneficial. by the area within the polygon ABCD. The heat Material properties limit the maximum temperature
Entropy is an abstract property of steam which rejected to the condenser is represented by the rec- within the cycle.
increases when heat is added and decreases when tangle ADFE. In the context of power generation,
heat is rejected. Its magnitude is such that if the Thermal Efficiency q is defined as:
temperature at which heat is transferred is multiplied 3.1.3 Practical cycle using s u p e r h e a t
by the change in entropy that results in the pro- The first development o f the Rankine cycle into a
cess, then that product equals the amount of heat Work done = (Energy for geneiation)/Heat input
(i.e., energy paid for). Hence the Thermal Efficiency more practical steam cycle involves raising the pres-
transferred. sure and temperature of the steam entering the turbine.
Now consider the simple Rankine cycle for steam, Of the Rankine cycle, based upon Fig 1.23, 1.23 is q
(Rankine) = Area ABCD/Arca EABCDF. The superheated steam cycle is shown schematically
shown scheinatically in Fig 1.22 and on the T-S dia- l t i l , 121 K;$iikise cycle T-S diagram
in Fig 1.24, and on the T-S diagram in Fig 1.25.
gram in Fig 1.23. In the s u ~ e r h e acycle,
t the saturated dry steam leaving
Water is pumped into the boiler by the feed pump The economic implication of cycle efficiency is a ~,q
(process A-B). In the ideal Rankinc cycle, there is no %
.S!
the boiler drum is further heated before entering the
major factor behind the development o f the cycle, . ,...
.:.wlrs!ie lcr~~lil~iil conditions. The effect o f changing turbine. For the same quality of steam entering the
temperature rise across the pump and points A-B are wllil~t maintaining or reducing capital cost per elec- ,
condenser (i.e., same point D), the increase in work done
coincident. The water is then heated to produce dry
saturated steam (process B-C). The dry saturated
trical unit supplied. The other major consideration in *;
9
,E
ie$jir:iiei i-~i~~dltiorrs is dealt with thoroughly in Section
8 i nl i l i l i rltilplcr. However, it is useful to consider is shown o n Fig 1.25. The quantity of heat rejected to
the choice of cycle, is the engineering feasibility of the condenser is the same as for the Rankine cycle.
it!, li4li*wi11,&criteria when attempting to change
* . ; I I I I I ~ Icor~~iitions: Hence, there is an improvement in the cycle efficiency.
,~
FIG. 1.22 Simple Rankine cycle power FIG.1.24 Superheat cycle plant
18
The steam turbine C h a ~ t e r1 Thermodynamics of the steam cycle
The superheat efficiency is greater than the Rankine tlierrnel efficiency from the 7 - S diagram is q(lichia,,=~
efficiency as Area (P + Q)/(I' i- Q i R) is greater (Area ABCDEF)/(Area GABCDEFH).
than Q/(Q + R). "; The reheat cycle benefits from reduced wetness in
This superheat cycle was chosen to Ilave the same the turbine exhaust, but presents an increased capital
turbine exhaust conditions as the ~ r e v i o u s Rankine outlay in terms of reheater pipewoik to, from and within
- A S " , ' ~ , ~ ~ ' cycle. However, a major advantage of superheating the boiler. The turbine is usually split into H P and
$ L P cylinders t o avoid the high thermal gradients
which would be introduced between stages of reheat
o n a single-cylinder machine.
I'
3.1.4 T h e r e h e a t cycle
3.1.5 Regenerative f e e d h e a t i n g
The desire for further increases in cycle conditions and
T o complete the cycle development of the steam cycle
consequent increases in cycle efficiency, led to the
t o that of Fig 1.21, the inclusion of regenerative
addition of steam reheat during turbine expansion. The
ENTROPY, s feedheating must be discussed. Physically, a propor-
reheat cycle is shown schematically in Fig 1.26 and
tion of the steam is bled from various points on the
FIG. 1.25 Superheat cycle T-S diagram o n the T-S diagram in Fig 1.27. Fit. 1.27 Reheat cycle T-S diagram turbine, which is then condensed to heat feedwater
In the reheat cycle, steam at a given initial tem- o n its return to the boiler. Figure 1.28 illustrates
perature is partially expanded through the turbine
the improvement in thermal efficiency for a simple
Area ABC,D (process C-D) doing some work, and then is fed back
~ ( s u P c ~ ~=
Il,e reheat cycle incorporates an improvement in Rankine cycle (Fig 1.29), by virtue of the bled-steam
c ~ ~ )
Area EABC, DF t o the boiler, where it is reheated to about original
i l ~ o i n a l efficiency aver the superheat cycle. The releasing all of its heat to the feedwater, and little
temperature (process D-E). The heated steam is then fed
- Area ( P + Q) through the remainder of the turbine before being
Area (P + Q + R) condensed (process E-F).
flc. 1.26 Reheat cycle plant FIO.1.28 Rankine cycle with regenerative feedhealing
[
20
i1
i
T h e s t e a m turbine Chapter 1 Ther~nodynamicsof t h e s t e a m cycle
3.3.2 Effect of r e h e a t conditions Allt!il!r~ important factor in the design of the re-
ti.-.- .
,nar~-i14llllc cffecl o f pressure losses in the pipework.
Now consider the selection of reheat conditions for
T
P/ fits jslwhllr~loss ~.esuItsfrom a throttling effect which
a single reheat cycle. Having established the steam
conditions at entry to the H P turbine, there are several , @$i!$v~h IIM ovi~ilableenergy for work (to be discussed
$$$elill lllih ~eclion).The oressure at which steam is
design com~romisesinvolved in the choice of reheat IN 11b0ut 25% o f ' t h e stop valve condition,
pressure and temperature. First, consider the boundary
conditions. The H P cylinder exhaust steam must be
sufficiently superheated to avoid any wetness in the
--.
WETNsESLlMi,
@
118 llpproximately a fourfold increase in
W@1811v. 'Thih necessitates the use of increased ~ i o e
ell are expensive and inflexible. The ;lait
cold reheat pipework, which would cause severe ero- IIIII~to weigh the merit of using larger pipes,
sion. As in the previous section, the exhaust steam
from the L P cylinder must be wet, but not greater fg
.?&
98 {Ape ~trtlsin parallel, versus the improvement in
@ p i # alflcicncy. The usual pressure drop is 7.5 to
than 12% wetness. These boundaries are illustrated, I@+% irl lhc HP cylinder exhaust pressure. Finally,
together with the effects of changing pressure, on ~4NrIliiinla will exist in the boiler on the range o f
the Moilier diagram (Fig 1.39). Now consider the
effect of changing reheat temperature for a constant
pressure drop in the H P cylinder (Fig 1.40). The
effect o f reducing the pressure or of raising the Eftact of pressure loss in pipework a n d
temperature of the reheat steam is to reduce L P Fia. 1.39 Boundary conditions for a rehcat line and the FiO. 1.41 LOPSof available energy due lo throttling
exhaust wetness. effect of changing pressure at constant ~empeiilture !cl o f pressure loss in pipework and valves the governor valve
26
The steain turbine Chapter 1 Thermodynamics of the stcaln cyclc
across the tiil-bioc cylinders is coiitroiled by liie Ellipse and its development to the current reheat cycic used
law relationship described in Section 2.1.2 of this 4 in CEGB fossil-fuel and AGR power stations.
chapter.
Pressure losses along pipe suns can bc caiculated
using equations and charts 161. Pressure loss is associated 3.4.1 S t e a m conditions
with pipe diameter, of surface roughness, steam flow rate The effects of increasing turbine stop valve pressure
and the pipe geometry (number of bends, expansions, and temperature and the effect of reheat have been
contractions). Simply reducing piping losses by re- discussed in regard to cycle efficiency in Section 3.3
designing pipe runs, or by adding to the number or of this chapter.
pipes, may increase the capital cost of the plant in It is also relevant to consider the major influences
excess of the benefit gained in running costs. on turbine efficiency. The most important factor in
t
turbine efficiency is blade length. Generally, an in-
crease in blade lengths implies reduccd leakage losses
3.3.4 Effect of final f e e d t e m p e r a t u r e s and secondary losses [5,7].
In the previous section, the concept of regenerative E/ A n increase in steam pressure at a given steam flow
reduces thc volumetric steam flow and hence reduces
blade length. Increased steam pressure also requires
thicker casing walls and larger horizontal joint flanges
and joint bolts. It also implies thicker steam pipe
walls which require additional length to obtain the
required flexibility. These difficulties are only partly
surface. In order to avoid a n increase in the stack I M~ATSUICTED I mitigated by the reduction in casing size and pipe
temperature, the air heater would have to be increased I i diameter made possibie by the smaller volume flow.
rNT"oP".S
in sire, and the cost o f this would exceed any sav- Another important effect of increased steam pres-
ing on the economiser. Consequently the ecollomic sure is the requirement of increased pumping power
F $ ( i 1.42 The effect of condenser saturation icmneraluic
optimum feed temperature is somewhat lower than on cycle work done
to raise the feedwater to the higher pressure.
the thermodynamic optimum. It follows that increases in steam pressure are only
Raising the final feed temveraturc also has imoli- ENTROPY S
a benefit in practice when associated with a n increase
cations for the design o f the'^^ turbine. Past prac- in unit size and/or an increase in steam temperature.
tice has been to use bled.steam from the HP turbine However, there arc several plant constraints affect- An increase in steam temperature has the effgct of
exhaust. The saturation temoerature o f the bled-steam ing the selection design exhaust pressure. Consider I,, clfeei of exhaust presmlre on turbine increasing the specific volume and hence blade length
the effect of lowering the exhaust pressure on the tur- expansion and therefore tends to increase turbine efficiency with-
controls the maximum feed temperature obtainable. %
To provide steam at a higher pressure with a higher bine condition line on the Mollier diagram (Fig 1.43). out any increase in unit size. There are vractical
saturation temmrature, rewires steam to be bled Expansion to a lower pressure results in increased disadvantages, which include the required increase in
from an intermediate point b n the H P cylinder. This wetness, and increased specific volume at the exhaust. 1 Ihr 1.1' turbine exhaust area affects casing size and pipe diameter, and increased thermal
is an additional complication and cost to the turbine The increase in exhaust wetness tends to increase I rii811 o f machine, in particular the ther- stresses especially when starting and loading.
plant. Despite the increases in capital cost, the benefit the erosion of the last-stage blades. However, more 11 01 lhc condenser (see Chapter 3). The
The influence of the combined effects of tem-
from improved cycle efficiency is such that the addi- significant is the effect of increased specific volume, I 1 0 plovide a certain volume flow rate perature and pressure changes and turbine efficiency
tional heater is worth including. implying the need for a higher volume flow rate. lit; ronfipufiltion of the L P cylinders since considerations on unit size can be illustrated by a
The design of the Advanced Gas-cooled Reactor The volume flow rate through the condenser is the 91 I ~ ~ C 4 I I double-flow L P cylinders may be
study of the 'standard' steam conditions specified by
(AGR) has resulted in limitations on the finai feed product o f the mean steam axial velocity and the 111 pi~rilllel to give the desired flow rate.
the BEA and CEGB from 1945 onwards.
temperature. The feed train is curtailed in order to annular exhaust area. The annular exhaust area is otid size of the chosen arrangement o f Table 1.1 has been simplified by the exclusion of
limit the final feed temperature to about 150°C. This limited by the maximum length of L P blade. At 3000 nl'lccts many other areas of design - the a number of units of close to the 'standard' 60 MW
limitation is imposed because of the allowable tem- r/min, the centrifugal forces o n the long blades be- lllicr; the plant arrangement; size of civil size, some of which employed reheat. It shows the
peratures in the gas cooling circuit. come very high and there is a limit to the mechani- general trend.
cal stress which blade roots can sustain. Hence, having rodoced all factors against decreasing There is a progressive increase in unit size accom-
established a maximum annular area, the increase in rrc, i l ~ edesign compromise is once more panied by a series of step increases of pressure and
3.3.5 Effect of e x h a u s t pressure volume flow rate must be accommodated by an in- ~pl'o~'cmentsin cycle efficiency versus the temperature, with a few notable exceptions. The main
The efficiency of the cycle is strongly influenced crease in exit velocity. Steam issuing from the last ity and therefore reliability exceptions are the two 375 MW supercritical units
by the L P turbine exhaust pressure. The back pres- stage o f the turbine with high residual velocity re- IIIIIY, a major factor affecting the choice for Drakelow C, commissioned in 1967-68 and the
sure of the condenser sets the saturation temperature presents a loss of kinetic energy. This kinetic energy p~r'ssure is the ambient temperature at two 550 MW cross-compound units for Thorpe Marsh,
at which the expanded steam rejects its latent heat performs no useful work on the turbine blades and ('\I1call reject heat. This factor seasonally commissioned in 1963-65. These units could be said
of vaporisation to the cooling water. Consequently, therefore is a loss of available energy, known as the tin Ihrraial efficiency of the plant. to have been ordered before their time and have not
changes in back pressure affect the temperature of 'leaving loss', and varies with the square of velocity. been followed by further development.
cycle heat rejection. The effect of a change in con- The other loss associated with the turbine exhaust is The steam temperatures can be seen to reach a
denser saturation temperature on the cycle work done the 'hood loss', which defines the hydraulic pressure plateau of 538°C and 565°C. The 538°C limit applies
is shown on a T-S diagram in Fig 1.42. Generally, loss between the last row of moving blades and the to oil-fired units to avoid the use of austenitic ma-
a low exhaust pressure is sought as it improves cycle condenser; this also varies with the square of the terials in the boiler. These suffer heavy corrosion due
efficiency. same velocity. @,'lion deals with the superheated steam cycle to the sodium and vanadium content o f the fuel oil.
29
T h e stearn turbine Chapter i Thermodynamics of the steam cycic
har.
..~~ Thev also have bled-steam extraction from H aspects relating to the steam cycle for a Pressurised
exhaust, I P exhaust and four stages from the notably spare rotors. Water Reactor (PWR).
turbine. trr the new coal-fired proposais, it
FIG. 1.46 Condition lines for current CEGB designs The diagram shows how much larger are the I Ibcrcil that, although the condition lines
and L P heat drops than those of the H P turbine 111oiclerbines will be very different from
1 Iunill. because they will be designed for
3.5.1 The PWR s t e a m cycle
It is also notable how close together are the I P a n
L P expansion lines for all four examples. The H Ihe order of 30% increase in power The PWR power plant features three principal heat
(a) 660 MW oil-fired with BFP turbine.
expansion line for the subcritical coal-fired machi ' I1 also embody the most recent blading transfer processes. In the primary circuit, fuel is
(b) 660 MW AGR with BFP turbine. is not very different from that for the two 660 M lfic of detail design improvements. irradiated, liberating heat which is transferred to a
units, although its higher pressures will mean redu le how little difference there appears secondary steam cycle. In a nuclear power station
(c) New subcritical coal-fired with motor-driven feed specific volumes throughout. The new supercritical U critical and supercritical condition the plant performing this function is known as the
pump. has larger H P and I P heat drop than the subcritic lnri LI' sections. It should be added Nuclear Steam Supply System (NSSS). In the second
machine. This implies additional available work b cr pressures quoted are approximate cycle, the steam generated is expanded to drive tur-
(d) New supercritical coal-fired with motor-driven feed this is bought at the price of increased feed pun1 Ily optniised values. bines which generate electrical power. Finally heat is
pump. power. t/l.I' inlet 'crossover' pipework merits rejected to the Cooling Water (CW) in the condenser
The feed pump power is a n important part o f t handles low pressure steam - this is the third heat transfer process. The PWR
cycle selection. to minimise pressure losses. general arrangement is shown in Fig 1.47.
The steam conditions for these cycles are summarised The NSSS consists of the reactor, the reactor coolant
The low back pressure of the AGR is clearly a ate branches where the 1P
below: system (RCS) and a number of auxiliary and safety
parent. This pressure is largely site-dependent and and where the LP inlet steam
a function of the mean year-round cooling Wat ed with a number o f flexible systems. The RCS consists of the reactor within its
(a) 660 MW oil-fired 160 bar/53S0C reheating to
temperature. The oil-fired 660 MW unit is locat pe/casing expansion differ- pressure vessel and three or four cooling loops con-
538% at 39 bar (24.4% TSV) with 61 mbar con-
on the Thames where the water temperature is qni Ircllnics installed above, and sometimes necting the reactor to the primary/secondary heat
denser pressure.
33
Chapter 1 Thermodynamics of the stearn cycle
,
The steam turbine
q,ii:I!t~ i,y iedi~cingwetncss. Thc iocarparation of a
r . l i ! ~ i . i i i ~ ~ i l l i surface
il~ would necessitate an unwarranted
iriiii~~Iii,titioii ill the design of the steam generator. The
i!i.risii ~pi:~cliceis to reduce the 'pinch point' to a
$ 1 1 1 1 1 I 1 i i i i r ~ (see
i Fig 1.48) whilst uptimising steam gen-
~iii!i)i cosl against improvements in overall cycle
~I~Iv~cIIL'?.
I~811iiiiiernow the cycle for the turbine-generator
Ll'!jl 1.47). The slightly wet steam leaves the steam
# @ l t ~ ~ ~ ' ~!)asses % l l ) lthrough
, governor valves and enters 2
f l i p lit' turbine. The steam is expanded through the
IIiV~orhinewhere its pressure reduces and its wetness
3
L l i r . ! o i i ~ ~ Tile ~. Wet steam then passes through a mois-
iiiir ncl~ilrntorwhich returns the steam to a near-dry
iai~liiilcd state. The steam is then reheated in two
*!ii!i~!,. 'I-he first reheat process uses steam bled from
e tiil~j>i~~g on the HP cylinder, the second uses live
ataitlli taken upstream of the governor valves. The
uti:iilli leaving the reheaters is in a superheated con-
~ l l i i i i r i 11erorc entering the LP turbine where it is
~ - i ~ ~ : ~ to ~ i ai l low
r d pressure. The low pressure steam
1,. ii~nilrmscdin the condenser, rejecting heat to the Fi(i. 1.49 Expansioll of slealii fcorn inilial colldiiioils
6 i V . I lhc condensate is pumped through several stages wiillout reheat or tnoisiure separation
i s ! i I; Ilcnlcrs to thc de-aerator.
I lic dc-aerator is a large direct contact feedheater
w l i ! i i , iprovides for oxygen removal, a buffer store
it! iccilrsilter and sufficient gravity head to overcome This expansion results in steam at the later stages
!lie I I I : ~ positive suction head of the boiler feed pump. with a moisture content of 25%. A high moisture
I l i i lrerlwater is pumped through several stages of content is intolerable as it results in blade erosion and
III' I,csters before return to the steam generator. stage efficiency losses. The undesirability of blade
erosion was discussed earlier in this c h a ~ t e r As
. steam
exchangers (steam generators) The reactor vessel and _------ ..,.~
: ,*Z,,S'#<,<..',
is expanded through the turbine it starts to condense
cooling loops arc filled with demineralised Water, which
is pumped around the primary circuit. In this system,
boiling within the reactor is suppressed by maintain-
I,
- / I
&.t\:> 'Cycle considarations
1 i,tirii!ul now the effects of the varrous nroceswr
in the wet region along the 'Wilson line' which
corresponds to a wetness factor of 3-4% (see Fig
.~~~
~ ~ ~ - 1.50).
- - Above the Wilson line, the steam behaves as
ing coolant water pressure in excess of the saturation 11ptitt 1111: thermodynamics and economics of the wet dry steam; below the line, wetness becomes apparent
corresponding to the coolant temperature at ils,&~,i ?yule. Earlier it was concluded that the inclu- in the turbine expansion. Water droplets entrained in
from the reactor. The pressure is controlled al!'ir 111' :I superheating surface within the steam gen- the steam flow only accelerate to a small proportion
system and a surge tank, known as the oiiiiir was economically impractical. However, it is of the dry steam velocity as they pass through the
by a
pressuriser, connected to one of the Cooling loops. rlnhi~sblcto reduce the steam wetness as far as possi- fixed blades. The resultant mist has a velocity which
he secondary circuit is of major interest to this tilr wilh the moisture separating equipment within does not suit the inlet velocity triangle of the moving
discussion, The fcedwater enters the steam generatpr, 1111; olrir!?~generator. The Westinghouse four-looo 3425 blade (Section 1.2.2 of this chapter), neither in mag-
its temperature increases up to its saturation -1 $:, kOW (Illermal) design, which ha; been adapted ;or the nitude nor direction. As the mist progresses through
temperature. AL the saturation temperature, the water 'II- I
I
I
,,.&
@ lIt('u first PWR station at Sizewell, provides steam to the turbine, the droplets migrate toward the blade
changes state to steam which leaves the steam genera- :$
e Ill* 111rbinewhose full load conditions are nominally: tips by virtue of centripetal inertia. The resultant effect
tor wet. The heat exchange process for both ! ! IS
-,
C V.C.I ~ S is shown on a Temperature-Enthal~~ (T-H) I I
U"151LDWXSPEcIFIczN~"a~~~
mx,'
I
$.d & l'rciisore = 66.6 bar
of the wet steam is a mechanical drag corresponding
to a 1% cylinder loss for every 1% wetness.
diagram (Fig 1.48). The effects of a high moisture content are un-
~h~ wet steam produced in the steam generator is Tempera,YIe ~ g a i n s i(mars x, "e'll~'erature = 282'C attractive from the viewpoints of turbine efficiency
of a lower quality than the superheated steam con- specific enthalpy, for the primary and secondary <"cutrS
ditions from both fossil-fired and AGR-powered plant. in *he $team generator of a PWR
is the pioducl of mass and
* Maximum wetness factor = 0.25%
and operational economics. The cycle described earlier
included a moisture separator reheater (MSR), which
ow^^^^, there are limitations to the steam, condltlons
attainable. On the primary side, the m ~ X m U m!em-
enthatpy of the two nutds. aqh must be the ,i' takes partially expanded steam, removes the moisture
Same for both piacerrer as it equals t h quanntY
g I IN' exhaust pressure in the condenser is of the order and reheats to a superheat temperature. The choice
~
perature is restricted by the desirability of avoldlng heat transferred
of reheat or crossover pressure is affected by various
boiling in the reactor core, as heat transfer 8 30 mbar. The expansion of the steam from the parameters for a machine rotating at 3000 r/min;
coefficients for steam are considerably !owe1 than ,j llllIi111 conditions to this pressure would result in an these are:
that for water. Consequently the primary clrcuit outlet conditions are designed factor in the final sages. ~h~
temperature, TI, is less than the saturation value for is heated and the resulting steam/water on a Mollier diagram ( ~ 1.49)
i ~ The maximum wetness in the LP turbine exhaust
that Having established the primary circuit through moisture separators, ~ h i c himprove the with 85% efficiency. (lo- IZrna).
conditions, the steam generator and secondary circuit
The sreain turbine Chapter 1 Thermodynamics of the steam cycie
MOISTURE
SEPARATOR
To LP
CYLlNOERS
.
than that for the LP turbine as the blades are shorter live and bled-steam (double stage reheating).
and the tip velocities are considerably Less.
Considering these parameters on the Mollier chart The final terminal temperature difference achieved
(Fig 1.51) presents a 'window' within which the cross- between reheated steam and live steam.
over pressure can vary. The resultant LP condition
line is very similar to that of a conventional LP cyl- The pressure loss across the reheater
inder o n a fossil-fired or AGR plant. The option to
replicate the LP cylinder is attractive, as it presents TO LP
CYLINDERS
savings in terms of design and manufacture and of- Although all these factors are considered simui-
fers a utility, such as the CEGB, the option to ra- taneously in the design, consider the choice between
tionalise its national spares holding. The replication single and double-stage reheating. The plant arrange-
of the LP cylinder would, however, restrict the varia- ments for single and double-stage reheating are shown
tion in crossover pressure still further. in Fig 1.52. The variation in net cycle output against
The inclusion of steam reheating following mois- total reheater surface area (Fig 1.53), shows a con-
ture separation has obvious advantages in terms of sistent advantage over the single stage reheating.
improving the LP exhaust wetness. The more effective The thermodynamic benefit derives from using a
the moisture separator, the less reheating is required; higher proportion of the high quality, dry steam pass-
modern separators can produce steam with wetness ing through the turbine to do work. Hence the HP
factors of 0.25% or better. turbine efficiency is improved, since wetness reduces FIO.1.52 Single and double-stage reheating plant
The steam turbine Chapter 1
Thermodynamics of the steam cycle
--
1.4
IOiI i/liliii ,,l,i,il,~
z 2 . 0 ~ / 1 . 5 ~= 2.05
5 02 iilliil illlii I!,c~CIII of rotor 1.43 = 2.74
Z
5
$ <jolinnriniici wcigtli of 2.05 x 2.74 = 5.60
I
-f
I of rlle half-speed turbine. The dimen-
stage and cylinder efficiency. The other benefit of The principal factors involved in a comparison
.
unr lo the forgings of H P rotors of achievement of zero erosion is likely to be more
two stages over one concerns the efficiency improve- half and full-speed turbines are:
" furbine have resulted in a crossover difficult with a half-speed machine.
ment associated with dividing the temperature rise
across an increased number of heaters (in a similar xelative sizes and weights of the turbines and! ; @ ~ ~ 8 i ~ i i ~tlliI11 1 l s optimum.
i. These higher crossover The LP cylinder for the full-speed machine is si-
way, the increase in the number of feedheaters in- differences in their constructional features. bi 4,' ., ,li~qlllrr 1111 additional inner casing in the
$$%@$i.i '
milar to that of a fossil-fired plant. Consequently,
creases overall cycle efficiency). The benefits to op-
Relative exoectations of reliability, operational fleai. sS,
# :>?@ P i l h i l i . l 11) 11v0id excessive thermal gradients. In
Me&#+ibiaii. lllr lillgr size of the individual components
though there are few differences in blading erosion
problems, the experience of UK utilities is in the
.
erating efficiency must be judged against the increased
bility, and ease of maintenance. I t t i l l rpc,cd lilrbil~c,farces the designer to 'over
capital cost of the additional plant. The increased full-speed area. The design of half-speed LP rotors
i i i i l l i . u~~lislr~~clionalfeatures (see Fig 1.55). involves a shaft with various discs, shrink fitted; this
capital cost includes extra heating surface, a H P cylinder
Relative thermal efficiencies.
bled-steam tapping, extra pipework and increased pres- type of rotor presents poorer dynamic behaviour
sure loss in the reheater. ?WZ and is more susceptible to stress corrosion cracking
b Economic comparisons.
The effect of H P exhaust pressure upon the choice &?it#biiiir., o,~c'rlr,h,,lol flexibility and maintenance problems.
between single and double-stage reheating, is shown . ~ ~ # i i ! ? l i i ! l ol yl f1111 and half-speed turbines are just There are two disadvantages associated with the
in Fig 1.54. Size, weight ond construclion half-speed machine which are related to plant op-
@ $$ ~$fs*niliar~l In llle cho~ceof machine as efficiency
The ootimum pressure is shown, but there is little For equal stress levels in geometrically-similar turbi 111d need to be considered. eration. The larger diameter of the H P rotor leads
penalty associated with deviating from the optimum. rotating components, all linear dimensions should lillll 111 observe that there is no valid t o increased thermal stress. In addition, the rate of
However, this curve shows the general benefit of double- inversely proportional to the speed. Theoretical vs lllltion of experience to support any increase of steam temperature at the inlet to the LP
stage reheating over a range of exhaust pressures ollr design being more reliable than the cylinder may have to be restricted during start-up, to
the last-stage blades of a half-speed turbine could
made twice as long as those of a full-speed tur mmr be placed upon objective assess- avoid losing the shrink fit rotor.
and could be carried o n a rotor of twice the diamete I (including engineering) differences There is no reason to suggest that the frequency of
3.5.3 Full-speed or half-speed machines leading to an exhaust area of four times the. s i rccs of difficulty in various areas maintenance of the half-speed machine is significantly
However, practical half-speed turbines are limi nnd operation. different from that of the full-speed machine. However,
The final issue dealt with in this section involves a
by weight and physical size to be about 40% la I !iYslcmatic differences between the
there will be increased problems in lifting, handling,
comparison of half-speed (1500 r/min) and full-speed
than full speed turbines: Table 1.2 gives a compari transporting and machining components of the half-
(3000 r/min) machines. The study is limited to the 'ill1 re&ard to the H P blade and rotor
between realistic half and full-speed machines in te speed turbines, due to their weight and size.
steam turbine rather than the generator, as the tur- ltionary components of the H P cylinder
bine is more affected by the wet steam cycle. It is, of relative sizes and weights. hi pressarc differences with wet steam
however, pertinent to observe that generators at 3000 Note that the total relative volume and weight (ilucl,; if leakage flows are generated,
r/min and 1500 r/min are technically feasible up t o the rotors and casings per unit exhaust area for 1 IBcI of wire-drawing erosion. The in- Relative thermal efficiencies
the largest required outputs. There are substantial half-speed turbine is 2.85 times the full-speed turbin dii~~cnsions of the half-speed turbine Marginal differences exist between the two designs
differences in the weights and manufacturing costs The manufacturing costs associated with the larg k I~aditngsat the joints as great as with regard to the internal cylinder efficiences. They
of Lpole and 4-pole generators favouring the full- half-speed machine are higher as more materials a lhc flill-speed machine. Therefore the can be summarised as:
38
i i i e steam turbine Economics of the sleatn cycle
speed machine resuils in higher leakage loss in tilc ti. v~~lIill~elsic flow rate, and tiierefore
last few stages of the L P cylinder-. r i l llir slrnm, increases as tile exhaust
ii~iillci.ri.Ail increase in velocity mcans
r The half-speed LP cylinder experiences higher tip i l i Ikiliclic ellcl-gy of the steam at thc
losses due to the increased radial clearances asso- i111d therefore a loss of power due
ciated with a more flexible rotor. Ica\,ing loss.
e The full-speed machine has marginally higher tip i l k 1 1)resSllre is reduced. the cor-
losses in the last stage L P blade due to aero- xirlilrlilion temperature is reduced.
dynamic effects. litole htearll is extracted from the tur-
lir iwni iIir iondcn3atc in the first feedwater..~
141 leas steam passes through the last
Economic comparisons flrrbine, giving a further loss in
It has already been shown that the half-speed turbine
is more expensive than the full-speed turbine of equal
output and exhaust area, with no advantage in effi-
ciencv or reliabilitv. Hence the full-meed turbine will s lilcan that there is an 'op-
be advantageous whenever its exhaust area can match ' where the greatest nct power
the value which is desirable for an economically achiev- when the effect of point (a)
able condenser pressure. Fit, 1.56 Regions of power outpui and coolins water 18, ,
ilnd (c). At exliaust pressures
In order to establish the regions of potential eco- temperature$ favouring econoinic application of 30W r/mili ll1111, ilie incl.ease in power due ta (a)
and ISW r/miil turbines, assuming current, iasr-stage blad? duc to (b) and (c), so a net
nomic application of the two types of turbine, it is lengths are used to give m exl~austarea of 65-70 mi also invoived in the choice of design exhaust pres-
.
necessary to consider:
. pressures.
. available. rated output, whilst using seawater cooling. Howe improvement of cycle efficiency. The importance of
modern blading developments will enable the de lllc corresponding characteristic
efficiency in reducing the unit cost of electricity can
Available total turbine blade exhaust areas for full- of high speed machines with much larger exhai best be seen by examining its relation to other factors
areas, suitable for outputs in excess of 1000 MW. 191, nlrbiae heat rate with exhaust
speed turbines and the regions of outputs and ill I'il! 1.57, is obtained from the affecting cost. What matters most to the utility man-
condenser pressures where they are cconomically ager is the reduction of the total lifetime cost of the
11 iiilta relating to the turbine ex-
advantageous 111t%haflows and the heat rejected. plant (refer to Volume A for the full discussion).
The major concern of this chapter is the iifetime gen-
I' is tlscd liere with respect to the
4 Economics of the steam cycle i i l l i l 1hc::il rate. Economic factors are
eration costs of turbine-generator plant, which breaks
Half-speed turbines are economical only in circum-
stances where the largest outputs are combined with
very low condenser pressures, favouring the adoption
of larger exhaust areas than those which could be
4.1 Choice of exhaust pressure
The turbine efficiency depends, to a certain extet
.
down into:
Capital cost.
Fuel cost.
provided by currently available full-speed turbines
on the choice of turbine exhaust pressure. This ch
(see Fig 1.56). Even this region of economic appli- Operating and maintenance costs.
is based on both thermodynamic and economic groun
cation of the half-speed turbine is under threat from
the impending availability of full-speed machines with Following consideration of thermodynamic optimis
tion, the economic factors influencing the wh For a valid c o m ~ a r i s o n of new designs,
greater exhaust areas. - . all these
spectrum of turbine.generator plant optimisation cost elements musi be considered simultaneously at a
described. The form of economic study to per certain reference date, e.g., the commissioning date. The
Turbine-generator for the CEGB PWR selection of the turbine exhaust pressure, conden Capitai cost is conditioned by the timing of stage
The proposed station at Sizewell B will incorporate
a single 3425 MW (thermal) PWR of a four-loop
design. The NSSS will provide steam to two full-
speed turbine-generators, each with a gross output of
and cooling water parameters is then given.
4.1.1 T h e r m o d y n a m i c optimisation
/ payments and the interest rates predicted over the
construction period. Similar considerations a .. o ~.l vto
the Fuel cost and Operoting/Maintenance costs, with
interest rates being the determining factor. To enable a
The power developed by a steam turbine suppl'
622.5 MW. 6 7 8 9 1 0 comparison between plant of different ratings, these
with a constant mass flow rate varies on the exha
The current turbine design incorporates a means kXI4AUSI PRESSURE costs are expressed as a Capital cost factor, measured
pressure changes for the following reasons: l"P5lli)~ExHnusrrRsssunE
of isolation of the steam supply to enable main- in f/kW.
tenance work to be performed o n one machine whilst (a) As the exhaust pressure is reduced, the isentro The Capital cost comprises not only the cost of
continuing to operate the other. This means of iso- heat d r o ~across the last stage increases and the turbine-generator itself, but also the costs of the
lation will improve generating availability. additional work is done in the turbine. I,"! licul rate cllaiacieristic turbine hall to house it and the services required.
The steam turbine Chapter 1 Economics of the steain cyclc
.
?,.
\
The historicai trend has been to larger, higher output 4.1.3 Economic opt-imisation of exhaust -$
r $lit iiiliiiitil,, casts are: A sitc study is undertaken to obtain thc iempcra..
plant of compact design, which has had a considcr- pressure, c o n d e n s e r a n d CW s y s t e m ,$ t u x of Llie water sourcc over a !period of a year, so
u p to now we liave colisidered the design ,$ a !I". cils! oc additional pumping power (this will that an estimate o f tile average annual CW inlei
able impact on reducing the Capital cost factor. The
practical problems of transport and assembly indicale
diminishing returns in this trend, which suggest that
fhe turbine. The economic a~timisation is highly
~~~~ ~~
CML1NEWATlllrlWIUIW
The capital cost of the turbine and of the buil NUMBEllOlTUBES
VaRIAaLs
ing to house it (this will vary if longer last-stage
\ FUEL
COSTBIW
blades or a different number of turbine cylinders t
are chosen). FIG. 1.62 Relationship between hear transfer parameters
42 43
The steain turbine Chapter 1 Economics of the steam cyc:iv
s Incieineots of CW l'iow wili affect CW puolp costs quite possible that these wiii not be used, becaosc \!I< lpioduce a range of CW iiilct temperature of bc shown by comparing lire lrcal laic (kJ/kWii) ot
there are Surtliei coiistiainls on the desigir yet to bc liriwecii 5-17"C, corresponding lo a variation fioni modern large capacity turbine-gcneialor planl, i n
s Increments of CU' fro\\, will afScct CU' systcni casts considered. i l i , . irleal turbine exhaust pressure of i 15 mbar. This volvirig seven stages of beating, with a hypothetical
r Increments of coridcnser surface wili affect con-
The most significa~~i consiiaints, after thc turbine i.<ii~idbe responsible for a change in turbine efficiency -
nlant of eauivalcnt electrical eelieratinc
. canacitv,
. . brii
exhaust area and condenser lcngth previously men- (11 around 0.7°/0. without feedheating plant. Thc comparison is made
de~isercosts.
tioned, arc the limits on CW velocity. There is a 11 cannot bc assumed, either, that all the condenser with the assuxnntions that the cyiindeis of a muiti-
0 Changes in output wili affect the running costs maximum velocity permissible to prevent tube erosion li$bcs will bc operational throughout the lifetime of cylinder tandem turbine have the capacity to pass
and a minimum velocity to avoid silting. Environ- 111c condenser. Material too small to be trapped by the total quantity of steam sul)plied by the boiler,
e Increments of CW flow and head will affect the mental considerations enforce a limit on the maximum Ihc screens may build up in the tubes, restrict the that the exhaust pressure is identical, that the 'leav-
consumed CW pump power and will therefore af- temperature of the C W discharge into the river or sea I'io\\, and eventually block it entirely (known as fouling). ing loss' is identical and that the condensate from
fect the running costs. so that fishing is not affected. 'The problem can be alleviated either by regular main- the turbine condensers is pumped, as feedwater t o
The exercise can be repeated with one of the fixed lcilance or through the provision of automatic cleaning the boiler, a t a typical condensate temperature o f
parameters changed t o a new value. In this way, the by circulating foam rubber balls that clean away the 35°C (for a temperate climate plant).
If the individual costs are calculated for the grid of change in costs using different exhaust annulus areas dIr.1 and scale formation. The effects of erosion at The difference in 'heat rate' of the two turbine
points on Fig 1.62 and then summatcd to give the can be found. A similar analysis can be undertaken for lllc higher velocities can be practically eliminated by plants is found t o be significant, the heat rate o f the
total cost at each point, wc can plot contours of a tower-cooled system, where CW is cycled between llir use of hard materials such as Titanium for the plant equipped with the seven-stage regenerative plant
constant cost, as shown in Fig 1.63. the condenser (where it receives heat from the steam), coi~denser tubes. Changes in tube material and in being only 0.86 of the hypothetical plant of equivalent
Computer programs have been devised which will and the cooling tower where it transfers the heat to loilling factor, arc evaluated during the design to capacity but without feedheating plant.
evaluate the best design combination of parameters the rising air. (For a full explanation of the 'indirect confirm the mosl economic choice for the full range A full treatment of the economic benefit of the
for minimum total cost and Fig 1.63 is a typical cooling' system see Chapter 4.) of operating conditions. turbine plant with feedheating would involve consi-
graphical output. From Fig 1.63 it can be seen that The economic optimisation calculations are based deration of a boilcr plant designed for a high feed-
the smaller the contour, the lower the total cost. The on a constant CW inlet temperature and the assump- water temperature and a hypothetical boiler design
most economic design parameters therefore exist at tion that all the condenser tubes will bc available. In suitable for feedwatcr delivered to it at condenser
the centre of the smallcst contour. It is, hawevcr, reality, the seasonal changes in temperature in the temperature, but the figure 0.86 provides a goad
4.2 Regenerative feedheating measure of the improvement wrought by bled-steam-
'llic principle of 'preheating' boiler feedwater before heated feedwater plant and of its benefit in terms
I l k admission t o a boiler was well established before of reduced fuel consumption.
t l ~ cturn of the century. The expression ‘regenerative'
Il~ipliesthat latent heat in steam, or sensible heat in
boiler flue gases, is captured, reclaimed and set to 4.2.1 Feedheating plant s t a g e s - s u p e r h e a t
work again in the fluid cycle. cycles
Ihrly examples of feedheating involved the dis-
The optimum number of feedheating stages, in strict
ullikige of exhaust steam into the tanks from which
terms of cycle efficiency, could be as high as the
llic feed pumps draw their water and the use of
number of steam expansion stages in the associated
'~~i:o~iomisers', which captured heat from flue gas and
turbine cylinders. But it is not practical, in cnginecr-
lrd lo economy in the use of fuel.
ing terms, to provide steam extraction points at each
'The practice of preheating the boiler feedwater has
stage in the cylinders, because of the casting/casing
ci$~itiibutedas much to efficiency improvements as
complexity that would arise and the additional and
itliy other single development in steam power plant.
excessive length of the complete turbine, with cor-
In this section 'regenerative' feedwater heating plant
respondingly long rotors.
iising steam extracted from the turbine is covered;
As with most engineering designs, a compromise
ieedheating plant involving the 'economiser' is dis-
between the academic optimum design and a design
cussed and described in Volume B.
which is practical; producible and commercially viable
From the early days of utilising latent heat from
is necessary.
lhe exhaust steam from steam eneines - and small tur- The type of power plant with which the turbine
bllles to preheat feedwater, the principle of feedwater
plant is associated also influences the number of feed-
heating has been progressively widened; modern ~ l a n t
heating stages because the steam-raising plant eco-
I b very sophisticated, involving multiple steam ex-
nomics interact with the turbine plant.
Iraclions from steam turbine cylinders, L P heaters,
For electricity generation in the UK, the following
combined heating/de-aerating plant, H P heaters, L P
steam-raising plant sources have featured in recent
rlrains pumps, H P drains pumps, pressure cascading
years:
111 drains and the incorporation of other plant, such
tua moisture separator/reheaters. which are used in
u'et steam cycles.
The academic treatment of regeneratve feedwater
CWI#NGW"llrlFLOl"PATIII9~S heating and its place within the cycle was covered
in Section 3.1 of this chapter and illustrated by Advanced gas-cooled reactors (AGRs).
Ikankine cycle diagrams. The impact of feedwater
RO. 1.63 Effect of cost Iheating plant upon the turbine cycle efficiency can Pressurised water reactors (PWRs)
The steam turbine Chapter 1 Economics of the steam CYL~C
Coal-fired and oi1:fired pla,ils yield similar numbcis slightly diffcrcnt systems, such as eithcr one or two
of fcedhcating stages as optimum, about three LP entiactioo poinis oil a boiler fecd pump turbinc, will?
stages, a heating/dc-aerating stage and two H P stages, a corresponding number of HP fcedwater ileaIel.s,
leading to a final fcedwater ternpclratol.e of about depending on their manufacturing costs and their
250°C. relationship to the then prevailing worih of cycle
An optimisatior~ technique is used to determine efficiency. The finai H P feedwater heater has, in every
the number of feedwater heaters, with practicalities case, used steam exhausted from the H P cylinder of
still dominating. the main turbine (i.c., the same point in the cycle as
In a world of changing economics in the field o f the supply to the feed pump turbine).
fuel supply, at1 upset in prices, upward or downward, For large capacity plant, HP feedwafer healers of
such as experienced with oil supply prices can lead the 'tubeplate' type (as illustrated later in Fig 1.691,
to a significant difference in turbine and turbine plant cannot be made sufficiently large to perform the
configuration. It is necessary at the inception of a entire feedheating plant stage duty because o f manu-
power station project to revalue cycle efficiency in facturing limitations. These limitations involve tube
the light of prevaiiing fuel prices and best predictions. plate diameter and thickness and tube hole drilling
AGR planrs are found to bc most economic with a length.
moderate final feedwater temperature of about 150". The provision of heaters in pairs has proved ne-
This is because the lower temperature produces a cessary at each heating stage to permit the stage duty
wider 'approach tcmpcratore' ta the reactor coolant to be performed. Each 'line' (or bank, or 'string')
gas, and a greater 'log mean temperature difference' o f heaters can be by-passed in the event of a fault
(LMTD) for the steam generators associated with the to permit continuity of feedwater flow to the boiler.
reactor. This wider LMTD, produced by the feed- The heat transfer surface area for heaters (of all
water temperature of 15O0C, is beneficial in that the types), and therefore the overall size of the heater,
steam generators, encompassed within the concrete is carefully optimised. The optimisation involves manu-
pressure vessel with the reactor, can be smaller, so facturing cost versus the lifetime value of efficiency
the pressure vessel is smaller and lower in capital based on fuel cost and the predicted utilisation for
cost. the type of plant.
The final feedwater temperature is 'optimised' - For relatively high fuel cost applications, an ad-
i.e., the value o f cycle efficiency, costed at a rate ditional heat transfer section is incorporated in heaters
appropriate to the use o f nuclear fuel over the life as a 'drains cooling' section. The condensate of the
of the plant, is related to the capital cost variations heating steam is cooled to a temperature lower than
of steam generators, etc. The lowest sum of lifetime saturation temperature by the ingoing feedwater, there-
operating cost and capital cost determines the op- by increasing the effectiveness of the heater in the
timum design, which includes the corresponding final cycle.
feedwater temperature as a design parameter. Further features of feedheating plant - and suitable
The outcome of this AGR plant optimisation is for any type of main plant - are those of 'pressure
that three LP feedwater heaters are used, in con- cascading' and 'drains pumping'. Heating steam, after
junction with a fourth combined heating and de- being condensed in a heater, is led, as drains, to a
aerating stage, to provide a final feedwater temperature lower pressure heater where it 'flashes-off' and sur-
of about 150°C to the complete exclusion o f H P renders part of its remaining heat to the lower pressure
feedwater heaters. The boiler feed pumps draw their heater. This principle can be applied to all heaters
supply of water from an elevated tank, forming the in a bank as a 'cascade'.
combined heating and de-aerating stage, and deliver Drains pumping involves collecting drains after
the water directly to the 'economiser' section o f the cascading and pumping them back into the condensate
reactor steam generators. feed system at a point that closely corresponds to
Economic systems evolved during the past two their temperature. Figure 1.65 illustrates both cascad-
decades for both fossil-fired and AGR plants involved ing and pumping for the two L P heaters.
'back-pressure furbines'(driving the boiler feed pump),
with one or two steam extraction ooints for H P feed-
water heaters.
4.2.2 Feedheating plant s t a g e s - wet s t e a m
The driving steam for the boiler feed pump turbine
cycle
is taken from the exhaust of the H P cilinder of the
main turbine, and is therefore steam which has been A PWR station is now under construction in the UK,
expanded and has lost part of its superheat (Fig 1.64). based upon a standard design for large capacity plant
Steam extracted from the boiler feed pump turbine (1200, 1300 MW). This design, designated 'Standard
is therefore relatively low in superheat and the heat Nuclear Unit Power Plant System' has a feedheating
to be surrendered to the feedwater is mainly the latent plant involving L P heaters, a de-aerator/heater and
heat which is beneficial to cycle efficiency. H P heaters but with certain variations arising from
Various main plant manufacturers have evolved the wet steam cycle of the PWR.
T h e steam turbine Chapter 1 Economics of tlie s t e a m cyciii
..
Steam admittcd to tlic H P cylinder of thc turbine is sccovcicd and introduced into thc H P fccdwalei lii, t,!c:lc inuolucs four stages of 1.P fcedheating, o f typically 5 pg (of oxygen) per kg (of water), i . c ,
is at a dry saturated condition, i.e., without superireat, heate1.s at appropsiatc temperature points in the cycle. riix i:i :ici:iioi/lieater and thl-ec stages o r I-1P feed- five parts per billion.
On expansion thrauglr tlie cylinder, tlie steam bc- The PWR steam generators liave a continuous I i i ~ ! ~ i i t i i i~i,i l i i ail ultiinatc heater utilising condensate Desigii piacticc has bcen lo iilslall lligli level plant
comes wet. The water fraction is removed in a passivc 'blowdown' system to limit the concentsation of slight liiiiii l i i v secondary reheatei to preheat thc feed to in an auxiliary plant annexe between the boiler house
'moisture separator' and the water and its heat is impurities in the steam generators. The 'blowdown' fi l i i i ~ i ~ r ~ iof ~ i 226°C
~ ~ r u before admission to the steam and tuibinc hall, at a level set by boiler house steel-
reclaimed and pumped into the fccdheating system at water, at a temperature approximating to boiler satura- ~ ~ V ~ ! W ~ , ~ I ~ ~ I S . work. l'ro\,ision of generous margins over the steady
the de-aerator (where separator water temperature tion temperature, is passed through a heat exchanger state NPSH iequiremeols of suction stage feed pumps
and de-aerator temperature coincide) for maximum incorporated in the LP fecdheating plant upstream of has oroved oossible.
efficiency (Fig. 1.65). Thc dried steam is then passed the de-aerator/heater, where the heat is recovered. 2 2 1,medwater de-aeration
~~
Typically, tanks have had a total volume equal to
through two-stage reheaters for superhcating, steam Condensate, formed from bled-steam extracted from about ten minutes feedwater flow rate, with an eight
jiiuitwlller chemistry requirements are stringent with
being the heating medium. Steam bled from the HP the LP turbines and supplied to LP feedwater heaters, minute store to provide a buffer for transients and time
Wpiiil lo lllc permissible level of dissolved oxygen.
cylinder is used in the primary reheatei- and live steam is collected in a drains receiver and pumped into the t o unload the plant should the condenser extraction
l'hc rrluill concern is that of minimising waterside
(i.e., at boiler conditions) is used in the secondary de-aerator/heater tank for recovery of both condensate pumps fail. The mass of water stored is about half a
Vi?l'iriiioii o i boiler tubes. Waterside corrosion and
reheatei. Condensate formed from the rehearing steam and heat. Iliailllc i:orl-osion lead to thinning of tube walls and tonne per megawatt of plant capacity (i.e., about
Iiir ~~t!hrvql~ent risk of rupture by the internal fluid 330 t for current 660 MW plant).
iilakiii! c In summary, this type o f combined plant, which
"".
A il,~lliflca,lt
% ' , ' feature of British designed is described in detail in Chapter 3, fulfils important
(iitilil bccn the combined 'feedheating/de-aerating/
liila
primary functions:
* f i l ? i hiorage plant'. This is illustrated in Fig 1.64
WI!ii'ii i~lhowsthe ~ o s i t i o nof the de-aeratine/feedheatine
j#lrit! wiiliin typical turbine plant and Fig 1.66 is a
alli!jili. lil~~stiation
f~~wlI~~:n~lit~,~, ..inlant,
of a typical high level de-aerating/
~~ ~~~~
-
----Y*,Nn~WI"sPU
-e e ~ r m n~ mc ~
--- ~~~WY,e~ONIII*LT8
D%,WS
FIG. 1.65 Simplified feedwater heater arrangement for a PWR FIG. 1.66 Typical high level de-aeratoilfeedheatei
T h e s w a m turbine Chap Economics of the steam cycic
Keliable and effective service over sevcral decades has British practice l o r tlic stedin supply to the bn 11, 'rl'ill' iiilo tile crossover jpipe. If a for heating tire condensate, with consequentiai in)-
been obtained from plant of the designs described, fced pump turbine has been, as caplaioed earlier, 1 : I , I deficiency is supplied provement in cycle efficiency. Bled-steam valves are
but changing cconon~icsand competitiveness lrdve now use steam partly expanded through and exhausted I'l-0 I ' rlossovrr, at the same pressure but omitted - both the traditional isolating valve and
icd to a change in design. the H P cylinder of the main turbine (sometimes kno\ the non-return valve. It has been established by cx-
The design illustrated in Fig 1.67 invoives the as 'cold reheat deorn'). This steam, after furthei li11i1)il.~viieretlie heatei./de-aerator 'floats' periment and experience that steam refiux on turbine
direct injection of steam into the body of stored pansion thiough the boiler feed pump turbine, cont I p u m p turbine exhausi and the trip, when the stage pressure collapses to condenser
water through a series of vertical perforated tubes oniy a modest amount of superheat and this exlial literconnected piping, has proved pressure, is negligible and hence there is no significant
immersed in the waier, and the admission o f con- steam is used to supply the combined feedheatin feed pump turbine is unavail- contribution to rotor overspeed.
densate through self-regulating sprays. The condensate de-aerating plant. hy elcctric pumps are used, the heater/ With the heaters being almost completely within the
is heated almost t o saturation temperature; steam Because the steam requirement of the boiler fc supplied entirely from the I P / L P condenser 'neck', there is economy in turbine hall area
rises through the water and gases are liberated and pump turbine cannot be exactly matched to I lion can continue unimpaired. Such and in the elimination of supporting steelwork, access
conducted away through small vents adjacent t o the steam requirement of the feedheating/de-aerating 1118 ioo is advantageous and removes ladders and platforms.
sprays. throughout the load range, arrangements are necess o f one plant item upon another. The omission of an isolating steam valve prompted
The water passes at low velocity through the tank t o pass any excess steam, or t o supply any stc a steam turbine drive for the the development of improved methods of prevent-
at a rate corresponding to the plant load and is deficiency from another part of the cycle. Ilc economic benefits and the flexibiiity ing heater flooding. Neck heaters arc equipped with
almost at saturation temperature. The remaining dis- An effective means of accomplishing these reql iliril hyslcm are clear. If boiler feed pump valveless primary drains and a valveless secondary
solved gases arc liberated: they rise to the surface ments is to design the boiler feed pump t o exhaust ~lred,tllc system described above would drain, the latter being arranged physically a little higher
and steam space and are then conducted away through a pressure approximately equal t o the pressure of I i ~Ulll~ly from the main turbine only. than the primary drain outlet.
small vents, the water being brought up t o saturation main turbine IP cylinder exhaust. This exhaust sle External L P heaters, although still of the traditional
temperature by the injected steam. This design and is supplied to the L P cylinders and the boiler fc form, are now arranged in a horizontal attitude, elevated
pump turbine exhaust, the heater/de-aerator and t ~ r r r ~ u rfeedwater
e heaters
its function arc covered fully in Chapter 3. so that the bled-steam piping from the turbine falls
For thermodynamic economy, the bled-steam used main turbine IP/LP crossover pipes are connect (1.1') feedwater heaters are basically to the heaters, thus assuring drainage. This minimises
in the de-aerator should ideally be without superheat - together. ir!r'~ll.d 'tube and shell' heat exchangers, the risk of water entering the cylinder and the possi-
the use o f superheat is a wasteful way of heating water The steam pipcwork is arranged so that, du Ilailte I)assing through the tubes and bility of damage by impact o n rotating components.
when it could be more effectively used by being con- piant operation, the fced pump turbine exhaust stet Ibcinl! admitted t o the shell. This type The heaters are 'stacked', so that the ultimate
verted t o mechanical work in a turbinc. is preferentially used by the heater/de-aerator, w 111lpcdvcrlically, has been used for many L P heater can drain its bled-steam condellsate into
le'o ildvaaces worthy of note have been the next heater, and that heater can drain its con-
II ycllrs and are now treated as modern densate into the condenser above the working level
The steam turbine Chapter I Econoinics of the steam cycli:
,.
I\ b~;iriation on the traditionai design o f l i p lheater al.c;!s and increased tinit rating, serve la reduce capbiai
2
Q irlil; ils thick ihemisl,heiicai prcssul-e iiead, luheplate and operating costs arid arc therefore beneficial lo
".
@ b
E
0
8,
%L $
l i i , d sledni shell, is a design based o n boiler tech-
tiiili)l:!' in which inlcl/outlet headers and serpentine
lt~iics arc all contained within a steam shell, as il-
the consumers.
generator unit output can be maintaincd with the As the powcr reqilii.e~lle~li
o f a boilex feed pump psouisioii necessary [or 50% eiectric fecd pumgs, wiiicll
loss of one main duty fccd piiml~. This ensures ti)! a typical 500 MW unii is approximately 10 MW, includes eqilivaie~ll bled-steam pipework for tiic HI'
inaxiillum plant availability. i t can be seen that the clioicc of an economic and beater alone, 11lus elcct~icmotors (including reinforce-
For the majority of 500 and 660 MW units, thc leci~nicallyacceptable variable-speed boiler feed pump ment of tlie station electrical system to cope with thc
most economic solution has been a 100% duty steam iliive is a decision of major importance. The possible high motor-starting currents). Also, the first option
tuibine-driven feed pump with two x 50% electric lyiies of boiler feed pump val-iable-speed drives which usually includes a live steam connection direct from
motor-driven start/standby sets (higher capital costs ii;ii,c been considered by the CEGB for use on large the boiler to the feed pump turbine for operational
but lower running costs than ail-electric pumps). puneraling units arc: flexibility, even though the electric pumps are aften
The situation is now changing for units over 660 used for starting. The live steam pipework is expensive,
e I'ixed-speed electric motor with variable-speed
MW in that the saving in capital costs of having due to its high pressure duty.
150% (three x 50%) feed pump capacity compared coupling.
There is usually no extra capital cost attributable
with ZOO%, begins to outweigh the increased com- D Converter-fed variable-speed (electric) motor (VSM). to the required increase in rating of the main IP/LP
plication o f having two pumps running in parallel turbines and the generator needed to supply the extra
for full-load operation. Other advantages of having e Back pressure steam turbine power for electric motor-driven feed pumps, since it
three idcnticai 50% duty pumps include reduced requires only a marginal increase in steam flaw (3%)
spares holdings, quicker maintenance, modular con- r ('ondensing steam turbine of the main unit.
struction with a more compact layout occupying less With all-electric feed pumps, the system is more
station floorspace, and less complex and expensive compact (less floorspacc) and simpler, needing fewer
pipework. I I I addition to these choices, the option of slipring spares holdings. Because the pumps are frecd from
Feed pump size has more recentiy been influenced ilidtiction motor, regulated by resistance in the rotor
tile constraints of steam pipework they can be placed
.by two other factors: cllcuit, has been considered and used in the past.
in the ideal position for NPSH considerations, on
lliis relatively cheap and simple solution, using large
the basement floor (instead o f a few metres above
international market appeal - 50% duty pumps llitiiiil rheostats with mechanically-movable tapping
I,oiiirs, has proved unreliable in practice, with a high it to accommodate the steam inlet pipework below
for large (over 660 MW) units have the greatest
l~~iiiiitenance burden. tile pumps) directly beneath the de-aerator (NPSH is
worldwide market potential, whereas 100% duty
defined in Chapter 4 and de-aerator height, etc., is
pumps would require new pumps to be designed that the boiler is designed, and also to allow for a & i'ariable-speed electric motors and condensing steam
discussed in Chapter 3). These factors can lead to
50% duty pumps means that no variable-speed wear and transient conditions, and to act as an op- fj Flu. These two types of drive are not feasible for
motors or couplings large enough for 100% duty erational margin. 8 IIPr with the higher speed 'Advanced Class' pumps Running costs
have yet been developed. At the value of fecd flow corresponding to the $ Ilacd on 500 and 660 MW units so far, due to con- A steady state model of the thermal performance of
turbine design quantity, the head produced by the g \'CIIPI size limitations and blade vibration and stressing tile turbine and fecdheating/pumping plant can be
pump is in excess of that required to pump the water ~llil'ici~ltics. incorporated in a computer simulation program. Such
to the boiler. This excess pressure can be minimised f
4.3.2 Feed p u m p duty, margins, a n d t h e need
f o r variable s p e e d
The duty of the boiler feed pump as determined by
if the pump can bc driven at reduced speed: if this
is not possible the excess pressure has to be broken E,
1, /\ technical description of electric motor drives
h'r~iinble-speed,induction, synchronous, etc.) for feed
I~Iltili)sis given in Volume D. A description of the
a program can then be used to compare overall cy-
cle efficiencies (it calculates the cycle heat rate) for
different input data and can be used to compare the
the boiler and turbine pressure flow conditions, is down across the feedwater regulating valve. As can E II*V o f steam turbines for driving feed pumps can thermodynamic effects on the overall cycle of steam
given by Fig 1.71. Shown on the diagram are the be seen from Fig 1.71, at low values of feed flow, 'g I!,, found in Section 9 of this chapter. turbine-driven and electric motor-driven feed pumps.
boiler feed-pump characteristics, i s . , the relation-
ships between the head produced by the boiler feed
pump corresponding to the particular value o f feed
the excess of head produced by the pump over the %
system resistance head is considerable. On typical
British sets of 500 MW and over, variable-speed drive -$
1 d,9.9 Economic comparison of s t e a m turbine
Figure 1.72 illustrates these thermodynamic effects
graphically for a fixed 900 MW sent-out (SO) unit
with a fixed main turbine exhaust area and pressure,
flow pumped, and the boiler feed pump speed. Various is always adopted because the cost of providing it is dllvus w i t h electric m o t o r drives for 50% feed pumps. Also shown, is an example
head/flow characteristics corresponding to the operat- much less than the operational and financial losses calculation to determine the additional work done
ing range o f pump speeds are indicated. The curve that would be incurred by this breakdown of pres- in the main turbine due to changing from a back-
sure. In addition to this, all conventional plant is I%/,i,iro/ costs
denoted as 'system resistance' is the relationship pressure feed-pump-turbine drive to a n electric-motor
between feedwater flow and the head that has to required to be capable of two-shift operation, i.e., i)ll the majority of 500 and 660 MW units, a variable- drive. This calculation is continued in Fig 1.73, where
be produced by the boiler feed pump to pump the to be shutdown overnight and started in the morning. ~pcl'ddrive to the 100% duty feed pump is provided the additional work done in the main turbine due to
feedwater into the boiler. Also shown in the dia- During an overnight shutdown the boiler pressure Iby ti back pressure steam turbine, using bled-steam nor having steam turbine driven pumps is compared
gram are the design values of feedwater flow for the falls significantly, such that during the start-up period Iloni tile main turbine H P cylinder exhaust and ex- with the electrical power used (and associated gen-
turbine plant, boiler plant and the feed pump itself. next morning, the boiler feed pump is only required Ilnllhling to the main IP/LP crossover. Bled-steam erator, transformer, cabling, motor, gears and converter
It is normal practice to design the boiler to pro- to deliver some 100-2043 bar instead of the approxi- li~ppingson the feed pump turbine itself have been or fluid-coupling losses) to drive the motor-driven
duce a higher rate of steam generation than that mate 230 bar closed-valve full-speed pressure o f the tlkerl in the past to supply steam to one or more pumps. It can be seen that in this case, which is for
appropriate to the value used in the turbine-generator pump. For this reason, the pump that is used during klaDcr of H P feedheaters. a back-pressure feed pump turbine with no bled-
design. This margin is normally about 5 % and is the start-up period should have a speed range down !,ti, large modern units (over 660 MW), the capital steam tappings to H P heaters (for a future 900 MW
intended to cover application variations (e.g., site to approximately 70% full speed to avoid excessive k'tlata of the extra bled-steam pipework and the boiler unit), there is a unit heat rate improvement with
conditions such as available cooling water) at the time IBGd PUIIIP turbine are significantly greater than the electric motor-driven feed pumps.
55
Tile steam turbine Chapter 1 Economics of the stealri i:yclr:
..
Ill' exhaust, and is therefore a lower grade o f speed, has a soft-start capability (oniy 1.5 times against
r l than that used for the back pressure turbine, 4.5 times full-load current) which salves the station
lllc steam is exhausted to the feed pump turbine's electrical system problems.
condenser o r to the main condenser. This has
'vantage of reducing the steam flow (and hence
loss) through the main LP turbine, or of Running rosrs
18 its required exhaust area.
In addition to the flow and head margins applied
SPECIFIC ENTROPY, ~JI~QK ;I3 operating data demonstrates that feed pumps
to the feed pu,np (and hence to the drive, that
licilicve the same availability figure regardless of
been described, clcaric motor drives are cur.
A ADDITIONAL HEAT SUPPLiED IN REHEATER (if dl.iver. Hence the savings in overall CEGB
=62.g (3588.2-31232) = 2924MW = 1 49°/0TOTAL HEAT SUPPLIED to be able to give their rated
. I I I rlilming costs froin the higher feed pump system
output at a eicctrical system frequency of
(3 ADDITIONALWORK DONE IN IP TURBINE i i i l i l i l i i ~of a 100% steam and two x 50% electric
=62g (3588.2 .29735) = 38.65MW = 4,29°10 TOTAL POWEROUTPUT 49,5 Hz so, at the operating condition of
i l>llws, colnpared with three x 50% electric
C ADDITIONAL WORK DONE IN LPTURBINE Hz, is again a margin to be
Iiilln~s,are not significant. (Typical feed pump
(DUETO DIVERGENTCONSTANT PRESSURE LINES) for, in this case by VSM converter or by cou.
=62.g (785.4 .689.8) 0.852 = 4 . 4 4 ~= 0.48NTOTAL
~ POWER OUTPUT 1 availabilities would be 99.96% compared with
(DUETO REDUCED WETNESS LOSS) = 0.22% TOTAL POWER OUTPUT piing slip, Hence, the normal duty point for the feed
pump drive has significantly less power output than
MW TOTAL
HEAT SUPPLIED its 100% rated output. Figure 1.74 compares the
MW GENERATED MW SENTOUT (BOILER 8 REHEATER) kgbTSV overall efficiencies of VSM and motors with fluid
BASIS: Economic c o m p a r i s o n of variable-speed couplings, for decreasing pump outputs. Even at the
1 BACK PRESSURE BFPT 900 900 1962.4 772.0
2 INDUCTION MOTOR 925 900 1954.2 757.5 r &%MI drive with induction m o t o r plus normai duty point, the advantage of VSM drive can
3 VARIABLE SPEED MOTOR 923.5 900 195j.o 756.3 clearly be seen, and the difference in efficiency affects
station lifetime costs signficantly. This difference at
the duty point is mainly due to two factors:
F,C. 3.72 ~ h ~ ~ ~ ~ o d y effects e the change to inotor-driven feed PulnPs
n a m i of
Fluid coupling slip - it is an inherent feature
lllc presently preferred auxiliary electrical system
of fluid.drive designs that there is still some slip
illlie of 1'1 kV, the direct on-line starting of squirrel-
'''duction the input and output turbine,
for 50Vo duty feed pumps On
even at their rated output, which creates losses in
=he back pressure turbine option considered above problems have occurred with this type o f ~iiodernunits (900 MW and over) would involve
form of heat in the working fluid (removed
.
has no bled.steam tappings for HP heaters because Overseas electricity utilities have tended to use c0 cvelopment o f quick-switching techniques not by coolers),
it has bee,, found [hat, in practice, the improvement densing turbines with their slower 'International fly available. The squirrel-cage motor and geared
they give to the overall cycle efficiency can be offset pumps because they can give a better overall lllic coupling gives the minimum first cost, but Gearbox losses - VSMs have the same advantage
by the effect of the main boiler feed pump availability cycle efficiency (heat rate). Steam is usually extracted lirect drive high speed synchronous motor (about as steam turbine drives in that they can drive
on ~p heater ALSO, feed system stability from the main turbine IP cylinder exhaust instead Of r/min), fed from a converter to give variable the high speed (high power) pressure stage pump
T h e sream turbine Ciiapter 1 Economics of the stearn cvcli.
/
Sizing of the by-pass system is based on the most
$
iiidilous duty, in this case the abilily to run-thiougl~ ,.
8 ti trip to house load. The H P by-pass size is usually
8 i.spressed as a percentage of the H P stop valve flow m-
@ at rated full-load conditions. T o cater for a load
f,
c t i o to h o s e l o a d the size of the b. . m will
t i
lii. given by:
.
turbine governing and interceptor valves to close pass, there will be a much higher flow through the
or some compromise between the two. tlcsign of other plant in a major way. To cater for
r a.~ i d i y . T o accommodate the reduction in steam
~
by-pass and the turbine exhaust pressure is consider-
flow. the boiler firing rate must be rapidly reduced 0,
. ~~
starts. the by-pass
.. may be used to bring the supply of spraywater on top of the maximum ably higher. Normally this value of exhaust pressure
to a minimum. On most boilers, with the possible the main and reheat steam temperatures to a posi- U P by-pass flow, it is necessary to increase the rat- would only be attained with a much higher flow
exce~tionof some oil-fired units, this involves a firing tive ,,,ismatch in order to minimise the time to In); of the condensate extraction pumps. through the turbine. The H P turbine is therefore
trin which necessitates a ourgine
- ~ - ? ~~~~ . operation for several inad ~. . i t .h i.navailable
~ ~ ~ stress
~.~~~~ ~ -
mareins The increased flow and high enthalpy of the by- operating with its efficiency considerably reduced and
hours prior to reloading. If a by-pass is supplied, a purs steam increases the size and cost of the con- in addition is producing some rotation'loss heating.
large proportion of the excess steam can be diverted In general, the by-pass provides for a smooth deliser significantly. Figure 1.77 shows how the A typical condition line for the H P turbine is shown
through the by-pass system. If necessary, the boiler warm-up of boiler components, including the re- iudditional heat load relates to the H P by-pass size. on the Mollier diagram in Fig 1.78.
F&ri
%(
*r g
$,+ The steam turbine Cliapler 1 Economics of the steam cyclc
..,,
&
up of the boiler and tu~.bine,11s economic impact is
most readily appreciated by considering the effect on
hot starts following an overnight shutdown. This is
the duty normally seen by a unit allocated to two-
shifting. Figures 1.79 (a) and (b) depict tlie diffei-
ences in unit start-up with and without the by-pass
in operation. The start-up time is roughly 15 minutes
less if the by-pass is used. The saving may be coil-
siderably more if the boiler/turbine is not a flexible
unit designed for two-shifting.
Depending on the intended duty of the plant, this
may represent a significant saving to lifetime costs.
There is also a small saving because, without a by-
pass, water would be lost through the superheated
vents as part of the standard start-up procedure. A
further advantage of the by-pass system for start-up
is that inexperienced operators are more easily able
to bring the steam conditions to appropriate values
before rolling-off the turbine. Against these advantages
must be set tlie cost and maintenance burden asso-
ciated with the supply of a by-pass system. In general,
a small capacity (35%) by-pass system is unlikely to be
iustified on the erounds of im~rovementof start-ur,
capability.
One notable exception is the once-through boiler,
where a substantial bypass flow is required for a
lengthy period during start-up. The CEGB AGR ma-
chines, which use a superheat steam cycle, are examples
of this. The AGR also needs to use the by-pass for a
lengthy period during shutdowns, particularly if the
reactor is to bc maintained at temperature in readiness
for the next start-up.
(d) I~ollawiiiga turbine trip or sliutdowo, lo maintain only i-eqilircs a by-pass capacity of 40% and is ac- Ii Turbine b l a d i n g mid blades need to be very robust, Tlie diapliragnl
the reactor and steam generators in a hot-standby complished williout discharge lo atmosphere. lhas the atlvantagc of a i-clatively S ~ R I I diameter a!
condition, ready for turbine restarting. Both condenscr and atmospheric sets of valves are llle stcam seal between diapliragin and rotor, hiit
required to open fast, particola!-ly for duties (b) and this labyrinth scal niusl be as good as possible to
(d). The opening time of approximately three seconds
L1 Impulse stages deal with ibc high pressure drop. Tlrc radial iabyrintll
A diagram of a typical by-pass system configuration
is shown in Fig 1.80. The main by-pass is through permits containment of tile steam pressure rise witll- seal ensures adequate insensitivity to axial dispiace-
six parallel sets of control valves into the three con- in the settings of the atmospheric valves for the 6.1.1 Moving b l a d e s - details a n d c o n s t r u c t i o n rnent between the rotor and the casing. A typical
denser sections. Valves I, 3 and 5 are niodulating reactor trip case. The valve closing rates are designed lli !lie impulse stage, invented by Professor Rateau, impulse stagc arrangement is shown in Fig 1.81.
valves used for all three functions but sized to be to protect the turbine and condenser in the event llic imajority of the lieat drop occurs in the station-
capable of performing the cooldown duty (c) on their of a system failure. A closure time of 5 seconds is itry blading and the driving force on the stagc arises
own. Valves 2, 4 and 6 are capable of being switched provided to protect against high condenser/turbine from the change in momentum o f the stcam across
open or closed and arc only used for duties (a), (b) exhaust pressures in the event of a condenser cooling llic tiloving blades. The impulse design possesses the
and (d). An additional dump t o atmosphere is also water failure. The effects o n other plant are similar itdvi~ntages o f compactness and comparative inscn-
provided for duty (d), sincc infrequent discharges t o those discussed for superheat plant and are taken hllivity t o blading clearance since little pressure drop
to atmosphere are permissible for short durations. into account In the design. Itikcs place over the moving blading. However, the
This reduces the duty on the condenser, permitting The provision of sufficient by-pass capacity t o liioving blades are subject to disturbances from the
considerable economies to be made. Thus, in the avoid tripping the reactor in the event of a turbine- Ilur/.le wakes, so resonance must be avoided and
evcnt of a turbine-generator trip, valves 1, 3 and 5 generator trip justifies the by-pass on economic grounds. rie;iln bending stresses must be kept low; also, sincc
are opened first, followed by valves 2, 4 and 6 and If the reactor were allowed to trip for a turbine l l ~ u~nomentunichange is relatively high, the moving
finally, if necessary, the atmospheric dump valve. problem lasting for perhaps only 30 minutes, there Irliides have t o be robust and tend to be heavy. It
For one reactor, the total capacity is arranged to be would be a severe availability penalty. I,. ihcl-efore regular practice to attacll the iadivid-
approximately 70% of the full MCR steam flow with The problems of implementing a by-pass system ll~llly manufactured blades to a wheel disc, often by
about 10% being accommodated by the atmospheric are addressed in Chapter 2. Thcse matters are proper- ,IlsildIe roots which engage with corresponding axial
dump valve. In association with further relief valve ly dealt with at the design stage and result in systems i l ~ ~ ~ o l d machined
ers on the whecl rim.
capacity in the reactor system, this permits a trip of which provide economic benefits by achieving better One or more protrusions arc left at the outer end
the total turbine-generator capacity. A reactor trip co-ordination between the turbine and boiler systems. 111 i l i ~ . moving blade. These pass through holes in a
ri,\,rrband which may in turn fit into a slot machined
Ill tlic outside of the blade: when these protrusions
nl tenons are formed into rivets, they keep the cover-
btisd in place. The coverband acts as a seal and braces
lllc blading t o reduce vibration. Each length of coves-
I)tlnd ties a short length of blades together and may
l i l t i t , tip to the next length or overlap, so that an
retleniely robust construction is created. Since a cer-
li3i11degree of reaction builds up towards the outer
!ll~i~iieterof all impulse blades, axial scaling fins arc
lur~iicd integral with the moving blade shroud or
~,o\'erband.
64
Tl?e sreain turbine Chapter i
Figure 1.82 shows the arrangcrneill of such a 'This type of blading was designed and developed b)
stage. 'The iiazzlcs, of the convergent-diverge~~t
type, Sir Charles Parsons and lends itself lo ecoi~omiczil
produce "cry high stearn kinetic cncigy, sonic of production of blades from standard rolled sections.
which is absorbed by the first raw of blades, the Only a sinall heat drop can be accommodated pci
remainder being deflected back by the slationa~y blade row, due to the comparatively high velocity
guide blades and used in the second row. Both moving ratio required for good efficiency; this means that a
blades and nozzles are machined froin tlie solid and large number of expansions are required. Steam ap-
are nccessaiily very robust. proaches the moving blades with a velocity that is
low and substantially axial in direction. Consequently,
the driving force applied to the moving blades arises
almost entirely from the reaction force of the steam
as it accelerates through the moving blades. The force
applied to the moving blades is thus fairly steady, witli
very little disturbance arising from the nozzle wakes
of the fixed blades, so fairly high bending stresses
can be employed in the moving blades without risk
of fatigue failure due to vibration.
Since the pressure drop across the fixed blades is
small, diaphragms are not required, but small tip
clearances are needed throughout the turbine to pre-
vent excessive leakage losses. This was achieved iii
earlier turbines by axial sealing and end-tightening.
With solidly-coupled shafts which expand either
side of a single thrust bearing and with multi-casing
arrangements, end-tightening is not feasible and a
compromise has to be reached between fine clearances
sure drop develops across the moving blades and
to reduce leakage and large clearances to accom-
the steam leaves the moving blades at a higher speed
modate differential exvansion when starting. - to offset the higher peripheral speed, enabling the
Modern reaction turbines generally employ a com-
steam to leave the blades with the minimum of swirl.
bination of axial and radial sealing at the stators and
The stage is designed to have a fairly low degree of
rotors, and for this purpose, the rotor blades are
reaction at the base and, since the pressure drop
provided at their outer edge with shrouds formed
across the fixed blades decreases in response to the
of sections integral with the blade (see Fig 1.83).
These mate with replaceable finned sealing segments
I Aerodynamic a n d mechanical c o n s t r a i n t s increasing pressure drop across the moving blades,
lti i.;iily machines, the last few low pressure moving reaction increases with blade hcight. The radial tcn-
in tlie casing. Fins formed on the inner diameter of
lilii~lc~ were of constant cross-section. Thc stl.ess in sion duc to centrifugal force and the aerodynamic
the fixed blades provide sealing at the rotor.
l l i i i l y p c o f biade increased quadratically from the effect o f change of steam flow resiilts in a highly-
Small reaction-type blades can be manufactured
!ip lo the base and attained its rnaxiinum ijaiue in twisted moving blade, having a robust low reaction
by cutting from rolled bar of the requisite profile
Iri~asitionfrom blade to root: this placed a re- section at the root and a slim high reaction sectioit
or machining from bar, while larger blades may be
ii:lio~l on the length of blade that could be used at at the tip, see Fig 1.85.
separately cold-rolled after which the root portion is
heated and forged. Blades may also be machined from iionous speed. Modern last-stage blades have a
envelope forgings o r produced by precision forging, so section which reduces exponentially with the
that the profile requires no further machining; this of the radius. The tensile stress due to centri- 5.3.2 Blade t i p restraint
is valuable where tough materials make machining ss is then virtually constant over the gl.eater The use of long blades and large blade chords in-
difficult. Final machining can also be awkward where I of the blade length and this has enabled blades volves an increase in pitch and this creates compli-
integral shrouds and root fixings interfere with the lo 940 mm long to be used on 3000 r/min cations in the various devices used to stiffen the
machine tool. T o facilitate manufacture, modern prac- blade assembly and dampen vibration. A coverband o r
FIG. 1.82 Velocity-coinpounded (Curtis) stage O n modern blading, the tip diameter is typically
tice is to braze together short groups of blades before lacing wire must behave as a beam spanning the blade
machining the circumferential serrations on the sides Iloul double the base diameter, so that at the mean, pitch in resisting centrifugal loading, and must also
of the roots, see Fig 1.84. The brazing also permits Ill? blade pitch, i.e., the circumferential distance be- accommodate the substantial circumferential strains
easier assembly. Groups of blades are fitted in the lwrcli adjacent blades, is about 1.5 times the pitch due to radial elastic extension of the blades and the
5.2 Reaction stages rotor or casing in circumferential grooves which have UI liiu base diameter. The peripheral speed is also tendency of the blade to untwist at speed.
corresponding circumferential serrations machined in 1.5 ti~nesas great as at the base and the effect of When lacing wires are used, they are usually of
their walls. The blades arc secured in the grooves lI11h increased blade speed is to change the direction the 'loose' type with circumferential restraint on only
5.2.1 Fixed a n d moving blades - details a n d by similarly serrated side-locking pieces cut from rolled at' 1!1c incident velocity of the steam relative to the one blade in each group,
- ~
and are free to move
ConstruCtion strip. A suitable stop plate at the half joint locates fr~<~\'iiig blade. The moving blade inlet angle is there- circumferentially in adjacent blades, centrifugal forces
Although called 'reaction', these stages in fact employ the fixed blades in the circumferential groove and l b t c set to line up with the direction of the incoming providing the necessary damving
. .throurh friction. Thc
equal degrees of impulse and reaction, resulting in prevents the blade segments from rotating due to iilci~ni flow and the moving blade section is also gaps between adjacent lacing wires can introduce
the fixed and moving blades being of identical section. torque reaction. c l ~ ~ ~ n g This
e d . reduces the outlet angle so that a pres- complications in vibration patterns on long blades
66 67
Turbi~tchiadin(>
2F--F
Zigzag spool rods shown in Fig 1.87 are frequently exhausting directly to vacuum. The net result was
incorporated in the tips of the last-stage L P blades that, without lengthening the blades of the last row,
of modern turbines. The spool rods provide no re- but by lengthening those of the previous row, the
leaving loss was appreciably reduced.
-
straint against circumferential exoansion or centri-
xK
fugaal untwist, but the reduced sections at the ends
of the rods are forced against the holes in the blades
by centrifugal action and the sliding friction provides
effective damping, minimising blade vibration and 5.4 Moving blade root attachments
high frequency flutter at the blade tip. The last-stage blades of large turbines develop centri-
fugal forces of hundreds of tonnes when running, tbilncllned
A recent variant to the spool rod is the ball-
jointed tip tie. The dumb-bell-shaped tie rod fits into
a fixed ball-shaped socket in one blade and into a
very efficient methods of attachment are therefore
needed.
Systems in use at present include rhombus fixings
I'IG. 1.67 Zigzag rpool roc1 lip-tier
i~
iclCurved
sliding ball socket in the next blade. In common with
the spool rods, centrifugal strains are not restrained in a peripheral slot, finger-shaped pinned fixing and close staggering o f the blade cascade and the
but the ball-joints provide more controlled damping straight or curved fir-tree roots. Fir-tree roots provide
and the evaluation of tie rod stressing is more re- a n excellent method of attachment, since they permit lhc shaft teeth. FIG. 1.88 Types of fir-tree roo,
A
stages ellsiil.es rigidity i n any typc of root fixing at to take into account the torque ieactioli 0x1 t l l c
$
synchronous speed but, contrary to thc fir-lrec root, rliapl~ragin.
tlic multifol-k pinned root provides a rigid fixing Ail keys have provision for adjustmcnt, so thal
when the macl~ine is statiannry. This enabics the correct aiignmeot of the diapliragms can bc achieved.
zero speed vibl-atioii characteristic of the blades t o A typical arrangemcnt of diaphragm support and
be confi~.medwith confidence and ensures a smooth location keys is shown in Fig 1.89.
unstepped spectrum of characteristics, as tile machine
is r u n up. Replacement of multiforked blades, how-
ever, involves further reaming of the securing pin 5.5.2 Radial s u p p o r t p a d s
holes. This is awkward in-siru and can only be carried
The provision of this system of kinematic support
out a limited number of times.
becomes progressively more difficult as the diameter of
the diaphragm increases. As the size of turbine has
increased, the basic concept of kinematic support has
been modified t o suit the circumstances.
5.5 D i a p h r a g m c o n s t r u c t i o n and support One alternative has been t o fit keys in both half-
diaphragms so that each is supported independently
at the horizontal joint. This arrangement requires that
5.5.1 Kinematic s u p p o r t there is a gap between the half-diaphragms for ex-
pansion, resulting in a steam leakage across the half
AIi diaphragms are dividcd at thc horizonlai joint
joint: it also requires more machining and fitting.
into two scmicircuiar halves l a permit assembly.
Thc difficulty in proxaiding kitiematic support for
Iliaphragms arc located in the turbine cylinder as
large diaphvagms occurs inainly in LP turbines, where
close as practical to the horizontal and vertical axes
the outer ring diameter is large. In the LP turbine,
of the machine, in order to reduce to a rninilnum
the differential temperature between diaphragm and
the effects of differential expansion. Particularly when
cylinder that has to be accommodated is much reduced.
the machine is small, the ioss in output arising from
This, together with the need t o provide some form
the internal ciearances can bc significant. It is for
of stop-plate for the top half-diaphragms, led to an
this reason that the practice developed of supporting
alternative arrangement where, in the running condition,
and guiding the diaphragms in the inner cylinder by
the top half-diaphragm is supported on the bottom
keys in each half. This method of iocation, which
half-diaphragm, which itself just rests in the recess
is known as kinematic support, is generally used on
in the cylinder. The clearance for differential expan-
current H P and IP turbines o f the disc and diaphragm
sion is achievcd by exact machining of the outer
type, and o n the early stages of L P turbincs.
diameter of the diaphragm.
The details of a kinematic support systenl are in-
A more practical arrangement is to machine a
flt~cnccd by the method of manufacture. As the
generous radial clearance between cylinder and dia-
adjacent surfaces of the cylinder and diaphragm are
phragm and to fit the haif-diaphragm with a nuinber The first four L P diaphragms are usually a welded
circular, the diaphragm has t o be supported on keys hli~iids fitted into grooves machined in half rings,
of radial support pads which are then dressed to construction, similar t o the H P and IP, with stainless
fitted into milled recesses in both cylinder and dia- wllirh may be machined from plate or may also be
obtain the required location of the half-diaphragm. steel blades, rims and centres. Later stages may have
phragm, as close to tile horizontal joint as practical. ci~st.The diaphragm half rings are then built up by
Differential steam pressure forces the diaphragm pre-machined biades cast into cast-iron inner and
Transverse location of the diaphragm is achieved by weirling the nozzles to the inner and outer half rings
outer rings against the downstream axial face of the outer rings. Cast iron enables optimum shapes of
keys o n tile verticai centreline fitted into milled key- lhc axial faces of the half rings. Castings in stain-
circumferential recess in the inner cylinder. T o prevent
ways. Adequate clearances are provided o n fitting the steel suffer from the formation of regions of steam passages t o be formed. These diaphragms may
the diaphragms seizing in this recess, and to permit
keys t o ensure freedom of movemetlt for differential n ferrite, particularly near the trailing edges o f also be cast as complete halves in stainless steei.
adjustment, small crushing pegs are fitted in the up. Very large modern last-stage L P diaphragms have
expansion. T o avoid steam leakage between the two (1 blades, and cracking near changes in section
stream face of the locating spigot. massive sections for the rims and centres and can be
halves o f the diaphragm, the top half sits o n the .ss cooling rates are very carefully controlkd. Also,
Temporary support pads may be fitted and adjusted
bottom half, and keys at the half-joint are arranged 81cc the welds penetrate only part way into the inner extremely heavy if made from solid castings. The rims
t o achieve the correct positioning of the diaphragm and centres are therefore sometimes fabricated from
in line with, and transverse to, the machine centreline. d outer half rings, a circumferential crack exists
in the cylinder. The packing bush radiai clearances
This iocates the top half-diaphragm axially and ra- fbe middle of the rings. Radial cracks also exist plate into semicircular hollow box sections. Weided
are bored to a charted size and checked with the
dially with the bottom half-diaphragm, and provides Iween each nozzle section where they butt against constructions are always heat treated t o remove iocked-
rotor in position. If necessary, the temporary pads in stresses and allowance must be made for distortion.
an effective steam seal. The keys o n the bottom half c another. These cracks weaken the assembly and
are adjusted t o optimise radial ciearances. When the
horizontal joint have to be sized t o take the weight II provide initiation points for fatigue crack propaga-
desired alignment has been obtained, the thickness
of the complete diaphragm. rn. Investigations are being carried out t o develop
of the temporary support pads is gauged and the final
T o enable the top half-diaphragm t o be retained sided diaphragms, using full-penetration electron
in the top half cylinder when it is raised, stopplates support pads ground t o size.
welding. This will largely avoid the problems 5.6 Blading m a t e r i a l s
are ~ r o v i d e d at the horizontal ioint o n e a c h ~ s i d e . tcrnal cracks or voids.
