ID Text1 Task Name Duration Start Finish Resource Names Resource Predecessors 2018 2019
Type Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
1 SHAHIGARI TO SHAHPUR CONSTRUCTION OF YAKMACH-KHARAN 521 days Mon 7/31/17 Mon 7/29/19
ROAD PROJECT (SECTION-II)
2 SHAIGARI TO SHAHPUR.1 MOBILIZATION SCHEDULE 62 days Mon 7/31/17 Tue 10/24/17
3 B1000 Letter of Commencement 2 days Mon 7/31/17 Tue 8/1/17 Project manager 8/1
4 B1010 Possession of Site 4 days Mon 8/21/17 Thu 8/24/17 Project manager,Structure Engineer,Skilled
3 Labour 8/24
5 B1020 Establishment of Offices for employer/Engineers 16 days Fri 9/1/17 Fri 9/22/17 Foreman,Highway Engineer,Masons,Material
3 9/22 Engineer,Skilled Labour,Supervisor
Engineer,Project manager,Site
6 B1030 Construction of accommodation for Employer/Engineer 15 days Fri 9/1/17 Thu 9/21/17 Foreman,Highway Engineer,Masons,Material
3 9/21 Engineer,Skilled Labour,Supervisor
Engineer,Project manager,Site
7 B1035 Mobilization of Machinery/Equipments at Site, Establishment of Site 3 days Fri 9/1/17 Tue 9/5/17 Excavator,Tool & 3 9/5
Lab,Installation of Batching Plant,Installation of Asphalt Plant and Plants,Grader,Buldozer
8 B1038 Provision of all types of General Items to Consultants and 60 days Wed 8/2/17 Tue 10/24/17 Project manager 3 10/24
Employer's Representatives
9 SHAIGARI TO SHAHPUR.9 SITE SURVEY WORKS 22 days Thu 9/21/17 Fri 10/20/17
10 SR1000 Arrangement & Execution of Site Survey 22 days Thu 9/21/17 Fri 10/20/17 Foreman,Surveyor,Supervisor,Skilled Labour
7 10/20
11 SHAIGARI TO SHAHPUR.4 KM(50+000 TO KM 60+000) 55 days Mon 10/23/17 Fri 1/5/18
12 SHAIGARI TO SHAHPUR.4.2 Levelling & Grading 55 days Mon 10/23/17 Fri 1/5/18
13 A1140 Cleaning and Grubbing 35 days Mon 10/23/17 Fri 12/8/17 Surveyor,Labour,Project manager,Highway 12/8
10 Engineer,Material Engineer,Grader,Excavator,Tool & Plants,Trector Trolly
14 A1150 Removal of all Types of Trees 17 days Mon 10/23/17 Tue 11/14/17 Surveyor,Labour,Project manager,Highway 11/14
10 Engineer,Material Engineer,Tool & Plants,Trector Trolly,ELECTRIC SAW,Front End Loader
15 A1160 Breaking & Scarification of existing pavement & Structures 55 days Mon 10/23/17 Fri 1/5/18 Surveyor,Labour,Project manager,Highway 1/5 120 HP
10 Engineer,Material Engineer,Tool & Plants,Buldozer
16 SHAIGARI TO SHAHPUR.4.3 Earth Work 124 days Wed 1/3/18 Mon 6/25/18
17 A1040 Excavation (Suitable/Unsuitable) 29 days Wed 1/3/18 Mon 2/12/18 Site Engineer,Surveyor,Project manager,Supervisor,Skilled
10 2/12
Labour,Excavator,Dumper,Trector Trolly,Loader,Water,Water Truck
18 A1050 Compation of Natural Ground 23 days Fri 3/2/18 Tue 4/3/18 Surveyor,Labour,Site Engineer,Highway 10 4/3 Truck,Water,Grader
Engineer,Lab Technician,Excavator,Trector Trolly,Dumper,Roller,Water
19 A1060 Formation of Embankment from out sout source . Suitable excavated material 46 days Mon 3/26/18 Mon 5/28/18 Surveyor,Labour,Site Engineer,Dumper,Trector
10 Trolly,Excavator 5/28
20 A1070 Sub- Grade Preparation works 42 days Fri 4/27/18 Mon 6/25/18 Lab Technician,Water,Highway Engineer,Water
10 Truck,Roller,Grader 6/25
21 SHAIGARI TO SHAHPUR.4.1 Protection Work & BOX 162 days Wed 1/3/18 Thu 8/16/18 Labour,Excavator,Trector
CULVERT-BILL NO (4 &5) Trolly,Dumper,Site
22 A1080 Structural Excavation 36 days Wed 1/3/18 Wed 2/21/18 Site Engineer,Surveyor,Project manager,Supervisor,Skilled
10 Labour,Excavator,Dumper,Buldozer 120 2/21 HP
23 A1090 Lean Concrete Works 20 days Tue 1/23/18 Mon 2/19/18 Surveyor,Labour,Site Engineer,Lab Technician,Project
10 2/19
manager,Material Engineer,Structure Engineer,Scoffolder,Steel Fixer,Transit Mixer,Concrete Pump,Concrete Batching Plant,Cement,Steel,Water,Crush,Sand
24 A1100 Stone Masonry Works 34 days Thu 3/22/18 Tue 5/8/18 Surveyor,Labour,Site Engineer,Lab Technician,Project
10 5/8
