Академический Документы
Профессиональный Документы
Культура Документы
1972
Recommended Citation
Roskopf, Robert Frank, "Trickling filter-activated sludge combinations for domestic wastewater treatment " (1972). Retrospective
Theses and Dissertations. Paper 4773.
This Dissertation is brought to you for free and open access by Digital Repository @ Iowa State University. It has been accepted for inclusion in
Retrospective Theses and Dissertations by an authorized administrator of Digital Repository @ Iowa State University. For more information, please
contact hinefuku@iastate.edu.
INFORMATION TO USERS
This dissertation was produced from a microfilm copy of the original document.
While the most advanced technological means to photograph and reproduce this
document have been used, the quality is heavily dependent upon the quality of
the original submitted.
1. The sign or "target" for pages apparently lacking from the document
photographed is "Missing Page(s)". If it was possible to obtain the
missing page(s) or section, they are spliced into the film along with
adjacent pages. This may have necessitated cutting thru an image and
duplicating adjacent pages to insure you complete continuity.
3. When a map, drawing or chart, etc., was part of the material being
photographed the photographer followed a definite method in
"sectioning" the material. It is customary to begin photoing at the
upper left hand corner of a large sheet and to continue photoing from
left to right in equal sections with a small overlap. If necessary,
sectioning is continued again — beginning below the first row and
continuing on until complete.
University Microfilms
300 North Zeeb Road
Ann Arbor Michigan 48106
by
DOCTOR OF PHILOSOPHY
Approved:
1972
PLEASE NOTE:
i nd i St ! net print.
Filmed as received.
INTRODUCTION
LITERATURE REVIEW
Parallel System
Cost of Domestic Wastewater Treatment
Summary
Plant description
Operation
Operation
Compositing Samples
COD Analyses
BOD Analyses
Suspended Solids
Dissolved Oxygen
iii
Primary Effluent 80
Nitrification 150
iv
Page
Smnmary 153
Parallel 161
TF-A 163
A-TF 167
ACKNOWLEDGEMENTS 191
APPENDIX A. ABBREVIATIONS 19 2
LIST OF FIGURES
Figure Page
Figure Page
Figure Page
34. Daily flow and BOD trends during the pilot study 133
LIST OF TABLES
Page
INTRODUCTION
generated the interest and defined the scope for this study.
Babbitt and Baumann (6), and Fair, Geyer, and Okun (25).
similar situations.
Since either process can be used as the first stage of a
feasibility.
PE TF
TRICKLING FILTER
RETURN
WASTE SLU06E
SLUDGE'
PARALLEL
3-7-69 TO 6-20-69
PE TF
SERIES TF-A
6-20-69 TO 10-18-69
PE TF
WASTE SLUDGE
SERIES A-TF
10-18-89 TO 1-15-70
engineer.
8
LITERATURE REVIEW
that which takes place in the short time required for passage
trickling filters.
and other corn products. The waste liquids were at times equi
filter.
Miller (57) reported on the use of bacterial filters at
for this plant were a final effluent with BOD and suspended
solids of 20 mg/1.
wastewater had a BOD of 841 mg/1 and the dry weather flow was
domestic in nature.
14
did not affect the filter operation. This application was not
systems.
average of once every ten minutes, but the rest period was
used.
effluent BOD was in the range of 4.5 to 17.8 mg/1 with total
and using lime to adjust the pH. This process was successful
process.
of the course.)
observed when the plant was operated in this manner, but filter
raw wastewater BOD ranged from 114 mg/1 up to 1,370 mg/1 in the
various plants, and the overall BOD removal achieved with the
works wastewater.
sludge process.
had a BOD of approximately 450 mg/1 and the final effluent BOD
was approximately 20 mg/1. Average daily flows were approxi
clarifier.
before the trickling filters. The new 22.5 mgd plant will
treatment.
toxic wastes.
mately 97 percent.
has been used in Germany (65): but as with most other applica
reducing the influent BOD from 471 mg/1 to a value of 230 mg/1
26
floe absorbed dye and was killed when activated sludge was
was better when the waste was mixed with domestic wastewater
stage roughing filter and found that the roughing filters did
wastewater treatment.
with a 2,200 gal aeration tank and a 370 gal settling tank.