The diaphragm is located axially against a machined A more modern method of construction is to
recess in the cylinder which offers frictional resistance 5.5.3 Diaphragm c o n s t r u c t i o n ~ctrochemicaiiy machine each complete half ring 5.6.1 12% Cr s t e e l s
to the expansion of the diaphragm relative t o the H P and I P diaphragm nozzles may be individually I of a solid stainless steei blank, thus obviating Turbine blading alloys are chosen for their ability to
cylinder. When sizing the support keys, it is usual machined or cast and the inner and outer blade up- l e problems of welding and casting. provide properties particular t o the mechanical and
The steam turbine
ca\~irnnmental service u,liicli tlky must cndorc. One gcsatuic bladcs. Aii siccis of lliis type ieqiiive tlic irhiliancc but in01 as good as Sleiliic 6 , whicli is 'Tlic vibiaiioii clr;iiacteiistics of t u ~ b i n e iniicl~iix
o i thc first considerations of 1.i' biading, for exampic, addition of an nustcnite-forming clement to pl-eveol cc>i~iinoniy!ired as an erasion shicld on steci I,[' blades, as lnicasiised n,,clci- opciating condiliol~s, ;air
is the ability to rcsist cosiosion and scaling in fast.. the fol.m;itioo of ?ones o f delta ferrite in thc material. lilii<ii~ig. usually found to be cxtiemely complox and oiici,
flowing wct steam. This generally roles out low alioy Nickel is employed for this purpose but its conlenl 'i'lic yield sticrrgth o f a typical titanium alloy in quite different from tl~eoretical predictions. There
steel and blades are made froin either stainless steel is limited in ltigli temperature blades becaiisc liighci l11r anncaled condition is approxirnatcly 50% bettel~ are several reasons for this.
or titanium alloys. A sccond icqiiiicmenl Is adequatc percentage additions reduce creep strcngtli. T11e addi. l11ii11 standard 12% chromium stainless steel material, First, in spite of tlte advances in finite element
tensile strength to resist steady centrifugal and bcnd- lion of niobium to the 12% Cr Ma V steels increases sil<leven slightly superior to the Super 12% C r steels: computatio~i in recent years, the intricate geometry
ing stresses. Sucngth without ductility Is not desirabie; stress rupture strength and creep strength in the short I l l ? ductility is somewhat lcss, The fatigue strength of a blade, whlcli is denlanded for aerodynamic pes-
ductility is needed to accommodate stress peaks and term, but the strengthening effect falls off with time 01 iilanium alloy is, however, generally higher than farmance, makes it a very difficult component to
concentrations. Ductility aiso is needed to resist rub- so that the long term properties are no better than tltr 12% Cr stecls. analyse theoretically. Consequently, predictions for
bing, and, in the case of shrouded blades, t o permit those of the 12% Cs Mo V steels without niobium. 'Titanium alloy is not as readily forgeable as 12% the modes and freooencies of a sinale cantilevered
the peening of tenons to secure the shroud. Impact Typical British steels for high temperature blad- VI inaterials. The titanium alloy has to be forged at biade may not always be very accurate. Then, a second
strength is also necessary, since contact with foreign ing include FV 507, a ferritic casting alloy with good a lower temperature which means that more energy factor which compounds the problem, is the existence
objects is sudden. Water slugs can produce impact tensile and crecp properties combined with low thermal i b re~iuiredto forge a certain amount. Also, since all of muitiple interactions between each blade and all
loading. expansion, and Esshcte CKM 12 from British Steel, tlililliilln alloys are very activc chemically at high the other blades in the same stage due to coupling
Since most blade failures are due to fatigue, ade- a heat tieatabic martensitic 12% C i steel alloyed with I~~liipcratures, surface contamination is another pro- through the disc and shrouds or lacing wires linking
quate fatigue strength is a crucial property. The blades molybdenum and vanadium. Both tltese alloys havc I,Iclii encountered when forging. adjacent blades. These interactions lcad to the predic-
are under steady centrifugal stress while operating, good long term creep strength at temperatrives up hlnchining is possible, if slow speeds are used, tion of a muitiplicity of modes in the working fre-
and this must be incorporated into the fatigue strength t o 650°C. 1 ~ 1 1 1 :I propensity for cmbrittlement by contamination quency range, where for a single blade there are only
considerations. Since L P turbines can see wet 'aggres- The intermediate blades, wlticll are neither highly clld lack of heat penetration make welding difficult. two or three. Thc vibration of a fully-bladcd disc is
si\,e environments', the fatigue strengths upon which stressed nor very hot, can be made from 12% C r steels I I I L , ~gasI welding is the normal solutio!~ but this is therefore much Inlore complicated than is suggested
- are based must account for environmental
designs with leaner alloying content and lieat-tl-eatcd to the lltiie consuming and costly. by the characteristics of a single cantilever blade.
degradation. appropriate hardness. A typical steel is FV 448, an 'l'llc main problems of titanium are high cost and An individual blade, cantilevered at its root, has a
Material damping is also considered of high im- 11% Cr, 0.6% Mo, 0.25% V, 0 . 3 % Nb steel with good I!I,O~ vibration characteristics. The cost of titanium set of natural frequencies in the operating range which
portance. The vibratory stress devclopcd in a turbine creep resistance up to 550°C. ~ l l l l y is several times that of standard 12% C r blade arc classified in three groups: 'flap' modes, 'edgewise'
blade is inversely proportional to the damping. One The corrosion and scaling resistances of the latest I~li~lcl-ial and a row of titanium blades normally costs modes and torsion modes. The disc carrying a set of
of the reasons 12% Cr stalniess steels are so widely so-called 'Super 12% Cr' steeis are at least equal to l\so la three times that of a steel row. all factors such blades itself possesses several natural frequencies
used in blades is due t o their superior marcrial those of the simple 12% Cr steels and In many cases within the same range, each one of these being associated
damping. significantly better. General corrosion resistance In , material damping of titanium is very poor, with a mode mode shape having n nodal diameters
Notch sensitivity also affects fatigue response and, steam is better than the grades containing less than g from 10% t o 40% of that of 12% Cr blade (and possibly one or two nodal circles as well). The
since Stress concentrations are unavoidable, parti- 12% chromium: the ferritic grades are much lcss ' I. Thus there is a potential for higher vibratory complete bladed disc has a very large number of
culariy near the root, a low notch sensitivity is very prone to stress corrosion cracking than the austenitlc when opera tin^ the titanium blade a t o r near modes of vibration in the same frequency range, and
desirable for good blade life. Unfortunately, whereas steels. tarl~ilance.Also Young's Modulus of titanium is low each of thesc will constitute a unique mix of the
high tensile strength desirably Increases fatigue strength, Welding is considered the mast complicated fabri- brill, since the flexibility is relatively high, natural individual blade and disc modes. Some of thesc as-
it also increases notch sensitivity. cation process lor the Supcr 12% Cr steels because 111':iiirncies arc depressed and harmonics are more sembly modes will be identified as being 'prcdo-
The short blades in the H P turbine work at tem- of their high hardenability. The martensite formed t'ln\i'iIed in the running range. minantly disc' modes, while others will be Immediately
peratures near to the maximum steam temperature, in the weld metal and heat affected zone (HAZ) is 111 view o f the lower cost and imoroved ~ r o n e r t i e s associated with one of the biade cantilever modes,
so creep strcngth is vitally important in this region, hard and brittle and must be tempered. However, ril llir Super 12% Cr steels, it is'unlikel; that ti- in both cases by virtue of the iespectivc natural
with the amount of permissible creep usually restricted when temperature recommendations outlined by the iilli~ltiialloys will supersede tltese steels for L P mov- frequencies.
t o 0.2% deformation in 100 000 h. various producers of Super 12% C r steels are fol- blading on UK steam turbines in the near future. Other modes exist which are associated with tlrc
The conventional 12% C r steels have an ideal set lowed, welding does not present any unusuai problems. waver, because of its hlgh strength/weight ratio, fully-bladed wheel assembly and arc quite distinct from
of properties for turbine blading as long as the Information concerning production, constituents, ' Irn is used extensively for lacing wire and for disc or blade modes. When there is additional inter-
temperature does not exceed about 480°C. Austenitic properties and application of the Super 12% C r steels landing and shrouding. blade coupling provided by some form of shrouding
steels have been tried but, in general, have not been is given In [81. either at the tip or part-span, then most of the modcs
satisfactory, except for the short blades in the HP of the complete structure will tend t o be wheel modcs,
turbine where damping capacity is not as crucial as and small modifications to the shrouding or lacing
it is for the longer blades in the later stages of the 5.6.2 Titanium can result In significant changes in the pattern of
L P turbine. Austenitic steels, however, have relatively Because of its hlgh strength/weight ratio and excellent Blade vibration control wheel natural freauencies.
high coefficients of expansion and tend t o be avoided corrosion resistance, titanium has been considered as
because of this. Ferritic steels of the FV 520 type a n alternative t o 12% Cr steel for low pressure lur-
have been used for last-stage LP blading but have bine blading. Since the density of titanium is aboul
Natural f r e q u e n c i e s a n d excitation 5.7.2 S o u r c e s of vibration excitation
now been generally superseded by steels such as FV 60% of that of steel, a titanium blade nearly 40%
566, which were designed for applications where good longer than a steel blade can be substituted, assuming Vibration excitation can arise from a variety of sources
impact properties are required at medium-to-high comparable stress levels in the blade root. of the large number of blades in any turbine but principally involves the following categories:
strength levels. Mechanical properties have been im- T h e corrosion resistance of titanium makes the nc, the existence of unavoidable sources of
proved by the addition of molybdenum and vana- material highly attractive for blading subject t o pit- ilion excitation and the serious consequences of (a) Non-uniform pressures, velocity or changes in the
dium, and suitable heat treatments t o give adequate ting, stress corrosion and corrosion fatigue. Laboratory l'itiiure of just one blade, an intimate knowledge angle of steam flow resulting in a periodic fluc-
creep resistance in the short hlgh temperature blades, tests have also shown that certain titanium alloys are Iri~dcrstandingof the vibration characteristics of tuating force on the rotating blades. This may be
and adequate proof strength in the long low tem- superior t o 12% chrome stainless steel in erosion Iblitdes in their operating environment is essential. caused by:
Tlie stearn Turbine Chapter 1 Turbi~icl~laiiiii(i
..
slcan1 soiati,,g ia,,s or.ci o,iiy 3 1 1 1 ~stationa~yS i o \ ~passages, tliese call incItIdC: 8 iiI:iil~,ii or inaliiial Srcqoencie can be clicckcd. IPio-
par~ioilof its circolal- path (liariial admissioll). viili'il ilia! cantileuci vihi-atioii tcsts confirm that tlic
cxis,;,, of some e Acoustic resonances in inlct \>assages, erlractio~l
lines or other cavilies, excited by the fio\l past
..lii,:lc-blade rrequincies are in accordance a,itl~ re-
~(ili!cinents,a complete bladed disc is manufactu~erl.
l i p turbines but not in LP stages.
thein. I l l i . bladed disc is thcn tested by fitting piezo- VI~HFIIIt i ~ ~ o <or
i r ~,,<!~C,,,OI$IC
t
c A change in the direction of' flo\v, partico- (.lcl.l~iccrystals at selected positions on the wheel and
larly from axial t o radial a1 exit from moving
r Voiler-shedding fr,om stay bars, etc. icruiding the modal shapes and natural frequencies.
blades. Good aerodynamic design shouid mini- e unsteady flaw separation from stationary bladcs, etc. Siilce the natural frequencies o f all blade rows,
mise the magnitude of this non-uniformity t~ircilt llie last few L P stages, arc generally above 9
m Unstcady shocks in choked stationary blade pass-
and ensure that multil,le I~armonics o f the e i ~ l l t h engine order (400 Hz for a 3000 i/min 2
. synchronous speed are not produced.
Flow
of extraction
by the prcse,lce
passages for feedheatel
ages.
can to excitation at even multiples unsteady aerodynamic force. Also windage, particularly near the blade I'l~i. 1.90 1'1,~icnl'Carnpbcii Diaginsi' fo, a
of rotationai frequency. r Recil.culating fla%', particularly in last-stage LP xiid cause overheating and make tlic results loir' pressare blade
.
l i l l lo interpret. For thesc reasons, the complete
Leakage through gaps in stationary blade ti disc is run in a vacuum wheel chamber, whcrc
shrouds and diaphragm discs at llorizontal unsteady condensation shocks, caused by SUperSatUra- i~il;~)'of magnets is used to stimulate impulses
joints. The current arrangement o f diaphragm in diverging passages, I f a wheel mode and a harmonic of rotatiollal
1~ 011 each blade as it Passes. The disc is r u n U P
support precludes this effect. fl.equeitcy coincide below the engine order,
('yo synchronous speed and the blade vibration selected modes may be 'tuned out, by adjusting the
lcctcd by strain gauges or crystals. Signals are blade mass,
Eccentricity of diaphragms and other station- * necessary condition for high resonant "ibratory 11 o ~ either
t through slipi-ings on the shaft or,
near the tip. ~h~ geometry
of tip ties ol. coverbands can be altered, or material
ary elements with respect to the rotating blade is the coincidence between the frequency of a reccntl),, by telemetry and the frequency and added to/removed from material
assembly. Again, current design practice should harmonic component (of significantly high magnitude)
minimise this. and tile natural frequency o f a mode of vibration of o f these components may be changed. Altering the
i. rr'ilmining particular resonances, it is possibie position of shrouding change
a blade, or a blade group, or bladed disc assembly. modes over the speed range.
.
0 Ellipticity of stationary parts, such as end With a continuously-connected blade row, a resonance frequency of modes and it may eve,l be pas.
lilt drawl1 011 a 'Campbell Diagram' similar to ~ i b kin certain
walls, seals, etc. condition is associated with a multinodal standing to adjust the blade
''$1 in Fig 1.90. Radial order lines througi~ profile. Experience has shown that a continuous lacing
in the gauge tl,ickness of wave pattern around the circumference. This, how- 1 rellresent events that occur a fixed number
ever, is not always a sufficient condition. It is also or tip tie arrangement is less likely to form complex
stationary blades, Modern quality and inodes of vibration than blades connected in groups
this effect necessary that the distribution of vibratory deforma- or packets, and is more predictable. Complex modes
tions and the distribution o f exciting forces have a resonance occurring dur- are likely to be excited by high frequencies and are
Moisture removal slots. relationship that permits a net input of energy into the It is usual t o confine attention to within almost impossible to 'tune outx,
vibration. speed (i.e., 2820 t o 3180 r/min).
For example, consider a long blade vibrating in a The damping afforded by 'loose' pins, tip ties,
tllis speed range, the specified requirement is lacing wire, etc. and the choice of blade material,
All the above sources give rise to excitation fre- mode with one displacement node (point of zero dis-
n o resonances up t o the eighth engine order. minimises the effect o f random or broadband exci-
quencies a t the rotational frequency or low multi- placement). The upper portion of the blade deflects
tation which is difficult to quantify. Damping re-
ples (harmonics) of that frequency. in one direction when the lower portion deflects in
duces the response to resonances as erosion or impact
the opposite direction. If the distribution of exciting damage changes the natural frequencies of particular
(c) Nozzle wake excitation caused by the aerodynamic force along the height o f the blade is essentially
modes and bring these natural frequencies into closer
force.fluctuations seen by the rotating blade as uniform, then the upper portion of the blade wants
coincidence with harmonics o f rotational speed.
it passes each stationary blade or traverses each t o respond a t a phase angle 180' different from that
stationary blade pitch. hi^ is seen by the rotating of the lower portion. The net response of the blade M e t h o d s of vibration control
blades as excitation at the nozzle passing ire. to this exciting force would therefore be very low. 1111 lacti tical to 'tune' blades to avoid reso-
quency (rotational frequency x number of stationary ill~o\'cthe eighth engine order. The harmonics 5.8 ~~~~i~~
protection
blades) and its multiples. 'lorc together and natural frequencies cannot
5.7.3 Verification of estimated natural frequencies lli~lcd or controlled to sufficient accuracy.
a n d w h e e l c h a m b e r tests luly, excitation forces at these high frequen- 5.8.1 Erosion m e c h a n i s m
A number of sources can also give rise t o excitation After a prototype blade has been designed on paper, illill and are incapable o f exciting complex The last stages of large condensing turbines operate
having n o direct relationship t o rotational speed. In a single blade is made in mild steel so that the cal- in the wet steam region, where the steam contains
74 75
Tlie steam liitbine Turbine casiogs
--
5 iZO1O ioi\arel. 'l'iirbiiie biade eiosion is initiated by there foliows a tcstiary period during W I I I C ~ ) l i i i ., r ~ ~ ~ ~ ~ l > l ib!c! ; t111e
! c ~need
i f o r intcrna sliell at tlie capciise of the ouler sheli, it also perinits
a reiativcly stuaii proportion of the water dropiets lerial ion by erosion falis logaritillllicaliy nil\. iilp lhciiili splil along their liarizolll;iI siniplc blcd-stcaln tapping ;it !he iotcr-shell conditio~li
in tlic steain separating olit and coiiecting o n tlic arid after about a year iniay almost ceasc, 'it! i i t i j ~tlic lolor to he inserted as a colil- and reduces the net tliri~slon l11c 1-11' rotor.
concave prcssure facc of thc diaphragm biades, where babie explanation fur this is that thc poirr t $1-. Sul~sii~iitialfianges and bolting arc Tiipic casings have bcen used on some modern
a film is formed which is drawn towards the trailing surface ai' the blade where erosion has 2 wllliiti~~iti the ~liessuscforces at llie lioii- toshines to fuillicr reduce the stresses on the hot
edge by the drag of the steam. Here the filni grows are partly-filled with water. This cushions llic ii111 'I Ill. ~clalivelyniassive flanges respond inncr casing, and hence reduce therillai distortion.
and passes around the trailing cdgc an to the convex o f the drops sti.iking thc blade and the impacl 11s ielnl,urature cilangcs Illail thc rest The inner casing is enclosed in a ba~.rel-iike sleeve
facc wilere, usually in a region of strong secondary are only transfericd to the material in a t i l t , resulting in different rates o f expao- wiiicli has no lhoiizontal joint. The inner casing is only
flow, droplets move back and forth increasing in form. hcilinjpog of temperature stresses and lightly stressed and can be relatively thin with light
sire until they are torn away by the shearing action of Itl~oi~yh rliese are minimised by the ap- flanges, whilst the barrel casing which encloses it is
the main steam flow. Relatively iargc drops (50-200 litingr warming steam. Further stress more highly stressed. 'The barrel casing, however, having
pm in diameter) are produced and have t o be acce- 5.8.3 Protection a n d erosion shield materlo Ir sct up by the gland housing and steam no flanges and bcing of uniform thickness, can easily
lerated fro111 rest by tlie steam. These laigc drops be designed to accornmodatc the strcsses whilst also
Methods have been investigated for collecting
arrive at thc inlet plane of the moving blade row at c i ~ s i n gare of cast construction and are remaining iciativciy thin. The pressure between the
from thc stationary blade passage, including rein
only a fraction of the absolute velocity of the stcam i i,rirrs-section to minimise non-membrane inner casing and the bal-iei is controlled by small
and arc subsequently struck by the convex surfaces by suction through slots near the outer edge
inl,)rr!,, bolting, steam penetrations and other radial passages tlirough tlie inner cylinder wails and
of the moving blade r o u ~ ,This causes the abrasion low fixed blades or by bled-steam belts
8th l i ~ ras possible symmetrically arranged piston ring seals between the innei and barrel casings.
on the leading edge of the blade known as erosion before tlie last stages. These methods have 11,
ir11ni~1 asymmetry and hence distortion. One disadvantage o f this form of triple casing is
Fig 1.91. advantage that they autoinatically reduce perfoiln
ti~tly be fabricated or a combination of the dilficuity in assembling and dismantling tlle HP
The adoption of higher heat drops in the iasl
I,! li~brications. cyiieder. On assembiy, the rotor has t o be fitted into
together with higher mass flow loading and i
t i t it11 ipiessurc vessels, the integrity o f the tlie inner and outer lower half, the inner casing boited
pressure at inlet to the moving blades, can lea<
SIATIONRRY DIAPWRAOM cukeil after manufacture with a hydraulic up, and then the rotor and innei- casing lifted and
smaller droplets whose velocities more rapidly t
o 150% of the highest working pressure. mounted in a special jig to allow the barrel to bc
proach that of the entraining steam. This can icr~t
threaded over them. Thc assembly can then be lowered
in reduced imnact velocitv and erosion effect.
back into the bottom half of the outer casing, and the
It bas been the practice for inany years to pro1 Nigh pressure c a s i n g s top-half outer casing added.
tlle leading edge and part of the convex surfa
oilctti 1~1l-bines,with steam pressures over 100 The steam inlet pipes pass througli the outer casing
the last-stage moving blades by surface harde
i!~licigsgreater than 100 MW, have H P casings and deliver the steam into the inlet belt o f the inner
a
IMPACTVELOCITY or by the attacliment (by silver soldering, or $11
J i'.ahcll design (Figs 1.92 and 1.93). This has casing. The inlet belt is formed by a n extension to
-----(--===*----
-----------&--DROPLET VECTOR
recently by electron beam welding) of a shield m
plcrl because of the difficulty of designing a the main casing which ensures that the inlet steam
TRIANGLE from a hard material such as tungsten, chromium t
STEAM VECTOR !;it18 lo withstand the thermal and pressure cannot come directly into contact with the rotor but
TRIANGLE steel or Stellite 6 0 .
IKI yct be capable of flexible operation. With must first pass out through the nozzlcs and the first
Attachment is always followed by the most stringet ili,rliell casing, the space between the shells is raw of moving blades. T h e inlet belt is often blanked
non-destructive examination of the joints. Erosion v,illi sleani at exhaust conditions, allowing each at the casing joint t o reduce the pressure on the joint
thc original biade material around thc shield ci
to bc designed for smaller tcmperature and face, although care must be taken that the admission
lead to undercutting of the shield material and eventi1
1. ililfcrentials. A baffle is farmed between thc o f stcam to the first stage is not interrupted.
shield detachment. Coverbands, blade upstands $31
ii..in>:s near the exhaust end as part of the innei- With steam temperatures at inlet in excess of
tip ties can also suffer from droplet erosion. It
i.;isiii~g.The baffle extends almost to the outer 538"C, separate nozzle boxes of heat-resistant steel
therefore considered prudent to inspect the blad
docs not seal against it. The turbulent cr- are sometimes used t o protect the casing from the
I'lci. 1.91 Relative inipacf relociiy onto iari-stage during overhauls. Even if tlie erosion shield do
is directed by the baffle to the exhaust full temperature. These take the place of the inlet belt,
lnovilis blades not become detached, the shields wili erode in tin1 nd prevented from cooling the inner casing; delivering steam from the inlet penetrations t o the
and will probably need t o be replaced at least oil uces the tcmperature differentials and hence first stage nozzles.
during the life of the machine.
,!I the inlet end of the inner casing. Steam leaking Some overseas units have nozzle governing instead
tl?e gland between the inner casing and the rotor of the throttle governing employed on all large CEGB
5.8.2 Erosion progression
nlet end is piped away to the exhaust connec- machines. With nozzle governing, the inlet belt is
When a drop impinges on t o the blade surface, a the space between the casings contains divided into sections, each controlled by a separate
very high pressure shock is generated for a short xhaust conditions with a gentle flow being valve opening in sequence, resulting in a more com-
period. The pressure wave causes plastic deformation 6 Turbine casings ~ l i ~ i n eby d leakage through the outer casing giand. plicated casting and the need for stronger first-stage
of the material and repeated plastic deformation rriialier Dressure differential oermits a thinner moving blades.
leads t o an increase in the internal stress. After a ~\,liich,combined with the larger surface area of The stationary blading is carried in diaphragms
certain time, the stress concentrations in some areas \hiecasing, allows quicker warming of the turbine which are supported and guided in the inner cylinder
exceed the tensile strength of the material, a n d cracks 6.1 Forms of casing construction iirt-up. Thinner shelis are also easier t o cast and by keys near the horizontal joint and vertical centre-
form. During this incubation, o r primary period of A turbine cylinder is essentially a pressure vessel wit kcly to have fewer defects. line, permitting concentric expansion. O n modern
erosion, there is little or no weight loss. When the its weight sunnorted at each end on the llorizonta 11 sornc machines. reversed flow blading has been machines the tip seals and shrouding for the moving
cracks spread and join, however, the result is material centreline. l t i s designed to withstand hoop stresses , where the steam is diverted b a c i between blades are usually carried on an extension of the
breakdown. Tiny pieces of surface material are re- in the transverse plane, and t o be very stiff in the ngs part way through its expansion, continuing adjacent diaphragm. Earlier designs had separate
leased and, during this secondary period, erosion rate longitudinal direction in order t o maintain accurate the final stages in the opposite direction. sealing strips supported between the diaphragms.
increases t o a maximum. cieatances between t h e stationary and rotating parts rangement gives a higher inter-shell pressure H P cylinders o n wet steam machines, such as those
After the surface has become uniformly pitted, of the turbine. temperature, reducing the stress on the hot inner on PWR stations, are different in design, being more
76 77
constrilctioli wiili a n iniicl casing containing d i ; i ~
piiragrn siipporis, blcd-steam and water cntraclio~,
beits, and a n oilier casing directing the exhaust la
thc condensers and providing sui~ctuialsupport for
the inller casing (Fig 1.96). This is not always so,
Ihoweves, particularly with pannio condensers where
a single casing may bc employed. The large size of
LP outer casings combined with their low pressure
loading favours a fabricated rather than cast con-
struction, Inner casings which are more complex can
be fabricated or cast depending on economic consi-
derations. All casings have boited horirontai joints.
L P cylinders are virtually all of double-flow design
but vary greatly in layout due to the different can-
denser configurations. The latest practice for con-
densers is similar to early 'undcrslung' designs with
separate condensers underneath each cylinder, tubed
transversely, allowing easy access t o both condenser
and LP cylinder. Foundation columns, bearing and
cylinder supports are located between condensers.
However, during the development of 500 MW ma-
chines, variations of thc turbine and condenser ar-
rangement were tried, both to simplify the L P casing
support arrangcmenls, to increase the area and shorten
the exhaust connections. The four arrangements used
.
were:
6.2.1 Flange design after a period in service, they are often found to
The forces taken into account in flange design are have distorted so that they no longer fit, typically
illustrated in Fig 1.98. The flange is assumed to seal leaving a gap between the fianges on the inside face.
at the inside edge, with the faces subject to a contact Thls is due to temperature differences through the
pressure greater than the internal cylinder pressure. casing on-load causing thermal stresses which relax
T o minimise bending stress on the flanges, the bolt by creep. When off-load, opposite stresses are then
centreline is arranged tangential to the siieli as can induced which distort the casing. This is generally
be seen in Figs 1.93 and 1195; this produces the typi- confined to inner casings as there is very little tem-
cal thick narrow flange seen on H P and 1P cyiinders, perature differential through a n outer casing on-load
! I .7 \\ rb < . . < , . o l ! . I I I I ~ : . : , l P . : . ~ : . . ~ : r ~f.a~.. \l\<'~.rt,#fu: 1 . h ~ I > h ~ r ? t l.IN>.
! :<>J: L . : ~
The seal is obtained by simple metal-lo-metal contact due to the external lagging. i n addition, distortion . > : r... 1 I . . I .:I! ,1>...1,::., < "<.J. ! : , c ] 1,: ,,.:L">b~.ol<~8r
of the flange faces, after careful bedding on initial
assembly.
can occur due to relaxation of residual casting stresses.
If distortion causes a small flange leak on an inner
A .
When flanges on H P and IP cylinders are unbolted casing, it may not be noticed unless large enough to
The steam) turbine Turbine casin(j!:
lhead of the inill or enlircly ciicolai nuti a,itii siii;iIi riaiiii I>ul ihas uic ;adi,antagc of alloa~ingimmediate by lhc barrel casing, i t is lpossiblc lo lhavc exiiaiistr
holes diilicd in tllerii, aliowing then, lo be lurned by r l ~ i - c l . i of
~ , ~the bolt lellsioil ~ ~ ~ i l h owaiting
ot for ten^ ;it ail four bolla,n corners of liic lawel- casing.
tommy bars. Bccarlsc of f~.iction,ihc iiecessal.y bnlt ~ w ~ ~ : ~ l ~stabilise,
t w s t o agaili by measuring the cxteosion
tension could not be achieved in the large diaincic~ iiiici cylinders are assembled with the lower i~alf
casing baits simply by turning the nuts, even if lolgc 11,c casing rcsting in its final position insidc tile 6.3.3 IP e x h a u s t s
flogging spanners could be used. Instead, the i i l t l s ili:i czising. It is thtis awkward lo usc norniai bolls
11' cylinders gcnel-ally have two or four inlets ar-
are first tightei~cdby hand; the bolts are then heaicil llii! inner casing and studs are often used instead,
ranged in a similar manner to the H P . The IP exhaust
t o expand them, and the nuts again tighteocd thy : screwed into the lower casiing and then tight-
positions are detcrmilied by the positions of the
hand tilrough an angle calcuiated t o give the correcl in the normal manner. Alternatively, a square
crossover pipes to the LI' inlets. With underslung
bolt-tension after the bolt coois down. By measurin on the bolt a t the horizontal joint a l l o ~ , sthe
condensers, the LP itlieis and crossovers are usually
nut t o be assembled and tigittened before the
o n the top half, hence I P exhausts are also at the
top. However, arranging IP exhaust and LP inlet
pipes in the lowcr half casing reduces the amount
rod into a thin hale drilled down the centre of ea lernal flange, but L P casings may also be bolted
af pipework to be disconnected when cylinders arc
bolt, thus heating the bolt without sig~tificantlywar8 IIP some of the internal webs if access through
opened, and is thus easier if thc condenser arrange-
ing the flanges (Fig 1.99). Tlic same method can i ~ilioiesis possible. Thc bolts used on L P casings,
ment allows it.
used for undoing or retightening the bolts. ~ l iof smail diameter, are tightened by spanner
An alternative method of tightening the bolts ilic conventional manner to a controlled torque.
pedestals'baseplatea.
Steam valve gear pivots.
to feed each bearing and with this arrangement oil
leakage does occur. On modern units, the high pres- Previously, attempts were made to provide autom;,.
sure pumps are mounted in or on the bearing pedestals tic greasing systems, using a motor-driven multi-
(see Fig 2.66). Details of the pumps used are given piston pump with long pipelines conveying the grease
in Section 6.2 of this chapter. A pressure relief valve to the various components. Unfortunately, separation
is fitted in the discharge line from each pump in order and hardening of the grease constituents in the pipe-
to prevent over pressurisation and overload damage. lines resulted in frequent blockages and inadequate
lacking oil is also provided to the turning gear journal lubrication.
bearings during start-up and shutdown. Modern plant uses bearings consisting of a sintered-
The pipework systems use Class 1 welded pipe joints bronze matrix, impregnated with PTFE, on a steel
and all the high pressure pipework is contained within backing strip. These bearings are now used under the
the pedestal. Figure 2.67 shows the arrangement used main pedestals and are provided with manual greasing
for the turning-gear jacking oil pump, but is typical of points. The greasing channels are provided with suffi-
these installations. cient area so that the total grease pressure can over-
come the deadweight and allow the grease to spread
over the bearing surfaces. Grease leakage 'tell tales'
are provided so that the effectiveness o f the greasing
operation can be checked. In order to prevent the ingress
6.10 Greasing systems of grit and foreign matter, the pedestals are provided
Various components require greasing in operation to with dust shields.
ensure smooth linear or rotational movement between Examples of the greasing points provided on the
components; oil lubrication is not appropriate. These main steam valve gear pivots are shown on Fig 2.68.
Turbine plant svsteins Gland sealing system
-
7iiis priocipie can bc extended to a greater iiumbcr
oC iaise diameter fins, bu! !he iiombev of effeciivc
restrictions pel. i i r r l t o f axial Ieiigth becomes progres-
sively less and it beconies preferable to adopt a simpler
form of seal, such as those shown in Fig 2.69 (a), where
the larger number of restrictions compensate for the
decreased efficiency compared with the stepped gland.
Another design of giand that is independent o f
differential expansion is the vernier gland shown in
Fig 2.69 (d). Both the shaft and seal ring are finned,
the pitch of the fins being slightly different on the
two seal components. This has the advantage that some
of the fins will always be directly opposite, providing
a -areater restriction.
Figure 2.70 (a) shows a form of labyrinth gland with
axial as well as radial fins which increases the number
o f restrictions in a given length of gland.
The tip thickness of labyrinth glands is made as
i:l(i. 2.67 Sllatl luvriirig gear, jacking oii pump
thin as piacticabie so that if a n accidental rub occurs
between thc shaft and the gland, the fins will rub away
with little heating of the shaft. A heavy rub would
quickly generate so much heat that the shaft would
7 Gland sealing system
bend and become unbalanced.
198
Gland sealing system
Turbine plant systems
The radial clearance and diameter 01' thc labyrinth leading slcain back lo iu, appropriate stage iii
gland is made as slnall as possible, since the leakage turbinc or to a feedheater after each sectio~,.
f l o , ~tiirough the gland is directiy proportional to the result, heat is returned lo the cycle.
leakage area. In praclice, the niinimuni radial clear- The arrangement of the final glands section l t i i
velocity through the final restriction cannot exceed glands is connected to the gland steam cond
mass flow will occur. Thus for a gland with a given through the outboard gland section.
number of restrictions, there is an associated pressure At low loads, live steam enters the system thic
ratio that produces the maximum leakage through a motorised isolating valve and a pressure redu
valve to the U P dcsupc~hcater.Here the steam is m i
Tlie gland sealing system is designed to supply to a temperature suitable for the H P / l P glands. I
steam to seal the turbine shaft glands at all operating then passes through a inotorised isolating valve to 111
conditions and to extract leak-off steam from thc HP/IP glands or, via a separate ~notorisedvalve, lo $11
LP desuperheater which further cools the stcam to
7.1.2 S y s t e m layout
A typical gland sealing system is shown in Fig. 2.71. LP desuperheater and is used to seal the LP glan
ATMOSPHERE
T o ensure that the steam is supplied to the glands F,G. 2.71 ~ ~ ~ igland
c a tsealing rsrtem
at a suitable temperature, it is cooled by desuper- 7.2 Temperature and pressure control
heaters. An H P desuperheater regulates the tempera-
ture of the steam of the HP/IP glands and an LP
desuperheater regulates the temperature of the steam 7.2.1 Temperature control
to the LP glands. Some systems also employ a third The temperature of the steam supplied to the glands
desuperheater to cool the steam which is bled to an is controlled by two desuperheaters; one for the HP/II'
LP heater during on-load operation. system and the other for the LP system. The waterspray
In order to reduce the loss of energy in external type of desuperheater is generally used although thr
glands at the ends of the H P and I P cylinders, and tube and shell type of heat exchanger may be in usc
to promote a gradual temperature gradient along a on some smaller units. A typical desuperheater is shown
shaft, it is usual to divide such glands into sections, in Fig 2.73.
201
Gland sealing system
WATER
COYER PLATE
PACKINGILEAK-OFF
STMM
NOZZLE
BAFFLE TUBE--
BOTTOM DOOR
(bl LPgiandi
FIG. 2.73 Gland steam desupeihcatei
FIG. 2.72 Final gland arrangementr
drain connections on the desuperheaters glands progressively reduces and eventually reverses,
allow ,drainage to pass to the clean drains tank as leak-off steam becomes available. Consequently,
The dnuperhieaters cooling water which
is the reserve feedwater tank through heater is cornpenate. by tb automatic or ing valve, a strainer and a drain trap, the rise in pressure at the glands causes the live steam
a motOrised closing of the valve to admit the amount of wale,, pressure regulating valve to close progressively, thus
valve. The water supply is then necessary to maintain the maintaining a constant supply pressure at the glands
controlled by regulating valves. Each valve is ad. outlet
perature, -up and shutdown, when live steam is and eventually closing completely. The L P glands are
justea by a on receipt of a signal from a
The steam temperatures are in the con, the pressure at the glands is controlled by the now sealed by steam leaking from the H P and I P
?"'Or in the desuperheater outlei. ~ n y t r o ~
Increase Or and locally; high and low temperature re reducing valve in the live steam supply line. glands, and the pressure at the glands is controlled by
in temperature at the desuper- alarms are included to indicate a fault condition, creases, the steam flow to the H P / I P a leak-off valve which dumps steam to a n L P heater.
203
Turbine ~ l a n svstems
t Flange heating system
sufficient to draw air into the glands where it mixes the H P and IP casings tend to heat up more
with steam leaking from the cylinder; the air is se- thali the large masses of metal in the horizonta
parated in the gland condenser and passed back to the flanges. The function of the flange heating systci~j
atmosphere via the vent fans. The steam is condeiised t o pvovide steam heating (at app~.opl.iatecondilit~j
and the condensate passes to the main condenser. A 10 the HP and IP outer cylinder flanges, theichy I
IPRSSSUREIRhNSM171IR
typical gland steam condenser is shown in Fig 2.74. ducing the difference in 1emperatul.e between eacii
Thc condenser typicaily consists o f a steel shell the cylinder casings and their associated flange
closed by a dished-end warerbon cover incorporating a boits. This prevents excessive thermal stressin
tubeplate into which are expanded U-tubes. Cooling cylinder distortions.
water, provided by local river water or seawater, is
F ~ C .2.76 T ~ HP alld
~ I P ~tulbiile~ nangc
~ ileatins
I system
Steam leaves each flange from outlet pipes which steam pressure has a corresponding effect on both
converge into one pipe, fitted with a flow regulating flange and cylinder steam pressures. As a result, rapid
heating due t o condensation heating is maintained at
Subsequently, the combined flows from each side the same relative levels, thus enabling the difference
of Ole turbine are joined and led either to a suitable in temperature between the casing and the flange to
reedwater keater or t o a drains receiver. be maintained within acceptable limits.
Suitable steam distribution is achieved using bal-
ancing orifices installed and set during commissioning.
Once the correct orifice size has been determined, it
CASING remains unaltered.
'The HP and IP flange heating systems are brought With the system as described above, the flange
into operation by the remote manual opening, from heating steam temperature is always higher than that
PIC. 2.74 Gland Elearn condcnser Fie. 2.75 Turbine half-carings joined at horizontal flanges the central control room, of the motorised isolating o f the steam within the cylinder casing. In some de-
204
EMEROENCYSPRAY
WATER PUMP
signs, however, the steam supply is taken from inside the possibility of excessive casing distortion. T F ~ G .2.78 LP eriiausi pray cooling syiteii,
tile rekvant casing and hence its temperature is always done by spraying cooling water into the exhaust space,
equal to that of the steam within the casing. whenever necessary, downstream of the exhaust giii
vanes. The exhaust steam is cooled and then re xhaust guide vanes. Initially, a number Of these keep the L P exhaust steam temperature within accep-
cuiated to cool the casing. A typicai L P exhaust coolinl, may be blanked off, to be used as additional table operational limits during no-load or light load
system is shown in Fig 2.78. iozzles if extra spraywater is found to be ne- operation. A temperature detector, incorporating
9 LP exhaust spray cooling system During normai running o f the turbine, the coildcii. during the subsequent running of the turbine. theimocoupies, is situated in one exhaust flow of each
sate extraction pump supplies the spraywater to lllc ,r liangement of the spraywater nozzles is shown LP cylinder and this measures the exhaust temperature.
system. The condensate supply, before reaching tilr In operation, a signal is passed to thc temperature
spray nozzles in each end o f the L P turbine cyinder 11 nozzle is designed t o provide a spray of atomis- controller, via a n amplitude selector (this ensures that
9.1 Function and system layout
exhaust, normally passes through a manuai isoiatit~g les which will evaporate quickly, thus promoting the LP exhaust with the highest temperature is selected),
During the low-load running o f a turbine-generator valve, a pressure reducing valve, a strainer to remoup ]>id cooling of the exhaust steam. which operates the spraywater control valve.
unit, tlle volume of steam flowing through the last row dirt particles, a flow indicating switch (~neasurin~watcr Suitable safety measures are built into the system to When any individual sensing element detects a pre-
o f the L P turbine blades is reduced considerably and flow to sprays) and a pneumatic flow control valve, ctly maintain spraywater supplies so that a n effec- set low exhaust steam temperature, the controller will
the smooth aerodynamic flow of steam through these with manual inlet and outlet isolating valves. A pres. 1 , atomised
~ ~ spray is available when required. This is open the spray control valve to pass a minimum quan-
blades is lost. The L P exhaust steam is recirculated sure switch is usuaiiy fitted across the strainer to mea. ,orlnally achieved by installing an automatic valve in tity of water. Further increases in temperature will
and, as a result, ellergy is transferred from the blades sure any difference in pressure, thus indicating whethe lit supply system to ensure that the spraywater flow is allow proportionally-greater quantities of water, rising
to the steam, resulting in a significant temperature rise blocking has occurred. A by-pass, with a manual iso ove a ~ e minimum
t level. This valve is arranged t o t o a maximum water flow at a preset high exhaust
o f the circulating steam. In addition, if the condenser lating valve, is usually provided round the spray contro ,en or close rapidly near this minimum set point. The steam temperature.
back pressure is high, a smaller volume of steam will valve and its associated isolating valves. ninimum flow requirement may result in a slow cycle The temperature detectors can have an inherent
flow through the system, causing a significant worsen- An emergency spraywater pump driven from a DC
ing of the situation, of valve opening and closing during low load, but this time lag and, under certain circumstances, an overriding
Protected power supply will cut in automatically in control is necessary to produce a two-minute burst of
The excessive temperature rise caused by these ef- the event of a failure o f the normal spraywater sup- A temperature detector is located in the path Of the spraywater at maximum flow.
fects can result in an undesirable restriction on the ply. The emergency pump draws its water from an
length of time that the turbine can run with no load, exhaust steam downstream o f the spray nozzles to In the event of the condensate extraction pumps
auxiliary water tank and discharges into the spray- the signal for the automatic start and control failing, the emergency spraywater pump is brought
and possible uneven heating of the exhaust casings water line upstream of the strainer. The emergency of the spraywater quantity. into operation automatically, provided that the turbine
leading to serious distortion and adverse effects on supply line normally contains a manual isolating valve,
turbine alignment. gland steam isolating vaive is open. This condition is
a n emergency spraywater pump and a self-activated detected by a limit switch situated on the isolating
The L P spray cooling system is provided to ensure isoiatine valve.-
that exhaust temperatures under these conditions are
~~u
valve. Loss of supply from the extraction pumps is
maintained within defined limits, thereby minimising
Each L P turbine exhaust flow incorporates a split 9.2 Control indicated by a pressure switch located on the supply
ring of spray nozzles, the ring being located outboard A" automatic temverature control system is fitted to line from the pumps, which is able to detect low water
802
.oh01 Les j o anlen e molaq s l p j peol aql alesuapuoa aqi jo asodsip 01 pap!hoid ale s a y II
uaqm Zu!uado a!lewolne l o j uo!s!noid aq Lew alaql 10
uMoplnqs ialje pauado Lllensn ale sahlen iLliem pue
~ a l s e waqL '[eu8!s aimeladwal 10 peol e w o i j Llles!l SJiZZOU iaiemr(eJds j o lualuasuei~y ~ L . T.ora
-ewo$ne pasola aq uea aqeh a q ~'Lfah!)eurallv 'pasola
aq ues sahle.4 iLiiew pas!lolom aqz pue su!elp aql
q a n o ~ q l%u!ssed aq ~I!M weals Lip itluo ley1 awnsse
01 alqeuoseal s! i! 'alnssaid au![ aql 01 Su!puodsailoa 3011VH3SIO dWnd N0113VillX3
WOM3 0333 t131VM AVildS
arnleradwal uo!ieinles aql ahoqe 3 0 0 Llalew!xoldde ~
ON3ISnVHX3M3H1001
jo a ~ r n e ~ a d w ea llv 'a81188 ainleiadwal e pue aainos 0333 M31VM AVildS
u!elp aql le (arnleiadwal uo!;elnies ~ o q 01 s palelq![ea)
a8ne8 a~nssarde q l ! ~pap!noid s! au!l u!eip qaea
'uo!lelos! l q s ! ~ap!nord ol alqe
sLe(emleuaql s! anlen ialsew a q j 'aAlEA iLllem aql 01 paU!j
-uoa s! lalem su!eip aql 8u!lnoiq1 w o i j spas anleh aqi
jo uo!leio!ralap alq!ssod 'LeM s!ql U I 'ahleh ~ L l i e w
aql Lq pamOllOj lSl!j suado ahlen latsew aql 'dn-llels
IV 'sanlan iLllew pue lalsew aql bq pa11o~luosLlle 'alesuapuoa aql l o j lallno ue saprnord malsLs
-nsn s! 'lueld aql jo uo!lerado 8u!rnp pasop Lllew~ou agJ 'sarnie~adwal[claw pun weals uaamla
ale q ~ ! qSU!BIP
~ J S O ~ I U! ~ a i e mSU!BIP j o MOD aqL -j!p e u! silnsal suo!i!puoa weals so peol u
lOJlU03 Z'01 e uaqM uo!isrado jeurlou 8o!1np s l u ~ o osle
j I
lSnVHX3
'lassan sn!elp sqi u! 15~51 3 0 3015 M3HlO 01
0333 1131VM AVildS
aql jo uo!leJ!pu! jeJo1 san!8 ssa[%iq%!s v '1~suapuos 's.iapu!lL~ ao!qim ail1 ii!ql!~ alesuapuos jo il
aqi 01 .!an!aaal su!e~p aql w o q ajesuapuos ayi IJ!I aql u! sllnsal slelaw laloo2 q1F.n IJeluos oio
01 p a q n b a ~ale sdwnd 'sl!un awos u g .IssuapuoJ sql meals aq1 'au!q~nl e J O po!rad dn-lle?s a[(
jo wolloq aql 01 su!erp axesuapuos Su!u!ema.l aqL
'sLelds aql 01 pailddns lalem jo
lnohel walshs pue uo!$Dunj
lunowe aql sajeln3al rosuas ainleladwal e pue dwnd
uogaerlxa alesuapuos aql Lq paqddns s! iteids aql
IOJ luelooa a q j 'sLelds Su!leaq~adnsap ql!m palllj ale swa$sAs s u ! % ~ g
STUJA aql saw!iawoS 'rasuapuoa =!em aql oi paluah s!
qqqm weals oiu! saqselj rap* su!eip aqi jo awos
lassah s!ql Su!ialua u g 'lasuapuoa aql reau p a i e ~ o l I N 3 W 3 1 3 DNISN3S
'sran!asar su!erp aql 01 peal s a y iqerp neals IIV 38niVii3dW31
'as!j!'o aqi 01 uo!l!ppe u!
ssed-itq panjen e sale~od~oso! an!$ aqi 'rln-irels 8u!.1np e ~ 0 1 a qsjlej peal ail1 .so [anal s!in spaaaxa arn~i
alesuapuoa jo uo!oallos s51-el e aq 01 .(jay![ s! alaqr
amqM saseld u1 'molj aql Ia!rlsa.I 01 sa~ejda3!J!IO aherj
saw1 qJnS 'a8eu!elp snonu!]uos ap!ho~d 01 ,(mss53
-su ale sauq u!erp 'uo!lelado [awron Su!inp laM s!
weals aql alaqM 'sapu![La sql se q3ns sam!Sar u~
su!elp snonu!iuo3 2'1'01
CONVENTiONhl
SlNGLt ORiFCE
VhlVE
212 213
lliiough the employment of desuperheater spraywater.
'Tlic spraywater supply to the pressure control valve is
. If condenser pressure is too high.
litken from the main feed pumps and has its own set Unlike the nuclear by-pass system, the pressure control
c11 !pressure control and isolating valves. The presence valves will fail locked in their last-held position if
(11 warming piping and drains in Fig 2.86 will be dis- there is a loss in electrical power. The spraywater
LA7ikli
iiivt c~issedlater in this section. pressure control valves also fail locked in their last-
Iluring start-up the pressure control valves are held position.
xned manually until the valves are more than 10% The LP by-pass system consists of four lines taken
,en, at which point the system is controlled auto- from the four hot reheat pipes (upstream of the IP
atically. When the boiler steam pressure reaches a turbine control valves). These four lines are then con-
xcified value, the by-pass system automatically keeps verged into two. The steam in each line flows through
ie boiler at that value. In the event of a turbine trip, a n isolating valve, a pressure control valve and then
ii signal is sent to the control valves to open rapidly. into the condenser dumo tube. The LP by-pass system,
CONDENSER Alternatively, in order to protect the cold reheat piping therefore, is very similar to the by-pass system on a
system, the pressure control valves can be ordered to nuclear plant: it behaves in the same way as the HP
close rapidly under the following conditions: system, the pressure control valves opening or closing
under exactly the same circumstances.
o When the spraywater pressure 1s low
.
If the steam enterlng the cold reheat plpes is at too
can greatly benefit the plant. Their addition, however,
hlgh a temperature
does result in a few oroblems such as noise, water
If the pressure m the cold reheat system is too hlgh Ingress and thermal shock.
214
Turbine plant systerrls Operationai flexibiiity
11.4.1 Noise O i l tile conti0l v;ilvcs that exil lo almospheie (1i;iii itilili~iooto loadfoilowing cyclcs, This ici]uiiemeot iinoccessasily. Stcani coirditioris at tile stop valves
li usas discussed earlier liow iargc pressure drolis across on nuclcai plant) by includirig n sileilcer. l,,,l>ii,ued ficxibiliiy has resulted i t ? all 500 M\h' and sliorild alloiv for tlie temperatucc drop due to Ilirol-
valves induce co~isiderablc i~oise. Figure 2.87 slio\~~s \.lW t u r b i n e - g e n e r a unils on the U1< system tling at steam adn~issiolilo the turbine (sec Section
ho\v !lie proportion of energy loss converted to noise esigned to be capable of operating a two-shifting 1.3 of this chapter), It is pal~ticulal~ly
importali1 wIleI1
(acoustic efficiency) increases with the sizc in pressure 11.4.2 Water i n g r e s s i n addition t o thc requirement for high effi- carrying out hot starts, that thc late of roll-lip to
drop. This effect is reduced dramatically by using valves With the pressure conual valves shut, a large hoiii1.1 ase-load operation during early life. Typical speed and initial block loading is sufficient to pre\,eol
that employ adiabatic flow with friction, as discussed o f condensation wili occur in the steam lines. 11 11 ooal requirements for modern high merit tur- a reduction in turbine tcmpcratuie. The range of tcnl-
eariier. Noise can be reduced further by increasing tlie condensation were allowed to remain, water wa plant are shown in Table 2.2. pcratuie cycling should be controlled as far as possible
thickness o f the downstream piping and covering it passed through the system when the valves are ai t o minimise the risk o f thermal fatigue.
with acoustic insulation. Figure 2.88 shows the ratios resulting in damage t o the valves and conden Figures 2.91 and 2.92 show typical run-up curves
Tnai.s 2.2
o f pipe thickness to pipe length used to create further avoid this build-up, drains are located at strate for a warm start (after a weekend shutdown) and a
noisc attenuation. Even rno1.e attenuation is achieved tions, for example, in the busmain and upstreiini T j p i c n l opernrionnl requiie,8ir8ilr hot start (after an overnight shutdown) respectively.
each control valve shown in Fig 2.85. Drains arc ill The rapid loading shown during the hot start i~idicates
present on the HP system o f the fossil-fired plant silo\ the importance o f maintaining a steady rate of rise
in Fig 2.86 t o prevent ingress of water from 111 of temperature. Run-up procedures must be adhered
Spraywater system. g) viti? iu~>-up lo full-load 5000 to in order to minimise cyclic thermal stresses in the
iii 30 niiiiutes turbine and thus prevent thermal fatigue problems
1000 during the life of the turbine.
11.4.3 Thermal s h o c k 8 ii;,r~s starts ioiio~isg> 120 lhoi~s
200
The drain lines at the upstream section of the colit pvoionged r l l u t d o w ~ ~
valves serve a duai function. As well as maintaininlr 11 12.1.3 Load cycling
pipework free from water, the)' also maintain the viil
I ,,,li~.io~~owi~ip
Clia,>geiof loud iii 50.- iOO0lo 4000 The amount of load cycling that a turbine is expected
load range. Asruining
bodics at a temperature wllicll will avoid any large l i of 3
~liiniintn~r hours belwccn
t o carry out (i.e., defined as cycling between 50%
ma1 shock t o the valves when the by-pass comes i i i l c cyciei. and 100% load) needs to be controlled. In addition
operation. to specifying tlie number of load-following cycles
required during the life of the plant, thc time taken
t o carry out ioad changes should be such as to mini-
11.4.4 Leakage f l o w s 2.1.1 B a s e load mise cyclic thermal stress. This means avoiding rapid
An almost inevitable problem with by-pass systems, ider normal conditions, all high merit plant would bc cooling or heating of the turbine when inlet steam
with most steam systems, is leakage flaws. Leaks fr ~pectedt o operate in a base load regime. This involves throttling is applied or removed to achieve the desired
valves reduce the efficiency of the plant, so valve ng periods o f continuous operation, with infrequent load change.
designed t o be as secure from leaks as possible. Du )i+,ti times' to facilitate statutory testing, inspection
the life of the plant, leaks are likely t o occur, but ,nil overhaul/maintenance periods. Base ioad units
kept in check with regular maintenance. Taking all t l ~ In inot normally accumulate a high number of hot or 12.2 I n f l u e n c e on m a c h i n e design
considerations into account ensures a safe, ef iviixln start cycles or load-following cycles. Figure 2.89 The need for flexibility has brought with it inherent
and reliable system which provides flexibility bet\r,ecli ows typical run-up curves for a cold start on a problems which have needed to he redressed at the
the boiler/reactoi and turbine conditions. MW turbine-gcncrator. In this particular example, design stage of the turbine, with the knowledge of
-load is achieved after nearly six hours, excluding future operational requirements. The main probleni
1111. time taken t o achieve satisfactorv steam conditions is the effect of thermal cycling with respect to thermal
iil the turbine stop valves. This long run-up time is fatigue damage. The flexible mode of operation in-
12 Operational flexibility 11111 only to limit differential expansion rates and rotor volves some degree of temperature cycling of com-
eccentricities, but also t o limit thermal stresses within ponents, leading t o strain cycling of inaterial in the
tlic turbine, critical regions. The damaging cumulative effects o f
12.1 T y p i c a l o p e r a t i o n a l regimes thermal cycling (i.e., stress-strain cycling) must be
Power station output, and therefore generation, need assessed over the turbine life t o ensure that sufficient
to be regulated constantly t o match consumer demands, 12.1.2 Two-shifting margin exists in the design for the effects of steady state
Economics demand that the base load should be pr Onc of the most important factors when considering creep.
vided by the most efficient plant, which mainly includ two-shifting operation is t o keep the turbine tempera- Figure 2.93 shows a typical stress-strain cycle as
nuclear and large-capacity coalfield-sited coal-fired st;$- illies as high as possible during shutdown. This means experienced by the surface of a large HP rotor. The
tions. More expensive, or less efficient, generating plant Illat the machine needs to be deloaded as rapidly as cycle shows the effects of two-shifting using a typical
(small-capacity coal and oil-burning stations) arc possible. Figure 2.90 shows typical shutdown curves 'warm' start where the temperature gradients cause
therefore needed t o vary output t o match demand. The lor a 660 MW turbine-generator, in which the machine thermal strain. O n heating with steam at 565°C the
plant that is required t o run intermittently to matcli is shut down within 20 minutes, with the last 50% surface attempts t o expand but is compressed by
demand operates what is known as a two-shiff regime, of load being shed in approximately 2 minutes. Main- restraint from the underlying material. This compres-
so called because o f the requirement t o run during the taining the turbine temperatures in such a way ensures sion, represented by line A-B in the figure, may cause
two daytime shifts but t o shut down during the nigh1 o faster run-up and reduces thermal cycling of the the surface t o go into compressive yield, represented
shift. Such plant may also be called upon t o shut down turbine components. When starting, it is imporlant t o by line B-C, in areas of high stress concentration.
over the weekend. It is now common for 5W MW and ensure that the steam inlet temperature is matched to Subsequent heating and expansion of the underlying
FIG. 2.88 Ideal pipe dirnensiolls 660 MW machines t o carry out two-shifting operations tile metal temperatures t o avoid cooling the turbine material then causes tensile stressing of the surface
216 217
iiME.rn,"
iiME.m#n
r---
.laql!a 01 plezeq ou luasa~d01 se Sem e clans u! pa81eq~
I131VM -s!p aq lsnm I!e paleaq aq& 'sadrd iahossola
ON11003
aq1 urolj swan B!A s~sneqxaau!qlni 41 aql urolj I!-+
-
'SaAleA dwnp laleaqal aql e!h alaqdsoluie 01 Bu!)sneqxa
l e a ~ p pue
i sad!d leaqar ploa a q 01
~ suo!laanp qloq u!
1131711
i3iNl siw awis-2 OW aurqlnl d ~ aql JO anaalr m u ! aql pue lapuysa
no aql naam~aq9u11ama I!V 'sau!qml pue d ~
111 i o j mou i!e JO uo!mal!p aql smoqs s ! q ~'96.7. a!d JO
Iuama9uelie a!leluwerse!p aql u! u ~ o q sS! lo)e1aua9 NOIL~SO ~
H3V3
S3IVld 331di80
11 '!lo!suedxa le!luarajj!p aql jo loliuos laaaq Su!n\olle
'inill 'iorol aq3 $0 leql ueql laq%!q s! slooa Bu!sea aqi
tq>!q~le ale1 aql leql sarnsua s ! q ~'ssu!ses ralno pue
raou! aql UasMlaq aaeduaiu! ail1 olu! i!e a111 Bu!)3alu!
q paha!qae s! 8u!iooa 'uo!suedxa le!loarajj!p ah!l!sod
. . . . ..
1003 i!e-PaJ.iOJ J o asn aql ql!M 'ilT~3!dLl:S~LU!I
~.
I~~loloa lalJW~q!SSOd se uoos se In0 pa!Ue3 aq 01
! ,~sueualo!euBo!lqeua snql 'aw!, Jlq!ssod isal.loqs
-!dLl sMO1ls 56'2 s J n 9 ! ~'iolOl aql J O uo!nas [e3!1!12
ti! ;rll!lleq Jjo eayel aq 01 au!qaew aql ,qle ol '4' salefnu!S li3!qM a102 IBllUa3 8 q l ! ~saqoid sin)
-e'admal J0 asn aql PaAa!li3e s! Su!iol!uom ~ I I J
."
I I I I iiretu aul 10 a u.. , ,~
r i o o ~rie-nJJ.,oI
~ $ < . asod,nd 2 , ,<&r
'palles sam!laruos a.le
6u!loo3 r ! e - p a 3 i o j &'ZL Laqi se 'SIOI!UONI a.lnl!p~tadxaa j , ro s t o ~ ~ u o ussa.,rs
,
JO lualudojanap sql inoqe 1qSnolq luaura.r!nba.I Su!rol
-!uom s!qL 'au!qinl aql jo aj!~jeuo!lelado agl u! Insso
IOU II!M a8eurep an8!lej e~eur~aq~ 1eq1 a.insua plnorls
' ~ o i o i541 J O seaie !ea!~!.rs u!ql!n ssarls s ! q ~' p a p a a m IOU ale slahal ssalrs jeutxaql a1qeMoile
I sill arenleha 01 mo pa!rlea s! s!sAjeue ssalln wnm!xeur aql leql 0s paiol!uou ale 'sro1o.i d l pue d ~
I a.lsgM ' i a ~ n d u o ae olu! p q uaqi s! elep s ! q ~ "9.a 'scuauodmo3 je~!r!is U!~I!M S15ASj SS311S [BU1.13ql
ill! aqold qloq IOJ awes aql s! q3leurs!w ainlerad leql le!a!Jauaq s! I! dll-sun1 9u!.lna 'papaaaxa lo" lnq
lii.>iu/rneals leql sueam S!IIJ '21e.1 a u a s aql re 'paqaear s! lrws qma 01 pale1a.1 pna[ sss.11~ie[na!l.led
i i i l i l a,n j o seare l e q i 3 pcre aqo.id ail1 '9u!joo~ e ieqi uo!lduInss-e aql pun nc!aual!nba.I leuo!is.la
11 i i ~ l n pteqr os pauo!l!sod are saqord sq) 'uo!reI -do sl! no paseq s! ~ole1aua8-a11!qinlaql jo sf![ arfL
I! i.'.,i.ios rod '.rolo.i aq1 01 pai~!mpe se meals st11 s~o%!uoru$sails E ' Z ' Z ~
Turbine plant systems Wet stearn turbine pi
to give a cooling rate which allows eccenlricilics and flow at the entry lo the L.P cylindeis, and th
differential exgarisions l o be maintained within the adequately lhigh cfficicncy of blading. Higher I
manulactuicr's specified limits. ~ I C S S U I C S help to miilimise the sire of the or
segarator/rehcaler, and tlie mean diameter and lriigll
of the H P cylinder exhaust blading.
12.3.2 Cooling s y s t e m Thc inlet steam conditions also dictate the scai~tl
The cooling air is provided by a sysreni consisting of of the 1-IP stop and governor valves, which a
oil-free compresscrs or blowers, distribution and ex- similar in arrangement, size and thickness to
haust pipework, supports, valves and control gear, and valves on a conventional unit. A typical back-I(
fillers or air conditionine- olant.
. The svstem shown in arrangement is shown in Fig 2.98. Because $11
Fig 2.96 employs a single multistage compresser. It is temperature (about 280°C) and pressure do n
normal to install sufficient capacity to meet the cooling a material with high temperature strength and, sine
requirements of one turbine only, with pipework pro- steam at inlet is insufficiently wet to cause er
vided to enable cooling air to be supplied to any of a low carbon steel is used fox the valve chest
the units in the station. loop pipes supplying steam fro111 the chests l o I I
It is important that the air supply is filtered to ensure H P cylinder may also be made from carbon steel
the removal of small particles and also that it is free the same reason. The loop pipes are generally ariai!
of any corrosive gases, such as sulphur dioxide and to be as short as possible to limit the quantity
chlorides, as emitted from the stack of fossil-fuelled steam which might overspecd the machine in the i.!,cl
stations. Moisture separators should also be installed, of load rejection.
along with suitable pipework drains to ensure llial the The H P turbines of large wet steam machines t
air supply is dry. usually of double-flow design, similar in appeal;$
Fieurc 2.96 also shows lockinn double-isolatine valves to tile IP turbines of conventional units. As ma)
seven stages of moving blades in each flow are ca
by a rotor which, in tlie UK, is nonnaliy of a mona I
from the turbine when not in use construction. Diaphragms or fixed reaction bladitr
are supported by carrier rings bolted to the outer cissill
at the horizontal joint as in conventional macliitl
This effectively forms a double-shell construction
permits moderate casing thickness, flange and bolt
13 Wet steam turbine plant to be employed.
For impulse blading and an adopted rotational.
of 3000 r/min, the bladed wheel diameters tend i r
13.1 Influence of steam on components relatively small and, with the high specific steam .
The steam produced by a modern light-water reactor, sumption, the blade lengths become relatively I
such as a PWR or BWR, is of poor thermodynamic The double-flow arrangement serves to keep the . ,
quality. The pressure is typically in the range of 65-70 lengths, and hence the blade stresses, to conservat
bar and since thc steam is around 3% wet, the tem- values.
perature corresponds to saturation conditions. It there- Care must be taken in the design of the H P c ~ s i
fore follows that the steam mass flow per unit of to eliminate crevices and pockets where water 11
generation is about 80% higher than in fossil-fired or collect, otherwise, during sudden load reduction, 110
AGR power stations. of standing water could flash-off and overspeed I
The very modest steam conditions at the turbine turbine.
stop valves results in a very large volumetric flow. It is normal practice to pack the shaft end glan
The turbines consist of one high pressure and two or with live steam which has been throttled and 11
three low pressure cylinders, with the steam exhausted therefore acouired a small amount of suverheat. TI
from the H P cylinder being dried and reheated in also removes the possibility o f erosion damage to II
external moisture separators and reheaters before be- rotor and other components in a n area of high mol
ing readmitted to the L P cylinders. A typical turbine ture content at the end of the H P expansion.
arrangement is shown in Fig 2.97. Unlike high tem- The steam leaves the H P turbine with a well1
perature reheat turbines for fossil-fuelled power stations, of between 10% and 15% dependent upon tl
where reheat pressure affects boiler design and is lected crossover pressure. If the steam were then p
therefore not a free choice of the turbine designer, the directly into the LP cylinder without any form
reheat pressure in turbines for light-water reactors is mechanical drvine . - or reheat. the terminal wetness
chosen by the turbine builder to suit the turbine and condenser pressure would exceed 20%. This would cao
moisture separator/reheater design, performance and unacceotable LP movina.blade erosion, oarticularly
economics. Due to the very large mass flow of steam, the last stages, and turbine efficiency would bc i t
it is not necessary to select a low reheat pressure paired. Reheating is therefore always employed
in order to preserve a n adequately high volumetric saturated steam cycles.
226
Turbine plant systems Chapter ? f Wet steam turbine plant
:ill lileir stages to stcaill ptessllics ant1 1empcratiil.e~ HI' cylinder into b l c d s t e a o ~pipes and into the caid
!irtually i d e ~ ~ l i c alol those 1'01 fossil-Coellcd stations. rchcat pilics, whicir are drained at a11 times to llrc
it is therefore $possible and desirable to use LP cvl- drains icceivcr; the Ll' cylinders into bled-sleam pipes
intieis of identical design to those used in turbines for and lhe condenser. if gockets at each end of the H P
ii~ssil-fuelledstations. However, enhausl volume fiow cylinder arc formed in the casting between the coid
ii 60-70% greater than for a fossii-fired unit of the reheat branches, these are drained cootinuousiy into
m n e rating. If, therefore, exhaust losses are to be the coid reheat pipes.
Ikcpt to a minimum, either the exhaust annulus of each Intcrstage drainage introduces considerable quanti-
1.1' turbine must be increased or the number of LP ties of water to the feedheater system and the provi-
llirbines must be increased. sion of exlra laree drain arrangements in the design of
In the USA, half-speed machines have been adopted this system requires careful consideration. In common
l'cv use with iarge output light-water reactors. Power with conventional machines, every effort is normally
g r ~ ~ e r a t i ois
n at 60 Hz, which limits the choice o f made ta ensure that there is no oossibiliti' of water
rotational speed t o 3600 r/min or 1800 r/min. The refluxing to the turbine. Present specifications require
ilrcsses in the exhaust blades impose a limit l o their individual routing of drains t o thc turbine drains re-
lul~glh in full-speed machines and hence a limit in ceiver and prohibit the commoning of drains from
Ihc cxhaust area ner turbine. This. ~,toeether
~ . " with
~~
thr
........ sources at different potentiais.
FROM
STEAM GENERATOR
TO HP TURBiNL w,idcspread use of 1800 r/min LP turbine elements in
ci,~iventionai power plants, has led naturally t o 1800
I : , ~ , 2.98 ~ ~ ~ k . t ~ alrailgemoi~i
. b ~ ~ i , or H13slop a#?dgovernor valves ~/iiiin as the design speed for PWR turbines in the
hO IHz system. 13.3 Erosion protection
111 a 50 Hz system the position is entirely different.
Steam enleis the H P turbines slightly wet and i t be-
h41icb larger turbine exhaust blade annulus areas are comes progressively wetter with each stage of expan-
In order t o avoid the complication o f additional t~vi~iiable and still longer blades are being deveioped; sion, but the moisture droplets are very small and
ISWP nrnrtrntions into the reactor. steam is oassed tr~eking3000 r/min turbines economical for large out- are so well entrained in the bulk steam flow that the
purs and different condenser pressures. Half-spccd velocities of droplets and main steam do not differ
turbine hail where the wet steam is dried mechanically 'hines are invariably more expensive than full-speed
significantly. Blade path erosion is not therefore a
before entering a reheater, also situated in the turbine ines. The design of the LP turbine elements can
significant problem and the biades can be made from
hall. Here the steam is superheated by the use of live sed upon extensive experience of identical oroven
12% chrome stainless iron coupled t o a NiCr MoV
steam which results in a performance improvement of llponents for conventional power stations. Howevcr, forged rotor, as in conventional machines.
about 1.5%. The thermal efficiency can be increased clear power generation leads in itself to increases
Centrifugal stresses are generally low and, since the
rlic size of generating units, and it may be necessary
-,a further 0.3-0.5% bv two-stage superheating, i.c.,
hv steam temperature is far below that at which creen has
I i'aiisider half-speed machines for future very large
by using b~ed-steamfro; the HP t u A n e as heating t o be taken into account, only medium-strength ferritic
I I ~ I ' . requiring large annulus areas, particularly in
steam in the first stage and live steam in the second
---.-- The
stage. - .
efficiencv imorovement
. ~ a i n e dby bled- -----.-- nbination with the low cooling wale,. temperatures
lii;riy in UK plants.
stainless iron need be used for the blading.
Where changes in flow directioli are induced in the
steam reheating has t o be balanced against the in- casings or pipework, or where pressure differences exist
creased capital cost, and is dependent o n the cross- across joint surfaces or pressure seals, water droplets
over pressure, bled-steam pressure and the rcheater can combine and there is considerable potential for
terminal temperature differences. The bled-steam rc- F ~ G .2.99 %utterfly type low nreiruie i>xerccntoi valve
Water extraction devices erosion. The H P casings, fixed biadc carriers and cold
heater improves the cycle efficiency by reducing the reheat pipes must therefore be made from a chromium
steam demand of the live steam section, but it also the steam enters the turbines wet and becomes
essively wetter as it expands through the H P alloy steel such as 2.25%Cr 190Mo. Such alloys resist
incurs a n additional pressure drop of the reheated
shedding to zero load, the interceptor valves cl ~ g arrangements
, are usually made for internal the formation of the surface oxide layers, which would
steam through the tube bundle and requires additional be continuously removed and reformed by an erosion-
drainaee facilities. Despite these factors, bied-steam rapidly, preventing the steam present in the SeParato tlre extraction at each stage. Where appropriate,
and reheater, together with any water which migh aeitls fitted t o stationary components are slotted corrosion mechanism. It is also essential to protect joint
rr.lle311ng 1% bccdmin& increaslngl) c;ansmrally \iable
.ind i s normally dircred on prescnl rlcanl n~a:h~nr,. evaporate off hot walls and pipework, from overspeed ennit extraction of water collecting o n the outer faces subject to a pressure drop against cutting by wire-
ing the turbine t o unacceptable limits. The valves oundary. This water is either removed with steam drawing erosion, and to protect surfaces which might
- \ulumc.lr(; flon at LP c)llndcr
Bcc;luie o f rnc larac
designed so that steam forces assist closure as soon from extraction points between the fixed blade be subjected to impact from water droplets flung o f f
inlet, the interceptor valves tend to be very large.
a small degree of rotation is imparted. The valves or, in stages which have no bled-steam tap- the shrouding of the rotating blades. This requires
This precludes the use of normal plug valves; instead,
butterfly valves similar t o that shown in Fig 2.99 are fitted with bearings which are capable o f operatin8 rained through the casing via pipes, drillings the use of very erosion-resistant alloys, such as 13%Cr
normally used for this application. Since there are no relatively high temperatures and have shock absorbi ces t o a stage at lower pressure. or 18%Cr stainless steel. Austenitic steel facing can be
right angle bends and n o restriction t o the flow, they characteristics. 'Illel extraction grooves may also be incorporated provided by weld deposition and 13%Cr inserts may
have the advantage of providing very low pressure The thermodynamically optimum choice of the cro m necessary to assist the feedheating belts in ex- be located by seal welding.
drop in the normal operating fully-open position. over pressure between HP and L P cylinders, and I Iiig additional moisture. These consist of a n annular T o minimise the possibility o f joint jacking by cor-
Butterfly valves are used for both stop and governing universal application of steam reheat, result in i ' c in the cylinder wail at the trailing edge of the rosion products, horizontal joint bolting must be ar-
valves, the two valves being arranged in a single chest conditions t o the L P cylinders which are closely . lli biades connected to a series of nozzles which ranged to ensure that water penetration is restricted.
weided into each hot reheat pipe. ilar t o those encountered in a high temperature irirge water and a small quantity of steam into It may be necessary to protect certain joints by placing
The valves may be used in a reheat governing mode, heat fossil-fuelled cycle. As a result, L P cylind between blade rings and outer cylinder. short stainless steel sleeves around them and incor-
for water-cooled reactors are subjected througliol 111: turbine cylinders should be self-draining; the porating stainless steel barrier keys.
as in conventional machines, but in the event of load-
229
Turbine plant systems Wet steam turbine
Sevcic erosion Ihzii lbecn cxpciieoced by conliiicilial noiinally lbori?.onlal ioicl pips Lliriiilgll a i1ivei.ging c l i l , I1ii.h ive/oci(,) g'ciotie Se,io~atoi
~nanofactoiers or, loa, alloy axid cal.bon slecl casings ical channel la a io\r of supirier bladcs. The s w i ~l r ~ 'I lit' major ~pl-obleol \$,it11 cyclonc or ccntrifogal sc-
and pipework in wet stcan1 macliines. 'Alstboin' ori- blade ring imparts tangei~tialvciocily, or swirl, to i l ~ i jiiii:iiors is the uressuie drop produced by swirling the
ginally niade 131' casings in f CrMoV hut, in view of s t ~ a t nand helps to agglon~eiatethe watei- dl-oplcts. 'I'ilr iiti.;iiii in a relatively large diametec drurri and then
cnpeiience gained at Muhlcbcrg, Beznau and Oskar- watei- films forming on tile aerofoil surfaccs o f tlic i;l!;iigl~teningthc flow at exit iron1 tlic scpaiatol. One
sliamm and in Germany, intend using a steel with at swirlel blader are subseqiiently detached as coarsr iorihod of reducing the pressure drol) through tllc
least 11% chrome lo luture to give satisfactory erosion droplers by the main steam flow. The droplets are then h~i>;iiatol. is by swirling the wct stem tli1.oug11a nitmbei
protection. They curl.ently make pillework bends in centrifuged by the stcam flow and deposited onto tlic 01' ielativcly small diameter tubcs or cells arranged in
2 i % chrome steel and apply a high-chrome cladding inner surfaces o f a loui,red liner which reinoves and it bundle in an enlarged section of cold reheat pipe. A
protection on interceptor valves. CEM (Asca Brown partitions the free water from thc main steam flow. typical separating cell and vertical assembly arrange-
Roveri) protected low alloy diaphragm groove facings The louvred liner is provided with a series o f narrow Inciii used in the Stein lndusliie design . is shown iii
and similar facings for gland groovcs with 13% chrome axial apertures uniformly distributed around its pcii.. I:i$ 2.101.
cladding but, having found the cost of achieving a phei-y lo entrain the water droplets. Separated watch. I n colnmon with the NEI-Parsons design o f cyclone
satisfac1ol.y 13% chl.ome deposit prohibitive, now supply films then cascade around tile outer surfaccs of tllc ruparator, a set of turning vanes at the cell inlet im-
13% chrome castings for wet steam HP inner and outer louvred liner. To encourage the separated water lo litisls a swirling motion to the steanl/watei mixture.
casings. flow over to the louvrcs, steam is extracted from tlir Inslead of a louvrcd drum, an annular skimmer slot
separator vessel and passed to a heater in the fecrl I!,cinployed t o collect tllc watei and a small flow of
train. The separated water is also passed from tlil, ~xlractionsteam is allowed through the slot to improve
vessel, via drain pipes, to a convenient point in tiit. liioisture removal. Another sct of guide vanes at the
13.4 Moisture s e p a r a t o r r e h e a t e r s ( M S R s ) regenerative feed train. crli outlet straibhtens the flow and helps recover rota-
Separators and relieateis fall into two main types. In order to ensure that steam leaves the separator tional kinetic energy. Since the flow does' not depart
Manufacturers such as Westingl~ouse, Asea Brown with the minimum o f swirl, anti-swirl vanes arc fitted hif:~iificantIyfrom the axial direction tlirougllout the
Boveri, GEC, etc., combine the two units into a single into the outlet nozzle. These vanes ensure that a low hcparation process, pressure drops a1.e generally small.
vessel or MSR; whereas Parsons, Stein Industrie, etc., energy axial flow of steam enters tlle rebeater, mini- hlso, because the cell bundle is not mllcli larger than
favour individual vessels connected by large bore mising the risk of disturbancc to the reheater tube IIIC diameter of the pipe on which it is fitted, tlle
pipework. bundlcs. separator may be retrofitted into existing installations
The performance of cyclone separators is very de- s'ith the minimum of disturbancc.
pcndenc o n the droplet size of the water entering thc In tests carried out a t Bugey I1 power station, the
13.4.1 S e p a r a t o r s vessel. Very high efficiencies (of the order of 98%) l>ressuredrop for an inlet velocity of 50 m/s was about
can be achieved with a wetness of, say, 12% if thc 150 mbar and the moisture content at outlet from the
Cyclone seprrralors
droplets are relatively coarse, but efficiency falls con- separator was 0.3% compared with 11.4% at inlet.
siderably if the separator is presented with steam o f Ifowever, 10% of the main steam flow was extracted
In the. NEI-Parsons design o f separator, shown in the same wetness with droplets in the sub-micro metre lo assist water rcmoval.
Fig 2.100, water droplets are recovered from the steam range. Tests t o determine separator efficiency, using Stein lndustrie have also developed a horizontal
by centrifugal action. The vessels are conveniently located superheated steam artificially wetted in a spray-type liigh velocity separator, in which a portion of the
in the cold reheat pipes from the H P turbines, generally desuperheater, generally give optimistic efficiencies aleam from the bleed-off is passed into the central tube
one vessel pel- pipe. The wet steam is passed from a since the large water drops produced by the desuper- ill the separating cell and recirculates through slots
heater arc easily separated from the steam. Measure- i i l this tube just downstream of the inlet vanes. The
ments taken o n site on practical installations have ,net leak-off flow is thereby reduced and good sepa-
confirmed separation efficiencies in excess of 95% liition efficiencies have been reported from rig tests.
SWIRLER BLADES
EYTRACTlON STEAM BAANCII
/
for an inlet wetness of 12%, and 93% at very high 'The performance of this type of separator has not
moisture contents above 20%. lhowever been repeated o n site, possibly because the
ISWIRLVANES
A major f a d o r in achieving these high efficiencies drainage systems are less than adequate on site and
is the growth in droplet size from a mean diameter of also because of the difficulty, expressed above, o f
about 10 microns at HP turbine exhaust to about 120 reproducing an a n HP turbine exhaust water droplet
microns in the transfer pipe t o the separator. Further size distribution in a test rig.
agglomeration of water films o n the surface o f the
COLD
REHEAT STEAM
swirler blades results in droplets o f about 240 micron
STEM diameter being centrifuged to the louvred drum. Wire mesh separalors
iNLEi OUllET
Erosion and corrosion are minimised by employing The early designs of combined moisture separator/
suitably resistant materials in areas subject to im- rehcater supplied by GEC, Asea Brown Boveri and
pingement. At the separator inlet, where moderate Westinghouse incorporated a wire mesh separator.
steam velocities and water droplet sizes generally prevail, The water separation characteristics had been sub-
2.25%Cr I%Mo steel is used for the inlet pipe and ject t o theoretical and experimental investigation and
cone pieces. In the main steam space, where velocities was established in a number o f industrial applications.
and droplet sizes are greater, the swirler blades, louvres Brodie [41, who studied the extraction properties of
and internal cladding o n the pressure vessel are of wire mesh in an atmospheric air/water flow, had de-
12% Cr low carbon steel. The basic pressure vessel monstrated that a residual steam wetness of 0.1-0.2%
PIG. 2.IW Cyclone separator Is manufactured from carbon steel. could be obtained but only over a narrow range of nc. 2.101 High velocity cycione separator
230
Turbine plant systems W e t s t e a ~ nturbine plant
\,cry lo\+! ilcam velocities of the oldel o f 1 - 2 m/s. is collecled on llic sloping bas? of each tray aii(l i~lenicnts do not lhave a clear uppcr limiting velocity
I'iirthes tests carried oul by GEC coniiroied that good drained to she base of tlie vessel tliroulih funnels ail<l :ind are tlierefoie moi-c tolerant af possiblc excessive
separation performaocc could be cblaincd for cross- pipcwoik. Irlcal velocities. Chevron separator performance also
over conditions in w a stcam turbines and gavc good A scheme devised by GEC is shown in Fig 2.103. leilds to be as good as wire mesli performance at
correlation with thc previously predicted upper limit- Steam enters froin tile base o f the vessel and is dii i~ricetile steam velocity. Modern designs of chevron
ing velocity. These, and other investigations, showcd tributed along the length of the vessel by a series ni aeparator regularly extract 98% of the watei from
that wltcr is cxlracted when the approach velocity is perforated plates which also act as water collectols, 12% wet H P exhaust stearn. Because chevron sepa-
siifficient t o cause inertia lmpactio~i of droplets o n Each hole in the distribution plates is provided with $1 rators are able t o give satisfactory performance at
the wires o f tlle mesh. After deposition, the droplets raised lip on the upper surface o f the plate t o prevelil lhigher steam velocities, they require a smaller frontal
coalesce and run along the surface o f the wire under the separated water draining into the steam flow a110 iiica for the same steam flow, giving a more compact
the Influence o f gravity until they reach a point where becoming re-entrained. The holes are o f such a sizc ;lirangement.
two wires cross. This point soon becomes overloaded and pitch that they ensure diffusion and downstreain Chevron separating elements are produced in various
with water and large drops fall from the mesh against mixing of the steam. Water is collected in drainage fol.rns. Basically, the elements are parallel corrugated
the direction of the steam flow. troughs set into the perforated distribution plates and ~)ialeswhich induce separation of the water droplets
The wire-mesh mats must be disposed as near hori- is led to the bottom of the vessel. From there, tlic by inertia and impaction. Earlier types incorporated
zontally as possible and, in view of the necessary low separated water is piped to a heater i n the feed train. Iiooks or stops in the corrugations to induce even
velocity, the mats have to be very large (80 m2 for !inore sudden changes in the steam flow. Thcse elements
a 300 MW machine). This, in turn, requires a steam were complex t o make and the slight performance
Chevron or corrugated-plate separators
distribution system capable of coilecting and draining in~provementdid riot warrant the additional complex-
the separated water falling from tile mesh without Although mesli separators arc most effective in re. ily and expense. Current designs employ simple cor-
causing re-entrainment, or impairing the uniforrnity moving moisture, their major limitation is the massivc rugated plates, sometimes with curved sides or, more
of the steam flow. Different manufacturers achieve size imposed by the low iimiting velocity. A mesli recently, with flat plates in a zigzag pattern.
this using different ingenious methods. Figure 2.102 separator which is almost 100% efficient at 1.5 m/s The droplets captured on the corrugated platcs
shows a cross-section through an Asea Brown Boveri may only be 60% efficient at 1.7 m/s, since the steam coalesce to form a film of water which drains down
arrangement. In comnlon with all mesh separator velocity is then just sufficient t o prevent the watel Iiie corrugations. If this film is allowed to accrlmulatc
designs, the wire-mesh mats are conveniently incor- falling, and re-entrainment occurs. Chevron s e p a r a t i n ~ over a large depth of plate it could grow to a thickness
porated in the same vessel as the reheater tube banks. which would result in re-entrainment of water by the
Steam is channelled along the lower side of the vessel sleam flow. Hence, the chevron plates must be either CHEVRON
o f a limited depth or the corrugations must be fitted SEPARATORS
(the left-hand side in the figure) and directed dia- REHEATED STEAM
gonally through three mesh trays in parallel. Water REHEdiER with water-collecting channels shielded from the steam
TUBENEST
Ilow. The design of the final drain-collecting device, at
the bottom of the vane, also requires detailed atten- FIG. 2.104 Cross-section of rwo-stage MSR with
lion to ensure that it does not induce re-entrainment. ellevion separators
A typical MSR design using chevron separators is
shown in Fig 2.104. After general steam distributioi~
within the vessel, the flow through the separators is structure is supported a n two integral tubular sup-
controlled by perforated plates located in front of ports which penetrate the shell and provide support for
tach packet of chevrons. the tube elements and integral framework. The tube
In order to avoid any problems from wet steam elements are therefore allowed to expand vertically from
erosion and off-load corrosion, components used in this tubular support near the base inside a sliding
tlle construction are normally stainless steel. Separator linkage arrangement. The tube elements are also posi-
plates, for example, may be in austenitic stainless steel tioned centrally within a support frame which locates
and the distribution plates in 13% chrome ferritic the elements inside the shell and ensures that the shell-
steel. Internal supports for these elements are designed side steam does not by-pass the tube elements. A full
l o avoid resonant vibration and lo allow for differ- diameter bolted joint is provided near the top of the
cntial thermal expansions. shell t o allow the upper dished end to be removed for
access t o the tube elements.
Each identical tube element contains a number of
13.4.2 Steam-to-steam reheaters straight externally-finned tubes welded into similar up-
per and lowei headers. Welding is done with an auto-
matic TIG welding system, using a two-pass technique
Vertical reheaters
followed by full NDT. The headers are rectangular in
Vertical reheaters have been developed in recent years section and trough-like in shape, the side opposite
by NEl-Parsons for Canadian machines and by Deutsche the tube sheet being in the form of a coverplate or
Babcock and Wilcox for machines in Europe, parti- lid. The covers are bolted t o the headers and a soft
cularly in Germany. metal gasket is incorporated between the cover and
A typical NEl-Parsons deam-to-steam reheater is the trough section to ensure a leak-tight seal.
Flc. 2103 Croro-seaion of an eariy single-stage MSR
shown in Fig 2.105. The shell consists of a large ver- The tubes in each element are arranged in a narrow
FIG. 2.102 Wire mesh separator with mesh seDararors tical cylinder with dished ends top and bottom. The rectangular pattern with the long span being perpen-
232 233
Titrhine uiant svstelns Chapter 2 \Met steam turbine plant
rather tiiaii the heal transfer coefiicico1 o f the exiendcil ii1:lles most bc Silted w'illi carc la ensure lhai no floor. Shell-side relief is normally accornlllodalcd oil
tube surface. ll;linage occurs to the lube fins on assembly. By ad- vcsiical schcaters by a coinbinatioii of burstillg dia-
On recent wet steanl machines, economic factoii .iiisiing the sPacill'2 01' these plates, the vibraiionai phiagins and pressure vali,cs i n the blot le],cat
dictate two stages of reheat. The exhaust steam from ~:ll:~~acteristics of the tube can be arranged to be lines between tiie re~,eate,.a,ld tl,c interceptor
the external separators is directed across the outsidc clcay o f damaging vibrations, w~hether rnccl~anicall~
o f tile tubes in a single pass in a manner which is very r18 Slow-induced.
close to pure crossflow. The reheating steam is supplied Oil-load detectioi~ o f tube leakage be deter. I I ~ ~ I separaror rehealers
~ ~ o I ' ~ z omoislure
t o the upper header of each tube eiement and condenses milied by isolatitlg each tube element and comparing The overail size of the MSR vessels incorporating wire
on the inside o f thc tube. The condensate is piped fro111 lllr internal 'settle-out' pressure with the prevailing mesh separators was originally governed by the Ilro-
the bottom header and passed to the feed train. The i;l~cll-sidepressure. vision of sufficient area of horizontal mesh. It was
heating steam supply t o the elements through which the l1 Canadian units, in the event of any tube leak- most convenient to dispose the vessels horizontally
separator exhaust steam first passes, is obtained from the particuiar tube element is isolated until it and position the heater elements above the mesh. The
iiEhTED
STEAM
a tapping o n the H P cylinder. The shell-side steam, then be replaced by a spare element at a convenient steam distribution system was beiow the mesb and the
INLETS passes through fiirthci elements, which derive their i!;ige: the leaking element tubes are then plugged. steam inlets were therefore positioned in the bottom
heating steam from the live steam pipework upstream 1 1 ) ~ elements are removed by taking off the shell of the vessel. The hot reheat connections were posi-
o f the H P stop valves. The healing elements impart a ~'r\'ei, cutting the tube-side stealn supply and drain tioned on the top the vessel.
small degree o f superheat t o the shell-side steam, whicli l>il)rs (jive or bled), and iifting out the tube element. With one vessel located each side of the L P cylinders
then enters the LP cylinders through the LP inter^ I l l c i.cplacetncnt o f a tube eiement is sitnpiy the re- at engine room floor level, the cold reheat pipework was
ceptor valves in a condition almost identicai to LI' rcrrc o f element removal. routed from the H P turbine exhaust to the bottom o f
inlet conditions in a fossil-fired plant. A tnrobienl wit11 vertical reheaters is tiiat the maxi- the MSR and the llot reheat pipework from top of
Occasionaily a smail percentage of inlet steam from !!Iliili height of the crane hook has to bc sufficient the vessel t o the ~p cylinders.
the separator exhaust is allowed to pass on either side, it1 tile heating elements out vertically. TO reduce With the adoption of inciined separators,
and also around the top and bottom, o f the tube hailk 1111: ;llnount of cutting during dismantling, the live it was no longer necessary to limit the stealn distl.i-
and finally exits with the superheated outlet steam. iitlii i'lcd-steam pipework normally enters the shell butio,, system to the lower section of vessel. A
This by-pass steam cools the reheater outer slleli and :Ir lhe side wall rather than through tile shell typical schematic of a two.stagc MSR is
minimiscs the vessel deformation which can be caused This pipework from the sheli wail to the ele- shown in Fig 2.106. he steam is introduced into $he
-u by the temperature rise in the sheli-side steam as i t
BLED
STEAM
LiVt
SIEANI
passes from one side of the vessel to the other.
