Вы находитесь на странице: 1из 16

OBRA : "MEJORAMIENTO DEL ORNATO DE LA PLAZA DE ARMAS DE LA CIUDAD DE AZANGARO, PROVINCIA DE AZANGARO - PUNO"

LUGAR : AZANGARO Horas/día 8.00 % ESSALUD 6.00%


PLAZO : 180 dias RMV S/. 750.00 Tasa anual 2.50%
FECHA : 2/13/2019 % a SNP 13.00% Fila iteración 36

DESAGREGADO DE GASTOS GENERALES

A CARACTERISTICAS
Costo directo S/. 907,475.47
Gastos Generales 13.8656% 125,826.92
Utilidad 8.00% 72,598.04
Sub- Total S/. 1,105,900.43
IGV 18.00% S/. 199,062.08
Total 1,304,962.51
Plazo de ejecución : ( meses) 6.00

B GASTOS GENERALES VARIABLES


B.1 Personal Profesional y Tecnico Cantidad Tiempo Costo Participación Parcial Total
Ing. Residente 1 6.00 S/. 3,300 100.00% S/. 19,800.00
Ing. Asistente de Residente de Obra 1 6.00 S/. 1,600 100.00% S/. 9,600.00
Ing. Electrico 1 1.00 S/. 2,500 20.00% S/. 500.00
Especialista en Medio Ambiente 1 2.00 S/. 2,500 20.00% S/. 1,000.00
Arqueologo 1 2.00 S/. 2,500 20.00% S/. 1,000.00
Total gasto personal técnico S/. 31,900.00
B.2 Personal Administrativo y Auxiliar Cantidad Tiempo Costo Participación Parcial Total
Administrador de Obra 1 6.00 S/. 1,500 100.00% S/. 9,000.00
Topografo 1 4.00 S/. 1,500 30.00% S/. 1,800.00
Guardian 1 6.00 S/. 900 100.00% S/. 5,400.00
Maestro de Obra 1 6.00 S/. 1,600 100.00% S/. 9,600.00
Jefe de almacen 1 6.00 S/. 1,500 100.00% S/. 9,000.07
Total gasto personal administrativo y auxiliar S/. 34,800.07
B.3 Gastos Oficina de Obra Cantidad Tiempo Costo Participación Parcial Total
Equipo de computo inc. impresora 3 6.00 S/. 60 100.00% S/. 1,079.17
Agua personal (bidones) 1 6.00 S/. 22 100.00% S/. 132.00
Bloqueador solar 1 6.00 S/. 57.63 100.00% S/. 345.78
Materiales y Utiles de Escritorio 1 6.00 S/. 20 100.00% S/. 120.00
Fotocopias e Impresiones 1 6.00 S/. 30 100.00% S/. 180.00
Muebles de Oficina 1 1.00 S/. 900 100.00% S/. 900.00
Materiales para limpieza 1 6.00 S/. 20 100.00% S/. 120.00
Exámenes médicos 1 1.00 S/. 521.56 100.00% S/. 521.56
Total gastos oficina de obra S/. 3,398.51
B.4 Oficina General Cantidad Tiempo Costo Participación Parcial Total
Contador 1 6.00 S/. 2,086 20.00% S/. 2,502.80
Jefe de Logistica 1 6.00 S/. 1,960 20.00% S/. 2,352.00
Total gasto Oficina General S/. 4,854.80
B.5 Servicios Oficina General Cantidad Tiempo Costo Participación Parcial Total
Alquiler 1 6.00 S/. 120 20.00% S/. 144.00
Utiles de escritorio 1 6.00 S/. 250 20.00% S/. 300.00
Movilidad 1 6.00 S/. 300 20.00% S/. 360.00
Total gasto Servicios Oficina General S/. 804.00
B.6 Beneficios sociales Unidad Tiempo Cantidad Costo Parcial Total
Asignacion familiar Glb 1 S/. 3,360.00 S/. 3,360.00
Essalud Glb 1 S/. 4,935.29 S/. 4,935.29
CTS Glb 1 S/. 8,153.31 S/. 8,153.31
Vacaciones Glb 1 S/. 7,096.70 S/. 7,096.70
Gratificación Glb 1 S/. 14,886.20 S/. 14,886.20
Total gasto Beneficios Sociales S/. 38,431.50
B.7 Equipos no incluidos en costos directos Unidad Cantidad Tiempo Costo Parcial Total
Transporte para tramites varios glb 1 6.00 S/. 30.00 S/. 180.00
Total equipos no incluidos en costos directos S/. 180.00
B.8 Cartas fianza Tiempo Monto Tasa mensual % x amortizacion Parcial Total
Carta Fianza Adelanto Efectivo (20%) 6 S/. 1,105,900.43 0.208% 62.50% 1,727.97
Carta Fianza por Fiel Cumplimiento (10%) 7 S/. 1,105,900.43 0.208% 100.00% 1,612.77
Carta Fianza Adelanto Materiales (40%) 6 S/. 1,105,900.43 0.208% 62.50% 3,455.94
Total cartas fianza S/. 6,796.68
B.9 Polizas Tiempo Monto Parcial Total
Poliza CAR 1 S/. 120.00 150.00
Poliza SCTR Salud 6 S/. 33.35 200.10
Poliza SCTR Pensión 6 S/. 36.50 218.98
Total polizas S/. 569.08
TOTAL GASTOS GENERALES VARIABLES S/. 121,734.65
OBRA : "MEJORAMIENTO DEL ORNATO DE LA PLAZA DE ARMAS DE LA CIUDAD DE AZANGARO, PROVINCIA DE AZANGARO - PUNO"
LUGAR : AZANGARO Horas/día 8.00 % ESSALUD 6.00%
PLAZO : 180 dias RMV S/. 750.00 Tasa anual 2.50%
FECHA : 2/13/2019 % a SNP 13.00% Fila iteración 36