manager,Material Engineer,Scoffolder,Structure Engineer,Cement,Water,Sand
25 A1110 Fitter layer of Grangular Material if required 31 days Mon 6/25/18 Mon 8/6/18 Surveyor,Labour,Site Engineer,Lab Technician,Project
10 manager,Material Engineer,Scoffolder,Water 8/6
26 A1120 Concrete Works Class-A 23 days Mon 4/2/18 Wed 5/2/18 Surveyor,Site Engineer,Lab Technician,Project
10 5/2 Fixer,Transit Mixer,Concrete Pump,Concrete Batching Plant,Cement,Steel,Water,Crush,Sand
manager,Material Engineer,Structure Engineer,Labour,Scoffolder,Steel
27 A1130 Granular Backfill with approved Material 28 days Mon 7/2/18 Wed 8/8/18 Surveyor,Labour,Site Engineer,Lab Technician,Project
10 manager,Material Engineer,Water,Front End Loader,Excavator 8/8
28 A1230 Grouted Rip Rap Works 31 days Thu 7/5/18 Thu 8/16/18 Surveyor,Labour,Site Engineer,Lab Technician,Project
10 manager,Material Engineer,Water,Sand 8/16
29 SHAIGARI TO SHAHPUR.4.5 Sub Base & Base Works 63 days Fri 8/17/18 Tue 11/13/18
30 A1020 Granular Subbase Works 31 days Fri 8/17/18 Fri 9/28/18 Lab Technician,Site Engineer,Surveyor,Labour,Project
10,20,28 9/28
manager,Highway Engineer,Skilled Labour,Aggregate,Grader,Water,Roller,Tool & Plants,Excavator,Dumper
31 A1030 Aggregate Base Works 32 days Mon 10/1/18 Tue 11/13/18 Lab Technician,Site Engineer,Surveyor,Labour,Project
30 11/13
manager,Highway Engineer,Skilled Labour,Aggregate,Grader,Water,Roller,Tool & Plants,Excavator,Dumper
32 SHAIGARI TO SHAHPUR.4.6 Pavement Works 40 days Wed 11/14/18 Tue 1/8/19
33 A1210 Cut Back Asphalt Prime Coat 27 days Wed 11/14/18 Thu 12/20/18 Oil,Skilled Labour,Supervisor,Forman,Site 31Engineer,Project manager,Material Engineer,Aphalt,Water,Tool & Plants,Highway Engineer,Water Truck 12/20
34 A1220 Asphalt Wearing Concrete Course 13 days Fri 12/21/18 Tue 1/8/19 Load Test Machine,Skilled Labour,Supervisor,Highway
33 1/8
Engineer,Site Engineer,Project manager,Material Engineer,Forman,Loader,Excavator,Oil,Asphalt. Water,Tandem Roller,Aggregate,Combination Roller,Tool & Plant
35 SHAIGARI TO SHAHPUR.4.4 Ancillary Work 73 days Wed 1/9/19 Fri 4/19/19
36 A1170 Pavement Marking & Fixing of Reflected Studs 31 days Wed 1/9/19 Wed 2/20/19 Site Engineer,Skilled Labour,Supervisor,Road
34 Marking Machine,Studs,Trector Trolly 2/20
37 A1180 Right of way Marker as per given size 47 days Wed 1/9/19 Thu 3/14/19 Supervisor,Site Engineer,Skilled Labour,Tool
34 & Plants 3/14
38 A1190 Installation of Kilo meter Posts as per Drawing 40 days Wed 1/9/19 Tue 3/5/19 Skilled Labour,Project manager,Site Engineer,Surveyor,Supervisor,Concrete
34 Batching Plant,Shuttring Plates And Scaffolding,Transit Mixer & Concrete Pump 3/5
39 A1200 Installation of all types of Traffic Road Signs 14 days Tue 4/2/19 Fri 4/19/19 Site Engineer,Skilled Labour,Tool & Plants,Supervisor,Water,Cement,Trector
34 Trolly,Masons,Concrete Batching Plant 4/19
40 SHAIGARI TO SHAHPUR.2 KM (60+000 TO KM 70+000) 55 days Mon 10/23/17 Fri 1/5/18
41 SHAIGARI TO SHAHPUR.2.2 Levelling & Grading 55 days Mon 10/23/17 Fri 1/5/18
42 A1240 Clearing and Grubbing 36 days Mon 10/23/17 Mon 12/11/17 Surveyor,Labour,Project manager,Highway 12/11 & Plants,Trector Trolly
10 Engineer,Material Engineer,Grader,Excavator,Tool
43 A1250 Removal of all Types of Trees 18 days Mon 10/23/17 Wed 11/15/17 Surveyor,Labour,Project manager,Highway 11/15
10 Engineer,Material Engineer,Tool & Plants,Trector Trolly,ELECTRIC SAW,Front End Loader
44 A1260 Breaking & Scarification of existing pavement & Structure 55 days Mon 10/23/17 Fri 1/5/18 Surveyor,Labour,Project manager,Highway 1/5 120 HP
10 Engineer,Material Engineer,Tool & Plants,Buldozer
45 SHAIGARI TO SHAHPUR.2.3 Earht Work 123 days Wed 1/3/18 Fri 6/22/18
46 A1270 Excavation (Suitable/Unsuitable) 29 days Wed 1/3/18 Mon 2/12/18 Site Engineer,Surveyor,Project manager,Supervisor,Skilled