DRllNS DRAWS On NEI-Parsons reheaters in Canadian machines,
all components, with the exception of the tube elemen
FIG.2.105 Vertical type relleater header-gaskets, are made from carbon steel. In orde
t o protect the heat transfci surfaces on the inside
and outside of the tubes from rusting during pro-
longed shutdown periods, heated air is blown througll
dicuiar t o the direction of the shell-side steam fiow. the reheater elements on the sheil side to keep tilc 'led on its own foundation from the basement and the separator eiements, TO op.
This results in the minimum shell diameter, and faci- ambient internal temperature above the dew poinl
litates element interchangeability and ease of nlanu- This prevents rust forming on the outside o f the tubes
facture, erection, leak detection and replacement o f and the shell internals. The tube bores are protected
L ~ VINLET
ESTEAM
elements, if necessary. during shutdown periods by nitrogen blanketing. Ex-
Steam condenses as it passes down the tubes and ternal erosion-corrosion of the tubes, tubeplates and HOT REHEAT
the vertical tube arrangement obviates problems o f vessel at full and part-load is minimised by limiting
slug-water flow that can occur with horizontal con- the venting and flow velocities. Wet steam erosion of
figurations. Complete drainage during shut down or thc tube bores is minimised by using low reheating
eiement isolation is also ensured by the vertical steam velocities o f the order of I m/s and a downward
arrangement. flow direction which results in a steady annular flow
The heat transfer coefficients are very different o n pattern.
the inside and the outside of the reheater tubes. On The tube length or support has to be arranged to
the inside, where the heating steam is condensing, the ensure that the natural frequency of the tube bundl
heat transfer coefficient is much higher than o n the is clear o f machine frequency, low harmonics of m
outside which is in contact with the nominally dry chine frequency, flow-induced Karman vortex sheddi~
steam at low pressure. Externally-finned tubing is frequencies and acoustic standing wave frequencie
therefore used to enhance the heat transfer capability Tube diameters are normally chosen t o ensure th
on the shell-side and hence reduce the total number the tube natural frequencies are clear of aeroelast
of tubes, reheater size and shell-side pressure loss, frequencies, but tube first-mode natural frequenci
compared with an unfinned tube arrangement. The have been found close t o acoustic standing wave f r
length and number of tubes and the fin profile are quencies. In a n attempt t o avoid this, horizontal su
chosen o n the basis of a cost optimisation. The critical oort olates adjacent t o and within the tube element ar
variabie in this cost optimisation procedure has been
found t o be the pressure drop across the reheater, FIG. 2.106 Typical horizontal two-stage rnoisluic separaiorrelleatci
Turbine plant sysrems Wer sreain .turbine plant
elation, i t is ncccssary la segregate llle incoining caul sidcs o l tiie ii~bcs. The relatively l o x iatc piiatc tubes, to balance the plessilic drop lliiougli
steain from tiic reheated steaol. A close-fitting slil-oiid translei between superheatcd sleanr and the tii1,c ti i llic vessel to perinit lubenes! replacement: thc incst to the extent tilat, wilir a slllall veot flow, llic
is theieforc often provided to guide the stcan) from the el.aIly dictates llic use o f extci,lally-finned tnhe!,. i i l ~ l hc a rare occu1,rencc and might not be titbe temperatiisc diffcreirtials are maintained at an
relieatel to the outlet connections. Where the hot shroud Early designs of MSR were based on p~ii,li ili the life o f the plant. Leaking lubes de- acceptable level and thermal st~.ainsare minimised.
is in close proximity to tile outel. shell, it lmay require predictions of the ircat transfer and prcssure d l rncleased lheating stearn flow woi~ldnormally Vent lines are normaliy ied to healers in tiie feed
a thernlal shield t o prevent local heating and distortion flo\$, across tubes. However, the condensation j i oiit of service by plugging. trains for thermodynamic recovery, but on start-up
o f the shell. T o cater for temperature differentials, which inside tile tubc produces a two-phase flow wli obes are suppoitcd by drilled plates spaced so and low-loads it is sometimes necessary to provide
could cause unacceptable distortion, the earlier shroud the time was not fully understood. The con ,ithe most cxtrcme conditions of operation a slightly enhanced vent flow. An additional line is
designs were divided into a number of panels held in were therefore simulated in tests which showcil I >noharmful vibrations. The distance between then provided which is usually routed to the condenser.
place by clamps, which permitted relative movement the flow was initially stratified and progressed lhv jpiiits is such as to limit any vibrationaliy- It is possible for conditions to arise which cause
without significant leakage. In a Swedish unit, a com- wave-flow and slug-flow to plug-flow a t the tube .tresses and the effect of the gas flow across a pressure rise in the H P turbine and consequently in
bination of pressure differential, thermal distortion and
discontinuity of shape was sufficient to cause a section
of shroud to collapse away from the clamps. The
section then vibrated in the steam flow and failed by
Eaiiy designs of reheater in the UK, using I
tubes in carbon steei, suffered extensively from e
of the inside of the tubes, particularly at the I
bends, and the impact of high velocity steanl
to acceptable levels.
llural frequency and mode shape of the tube,
ilcd in the nest, are caiculated to avoid the
nodes. It Is not possibie t o eliminate all forms
.
the MSR, these are:
Conderisalc froin the drains ianks is normally routed 'The a i r a n g e m c n i and control of thc livc steam diiii,r
to a heater Slash vessei or drains cooler Sor tiie1.- is ver)' si~iiilar to the bled-steaai drains exccpl 11i;ii
inodynamic gain. If liowcvei the heater bank is aul of rile condensate i s finally r o i l l e d l o a ihealeu flash v c ~ . i l
scivice, either a three-way valve routes the drains to further along llre fccd traio.
rhc condenser Slashbox, or a motoiised valve in the
Iilie to the heaters closes and ail emergency drain
valve in the line to the condenser flashbox opens in
response to a high level signal from the level controller A P T E R 3
in the drains tank. This emergency drain valve also
14 References
opens in response to a high water level in rlie heaters. ill Heilbrone. F. S.: Lffeeis of noscd steslii and ~ a l e upo,,
i ii~i
All valves and drain pipework must be sired to pass
ovenpeed or lavge siealii luibiiies alter sitddell loss of io;$ii:
P r o c 1Meci1C. Volume 180. Pall 3J: 1965-66
Feedwater heating systems
the bled-steam drains at maximum turbine capacity.
I21 Kcailon, W. I.: Srealli Iltrbirie llleory and piactice: Pitman
Drains tanks are sized such that the time taken to fill
131 Nel~oil.W. (i. and Walennai?. A. \\'.: Advances i ~eomirci.
?
the volume bounded by tlie tankwalls, and the upper cia1 aeroplane 1i)~drauiicfluidr: SAE Camniiilce A6, Aerosjiarr Ililrodu~tio" 64.1 Length of U-tubes
and lower limits of the control band, will be several I'iuid Power and Control Tcclinologies. Uostoii: 1974
1 Feed system design 6.4.2 Tube siipport plates
times the control valve stroking time. 141 Urodie. J. K.: Ealrainmeiii studies Phi) ~heiis: Herio~-W;,li 6 5 Bled-steam inlet
Non-return valves are usually provided in the line Usiversiiy: 1969 I.' Introduction 6.6 Ti>cirnal design
1.2 Functional needs of the system 66.1 Desuperheafing section
t o the heater flashbox to prevent possible refluxing 1.3 System configuration 6.6.2 Condensino section
of water during transient opc~.ation, or backflow to 1.4 Component design parameters
the condenser flash vessel from the heaters in the 1.5 Compon~nflevels
1.6 Maintenance 01 system water content
event of valve malfunction. Since MSR vessels are 15 Additional references
situated at or near engine room floor level, sufficient
1.7
1.8
Protection against usc of contalninaled feedwater
Protection against ingress of waterlateam to
- , ~~~~ ~
Uergscxarrer. G.:Reii~ioicerlconcrete Soi~ndacioiisroi sican? tarbil~c. 6.9 Alternative designs of heater construction
height is available underneath tlie vessel to accommo- Elekt: ib,irir, Volt~nie59 pp 805-809: Nove#l~bei1960 turbine$
1.9 Summary 7 De-aerating feedheafers
date adequately-sized drain tanks and pi.ovide a falling 1:iiiI~eibcrl. W. A and Barncil, J. H.: Causes oS movcnlenf i8, 7.1 Introduction
drain to all possible destinations. The base o f a vertical reiniorcetl concrete turbo-blocks and dei,elopme~>rill turbo-bloc!. 7 HP feed svstem 7.2 TiieimaIIhydraulic design
reheater, however, may be low in the turbine hall design and coiirirudio81: P ~ OIhlecLE.
C VOI~IIII~ 181. Par, I No 22, 7.3 De-aeietor construction
and a positive static head may not be possible for all pp 589-614: 1966-67 8 LOW pressure heaters
2.3 system configuration
operating conditions. In this case, it might be necessary 1:iinl. I.J.: Plasl arpccir o f lurbine generator rouiidniiooc: Pror. 8.1 lntrodu~tion
2.4 HP heater drains system
IMechE, Volurile 181, Par, I No 22, pp 567-578: 1966-61 2.5 Pipewoik arrangement 8.2 Surface type low pressure heaters
to provide a pump which would have to be sited in the 8.3 Construction of iow pressure heaters
basement, or even in a pit, in order t o provide the itaupi. L. and Frobs1 P. H.: Civil engineering and vibratioa aspect, 3 De.aeratof System 8.4 Water header, tube bundle and sheli
or steam iuibinegeneiaioi foundations in Germany: Proc. IMechE. 8.4.1 Tube thickness
appropriate net positive suction head. Otherwise par- Volume 181. Par1 I No.22, pp 579-588: 1966-67 3.1 Introduction
3.2 De-aerator heater 8.4.2 Fiow srea thickness
8.4.3 Tubeplate
ticular drains might have to drive against an adverse
Piaefckc, R. 0.: Steel foundations for tile suppoi, o f high-speed 3.3 De-aerator storage tank
static head. snachinery: i'rac. IMecliE, Paper C7: 1983 3.4 De-aerator elevation 84.4 Wafer header wall thickness
3.5 Piotecfion systems 8.4.5 Wafer header branch thickness
3.6 Protection valves 84.6 Compensations for openings in the waterbox
,a 3 7 Plpework 8.4.7 Shell and dished end thickness
8.5 Heater tube lenglll and fube supports
i 3 8 Boller feed pump sucfton f~lters
85.1 Tube support plates
2 4 LOW
41
pleESUre feed system
Inilod~~ilon
8.6 Bled-steam inlets and drain outlets
8.7 Thermal design
42 Low pressure system configurat8on 8.8 External drain coolers
43 Plpework and valves 8.8.1 Thermallhydraulic design of a fiashing drain cooler
88.2 Thermallhydrsulic design 01 a water-to-water drain
5 D B S ~ S o~f Sfeedheafers Coder
6 Hlgh PIBJSUrB feedwafer heater* 8.9 Direct contact low pressure heaters
6 1 Functronal needs 9 EvaporafOrS and other means d water treatment
6.2 Con~trucfionof high pressure heaters 9.1 lnirodu~tion
6.3 Wafer header, tube bundle and rheii 9.2 Types of bied-steam evaporator
63.1 To find tube thickness 9.3 Sulface type evaporator
6.3.2 Area required for flaw through the tube bundie 9.4 Flash type evaporators
6.3.3 Tubeplafe thickness
6.3.4 Water header wall thickness 10 Future developments
6.3.5 Hesder branch thickness 10.1 HP feed system
6.3.6 Compensation for openings in the water header 10.2 Ds-aerator syslem
6.3.7 Shell and dished end thickness 10.3 LP feed system
6.4 Heater tube length and tube supports 11 References
Feedwater lieatirig s y s t e m s Introduction
Introduction 1:oi all slationi, tllc SVI' is 160 bar; thc ill ' I I' llcalci syslellis a,hicli weie 1iiL.n current!? route was pruvidcd for tlie B1:P'T enhaus1 to tlle coo..
llcgeoerativc fccdl~calinglhas long beco iccogilised as 565°C for coalfired hoilers and 538°C for oil 1 dcnsci, llie BI:I"I' wiild also be itin-up will1 llie alaiii
a means of improving turbine-generator plant effi- boilci-s. 'The cold rclieat pressure vai-ics b c l ~ v r i ~ ~ i concluded from the review, tllat r u b ~ ~ i asui-
r unit. 0'1 irrcreasc cycle efficiency, lhcalcr bleed poillts
ciency and the first practical installation was on a atid 44 bar. As all feed systems for these onil, I I P lheatei feed systems weie more cost on the BI:I37 are provided. However, more Illail onc
3 b1W set in a British gower slatioii at Rlaydoii Bul.ii cold reheat ( H P turbine exhaust) to stlpp lnd they have been used for all subsequent healer attached lo the BFPT can cause difficulties
near Newcastle-upon-'Tyne in 1916. tlle final licater, the final feed tenipeiatiire ( in the fccdlieaters downstreani of the heaters from the
From this modest beginning the modern fcedheating only vary by a small amount doc t o the c f i il size increases, so does the power needed BFPT. The manner in which the BFPT bas been
systeni has evolved, a typical feed system consisting of small variations in cold reheat pressure and I llle boiler feed pump (BFP), which is about integrated into the various feed systems is show11 in
sin to eight heat exchangers, each bleeding steam from ininal temperature difference (TTD) o f the fin;il I 01 main unit output. Multiple electrically- Figs 3.1 t o 3.6.
the appropriate turbine cylinder. heater. 1ll;l's could have been used but a more cost Cooling of the generator by condensate is not
T h e economic justification for the use of a parti- Because of the economics of the advanccd I,C solution at the time was to provide a tur- employed for the latest units. The complex and costly
cular configuration of feedheaters is given in Chaptcr cooled reactor (AGR) cycle, a lower final feed Iiiving a full-duty feed pump. From Figs 3.1 arrangements needed to ensure maintenance o f prime
i of this volume, in which it is explained how the perature o f about 156°C was specified (see Chal~t ii is seen that each system uses a back pres- and freedom from boiling o f stagnant condensate in
theory of regenerative feedheating is combined with which has resulted in a feed system having thi. ltithine as the BFP drive. Steam is taken from generator coolers on cessation of condensate system
the economic information the purchaser makes avail- aerator as the final heater. I l l cnlraust, expanded through the turbine and flaw was the reesan why a simple cooling package,
able to the manufacturers to determine the most Thc relevant cycle details for the feed system I to the main turbit~eor t o a heater. A live with indirect coolers using condenser cooling water
appropriate number and disposition of feed stages. pressurised water reactor (PWK) are also shoi\il ru,ply from the main boiler is provided on (CW), was developed and is now used. Thc loss in
When the ideal cycle has been evolved, it is tho] used Fig 3.6. ation o f boiler feed pump turbines efficiency is accepted in return for increased opera-
as a basis for tlie determination of a practical design. The steam caaditions for the 660 MW PM'I' to enable the turbine to drive the feed pump tional integrity and simplification, with consequent
The economic need to replicate proven turbine and 67 bar, 0.25% wet, result in the stop valve flow I, dl conditions of unit load. As an alternative reduced maintenance costs for the condensate system.
feed system components, whenever practical, places approximately twice that of a convention
restraints o n the manufacturer. Usually these are o f a unit and, in consequeiice, all flow c o m ~ o n e n t sini
minor nature and will only changc the ideal blccd be approximately 1.5 times tlicir normal size I
point pressures by a few tenths of a bar. Thc minor coinmodate thc doubled flow. The I'WR feed
loss in efficiency is accepted in return for the use o f is also more complicated than conventional f
proven plant and the lower cost resulting from the fired units as provision has to be made to a
replication of existing designs. reheater a n d separator drains into the feed system
The main parameters for the feedheating systems all conditions of operation, as shown in Fig 3.6.
of a range of typical modern 500 and 660 MW units Table 3.1 shows that the latest stations, such
are shown in Table 3.1. T h c corresponding heater Littlebrook D and Heysham 2 , are provided witli
arrangements are shown o n Figs 3.1 to 3.6. bular surface type heaters t o the exclusion o f
The turbine/boiler main cycle parameters of stop 'direct contact' (DC) heaters (i.e., feedwater and h
valve pressure (SVP) and stop valve temperature (SVT) steam in direct contact within the heater shell).
have been standardised for all modern fossil-fired 500 changc in design philosophy was the result of a
and 660 MW units. view, in the early 1970s, of the cost effectiveness
-
Sl01, Final Number of Tyne o f Fig ref
Sil" valve feed stages 1.P
pressure lenip heater
(bar) (OC)
Oil DC
Grain Oil DC
Oil Surface
Drax
Coal Surface
Heysham 2 660 Nuclear 159.6 538 45.2 156.4 0 4 Surface 3.5
Projected
PWR unils 660 Nuelear 66.77 + 5.86 226.7 3 4 Surface 3.6
water level in the tank is restored to its normal work- caused to turbines by the ingress of water or a water/
ing level. If the dc-aerator tank level is higher than the steam mixture from the feed system have been reported
setpoint, the outsurge valve is opened and the excess [3,4,51.
- from the svstem to the RFTs until
water is dischaired There are scvcral potential sources of water within
normal working level is restorcd. The method by which the feed system which can flow or be induced into the
lilese systems are integrated into the L P feed system is turbine. The potential sources are as follows:
iiescribed in Section 4 of this chapter (a) High water level in an H P or L P feedheater. The
high water level could be caused by a tube leak o i
failure of the drainage arrangements.
1.7 Protection against use of contaminated (b) High water lcvel in a de-aerator. If there is a
feedwater mismatch between inflow and outflow the vessei
Siiould there be an inleakage of cooling water into can flood.
the condenser, the feedwater to the boiler could be (c) Undrained bled-steam lines. When the bled-steam
contaminated. Contamination of feedwater can also is wet, tlie water in the steam is deposited on the
result from the inadvertent release of chemicals from a pipework walls or is separated when a valve or
polishing plant. bend is encountered. Condensate is also formed
Modern boilers can sustain severe damage from on start-up, while the lines are being warmed to
contaminated feedwater. T o prevent feedwater of an operating temperatures.
unsuitable quality beinp fed to the de-aerator storare
tank and f'om there to
the boilers, or outsurged t o
In the case of items (a) and (b), if the rising level is
the reserve feedwater tanks, protection valves which
are tripped shut on high conductivity levels are placed allowed to continue unchecked, then it could flood
upstream of the outsurge connection and downstream into the bled-steam line and back to the turbine.
of the polishing plant (if provided), as illustrated in With regard to item (c), if there is continual fall from
Fig 3.14. The hardware and detail design is discussed the points where the water is accumulating towards
in Section 4 of this chapter. the extraction point on the turbine, it will most cer-
tainly flow against tlie steam flow towards the turbine.
The other means bv which water o r a water/steam
mlxture can be induced into the turbine is by a pres-
against ingress of water/steam sure reversal between the feed heaters and the turblne
FIG.3.9 Piclorial iepresenlation of the relalive levels of heaters and feed pumps for a po>vei station using horimnfal to turbines bleed ooints. A oressure reversal is caused bv a unit t r i ~
HF and L P tubular surface type feedheaters
Many well documented instances of damage being or a sudden load reduction.
254
Feedwater lheating systems
"aL"e8 A,#oPeN#%
SPI1INTCLOS,MG
-- "AL"clo"AINT*IY
~ C O W ~ A W , ~ " ~ . ~ ~
LlYlilNCONDiNSliiB
,
, f
~~Cm~~~, ,
To9IULO(ooPrNT#m
nc. 3.14 Devices installed ar nrotection against the use of caniarninalcd feedwater
~*~S"UlilYALI1.
~-
~-
Ir1SULGI"ALYE
((1) A non-return valve is placed in the bled-steam line cuits to close the protection valves.
as close to the turbine bleed point as practicable.
For the de-aerator and H P heaters, these are In some instances the pumps which discharge to
a particular heater are tripped.
power-assisted non-return valves. For the LP heater
bleed points, free-acting valves are normally pro- (f) All bled-steam lines have an adequate fall towards
vided. On very low pressure heaters, the omission a drainage point. Each drainage point is capable
of the non-return valve is permissible if the con- of draining by gravity t o the drain receiver vessel,
FIG. 3.13 Typical ilisurge and outsurge system ditions given in (g) have been satisfied. which is at condenser vacuum. Any pockets of
(b) Power-operated bled-steam isolating valves are water which can be formed by the closure of valves
provided on each line between the turbine and a have drains,
return valve, the bled-steam isolating valve is also Flow in both normal and reverse direction must heater, as close to the heater as is practicable. Again,
arranged to be shut on unit trip. (g) In the case of very low pressure heaters such as
be considered and, where provision to prevent flow on very low pressure heaters the isolating valves turbine moisture extraction condensers (which ex-
Reverse steam flow can also carry quantities of in one direction is provided, care must be taken to can be oinitted provided the conditions given in (g) tract a steam/water mixture before the last blade
water from heaters and undrained low points in the ensure that there are no 'sneak' paths to bypass thc have been satisfied.
bled-steam lines into the turbine and cause damage, in the LP turbine), the pressure drop caused by
protection. It is evident that the protection system the isolating and non-return valves as specified
particularly to the large LP turbine blades. These must contain flooding and also prevent back flow of (c) Feed or condensate isolating valves are provided,
'back flows'can induce cooler steam into hot cylinders, where appropriate, to shut off the supply of water in (a) and (b) may be unacceptable so, instead,
steam. duplicate unvalved drains (which can drain the
with the consequent risk of thermal distortion. The following provisions (illustrated in Fig 3.15) to a heater or group of heaters.
heater by gravity alone) are provided between the
This is an example of how a system must be have been made on all 500 and 660 MW units withi,, (d) Duplicate level sensing devices are provided on heater and the condenser. The feedwater flow to
designed to allow for all conditions of operation. the CEGB to prevent these possibilities: each heater, either of which will actuate trip cir- the heater is also isolated in the event of a high
UP feed syslenl
FIO.3.16 Diaillaee airanaemenrs for very low oresrure l>eaters without valves in bled-seam lines
b%, these principles are expressed in terms of detailed 2.2 System parameters
stem design, the feed system description has been The final feed temperature (FFT) out of the ultimate
,lit into three sections, viz: HP heater is fixed within a few degrees by the bleed
pressure and steam temperature available to the heater.
HP feed system. On all current 660 and 500 MW units, the bleed point
is the HP exhaust or 'cold reheat' pressure.
De-aerator system and associated plant. The feed temperature out of a heater is conditional
on several factors. First, a bled-steam pipework tem-
LP feed system. perature loss, usually l.l°C, which is subtracted from
the saturation temperature equivalent of the bleed
FIO.3.15 A typical feedheating plant - rhowing proteetion eauipment point pressure. The resultant temperature is the sat-
uration temperature equivalent to the pressure of the
HP feed system steam entering the heater shell. The heater thermal
performance and hence its heat transfer surface is
water level in the heater. The protection provided of protection relay and associated tripping circuils determined by the values of the temperature terminal
is illustrated in Fig 3.16. are described in Volume F, which deals with control differences (TTDs) on the steam and drain sides.
and instrumentation. 2.1 Introduction The steam TTD is defined as the temperature dif-
The HP feed system is defined as the group of heaters ference between the saturated steam temperature at
Recause of the short tlme scale in whlch the com-
~
and associated equipment whlch is situated in the feed entry to the heater shell and the feed water leaving the
mencement of water feed back to the turbine can pipework between the boiler feed pump (BFP) dis- heater. The drain TTD is the temperature difference
occur, all protection measures are automatic and the 1.9 Summary charge and the boiler. Their function is to accept water between the feedwater entering the heater and the
~-~each tvne The ~revious sections give an outline of the maill from the boiler feed pumps and raise the feedwater drains leaving the heater. To achieve optimum HP
hmrlwnre nrnviaiona
r.......... for , of heater is detailed
-~~~~~
~
r
in the appropriate section of this chapter. The types principles for overall feed system design: to explain temperature to the final feed temperature heater performance, it is usually necessary to partition
B
~- ....
e bled-steam isolating valves close o n all heaters In the event of sequence malfunction, it is possible to
have both isolating and by-pass valves shut a t the
~ ~
"lGIIW"TERLEYELTR,P
HIOHWATLIIICVEL ALARM
N O W L L WORKINCIIEVEL
- IROMFEEDPUMP
1 BLEDSTEAMNONREIUI~NVAIVEHP"IISPRINGASS~ST~DCLOSINC.I
2 B L L D ~ E l M N O N R E i U i l N Y A V E H P W SPRNGbSSiSTEOCLOStNCi]
3 BLLO~EAMISOLATINC-VALVEnnA(M&noPmATaa,
1 BLEDSTEA~ISOlA-IIN(.V*IV~~P~lMOPilROPERmEo
6.
I BhNYNLEIIELDWATERISOLAT<MOVhLYE
BANKNLLTIECOWA~ERISOWT<NOV~LVE~IPN~VALVE MO/OROPER~~~~)
MOTOIIoPEbATLD
I WNKOUTLEIFEBDWAICR1SOLhitNCiVALVE(MOIIIROPEkATECI
8 SPRINGLOADEDBIPbSSVALVES
11 118 the spring-loaded by-pass valves. rate of flooding, the time for the water to rise from
Another principle in current use is to utilise the the normal working level (NWL) to the bottom of
n the high pressure feedwater to close the the bled-steam connection is about 8 s. T o provide a
olating valves. The use of feedwater energy margin, a factor of 2 is used to allow for the valve
a1 When fop healer bypassed Ieedramr
temperelure to mils, -mvc bl One ban@bypa$reddue
IOfBYIlon lop hsafer
in bank-
€0 x2517 + 40 x 185.4 asons why medium-actuated valves were con- meet these needs, valves with a closure time of about
= 2,5ec
1w : reliability and speed of actuation. 4 s are required; however, the flooding time of vertical
Pic. 3.18 Configuration! single
lor-operated parallel slide valves o f the size HP heaters can be extended by making the steam
double hanks o f HP heaters
ircd for HP heater isolation duty have a mini- pipework loop vertically to a suitable level before
265
Feedwater heating s y s t e m s
.
of the heaters), a n d the slowing down of the closing sure head t o raise the drains t o the de-aerator stora contacts are houred in 5 and 6 in the terminal block. The (c) Mobrey float switch arrangement using condensation
stroke over the last few millimetres to ensure that tank. The drains are then diverted t o the condens switch assembly is mounted in a waterproof housing 9 method. To on-load-tesc column 3:
n o hydraulic shock can occur due to sudden valve
closure. As the feedwater isolating valves have a
T h e converse applies o n increasing unit load. In this in
stance, the level in the heater is used t o determin
which b attached to the "on-magnetic siainless steel
diaphragm nange 7. The whole assembly is ciamped to the
standpipe or flosf switch chanlber by the back flange 8. . Switch ~olumn3 to IICSL' state
Ciose valve g
Wait untii the rcrt lamps indicate that float switch
protective function, high integrity is important. T h e
use of the feedwater as a medium to close these valves,
ensures that a pressure source to actuate the valves
is always available and the actuator can be made t o
t h e destination of t h e drain water. A rising water level
in No. 6 heater opens the control valve to the No. 5
heater flashbox or t o the de-aerator storage tank. Th
destination chosen is under the manual control o
(b) Mobrw float switch arrangement using vaeuim to
. .
lift the water to on-load-test the switches. To on-load-test
eoluinn 1:
Switch column I to 'lest' state
Close vaive a
. . ~CIUBICS correctly, typically up to 30 minutes.
Open vaive g
Check that test lamp indicates char water level ir liaw
below trip level
Switch columni and repeat prac~duie
268
OLZ
Llwa!uahuoa aq 01 voMad!d aql smolle lnoLer ialeaq s! qlomad!d meals-palq marua%ue~~e
JO n a u o a ar!,L a1no1 ale!idoidde aql !lassan qseu lasuapuos aql 01 30 sanu!luos [anal IaIeM aql 'lolaiae-ap aql 01 pa%~eqa
~e~uoz!ioq a q 'la~eaq
~ lea!llan e 103 LZ'E 8!d pue i n o ~ e l luawa6uelle y ~ o ~ a d ! ds.1 [assah qseu aql 01 su!erp ialeaq lsai!p 01 aseqd!~ue u! -s!p aq louues lam* aql uaqm 'peal i!un %u!glej u o
laleaq d~ leluoz!loq e l o j luawa%uslle yiomad!d S u ! y l o ~'p pue g sanpn uo!laalas alnol su!elp j o asn 'iasuapuos aql 01 au!l aql u! aqeh l o i ~ u o su!eip aql
aql smoqs 92's ain%!d 'anleh uo!lelos! ue jo %u!uado Lq palaalas s! atno1 sukeip ~ a l e a qd~ 8 'ON a q ~ suado uaql laha] l a l e ~4u!s!l aql 'yuel io~erae-apaql
uo ylomad!d aql %uole l d a ~ sBu!aq ~ a l e mJO slaysod ',8u!?unq, luanaid 01 01 su!elp iaieaq d~ aql IJ!I 01 ~ua!s~jjnsu!s! ~e!lua
SWa~alds ! q ~'pau!elp ale pasola aq plnoa qa!qm sah~en palunow saqal!ms leou Lq 'papaau se 'pa?le)s piia peal %u!s!l pue %u!llej uaamlaq ohor lnoqe Lq lasjjo -laJJ!P alnssaid aql j! !yuel lolelae-ap aql 01 ahleh
uaamlaq suo!laas leql alnsua 01 uayel s! ales fe!sads paddoas ale sdmnd aqL 'Ilamloq lasuapuoa aql o i ~ l sle Laql :lu!od lahoaZusq:, aql au!rulalap 01 pasn ale ~ o i l u o asu!e~paqi suado ISXJ ialsaq d~ s .ON aql u!
.yiomad!d aql u! lu!od sdwnd su!eip Lq padwnd ale lassah qseu lasuapuon Sa!pl!MS alnssaid OMJ, .au!qin$ u!em aql uo saqs~!ms laha1 lalem 8u!s!1 v 'lasuapuoa aql l o ~ u e al % e ~ oaql
s
uo!laallos le~nleuqaea le pap!noid are sdeil u!eip l o aql 01 pa%mqas!p su!erp aqL .rua~sLs10116oa [anal 3111 asnssald Lq pallonuoa s! 'esian as!n l o 'lassan qselj ale su!elp a q ~lo3 a[qel!ehe srro!leu!aap aql 'ialeaq
sas!J!lo Lq p a ~ ~ o n u osau!!
s u!ev ql!m slod u!elp 'pua sa!J![dm!s qs!qm 'sanlen [olauos aql 01 sleu%!s qs~!.,~ asuapuo9 aql 01 a%leqas!p i o j role~ae-apaql 01 pas!el d~ ainssald lsamol aql s! s!q~ asnesaq 'Inq aid!:,
s!ql 01'dn pawlem %u!aq s! pup plea s! y ~ o m a d ~ d 01 paau ou s! a ~ a qsahlen~ uo!lsa[as a l n o ~su!elp at{ aq w o i j qs~!ms su!erp qqqm l e IU!O~ aq& 'SZ'E -u!id iel!w!s e uo YIOM su!elp laleaq d~ JaqwnN
aql u a q ~luasaid aq Kluo plnoqs atesuapuoa ' y i o ~ Kq pau!m~a~aps! qled MOU su!e~p aql s v .y pus u! umoqs s! s ~ a ~ e ad~
q lea!lian ~I!M pala!sosse '51 AXN a41 Lq pamahaid s! ~ o ~ e ~ a e -aql ap w o l ~
-ad!d d~ aql u~ 'WOJ Lew qs!qm a~esuapuosLue JO S ~ A I E A Lq S! laleaq d~ L .ON 103 leql pue 'Z pun ISLS 1011uoa SU!E-IP ialeaq d~ a~!~euratyeu v I anleh qanoiql mouysea .iasuapuoa aql 01 a8ieqs
pau!eip Llalaldwos ale Laql leql osle pue papaasxa IOU sahleh Lq s! laleaq d~ 8 .ON U! l a ~ a 1aq1 JO forit1 ' ~ o ~ e r a e - aaql
p 01 sliaha, -s!p su!erp aql pue uado 01 papuewmo9 s! iasuapuos
ale saaueu au!qlnl aqi pue ialeaq aql uo swamow aqL 'anoqe paq!lssap saqsi!ms ainssald aql J O I noi a%leqss!p y e l p aql prle sllej [anal l a ~ e maql aql 01 au!l aql u! g anlen aql ' y u e ~io~elae-apaql
Pue slsnlql alqemolle aql leql arnsua 01 iueliodru! aql Lq pale!l!u! aauanbas anleh e Kq pau!mjalap am!] qans l!lun iasuapuoa aql 01 pa8ieqss!p uaql 01 Su!elp aql IJ!I 01 alnssald le!~uaiajj!p lUa!3!JJnSU!
su!erp a q l 'lasuapuoa aql 01 ahpn loquoa aql s! aiaql asnesaq asp 01 sanu!luos laha[ aql 31 'spaau
lo 01 leu%!s e spuas ia]lolluos lanal SI! [!lun as!, 01 UalSLS 01 %u!ploJse paqst!ms s! pue ~ o ~ e l a daql o
SJaleail !eJ!lisn lo) UalsLn ru!elp laleaq d~ uv ST( .OPJ
FIG. 3.27 ~rrangerncntof HP heater bled-swam pipework for vertical heaters at Drar Cornpietion power station
3.3 De-aerator storage tank
3.2 De-aerator heater The main function of the de-aerator storage tank is
A cross-section through a typical de-aerator heater to provide a reservoir of feedwater whicj,
272 273
PIO.3.28 Section f l ~ r o i i g l la iypicai de-aerator lhcntel
can be drawn upon by the boiler feed pumps when The highest ievel to which the condensate can
needed. is determined by the manufacturer, such that t
The capacity of the tank and the quantities o f feed- maximum velocity o f the steam flowing across t
water stored at the various Levels within the tank are surface of the water will not cause water pick-up
determined by the following functional needs: 'sloshing' of the tank content. In this context, w
pick-up is defined as water which is stripped fi
(a) To store sufficient feedwater to meet the re-
the tank surface and transported to the de-aer
quirements for flexible operation.
head by the action of heating steam. Damage to
(b) T o provide control levels for the operation of the de-aerator head internais can be caused by the iml PIG. 3.29 'Tyi>iciil de-aerator lank lei'els
insurge and outsurge systems without exceeding of the water which has been carried over. The lien
the hieh water level. can also become flooded due to the drains being II
able to cope with the extra water burden.
(c) Even when working at the top of the normal i, allow the insurgc and outsurge system to operate during a transient, the water travelling down the suc-
'Sloshing' of the tank content is caused by tl
operating level control band, to accept the con- formation of waves in the tank which close the stea niiel~eiidently without hunting. tion pipework must gain sufficient static head to pre.
tents of the condenser hotwell in the event o f the pathway and are then propelled the length of t h e t a vent boiling. The important factors are the rate at
condenser level control valve failing to the open by the force created by the heating steam bei which tank pressure reduces o r decays and the rate o f
position, without exceeding the high water ievel. tracted to the head. For a more complete expla flow down the suction pipework. The limiting case
(dl From the same initial working level as in (c), to o f the mechanism, reference should be made De-aerator elevation found for CEGB plant is a hot restart of a feed pump.
accept half-a-minute's-worth of CMR flow without paper on the subject o f de-aerator tank inst elevation of the de-aerator must be such that In this case the extraction pump is lost, the standby
exceeding the high water level. by Cranfield and Wilkinson [7]. On the latest ction head requirements of the feed pumps can fails to start and the feed pumps draw down the de-
of de-aerator, only a fraction o f the steam is isfied under all credible modes of operation. aerator tank until the unit trips or is shut down. On
(e) From the level indicated in (c), to accept water over the tank surface, the majority being introduc cal de-aerator tank and suction pipework con- unit restart, the water in the condenser which has ac-
accumulated in the condenser hotweil after a unit local t o the head. The small flow across the tank ji~urationis.shown in Fig 3.30, the tank content, pipe cumulated after the extraction pump trip, has to be
trip when the extraction pumps are restarted with- retained to scavenge any oxygen within the tank and lcngths and component elevations being indicated. pumped forward to refill the depleted de-aerator.
out exceeding the high water level. transport it to the head. The head is vented to remov la addition to the static head indicated, there is Assuming that the tank is at full-load conditions but
any accumulation of non-condensable gases. +Is0 the pressure head within the vessel. Under steady only partially full, the 100% cold condensate inflow
The rest of the working levels in the tank are dete f a t e conditions, the water within the feed pump suc- into a hot depleted tank produces a rapid pressure
Figure 3.29 shows a cross-section through a typical mined applying rules (a) to (e), above. From Fig 3. ion pipework is at the saturation temperature equi- drop within the tank. The feed pump is started on
de-aerator tank for a modern 660 MW unit. Indicated it will be seen that the insurge and outsurge valv valent to the pressure within the de-aerator. T o ensure leak-off, so the feed velocity is at its slowest and
are the various levels and the resultant actions which have been provided with separate control bands. hat boiling within the pipework cannot occur when hence the time for the column of hot water in the
are initiated. dead band is placed between the two control ban 8 sudden pressure reduction in the tank takes place suction pipework to gain static head is at its greatest.
274 275
F e e d w a t e ~hearing systems D e ~ a e r a t o rsysten?
isolation on a high watci level is no1 needed arc the forward steam flow falls to a low value. This is I
HP heater drains and the feed pump leak-offs. This cause the steam fio\v on the underside of 1111. 11
is because the feed pump leak-offs are purely circulatory creates an opening force w l ~ i c l is
~ greater tl~itli I
flows between the tank and the boiler feed pump, and spring-closing force. The hied-steam isolating
ihe roalriil \ral\rc is dcieiinii~edbp lhc sigoal i ' i < i t v I I,,imp Svoiii the disc1,;irgc of tlle dilly l ~ t ~ m l ) .
Icvei conisoilel- oil ilic dc-aclatoi, l l i c rnaxii~~iiii: O n all 500 h4W iinils and 111rcarliei 660 M W iilllls
will1 DC lhealcl-s, cooling o f tlic gcnclalai by con-
densate was incol~poralcd in !be reed rrain immc-
cliatcly after the extraction pump, as illustrated in
Fig 3.41.
The ieason for placing it in thc feed system was lo
reclaim lbe generatar losses as heat input lo thc reed.
by the opcrator as needed. lo practice, it was round tllar for large rnodern power
T o supply the de-aeratoi- with feed from the I
under emergency conditions a 30% make-up pi
may also be provided. The pump can also be used I
fill the de-aerator, avoiding ihc use of the extractio
.
stations the following difficulties were experienced:
iiiisisted-closing devices as these are not manda- average overall heat transfer coefficient has to be
101 LP heaters. found and used to determine the heat transfer surface
area needed. From the tube size and feedwater flow,
the tubenest diameter is found. With the tubenest
diameter known, the heater diameter and the main
structural details of the shell and water heater can be
ibim of feedheater design is to provide a heat determined by use of the appropriate design standard.
liigel- that will raise the temperature of the in- The length of the heater is a function of the heat
IV feedwater t o a specified outlet temperature, transfer surface needed. A detailed explanation of
I d~.awinga predetermined amount of steam from thermal/hydraulic design is given in Section 6 of this
,bine cycle. There are four groups of heat ex- chapter.
used in the feed system to fulfil this function: De-aerator head and DC heater sizes are deter-
mined by the need to accommodate the sprays or
Ir pressure feedwater heaters. trays used to create sufficient water surface area to
transfer the heat from the steam to the water, as
erator heaters. needed by the cycle. The vessel diameter and length
is determined by the need to contain the requisite
w pressure feedwater tubed heaters. number of sprays or trays.
FIO. 3.41 Diagrammatic arrangement of generator coolers is an LP feed system There are long established British Standards for the
R, pressure feedwater direct contact heaters.
structural design of feedheaters and these are used by
the CEGB to specify a uniform design standard for all
valves of the spring closing/air opening type similar pipework is shown in Fig 3.42 and shows cle lcsign of each type of heat exchanger is deter- components, materials, welding and testing.
to those used for bled-steam isolating valves. the principle of the heaters being below the cylin i by the thermal, hydraulic and structural needs Until 1976, the standard used was BSlSW 'Fusion
bottom level and above the condenser Level.
288 289
Feedwater liealilig systelns liigli pressure feedwater lieafers
)has bee11 used for ;ill liealeis ordered since 1976 and nicans by !+iricll lllc cooseqiielll lheiil liailsfcr su1'f;iCi.
will be used for all iiitoie piaot, I-'or a specific heal areas are foiiiid is shown in Seciioii 6 of this chaptel.
<WX"",,., ,mALe:,r, -,,or STCAL,
cxcbanger size, the standard is used to determine thr Figure 3.41 iilust~atesthe way in which the kcri " " ~ " ~ D L I U Y L i 3 i l i i i l r riiC:lO\
lhichness of all giessuic )parts sricli as shell, lubegiaie temperalore increases as i t passes through a t!'l~ic~il
and Naatcr header, branches, etc. 'The materials, weld two-pass horizontal heater of the U-lobc lype. 'i'lir
details and procedures, as well as relief valve capacity heater has both integral drain cooling and d e s o l ~ i ~ .
and vessel pressure testing, are also defined. heating sections as shown (Fig 3.44).
In certain specialist areas, such as heater internal The desuperheating section is placed on the oullcl
design, the 'Standards of Tubular Exchanger Manu- end o f the U-tubes in order that the incoming super.
factol-ers Association (TEMA) 1978' [I21 can also be heatei steam can raise the feedwater near to or abovc
applied. the satiiraiion temperature of the body piessuie be..
The lieat transfer cocfficients are determined by a fore it leaves the heater. 'The drain cooling section
manufacturer's experience with a particular design of is placed at the inlet end of the tubes to allow lllc
fecdheater. However, a good approximation to the outgoing drains to be cooled t o as near to the ill.
coming feedwater temperature as needed. Steam entelr FIG. 3.44 Steam axid water Flow nalhs iii u typical lhaiizo~~tal
H P lheatei
design values for surface type heaters can be obtained
by reference to the 'Guide t o the Design o f Feed the desuperheating section and is reduced in tenl.
Waler Heating Plant (BEMA) 1968' [I31 or 'TEMA perature by transferring its heat to the feedwater l(1
1978' [12]. within 27OC o f the temperature of saturation of ill?
condensing scction pressure. The steam then flows lo
the condensing section, where it leaves as water at sal.
"ration temperature to enter the drain cooling sectio~i. lining cost due to the loss of cycle cfficiency, !heaters Z CONRT S
~ R ~T L~O. ,~S ~T S
, S
~ SR~OT ,~O ~ O ~ C
6 High pressure feedwater heaters A watec seal is niaintained at the inlet to the drziin II be constructed without drain cooling sections or _,DE~UPLR~~E~INGS~OO~
.
heaters is determined by two main needs:
F ~ G .3.43 ~enlpciat~re
rise of feed water as it passes ~ i ~ o u ganh HP healer nto the back of the tubeplate by the 'Foster Wheeler method of tube attachment has been used for many
Feedwater heating systems Iiigh pressure feedwater hearers
6.3 Water header, tube bundle and she 6.3.2 Area required f o r f l o w t h r o u g h t h e t u b e
6.2 C O n ~ t r ~ ~ t iof
O nhigh pressure heaters The dominant influence in determining the thick bundle
The construction o f the pressure envelope o f vertical of various parts of a water header for an H P heatel As all H P heaters employ U-tubes, the number of holes
and horizontal H P heaters is very similar and the a given pressure on the feed side is the tube bu 1'1G 3.48 Typical forged H P Ihealer 'bottle' water to give the flow area needed is equal to the number of
only differences are the arrangement o f the heater diameter, which is governed by the liumber of t Iti.iider - monobloc consiriiefion wirh we1ded.o" branches Us. Taking a typical 660 MW feed flow and two-
internals, support feet, etc. needed to provide the flow area for the feedwate bank heater configuration:
Required area = 0.32/2 'Tile bore of the branch must be found first: if a
= 0.16 m2 city of 3 m/s is assumed, the cross-sectional a )
0.32/3.0 = 0.107 m2, giving a 0.37 m bore. Thcr
Number of holeslflow = 0.16/(1.713 x 10.') !
= 934
6.6 T h e r m a l design
Earlies in this section i t was explained how thc tem-
' guide the
Ol- water across the lubes to
'The drains water is guided tiiioiil,
section by anotiler
perato1.e of tile high pressure feedwater varies as it
bai.,.l,~s,
1)rovide efficient heat transfer.
,,
1)ermissibIe values of baffle l)itcil ; , , r
passes ti~rouglian HP heater. Tlic heater temperature
limits, coiilbined with the physical size of tube bundle
from a design code, such as TEMA I);'/, diameter, shell diameter, tube size, etc., are the factors
which determine tile heat transfer surface area of a
wllich is used to predict if coilision heater.
Figure 3.51 (a) shows typical heat balance informa-
tion for the ultimate stages of feedheating for a 660
desuperheating section.
MX' unit. Also shown, is the associated temperature
orofile for the ultimate stage of feedheating (Fig 3.51
(c)). The basic equation used to find the surface area
(A) for each section is A = (q,,,h)/K(LMTD):
and desuperheating flow area and therefore increases tile
the tube
The sketch illustrates
plates act as baffles to dis-
because tubes are long
certain conditions be
objects, t i , i. i n turn influences thermal design. For where A = heat transfer area, m2
by randoll, q,, = mass flow rate, kg/s
h = specific enthalpy change through zone,
J/kg
K = oveiali heat transfer coefficient, W/m2K
LMTD = log mean temperature difference, as
tubular spacers at appropriate illter- defined in Fig 3.51 (d)
~ e i d i n gthem t o a structure within the
,ich is anchored t o the heater tubepiate. Figure 3.51 (a) and (b) illustrate how the heat
e close together in the desuperheating balance information is used to find the enthalpy rise
ling sections, but wider apart in the through each section in turn and the resultant tem-
perature profile.
From this information, the surface area for each
section is calculated in the manner described below.
I aspects o f the thermal design are found
11 6 of this chapter. 6.6.1 Desuperheating s e c t i o n
The bled-steam has a high degree of superheat which
allows the feedwater at the exit of the desuperheating
section t o approach very near to, or to be slightly
above, the saturation temperature equivalent of the
pressure at inlet t o the desuperheating section.
must also be given t o ensuring that local T o prevent erosion due to wet steam flowing through
e ~ ~ c i t i eare
s not present at the steam inlet t o the exit of the desuperheating section it is established
eater. There must be ample area to ailow the practice to retain about 28OC of superheat at the end
of the desuperheating section, so T 2 is made equal
t o the saturation temperature equivalent t o the pres-
sure in the condensing section plus 28'C. Figure 3.51
~,is based on this assumvtion.
(c)
The temperatures in the desuperheating section are
used t o evaluate the LMTD as shown in Fig 3.51 (dl,
so the only unknown in the equation to find the
or baffle to protect the tubes in terms of the surface area is the heat transfer coefficient.
lilllitingvalues o f e(v,,)2 where e is the steam density The methods of calculating the heat transfer co-
(kslm3) and ,v,, is the velocity o f dry steam (m/s), as efficient for a particular tube bundle are given in
detail in BEAMA 1968 [131 or T E M A 1978 1121: for a
typical desuperheater in the last stage HP heater its
v,,(max) = J(2250/e) m/s
value is about 500-600 w / m 2 K .
The heat transfer coefficient increases with the in-
If a velocity greater than this value is t o be en- creased velocity across the tube bundle. The higher
countered, even for short periods of operation (e.g., the velocity, the greater the pressure drop across the
Fa' Typicai arran&!emenr of tube supporl Plater in the desuller~eaiing, and cooling seclionr desuperheating section, which in turn reduces the sat-
of an HP heater
previous heater by-passed), the provision of a larger
branch or some form of impingement plate is needed. uration temperature within the condensing section.
296
297
Feedwater heating systems High pressure feedwater heaters
t exchanger dcsignex lras to reach a cosl as the nieair effective lcngtli of a U-tobc i n dctei-
i-ornise between increased condensing ~i~inirig ihe lheater siieli length.
rainst decreased desupei-heating surface The baffles within the lheater shell, which forol lire
ve ocity being dependent on the pitch of tbc compal.tmcnts tlixougii which thc steain or condensate
i ilic desoperheating section lo]. a given tube flow, have windows so that the fiuid can pass longi-
. Once an acceptable compromise liar been tudinally, Tiie area used is equal lo, or greater than,
that available for cross-flow.
From the ieferences given to find the lieat transfer
coefficients 1141, it will be seen that the theoretical
i\ ilcscribed earlier in this section). values arc modified to allow for leakage through the
aiirface area can now be calculated. From the tube/bafflc plate clearances, lack of true cross-flow and
iu~nberof tubes and surfacc area/metre iength the stagnant areas in the corners of the compartments
I,?, ihe length o f the desuperheating section is formed by the baffles.
'The baffle pitch may need slight readjustment The lieat transfer coefficients obtained by using
tile overall length requirement. these references, assume that the condensing section
within the healer is adequately vented to the condenser
t o avoid the accumulation of air or non-condensable
'ondensing s e c t i o n gases withi,? the section. The lieat transfer coefficient
used to determine surface area is significantly infiu-
SI<" 001,100:
enced by "on-condensables which tend to form a
gaseous muff around the condensate film on the out-
~rgsection. The effect of thc 28°C of supcr- side diameter of the tube. The slowing of the diffusion
o f vapour into tile condensate by the non-conden-
sables, significantly affects the condensing section per-
formance. This is a most imporlant factor in heater
I lbo found by reference to BEAMA 1968 1131 performance, and an unexpectedly poor performance
l A 1978 1121. The baffle pitch is determined from a new heater can be usually traced to incorrect
iecd lo distribute the steam throughout the air venting. The usual vent rate is about 0.5% of the
, ~ , ~ ~ m m , ~ , u , e p ~ o ~ , 9 ~ ~ o ~ ~ ~ , , m ~ , ~ ~ c ~ t ~ t I I section
~ and is usually about the maximum bled-sleam flow t o the heater.
,ic without the risk of tube vibration. The Accumulation of air can also occur in the drain
cooling section and cause pockets in the corners local
to the baffle plates. This reduces the available heat
hc per unit length and the number of tubes. transfer surface which again reduces heater performance.
N I ~ ~ ~ ~ L ~ ~ ~ U ~ ~ ~ ~ ~ ~ ~ I N ~ ~ t ~ l ~ l : ii '~\\~o-flowU-tube heater, as illustrated in Fig For an overview of the complete thermal/mechanical
llic condensing section inciudes the return bend design of HP heaters, reference should be made to
C o ~ ~ I O E P I s , ~ T 5 ~ . T , o l Y ~ , T ~ , ~ ~ ~ ~ ~ ~ ~ , L o ~ ~ ~ ~ ~ ~ ~ E ~ T ~ N ~ ~ , ~ ~ ~ ~ ~ ~ ~ r 'ti' and p a n of the bottom return leg. the Heat Exchanger Design Handbook 1984 [19].
CoollN9SL",OnS
Should cycle economics dictate a low first-cost feed
system, then H P heaters can be used with n o drain
I N I ~ ~ ~ ~ L ~ ~ l l N ~ ~ ~ L 1 ~ ~ ~ ~ ~ ~ i o ~ Drain cooling s e c t i o n cooling section and/or no desuperheating section. Where
11s section the condensate formed in the con- no desuoerheatine section is orovided, a small section
section has further heat removed by transfer local t o i h e steaminlet is baffled to help t o absorb the
~coniingfeedwater. The equation for the calcula- superheat, but is not allowed for in the calculation of
the surface area is as before. The LMTD is the surface area.
using the temperatures shown in Fig 3.51 (c). The omission of the drain cooling section means
lent transfer coefficient is found by the methods that the drains are discharged from the heater a t sat-
1 BEAMA 1968 1131 o r TEMA 1978 [12]. The uration temperature and there is n o need for a fixed
f the drains condensate across the tubes is im- water level in the heater shell t o protect the drain
n determining the heat transfer coefficient, so cooling section from erosion. The design procedures
fflc pitch is important and the subject of an to determine the surface area o f each section is the
'c iwocess during- the design." same whatever combination of sections is used.
,dlOaioim,"r,m*iMTD
~icalfigure for the lieat transfer coefficient in Vertical-attitude heaters differ slightly in the inter-
n cooling section will be about 19W W/m2 K. nal arrangement of components but use the same
Ill, tube length is found from the drain cooling design principles for mechanical and thermal design.
FIG. 3.51 Thermal design
as explained above
toll1 of tile heater to accoaliilalc in tllat half of the HP lieatei is tlie watci header, '1'0 i-ediicc ;illou, a sn~aiicrnumber of artachments lo lo lhc de-aerator tank is used. Cllaptci 4, Section
shell nut occiipied by tile desupcrlieating sectioii. A and aiso its tlievmal inertia, designs incorlrili to the header to gain access for tile attachment 14.7 of this voiurnc describes the system and lloiv
ware) icvci is ~iiainlainedin thc buttonl of rile heater, drum-type !water header have becn constiiicti, lo tlie headers. i t functions.
tllc i)Ul.pose being to sedi tltc drain outlct to prevent Figure 3.55 (a) and (b) shows two diffu~c~it lieaters suffer from some tube erosion in the
erosion due lo two-phase flow adjacent to thc drains lions for constructing ail H P beater witho~u r i I' the bifurcations but, in general, have been a s Accept the H P lieate? drains,
oiitiet. The air vcnls are placed at the top o f the shell i'entional water head. The heater shown o n 11 design. Because of the high cost o f con-
as all inon-coildensable gases and air wili rise to that e Heat tile tank content from cold t o provide hot
was constructed for Thorpe Marsh power ,I,, the development of this design was not
point. employed a central header with the mild stccl de-aerated water for unit start-up.
These two short descriptions of current H P hcaters radially disposed, the tubes being welded to tlir
illustrate how the design principles, explained earlier by the Foster-Witeeier method. T h e length 01' t i
in this section, are implemented in practice. The following examples of different manufacturers'
was such that they had to be constructed frorii de-aerators show how they achieve these objectives
lengths o f pipe butt-welded together. This ICI by different design philosophies.
tube was difficuit to handle and adequate pr( @-aeratingfeedheaters
had to be made within the shell to support t o t
6.9 Alternative designs of h e a t e r c o n s t r u c t i o n The only drawback to this design was its higli
A brief description o f older heater designs is inciuded canstructioo. 7.2 T h e r m a l l h y d r a u l i c design
to indicate how othei- approaciies to provide cost ef- The heater illustrated in Fig 3.55 (b) was co~,. Figure 3.56 shows a typical de-aerator and feedwater
fective H P heaters have been tried. liom the condenser (condensate) which has
by GEC and used mild steel tubes manually-weld storage tank, the head of which heals and de-aerates
The most expensive cornpotient in the construction calcd by the 1.P feedheaters is supplied t o the
bifurcation pieces which were, in turn, weld the incoming condensate before it drains by gravity
of a conventional hemispherical water headei- type o f tior to be further heated and de-aerated
superltcate~type headers. Tile bifurcation into the storage tank. The design uses spray nozzles
itory to being fed to the boilers by the boiler
to produce a fine film/spray t o maximise the surface
urn],, via the H P feed train. De-aeraton on
area of the water available to the steam for heat
i large units are designed to provide feedwater
transfer and to minimise the distance that the oxygen
- .~~ .. ~...
~ liom the storage tank with not more than 5
FEE0 WATER .,-. has t o travel t o be released. Any residual oxygen is
11s per kilogram &/kg) of oxygen.
released while the water is further heated as it passes
o n is achieved by the application of Henry's
over a series of perforated trays, which causes the
llicli states that the quantity of gas dissolved in
condensate t o fall as a continuous 'rainfall' from tray
CONNECTlON EYE 1 quantity of solution is proportional to the
t o tray.
ssure of that gas over the solution. When
The heat transfer coefficient in the fine film/spray
-JACKING SCREW applied t o the removal of oxygen from feed
zone is about five to ten times the value for the drop
phere above and around the
phase of approximately 14 k w / m 2 ~ As
. nearly 90% of
ate contains no oxygen, then the dissolved
the temverature rise occurs in the film uhase, the
'I1 escape t o that atmosphere in an attempt
temperature difference between the water drops cas-
cading from the iower trays and the steam is small. The
nstruct a de-aerating heatei to release the
additional trays, however, arc needed to allow time
amount
~iil~ii of oxygen from the incoming con-
for the residual oxygen to escape and also to heat the
Ir, the following factors have to be considered:
water to the saturation temperature equivalent to the
lime for the dissolved oxygen to travel to the prevailing pressure.
The steam flow path is shown by the arrows in
cc of the water.
Fig 3.56. A small flow of steam, along with the oxy-
clwtll time is needed for the steam to heat the gen and non-condensable gases, is extracted by vents
ate and so Increase the equilibrium pressure o n the top of the head. The mixture of steam and
en in order to release it. oxygen, if vented directly to the condenser, would
constitute a heat loss. T o save this heat, a vent con-
~ r f a c etension of the water. denser is provided t o heat the incoming feed by con-
densing the vapour and extracting the heat irom the
lime taken for the diffusion of the oxygen
.. .- and non-condensable -gases.
oxveen
the water into the steam atmosphere. The oxygen and non-condensable gases are extracted
from the vent condenser by venting it to the conden-
ser, from where the gases are discharged by the main
rlorage tank associated with de-aeration has t o
air extraction pumps.
DRAINOUTLET 1 lhc following needs:
The storage tank associated with the de.aerating
xpproximately 7-10 minutes' worth of CMR function stores about 300 tonnes of feedwater in a
tts defined in Section 3.3 of this chapter. tank o f approximately 4.5 m diameter by 32 m long:
it is accommodated o n an elevated floor in an annexe
>I the leak-off flows from the boiler feed between the boiler house and turbine hall.
>s, when needed. At low loads, when the flow Diffusers are provided to discharge the leak-offs
yli the feed pump would be less than about and the H P drains into the tank, as indicated o n Fig
FIG. 3.55 HP feedheaters with cylindrical headers a special leak-off system which discharges 3.56.
Chapti.! :4
Feedwater heating systems
i i 1ic;ited by a large vcnt condensci ~i,l~icli
cootribiites sllows a section through a typical Stork iie-aerator,
it11 iir~irl-eciableproportion of the ternjlel.ature rise over with the steam and watci paths indicated.
!It,: ticater. This reduces tlic heating requi1,ed during There is no de-aerating head as such, but in tlie
li;iiisit through the trays. space above thc working water levei in the lop of the
'I'iie condensate is directed onto the top tray from storage tank there is a series of speciallp designed
w11ere it cascades through tlie rest o f the trays to flow sprayers, which spray the incoming feedwater onto a
I,) gravity into the storage tank. The steam/water flow ring of plates which further breaks up the water.
pslhs are indicated on the figure. The sprayers are designed to create sufficient spray
' ' steam flaw to the vent condenser is about area and water droplets to provide the necessary heat
"10 of the bled-steam flow: any oxygen and transfer surface t o heat the incoming feed to as near
in-condensable gases are swept away in this vent to the saturation temperature (corresponding to the
)w. The vent condenser is vented to the main con- pressure within the de-aerator) as practicable. In prac-
er, as indicated, and the gases are discharged tice, the temperature of the feedwater in the tank has
the main condenser by the air extraction pumps. been measured t o b e within 1-Z°C of the saturation
'The feedwater storage tank associated with the temperature. T h e stored water in the tank is therefore
lc-aerating heater on Fig 3.57 is similar in size and heated t o the saturation temperature of the incoming
; provisions for leak-offs, HP drains, etc., to heating steam as it enters the fank through the sprays.
described for Fig 3.56. The other features de- A steam distribution system in the form of a 'rake'
ed for the first de-aerator storage tank are also is provided, the teeth of which arc vertical tubes per-
v
forated at their ends. Thc end which is oerforated is
I .0, k~W0
S//A,A1,JPJINB/UB/NL5/SY
\
0,SI"IOulmY ,.,PIS
7a
PUUPIUCTtON I,/
S,E*,IRI~,,NO,"I6XESI
\
510"AGET"N*
A design of de-aerator currentiy intended for use
a,illiin a CEGB power station is the 'Stork' de-aerator.
positioned to be always below the lowest working
feedwater level. The heating steam introduced into
lOlNS"tlrN8XiND
O@TAN<COWTEN. 'Illis type of de-aerator employs a different approach the tank content via the steam 'rake' is nearly at the
lo llle task of extracting the oxygen and other non- same saturation temperature as the tank content and
i~>ndensabIegases from the condensate. Figure 3.58 is therefore not condensed, but bubbles through the
I:!<;. 3.56 Sectio#>illlougl~ a typical ~pra)./truyl y l x dc-acrrcoi niid associaled aiora8e iank
The steam coiis used t o boil and thereby de-aerate Vertical baffles are also needed t o prevent possib
the tank content prior to unit start-up are also shown 'sloshing' of the tank content from end t o end und
in Fig 3.56. conditions of abnormal steam flows across the tal
Unless provision is made to induce movement o f surface. The transfer pipes between the tank and I1
the tank contents, stagnant areas o f subcooled water de-aerator head arc of generous size t o ailow flow
will resuit. A distribution system is provided to pre- vapour to the head when the tank content boils ill1
vent direct discharge of the incoming heated and de- to a i.eduction in de-aerator tank pressure.
aerated feedwater from the boiler feed pump suctioll The de-aerating head shown in Fig 3.57 employs 11
pipe connection. By use of a distribution system, ade- different design phiiosophy, using trays only to obtait~
quate mixing of the tank content is ensured. the de-aeration of the feedwater. The incoming feed
oscd for LP heaters, nccd a tube wall thick- do no1 allow for the effects of openings in the vesscl
ai ieast 1.2 om to g~.cverit the tube wail walls. Tlie compensations needed around the various
openings to conipeiisate for the penetration arc
calculated, as fox HP headers, by the application ol
,ifecdwates pressure requirements, it nevei- Clausc 3.5.4 of BS5500 [ I l l .
iows for corrosion damage and aiso makes
8.4.7 Shell and dished e n d thickness
The pressure range over which LP heaters operate
blCr,ONl""O"B*
ITSAMNLeT is from maximum bleed point pressure to full vacuum.
i f the shell thicknesses were determined by differen-
FIG. 3.60 Seciion ibrougil s lypical lhorironlal LP liearci, Heysham 2 po>!,el riac,oll t of the depth of the tubeplate. The light tial pressure alone, the thickness of the lower pressure
is to close the gap between the tube and heater shelis would be insufficient to withstand loads
le, where water could penetrate and possibly from pipework or being lifted into piace during the
,revice corrosion. The mechanism of rolier- course of plant erection. In practice, shell thickness
iig tubes into tubeplates is described in depth is not made iess than about 12 mm but this again
depends on individual manufacturer's practice. Ex-
ternal stiffening rings are sometimes aiso used to
permit the use of slightly thinner shells. The dished end
thickness is chosen to suit the shell thickness.
*OO?AlOAl nv31s
'paii!aiiaiap s! ssej.lns
1leati si(i 'ralileilJ sjijl jo 9 uo!isai. u! iia,\!$
)s sill 81i!s(l (i.i.flV1a q l 8iI!lu[n~[i.?.lo ssodind
Feedwater heating systems Evaporators and other lneans of water rreatmenr
described far 1iP !heaters. The lhcal balance to detci- of the Incoming condensate for presentation
mine the rise ovci the drain cooler is shown in Fig healing steam, 'The rnaximun~heal transfer coc S P R A Y TUBE
3.62 (0 and the resultant temperature gradient is
illustrated by inset (e) of the figure. Again, U-tubes droplet flow.
are. roller-expanded into a mild steel tubeplate. The The slielis and dished ends are constructed o i ill1
shell is of all-welded steel construction. steel. As the last station to be constructed wit
The baffle arrangement, however, is different as heaters was ordered before 1976, all the D C h
the baffles are required to guide the water across
the tubes and to prevent leakage between the shell
and baffle. The baffles are semicircular and a close mined by the need to accommodate the spra
fit in the shell. The path needed to be taken by the
drain water is shown in Fig 3.62 (d). to heater. Figure 3.63 shows a typical horizontal a1
tude DC heater of NEIP manufacture, employiny
system of jets which impinge on plates to produ
8.8.1 Thermallhydraulic design of a flashing a fan-shaped film. The feedwater from the previo
drain cooler heater is introduced into the channels which run aloi
The temperature of the feedwatei leaving the heatel the axis of the vessel. These distribution chaiin
for a specified temperature difference is found by are bridged by pipes across the inside of the si
performing a heat balance over the drain cooler (Fig
3.62 (c)).
The temperatures required to complete the diagram
shown In Fig 3.62 (b) are now available. Assuming water t o the saturation tempeiature coriespon
that all the condensate flows through the drain cooler
tubenest, then the tubenest will have the same number
of tubes as the LP heaters in the feed system. The
overall diameter will also be the same. The LMTD is extracted. The heater is continuously vented
calculation is shown in Fig 3.62 (b). The heat transfer condenser. The steam inlet has a baffle which
surface is then found using the same method as for a the steam along the axis of the shell.
normal L P heater. The drain outlet is at the centre of the heater ail
is fitted with an antivortex device. As discussed earl1
in this section for horizontal LP heaters, a nalor
drainage level in the heater exists dependent on 111
8.8.2 Thermallhydraulic design of a warer-to-
flow rate into the heater, the heater shell diametei
w a t e r drain cooler
etc.
The temperature out of the drain cooler is found by The DC heater illustrated in Fig 3.64 was milti
a heat balance over the drain cooler as shown in factured by GEC. The design philosophy is slnlil
Fig 3.62 (0: however, in this case the drains flow is to the de-aerator head shown in Fig 3.57, but will
treated as hot water. minor differences to adapt the principles for 1)
The heat transfer coefficient is calculated as for an FXG.3.63 Tynieal arrangement of a lhorizon~aldirect contact LP Iheater, lncc B power station
heater service.
H P or L P internal drain cooler, using the temperatures
A water distribution header directs the inconii
indicated in Fig 3.62 (e). condensate through perforated windows in its "nil
The tubenest will have the same number of tubes Evaporators and other means of water Current practice is to use a chemical raw water
as the first LP heater for full condensate flow, and will treatment plant followed by filters and mixed-bed
have the same shell diameter as the L P heaters. deionisation plant. For the AGRs and for the pro-
The baffle pitch is determined by the need to main- jected PWR, a full-flow polishing plant in the feed
pressure.
tain the velocity of the water across the tubes to give The illustration shows the provision made to all train is provided to ensure the high quality of boiler
the needed heat transfer coefficient. feedwater.
the steam free access to the water cascading
The drain cooler actually used depends on the traditional method of producing high quality A full description of the raw water treatment plant,
the trays. Steam flow is directed to the lower
manufacturer's assessment of the most cost effective for boiler feed was to distil water by the eva- filters and mixed-bed deionisatlon plant, and a full-
of the heater t o ensure that water cascading f I
type for a particular installation. ration o f treated raw water. Treated water is boiled flow condensate polishing plant is given in Volume E.
lie evaporators by the application of heat in the However, to provide a complete description of modern
nest of trays from just below the cold water entry n of L P bled-steam from the turbine or a steam plant, the following section gives details of typical
point. ply from the auxiliary boiler. The resultant vapour steam evaporating equipment which is currently in
8.9 Direct contact low pressure heaters Double drain outlets are provided to ensure a ndensed and can be used to replenish the reserve use in large CEGB power stations.
In both thermal and mechanical design, direct contact quate drainage, taking into account the princip
(DC) L P heaters are very similar to a de-aerator heater discussed earlier in this section for horizontal I
head. They are cylindrical vessels arranged in either heaters. tment by the deionisation method has made it with a daily output of about 3% CMR steam flow.
the horizontal or vertical attitude, equipped internally The trays and perforated distribution inlet window conomic to install bled-steam evaporators for the The water treatment plant has also to provide water
with a means to maximise the heat transfer surface are made o f stainless steel to prevent eroslon/corrosioii. to meet the additional losses of two-shift operation.
Future developrne~ils
9.4 Flash t y p e e v a p o r a t o r s
Flash evaporators have been available for inany years.
They have only emerged within the last two decades
I:i(i. 1.64 Typical airnllgernezil of a lioiizo~~rl
direct cori<aci 1.1' Ihcalci. Herrhs8r i lioi\'ez riatioil
li ensures circulation to the heating cham- as a viable proposition for large scale distiliation,
us heat exchangers are also added to increase due to thc fact that multiple-effect or multistage
I efficiency of the process. plant can now be built in the very large sizes required
the filling of boilers and the feed system after main- stage and is finally removed by means of an e feedwater is pumped successively through for potable water in arid countries. Thanks to modern
tenance, and the special needs of chemical cleaning pump. s/cooiers, a preheat and a vent vessel to methods of raw water pre-treatment they can also
and commissioning. tor. After vaporisation in the evaporator, operate continuously for long periods.
nsed into distillate and delivered to the Large multistage evaporators can be built econo-
harge point by a distiliate pump. mically on the 'egg crate' principle, each stage con-
sisting of a narrow vertical compartment in the crate
9.2 T y p e s o f bled-steam e v a p o r a t o r with raw water on its way to the heat input section
Two types of evaporator have been used by the CEGB traversing each compartment in straight tubes. Figure
(discounting the horizontal submerged coil type as 3.69 illustrates the construction of an experimental
inappropriate for large modern power station feed- 10-stage flash evaporator which has been in service
water treatment). with the CEGB.
The first is the surface 'Vertical-tube' type invented Since heat consumption varies inversely with the
by Kestner in 1909. Figure 3.65 shows the arrange- I, evaporator and condenser. number of stages, the flash evapoiator can compete
mcnt of a typical vertical-tube evaporator. The water re vented from the feedwater in a vent successfully with other forms of evaporation plant
inside the tubes is boiled by the heating action of by having multiple compartments or stages in a single
the bled-steam o n the outside of the tubes and a vessel. However, even this economic form of water
mixture of vapour and water is expelled from the lporator. It is then circulated to the heating treatment plant is not as cost effective as a modern
top of the tubes. The water spills into the central polishing plant for the production of boiler feedwater
downcomer and the process continues by natural cir- and no further installations are planned.
culation. The rising vapour passes through baffling
to reduce the quantity of entrained droplets thrown
up by ebullition and is then condensed in an external or vapour condenser.
vapour condenser. Any non-condensable gases carried MAxE,up,wLE,+
team condensate from the heating chamber, 10 Future developments
-
out with the vapour are vented. ludes that from the preheater, passes through The development of feed system design and its asso-
The second type is the 'Flash' evaporator. A sche- ciated components is dependent upon the cycle steam
matic diagram of a two-stage flash evaporator is conditions and the turbine-generator unit capacity
shown in Fig 3.66. The raw water is heated near to
saturation temperature of the heating steam and is
then cascaded through the evaporator in series, which
is at a lower pressure than the water. A proportion
-
;.:'.:,
.
WLIINCISIEW
IPY~POY~
IlEDWAIIR
CONTINUOUS
8LOWOOWN
chosen for the next generation of power stations to
be constructed by the CEGB. Present indications are
that non-nuclear stations will be coal-fired, with sub-
critical or supercritical steam conditions and a unit
of the hot raw water flashes in each stage and is capacity o f about 1.5 times the current 660 MW units.
condensed by the raw water on its way to the heat FIG. 3.65 ~ y p i c a larrangement of a 'vertical-tiibe' 1 lhese vessels and discharges to atmosphere. The need for the development of systems and com-
input section. The distillate cascades from stage to evanorator IC system maintains a vacuum at the hack end ponents for a number of specific plant areas has been
316
Feedwater hearing systems Future developments
j IS] 12S1 S,n,~d;ivd 21-4: 'Scaiiilcri steel reed wale, lheaiel iiibcs carbon i ~ l o c e s s i ~Prac
~ ~ . 129: Al3ril 1970
lot lhigli prcsaiire a~,i~lratioss':Llcct~icitySapply I#~dusli?: 'lieu,
erd,anger desigl~ lhal?dbook': Hemispbclr I
Mavci, 1982 Corporation: 1984
l i b ) CEGB Standard 234102; GDCD St.psduid 56. lssae 2: 'Carboll e r .C, elid Crow, I. Ci.: 'Onrei o i I
~ ~ ~ . d i iG.
axid Allor Stocl Feed Watcr tieater Tuber': Dcceillbci 1980 supernate8~fFluid is Surge Tasks': Clieiiiicai
. . ,.,.,,,. . <. ,,,\.: ..,' i::i, ,,: .. science, Voli~me26, I'agec 211 lo 219: 1971
.. , , .. I I.. . ,I,. I ,. ,>,>
% ! ' ~ ' , . . , .?> h t
crasrieid, R R.: ' ~ r a i sdischarge chaiacterislics
I,. 1, ,,;. . .
. :: I .I: '.?: j ~ u i n a oi
i Mecl,allicd Engineering Scic C H A P T E R 4
[18j 'Sl~oisgren,I. T.: 'Predict exchanger lube damage': Hydro 23, No. 2: 1981
8 Plant testing
8.1 Introduction
8.11 Test codes and practices
9 Future devslopment~
COnden~eisurface area. turbine exhaust pressure and
9.1 Aims and objectives
9.2 Resesrch end development
9.2.1 Tubenest layout
9.2.2 Thermal performance properties of tubing
PUMPS
10 Air e x t r s ~ f i o nsquipmenf
10.1 lotioduction
10.2 Determination of sir extraction quantity
vironmenfsi can~iderstions
10.2.1 The mechanism of air extraction
,1 Cooling weler quality 10.2.2 The condenser air cooling section
Corrosion prevention 10.3 Revisw of air extrsction equipment
Other copper-slloy tube failure mechanisms 10.3.1 Hydraulic air pumps
Matetlal seiection 10.3.2 Liquid-ring type air pump
10.3.3 Air ejectoripump Eystems
10.3.4 Steam eiactoripump systems
10.4 Quick-start plant requirements
10.4.1 Type of plant
10.4.2 Starting times
11 H Y ~ ~ B Y BI S
I cP B C ~ Sof centrifugal pumps
BEAMA design recommendations 11.1 Specific speed
CEGB specifications 11.2 Net positive suction head
nfluence of tubeplate and tubenest geometry on thermal 11.3 Suction specific speed
li.l.1 Subjective design evaluation 12 Circulating wafer pumps
li.3.2 Computer assisted design evsiuaiion 12.1 lntr~ductlon
12.2 Horizontal split-=sing pumps
12.3 Vertical pumps
12.3.1 Veriicai metal-casing pumps
Con~tr~cfionald~veloprnent 12.3.2 Concrele volute pumps
Construction mafarials 12.4 Gearboxes
Design forces and stresses 12.5 Shaft seals
Methods of manufacture and oonstiuclion 12.6 Pump testing
12.7 Materials
1 3 Condenser extramion pumps
Condenser tube cleaning system
Special consider~flon~ 1 4 Boiler feed pumps
14.1 inttoduction
Ollerationsl life limiting constraints
14.2 Feed pump developments
7.1 Condenser sir inleakage 14.3 Advanced clsss feed pump construction
14.4 Axial thrust
14.5 Gland sealing
14.6 Pump layout and drive
14.7 light load protection
14.8 Testing
7.2.3 Bubbler devices 14.9 PWR feed pumpsets
'1.24 Tracer g ~ methods
s 14.10 Future trends
7.2.5 Flame and smoke methods
7.2.6 Uitrasonic method 15 Miacslianeous pumps
1.3 Condenser fouling and 15.1 Sewice water pumps
7.3.1 Condenser fouling 15.2 Chemical injection pumps
7.3.2 On-load condenser cleaning 15.3 Fire pumps
7.3.3 Off-load condenser cleaning 1 6 Reference$
Condensers, pumps and cooling water plant Econoinics
mast effective heal sink, and therefore meet the rc.. of the plant components.
The screening pirrrii must i-emovc any debris l'rot STEAM
quirements of the condensing plant and cooling water CONDENSER
(CW) system. the cooling water which is large enough to block 11
Typical atmospheric heat dissipation systems are condenser or auxiliary cooler tubes. It must b ,
illustrated in Pig 4.1. Those most commonly used are: to keep clean, even during periods of excessive d ( 8 ) EvainidlVD EOD"S
T o collect the useful residual heat from the drains The aim of the designs is to ensure that these ob
of the turbine feedheating plant, and other aux- rives are met within the framework of the followi PUMP
iliaries. practical considerations:
The aim of the C W system Is to maintain a supply Econon~iesof size, space and pumping power.
o f cooling medium to extract the necessary heat, in
order that the condensing plant can meet its objec- Ease o f maintenance and construction.
tives. It achieves this by the use of effective screen-
ing equipment, circulating water pumps, valves, and
.. cooline- towers.
(where necessarvl
The economics, design, construction and functional 2 Economics
requirements of the above systems and associated The detailed design of the condenser and its a
plant components are discussed in detail in the sec- ciated CW system requires careful optimisation
tions which follow. parameters which include material selection, coolin
Since many pumps of different types and duties water flowrate, condenser surface areas, and turhin
feature in the above systems, aspects of their design exhaust pressure, etc., in order to harmonise 111
are collectively considered in later sections o f this
chapter. These include condensate extraction pumps,
performance inter-relationships between all t
ferent plant components, and to produce a
14
cooling water pumps, circulating water pumps and offering maximum efficiency and reliability, and
feed pumps. mum running and maintenance costs. Flc. 4.1 Typical atmospheric heal dissipation systems
Condeiisers, pumps and cooling water piant Econolnics
2.1.2 Computation
The problems to be solved can be classified into thrcc
326 327
Condensers, pumps and cooling water piaiit liistorical developinent viid layout
..
sullcd in consislenr concepts of condcnsiog plaiil mcnls were niade in sevciai other aspecli.
iayout. feature of these coridcnsers was that they a
Tlie costs incurred in exterisivc design work, and singlc-shell design; otherwise they differed cai
the development of special manufacturing techniques, Tlie most obvious differences relate to thr
have becn spread over a large number of units which arrangemenr. Figure 4.5 (a) illust~.ates e
have progressively benefited from minimised commis- arrangement, and Fig 4.5 (b) an axial a i .
sioning problems, and increases in service reliability Each o f these has advantages, as will be
and maintainability. During this "criod the size of latel. sections. When considering thernlal p
generating plant bas also progressively increased from the transverse design is simpler and easier i
120 MW to units of 660 MW. A difficulty with the axial condenser is thsr t i
Standardisation of approximately fifty machines tubes naturally result in a rather large dificrclt
was achieved in two stages: first at a unit sire of 120 thermal performance between inlet and ooilel
MW, and later at a unit size of 500 MW. The latest so making the effective extraction o f non-con'
machines a f 660 MW sire represent an evolutionary more difficult.
development: at present, there are some 23 machines The axial arrangement, however, has a c;lpiii~l <a,Am,," ude'nung
at this rating either in service or under construction advantage because o f the smaller number of (I
in the CEGB. rubes involved. This results in a saving in $11
Certain features associated with 660 MW turbines of manufacture of the expensive tube piarcs.
have had a major influence on the development of allows a simple turbine-generator foundation i
condenser design and iayout. In order to appreciate ment in which the LP turbines are suppoi
the significance of these features, a slight digression parallel foundation walls, one along each sic
to highlight the development of their design is worth- process of tubing the condenser can use ti1
while. under the electrical generator, which is kept
Single shaft turbines running at speeds of 3000 major plant items for this purpose.
r/min have become increasingly compiex, as set rat- Again, due to the length o f tubing involvc~l
ings have increased by increasing the steam mass an axial design, it becomes necessary to
flow. Increasing the steam mass flow has demanded sures to avoid large scale axial migration o
a need for multiple L P exhausts with last row turbine towards the cold end, which may invoive ado
blades approximately 914 mm long, and a n exhaust opposed cooling water flow. This can be don
area of approximately 6.7 ma. having two separate water passes with the Fi<
While the turbine n~anufacturers (each of which opposite direction, as illustrated in Fig 4.6. Sc
has developed its own blading design) have made arrangement can complicate the culvert layout, r
improvements to details such as aerodynamic pcr- water pipework and valve layout, and result i>
formance, erosion shield vibration characteristics and ditionai costs. Desienine the condenser as ;I
exhaust blading has increased the operating capability tion and is now standard British practice for: ;ax
to very much higher specific steam loadings. condensers.
Economic considerations have also favoured substan-
tially increased turbine exhaust specific loadings. This
is reflected in the 660 MW machines at Littlebrook D,
where a four LP turbine exhaust design - .(of aooroximate-
., 3.2 Phase 2
I! 7 . 3 ni2 annulu, area per r \ l ~ a u , t )h3s becn adopted This phase covers the remaining 500 MW units 1,
S t r ~ c t u r arela~ioltchtp~
. bctueen turb~neand ~ ~ u d c n c r r . all excevt the most recent 660 MW units. Conlnilt
~ ~
and the method of overall support, have also developed with phase 1, it is characterised by a radical
as unit ratings have increased. ferent design: the axially-tubed side-mounted coil
Three main phases of design exist within a period o f ser. The develooment of the side-mounted cond
development which covers early 120 MW plant right coincided with a general move towards the us
through t o the present 660 MW plant design. Justifica- steel foundations.
tion for these various changes are now discussed. In some arrangements, this becomes a 'pan~i'
design as shown in Fig 4.5 (c), in which conde
and turbine are seoarated and connened
~. ~ ~ to .~
. . . ~ ~
other by short ducts (either rigid or with fl
3.1 Phase 1 bellows, deoendina. upon. the details o f the tur
In this phase, which covers about half the total num- and condenser support arrangements). In other case (dl """I" P'""8e'
,E,And,iy ,nlBgrBl
bet o f 500 MW turbines, the underslung condenser the condenser and turbine are combined to form ti
arrangement used on previous 120 MW and 200 MW 'integral' condenser design (Fig 4.5 (d)) in which 11
units was retained. The reinforced concrete turbine- condenser shell encloses both the condenser tubes art
generator foundation block was kept, but develop- the low pressure turbines. FIG.4.5 Condenrcr eonfiguratianr for recent British 5W and 6W MW units
330
Coi~densers,pumps and coolihg w a l e , platv
Enviroritncntal considerations
with high inlet water velocities and air release. If impingement attack cannot be controlled EXAMPLESOF TUBE
PLUGGiNG
The attack has the same characteristics as general ventive maintenance, consideration can be g
suspended-solid burden. It has been suggested throat inserts (Fig 4.9). These are nylon inserts 1
lance of the material to impingement attack. the insert initially absorbs water and effectively
itself into the tube.
(c) Impingement arrack af iodgcddebris General debris Thelc is a 0,24 m,n feather on the
causes 11artial blockage of the condenser tubes
edge of the closely to the tu
and gives rise to high local water velocities of thc
to pl.event significant disturbance to the waleilio
Order Of m/s. This the threshold value Tests confirm that erosion problems from debris loci
for conventional copper alloys and causes severe
in these inserts are contained and cause no dama!?c !
highly localised impingement attack.
the tubes.
Tube failures caused by general debris can be
minimised by concentrating attention on removing
the source of the problem.
4.1.2 O t h e r copper-alloy t u b e failure mechanis
(d) Iron oxide scale This is produced from the cor- Other types o f copper-alloy tube failures can oc
rosion of carbon steel waterbox and CW pipe- and these are briefly reviewed under each of the
work components and is prevented by applying lowing headings:
cathodic protection or by protective coatings (see
Section 6.2.3 of this chapter). The oxide scale (a) Deposil nflock.
which forms as easily dislodged 'plate-like' sheets,
becomes lodged in the tubes and causes failures (b) corrosion.
due to highly localised impingement attack. (c) Stress corrosion cracking.
(e) General wolerborne debris This is produced from Corrosion ,ofigue, FIG.4.9 Condenser tube reduced lhioal inserts and rubc piugr
ineffective screening plant allowing shells, wood
and marine debris to pass, in addition to debris (e) Steamside ommonia corrosion.
from the culverts in the form of concrete spoil.
(f) Mussel fouling This is caused by ineffective (a) Deposit attack Deposit attack on condenser tuba
use of low level CW chlorination or bio-fouling occurs under conditions of stagnant or low watc
equipment. velocities, generally less than I m/s. Depositio~
Condensers, p u m p s a n d cooling water plant
o f iocil materials, such as sand and sill i,articics, conditions (Fig 4.10).
causes oxygen depiction at the particle-to-tube ma-
No1 spar co,7osiu,i 'l'liis rorm o f locali
teriai interface, leading to diffeicntial aeration and
Colrosiol7 occurs at 'hot spots' a n lllc
anodic dissoiution of the tube material. The pre- tube wall which can occur because of i
sence of decomposing biological materials and pol- velocity and/or high heat fluxes. Thesc coil
luted water, particularly sulphide-containing water, can be caused by paor stcam distribinioii
accelerates this type of attack. Deposit attack call absence of water on the cooling water sid (2,) 1.OCill Iligl, l",l,pela,,,les 01, i l l C ",,,side of iilbes
be experienced in both inland and coastal power can lead 10 abl>or~iialirrapid currosioi?al coiieipondilip
tube. The cupro-nickel alloys are less resisl ipositi081~081 i l ~ eillside (cooliiig water ride) of tile tubes.
stations, particularly in Iocatiol~swhere polluted aluminium brass t o this typc of attack. !lo! Hot S I > O ~ ~oirobioiitakes the form o f a highly locatiscd
waters are used. this form of attack is rarely experienced ' ~ i t t i i l gattack, a eliaracieristic feature being 11,;ti t l ~ cpiii
By maintaining the cooling water velociiy in often coniain meialiie copper. he iilosiiatioii shows a
steam condensers as the steam side tern arclion illlougha pit filled witti s,elallic eopilez produced
the tube above I m/s and avoiding stagnant con- are not high enough (Fig 4.11 (a)). by a iiol sliof attack in a copperf100lo >nickel alloy tube.
ditions in aggressive media by flushing and peri- Problems can be exoerienced in the dullll~al#&im@$%j.
odically refilling the condenser with town water sections of the condenser or in sepalxic
during shut down, major deposit attack may be steam condensers with high superheat, where
prevented. However, a permanent solution can be steal11 impingement o n the tubes occurs. l:el
achieved only by the selection of a more resistant in titanium tubing can provide a satisfacl<
material. Such materials are the 70/30 and 90/10 tion or, alternatively, an engineering sol
cupro-nickels (of which the 90/10 is claimed to avoid direct steam impingement such as re
have the better iesistance) and titanium. Titanium of steam flow can be found: the introduciio
offers the best solution, as it is immune to this effective steam desuperheating is also con
type of attack under normal condenser operating t o be a satisfactory option.