DESAGREGADO DE GASTOS GENERALES

A CARACTERISTICAS
Costo directo S/. 907,475.47
Gastos Generales 13.8656% 125,826.92
Utilidad 8.00% 72,598.04
Sub- Total S/. 1,105,900.43
IGV 18.00% S/. 199,062.08
Total 1,304,962.51
Plazo de ejecución : ( meses) 6.00

C GASTOS GENERALES FIJOS


C.1 Ensayos y pruebas Unidad Cantidad Costo Parcial Total
Ensayo de agregados
Desgaste por abrasión und 1 S/. 50.85 S/. 50.85
Impurezas orgánicas und 1 S/. 33.90 S/. 33.90
Material que pasa por la malla 200 und 1 S/. 16.95 S/. 16.95 S/. 101.69
Ensayos de concreto
Diseño de mezcla und 2 S/. 127.12 S/. 254.24
Resistencia a la compresión und 12 S/. 12.71 S/. 152.54
Briquetas (testigos para probetas de conc) und 3 S/. 50.00 S/. 150.00 S/. 556.78
Ensayo de mecánica de suelos
Contenido de humedad und 4 S/. 8.47 S/. 33.90
Analisis granulometico por tamizado und 4 S/. 50.85 S/. 203.39
Valor relativo e soporte CBR und 4 S/. 101.69 S/. 406.78
Proctor modificado und 4 S/. 33.90 S/. 135.59
Limite liquido und 4 S/. 16.95 S/. 67.80
Limite plástico und 4 S/. 21.19 S/. 84.75
Densidad de cmpo (in situ) und 4 S/. 25.42 S/. 101.69 S/. 1,033.90

C.2 GASTOS FINANCIEROS Cantidad Costo Participación Parcial Total


Gastos de Licitación y otros
Preparacion de documentos para la firma de contrato 1 S/. 150.00 100.00% S/. 150.00
Gastos notariales 1 S/. 180.00 100.00% S/. 180.00
Liquidación de obra 1 S/. 964.00 100.00% S/. 964.00 S/. 1,294.00
TRIBUTOS
Sencico 1 1,105,900.43 0.10% 1,105.90 S/. 1,105.90