The raw flow varied from 8.6 to 10.7 mgd. The trickling
the four available aeration tanks were used and the sludge
280 to 320 mg/1 and the flow averaged 2.17 mgd. In-plant
and the records indicated that the trickling filter load was
of 1963 through 1966, raw flows averaged 1.2 to 1.3 mgd; and
plant operation and maintenance costs were in the range of
200 mg/l and the final effluent BOD was in the range of 7 to
13 mg/l. The operator did his own lab work and used four- to
flora and fauna and prevent growth of wild yeast and molds
288 mg/1, and 90 percent of the raw BOD was removed. With
36
when the fine paper mill effluent was treated with the trick
about 0.2 mgd, and the plant effluent, which flows into a
final effluent.
and solids were lost over the weir of the final settling teink.
that the BOD of the primary influent was 221 mg/1, the
^ ^ W» MO.»** W • W A* «b W W* AW ^ O ^ W W&C» ^^ ^ ^
a BOD of 500 to 600 mg/1, and the final effluent BOD often was
less than 10 mg/1. The trickling filter loading was approxi
mately 60 to 70 lb BOD/day/1/000 cu ft at a corresponding
hydraulic loading of approximately 7 mgd/acre. Assuming 50
BOD/day/1,000 cu ft.
raw BOD often was between 1,000 and 1,500 mg/1 at night and
between 300 and 500 mg/1 during the day. The six-month
average BOD of 24-hour composite raw wastewater samples was
545 mg/1 during the last six months of 1971. Typical grab
loaded plant was operated and maintained by only two men and
effluent.
that the two trickling filters were not being used at the
designed for a large industrial waste load which had not been
realized by 1972.
The raw wastewater BOD varied from 300 to 800 mg/1, and
plant, and plans were made to cover this unit before another
winter season.
Parallel System
BOD removed basis, the activated sludge system was much more
5.0 feet. When the plant was operated as designed rather poor
RAW
WASTEWATER
1*
PRIMARY
TREATMENT
0 53
ACTIVATED
SLUDGE
in the range of 400 to 600 mg/l and the final effluent BOD was
1
^Howard Helgeson, City of Faribault, Minnesota, private
communication, 1971.
47
shown in Figure 2. Flows averaged about 3.8 mgd and the raw
costs vary with the type of treatment being used and the size
reflected in the fact that the unit cost of a 1.0 mgd primary
to four times as high as the total per unit treatment cost for
112 gpd/cap over the past 18 years (89). The par capita cost
can be obtained.
In 1968, Stephan and Weinberger (79) discussed the
$20 per person per year. Since the present potable water
source and treatment probably costs the typical resident of
such a community between $2 to $5 per year, the direct reuse
1/5 to 1/3 the cost of obtaining fresh water from the sea. It
can be seen that for less than 2<: per person per day, primary
operation.
Perhaps one additional point should be made to establish
Summary
been extracted from the literature and these data have been
Grove City,
Pa. Domestic 74 -- 59 84 (67)
St. Paul,
Minnesota Refinery 10 — 46 — — (33)
Belleville, Domestic,
Illinois brewer, meat 385 16 170 38 27 93 (47)
Ortonville,
Minnesota Domestic 210 10 60 30 65 80 (p. 34)
Northampton, Domestic &
England industrial 50 0 15 115 10 60 80 (61)
Maple Plaine,
Minnesota Domestic 185 12 17 — — — (p. 31 )
San
Buenaventura,
California Domestic 221 17 39 24 62 62 (13)
Milan, Domestic
Illinois & meat 550 15 65 22 50 — (p. 39)
plant operator usually knew the raw and final effluent BOD,
engineers.