(c) S1res.s corrosion oockiiig Failure of colbdeiises the iemperalilre diffei-encc between the turbinc ex-
tribcs by cracking ondci the combined action or ei'fecls. isuiating against galvanic action. haust steam arid the cooling watci is as low as pos-
tensile stress and corrosion has occurred in !he construction, tubeplates manilfaciiired sible if the bcnefils o f the Rankine cyclc ate to bc
pas1 owing to high residual tensile stresses inad- e Compatibility with other CW sysrein mateli;ilr, realised, providing tlial the ~neclianics used are con-
iilotninium bronzes ASTM-BI71 Alloy D, and
vertently remaining from the tube making process. M.lil7l Alloy E, have couple potentials with ti- sistent with previously discussed economics o f platit
However, with modern coadense~.tube production Experience has indicared lilal studies of 11 bes of -215 IIIV (SCE) and -133 mV (SCE), optimisation.
practice, such failures are now uncommon (Fig yield materiais which initially appear to bc an ly. The co~.rosioilrates of aluminium bronzc
4.11 (b)). sivc choice, hut because of their inherent11 I tes are therefore low enough to allow their use
Cracking can result from stress corrosion at corrosion-resistant properties show a higher ccoi,<i~ IOIXI any protective coating. The waterboxes, how-
the tube-to-tubeplate expansion joints. The cracks return when plant availability and retubing cosls tile still protected with suitable coatings as in a
initiate at the edges of the expanded regions on taken into consideration.
5.1 Theory
the CW side of the tube and propagate into the The condenser is the beat sink for steam power plant.
vice trials have been carried out at a number
tube wall under the influence of residual stresses The condensation process is accomplished by the
Copper-based malerials r stations, listed in Table 4.3, under various
remaining from the 'rolling-in' operation. The cor- transfer of heal from the steam exhausting from the
conditions ranging from the particularly
rosive medium is suggested to be ammonia, formed As previously illustrated in Fig 4.9, the copper-b turbine to the water used for cooling. Steam is con-
sand-laden waters of Bristal Channel power
from the decarnposition of oiganic slime, and con- tube materials are liable to varying degrees densed at substantially constant pressure and its heat
centrated by evaporation during outages. Effective lo the pollutcd environment experienced by
pingement attack, depending upon the operatin content (enthalpy), which is given up, raises the tem-
media control such as washing with cleaih water de power stations.
ditions. Thcse matel.ials, however, can be o perature of the cooling water as it flows through the
before prolonged outages or fitting protective sleeves, lowing the satisfactory performance of the ti-
employed providing that a good margin of tubes (Fig 4.12). Referring to Fig 4.13, which illus-
1111 tubes in these trials, two condensers were
appears to provide a solution to this problem. is maintained between operating conditions aoil trates a basic heat flow diagram, there are three factors
impingement attack threshold, and providin~!, I I rllcil with titanium; one with seamless tubing and
which determine the enthalpy of the steam at the
- can occur ill, seam-welded tubing. Results from these
.
(d) Corrvsion .fati,eue
. Coirosion fatiaue steamside corrosion conditions are satisfied. M'll turbine exhaust:
in any tube material and is caused by steam buf- freedom from erosion or steamside corrosion ctizii onfirmed that the tube installation procedures
feting, or structure-borne vibrations, in association be assured, it is necessary to use a matcrial s~lclt sequent service has been satisfactory.
The conditions and heat content of the steam leaving
with inadequate tube support. Generally, failure 11years ago, titanium was considered extremely
titanium. the boiler.
occurs at midspan where tube thinning occurs due c and unlikely to become economic.
to excessive movement and contact with adjacent st constraint on the use of titanium tubing The efficiency of the turbine in converting this heat
.
tubes (Fig 4.11 (c)). Additional support plates or Titonium bu minimised by a reduction in the required energy into work.
the fitting of antivibration damping equipment Over the past twenty years, work has progressed wall thickness, This, coupled with savings ex-
solves this problem. tile development of titanium for use as a condcn I lrom leak-free operation, establishes the use The selected heat sink temperature
tube material. Its major attribute is a tenacious o anium as a n economic material for power sta-
(e) Stearnside ammonia corrosion Aminonia corrosion film, which rapidly repassivates if ruptured under z >ere aggressive attack is either experienced or
usually attacks brass alloy air cooler tubes in the ma1 condenser operating conditions. Jet impingem 5.1.1 Heat rejected
form of pits on the external tube surface, with tests on both welded and seamless titanium tubing result of the favourable in-service trials and Equating the total heat per kilogram o f steam leav-
grooving at points adjacent to tubeplates and sup- water velocities of 10 m/s for 60 days have slio ~g economic competitiveness, titanium tubing ing the boiler 11, wit11 subsequent heat losses 11,. h b ,
port plates [2]. Titanium and the capper-nickel the material to be immune to attack. Under tb h,, and the heat equivalent of turbine-generator work
alloy tubes are highly resistant to this form of conditions, aluminium-brass and cupro-nickel tub I tittack of the condenser is considered possible. output h,v, then the heat at the turbine exhaust 11,
attack and the problem can be solved by retubing failed rapidly. Titanium tubing manufacturers (Imp tests, which are carried out at new power can be represented by the equation:
in an appropriate material. Metal Industries Ltd. [3)) quote impingement at oil sites prior to the ordering of titanium, confirm
threshold values of 20 m/s in clear seawater ar I in all cases the corrosion resistance is good, and
m/s in water with a high sand content. Thus, even 1 no operating problems arc envisaged.
4.1.3 Material selection localised tube blockages where water velocities
The need for a materials selection strategy has been rise to 6 m/s, the tubing retains its resistan The heat flow rate rejected to the cooling water @,
touched upon briefly in the consideration of CW qua- impingement attack, whereas this velocity woul is found from the equation:
lity. The objectives of such a strategy are to ensure beyond the reliable range of the copper-based mat
that the costs associated with leaking condenser tubes (Fig 4.8). Thermal design
are minimised throughout the life of the plant. This The use of titanium tubing in condensers desigl c preceding sections outline the functional require-
can be established by studying the following technical for conventional copper-based tubing materials, 11 of condensing and C W systems, and illustrate
and economic considerations: ever, poses a problem of incompatibility between tu ciivironmental studies into cooling water quality where q, = CW flowrate, kg/s
tubeplate materials. tiiken into consideration when choosing the geo-
The estimated life of candidate tube materials from Couples of titanium and naval brass, and titanium a1 lhical location of a new power station, and how
test rig trials, manufacturer's literature, experience, iron/steel have junction potentials of -288 mV nt Added to this is any heat rejected by drains from
aspects, in turn, affect the economics of plant
etc. -660 mV respectively, in relation to a saturated cal feedheaters, etc., which may be discharged within the
me1 electrode (SCE) [41. This creates the potential p 4 ,hasis has been placed on the importance of condenser.
The predicted number o f outages and associated
costs. blem o f anodic attack of the tubcplate material wh selection of materials in order to avoid un-
could lead to penetration of the tubeplate within bly high availability a n d maintenance costs.
The number of retubes required. design life of 30 years. Where naval brass tubeplat eration has also been given to the choice o f 5.1.2 H e a t t r a n s f e r
have to be used, such as in retubing situations, 111 le and condensing plant arrangements. The heat is transferred to the cooling water across
The capital costs of materials and retubing costs. practice has been to coat the tubeplate and waterbo Ihc objective of thermal design is to ensure that the condenser tubes (Fig 4.14).
340
Condensers, pumps and cooling water plant
and therefore
al resistance to heat transfer RT of the tube
d.P = (aD dP)U0 (4.2)
RT = R, + R, + R, m2 K/W
where D = mean diameter of tube.
U = l / R T w/m2K
d+ = q,,c, dB, (4.3)
A = 4,/UO,,, (4.10)
.
I>
-THE RADIAT~ONHEAT LOSS Steam Surface Condellsers [ 5 ] .
-THE BEARING HEAT LOSS AND MECHANICAL LOSSES
b, "4EGtNER"IORClASAND LiOUIOC001.FR HEAT LOSSES
nh,, H E A T ~ TTURBINE ix~nusr
T O T A L HEAT OF THE CONOENSATE FIG. 4.14 Ilea! tlal3riei reiisiancei vlld fillni The Brilisil Eiectricai and Aliied Manufacturers
n, .- ~ ~ a r ~ a u v a ~ t i r i o i r u nGsEi Nr Er R~~ O H ~ Y O R K O U T P U T
Association (BEAMA) publication 011 the Recom-
mended Practice for 1be Design of Surface Type
I'iC 4.13 Basic heal flow diagram Steam Condensing Plant [ 6 ] .
1/q,,c, = - O*)/Q.
9 Tube thickness.
,,trier Equarion The Fourier equation for
tional heat transfer is used lo express the 0 Tube material.
lieai flow in terms of heat transfer surface e Number of cooling waler passes.
cacfficient of heal transfer and meari teni-
lii. difference and is written as follows:
8 Service conditions:
r Tube cleanliness
q,,,L = AUO,,, (4.13)
r Air inleakage.
CONDENSATE
OUT
=
11,,>~ mass flow rate of condensed steam,
5.2.2 BEAMA design r e c o m m e n d a t i o n s
1. = specific latent heat, kJ/kg The thermal design procedures set down in the BEAMA
design recommendations (61 are very similar to tilose
followed by the HEI, except differences occur in the
linionce Equation This equation is usually statements regarding tube cleanliness, and the correction
factor for cooling water temperature as applied to the
overall heat iransfer coefficient (Fig 4.11).
The curves for the BEAMA heat transfer coefficients
qmsL = q,,,,cor (4.14) are based on tubes in the brushed-clean condition and
include an allowance for the normai oxide film coat-
ings which are an inherent feature of any tube during
<I,,,,, = mass flow rate of cooling water, kg/s its operational iife, whereas the HE1 curves relate to
c = specific heat of cooling water kJ/kgK tubes in the clean, as-new condition. In addition, the
BEAMA curves for cooling water temperature cor-
rection are based on a mean temperature, and not on
tube inlet temperature as in the HE1 curves.
Taken collectively, these departures have very little
In can be established for a given performance
effect on any design, providing due recognition of
ed on eight principal variables, which are:
these differences is made.
- BEAMA RECOMMENDED
HEAT TRANSFER
COEFFICIENT-(BRUSHED
0 A TUBES1
0
BEST FIT CURVE
DES~ONCORRECT~ON
FACIOR
0
A
A
0 v
A
8.8..
I
20
VELOCITY THROVGW IUBES -mb
.GI' 4.17 Graphs indicating differences in assum~tionnmadc by HE, 151 and BE^^^ ,61 design documents
FIG. 4.18 Typical condenser test results or ])eat transfer coefficient plotted vetocity in
349
Co~?densew,piimps atid cooling water plant
-p
5.3.1 Subjective design evaluation (Section 6 of this chapter), and also design val
'The tubenest geometry and its dispositioi~relative to the amount of air entering the coltdenser in th
the turbine exhaust have a considerable effect on will have been established.
the distribution of steam over individual groups of
tubes which, in turn, influences local heat transfer
Preliminary considerafions of fubenesl arrungn?irrrf
rates, and tubenest ventilation. More perhaps than
any other feature of large condensers, tubeplate and A number of decisions relevant to tubenest arrangcnr
tubenest arrangements may differ considerably between can be taken at this stage:
one design and another. This can be seen from the
many arrangements employed on the 500 MW series,
Fig 4.19. Each manufacturer of condensing plant ar-
extent to which the total number of tubes may
rives at his own solution independently. This high-
subdivided into separate banks, each associated u
lights a point which emerges from exoerience. that
its own tubeplates and waterboxes, air extract
tubenest arrangements which are apparently quite dif-
points and cooling waterside isolation. It is coniln
ferent can be of equally good performance, orovidina
nowadays t o restrlct the number of tubes supplld $@
that proper attention is paid t i a number df general
from any waterbox t o around SGQO, which has b
principles.
found through experience t o be a number which d
not inconvenience on-load Leak searching or I U
External conslrainls cleaning. Flo. 4.19 Typical lubenesl eonfibuialionr for 5W M W condensing plant
In designing the tubenest arrangement, a number of
external influences and constraints have to be taken Subdivision of banks Consideration may also
into account. The main external constraint has already given to subdividing the individual banks into 1,s
Condensers, pumps and cooling water plant Thermal design
Detailed corrsiderations of tubenest arrorrgernent High pressure drop in the tubenest This is i n
As a first stage in tubenest design, it is necessary to concerned with tlie pressure drop in the main
choose a basic concept. The two main features by densing section of the tubenest. Once the incoi
which the various possible concepts can be mast easily sable gases and residual steam have reached 111
characterised are the steam flow approach pattern cooling section, it might be assumed that tlic
to the tubenest and the disposition of the air cooling metric flow is small, and that the pressure illal
s~ction: therefore no longer a significant problem. This
ever can be a dangerous assumption (Fig 4.19 (I
352
Condensers, pumps a n d cooling wale1 ~18111
anrl the condenser air eatractioii poiiii caii bc envi- lemperaioie. I'liis jnicaiis 111e diSScvclice
liiili coiifigui-ation, arid coaling water flow, togetllei with tiit.
saged as being divided inlo lw'o pails; one across the tl~eoiclicaicold and 1101 end perSor.m- CW inlei lemperaturc.
tlic main condensing seclio~l,ilir othci ;!cross the air For a more detailed understanding of llic c o w
cooling section. Tliis C O I I C ~ I )is
~ ~ ~ i i ~ l ~ l i c by
a t e1111.cc..
d therefore inherently small. poiei lcchniques currently being iesearched, the reader
dimeitsional effects whicl? ate discussed later, but arc should refer to a paper presented at tile International
llle basis of I\vo imgo~.taiil gelieral principles (see Symposiuni on Condensen: Theory and Practice 181.
Fig 4.21): 1 liiiellv mentioned, this is a variation where thc
iidcnser is divided up into two or three corn-
a The resistance l o steam flou, along all actual flow tnxnts, one corresponding to cach double-flow
paths between the turbine exhaust and the entry turbine, the total C\?' temperature rise is, 6 Mechanical design
to the air cooling section should be equal. Wig11 eicfore, divided into a number of separate steps.
resistance paths tend to cause stagnation, resulting s compartments operate at different
in the poor thermal performance of associated to achieve balance in tlte air extraction
tubes. usual to connect the air pumps directly 6.1 Introduction
end compartment, and then allow the
Present day power station steam turbines require very
e There should be no major routes whereby steam can artments to vent into the ail. suction
large condensers: the basic problems are those asso-
reach the air cooling section directly, without first II~.via restriction orifices.
ciated with translating conceptual ideas into func-
passing through the main condensing section. If tional mechanical designs. As already discussed in
this occurs, it may become impossible to maintail1 of iiiree-di,nmsioria/ design Figure 4.22 shows
previous sections, the disposition o f condensers has
a satisfactory pressure difference across the con- i examole of the use of three-dimensional air
largely been influenced by the generic development
densing section and it will tend to stagnate as a >lingsections.
of turbines. This has made it impractical to specify
whole. Also the air cooling section will become 1, addition, 'disc' baffles can be installed in the
AIR COOLING a unique set of design rules which will complelelp
overloaded with steam, and will itself manifest a PLATE SECTlON - (li1i1, i lrai axial passage. Steam which is flowing axial-
cover thc diversity in constructional desians.
. How-
high plessui-e drop. f~.om the hot end of the condenser is forced
ti-li into the tubebank, thereby increasing the
ever, there arc many features common to all designs,
la)eeforemodlllcaton and thcse will bc discussed in detail with reference,
ce o f the steam flow path froin the ho;end,
lping to achieve correct balance of pressure where applicable, to relevant design codes, standards
Inundorion of lubes This is a problem which is and specifications.
directly related to the number of tubes in the tube-
TUBES REMOVED TO FORM n 10 of this chapter, looks at the position
nest. Reduce the number of tubes in each bank NEW AIR SUCTION PASSAGES
TUBES REMWBO TO FORM (ORIGINAL SUCTlON PASSAGLA nctional requirements of the air cooling sec-
(particularly in the vertical plane) and inundation NEWSTEMLANE BLANK50 OFF)
1011 in more detail, and describes its influence on
is reduced. 6.2 Constructional development
lii: design of the air extraction equipment.
An alternative is to place collecting trays at key The main areas of mechanical design are discussed
positions within the tubenest which will catch the under three main headings, these are:
condensate and divert it directly into the bottom of
the condenser (condenser hotwell) through a system C o m p u t e r a s s i s t e d design evaluation Construction materials
of gutters. nd and more recent design evaluation meth-
Condensate drainage can cause ondersooling. AI- computer techniques to assess the perform- r Design forces and stresses
though this is not generally a serious problem, it can steam condensers. The computer program
be avoided by allowing a small amount o f steam to $tl;ites the fluid flow, heat transfer and air con- Methods of manufacture and construction
enter below tlte tubenest to reheat the condensate lion processes locally through the condenser.
before it finally falls into the condenser hotwell. the interaction of these processes is very com-
Ihe program begins by representing the con- 6.2.1 Construction materials
s a series o f parallel slices perpendicular to The constructiotl materials may be conveniently di-
'Three-dimensional' eflecrs These effects have a sig- flow. Each slice is divided Into a number o f vided into those used in contact with the steam, and
nificant detrimental effect on the performance of fro1 volumes so as to represent both the tubenest those used in contact with the cooling water. Gen-
large condensers. The problem arises from the fact I i11c steam access lanes. The program first finds erally, plate materials, hollows and bars comply with
that, theoretically, the amount of steam which con- cam flow pattern, and calculates the local con- BS4360: 1972 [9] and BSISOI: 1964 [IO].
denses at the cold end of the condenser is greater lion rates starting at the CW inlet. T h e laws Details of materials for components, such as con-
than the amount which condenses at the hot end. ,PI Alter modillml,m servation of mass, momentum and energy are denser tubes and tubeplates which are in contact with
However, in practice this frequently cannot exist, be- to each cot~trolvolume to produce a large the cooling water, are thoroughly discussed in Section
cause it requires that the pressure drop through the I- o f , simultaneous equations for each slice. 4 o f this chapter. In addition, a n interface clearly
tubenest should be greater at the cold end than at program also calculates whether air pockets exist exists between selection of tube material and struc-
the hot end, and this is not possible if the air ex- FIG. 4.21 Ailernalivearrangements roi
steam-nor/iiii. ic tubenest, and identifies where they will form. tural design. It is important, therefore, to select these
suction in undcnlung condensers
traction point pressures are the same at both the sizes of the air pockets are determined by the materials early in the design stage in order that tube
cold end and the hot end. at the air vent points - the higher the vent support arrangements and the effects on structural
Although this phenomenon is sometimes accepted re, the larger the air pockets. From the solu- stiffness may be finalised.
as a fundamental factor in condenser performance, Use of a /ow CW temperalure rise, and avo1 1 the condenser vacuum can be predicted for given On conventional power stations, condensing plant
various measures can be taken to minimise its effect: of close approach between CW outlet tempt :a of steam flow, air leakage, condenser surface components which are in contact with steam are nor-
354 355
Mechanical design
-.
iii;iliy co!lstriiclctl froin eitlici reirrous or inon-Scrious sideration. These include Forces resuitirig fzom \,ariaus
,ii;iiel-isis. Recent specification:, for a Prcssulised Water connections, such as CW cannectionr to the water-
ilractor (I'W11) power statioll have indicated tliat boxes, and operational loads of the condenser struc-
~ioi~-ferrousinictals sliould not be useri, since the ture which must be considered when designing the
Iwild-up of deposits fro111 con-osionlerosioo effects LP turbine inountings and supi?ort foundations. Thesc
ii~sociatedwith non-ferrous materials, could be passed latter loads are of particular importance in the design
ihiough the feedheating plant, and jeopai-dise thc of integral and side-mounted condensers, where struc-
iilvel-ted tube bundle of the stearn generator, The tural stability is necessary to secure turbine alignn~ent.
atearn generator, unlike conventional boilers, has much Design stresses for the structures a1.e given in BS1501:
Eleater restrictions on the frequency of biowdown 1964 [lo]. In practice, however, these stress levels are
rarely realised, since the plate thicknesses are usually
optimised well within the limits OF stress to satisfy
minimum deflection criteria, and to conlply with the
Design forces and s t r e s s e s economics of manufacture.
main forces acting on condensers are shown in
.23 for vatious condenser configurations.
6.2.3 Methods of manufacture and construction
The methods used in the manufacture and assembly
of large condensers arc outlined, and the factors
influencing the extent of manufacture carried out at
works and site are discussed.
Traditionally, condensers for British turbines of
i 120 MW rating and above have always been shop
d I \, = force due to coohng watei static load~ng,N manufactured as a multitude of components which
are transported to site for final assembly and tubing.
1.1 = reaction force on turbine exhaust flange, N As already highlighted in Section 3 of this chapter,
however, economic considerations have recently led t o
a preferred arrangement in which each LP turbine is
= Sc = reaction force on condenser foundation
combined with its own transversely-tubed underslung
steelwork, N
condenser. This has allowed the development of a
modular condenser design so that one, two or three
I.$\\ = reaction force due to static and dynamic modules can be combined to cover a large range of
loadings from flawing cooling water, N possible turbinc ratings. This modular concept has
a high attraction for turbine manufacturers, parti.
I = Stc = reaction force on titl.bine/condenser cularly where they are competing in world markets.
foundation steeiwoi.k, N Now, before dispatch from the works, the condenser
shell sections, tubeplates, Support plates, baffles and
waterboxes are temporarily assembled and carefully
1: = reaction force due to springs, N
aligned so that final welding of the shell sections can
proceed rapidly and efficiently in the power station
= force on waterbox support, N prior to tubing.
There are a number of advantages to be gained
c = mass of condenser, N from maximum fabrication and assembly of condensers
at the manufacturer's works:
I = mass of LP turbine, N
8 It enables fabrication and erection to be carried
out in favourable environmental conditions, with
to = combined mass of LP turbine/condenser ready access to specialised machinery, welding, fitting,
inspection and test facilities.
w = mass of waterboxes
It provides a location where there is a high density
o i skilled labour and supervision in the various
disciplines.
n be seen from Fig 4.23, the largest single force
ultimately affects the design of the condenser Conflicting requirements between contractors for
is that which results from the vacuum, Fv. Ln space, access, cranage, etc., d o not exist. These can
on to the forces illustrated in Fig 4.23, there lead to reduced productivity which is detrimental to
external loads which are also taken into coil- the overall station construction programme.
P,Ci 4 22 ,,,,derlluns condenser for 660 MW unlt ehowing three-dimenclonal ax cooltng secuons
'uo!lea!.rqe~ j o sa!mouosa
pue 1113ua~lsJOJ Pas!iu!ldo a l e rla!qM sq!s pua saleid
3u!sn p ~ o lUnnseA a111 1su!e3e pauaJj!ls s! ljsqs aqL
'sauuol oOZZ s p a a m a r n l ~ n l l sa%p!lq le13a)il! aqi j o
1r18!a~ ieuo!le~ado J ~ L .s!xe au!q.rm a q ~01 as.lansue.1,
a l e saqnl aql leql 0s pa9uelia st rsauaon, , ~~~~~
,... 9--*
rrr
'la!liea Pals!! s3u!peaq a q ~.lapun p;>r
.IU!O/ isneqxa u!ew s q l ~ u i p j a f ialoJaq s11oq aq MOU !I!M .iasuaprro3 Sun!s.rapun 1 S I J A S
3~!!!3~alLq UO!I!SO~ Bu!lerado jemiou i!arll 01 palsnl -1EIOJ B iUlOJ q ~ ! i ls ~ u a u o d r n oJ O ~/ B U [en
-pe s3u!ids aql pue raiefi rn!M pall!^ sri: ssqnl pue .to Llqrnasse pua arniaejnueiu aql [I! pas"
5axoqlalEM aql '3rr!ses lsneqxa ao!qlnl ail) 01 pall!m
-?tier1 Su!aq s i u a ~ u o as1! 1 0 IJSUJp1105 JO lq3!aM
all1 p!oAe 01 pui: 's3o!ids [!o3 uodn palloddn? s! issuap - ~ .lasirapiloa
p j o ids>~ros.ie/npocu srli 5.1311,
-110s arlL 'Plea .Iaql!a ie s.ra!d uo!lepnnoJ sql oi s3p!rq r a LIE S M O ~ I SPZ'P ~ . l n 9 ! ~ ! oi t r o d s ~
2111 pa!.I.lea 911!aq r113!JIn aii!q.lni 5111 ' S ~ U ! . I B LIB
S~ -1los suralqoril auioarano oslv sni.i! ~ n q'a.
<13Ilil!!i(J 47 aqi 3u!tu1od1oso! ainisnirs a3p!iq J.J!IS j o poqisar ielnpoiii E ps~s!.i~saraxio L[J!LI,-
I: ~ t i l !13Suapl103 3111J O j[eg do1 aiji srirni ( s z ' ~ 8 ~ 1 ) -El!"'!! ~ ~ o l i s y i o m
I ~ ~ I J #([lie
!! loll a,\eq s.~ain~,,!l
a.
Condensrrs. ~puiiipsand cool~tigwarpi plant Clidp~~
4 2 Mechanical des~gri
- 4 -
Condensers, gumps and cooling warer plant Mechanical design
Wo'orerho.x~c 1'aclnrc o i condenscl.s, hui also oil kiioivlcdgc i is puuely onc of cconomy; porting striictiiic for the plate. Leak-tight slidiilg
1)cpending on tlic nii11,bcr 01' lpasses, Iransversc iioni inodci tests and fso,ii tests on otliei 1:iiy lready mentiained, it is a icquireolent joiilts are used to compensate for expansion. Vaiiolis
ii~lde~sluog colldcilrers ma). have inlet, ootlet and re.. denseis ill Britain, and oreiseas. us makeiiais arc noi to be used for tlle inethods may be used in combinatiori to providc
tuiii waterboxn. In every case the waterbox dio~ensions Clean conditions arc established within the coiiili design. Boll hole drilling ai' cl~al-acteristicsconsistent with tlie design requiremenls
ate sufficiem lo allow easy access for. ins;~ection via ser shell prior to cominalcemeri! of tubing. ate is carried out either by a jig or template and specific service conditions. Details of configura-
bolted and hingcd maniioie covers. The major design is u s ~ a l i )started
~ at lhc bottom rows, worki iuc ~niatchingwith the %,aterbon and shell flange tions commonly used on large condensers are shown
objectiucs to be realised in their construction, in ad- giessively upwa1.d~.When the bottoni io\vs on Fig 4.27. Figure 4.27 (a) sllows a typical double
dition lo acccss, are those of pressure and vacuum plele, it is ~~ossible to remove personnel as tl inner stecl tubeplate and lubeplate arrangement, using a combination of the
loading, and support. tlleil act as supporting &"ides when inserling suhvtji~, ndensei- shell is crucial and requires t articular lined and sliding joint, the inner and ourer tubeplates
The static and dynamic forces generated by tile rows of tubes. Guide bullets in tlie leading end 01' I it cannot be easily renewed once tubing is being of the same material. This design was extensively
flowing cooling water are taken by the waterbox struc- tube greatly assist the tubing operation. Figure 4.26 shows a typical detail of a used on the 500 MW condensing plant.
ture (Fig. 4.23), which is shaped to promote a smooth d flange joint. This joint is sealed with a Figure 4.27 (b) shows another typical double tobe-
flow of water through the tubcplate and tubes, and roofed fibre cloth and cord-filled dumb-bell plate arrangement, using rolled fixings at each joint;
Tubeplaies
prevent erosion at the inlet. Flange rotation is pre- ch is manufactured in one piece. The bolt the tubeplates arc o f dissimilar metals, hence the need
vented by selecting plate sizes of adequate stiffness The provision for double tubeplates has been mandti jointed up with a water test for the wide interspace gap to accommodate bending
or, alternatively, the pidtes are stiffened by external for UK power station contracts over the past ye81 id a drilling from the hydraulic connection niovements and to reduce shear stress in the tubes.
reinforcement, usually in the fornl of ribs. eliminate any possibility of cooling water enterinp I lbeplate periphery breaks into this groove, This is the method proposed for the PWR design.
The waterhox flanges are jig or template drilled to steam space of the condenser. Each tubepiate in1 the joint to be hydraulically tested prior lo Figure 4.27 (c) shows a double tubeplatc arrange-
ensure matching with tile tubeplate and shell flange. space is drained to a low level drain vessel ivhicli Access for tubeplate inspection may be gained ment of similar design t o Fig 4.27 (b), but here tlle
Earlier waterboxes were generally protected against niaintained at the condenser absolute press, ilic waterbox, which is fitted after all tube fixillgs tubeplates are of similar materials and the need for
corrosion in service by cathodic protection, with pro- means of a connection to the ail- pump suction lin ~npiete.Aftzr completc erection, when all tube the wide interspace gap is eased.
tectlon bosses provided to receive anodes. It is now equalisation of pressure on either side of thc it11 invc been expanded and packed, tile space be- Figure 4.27 (d) shows a typical doublc tubeplate ar-
normal practice to offer protection against iron oxide tubeplate ensures that no leakagc occurs across. i ilie tubeplates is filled with a fluorescent solution rangement, using a combination of fixed and sliding
scale by means of a rubberised coat, applied to grit- Therefore, any leakage into the interspace will I l~ressure,and the tubeplates examined from both joints, with dissimilar tnetals for the inner and outer
blasted surfaces pi;or to dispatch ta site. ~inilerultraviolet light to prove the absence of plates, as used on the more recent Heysham 2 and
interspace can be hydvaulically tested to a pr Tortless power station designs.
of 0.7 bar during maintenance overhaul via 2 Each of the above arrangements has been employed
Condenser shell water connections on the tubeplate periphery. A successfully. Typical tube sizes are 25.4 mm OD and
The condenser shell forms the boundary of the steam is fitted at the top of the tubepiate interspaw 1.2 mm wall thickness; tubeplatc materials are mild
envelope. The structure comprises a flool, two side- ensure that it is full of water. iclhod selected for securing tubes to the tube- steel and rolled naval brass, Muntr metal or aluminum
wails, and end plates with provision for expansion The formulae and rules governing tbe sizing l,l-ovides leak-tightness and strength as a sup- bronze for the outer plates (see Table 4.2). Titanium
and location of tubeplates. The build-up of a con- tubeplates have been based on the following stantlar
denser sllell varies between manufacturers. British and codes which have been progressively amended I
experience has shown, however, that the various line with tubeplate developments:
manufacturing practices produce end products which EXPANSION
SINGLE BELLOWS
CONVOLUTION
are compa~ablein quality, cost and construction time.
The sections making up the condenser shell are
BSI500 [Ill.
,
BS1515 Parts I and 2 (12).
invariably built up from steel plates welded together,
the only exception to this being the tubeplate attach- TEMA Standards: Tubular Exchanger Manufaot
ment, which is arranged for bolting or studding to Association Standards, Fourth Edition 1959,
shell and flanges. The shell is sometimes stiffelled for Edition 1968 (131.
vacuum and structural loadit~gby separate stiffening
members, but more generally the necessary support ASME VIIl Standards: American Society of
is provided by welding the intermediate tube support chanical Engineers - Boiler and Pressure V
Code Section 8, Divisions 1 and 2 (141.
plates direct to the shell. After welding, all shell
envelope and major structural welds are crack-detected.
using magnetic particle non-destructive testing or an The wider use of computer techniques in the desi
equivalent clleck. of tubeplates is presently being researched. An
ample which has been used is a beam element prog
which is based on the theory of beams o n elasti
Tubenests
foundations, and analyses the effects of pressu
The design and layout of tubenests is extensively edge loading from the waterboxes.
covered in Section 5 of this chapter, which empha- The methods of manufacturing of the tube
sises how the disposition of the tubes within the shell vary. The steel (inner) tubeplate is often drille
is the heart of any condenser design. The present and used as the jig for drilling the non-ferrous (outer
tubenest arrangement consists of an upper and lower tubeplate. Sometimes, however, inner and outer tuba
tubenest, each taking the form of a 'folded band' plates are drilled together, even where they are o
of tubes (Fig 4.20 (b)). This design draws not only dissimilar materials, to ensure accurate tube-1101
on the experience gained during many years of manu- matching between the two tubeplates. The reasott f o Fio. 4.26 Dmaiis of beliars and flange joinis
362
Cli Mechanical desigi~
Condensers, pumps and coolinil water llialll
:I I I , .<a,. L h ..,J\>I>Ic.'
l 4 ~ l ~ ' ~ ~1, ~:d'tlcJ ~ ~ nJu' ~ l3, Jrl,?~ ),..I:,. <.lJ l!,t:c[
. u I , . l 1 t l ~ !:rat, u > l n d . I ~ : t l l . h l . ~ . : ~ ~llc,!
~ ~ ~1 >!I:! .\
ta,v$,l l',~r:~:-l.~c a v \ \ :?.ken 11. ~ c I I ! ~ . ~ ! '.!.
1-1. I: eil.olr. '11;' o \ ~ I . < ~ A P : , o , .IJ.),)I
.I. s ! . J rhe
MlLDSTEEi MILO STEEL
$ 4 ' l..l~:~,l,tc ) < > L > 0 < 2 , . o:.", 0,. ..,".,,l~l,.~,,
BRhSSOUIER INNER iNNER BRASS OUTLR 8 8 I .I t u l ~ c p l ~ l :: (~
I . , l l l ! < l .,.d ,,-,L, ,,l$.,,.d'~
'(I ~'.~.t.cd.>r c\t'.,nJvd d ~ i db:llc! . I , ;$pl,t>
. , . 8 1 1 . 1 :.J:L~,,:< i J < ,.!k,>,,~Ic~ v,,c ., >,,,.,la,
, . ' 111. I . I > L ~ 3 r c 11:I h.ll~tl I U I . I I I ~ I : I U I C I ~
'.I . . I. . . t V ~x:>.~rluir..~! ~>dttc!r:,I , : ,.:I: ~111.1 ? I . ~ (
I ~ ~ . l l ~ ~ . l ?~t~cr!2n:c,
".~l c,o,, :\<,, 6 \ , , C I < ' . L ,
. , I .r.:: :< ,~l!,':l)\ <%d,)~ltcJ I ~ O
I I J Lt ~~ , Ij : I I : . I I H , .
Fit; 4.28 Turbine l a condcascr joint (for underslung
coiidesseirl
, . . .I . , ! : ,. .XI 'I. c ,l,'l., c,,a
8 . , t \,,,,:< ,,,, l
purposes. They support the tubes in order to control
. . I ,.,..I !uhc I I I ' ~ I ~ I I ~ III:~,I:~I
I ~ . x t ~ 3 1 . \ 1 d :+
n vibration, and provide means for bowing the tubes
". ~ v ..,I~ ~ oc InjdrkcJl! d ~ i t e r c n t . :\:cpl ~ I L W to assist drainage. Also, they provide a convenient
. . .1*t0.881 I I arc I C~llc:tl\el). ,u:rlcr rn,rmJl method of reinforcing the sheli against the external
8 -1818 . . I ! ~ I IL ,C 1 u l a 1 I ! 5111 pressure forces.
. ,,1 . : I c r a l o t . S I C 1511 The spacing of support plates is controlled by the
1
.,I.,. td~lurcd! thc Iul>c 1.21n1.'Tw ~ : I I ~ . I -criteria governing tube vibration, but usually the maxi-
a . , > I lb:r~%ecn41ell JLICI ! L ~ C *<I!. I . I ! & ~ mum dimension does not exceed 60 tube diameters.
1 I 1 .l:,l~:, .at1 I>: <>< Ih,&l, LC 22 .#.,,. \ With the intl.oduction of titanium tubing, tilt spacing
. ., ').at; t:\ir.; ilTllllldCII~C111\itnilsl I., 111. 4 2 - can be as low as 35 lube diameters which satisfies
8 m. ,, 11 \ ~,:x:kcJ gl.it~d J , > L , I I , , 3lm; U . I O the criteria of freedom from fundamental frequency
I . < . I . c~;,nllneJa, i ( , o s , ~ b . ~ j~lrri,t,n I., vibration from both machine and steam-flow-induced
' ust, t.11:;111 prdb1''m. bt.1 lans bccll .ibalidonc2 sources.
. I . , ' . t!n!clihbilil>. l h u praai:ai s o l u t ~ d , ~ Where support plates are used as inherent stiffness
,5( .. 1 . . t '11) o $ r the uac of ehpan,t,r b c l l o , ~ ~ members for sheli reinforcement, the plate strength
,$.
;
' iti
j. 1.8
8
.-I1.
. t 1,s.,~I.I.~~t~tl.ln
tttb:plate 1 1 r i ~ rat one cnJ. ~u,ilsll)
typci . <l-iL; 4.26,. and attachments receive consideration as edge-loaded
MlLOSTEEL MlLO STEEL BRASSOUTER s, perforated diaphragms and are stiffened to avoid
BRASSOUTER iNNER
buckline, if required. The plate thicknesses can vary
from 16 mm to 38 mm, depending on the design cri-
PACKEOGUNDS
PACKED GLANIIS
/ I ,,,,,,,< 101, ,I
teria. The tube hole drilling is carried out by multi-
, J I I I I . I C I ~ ~ I . I I L ?: ~ n d c ~ ~ r ci,' r atta:llcd 13 the spindle numerically-controlled drilling machines, and
.*., - '\84,,!, 1,
: *.
, e
,,l,l.t,& it is common practice to 'stack drill' up to seven
, .'. w..! ~ c t d i a sl~ostni n Pii! J . 2 ; l h h is support plates at a time.
.*;, B .:~vrt, .% 3
1.1 . Ir.,tl ucld. srslded t r o n l [he insldc, \ r l t l l
'*?.
...I.., s. ,.'.IN,. m,.,., In$ ,lril'. Aflcr .'Jnlpletion, the aeld I,
. ,**!:11. , # * . I . . ..111, .~;l;k-dcrcaed for soundrlel,. Branches, connections and reinforcetner~f
,.'$
.. '.', 112.8. I. I . O I I , ~ V I I > C ~ >3rc b o l t e d 10 tne turbine Ordinarily, reinforcement may be dispensed with be-
'".s . . I I , ! $ . I llc\~blc~ C I I J W S j ~ ~ n l , . cause plate thicknesses are in excess of those that
;j2$ require compensation. Details of any opening or branch
,.,.
I a
connection to the shell which requires compensation
and reinforcement must comply with the standards
Pm. 4.27 Tubc.to.tubeplate fixing arrangements for large condensers set out in BS1500 [Ill.
Condensers, pumps and cooling water plani Operational life limiting constraint$
I Pumps, gipci.orli
a i d ralvcr
1.5 times ma*. woiking
pressare
the tubes, with a resulting loss in condenser ef
genaled compoonds in ;in air stl.ealn, 1'0s iiiiiiimuin ge is oot usilig coiidoctivity )probes s i'lamc and siuokc techniques; the flil~nc from a
toxicity and maxirniln sensitivity thc lialoge~iatedconi- lion lo make divcct measuicments of air leaha il oil-load. l.11~ tubenest causing tile pro- taper (or smoke) is uscd to indicate a flow of air
poonds cl~iorofluorocarbon and dichloiofloaro- a i)eriociic basis, or i\,iien a condenser peiioit identified by an increase in condensate coli- into a leaking tobe.
inethane (trade narlles Freon 12, lsceon 12 or Arcto,? problcm exists, The metliods employed ilicl~iiii: his is si~nplificd in transversc underslune
12) are itsed. e Ultrasonics; the 11oisegenerated by air !lassin&tll~ough
use of Pitot tubes, anemometess, lhot wire 8811 , wilere multi-seclioning local
Of the leak detectors mentioned above, only the i n condensate conductivity will be signifi- a leak is detected'
meters, rotameters and orifice plate assernhii
LEYBOLD equipment tias a detectol. probe which can Measurements are made both a n the air 11 the location of the leak, and therefore easily
be immersed in the gas to be tested. This equipment pipe and at the air extraction plant discharge. The sensitivity and application of these techniques
is used by irlstalling the probe in the air extraction necded at bath locations. The assumption nlad ~ i n gidentified which condenser tubenest is at are discussed below.
pipe from the condenser, whereas the other detectors measuring in the condenser air suction pipe is I tiic second stage is to determine the level of
sample from the air extraction system discharge. water vapour present is satura:ed. When lneast~r iikage in that nest. This can be found either by
Most leakage points are found at flanges and joints, ,g the cooling water level in the waterbox and 7.2.1 Ffuorescein
the air extraction plant, if more than one piis
and are usually small cracks or holes. These can nor- opcrating, the flow between the pumps is no1 iii ring the condensate conductivity or by intro. The steam side of the condense1 is flooded to above
mally be sealed with any of a number of proprietary evenly distributed. trace,. gas the waterbox, dropping the the tubcnest with a 10 mg/kg solution of the sodium
metallic resin or rubber-based sealing compounds. water level, and monitoring at the air extrac. salt of fluorescein. A search is carried out in the
n l For the appearance of the gas as the leak is
waterban using ultra-violet light to detect traces of
fluorescein. The tube which is leaking is therefore
7.1.2 Measurement of air leakage rate 7.2 Cooling water leakage in condens. [Cresting are identified. There are, however, disadvantages of this
.
that these two
Apart from the air extraction system (see Section 10 The methods employed in British power statioi I , ble for all power stations, e.g., the former
of this chapter), air leakage measuring equipment is the detection of leakage of cooling uaater inl s satisfactory at sea-cooled stations, but, it is I~ is restricted to underslullg off-load.
generally not insrailed as permanent instrumentation condenser, and of the conseque~~t pollution of lble for freshwater-cooled stations wilere the
on British power stations. As in locating the air leaks, condensate are: ,thod is adopted. The reverse action of water pressure on the tubes
there are several techniques available to measure the procedures are adequate for narrowing the c o n ~ p a ~ cwith
d normal operation is known to close
I.ate of air leakage. r Condensate conductivity. search to within two or three rows of tubes, up the leak in some cases.
Operational techniques are used to determine whether !* ingc three provides techniques which will precise-
a reduction in condenser performance is due to con- * Sodium contamination. T ~ I Cthe source of the leak. The water pressure is low at the top of the condenser
and small leaks may escape detection.
denser fouling, or air inleakage overloading the air techniques used include:
extraction equipment. The operations carried out, which Location of condenser leakage is influenced bg Residual fluorescein can affect feedwater and boiler
only require measurement of condenser back pressure, ,rescein metllod; the side of the colldenser
following factors: looded with a fluorescein solution. water analysis, and impair judgement as to whether
are: repair of the leak was successful.
CW supply, i.e., fresh, estuarine or seawate I or film methods; the condenser tubeplates
Isolation of the air extraction equipment from the overed with a foam or thin film material whilst This method requires an operator to carry it out.
condenser on-load, and monitoring the subsequent Condenser design, i.e., underslung or pannier. vacuum is maintained o n the steam side.
rate of vacuum decay.
~bbiecdevices; air bubbling through a jar of water 7'2'2 Or methods
Changing the number of vacuum pumps in senice, Experience bas shown that the techniques us. The principle of this method (Fig 4.30) relies on the
used to detect a tube leak.
and establishing the effect of this on the vacuum. locate the region of leakage in fresh water cond development of a vacuum in a leaking tube. If the
a1.e not sufficiently sensitive to locate leakap gas methods; a halogen gas detector is tube is then sealed at each end, the vacuum draws in
Seawater condensers. Also, the introduction of p 11icd at the air extraction equipment and the a foam blanket or a film of polythene or paper, and
Typical unacceptable vacuum decay rates are 4 mbar/ type condensers for the 500 MW units mean] I xct tubes sprayed with gas. thus identifies the location of the leak.
min and above, as compared with expected rates of flooding the steamside with fluorescein solutioli,
approximately 1 mbar/min. most popular method of off-load detection
Wllere these techniques are not either favoured underslung types, was no longer possible. Undersit
or practical, other diagnostic techniques are often transverse condensers, however, have an advanta
employed which require measurement of: that they can have up to six separate sections w
M
Generally two ogeralois, each with a ihilni generator, metiiods of on-load and off-load cleaiiini! iil
arc required. Pill-hole leaks wilh a leakage rate of densei's are now described.
400 mi/h can be located, and 5000 tubes/lioiii can bc
tested.
The success of ibis method relies on being able lo 7.3.1 Condenser fouling
establish a vacuum of 330 mbar. Various forms of fouling havc already beel! i
in detail in Section 4 of this chapter, wl~icii
at the erosion/corrosion of condenser tubi!s
7.2.3 Bubbler devices impingement attack.
Figure 4.31 shows the two different types of bubbler Basically there are three aspects o f fouli
which are used for tube leak detection. arc beyond the scope of the CW scree,,
Figure 4.31 (a), the conventional bubbler, monitors installed:
the flow of air through a hole when the leaking tube
is under vacuum. The method will detect leaks down Blockage by debris.
to 175 ml/h, and an arrangement is adopted where Biological siimcs.
I0 tubes are monitored simultaneously, enabling 700
tubes/hour to be checked. Two operators are required 0 Scaling.
for this method which is suitable for off-load use
providing a vacuum of 330 mbar can be obtained.
Figure 4.31 (b), the MEL bubbler, is similar in prin- Blockage by debris of tube and tubeplates \
ciple to the conventional bubbler except that the tensively covered in Section 4 o f this chapter.
suspect tube is evacuated with atmospheric pressure Biological fouling refers to marine life wi~icli
on the outside of the tube. 'This method can iocate tribute to the formation of the slimy deposits
leakage races of only 35 ml/h, the test iate being up heat transfer surfaces of condensers. These
to 200 tubes/hour. bacteria, fungi and algae. The slimes formed !by I
micro-organisms adhere to the metallic surface, I
heat flow and form a laver to which other sust,e
7.2.4 Tracer g a s m e t h o d s matter can adhere to reduce condenser perforill
further. Some forms of marine life, such as ti1 ATMOSPHERIC PRESSURE
Detectors for halogen organic gases are extensively
and barnacles, can cause by restrictin
used for both air and cooling water leakage loca-
tion; Section 7.1 of this chapter gives details of the and blocking tubes,
method. Scale formation is caused by the depositio
reaction of inorganic material on heat tiansfi'r
Generally leakage rates of around 1000 ml/h can
faces. It usually occurs at inland river-cooled stal
be detected with the unit on-load or off-load, as long
using cooling tower systems. The scales are lirtl
as a vacuum can be obtained. One operator can carry
calcium carbonate or calcium phosphate, or niix
our a search using a transmitterldetector, although
of both, and arise from variations in their solil
lnore normally two operators arc employed.
products with temperature and p H changes (Fig 4
The temperature effect is due to the inverse solub
cllaracteristics of calcium salts. The pH changes tt LiUM
7.2.5 Flame a n d s m o k e m e t h o d s I'
by carbon dioxide stripping in the cooling tow
These methods are fairly insensitive and involve the
use of lighted tapers o r smoke tubes. Due to their
insensitivity, these are generally used as primary meth- 7.3.2 on-load condenser
ods of detection when massive leaks are suspected. T~~ methods of on.load fouling preven
are employed to avoid unnecessary costly shuld
of condenser plant, in order that efficient thro
7.2.6 Ultrasonic m e t h o d costs are realised:
Again, this is a fairly insensitive method which is
not generally used. It involves the use of ultrasonic Chlorination of the cooling water.
detectors to pick up turbulence effects of the air TUBE PLATE
near a pin-hole. Owing to the noise from the steam Fine filtration, plus tube cleaning using rubber b~
flow, and to a n extent tube vibration, only leaks ibi M E L. bubmr
close to the ends of the tube can be detected. Intermiltenr chlorinalion of the cooling water enlel
the condenser is carried out on all British 110
stations, and forms the accepted on-load foil
preventive technique. It is effective in controlling F ~ G 4.31
. n b e teak detection using bubblers
7.3 Condenser fouling and cleaning growth of mussels in seawater systems, and the for
The types of fouling encountered in condensers, and tion of slime in freshwater systems.
Coiidensers, i?umps and cooling water plarit Plant testing
8 Plant testing
8.1 Introduction
Condenser thermal performance tests are carried out
when the unit is recommissioned. for two reasons:
tions have experienced stress-corrosion crack-
e As acceptance lesfs to establish that a condenser
anded tube ends from acid cleaning.
meets its specified Performance, and is capable
of producing the desired condenser steam inlet pres-
sure when operating under specified conditions.
ncss in cleaning tubes, and requires a charge In both acceptance tests and routine tests, a high
I approximateiy 1 tnls. standard of instrumentation is required, particularly
in the measurement of the condenser steam inlet . ares-
sure, and the cooling water temperatures. Routine
tests generally use less instrumentation than acceptance
irlhod uses either high or low water PressuIe, tests, but only when it is certain that this is not
,dine a n the application. detrimental to accuracv.
1'10. 4.32 Graph or soiUbiiili ot caicium phosphate with cilangei iil ~cinpcial!iie and pH
make arrangements for any necessary preliminary work. which water is drawn into a mixing vessel. @ DIFfERENItkI PRESSURE
For example, discussions include reaching agreement boles or thermocouples are situated at cetl
with the manufacturer on: of equal areas, one hole or thermocouple to c
0.2 mZ of pipe area.
Interpretation of contractual guarantees
(C) Flow measurement The flowrates of cooling \vi I:xc. 4.33 Points of ntearuvcslent for condenser test
Location, type, and calibration of test instruments
(Fig 4.33). condensate and extracted air may be requ
when assessing condenser performance. Mrtl~
Means of obtaining the desired operating conditions. of determining the CW fiowrate include: ( oridcnser heat load deterf~~inationSite Test Code milar to that o n the rest of the condenser. The
No. 3 recommends that condenser heat load should common inlet temperature and individual tubc out-
Isolation of the plant for test purposes. Condenser heat balance
bc iierived from a calculation of the heat rejected let temperatures and flowrates are measured, from
The procedures to be followed for calculating results. Velocity/area methods. by the turbine-generator, preferably using heat rate which the cleanliness factor of each sample fouled
dnta obtained concurrently with the condenser test. tube is calculated according to Site Test Code
Differential pressure methods. No. 3 [IS], Appendices A and B.
BY agreement, the official report of an acceptance 7idDe cleanliness and air blanketing Both on-load The off.laad method reauires s a m ~ l etubes to
test may be produced by either party to the test, or Tracer methods. imd off-load methods for the determination of be withdrawn from the condenser. In a laboratory,
by representatives of the parties working together. condenser tube cleanliness are required, and also the cleanliness factor is determined by measuring
(he occurrence and location of air blanketing need the thermal resistance of the fouled tubes and
These are listed in descending order of preferel
lo be identified. comparing this with the thermal resistance of some
Test measurements and the Site Test Code No. 3 [IS] shouid
Figure 4.35 illustrates the on-load method for of the tubes after acid cleaning.
consulted for qualifications.
(a) Pressure meosuremenr The test pressure mea- iictermining condenser tube cleanliness. Briefly, Air leaking into an inadequately vented con-
Several methods are available for measul
sample tubes in groups of three or four are se- denser will blanket the tubes, impede condensation
suring system must give the mean static pressure the rate of air leakage into the condenser, n
lected such .that operating conditions throughout and increase the condenser pressure. The position
at the condenser inlet from each individual LP reference should be made to Section 7 of I
!lie condenser are represented. Separate supplies of air blanketing can often be inferred from mea-
turbine cylinder to within $0.3 mbar, Fig 4.33. chapter which covered these aspects. General
of CW are provided for each sample tube by surement of the CW outlet temperature distri-
It usually consists Of separate sets of pressure the preferred position for measurement is
tneans of insulated pipes passing through the bution at the tubeplate.
sensing holes linked by manifolds to which the air pump discharge (Fig 4.33), because me
\r,aterboxes, and one tube in each group is selected An abnormally low temperature rise indicates
test manometers or transducers are connected. ments at the air pump suction require detert
21s a clean tube which is acid-cleaned before the probability of air blanketing somewhere along
The same plane should be used for measuring tion of the steam/air ratio, and are made diffic
commencement of the test. the condenser. A more precise indication of the
both the condenser pressure and the turbine LP by the low density of the steam/air mixture. Cooling water is pumped fhrouglt the clean position of the air blanketing can be made by
cylinder exhaust pressure, fig 4.34. The measurement of condensate flowra
tind corresponding fouled tubes at a flowrate si- inserting a small probe into the steam space to
In addition, the steamside pressure drop should described in CEGB Site Test Code No. 2 [I
375
374
LLE 9LE
.sa!lleuad jeuo!lelado Zu!lln3u! l n o q l ! ~'pasnp sfe!ll aql 30 ssaaans aql 30 ljnsal B s v 'E'P a1qe.L lonls J O a s u e u l o j ~ a dlemraql aql j o 8u!puelslapun :Ol ale lueld %o!suapuos 30
-a1 aq o) az!s alsldaqm pue ql8ual aqnl llelano a q ~ 'suo!l!puos Bu!lalado 8u!Llen Japun suo!le~s~ a ~ a d IIJq e aAa!qse 01 In0 Pa!llel 8u!aq S! IroM luam su8!sap almnj 103 sah!lsalqo pue sm!e aql '!e~auaZ u~
SMOlle u%!sap aql 'asuemloj~adaqnl ~u!s!m~xem~8 laqmnu e 18 ]no pa!rres alaM sle!iI 8u;qni urn!li [wap pue qsleasal 'sua!sap auqd a w n 3 30 (,m/Q)
'pasea131q ~ ~ ! A J ~ S - U'uo!sola/uo!so~Ioa
I 30 slaajja aql isii! atldes 8u!suapuos s!j!sads aq) asealsu! 01 lapro u~
sa~!ma!qopue sur!t/ L.6
luawdola~appue qaeasau 2.6
anoqe O ~ O EL[a~m!xo"dde aq 01 pa~em!lsa s! lua!s -em aqnl lasuapuos sranoa laldeqa s!ql 30 p u
-!jjaos sajsueq ieaq llesaho u! asearsu! lei01 aqJ w u a l u d o l a ~ a pa ~ n ~ n6 j
'a8eu!elp alesuapuos
8u!ls!sse lua?!~~aosl a ~ s u e l lleaq ap!smea)s aqi 6u!q,,a 'Q!l!qel!ehe pus Ll!l!qe!lal alnsas (s)
sa!uado,d a3uaw,o,lad ;sw18qL l.Z
sluaur8ne osle 11 'leaq 30 ~ a j s u e ~aq) l ~!q!qu! pue auspuo3 a q l j o asuemlojrad [ernraq~aql as!m!mK (q)
[fern aqn) aq? Buole dn pl!nq iou op ssaitel Llepunoq
'9E'P 8!d u! u ~ o q sse 'sisauaqnl
'lasuapuos aql 30 az!S aql aS!m!U!K (el aql u!ql!~ arnssald pue am~eladma]aq) amseam
sap!s lalem pue meals qzoq uo a8plr les!laq pall01 e uo!iaas u! pau!llno ale luaudolanap Japun 4 1 1
seq 11 .8u!qnl pado, 30 aldmaxa ue s! L E ' ~adn8!d awmelSold ilo!les!m!ldo lasuapuos a 30 sl!ei3 siaruapuo~Bunlsiapun lo] tuaiua~nrearu a~nrraldlo Ju.id .9,d
'raldeqs s!ql J O 1.6 '4sua!a{j~a3!u1eui(pou1laql u! sluaman
uo!laaS u! uah!8 san!naCqo PUP. SUI!~ 30 IS!^ aql u! as!lea 01 .raplo u! 'sanb!uqaal s!sAlme ralndiu 'aNBp"r?B"n,5rs~"n , r a ~ / q ,
(q) pue (e) smai! Ljs!les 01 'Su!qnl (padol) 41iamoa8 sinoKei isauaqni rasuapuoa jo uS!sap aql as!ul!i
pasuenpe j o asn aql s! panZ!gsanu! Su!aq tqluallns paau aqi as!uSosal s ~ a i n ~ s e ~ n ulasuapuos
e~u )((I
s! q ~ ! r lFJu!qni
~ rasuapuoa u! luamdofa~aplaqloov anohel l s a u a q n ~
8u!qn) i(rlauioa8 PaJIlflApV
@
-
31VHMOld
3t(niV83dVi31Y i V 3 l l i W301 3 0
?I+"lWldVHI
0
SINlOd lNalY4HnSV3N
N O I I Y Y I W t l 3 l 3 0 "09 U3lV-M DNiLV7I73133ii
U3iY,i\\ 3N11003 -
NI M3
1110
3iVSN30N03
.
to 2.2 m/s, and tube lengths varied from 12 m to
18 m. Tube maintenance.
Table 4.5 shows the minimum cost, optimum CW ~~b~ cleanliness,
quantity and condenser parameters possible within
the constraints imposed o n the system being studied, Modular construction. TABLE
4.5
i.e., a CW flowrate of not less than 1.68 m/s and Oj~li,,$i$alionsludy resultsfor plain ond roped lilonium rubing
a CW temperature rise of less than 12'C. In particular, the maintenance of condenser t
Total Hcai ~ube CW nowrate
This suggests, for the two optima in Table 4.5, without access t o the waterbox is being investiga CW
Tube Tube optimum cost transfer veiociry, per set
savings of £200 000 by using roped tubes, however, ienglll (3 sets), areaiscl. m/r kp/s *PC
design
when compared to the existing condenser using conven- m C ~niliion mi
tional tubing materials, savings in the order of £2.6 PUMPS
million are calculated. Plain 15.1 43.2 29590 1.68 17790 11.0
An itnprovement in the overall heat transfer co- 10 f,ir extractionequipment 12.2 43.0 21786 1.68 16379 12.0
Roped
.
efficient of roved tubes is clearlv illustrated bv the
defined reducion in tube length and CW quantity,
and hence the size of tubevlate reauired to achieve lo.' Introduction
these savlngs The objectzves of the alr extraction plant are.
...~~. "-
s 'TO icniove air ivhicli has ieaked into the condenscl' 'The desigii air lcakngc i;itc\ ~,ici?liliii i ! i of how this is achieved arc described, and the Lions oS vacuunl niaint.aining and vacuulri l i t i , . i m / 8 ,
via flanges and glands effectiveh. 4.4 are known to be lhiglhei I!I~U! I I I O ! , ~ l ~ c i c ~ quipment types are reviewed. either in full or in pa1.1, depending upon the v c i l i ~ i i i i .
some othcr countries and, iii ~ n l l m y ill!,il#l to be evacuated and the time specified for syiiciii,i
e To remove other iiicondensabie gases that are pre- cousidcrably in excess or niv Ic~lk.l$?!.<% l % \ v L < ni~iiigthe machine.
sent in tlle steam exhausting froin the L P turbines. on British plan1 in practice. The c o n d e n s e r air cooling s e c t i o n It is interesting to note that the last-row bli~ir,,
However, experience has sllowll l i l i i l . O i i I' lci for the air cooling section to perform ef- o f a 660 MW turbine will overheat if they run ;ii
the adoption of these ratings lhna 1hui:n oc,rllc 1 I?, its position within tile condenser and the speed and at iow load in a poor vacuum. Therefor',,
It is important that both are removed from the con- justified as a means of countel;irlilI)i lilc i'i,illl Il)d of venting must be optimised, and the trans- a vacuum o f 677 mbar(a) must be obtained befoir
denser, as their presence in any quantity impairs the 01' incondensable gases from the condensing zone steam is admitted to the turbine, and a vacuum of
heat transfer performance of the condenser. Con- I
High air leakage, duc to val\'e pt~ckii~l> 880 mbar(a) for full speed. It is important that the
versely, excessive air extraction capacity should be joint leaks, etc. nsures that the air cooling process is achieved time taken to bring boiler and turbine plant on-
avoided, and reasons for this are discussed later. inirnum pressure loss through the condenser, load shall not be increased by insufficient extraction
The air extraction plant must be capable of func- Higher than design pressure loss tl~rollal~
Ill withoul creating stagnation regions within the capacity.
tioning under two cegimcs: one during normal opera-
tion, the other when raising vacuum on the turbine-
generator unit. . denser and air extraction pipework.
.
Rotary pumps (e.g., Le Blanc), which use water
When raising vacuum, the air extraction equipment system.
is faced with a large quantity of air which must be
.
from the cooling water inlet end of the with separate booster pumps for vacuum raising.
removed, and must therefore have the capacity for Adverse effects of part-load operalion I
the other uses multi-point extraction from
reducing the pressure in the condenser quickly to a cooling water temperature conditions.
points along the condenser lengt,h; these are Hydraulic pumps, which work on the water-jet
level which aliows the turbine to be started. lled for a pannier condenser in Fig 4.38. principle, for vacuum maintaining. Pumps of this
The considerable experience gailled, ptllliclil I' cooling sections designed on the first principle type have reasonable vacuum raising cliaracteristics,
from 500 MW turbine condensers, h;~slerl 1 0 I! lllc basic features of a redistribution passage but usually require to be supplemented by liquid-
greater understanding o f the factors iafil~c~~i:i! lic steam and incondensable gas mixture in the ring pumps for vacuum raising duties.
10.2 D e t e r m i n a t i o n o f air e x t r a c t i o n q u a n t i t y inleakage and its effective removal from Iinpo ~rxialdirection, together with a baffling arrangc-
T o ensure adequate removal capacity under operating densers. )wards the cold end of the condenser to force A system which consists o f an ejector and a pump.
conditions, the capacity of the air extraction plant The limiting difference between lh ' tiire across the tubemst before final extraction. The ejector provides the first stage of compression,
must be greatex than the maximum amount of air temperature and the cooling water d i-point extraction condensers, the steam and and a liquid-ring pump provides the final stage of
and non-condensable gases expected to be removed able gas mixture usually make one trans- compression to atmospheric pressure. This system
from the condensate. , of the air cooling section tubes, and no uses both the ejector and the pump for vacuum
The main parameters which determine the quantity performance. Most large condensers in opernl es are provided for reintroduction of the mix- tnaintaining duties, but the pump is used in iso-
of air to be extracted from the condenser and, hence, temperature differences in excess of this figuic: lo the air cooling section tubenest. lation for vacuum raising.
the design of the condenser air cooling system and air thinking suggests that a temperature differen i$icnsers with single and multiple water passes,
removal equipment are: to 5OC Is desirable if pressure loss on 11 will, single and multiple vacuum arrangements
and/or excessive steam carryover to the nllopted both types of air cooling section, and A summary of the development of air extraction
.
r The design air leakage into the condenser.
The degree of sub-cooling of the air/steam mixture
leaving the air cooling section.
equipment is not to become a critical fact<
mining condenser performance.
erally operated satisfactorily.
ingle-point air extraction concept generally
higher pressure drop in the condenser to
lisfactory flow through the air cooling section
equipment is given in Table 4.7, wilicll indicates the
number of installations of each type of equipment
associated with 500-660 MW turbines in the UK.
It is quite clear from Table 4.7 that the use of
multi-point arrangment, but it reduces the rotary and hydraulic air pumps has virtually been
r The limiting approach temperature difference 10.2.1 T h e m e c h a n i s m of air extraction
I? o f excessive steam carryover t o the air phased out in the 660 M W designs. The reasons for
between the saturation temperature B P , T cor- The mechanism by which non-condensable Bl this change in policy are discussed below.
responding to the absolute pressure p, in the transported between the points of entry to I h the introduction of air extraction equipment In the initial stages of the 500 MW programme,
condenser, and the CW outlet temperature. denser shell and the discharge to atmosphrrc incorporates a direct contact pre-condenser, orders were placed for two air pump systems on
subdivided into three stages: over o f steam is not such a critical factor which there was previous British experience; these
Table 4.6 indicates recommended values for typical 'rmining the air extraction capacity. being Le Blanc pumps and hydraulic air pumps. Both
Transfer of incondensable gases from the systems, however, could only offer a small contri-
fossil-fired power stations of varying size. condensing zone to the air cooling sectioll bution during vacuum raising, and relied on supple-
condenser. mentary equipment to enable units to be loaded within
TABLE 4.6 R e v i e w o f air extraction equipment 20 minutes.
Cooling o f the incondensable gases and as
Design oir ieokagc roles for typic01 fossil-,ired siorions lia development of air extraction equipment The 'ejector plus pump' extraction systenl was
steam in the air cooling section.
condensers has evolved through the use of introduced into Britain during the early 1960s. Initially
Turbine size. MW Extraction and compression of the incondc clion pumps. Steam-jet air ejectors were in this system only used atmospheric air as the motive
11 use, but, for the higher pressure and fluid in the ejector stage, and incorporated a liquid-
gases from condenser vacuum to atmosphert!.
Design air leakage rating, kg/h tilrc cycles adopted today, these have proved ring pump for second stage compression. This gave
Design air suction lcss economic than air pumps, both in capital better vacuum raising characteristics than the hy-
ienipcrafure at oiltlet. C
' In order to meet the objectives outlined earli draulic air pump, which offset the slightly higher
Limiting CW outlei temperature is important that all three stages in the procc Iv different air extraction equipment designs operating costs of the system for vacuum maintain-
carried out efficiently. en developed, all of which combine the func- ing duties.
381
Air extraction equipment
X
10.3.2 Licluid-rintt- tvne
.. air numn
. .
: 0 . I I Hydraulic air p u m p s This is essentially a centrifugal displacement pump.
A multi-blade impeller revolves within a n offset casins
. \ I,,) ..$I Il!draui\i XLI putnp arraopcmrn: !r \i>;\srl which is partially full of water. The rotating impeller
$ .?t I . . .I 39. I'll: l , ) . l r , ~ u lpump
~~ unit 1, a !%a.cr-
throws the liquid outwards, resulting in a solid ring
of liquid revolving in the casing at the same speed
r. rccirculating lift pump, and a covered water
as the rotol, but following the shape of the casing.
ld air separation tank. Figure 4.40 shows how this alternately causes the
watcr tank serves the dual function of acting liquid to enter and recede iron] the interblade spaces
___)
il:;it sink for the air and vapaui drawn from the on the impeller. The provision of inlet and outlet
and providing a suction supply for the lift ports enables this pump action to be used for eva-
cw ~ N L E T recirculate the sealing water. cuation of air from the condenser. The advantages
up water is introduced t o the tank at the of this type of pump are that it is simple and reliable,
I11 to replace any losses, and maintain the tank at with large clearances on rotating parts, and no valves
iy temperature. The tank overflow is controlled or pistons.
weir, and is discharged to waste.
in8 water from the tank is circulated to the
'
ONE PANNIERSHOWNONLY air pump where it is fed into a series of 10.3.3 Air e j e c t o r l p u m p s y s t e m s
Streams of water leaving the nozzles pass Figure 4.41 shows a typical arrangement, using air
blades of a spinner which is mounted on as the motive to the ejector. The system comprises
11 of a shaft, and is free to rotate. The blades a n ejector stage and a liquid-ring pump stage, which
led so that the sealing water propels the combines to give two stages of compressio~~ of the
and, in doing so, is broken into slugs. The condenser a i r h a p o u r mixture.
(hi ~ ~ i t , - p oaiiexlra~lon
i~i u'hich ,discharges from the spinner seals poc- Figure 4.41 (a) illustrates the system when operating
Ol' air in the diffuser, pressurises them, and to maintain vacuum in the condenser. The a i r h a p o u r
illges the mixture into the tank. The tank is suit- mixture from the condenser is first drawn through
FIG. 4.38 Single and multi-point air eriraciion vcnted, and the sealing water is recirculated to the vapour cooler. This is a direct condenser which
receives recirculated seal water, of towns water qua-
nir suction line t o the water-operated ejector lity. This cooler reduces the vapour quantity of the
[,rates an electrically-operated isolation valve mixture before compression by the ejector stage. The
C-type non-return valve t o prevent backflow ejector uses atmospheric air as the motive fluid and
llnd water to the condenser in the event of compresses the a i r h a p o u r mixture to a pressure of
failure. Some arrangements also include a about 135-170 mbar.
383
..
INIERNALINLEIPORI
(NTERNIIL DlSCHIHCit PORT
--
.-
--.
-
=--- WATER
~c condensate from the vapour cooier and the 10.3.4 Steam ejectorlpump systems
-
- CWLINGAND MOTIVE
last vacuum raising, booster Pump arrangements is pumped to waste by a cooling water extractor
PIG. 4.39 Typical hydraulic aii pump airangment
'iar to those described for hydraulic air pump pump.
ms) are incorporated, these booster pumps are The motivating steam for the ejector is vent stekrl>
iged t o shut down automatically at about 50 from the de-aerator which would otherwise be dumped
to the main condenser. Since de-aerator pressure varies
385
----....---
-
-
-
COOL1NG WATER
USUAL NUMBER OF "NILS2 x 700%
-
TOWNWATER OR CONOENSATE
SIEAM
AIR VAPOUR MIXTURE
Fic. 4.42 Steam ejector and liquid-ring pump air airaecio~lmainlainins system
-
- CWLINCI WATER
---- T O W N M T t R OR CONDENSME
-
-
ELECIRICAL
AiR
4iA YAPOUR MIXTURE
I° vacvvm ralrno DPsral,o"
387
Condensers, pumps and cooling watel plant liydraulic aspects of centrifugal pumps
148 5W
DATUM
DATUM
nc. 4.45 rum,, efficiency vers US specific speed and punlp size
is not exceeded. These costs could offset the apparent in pump design - head, flow and speed. All
cost savings of £134 764. metrically similar pumps have the same specific
It would appear that the intermediate vacuum which is calculated in non-dimensional units r, pumps, optimum efficiency when using low 11.2 Net positive suction head
pump size (pump B) can meet the traditional vacuum the following formula: i prime movers necessitates a large number of The net positive suction head (NPSH) is an im-
raising time of 20 minutes, and offers some cost portant concept in judging the suction behaviour of
saving, aithough not as significant as pump C. n, = 2 ~ n ( q , , ) ~ ' / 6 0 ( g ~ ) ~ ~ ~ !s comparison, efficiency optimisation could be
a centrifugal pump. A distinction needs to be made
The extra pumping capacity of the option would llieved by using single-stage high speed machines.
between the NPSH available to the pump and the
be more tolerant to any increases in air inleakage where n = pump speed, r/min 11 these extreme options, however, can have their
NPSH required by the pump.
above 40 kg/h, and therefore less emphasis would I potential disadvantages. The high speed ma-
q, = flowrate per impeller eye, m3/s The NPSH available is the difference between the
need to be placed on achieving and sustaining low ' can lead to excessive impeller tip speeds and
H = generated head per impeller, m equential erosion problems, while the slow speed iniet head to the pump and the saturation pressure
air inleakage rates from the associated plant.
g = acceleration due to gravity, m/s2 Ingernent results in a flexible shaft design unable of the liquid being handled. As the available NPSH
'ater for transient operational requirements. Thus is reduced, cavitation commences, first at flowrates
pump hydraulic design is usually a compromise away from best efficiency and eventually over the
There is no firm demarcation between the \ complete operating range. This is a result of the local
pump types. Each merges into the next, so take account of all relevant factors, including
11 Hydraulic aspects of centrifugal ,hanical limitations and suction head considerations. pressure falling to the vapour pressure of the liquid
a given specific speed there can be two p
pumps le effect of moving away from best efficiency can at the particular temperature condition. Operation
differing construction. However, specific sp
en in Fig 4.46. A specific speed below optimum in a cavitating mode for extended periods results in
be defined as falling into the following catego
the peak level of efficiency, but there is a erosion damage, regardless of impeller material. Feed
uential improvement in the spread of higher pumps with a high head per stage are most liable to
11.1 Specific speed Type of pump Specific speed rang? cy. This can be of use when plant is required cavitation damage because of the higher energy input
(IS0 notation) perate frequently over a large flow range. to the fluid.
Centrifugal pumps are traditionally divided into three
basic types: radial flow, mixed flow and axial flow. Radial flow 0.2 to 1.8 oving to high specific speeds is seen to produce Cavitation performance breakdown has been shown
The names indicate the direction of flow of liquid Mixed flow 1.8 to 3.0 eeper head/flow characteristic. This can be ad- t o be directly proportional to (shaft speed12 for a
through the impeller. The term specific speed (n,) lnlageous when operating pumps in parallel as it centrifugal impeller. It has also been shown that the
Axial flow 2.8 to 8.0
can be used as an aid to the classification of the oiinises the risk of unstable operation. One dis- head drop at which unacceptable cavitation damage
pump type and is indicative of the shape of the im- vantage of the high specific speed designs is the in pump impellers occurs, increases with pump speed.
peller and the pump hydraulic characteristics (Figs It is evident from Fig 4.45 that to optimise the npe of the power/flow characteristic which can be From these findings, it is evident that the suction
4.45 and 4.46), which are taken from Steponoff [19]. draulic selection on an efficiency basis, a spe lest at closed valve. This results in excessive motor head levels needed for high speed pumps are signi-
The expression involves the three fundamental factors speed around 0.8 is necessary. For high-head I ngs to cater for start-up requirements. ficantly greater than those for lower speed machines.
391
Cotidensers, pumps and cooliiia water alant Circulating water pumps
Suction specific speed CCGB experience baa beeti gencsaliy based oil
cinr siiclioir syccific speed (n,,) cxpl-csscs the lhydieuiic designs wliel-e tlic specific speed bas been
3 1 capability of the piimp iiiipcllcl- and is defined limited to 1.6. This iediices the risk of both head/
iiow clial-actcl-istic instability and high gowe~.sat low
- a -cood efficiencv. sol-ead
flows. I t also ri\,cs . over
n,, = 2nn(q,)oS/6~(g~~~~)0.75 thc range of operating flowratcs. 'The head/fIou~rate
and absorbed power characteristics are now controlled
EFFICIENCY %
OF NORMAL
n = pump speed, i./min
q,. = fiowratc per impeller eye, m3/s
NPSH = net positive suction head, m
.
by the following specification:
.
CAPACITY % OF NORMAL CAPACIIY % OF NORMAL diameters and improved suction capabilities the maximum ~ ~ u n o ucondition.
t
EFPlClENCY HEADCAPACITY
llnd pump best efficiency (BEP). The large eye
lead to problems of inlet The input power rises continuously as the flow
off-duty conditions, with is increased from zero to the rated flowratc.
hcquential pulsations in the pump and adjacent
()?work. At flowrates away from BEP, incidence
scs flow separation within the impeller. This se- Circulating water pump speeds arc normally in the
inled flow is then directed backwards out of the range 150-300 i/min. Low spccd motors, suitable
'l'lic larger the impeller eye, the nearer to the for direct coupling to the pumps, are expensive and
is the flow at which this recirculation occurs. it is usually economically justifiable to include a
BRAKE 1 Prevent the damaging effects of inlet flow re- stcp-down gearbox between the pump and motor.
$HORSEPOWER% lation, leak-off flowrates need to be sized so as The combined efficiency of a I000 r/min high speed
OF NORMAL
cllsurc that pump throughput is always in excess motor and associated gearbox can bc similar to the
ille amount at which recirculation commences. low speed multi-pole motor. When comparing capital
a applies particularly to both feed pumps and costs of the two ootions. the costs of extra cranaee -
equipment and the additional civil work to support
111 the absence of detailed information of pump the heavier motor have to be added to the direct drive
0 21 50 7S >OD 125 550
liability at the tender stage, the CEGB normally pumpset costs. The two main advantages of the dircct
CAPACITY % OF NORMAL iliiires that the suction specific speed bascd on the drive option are its simplicity, which can lead to higher
Sli available to the pump should be limited to availability, and the elimination of any noise control
BRAKE-HORSEPOWER
requirements arising from the high speed motor/
gearbox combination.
For fiowrates over 10 n?/s, main cooling water
pumps arc now bascd on the concrete volute type.
Circulating w a t e r pumps Below around 6 m3/s, it is impractical to consider
concrete volutes because of physicai access limitations
in the mechanical seal area, and metal casing designs
The minimum NPSH required can be defined as that to avoid cavitation problems [ZO]. have been used. Between 6 and 10 m v s the CEGB
value of NPSH needed by the pump under long term Visual cavitation tests are carried out on a sp ,I Introduction have so far installed only metal casing pumps, al-
load conditions to prevent the occurrence of harmful test facility, where, for example, a perspex wind ructural design of main circulating water pumps though concrete volutes have been successfully used
cavitation effects, in particular that required to avoid allows an uninterrupted view o f the impeller eye, EGB has changed over the last 20 years from elsewhere.
cavitation damage and ensure satisfactory operation. enables visual observations t o be m a d e uni tal split casing double-entry designs to the
Normal practice for determining the NPSH re- stroboscopic lighting. This is a n important to spindle bottom inlet single-entry type. The
quired to limit cavitation damage to a n acceptable allowing the exact cavitation inception point to tal pumps, while easy to maintain, require a
level is based on head drop tests. For high duty feed determined, which effectively defines the zero cav floor space, and the weight problems on the 12.2 Horizontal split-casing pumps
pumps, the assessment of visual test data is now also tation damage line. Although observations o f I units necessitated the use of multiple casing Double-entry horizontal split-casing type pumps (Fig
used as a n additional means o f assessing the adequacy pressure face o f the blade are difficult, this pr s. The alternative vertical spindle pumps, now 4.47) have been installed on CEGB stations to cover
o f NPSH margins. can be overcome by using acoustic inception ly specified, have been developed for both a wide range of duties up to 18 m3/s and 24 m gen-
The NPSH head d r o p test can be included as niques to establish the onset of cavitation. I casing and concrete volute applications, with erated head. This design of pump has the major
a standard proof o f performance test, with mea- checking NPSH adequacy using the visual techniq~i clloicc depending on the overall economics o f advantage that the top section of casing and the
surements being taken to establish the NPSH a t current practice requires the available NPSH to Ihtl\ installation. They have significant advantages rotating element can be removed without breaking
which a 3% drop in generated head occurs. From a margin over the visual appearance NPSH, wh >pared with the horizontal designs in terms of thc either the pipe joints or disturbing the alignment.
data available, it is considered prudent to provide itself is associated with bubble cavities having n apactness and cost of mechanical, electrical and While this feature gives good accessibility for both
for feed pumps at least 3 x 3% head drop NPSH agreed maximum length. I engineering work. overhaul and maintenance work, the horizontal design
392
:ondenscrs, piimps a n d cooling water 111ont chiii,li: Circulatilig water pumps
i nomher uf disadvantages apart from the large duct. Tiic asseinbly then acts as both a sealing ring
area i-cqilired. In ipariicular, the preference for for [lie top covci and also as a ccntral location
ling llic uilit with thc iiiipeiler cyc beiow mini- araunrl which the precision-made voiute sllutleiirlg
water level, to eiiminale the need for com- framework is assembled piior to concrete pouring.
prilliing equipment, results in expensive civil The volute shotteiing is iiorrnally provided by the
ivations. The physical size of thc large metal civil contractor to thc pump manufacturer's dimen-
has also brought about both manufacturing sions, and can be re-used on all pumps on the same
lties and fiexing problems with the complicated contract. Figure 4.49 shows the various stages of
construction of the volute. From experience, it has
been found that no special protective coating is re-
quired on the concrete to guard against the effects
o f the water being pumped. Both wear and life
Vertical pumps expectancy of the concrcte are excellent and no pro-
blems have been reported on CEGB pumps at inland
3 . 1 Vertical metal-casing p u m p s or coastal stations over a 20 year operating period.
lute casing designs have been used by the CEGB A fabricated steel bearing bracket is mounted on
iIilmping duties up to around 8 mi/s. On low head top of the pump cover and bolted down and dowelled
a1 applications, standard gear-driven units have into position to secure correct alignment. The speed-
lstailed, while on the higher liead inland cooling reducing gsarbon is !mounted on top of the bearing
applications, it has been possible to use a direct bracket, with the unit incorporating the pumpset
I- drive while still retaining the same equivalent forced lubrication system. The rotating assembly is
,cific speed a s the equivalent gear-driven units. supported by a combined thrust and journal bearing
llernative bowl pump designs have been used which can be located within the gearbox. Access to
iisivciy on overseas applications. With this design, the bottom bearing and mechanical seal is gained
l u m p forms part of the piping and its intake is from within the tubing.
rn a relatively unsophisticated suction chamber;
~nerallyhas a smaller civil engineering cost than
equivalent concrete volute design. There is no
nplicated volute to construct, and as the pump has 12.4 Gearboxes
nalier overall diameter than the concrete voiute, Gearboxes, when included on vertical pump units,
pumphouse floor area is smaller. On thc debit must be of the coaxial type with the pump, motor
and gearbox centreiines positioned vertically above
each other to ensure an equal load distribution on
the support ring.
c normally has to bc sized to take the total Coaxial gearboxes may be either of the muiti-
I 11111 weight for installation and overhaul. As the layshaft or epicyclic designs. With recent epicyciic
111111) is withdrawn vertically for major overhaul designs, it has been possible to combine the gearbox
a suction isolating valve is not required. This and the pump by mounting the impeller on the low
er leads to a relatively long pump to facilitate speed output shaft of the gear unit (Pig 4.50). This
I isolation. One major technical disadvantage arrangement eliminates the need for one journal
the bowl pump is the need for submerged shaft bearing, which in turn reduces the overall height of
iring bushes. These are not readily accessible and the pumpset leading to a more compact arrangement.
lave a relatively short life in silt-laden water. A further reduction in pumpset length is achieved
sting problems have tended to limit the size of by combining the thrust coliar into the coupling hub,
as shown in Fig 4.50.
of cast iron necessitates the inclusion of sub- The gearbox is equipped with a complete forced-
ntiai allowances on coastal units to allow for lubricating oil system to provide a continuous flow
rosion/erosion effects over the life of the station. Of oil to the gear internals and the thrust and journal
bearings throughout the pumpset. The oil system
includes both gear-driven and standby motor-driven
C o n c r e t e volute p u m p s oil pumps, and the piping and non-return valve iayout
re 4.48 shows the sectional arrangement of a allows delivery of oil to the bearings and gears,
1 concrete voiute pump, which follows the whichever direction the pump is rotating.
e hydraulic principles as the conventional metal
lg designs except for the volute which is formed
F ~ O .4.67 ~orizon~ai
split-caring extraction pump at Dunsenerr B Power station ite on the concrete foundations. The pump casing
ists of permanently-embedded top and bottom 12.5 Shaft seals
'ng rings separated by the cutwater and stay Mechanical seals are included to prevent water es-
cs. These are carefully positioned over the inlet caping from the casing along the pump shaft. Split
TACHOGENERATOR C0NCIIEII;INIO
MOTOR srooi
1:iG 4.49 ConstrucLion or concrete voiuie
I designs are used (Fig 4.51). All the com- performance of the full sire pump and the cost of
OlL "RAIN
Ipollcnts to be carried out witllout any major itself. Model tests enable the hydraulic characteristics
of the full size pump to be accurately predicted. This
m the pump discharge o r a separate towns Scale models are also used to verify design pro-
ply. Figure 4.52 shows a typical seal flushing posals for the suction intake to the pumps. The model
nt on a coastal station, where the filtered normally comprises the forebay, intake screen cham-
normally taken from the pump discharge ber, draft tube, volute and discharge pipework. Com-
ng purposes while the pump is running. A prehensive tests are carried out to demonstrate the
f any large new circulating water pump design. use. For other stations where there are no suitable
an economic method of evaluating the likely open channels, the isotope dilution method is widely
397
MAINOIL PUMP
INFLATABLE SEAL
PLANET WHEEL
LOW SPEED Hli<i
used. This involves the injection of a tracer of work, and yields highly accurate results. The prir
known concentration at a constant rate upstream o f disadvantage arises from the strict safety precaul
the pump and measurement of the concentration at necessary when using radioactive tracers and thc the waterways. Special attention is required at the
a point downstream of the injection point where sulting inflexibility of the test programme. c use of austenitic ni-resist cast irons for the sleeve/sleeve and sleeve/impelier joints to prevent
adequate mixing will have taken place. The dilution An alternative flow measurement technique 18 material of cooling water pumps where severe ingress o f water onto the shaft surface, which can
technique is completely independent o f the velocity developed is the use of ultrasonic flowmeters, lilions exist is now increasing rapidly. This ma- cause corrosion fatigue. On horizontal pump designs,
of the pumped fluid, or the dimensions of the pipe- multiple transmission paths being included to I, particularly in its spheroidal graphite form, overlapping sleeves and radial O-rings have been
399
FIG.4.53 Horizontal split-casing extraction pump
Condensers, pumps a n d cooliiig water plant
Railer teed pumps
-
impeller inlet, the first stage impeller eye of a hori- which can occui on the a l t ~ r n a t i \ ~aliangeillr
e
zontal extraction pump should be vented back to the the punlps are operated significantly awa)' f~-oil3Ill
vapoui space in the condenser, with the vent piping duty points.
having an upward slope to the condenser. I'umps are specified with a requirement thar
In recent CEGB stations, where surface tubular tion erosion does no1 produce mechanical fail
COIlPilNG L D C K N U i
large split-casing pumps, particularly in sealing the is limited to 2.4 (ISO). COUPLING KEY
main joint and withstanding impeller radial loads.
VEHIICALIHRUSTANO
An alternative caisson type pump (Fig 4.54) has now JOURNAIGUlDEULARINC.
been adopted. The multi-stage vertical pump design
has several attractions over the horizontal split casing 14 Boiler feed pumps SPINOLESFIIING
PUMPDELIVCRI
pump: ARRLNGMENIAND
LE*K.OFT SISIEM
COFDELIYERV
The NPSH available is increased by installing the
pump in a pit, thereby reducing the risk of cavita. 14.1 Introduction
tion crosion.
To ensure that the extraction pumps have stable There should be at least two pumpsets capable
head/flow characteristics and are capable o f operating starting the unit. If a turbine drive is to fulfil t LWSE BELLMOUItI
in parallel over the complete operating range, the function, then a steam supply independent of
BEARING BUSH
pumps are now designed so that the generated head main boiler (i.e., an auxiliary boiler) is requir
rises by at least 1 % for every 15% reduction in
flowrate between the rated duty point and 25% rated If two o r more pumps are required to op
flowrate. in parallel, then the pumpsets should be able
Extraction pumps on CEGB stations have been accommodate run-out duties following 10% of
operated on either free suction or recirculation control. operating pump. FIG. 4.54 Vertical caisson extraction pump
402
Boiler feed pumps
Condensers, pumps and cooiing water plant
r TIi? pio\,ision of sufficient l>iirnying to were typically a sliou,n iri Fig 4.55; tile!' illcli ?/mill) to aciiicve tlie necessary lhigir licad pel- stage.
fro,,, ,.equire,,,ents ol)cl-ationai ~ i ~ long
. flcxibie shaft witli about sin stages and i l l i Slow speed boostcr pumps arc therefore required to
cumstanccs. It is lioililal practice to include a flow dual t111.ust from the impellers taken by ;I pravidc sufficient NPSH to linlil cavitation problems
rnaigio to accommodate additional demand by the tional balaiice disc arrangement. The bearin I>III damage, and having s cartridge co~istructiorl on the main pump.
turbine above its design rating during transient mounted o n separate pedestals which had I < With regard to NPSH, a conservative design ap-
flow disuirbances. A margin on pump generated moved before the $main pomp internals could i)i' V proach was adopted. De-aerator storagc tank height
head is also appropriate to cover for deterioration drawn. Glands were of the fixed labyrintli Or i i ~ ~ l l and suction pipewark layout were arranged to pro-
from intcrnal wear during periods between ring type, and the main bolted casing joint I specification, means that the pump nlust be vide a substantial margin of NPSH over the measured
overhaul. In the interests of keeping pumpset sizes jected t o full discharge pressure. pump 3% head drop NPSH, even under the worst
transient situation.
for replacement of the pump internals. iibstanlial head. After this the pump is enpccted 14.3 Advanced class feed pump construction
The pump casing consists of a forged steel barlei to
flexible shaft design of feed pump, and which are welded the suction and discharge branches.
awareness of overall economic considerations, :i I Extensive areas have stainless steel cladding to give
14.2 Feed pump developments concept was developed with the emphasis on ac ' " protection against erosion. Supporting feel are ar-
Boiler feed pumps installed on early 500 MW units maximum availability coupled with a dcsig~l ranged at the centreline t o give positive restraint to
movement upwards and downwards and yet ailow-
ing for free thermal expansion. Sliding keys control
thermal movement and maintain alignment with the
drive.
The pumps have all their bearings, both thrust
and journal, in housings supported off the pump
!!.I. requirements have been met by the develop- casing or internal cartridge. This makes the pump
NIISWIRLVANE more immune to the effects of pipework ioads and
SUCilONSiOPPERASSEMBLY
minimises the effects of shaft misalignment.