TOTAL GASTOS GENERALES FIJOS S/. 4,092.27

D INCIDENCIA DE GASTOS GENERALES


Descripción Valor Porcentaje
VARIABLES 121,734.65 13.415%
FIJOS 4,092.27 0.451%
TOTAL 125,826.92 13.8656%
"MEJORAMIENTO DEL ORNATO DE LA PLAZA DE ARMAS DE LA CIUDAD DE AZANGARO, PROVINCIA DE AZANGARO -
PUNO"
CÁLCULO DE BENEFICIOS SOCIALES DEL TOTAL DE TRABAJADORES (TOTAL DE OBRA)
(Sueldo+Asig) x ((Sueldo+asig+ES (Sueldo+asig+gra
Definiciones 10% RMV Sueldo x 0.06 (Sueldo +asig)/12
0.13 SALUD)/12)*2 tif)/12
Vacaciones Total a Pagar por
Personal Técnico Administrativo Cantidad Meses Precio Unitario Precio TOTAL Asignación * SNP ** ESSALUD Gratificaciones CTS
Truncas beneficios sociales

Gerente de Proyecto 0 7.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
Ing. Residente 1 7.00 S/. 3,300.00 S/. 23,100.00 S/. 525.00 S/. 3,071.25 S/. 1,386.00 S/. 4,168.50 S/. 2,316.13 S/. 1,968.75 S/. 10,364.38
Ing. Asistente de Residente de Obra 1 6.00 S/. 1,600.00 S/. 9,600.00 S/. 450.00 S/. 1,306.50 S/. 576.00 S/. 1,771.00 S/. 985.08 S/. 837.50 S/. 4,619.58
Ing. Electrico 1 6.00 S/. 2,500.00 S/. 15,000.00 S/. 90.00 S/. 392.34 S/. 180.00 S/. 509.00 S/. 259.98 S/. 251.50 S/. 1,290.48
Especialista en Medio Ambiente 1 6.00 S/. 2,500.00 S/. 15,000.00 S/. 90.00 S/. 392.34 S/. 180.00 S/. 509.00 S/. 259.98 S/. 251.50 S/. 1,290.48
Arqueologo 1 6.00 S/. 2,500.00 S/. 15,000.00 S/. 90.00 S/. 392.34 S/. 180.00 S/. 509.00 S/. 259.98 S/. 251.50 S/. 1,290.48

PERSONAL DE OBRA
Ing. Sanitario 0 6.00 S/. 6,000.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
Ing. De Seguridad y Salud (Prevencionista de Riesgo) 0 6.00 S/. 5,500.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
Especialista en Medio Ambiente 0 6.00 S/. 5,500.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
Ing. de Control de calidad y Protocolos 0 6.00 S/. 5,500.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
Administrador de Obra 1 6.00 S/. 1,500.00 S/. 9,000.00 S/. 450.00 S/. 1,228.50 S/. 540.00 S/. 1,665.00 S/. 926.25 S/. 787.50 S/. 4,368.75
Topografo 1 6.00 S/. 1,500.00 S/. 9,000.00 S/. 135.00 S/. 356.27 S/. 162.00 S/. 464.85 S/. 240.00 S/. 228.38 S/. 1,230.22
Guardian 1 6.00 S/. 900.00 S/. 5,400.00 S/. 450.00 S/. 760.50 S/. 324.00 S/. 1,029.00 S/. 573.25 S/. 487.50 S/. 2,863.75
Maestro de Obra 1 6.00 S/. 1,600.00 S/. 9,600.00 S/. 450.00 S/. 1,306.50 S/. 576.00 S/. 1,771.00 S/. 985.08 S/. 837.50 S/. 4,619.58
Jefe de almacen 1 6.00 S/. 1,500.01 S/. 9,000.07 S/. 450.00 S/. 1,228.51 S/. 540.00 S/. 1,665.01 S/. 926.26 S/. 787.51 S/. 4,368.78
Maestro de Obra 0 6.00 S/. 3,200.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
Jefe de almacen 0 6.00 S/. 3,000.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
Auxiliar de Almacen 0 6.00 S/. 1,800.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
Chofer 0 6.00 S/. 2,500.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
Tareador 0 6.00 S/. 1,800.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
Planillero 0 6.00 S/. 1,800.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
Gerente General 0 6.00 S/. 12,000.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00