upon, best way cf combining the two systems and very little
used throughout this study are located at the Ames, Iowa water
TRICKLING FILTER
NO. 2
(ONE Of THREE) PREAERATION AND
«HT REMOVAL OXICEST
3" PILOT FILTER
EFFLUENT
54"M.H
OUTFALL-J
PRIMARY- SEWER TO
SETTLING SKUNK RIVER
TANKS
PILOT
I 1/4" PLASTIC PIPE FILTER
2 1/2" COVER) 24" CONCRETE
SEWER
Figure 3. Pilot plant location at the Ames/ Iowa water pollution control plant
VVASTE
FLOW
M • VALVE
N » CHECK VALVE
AERATION
TANK
(COMPLETE MIX)
54 MANHOLE
r~
I 1/4" I 1/4"
r DIAM
TRICKLING FILTER
SUMP
AND PUMP
WASTE 4 TILE
SLUDGE TO WASTE
OVCRFLOW
12'-9 1/2"
6 ' - 10"
AERATION TANK
EFFLUENT AM LIFT
PUMP.
mSTE
SLUSOE
7 RETURN 3 <SSL^
Î
SLUOOE SPLITTER BOX
PLAN VIEW
INFLUENT
CONTROL
PANEL ~
SLUOOE SPLITTER
BOX AIR HEADER
BLOWER
HOUSE
INFLUENT
EFFLUENT
DIFFUSER:
(3 PROVIDED)
SECTION A-A
Plant description
process (14). The influent flow for the Oxigest was either
hp). The pump was located at the effluent end of the primary
by the air lift return sludge pump. Mixed liquor entered the
settling tank.
plant outfall sewer. During the portion of the study when the
Operation
flow.
the pump. Each time the main plant was shut down for a short
period of time, the pump would air lock. In January, 1970
near the end of the study, the pump plugged and froze solid
normally recycled all the sludge back into the aeration tank.
Sludge was wasted from the system for approximately one hour
Thus, on a typical day sludge was wasted for about one hour
and again after wasting sludge for one hour. The solids con
wasting period, and the flow rate was less. This was not
less sludge was wasted from the system, the build-up would
continue until solids passed over the settling tank weir with
breaks down.
67
ment plants. The filter was designed and built to serve for
Plant description
Operation
^ «3 f AA W* * W A* A ^ a_r w
trickling filter.
During the series A-TF portion of the study, the maximum
between the two units. Although this pump was not specifically
REMOVABLE VENT
SECTIONS
N
4" GATE
VALVE
TO J*AJTE
CT\
VÛ
FLOOR DRAIN
4" ALUMINUM
PIPE AIR VENT I'X l'-6" UNDKRDRAIN TILE
l«'-|0"
2" SHAFT
7'-0'
OUARTZITE
filter ROCK BUILDING 2"X4" STUDS
AND 1/2" PLYWOOD »
BUILDING
WALL
t=;:
I 1/2" BLACK
IRON PIPE
SAMPLE PORTS
2'-0'
ELEV. 71.22
INVERT AT
ELEV. 69.1 3 PUMP
would fill with solids and plug unless cleaned several times
arms, and a board with a hook in one end was used to clean the
satisfactory.
many flies were noted around the pilot filter especially when
the flow rate was relatively low. The rock media and under-
back up and flow out the air vents on the east side of the
filter. A high pressure water jet was used to flush away the
sump refilled.
Grab samples are better than no samples, but the sample col
lection should at least be staggered, if possible, to simulate
pilot filter effluent line into the 2-ft diameter sump. The
Oxigest settling tank weir. This was the only one of the
sample.
4 AM, and 6 AM. The Oxigest and pilot filter effluent samples
sampling period.
below.
Compositing Samples
samples were obtained. Since the flow to the pilot units was
discussion.
76
pages.
COD Analyses
BOD Analyses
Suspended Solids
Dissolved Oxygen
pH
settling tank.
80
Primary Effluent
and the variations in the raw wastewater flow rate for the
corresponding days are shown in Figure 9. The routine
2aO(-
200'
I 50 -
lOO .