10 2/12
Labour,Excavator,Dumper,Trector Trolly,Loader,Water,Water Truck
47 A1280 Compation of Natural Ground 23 days Fri 3/2/18 Tue 4/3/18 Surveyor,Labour,Site Engineer,Highway 10 4/3 Truck,Water,Grader
Engineer,Lab Technician,Excavator,Trector Trolly,Dumper,Roller,Water
48 A1290 Formation of Embankment From out sout source/ Suitable Excavated Material 46 days Mon 3/26/18 Mon 5/28/18 Surveyor,Labour,Site Engineer,Excavator,Trector
10 Trolly,Dumper 5/28
49 A1300 Sub-Grade Prepation works 41 days Fri 4/27/18 Fri 6/22/18 Roller,Water Truck,Highway Engineer,Water,Lab
10 Technician,Grader 6/22
50 SHAIGARI TO SHAHPUR.2.1 Potection Work & BOX Culvert -BILL 162 days Wed 1/3/18 Thu 8/16/18 Labour,Excavator,Trector
NO (4 & 5) Trolly,Dumper,Site
51 A1310 Structural Excavation 35 days Wed 1/3/18 Tue 2/20/18 Site Engineer,Surveyor,Project manager,Supervisor,Skilled
10 Labour,Excavator,Dumper,Buldozer 1202/20 HP
52 A1320 Lean Concrete 20 days Tue 1/23/18 Mon 2/19/18 Surveyor,Labour,Site Engineer,Lab Technician,Project
10 2/19
manager,Material Engineer,Structure Engineer,Scoffolder,Steel Fixer,Transit Mixer,Concrete Pump,Concrete Batching Plant,Cement,Steel,Water,Crush,Sand
53 A1330 Stone Masonry Works 34 days Thu 3/22/18 Tue 5/8/18 Surveyor,Labour,Site Engineer,Lab Technician,Project
10 5/8
manager,Material Engineer,Scoffolder,Structure Engineer,Cement,Water,Sand
54 A1340 Fitter layer of Grangular Material if required 30 days Mon 6/25/18 Fri 8/3/18 Surveyor,Labour,Site Engineer,Lab Technician,Project
10 manager,Material Engineer,Scoffolder,Water 8/3
55 A1350 Concrete Works Class-A 23 days Mon 4/2/18 Wed 5/2/18 Surveyor,Site Engineer,Lab Technician,Project
10 5/2 Fixer,Transit Mixer,Concrete Pump,Concrete Batching Plant,Cement,Steel,Water,Crush,Sand
manager,Material Engineer,Structure Engineer,Labour,Scoffolder,Steel
56 A1360 Granular Backfill with approved Material 28 days Mon 7/2/18 Wed 8/8/18 Surveyor,Labour,Site Engineer,Lab Technician,Project
10 manager,Material Engineer,Water,Front End Loader,Excavator 8/8
57 A1370 Grouted Rip Rap Works 31 days Thu 7/5/18 Thu 8/16/18 Surveyor,Labour,Site Engineer,Lab Technician,Project
10 manager,Material Engineer,Water,Sand 8/16
58 SHAIGARI TO SHAHPUR.2.5 SUB BASE & BASE WORKS 63 days Fri 8/17/18 Tue 11/13/18
59 A1380 Granular Subbase Works 31 days Fri 8/17/18 Fri 9/28/18 Lab Technician,Site Engineer,Surveyor,Labour,Project
10,20,57 9/28
manager,Highway Engineer,Skilled Labour,Aggregate,Grader,Water,Roller,Tool & Plants,Excavator,Dumper
60 A1390 Aggregate Base Works 32 days Mon 10/1/18 Tue 11/13/18 Lab Technician,Site Engineer,Surveyor,Labour,Project
59 11/13
manager,Highway Engineer,Skilled Labour,Aggregate,Grader,Water,Roller,Tool & Plants,Excavator,Dumper
61 SHAIGARI TO SHAHPUR.2.6 Pavement Works 40 days Wed 11/14/18 Tue 1/8/19
62 A1400 Cut Back Asphalt Prime Coat 27 days Wed 11/14/18 Thu 12/20/18 Forman,Skilled Labour,Supervisor,Oil,Site 60Engineer,Project manager,Material Engineer,Aphalt,Water,Tool & Plants,Highway Engineer,Water Truck 12/20
63 A1410 Asphalt Wearing Concrete Course 13 days Fri 12/21/18 Tue 1/8/19 Load Test Machine,Skilled Labour,Supervisor,Highway
62 1/8
Engineer,Site Engineer,Project manager,Material Engineer,Forman,Loader,Excavator,Oil,Asphalt. Water,Tandem Roller,Aggregate,Combination Roller,Tool & Plant
64 SHAIGARI TO SHAHPUR.2.4 Acillary Works 74 days Wed 1/9/19 Mon 4/22/19
65 A1420 Pavement Markiting & Fixing of Reflected Studs 31 days Wed 1/9/19 Wed 2/20/19 Site Engineer,Road Marking Machine,Supervisor,Skilled
63 Labour,Studs,Trector Trolly 2/20

Project: YAKMACH KHARAN Task Progress Summary External Tasks Deadline


Date: Fri 10/13/17 Split Milestone Project Summary External Milestone

Page 1
An evaluation version of novaPDF was used to create this PDF file.