DE OFICINA
PERSONAL
Secretaria de gerencia 0 6.00 S/. 2,400.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
Gerente Administrativo y Financiero 0 6.00 S/. 5,500.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
Secretaria 0 6.00 S/. 2,000.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
Contador 1 6.00 S/. 2,085.67 S/. 12,514.00 S/. 90.00 S/. 327.70 S/. 150.17 S/. 425.14 S/. 217.15 S/. 210.07 S/. 1,092.53
Gerente Tecnico 0 6.00 S/. 5,500.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
Jefe de Logistica 1 6.00 S/. 1,960.00 S/. 11,760.00 S/. 90.00 S/. 308.10 S/. 141.12 S/. 399.70 S/. 204.16 S/. 197.50 S/. 1,032.49
Total S/. 143,974.07 S/. 3,360.00 S/. 11,070.85 S/. 4,935.29 S/. 14,886.20 S/. 8,153.31 S/. 7,096.70 S/. 38,431.50
Nota:
* La remuneración mínima vital (RMV) está establecida en S/. 750 a la fecha.
** Este concepto es un aporte que se descuenta del sueldo del trabajador como pago a cuenta de su jubilación. Los demás rubros considerados son aportes del empleador y se pagan todos los meses.
Cálculo de personal (STAFF) que requiere viáticos Cálculo de personal (obrero) que requiere viáticos
Nº personas Requiere Nº personas
Nº Descripción STAFF viático con viático
Descripción Total HH % considerado Total considerado

1 Gerente de Proyecto 0 No 0 Op. Equipo liviano 164.35 0.00% -


2 Ing. Residente 1 Si 1 Capataz - 100.00% -
3 Ing. Asistente de Residente de Obra 1 Si 1 Operario 4,981.83 70.00% 3,487.28
4 Ing. Electrico 1 Si 1 Oficial 4,477.67 50.00% 2,238.84
5 Especialista en Medio Ambiente 1 Si 1 Peón 6,017.20 0.00% -
6 Arqueologo 1 No 0 Topógrafo - 100.00% - Total HH consideradas
7 Ing. Sanitario 0 No 0 Op. Electrom - 100.00% - 5,726.12
8 Ing. De Seguridad y Salud (Prevencionista de R 0 Si 0 Total personal que requiere viáticos 4
9 Especialista en Medio Ambiente 0 Si 0
10 Ing. de Control de calidad y Protocolos 0 Si 0 Cálculo de viáticos
11 Administrador de Obra 1 Si 1 VIATICOS PERSONAL OBRERO (costo por mes) VIATICOS PERSONAL STAFF
12 Topografo 1 No 0 Descripción Costo Descripción Costo
13 Guardian 1 No 0 Habitación x 6 personas S/. 60.00 Habitación x 3 persona(s) por mes S/. 0.00
14 Maestro de Obra 1 No 0 Número de personas por habitación 6 Número de personas por habitación 3.00
15 Jefe de almacen 1 No 0 Habitación por persona S/. 0.00 Habitación por persona S/. 0.00
16 Maestro de Obra 0 Si 0 Alimentación por día (des + almu + cena) S/. 0.00 Alimentación por día (des + almu + cena) S/. 0.00
17 Jefe de almacen 0 Si 0 Pasaje ida y vuelta (Lima - obra) S/. 0.00 Pasaje ida y vuelta (si es avión sin IGV) -
18 Auxiliar de Almacen 0 No 0 Pasaje por persona x mes S/. 0.00 Pasaje por mes -
19 Chofer 0 No 0 Viático por persona por mes S/. 0.00 Viático por persona por mes S/. 0.00
20 Tareador 0 No 0 Viático por persona en toda la obra S/. 0.00 Viático por persona en toda la obra -
21 Planillero 0 No 0 Viático en toda la obra S/. 0.00 Viático en toda la obra S/. 0.00
Total personal que requiere viáticos 5 Total viáticos todo el personal S/. 0.00
Cálculo de personas que requieren bloqueador (STAFF)
Nº personas
Nº personas Participación Requiere
Descripción STAFF día Bloqueador
requieren
bloqueador