ORhYLOC SEALING RING The 'cartridge' inner pump assembly, complete with
substantially stiffened shaft with the number of integral bearings, is designed so that it can readily
MECHANICALSEAL
COYER PUiiE be transported to a suitable maintenance area as a
package unit. The cartridge components are pre-
assembled on a manufacturing jig so that no subse-
quent adjustment is necessary to ensure component
Illrrnai clearances enlarged to ensure that the concentricity, and minimal adjustment is required to
liiaip is capable of dry running without damage. achieve the necessary degree of coupling alignment
after the cartridge is installed in the pump barrel.
MECHANICAL SE lplacement of the heavy externally-bolted dis- O n ilisertion into the barrel, the suction and dis-
Irge cover by a n internal self-sealing high pressure charge ends are slid apart and located at their res-
pective ends of the barrel. Three joints are made
during this operation; the suction ring section and
main cover joints. Although different designs of
pump have been adopted (Figs 4.56 and 4.571, car-
11 external oii-lubricated thrust bearing. tridge replacement follows the same strict methodical
procedure.
dge' design, permitting rapid replacement of T o ensure rapid cartridge changeover, the normally
mp internals with a spare element (an alter- heavy externally-bolted discharge cover arrangement
design was also developed using the concept has been replaced by an internal self-sealing high
11' removal and replacement of the complete pump pressure joint system. Rapid replacement of the car-
lllit, having a special bolted arrangement o n the tridge necessitates the use of specially designed with-
iiijacent suction and discharge pipework). drawal gear as illustrated in Fig 4.58.
CoOLlNG WATER CONNECTiONS
The impellers are o f high quality precision-cast
stainless steel, with the castings subject to extensive
. result of the stiff shaft is that, even with the radiographic inspection and stringent dimensional
xlnil~m permitted worn internal clearances, the control to ensure repeatable cavitation performance.
r transverse critical speeds in water are well above The first stage impellers are designed to have a ca-
mating speed range. This permits relatively high vitation life of 45 000 hours when operated in the
FIG. 4.55 500 MW main boiler feed pump oilal speeds (typically in the range 6500-8700 range 80-100% of the rated flow.
405
"--
<~
"si-
8
.
R
Condensers, pumps and cooling water plant Chaotei 4 i
Boiler feed pumps
Boiler feed pumps
SlhllOSIILL Siihl
C""FI1
SHAFT SLEEVE
IIYURO GLAND
BUSH
--- SEALFLANGE
W A i W THROWER
ROiAliNG FACE
SIAIIONARY FACE
taken from the condenser extraction pump discharge of these long slender shaft designs, in additic SPRING HOLDER
and fed direct to the feed pump glands. The injection minimising running and standby leakage. As a
pressure would be controlled at approximately one of the early satisfactory performance of mech;
bar above the gland unloading pressure. T o cater for seals, there has been a progressive developmrlil
start-up conditions and interruptions in the supply mechanical seal systems up to the high speed viil,i FLANGE
'The overail unit (Fig 4.54) cooil~iiscs, witiiiii tile lion. lo #lie boiler and the lcalc-off i?o\v. Aisc,,
casing, a nuid coupling and step-og gears. For tile prcssore diffeicntiai tappings are not reqoiie<l i t , I
high oulput speeds required on advanced clasi gomps, position.
stcp-ug gearing is included on boti, the input and Eiectiically-operated valve actuators have b c i i i I I
output sides of tiic coupling. on many stations bill as failure of the e1cctric;iI i.
The fiilid coupling incorporates two separate oil plies woi~ld rendel. then1 inoperative and pomji
systems drawing from a common sump. One system tection would be lost, the electrical supply
provides lubricating oil to thc fluid coupling and to valve is taken fvom separate station switchh
and the driving motor. The oil is drawn from the electropncunmatic systems lhave resulted in a pref
the second system, oil used as the working fluid is of the pneumatic system is that the spccd of i
circulated by the dynamic head generated at the scoop tion is readily adjustable.
tip in a closed loop. Make-up for this closed loop is To provide maximum protection to the pun111
provided by a gear-driven centrifugal pump dwing piping system under all foreseen operating COLI
normal operatioll and a motor-driven gear type pump the valves lihust be capable of opening r a p i
for startilmg and standby duties. Both circuits include the other hand, very fast opening can lead
oil coolers. acceptable shock loadings on the feed systenl
experience, valve opening times of up to IS
been found acceptable, dependent on the feai
commenced.
The configuration commonly used on CEGB stations For steam turbine driven pumps, it is not pracll
(Fig 4.62) consists o f 2 x 100% parallel slide leak-off to specify full works testing and instead part-spc
Valves, arranged in parallel, with a separate pressure interim hydraulic performance tests are carried oul
reducing vessel downstream of the valves. T h e ini- the manufacturer's works to d e m o ~ ~ s t r a tthal
e I
tiation signal for leak-off valve operation is taken pumps have reasonable prospects of achieving 111
from an orifice plate located in either the suction specified requirements on site In terms of rated di
or discharge pipework. Installation in the suction and hydraulic characteristics. These interim tests I
pipework is preferred since this location senses total followed by full-load acceptance tests on site wit11 I
pump throughput, i.e., the summation of forward plant in service.
Condensers, pumps and coolitig water plant
guarantees.
The thermodynamic method of determining pump
efficiency has now been successfully applied t o CEGB 14.10 Future trends TIC. 4.65 PWR feed pump
feed pumps. This method compares the isentropic
enthalpy rise across the pump with the measured
enthalpy rise, and has the advantage over the con-
ventional torquemeter method in that it is suitable with 100% standby capacity and substantial sp
for continuous on-line monitoring o f plant perform-
ance. Accurate measurements of the temperature and
pressure parameters at pump suction and discharge
are required, and suitable equipment is now installed necessitated very tight internal running clearallces till
o n new plant. In calculating the thermodynamic
efficiency, losses resulting from gland sealing, balance
water, bearing friction and heat transfer have all to inability t o withstand vapour lock or thermal trar will be continued, but with a limitation on
be taken into account. These secondary losses can conditions. ller speed t o minimise risks of impeller erosion
be derived at the initial commissioning test by com- A comparison of operating experience has den11 g off-duty operating conditions. A likely eco- 15 ~ i ~pumps~ ~ l
paring the conventional torquemeter acceptance test strated the effectiveness of providing rugged relia c solution is a three-stage machine with booster
results with those obtained from the thermodynamic feed pumps and highlighted the strong financial
method. centives of installing spare capacity to maximise f
pump availability. It is now evident that overs
ultilities are moving towards CEGB practice.
When determining standby requirements, the cu
14.9 PWR feed pumpsets rent trend is t o provide 3 x 50% pumpsets. TI1
The feed pump generated head requirement o n a arrangement meets the basic objectives listed in II
water reactor unit is in the region of 900 m. This is introduction to this section and achieves them tor with consequent reductions in station civil parate categories, pipeline-mounted pumps and sump
considerably lower than that necessary o n a fossil- larger fossil-fired plant without any excessive extr
fired station and allows the use of a single-stage polations of existing technology, by taking maxim11
double-entry pump. Changing t o the simpler double- advantage of UK manufacturer's international e
entry design, eliminates the need for any balance perience to produce reliable plant.
drum to rcdcl against large ~mpellzr lw.rdinp, This A 3 x 50% configuration with quick-start variab
Ic3ds to an tnlpro\.emcnr in pump hldraulic effalen. speed motor-driven units represents a low capital a
cy compared with the equivalent multi-stage pump through life cost option for a practical plant arrang
41 6
Condensers, pumps and cooling water Illant
,t!lii I'iesaii~e Yeircl Codc, Seczlo~i8, 13irisio8,r I and 2 of Specific Sp~ctl':'riiil)s ASMII: 1943
c 1:GB: 1'erf~)linasceor Sulfsce-lipc Steam Colideiiserr: Site 1201 <;rirc. E.: ,Nett liosiiive suction lhehd ieqiiiieo~e~?fs for a\,oid-
ierl Code No. 3: 1981 ~ ~ I CofC u ~ ? a c c e ~ l a bal ic- i i ~ t i o terosion
i it, ceni>i(ugaipurni,~':
lJS752: 'Test Code for Acceplaiicr. of S~eairi'siirbiilei': 1974 IMecllI Ci63: 1974
('liG8: 'Steam Torbi~?e-Geseiaioineat ~~i~ T C S ~ ? ' :site I211 US5316: 'Speciiicalioi~ for Accci,rance 'Tests for Ce~?lvirugal.
( o d e No. 2: 1978 Mixed Plow and Axial Pumj>s'
hlnericaa Sooery of Mecllar$ical ~ n e i n e e r s(ASME): 'stvaciurai 1221 855257: 'Specifieatios for End-suction Cenil.ifuga1 13umpr
I'l~nrucleiiriicsof Hclicnl-Corrueated Heat Excliangcx n b e s (16 bar)': 1975
I,? ASME': 1975
1231 BS4082: 'Spccificalian for External Vimciisionr for Vertical
ELECTRICAL TERMINALS StcPanoff, A. 1.: 'Cenoiiugai P u m p Perfoiniancc as Function In-line Ccnrrifugal Pumps'
COOLING JACKET
OIL RESERVOIR
420
Types of ti~rbine
PELTON TURBINES
SPEClFlC SPEED n,
It is an example of the pure impulse machine in shaped lobes; the central ridge which divides them
'hich the whole of the pressure head is converted splits the water jet and guides each of the two flows
1 velocity in one or more nozzles in parallel, the through an angle of about 165'. Ideally, for maxi-
1s from them impinging on buckets mounted on mum momentum transfer, the jet would be turned
Ie runner. Each bucket consists of a pair Of spoon- 180" but this is precluded by the need to direct the
425
liydraulic turbilies Types of turlline
HlGW PRESSURE +
WATER INLET
discharged water away from the runner and from disposed around the full circumference. The ant
the path of the following bucket. For similar reasons, these vanes can be varied to control machine i,
the central ridge is scalloped at the tip to give a clear and the water is uniformly distributed to theni I
path to the jet impinging on the working bucket. spiral casing.
Theoretically the maximum efficiency of this type After being directed onto the runner, the
Of turbine occurs when the bucket peripheral speed flows radially inwards, being turned by the I
is one half that of the impinging jet. This is im- blades so that it discharges axially into the i
D R A R CONE
AND D R A R TUBE
required. In practice, the ratio of blade-to-jet speed lies maximum efficiency of Francis turbines is 9 4 9
between 0.46 and 0.47. Both horizontal and vertical shaft mounting c;in
I:~c,$ 5 i7raseisiurbine for leu. head applications
The efficiency o f the Pelton turbine can be o f the employed.
order o f 92%. Control of end thrust is important. This
Water is directed onto the buckets by means of largely from the different pressures between th
nozzles, the flow of water, and hence the output, being and rear shrouds and their respective casings.
controlled by a central needle, or spear, whose bulbed rear shroud, the source of pressurisation is so
head varies the flow area as it moves axially within high pressure at guide vane exit, whereas th
quired after loss o f load from the driven machine, As well as this varying pressure distributioo,
cannot be effected by rapid closure of the spear front face o f the impeller also experiences draft 11
due to the water hammer effects referred to earlier. pressure over the whole eye (i.e., the area o f
Shutdown is therefore effected by inserting into the impeller facing the draft tube).
jet either a cut-off to destroy its kinetic energy o r a Since the areas involved are often large, the t11re
deflector to direct the jet away from the bucket. The resulting from even small pressure differences ca
jet of water is then shut off at suitably safe rate. considerable. It is usually reduced by control o
pressures on the top and bottom shrouds, thro
tire oilier end o f t l ~ ccrank bciiig located in a icgu- 2.4 Tubular rurbines
laling ring. Rotation of lhc rcpiiialing ring movcs The Kaliiaii turbinc has been uzideiy wscii iii I
t l ~ ccranks, and ileiice ilic guide vanes, in syochronism and tidal power sciiernes, iuhere a coinpaiaitivlr
GUIDE VANE
OPERATING
throi~gb the required angle. This rotation is lpio- lhcad o r wafer is available. Howcver, tlicic : i i i MECHANISM
rotates the blades. The servomotor system which op- since they arc hallow and large enough to gal
erates the cross-head can be within the hub o r outside to the generator for maintenance, must be <
the machine, connecting with the cross-head by hy- designed if unnecessary hydraulic losses a,
draulic means (Fig 5.6) or through a control rod disturbances are t o be avoided.
within the holiow shaft. The optimum relationship Guide vanes, sometimes called wicket galcr,
between runner blades and guide vane angle is con- located in the annulus between bulb and carin&
trolled by a cam system in the operating mechanism. control the fiow of water t o the runner.
lnstallation is usually as a vertical shaft machine. Several combinations of guide vane/runne~ b
This configuration has the following advantages: control are possible:
Bearing and lubrication system layout is simple.
Variable guide vanes and runner blades
Electrical generator installation. access a n d
maintenance is made easier. This combination provides the best efficiency
the load range. It also allows a useful variaal
s Turbine support and secure embedding of parts, tidal power schemes. Thus, as well as operatin]!
such as the inlet volute, in a heavy concrete mass turbine in either the ebb o r flow direction, tllc~
are facilitated. the capability for pumping in either direclion
Equipment can be mounted o n the top cover and improve the head availabie for the next geneml
is easily accessible for maintenance. cycle. u
Submersion o f the runner below the tailwater level
t o obviate cavitation is achieved with minimum Variable guide vanes, fixed runner blades WC. 5.6 Kanlan turbine with delail of the hub mechasisn, far varying llle blade angle shown on tbe insel
civil costs, compared with submersion of the com- Load is satisfactorily controlled over the camp
piete set. operating range by varying the guide vane 1111
428
Hydraulic turbines
ivil to thc till-bines froin !lie lop lakc, discharging I'uolp casings iirc in casl steel welded lo a lplale sicel
lii ilie iower. l'hc scts can be r u n in this mode "Oillt~.
i t demand is met or otiici plant can be starled. Whilst pumping, the drive imust take lpiacc from the
oil-peak lxriods the water is pumped up from motoi- through the turbine, wilicli is filled with air to
lower inlo $he upgei lake ready to meet the next rcducc pumping Iosscs. The pump is disengaged whilst
the turbine is in opcsatiori in tile generating mode
i e requirements of the set for both a tol-binc and a coupling is provided for this purpose. Syatem
pumping role can be met in lwo ways; either by iequirernents did not justify the expense of a coupiing
1',separate pumps and turbines or by a singie capable of cngagement/disengage~ncnt at full spccd
~l~ii)-turbinewhich combines both duties in one and so tliesc operations are conducted whilst the ma-
lo!, and which reverses direction between roles. chine is stationary. A toothed gear, sliding-muff type
o f coupling is used, engagement being actuated by oil
pressure and a positive mechanical lock inserted during
periods o f rotation.
F f e s t i n i o g p o w e r station
tation, part of the CEGB system in England
'ales, is an example of the separate pump and
,i!,c system and was completed in the 1960s. The 3.2 T h e reversible p u m p - t u r b i n e
~ i i j iand turbine are mounted in tandem o n coaxial Such a machine enables both pumping and turbining
iil\s, at one end o f which is a unidirectional motor- to be performed by the same runner or runners. It is
effectiveiy a Francis turbine whose runner geometry is
'1'1,~ upper reservoir operates between extreme levels a compromise between the optimum for pumping and
,1113 and 502 m abovc sea level and encloses a generation. During generation, the turbine output is
11iige volume of 1.7 million cubic metres giving a absorbed by tile generator; whilst ptlmping, the geo-
Ili'iation time of sonlc 4.5 hours. The lower reser- eralor acts as a motor, driving the runner in the
lcvel correspondingly fluctuates between 182 and opposite direction.
A desirablc featurc of this design is that it is
e cross-sectional arrangement of the sets and considerably cheaper than a type employing a se-
relationship to the lower lake arc shown in Fig parate pump and turbine and the necessity for a
). Pour pump-turbines, each of 90 MW maximum clutch between the two is also eliminated. Also. since
Inciatins capacity, are arranged in an overground the same runner is employed in both the turbining and
reduce civil costs and t o facilitate flood pumping directions, the need for separate suction and
disposal in the remote event of a burst. discharge piping for the two components with the
h pump-turbine is arranged in a vertical con- associated mechanical and civil costs is similarly un-
on with the pump mounted below the turbine necessary. Thc efficiency of such a unit as a pump or
liar it may have maximum submergence for mini- turbine is usually some 1 % lower than a corresponding
ion of cavitation. The piping system, connecting optimally designed machine of similar size. Typical
r lake, bifurcates, as shown in Fig 5.10. maximum vaiues for very iargc machines might be
upper branch connects l o the turbine inlet via 92-93% when pumping, and 93-94% when turbining.
I~yilraulically-operatedinlet valve and the lower to Subsequent to the construction of Ffestiniog power
, pump outlet through a similar valve. station, considerabie worldwide experience had been
I:nclt single-stage Francis turbine runs a t 428 r/min obtained with single-stage reversible pump-turbines.
111 a maximum efficiency of over 93%. The high- Therefore, for their pumped-storage station at Dinor-
ilc steel spiral casings are constructed in halves wig, the CEGB decided to install such machines. The
111 site-bolted flanged joints. The variable guide first sets were commissioned in 1982 and, since it
st stainless steel are operated through a represents one of the world's major pumped-storage
and link system which is auto~naticallygrease- schemes in terms of both unit capacity and operat-
icated. The runner is in 13% chromium steel and ing head, it is used as an example of modern practice
in this field.
a maximum diameter of 1.93 m.
Ihe vertical two-stage pump is of double-entry
FIG. 5.9 Rim generator ('Srraflo') t~lrbine
. Thus the second-stage impellers are disposed
o-back as a sinale rotor and the first staees
be mounted outboard of it (see Fig 5.11). Suc-
-~~ 3.3 Dinorwig p o w e r station
It provides a convenient form of system frequen- pumping at periods of low system deman on from the lower lake is therefore via a breeches
cy regulation especially during periods of rapidly coroliary of this is that margins o n system capa 3.3.1 The site
ipe which conveys water to the suction of each of
changing demand. can be reduced. lr first-stage impellers. Each o f the two 2.5 m This station is Located near Lianberis in Wales, in the
meter first-stage impellers and the 2.6 m diameter Snowdonia National Park; an area renowned for its
It facilitates load curve smoothing by using con- Operation of the system requires two lakes or we nble-entry second stage are manufactured in 13% natural beauty. This fact dictated some of the design
ventional or nuclear plant to provide power for storage reservoirs. During generation, water is romium steel and are keyed to the pump shaft. features of the station.
432
liydraulic turbines
lo i-cfili the upl,el reservoir by i)uml,iog froiii the lowel 111 order to nlcel sucli sirol-t loading times,
in a six-lioui- period. ccssary for the machine la be kept for ion
A schcnlatic plan and elevation of lllc site is shown at synclironous spced. In the generation
in Fig 5.12 whilst a section tirroug:1 the underground this could be effected by allowing a sinali thrr,\ii! 11
station itself is shown in Fig 5.13. of water to generate sufficient power to o v v i r i i
macllinc losses. This is unattractive since:
Associated with the above is a requirement to meet Routine generation starts and stops, up to four
these system needs within certain time scales. Whilst per day.
it was never envisaged that there would be any de- Change from spin-generation to generation and
mand for rapid adoption of the pumping role it is versa, up to 13 times per day.
essential that the machine is capable of changing
modes within very short time scales as follows: Emergency loading and change from pumping I
generation.
Standstill to no-load generation 90 s
Pump and turbine trips.
No-load synchronised to 1320 MW output 10 s
Emergency pumping to spinning-in-air (both In total, this represents 7500 loading/unloading c)
in the pumping direction) 10 s per annum. A fundamental consideration is the
Pumped-storage
during each of tliese cycles tbc MIV shuts, Illus sllaft and thc upper sllioud seal u,llici> ariinil blo\i-
~.isingthe penstock and turbine casing to [he down air into the s)atern, togettier wit11 the peripheral
oressure of some 6 bar, then re-onens to drain pipes which arc opened under these conditions to
uriseihem again to 50 bar. Over its 40-yea; design discharge the cooling water supplied to the ogpct and
:, (lie machine is thus subjected to 300 000 cycies lower seals.
Figurc 5.15 shows the guide vane apparatus, in-
' ' e requiremelit to design for a fatigue life is un- dicating the substantial bearings employed and also
in water turbines. In this instance, consequently, the manner in which the reguiating ring rotates the
.
s thought necessary to use a fracture mechanics
plr~oachto the design, adopting the ASME standards
vane through the lever and locking assembly, which
incorporates a friction clutch. Seals are fitted on the
licable to nuclear pressure vesseis. Essentially this end faces of the guide vane blade to miriimise water
lnes that defects present in the steel, which are leakage and both these and the guide vane bearings
ller than those detected by non-destructive test are equipped with an automatic greasing systein.
lhods and cansequently repaired during manufac- In the turbining direction, the guide vanes are
will grow under the varying stress field. Over infinitely variable between fully closed and about 32"
llant life, these initial defects must not grow to o f opening rotation to achieve the required output.
approaching the critical defect size, where the In the pumping direction, however, the guide vanes
can grow in an uncontrolled manner. Due to are opened to a notninally fixed postion, although
herent uncertainties of crack detection during pump performance can be optimised for varying speed
lofacture, the design allows for inspection o f cri- and head by minor variations in the angle between
I areas during the life o r the piant. As shown in 20' and 30" o w n .
14, one such area is the spiral casing, which
--",
c
.-0 11 t been invested in concrete over critical welds
i as occur between the spiral casing and the 3.3.6 Valves
"L
'ilg. In turn, this has necessitated placing a rub- The valves piaced either side of the pump-turbine
0
n iiiembrane between spiral casing and concrete to are similar to those used in many types of turbine.
.-an3 b panting and flexure of the spiral casing dur- Those. used at Dinorwig will be described in detail
i
i: pressure cycle whilst still providing adequate as an example of modern practice.
6 nt of the spiral by the concrete. Provision is
made in the design for grout injection should
B0 ,ap develop with time.
The main inlet value (MIV)
5 the pump casing and inlet spiral are com- Each MIV is a 2.5 m bore rotary valve, interposed
c
.- structures, the stresses in them were deter- between the main and intermediate penstocks, which
" 0th by finite element methods and photoelastic isoiates the turbine from high pressure water at each
5:
-
w
rn
iilysis of a plastic model. shutdown (see Fig 5.16). Tile vaive rotor rotates
within the valve body on two trunnions to which are
P
UI
attached the operating lever arms and closing weights.
6 Machine lavout The valve is held open by the upward thrust on the
nine-bladed runnpr in cast stainless steel has a lever arms from two servomotors (or rams) filled with
Ilum diameter of 3.8 m and an eye diameter of oil under pressure. The system is thus 'fail-safe' since
ti see Fig 5.14). The vertical drive shaft is mounted the valve closes under the action of the weight alone.
ingle guide bearing of tilting-pad design. Lu- The rate of closing is controlled by restrictors in the
n of the bearing is by a self-contained system with oil discharge line.
>il reservoir and integral water-cooled oil coolers The MIV is closed each time the machine shuts
osed within the bearing housing. Oil circulation down and, in this condition, leakage between the
ugh the coolers is maintained by the head gen- near-spherical valve rotor and body is prevented by
I by shaft rotation. The thrust from the p u m p a service seal. This is in the form of a stepped ring
le runner and motor-generator to which it is which slides axially in its stainless steel housing to
t y coupled is taken by a tilting pad thrust bearing seat against a ring attached to the rotor on its inter-
~nted in the motor casing. It must be sized to mediate penstock face. The seal is operated, as well
the widely vdrying thrusts achieved during pump as being held on and off, by penstock water pressure
turbine operation and, in particular, those tran- acting on the appropriate face of the stepped ring.
t i which occur during mode changes. Leakage of The seals between stepped ring and valve body are
I jlressure water from the upper shroud of the D-shaped to prevent rotation within their grooves:
ley along the clearance between the shaft and they were the subject of considerable testing t o ensure
pump inner top-cover is minimised by a balanced that they met the six-year life required of them.
of the type referred t o in Sectiun 2.2 of this A similar seal is provided on the penstock face of
the valve rotor but it is only operated to provide
lhnwn also in Fig 5.14 are the pipes between the additional safety during maintenance. Under these
Hydraulic turbines Additional references
T/IPdrNJ) I u D ~r,oiee 3.3.7 Testing 10 enable ipeiformance deferioiatioll to be monitored Stotio,, "Ut,,,,I
The d r a h lube vaive (1)TV) (see Fig 5.18), is piaccd I'oli-size testing of tiic installed p o m p t i i ~ l i ' tiring service, eacli machine is equipped with tap- Average generated station output 1680 MW
011 the tailwater side of the p ~ r n p - t ~ ~ ~ aiid
b i ~is l ~ verify efficiency guaiantees, sequircs rneasurell ' points in the intermediate and lower penstocks Generating period at coilstant output 5 11
d isoiate the machine froill tile lower re-
~ ~ i o v i d c to power, net head and watei flow as devailed i ~ i ling thermodynamic testing o f the machine ef-
Average individual pump power input 283 MW
sei-voir during maintenance, and to close in the event 1.1 of this chapter. Difficulties and costs y to be undertaken.
of a major burst to prevent station flooding. It is ing for tile accurate measurement of the lar?, 11s method does not require any flow measure- Pumping period 6.3 lr
normally left open and does not form part of any involved make such an undertaking unattraciiuv l i i i I r m It measilres tllc internal efficiency of the ma-
automatic operating sequence. both practicai and contractual considerations. Ihii~e by comparing the actuai enthalpy change of
(six ofn
Pu,~~p-T~o.Dincs
Each DTV is a 3.75 m diameter buttesfiy valve, For this reason the comprehensive tests c a r ~ i i , ~ i Ir water due to the work done in passing through
the rotor being of the lattice type. Integral eccentric by the manufacturer on the one-eighth scaie ~ I I machine, with that which wouid be experienced Type Reversible Francis
tronnions ensure that should it be inadvertently left logous model of the pump-turbine and cor lile water experienced an isentropic change from
shut during turbining, it will flip open under the tur- full-sized machine values by established means 1 1 1 I to final pressure 01. head. The ratio of these Turbining (Generating)
bine flow. Opening and closing is performed by a accepted by the CEGB as evidence of the , , iles gives the machine The main probiem
servomotor and lever and weight system, in a similar liie method is that of accurate measurement of Maximum output/net head U p t o 317 MWl535.8 m
ability to meet efficiency guarantees. Howeve
manner to the MIV. firmation of this and to cstablisb a referel small temperature difference (typically 1 t o 2'C) Minimum output/net head U p t o 280 MW/487.9 m
111 which cnthaipy changes depend but for this, Maximum flow 70 m3/5
I olher details of the method, see [21. Synchronous speed 500 r/min
Maximum transient
BWDE
runaway speed
/ S o m e d e t a i l s of t h e D i n o r w i g p u m p e d -
SIIDINGAOINT
800"
I
Pumping
Rated discharge/head 50 m3/523 m
6.7 million m3 Maximum power input 318 MW
634 m Synchronous speed 500 r/min
600 m Min/max frequency 49/51 Hz
4 References
iII 'lnfeiiiational Code for Model Acceptance Tcrrr of Hydraulic
Turbines': iEC Ptkblicalion No. 193
12) Thom. A . S.: 'Tl?eriiiodyi?aaucTesting or'l'urbiner and l'ul,ipi'
IMecllE \'"I. 7 No. 3: 1965
5 Additional references
Gutl~rie.Biown, J. (Ed): 'Hydro-Eieetrie Engin~eiiiig Practice':
Biackie & Son
Headland. H.: 'Blaenao Fferriniogand other Medium-Head Pumped
Storage Scllemei in Oreat Biilain': lMechE Proc. Volume 175
No. 6: 1961
'The Dinorwig Power Station': Papers presented at a major achieve-
ment symposium: iMechE: 1985
nerator
Introduction
,
130th the pace o f development and the rate of Other parameters, such as hvdraulic vressure and
,]case in unit output has slowed markedly in re- dielectric loss test values, are specified in various
il years, as greater emphasis iias been placed on CEGB Standards.
reliability achieved by proven designs, and on Specific requirements for a new generator are con-
. advantages of interchangeability of major plant tained within its own specification, which covers items
peculiar to its location or duty, for example, tem-
perature of cooling water, power factor and reactances.
Where necessary, these requirements may differ from
those in the appropriate Standard. The expected op-
Standards and specifications erational life is quoted in the specification; this is
British Standard covering generators is BSS000, currently 200 000 hours, with 104 start/stop cycles.
i refers to many parts o f BS4999. The corre-
These values are used in design calculations, e.g., crack
roading international standard is IEC 34. Standards
growth rate by fatigue.
)ccific for turbine-generators are BSSOOO Part 2 and The following Standards are relevant:
!(' 34 Part 3. These standards specify acceptable
aracteristics, values o f temperature, vibration, noise,
unbalance, harmonic content, excitation control i E C 34- I : Rolaling electrical maellines - rating and perforisance.
and tolerances, and test conditions, e.g., high I E C 34-2: Rotating eleciri~almachines - methods for determining
IOSI~S and efficiency from tests.
Syiicliro~iousgeneratoi i1iiii:i:
..
-
- i~ S E ~ ~ V I C C
SUPLRCONUUCTlNG
the rotor rotates inside the stator bore, a con-
c i o r fixed in the stator will be subjected to an
lproximately sinusoidally varying magnetic flux den-
output is rectified for use as an excitation supply
conlinoiliy operate at 150 Hz or 400 Hz.
drical rotor 50 Hz generators have two poles line voltage = J 3 x phase voltage
34- 3: Ratings and characierirlies of )-phase 50 wr turbine 2 Synchronous generator theory peratc at 3000 r/min, or less commonly four and line current = phase current.
type macPiner.
Some basic principles of theory and desigll
IEC 34-4: Metliodr ioi derermi,,ing sy,lcl,ronoui ,nac,,ine qua,,. tablislled in this section in order that the de
tities from tesci. matter in later sections ma). be more easily land
2.5 R o t a t i n g p h a s o r s
A sinusoidaily-varying voltage has an instantiif
value v at time t expressed by:
The output is specified as a maximum conlhuous
rating (MCR), which implies no guaranteed sustained v = V sin (2af)t
overioad capacity. Tile standards specify very short
term overcurrent capability, and acceptable variations where V = maximum vaiuc of v
in voltage and frequency. Samc sustained overload
f = frequency in Hz 17i~i. 6.6 ~oiatingphasois
capability may be possible by operating at a hydrogen
pressure greater than the rated value, by agreement.
Although operation at 0.85 power factor (lagging) T h e same relationship can be derived by rotatiti
is specified, generators on the CEGB network gen- phasor of constant magnitude V at a constant sl
erally operate at power factors of 0.9 or higher, and (Fig 6.6). At time t, when the phasor is at an
this allows operation at higher than rated M W if 0 t o the horizontal axis, v = V sin 8, i.e., ti1
this is available from the turbine, u p to the limit of jection of V o n t o the vertical axis.
rated MVA (see Fig 6.5).
In a synchronous machine, all tile sinusoiilal
varying quantities (voltage, current, etc.) can hr
presented by phasors rotating together a t synchroiiintt:
speed. The rotating phasoi diagram can be tho~ii:I~l
2.4 M M F , flux and magnetic c i r c u i t of as a snapshot of a set of phasors which ail i<ititls
Direct current circulating in coils wound into the together while maintaining the reiationships to r;irll
rotor poles, causes them to act as electromagnets, other.
In a three-phase machine, with balanced ciectricul
output, conditions in one phase are repeated exnclly
OPBR~TIONABOYtRATED MW in the other two, with time delays of 1/(3fJ an
PERMlSSiBLE IN THESE AREAS
(30. For clarity, one phase is chosen, a n d its ph
2.6.2 Rated voltage, rated stator current a n d reactance. r l i c ierni syrichronolic reoclnnce (X'I ; Xi-)
rated power f a c t o r is used io express this cffect, the IXd drop lbi.irfp
If llic poivcr i a c t o ~is expressed as cos $, y', is thc added lo the IX, drop in the diagrams.
angle betwecii the voltage and current phasors, as As the lagging power factor of the load i8~,i,.rlir:
shown in Fig 6.8 Sol a lagging power factor. i.e., cos y', is smaller and 4 larger, the required I\Ihll ,
Current circulating in the stator winding rcsults in F, increases, i.e., more current is required i!, l l i i
vollage drops: IR due to the winding resistance R, in rotor winding (Fig 6.9 (a)). Conversely, if the lit(q!Jiifi
phase with I, and IX, due to the winding 'leakage power factor increases or goes beyond unity i l l l r i llir
reactance', X,, lagging i by 90". R is negligibly sinall, leading regime, the rotor current must be re<llir~il
and the resistive voltage drop is neglected henceforth. (Fig 6.9 (b)).
An 'internal' voltage E must be generated in the
winding such that after subtracting (phasorialiy) the
Ieakage-reactance drop, the rated voltage V is pro-
duced at the terminals.
2.7 Torque
In order to generate E, fiux density Be and MMF
Fe arc required, such that the voltage, flux and MMF The mechanical torque provided by the prime nrnrat
phasor triangles are ail similar. Tile pbysicai meaning is balanced by a n electl.omagnetic torque causcil lij
o f this is discussed later. the interaction o f the magnetic fiux and the ckillrni
Current in the three-phase stator winding produces fiowing in the stator windings.
its own MMF, Fd, which acts in tile same direction The rotor shaft must be designed to transmit li11t.d
as F,,. An MMF, F, must be provided, such that, torque, and the stator must be abic to withsl;il,ti t i
when the Fd component is subtracted vectorially, similar torque reaction. In practice, the design i i i 1 1 6 1
the resultant is Pe. This is achieved by increasing the cope with the very much higher torques proiiiscuil
rotor winding current and by the rotor moving ahead during certain fault conditions.
o f its open-circuit aiignment, by the 'load angle', S,
as silown.
This demagnetising effect of the stator winding
current is known as artnolure reaction, and can be 2.8 Three-phase windings
seen from the diagram to be similar in effect (though The voltages and currents produced in each ~ p i i FIG. 6.9 Pliasor diagiaiiis for lagging and leading loads
much larger in magnitude) to that o f the leakage must be identical, apart from their phase displ
inents, in order to axaoid the damaging effects of profile which cannot be shaped to produce a sin-
tinbalance. usoidai fiux density variation (as can, approximately,
In this and the next section, a complete two-pole a salient pole on a multi-polar slow speed generator).
$:enerator is considered, for simplicity. In a machine The flux density variation in a turbine-generator is
\ ~ i t l l2n poles, a two-pole segment is exactly repeated of a stepped rectangular form (Fig 6.11), which con-
11 times, and can be considered as elect~omagnetically tains a fundamental with odd harmonica of significant
cquivalent to a two-pole machine. amplitude. The voltage induced in a single stator con-
An economic design of stator winding has many ductor would contain similar unacceptable harmonic
conductors connected in series, so the individual con- components.
liuctor voltages are additive. Each 'go' conductor is In a series-connected winding occupying several
connected to a 'return' conductor, acted on by the adjacent slots in the stator, the voltage induced in
pole of opposite polarity, and thence to a third con- one conductor will be displaced from that induced
ductor adjacent to the first, and so on through the in Its nelghbour by the electrical angle subtended
phase. The 'return' conductors are disposed in a layer by the two slots, a in Fig 6.12. The sum of n such
displaced radially from the 'go' conductor, both in voltages is V + 2Vcos ol + 2Vcos 2 r ~+ ... 2Vcos +
the slots and in the end region. (n - + ) a if n is odd, or, 2Vcos a / 2 + 2Vcos 3a/2
The usual and most economic arrangement Is for + ... 2V cos (2" - +)a,if n is even. The ratio of
the winding.of one phase to occupy one-sixth of the this to nV is the distribution foclor Kd ( < 1).
circumference, with a parallel section of the same The effect of distribution on the third harmonic
phase occupying the position diametrically opposite voltage is to triple the effective angle, so that the
(see Fig 6.10). surnmated voltage is:
MMF PHkS:SORSROTTEOBACK
THRoUGH SOI TO SNOW
SiMlLARiTY Of TRIANGLE 10
V3 + ZV, cos 3 a + 2V3 cos 6 a + etc.
VOLTAGE PHASORS
2.9 distributed and chorded and the resultant third harmonic voltage is very much
winding reduced. A similar argument applies even more effec-
FIG. 6.8 Phasor diagram Eor load conditions A cylindrical rotor generator has a circular rotor tively to harmonics of higher order.
T h e generator h
Cl~i.lllir~ Turhine-genera~orcomponents: the rotor
. .<
3 Turbine-generator components: the8
rotor
The rotor milst carry the excitation winding, l'i,,
a iow reluctancc path for the magnetic flux,
transfer the rated torque from the turbinc 1 0
electromagnetic reaction at the air gap. Steei i.
only material which meets these r e q u i r i : ~ ~ MMF DUE
TO COlL
econotnica1ly. A single steel forging is uscd.
which the centrai cylindrical body and its s u p l ~ o ~ t i
shafts are machined.
/---\ EI:liECION
IUNONdEMIbt. WLl"rl(
THE E F i i C i O N i i , !
FUNOAMENIAI V<il I,,, ,, I. EiitClON
THIRDHARMONIC
VOLTAGE
EFrECl ON
SIIIINHARMONIC
VOLTAGE
"5
PIC. 6.12 Tlie errcc~of disiributing the rlalor winding over rcvcral dois i:l~cumfereniial plane, at intervals axially along the Because the rotor winding slots are cut radially,
i t is not possible to fit a preformed coil into the slots
Iluring a three-pliasc sudden short-circut at the since the span o r a coil is smallev the iower down
,:rzieratoi terminals, torque peaks of Sour to five the slot it is, and considerable distortion would be
litiies full-load torque are experienced between the required to get the coils in. Each turn is therefore
tracking distances from the winding to the rotor 0 The whole centrifugal force of the slot conteots, I
I I' turbine and generator shafts. The generator rotor assembled separately, either as half-turns or in more
ali;iSt and coupling at the turbine end must be designed pieces, with joints either at the centres of the end-
insulation must therefore be more substantial than between the maximum tooth stress at overspecrl
the Operating voltage of about 600 V would require the proof stress of the steel.
.
proportion of the coupling bolts are fitted, the content to improve its creep properties, is used for
in other applications. the coils. Depending on the method of ventilation,
irers have a clearance to the coupling holes.
Passages for a n appropriate flow of cooling gas The optimisation of these conflicting require! lournal and journal-type shaft seal surfaces are rectangular sections with grooves and/or slots, or
must be provided in the winding copper section, has led, in the latest designs, to a departure ound and polished to a high degree of circularity. tubular rectangular sections are used. When a trape-
and also in the steel body section in some designs, parallel-sided slots to slots o f trapezoidal section verall, good surface finishes and absence of sharp zoidal slot is used, the sections may be o f several
to ensure that the specified temperature rise is 6.'s). >Itmishes are called for. Radii are made as large as different sizes. One or two turns in the width of the
not exceeded. The winding slots are cut in diametrically opl?i ~v;~cticable
to minimise stress concentrations. slot are normally used. Radialiy-aligned slots provide
gas exit passages (see Fig 6.17).
T h e coils are not individually wrapped with insuia-
tion. Instead, slot liners of moulded glassfibre, or a
no loss due to magnetic hysteresis or eddy currents, pendicular axes would produce a twice-per-rev01 .2 Rotor winding composite of glassfibre and a more flexible insulating
458 459
Turbine-generator components: the rotor
URRENTCARRYING
CONDUCTORS
(Fig 6.18). Thick layers of insulation niaterial on the Fans mounted on the rotor, primarily to circi
inside surfaces of the end ring and end disc insulate hydrogen through the stator, assist the natural PiO. 6.15 Optimi~ationor a rotor seetioii
thein from the end windings. The spaces between through the rotor (see Fig 6.19).
turns in the end windings are partially filled with The ends of the winding are connected to flexil
insulating blocks, which ensure that the coils do not leads, made from many thin copper strips, which r,
distort, and which contain holes and passages for radially inwards onto the shaft a t the exciter ell because of the coarse grain structure, particularly
ilgal force. For electromagnetic reasons, these rings
the transfer of ventilating gas. These leads are housed in two shallow slots in tnve traditionally been made from nonmagnetic steel, where the shape is complex.
Because direct current circulates in the winding, shaft and are retained by wedges. At a point axi pically a 18% Mn, 4 % Cr austenitic steel. A 0.2% An austenitic steel, containing 18% Mn 18% Cr,
there are n o eddy current or other frequency related beyond the end windings, the leads connect oof stress of IMK) M N / ~is available
~ to cope with has recently been developed which has shown virtual im-
losses in the rotor winding. The resistance ( 1 ' ~ ) loss, radial copper studs and thence to D-shaped col lie high operating stresses. A ring is machined from munity to stress-corrosion cracking in exhaustive
amounting to 2 MW at rated load, together with the bars housed in the shaft bore. Seals against hydr single forging, and is attached to the end of the tests, while maintaining other properties at least as
rotational (windage) loss, must be dissipated, and the leakage are provided on the radial studs. Fronl tor body with a shrink fit designed to provide a good as the older material. This alloy is being used in
average winding temperature must not be allowed D-leads, connections are taken either to slipri, iall residual interference at 20% overspeed. The new machines and for replacement rings, eliminating
to exceed 115°C. A cooling system is used, in which or to the shaft-mounted exciter connections in the need for periodic inspection.
aterial has proved to be liable to stress-corrosion
hydrogen is in direct contact with the copper con- brushless machine (see Fig 6.17). The end ring is re vented from moving axially
cracking at the stresses invoived, and all the surfaces ex-
ductors, for optimum heat transfer. The high ro. ept the shrink fit are given a protective finish t o either by means of lugs mating with similar lugs on
tational speed produces a pressure head through the
risure that hydrogen, water vapour, etc., does not the rotor body, or by small spring-loaded plungers
rot01 Slots which causes hydrogen to flow from both
iave access to the surfaces. Even so, it is recom- locating into grooves (see Fig 6.20). In both these
ends, under the end windings and axially through sub- 3.3 Rotor end rings ,,ended that rings are removed occasionally for de- designs, the ring must be rotated through a small
slots in the rotor and channels in the coils, whence Thick end rings are used to restrain the rotor clld ailed surface crack detection using a fluorescent angle, when fully home axially, in order to lock. In
it emerges radially through the wedges into the airgap. windings from flying out under the action of cen~rlc dye. Ultrasonic scanning is not entirely satisfactory, a different design, a screwed ring is used t o pull the
The generator clhi%,ll,:,
ti
....,
*8
g
components: the rotor
Tiiibii~e-geneiato~.
4. -
$
s,.,,31,,14,
TERMIN,,, :,I,,,,
END BELL
i
3.4. W e d g e s and d a m p e r s
- INSULATIONSTRIPS
NYLON PAPER
BETWEENTURNS The winding slot contents are retained by a u'iilgc,
which must be designed to withstand the crl~,liii~i
stress on its lands and the bending stress acroar 116
width, bearing in mind that it contains holes at al,!li
through which hydrogen passes. It must also br I,I,II
magnetic in order to minimise flux leakage aro11n11
OUieoARD
the rotor circumference, and to ensure a reasonable ~cili, END
EPOXIDEGLASS
tance value.
Extruded aluminium section is generally used,
chined in the regions of high stress. If shorl
lengths are used, the potentiality for localised
initiation in the rotor teeth exists. One c o n t i a i ~ a ~
wedge per slot is therefore commonly used, alli~ollelj
these are more difficult to fit.
During conditions of rapidly changing flux, fw c h
ample, during system faults, or when an altcit!i~l
ing flux links the rotor during unbalanced elcci~ii:iil
loading, when negative phase sequence currents it1111
fluxes occur, current is induced in the surfacr i r l
the rotor. Because the 'skin depth' of the magnrllr
rotor steel is about I mm whereas that of the ino,~
magnetic wedges is an order of magnitude grcalol
current flows preferentially in the wedges, whi
form a 'damper winding' analogous to the rot0 Ihc slits, and prevent hot spots at the ends of the several brushes and holders o n one of several
of an induction motor. The wedges are of slits. movable brackets, each of which can be withdrawn
cient cross-sectional area to carry the curren for brush replacement while running on-load, if SPe-
responding to the expected unbalanced load, wi cial precautions are observed (see Fig 6.22 inset).
FIG. 6.18 Rotor slot damage due to overheating, but the areas of cu Brush pressure is maintained by constant Pressure
transfer into the end rings (which act as the s I 3.5 Sliprings, b r u s h g e a r a n d s h a h earthing springs. A brush life of at least six months
circuiting rings) have to be carefully designed. Thin Connections are taken from the D-leads in the bore, be obtained.
per sheets with 'tongues' fitting under the en ll~rough radial copper connectors (which may have The brushgear is housed in a separate coflPartment
ring through its final few millimetres, and this also of the wedges form an interleaved ring under tli back-up hydrogen seals) and flexible connections, onto of the excitation housing, separately ventilated by a
locks it circumferentially. inboard end of the end ring, and assist in the avoid. the sliprings (Fig 6.21). For a 660 MW generator, shaft-mounted fall so that brush dust is n o t distri-
The ring must be heated to about 3W°C to expand ance of localised areas of preferential current transfc~ tlie rated excitation current is about 5000 A, and buted into other excitation components. mall leakages
it sufficiently for the shrink surface to pass over its and hot spots. sliprings must have a large surface area and run cool of hydrogen past the connection seals which might
mating area on the rotor. The heat is applied by a In pole faces having axial compensating slols, o in order to transfer this current satisfactorily. One accumulate in the brushgear compartments during pro-
special cylindrical electrical heater. If a gas heater is similar arrangement is provided. In those with croaa.. design uses two sliprings of the same polarity in longed shutdown periods, are safely diluted by the
used, the ring surface is protected from the direct pole slits, a few very shallow axial slots are cut lo parallel. The ring surface is grooved and drilled to im- fan on start-up before excitation current is applied. Win-
flame by a thin metal cover. accommodate copper damper strips, which are rc. prove its surface cooling. dows in the cover permit easy inspection Of the
The inner diameter of the ring is machined with tained by wedges, t o transfer the surface current acroh!, The brushgear shown in Fig 6.22 is arranged with brushgear.
i l l c generator
- Turbinegenerator c o ~ n p o n e n l s : t h e rotor
Monitoring o f excitation current and voltage and It is normal for a large generator t o prodo
rotor winding temperature by resistance measurement, on-load voltage o f 10-50 V between its two
is simply achieved in a generator with sliprings, using ends, due to magnetic dissymmetry and other cat
a current shunt and voltage connections in one of This voltage would drivc current axially througl~
the excitation cubicles. Rotor earth fault detection, rotor body, returning through bearings and joorlli
and tile application o f tests such as the recurrent causing damage t o their surfaces, and insulatioil bii
surge method for shorted-turn detection, are also riers are provided t o prevent such current circu1;ttio~
simply arranged. These need only be at one end, the exciter end,
Where no main excitation sliprings are fitted (Fig must be present wherever the shaft would otherwise
6.231, signal may be transmitted from the shaft, via tact earthed metal, for example, at bearings, seals,
telemetry. Alternatively, a set o f light current sliprings scrapers, oil pipes and gear-driven pumps.
and brushgear may be provided for signal monitoring some designs, two layers of insulation are provi
and protection purposes.
with a 'floating' metallic component between 111 ,
466
F
& ~ " ~ b i n e - g e n e r a t ocomponellts:
r the rotor
T h e generator Cl,iiliiiii ti 2
.,., !F' -.
D
1 IiUUBLRGLOVE
INSlllhlCD HANDLE
so that a simpie resistance measurement between the It is important that the shaft at the turbine end
fioating component and earth confirms the integrity of the generator is maintained at earth potential,
of the insulation. and a pair of shaft-riding brushes connected to earth
While all the insulation remains clean and intact, through a resistor achieves this. Because carbon
ii voltage will exist between the shaft at the exciter brushes develop a high resistance glaze when OP-
end and earth, and this provides another method erated for long periods without current flow, a spe-
of confirming the integrity of the insulation. A shaft- cial circuit passes a 'wetting' current into and out
riding brpsh enables this shaft voltage to be moni- of the shaft through the brushes; this circuit also
tored, and an alarm is initiated when this falls below detects when brush contact is lost (Fig 6.24). A
;i predetermined value. different scheme, in which a current carrying contact
468
FIG.6.22 Slipring brushgear and brushes
JUNCTlON BOX
RESISTORS
--.-
-+
4
BRUSH
VOLTAGE MONITOR BRUSil
LlNK
JUNCTiON BOX
FUSE HOLDER
-_iJ
lieated and the rotor is run at 20% overspeed. This ally be partially offset by balancing, so that conditions
subjects the rotor to stresses greater than it would at operating temperature are optimised (see Fig 6.27).
experience in service, and also causes the winding Imperfect equalisation of the stiffnesses (see Section
and end rings to settle into their final positions. 3.1 of this chapter) will cause 100 Hz vibration to
Trim balancing is then carried out, if found to be occur, superimposed on the normal 50 Hz. It is im-
necessary. portant to distinguish between these components when
Some rotors exhibit a relationship between vibra- presenting or analysing vibration amplitude readings.
tion amplitude and temperature. A few degrees dif- A significant crack in the rotor will have a com-
ference in temperature between one pole and the paratively greater effect on the double frequency vibra-
other, due to inequalities in ventilation, for example, tion component; 'run-down' traces are recorded and
FIG. 6.25 Axial flow fans on rotor can cause this. If the effect is consistent, it can usu- analysed, to provide assurance that no significant
471
The generator C I 1; 8.,
88
. . . ,
OILOEFLECIOH OIAPHHhllMOUIEA NSUlhllNG i i N G S
RETAINING RiNG
SECOND
CRITICAL
lA LoA@
i i N l \ i HOT
OPERNINGPOINT ORIG41"!,i
CHIIICAI.
INCREASL W I I H
TEMPERATURE
INCRIA!il(
,,,,,,,,,,,
AFTER O F i S E i B A W N C E C O i C
SPEEU. llm#n
6
~ I U 27 R O , O ~ vlbrailon a
change has occurred since the previous run down. and are connected to the same lubricating oil systv~~i
Oil whirl in bearings can cause vibration at 25 Hz. Seals are provided in both endshields to prcvclt!
Vibration amplitude and phase are recorded at the escape of hydrogen along the shahs. Mosl ir
generator and exciter bearings by accelerometers these seals are like small thrust bearings, in wlr
mounted on the bearing supports and by proximity a non-rotating white-metalled ring bears against FIG.6.28 Thrust-type sllaff real
probes which respond to the shaft movements. Var- collar on the shaft (Fig 6.28). Oil fed to an an!,\
ious degrees of sophistication, up to complete Fourier groove in the ring flows radially inwards acros. II,I;
analysis, are available. face into a collection space at frame gas pl.cssiito,
The torsional resonance of the generator rotor while the radially outward flow is collected i n rti absorbent.' If left inside an open stator, dry air must be transported. The completed core and core
coupled t o the turbine rotors is of the order of atmospheric air compartment. The seal ring niuri I>? be circulated. assembiy was inserted into a substantlai Outer casing
13 Hz. It is important that this is significantly dif- held against the rotating collar, and must thrlrltr~,- Protection applied to journals, sliprings, etc., must for in-works testing and finally at site.
ferent from the frequency of torsional exciting in- be able to move axially to accommodate the thc~iriiti be removed before operation. Blanking tape and one-piece stators for 660 MW generators can
fluences, of which the excitation and steam governor expansion of the shaft. collars, designed to prevent ingress of foreign ma- be transported, the two.piece concept has been con-
control (I - 2 Hz), and transmission system resonances Some machines have seals which resemble terial into the winding, must also be removed before tinued (see Fig 6.1).
are the most important. journal bearings (Fig 6.291, in which oil is appl operation
Transient oscillations in torque occur during elec- centrally and flows axially inboard to encounlet 11
trical disturbances, e.g., during switching operations, hydrogen pressure and axially outboard into ail
lightning strikes, imperfect synchronising events, etc. mospheric compartment. Such a seal does not I 4.1 Stator core
Some of the torque cycles may be large enough to to move axially, since the shaft can move freely in 4 Turbine-generator components: the The core provides paths for tile magnetic flux from
cause plastic deformation in the turbine-end shaft it. Details of the seal oil system are given in Sec stator one rotor pole around the outside o f the stator wind-
and at the generator/exciter coupling. 5.3 of this chapter. The stator must carry the output winding, provide a ing and back into the other pole.
low reluctance path for the magnetic flux, and with- As the rotor rotates, carrying its flux distribution
stand the torque produced, both at rated load and with it, all points in the stator core experience a
during faults. sinusoidally-varying 50 flux density. This would
3.9 Bearings and seals 3.10 Size and weight When generators rated 300 MW and above were induce a 50 Hz voltage of 700 V mially in a
The turbine-end bearing is located in a common ped- A rotor for a 660 MW generator is up to 16.5 ili first specified,'it was found that the smallest prac- solid core, and to prevent large circulating currents
estal with the LP turbine outboard bearing. The ex- long and weighs up to 75 tonnes. It is provided I!~III ticable stator core, assembled into the lightest pos- with their associated losses, the core is made ,of thin
citer-end bearing is either located in the endshield a cradle for transport. The rotor must never bc 11. sible casing was too heavy for transport by road steel plates coated with an insulating material; the
or in a separate pedestal. The white-metalled bearings lowed to be supported on its end rings; the weigkl in the UK, within the statutory limitation of that voltage induced axially in plate 1 s about 50 mV.
are spherically seated for ease of alignment, are pres- must be taken by the body surface leaving the old time. Since it is not practical to design a core in The sheet steel from ~ h i c hcore plates are cut
sure lubricated and are provided with jacking oil tap- rings free. Lifting slings must only be used ovcr tlr. sections for on-site assembly, and complete core conforms to ~ ~ 6 0 which
1, specifies dimensional lim-
pings. They are similar to the turbine bearings (see body length. It must be protected from water con. building and winding on site has disadvantages, a its, magnetic properties, silicon content (normally 3%)
Chapter I), except that the outboard and exciter bear- tamination, while in transit or storage, by the use ol design evolved in which the core and windings were and state of annealing, and test m e t h o d s Sheet thick-
ings are insulated (see Section 3.5 of this chapter), a weatherproof container with an effective moisti\tr assembled into a skeletal core frame, which could nesses used are 0.35 and 0.5 m m , with a specific
The generator
Cl~z%!b!t'$
$, Turi>inegeneratoi colnpoiicnts: tile stator
...
A n infra-red camera is used to scan the stator bore The net axial length of magnetic steel presented to
total loss value at 1.5 tesla and 50 Hz of 3.55 W/kg, where required, for the passage of cooling gas, l i y Idi areas of higher than normal temperature during the flux is less than the measured stacked length by
or better. building in a ring of thicker piates to which sni;ill ,iich a test. a factor between 0.9 and 0.95, known as the stacking
Core plates are cut to form segments of an annular steel bars have been welded. These bars are aligi~cil Some designs include a bonding agent between Jocror. This is because of the varnish iayers (and
ring, twelve segments per ring being common. Wind- in a mainly radial orientation, and serve to distribtltc layers of core plates to ensure that individual plates, adhesive if present), and the air spaces between core
ing slots, iocation notches and holes for ventilation the gas througil the ducts. Holes in the plates ;nc ;and particularly the teeth, do not vibrate independ- plate layers due to uneven plate thickness and im-
(if required) are cut in one pressing operation. The arranged to be in axial alignment and thus form axirll catly. Any wavyness in core build-up is corrected by perfect consolidation.
use of dedicated dies is justified, since nearly a quar- ventilation ducts in some designs. At intervals durine 111e use of suitable packing material. Slots for the stator winding conductors (bars) extend
ter of a million core piates are used in each 660 MW core building, heavy pressure is applied to consolidalc Grain-oriented sheet steel, whose magnetic pro- radially from the bore. These slots have parallel sides,
generator. The punched plates are ground to remove the assembly of plates. perties are deliberately made different in the two so that the deep bars can be inserted radially, the
edge burrs, and are then coated all over with one or When the build is almost complete, and with prch. perpendicular axes, is used in some designs (Fig 6.32). teeth between them therefore increase in section with
more thin layers of a baked-on insulating varnish. sure applied at the top end, the core is subjected ti, increasing radial disrance. The flux density in the
];lux in a circumferential direction behind the winding
With the core frame axis vertical, and one core a peripheral 50 Hz magnetic flux, which causes t l ~ r slots is arranged to coincide with the low loss orienta- teeth is therefore preatea at the bore, at the tooth
end plate in position at the lower end of the frame, plates t o shake down further, following which llio tion, which enabbs the back of the core to be op- tips, and is usually about 2 tesia for an acceptable
a ring of core plates is assembled, located on dove- space created is filled with more core plates and thr crated at a higher flux density than with non-oriented specific loss in the teeth. Since the slots and teeth
tail-shaped keys on the inside periphery of the frame. top end plate is assembled and pulled down. Core core steel, for the same specific loss. The opposite is are roughly equally wide at the gap, the mean peak
The radii1 butt joint between plates has as small flux tests are also carried out on the completed corc, true for the teeth, where the flux is radial and the flux density in the air gap is typically 1 tesla. The
a gap as possible to minimise magnetic flux distor- with a flux density in the back of the core 90-100010 specific loss is higher than normai. A reduction in peak flux density in the core back is typically 1.5
tion. The next ring of core plates is assembled so of the rated value, in order to demonstrate free do,^^ outside diameter should be possible from magnetic tesia. Some leakage flux in the end winding regions
that its butt joints do not coincide with those of from significant faults (Fig 6.31). If sufficient acoi- considerations, but the mechanical properties are ad- penetrates into the ends of the core. The axial com-
adjacent rings (see Fig 6.30). dental contacts between adjacent plates occur, il is .ersely affected. Core piates of grain-oriented steel ponent of this flux induces alternating voltages in the
Gaps in the build-up of core plates are created, possible for current to flow, causing local hot spots. ,nust be specially annealed after punching. teeth, and current flows around the teeth, as shown
Turbine-generator components: the stator
1-i<i. 6.37 C08c end-place and icieci? are included components due to: Fio. 4.24 ~eyshaln2 condenser - modular construction
OISIkNCE FROM
SLOT BOllOM, X
e Currents induced in core end plates, screens, and forces are produced, both at rated load and parti-
end teeth. cularly when large current peaks occur duringfault
conditions. The end turns must be strongly braced
Harmonic currents induced in the rotor and end to resist the peak forces and also to
lrable material between it and the support cone, nals are housed on the external stems of the biishings.
packers between the bars arcli-bind the structure The connections from the genciatoi terminals to thc
EACH DAR COMPRiSFS mfcrcntiaily. The inner layer is treated similarly, generator transformer are described in Volu~iie D.
P GROUPSOF BOTTOM INSULATION
2 STACKS OI STRAPS
4 /PACKING STRIP AND
CONrORMRBLE DOUGH
Phase isolated connections are always adopted, so
,y through-bolts, completing the very rigid structure. that an electrical fault at the connections must start
'ome designs use sheets of insulation material to as a line-to-earth fault, which is much less damaging
lose any spaces and prevent the accidental ingress to the generator than a line-to-line fault.
CROSSOYEH INSULATION
1
GROUPVERTiCAL
SEPARATOR copper has been noticed after very many years' ex-
perience. Any erosion of copper is detected by the
4.5 Electrical connections and terminals monitoring equipment.
13ectrical connections between one conductor bar and Water is passed into one or more inlet manifolds,
ALL HOLLOW
COPPERCONDUCTORS - MAIN INSULATION WRAP
$he next in series are made differently in different
iicsigns. In one, a common electrical and water con-
which are copper or stainless steel pipes running cir-
cumferentially around the core end plate. From the
1 STRAP INSULATION
iiector is formed by a copper tube bent into a U-shape,
;mid brazed onto small copper waterboxes into which
till the bar subconductors are brazed. In another, the
electrical joint is made by a solid copper bolted joint,
with the water connections separate. It is common
practice to insulate the joint or to enclose it in a
rubber housing.
The conductor bars at the high voltage end (line
manifolds, flexible PTFE hoses are connected lo all
the water inlet ports on the stator conductor joints.
In a two-pass design, water passes through both bars
in parallel and is transferred to the two connected
bars at the other end, returning through similar hoses
to the outlet manifold which adjoins the inlet mani-
fold. This design minimises the number of hoses,
but requires a larger pressure head of water across
end) and the low voltage end (neutral end) of a phase the winding (see Fig 6.43). In a single-pass arrange-
band are electrically connected t o tubular connectors ment, hoses connect both ends of a bar to the
I, PROTECTlVE DRiYiNG SiRlP which run circumferentially behind the end windings manifolds, which are located at opposite ends.
at the exciter end, to the outgoing terminals, usually Thin metallic-sleeved components are crimped in-
with line terminals at the bottom and neutral ter- side and outside the ends of the PTFE hoses, and
minals at the top, although other arrangements do these are then attached to bosses on the manifolds
exist. These connectors are internally water cooled, and winding connectors, using screwed-up olives,
and must be insulated for line voltage. O-rings or brazed joints. The casing hydrogen pressure
Terminal bushings (Fig 6.42) are proprietary paper- is everywhere greater than the water pressure in the
insulated items, with internal water cooling from the winding circuit, so that any leakage is of hydrogen
stator winding water system. Their insulation must into water, rather than the reverse, which would be
be capable of withstanding the hydrogen pressure in damaging to the winding insulation.
the casing, with no perceptible leakage. It is common The loss input into the water circuit at rated load
practice to flange-mount the terminals on a plate of is designed to raise the water temperature by less
nonmagnetic material, and to arrange for a terminal than 30°C. With an inlet temperature of 40°C, there
lo be withdrawable from outside the casing. Current is plenty of margin before theitemperature at which
transformers for instrumentation and protection sig- boiling would occur, 115-120°C at the working pres-
%
.
Tlie generator g
-- Clhi$i)r,, 0
........, @ - li~rbirie~generatoi
cornpo~~er~ts:
tlie slator
d,
@
&
RING SEALS
OUTER STATOR
FRAME
AiUMlNlUM
TERMtNAL
PLATE
TUliULhRCOPPER
ICONDUCTOR
PiFE HOSE
,CONNECTIONS
CONNECTION PALM
AIR SiOE
circulated for a lcngthy l,eriotl, to waini the winding runners lo accornrnodatc the hydrogen coolers. At
bcforc thc generator is excited. the ends, thick r i n g provide facings for ihc separalc
end shields. Internai supports for the core frame, in
the forni of horizontal footplates or spring plate fix-
ings, arc provided, and external feet support the
4.8 Stator casing complete assembly. Lifting trunnions are usually made
The casing contains the stator core and core frame, detachable.
and must resist the load and fault torques. It must The design of the welded joints is carefully con-
also provide a pressure-tight e~lclosurc for the hy- trolled to avoid the presence of unfused lands wherever
drogen. Historically, casings have been made strong possible. The main welds have to be leak-tight against
enough to withstand the pressure developed by a n hydrogen at 4 bar, which is a very exacting require-
ignition of the most explosive mixture of hydrogen ment. The complete casing may be too large to be
and air, without catastrophic failurc. stress-relieved in a n annealing oven, in which case
Because any mixture of hydrogen and air within it must be assumed that stresses up to yield stress
the explosive range is not allowed to occur, attain- exist in the welds. In one design, the casing is con-
ment of explosion pressure is not a credible condition, structed in two halves, which are stress-relieved before
and to specify the casing on the basis of withstanding being welded together.
such a pressure without leaks, as would be required Thc end shields are thick circular fabricated steel
by BS5500, is unrealistic. Consequently, the full re- plates, ribbed to withstand the casing pressure with
quirements of the pressure vessel code are not invoked, minimal axial deflection. They house the shaft seal
though some o f them are applied. This pragmatic stationary components and, in some designs, the out-
approach has been justified by worldwide experience over board bearing. Leak-free sealing o f the end shield/
fifty years. casing joints against the hydrogen pressure, as with
Casings are fabricated steel cylinders o f up to all other casing joints, is effected by gaskets, O-rings
25 mm thickness, reinforced internally with annular rings and sealing compounds injected into grooves.
and axial members which strengthen the structure and The Completed casing assembly is hydraulically pres-
form passages for t h e flow of hydrogen (see sure tested, and finally must be demonstrated to be
Figs 6.44 and 6.45). Internal spaces are provided with leak-tight to a level corresponding to a fall from
sure. Monitoring the temperature of each bar by horizontally inside the casing; they consist of banks
thermocouples, either in the slots or in the water o f finned o r wire-wound tubes through which waccl
outlets, enables a reduction o r stoppage o f water flow flows in one or two passes while hydrogen flows ovrt
in a bar to be detected. them. The coolers are arranged so that their headers
are accessible (for tube cleaning) without degassing
the casing. The tubes and the cooler frame must be
supported so as to avoid resonances close to tllc
4.7 Hydrogen cooling components principal exciting frequencies of 50 Hz and 100 Hz.
The advantages of hydrogen cooling, and its para- It is most important that moisture does not con-
meters, are described in Section 5 of this chapter. dense on the stator end windings, since electrical
Hydrogen enters the generator casing through a n breakdown may then occur. The dewpoint of the hy.
axially-oriented distribution pipe at the top, carbon drogen (at casing pressure) must be at least 2 0 ~ 1
dioxide for scavenging being admitted through a simi- lower than the temperature o f the cooled hydrogcil
lar pipe at the bottom. emerging from the coolers, and this is continuously
The rotor fans circulate hydrogen over the end monitored by a hygrometer. In normal on-load op-
windings and through the stator core, while a parallel eration, the stator winding water maintains the wind..
flow passes through the rotor. At rated load, the ing temperature above 40°C; if condensation occurrctl
hydrogen temperature increases by about 25'C during it would be on the hydrogen coolers first. Durinp
the few seconds taken to complete this circuit. Two run-up, however, the stator winding water is likely
or four hydrogen coolers are located vertically or to be cold, and it is either pre-heated electrically, or FIG.6.44 Outer stator caring
4
The genelator
CI??I,~<',I ,
.
.
*$ Cooling systems
*
2
@ rated hydrogen pressure o f not niare than 0.035 bar ductivity and specific heat of hydrogen, thc effect
k5 in24h. is that heat removal from heated surfaces is up
a Some of the core vibration is transmitted to the to ten times more effective. icsultine- in iower tem-
casing, and rotor vibration is transmitted through the peratures. Coolers can also be considerabiy smaller.
end shield and the foundations, The casing assembly
iiiust be designed to avoid resonances in the range e The use of hydrogen imposes the need fox hcime-
of these exciting frequencies. tic seaiing and condition control, which helps to
Drains arc arranged so that any oil or water col- ensure that the original electrical clearances are
lecting in the bottom of the casing is piped to liquid maintained.
leakage detectors, which initiate an alarm. Distri-
MOW imnporfanfly: the degradation of insulation
bution pipes for hydrogen and CO, are built-in; a by oxidation processes cannot occur in a hydrogen
temperature sensor at the CO, inlet initiates an alarm
atmosphere.
if the incoming gas has not been adequately heated
and could chill the fabricated casing locally. Electrical
iheaters are fitted in the lower half of the casing to The disadvantages are:
maintain dry conditions during outages. Since concet~trationsof from 4 % to 76% of hy-
The casing is bolted down to the supporting steel- drogen in air are explosive, hydrogen must not be
work on packing plates which are machined after aliowed to escape from the stator casing and its
triai erection to provide the correct alignment. Axial associated pipework in significant quantities and
and transverse keys prevent subsequent movement. become trapped in potentially explosive pockets.
The weight of the casing, complete with core frame, The casing and end shields have to be o f rugged
coolers and water, is up to 450 tonnes. construction and leak proof, demanding meticuious
welding techniques. Penetrations such as the rotor
shafts, and all outgoing connections, must be posi-
tively sealed, the former requiring a sophisticated
5 Cooling systems sealing system.
A generator of this type has an efficiency o f about
98.5%. Even though the losses are low in terms of A comprehensive gas control system is required.
the ootput, tiley amount to some LO MW, ail of For generators rated much above LOO MW, air cool-
which must be removed by the cooling systems; the ing is not practical; more than half the total loss
heat lost by convection and radiation from the casing would be due to fan and rotor windage. At 500
is not significant. and 660 MW, hydrogen pressures of 4 or 5 bar are
In some stations, most of the generator (and exciter) economic; higher pressures than this have little or
losses are transferred into the boiler feedwatcr system no advantage. The only practical alternative at
- condensate in the heat exchaneen.
bv usine, - Whiie these ratings is complete water cooling including
such an arrangement can be economic, there is a the rotor, which has not been adopted in the UK,
Penalty in the form of added complication, and the and only rarely elsewhere, because of leakage pro-
most modern stations do not have this feature. blems at the very high water pressures produced
by the rotation.
inonitoi the pl.opoi-lioil of C O , in the gas passing lo iored by several thermocouples, wliosc readings s l i ~ ~ i i l i l
atmosphere; when this is sufficiently high, lhe C O , be averaged, at the inlets to and outlets fl-olii 111i
TE:cq
~~ .... ~
~
inlet i s closed (see Fig 6.46). hydrogen coolers. Typically, hydrogen is ciucill;itvil --,-.--"I-
1-ligh purity hydrogen from a central storage tank at 30 m"s which, with a full-load loss input af ;$l>i!iit
GENERATOR STATOR CASING END
or electi.olytic process is then fed through a bus nrain 5000 kW, results in a temperature rise of the olrlvi ($1
a1 about 10 bar to the gas control panel, where its 30°C. The cooled gas should nor be hotter than lO"1 ,
pressure is reduced before being fed to the casing so the temperature of the gas entering the cooirih
through the top admission pipe (Fig 6.47). Being very should not exceed 70°C.
much lighter, it displaces the C 0 2 from the bottom Water cannot normally leak into the casing fi-OIII 1111-
of the casings via the C 0 2 pipe to atmosphere, again stator winding water circuit or the hydrogen coolc~!~,
with some degree of mixing. When the proportion since the water pressure is lower than the gas pressilir
of C 0 2 in the vent is low enough, the proportion in both circuits. It can be released from the slinS!
of air left in the casing will be very low, and if the seal oil, particularly if the oil is untreated turl>i~ir
casing is then pressurised with hydrogen t o its op- lubricating oil which has picked up water froril t110
erating pressure (say 4 bar), the proportion of air turbine steam glands. It is imponant that the ~moie
will be reduced to a quarter of this low value. The ture content of tllc casing hydrogen be kepi lor),
complete process normally occupies a few hours. enough to prevent condensation occurring on l l i u
Separate procedures are followed t o ensure that coldest component, which may be the water coolcd
other components, such as tanks, are properly scav- winding. The differential pressure is used to circlllutc
enged, so that dangerous mixtures do not occur. The a flow of hydrogen continuously through a dryri,
reverse of the foregoing procednrc, using C 0 2 and typically of the twin-tower type, using activatetl I ~ I I I
tllen dry compressed air, is followed t o remove mina, with automatic changeover and regeneratiol~,A
hydrogen from the machine for inspection or for a inotor-driven blower maintains the flow througi, 1111
prolonged outage. rotor when the rotor is not running at speed (scc ].if:
In one design of 500 MW generator, air is removed 6.49).
from the casing by drawing a vacuum, using the Continuous monitoring of the humidity of the r l l r .
pump normally used to degas the seal oil. The shaft in& gas is provided by means of a hygrometer. i l i i
seals are arranged to seal effectively under this unusual maximum permissible dewpoint is not less than 20°C
operating condition. When the vacuum is as low as below the cold gas temperature, measured at cusion
can be achieved, hydrogen is admitted, the resulting pressure. It is i m ~ g r t a n tthat this caveat is observed,
purity when pressurised being sufficiently high. particularly if the dewpoint is being compared with
Normally, hydrogen purity remains high, since air that of a sample drawn from the casing and measulcil
cannot leak into the pressurised system. Some air at atmospheric pressure.
may, however, be released from the shaft seal oil Hydrogen is circulated by the fans through tlic
flowing into the casing hydrogen space. Replacenlent stator core and end windings, the precise paths biiiii:
hydrogen to make up for leakage is usually sufficient different in different designs. The rotor acts virtuzill?
to maintain the required purity. as its own fan, hydrogen being drawn through liii.
The differential pressure developed across the windings and exhausted into the airgap, again tiil
rotor fans is used to circulate a sample of casing ferently in different designs. The hydrogen removr,.
hydrogen continuousiy through a katharometer-type the electrical loss in the rotor winding, the 'iron lirv,'
purity monitor, which initiates an alarm if the purity in the stator core, the windage loss produced by llic
falls below a preset value, typically 97%. The purity rotor and fans, and most of the electrical losses gcn.
monitor (and the gas analyser) can he calibrated with erated in the frame and end winding structures.
pure gases from the piped supplies. A check on the Because it is impractical to ensure that potentially
purity is also possible by monitoring the differential explosive mixtures of hydrogen and air never occur
pressure developed by the fans, which responds in the small bore instrumentation pipework, thosu
markedly to the change in density produced by air instruments and devices containing electrical circuil~.
impurity. in contact with the gas, such as katharometers, mu*;!
A Pressure sensitive valve admits hydrogen from be intrinsically safe in such mixtures. This means thsl
the bus main if the casing pressure falls below a pre- a sudden break in an electrical circuit must not br
determined level, while a spring-loaded relief valve capable of providing enough spark energy to ignitr
is set to release hydrogen to the outside atmosphere the gas.
if the pressure becomes excessive. It is important It is impossible to ensure complete freedom f r o r ~
that these two pressures are not set so close that Leakage of hydrogen over the lifetime of the plan:,
:t,.
s.>
wastage occurs, particularly as the gas temperature and the areas near to potential leakage sources arc ----
p,,,.:.
F,,', ,
kz
.
,, and pressure changes when on-load cycling. Monitoring
of the hydrosen
. - cansumotion is a reeentlv introduced
classified into zones of differing degrees of hazanl,
described in detail in CEGB Code of Practice 098/311:
- AIR
CO*
b;izi
~,.
feature on some units (see Fig 6.48). .
The temperature of the hydrogen is normally moni-
'Code of Practice for the Design Principles relating
FIG.6.46 Generator gas system - displacing air with CO?
<:,+
$< to the use of Hydrogen in Large Generators'. Zones 0
Cooling systems
.-
FIG. 647 Oeneialor gas systenl - displacing co2 with H, FIG.6.48 Gcneralor gas ryrtem in normal operation
The generatoi Chap11 8 i Cooling systems
station, and to admit C 0 2 to the casing, duplicated in the white-oietalled ring, and fIou,s along the clear-
valves are provided, one set being located remcte from ances between the shaft and the bore of the seal,
where any fire is conceivable (see Fig 6.50). both outwards to tlie drain and inwards to the hy-
Hydrogen has been used universally for 50 years drogen pressurised space. The inward flow rate is
for high speed generator cooling, and incidents such much greater than that for the thrust type, because
as this have been very rare. The meticulous attention it is not inhibited by centrifugal force, and it would
to safely precautions both in design and operation be capable of contaminating the hydrogen purity to
lhave been largely responsible for this good record. an unacceptable extent. T o prevent this, all the oil
fed to the seals is subjected to vacuum treatment, in
which much of the air and water is removed. Against
this disadvantage, it is claimed that the journal type
5.3 Shaft seals and seal oil system seal is inherently better able to withstand disturbances
Seals prevent the escape of hydrogen where the rotor of the shaft by expanding to provide a larger clear-
shafts emerge through the casing end shields. What- ance for oil flow if it is heated by excessive shaft
ever their design, they are located in the end shields, movement
and are inboard of the bearings. Two types of seal More sophisticated versions o f tlie journal type seal,
have been commonly used: the thrust seal and the one of which has two separate oil supplies for inward
journal seal. and outward flow, have been developed to avoid the
need for vacuum treatment (see Fig 6.29). It is also
possible to keep the oil supplies separate from the
5.3.1 Thrust t y p e s e a l main turbine lubricating oil supply, which is the source
In the thrust type seal (Fig 6.281, the seal ring acts of most of the entrained water.
like a thrust face, bearing onto a collar on the shaft.
Turbine lubricating oil is fed to a central circum-
ferential groove in the white-metalled face of the 5.3.3 Seal oil s y s t e m
seal ring, at a pressure controlled to be greater than In the conventional seal oil system (see Fig 6.51), the
that of the casing hydrogen. Most of the oil flows main seal oil supply is taken from the shaft-driven
outwards over the thrust face and drains into a %ell. lubricating oil pump, with its pressure suitably re-
A small proportion flows inwards, against centrifu- duced. The pressure is further controlled by diaphragm
gal force and with only the oil/hydrogen differential valve which maintains a constant differential pressure
pressure behind it, into a drainage compartment which above casing gas pressure at the seals. The oil is cooled
is at casing hydrogen pressure. This oil can release in a water-cooled heat exchanger, and finely filtered
entrained air and water at this point, thus contami- to prevent metallic particles gaining access to the small
nating the casing hydrogen, as noted earlier, and it clearances at the seal faces.
is therefore important that the inward oil flow is Because it is necessary to maintain the shah sealing
small. oil at standstill, to prevent hydrogen escape, motor-
The seal ring is attached to a housing which must driven seal oil pumps are also provided; these act as a
lhe free to move axially to accom~nodatethe 30 mm back-up in emergencies, and are initiated by falling
or so of axial movement imposed on the shaft by seal oil pressure. They are commonly vertical pump-
tliermal expansion o f all the coupled rotors down- motor units mounted on the top o f the lubricating
stream from the turbine thrust bearing, as they pass oil settling tank with the pumps submerged. A battery
F10. 6.49 Oas dryer and blower from cold to hot conditions. The housing is arranged fed DC motor-driven pump may be provided as a
lo move inside a stationary member, using rubber back-up in case o f supply failure, but this would
sealing rings to contain the oil and to create a n axial be expected to operate only a few hours while the
pressure at the seal face. hydrogen is scavenged.
and 1, in which explosive mixtures exist continuously virtually impossible to eliminate some potential ignl. In some designs, an additional chamber between The oil flowing to the casing side of the seal is
o r occur in normal operation, should not be present tion sources, such as the rotating shaft rubbing a n oil fixed and sliding components is fed with oil at a in a pressurised hydrogen environment and must be
if the principles outlined above are followed. Zone 2, scraper ring, or sparking at brushgear. separately controllable pressure so that the overall collected in a 'break pressure' tank, which releases it
in which explosive mixtures are unlikely to occur Another potential source of ignition occurs wheir pressure at the seal face can be varied. In another through a float controlled valve and enables it to be
and, if they do will only exist for a short time, covers currents are induced in pipework loops, as may irr. variation, additional pressure is provided by springs. returned to the drain tank. The possibility of hydrogen
instrumentation as previously noted; the hydrogen the case when pipes are routed near to main con. entering the drain tank is recognised; low level alarms
dryer and blower, the detraining tanks, and the in- nections. Here, flanged joints are insulated to break give a first warning (some form of pressure loop is
terior of the control cubicle to which hydrogen is the possible current path. 6.3.2 J o u r n a l t y p e s e a l usually provided) and a blower exhausts the gas above
piped. Also classified as Zone 2 are the areas into If a serious rupture occurs, e.g., the break-up ol llere the seal resembles a short journal bearing float- the oil in the 'hydrogen section' of the tank to at-
which hydrogen may leak, through gaskets, seals, etc., a shaft seal, hydrogen may escape very rapidly, and ing on the shaft. In this case the shaft can freely mosphere. This blower also serves to reduce the
knowing the normal pressure behind the gas and its if it encounters a source of ignition, say the shall Inlove axially through the seal, and it therefore does pressure in the bearing housings (communicated via
propensity for rapid upward movement. Sources of rubbing, it will burn intensely in the ambient air. 111 not have to accommodate the thermal expansion of the half empty drain pipes) below atmospheric, thus
ignition are not located in such areas. It is, however, order to vent the casing to atmosphere outside tlir. tile shaft. Again, oil is fed to a central annular groove reducing egress o f oil vapour at the bearings.
497
The generator
Cha1,ii.l 1.
.
498
FIG 6 50 Generator gas system - emergency scavenging
i
,!
#
FIG 6 51 Seal oil system
F- E* ;.=>=.* - -
2 ='.E -
>
? c ;Z2>z g
.?Eo*.- " . O " O
psJ
$$?S$"
"?G$ a3 g2-2 2
gbfZ.5 .-.-?E
-" g g -$: 3 - ge *gz:.z
-" 2 ~ " ~ C8 a. Sg - :J m
2 : O z
cm
2.EGk.= E c . - m
-e s o 5 s g i K.G
5.5 o z = . E C l 0s
03.2; 2- "P- 8
=.
h:g;scos
5 2 0 1m "m c:z % E
2, 0
o
".CC5 ".Z$
g ,c .C ,? " " F .O :
'0 %
E 9 5.22
z3m5%;~tk::
3
" o z
g.gpgg a " " a
,= " = a "
-
m $ g a0 0a s" sG:g 2z . ,E
42
-2 + = :25 8 m gE g3'a"a-
2
2
o o m m ~
m
8
TI?@generator
~ l i a p i i .(.~ f Cooli!?g systems
Y
,h,, c7 "h,nm,,,, =,
\ HORIZONTALFRAME
ENOMR i
COVER
PLATE
!~%&,TuBEdihiE StCURtNO
INLETAWL) OUTLET /- * SCREW
WATERBOX DOOR
504
i i i e generator CI,?i~~lcv
I,
tlie introdoction oi' thc rectified AC excitcr. I'iicsc iixciler icsponsc ratio :~
SUPPLY TERMINALS
CWLlNGWAiER INSULATED CLAMPING
INLET YENTIMION
ROC( HOLES
EXCITER STEELCOUPLING
BEOPMIE SUSHliND BOLT
FUSE PIN
IUNGSTFN HRLOGFN
LlOiiTSOLiRCF
BLOWN
REMOii
OETFCiOR ALARM
CiRCUli CIRCUITS
i."C*iAi*RM
NDICAICJR
LAMP
An alternative brushless exciter design consisting The need for the two diodes in series was deter-
o f a rectifier witii a 3 - 2 - 2 - 8 arrangement o f connec- mined from consideration of two diodes failing simul-
tions tolaiiing 96 diodes is also in common use. The taneously in the same phase of the rectifier. If the
notation signifies three AC connections, two D C con- series diodes u,ere not present, tlle resuit would be a
nections with two diodes in series and eight parailel short-circuiting of the generator rotor.
paths per bridge aim. The rectifier is designed to Indicator fuses are connected in parallel with the D Fla. 6.66 Rectifier nlodule (anode)
maintain rated output following the failure of up to main fuses as a secondary method of determining 9
two paths in any bridge arm. diode failures. When the generator is shut down, in- Q
A circular row of fuse modules and two circular spection of the indicator fuses readily identifies failed
rows of diode modules are contained against the cen- diodes. indication and phase location of up to three blown fier is fed via the mixer unit 4 to the transmitter
trifugal forces by a steel retaining ring. The diode For cooling purposes, air is circuiated in a closed fuses per phase, making a total indicating capacity 10 to give direct frequency modulation of the trans-
modules consist of anode and cathode units, which are ventilation system which contains a water cooled heat o f nine blown fuses. The other changes are the use mitted carrier frequency.
used in the positive and negative arm of the bridge. In exchanger. Air from the outlet side of the cooler cir- of a single transmitter, directly modulated by the The transmitter output is transferred via the aerial
contrast to the mark 1 systems, the mark 2 is fused on culates within the main enclosure. The self-fanning field voltage, to which are added sub-carriers contaie- to a carrier amplifier 16 and demodulator 17 to give a
the AC side of the rectifier and advantage has been action of the fuse and diode modules draws air from ing the rotor current, blown fuse and earth leakage mean output voltage proportional to the carrier fre-
taken of the improved peak inverse voltage capability the main enclosure througll the rectifier. information. quency. The output is then smoothed and scaled to
of modern diodes to eliminate the capacitor fuse cir- produce a n output corresponding to the DC field
cuits. A typical mark 2 diode module is shown on voltage.
Fig 6.66. 6.2.3 Telemetry system Voltage
Fusing on the AC side means a reduction in fuse T h e telemetry system employed on this design of The field voltage measurement is taken differentially
size, as tlle elements are no longer subjected to the rectifier makes use of the principle of frequency di- at each end of the shaft. as shown on Fie 6.67. Ear'" leakage de'ec'ion
high induced generator field voltages which occur vision multiplexing and includes a number of addi- Voltage measurement is made via a voltage "divider Rotor earth leakage is detected as a voltage devel-
during system faults and pole slipping incidents. tional features. The most significant of these is the and differential amplifier 1. The output of this ampli- oped across a resistor R6 which produces a frequency
8
change nt the ootpot o f a voitagc-to-frequency coil- of these sliprings.
vcster 3 , This oolpot is added to the voltage signal Thc hi-ushes arc designcd to opciatc contiotlolisiy i l l
in tlie t~ansmittcl-input inlirer 4. TIlc eartii lcakage order to acilievc ~lniotei-iuptcdrotor earti? Paul1 ilro-
signal is isolated from tlle carrier denioduiatoi 17 out- tcctian. This airaagcmenr is lightly loaded and \ ~ o u l d ,
put by a band-pass filler 22 and pioccsscti t o provide after a sliort period of operatior at iow current.
an earth leakage alarm signal. develop a high iesistancc contact film, resulting in
incorrect iwadings. T o oveicomc this difficulty, a
constant current is circulated through the two brushes
Field currenr ,neasure,iie~il ('brush-wetting'). This continuous flow of current
Field curreilt is measured by means o f eight series- maintains the interface resistance constant at normal
connected current transformers ( T I - T 8 ) in phase A levels.
of the main exciter output. Since each current trans- A signal propartional to generator rotor current
former (CT) surrounds a conductor between the fuses is obtained from a search coil mounted in tile
and the associated rectifier in one phase, the total quadrature axis of tlie exciter field coils. The output
output from the current transformers corresponds to signal is filtered and converted fronl a voltage to a
the total phase current. The C T output modulates the standard 4-20 mA current signal suitable for use
voltage-to-frequency converter 5 over a range of field with the station central logging computer. The field
currents from 0-6000 A DC. The signal carrying the voltage signal is similarly conditioned and buffered
current information is selected by a band-pass fiiter to protect the instrumentation from tile high voltages
20, dcmadulated and rectified to give field current induced in the rotor field following incidents, such
indication. as pole siipping. The currcnt and voltage signals are
subsequently processed to providc an average rotor
winding temperature measurement.
Blown fuse indicafio!! Continuous monitoring of the rotating diode equip-
Eight CTs (T9-T16) in each phase, identical lo those ment is considered unnecessary, given the proven
used for current measurement, are each loaded by a operational reliability of the equipment. This is the
transistor switch (TRSI-TRS8), shunted by a resistor simplest and most robust o f the described schemes
(K17-R24). The resistors are connected in series but t o monitor essential rotor quantities. It has the added
under normal operating conditions each one is shorted advantage that generator rotor RSO (recurrent surge
out by its associated transistor switch. The resistance oscilloscope) testing can bc carried out, a facility not
of the circuit is therefore low. If a fuse operates, available with equivalent telemetry schemes.
the associated transistor switches off and the circuit
resistance increases; further fuse failures result in fur-
ther increases in resistance. This arrangement is re- 6.2.5 Rotating rectifier p r o t e c t i o n
peated on each of the three phases and connected t o The main exciter is protected against the effect of
the summing unit 40 which, by supplying a current diode failure by the provision o f fusing, either on the
to each of the circuits, provides an output voltage AC or DC side of the rectifier. When a diode fails, it
proportional to tile number of blown fuses in each usually fails to s i ~ o i rcircuit, blowing the high rupture
phase. The output of the summing unit controls the capacity (HRC) fuse, which in tuin blows an ejector
output of the voltage-to-frequency converter. pin indicator fuse t o initiate an alarm. On the mark I
The blown fuse information is selected from the system, the pin is detected by a pllotoelcctric cell,
receiver carrier demodulator 17 by a band-pass filter and an alarm is raised in the control room. In contrast,
21. The signal is then recovered by the demodulator the mark 2 system can identify u p to nine individual
24. T h e output waveform for the circuit corresponds diode failures.
t o the number of blown fuses so the waveform is On the basis of the proven high operational reiia-
analysed to give the number of fuse failures. Phase bility of the rotating diodes, it is not now considered
identification is carried out by a strobe generator 30 necessary to continuously monitor the rotating system
which produces three separate pulses that coincide for failure. Present practice is t o examine the indica-
with tile centres of each positive phase current period. tor fuses o n an opportunity basis and during planned
maintenance overhauls.