Purchase a license to generate PDF files without this notice.
CONSTRUCTION OF YAKMACH TO KHARAN ROAD PROJECT
SECTION-II (SHAHI GHARI TO SHAHPUR
FROM KM 50+000 TO 100+000 (LENGTH = 50.000 KM)
ID Text1 Task Name Duration Start Finish Resource Names Resource Predecessors 2018 2019
Type Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
66 A1430 Right of way Marker as per given size 47 days Wed 1/9/19 Thu 3/14/19 Supervisor,Site Engineer,Skilled Labour,Tool
63 & Plants 3/14
67 A1440 Installation of Kilo Meter Posts as Drawing 41 days Wed 1/9/19 Wed 3/6/19 Skilled Labour,Project manager,Site Engineer,Surveyor,Supervisor,Concrete
63 Batching Plant,Shuttring Plates And Scaffolding,Transit Mixer & Concrete Pump 3/6
68 A1450 Installation of all types of Traffic Road Signs 15 days Tue 4/2/19 Mon 4/22/19 Site Engineer,Skilled Labour,Tool & Plants,Supervisor,Water,Cement,Trector
63 Trolly,Masons,Concrete Batching Plant 4/22
69 SHAIGARI TO SHAHPUR.3 KM (70+000 TO KM 80+000) 214 days Mon 10/23/17 Thu 8/16/18
70 SHAIGARI TO SHAHPUR.3.2 Levelling & Grading 55 days Mon 10/23/17 Fri 1/5/18
71 A1460 Cleaning and Grubbing 36 days Mon 10/23/17 Mon 12/11/17 Surveyor,Labour,Project manager,Highway 12/11 & Plants,Trector Trolly
10 Engineer,Material Engineer,Grader,Excavator,Tool
72 A1470 Removal of all Types of Trees 18 days Mon 10/23/17 Wed 11/15/17 Surveyor,Labour,Project manager,Highway 11/15
10 Engineer,Material Engineer,Tool & Plants,Trector Trolly,ELECTRIC SAW,Front End Loader
73 A1480 Breaking & Scarification of existing pavement & Structures 55 days Mon 10/23/17 Fri 1/5/18 Surveyor,Labour,Project manager,Highway 1/5 120 HP
10 Engineer,Material Engineer,Tool & Plants,Buldozer
74 SHAIGARI TO SHAHPUR.3.3 Earth WORKS 123 days Wed 1/3/18 Fri 6/22/18
75 A1490 Excavation (Suitable /Unsuitable) 29 days Wed 1/3/18 Mon 2/12/18 Site Engineer,Surveyor,Project manager,Supervisor,Skilled
10 2/12
Labour,Excavator,Dumper,Trector Trolly,Loader,Water,Water Truck
76 A1500 Compation of Natural Ground 23 days Fri 3/2/18 Tue 4/3/18 Surveyor,Labour,Site Engineer,Highway 10 4/3 Truck,Water,Grader
Engineer,Lab Technician,Excavator,Trector Trolly,Dumper,Roller,Water
77 A1510 Formation of Embankment From out sout source/Suitable Excavated Material46 days Mon 3/26/18 Mon 5/28/18 Surveyor,Labour,Site Engineer,Excavator,Trector
10 Trolly,Dumper 5/28
78 A1520 Sub-Grade Prepration works 41 days Fri 4/27/18 Fri 6/22/18 Roller,Water Truck,Highway Engineer,Water,Lab
10 Technician,Grader 6/22
79 SHAIGARI TO SHAHPUR.3.1 Protection Work & BOX 162 days Wed 1/3/18 Thu 8/16/18 Labour,Excavator,Trector
Culvert-BILL N0 (4&5) Trolly,Dumper,Site
80 A1530 Structural Excavation 35 days Wed 1/3/18 Tue 2/20/18 Site Engineer,Surveyor,Project manager,Supervisor,Skilled
10 Labour,Excavator,Dumper,Buldozer 1202/20 HP
81 A1540 Lean Concrete 20 days Tue 1/23/18 Mon 2/19/18 Surveyor,Labour,Site Engineer,Lab Technician,Project
10 2/19
manager,Material Engineer,Structure Engineer,Scoffolder,Steel Fixer,Transit Mixer,Concrete Pump,Concrete Batching Plant,Cement,Steel,Water,Crush,Sand
82 A1550 Stone Masonry Works 34 days Thu 3/22/18 Tue 5/8/18 Surveyor,Labour,Site Engineer,Lab Technician,Project
10 5/8
manager,Material Engineer,Scoffolder,Structure Engineer,Cement,Water,Sand
83 A1560 Pavement Markiting & Fixing of Reflected Studs 30 days Mon 6/25/18 Fri 8/3/18 Surveyor,Labour,Site Engineer,Lab Technician,Project
10 manager,Material Engineer,Scoffolder,Water 8/3
84 A1570 Concrete Works Class-A 23 days Mon 4/2/18 Wed 5/2/18 Surveyor,Site Engineer,Lab Technician,Project