Gerente de Proyecto 0 100% No 0

Ing. Residente 1 100% Si 1

Ing. Asistente de Residente de


1 100% Si 1
Obra

Ing. Electrico 1 100% No 0

Especialista en Medio Ambiente 1 33% No 0

Arqueologo 1 33% No 0

Ing. Sanitario 0 33% No 0

Ing. De Seguridad y Salud


0 100% Si 0
(Prevencionista de Riesgo)

Especialista en Medio Ambiente 0 100% Si 0

Ing. de Control de calidad y


0 100% Si 0
Protocolos

Administrador de Obra 1 100% Si 1

Topografo 1 100% No 0

Guardian 1 100% No 0

Maestro de Obra 1 100% No 0

Jefe de almacen 1 50% Si 1

Maestro de Obra 0 100% Si 0

Jefe de almacen 0 100% No 0

Auxiliar de Almacen 0 100% No 0

Chofer 0 100% Si 0

Tareador 0 100% Si 0

Planillero 0 100% No 0

Total 4
Cálculo del promedio por día de personal obrero en obra
HH HH HH HH
Descripción Estructuras Arquitectura I. Sanitarias I. Eléctricas Total H.H.

Op. Equipo liviano 164.35 164.35


Capataz 0.00 -
Operario 4981.83 4,981.83
Oficial 4477.67 4,477.67
Peón 6017.20 6,017.20
Topógrafo 0.00 -
Op. Electrom 0.00 -
Número total de horas hombre 15,641.05
Número de trabajadores promedio 11

Total de personas que requieren bloqueador


Descripción Nº Personas % Uso Total personas

Obreros 11 20% 3
Staff 4 30% 1

Total de personas que requieren bloqueador 4

Cálculo del costo del bloqueador


Cantidad de bloqueador x mes x
persona (litros) 0.165
Cantidad de bloqueador para la
obra (litros x mes) 0.693
Costo por litro S/. 83.16
Costo total de bloqueador x
mes S/. 57.63
Nota: La cantidad de bloqueador por persona está
establecida por el fabricante y es de 0.165 lt/mes
SE OBSERVA Q ES MEJOR TOMAR DE LA GENERAL

hh
Nº Descripción Cantidad
1 Gerente de Proyecto 0
2 Ing. Residente 1
3 Ing. Asistente de Residente de Obra 1
4 Ing. Electrico 1
5 Especialista en Medio Ambiente 0
6 Arqueologo 0
7 Ing. Sanitario 0
8 Ing. De Seguridad y Salud (Prevencionista de Riesgo) 0
9 Especialista en Medio Ambiente 0
10 Ing. de Control de calidad y Protocolos 0
11 Administrador de Obra 1
12 Topografo 1
13 Guardian 1
14 Maestro de Obra 1
15 Jefe de almacen 1
16 Maestro de Obra 0
17 Jefe de almacen 0
18 Auxiliar de Almacen 0
19 Chofer 0
20 Tareador 0
21 Planillero 0
Total 8

Costo de Examen Médico




Nº Descripción exámenes C.U. Total
personas
en la obra
1 Obra 5 1 S/. 40.12 S/. 200.60
2 Staff 8 1 S/. 40.12 S/. 320.96
Total S/. 521.56
Nota: El costo de S/. 40.12 se encuentra actualizado al 31/12/2018 (cotización); el exámen se realiza una
vez al año.
Resumen Costo Directo
Ítem Subpresupuesto Valor
001 ESTRUCTURAS 907,475.47 actualizar valores con ultimo ppto