THURSDAY
C 10-50-69)
50 '
300I—
280 —
200 —
o
ISO —
o
m
ow<
TU-ESDAY
( 2-18-69)
lOOL s
tei
$
OUL
501
Z
o
w
aw
2SO
r 160
140
200i—
t20
150 — 100
#0
100 —
SUNDAY
60
(2-9-69 )
40
50L
~1 1 1 ! 1 1 i 1 i r
67\M I2AM 4PM 8PM r2PM 4AM SAM
iOAM 2PM 6PM lOPM 2AM 6AM
6.0 f—
I 10
5,0 100
»0
4.0 80
THURSDAY
10-30-69 70
3.0
I&
2.0
6.0
o
z
130
5.0
120
% 110
z 4.0 100
UJ
r> 90
TUESDAY
2-18-6» 80
5.0
> 70
<œ <
S
Z 60
a:
I 2.0
0.
6.0
r
5.0
120
..= j- 110
100
90
SUNDAY
3.0 r- 80
2 - 9-69
70
2.0 I 1 i I I I I I I I I II
a A.M. I2N 4P.M. 8P.M. i2M 4A.M. 8A.M.
10A.M. 2P.M. 6PM. iZP.M. 2A.M 4A.M.
200-
TMUfWDAY
I50-
100-
&0-
PILOT PLANT
AMES PLANT
200-
o<
o TUESOAY
ISO- 2- is-ca
Û
o
> lOO-
Ui
o< 50- PILOT PLANT
wK
AWES PLANT
uUioc ZOO-I
UI
a.
SUNDAY
!50-i
50-I
AMES PLANTS
I
aÀJM. I2N i 4 IRM. I 8P.M
I I I2M I I 4 IA.M. # A.M.
lOAJH £P.M. CP.M. 10 P.M. 2AJN. #A.M.
TIME
although the flow to the pilot units was held constant, the
variation in pilot plant loading was similar to the variation
Beth systems received only primary effluent with the one major
as the top BOD curve and the BOD of the plant final effluent
V/ 5
150
150
140 140
130 130
120 120
110 110
100 100
90
00
70
60
50
40
30
20
10
0
APRIL MAY JUNE JULY AUGUST SrPTMEWR OCTOeER NOVtMMR OECCWifl JANUARY
1970
Figure 11. Daily hydraulic load and BOD trends in the Ames
trickling filters during the pilot study
87
BOD load applied versus BOD load removed. These data were
collected during those days in 19 69 when samples were collected
units. The BOD applied was based upon the flow and strength
rather well around the "Ten States Standard" design curve (36)
-12
HOTI- ô = DATA COLLECTED DURING FLOODING, AND
OR 2 DAYS THEREAFTER
—6
REGRESSION LINES:
—4
_i 1 1 1 1 I r T" T" I
6 s K) 12 14 16 I#
BOD AP# LIED, L B / DAY / 1,000 CU FT
Figure 12. Performance of the Ames trickling filter during the pilot study
89
flooding.
time) each trickling filter for 24 hours once every life cycle,
ing and performance are present in Figure 11. When the plant
this time, and several hours and perhaps days, were required
1w
140
UO
lA)
; I 10
' 100
90
80
/O
60
40
30
20
10
0
'5MARCM
15 '21 S APRIL
IS 25 5 «AA'
15 25 5 A fJf
5 25 5 JULY
15 25 5AUGUST
15 25 5 15 25 5:)CIOBt»
I! 25 5NOVIMtff
15 25 5DlCIVefS
15 25 5JANUAfV
15 25
eo 80
70
70
60 •60
30
to
40 •40
50 •30
20 20
WATEFf POCLUTlQ'i .;Qf4IfiOL.^LAj IL
10 AME5» IQWA ^ lO
MEAN MR TEMPERATURE, "F -O
0 FINAL TF f LUENT TEMPt MATURE,*F
PRIMARY I SFLUENT TE»PERATURE, « -lo
-10
90 go
•80
eo
-70
70
60 •GO
•50
50-
• 40
40
23 23
25
APRIL MAY JUNE JULY AUGUST SEPTEMBER OCTOBER NOVEMBER OECEMBEH
the inlet to the Ames plant preaeration and grit removal tanks,
each day (once per 8-hour shift) by the plant operator. These
Figure 14.
treatment plant, and the warm summer and fall air temperatures
year there were cross-over points where the mean air and waste
and fall days have a high temperature that exceeds the waste
operation.
trickling filter. This curve is not the same as the top curve
of Figure 11, since different composite samples were used for
both Figures 11 and 15. They are the result of many students
time. The sharp up and down trends are due to the Tuesday-
was loaded at a much higher hydraulic rate than were the full-
scale filters.