10 5/2 Fixer,Transit Mixer,Concrete Pump,Concrete Batching Plant,Cement,Steel,Water,Crush,Sand
manager,Material Engineer,Structure Engineer,Labour,Scoffolder,Steel
85 A1580 Granular Backfill with approved Material 28 days Mon 7/2/18 Wed 8/8/18 Surveyor,Labour,Site Engineer,Lab Technician,Project
10 manager,Material Engineer,Water,Front End Loader,Excavator 8/8
86 A1590 Grouted Rip Rap Works 31 days Thu 7/5/18 Thu 8/16/18 Surveyor,Labour,Site Engineer,Lab Technician,Project
10 manager,Material Engineer,Water,Sand 8/16
87 SHAIGARI TO SHAHPUR.3.5 Sub Base & Base Works 63 days Fri 8/17/18 Tue 11/13/18
88 A1600 Granular Subbase Works 31 days Fri 8/17/18 Fri 9/28/18 Lab Technician,Site Engineer,Surveyor,Labour,Project
10,20,86 9/28
manager,Highway Engineer,Skilled Labour,Aggregate,Grader,Water,Roller,Tool & Plants,Excavator,Dumper
89 A1610 Aggregate Base Works 32 days Mon 10/1/18 Tue 11/13/18 Lab Technician,Site Engineer,Surveyor,Labour,Project
88 11/13
manager,Highway Engineer,Skilled Labour,Aggregate,Grader,Water,Roller,Tool & Plants,Excavator,Dumper
90 SHAIGARI TO SHAHPUR.3.6 Pavement Works 40 days Wed 11/14/18 Tue 1/8/19
91 A1620 Cut Back Asphal Prime Coat 27 days Wed 11/14/18 Thu 12/20/18 Forman,Skilled Labour,Supervisor,Oil,Site
89Engineer,Project manager,Material Engineer,Aphalt,Water,Tool & Plants,Highway Engineer,Water Truck 12/20
92 A1630 Asphalt Wearing Concrete Course 13 days Fri 12/21/18 Tue 1/8/19 Load Test Machine,Skilled Labour,Supervisor,Highway
91 1/8
Engineer,Site Engineer,Project manager,Material Engineer,Forman,Loader,Excavator,Oil,Asphalt. Water,Tandem Roller,Aggregate,Combination Roller,Tool & Plant
93 SHAIGARI TO SHAHPUR.3.4 Ancillary Work 74 days Wed 1/9/19 Mon 4/22/19
94 A1640 Pavement Marking & Fixing of Reflected Studs 31 days Wed 1/9/19 Wed 2/20/19 Site Engineer,Road Marking Machine,Supervisor,Skilled
92 Labour,Studs,Trector Trolly 2/20
95 A1650 Right of way Marker as per given size 47 days Wed 1/9/19 Thu 3/14/19 Supervisor,Site Engineer,Skilled Labour,Tool
92 & Plants 3/14
96 A1660 Installation of Kilo meter Posts as per Drawing 41 days Wed 1/9/19 Wed 3/6/19 Skilled Labour,Project manager,Site Engineer,Surveyor,Supervisor,Concrete
92 Batching Plant,Shuttring Plates And Scaffolding,Transit Mixer & Concrete Pump 3/6
97 A1670 Installation of all types of traffic Road Signs 15 days Tue 4/2/19 Mon 4/22/19 Site Engineer,Skilled Labour,Tool & Plants,Supervisor,Water,Cement,Trector
92 Trolly,Masons,Concrete Batching Plant 4/22
98 SHAIGARI TO SHAHPUR.5 KM (80+000 TO KM 90+000 55 days Mon 10/23/17 Fri 1/5/18
99 SHAIGARI TO SHAHPUR.5.2 Levelling & Grading 55 days Mon 10/23/17 Fri 1/5/18
100 A1680 Cleaning and Grubbing 35 days Mon 10/23/17 Fri 12/8/17 Surveyor,Labour,Project manager,Highway 12/8
10 Engineer,Material Engineer,Grader,Excavator,Tool & Plants,Trector Trolly
101 A1690 Removal of all Types of Trees 17 days Mon 10/23/17 Tue 11/14/17 Surveyor,Labour,Project manager,Highway 11/14
10 Engineer,Material Engineer,Tool & Plants,Trector Trolly,ELECTRIC SAW,Front End Loader
102 A1700 Breaking & Scarification of existing pavement & Structures 55 days Mon 10/23/17 Fri 1/5/18 Surveyor,Labour,Project manager,Highway 1/5 120 HP
10 Engineer,Material Engineer,Tool & Plants,Buldozer
103 SHAIGARI TO SHAHPUR.5.3 Earth Work 124 days Wed 1/3/18 Mon 6/25/18
104 A1710 Excavation (Suitable/Unsuitable) 29 days Wed 1/3/18 Mon 2/12/18 Site Engineer,Surveyor,Project manager,Supervisor,Skilled
10 2/12
Labour,Excavator,Dumper,Trector Trolly,Loader,Water,Water Truck