Total S/. 907,475.47 Va en celda de GG


11,613,660.36 4,498,520.44
5,404,283.45 3,561,478.63
542,941.67 1,565,026.50
5,328,785.51 836,170.61
Liquidación de Obra
Nº Descripción Unidad Cantidad C.U. Total
1 Ing. Asistente Mes 0.5 S/. 1,600 S/. 800
2 Dibujante Mes 0 S/. 3,000 S/. 0
3 Copias de planos Plano 20 S/. 6 S/. 120
4 Material de oficina Paquete 4 S/. 11 S/. 44
Total S/. 964
TIEMPO DE EJECUCION 2da 6 MESES

ESTR ARQUIT SANIT ELECTR


CAPATAZ - - - - HH
OPERARIO - - - 4,981.83 HH
OPER EQ LIV - - - 164.35 HH
OPER ELECTRO - - - - HH
OFICIAL - - - 4,477.67 HH
PEON - - - 6,017.20 HH
TOPOGRAFO - - - - HH

- - - 15,641.05 HH

SEGUNDA FASE 15,641 HH

PERSONAL OBRERO 10
STAFF Y ADMINIST 23

fase 1 fase 2 fase 3 CAPATAZ


estr EDIF 115,328.38 116,860.43 47,287.62 279,476.43
arq EDIF 71,119.41 76,001.40 15,471.51 162,592.32
sanit EDIF 6,918.34 6,921.99 2,390.61 16,230.94
elect EDIF 10,868.86 12,112.53 2,097.59 25,078.98
estr EXT 46,080.78 25,558.11 29,643.53 101,282.42
arq EXT 51,466.73 33,339.57 17,175.81 101,982.11
sanit EXT 18,099.13 12,664.91 13,006.91 43,770.95
elect EXT 3,489.40 3,929.59 243.77 7,662.76

323,371.03 287,388.53 127,317.35 738,076.91

224.56 171.06 176.83

192.207528646

Esto del total para 16 meses


Descripción Cantidad Und.
CAPATAZ - hh
OPERARIO 4,981.83 hh
OFICIAL 4,477.67 hh
PEON 6,017.20 hh
OPERADOR DE EQU 164.35 hh
OPERARIO ELECT - hh
TOPOGRAFO - hh
15,641.05
4.07 trabajadores
FASE 1 6 MES
FASE 2 7 MES
FASE 3 3 MES
Nº Descripción Cantidad
1 Gerente de Proyecto -
- 2 Ing. Residente 1.00
4,981.83 3 Ing. Asistente de Residente de Obra 1.00
164.35 4 Ing.de Costos y Valorizaciones 1.00
- 5 Ing. Electromecánico 1.00
4,477.67 6 Ing. Estructural 1.00
6,017.20 7 Ing. Sanitario 1.00
- 8 Ing. De Seguridad y Salud (Prevencionista de Riesgo) 1.00
9 Especialista en Medio Ambiente 1.00
10 Ing. de Control de calidad y Protocolos 1.00
11 Administrador de Obra 1.00
12 Médico ocupacional 1.00
13 Secretaria 1.00
14 Dibujante 1.00
15 Guardian 2.00
16 Maestro de Obra 2.00
17 Jefe de almacen 2.00
18 Auxiliar de Almacen 1.00
19 Chofer 1.00
20 Tareador 1.00
21 Planillero 1.00

Total 23.00
OPERARIO OFICIAL PEON TOPOGRAFO OPE LIV
OPER ELECTROM
1,276,297.53 mejoramiento vias
1,635,879.71 mejoramiento vias
2,014,479.20 mejoramiento de calles
562,077.00 mejoramiento de parque
1,093,490.33 construccion de complejo
604,317.35 construccion de complejo
262,147.37 mejoramiento de area deportiva
394,575.63 mejoramiento de plaza
302,811.44 mejoramiento complejo deportivo

3,219,419.12