Should a major fault occur, such that a complete
6.2.4 I n s t r u m e n t sliprings bridge arm is either short- or open-circuited, major
An alternative scheme is shown diagrammatically o n damage can be caused to the excitation system. T o
Fig 6.68 and uses shaft-mounted sliprings. Connec- protect the unit in the event of such a failure, it is
tions are taken from the exciter upshaft leads through CEGB practice to provide bridge arm failure prolec-
the shaft bore t o instrument sliprings mounted o n tion. This device initiates a turbine trir, o n detection
the permanent magnet generator shaft. These slip- of a failure.
rings permit direct measurement of field voltage. The The detector monitors the amount of ripple induced
rotor earth fault indicator relay is connected t o one in the main exciter field, which in a healthy rectifier
Tlie generator Chaptii~1 l.xcilation
ciatcrl \ ~ ~ i ttlic
h cxcilcr is ihc lpiincij>al cause of dciay, voitages iippeai across the ,cciiSiei in tlic l e i e i h c
its removal greatly improves the speed of cncilalion diseclioil, i t is CECH lpsaciicc lo use diodes with ;i
system response, enhaticirig generator transient stability peak invnse capability of 3 . 4 ~ 4 . k\',
2 illus providin~
margins. ample margin.
A feature o f all static excitation eqilipment is tlle T o protect the diodes against voilage spikes (caused
need for sliprings and brushgear which require regular by diodc commutalion effects and external s\+~itcbing),
maintenance. As this is cair-icd out on-load, an inter- each diode is provided wiih a dV/di suppression cir-
lock system is normally proi'ided so that access to cuit, consisting of a capacitor and series resistor. In
the slipring enclosure is prevented, unless a safety addition, each rectifier section has a resistor-capacitor
procedure has been followed. No further mention of suppression network connected across the DC output
sliprings or brushgear will be made here, as a detaiied to limit voltage transients coming from ihc DC side
account of the equipment is given in Section 3 of this o f the rectifier to within the peak transient voltage
chapter. rating of the diodes.
The rectifier diodes are easily damaged by ovcr-
currents and arc thcrcforc individually protected by
6.3.2 General description of s t a t i c diode rectifier high speed, high rupturing capacity fuses, with micro-
equipment switches for fuse failure indication. These fuses op-
A static rectifier system is an assembly o f diodes and erate for an internal fault ro isolate the faulty diodc
diode protective equipment. Typical 660 MW rectifiei- and allow conti~iuedoperation o f the ~.emainingdiodes
units consist of up to four self-contained, three-phase, in the arm. The ,nost severe fault experienced by the
full wave bridges. The number o f diodes per section are diode is a short-circuit on the DC side of the icctifier;
selected so that MCR requirements can be niet with one this is cleared by HRC fuse operation.
section out of commission. Each section is provided Overcurrents due to system faults or slipring fiash-
with AC and DC isolators, and an interlock system overs are ciearcd by DC cir,cuit-breaker operation.
ensures that, during on-load operation, access can be
gained to one section only.
Diode rating is based on the continuous and peak 6.3.4 S t a t i c thyristor rectifier s c h e m e s
inverse voltages, together with the current/time rating T h e thyristor has radically changed the role of static
on overload. A typical rectifier bridge has a number rectifier equipment, as it no longer plays a passive
of parallel paths per arm (the diodes being specially but an active role in tlle control o f generator excita-
selected to ensure satisfactory current sharing) with tion. One of the principal features o f this form of
one diode in each parallel path. excitatioll control is its very fast rate of response
To dissipate the heat generated during rectifica- due to the elimination of a main exciter. A typical
tion, the diodes are mounted on heat sinks. Cooling thyristor excitation scheme is shown on Fig 6.69.
is provided by either forced or natural air circula- Excitation power is generally taken from an excita-
tion and alarms are generally provided to warn op- tion transformer which is connected to the generator
erators of high temperature conditions which require output terminals. With this arrangement, the trans-
investigation. former primary voitage follows the generatoi terminal
is the sixtll harmonic of the exciter fundamental frc- excitation system. Early equipment contained diodes Busbars are used for the AC connections from the voltage during normal and fault conditions. Under
quency. This ripple is associated with the normal o f relatively low rating, where up to three diodes weir main exciter, and for the DC rectifier output to the fault conditions the excitation power transformer must
three-phase full wave rectification of the exciter ai- required in series to meet reverse voltage requiremenls generator field winding. The busbar system, like the be capable of meeting the field forcing requirements
mature voltage. Should a bridge arm fail (to either during pole slipping. This, together with a cautious exciters, is rated for 110% MCR and is capable o f at reduced terminal voltage, and of withstanding the
open- or short-circuit), a component of ripple at the design approach, resulted in high spare capacity. withstanding the mechanical forces arising from the overvoltage experienced following a load rejection.
exciter fundamental frequency appears in the exciter The rapid development o f semiconductor techno- worst overcurrent fault conditions. An alternative scheme, which is not subject to
field. This is detected by a band-pass filter tuned to logy has resulted in a reduced number of simpler, All rectifier equipments supplied to the CEGB must system voltage variations, is the compound source
the exciter fundamental frequency. Once the input is more compact devices, capable of operating at high meet the requirements of ~ ~ 4 4 1which7 covers both rectifier system. These static systems use both current
o f sufficient magnitude to overcome an internal bias voltage and current levels. Equipment of this type routine and type testing. and voltage sources (generator terminal quantities) to
signal, which is set to prevent spurious operation, a has a record of high reliability on the CEGB system, make up the excitation power source.
relay is energised which initiates a Category B unit and is currently in use on a number of 660 MW units. T o ensure integrity under 'black start' conditions,
trip. With the introduction o f the thyristor, the role o f 6.3.3 Rectifier protection however, a scheme based on shaft-mounted exciters is
the static rectifier has radically changed. The thyristor Diodes are susceptible to overcurrent, which causes a n attractive alternative. The exciter runs continuously
rectifier plays a n active role in the control of excita- excessive heating of the element, and to overvoltages at ceiling output with low power factor, providing
tion power t o the generator field. Like the diode, which can pierce the rectifying element and cause com- the thyristor converter with a constant voltage source
6.3 Static rectifier excitation equipment the thyristor conducts current in one direction only; plete breakdown. It is therefore essential for system o f excitation power.
however, unlike the diode, the point at which con- integrity that both the operating and ceiling voltages The thyristor rectifier unit is arranged in several
duction takes place can be controlled. are within the capacity of the diodes. isolatable sections so that any one section can be ser-
6.3.1 Introduction Excitation power modulation is achieved by con- During generator pole slipping o r asynchronous op- viced wllile the remaining sections provide full MCR
Excitation systems based on the static semiconductor trolling the thyristor firing angle, eliminating the need eration, the peak voltages appearing at the slipring excitation requirements. Thyristor free-wheel and pole-
diode bridge were the first alternatives to the DC for a main AC exciter. As the time constant asso- are about ZMX) V on a 660 MW machine. Since these slip crowbar circuits are generally included to protect
Excitatiori
GENERATOR F L U
VOLTAGE V,"
CURRENT IHYRISlOl(
CONTRO~. CONiROl
SIGNAI
SIGNAL
I
I,-F l E l D I I M t CCMSTANT
i,- SUPPRESSlON ?$MEFORAIHYRISTOR EXCITER
the thyristors from excessive overvoltages. Direct cur- to connect a number of thyristors in parallel. This I>-SLlPPRESSlON iiMC FOR AN AC RECIIFIER EXCITER
rent voltage transformers (DCVTs) trigger the crow- presents difficulties, since individual thyristors havt
bar into operatioll on detection of an oveivoitagc different forward path characteristics, causing one io
condition. Free-wheel thyristors provide a path for cotlducl the majority of current; if allowed to cori.
stored energy in the rotor during thyristor commu- tinue, this would cause breakdown. Forced curre,,!
tation and system fault conditions. The pole-slip crowbar sharing, by the addition of a low value resistance 01
provides a path for the induced reverse direction poie- inductance in series with each anode, is llor~nallyuscd 6.4 The v o l t a g e r e g u l a t o r erators and continue to provide reliable operation.
slip current, so avoiding excessive pole-slip voltage to obviate this. The rapid developments in the field of semiconduc-
developing across the rotor terminals. Thyristor cooling is provided by a natural or forced tor technology brought about the introduction of the
The DC output Of the thyristor rectifier is provided air scheme. Temperature detectors mounted within the 6.4.1 Historical review transistor amplifier and the thyristor output ampli-
with voltage and current surge suppression circuits air circuit provide early warning of high temperature fier, which have increased the speed of response and
Early designs . of voltage regulator equipment had a
which are designed to protect the thyristor from volt- conditions, aliowing appropriate operator action to be improved the overall system performance. Subsequent-
large deadband, were slow to respond to system changes
age spikes generated during thyristor commutation or taken. On future large plant, the higher current ratings ly, the discrete compone~ttaperational amplifier has
and required regular maintenance. This was due main-
field circuit-breaker operation. In addition, individual and associated losses may make it necessary to use been replaced by integrated circuit equivalents. A
ly to the use of moving mechanical components within
thyristors are protected against dV/dt breakdown by water cooled thyristor equipment. typical modern dual channel arrangement is shown
the automatic voltage regulator (AVR). T o eliminate
a capacitor-resistor suppression circuit connected in Thyristor excitation systems can improve the steady on Fig 6.71.
these difficulties, AVR systems were developed which
parallel (identical to the circuit used to protect diodes). state and transient stability limits considerably because Future developments in the field of AVR design will
made use of the cross-field generator or amplidyne.
Overcurrent protection is provided by a series-connected of their ability to change the generator field voltage centre around the use of digital microprocessor tech-
The amplidyne was used as the regulator output stage
HRC fuse. In the event of an individual thyristor almost instantaneously. They are therefore finding gen- niques. These discrete time controllers offer a number
and controlled the field of the DC exciter.
drawing excessive current the series fuse will rupture, eral application on generating plant which is connected of potential advantages, most notably the introduction
The amplidyni and DC exciter were, in turn, super-
electing a striker pin which initiates an alarm. Over- to the periphery of the main transmission system, of adaptive control strategies.
seded by the magnetic amplifier and AC exciter. In
current excursions are normally controlled by the AVR
to within tile rotor heating limit; however, in the
where the inversion mode of operation, in which the
field current is rapidly reduced by the reversal of
....- - -....~
+hi? ., the
~~~. ~ -
magnetic am~lifierwas used as the
regulator output stage controlling the main exciter
event of a prolonged overcurrent condition, the ex- energy flow, is exploited to the full. The rapid field 6.4.2 S y s t e m description
field. The output from the exciter was rectified by a
citation is tripped through the field circuit-breaker. suppression achieved following isolation from the sys- The AVR is an essential part of the operation of a
diode bridge and taken, via slipring connections, to
To meet the high current requirements of large tem under load rejection or fault conditions is illus- modern electrical power system. It is at the heart of
the generator field winding. Schemes of this type were
turbine-generator excitation systems, it is necessary trated on Fig 6.70. the excitation control systems around which the re-
successfully employed on all the CEGB 500 MW gen-
The generator (;l?a~>~t.t
I,
-. .... .
being coii~paiedusill, thc i-cfercocc voltage. Piovisioll iiiiiial voltage and, if it exceeds a sale lcvci (nari~lail?
is made foi tl,e operalor to change tire iefeieirce 1.3 pu), the thyristor coii\,ertes is imn~ediatelyswilchcd
\,oltafe in iesilo1ise lo syslem reqilirements. into the inverting rnadc, which reduces llie lield ciiw
1x1 addition lo llic basic voltage co~itrai require- rent in minimum timc. This relay is oillp active dori~i~!
mcnt, the AVR includes control loops which perform unsynchionised operation.
other vital tasks. These controllers, which include the The ovel.fluxing relay is also only active during oil.
MVAr limiter and overfluxing limiter. are discussed synchronised operation, when there is a chance that
in detail in Section 6.5 of this chapter. the geoel.ator transformei. could be overfluxed if the
safe voltage/frequency ratio is exceeded. A special
relay detects this condition and initiates an alarm.
6.4.4 A u t o follow-up circuit Control loops within the AVR will act to reduce this
With a dual channel design, both regulator channels to a safe level but, if the condition persists, the thy-
can be active at the same time, each providing half ristor converter is switched to the inverting mode and
the total generator excitation requirements. An alter- the excitation is tripped.
native arrangement allows for one channel to be active, Most faults within the regulator loop give rise to
whilst the other follows passively. Should a channel cithei an over or under excitation condition. There-
trip in either scheme, then the other picks up the fore comparator circuits are used to monitor reglllator
full excitation requirement of the generator in a and converter bridge input and output levels. Alter-
'bumpless' manner. This is achieved using follow-up natively, a singlc comparator monitors the thyristor
circuits which track the primary (or active) channel output current and compares it with maximum and
and drive the standby channel output while a dif- minimum field current limits allowed. Transiently, these
ference exists between the two. limits are exceeded during system faults, but the chan-
nel is tripped if thc condition persists beyond a few
seconds.
6.4.5 Manual follow-up
This is similar to the auto follow-up but is used to
adjust the manual control system in response to 6.4.8 Thyristor converter protection
automatic channel changes. In the event of an AVR In addition to the above, AVR channels are tripped
1 . EXCITAT8ON
OYSRFLUX
failure, the manual control takes over in a smooth if any of the indicator fuses protecting the converter
TRIP8 ALARM
TOTAL CURRENT bumpless manner. thyristors rupture. The thyristor converter is further
protected by a temperature sensing device which Op-
erates in the event of excessive heating.
PIC. 6.71 Dual clialliicl AVR 6.4.6 Balance m e t e r
A balanCe meter is provided in the power station
control room and in the AVR cubicle. This monitors 6.4.9 Fuse failure detection unit
the difference between the automatic and manual The regulator relies upon a signal from the generator
maining equipment operates. The central function of terminal voltage also changes, increasing the error sij, control output settings. During automatic control, the voltage transformers for its controlling action. Loss
the AVR is to maintain constant generator terminal nai. The error is amplified by the regulator and osr.,i follow-up circuits ensure this error is minimal, whereas o f the signal is due in general to failure of the fuses
voltage under conditions of changing load. There are, to increase or reduce excitation, as necessary, to brini during manual control no such facility exists to adjust in the voltage transformers. A fuse failure detector
however, a number of other functions which are the voltage back to its original value. The need for ;i the AVR, and a large discrepancy can therefore exist. unit monitors the input to each channel and compares
required from the AVR, if a large generator is to rapid, stable response following such changes is ol During manual operation and prior to selection of it with that of a check or reference transformer. If
operate satisfactorily under all operational conditions. paramount importance and, since control systems i l k . AVR control, the balance meter is consulted and an a fuse fails in the voltage transformer supplying the
The CEGB currently specifies dual channel AVR ing such high steady state gains would rapidly becotnr adjustment is made so as to avoid large MVAr dis- reset voltage, the channel is tripped; a fuse failure
equipment complying fully with EES 1980 together with unstable, special signal conditioning networks are in. turbances following control changeover. in the reference transformer initiates a n alarm.
manual back-up control on all 660 MW plant. This cluded. These consist of phase advance and phasc
provides maximum reliability as the loss of one chan- lag circuits which have adjustable time constants a!.
nel does not inhibit operational performance. Facilities lowing accurate tuning of the voltage response. To. 6.4.7 AVR protection 6.4.10 T h e digital AVR
are provided to repair the faulty channel while the gether, these circuits act as a notched filter, reducinf: The AVR plays a vital role in the unit overall pro- The rapid development o f the microprocessor has
generator remains in service. On small gas turbine gain at generator electromechanical oscillation frequer).. tection scheme, as it controls suppression o f the gen- brought about the increased use of digital electronic
plant, single channel AVR equipment is specified. cies, whilst permitting the high gains necessary foi erator field after faults. In addition, it is necessary techniques in a number of industrial control appli-
accurate voltage control. The setting of the time c o n to protect against AVK component failure which would cations. While the present generation of solid state
stants is of great importance, as transmission systern otherwise jeopardise generator operation. AVRs meet all existing CEGB functional requirements,
6.4.3 T h e regulator dynamic stability is sensitive to AVR settings. For The field suppression circuit accepts signals from there are advantages to be gained if microprocessor
The AVR is a closed loop controller which uses a this reason, sophisticated analytical techniques (sec the main unit overall protection scheme, in addition schemes are considered.
signal proportional to the generator terminal voltage Section 6.7 of this chapter) have been developed and to signals from the overvoltage and transformer over- High reliability, which has been a feature of pre-
and compares it with a steady voltage reference. The applied in order to obtain optimal performance. fluxing relays. The circuit switches the AVR thyristor sent AVR equipment, can be expected to improve
difference or error voltage obtained is then used to The AVR accepts the generator terminal voltage converters to their inversion mode of operation and still further due to the reduction in the number of
control the exciter output. signal via its own interposing voltage transformer. then trips the excitation. components, since much of the control logic, at pre-
If the load on the generator changes, the generator The voltage signal is then rectified and filtered before The overvoltage relay monitors the generator ter- sent carried out by electromechanical relays, will be
T h e generator Excitatioti
Cl~ailti!t i
.
software s~)ecificd.Cosl advantages are also envisaged 6.5 Excitation control llii~.iagsysleiu lauli conditions, the AVll reacts to at one end or a tsanso~issionlinc osciilate willi iesilect
us standard memory circi~itsreplace the present cus- In addition to tlic basic voltage contrili loop, ~ ~ I o c I ~ I , ! boos1 excitation; normaily this siloation lasts only to ti~oscat the olilei end. TIlese oscillalions, knowti
tomised printed circuit boa1.d~.I-lowevei, the principai exciiation eqoi~)rnenlincludes a number of ail<Iiixi,!ijii ~nilliseconds beforc cil.cuit-breaker operation clears as power s.vste,,i osci//aiioris, are load dependent and,
moti\~ationlies i n tile iangc of sophisticated control- ii~iiitel.circuits. Tilesc li~nitersopcrste as parallel i , i i t the fauit. I-lowever, it is necessary to ailow for tile if not prevented, severely linlit the MW transfer across
ler designs tliat lhc iuicroprocessor makes physicaliy trollcis, in that their signals replace the genci:it~li longest back-up protection clearance times and hence a the transmission system, To obtain a solution to this
realisable. One class of controller is the adaptive voitagc as the controlled variable whenever tliosi ill dciay of up to 5 s is specified. After this delay, the problem, an understanding o f ihc basic lmachine lor-
regulator, which (as the naine suggests) is capable of pill signals exceed predefined limits. que relationships is necessary.
rotor currciit iimit ci~.cuit generates a signal which
adjusting its structure to take account of changing For a generator to remain in synclironism following
opposes that from the AVR and ramps excitation
plant conditions. This type of regulator, shown sche- system faults, it must produce a braking torque to
6.5.1 Rotor c u r r e n t limiter current back to a safe value.
matically on Fig 6.72, consists of a recursive real- balance the accelerating torques introduced by changes
time parameter estimator (based on s form of least All exciters are capable of supplying generator lirkl
current well in excess of that I.equired for noriiti,i to the eiectrical transmission system. The braking tor-
squares structure) which is used to identify the con- 6.5.2 MVAr limiter que can be separated into two components:
trolled plant. The estimated plant model is then used MCR opeiation. This field forcing capability or 111;ii
gin is necessary during system fault conditions, ~ , I , r i , , Modern AVR equipment is capable of controliing
by the regillator to form the control law. A wide generator operation at rotor angles of 130' to 140'. e The synchronous lurque, which is in-phase with
the additional reactive power provides the much aeedril rotor angie changes and is necessary to ensure res-
choice of regulator/control law designs exists; typicai This mode of operation is not, however, tenable when
boost of synchronous torque. However, this ciirrr~~t toration of rotor angle following displacements.
strategies include poie placement and minimum var- transient stability criteria are taken into account; it is
must be restricted in duration because o f the diinfrr!
iance. Botll have a very flexible structure, making it therefore customary to limit the generator operation
of overheating the generator rotor which would c;!tisi The damping torque component, which is in-phase
a simple matter to include additional input signals, to a rotor angle of 75'.
insulation system degradation. To prevent overhr,it with rotor speed changes and provides damping of
such as machine accelerating power (which has been in&, the exciter field current signal is applied to i l l < The permissible leading MVAr varies with the square
demonstrated to enhance transmission system dyna- rotor oscillations.
rotor current limit circuit which detects values ( , I of the generator terminal voltage, the limit line being
mic performance), and post-fault recovcry. field current in excess of 110% MCR. defined by the following equation:
Where generating units are connected to the grid over
MVAr .+ MW = V2 high reactance tie lines, fast response excitation sys-
tems are vital to maintain system transient stability.
This has the effect, however, of reducing the inherent
CONVENTIONAL
SPEEDGOVERNOR generator damping torque; consequently, under cer-
The in-phase and quadrature components of stator tain load conditions, generator rotor swings following
current are obtained from a form of phase sensitive system changes will have little damping.
rectifier. Tile signals are then compared with the As the component of torque in question is strongiy
generator terminal voltage bias and, if the iimit set- associated with rotor speed, a logical starting point
GOVERNOR
VALVE REF
I t POWER
ting is exceeded, an output is generated which acts to
boost excitation and reduce rotor angle.
for investigation is the generator torque speed loop
shown in Fig 6.73 (a).
The introduction of a n AVR, while enhancing syn-
iURBiNE
GENERATOR
GENERATOR
OUTPUT
chronising torque, has a deleterious effect on the small
6.5.3 Overfluxing limit inherent generator damping torque (the latter is ob-
VOLTAGE
In addition to the overfluxing protection circuit, mod- tained by means of poleface windings or induced eddy
ern AVR equipment includes overfluxing limiter cir- current effects). This presents some difficulty, as from
cuits. This is a closed loop controller which monitors considerations of transient stabiiity a fast response
the voltage/frequency ratio during unsynchronised op- high gain excitation system is necessary, however, its
implementation could result in reduced power system
I ANALOGUE To
DIGiiAi
CONVERTER I eration. Should a predefined ratio be exceeded, the
limiter generates a signal which acts to reduce ex-
citation and thereby prevent generator transformer
damping and a consequential reduction in load trans-
fer capability.
T o counteract this, a device known as a power
overfluxing.
system stabiliser (PSS) has been developed. Figure
6.73 (b) shows the addition of such a device to the
RECURSlYE 6.5.4 S p e e d reference controller torque dpeed loop. A signal derived (in this case) from
PARAMETER shaft speed is used as the input to the stabiliser; this
ESTlMAIiOR COMPARaTOR In accordance with current CEGB functional require-
ments, this feature controls the application of excita- is then orocessed and conditioned to provide sufficient
tion during the turbine run-up sequence. This limiter phase lead to compensate for the phase lags inherent
I PARAMETER
CONTROLLER
unit ensures that voltage is brought up to nominal and
the unit synchronised with the minimum delay.
in the generator plant and transmission system. The
output of the stabiliser is superimposed onto the AVR
demand signal in order that an increased damping
torque component is produced.
OPTjMkL WITH ADAPTIVE A comprehensive linearised generator and power sys-
CONiROL
SBNAI. 6.6 The power system stabiliser tem stabliser representation is shown on Fig 6.73 (c),
where it can be seen that the PSS signal is fed to the
block denoted as GEP. This represents the generator,
6.6.1 Basic c o n c e p t s exciter and power system, detailed knowledge of which
FIG. 6.72 Block diasram or adaptive exci~ationcontroller
Situations have occurred where groups of generators is vital if the PSS is to compensate for the phase
526 527
Excitation
lag within <;El' arid piodocc a component of geo- if uncoriecled, will result in prolonged rotor swings
clator tosquc in phase with speed changes. This in- in lllc region Of 0 . 9 - i . 6 14%.
formation can be obtained in a variety of ways, nota-
bly by on-load frequency response analysis, using puise Infra-plant ~iiodes
injection techniques and by computer simulatioil tecli- Intra-plant modes of oscillation occur between units
oiqoes based on representative system models. within the same power station. Unlike the above,
these are not power transfer dependent but rcsult from
interaction between generator excitation systems. If
6.6.2 Characteristics of GEP
action is not taken, intra-plant interactions will limit
Extensive system investigations are used to establish the available PSS gain and hence its effectiveness.
the characteristics of GEP. Ail operating modes o f
the plant arc examined to identify the conditions
under which stability is marginal. In general, operation 6.6.4 Principles of PSS operation
at leading power factor during times of low system PSS action is inhibited during steady state trans-
AND demand are the most critical. However, in the case of mission system conditions, as it has a detrimental
EXC1TER
pumped-storage plant, which will generally be opeiat- effect on voltage control. A steady state voltage offset
7 ing in the pumping mode during these periods, the is prevented by the use o f a washout circuit at the
situation can bc more critical because of the large PSS input. The washout circuit, shown on the PSS
machine rotor angle with respect to the rest of the block diagram on Fig 6.74, is essentially a differen-
system. tiating circuit which attenuates low frequency changes.
A series of simulation studies is then conducted, The time constant of the circuit, Tw, is chosen to
using detailed plant representation (including the AVR washout low frequencies but not to interfere with
. ....,
. .. and PSS), the results being assessed by the analytical the signal conditioning networks at system electro-
- .... . , ,. , . . . ,
.- ....
. . I > I . .
~,.,..,
.. . - ,. . e.:., , . ...,, . . ,,.."..'.
., techniques described in Section 6.7 of this chapter. mechanical frequencies.
I. I .
.I,
/ ;
. F
(..
/
, ,..
9
,-,<
:
'
I,..
,.',..,,*
.,.,,,
;-,,
The model PSS settings are adjusted until optimum The signal conditioning network provides the phase
excitation performance is achieved at all critical op- compensation, so that a torque is produced it, phase
erating conditions. These settings are then used as a
basis for plant commissioning tests, thereby reducing
with sneed changes.- This network essentially shapes
the PSS characteristic to provide the best damping
expensive on-site testing. oerformance at all electromechanical modes. Generally
this is achieved by maximising stabiliser gain (within
the constraints imposed by the power system control
6.6.3 S y s t e m m o d e s of oscillation
loop) and shaping the phase characteristic so that it
Examination of the basic torque-speed-angle loop in has a slightly lagging value at the particular inter-
Fig 6.73 'yields W,, (natural frequency o f electro- area oscillation frequencies o f concern. T o prevent the
mechanical oscillations) = \/(u,Ki,/M) rad/s. For intra-plant interaction, tuning should ensure that the
typical values of machine inertia (M) and synchron- overall phasc characteristic is not greater than 90"
ising torque coefficients (Ki,), the frequency range of lagging at frequencies up to 4.0 Hz.
interest is 0.2-4.0 Hz. Within this frequency range, It is important to ernphasisc that PSS action is
the oscillatory modes can be broadly divided into intended to improve the system damping following
three main components. small disturbances. PSS action following system faults
will degrade AVR performance, and hence system
Infer-area or infer-lie osciliafions recovery; therefore, the stabiliser output is limited, so
Inter-area oscillations range typically from 0.2-0.6 Hz that AVR action is dominant during the first post-
and occur where two generation groups are connected fault cycles.
by a weak tie line; they tend to be power transfer
dependent. Inadequate damping of these modes will 6.6.5 T h e c h o i c e of stabiliser signal
result in operational difficulties, since power transfer
A n obvious choice for the stabiliser input signal is
capability is reduced. These low frequency inter-tie
rotor shaft speed, measurements being generally made
oscillations have been initiated by random events oc-
at the H P turbine pedestal. The drawback with this
2urrLng d ~ r w gperlod5 of h ~ g h\I\\' trdn,icr o\cr ae3L
form of signal is its inherent susceptibility to shaft
trxlilnlrrlun l i u k i and or unu,oal load d~btribution.
torsional frequencies. This term refers to the reso-
.-------
i
iC1
OErEf-A'OeEXc~TER
COMPREHENSlYE LINEARISE0
SYSTEM iGEPl_ _ _ _ _ - 2
craloi- to the systeor increases, the synchronous tor- oscillatory respoiise. It is possible lo simplif), llie
que component is reduced. Under these circumstaoccs, inteiprctation of the roo1 locus diagram by considei-
thc AVR bucks and/or boosts lhc generator field ing those poles which lic furtliest to llie right as
current in such a way that the generator itself develops dominating the syslenl res1)onse.
the additional synchranising torque. 'This approach is extended to rile n>ultivasiablc situ-
A properly tuned AVR tlierefoie performs a vital ation by making use of modern state variable theory.
role in the maintcnancc of stable system operation The system considered is first linearised about the
under all operating conditions, and this section is operating point of interest and the equations o f stale
concerned with the methods developed and employed formed.
to analyse AVR performance, and hence to arrive at
tuned settings. X = AX + CV Input equation
Y = DX + FV Output equation
6.7.1 Frequency r e s p o n s e analysis
Frequency response analysis is based on the injection where X is the vector of stare variables, Y is the
of a sinusoidal signal at the input to the AVR and vector of output variables, A is the state matrix and
thc corresponding measurement of generator terminal C,D,F arc the feedback, input and output matrices,
voltagc magnitude and phase shift. This procedure is respectively.
repeated over the range of frequencies necessary to A series of simulations is conducted over the com-
identify the plant, which in the case of the generator plete generatox operating regime, using a detailed
ERROR excitation system is 0.2-4.0 Hz. Results are plotted model of tlie turbine-generator and excitation sys-
in the form o f inverse Nyquist or Bode diagrams, from tem. The dominant poles (or equation solutions) are
which information on system stability and damping plotted for a range of control settings, and those idcn-
can be obtained. These tests call be repeated for a tified as providing optimal damping at the most critical
REFERENCE VOLTAGE
range of AVR settings until an acceptable system operating condition are selected for commissioning
response is established. Performance indices used in purposes. This method of analysis therefore provides
GENEHATOR TERMINAL
VOlTACIE this form of analysis are system gain and phase mar- advanced information regarding equipment settings
gins, both of which are measures of relative stability. and plant performance, thus reducing expensive com-
In general, a phase margin of 40' or more, and a missioning time.
gain margin of 6 decibels is considered good design
FIG.6.74 Power syslern rtabiliser - black diagram practice for most feedback control systems.
An alternative approach is the injection into the 6.7.3 Large signal performance investigations
AVR summing junction o f a short duration iectan- The foregoing methods are based on the response of
gular pulse. The corresponding machine terminal volt- the excitation system l o small signals; hence non-
mation is required of the shaft torsional conditions 6.7 Excitation system analysis age response is measured and harmonically analysed linearities can be ignored and the system assumed to
so that, if possible, speed probes can be mounted at Trends in modern generator design, with the cmpha- by a computer, using a fast Fourier transform pack- bc linear.
a torsional node and suitable torsional filtering can sis on large thermally-efficient but electrically-remote age. The results are then plotted in the form of an It is equally important, however, to investigate the
be applied.
centres o f generation, have combined to reduce trans- inverse Nyquist diagram from which measurements perforinancc of the turbine-generator plant following
Because of these considerations, use is made Of a
mission system stability margins. As a consequence, can be made of relative stability and damping. This substantial changes in operating conditions. In these
signal derived from generator electrical power which the primary responsiblity for power system dynamic approach has a number of distinct advantages, par- situations the non-linear characteristics of the plant
is related to shaft speed by the following relationship: and transient stability rests with the generator excita- ticularly during on-load testing as, unlike variable must be taken into account to obtain realistic results.
tion system. frequency techniques, pulse injection testing can be These large signal performance investigations pro-
1
Au = -
M
j (P, - P,)dt (6.1) oscillations. without the risk of exciting power system
undertaken vide a means of evaluating excitation system response
following a major transmission system disruption (gen-
Dynamic sfabilify refers to the system performance
following small load changes which, under conditions erally a three-phase fault at the generator transformer
where w is shaft speed change, P., is mechanical of high MW transfer over long distances, can result in high voltage terminals is used for standard studies
input power, P, is machine electrical Power and M is sustained oscillations in the region of 0.5 Hz. If these 6.7.2 S t a t e variable analysis -
and investiaations), . which could jeopardise system
~
the angular momentum. If the mechanical Power is oscillations are not rapidly attenuated, severe limits A common method used to assess the performance transient stability.
assumed to remain constant, Equation (6.1) is sim- and stability of feedback control systems is to track Transient stability analysis is primarily concerned
will be imposed on transmission system operation.
plifled to: the path taken by the roots or poles of the closed with the effect of transmission line faults on genera-
loop transfer function. Changes in system parameters, tor synchronism. While certain simplistic approaches
Transient sfabilily is concerned with the ability o f a
A* = - -I Pcdt (6.2) generator o r group of generators to maintain syn-
such as gain and time constants, cause these poles exist dealing with the case of a single machine operating
M to move. The path taken by the poles in response onto an infinite bus (such as the equal area stability
chronous operation following system faults. Under to control system changes can be plotted and are criteria), a full multi-machine solution is generally
such operating conditions, the generator requires a known as a roof locus. Referring to Fig 6.75 any necessary requiring the use of digital computer slmula-
The major advantage of this form of stabilising signal boost of synchronous torque. This is provided by the roots appearing on the right hand side of the S-plane tion techniques. These simulation packages represent
Is its insensitivity to torsional oscillations and the transmission system in the form of a synchronous imply an unstable system. Roots on the real axis in- in detail the generator, transmission and excitation
simplicity of measurement. Its adoption, therefore,
has both technical and cost advantages.
comDonent of the oost-fault infeed. However. as
~ ~~.~~-the
.~~. dicate a n exponential o r overdamped response, and systems, and solve the governing non-linear differen-
reactance of the transmission line connecting the gen- roots containing a n imaginary component imply a n tial equations by numerical integration.
levels ;arc monitored at all liic beai.ing ihoosings and
at ,he shiifis adjacent to lbc generator bearings duti~i?,
iliii-tip.
@
voltage of the generator can be deteinlined by the
manufacturer to give the most economic design. Once
FULI.
MAGNITUDE the first of a new rating has been decided, a degree LOAD
of standardisation is imposed to allow generator trans-
former units to be made interchangeable, 22 kV being ROTORCURRENT
1.i ur!ia~81eill~~squ,,b,,un,
lit
Capability chart
capability chart is a MW-MVAr diagram, for
Iiicl, the limits of leading MVAi were discussed
7.6 Steady short-circuit conditions, short-
circuit ratio
Anothcr relationship that is established during works
testing, is between the field current and the stator
A constant MW limit can bc drawn at the rated current with the three stator line terminals short-
7.4 Steady state stability "2 ~!o!r,cl- output of the turbine, though the maximum circuited (Fig 6.79). In this condition, the voltage re-
The power produced by a synchronised generatol. can Ixtnvcl. capability of the steam system may be signi- quired to ci~.culate,say, rated current through the wind-
be expressed as (VE sin b)/(Xd). For a given machine, lil.;$nlly greater than this. The circular locus of rated ings is very low ( = XE, say 0.15 per unit) and there-
operating at a terlllinal voltage V, the syncllronous rt;ilor current cuts the rated MW line at the rated fore the flux is also very low and conditions are lin-
reactance Xd is a conslant parameter, and if tbc hd\'A and powcr factor point, but does not in prac- ear, since there is no magnetic saturation. Most of the
'internal voltage' E, or rotor current, is kept constant, 1ii.i. impose a limit. The rated rotor current, also a considerable magneto motive force (MMF) produced
power varies as sin 6. At rated conditions, 6 is about ciicolai locus but with its origin at the 0 M'h', by the rotor is required t o counteract the armature
45-55O. liiitcd MVA/Xq MVAr point, imposes a limit at con- reaction MMF produccd by the stator winding.
From this position, a sudden increase in steam clilions of MW and laeginp.- . .power factor both lower Kunning under these conditions in order to cir-
\
throughput, or (more likely) a sudden demand for 111an rated. Such a capability chart is used as the culate current through the windings to dry out the
more power into the system, perhaps because of a
fault on the lines, results in a n increase in 6 and in
generated power until a new equilibrium position is
RATED STATOR
reached (Fig 6.77 (a)). CURRENT
This is valid if b is less than 90' before the sudden
change. Once 6 is greater than YO", a demand fol.
more power cannot be met by an increase in load
angle, and the generator rotors cannot attain a posi-
tlon o f equilibrium (Fig 6.77 (b)). The rotor then
accelerates to just above synchronous speed and 01)-
erates in a non-synchronous mode ('pole slipping'),
with large power and voltage oscillations which are
unacceptable to either the transmission system or the
boiler controls. The situation may be relrievable il.
the voltage regulator can initiate a rapid increase in
the field current, increasing E in the equation, to
prevent instability (Fig 6.77 (c)).
Load angles approaching 90' are associated with
operation at leading power factor, which is not a
normal requirement in the UK. However, studies of
the transmission system under ail credible conditions AOTOIIANGLE 8
of loading, line outages and faults are carried out to iiiMsinlalning rlsbibYinrcoas#ngoic~~aiol,
(Note Ilia1 diileici~tconsiderations apply to 21 s : i i i ~ ~ ~ ; 'Tlic lolal loss is typically 9300 hW, and Ibc cffi- nents oScoi~ccri,a r c the i,egativr sequcnce components.
golc inacliinc, where ihc geonletry of tiic rnol;i,r:i, cicncy is 98.6010, The efficiency is sliglilly lhighes a: I n order to cit.coIatc nega~i\;c seqtielicc cu~renls
IPallls is very differen1 when ol)eratiiig near tbc qii;,<i about 80% than at 100% MW load, and also im- ihl-oilgli the generator stator and tiaiisfosmci wind-
iature axis frnm tliat ill the direcl axis, and Xd ;tzi,i proves as the power factor incl.edses lowarils uniry. ings, a system of negative seqiieocc voltages must be
Xq have dissin~ilarva1ucs.i The losses shown in tne list are renioved by tlic v a r ~ producerl by negative sequence flux, i.r., (lux rotating
ious cooling systems described in Section 5 o f this at synchronous speed but in the opposite direction of
chapter. The total loss removed by each system is rotation to the main flux. This tilts the rotor at twice
therefore known, and the flow rates are designed to the rotational speed, and indoccs a 100 1-17 voltage in
7.7 Synchronous compensation maintain an appropriate tempeuatul-e. In thc llydro- the rotol surface. 100 I-iz current flows in the outside
While operation in this mode is not foreseer i i i i gen system, 30 m3/s of hydrogen is circulated, being 'skin' of the rotor body, in the wedges and in the
generators o f this rating in the UK, a note here i s cooled to about 40°C by the heat exchangers, and top winding conductors, as if these components were
included for completeness. A generator, synchronisril reaching about 65°C on entry to thc coolers. The part of the squirrel cage of an inductiotl motor.
to the system, ma? be used to generate o r absoll stator core will attain about 75'C, except at the ends, Additional heating therefore occurs in these regions;
reactive MVA, while drawing its loss power froni ~ l i i which are likely to be hot, but within the BS limit in particular, in positions where current transfers
system. By varying its excitation, it can be 0per;ilciI o f 120°C. The rotor winding will reach an average from one componen? to another, sucli as at the wedge
over tlle range shown on Fig 6.78, to meet thc rv temperature of 105°C with local hot spots perhaps ends, and at the endring shrink faces.
quirements of thc system. It is not normally possibl~ 20°C higher than this, which poses insignificant ther- Because of the potentially damaging effect of this
to drive the turbine at rated speed with no steam flou, mal stresses on thc insulation and creep conditions on extra heating, limits on the extent of unbalance have
and s~nallergenerators operated in this way are <li. the copper and aluminium components. to be established. These are conservatively set to ini-
coupled from their turbines. At large values of leadilii, In the stator winding water system, conditions differ tiate alarms when the negative sequence component
FIG.6.79 Opeii- and slioil-cimuii cliaiacierisiicr reactive generation, stator core end temperatures mziy exceeds 5% of the rated current and to trip at abovc
between single and double pass arrangements, but
be high, because the axial components of MMF frojii with inlet water cooled Lo 40-C, the outlet water will 10%. The component is detected by a three-phase cir-
both stator and rotor windings become more in ph;,s,., not exceed 70°C. Hence the winding copper will bare- cuit designed to respond to negative seqllence current.
insulation is not a normal requirement for these large resulting in higher values of axial leakage flux. ly exceed 70°C, and then only at the water outlet In some designs, copper shims are placed in the
generators. It may, however, be necessary to demon. end, and the winding insulation will nowhere exceed ends of the rotor slots, below the wedges, and cxtend-
strate the capability of the connections between gen- iOO°C. CEGB specifies Class F insulation with Class ing outboard of the rotor body to form a colltitluous
erator and transformer, in which case the short. B rises, which are very comfortably met in these ring, in order to assist circumfcrential currcnt flow
circuit would be applied at the transformer terminals. 7.8 Losses, efficiency and temperature designs. and to minimise the small intense hot spots where
Manual control o f excitation is essential. Many separate components of loss can be identified, A considerable advantage of water cooled windings current transfer is concentrated. Where circtlmfer-
The open- and short-circuit characteristics enable some of which are substantially constant irrespective is that the temperatures arc inherently constrained to ential slots are cut into the pole faces (Section 3 of
certain parameters to be established. Short-circuit ra- of load; others can, for simplicity, be assumed i i , be very low, thus maximising the intrinsic life o f tlle this chapter), means for transferring surface current
tio (SCR) vary approximately as (stator c u ~ r e n t ) ~These
. col~i. insulation. Also, since the temperature rises of the across the slots are provided, usually in the form of
Ponents are listed below, with kW values given for ;I core and windings are similar, problems associated copper strips retained by wedges in shallow 'pole
typical 660 MW generator at rated conditions: with differential thermal expansion arc minimised, face slots', to avoid overheating at positions of currcnt
- Rotor current for rated voltage on open-circuit
and it has not been found necessary to incorporate concentration.
Rotor currcnt for rated currcnt on short-circuit
Consranr Iossa Coolonr loss, k i l features in the end windings to accommodate axial The shallow surface current paths must also handle
Fan ioss Hydrogen 600 movement. the very much larger, short duration currents imposed
Rotor windage loss by unbalanced conditions during transient faults. A
Hydrogen 350
Othel. windage loss rough criterion of acceptability is provided by assuming
Hydrogen 150 that the heating is proportional to ~ ( l ~ ) where ~ t ,
This rough measure of steady state stability is nearly Open-circuit core (iron) loss Hydrogen 950 I, is the negative sequence stator current (per unit)
the reciprocal of Xd; minimum values of 0.4 and Bearing loss Lub ail 600 7.9 Electrically unbalanced conditions and t the time (in seconds) for which the condition
0.5 are specified for the 500 and 660 MW units, re- Shaft seal loss Seal oil 100 The amplitudes and phase displacements of the three- persists. This is only approximately valid for times
spectively. Rotating exciter constant loss Exciter air 100 phase voltages and currents in the transmission system short enough for heat dissipation to be ignored. Per-
Auxiliary system losses, e.g., motors - 100 are usually symmetrical t o within about I % , which missible values of of about 3 are usual for
Synchronous reactance Xd may be quoted as the does not impose any significant difficulties in the 500/660 MW generators, and 'instantaneous' irip-
reciprocal o f short-circuit ratio, in which case it is Variable losses Coolant loss, kM' generator. However, it is possible for much larger ping is initiated if this value is exceeded (see Fig
the value corresponding to the degree of saturation Stator copper loss Stator winding water 1600 unbalances to exist, for example, if one phase o f a 6.81).
at rated voltage on open-circuit (which is not the same circuit-breaker remains closed while the others are The surface current paths are also involved in any
Eddy current ioss in
as that at rated load). It is of interest when discussing windings Stator winding water 600 open for considerable lengths of time, then the ability condition in which the generator is connected to the
operation close to the stability limit, in which case of the generqtor to withstand such conditions must system but is not operating synchronously. This may
its unsaturated value is appropriate and given by: Additional core loss,
due to higher flux and) be established. happen on total or partial loss of excitation, and
can usually be tolerated by the generator for a short
Rotor current for rated current on short-circuit
end loss
Lass in core end olates I Hydrogen 1600
The well known method o f resolution of unbal-
anced phasors into systems of symmetrical components
is used in the analysis shown in Fig 6.80. Because
time, although slip frequency surges will occur on
the system. Because the induced currents are at slip
Rotor current for rated voltage on airgap line and frame
Loss ill rotor surface
Rotor copper loss
J Hydrogen 2400
generators are invariably connected to transformers
whose LV windings are arranged in delta, which there-
fore d o not have a neutral connection, zero sequence
frequency, they are able to penetrate further into the
rotor, wedges and winding, and the thermal conditions
are not as critical as with the 100 Hz currents pro-
Variable excitation loss Exciter air IS0 voltages and currents cannot exist. The only compo- duced by unbalanced operation.
537
Tlie generator
Chapt(ii I:
$'!-11111591111F i ' A i l i i C L 1 I I I I I N i
1 W i S MCR CUiiRiiNi
10
70
20 30 50 60 70
embracing the stator winding slots, the airgap and change of flux induces currents in the rotor surface
the rotor slots, with a small component associated paths, and for the first few cycles, say up to 200 ms,
with the end windings, and is affected by the degree conditions depend more on a reactance linking these
Fic. 6.80 Unbalanced pliase eonditionr of magnetic saturation. The normal value for un- surface flux paths with the stator winding. This is
saturated transient reactance is of the order of 0.3 referred to as the sub-transienl reactance, X d " , with a
per unit. value of about 0.2 per unit. It is this reactance which
7.10 Transient conditions It is this reactance which controls the initial rise- limits the current in the first few peaks after a fault.
vious position, i.e., 6 changes, so that the electrical For a three-phase fault at the generator terminals from
of-voltage when load is suddenly tripped off; typi-
Changes in the load demand, system operation con- power generated changes to restore equilibrium. The
cally the voltage rises instantaneously to 1.3 per unit rated voltage open-circuit, the RMS value of the initial
ditions and the response of other generating units, combined effect o f similar load changes occurring in and finally reaches a value determined by the pre- current peak will be V/X,", i.e., 1/(0.2) = 5 per unit.
mean that conditions at the unit transformer terminals many units acts to restore the system frequency to its vailing value of rotor current. Also, transient reactance The peak value is J 2 times this, and, if the par-
are constantly changing. Increase in overall demand original value. is used in calculations involving the stability o f the ticular phase experiences full asymmetry (depending
causes a fall in frequency to which the speed gover- Coincident with the change of load will be a change unit with the system during a transient fault situation. on the instant at which the fault occurred), it is pos-
nors of all the connected turbines respond. Their rate in system voltage, which causes the voltage regulator Such studies require accurate representation of gen- sible for the first peak to reach 2 4 2 x 5 = 14.14
o f response depends on the settings of the individual to adjust the excitation to restore the original voltage erator parameters, and in this context it is important times rated current. In practice, flux decay results in
governors, some units being deliberately arranged to value. (A large voltage change may require a trans- that its specified value has been met (see Fig 6.82). the maximum current being about 90% of this value,
act more responsively than others. former tapchanging operation to maintain the gen- During conditions of massive change, such as those but if the short-circuit is applied from a condition of
A highly responsive unit varies its steam inlet valve erator terminal voltage near its rated value.) that occur during a close-up fault, when the terminal load, i.e., with increased flux and a higher 'internal'
position frequently, causing the steam throughput to Flux cannot change in the machine instantaneously, voltage may be suddenly reduced to half its rated voltage, the peak current could be greater.
change and altering the torque equilibrium. The ro- and the rate-of-change is influenced by the transient value (or even to zero for a fault at the generator or Such peaks o f current result in enormous forces
tors move forward or backward relative to their pre- reaclance X d . . This depends largely on the flux paths transformer low voltage connections), the very rapid on the stator windings in the slots and end windings
538
Tlie generator CI7apti.i t. Meciialnicai considerations
.
~hioogli a ncuisal eariliing device, designed to linlil
the fault current in tlie event oC B s t a t ~ wiiiding
i Pail11
to earti,.
The neutral earthing device of eailicr generators
consisted of a wales rcsistoi, designed lo limit tlle cur-
rent in a line lo earth fault to a maxirnunl of 300 A.
Morc recent machines use a small single-llhasc dis-
tribution type transformer with its primary connected
between the generator star paint and earth, and its
secondary loaded onto a resistor. This arrangement
limits the fault current to about 15 A, and was ori-
ginally intended to allow a n internal fault to be sus-
tained while load was reduced, rather than requiring
an instantaneous trip. Modern practice is to trip in-
stantaneously oil fault detection, even with this form
o f earthing. In both cases the sensitivity of protection
is such that a fault at less than 10% from the neutral
point is not detectable, and could persist, though the
low voltage to earth in this part of the winding makes
OPENCiRCUii CIIARACTERISTIC ASSUMES NO VOLTAGE R B G U L A I O R A C ~ ~ O N
fault initiation less likely and fault current compara-
tively low.
FIG.6.82 Voltage lire oil rated toad ibrou,-oll
8.1 R o t o r t o r q u e lifc. Kesilits fvom inodeis do not scale accurately i i l t c i to take the creep beliaviour of aiu~niniulninto con- solational hoop strcss due to the rataiioll o f the
At a constant ioad (eicctricai output and generator at llic most exireme (anrl ti~c~.cfoie inust dan~agi,,!.) sideration at teinpeiatuies in excess of iOO"C, but ring. At rated speed and ovcispecd, tile strcss al
loisesi of P kM', tile torque (Nm) cxpericriccd at the stress, the lhiglily non-linear erfects or inalcrial daiiii, it is not usual for wedge temperatures to exceed this the shrink-fits may be less than tliat in the centre.
lol-bine-generator coul)iing is 95451' divided by (i/iain). ing ntust be considered. valuc (see Fif 6.85). Thcri- is also an axial stress due to the higher thermai
The coupling ii~iist be capable of tl-ansmitling the In tile UK, where ltigh speed rcclosurc is not ( l i ; ~ i . Pole
~.face wedees
~ - are much less stressed, and are expansion o f the copper in the end winding relative
to that o f the steel ring. As noted in Section 3.3 o f
torque associated with rated output continuously wit11- tised, sub-synchronoos resonance due to the use oi conimonly made of steel.
out deformation. Tliese couplings commonly have series capacitolr is nor a piobiern and the operaii~,~: The most inboard of the field lead wedges may this chapter, direct contact of the end disc onto the
four o f their bolts closely fitted into both coupling of the tranmiission system is under close conlrr>i. be unusually highly stressed because of thc extra CF shaft is not normal, since the flexure of the shaft
flanges, while the other bolts have smaller diameter it is tl~oughtthat the combination of very ltigh stresscs loading imposed on it by the section of connector would transmit a small alternating stress onto the
and a clearance in the coupling holes. The torque is and very low probability of occurrence results in ;nii leading into the winding. highly stressed ring which could promote crack pro-
transmitted partly through the fitted bolts and partly acceptable risk for rotors designed to conventioniil The shrink-fits of the end ring onto its seatings pagation by high cycle fatigue. Again, it is important
through friction between the flange faces. The full specifications, and that iifetilne monitoring is iloi on the rotor body and end disc reduce as speed that the stresses under all conditions are attalysed in
torque must also be transmitted tlirough the shaft justified. increases, and are greatest at standstill. There are detail, and this may necessitate a three-dimensional
end at the turbitie end, which must therefore be de- The exercise llas highlighted the need to avoid therefore large circumferential strains at the ends of finite elemeltt computation in order to ensure free-
signed to witl~slandit. stress raisers such as unnecessarily small radii, and t i , the rings, and carrespondingly high stresses, at stand- dom from high stress concentrations, particularly at
In the very much larger section of the rotor body, ensure a high quality surface finish. It has also drawl) still. As speed increases, the centrifugal force of the the sudden changes of section involved (see Fig 6.86).
shear stress due lo torque is very lnucll less than in attention to the need to design the generator to C A . rotor end windiilgs imposes a load and stress in the In the rotor conductor nearest the wedge, it is the
the shaft ends and is not of significant magnitude. citer coupling t o withstand torques of the order ol central part of the ring, which combine with the compressive stress produced by the centrifugal force
Also, the transmitted torque reduces in a linear man- the rated generator torque, since it has been sbowll
ner along the length of the rotor body, so that at tliat these can exist during tl.ansient conditions.
the exciter end, only the small torque required to The requirement for torque transnlission places :r
drive the rotating exciters (and any other coupled cquip- limit on the minimum diameter of the shaft and therefoi-r
ment) has to be transmitted, o f the journal. An acceptable compromise belwec,,
As ~notcdpreviously, during electrical faults, stator the higher loss associated with a large diameter and
currents of many times rated value occur, and these adequate hydrodynamic stability results in a bearlny
cause electrontagnetic torques of a similar magnitude. somewhat shorter than its diameter for these ratings.
The torque reaction at the turbine to generator cou- Bearing performance is described in Chapter 1.
pling and in the associated shafts depends, among
other things, on the ratio of inertias of the turbine
and generator rotors, but can also be several times
rated torque. The specification requiles that the shaft 8.2 S t r e s s due to c e n t r i f u g a l f o r c e
and coupling shall be designed to withstand stipulated All rotating components are subjected to stresses due
fault conditions, without failure, though not neces- to centrifugal forces, and are designed so that thc
sarily without permanent distortion of coinponetits yield stress o f the material exceeds the stress at over-
such as coupling bolts. It is not unknown for the speed by an adequate safety factor. Usually the com-
fitted coupling bolts to exhibit distortion after a severe ponents closest to the limit are the rotor teeth, rotoi
electrical fault. wedges, end rings and outermost winding conductors.
Materials subjected to repeated high stresses ea- The tensile stress in the rotor teeth was considered
hibit a lifefirne, during which damage is accumulated, as part of the rotor optimisation in Section 3 of this
and at the end of which failure occurs fairly rapidly. chapter. It is greatest at the tooth root, but will have
Much effort has been devoted to establishing models local concentrations at the wedge dovetail. There will
of turbine-generator shaft systems in order to be able also be a high local stress where the wedge transfers
ta predict their remaining 'life' (i.e., ability to with- the centrifugal force (CF) load of the slot into the
stand further faults), knowing the history of the faults tooth. Detailed finite element analysis is carried out
t o which they have already been subjected. This has to ensure that unacceptable stress concentrations are
been done analytically, knowing the torsional char- avoided. These stresses ate constant at constant speed,
acteristics of the rotor system, and computing the so that the only cyclic factor is the number of stop-
shaft torques due to postulated electrical transients. start cycles, which is relatively few ( < 10') over the
It was found that in the case of rapid reclosure of a lifetime of the machine. Thus crack propagation by
circuit-breaker following clearance of a faulty line, high cycle fatigue from this mechanism alone is not
the magnitude o f the peak of torque depends very of concern.
-
critically on the timing o f the instant of reclosure. Similar considerations apply to the slot wedges, in
This has also been demonstrated, during transient which the loading pattern is similar to that in a short
conditions, using values of stress obtained from strain beam in bending, uniformly loaded on its underside,
gauges fixed to the shafts. Devices which calculate and with built-in ends. Aluminium alloy wedges are
shaft torques from electrical inputs have also been commonly made from extruded sections, but have
used. the outermost layer (1 mm, or so) machined away
It is difficult t o relate measured or calculated torque where stresses are high, so that the properties of the
peaks accurately to damage caused, o r to remaining parent metal are fully realised. It would be necessary Fia. 6.85 Finite element mesh for tootli.wedge slier$ calculations
The generator Electrical a n d eieclromugnetic aspects
--
8.3 Alternatirig s t r e s s e s , i r e t t i n g t t n ~ i1;riiiji;is
One feature of this is ti~arthe rotor must usoaily he second increases the rcquiscd Siiix magnitude; both
A stationary color sags under its o w n \+'rif:i,~,i j r i i - i ~ ! ~
run down in speed before the changed vibratioii dis- increase saturation, the effects of whicli arc highiy
a compressive stress in tile ootermost i l i ~ c >( i i i i i , appears, wi~ent i l ~cycle can he repeated. non-linear (see Fig 6.87). Oric result o i this is that
top and at tile axial centrr of about 15 k4l';i. i + ; i t , Oncc the rotor is at speed and tempcratilre, it does overall iron losses will be higher than those calculated
a corresporiditig Lerisile stress at thc bottain i i l i l i i not tend to suffer froin high cycle effects. It is more for no-load conditions, and their distribution u'iil dif..
same magnitude. As the rotor rotates, eaoli l ' i i i ~ i I.,+ vulnerable to effects promoted by reiative mo\,ement, fcr. Anoti~eris that the calculation of the required
periences a coInpTessive/zero/tcnsilc~~er~~/cc~~i~~~t~~~, such as abrasion, when running at lower speeds and MMF (rotor current) required for any load condition
sive Stress cycle once per revolution. Sincr IS ~ t i i i i , ~jhile barring, when the cei~trifugai locking-up is cannot be accurately based on the simple phasoi-
operating at 3000 r/min accunlulates 1.5 x i(i" vyvlc; absent. diagram. Since the rotor is necessarily designed with
in a year, alternating stress due to bending l t t ~ , 1,. little margin, accurate calculation of the rotor current
be considered in the design. Tilough its msgliiltl,lt; needed for rated conditions is essential.
is small, it is superimposed otl the high steady sti.t.s.rcu
in the rotor and wedges identified above, and c;ul 8.5 N o i s e
mote the growth of cracks by high cycie fatig,itr. The generator rotor, with its fans, generates very
One source o f crack initiation may be frcttini:, l i
high noise energy at speed. The spectrum is wide, but
a once per cycie movement can occur, say at the ~:,,l,
contains peaks at frequencies related to the number
between two short slot wedges, the resultant loc;ilisi.d
of fan blades and siots.
damage may bc sufficient to intensify the local srii.;..
The other main sourcc of noise is generated by
field at a minute 'crack-tip', from wiiich the ; ~ i i i i
the stator corc when magnetically excited. As pre-
nating bending stress can propagate. Such featusus ;sir viously noted, the magnetic forces 'ovalisc' the stator
avoided wherever possible, and particularly oe;il i i i , core, causing vibration and noise at 100 Hz and niul-
axial centre uahere alternating bending stresses ;,$,. tiples. The main component of magnetic noise, how-
highest. The concepts of fracture mechanics arc iiri-,i ever, arises from distortions on a much smaller scale,
to study such crack tip stress intensification. that o f the magnetised iron crystals, in the pheno-
menon known as magneloslricrion, at 50 Hz and
multiples thereof.
The robust stator casing acts as an effective sound
8.4 'Slip-stick' o f rotor windings attenuator, and little can be achieved to reduce the
One effect not mentioned in Section 3.8 of this ciiap transmitted noise further, for example, by the acoustic
ter is the behaviour of the rotor winding during i t treatment of the inside surfaces. In practice, the major
loading cycle. The rotor is run up from cold, anti sources of high noise intensity tend to Occur in the
though the windings and rotor body are warmed thy driven components such as exciters, wldcli have fans
gas friction, there is iittle differential in thermal effect operating in air and no heavy steel surround. Some- t:ic 6.87 I'tux diitiibutioi~on load
at this stage. At speed, the winding conductors aic times the complete line of driven units is housed under
iocked together and to the wedge by the centrifug;li an acoustic cover to attenuate these sources. Access
force, unless an axiai force can overcame the frictioi, doors and windows must be provided, and these can
between them. reduce the effectiveness of the covers. A method previously used took as its basis the
When current is applied to the rotor winding, i t A sound power level o f 93 dBA is specified at simple no-load unsaturated phasor diagram, and de-
reaches a higher temperature than the rotor body, 1 m distant from the plant. Legislation map require fined a n imaginary reactance, the 'Potier' reactance,
and as the coefficient of thermal expansion of copper this to be reduced for new plant in the future. empirically derived, which was used to define a 'Potier'
is nearly twice that of steel, the conductors experience voltage drop, IX,, for the given ioad conditions. An
an axial force directed outwards from the axial centre. internal voltage required to overcome this voltage
As the differential temperature increases, the axial drop, the 'Polier voltage' was thus established. The
forces increase, until slippage occurs at a point where 9 Electrical and electromagnetic aspects MMF difference between the airgap and open-circuit
the build-up of axial force is able to overcome the characteristics at the 'Potier voltage' was then pha-
Some electrical and magnetic aspects of generators,
friction. Because the 'bottom' conductor experiences not previously considered, are dealt with in this section. sorially added to the unsaturated MMF phasor. In this
the least centrifugal load, it is most easily able to way, the increasing and non-linear effects o f sat-
overcome friction, and a shorter length of it remains uration were taken into consideration (see Fig 6.88).
FIG.6.86 End ring lug area - finite eiement mesh and frictionally-locked than those o f coils further up the Present methods use finite element calculations,
s1iess CO"1OUrS slot. Slippage in most windings appears to occur in 9.1 Flux distribution on load which can be reduced to two dimensions for the
small steps, apparently randomly, though possibly re- central part of the machine. Even so, the detailed
When, in previous sections, magnetic flux densities
peatably, so that the release o f the axial forces does geometry and non-linear magnetic characteristic make
have been mentioned, operation at rated voltage,
not result in sudden changes in vibration of sufficent the calculation complex.
of all the other conductors in the slot which is of no-load has been assumed, where the load angle is
magnitude to be significant. In some rotors, however, In the end regions, a three-dimensional approach
concern, particularly where the copper area is reduced zero and the rotor operates in the 'direct axis'. In
due to higher frictional restraints having to be over- practical load situations, the ioad angle is 40-50' is almost essential, although various schemes have
by ventilation grooves and slots. Some creeo of the....
copper may be observed at such slots after many years
. ~ ~
come, the release of much larger axial forces appears and the effective flux level must be large enough to been devised in which simplifications can be made.
to cause the bending moment to change significantly, overcome the leakage reactance voltage drop. The In addition to the difficulties already noted, the thick
in operation. resulting in a noticeable sudden change in vibration. first effect distorts the flux pattern markedly; the conducting plates in which non-linear eddy currents
545
I-llc geiicraror TIectri~aland electromaclnetic aspects
Chaptiif ti
content than that specified in BSS000, in \+,l,ich ccr- soiii-cc impedance, and can ciiculale significanl cur-
rain langes o f frequency arc more highly weighted rent through bearings, seals, erc., causing eventual
than others because of their cflcct (in the lransmission brcak-up of white-metalled surfaces.
system) on communications lines. This now rather oul- Voltages of the same frequency as the shaft-driven
dated concept is still accepted as an agreed and useful excitation lnacllines can be measured on the generator
crite~.ioti,since high harmonic levels can induce high shaft, but these arc capacitively coupled, have a high
local losses in parts of the generator, e.g., the rotor source impedance and will not sustain a large current.
surface. The steam turbine rotors may develop a voltage
In practice, harmonics arc generated by the con- due to the electrostatic action o f steam and water
nected loads, a recent trend being the even-order droplets on the blades, and one function of the shaft
harmonic requirements of equipment using thyristors. earthing brushes is to cnsure that this is discharged.
This must be supplied by the generators and must A phenomenon which has occurred (rarely) on tur-
therefore appear in the flux wave, causing rotor surface bines is that, where a rotor or rotors have a degree of
losses similar to those produced by unbalanced load oermanent magnetism and there are contacts of low
conditions. resistance between shaft and earth at suitable axially-
Rotor windings occasionally develop short-circuits separated locations, the small generated voltage can
between adjacent turns in a coil, and while this is not circulate a small current through the turbine casing,
usually of great concern, the difference in flux pat- which, in certain designs, can act as a partial 'turn'
tern from the two poles is detectable, using a small of a winding encircling the shaft. This then produces
flux coil mounted in the airgap. When the signal from an MMF and therefore a higher shaft voltage, the
one pole is offset against the signal from the other, whoie process building up until many thousands of
differences reveal any abnormality. Ailother method amocres circulate, causing damage at the contacts. It
which has been suggested uses the presence of second is therefore important to cnsure that deliberate con-
harmonics in the stator current, as noted above, but tacts, such as eartlnng brushes, have a resistance (say,
PIG. 6.88 l'oliei coiisiructioli foi on-toad excitation current
this has to be able to reject those imposed by the load 1 ohm) deliberately included in series, and that heavily
requircmcnts. magnetised shafts are de-magnetiscd (see Fig 6.24).
The residual magnetism of a generator rotor will
normally produce a voltage of several hundred volts
are induced, and other conducting components, must tance. If higher values are required than the 'natural' at speed, even without external excitation; and access
be included in the modelling. It has reached the design produces, the leakage reluctance can be re-
9.4 Magnetic pull to terminals, connections, etc., must not be allowed.
stage of refinement where detailed changes, say, in the duced by making the Slots narrower, and/or sinking
thickness of magnetic screens, can be modelled in them deeper into the core. Again, this is extravagant If the rotor is exactly centred in the bore of the sta-
order to optimise the design, and to indicate where and results in a larger design. tor, the magnetic pull between one pole of the rotor
potential llot spots may occur due to unwanted flux If lower values are required, it is not usually suf- and the stator will be exactly balanced by that o f
collcentrations. the other: If not centred, there will he an unbalanced 9.6 Field suppression
ficient to manipulate the slot geometry, and a mow
pull acting as an attractive force on the pole with If an eiectrical fault occurs in the generator, the
basic change to the design might be needed.
the smaller air gap. However, the air gap of these connections, or on the generator transformer, the
Using computer programs similar to those men- protection will act to trip the main circuit-breaker.
tioned in the previous section, more accurate repre- large machines is so large (80 to 130 mm), in order
9.2 Control and calculation of reactances to achieve the required synchronous reactance, that This will extinguish the stator current within one
sentation o f the reactances can be made, over the cycle of circuit-breaker operation but the flux cannot
The reactance of an inductive circuit determines its range of load conditions, than is possible by simple centring the rotor to a readily achievable accuracy
does not impose a magnetic pull at all comparable be reduced so quickly. In all except brushless ma-
voltage/current relationship. In a generator, different calculation.
with the gravitational force on the rotor. chines, a field circuit-breaker is connected in circuit
reactances are identified in order to model or de-
between the excitation source and the rotor winding.
scribe voltage (or flux)/current relationships under Similarly, the net axial magnetic force on the rotor
If this were to be opened, the instantaneous reduc-
different circumstances. is zero if it is axially centred in the stator, and this
tion in current would induce a large (several kV)
The synchronous reactance, Xd, relates the arma- 9.3 The cause and effect of harmonics is the condition normally achieved at rated load with
voltage in the rotor winding, with the risk of insulation
ture reaction MMF (proportional to stator current) to As explained earlier, stator winding distribution is the rotors at their normal temperatures. With the breakdown.
the MMF needed for rated flux in the air gap. For a designed to minimise the generation of harmonic volt- usual axial offset which occurs with the rotors cold, Instead, a field suppression resistor is inserted in
given design of machine, increasing the radial length ages and currents. the axial magnetic pull is only of the order of a few series with the rotor winding, the excitation source
o f the air gap proportionately reduces Xd and im- The stator winding is invariably star connected, so thousand Newtons and is not a significant additional circuit being opened subsequently. The resistor has
proves steady state stability. This results in a larger that triple harmonics cannot occur in the line voltage load on the thrust bearing. a n ohmic value o f 1 to 3 times that o f the winding,
outside diameter, and a higher rotor current at full o r current. Since one pole of the rotor is identical and reduces the current (and flux) rapidly, without
load. with the other, it cannot produce second-order flux imposing an excessive voltage. Thus the ability of the
The stator leakage reactance, X,, is not a specified harmonics, which would make the two halves of the flux to prolong the current in the fault is safely
quantity, and its value is a matter of economic design. flux wave dissimilar. The only harmonics of signi- 9.5 Shaft voltage and residual magnetism minimised.
The transient and sub-transient reactances, Xd' and ficant magnitude which will appear are those of order In brushless machines, direct suppression o f the
The production of a voltage (predominantly at 50 Hz)
Xd", are specified. They describe the flux/current rela- 5, 7, 11, 13, etc., with diminishing amplitudes, and from one end of the generator rotor to the other oc- rotor winding current is not possible. The exciter field
tionships during transient changes, and under these cir- those near to the rotor slot pitch, e.g., 41 and 43 current is rapidly reduced by the operation of the
curs because o f some asymmetry, either of the position
cumstances, the amount of flux encircling the sta- for a 42-pitch rotor slotting. The no-load rated volt- exciter field switch (this also applies in a non-brush-
of the rotor in the stator, or some difference in mag-
tor slots, rotor slots and end windings are of impor- age wave must not contain a greater total harmonic less machine), or by inversion of the thyristors, but
netic properties. This mechanism has a low effective
547
Operatiotial measurement, control, monitoring and prolecriol?
tile rotor clllreiit ihas an efrcctiveiy zcro Iesistaitcc ing, a iarge fault current a,ouid flow,, with dangel i l l 10 O p e r a t i o n a l m e a s u r e m e n t , c o n t r o i ,
wiriding surfaces, ,nay occur, particula~.iy whel.e the
llalli through the rotating diodes, and decays with thc maintenance opei.alor. It is considered prctrl m o n i t o r i n g and p r o t e c t i o n
seoii-conducting surface tieat~neiit layers becomc bro-
the rraloi-a1 time constant of llie ivinding (src Fig 6.89).
able not to apply ao earth, but to elislire that I I , , ken or damaged, but again this does not norlnalls M~~~ of these sirbjects have becli mentioned in pass-
operator is properiy clothed and is using special 1,; lead to breakdonan. Mucii more likely is ~nechaiiical i,,g. I,, this s e c t i ~ i i ,each group is consideied as a
sulated equipment. damage to the insulation by pieces of core pu11chi11g co.ol.dinated
9.7 V o l t a g e in t h e r o t o r winding which become delaciled, magnetic debris (which call
At rated load, the voltage required to circulate rated cut 'wormholes' into the end winding insuiation un-
rotor current is of the order of 500 V. During field der electromagnetic forces), and abrasion of packing
9.8 Stator winding i n s u l a t i o n blocks into insulation. For these reasons, insulation 10.1 R o u t i n e i n ~ t l ~ m e n t a t i ~ n
forcing, this may rise to almost twice this value for In normal operation, the highest voitage to eaitii
a few seconds. The rapid decay of current during field thicknesses have not been reduced to take advantage provisions vary between manufacturers and have chang-
occurs in the winding bar (and connection) at the hi(.li o f the superior electrical properties available with ed over thc but the following is representative.
suppression may possibly induce 1500 V briefly in voltage ('line') end o f each phasc. This amounts to
tile winding. During transient fault conditions, the modern insulation systems.
23.5/\13 = 13.5 kV (RMS) for the 660 MW uniis.
requirement o f maintaining the previous flux level may Considerable effort has been devoted to devising
Voltage to earth on the other conductor bars is i c . means of detecting signs o f insulation deterioration, 10.1.1 Temperature
cause large currents to be induced into the winding, duced through the winding to effectively zero at ti,?
with correspondingly high voltagcs (1500 V or so). for instance, by observing discharge activit)' in a ~ h ~ ~ , , , ~ c o u are
p l e sused to detect the temperature
neutral end. The eiectrical stress in the insulation
~~.~~~~~ i.
oermanently installed, capacitively coupled device, or in:
The highest voltages are likely to be appiied during riot high even on the line-end bars; all the bars arv
asynchronous operation, during which the induced by radio frequency aerials inside the casing; both
similarly insulated. Stator core - in teeth, back of teeth, core ends
alternating rotor current (at slip frequency) seeks to methods are still being developed. Discharge energy is
The system of insulation has to undergo searchin!: nrcdominantlv in the I MHz range, whereas corona and axial Cetltle.
reverse. This possibility is blocked by the excitation type tests before it is approved for general use, aaci ,~
~
diodes and high voltage peaks occur ( 2 2 0 0 0 V) at discharge, which also occurs, is predominantly at a 8 Core end plates and end plate screen - these are
even then, quality control tests on production bays
the sudden changes in current. higiiei frequency. Occasional 'fingerprint' measure- permitted to attain higher temperatures than the
include the destructive cutting up of two sacrificial
.
The winding insulation of a new rotor is finally ments can show, whether either activity is increasing core if not in contact with insulation.
bars per machine to ensure freedom from cavities i l i
tested at 3500 V, having withstood higher test voltages the insulation, among other quality checks. with time.
during manufacture. However, the arduous operating In operation, electromagnetic forces cause tile bars Similarly, an overall measure o f the insulation ~~d~~~~~ inlet to and outlet from coolers -
conditions may cause insulation to become physicaily to vibrate at 100 Hz in the slots and end windings, integrity of a whole phase can be gained by mo- to ailow averaging.
damaged, displaced, or just oily or dirty from con- nitoring the capacitative component of currcnt at
to an extent Limited by their restraining devices. 11' Stator winding, either one per slot or in water outlet
tamination, and such high voltages are less easily bars becomc loose in their slots due to relaxatioii various voltage levels, usually expressed as 'tan delta'
withstood in an older rotor. values.~~,i.e.., a measure o f (very
. . low) Dower factor. hose - basically to monitor water flow in in-
of ripple springs or wedges, the layers o f insulation ~ ~
When brushes are being changed with the generator Breakdown, however, is most likely to occur from dividual bars,
tape may become locally de-laminated, in spite of
on-load, it is common practice to ensure that the one local area of damage, as already noted, and the
the bonding resin. Electrical discharges can occur at Hydrogen seal faces - to detect rubbing, or oil
.
excitation control is on 'manual', so that the rotor such sites which might eventually lead to electrical poor results from this local area are swamped by the
starvation.
cannot be subjected to field forcing voltages, and to breakdown of the bar to earth. Fortunately, in a hy- better measurements of the rest, so that such methods
disconnect the earth fauit indication biasing voltage. drogen atmosphere, carbo~lisatianof the surfaces does are relatively insensitive. Stator frame, at C 0 2 inlet - to detect freezing.
It may be thought to be advantageous to earth the not occur as readily as it wouid in air, and brcak- Stator insulation withstands more than twice its
slipring being worked on deliberately, but if this were downs from this cause are uncommon. Discharge on rated line voltage, i.e., >2[J3 x maximum (phase)
Resislortce eleme,lls or other thennometers are used
.
done and an earth fault developed in the rotor wind- the bar surface, either in the slot, or across the end ooerati,te- .. and an insulation sample
stand at least twice this again, so there is a huge for:
safety margin on intact insulation, Even so, testing Water inlet and outlet temperat,lres in all water.
at high voltage is destructive, and repeat testing in cooling systems.
service is deprecated.
If an earth fault occurred at one of the phase o i l outlets from hearings and seals
ends, the voltage at the neutral would be elevated,
and that at the other ohase ends could rise to 43 x Seal oil at outlet from Cooler.
normal. This condition would persist for only a few
seconds, at most, before the protection acted to trip
r Hydrogen to and from cooler, as back-up to ther-
mocouples.
the unit and suppress the flux. In normal operation,
the maximum voltage a winding can attain is limited r An ohmmeter is used to display rotor winding
to about 35% above rated, for example, if rated temperature.
load were tripped, but again this would quickly be
suppressed. Temperatures are monitored during works tests
Surges arising from switching or other operations and during on-load commissioning, to ensure that
o n the system are greatly attenuated in the generator the specified limits have not been exceeded. The
transformer, and d o not pose a significant hazard to alarm level would normally be set above the high-
the generator winding. These large machines do not est temperature attained at rated load with the
have multi-turn coils, which are more at risk from warmest ambient conditions, but recent thoughts
surges. The surge withstand voltage is quoted at about are that this practice may miss early warnings of
85-90 kV, but surge withstand tests are never carried developing abnormalities. If a measured tempera-
FIG. 6.89 Field suppression circuits ture is related to other parameters, such as current
out.
548
lil olhei similar sigliali to scc tliiil its imaguili~tlc
i n llic cstal~lislicdscatlci paltcl-n is correct, by oiing s IExciialion voltage, cilirelit
a dcdicuted mici-o~)ioccssoi,a moie inlorinalive @ AVR indicalions (locally, on AVI: ganel).
indication can be lpiovided lo ihc opcratoi.
0 Diode faiiure.
e Seal oil (and thrust oil, if separate). 10.2 Logging and display
0 Vacuum in seal oil treatment lplartt (if used). Transducer outguts arc received as inputs to the com-
puter at intervals determined by consideration of what
event could have czused a signal different from nor-
Differential pressures are monitored between: mal, and in what time scale tllis could cause damage.
e llydrogen and stator winding water. Readings may be logged oniy when outside ihc normal
range or, alternatively, readings within the range may
0 Hydrogen and seal oil. be logged at intervals.
The most moderr1 stations display only the essen-
e Fan inlet and outiei. tial information coritinuousiy to the control room
operator. Some systems display 'by exception', i.e.,
when a parameter falls outside its expected range.
10.1.3 Flow
All information is available on demand, on VDU
Flow rates of the following are measured: screens or printc1.s.
iliemsel\,es. Wlien judgcd jointly, clues inay bc ob- wiiicli tile pliimbiiip atid insulated co~iocctioii<l i t i t ,
iaiiicd wliicii ii~dividualreatiiligs o~ighi inat have re- to witi~stsiid wit11 no detectable leakage. Siax~~Ir.,~.
/:
LAMINAill> RON COW
vealed. stecl ]pipes, with soine welds iiavilig Lo he n,:iciv i t , CONCRCii SiATOii
siiu, %,ere found to be necessary in the U1< expciieiwr
STATOR WtNDING
Neveilheless, watcl- cooling Lhc rotor windin: ; m i l t
other parts, for example, the stator core, may he ;ti! OUTER ROTOR
12 Future developments answer if unit ratings much above 1300 M W arc rii INNER ROTOR Wi'lii
SUPERCONDUCTING WiNDiNG
visaged. One difficulty, that of aqueous stress c o ~ VACUUM
rosion of rotor end rings, has been removed witli
12.1 Extension of present designs the advent o f 18/18 rings. A major advantage I\
that in an ail-water-cooled generator, hydrogen i \
The choice o f 3000 or 1500 r/min for future tuibioe- 1x0 longer necessary, and the casing cat1 be of rnucli
generators is made almost entirely from considerations lighter construction. The rotor can operate in a pariii~i
of the steam turbine and its steam cycle. In general, vacuum to reduce windage losses.
if a two-])ole generator can be designed and manu-
factured at a particular rating, then so can a four-
pole generator, its overall dimensions will be a little
larger. 12.3 Slotless generators
The present UK designs with water cooled stator
The very large radial dimension of the air gap in the
windings and llydroge~icooled stator core and rotor
660 MW design appears to be a waste of space, and
can be extended to at least 1300 MW by extrapola-
prompted much activity in the 1970s into the design
tion. Increases of the order o f 10% to the rotor and
o f generators with slotless stators and even slotless
casing diameters, electrical loading (ampere conductors rotors. lo s siotless stator, winding conductors oc-
per metre of circu~nference),magnetic densities and cupied a radial dimension of about half the stator slot
voltage, and pe~.haps25% on length over the pie-
depth, and since there were no teeth, could occupy
sent designs, would be envisaged (see Fig 6.3). The chines from a n established design acllieve a settled
twice the circumferential distance. This is economical At the higher flux densities envisaged, an iron core
increased diameter and length of the rotor result in reliability of better than 99%, and operate at an
on outer core diameter, and because the conductoi- offers no advantages and the disadvantage of the
the critical speeds and alternating bending stesses efficiency of better than 98.5%. Those breakdowns
bars are not embedded in iron slots, a more eco- magnetic core loss, so a cast 'concrete' core is en-
being similar to those of the present machines. A visaged. Some form of outer environmental screen which d o occur are generally due to lapses in qualit?
nomical design of insulation should be possible.
judgement would have to be made about the number around the core is necessary to prevent leakage flux control, or if in old machines, to practices long since
The idea has not been pursued, largely because
of parallel paths in the stator winding of a two-pole from inducing currents in support steelwork, etc., overtaken. Thus the impetus for embracing new ma-
it was overtakei~ by the superconducting generator
machine. If only two paths are used, the number terials and technologies is not great.
concept, which promised greater economies of size, this . . take
..... can ~~~ ~ the form of a n annular magnetic o r
of slots and bars is low, but the bar forces become conducting copper screen.
better efficiency and the prospect of much larger unit
very large; if four are used the circuits cannot be Many problems remain to be solved, and develop-
ratings than any other design.
exactly balanced, and circulating currents and losses ment is ongoing in several countries. If the technique
are generated. Parameters, such as reactances and cffi- reaches the stagc where reliability is as good as for 13 Other types of generator
ciencies, would not be very different from those of conventional machines, it offers the possibility of up Generators, other than the 500 and 660 MW turbine-
the present machines. generators and direct coupled AC exciters for tur-
12.4 Superconducting generators to 5000 MW in one generating unit, a prospect not
T h e phenomenon of superconductivity can be applied available through any other known technology. bine-generators, described in the ~ r e v i o u ssections, ill
to DC circuits, but cannot sensibly be used with the operation by the CEGB include:
.
12.2 Extension of water cooling rapidly changing fluxes and currents involved with
Turbine-generators of lower rating.
50 Hz (see Fig 6.95). It is therefore used only in the
Since water cooling has been used so effectively for 12.5 Auxiliary systems
rotor windings, where it has two advantages: Water turbine driven salient-pole synchronous
the stator winding, it may be wondered why it is not The most likely other areas for new developments
used in the rotor winding where space is at such generators.
The rotor I*R loss is reduced to zero are those o f instrumentation, control and diagnosis.
a premium. Water cooled rotor windings have been New tecllniques are continually being investigated Diesel engine driven salient-pole generators.
successfully operated; in the UK in a 500 MW unit The rotor current and MMF can be very large, so for instrumentation, and in the environment of a gen-
with a n experimental rotor for a few months, and that higher levels of flux density can be used than erator, the means of communicating the signal non- Induction generators.
internationally in a few units commercially. are permitted by iron saturation. electrically in order to avoid the pick-up of spurious
The more intensive cooling provided by water means electromagnetic signals and noise are very well worth
that smaller winding copper sections can be used, but A very brief survey of these groups follows
pursuing. Here, fibre optics are expected to be pro-
this increases the resistance and therefore the I ~ R The need to maintain the rotor winding at a tem- minent. Also, the use of microprocessors to relate one
loss. In a hydrogen cooled 660 MW rotor, this loss perature of 10 K means that only that amount of parameter to others, as previously noted, will become
is about 2.5 MW at rated load, so a worthwhile heat which can be removed by the refrigerant can more common. Perhaps automatic diagnostic tech- 13.1 Turbine-type generators of lower rating
reduction in section brings an expensive loss penalty. be allowed to pass into the rotor, so that elaborate niques will reach a stage where they can be used with Virtually all the steam turbine driven turbine-generators
There are difficult problems to be solved in feeding heat shields are necessary. Liquid helium is used as confidence, and selective recording of non-standard now in operation are hydrogen cooled. At the lower
the water into and out of the rotating rotor, but the the refrigerant, the windings being made of a ni- signals will be introduced more widely. end of the range, machines of 60 MW have a rated
major concern is that the centrifugal force imposes obium-tin alloy embedded in a copper matrix. The It should be recognised that generator design and pressure of 0.1 bar, i.e., just above atmospheric.
very high pressures (20 MPa) in the water circuit, rotor body is made from a stainless steel forging. manufacturing techniques are old-established. Ma- Above 200 MW, water cooled stator windings are used,
Otiiei types of generator
The aene!.stor cl>;?)>?,>l
1,
---
..
tbougli there are soiur onits i n irliicir l~iglier!pi-ersoic i'he coinpaiatively low speed incant large ditiiiictr! ...
lhydi-ogcn is biowt~thiongli the lhoiloa* candiictors aT and 081-silt asseinbly of tile slalois was es~c~iti;iI(w
the itator u,indiog. 1;ig 6.97). Air cooling was adopted, mainly S o ic;i
ill olllei respects, tbc geliciatois are \,cry silnilai sons of iciiabiiity. Paitl!, on account of illis. III,.
to tile larger, morc moderr, units, except tiiat tiicy aye stator ~rindingbars were unusually deep, \villi :I 1;iip
iess intensively rated. I n some cases, a degree of nuiuber of subconduclors, necessitaling a 540' l l o ~ ~ l ~ v l
refurbishment bas been carried out to extend their transposition. The core was stacked iri situ, being c o l i ~
operating lires beyond the 25 years or so already pressed with hydraulic jacks at intervals, and b a i ~ l c < l
achieved. logether for meciianicai stability
There are aiso a number o f gas turbine driven A fabricated steel spider surrounds the forged slrrl
generators intended for peak load arid synchronous shaft and carries the keyed-on laminated rim and polus.
compensation duty. These have ratings up to 70 MW, Great care was taken to ensure the integrity of liic
and are usually air cooled. The single-piece stators are welds, which are subjcct to a n uilusual amount 01'
o f lighter constriiction than is necessary in hydrogen cyclic stressing.
cooled units, and the auxiliary systems are minimal. Ventilation is provided by motor-driven fans blow-
In some cases they were designed for unmanned sta- ing cooled air onto the stator end windings top and
tions, so manual monitoring equipment and sophis- bottont, with some booster fans for thc centre of tlic
ticated logging is minimal. Brusl~less excitation is core. Water cooled beat exchangers are nlounted a1
universal, for reasons of minitnum maintenance, and the outside diameter of the core.
even the fuses protecting the excitation diodes have The thrust bearing has an arduous duty, having
been omitted. a load o f 510 tonnes and requiring larger thrusl
A noteworthy feature of the most recent of these pads, at the specific ioading, [ball had previously
units is the facility to disengage the prime mover, been used at the specific loading and speed. Each
or, in the case o f the Quad-Olympus units (Fig 6.96) pad rests 011 a 'mattress' of coiled springs, and is
ill which the generator is dl.iven at both ends, both arranged to pivot centrally to allow for rotation in
prime movers. Then, after a period of peak load gen- both directions. Lubrication is by oil bath and natu-
eration, the synchronous clutches are disengaged, leav- ral oil circulation, with an immersed water cooled
ing tile generators operating as synchronous compen- heat exchanger.
sators, with excitation controlled to suit the require-
ments of the system. When peak load or emergency
generation is next required, the gas turbines are run- 13.2.1 Excitation and control
up to speed and the clutches moved into engagement. Two variable-frequency starting equipments are pro-
vided for the station, each rated at 14.8 MVA, consist-
ing o f air cooled thyristor rectifier/AC connector/
inverter banks.
13.2 W a t e r t u r b i n e driven salient-pole s y n - On starling as a puinp, the stator winding is fed
c h r o n o u s generators with low frequency AC from the starter, using forced
Tilere are only a few of these on the CEGB system, commutation at speeds below 10% and natural con]-
but the most recent, the pumped-storage units at lnutation thereafter. It is run to just above 500 r/min
Dinorwig, rate a brief description to campienlent the and is synchronised as it runs down through syn-
water turbine section in Chapter 5. chronous speed. There are also arrangements for start-
The six generators are each rated at 330 MW, 0.95 ing one unit as a pump from another, being driven
power factor, 18 kV, 500 r/min, and have a motor up to speed by its turbine.
rating sligl~tlylower when operating in the reverse Excitation power is taken from the generator ter-
direction. minals, through a transformer to a thyristor bridge,
The very onerous requirements included: whose output is controlled by the AVR, and then to
the sliprings which are located at the top end of the
Full speed, no-load to full-load, in 10 s. rotor shaft.