105 A1720 Compation of Natural Ground 23 days Fri 3/2/18 Tue 4/3/18 Surveyor,Labour,Site Engineer,Highway 10 4/3 Truck,Water,Grader
Engineer,Lab Technician,Excavator,Trector Trolly,Dumper,Roller,Water
106 A1730 Formation of Embankment From out sout source/ Suitable Excavated Material 46 days Mon 3/26/18 Mon 5/28/18 Surveyor,Labour,Site Engineer,Excavator,Trector
10 Trolly,Dumper 5/28
107 A1740 Sub-Grade Prepation works 42 days Fri 4/27/18 Mon 6/25/18 Roller,Water Truck,Highway Engineer,Water,Lab
10 Technician,Grader 6/25
108 SHAIGARI TO SHAHPUR.5.1 Protection Work & BOX Culvert - BILL 162 days Wed 1/3/18 Thu 8/16/18 Labour,Excavator,Trector
NO (4 & 5 ) Trolly,Dumper,Site
109 A1750 Structural Excavation 36 days Wed 1/3/18 Wed 2/21/18 Site Engineer,Surveyor,Project manager,Supervisor,Skilled
10 Labour,Excavator,Dumper,Buldozer 120 2/21 HP
110 A1760 Lean Concrete Works 20 days Tue 1/23/18 Mon 2/19/18 Surveyor,Labour,Site Engineer,Lab Technician,Project
10 2/19
manager,Material Engineer,Structure Engineer,Scoffolder,Steel Fixer,Transit Mixer,Concrete Pump,Concrete Batching Plant,Cement,Steel,Water,Crush,Sand
111 A1770 Stone Masonry Works 34 days Thu 3/22/18 Tue 5/8/18 Surveyor,Labour,Site Engineer,Lab Technician,Project
10 5/8
manager,Material Engineer,Scoffolder,Structure Engineer,Cement,Water,Sand
112 A1780 Fitter layer of Grangular Material if required 31 days Mon 6/25/18 Mon 8/6/18 Surveyor,Labour,Site Engineer,Lab Technician,Project
10 manager,Material Engineer,Scoffolder,Water 8/6
113 A1790 Concrete Works Class-A 23 days Mon 4/2/18 Wed 5/2/18 Surveyor,Site Engineer,Lab Technician,Project
10 5/2 Fixer,Transit Mixer,Concrete Pump,Concrete Batching Plant,Cement,Steel,Water,Crush,Sand
manager,Material Engineer,Structure Engineer,Labour,Scoffolder,Steel
114 A1800 Granular Backfill with approved Material 28 days Mon 7/2/18 Wed 8/8/18 Surveyor,Labour,Site Engineer,Lab Technician,Project
10 manager,Material Engineer,Water,Front End Loader,Excavator 8/8
115 A1810 Grouted Rip Rap Works 31 days Thu 7/5/18 Thu 8/16/18 Surveyor,Labour,Site Engineer,Lab Technician,Project
10 manager,Material Engineer,Water,Sand 8/16
116 SHAIGARI TO SHAHPUR.5.5 Sub Base & Base Works 63 days Fri 8/17/18 Tue 11/13/18
117 A1820 Granular Subbase Works 31 days Fri 8/17/18 Fri 9/28/18 Lab Technician,Site Engineer,Surveyor,Labour,Project
10,20,115 9/28
manager,Highway Engineer,Skilled Labour,Aggregate,Grader,Water,Roller,Tool & Plants,Excavator,Dumper
118 A1830 Aggregate Base Works 32 days Mon 10/1/18 Tue 11/13/18 Lab Technician,Site Engineer,Surveyor,Labour,Project
117 11/13
manager,Highway Engineer,Skilled Labour,Aggregate,Grader,Water,Roller,Tool & Plants,Excavator,Dumper
119 SHAIGARI TO SHAHPUR.5.6 Pavement Works 40 days Wed 11/14/18 Tue 1/8/19
120 A1840 Cut Back Asphal Prime Coat 27 days Wed 11/14/18 Thu 12/20/18 Forman,Skilled Labour,Supervisor,Oil,Site
118Engineer,Project manager,Material Engineer,Aphalt,Water,Tool & Plants,Highway Engineer,Water Truck 12/20
121 A1850 Asphalt Wearing Concrete Course 13 days Fri 12/21/18 Tue 1/8/19 Load Test Machine,Skilled Labour,Supervisor,Highway
120 1/8
Engineer,Site Engineer,Project manager,Material Engineer,Forman,Loader,Excavator,Oil,Asphalt. Water,Tandem Roller,Aggregate,Combination Roller,Tool & Plant
122 SHAIGARI TO SHAHPUR.5.4 Ancillary Work 73 days Wed 1/9/19 Fri 4/19/19
123 A1860 Pavement Marking & Fixing of Reflected Studs 31 days Wed 1/9/19 Wed 2/20/19 Site Engineer,Road Marking Machine,Supervisor,Skilled
121 Labour,Studs,Trector Trolly 2/20
124 A1870 Right of way Marker as per given size 47 days Wed 1/9/19 Thu 3/14/19 Supervisor,Site Engineer,Skilled Labour,Tool
121 & Plants 3/14
125 A1880 Installation of Kilo meter Posts as per Drawing 40 days Wed 1/9/19 Tue 3/5/19 Skilled Labour,Project manager,Site Engineer,Surveyor,Supervisor,Concrete
121 Batching Plant,Shuttring Plates And Scaffolding,Transit Mixer & Concrete Pump 3/5
126 A1890 Installation of all types of Traffic Road Signs 14 days Tue 4/2/19 Fri 4/19/19 Site Engineer,Skilled Labour,Tool & Plants,Supervisor,Water,Cement,Trector
121 Trolly,Masons,Concrete Batching Plant 4/19
127 SHAIGARI TO SHAHPUR.5 KM (90+000 TO KM 100+000 55 days Mon 10/23/17 Fri 1/5/18
128 SHAIGARI TO SHAHPUR.6.2 Levelling & Grading 55 days Mon 10/23/17 Fri 1/5/18
129 A1900 Cleaning and Grubbing 36 days Mon 10/23/17 Mon 12/11/17 Surveyor,Labour,Project manager,Highway 12/11 & Plants,Trector Trolly
10 Engineer,Material Engineer,Grader,Excavator,Tool
130 A1910 Removal of all Types of Trees 18 days Mon 10/23/17 Wed 11/15/17 Surveyor,Labour,Project manager,Highway 11/15
10 Engineer,Material Engineer,Tool & Plants,Trector Trolly,ELECTRIC SAW,Front End Loader
131 A1920 Breaking & Scarification of existing pavement & Structures 55 days Mon 10/23/17 Fri 1/5/18 Surveyor,Labour,Project manager,Highway 1/5 120 HP
10 Engineer,Material Engineer,Tool & Plants,Buldozer
132 SHAIGARI TO SHAHPUR.6.3 Earth Work 123 days Wed 1/3/18 Fri 6/22/18

Project: YAKMACH KHARAN Task Progress Summary External Tasks Deadline


Date: Fri 10/13/17 Split Milestone Project Summary External Milestone

Page 2
An evaluation version of novaPDF was used to create this PDF file.
Purchase a license to generate PDF files without this notice.
CONSTRUCTION OF YAKMACH TO KHARAN ROAD PROJECT
SECTION-II (SHAHI GHARI TO SHAHPUR
FROM KM 50+000 TO 100+000 (LENGTH = 50.000 KM)
ID Text1 Task Name Duration Start Finish Resource Names Resource Predecessors 2018 2019
Type Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
133 A1930 Excavation (Suitable/Unsuitable) 29 days Wed 1/3/18 Mon 2/12/18 Site Engineer,Surveyor,Project manager,Supervisor,Skilled
10 2/12
Labour,Excavator,Dumper,Trector Trolly,Loader,Water,Water Truck
134 A1940 Compation of Natural Ground 23 days Fri 3/2/18 Tue 4/3/18 Surveyor,Labour,Site Engineer,Highway 10 4/3 Truck,Water,Grader
Engineer,Lab Technician,Excavator,Trector Trolly,Dumper,Roller,Water
135 A1950 Formation of Embankment From out sout source/ Suitable Excavated Material 46 days Mon 3/26/18 Mon 5/28/18 Surveyor,Labour,Site Engineer,Excavator,Trector
10 Trolly,Dumper 5/28
136 A1960 Sub-Grade Prepation works 41 days Fri 4/27/18 Fri 6/22/18 Roller,Water Truck,Highway Engineer,Water,Lab
10 Technician,Grader 6/22
137 SHAIGARI TO SHAHPUR.6.1 Protection Work & BOX Culvert - BILL 162 days Wed 1/3/18 Thu 8/16/18 Labour,Excavator,Trector
NO (4 & 5 ) Trolly,Dumper,Site
Engineer,Surveyor,Roller
138 A1970 Structural Excavation 35 days Wed 1/3/18 Tue 2/20/18 Site Engineer,Surveyor,Project manager,Supervisor,Skilled
10 Labour,Excavator,Dumper,Buldozer 1202/20HP
139 A1980 Lean Concrete 20 days Tue 1/23/18 Mon 2/19/18 Surveyor,Labour,Site Engineer,Lab Technician,Project
10 2/19
manager,Material Engineer,Structure Engineer,Scoffolder,Steel Fixer,Transit Mixer,Concrete Pump,Concrete Batching Plant,Cement,Steel,Water,Crush,Sand
140 A1990 Stone Masonry Works 34 days Thu 3/22/18 Tue 5/8/18 Surveyor,Labour,Site Engineer,Lab Technician,Project
10 5/8
manager,Material Engineer,Scoffolder,Structure Engineer,Cement,Water,Sand