From rest to full-load in 100 s. The synchronous operation of such machines fol-
lows very closely that of steam-driven turbine-gen-
From full-load pumping to full-load generating in erators. The electromagnetic Loading is considerably
90 s. less, leading to a smaller radial air gap. The very
different magnetic path presented by a pole centre
5000 stop/start cycles per year. line and an inter-pole gap results in marked differ-
hlultiple load cycling from 50% t o 100% for system ences in direct axis and quadrature axis synchronous
frequency regulation. reactances, compared t o a turbine-generator in which
they are almost identical; this is the 'saliency' effect.
Availability of 98% and mode change reliability of By applying excitation in the reverse direction t o
99%. normal, an increase in the steady state stability can
SUBJECT INDEX
Acceleration
leedbaek
aoverr~on.130
~ c c e p l i n c ecesir
cosdenscm.373
pm~edures.374
Acidcicaning
candeasers.372
AClUalOrpiStolls
governor valve ielnys, 145
Adiabntic now Wiih iric,io,,
pressure canlrol vr1vcs
noise. 21 1.216
Advanced gas-tooled rcacloli run-up, 134
iccdwatei Auxiliary sysieinr
fempcralaie. 46 generators. 559
sieanl luibirles i,,s,iumen,a,io,,. 174
sires, i22
Aii
inieakage
~ o ~ ~ d c ~ ~366
sers.
icskage lecdwaicliiesfers
mearuresies1.368 uenicnl. 301
leaks Baffles
locaion.367 d e - a c r ~ i i n g f c ~ d h c a 308
~e~~,
Air blailkeling lcedwaler lhcaiers. 297
co8ldcnSCrs.375 BRlancemeien
lubcncsls nittomatic voltage regulators, 525
colidessers, 352 Balelicing
rotors, 96.470
muili-olanc.97
dynamic. 97
Bars
Stators. 475.482
vibration
stator windings.548
Base level govcmois. 141
Rc.6.97 Dirlorwig ~nloroi-generatorduring site winding ~ icxtractjnn
r pumps Base load
(rce also colour piioiograpii between 1pp 482 and 483) condei,rers.378-390 neain iurbil,es. 217
A i r g r p flux coiis Baumann C X ~ ~ U S ~
gC""8,"'" binding. 68
moni,oring.552 Baumannexhausttuibines. 4
n,,,,,i,,g C"lli. 55
valiablo-speed-n?olo~.ddiiiii
~ * ~ i l costs.
R l 57
economics. 51
eificiilcy ">",lint COSIS, 57 ~ ~ ~ i - f ipianl.
r e d 46
Electrical cmsian ~ e suction
d Ivmps oii-iired piant. 46
i o u r , ~ bcnrisgi.
l 108 b ~ i l c r f e c dpumps. 412 ~rgen~r~!iuC. 242
Eleclricili lrijiping Feedwater ~c0no,"ic1.45
LUrbillc1~101cClioll,167 ~~n,al,,ina/i"l> Rnnkinecycic.?l
Eicciricii" dislribiiiinn
AC v; DC. 447
ccor1omics.41
Rsnki8iecycie. 28
pmiectio#~,
do-aeration.49
255,259,281 ua ~ .
. .. seam cvcic. 46
Fecdwacr hcnling cycle
Ele~lioinagnclicinductioil. 450 Steam cycle tcinperaluie CEGB, 33
Elli~)seiaw economics. 40 d rcacton. 46
a d u a ~ m gas ~ ~ ~ dlbeaiing
~ e plalil
e r
oufpul, 8 noain ,urbi,,es F~edwalelheaderS p~Oieciion qnipment. 260
Emergency siog heat ram.41 10," plCSBure ~ ~ ~ dlh~ating~ ~ systems.
t e r241-322
turbinepioteciios. 172 pmtcction, 164 flow area.311 design parameters. 250
Emergency ,tip valves ttips, 165 t~bcthicknessos.310.311 camnoncni loucls, 251
on-load resling, 166 unloaders. 137 ~Ii~lls
turbine prulcctioi~,166 unloadinggcai. 130 constmaion. 310
Elid " g r Exhaust rprny cwiing syscernr
mrara. 460 low presstire. 206-2W
End wi,,dings ~empeis~uree~r~cml
SlillOTS
suppon1,483
aucomsfic.207
Exhaust $team .~
...- .
parameters.26i
Enthaipy-entropy lliagrarns low pressure bled-neamin~cir,297 iiigh pmsruic feed system. 320
Rankinc cycle. 18 iernperature control. 207 %tiah Standards, 289 iow pi0SEUrC, 321
Blliopy. 18 Exiiausis c~ndenringsectionr,299 low feed s y s l m
Environment steam iurbitlc casings. 85 de.e-aoraling.305-308 iubulnisrlai-etype HP henlcrr.252
condelnseis.333-341 stesnl turbines, 4 de-aoraton, 289 water COnlOni
Eroriol~ Extenlal eificicncy mrimcnance. 253
biadcs. 75 cyiinders. 13 ~ ~ " i t si~iniess
ic imn
progression.76 E~llra"lionp","~s de;dopmeas;s3 bladillg
shieid nlatetials. 76 condensers. 4CU402 direct contact LP w ~ ~ n e aibincs,
an 229
CYCID~C SCpsralOrs con~ponentlove! diagram. 251 Ffe~fi,,iogpWCisladon
wet ~lcainturbines. 230 Fans drain cooling sections. 299.301 ,,~~pedslorage.433.414
hydraulic mrbines. 423 mt015.465.470 drains. 210 F ~ D~ I ~~ r r cmcasvrcnlclil
nt
pr0,ection
welstean Lurhines. 229
Fatigue nrrrc-~ .
~ m ,n l e t i o noowcr siriion. 241 ~ ~ e i ~ a tsystems.
ion 519
mlon eievstion, 254 Ficld lead wedges
Es~heleCRM12 generaton, 544 final feed tempoiaturer. 28 m,on
hiading.12 Fatiguecracking flooding. 51 generaton. 543
EVBIKIT~~O~S journal beatings. 108 flow-induced vibration, 296 ~ i o l suppression
d
bled-steam Fatigue strength ciain power station. 245 generators. 547
fccdwaler heaiingsystemr, 316 blading ~~~~h~~ 2 AGR power nation. 248 Filrni
nash.316
venicsl-Iktype. 316
ehrorniu~?l
Fault cunents
steels, 72 hi-h .
...- orosnuie. 46.51.289-305
con~t~eiion.292
icedwaier henling sysccins. 315-3 17 generalon. 539 hotizonLal. 299
aswmbly.319 Fced pumps t h ~ m ~dcsgn.
al 291
nasii back-pre~~urc lube thickness. 292
fecdu,;iler healing syrass. 319 Steam iisbiiies. 115 venieai.3Ol cooling water
nasiltype condensing-type I , , ~Rc power station. 244 ~ondenscm.372
lcedwarcr healing sysicnis. 317 sieall turbines. 116 ~ i t i l e b m o k Dpower nuion. 246 hyd*"iic nuids
singie-stage low pres~ure,51.308-314 governing systems. 151
feedwalci hcnlingsys$cms.318 bled-$team i"ltIS, 3 n ~ i n afeed
i temperamre
rurfnce cype cons~ruefion.3W reedwater huliinz sysccms. 250.261
feedwater heating systems. 317
Excilalion
. "
economies. 57
dircct mnuc1.314
dished ends, 314
AC turbine goncralon. 506 induction-mocoi-drivenm drain ou~lers.312.314
adaplivecontmllcn. 526 capita1FOSIS. 57 cxtemsl drain cmlcrs. 312
conuoi. 526 e&nomics, 5 1 hotizornal-at~itudemmgoment. 283
future dcvelapmenis, 560 runningcosts, 57 shellr.314
turbine gelicraion. 5 W 5 3 2 margins. 54 SUM type. 308
Excitationequipmcnr moio~dtiv~n thermal design, 312
stsic rceiificrs. 520 thermodynamic effeea. 56 lube lengths. 31 1
Excitation System$ number <ubesupponplatcs.311
analyiir.530 economic%.53 lube suppons, 31 1
brushless size low pressare direct conlacl, 289
turbine generators. 5W economics. 53 low pressure abed. 289
EXC~LCT field S W ~ L C ~ C S steam turbines, 115 on-~osdtest facilities. 269
field suppression, 547 lhmugh-iifccosts. 58 pipework. 273
Excilcrs (see air0 Main exciron: Pilot cxcifers) lurbinogovemon. 156 prOstu"red water reacton. 48.249
A C voltage regulation. 523 lurbincs shclls.292
DC lurbino gcnmors, 5 M exhaust mute. 156 t h t m a l efficioney. 22
DC veilage regulation. 523 power rating. 157 cube lengths, 295
gear driver steam supply. 156 tube suppons. 295
lurbino-genera~on.504 vatiahlc spcod,54 akplate-typc hatizonlal high prcnsurc. 52
porfomancc testing. 508 variable.spnddrives tubular surface type. 254
transiencperformancc capital costs, 55 component leveldiagram. 256
turbine-gcnoiarars.506 eloettic moton. 55 wat~~to-~~te~drain~~I~n
t
! Subject Index
i --- ---
Coiiilo1. 205
i'1asgei Furca
*,aceiiil~bilie dri\,cii saiie81i-jrrlc rysciwonour. 560
slcaii cu~biziccnrii~pr.82 blows
G i n ~ ~reiling
rl systems, 200. 201
1:1as1iil8 draill C W ~ ~ ~ s detector syi~enl.515. 516,519 ~ p r c s u coii!iol,
z 2W. 203
lo>%'I""6airC feedwaicilicnieri. 306, 312 fnilille
$lean, lurbiiici. 19820.1
Illcrmai Ihydiviilicdeiig~i.314 deiecliozi ii~,ic,52~ ,e,llper"luie Control, 200
Fl~xibilily TV 44R
Gland steam eondeaseli. 204
stcna,iuibi~?cs binding. 72
G i a n d ~(see also Labyiyiill gliindr)
dssigr~217 FV 507
boilci feed pv8llps
cfficicncy, 39 bladisg.72 realing.408
noiv slea~nfuibincr,i98
corldcnsen Governillg
n,eilsurcn,est. 374 eloeimnic. 134
gencratoir highprcrsure. 128
insirumentatioi~.550 higll pressurn plus intermedinie pressure. 128
nlCilSUmmCn, parallel. 128
cirnuialillg i$,siei puxaps, 397 Govemingrysiems. 125-157
curbir>cs combined-cyclcpla~>l.118 digilalpmcerring. 140
dircclian.2 Gassing-up
functioss. 125
Piuidcouplingsiilr hydrogen coalii8g systems inecllasicai
reed pumps turbine generators. 491 reliability. 134
Gearboxes
vaiivble spccd driver, 57 Steamturbines
Fluoie~cein air extraction pumps. 395 o u e i ~ p e dpmfecBo8i. 164
cooliiig wii,ei ciict~la~inp water pumps. 398 Govcrn~ivnlverelays.142
ieakngc. 369 iced pumps conlml aniciype I , 145. 146
Flux variable s p c d drives. 57 conlml unit i y p 2. 147. 148
S Y ~ C ~ ~ ~gencmtois.452
~ O Y S
Ocnersloi phnsoidiagrams, 535 colitml unittype 3, 149
Flux dislnbulion Generalom, 446-562
20MW Gov0n10rvalves. 160. 162
GCIIOTRIOrS ~~~~
forcer. 145
on ioad. 545 aircwled. 449 guidcdnow lypc. 161
Foaillisg 6MiMW.448
high preasurc
i"ilibifi0" Cescmlars (sea alsnQuad-Olympur gentraton: Synchronour on-load leriing. 132
labricarisgoils. 193 geocrators: Turbine-geserutors: W i r ~ dgenerators) ii,,crmedialeprers"rc
F0:oan,s condition monitoring. 550 on-load ssiing, 132
conim1.549-555
coaling water
fulvie dcvelopmcntr. 560 .
muslliwin ivoc. . 163
leakage. 369 pressure dm],. 8
Fo~ced-ai~cwli"~ DC, 114
revene now. 163
diagnosis. 555-558
main turbines. 224 throttling
Forging eEciency, 536
flenibiliry.222
,itanium elecl"c1 aspcct~,545-549 Oovemon (see also Basc levol govcrnorsj
blading, 73 ~ l e c ~ r mcasuremenl.
i~sl 550 acceleration feedback. 130
F o s ~ i l d i c dplan, cleeltically unbalanced co!~dlfions,537
characleristics. 126
by-pars ayslen>~.213 electmmagnclic aspmu. 545-549
failure
Fouling exciter and power systems, 527
pm,ection, l M
biolo~icsl charaelcrixics. 529 iilicr-valv~monilorin~. 137
cosdcnsers.370 fixed speed AC. 114 speed rnfercnee. 131
condensen, 370 fu~uredevelopmcnts.558-559
s p e d reipoinir, 129
Foundations induction.562
stcam ,"rhinos
CDDCrele. 177
iotscs. 536
nl~dulaia"angement, 157
iIexiblc.l76 mainici,ance, 555.558
turbincs
resonaiicer. 176 mccllanical c ~ ~ l ~ i d e r a f i o541.545
nr,
feedpumpr, 156
spring. 180 nlonitorinp, 549-555 ~ r a i power
n station
Steamarbiacs, 175...181 on-load mosiioring. 552 fcedheaten. 245
movcmcili. 175 Open-circuit eondilions. 533 Gmses(srenlsoLilhium-bascdgieascs: Silicolie-barad
operalion.532-541 ficcasesi
operational measurement, 549-555 types. 154 . -
lunisg. 176 ourages purity
Greasingsyslems
Fourier equation mainlcnance. 555 steam lrbines. 196 monitoring. 492
hcai transfer nmleciion.549JSs Gril cleaning safety. 497
ieassembly. 557 temneraturc
condensen.347 condensen. 373
Fracture appearance transillon temperature running up 10 speed. 532 Guidcvanes monitoting.492
saliea.poie Hydmgen c w l i n g
mion, 96 Dinowigpowei station. 443
Francis turbines. 422.426 diesel engines, 562 pumped storage.441 Slalors
end thrust. 426 shuuing down. 541 vriable windings,488
Freon 12 slollcs~.558 tempraturn
tabular turbines, 428
sir leak detection speclfiesions, 449 trips. 554
Gundrilling
~landards.449 turbine-genoraton.447.491
condensers, 368 water headen
Frequency responseanalysis SlOsdy shon-circuit eonditlons. 535 tubcplaos.263 Hydmgen embriltlement
exCilslion systems. 531 Steady slale stability, 534 mton. 94
Fretting superconducling. 558 Half-sped machines, 229 Hydmgen pressure
mton Synchmnising.533 goncraton
instrumenlaion. 550
Halagen lcak detectors
lemperature.536
air leaks
IcsIing.555-558 Hydmgen seals
condensem. 367
transformers generaton
Hand baring
winding fault^, 554 turning gcar, 1II lubricalingoii. 183
arbine-tvoe lubricatingoil, 188
Harmonics
lowoikting, 559 chorded windings. 455 HysLern~i~
lYpoS.447A50 dislribula windings.455 stator cores. 476
unbalanced load faults. 554
generaton. 546
Subject llidex
3 Index
rllrfis.456
shrink-on.91
sires. 472
1Prolecii081.508 ~ t e a n iiiibiner.
l 90105
tt~rbinegenciaiors,s06 rei,ea,e,s, 149
Reliability flexibiliCy.223
Seclio". 507 "oilagCS.547
Pillrlcdimtr PtlrliPa(rrea1soAiicxliaclion jpum~ls:Aiipuinps; Boiler feed govenlitigsystcms
deR81ition. 134 teetii
blader, 69 ipumi>s:Caisson enlraclin#?jptimps: Centrifugal
pumps: Cilemical irUeciion pumps: Circulaciilg steam lurbincr lensiieslrers.542
Piixwork Oer oiro hp pipeiuo,k) ihermai 96.456
icslisg. nnbilily.96
cmsrover. 163 wateii,umpr; Coiicreievoluic punips; coxidenrate eriiciency. 39
de-acraiors, 279 exiinclio~ipunins: Extiaciion pumb>s:~ c e punips;:
d Rclicivalvcs
rehcnlcis, 149 threading.470
feedwalei hcaiers. 273 Feed suction pumps: Fire pusps: llydravlic pumps:
Jnckizig oii pumps; Oil bwsrerpumps: Oil pasps; Residual inarnciism torque
fced~agrhealillgsyslem~, 271 g ~ n ~ ~ a t542
on.
govemingsys~ems Ptiming pumps; Rotary pumps): 323-421 shafts
C",,rlrnsrrr ?"P-?"n geneia,on, 547 turbine-generalois.456
sl~inlesss~ccI, 154 vibralion.470
Rerisiance elements
tow pressure feedwaicilieatiiig ryscems, 288 weight.472
leh~alers Icin~ialremOssuiemCni
gencra,ors. 549 windings.
welded disc,
459.463
91
pressure loss, 27
Piping Re~ollance~
foundations. 176 ~0il~.459
lubricatinpoii. 188 can18 faull indiealion. 553
Piston iinqs Revemible pilmp-iurbines. 433
Rigidity slip-stick. 5 M
sleamiurbir~ccnsiilgs, 85 lempcrntvremearurcmeni, 466
Pisloycs$ts foundalioss, 176
Rim generator turbines, 432 vollagc. 548
stators. 476.478
Radial ruppan padr dcsign.431 Routille operational tcsis
Pilch factor, 456
diaphmgms.70 R W I imus condensers. 373
Plantoperaiion
turbine-geneintors Rnnkiaecyclc, 17 cxcitation systems. 531
cosls, 42 finai feed t e i ~ l p c r a c ~28
,~~, Rotary pumps
Plan1trip c o n i r o l l ~ ~ superheat. 19 ilirexlracli~n
~ Y B B S ES Y S ~ S Reaciancer condcnscn. 381
generators Roiafmgan,plifcrr governing syslems. 125
nuclear plnni. 213 Runaway speed
Poie face wedger calcuiaiion. 546 OXCilCm
conlmi.546 lurbinc-geaorarors. 504 hydraulic lurbinas. 423
genoi~lon,543 Rvnncrbiadcs
Post-incident records ReeriSerequipnienr Rolalingdiodeiles
saiicdiodc~ excitation rystcmr tubularfurbiner.428
insImmcnta,ion. 17.5 Ru~liiihibifors
lubricafing0ils. I93
Powcigei~einfion exciinlion equipment, 521 moniforing.519
mechanicaldti~~ Reclificrs (reeniso Rolali~lgreciifien; ~ , ~ ~ i ~ RoLalingphs~~r~
SlOBln IUrbincs, 114 Thytislorieerifiers) 1yn~hmno~sgcncralors.452
cicilation systcms.516.517 Roiarins rectifiers Safety
network frequency hydmgcneooling. 497
pmieciion.52i exciladon
€ovcmingsysrems, 125 turbine-gonora~on.513 Scale
seain turbines. 112 SIali~lhy~~~~rs
excitation sysicms, 521 excitation systems condensers. 370
Power system osciliations, 527 cleanine 372
Power S Y S ~ slabiliscn.
C ~ 527 Rchcaf pmtecion, 519
Camotcyclc. 30 Rotom scavenging
operation. 529
COlidili~,,~ alignment, 103.470 hydmgen cwling Sysccms
Pre~suie
slcamcycie, 26 R~iaipasiii"" turbinc-genernloir.49 1
colidcnscm
dllllble inr,mmen,a,ion, 173 Scieeniogpianr
acceplance ~css.374 coolillg waicr, 324
generators Rankineeycie, 30 balancing. 96
fin,-stage body.456
insirumeniaiion. 550
Picsrure cascading wcl Steam lurbises, 237 bmshlers
second-siaec conncciions.469 Seal oil prcrrurc
feedheating.46 gcncrstom
Pie~~umcOntmi wetrteam turbincs. 238 buill.up. 91
Reheat cyclc. 20.26 eonstiuerion.90 inammcnta,ios, 550
hiiers. 129
CEOB, 33 cw1i,,g,93 Seal oil rvsems
Presnuie control valvcr .
r., ir,g:n :u np <,-,r, l.
Reheaters criIiealrpeds, 97
~ Y - P ~ Ssystems.
S 21 I l L n l c c )cn:rl.lr' $97
draills current iimilers. 526
nuclearplant. 212 S:A .e* ' 1 . L > b ) o n m % ? ~ l .
spraywater wet sleam turbines, 239 dmm type, 91
eCollDmic1.59 ondrings, 464 mechanicai
fossil-fired plant, 215 h i l e r feed pumps. 41 l
Pres~u"~ed waterreae~o~ governing vaives. 128 fans. 465
pipework fast fraaure mfon.472
feed pumpsets. 416 ~ ~
steatntuaines, 198
feed SySIemS PrCSSUrelols.27 tisk assessment. 98
Pressure loss. 27 gcnerafors seasans
cycledotails, 242 cooling water
feedhealors. 249 reliCf V B ~ O S 149
. maintenance. 556
s t e m Supply residual magnetism. 547 temperaarc. 44
hedwatcr hesten. 48 Secondary ioss
seam cyclcn. 33 we1 sleam turbines, 237 high presSU'e
Stcam-to-steal,, ma~erials.94 blader
turbine-gencnton.40 efficiency. I 2
we, s t e m cycle. 46 peifamance monitoring. 239 ~ l r c ~ s m n t m129
i.
high tcmperarure operation. 92 Sclf-shifting Synchmnouscl~l~he~
w c l s l e m plant. 62 wet steam turbines. 233
valve$ inlcgral. 99 cuming gear
Ptimingpumps Steam turbines
lubrication. 185 PTDSEure IOSS. 27 inlemedialcoreseure
venics1 Semicondu~ton
Proflie 109s
wet steam turbincs, 233 static recliiicn
blader
Rchcaiing cxcitationcquipmont.520
efficiency, 12 Se~aralon(see also Cvelane seDaralon)
Roleciion steam tuaines
candoasen.366 effrcioncy. 114
Pmtcction and conlml equipment Rohcafingplant
double-scage, 37 cormgated-piarc
inrmmentation, 175 wet steam turbines. 232
single-stage. 37
drains
t
I -
Subject Index
Strbjed Index
Power Station
Practice
Third Edition incorporating Modern Power System Practice
Ail volumes are devoted to specific subject areas, and have been
written by authors who are recognized authorities in their speciality
fields. Since the pubiication of the previous edition in 1971, much
experience has been gained by the Central Electricity Generating
Board throughthecommissioningof its large modern power stations;
in addition, the wider issues of power transmission and system
operation had not been previously addressed. The scope oflhis new
eoll on nastncrefore been cons ocrab ) enhancba b) rnree aod11onal
i o .mes Srar,on Commrss on no. EHV Transm seon ang Svsrem
Operation. A completely up-to&te treatment of theoretical and
practical aspects is compiemented by thousands of illustrations:
innovative fiow diagrams, coiour and black-and.white plates, and
detailed cut-away drawings.The coverage throughout is comprehen-
sive and clear, ensuring that engineers and technicians will gain
maximum benefit from the wealth of information provided.
1-he steam turhino Chapter 1 1-urbine casings
and additio~~allyfioiii either tlic i P turbine or the ;ti law tcrnpcratores) and casiel- la weld Casings in reaction froin tile rotor into the foundations. In some
boiler fced pump turbine, lo current practice, steal11 tliese materaais arc cast rather than fabiicatcd be- cases, the paws are part of the lower half casing as
is not hied from the H P turbine except at the ex- c;iose of the difficuli), oI quality control and like- illustrated, alternatively they may be part of the upper
haust, although iutuie designs with higher final feed Iiiiood ol' thermal distortion in the thick sections half, simplifying the casting but necessitating tem-
teinperatuies ma), blecd steam from the later HI' ii,volved. I..P cylinder casings arc generally fabiicatcd porary supports for the lowci half casing when the
cylinder stages. I i o m carbon steel, although the inner cylinder may be halves are unbolted. Vertical guides on the vertical
In L P cylinders (Fig 1.96), the steam is bled-off ctist from spheroidal graphite iron. Large defects in centreline of the rotor act in conjunction with sliding
into annular belts within the fabricated inner casing ofistings are ground out and repaired by welding, but at the paw faces to ensure that the outer casing re-
from which it is piped to the feedhcaters, bellows iicvertheless the materials are chosen to have a high mains concentric with the bearing pedestal and rotor
being used to take up differential expansions between tolerance to the presence of defects u,hich may grow during expansion. Similar arrangements support the
inner and outer cylinders. The connection to the hled- diiring service. inner casing inside the outer, with paw supports on
steam belt is usually made at the bottom; if made High temperature bolts are either made from low either side to take the weight and torque reaction,
elsewhere, a drain connection must be provided at itlloy steels designed specially for creep-resistant bolt- radial keys in the plane of the steam inlets permitting
the bottom. The bled-steam connections are identical ing, for example, Durehete 1055, or from nickel alloys concentric expansion only, and axial keys at the ex-
in each half of the double-flow L P cylinder so that hiicli as Nimonic 80A. The nickel alloys are more haust end allowing for differential axial expansions.
changes in steam flow to the heater do not affect <creep-resistail1and stronger, allowing a tiore compact The paw supports o f the outer casings contain trans-
the thrust forces on the rotor. However, the connec- $ fiange with better thermal properties; however, they verse keys so that the H P and I P casings and bearing
tions may not be the same on all L P cylinders on 8 ilic cub~ectto stress corrosion crackme. .~ . a r t ~ c u l a r lifv blocks expand axially as one unit away from a fixed
a unit. If, for instance, bled-steam is required at wct or contaminated with sulphur compounds. Nickel point between IP and L P cylinders. The axial location
stage 2, stage 3 and stage 4 conditions, it may be alloy bolts are thus used mainly on inner cylinders between the rotor and the casings is at the thrust
taken from each stage on each cylinder, or it may \!,Itere the compact flange is most advantagcaus. bearing between H P and I P cylinders: this arrangement
be taken from stage 2 on one cylinder, stagc 3 on ).ow temperature bolts on L P casings are made ensures that the close clearances between fixed and
another and stage 4 on the third (for a three L P S ~ o ~normal
ii high tensile bolting steels. moving blades in these cylinders are affected as little
cylinder machine). The latter method involves sim- Iligh temperature wet steam is considerably more as possible by differential axial expansion between
pler pipework but has the pcnalty of less interchange- crosive than dry steam, consequently H P casings for rotor and casing on start-up and shutdown.
ability of spares bet\\,een the cylinders. Usual practice wet steam machines are either made from 2.25Cr
is to favour the arrangement requiring minimum spares iMo steel with stainless steel cladding at the joint
holdings. laces or entirely from a higher alloy steel. 6.5.2 LP cylinder s u p p o r t s
I P cylinders usually only have one stage of bled-
steam from within the cylinder, although it may also The L P cylinder casings are supported on feet in
be taken from the IP exhaust. a similar manner to the H P and I P casings, but
On double-casing cylinders, the steam may be bled because o f their relationship with the condenser they
are limited in axial movement. Consequently they are
between the inner casing and a carrier ring, o r be-
FIG. I I W Inlet pipe piston rings
Tile piston rings shown iiere, real between the inlet pipe tween carrier rings, into a belt between the ring and
pr I'ri achieve maximum efficiency in a steam turbine, either joined together and fixed axially to the foun-
and t l ~ eHP barrei and the itil>ci casings in a triple-caiilig the outer casing. On single-casing IP turbines thc tlttly small clearances are permitted between fixed and dation at the centre or each fixed individually at one
H P turbine 'Outspringing' rings are riiowl~between tile end. This causes larger differential axial expansion
bled-steam belt is cast into the casing, with slots cut choving parts at casing and diaphragm glands, and at
nine and !lie barrel casing, and ,stacked' rings belwceo
to allow the steam to bleed from the main steam i
# lili~ilutip seals. These clearances must be maintained
between rotor and casing than in the other cylinders,
file pipe and iliner caring.
ilndcr all operating conditions, so the inner and outer so the axial clearances are greater.
path into the belt. The bled-steam pipcwork can then
Diaphragms and carrier rings are located axially
simply be bolted to the outer casing. Many 1P cyl- . n ctirii~gsmust be supported in such a way as to main-
within cylinders by circumferential grooves in the
6.3.5 LP cylinders
inders have no bled-steam tappings, as steam is taken . .
ciiiii concentricitv with the rotor as thev exnand and
casings. They are maintained concentric with the cas-
from the boiler feed pump turbine instead; however, ~o~ltiact.
ing by radial keys at the horizontal and vertical
Steam connections to L P casings are made with bel- latest practice with development of variable-speed 'Ihe total axral exnanslon o f a 500 MW turbine
centrelines.
lows pieces to accommodate differential expansions. electric drives, is for electric boiler feed pumps and lor between cold and hot conditions is about 50
The bellows are short sections of pipe with thin hence bled-steam is taken from the 1P cylinder. ~ n ,occurring mainly in the H P and IP cylinders, - are all aliened
The casings - bv reference to the
re the temperature change is greatest. The casings horizontal and vertical centrelines of the rotor at each
corrugated walls, allowing relative movements of the Steam bled from H P turbines in the future is likely
supported to allow axial expansion and yet main- bearing. The alignment of the rotor itself is discussed
ends in both longitudinal and transverse directions. to be via a belt cast into the inner cylinder wall, with
I the axial clearances between fixed and moving in section 7.5 of this chapter.
With underslung condensers, a rigid bolted joint can connections similar to the H P inlet connections.
be used between the L P outer casing and the con- rles which may be only a few millimetres. Main-
denser, the condenser being mounted on springs to ,ling both concentricity and correct axial expansion
support its weight but allowing the required flexi- to a complicated system o f sliding supports and
bility. Bellows can be used on the exhausts with a 6.6 Casing and diaphragm glands
floor-mounted condenser but are inconvenient because 6.4 Casing materials Glands are used to provide a steam seal between
o f the large area o f the exhausts and because the H P and IP casings, where temperatures over 350'C fixed and rotating parts of the turbine: in particular,
bellows, being flexible, transfer the vacuum forces to are encountered, are made from creep-resistant ma- .I HP a n d IP cylinder s u p p o r t s between the rotor and the diaphragms and between
the cylinder and condenser foundations. terials. Two different low alloy steels are used; 2.25C1' alld IP cylinders are fitted with 'paw' supports the rotor and the cylinder casing. The glands are of
IMo for temperatures up to 538'C and 0.5Cr 0.5Mo rilcll end which rest on the bearing pedestals (Fig the labyrinth type, consisting of a series of fins on
0.25V for temperatures up to 565'C. The 2.25Cr 02). The paws are horizontal with the palms aligned the inside of the diaphragm o r casing in close proxi-
6.3.6 Bled-steam c o n n e c t i o n s material is slightly weaker and more ductile in creep, 11 lhe horizontal joint; they are well spaced towards mity to the rotor surface. Steam trying to escape
Steam for feedheating is bled from the L P turbines but it is also tougher (i.e., less prone to fast fracture ollter edges of the casing, as they carry the torque between the fins and the rotor suffers a series of
The stearn turbine Chapter I
*8: Turbine c s s i ~ l $ j n
:.s
? ~,
,b r $ ,.,..
'
v,.
s
g
RRACKET
1I ExHliusi
WE,.
HALF 8 HRLI'
CKER
LINER
I FOllNDAilON '
STEELWORK
.. KEY
/I BEARING KEEP
( k l LP frame centre gulde key (I1 IP Cylrnder centre gulde key t o LP frame
I
BEARING KEEP
LOCATCON BLOCK
ANTI-FRICTION
PLATE
LOCKING
PLATE
SQUARE KEY ANTI-FRICI3ON
BEARING PLATE
LOCATiON BLOCK
REARING
BEARING KEEP (91 IP Cylinder palm (LP end) ( m l HP and IP Cylinder palms ("1 HP Cylinder palm
I'iC. 1.101 S~pportand alignment keys for outcr HP. IP and LP casings Fic. 1.101 (eonr'd) Support and alignment keys for outer HP, IP and LP casings
88
The steam turbine Turbine rotors and couplings
l'lie insulation consists of up to 150 Illin tl m Dru,?, ty/)e rolor inanufactured from solid or hollo\r
of mineral fibrc which is applied either a s forgings (Fig 1.104 (c) and 1.104 (d)).
'mattresses' or sprayed on as loose fibres, !
s The welded disc l a l o r (Fig 1.104 (e)). These rotors
I y dependent oil thc temperature of the sl are not too common in the UK, where they have
be covered, enough insulation being used to been applied to LP turbine rotors. Overseas ap-
thc outside temperature to about 50°C. Asbesloa \ plications have included H P and IP turbine rotors.
used extensively for sprayed insulation in the
but all modern insulation is asbestos-free, becai
the health risk of inhaled asbestos fibres. For various reasons, monobloc forgings are preferred
The mineral fibre is held in position by wire 1110 but where the size has exceeded the forging capa-
which covers it and is attached to studs welded bility, the built-up disc construction has been used.
the outer casine and vassing out through the mini31 The current 660 MW UK designs all have monobloc
rotor forgings.
TIC, 1.102 Derail of support for HP and IF ouicr casilis Built-up rotors required very careful attention to
wire mesh support between them. The outsidc wit shrink fit and location geometries to avoid problems
mesh is then covered with 6-8 mm of cemenl in running and with fatigue cracking. While the discs
lowed by a thin coat of oilproof and watl may have facilitated non-destructive testing (NDT),
expansions which reduces its pressure in stages and sealant. A glass reinforced plastic may be uscii the NDT capability on monobloc rotors has been
restricts the flow through the gland. A detailed ex- the sealant to provide suitable mechanical slrclr developed to meet all the needs. With the monobloc
planation of the %,orking of glands and the different and life. method of construction, the L P rotors are more rigid,
types is given in Chapter 2. The insulation extends over the horizontal resulting in better dynamic behaviour. 660 MW plant
The H P cylinder has glands at both ends of the covering the bolt heads and has to be chippe employs rotors o f this construction almost enclusively,
outer casing and the inlet end of the inner casing before the casings can be separated: the joint rci andexperience has been good.
(Fig 1.92). They are housed in gland carriers, which on reassembly. It was the practice to provide test material from a
are supported either on keys to allow differential ex- It is essential that oil is not allowed to en1 bore-hole down the forging axis but, as confidence
pansion or simply on spigots in machined recesses in forging practice and material properties has in-
in the casing. -- - creased, the central bore has been omitted on some
The H P glands are longer than those in other severe turbine fires.
current designs. The benefit of reduced stress levels
cylinders because of the higher pressure drop required gives enhanced confidence in the longer-term fatigue
across the gland, and are often divided into several integrity of the rotor.
sections. The IP glands are similarly supported (Fig Welded rotor construction has the advantage of
1.94), but the L P glands may differ; if the bearings 7 Turbine rotors and couplings smaller forging components at the expense of high
are separate from the L P outer casing, then the L P integrity welding. The welded design, having been
gland carriers may be supported from the bearings adopted by countries lacking an intrinsic large forging
and connected to the rest of the casing by a bellows 7.1 Types of rotor construction capability, has been successfully applied by them to
piece (Fig 1.96). Four different types of rotor construction havc H P , I P and LP rotors. There are a limited number
The LP glands prevent air entering the cylinder, used on large turbine-generator units on the of welded L P rotors in service in the UK.
>.3;z
unlike the H P and I P glands which prevent steam system: ,$ High temperature drum-type rotors, manufactured
escaping. Thus the L P glands need a continuous sup- from hollow cylinders bolted to stub shafts, have
ply o f higher pressure steam, whereas the H P and 1P The monobloc or integral rotor, in which the WIIUP@
been prone to differential creep and have been re-
glands need additional steam only at start-up. This and shaft are formed from a single-piece f o r y i d
placed by monobloc drum rotors in current designs.
is explained in detail in Chapter 2. (Fig 1.104 (a)). &. ..fg Where constraints on last-stage blading design dic-
The gland carriers are split, like casings, along the tate, double-flow cylinders replace the single-flow
horizontal centreline and bolted together. TUR8INECYLIN design as used in the H P turbine. Double-flow I P
and L P turbines are standard for 660 MW designs.
With the single-flow H P turbine, the axial thrust has
to be balanced to some extent by a 'balance piston'
6.7 Lagging SELFSETT~NGCEMENT
RE~NFORCEDWITH
to reduce thrust bearing loads: for reaction turbines
The hot external surfaces of the cylinders are lagged, particularly (with a high pressure drop across the
INSULA7ION RETENTION moving blades) the balance piston is of substantial
i.e., covered with a thick layer of thermal insulation.
There are several reasons for this: proportions, as shown on Fig 1.105.
In contrast, a n H P turbine rotor with impulse blad-
ing is illustrated on Fig 1.106. This arrangement is
The loss of heat from the steam is reduced.
characterised by the reduced number of blading stages
The thermal stresses in the outer casing are sub- and larger blading pitch diameter compared with the
stantially reduced. reaction design. In addition, a very much reduced
balance piston is necessary, as the axial thrusts are
Danger to personnel is reduced TIG 1 103 Thermal lnsulatlon on tuiblne caslns 4 lower.
91
The steam turbine
1 3 , due to creep. The shutdown or load reduc- same steam temperature at the inlet as HP rotors
$1'111 Sillill follows, causes cooling of the rotor surface and, because o f their larger diameters, are subject to
equently tensile thermafstress in the surface larger centrifugal stresses. The bore of an 1P rotor
7.1.1 Design f o r high t e m p e r a t u r e operation operation, due to the cyclic reversals of thermal stre
1e stress-strain condition at the concentration under tile first few stages is therefore a criticai region
The increase in size of large turbines over recent resulting from the transient temperature gradients
Ows the line 3 - 4 with possibly some further for creep.
years, together with the higher steam inlet conditions tabiished during tlle heating and cooling periods. tension, at 4. As the rotor temperature On large machines operating with reheat steam at
often used, has made the design of turbine components thermal fatigue problem is accentuated by the incre llius more uniform at the part-load or shutdown 565'C, forced cooling of the rotor by cooler steam
in contact with high temperature steam more critical. scantlings on larger machines which result in high ilioll, the material stress-strain moves along the is employed. This method is particularly effective in
Fundamental considerations include creeu and thermal thermal stresses occurring within components durin 4 5 to point 5. At this point, the rotor tem- cooling the bore under the first wheel (Fig 1.109);
fatigue, both requiring control of the temperature transient conditions. Illre will generally be too low for significant creep with further increases in turbine size, additional cool-
distribution in components during steady and transient The inlet sections of H P and 1P rotors are t1 or and there is no stress relaxation, such as ing is needed to cool the bore o f the second wheel.
operation. At the design stage of high temperature critical areas for thermal fatigue, demanding caref d between 2 and 3. This can be effectively provided by introducing a sec-
turbine components, temperatures and thermal stresses attention to design detail and operational practices en the material at the point of strain concen- ond cooling steam flow between the first two stages,
are assessed to ensure that creep, which occurs as a A typical cycle of events undergone by material 1 is held at reasonably high stress (point 3), SO that gland leakage steam is replaced by cooler
function of time, temperature and stress levels d o the critical region of a turbine rotor is illustrated is a damaging effect o f the hold-time due to steam.
not exceed specified values and that thermal stresses Fig 1.107. The material undergoes plastic strain col rsibie creep strain. The effect of this is shown
due to cyclic operation are not of sufficient magni- pression during the heating period to point 1 on t
tude to cause thermal fatigue during the life of the diagram, at which point the thermal stress has reached lermal fatigue, which shows as surface cracks,
turbine. its maximum value. The stress then falls as the tern. occur when there is a net amount of plastic strain
Creep can be limited by close attention to detailed uerature o f the rotor interior increases towards that - . .
llic thermal cycle. Material wooertv curves are ~ ~ ~
7.2 Rotor materials
geometry in critical areas, such as blade fastenings, of the surface, causing the stress and strain at tlle Ived for combinations of plastic strain range, num- Developments in the field o f steam turbine design
in order that stress-concentrating features are con- stress concentration to move along the line 1-2. At of thermal cycles and hoid-time at the peak o f would not have been possible without corresponding
trolled. Rotor stresses generally are kept low in re- point 2, the nominal thermal stress is virtually z Icnsile part of the cycle. materials developments. The development of alloys
lation to the high temperature mechanical properties and stress at the concentration is the residual stre with properties which provide good creep-resistance
of the creep-resisting steels employed. arising from the plasticity which occurred at 1. Durin at high temperature and o f other alloys with good
Thermal fatigue is associated with changes in op- the period of full-load running, the temperature Cooling o f IP rotors mechanical and high fracture toughness has been one
erating conditions, such as occur during two-shift the rotor is such that this residual stress relaxes t IP rotors o f reheat turbines are subject to the area of considerable metallurgical accomplishment.
a
:t
f:
1
The steam turbine
I)/
IWIELIT~MEI
- - .- - - ... - - -.
!
I
I
I
I
I
i
sTc,A,,4""",,,<;
"NiOhOlNG
wlicrc E = creep strain
Typical
steel,
rupture
o = stress, ~ / r n m ~
t = time, 7
T
Typically,
on a creep
and
-
are
absolute temperature, K
n , m and B are materiai constants
curves
high
strain
show
shown
of
temperature
of
the
time
on
0.2%
powerful
Fig
to during
1.110
produce
turbine
effect
for
ofMo
stress
strain
operation.
the bore, the stresses are sucll that steam cooling may
rotor
and
8g
g
%
!i.
.. .,.
0,
10
10.
kI
two stages of the IP turbine are offset by increased tion was the accepted approach to non-destructive
STRA1NOURINCI
bore stress due to the longer blade length, which examination of the rotor forging whose simple geo-
demands an adequately high proof strength. metry, in the rough machined state, permits accurate
The requirement for good creep strength and the location and diagnosis of any internal defects pro-
mi*csrannaC~Y~ necessary proof strength in conjunction with a rotor ducing ultrasonic indications. Ultrasonic techniques allow
forging of heavy section is achieved on current rotors the material in the vicinity of the bore hole,
~ic.1.107 Typical stress-strain cycle at romr surface
by the use of 1Cr 1Mo 0.25V steel alloy. -
which is subjected to the hiehest taneentiai stresses
iluring overspeed, to be examined critically. This pro-
vides reassurance of integrity in circumstances where
7.2.2 LP rotors the compiex geometry of tile machined rotor prohibits
Also, the ability to produce components for use both For low temperature rotors, the main requirements the use of external examination.
at high and low temperatures, having large physical are relatively high tensile strength combined with high The purpose of the bore was to permit internal
size and uniform material properties which meet ri- toughness. inspection, but it also removed some of the central
gorous inherent defect acceptance requirements, testi- The 3.5Ni Cr Mo V monobloc rotor forging is Part of the forging which is where defects or segre-
fies to the improvements in steel-making techniques. currently used as it avoids the complication of shrink gation in the original ingot might be located and
fits in the case of built-up rotors. The manufactur- Provided the opportunity to obtain fracture appear-
ing facilities and forging technology required for the ance transition temperature measurements.
7.2.1 HP and IP rotors manufacture of monobloc rotor forgings of very large Inspection techniques have now developed to the
size and weight are fully able to meet the designers extent where external ultrasonics can replace the former
High temverature rotors are required to have a com- bore inspection. This is very significant as the LP
bination of creep strength, rupture strength and duc- requirements. No limitations are identified for the
forgings of 2-pole 900 MW units currently under rotor is subjected to high centrifugal stresses, the
tility. This is conferred by rotors manufactured from
consideration. last-stage disc being the most heavily stressed part of
forged Chromium Molybdenum Vanadium steel (Cr the turbine. The centrifugal load of the large rotating
Mo V), a ferritic material which provides the best The use of vacuum degassed ingots, single and l i ( i 1.109 .The effccr of coolill8 steam lemperatuie on !he
double upsetting procedures and the use of larger lnaximum 1P roloi bore temperature under the first disc blades sets up a tensile stress in the rim of the disc,
posaible creep properties. Creep is a high temperature and this stress increases with decreasing radius, its
phenomenon and traditional design methods involve presses capable of such forging operations, have all
contributed to a marked improvement in quality of maximum value being at the hub. The larger the bore
the selection of materials which provide the required Of the hub, the larger the maximum stress. If the
creep strength and creep rupture ductility during the large L P rotor forgings. Rotor forging for 660 MW
$uod fracture toughness. Ultrasonic inspection techni- bore is small, the hoop stresses are iessened.
designs of 100 tonne forged weight, produced from
required design life. 11um enense freedom from any internal discontinuities Ni Cr Mo V steel containing up to 3.5% Ni has
ingots twice this size, are provided for LP rotors.
&rc;itcr than 5 mm effective diameter. been used for both shafts and discs for built-up LP rotors
Vacuum degassing has eradicated the former pro-
The parallel application of visual and magnetic in- and is the first choice to achieve the tensile properties
The equation for creep is of the form E = o"t"'~-'/~ blems of hydrogen embrittlement cracking and gives
94
The steam turbine Chapter 1 .# . ., .,.
Turbine rotors and c u u ~ l l i n i ~ s
- fj
provides tile necessary f i a m c ~ ~ ~foi.
o f 1.P turbines.
o i hthc safe operati<>ri 8 ,sr,,tii.
jirwii
h ~ i l c nincaris
~ ~ tliat the u,cight is cvcnly dis..
;i~r,tiodthc axis o f the shaft. It cart bc checked
rotors via access Iholcs in eaclt gland housing. 1:igllic
1.111 shows ihe balance planes and site trim balance
bs
3.5% Ni Ci Mo V slccl has a lox,, value o f F ~ 1 ' l . ii, i,,Iiiiil: ihc rotor on liorizontal knife-cdgc supports. arrangements for a typical 660 M W LP rotor.
In tile water.-qoenciled and tcmpered condition, alld i',,jii,rric boirr~ice means Ilia1 tlle mom cot^ of the
with careful cont~.oiof composition, higil tcnsilc p r o i i ~ l !i~i.l~;~l;ince weights aiong the axis about either
pcrties can be matched with a FATT weli below iii.siifii: add up to zero. This is checked by spinning MOVING BLRDE SIAGES
ambient temperature and a consequential high fiacti~re tolor oil resiiient bearings, detecting the vibration, REAR
toughness. #,,,I itdiling or subtracting weights until the vibl.ation
lb twgiigiblc.
A nrodcrn balancing machine enables balancing t o
d out with a high degree of accuracy and
i1,sles to a large extent the trial and error pro-
7.3 Rotor testing and balancing used in the ~ a s t .
lors are normaliy balanced at low speed (400 r/min)
wi:igl~t adjustment made in two convenient planes,
7.3.1 Thermal stability
jut each end of the rotor. This adjustment may
During the manufacture o f turbine shafts, great efforts arying screwed plugs in tapped holes, or by
are made to ensure that the physical properties o l balance weights at specific circumferential po-
the forging d o not change in service. Thcre are thre Tee-slots are )machined circumferentially in
types of instability: lpllery of the rotor front and rear half-coupling
Permanent, due to asymmnrical coefficients o l r!.t:s to permit the weights to be positioned and
expansion across the diameter. This is avoided by ,cd
i. aim of balancing is to reduce the amplitude
close metallurgical control o f the for.ging process.
rll~ri~iion to a tolerable levei. which can he taken
8 Temporary, due to residual stresses in the rot ;!bout 25 prn at the bearing pedestals.
This is eliminated by stress relieving the rotor, bo rotors become larger and more flexible, it is
before and after machining, in a special furnace lngly important to understand their modal be- ROTOR BALliNCE
WEIGHT ACCESS PORT
in which the shaft is rotated. so that balancing can ensure smooth running COYER PLATE
8 Transient, due to differences in conductivity an larger L P rotors and generator rotors having
emissivity. The use of ferritic materials throughox speeds below running speed are overspeeded
has obviated the difficulties that occur. necessary, balanced in the fully-bladed con-
,
ill a vacuum chamber, where they can be run
IIIOI~Ibeing overheated due to windage.
An unstable shaft is likely to develop a 'bow' 111 11icvacuum chamber and the high speed pit, rotors
service, producing out-of-balance forces and cons ii,c 11,n in bearing bushes and pedestals as nearly as
quentiai vibration.
~$!ih~.ll,lv simulating site conditions. Facilities are avail-
alllr l,,r #measuring journal or pedestal vibration and
trii.iii! can be carried out at closely controlled
7.3.2 Overspeed testing lnywl~eiein the range required. Standards of
A 20% proof overspeed test is specified on all larg obtained during the factory testing must pro-
turbine-generator rotors at the time o f manufacture ficient vibration margin to take account of
FIO,i.110 Typical 0.2% strain and rupture propertie$ of
C, MO V $teeis for rotor forgings This allows the rotor balance to be satisfactoril ditions. Balance on-site is likely to be affected
(bj site trim balance arrangements
($
established throughout its operational speed range i;~.iirtionsin the stiffness of the bearing, possible
thereby providing sufficient margin over normal op inisalignment and the coupling of the indi-
erational overspeeds caused by electrical grid syste ally balanced rotors to form the complete shaft
necessary for large monobloc rotors. Welding tech- disturbances, and the regular 10% overspeeds expe FIG. 1.111 L1' rotor balancing iacililiei
niques are established for the design o f fabricated enced during overspeed bolt testing. Overspeeding the 11i-plane balancing is carried out at speeds
L P rotors employing a series of solid discs. Alloy rotor also proof tests the forging, as it applies cent, Icd with each critical within the running range.
steels for this application are subject to the conflicting fugal stress in excess of that experienced during norma weights are attached ta correct imbalance in
demands for tensile strength and weldability. operation, thereby providing a quantifiable measure ~c modes related to these criticals, as well 7.3.4 Critical speeds
Since L P turbine rotors may run at temperatures o f the margin against spontaneous fast fracture. balance in the modes of up to two criticals A stationary shaft supported between bearings has
not much in excess of ambient, the provision of running speed. Typical H P and 1P turbines a natural frequency of vibration, depending on its
safeguards against the danger of brittle fracture is ovidcd with two balance planes. The L P rotors diameter in relation to the distance between bearings.
important. The use of materials for discs, shafts and 7.3.3 Rotor balancing lllree balance planes and generators have faci- If its speed of rotation corresponds to its natural
monobloc rotors of the lowest possible fracture ap- When assembled with blades, the rotor is balanced to attach balance weights in almost any axial vibration frequency, the residual out-of-balance forces
pearance transition temperalure (FATT) and subject both statically and dynamically. For built-up rotors, are amplified, and can build up to a dangerous extent.
to stringent non-destructive testing and fracture me- each bladed disc is balanced individually prior t o lid site vibration levels exceed those specified, This critical speed is either above o r below running
chanics assessment (see Section 7.3 of this chapter) assembly. 11 is made for site trim balancing on the L P speed, depending on rotor construction. If below, the
96
T h e steam turbine Turbine rotors and coulilirig!;
.,...,,
, -
shaft is regarded as flexible, and care niiisi bc cxei- criticai speeds of a complclc line a1.e shown as fun p ~ ~ i a ~ n not ~ ~significantly
~ r ' e below the tcmpcralure liigir teml>eialilre steani iilrhine rotors opclaie lli
cised during run-up to ensure that the critical is lions of bearing flexibility, cxpressed as the deflection lsiirc rapcrieoced in ol,elation. The l~ossibilityof ;i ihc creep range and cracks within them couid lllerc.
passed as quickly as possibie. o f aii equivalent spring u n d e ~the static load ul3oil r $ i l i , l lirililc fiaclul-e cannot bc disinissed withoot a fore grow under steady loading. Rates of growill
Critical speeds decrease with increased rotor length the bearing. under cieep can be correlated with the linear elastic
and with reduction in rotor diameter. On current large eter K , via an equation of
units, the trend is to provide a rigid rotor (criticals
above running speed). Because of the increased rotor 7.3.5 Rotor f a s t fracture risk a s s e s s m e n t
length (necessary t o accommodate the required num- There have been major advances in the quality or by the requirement that it shall introduce
bel. of moving blade stages) on large units, rigidity monobloc rotor forgings (see Section 7.2 of this chapt rotor brittle fracture in service. The initial
has been accomplished by an increase in diameter. and in understanding the problems of brittle fractu
The rotors of large machines are joined by solid Rotor forgings can now be produced with grea
X 550.C
0 5254:
?d3. (i OSiC
id '.
10 20 30 40 50 50 70 80
lio. 1.133 Typical fatigue crack growth data for various K. M N I ~ ' ' ~
turbine steels between iW and 550DC
and lio~ita ihe accilrnulatcd creep strain to 0.2% in giowtl\ during thc sl>eciiied lifctimc service, s iiiici construction of large iii~~bii~egenciaiors
! 0 5 hours, ensuring that tlie stress in critical higli without fsiiilre caused by instantaneous fast frac ICS i l ~ euse o f a coupled sliah system.
temjleratoie regions is acceptably small. Calculated This will depend on whether the extended defect I l i i r i ;,re essentially deijices ioi tiansmittiiig
cieep crack growth is therefore small and iniay be longer or snlaller illan lhe critical defect size cai i t i l tl~cynray also have to allon, relative angular
simply added lo calcuiated fatigue crack extensions. latcd foi the otost adverse contbi~~ation of eve1 ii~iciil, iraosmit axial thrust and ensure axial
The region of maxiinum combined centrifugal and T o furtllei complicate the assessment, variations 0 l i t c i s allow relative axial movemenl. They mag
thermal stress, near the rotor centreline, coincides with rotor tenlperature diiring machine start-up prod11 h!,il'icd as flexible, semiflexible or rigid. On
the region where, for I.easons of ingot cooling and a corresponding variation in rotor forging fracui I lushine-generators (LC., up to 120 MW) semi-
heal treatment, the material fracture toughness is toughiiess properties which influence tlte instanta i, ;tnd flexible couplings were commonly used,
lowest. Valid plane strain fracture toughness specimens eaus critical crack size. Assessments must therefor ,I 1;trge turbine-generators it is now common
cannot be obtained without removing an unacceptably be undertaken at each critical operating conditio Iru to use iigid couplings.
large diameter core and samples taken elsewhere may for complete confidence.
not provide a reliable basis from which t o estimate
centreline properties. Consequently it is most common
t o measure toughness indirectly by using Charpy FATT
specimen results. Established correlations between F A T ~iignment,as well as axial movement. Double
and fracture toughness (see Fig 1.115) are used to 7.4
determine a Klc for the rotor material. The need for couplings arises from the limited lengtl
lo all cases, the crucial judgement to be made is of shaft which it is possible t o forge in onc piece an(
whether the rotor f o ~ g i n gcan, given the longest fea- from the frequent need t o use different materials So
siblc initial crack and maximum fatigue and creep the various conditions o f temperature and stress. TI1
180 -
I external gear teeth of involute form, which
$50-
I lo accommodate angular misalignment.
3'b NCMV ROTORS
X 1 CMVROTORS
120-
80 -
30 -
F ~ c .I . l l S Relationship between KIC and FATI for rotor materials F~o.1.116 Flexible couplings
The steam turbilic Tiiibi~ierotors anii coili,iir,g!,
----
lHalS coiq>Iinga, which are foigcd scpalalely flolli
tlic siiaft, arc assembled by heatiiig and shrinkin?,
them on io the shaft. Dowcls arc then insertetl hr- o ~:IIJEC
i
POIN; ~OIK
104
Bearings, pedestals iind t i ~ ~ t i i ~ (i )(~,? I I I
107
The steam turbine Chapter 1
- Bearings, pedestals and turning gr?a
wear, especially as new bearings 'bed-in', is to be cavity thus formed fills \r,it11 oil. As thrust jpicssose I
expected. I-lowevei, severe wear is a symptom of
trouble and can be caused by:
8.2 Thrust b e a r i n g s
The purpose of the turbine thrust bearing is to pio-
vide a positive axial iocation far the turbine rotors
relative to the cylinders. To achieve this, it must be
able to withstand the unbalanced thrusts due to blade
reaction and steam pressure acting on unbalanced
areas. It must be free from maintenance, except at
major outages. Since it is universal practice to use
solid couplings between rotors, only one thrust bear-
ing is required in each complete shaft line. It is
normally located close to the areas where blade/
cylinder clearances are minimum and operating tem-
peratures are highest and is split on the horizontal
centreline for ease of asssembly and maintenance.
All large UK steam turbines use the Michell tilting-
pad thrust bearing (Fig 1.123).
Although the net thrust on the white-metalled pads
in the on-load condition is always in one direction,
i.e., typically towards the generator, a second set of
pads, termed surge pads, are incorporated on the
opposite side of the integral shaft collar to take ac-
count of transient reversals of thrust which occur
108
The sreani rurbil7e CI7aptel. I' .f Bearings, pedestais und turning geiii
.,,..,.
g
@ I'cilviliils in tlie l l ' arca o l tire tuibiiic arc troi-mall\, - inside the line o l tlre liall.
all round tiic ioiot flange
i ~ ~ i i i l lbollcd
y and dowelled to the foundations, It joint bolts; any seepage from the ends of tliese gioovca
ADAPTOR FLANGE RXIAINOICATOH
BODY ,
TI+RUSTC3Al> T H R U S I ?All SO,' l i , li<lnri,ei, common praclicc at the high tempciatore
i 3 , i i l 01' liie ti~rbincto make provision either lor the
is collected and ]piped away lo a dirty-oil drains lank.
I
CON laving regard for the speed and size o f the bearing
CONTROLROOM 30 r/min, during start-up and shutdown by the ETG.
/._.._........ ..... i:oupling assemblies within the pedestals, the pro- An electric drive motor turns the rotors through a
I I I lo11 of oil mist is inevitable. The escaoe of this wormshaft and wormwheel, thereby providing a re-
..-A is prevented by the main oil tank vapour ex-
lors which, since the bearing drain lines d o not
duction gear. A jacking oil pump supplies high pres-
sure lubricating oil to the reduction gear.
LOCAL INDIC#TlON
AND ALARM 111 11111, maintain the inside of the pedestal at a Manual control of the motor is provided in the
air pressure than the turbine hall. There Control Room, and automatic stop and start faci-
I1 flow of air through the baffle ring and lities are also included in the motor switchgear. The
the surface of the shaft; this purges the oil motor overload trip is set at a value which prevents
NO 1 NOZZLE ack into the pedestal and via the bearina drains excessive torque being applied to a seized rotor. Elec-
Ihr main oil tank, whence it is discharged at a safe trical interlocking prevents the motor being started
iiotl. For details of the lubricating oil system see until jacking oil pressure is established.
A self-shifling synchronous (SSS) clutch is installed
TIC. 1,124 ~ h i u t tpad wear n~asuiemenrsysrern, reiying upon decreasing gap a: the naaale head causing a r i x in
leakage from the horizontal joint of the ped- between the drive motor and the turbine shaft and
indicated discharge oil pressure a a is commonly prevented by machining a groove provides a simple mechanical means of automatically
111
T h e steam turbine Chapter I' Turbine applicalio~,.;
l4Aia iiias~EiN~ti
<.OIOIIOI.VXLVE
BULK THANSMiSSlONP<PELINE
would otherwise ,~eed to be fed from tappings on domestic and industrial use. It is the purpose of
the main turbine IP cylinder. It is generally simpler C H P schemes to exploit this potential.
to arrange this with shorter pipe runs from the feed The condenser pressure in a typical turbine fo
pursued for future plant. the saturation temperature corresponding to the steanl
Condensing-type boiler feed pump turbines are also pressure, i.e., at 33-45°C to 49.5% for pressur
o f single-cylinder single-flow design and, because they 50-120 mbar. Unfortunately, temperatures as lo
exhaust into the condenser, their inlet steam conditions these would be unacceptable for transmission t 1.131. More than two pressures could be used of ach~evingcontrolled extraction pressures, since con-
I tile advantage o f liigher thermal efficiencies but trol valves can readily be supplied in the ii~tcr-cylindel-
ill^ expense o f greater com~iication.The extraction crossover piping downstream o f the 1P exhausts. The
Ill is i~assedto two district water heaters, so that asymmetry is provided by designing for a different
c i l ~ a l temperature rise is obtained across each number of stages in each flow of the turbine.
Figure 1.131 depicts three large existing turbines
STEAMTURBINE
BULXTFINSNISSoNIPLLNE
be the provision of bleed and condensate return tap- the economics o f such schemes are likely to
pings, with control valves as shown. The district water increasing favour.
system would include the heaters, pumps and pro-
vision for make-up and heat storage so that the
operating periods of the auxiliary turbine generator
and its loading schedule can be controlled with a 9.4 Combined-c~cieplant
degree of independence from the heat demand.
Such a scheme could provide heat as well as power producing process where the prime movers empl
FIG.1.132 Simple 'combined cycle' plant, employing one gas turbine and one steam turbine
to a large city located many kilometres away from more than one working fluid in a combination
the power station. turbines. The most common and practical form
which makes it attractive for countries with cold with variants of this basic theme.
winters. One difficulty which has prevented a more Figure 1.132 shows a combined-cycle plant i lliry steam turbine is able to make use o f this applicable to countries having an abundant supply
widespread use of such schemes is the cost and com- simplest form with the heat from the gas-tu llhe of the low temperature exhaust made possible of oil or natural gas where there is a need to rapidly
plication of distributing the heat thus provided to exhaust utiiised to generate steam in a heat-reco l o condenser. The condensate is returned to the extend the utilisation of these resources to meet the
hundreds of domestic premises. The most successful steam generator. This cycle makes use of the inh li generator, via a single combined feedheater populations' demands for electrical power. A phased
schemes have been applied to new developments of ent characteristics of the gas turbine process, wh de-aerator, followed by a pump. Typically the development could be implemented, the first stage
large apartment blocks. With ever increasing fuel combustion takes place and, following expansion 1, lilrbine output will be about 50% o f the gas being the installation of gas-turbine generators to
costs and the need to conserve valuable fossil fuels, the turbine, heat is rejected at a relatively high te meet the immediate needs for electrical power, thus
118 119
1-lie steam itirbine
T11c ijiiilcd l<ingdoin 11as also gone t l ~ s o u g l ~a 10.2 Supercritical plant As mosl modcin toibine blading in lHIJ and 11'
period of consolidation in the 1970s and 1980s. After Onc effective way of achieving increased thcrmal i. ,,ti51 c,lI,cr have ail m t i a cyiindo or it must tuibincs airzady has an internal eificiency in the range
a relatively rapid increase in unit size from 30 MW in ciency Is to increase stearn pressiiie. The limits il I>ii,c<lcylinder for the first two expansions. 90°/0 to 95%, ilic potential inipl-ovemcnt is 1101 iargc.
1945 lo 500 MM' In 1970, this lhas only increased to natural circulation boilci are around 180 bar, i i ~ y l i ~ ~increases
~ies rnaciriire iengtll and cost, Turbine makers h a w developed standard blading fa-
660 MW subsequently. Thc carliest 660 MW unit was ailhough assisted circulatioil may be used at i1ip.h co~nbii~cd cylindci may give tlic possibility inlilies of lhigli efficiency wliicli are tolelalit t o the
ordered in 1966 and was in se~wice by 1974. This ~ICSSUTES, an overall imp~~ovemeot in station efficiel~ ealing between the two e x ~ ~ a r i - range o f stcam flow incidence angles, which arise in
inodest rate of development has ixoduced piant of is not achieved unless the pressure is advanced r $ 8 , i l t i i : to lhc close proximity of sections at different applicalions aiid different conditions of op-
excellent thermal efficiency and reliabilitv... and UK about 240 bar, i.e., above tllc cl.itica1 prcssurc i!ii i i j l i l reheat temperatures. Combined H P / eration. Root and tip clearances are as small as
manufacturers' designs have becn progressively devel- water/steam (221.2 bar). Although the use of sup i i c ~ s iiave, however, been wideiy used by practicable, with as many flow constrictions as tile
oped and refined to take advantage of new technology, critical pressure requires special consideration in 111 ratrrpanies and their associates in machines design permits. The detailed geometry of these restric-
design methods, and manufacturing rnetllods in the design of the boilcr, the iniplications for the turbin tions can aliaw some reduction of the flow discharge
intervening years. only concern the higher pressure as sucli. 01' ll~ese developments prescnts technical coefficient, so that steam leakage through these clcar-
In the late 1980s, it has been judged that the time A further improvement may be obtained by in (~ivcnsufficient time and resources. Their ances Is minimised.
is right for a further increase in unit sire for super- creasing steam temperature. Most of the supercritica in practice depends o n potential customers The development of L P turbine modules is a costly
heat plant to 904 MW, in order to meet both domestic plant in service worldwide operates at 538"C, altho "cd that the potential return in improved and lengthy process, yet there is always an incentive
and overseas requirements. For the domestic UK needs, some 565°C plant exists, and there are some pion ot accompanied by additional risk either t o increase the cni~austaica of each flow seaion t o
ing units with temperatures as high as 650°C. At operational flexibility, or availability. seduce the exhaust kinetic cncrgy (the leaving loss).
this offers substantial benefits from the economies
higher temperatures, the efficiency is often boosle , tile development programmes embody This development may aisa permit, for particular unit
o f scale - typified by the physical dimensions of
still further by using double reheat. Apart from 111 I;itlge of research, design, rig testing, and sires and steam cycles, a reduction in the number of
tile turblne-generator being only marginally increased
efficiency benefit, this has the $merit of reducing 111 ~ p ucom~,onent testing, which, coupled with the LP cylinders: this is a wortliwliile objective to save
from tlie 660 MW units. The initial steam conditions
turbine exhaust wetness from thc high level that sucl ll k i i C prototype unit, will give the necessary cost and reduce the size o f turbine liall requiied. The
have bccn advanced from 160 bar, 565°C to 176 bar, lasr-stage and penultimate stage blading is always
advanced initial conditions would otherwise entail.
565°C thus providing an increase in thermal efficiency The use of supercritical plant has varied consid btc XI which such plant will be i~ltroduccdis the limiting area of design; in terms oT the stearn
without sacrificing operational flexibility. ably through the world. In both the USA and Japati depending as it does on factors
I ii~~cer.tain, bending stresses on the blades and the large mass of
For nuclear plant, the choice will be determined it has been used t o a considerable degree for lail lcclricity demand, fuel costs, the economic the blades which imposes a large centrifugal stress
mainly by the reactor type and size. For advanced gas- units for base-load operation, typically up to 700 M : 11,lhc extent of alternative energy sources, on the blade fastening to the disc. Lasl-stage blades
cooled reactor plant (AGR), the preferred reactor size tandem-compound and 1300 MW cross-compoun irbishment of existing plant for extended for 3000 r/min turbines have been developed up Lo
is in the 660-750 MW range. Being a superheat cycle, The initial steam conditions have normally been aroux 1200 mm long: this is believed to be about the limit
this requires a steam turbine almost identical to that 240 bar, 538°C. In Germany, supercritical plant 11 for conventional 12% Cr blade materials. Indeed,
for a fossil-fired unit o f similar output. Any turbines been in the smaller range, up t o about 200 MW. the 1200 mm blades in scrvicc in the USSR are made
required can therefore be derived from the existing the United Kingdom, two prototype units were bu from titanium alloy, and this is likely t o be the pre-
families of modules covering plant up to 900 MW at Drakelow C with steam condltions of 240 b ferred material for longer blades. In particular, the
''. rbine blading development
01 more. 593°C. introduction of longer last-stage blades is likely to
For water-cooled reactors, the reactor sizes are up At temperatures up t o 5 6 5 T C , low-alloy creel) r)llinent of turbine blading can be expected permit the use of 3000 r/min machines with the lar-
to 1200-1300 MW, although some enhancement of resistant stccls such as 0.5%Cr Mo V and 2.25 illlsc to mecl three objectives: gest nuclear reators in 50 Hz systems, althougli the
this may be expected. For the first UK PWR at Mo are used foi- the high temperature components 3600 r/min equivalents are much further away.
Sizewell B , the decision was made in 1979 t o employ The pressure determines the thickness of pressm lcril inanufacturing cost.
two 630 MW turbine-generators with the 1260 MW(e) containing sections such as steam chests and pi1
reactor, as these made substantial use of modules work. The combination of steam conditions. mate
developed and proven for the 660 MW fossii-fired thickness, and operating regime determines the pl
life in terms of creep and thermal fatigue. At pr ' il efficiency, including new L P blading of 11 References
plant, in particular the LP turbines and the generator.
sures of 240 bar and above. and narticularlv a t t le I exhaust area.
Those elements specific to the saturated steam cycle, [I) Tiaupel, W.: Steam turbines, yesterday, today and tomorrow:
such as the H P turbine, moisture separator, and higher temperatures o r where reasonable operation Pioc, IMechE 193 No 38. 391-4W: 1979
steam/steam reheater (see Chapter 2), had been de- flexibility is required, other high temperature material 121 Harris, 1. R.: The Parsons Centenary - a hundred yeais of
are used, such as high-Chromium (9-12%) ferritic I of blade manufacture can be minimised steam turbines: Proc. IMecliE 198 No. 53. 1-42: 1984
veloped and proven in plant supplied to overseas
by UK manufacturers at ratings up t o 110 MW. It alloys, or austenitic alloys. Austenltic alloys have sonic application of computer-aided design and 1' I . I h 2 : I . , 4 I) 1": :4..< .,l
Jv*!: s;le.J I
adverse properties, such as poor thermal conductivity Ire, in which the optimised geometry from P\<h . . r b n e , lo: % 11, ,,c~.:~aL.#., ~ s , # ~ , ln\ l%t . l k C I#.~::cI..v
is expected that, if there is a series o f PWR stations
and high thermal expansion, so the current trend is rnnce, vibration, and stress considerations is *;,,I Plllll ,, P,.,\",.<C, \\a';, Red.,,,, t$h?
in the UK, the decision will be made at some stage 141 Stodola, A , : Steam and Gas Turbines, Volume I p 316: Peter
to develop the ferritic alloys for use in the large cast d directly to the numerically-controlled
to select a single turblne-generator per reactor, thus Smith. New York: 1945
and forged components. Development programmes ar
taking advantage o f recognised savings in capital cost, (51 Traupel, W.: Thcrmische Turbo Manchinen, Volume I p 491:
under way in the USA, Europe, and Japan for d \loved, integrity blading can be obtained by at-
construction time and operational costs. In line with Springer-Verlag: 1966
signs and materials for the so-called 'ultra-supercrltica 011 to detailed design t o reduce stress concen-
developments elsewhere, it is not expected that reactor 161 Miller, D. S.: Internal Flow Syrtemi. Volume5: Biitish Hydraulics
piants of 350-1000 MW with steam conditions su y controlling the vibration characteristics to Research Asrocation: 1978
size, and hence turbine-generator size, will advance as 310 bar 590°C, and later up to 350 bar 650" nances near running speed, and by reducing
beyond 1500 MW in the foreseeable future. 171 Craig, H. R. M, and Cox. H . J. A , : Performance Estimation
all with double-reheat cycles. These plants are not, or improving the quality) of attachments such of Axial Flow Turbines: Proc, IMeellE 185. 32-71: 1970-71
There is therefore no perceived need for unit sizes to however, likely t o be in service until after the year uding lacing wires, and erosion shields. There
advance substantially in the next ten or twenty years, 181 Biiggs, 3. 2. and Parker, T. D.: The Super 120ia Cr Steels -
20W. nliince to be made between robust blading with aii update: Climax Molybdellum Company
beyond about 1000 MW for superheat plant o r 1500 The use of the double-reheat cycle introduces cctions and efficient blading which favouis a 191 Smith, D. M.: Journal Bearings in Turbo machinery: Chapman
MW for saturated steam plant. additional complexity. First, additional boiler contro sl)cci ratio (length/chord). and Hall: 1969
122
Governiiig system:.
- ..
13.4 Mo8stuie separator rel>c.itc~sIMSHsi
134.1 Separators
13.42 Stcanl~o-sicamreilearers
ii8rliinc totors 13.5 Stealn suppiy and drains systems
!%11(,3s nioilitors 13.51 First-siagc reilcat
<m<:<><I.t,i,
~oolir,g 135.2 Secandsfage reheat
cc,oii,,g at turbine 13.5.3 Performance ino~>itoring
(:ooli#,gsysfetn 135.4 System drains
C H A P T E R 2 135.5 Separator drains
135.6 Rehearer drains
it~lltro8~aeof steam on components
N,,,lol cxiiaciion devices 14 R e f e r e n ~ e ~
ib10tioil ipioteclion
Turbine plant systems 1 5 Additional references
1 Governing systems
1.1 Introduction 6.1 Lubrication requirements and typical ariangemenls
6.2 Oil Dumps
1.2 Governor characteristics
62.1 Main lubricating oil pump
Verning s y s t e m s system. T h e initiai transient speed rise following s u c i ~
12.1 Simple scheme - boilcr on pressure control
6.2.2 ~urbine-drivenail booster pump a ioad rejection, contaitled by t h e governor, is pri-
1.2.2 Turbi~iemaster load controller with boiler on pressure
6.2.3 AC and DC motor-driven auxiliary oil pumps marily d u e t o t w o factors:
controi
12.3 Boiier master ioad controller 62.4 Jackino-oii DumDs and "riming Pumps
1.3 Subsidiary functions 6.2.5 Other liumps Tile stored energy o f steam within tlie turbine a n d
1.3.1 Acceleiation feedback
fi 8 Oil tanks n i n g system o f a large
6.4 Piping used f o r electricity production via
it"ssociated pipework.
1.3.2 Unloading gear
6 5 Oil coolers
1.3.3 Gaveinor speed reference
1.3.4 Closed-loor, controi of turbine electrical load 6.6 Oii strainers and filters
6.7 oil purifiers and cosiescers
)power netwo1.k are:
* T h e time taken by the turbine vaives t o ciosc in
1.3.5 Overspeed testing
1.3.6 On-ioad testing
6.7.1 centrifugal separation systems
6.7.2 static oil purifieraicoalescers
$8 B 'I!% iiii)i;iin
liil
the speed rise within accentable limits
ihu ilnit becotne disconnected f r o m t h e l o a d .
t o t h e sensed overspeed
1.3.7 Automatic run-up and loading syrtemr 6.8 Oils end 4reases
1.4 Electronic governing 6.8.1 Oils It is aiways well inside t h e overspeed trip setting a n d a
- .orocessina
1.4.1 Dioital 6.8.2 Greases
illrol t h e steam valve positions (and hence
full analysis is given in Heilbronn [ I ) .
1.5 Goveinor valve relays 6.9 Jacking oil systems ,lt<i gcneratedj in response to signals f r o m t h e
1.5.1 Governor vslve relay and contioi unit Type 1 A n electrical governing system f o r a typical turbine-
6.10 Greasing systems lilr, o r f r o m a separate station automatic control
1.5.2 Governor valve relay and control unit Type 2 generator with multiple steam admission paths comprises
1.5.3 Governor valve relay and control unit Type 3 7 Gland sealing system
m a n y elements, a s depicted in F i g 2.1. Since it includes
1.54 Rehesfer relief valves 7.1 function and system layout
1.6 Hydrsulic fluid system a t least one closed-loop control function, t h e machine
71.1 Labvrinfh alandr llrvl t h e initial run-up a n d synchionisation o f
16.1 Filtration 7.1.2 sysiem lahut and network characteristics f o r m an integral part of t h e
1.7 ~oiierfeed pump turbine governors 7 2- Temosisfure
~,~ and Diessure contioi system. T h e orimarv feedback is o f turbine shaft m e e d
7.2.1 Temperature control
2 Steam chests. vaives and loop pipes i s in matching t h e power generated to which is usuaiiy measured by a toothed-wheel a n d probes
7.2.2 Pierrure control
2.1 Steam chest arrangements and construction 7.3 Gland steam condenser !I ~ l r i ~ i ~ i n dby
e dresponding t o network frequency at t h e HP end o f t h e machine. T h i s signal
. is orocessed
2.2 Steam chest materials by a m o d u l a r electronic system, o f t e n mounted in a
2.3 Cover seals 8 Flange heating system
2.4 Steam strainers 8.1 Function and system layout cubicle quite r e m o t e f r o m t h e turbine, t o f o r m o u t p u t
2.5 Stop valves 8.2 Control signals which are directed back t o each steam valve o n
2.6 Governor vaives I <,f these functions is a vitai o n e f o r t h e safety
9 LP e x h a u ~ f*pray coaling system t h e turbine. T h e processing is complex a n d is subject to
2.7 Loop pipework
2.8 Crossover pipework 9.1 Function and system layout detailed variations for each application; it generally
9.2 Control includes t h e following:
3 Turbine proteotive devices f these connections are opened, either by a
3 1 PosSibie hazards 10 Drains svstsmr
tern fault o r by t h e unit's o w n protection 8 T h e speed/ioad characteristics o f t h e machine when
3.2 Protection scheme 10.1 Function and svstem iavout
' s t e a m flow a t t h e instant o f disconnection synchronised.
3.3 Electrically-signaiied trips 101.1 Stait-up drains
3.4 Overspeed trip 10.1.2 Continuous drains le sleam flow necessary f o r steady state opera-
3.5 Mechani~ally-operatedtrips 10.2 Control 132 (3000 r/min) by t h e a m o u n t necessary t o A predetermined relationship between the high
3.6 Operator tripping facilities illl-load. T h e excess energy input m u s t h e pressure ( H P j a n d interceptor valve position.
11 By-pass Systems
4 Turbine instrumentation 11.1 Configuration rapidly i f an unacceptable overspeed is t o be
11.1.1 Pressure control valves Facilities f o r o p e r a t o r control.
4.1 classification of instrumentation I . Tile governor performs this function by re-
4.1.1 S u p e r ~ i ~ oinstrumentation
w 111.2 Isolating valves
lij! l o t h e initial change in speed t o close t h e
4.1.2 Efticien~yinstrumentation 11.1.3 Dump tube Features t o limit t h e m a x i m u m speed o f t h e machine.
41.3 Auxiliary system instrumentation 11.2 By-pass systems for nuclear plant
4.1.4 Condition monitoring instrulnentation 11.3 By-pass systems for fossil-tlred plant lilc oversoeed trios (described in Section 3.5 Features t o limit the o u t p u t in t h e event o f abnormal
4.1.5 instrumentation associated with protection and control 11.4 Problem9 with by-pass systems
11.4.1 Noise operating conditions.
equipment
4.1.6 ln~trumenfationto provide posl.incident records 11.4.2 Water ingress
114.3 Theimsi shock onnei is always maintained. T h e governor Features t o permit routine proving and testing o f t h e
5 Turbine foundations 11.4.4 Leakage flows
111s this safety function and, since it maintains system.
5.1 Tuning
1 2 Operational flexibility ii lilt r u n n i n g speed, ensures t h e continuity
5.2 Concrete foundations
5.3 Steel foundations 12.1 ~ypicaloperational regimes rilpplies f r o m its o w n generator a s weil a s T h e a b o v e functions are described i n detail i n Sections
5.4 Spring foundations 12.1.1 Base ioad
5.5 Sub-foundation 12.1.2 Two-shifting lily l o reconnect t h e generator t o t h e power 1.2 and 1.3 o f this chapter.
Turbine Governing s y s t e ~ ~ ~ s
6 P
g 9
WHEEL 8 PROBE
i i oil and off at will. On a large power system,
$ 9 :$
A
g units, similar consumer demands may apply >OD.
iciuations may be a significant percentage
0 e
48 49 10 51 12
FREQUENCY, H i
1
2880 3000 3120
SPEED, d m n
126 127
Turbitie lati tit systetns
qilency f by adjusting the sjleerl sclpoinl to give char- beioiv tlie overspccd trip setpoint 0x1 a Ihigh dioop go cii:liacIeristics described so far in this sectioii iue
nos. On it low droop govciiior (say 4% or less), 111 Ilitil soit the jparallcl connection of turbine-
acteristic a,b,, then a fali in frequency by a i l ainoont
overspeed niay be contained by tllc normal droati 1015 onto rlic p o ~ c systcm.
i However, same o f
a T wili give a inotional load o f value c 3 , However, ibis
value of ioad Will not be attained, as tlie tul-binc valves cliaiacteiistic witliout any oecd ibr thr special overs~>eid tolcs o f a governing system aiisc frolii a considera-
OEMAhl"iii> ion0
are aiready fully open at point b i . Tire speed selljoint limiting facilities. 01 llir types of plant being contraiicd and the way
TO INCREASE OR
In eitiier case, to lnieet the requirement of containillp li the control of the scparate boiler and turbine
is said to be 'avcrwound'. The disadvantage of this condi- OLCREASE
SPEED SETPUN,
tion is that, if asked to reduce load on the unit, the thc overspeed within the trig setl>oint,it will be necessary
operator is unable to d o so immediately until lie has t o closc all the turbine valves withiii a fraction of 11 e purpose of this description is to note the
reduced the speed setpoint to the line given by c2a2. second. When the speed error reduces, the goverl~ol lres affecting the governor. Three basic options
Normal practice is either t o draw the operator's atten- reopens the valves to the amount necessary to maintain cd, each of which may include enhancements
the speed at the reduced value of load. scribed) t o improve the response to particular
tion to the overwound condition by an alarm or to
provide an automatic reduction at the sctpoint so O n reheat machines such as that depicted in Fig 2 llional circumstances. i:io 2.5 Sci,elralic of a silnple ioad frequeilc), cosi~olici
that an immediate response is possible, if required. it is necessary to control nor only the H P govcrnillg
Facilities for droop adjustment are often provided. valves but also the interceptor governing valves folio\
Typically a high value of droop, like 25070, may be ing the rehealer. if the H P valves only were closed rapidly 1 Simple s c h e m e - boiler o n p r e s s u r e
beneficial in reducing transient steam pressure varia- on a full-load rejection, the amount of stored steam ill speed setpoint, which changes the load o n the turbine
tions if the system frequency fluctuates to a marked the reheater and associated pipcwol-k would be sufficient clne the governor speed setpoint is controlled to reduce thc error. This form of slow-acting integral
degree. The droop may be adjustabie within a range to ovcrspeed the machine to destruction. Thel-efolr, ollcrdtor t o load the machine by means of the error correction gives accurate droop characteristics
or alternatively switched from a selection of two or similar rapid response to close the interceptor governilig droop characteristics. Options for droop adjust- or controi to a fined load (infinite droop), if selected.
more values. Droop adjustment, or switching, on-ioad valves is provided. iic often incorporated. T h e master ioad controller may be included as part of
generally implies a ioad change uniess carried out at Most large turbine-generators employ rehealing cil~llmi~sioning purpascs it may also be an ad- the governing systcm or may be provided separately in
the pivot point of the characteiistic or uniess coupled intermediate pressure (IP) stcam to improve th a unit control scheine. Apart from providing accurate
with a simultaneous change in speed setpoint. Many efficiency. Thermal efficiency is reduced if thro I . 'l'l~esewould either prevent thc turbine valves linear droop cllaracteristics, the performance of this
governors incorporate facilities for a 'bumpless' change takes place in the interceptor valves, so these vaives a ,l?ening above a certain proportion of their travel scheme is very similar to the scheme described in the
in this fashion. usually fully open over the normai load range o f tl load measurement, would prevent further valve previous subscction.
Fieure 2.4 is a develovment of Fir 2.3, showing the machine. This operating regime is referred to as HI' I' above a certain load setpoint. Thc main dis-
"
characteristics of additianai overspeed limiting facilities governing and is achieved by applying a fixed bias to Ilulie of the overall scheme is that a ioad rejection
that have t o be built into the design so that the speed the interceptor governing valves, thus giving them 11 Id cause the turbine steam valves t o close rapidly, 1.2.3 Boiler m a s t e r load controller
rise on a ioad rejection can be adequately contained same speed/load characteristics as the H P gove sing all flow through the boiler, possibly with In this scheme, the output of the master load controller
valves but more open by the amount of the fixed om firing rate applied. Although the boiler safety described in the previous case is used t o set the boiler
(typically 50%). In the event of an overspccd, these valv would lift a few secolids later, there is some firing rate. The governor speed setpoint is controlled by
will close, albeit at a greater speed-error than the HI' ~ o o dof thermal damage to superheater tubes. a boiler pressure error signal, so that the turbine valves
iob OilOOP 21- DROOP governor valves. tt~vl~ioe by-pass system (described in Section 11 increase or decrease steam consumption in a sense to
h ltls chapter) is one option which could ameliorate
Another possibie mode of operation (often provider reduce the error. This responds very satisfactorily to load
as a switched option) is to allow the interceptor goverlr changes demanded by the operator as the boiler firing
ing vaives to operate in a throttled condition. Altliougll otllei disadvantage is that any load increase,
rate correction is made first and, subsequently, the rapid
the thermai efficiency is reduced, 'thc spinlling spare iri allplied t o the turbine manually by the opeia-
response of the turbine can easily control any pressure
capability' of the plant is enhanced: the capability o f fluctuations.
the machine to increase load rapidly iii response t ly matched by the boiler. Because the flow
However, rapid changes in frequency, particularly
either a reduction in the power system frequency 0 the pressure will fall to a degree dependent
the increase arising on ioad rejection, still produce
a demand by the operator t o increase load. This may the necessary governor safely response and abrupt
be important in power systems where there are iarge lls, the droop characteristics provided in the
changes in firing which cause large boiler pressure
fluctuations in network frequency, or where there at' overn nor are usually derived by measurement
fluctuations.
insufficient machines with good regulating characte~ position rather than electrical load. This may
istics. This mode of control is referred t o as HP PI i n Incremental droop deviations at any operating
IP governing or sometimes as parallel governing. In th due to the imperfection of valve linearisation
HP governing mode, the reheater pressure is normali uleristics (see Section 1.4 of this chapter).
proportional to the ioad o n the machine, but in the H
1.3 Subsidiary functions
plus IP governing mode, the aim is for a constant re- This section describes additional functions of gov-
heater pressure, at least over the load range of 50- 100%. Turbine m a s t e r load controller w i t h boiler ernors, giving typical characteristics of these features.
This means that at 50% load, instead of the pressure ressure control Not all governors include all these features; in some
MiNiMUM SPEEDER GEAR RANOE AT N O LOAD
FREoUENCY HI in the reheater being say 20 bar, it will be at the t~scrcomethe previous point about non-linear droop cases they may not be essential to the plant being
..-e
R ' C..rii,;.. : I.. :.I-c: L . .. c:3'il"
fuli-load value of 40 bar and the 'spinning spare'
capability will be improved by the additional thermal
llilcleristics, a separate load/frequency controller is
Ill having the features shown in Fig 2.5. Far any
controlled, or they may be carried out in other equip-
ment but operating through the governor. Equipment
C".l:..)F:,,i4.(
.:,s!; .,,a -,,,,, s u e . , :, ,.,:;,s.;..<:
li.. ? ? ' I , . , ,,-I-.,.C,PCD:1.. .i':iaR:
<.C.T.C>$>>
I-,.
storage available through having reheater steam a t the titlg frequency, depending o n the characteristics, for HP rotor stress control during run-up and load-
I . O.O.li.sTli: lR.,..C. . A :
fuli-load pressure. Thus the I P and L P cylinders will be u'ill be a demanded load determined by this ing is a typical example of the latter. It can be
able t o provide their full-load torque almost immedi- teristic which is compared with the measured performed by an external computer modulating the speed
ately, although there may iater be some decay until the " I load in the master load controller. The result- setpoint of the governor or it can be a n intrinsic part
boiler firing rate has picked u p to its full-load value. ?r signal provides the input to the governor of the governor.