141 A2000 Fitter layer of Grangular Material if required 30 days Mon 6/25/18 Fri 8/3/18 Surveyor,Labour,Site Engineer,Lab Technician,Project
10 manager,Material Engineer,Scoffolder,Water 8/3
142 A2010 Concrete Works Class-A 23 days Mon 4/2/18 Wed 5/2/18 Surveyor,Site Engineer,Lab Technician,Project
10 5/2 Fixer,Transit Mixer,Concrete Pump,Concrete Batching Plant,Cement,Steel,Water,Crush,Sand
manager,Material Engineer,Structure Engineer,Labour,Scoffolder,Steel
143 A2020 Granular Backfill with approved Material 28 days Mon 7/2/18 Wed 8/8/18 Surveyor,Labour,Site Engineer,Lab Technician,Project
10 manager,Material Engineer,Water,Front End Loader,Excavator 8/8
144 A2030 Grouted Rip Rap Works 31 days Thu 7/5/18 Thu 8/16/18 Surveyor,Labour,Site Engineer,Lab Technician,Project
10 manager,Material Engineer,Water,Sand 8/16
145 SHAIGARI TO SHAHPUR.6.5 Sub Base & Base Works 63 days Fri 8/17/18 Tue 11/13/18
146 A2040 Granular Subbase Works 31 days Fri 8/17/18 Fri 9/28/18 Lab Technician,Site Engineer,Surveyor,Labour,Project
10,20,144 9/28
manager,Highway Engineer,Skilled Labour,Aggregate,Grader,Water,Roller,Tool & Plants,Excavator,Dumper
147 A2050 Aggregate Base Works 32 days Mon 10/1/18 Tue 11/13/18 Lab Technician,Site Engineer,Surveyor,Labour,Project
146 11/13
manager,Highway Engineer,Skilled Labour,Aggregate,Grader,Water,Roller,Tool & Plants,Excavator,Dumper
148 SHAIGARI TO SHAHPUR.6.6 Pavement Works 40 days Wed 11/14/18 Tue 1/8/19
149 A2060 Cut Back Asphal Prime Coat 27 days Wed 11/14/18 Thu 12/20/18 Forman,Skilled Labour,Supervisor,Oil,Site
147Engineer,Project manager,Material Engineer,Aphalt,Water,Tool & Plants,Highway Engineer,Water Truck 12/20
150 A2070 Asphalt Wearing Concrete Course 13 days Fri 12/21/18 Tue 1/8/19 Load Test Machine,Skilled Labour,Supervisor,Highway
149 1/8
Engineer,Site Engineer,Project manager,Material Engineer,Forman,Loader,Excavator,Oil,Asphalt. Water,Tandem Roller,Aggregate,Combination Roller,Tool & Plant
151 SHAIGARI TO SHAHPUR.6.4 Ancillary Work 74 days Wed 1/9/19 Mon 4/22/19
152 A2080 Pavement Marking & Fixing of Reflected Studs 31 days Wed 1/9/19 Wed 2/20/19 Site Engineer,Road Marking Machine,Supervisor,Skilled
150 Labour,Studs,Trector Trolly 2/20
153 A2090 Right of way Marker as per given size 47 days Wed 1/9/19 Thu 3/14/19 Supervisor,Site Engineer,Skilled Labour,Tool
150 & Plants 3/14
154 A2100 Installation of Kilo meter Posts as per Drawing 41 days Wed 1/9/19 Wed 3/6/19 Skilled Labour,Project manager,Site Engineer,Surveyor,Supervisor,Concrete
150 Batching Plant,Shuttring Plates And Scaffolding,Transit Mixer & Concrete Pump 3/6
155 A2110 Installation of all types of Traffic Road Signs 15 days Tue 4/2/19 Mon 4/22/19 Site Engineer,Skilled Labour,Tool & Plants,Supervisor,Water,Cement,Trector
150 Trolly,Masons,Concrete Batching Plant 4/22
156 SHAIGARI TO SHAHPUR.11 HANDING/TAKING OVER PROJECT 21 days Mon 7/1/19 Mon 7/29/19
157 A1000 Punch List Correction works 5 days Mon 7/1/19 Fri 7/5/19 Highway Engineer,Lab Technician. Material Engineer,Masons,Forman,Project manager,Structure Engineer,Tool & Plants,Excavator,Trector Trolly,Labour,Water,Site Engineer,Sand,Transit Mixer &7/5
39,68,97,126,155 Concrete Pump,Concr
158 A1010 Handing over 5 days Tue 7/23/19 Mon 7/29/19 Project manager 39,68,97,126,155 7/29

Project: YAKMACH KHARAN Task Progress Summary External Tasks Deadline


Date: Fri 10/13/17 Split Milestone Project Summary External Milestone

Page 3
An evaluation version of novaPDF was used to create this PDF file.
Purchase a license to generate PDF files without this notice.

Вам также может понравиться