Turbine plant sysrelns C
1.3.1 Acceleration f e e d b a c k of \+'liicli wo~iltl ~nosiiiaily c a ~ s ca toibiric tril?. coi-l,oiatcs an invelne Cunctio~rso tiiat all ogstreaiii gob'ci
Acceleratioli feedback is commonly used to provide a iiicoi-oorated so that the colldition likelv to cat i b < r o i 120 mhas, as slrowir on 1:ig 2.7). nor processing lhas an almost linear cffect on the steiiill
secondary stabilising term to inipravc the damping oS tiil) is sensed early and thc turbine load is de demand at one nominal set of steam inout coiidilioni.
the governor and to assist tlie prim? safcty fiinction of to rcdiice the prababiiity of tripping. If a tr I-lowever, if tiie conditions vary, the significant non-
occur, then the ttansicnt effect an thc plant is redii ernor speed reference lioearities \\'ill aive rise to i~nperfections.Closed-loop load
thc governor in preventing overspeed due to a load
rejection. because it occus.s at a lower load. in#speed reference is the prime input by control ouercomes these imperfections by superimpos-
With a disconnection froni the power system, thc Low exhaust oressure unloadina-aear is norarali ilii. t~iibinecan bc conuolleti, either by the ing a trio~mingsignal onto the governor speed reference.
response of a governor without acceleiatioii feedback :,I J... $ 1 . ~,I..,II. 1. 1.1.tIl ..I..:I . I :.t111'1'; !' : I i . I . : I '1. I: I : . ., 11 .,. I...).. A block diagram of the load ioop is shown iii Fig 2.8
would be controlled by the speed error leim as modified I . . I . ! I I . I . ' I :1.11 I . , ' I 1. 1 3 1 1 . '.111,: . ~ p ~ . .)\:I
; ,A!,#.1 .+. arid the characteristic i t produces in Fig 2.9.
by the droop law. If the speed droop is set to 470, the
valves u,ould have fully closed by the time the speed was iscd or unsynchronised. Prior t o synchronisa-
peed reference range will extend from the
,
- -
4 % above nominal. A typical value of the initial accelera-
tion rate is 12% oer second, so it would be at least 0.33 rollable speed (typically 3 % of nominal) up
seconds before the valves had been signalled to the fully- cst spccd at which the turbine-generator
DEMANDED 1 0 A 0
closed state. In addition, inherent delays in tlie hydraulic ])able of synchronisation (104%). Once ERROR SIONAL
system mean that the valves do not achieve the signalled istic is shown in Fig 2.7. The purpose o f unlo I, the speed refercncc will be limited to thc TO INCREASe OR
DECREASE
closure response. Taking a linear acceleration rate o f is to reduce the effects or prohahilit)' o f a trip. SPEED SEXPOINT
12% per second, the time to reach an overspeed of 10% reason for providing a trip is discussed separate I maximum rates of increase or decrease of
VOLTAGE
would be 10/12 = 0.833 seconds. Because of the Section 3.1 of this chapter. T h e degree of unlo ANALOGUE
OF FREOUENCY
expansion of steam entrained between the steam valves FUNCTION GENERATOR
and the turbine, the turbine will continue to accelerate sibility of motoi.ing. The rate of unloading is ge uite rapid fixed rate which is compatible LOAO LOOP i R L o U E N N
CHARACTERISTIC
after the steam valves arc closed. T o contain the consistent usit11 the rate of incrcase in exhaust pr lium conceivable rate at which the turbine
o v e r s x e d within the trill setting of l o % , it is generally However, if the initiating cause o f unloading is ,e increased if warmed through and all
I usere at an optimunl. In this latter case, tile
necessary to incorporate an acceleration tern?.
A govcrnor incorporating acceieration detection can \ r ~ ) u / either
d be ~nanuallyraised by the operator
sense the need to close the steam valves as soon as its
measurement circuits are able to respond. The valves can the load. This is achieved by resetting the govern
be instructed to close a t maximum rate within 30 ms of speed setpoiot which has been independently reduc usually a single fixed rate.
the load rejection and should be fully closed 1W ms later. the tuibine-generatol- comes under control
Figure 2.6 shows a typical response t o a load rejection. to-synchroniser, o r if manual synchronisation
T o ensure that this form o f acceleration feedback only t o veto the operation of the loading gear until performed, another rate-of-change of speed
comes into play during a significant load rejection, a exhaust pressure has reduced to a value such that '$1 apply. This must be compatible with the
threshold is preset into the sensing system below which unlikely t o restrict the initial loading up to full-loa nising unit and is usually designed to give
lain synchronisation.
there is no outout. The acceleration sienal - must also be T h e veto is normally removed by the operator but,
forgotten, the veto will be automaticaily removed wli ~nchronisedand under operator control, the
present for a preset time before it takes effect.
lige is conventionally set to give full travel
u to + 6 % of nominal speed in 2 minutes.
1.3.2 Unloading g e a r lnor speed reference now acts as a load
Unloading gear may take several different forms, depcn- nd, if a 4% droop is applicable, this means
ding o n the plant being controlled. It is usually
complementary t o a protective function, the operation
basic speed governor. By liniiliiig thc load range over then tlic HP stog, 11' govcining and Ii'stog valves t i i i i i l
wliich the load loop is operative, the magnitude of the u~halegroup is closed. Valvcs arc opened in tiic
sudden load clianges on the boiler systern is limited if a reverse sequence and tlicl-c is also tlie cayability hi revcl
lox, speed droop is used. For obvious reasons (Fig 2.91, sing the sequence at any point \i,lIell llie glolill tesl is
spccd and load variations over which variable-droop only partially complete.
is pcimitted a1.e known as the box chal-actel-istics. On a typical wet steam (PWR) torbine, there will b
Consider a sudden fall in network frequency or1 a four H P inlet and six LP inlets so a group cannot b
nuinber of machines operating in parallel with different defined in the above manner.
droops but similar box size. Bccause the load loop is A vital part of the on-load test equipment is the pro
slow-actinp, through the governor speed reference, all sion of some means for the operator to monitor 111
machines initially cantiibute an increase in demanded performance of the valves. This may be done b
load. Then those machines with high or infinite load loop automatic initiation o f a chart recorder, giving a tin1
droops will slowly reduce in load, returning to a value base against which the opening and closing times
at or near theii original load. This allows the other valves ,nay be judged for conformity to the spe NO"
machines with low droop to pick-up load at a rate tion. Another method is to use an XY plotter wi
compatible with their boilers. The advantage of this actual valve position being plotted against the deman
arrangement is that some units can bc designated for ed position. This can be arranged to give a well-define(
rapid load pick-up, whilst those unable lo sustain such characteristic for a correct test, so that an incorrect tcst
a transient can still contribute usefully t o the control of is readily identified. A third method, likely to be
falling frequency. employed in the future, is t o make use of the VDIJs
provided in the control room for data processing. A
similar type of record to that described for the XY plotlcr
1.3.5 Overspeed t e s t i n g may be obtained, using a temporarily enhaoccd scann.
Overspeed testing to prove the actual value of trip ing rate for the valve position signal of tlie valve undet
setpoint of ovcrspccd protection systcms is an essential test.
subsidiarv function of EOVcining .systems.
. The testing is
carried out on an unsynchronised turbine. Initially, the t..i(i. 2.10 A ~ l ~ r n i l i iIUII-"8)
c and lovdi~~g
equip81~ciit
oneiator has to operate a key-locked test switch which 1.3.7 A u t o m a t i c run-up a n d loading s y s t e m s
permits a higher than normal governor speed range Automatic run-up and loading systems are provided f
up to + 13% rather than + 6 % . The normal governor two main reasons:
raise button is used t o increase speed t o the trip set- lilse o f the large number of plant-mounted trans- and load. The method of controlling these is dependellt
points. The full method of testing is described in T o assist the operator in making the complex sequenc providing inputs, careful consideration is given
.
o n tlle type and size of the turbine and the steam condi-
Section 3.5 of this chapter. of checks necessary prior to and during start-up. design stage to provide enough redundancy to tions for which it is designed. Thus large turbines
The abilitv to test the correct functioning.of cach i t fully automatic run-up and loading with high working at high main and reheat temperatures, w h e , ~
T o run-up and subscquently load the turbine in
turbine steam valve is necessary for both on-load opera- ~ilily.Most inputs are either dupiicated by 'master' specified for two-shifting duty, require tlle most
safe and consistent manner. Sophisticated schem
tion and also nrior to run-un. The latter is described as ~ck'transducersat the same measuring point, or sophistication if optimum run-up and loading rates are
can be provided whcrc the rate o f run-up or loadillg
valve exercising, the requirement being to stroke cach functional duplication built into the system to be achieved. A large wet-steam turbine for base load
is faster and less stressful for the machine than a
\,alve open and closed individually, t o test valve freedom of measurements made at entirely different operation requires control of stress in the H P chests and
human operator could reasonably achieve.
o f movement. As far as the operator is concerned this ng points (e.g., separate measurement of inlet rotor, but the L P chests and rotors do oat need any
uses the same controls as on-load testing, with the excep- I IPressure in left-hand and rigbt-hand steam chests), separate control a t all. Direct measurement of stress, by
tion that selecting 'exercise' ensures that the valves can The primary output of a typical system is t o the ba. i f one o f the minor input signals is lost, fully thermocouples measuring the difference between inner
only be opened if the boiler stop valves are closed. speed governor, either to increment the speeder ge lllltic operation may still be possible. The failed and midwall metal temperatures at suitable measuring
or t o the governor in such a way that failure of t llcers are identified t o the operator. points, provides a means ofcontrolling run-up or load
output signal gives a similarly rate-limited change ral minor input signals are lost or one of a changes t o the optimum values. Control is of a ciosed-
1.3.6 On-load t e s t i n g demand. Some outputs of digital state signals provid pair of major signals, automatic control may loop proportional form, acting into the governor as
On-load testing can only be carried out on groups o f interlock or initiation signals t o the governor and aut led such that there is only a fixed safe accelera- shown in Fig 2.10, so that stress is held constant at the
valves in turn. Thus, o n a four-inlet turbine, one group synchroniser, whilst others provide indications t o (if in run-up mode) o r fixed safe loading rate reference value throughout most of the run-up.
o f valves comprises the left-hand front H P governing, operator. The inputs and outputs are shown on One exception to this concerns the critical speed bands
H P stoo.. . I P "eovernine- and I P stoo valves. The on-load 2.10. The inputs to system depend on the degree further signals fail, only manual control may be of the turbine, which are determined by rotor dynamics.
test system includes facilities for checking the operation sophistication, in the most comprehensive case the ble. The turbine governor will provide a limitation Here the strategy is to ensure that there is a large stress
o f all the valve relay inputs. O n H P and I P governing
~ ~
would be as shown. rate-of-change of speed or load, but this will not margin before entering the critical speed band and then
valves the ability to close in response to governor signals The scope of the system described here assumes tha y be safe, particularly if a cold start is in to provide a rapid acceleration through it. Any 'hold'
is checked and also the means of tripping tlle valve in separate operator actions o r sequencing systems bri The operator must then decide whether there signals from the operator (or any other source) are vetoed
response t o the action of the protection system. O n H P all the auxiliary systems necessary for the safe opes ent desk indications t o permit progress, or to whilst within the band.
and 1P stop valves, the normal tripping and resetting tion of the turbine t o a satisfactory state of readin ill a safe condition whilst a repair is effected, or Provision is often made to 'hold' run-up and loading
action from the protection system is checked and also Thus lubricating oil, main and auxiliary CW syste ltt down the turbne. by vibration, eccentricity or differential expansion signals
the facilities provided as back-up for emergency closure. etc., will have previously been brought into servi Itc main requirement o f the automatic run-up and sensed by the separate Turbine Supervisory Equipment
Testing of a group of valves is carried out sequentially, A digital state signal will indicate that each of th 111 system is to limit the thermal stresses within the (TSE). These will also be vetoed within critical speed
starting with the closure o f the H P governing valve, conditions o r prestart interlocks has been satisfied. lc rotor and valve chests during changes of speed bands o r during block loading; outside these bands
133
Governing systems
liniil. l'lic 'bold' wili be released i f the contioliing not effective in tlla stearly state but comes i
l~araillctcrreduces to 80% of the application level, i f crtation transiently \\,lien required. Unloading g
the TSE signal continues to increase above thc 'hold' reduce the steam delnand \+,hen r e q i ~ i ~ e dOtlrci
.
limit, a second Limit is reached at which tlic operator puts, soch as the overspeed test spccd demand or val
is advised to trip the machinc. testing controls, are su,itchcd into service by t h ,
When the turbine reaches syochionoos speed, a num- esafor whcn required. Auto run-up and loading
ber of pre-synchi-ooising checks are ln~ade(e.g., the apply the demands of operator or thc unit colii
Autotnatic Voltage Regulator must be on 'Auto') and system for a change in turbine output to the speeder
then a signal is given to the autosynchronising systcm in the optimum manner. Note that the governor
tllat the turbine is ready and in a safe state to accept be split into two parts - a common processing syst
load. The governor speed demand is then increased or and a number o f individual valve controllers.
decreased automatically by pulses from the autosyn-
chroniser until synchronism is achieved, the circuit-
breaker being automatically closed by the synchroniser
following the operator's command to autosynchronise. ,4 Electronicgoverning
Alternatively, tile synchronisation and circuit-breakei-
Traditionally, the early mechanical and lnecha
138 139
Turbine plant systems Governing systi+~n:.
linearising filnction lhas to be intrutli~cctlioio tllc g o t . A. i\'ilh the anaioguc govciirar, individual valve 11icR1.G. are processed by tlic UCi.. Output c a i n o r a ~ ~ d s
errini lo restore the required iinearity. In ~ ~ a i i i c u i aillc
r, i:~iii)!ii'icrsa c c e ~ tllc
t t1ll.e~tiiglex slpeed channel outpots fsonl the UCL to alter the speed, load or operatint?
i.
moqh
valve arca/steam flow irlatiansl~ipis rion-linear ior v;ai- ti, iiiiil!ogue form and jpiaccss tlicm lo drive 111c s e i v o ~ o ~ o d etake eficcl through the HI.<?, but only iS thcy
lies of pressure ratio (across the valve) leis than l l i u viilvc coils oil each stearn valve. meet thc accelxability criteria stared at base level. This
criticai value. Refer lo Kearlon, gage 628 121 and llie 'Iiir sccond type of governor employing digital forni o f digital governor is shown diagrammaticallp
typical characteristic is sliown in Fig 2.16 (b). Depend. jili~rvssi~ig uscs a completely different configuration. A in Fig 2.17.
ing on the valvc shape, there will also bc a noir-1ioc;ii rrl!!wnlc single-channel, basic speed governor is pro- The BLG haidwareand software are totally standard
SIEA~.I FLOW iclationship between valve lift and valve area, giviii Vlilril lor each steam valvc. At this level, termed the base for all applications whereas, at the UCL, the hardware
WII.I.ANS llNE
the characteristic sllown in Fig 2.16 (c). T o iiiiearis ivcl governor (BLG), there is Ihigh integrity due to the is a standard niinicompulei but the software incor-
these two effects, the steam demand is shaped I> llliplc redundancy and built-in error checks which porates all functions and parameters special to the
linearising circuits t o give a characteristic of the far) liirle closure of the related steam valve in the event application. A particular feature of the design is the
in)
shown in Fig 2.16 (d). Additional versinc effects arisillg valve channel fault. ability of the UCL to provide communications to the
from the lever arrangement driving the valve position A1 tile upper control level (UCL), a single Unit Pro- operator via a multi-character dispiay panel. This permits
pick-off may also be included in the conipensatio~ provides all the other functions required in a the iuteractive prompting of the operator far every mode
LOAD 700% Each individual valve controller has thiee-channcl
in& system. All interfaces t o the operator and of operation and enables him to see the response t o
PRESSURE R A P S~~ P , valve stcam demand signals as input. its function i
,m"a , except the basic signals connected directly to his actions. Additionally, precise details arc given of
1 > CRITjCAI
#-
I
I
I X C A i
t o take a majority vote of these signals to form a s
nal demand, t o provide iinearisation and t o provide
position control of the turbine steam valve, using tile
'>A'41 '.
PLANT
HIOHWAY
(TRIPLEX) -___
lNTER.
computing element in its own right. The module also FACE
"Mi,
includes all the built-in features to ocrmit its use in the
. .
4ii3
provide interchannel communication for channcl
'1/
harmonisation and fault detection purposes. DUMP
SOiENOiD
As with a n analogue governor, '2 out of 3' majority
voting is carried out at key points in the system. Control
variables are entered bv means of setoolnts whlch can @ 8
BI'LED WHEEL
7
be ramped u p or down by the user. High priority d PROBES
STEAM DEMAND -- LINEARISING setpoints such as the speed and load setpoints are avai
CHARACXERISIIC able to the operator by direct access to the process0
Lower priority setpoints, which alter the control cha MODULE
(dl I
acteristics (e.g., droop variation), are accessed via a serial /xunmrl
communications link to the interface processor. Contro
!
modifiers, such as vacuum unloading, are sent t o th
channels from the interface processor via serial link
The system timing, the synchronisation between channe
--------------------------.
U6LLEYELLlOYERNOR 10 OiHER VAiVE MODULES I
VALVE LIFT 100% and the fault monitorine,. orocess
. are chosen t o suit the
:illy poveiiioi iaiill alarnr \vl~iclimight occur. I'hc ap- spool is slio\zn ill the ccntsal position \uith llic contrcil
erator may also seiect particular foons of disglay, for ports blanhcd-oll. This is referred lo as lhc 'null poi)-
example, to faciiitalc turbine run-"1,. tioii'. When llie spool moves, one control goit is opencd
'The Bl,G clianriel includes ail tlie iiard\rare and t o the supply port and tlie other opcns lo the drain goil.
signal routcs froin the speed probe sigrral-bus t o the Thc flow rate is proporiional t o ihc spool dcllectioii.
electrohydraolic scivo-valve o f its associated stcam When connected as a position controller, as showii
valve relay. As well as validating data inputs from the diagrammatically, the null position of the spoiil
\ / / DEMAND POSliiON
UCI., the B1.G incorporates extensive self-checking corresnands t o the condition of eauai 'demainded' aiiii
facilities, i n the event of a fault, the steam valve is 'actual' positions. An)' discrepancy with the positioi,
closed by an independent $means through its own measured by the LVDT causes a current to flow, resulting
faiisafe watchdog hardware. in a hydraulic fluid flow t o the power piston until the
required position is achieved.
T o avoid stiction of the valve it is usual practice
t o superimpose a 'dither' current o n the servo-valvc
1.5 G o v e r n o r valve r e l a y s amplifier output. This is a medit~nifrequency (1 kHz)
The output of the electronic speed governor requires low amplitude current which plays no part in the overall
conversion from a current signal to a mechanical force position control, but keeps the servo-valve spool in a
of sufficient power t o actuate the steam valves. It is tile 'live' condition, the effect being t o vibrate it by a negli-
function of the governor relays to perform this duty. gible amplitude at the 'dither' frequency.
The hydraulic relay has no competitor as a force The null is adjusted by altering the spring bias applicil
amplifier for steam valve actuation. it has the capabili- t o the armature. In the event of a loss of the electrical
ty to develop the high power needed for rapid valve signal driving the scrvo-valve, it is essential that the valvr
opening or closing, without a significant deadband or relay and hence the power piston is driven t o a closccl
hysteresis. position, so a 'null bias' is set t o give a small offset in
The usual arrangement for electronic governing is to this direction. The control characteristic of the servo.
employ a single separate relay for eacll stcarn valve, the valve in this condition is shown in Fig 2.19 (a). Also
conversion being carried o u t by a proprietary plotted (in Fig 2.20) is the corresponding valve internal
electrohydraulic servo-valve. There are many different leakage which reaches a peak at the normal controlling
forms of valve relay, of which three are used o n CEGB point of the valve. The servo-valve is likely to be the
turbines with electronic governing. These will be refer- most sensitive item in the hydraulic system owing to the
red to as Types 1, 2 and 3 in the descriptions which small clearances, especially in the nozzles, and the align-
foilow. Types 1 and 2 use the same proprietary servo- ment of the control edges of the spool with the ports
valve which will be described first. The servo-valve used in the valve body. The hydraulic fluid must be kept iii III3IYE ARM
with the Type 3 relay is inciuded in tlie description o r a pure condition with a low contamination level, othei- PORT
the relay. wise the control edges will become eroded and the inter-
Figure 2.18 shows a servo-valve in cross-section, nal leakare will increase substantiallv. If this leakarc
together with a diagrammatic rep~esentation of how persists, it will result in an excessive fluid cotisumption
it is connected in a simple position-loop controlling and a reduction in tlie fluid pressure, eventually resulting
a primary ram. The feedback t o the amplifier in the in the need to shut dawn the turbine and replace all the
governing system is provided by a linear variable worn componelus.
differential transformer (LVDT). The needs for the control of the fluid characteristics
The function of the servo-valve is to provide a n are described in the section on the fluid pumping system.
output flow rate of hydraulic fluid proportional to the However, a t this point, it should be noted that CEGB
input current. The input current, derived by the gover- standard practice is to provide a test rig in the laboratory
nor servo-amplifier is applied to the coils of a force for checking the characteristics of servo-valves removed
motor thereby deflecting the armature and drive arm from the turbine.
mounted in a flexure tube. The high pressure supply is Before going o n to describe the details of the valve
filtered and supplied via orifices to the boost chambers relays following the servo-valves, it is necessary to sel
and at either end OF the spool. The fluid from each out the requirements of the final drive t o the steam valve.
boost chamber is cross-connected via porting to the re- In the event of a failure of the hydraulic system, the
verse ends of the servo-spool. It travels down the centre steam valve must be capable of closing in less than 200
of the spool and returns to low pressure via the drain ms against any force acting to open the valve. The flow
port. The deflection of the drive arm will block one o r of steam through the valve usually generates a n opening
other of the nozzles and create a high pressure in one force over some part of the travel. Figure 2.21 shows FIO. 2.18 Basic servo-loon
boost chamber and a low pressure in the other, thus a typical case where the steam force acts to open thc
creating a force to move the servo-spool until the pres- valve over the last 70% of the valve lift. A substantial
sures are equalised. The spool deflection is thus pro- spring (or even a nest of springs) is provided t o give
portional to the drive arm deflection which is itself the closing force with a large margin over the steam
proportional t o the current. In the diagram, the servo- valve opening force t o overcome frictional effects. The
142
Turbiiie plant systems Governing systciii:;
1.5.1 Governor valve relay and control unit Type 1
Having covc~.edthc rcquircments, tlic Type I syste~rrwill
i-
be examined in detail. This is used on large reheai
o turbine-generators having four steam inlets to both HI'
4 and IP cylinders, each inlet being fitted with series-
i connected elnergency stop and governor valves. Since
ail control for both the run-up and loading phases is
T O ~ FORCE
L CLOSING VALVE carried out by the govcrnor valves, the stop valves must
PR~NGFORCE *STEAM FORCE)
be fully open whenever the turbine is needed for opera-
tion. The simple form of open/closed control required
for the stop valves will be described separately.
WPUI CURRENT
+ Figure 2.22 shows a diagram of the governor valve
reiay and control unit. The input stage, comprising the
servo-valve and actuator piston controlled by the
INPUT CURRENT. i r n ~
electronic system, is identical to Fig 2.18. The heart o f
ia) ~ ~ , ~ data
, b ~ ~ ~ ~ x the unit is the relay plunger, rigidly connected to the
actuator piston and sliding in the relay plunger sleeve.
In the normal position o f the sleeve, as shown it, the
diagram, the relay plunger is moved upwards by the
actuator piston when the steam valve is required to open.
-
This admits power fluid above the relay power piston
,el ~ ~ , ~ t - b ~data
po,n~ to move it do~,nwardsagainst the force of the valve
spring (not shown), and hence open the valve until such
time as the sweep-resolver position signal is in balance
with the valve position demand. This returns the servo-
amplifier output to zero with the actuator piston and
its transducer restored to the null position. Closing is
effected in a similar manner, with the relay plunger being
17xti. 2.21 Typical govertior valve forces moved downwards to allow fluid to be drained out of
the upper power piston chamber.
INPUT CURRFNi 2 mll Tripping is accomplished by the relay plunger sleeve
L ~ N ~ A R I TSYMMETRY
Y (UI ~ o n ~ ~ n u odea
vr
which, in the running condition, is held dowiiwards (in
B HYSTERSIS ENVELOPE the position shown) against Its internal spring by the
in presence of high pressure tripping fluid in chamber F.
PIG. 2.20 lnicrnat ieakage tiow cbaincicrisfics to meet closing demands. T o assist in this, parti-
~NPUTCURRENT ~f a trip occurs, fluid pressure is lost and the
lily where fast opening is required, hydraulic ac- ,,lay ,,lungel- moves upwards due to spring
111111atoi-s
are often provided adjacent to each steam force. F~~any position of the actuator piston, this will
These requirements are best met by a single-acting cause the power piston to be drained.
A secondary means of closing the valve relays o f ~i~~~~ 2.23 shows a diagram of the emergency stop
power piston opened by hydraulic fluid pressure and
llliliiiturbine unit from the unit protection system valve relay ,,,,it, Examining the operation of the relay
closed by the closing spring. Once the steam force and
,t also be provided. This will be described in detail in the tripped condition, this is held on
spring force are known, it is a straightforward design
later section, but from the valve relay point of view, its bottom stop so that power fluid entering chamber
task to calculate the size of power piston required. Again,
a large margin is provided to allow for friction and, B through port A is prevented from gaining access to
- where appropriate, the weight of the valve and linkage. I- &h'en high pressure tripping fluid is applied
(b, Conlinvovr data
The valve closing rate of 200 ms for full stroke (typical h through port C to chamber D,the relay plunger will lift,
superheat unit) is set by the need to control overspeed thereby allowing high pressure power fluid through port
in the event of a load rejection. The capability of opening S F to lift the relay power piston,
FIO. 2.19 ~o.laadflow characteristics
at the same rate is designed into the valve, as it is needed The dump piston acts as a parallel means of ensuring
in some applications to improve the transient stability that the valve is closed if tripping pressure is lost. IR
of power system networks. However, this facility is the normal running condition it will be held against its
figure shows a typical spring force characteristic and not provided on turbines supplied to the CEGB and the top seat by high pressure tripping fluid in chamber E,
the net force closing the valve. Frictional forces are opening of the steam valve is rate-limited to give a time thus the power piston fluid from port H apart
for full stroke of about 5 s. T o achieve fast opening and from a small warming flow,
kept to a minimum by designing the valve so that side
loads on the valve spindles are minimised. To open the closing, the servo stages which feed the power piston he orifice arrangement permits warming flows to the
must be designed with the appropriate size of porting ality, emergency stop valve relays (and sometimes lower end of the dump piston. In the event of a loss
"alve, it is necessary for the valve relay to supply a
to provide the required flow into and out of the power lor valve relays as well) are provided with a dump of tripping pressure, the dump piston will unseat and
force sufficient to overcome the spring force and any
piston. As well as the porting, there must be pipework having generous clearances and operated by the allow fluid to be drained rapidly from the power piston
steam closing force, such as that occurring over the
first 30% of movement shown in Fig 2.21. o f adequate size t o supply the fluid flow from the high liping system so that safety is assured. into chamber H.
144 145
Turbine plant systems Governing systems
dump piston has clearances one order higher than Figure 2.24 shows the control arrangements for a
ISOLATING 8 ay plunger and other servo components. The governing valve. Again, the input stage, comprising a
RELAY SHOWN IN VALVE OPENING POSITION FLUSHING
BLOCK 'lity of its seizure in the event of widespread fluid servo-valve and primary ram, is positioned by a servo-
ination is therefore remote. valve amplifier using the LVDT connected to the primary
orifices fitted to the systems of both the gover- ram as feedback. In this case, however, the positioning
and stop valves ensure appropriate rates of valve of the main ram is accomplished by mechanical and
-
DRAIN TRIPPING POWER ACCUMULATOR el in normal operation and prevent excessive rates hydraulic means without a further electronic feedback
7 1
TRIPPING FLUID FI UID IN FLUID IN TEST iilve travel when on-load testing. loop. The primary ram provides the input onto a
c arrangements of trip and test valves shown permit feedback linkage, the other end being connected to
POWER FLUID
oad testing of the valves in all their functioning measure main ram position. A pilot valve is connected
DRAIN FLUID to the linkage so that, with the spool aligned with its
ports, the main ram will be in equilibrium with the
ELECTRICAL CONNECTIONS
primary ram. A dump valve is interposed in the outlet
(2 Governor valve relay a n d control unit Type 2 port o f the pilot valve supplying the main ram. In the
c 2 control units are fitted to similar machines to normal operating condition, if the primary ram lifts, it
PLG.2.22 Governor valve relay and control unit (Type I) c 1 , but in this case run-up is carried out on the H P will lift the pilot valve, allowing fluid to flow at high
alves, with the governor valves partially open. The pressure to open the main ram. This will move
ol units for H P stop and H P and IP governor valves downwards to open until the main ram position
t lerefore similar. The IP stop valves require simple corresponds to the primary ram input and the pilot valve
tr/closed control only. is restored to the null condition.
Governing systems
Turbine plant systeins
arc of a sgiing-loaded type, set lo ope,, at a defincd
io\i,il itgainst its seat against ilic opening spring. IprCsSIIIP.
1: piutcciion fluid presstire is lost, tlie dunljr valve in addition, on sonle machines, there is a need to
VaLvE SPiWDLE FORK END
ti~,~.iii!e~l by its spring and relesses thc fluid supply supply relatively small release valves to release steam in
Iiic niiiin ram to drain, thereby closing the valve rapid- the rehealer system to atmosohere when the governor
'I iii. il11111pvalve iowcr seat is also closed by the spring valves and iiiteicegtor valves close soddenly in an emer-
liit~scuuing off the higii pl-cssure suppiy f r o n ~tbc gency. Allhougil the steam may not be at a sufficiently
111lu1o~ adjacent to the valve reiay. The dump valve high pressure to cause the relief valves to open, any
iolao be operated by an electrical signal to the residual steam trapped in tlie H P cylinder and reheater
' alve in the piotectio~i fluid line, thereby could give rise to overheating of H P blading due to
back-up means of tripping individual valves. churning in the relatively high density steam. The release
., the solenoid valve maintains thc tripping val\,es, located in the connecting steam piping between
to the remainder of the valves, but locally the reheater and the interceptor valves, are signalled to
the high pressure fluid above the dump valve open under the appropriate conditions to prevent this
in, causing the valve to trip. from happening.
'The relcasc valves may be hydraulically or pneu-
matically operated. Where an electronic governor is
Governor valve relay a n d control unit Type 3 fitted, they arc opened by energising a solenoid. Condi-
ys are similar to Type 2 but employ a different tions which signal their opening are:
nd servo-valve, known as a
. The primary ram displacementis directly 0 Loss of tripping pressure.
rniil ta the input current to the servo-valve. The
e High acceleration detected by governor.
I\,c employs a similar principle and configura-
!hat described in Fig 2.18, but feedback of ram Closure of ail interceptor steam valve relays.
$11 is introduced magnetically onto the force motor
llil~actsfrom the armature deflection pl.oduced by
n coils. The primary ram is used to drive the These conditions cover circumstances of machine tripp-
I I I I I I via a feedback linkage and pilot valve as in ing or turbine load rejection without tripping, where
relay, but there is also feedback of main ram churning could occur either during rundown of the
a the servo-valve amplifier by means of an machine after a trip or during the period of interceptor
Itis ensures accurate fine control over the full valve ciosure on load rejection.
i t ! !ilIo\i8any entrained air to be rclcased. Should variable-delivery cal~abililyniakes the use o f a spill-type
li:ial I ~ c allowed to detcrioratc for any reason or prcssu1.e control valve unnecessary. A cross-section of
boiier feed pump Lurbine is associated with the nyain described as tlie needs of the basic component. i lliere he a fault causing excess air lo be entrained a variable-swashplatc pump is shown in Fig 2.28. It will
unit, its control and protection systems are powered by considered. I'liiid returned to the reservoir, the air release be imnicdiateiy apparent that this is a much rnoic
the same supply unit for convenience. Screw-type pumps may be of the subxnersibic k i l l lllay be affected and excess air could be supplied complex device than the screw-pump shown in Fig 2.25.
Phosphate-ester fluids are used because o f their mounted on the reservoir top piatc, or they ma) However, since the flow can be made to exacriv match
superior thermal stability compared with water-based sel~arateiymounted. Axial-piston pumps and screw-ty the system requirements, the reservoir, pipework, coolers
fire-resistant fluids which would be unsuitabie for the pumps require that the pump suction pressure is adeqii~ and system filters can be scaled down accordingly. From
high temperatures norinally found in thevicinity o f steam to provide a lengthy service life. Failure to meei I Fig 2.28 it can be seen that the axiai-pistons are forced
valves. They also have the advantage that their viscosity suction pressure requirements will result in cavitation to reciprocate in their cylinders by rotation of the pump
and lubricating characteristics are similar to lubricating erosion of the pump components and eventual break-il barrel at constant speed and the movement of the slippers
oil, so that conversion o f earlier units running on high of the pump, with the release of numerous metalll against the fixed angle of the swashplate. The piston
pressure oil is possible with some care, subject to the particles. This would necessitate shutdown of the wliol displacement and hence the pump output can be varied
fitting of compatible sealing maleriais. These fluids also turbine-generator to replace the faulty pump and t o llur by tilting the swashpiate. Fixed inlet and outiet ports
have the necessary fire resistance and provide for a long the entire hydraulic system. supply and deliver the hydraulic fluid. The fluid is
service life from the system components. They can be The phenomenon of cavitation results from the cli~ pumped against the system resistance and a pressure
maintained in good condition for an indefinite period acteristics Of air in the fluid. Tlic solubility of controller senses the outlet pressure and modulates the
without the need for replacement. proportional to the fluid pressure, so that air b swashplate to regulate it to the desired value. Some
The fluid system is designed to permit either on-line present in the fluid at low pressure become dissoiv pressure oscillation is produced at a frequency equal to
when driven at constant speed. In these rotation frequency times number o f pistons, but this is
damped out by a local accumulator.
1.6.1 Filtration
lil? control valve and the excess flow is returned Filtration is an essential part of any fluid supply system
c r~servoir.Again, a separate pressure relief valve a n d the standards required are set by the smallest
investigated promptly, otherwise coinponent life will be atmospheric pressure, to colne out of solution in lhc ihr provided as an overall protection. A non-return clearances in the system - usually the servo-valve. The
very seriously affected. suction pipe and form bubbles. At some point within is fitted in the outlet flow of the pump line, so purpose of the filters is to reinovedebris from the system.
In basic form, the fluid supply system comprises a the pump, the pressure increases to the extent that 1 Iwo pumping lines can be coupled together. I t is quite normal for debris to be continuously generated
fiuid reservoir and a pump to deliver high pressure air returns into solution with a n abruptness which cau. lougll only one line is needed for operation, the within the system, some from wear processes by the
fluid. To ensure high availability two pumping lines collapse of the bubble and damage to any metal in 111 Iby line can be brought into operation either man- pumps and other moving components, some introduced
are needed, one being the duty line and the other on vicinity. Although such cavitation is usually avoided I> or automatically by sensing loss of pressure in externally via air entering through the reservoir breather
standby. Pumps are either of the screw-type (for use in good design, the user must be aware that blockage o r in the valve relays. Debris will be in the form of small
systems up to 80 bar) or of the axial piston variable- any suction filters could lead to a similar effect. Also,
delivery type (for use up to 150 bar). Additional system the reservoir is provided to give a definite fluid dwell
- in
uarticles susuended in the fluid and will be irreeular
size, shape and chemical composition. Filters are usual-
further rise in fluid temperature. Phosphate- ly given 'nominal' and 'absoiute' ratings, suggesting
~. that
ds have a high temperature gradient o f visco- n o particles larger than the absolute rating are passed.
1 40°C,the fluid has optimum conditions for tlie In fact this is not the case. Because of lack of uniformi-
mp. At higher temperatures, the viscosity will ty i n the size of passages in filters, a whole spectrum
o f particles will be passed, although the general
characteristics ensure that there is an increasing probabili-
ty that the larger the particle, the more likely it is to
ufes, the fluid starts out as extremely viscous b e 'captured' by the filter.
If a sample of fluid from the filter outlet is ex-
amined, its contamination level is described by the
number o f particles greater than a given size encountered
these reasons, coolers are necessary in all systems in 100 ml of fluid. With a 5 micron absolute filter in
, insome systems where cold-starting is essential, circuit, typical sizes of interest would be 1 micron, 5
ers may also be required. Coolers are o f the cross- microns, 10 microns, 15 microns, 25 microns and 100
-TO SYSTEM
double-pass shell and tube type, using demin- tnicrons. The total number of particies greater than each
o f these sizes would be recorded and if plotted on a
iog/(log)' plot (as shown in Fig 2.29), would give a
nearly linear form. Using these techniques, various con-
/ \ i~timers~on type, fltted either m the reservoir or m a tamination classes can be defined. A number of standards
SUCTION FILTER PUV.P SUCTlMi PUMP OISCHkRGC
PORT PORT -line. A schematic diagram of a typical pumping a r e in existence; the one gaining some international
111 is shown in Fig 2.27. recognition is the American NAS 1638 Standard, based
ems employing axial-piston variable-swashplate o n measurements taken with a n electronic particle de-
have similar arrangements for boost pumps, tector, using a iight-blocking principle. Another standard
Fio. 2.25 Pump suction arrangement for a separalely.moun1ed Pump I' filters, coolers and pressure relief valves, but their in widespread use in the UK is one published by a
151
SCREW PUMP AND M ~ A R
S S E ~ ~ ~ ~
AUXILIARY SCREWS
I
INSERT
I
organisation, Thermal Control Company Ltd Differential pressure drops across such filters are normal-
.hlo~~ England.
, This standard is based on extrac- ly alarmed and provision is made for on-line filter
100 ml sample of fluid from the system, passing replacement. Prompt maintenance in these circumstances
,ugh a filter membrane, and then comparing the enables the fluid cleanliness to be maintained and helps
c under a microscope with a series of reference to ensure trouble-free service from the system
representing different classes. components.
ause of the different measurement techniques and As well as particulate contamination, which is readily
f defining the 'size' of a n irregularly-shaped parti- visible - albeit under a microscope, contamination by
lie standards lay down different acceptability criteria water or chemical means is also possible. The former
ernis of numbers of particles) for systems incor- is likely to cause a n increase in fluid acidity and possible
CONE I
MRiN
orating fine clearance servo-valves. The system user is
i~ilvisedto opt for one of the available techniques and
formation of gels or salts, which cause components to
stick. Chemical contamination can result in severe
SCREW lihc il on a regular basis. Results taken from a normal electrokinetic erosion of fine clearances, especially if a
system then provide a reference point for what is abnor- source of free chlorine ions is introduced to the system.
2.26 Typical sere, pump IIIIII, which therefore requires investigation. For further information on these effects refer to Nelson
In a system incorporating components with clearances and Waterman (31.
01' 2 microns it would be normal practice to fit 0.5 The likely effects on turbine-generator operation,
iniicron nominal filters in the system to give typically if contamination is allowed to persist, would be high
NAS Class 7 or Thermal Controls Class 3 conditions. leakage flows through the hydraulic system - even-
Turbine plan? systems
AXIAL PlSXlNS
FRONT
emergency stop valvcs and the associated govciriing tllerc ~vouldbe gl.obiems of crcep vatchcting.
valves wliicir arc housed in steam ciiests. In order 'The iaaivcs clasc onlo i-enlovable-plate typ
lo reduce the lliermai stresses and lheilce ihc risk of which can be replaced when worn or damaged.
thermal fatigue, these sleani chests are of simple shapes scats are secured in place either by tnealis of a sc
and are manufactured either from closed-dic alloy steel ring or by screws tllat are locked in piace, and s o m a
forgings welded together, or from alloy steel castings. the seats are additionally prevented from rotating \ui
Similar steam chests containing emergency stop valves radial dowels. A diffuser is generally provided; ti
and interceptor valves are used in the hot reheat pipes either integral with the valve seat or machined as
from the reheater to the intermediate pressure cylinder of the valve chest.
o f the turbine. These steam chests are invariably The mating faces of the valves and their seats are faccll
manufactured from alloy steel castings, which are thinner with Stdlite in order to resist wear, mainly due to erosio
but larger than the I I P steam chests because of the much by steam. Such wear is most likely to occur when 111
lower steam pressure conditions. valve is cracked open: a jet of steam is then propelle
The steam chests are usually mounted alongside the at liigh velocity by the large pressure differential throuplr
turbine: on 660 MW machines they are either o n swing the narrow port opening. The Stellire facing also protects
links or on springs to accommodate movement due to against impact damage when the valves shut normally,
thermal expansion and flexibility of tlie H P steam mains. or during frequent liigh speed test closures. Cushioning
Tlie steam chests on 500 MW machines were keyed to devices in the relay system or slow motion testing can
be used to alleviate this.
The valve spindles are supported and guided by means
freely witli the steam piping. of specially treated alloy steel sleeves in the valve covers,
On modern large machines, the usual practice is to the materials of the spindles and the sleeves being selected
have four steam mains together with four emergency stop both to avoid excessive oxide build-up between 30 000
valves and four governor valves, two on each side of I1 overhauls and to ensure the minimum wear of thr
tlie turbine. On some of the early 660 MW nuclear components when subjected to the forces imposed 011
turbine-generators, however, the two stearn mains on the valve from steam, vibration and the operating gear.
each side join into one large steam chest, so that there Tlie bushes are securely locked in place, the clearancc
are only two steam chests in total. These steam chests. between spindle and bush being suitable for the operating
conditions of the valves. In order to prevent steam
leakage to atmosphere, there is a gland steam leak-off
used for the reheat steanl chests at the 1P cvlinder. sub-atmospheric connection from a chamber between the
On some current 660 MW machines, the stiam chest spindle and the bush to the turbine gland steam system.
arrangement is such that there is one steam chest on each Steam leakage from emergency stop \,alves is also
side o f the machine, which has an emergency stop valve prevented by means of a stellite back seat o n the back
at each end and the two governor valves are co~lnected of the valve head against the lower valve spindle bush.
to the common chamber between the stop valves. A
typical arrangement is shown in Fig 2.33.
Another steam chest arrangement employs the reverse
flow type of governor valve (see Section 2.6 o f this
2.3 Cover seals
chapter), permitting a more compact arrangement of stop
and governor valves. This requires two steam chests each On large modern H P valve chests, it is difficult to
side of the machine, which have sometimes been inter- provide an adequate bolted joint between the valve
chest and its cover. Current practice on these chests
connected before the emergency stop valve.
generally is to utilise pressure-assisted seal joints si-
milar to that shown in Fig 2.34. On reheat steam
chests, bolted flanged joints are used. These joints
usually have gaskets that are either of the Metaflex
2.2 Steam chest materials type backed up by a metal-to-metal joint face, o r they
employ an lnconel ring. All such bolted joints are
As stated in Section 2.1 of this chapter, the chests are
designed not to require retightening for at least 30 000
manufactured from alloy steel. On current 660 MW
machines operating at 565'C, the material is usually hours of operation.
0.5Cr Mo V steel, and on some recent machines operating
at 53e°C,the chest material is 2.25Cr steel. However.
011 larger unlrr operar~ngat 165'C'. it nin) be ncressar) B
to utl11.c highcr-<hrunir. f s r r i t i ~,tech xirh impro\ed 2.4 Steam strainers B
creep resl,tatl;c in order lo avoid clndul) r11i.k :hc,t ualls In order to prevent solid particles of foreign matter from 8
s hi;h wuuld prej~diceuprrational flr.xib~lit).Auctdnitic being carried into the turbine by the incoming steam and
sterlc would proside s gredrct impro\emml in crecp causing damage to the blading, each stop valve is
resistance but experience with these has shown that surrounded by a cylindrical strainer which has many
158
i
stearn
chests, valves and loop PiPC"
Turbine plant systems
. i i w L PIN
"&LYE SPRING
M A ' N E E L T governor
T ~ ~ VBIYCS provide accurate control nl I
steam flow rate entering the turbine, thus controlliii~iI
generator load when the machine is synchroniscd I < ,
grid. The present practice for the control of the st
flow rate during turbine run-up to speed is also I <
the governor valves; however, on earlier 660
machines and also on 500 MW units, run-up is can!
HALF COUPLING
ed by use of the emergency stop valve pilot-valv
conjunction with the governor valves. O n 660
I:,<;.2.34 i ~ r e i s ~ ~ r e ~ i l ~seal i ~ t ~valve c o r c ~jumi
8 1 ~type machines, the interceptor valves can also be used
governing mode, if required, to use the stored en
in the rcheatei to provide a quick response Lo frequ
variations
Small diamctei hoies, ranging frolll 5 - 2 mI11 depending ~h~ diameters valve opening are gei~erally EAM LEAK-OFF *
011 the o~anufacturer. Even particles of this size call culated to give maximum steam velocities o f about
cause serious blading damage, it is tflelcfore esserltial m ~ for
s ,lie valve head designs are such I I ~ Z
that a thorough steam blow o f all P ~ P C U ' O is~ ~carried they are to steam-induced vibration duii~ri!
STEAM CHEST
paEssuaE TAPPING *
As with the stop valves, it is essential that these v
close in an emergency; they are therefore similarly o WER SPINDLE BUSH
STEAM INLET
DOWEL FOR
.--VALVE SEA7
V A L V E STEAM CHEST
BUSH RETAINING-
SLEEVE
PRESSURE BALANO
ilkloicc is provided by separate ove!.speed trips. The .oine.
. The turbine is then triotlcd
. . on low iobricating-ail
i l l $ ijiur cannot overspeed when the generator is connected DSCSSIIIF.
~ i i i i i in synchronism with the electrical power syslenl in thc event of a compicte failure of the turbine gover-
iiri\:ork. The turbine is at risk during rurl-up and also ning system, i.e., failure of inlorc than one channel or
wiici, a disconnection occurs ori-load. Since disconiiec- a failure whicii renders the governol. opci-ative, the gover-
PRESSUREBALANCE
tioil can occur as a result of another tritl function, - to send trin-initiating signals lo the protec-
nor is desiened
tion scheme.
Water ingress to the turbine can occur due to tnalfunc-
circuit-breaker and the closure of the steam lion of boiler or feed controls, especially during a change
in load. In this case, wet steam or even slugs of water
could be introduced through the HP steam line. The
degree of hazard and the type of protection required
first close the turbine steam valves. Whcn the depends on the boiler type and steam conditions at the
flow has reduced nearly to the no-load value, the inlet to the turbine. When a drum boiler is used to supply
Itor may be disconnecred from the power system superheated steam, turbine protection may not be
ol-k without risk of overspeed. This is known as a necessary, providing loss of boiler firing is adequately
LPZ CYLINDiO
ry B trip and is particularly important in the detected and alarmed so that the operator can take the
f water-ingress trips or a manual trip follou,ing necessary corrective action. In the case of a once-through
an incident. if the event caused distortion of the boiler supplying superheated steam, it is necessary to trip
I valves and they failed to close, simultaneous the turbine on low steam temperature before saturated
LPI CYLINDER nection of the generator would promptly lead steam conditions reach the turbine. The dangci is that,
if not tripped, severe distortion could occur, causing
sits connection, the unit can bc safety shut down seizure of the turbine steam valves or fracture of the
turbine blading. Once-through boilers supplying dry
saturated steam represent less of a hazard due to chill-
FIG. 2.40 IP/LI' crossover pipework ,y B trips. These include governor failure and ing. However, the sudden ingress of wet stcaln could
ring oil failure as well as overspeed, watcr-ingress result in severe thrust loadings on the turbine and
nd the operator's emergency stop button. blading, so the plant must be designed to accept this or
be protected against it. Water ingress ,nay also occur
Some early 660 MW machines with pannier condensers Excessive temperature differentials.
used both crossover pipes and cross-under pipes. Similar from feedheating plant via hack-flow to the tapping
bellows arrangements were used to accommodate thermal Excessive eccentricity. points on the main turbine. The arrangements to protect
aaainst this are discussed in C h a ~ t e r3 on feedheating
plant.
If the plant is manned by responsible operating staff 011
a continuous basis, the last four items can be monitored
by supervisory equipment having preset alarm levels. Thir
to as Cotegory A trips.
3 Turbine protective devices allows the operator freedom to n~anoeuvrethe operatino 3.2 Protection scheme
conditions to reduce the dangerous condition. If unablr
The trip-initiating devices as described in the previous
.
to do this, the operator must trip the plant manually.
paragraph will be of two types:
3.1 Possible hazards The other dangers have more immediate effects
the plant and are generally detected by special trip g is excessive, the last-stage 1.P turbine blading
Devices where an electrical changeover contact
Abnormal operating conditions, including those where W I I ~ Creleases
~ the protection system hydraulic press omc overheated and damaged. Since the prime
operates.
the turbine and its systems are not working as designed, and thus closes all the steam valves and disconn of poor exhaust-pressure is likely to be loss of
ow, it is usual practice to provide high exhaust Devices capable of direct tripping of the hydraulic
re unloading gear as part of the governing system fluid system.
encountered are: effort to reduce turbine load and avoid tripping.
The result of a trip initiation will be to close the turbine
Overspeeding.
steam valves and trip the generator circuit-breaker,
Lubricating oil failure. having regard to the division into Categories A ond B.
from these devices, which are described in the re1 clow a predetermined value. Note that there is a The tripping system includes redundancy, so that the
failure of any one element in the system does not prevent
tripping, and is also designed to avoid spurious tripping
as far as possible. Figure 2.41 shows schematically the
Governor failure. Overspeed would have serious consequences for main functions of the hydraulic tripping system much
both plant and personnel, therefare the protective simplified. The interfaces with the electrical tripping
Water ingress to blading.
arrangements have been designed to eliminate any system and the stop and governor valve relays are also
Thrust bearing failure. possibility of a dangerous overspeed. shown. The diagram does not show the redundancy
The turbine governing system provides the first lirie associated with the electrical tripping system, which is
Excessive vibration. of defence against overspeed and t h e second line 01' described later in this section.
165
Turbine plant systetris 1-urbine protective devices
CIiapt<:$ 9
-...., ..
iii'i.iqic:cd trig, latcb levcr and t 1 . i ~lpii~iigerare in ihc contact5 ojlciatiog ihc siixi1ial.y relay 01'. Individual
I t i i i i t pedestal of necessity, liowcuc~,ail llic otlicr iinils sets o i contac~si l l tliis iclay theii encvgise llie solenoid
ing the emergency lrip i,alves, lest inter.lock, diio~ovalvcs of each stcao~ijalve relay. these being o f
11sand reset faciiities are impletnented by means Type 2.
piieiary co,npoi~ei~ts mounteil on a largc manifold Circuit I shows a typical CalezolyA tripping function,
, iji. i outside the ti~ihinecasing. Ihigl, LP turbine exhaust pressure, sensed by pressure
s\\~ircliesPS6 and 7. Tliesc are shown in the norn~al
running position; ivlien there is a trip conditioii, PS6
closcs and energiscs flag i-clay AXRI.1. Providing I'S7
3 Electrically-signalled trips also closes, TR3 is energiscd through contacts AXRI.l
ectrical tripping scheme is also shown in outline and AXR1.2. If the 'front' system is being tcsted, the
2.41. Any electrical trip function is signalled test switch will be in the T1 posilian and, instead of a
front and rear trip solenoids via duplicated trip initiation, lamp LPI will illuminate when PS6 and
rcli,!, contact systems. These relays are segregated into PS7 close. Test facilities, interlocked with the test switch,
('ulegory A and Category B trips. Separate contact sets enable atmospheric pressure to be supplied to pressure
r , l l tllc same relays trip the cil.cuit-breakers directly in switches PS6 and PS7, thus comprehensively testing the
1l1r case of the Calegory A trips and via low forward- functioning of all components through to the lamp.
Imwcr relays in the case of Category B. To enable Circuit 4 is very similar, in this case PSI and PS2
IIIP mechanically-signailed trips, e.g., the overspecd provide the Category B low rclay fluid pressure trip
Irii,, to signal opening of the circuit-breakers, loss of shown in Fig 2.41. Auxiliary relay TPR2.I is used t o
nlotection fluid oressure is sensed bv setsof Dressure nrovide other interlocks as well as trips. One contact,
p a\ritches that provide further inputs to initiate Catego,)' ?PKZ.I is connected it1 parallel with other Calegory B
:$,
I? isit~svia the low foiward-power relays. The uressure trip contacts to energise trip relay TR7. In torn, contacts
,.itjitches may also be used to trip the boiler and auxiliary on this relay, which are not shown, initiate ciicuit-breaker
, I I1 (lcvices, e.g., bled-steam non-return vaives, dependent lripping via the low forward-powcr rclay.
INTERLOCK "NIT
t oil the applicatioii. The 'I out of 2' tripping concept is provided by the
FROM F R I
SUPPLY UNll The low forward-power relays use power sensing via duplication in the rcar channel circuit, where complete-
voltage and current transformers to determine when the ly independent sets of transducers initiate tripping.
NOTES
power generated is less than about 1%. This ensures that Because o f the configuration of the turbine hydraulic
i SHOWN INTHE NORMAL RUNNING UNiRiPPEO CONOiTioN Ihe steam valves are very nearly closed and that an tripping system, a trip occurs as soon as any one of the
2 ISOLalNGAND HESET P A C I I i i E S NOT SHOWN
ovcrspeed cannot result when the circuit-breakers are turbine trip solenoids is energised.
opened, even if no further steam valve closure occurs. The examples chosen to illustrate typical Category A
FIG. 2.41 Hydraulic trip anil - simplified block diagraiii The above general principles may be implemented in and B trips have each used two pressure switches in each
iiifferent ways with either 'I out of 2' or '2 out of 3' channel. For other tripping funcctions some other forin
ii:ilundancy. Although the hydiaulic tripping system of redundancy may be appropriate. Thus, in some
previously described is a 'I out of 2' system, it will be au~lications,
.. hinh L P exhaust temperature is used for
The heart of the unit comprises two sets o f emernen- ditional hydraulic units before the subsequent turbine secn that compatibility with a three-channel electrical tripping, the sensing being carried out in each flow of
.!IrlP \ 3 1 \ ~ i,l l 1 Illr l ~ l l 1 1 1 ~ : 1 ~C.i.:. C l \ . l ; ~ i l < ~ l1 3 l t i l . run-up. For clarity, these have not been shown on the system is still possible. Each of the two systems is each exhaust. For a six-exhaust machine, 12 transducers
ill .,I . , ! ~ . r q > e : J t r ~bolt,
p ri~(,t~ntc.I
I:, ihc LIIYIII! ~ ~ i ~ L l . r . i diagram. ]now described in detail. wouid be used, six in each channel combined in three
. h a i ~ .l.lujd .XI !I.&IIprr,>brc L~ ~!LI)I,II:.I to rlw dn,cri::n. - T o exercise the system and ensure that any faults in The redundancy of the 'I out of 2' system is more pairs to provide immunity from spurious tripping.
cy trip valves so that if either is caused to trip, i.e., move the tripping system are identified and rectified without complex than a simple interpretation of this title suggests. Figure 2.43 shows the second method of implemen-
to the left, protection fluid is connected to drain via pipe delay, regular on-load testing is recommended. To test Additional transducers are incorporated in each of the ting the turbine-generator electrical tripping scheme using
A or pipe B and closure of all the turbine steam valves the front emergency trip valve, the interlock unit is two channels so that at least two transducers per channel, a '2 out of 3' majority voting system. Using this techni-
results. Control fluid pressure is maintained to avoid shifted so that the left-hand ends of the trip cylinders or four transducers in total, are employed. Series- que, it is virtually impossible for any single component
excess fluid consumption from the FRF supply unit. are isolated from each other. T h e same operator action connection of the two trip-initiating contacts in each or transducer failure to cause a spurious trip. Likewise,
The emergency trip valves are operated by spring- also blocks port A on the front emergency trip valves. channel permits any single transducer to fail without a single failure will not prevent a trip from occurring.
loaded trip plungers. When in normal operation, the While in this condition, any solenoid, manual or over- causing a turbine trip. However, no single failure of an Auxiliary contacts, not shown in the figure, give the
spring is held compressed by a spigot held in place by speed trip acting on the front trip valve will cause the electrical component will prevent a genuine trip from operator an alarm if there is a failure and inhibits on-
the Y-shaped trip arm and latch. Initiation of the emergency trip valve to move to the tripped position. occurring. Identification of faulty components is picked load testing until the fault is rectified.
overspeed trip, the manual trip or the solenoid trip causes Due to the isolation, protection fluid pressure is not lost up either by supervision circuits or by routine on-load The circuit is very simple, with the main functional
the spring-loaded latch to be released. H i g l ~pressure
protection fluid in the chamber at the left-hand end of
-
and the unit will run undisturbed throuehout the test.
A genuine trlp occurring during the test period will be
lesting of the trip-initiating transducers of the 'front'
and 'rcar' systems in turn. Figure 2.42 shows a simplified
blocks being.triulicated
. or duplicated as necessary. The
transducers are connected in three similar auxiliary tripp-
the emergency trip valve is thus released to drain and initiated by the rear trip valve and will result in the unit trip circuit for one Calegory A trip, one Category B trip ing circuits. In auxiliary tripping circuit 1, PS7 provides
tripping in the normal way. and the operator's emergency pushbuttons. The 'front' a typical Category A tripping function such as high L P
The detailed implementation of the hydraulic tripp- and 'rear' circuits are completely independent being turbine exhaust pressure. It operates auxiliary relay RL7
mid-position, operation of any one overspeed trip will ing system by each turbine manufacturer will vary. GEC powered by two different DC battery supplies. It is through a flag relay. The equivalent auxiliary relays
cause both emergency trip valves to move to the tripped Turbine Generators, mounts the complete unit in the necessary to energise the turbine trip solenoid SOL to in channels 2 and 3 are relays RL8 and RL9. On the
condition. front pedestal, with a short direct connection to the initiate a turbine trip via the emergency trip valve (circuit right-hand side of the diagram there are four circuits
The trip plungers and latches must be reset by ad- overspeed trip units. In the case of NEI Parsons, the 2). As a back-up, circuit 3 shows a duplicate set of each using a set of contacts from relays RL7, RL8
166
Turh~nepldnl systems
TRIP
-- CATEGORY h
TRIPRELAY
TR3
TEST SViTCH
LPI
I
I /
AUXILIARY RELAY
TRiP
CiHCUlTl EMERGENCYSTOP
PUSHBUiiONS
TRlP
CIRCUlla . TO OTHER
CATEGORY 8
r__
CATEGORY B
TRIP RELAYTR7
li~:.l\umentation associated with protection and e Tlirust bearing ,*'ear This measurement ensures that
cc>tiivolequipment. thrust pads wear is maintained within safc design
limits.
a i\i!,tiiimentation to p ~ o v i d cpost-incident records.
I'hc teo~l~eratures and pressures of steam and water in llritish Standard 752. Sincc many ol thc transdiicers I Instrumentation associated with protection Acconimodate the thermal capansiorr of tllc stsuctilre
are o~casuredlo confirm tliat the plant coinponcnts are have to be ixecalibsaled, UK practice requires that l l i t *md control e q u i p m e n t conditions.
and stalic parts of tiic platit under all ollerating
aperatiiig efficiently and in the intended manner. For illant is built with piovisioii for fitting the instrumei,ts
exampic, measiirclnellt of the steam and water condi- 'I i i i , comprises imtrumenlatioii used in conjunction
when a test is required, Thus thc manufacturer sup"lies
tions at the inlet and outlet of a feedwater heater enables
~ ~
ivilli ;i control loop, either locally or for tlic )nail1 plant Raise thc plan1 above the ~ u r b i n chouse floor to
pockets for insertion of tliermocouplcs and pressule
an operator lo confirm its satisfactory operation. ,.iiiituoI systems. The turbine governing system (de- provide access for electrical connections and pipe-
tapping points up to and including the primary isolatinji it.tibed in Section I of this chapter) is an exaniplc o f
Unsatisiactory operation is unlikely to prejudice the valve. Where possible, stcam and coniensate flaws ale work, Bottom connection of the main stcam pipe-
continued running o f the planl but does affect its ef- l l b ~latter, whilst any local control loops not covered work is particularly desirable to avoid dismantling
measured by differential pressure devices and so tlic
ficiency. This category of instrumentation therefore Iby Auxiliary Systems form part of tlie former. These pipcwork during maintenance and to prevent the
provision made on the plant as-built can again be confil~.
Ioriil controls are used to onerate plant prior to a unit
draws attention to maintenance activities which are
efficiency-related.
..~ .
ed to fixed orifices with suitable tannine ooints. The mail,
condensate flow measurement is one o f the most critical.
aluii-ul~or following maintenance, where operator action
pipework draining into tlie turbine. The height o f
the turbine abovc the basement floor level is partly
Alarms are derived from some parameters in this Srolrl the control room is not necessary. Also, some plant determined by thc need to accomnlodate the con-
Provision is generally made to insert the calibrated orificc
category, for example, steam temperatures upstream of tcijiiires controls which may not be immediately con- denser and condenser neck, when an underslung
plates in sections of condelisate pipework parallel to the
the H P stop valves. These alarms are less critical than rlcotcd with the minute-by-minute operation of the unit. condenser is used, and partly by consideration o f
main path. When tests are to be performed, the maiii
those derived froin supervisory instrumentation and I'iirtlier local controls are sometimes needed to permit condensate drainage iequiretnents. The bled-steam
path is isolated and ail the flow passes through the orifice
i t detailed fault analysis to be carried out following
thcrcfore the alarm processing may be carried out plates. Provision is also made for the connection of ;i piping should drain away from the turbine and the
exclusively in the data processing computer. Steam iili:l~tificationof a problem in the central control room. drains from L P heaters must be returned to the
transmission-type dynamometer to messure the power
temperatures upstream of the turbine H P stop valves are supplied by the boiler feed pump turbine (if fitted). condenser. For this to be achieved with gravity
used to provide data for the long term history. In some plants, a more limited range o f parameters drainage requires a certain minimum height differ-
Some o f the parameters in the efficiency insfrwnoi- 8.1.6 Instrumentation t o provide post-Incident ence between turbine and condenser hotwell.
is measured on a permanent basis to provide a routine
ration category are used for the heat rate test instl-umeri- tocords For inain turbine-generator plant, these require-
on-line efficiency monitoring scheme, usually combined
tation identified in the condirion nioniioring category. with boiler plant. Such schemes inevitably provide 'ilic detectors required to provide these records are ments have been satisfied by eithcr reinforced concrete
The rcquil.ement for accurate, calibrated instruti~entsfar less-accurate illformation than would be obtained from ileiived from other categories of instrumentation, mainly or steel support structures, which are described in
a heat rate test often pl.ecludes the use of the same plant acceptance tests, using recently calibrated trans- liilin the supervisory instrumentation. These records more detail in later sections.
transducers as tliose used for efficiency instrumentation. ducers. The value of on-line monitoring is that it enables )xovide critical plant data for desisnated periods be- It is also necasary to monitor the movement of
trends to be identified and appropriate maintenance work l u r c and after a n incident to enable the cause to be Uhe foundations througliout the life of the station.
scheduled. Where alternative plant operating strategies ii~vestigated. Thc recording is initiated by a unit or Settlement of the whole foundation in service is
4.1.3 Auxiliary s y s t e m instrumentation pI23nt trip (for example, the trip of a feed pump), or not very serious, provided that it is not large enough
are possible, for e x a m ~ l c ,selection of a standbv feed
These instruments confirm the satisfactory operation cliicctly by the operator on demand. These records are to affect electrical and steam connections, but dif-
pump instead o f a fauliy duty pump, then the opirator
of plant auxiliary systems. The description of thesc can take measures to improve the efficiency of the plant l>r~duced by data processing computers and, since con- ferential movement between bearing supports must
systems forms the content of this section and more linoous scanning of all the input parameters is necessary, be avoided if the alignment of the plant is to be
on-line. The scheme is implemented by a series of
systems are described in Chapters 3 to 6. All these some compromises have to be made in the scanning maintained within reasonable limits. Multi-limb mano-
algorithms processed by a dedicated computing system
systems require instrumentation for local operation or spccd. Thus, assuming a minimum scanning interval metric level measuiing systems are therefore installed
and is capable of displaying trends in overall performance
fault finding. Wherever their operation is essential of 3 s and depending on their relative positions in the on tlie bearing supports to monitor relative level
given by changes in heat rate, as well as the performance
to the main turbine-generator unit, facilities for re- of individual components. scnoning cycle, a parameter might respond up to 3 s chanees. A schematic diagram . of such a system is
"
mote alarms and indications in the control room are liefare or 3 s after the recording shows the trip to have shown in Fig 2.46.
necessary. operated. In specifying the requirements of the data 'Slave' units are fitted to each bearing support, with
Machine level insfrumenrarion
logging system, the turbine plant designer considers these a master reference unit at one point and the whole
This comprises equipment for automatically measuring limitations to provide a compromise which is both cost system is filled with water. A uniform level is thus
4.1.4 Condition monitoring instrumentation and recordinc- c h a n-~ e sin the relative levels of the turbine-
~ ~ ~ ~~~~~
cffcctive and valuable to operators. established by the water surface and movement of
This defined list o f instruments is used on a periodic generator bearing pedestals. Primarily used for fault
basis to confirm the absence of long term trends which the bearing support relative to the fixed water level
diagnosis, this equipment is sometimes sunplied .. built-in can be detected by suitable sensors fitted on each
might lead to unplanned outages and to define acti- by the turbine manufacturer. A n alternative approach
vities for future outages. T o this extent, some of the slave unit. Sensors using micrometer adjustment of
is to provide facings and connection points on the
a n electrical contact probe, and floats with LVDT
instrumentation in this category is of a diagnostic pedestals so that portable equipment can be used to make 6 Turbine foundations
nature. position measurement have been used in the past,
the checks during maintenance outages. 'The turbine-generator
. foundations consist of the support but both systems have disadvantages. Present day
The defined subcategories are: structure, the sub-foundation and the subsoil; they systems use a n ultrasonic sensor fitted in the base
Heat rate test intrumentation Shafl vibration insfrumenfafion perform the following functions: of each slave unit which measures the position of
The scope of the measuring points required for this the water surface by sound reflection technique.
Machine level instrumentation. Support the static load of the turbine-generator and
is more complex than the provision made for turbine Accuracy of measurement is typically k0.05 mm, with
associated pipe loads, and transmit these forces to
Shaft vibration instrumentation supervisory purposes. At each bearing, two transducers a minimum measurement range of +2.5 mm about
the subsoil.
measure vibration in the same plane but displaced at nominal level.
The purpose and scope of each of these subcategories 90' to each other. This facilitates the recording of shaft e Restrain the plant from undue movement due to Cooling water is circulated around jackets on each
is described below. vibration signatures on run-down and also orbit plots dynamic forces resulting from the load torque, slave unit to eliminate errors due to manometer water
may he taken on-load so that a complete picture of unbalance forces, electrical faults, etc., by trans- temperature variations. Air pressure variations are
changes in shaft dynamics can be formulated by an expert mitting and absorbing the associated energy. nullified by connecting the air spaces of each slave
Hear rare fesr instrumentofion
o r a n expert computing system. Such a n analysis can unit together in an 'air balance box' (not shown in
This comprises all the equipment necessary to conduct lead to improvements in the "rediction of maintenance Maintain the alignment of the plant under all op- figure). The balance box is then vented to atmos-
a thermal performance test on the plant as described routlnes
I erating conditions. phere at a single point.
Turbine plant systems Turbine fout?dations
duced as the elasticity o f support reduces the dynamic tion might be expected to be greater than with other
In designing turbine-generator foundations it is therefore forces transmitted to the sub-foundation and subsoil. )lot11 methods have been used, separately 01 in corn- types of support structure. This has not been the case
necessary to consider 'tuning' the foundations and there in calculating the loads on the structure, account \,ination, on occasions, although post-commissioning in practice, and post-construction tuning of reinforced
are two aspects to this: concrete support structures is rarely necessary. If tun-
must be taken o f pipework loads (both hot and cold) tuning is generally not necessary.
Turbine fou~idations
TURBiNE
NO. 2 i . P
LOCATlON
No 1 L.P. TURBINE
H P TURBINE
LOCATION '\
,
ilic load only, or even to dispense with a mass The thickness of the sub-foundation should not be
FIG.2.50 Steel suppoil structure for a 660 M W ioibinc-generator with two LI' cyliiideis and aii underslung condcnsci
licrele sub-foundation and install individual foun- less than one tenth of its length. The need for piling is
lions for each support column. The precise design, determined by the nature of the subsoil at a particular
I course, depends on subsoil conditions at the par- site. Discontinuity between the sub-foundation, the
Springs mounted in rows on structural concrete walih basement floor of the station and the foundations of
Differential settlement can also be corrected by jacking-
up each of the affected columns and inserting packing or in groups at the top of support columns have bee11 'Tlle spring support, concrete deck and support other plant is attempted to prevent transmission of vibra-
used and viscous dampers are sometimes employed i n Itrmns are no cheaper than other support structure tions to other plant and the building structure.
between the column base and the sub-foundation.
conjunction with the springs. Natural frequencies of x s : the economic advantagc claimed for spring
about 3 Hz for movement in the vertical direction arc andations lies in the possible reduction in mass of the
claimed for these systems. A hydraulic locking system I1.foundation. Cost reductions of 25% are claimed in
5.4 Spring foundations is used to pre-load the springs to a set deflection for vourable circumstances. 6 Lubrication systems
As the natural frequency of a low-tuned foundation construction and plant erection purposes. The sanie
support structure decreases, the isolation between the locking system can be used to allow the insertion of
support structure and the sub-foundation increases, packers, above a spring or spring-group, to correct for 6.1 Lubrication requirements and typical
and the sub-foundation is called upon to absorb less foundation column settlement: this also allows sprin 6 Sub-foundation arrangements
of the energy resulting from dynamic and transient to be changed after erection for others having a different ?art from any special designs associated with spring Forced lubrication of the turbine bearings is essential
forces generated in the shaft line and static sections springrate, if it is necessary to change the characteristics undations, the sub-foundation must be a massive in order to prevent damage due to wear or excessive
of the plant. of any part of the spring support system. 11 rigid concrete base designed to transmit and dis-
Such low natural frequencies are accompanied b white metal bearing temperature. Before starting to
The closest practical approach to complete dynamic the static and dynamic loads of the support
the possibility of greater plant deflection under tra turn the main rotating elements, it is necessary to lift
isolation results from mounting the turbine-generator e and plant above it to the subsoil. Rigidity is
sient conditions. Under generator load rejection or the rotors clear of the bearing surface: the jacking oil
plant on springs and this approach has been used ry to limit differential settlement of the bases system used to achieve this is described later in Section
successfully overseas. In the UK, condensers of the short-circuit conditions, torsional rocking of the plan1 support columns to a value acceptable to the
can impose vertical movements of 1-1.5 mm at the
6.9 of this chapter.
underslung type have been spring-mounted, as have 111.line-generator, and the sub-foundation mass is es-
The purposes of the forced lubrication of the main
smaller items of plant, but spring mounting has not yet springs, so pipe and electrical connections must be blished from design analysis to limit plant vibration.
bearings are:
been used for main turbine-generators. designed to accommodate this. he sub-foundation of a modern turbine-generator
Established overseas practice uses springs of the Because the sub-foundation is well isolated from CEGB station, the mass is typically (a) T o provide a hydrodynamic oil wedge between
helical-coil or plate type supporting a reinforced con- dynamic loads, it is possible to reduce the mass of the ombined mass of the plant and struc- the bearing surface and the journal bearing of
crete deck on which the turbine-generator is mounted. sub-foundation towards that necessary to support the sufficient thickness so that the particles of debris
Turbine plant systems Chapti:i 2
normally jpiese~it in tile oil will 1101 damage the ex~~eriencc has sliowr~that lin~itingtllc oii tempeiariili
bearing surfaces. leaving a bearing to 71CC, gives satisCac1ol.y heiliiiljr
~ ~
ilf~.
(b) To provide a fiow of cooling fiuid sufficient to On older units. the lubricating oii system !i;ri
maintain the bearing white metal temperature be- integrated with tile turbine control and protectio~, oil
low ilOeC, dissipating the heat at the bearing system, with the lubricating oil being supplied throiiirl~
due to: a pressure control valve. A typical arrangement is shoiu18
@ Thermal conduction. on Fig 2.52.
On modern units, the control system (see Sectioii 1.6
0 Friction between tlie journal, oil film and white of this chapter) normally requires a fire-resistant fliiiil
metal. (FRF) system with a pressure between 70 and 175 bar.
Turbulelice with the oil itself. The lubricating oil system on these units (Fig 2.53)
is provided using a directly-driven centrifugal punip
delivering oil at around I1 bar. The oil from the pump
The majority of the oil fiow is needed to cool the passes through an oil turbine which drops the oil
bearing. Because o f the problems of accurately mca- pressure to around 3 bar; the oil turbine drives a
suring the white metal temperature at the point of booster pump which supplies oil from the main oil
maximum hydrodynamic pressure in the oil wedge, tank to the centrifugal oil pump suction. This arraotc.
Inrbll allows the oii tank iocation to be optimised with seal-oil system (see Chapter 6 , Section 5) is provided to
fci:ard to oil drainage under gravity, whilst meeting the prevent hydrogen transfer to the main oil system; on
centrifugal pump suction-head requirements. T o protect these units, the supply from tlie main lubricating oil
lhc System against overpressurisation, a connection is system is used as a back-up.
Inken from the bearing oil supply line to a relief valve On modern units, the lubricating oil system supplies:
lounted on the oil tank.
' he directly-driven main oil pump provides a n Each journal bearing on the turbine/generator/exciter
cmeiy secure source o f lubricating oil under normal rotating line.
ing conditions. For normal start-up and shutdown,
11 AC auxiliary oil pump provides the lubricating oil The main thrust/surge bearing.
rpply. For emergency shutdown, when the AC supplies
arc not available or the AC pump fails to start when The generator hydrogen seals, either as the sole supply
AUXillARY
O i l PUMP
required, a DC auxiliary oil .
-- tn
~
--
. o r as a back-up system.
station cleall and dirty oil tanka, and also to the ,ii in pig 2.54.
l~urificaliotl system, with the pipework and JOURNAL BEARING
e From the station used-oii tank to the oil ta,,k,* Details of the various oil pumps used arc dcic,ii
JOURNAL BEARING
in the paragraphs that foilow.
To drain the whole of the oii inventory from the
LOCKlNG PLATE
unit oil system into the unit oil tank, and from the
unit oil tank into the station used-oil tank. 6.2.1 Main lubricating oil p u m p
BOTTOM HALF
WEAR RiNClS
JOURNAL BEARING
OIL OUTLET
--._01L DISCHARGE
FLANGE
-
.--. LUBIliUiiNrOii
rn"PASS
- U#*CriU"lO"I
- URA,WS system as the A C pump, or the pipework which feeds
vEMr 6.2.3 AC a n d DC motor-driven auxiliary oil oil directly to the bearings at around 1.5 har. Each pump
M NoM.~~un.vALv. has a capacity o f around 70-120 litres/s.
The AC and DC auxiliary oil pumps which supply oil
to bearings under start-up and normal shutdown, or
under emergency shutdown respectively, are centri- 6.2.4 Jacking-oil P u m p s a n d priming P u m p s
fugal pumps with a submerged suction. They are also The jacking oil pumps deliver oil at around 300 bar
suspended from the tank top and their arrangement to the individual bearings. The pumps used are motor-
FIG. 2.54 Lubricating oil transfer and conditioning system is very similar to Fig 2.56, hut with an AC or DC driven positive displacement and either multi-plunger
Turbine plant systems
P V M P BODY
SEALING RiNG
TURBINE C I \ S $ N G
DISCHARGE PIPE---
TURBINE TOP
JOURNAL BEARIN0
TAXE-OFF
PEDESTAL
LOW PRESSURE
MEASUREMENT
OUTLET PLUG
TAKE-OFF
PlSTON SPRING
PVMP COVER W i L E T Poll7
l i ~ cdischarge pressure is the same as for the other Pump duty Type Drive
jacking oil pumps. Purifier/oil conditioner Gear Electric motor
- oil
6.2.5 Other pumps Purifier/oil conditioner Electric motor
Various other pumps are used on the lubricating oil - water
PIG. 2.56 Turbinc-driven o i l booster pump system and oil transfer systems as follows:
pumps Or
Oil tank water/oil Centrifugal Electric motor 6.3 Oil tanks
gear Pumps, see Figs 2.57 and lubricating oil manifold and the gear pumps have vapour extraction On modern units, the main oil tank has a capacity of
2.58. around 75 m3 for the lubricating oil system oil inven-
a motor-driven positive displacement two-shaft gear
The arrangement utilises either one gear pump per Oil tank hydrogen/ Centrifugal Electric motor tory, with a normal working level volume of 50 m3:
pump.
bearing or one motor/pump unit for either one or oil vapour extraction a typical arrangement is shown on Fig 2.59. The tank
On some designs the turning gear is provided with
two bearings. The pumps require a positive suction a separate jacking oil pump. hi^ pump is a motor. Clean and used Gear or Electric motor, is designed with the oil return and the pump suction
pressure. The multi-Plunger Pumps are fed from the driven, positive displacement, two.shaft gear pump; separated by baffle plates, to assist in de-aeration and
oil transfer diaphragm or air
186
I 1urbtne piatit systems Chdlill i Lubrication systems
--
A C MOiORORlVLN A C MOIORDR8YEN
LU6HICATlNCIOIL PUMP
-
'
OILFLOW
' MPOIII1
8001 SEAL
O-RING ' 1
0 4 L SEAL
settlement and also to prevent the formation of stag- valves, two vapour extraction pumps are also mounted.
nant pockets of oil. The quantity of oil in the tank One to remove water and oil vapour from the tank and
and the internal design of the tank provide around the other to extract hydrogen and oil vapour from thc
seven minutes oil transit time from return to suction, detraining tank.
with the normal time limits being between five to
ten minutes.
The trend on modern systems is to provide a self-
contained section of the overall oil tank for the hy- 6.4 Piping
F ~ G2.59
. Main oil lank - general ariangenleni
drogen seal-oil system, the objective being to eliminate Pressure oil piping for both jacking ail systems and
the risk of hydrogen gas passing into the main lubri- lubricating oil systems on modern units is subject to
cating oil system. Where a self-contained system is special design precautions against oil leakage and fire
used, a back-up supply of oil to the hydrogen seals risk. The oil piping is sized so that the oil velocity is 6.5 Oil coolers dissipation requirements are around 2 MW per cooler.
is provided. Where the lubricating oil system provides between 1-5 m/s. Oil piping from the pump discharge 'The function of the oil coolers is to ensure that the oil On some designs, the oil coolers have the main
the hydrogen gas-side seal-oil, special precautions are is contained within an enclnsure/duct and the pipe- fcmperature leaving the bearings is below the permitted lubricating oil filters integral with the cooler shell. A
taken to ensure that any entrained hydrogen is released runs between pipe joints are as long as is possible. limit by removing the heat absorbed by the oil within typical example of a n oil cooler, which also shows the
and vented to atmosphere. A separate seal-oil loop All pipe joints are o f Class I welded construction. (lie pumps and the bearings. Redundant coolers are integral oil filters, is shown on Fig 2.60.
detraining chamber is used to ensure that all hydrogen At the exit from the ducted area, the pressure oil pipe provided in order to enable repairs and tube cleaning Arrangements are made for automatic by-pass of
is removed before the oil is mixed with the main oil is contained within a protective pipe, so that any oil lo be carried out whilst the unit is on-load. Normally, the oil coolers upon excessive pressure drop across the
system. leakage would be contained and would be detected at three 50% duty coolers are provided, but two 100% units coolers. Automatic control of the oil outlet temperature
Coarse-mesh strainers are provided on all oil returns 'tell-tale' drains. Pipe material up to the filters is mild nre sometimes used. is provided.
t o the tank to assist de-aeration and to catch any large steel; on some designs, the pipe-runs after the filters 'The oil coolers are mounted vertically with a two-pass
foreign material. Problems have arisen in the past with are in stainless steel to minimise the risk of corrosion water flow through the tubes and a single-pass oil flow
corrosion at the air/oil interface in the main oil tank products damaging the bearings. Automatic air venting through a series of baffles, to ensure even cooling. The
due to the presence of water/water vapour in the oil. of the pipework system from its highest points to the cooler shells are of mild steel and modern practice 6.6 Oil strainers and filters
The main oil tank is now fabricated either in stainless oil tank is provided where the air is not vented through is for the tubes to be made of titanium. The tube The oil strainers are coarse wire-mesh basket type
steel or mild steel with a special phenolic paint protec- the bearings. Oil filters are also provided with air vents nest has a fixed and a floating tubeplate to contain assemblies which are designed to catch large foreign
tion against corrosion. to the oil tank; these ensure that any air accumulation, lllermal expansion. The coolers are provided with re- material from the oil drains into the main oil tank.
O n the top of the oil tank, in addition to the sus- either in service o r as a result of servicing or inspection, movable end plates so that cleaning can be carried thus ensuring that material reaching the centrifugal
pended oil pumps and the bearing oil pressure relief is vented to the oil tank. nut without dismantling the water pipes. The heat pump suction will not cause pump damage. They can
188
Tiirhine plant systems Chapii'i 1 Lubiication systeins
.
IWICT,O"llli .-
TOI'TUBFPLAT
Oil. OUTLET-
BAFFLE PLATES
i l L l E i l CHAMBER
C O O l l H BODY ACCESSCOVERS i
-IILIERCIIAMBFR
OIL ,Nlil---..
FLIERCHAtIIIEH AIR
RELEASE CONNFCIION
04l'ltREN1IAI PRESSURL
GAUGE CONNLCTiONS
FlOWDiAGRAM
be lifted out of the tank to remove and inspect any of one compartment whilst the unit is on-load.
debris collected. Facilities are provided to enable a filter to bc
Two main systems of filtration of the lubricating primed and pressurised after service, before ~ u t .
oil are used: tillg a filter cimparllnent back into service. The filtej
norinally provides a capacity of around 106 litres/s
(a) Curlridge fillers fitted into the oil cooler casing under a pressure drop of 0.3 bar with both com-
which are designed to filter 13 litres/s of hot oil partments in service. Normal filter cleaning is
Fit. 2.61 Plate lyne oil filter
per cartridge, to a nominal particle size of 10 carried out automatically when a rising pressure
microns. Each cooler can have up to four dispos- differential reaches 0.45 bar across the filter. Ro-
able cartridges giving a total filtration capacity of tation of each plate filter assembly then occurs
around 52 litres/s, with two coolers required for against a scraper bar; the debris off each filter falls 'The oil for these duties is taken from the filtered oil housing and the cold lubricating oil, which results in
into a sump at the bottom of the filter irousing and supply to the bearings and passed through a duplex condensate being dispersed through the oil. The oil
100% duty.
is cleaned out on a regular basis. A typical arrange- plate-type filter system similar to that described above also collects wear particles, oxides, soluble acids and
(b) Duplex filters fitted after the oil coolers. These ment of a plate-type filter is shown on Fig 2.61. and shown o n Fig 2.61. This additional filter has only sludge. These need to be removed from the oil to
four plate filter assemblies in each compartment and ensure its long life and efficient lubrication. There
can be either multiple disposable filters, with facilities
lhas only manual filter cleaning. The filter provides are two main systems used o n continuous by-pass duty
for on-load replacement, or a duplex plate filter Where a plate-type filter is used in the main oil supply
which can be cleaned on-load. The plate-type filter a capacity of 16 litres/s under a pressure drop of whilst the unit is in operation, and an oil regeneration
t o the bearings, additional filtration is required for 0.2 bar with'both compartments in service. system is also used in the station oil system. The on.line
consists of two compartments, each with five filter the oil supply to: systems are described in the sections which follow.
assemblies. Each assembly consists of a series of
plates and spacers, which give the required degree
of filtration of 15 micron. Each compartment
normally passes 50% of the oil: facilities exist to
pass LOO% flow through one compartment in order
. The main thrust and surge bearings.
The shaft turning gear, jacking oil pump, gearing
and clutch,
6.7 Oil purifiers and coalescers
The main source of contamination of lubricating oil
is the leakage of steam from the rotor gland seals.
6.7.1 Centrifugal separation systems
This type of system has been used for many years but
requires careful adjustment for maximum efficiency,
as well as considerable maintenance. A schematic ar-
to allow replacement, maintenance or inspection The main oil pump, thrust bearing and cooling sprays. This steam condenses upon contact with the bearing rangement of the system is shown on Fig 2.62.
190
Tuibii?c plaiit systems
Lubiicatioii systems
~=:+=:z:-~
-1 1 Oil is taken froin tile inain oil tank at a rate of 17010
of the oil i~lventoiyper hour. Thc oil initially passes
lliir)ilgi~ a scrics arrangement of fine-nlesli sloping
screens. Thc water coalesces on the screens in water
droplets which iilil down to the bottom of each screen
and are led to drain. The oil then passcs through a series
o f polyolefinic bags which filter out the particulate
matter. Finally, the ail is pumped through a 5 micron
pressure filter and delivered back into the main oil tank.
The oil passes through the purifier at its operating
temperature and because it is not heated the risk of
bacterial/fungal growth may be greater (see Section
6.8 of this chapter).
Provision is made for the regeneration of used oil
within the station oil transfer system. Oil for regen-
eration is taken from the unit oil tank or the station
dirty-oil tank at around 1.1 m3 per hour and processed
in the plant shown schematically on Fig 2.65.
The oil is healed to 54.4"C and is then sprayed into
a chamber with a vacuum maintained at 913 mbar
below atmospheric. Under tiiese conditions the water
boils o f f , is removed by the vacuum pump and con-
densed. The dry oil is then pumped out of the vacuum
chamber and through a filter. The filter comprises a
pack of nylon-backed filter papers clamped between
perforated steel plates, and filters the oil to 10 microns.
From the filter, the oil is taken into the clean oil tank
prior to being pumped back into the unit oil tank after
it has been cleaned.
6.8.1 Oils
The oils used in steam turbines must provide ciean,
stable and efficient iubrication whilst exposed to the
severe operational conditions. They are also required
to be efficient at absorbing the heat generated in the
bearing. These conditions require the use of oils in-
corporating additives, particularly for the inhibition
of corrosion and oxidation.
The basic turbine lubricating oils are to British
Standard 489: 1983: CEGB Standard 207001 covers
lubricants for use by the CEGB and Table 2.1 is a n
extract which covers turbine lubricating oils. The spe-
cific grade used on the modern 3000 r/min tandem
turbine-generator is TO-32.
Additives are now used to inhibit oxidation, corro-
sion and foaming. An oxidation inhibitor is added to
stabilise the oil against oxidation and to passivate the
metals which act catalytically to increase oxidation. These
inhibitors maintain a low neutralisation value (acidity)
of an oil over many years of service. A rust inhibitor
in the oil protects carbon-steel surfaces from rusting
when in contact with water or moist air entrained within
192 5 nc 2 63 011 purifier bowl operat~on the oil circulating system.
f
193
Turbiiie plant systems Lublication systems
PEHTORATEO UEAEHKIING
PLATES IN VACUUM DRUM
.
When a turbine-generator shaft is rotating very slowiy, TANK ORAIN
tube nests. The basic precautions are: the normal lubricating oil supply cannot ensure that
ensure that the water of the oil in a hydrodynamic oil wedge will be maintained. Also
-I OIRIY OIL (WITH WATER1
operation is kept low by regular use of [he oil puri. additional lubrication measures are required to preven
. fier; the water content should not exceed 0.05qo. bearing damage and to minimise breakaway torqil "..- . DiRiY OIL (WATER FRtEl
when starting a turbine-generator from standstill. In b
To remove sludge deposits from the oil system circumstances the jacking oil system provides h . CLEANOIL
plant-sumps on a regular basis. pressure oil to the base of the bearing and floats
If bacteriai/fungal growth becomes a problem, the is capable of sustaining an adequate bearing oil wed
--- VACUUM
addition of the correct biocide to the oil will kill the (above 200 r/min), the jacking oil system and the no
bacterial/fungal growth. ma1 lubricating oil system are run in parallel. FIG.2.65 Oil regeneration plant - flow diagram
194