25 ?5
5 5
0 0
170 170
160 160
150 150
140 140
130 130
120 120
110
no
100 100
90
90
80
80
70
70
60
60
50 yv' 50
40
40
30
30
20
10
KJ 20
10
0
0
5 \5 SEPTEMBER OCTOBER NOVEMBER DECEMBER lANUARY
APRIL MAY JUNE JULY AUGUST
1970
1969
97
settled for one hour in the laboratory from early June until
filter are shown in Figure 17. There were days when the air
Also, there were summer days when the morning air temperature
was lower than the wastewater temperature, but the air temper
filter.
I::
o
C>— O
—
O Piio* filVt ffflufn*
Pik)t Filter loorfîng
15
10
{. 5 5
H 0 0
170 170
160 160
150 150
140 140
130 130
I?0
;
110
• 100 100
' 90 90
00 00
/o 70
60
50
\ 60
50
*) 40
30 3C
?0 X)
10 10
0 Ll.i_i 0
15 25 5 15 ?5 15 25 5 15 25 5 15 25 5 15 75 5 15 25 5 15 25 15 25
K\\f(cn APRIL AUGLTST SfPÎMfBFK OCrOBft NOViMWf MCTMAF* JANUARY
1770
90
30-
w
z
3
<
Q;
111
a.
X
!IF 40|-
30- 30
10 IZM
_L
4
_L
6
_L
LO
I
I2N 2
1
lb 10
•ài
AM PM
TIME
Figure 17. Hourly trends in air and pilot trickling filter
effluent temperature
101
the Ames and pilot plant performance could not be defined, but
this study. In any case, the influent to both the pilot and
-60
— 70
— 60
— 50
REGRESSION LINE.
-50
SLOPE =0.651
Y- INTERCEPT = 1.46
R :09#4 -20
BOD APPLIED, L B / D A Y / 1 , 0 0 0 C U FT
•O
70
60
50
40
PILOT TRICKLING FILTER
PERFORMANCE AS FIRST-
STAGE PROCESS
(EXCLUDING SETTLING)
50
REGRESSION LINE'
20 SLOPE » 0.921
Y-INTERCEPT : 0.76»
R « O.MC
10 NO. OF SAMPLES 54
0 -1~ I T"
20 30 40 SO 60 70 100 110 120 ISO 140
between the two lines represents the BOD that was associated
60 — 80
60- — 60
50. -50
40 -40
M
O
U1
30 — 30
20 — 20
10 —10
0 ~r T~ T-
10 20 30 40 50 60 70 60 »0 too
B O D ACPLIEU, LB / DAY/ 1,000 CU FT
the pilot unit was loaded at much higher rates than the Ames
COMPARATIVE PERFORMANCE
AMES AND PILOT
TRICKLINS FILTERS
OCaCN CURVE
(REFERENCE NO.36)
Figure 21. Comparison of Ames and pilot trickling filter performance (From Figures
12 and 18)
108
REGRESSION LINE
SLOPE
Y-INTERCEPT
NO. OF SAMPLES
Figure 22. Pilot activated sludge plant (Oxigest) performance when used exclusively
for secondary treatment
110
evaluations.
pilot unit.
Trickling filter
The BOD removal was generally less than 50 percent in the load
-14
14-
-12
12-
10-
-•
8 -
RE6RESSI0N LINES'
SO 22
BOO APPLIED, LB/DAV/L,000 CUFT
Figure 23. Pilot trickling filter performance as the second-stage biological process
60-1
50-
-40
-20
-10
10-
SO SO 40 80 #0 70 •0 90
Activated sludge
aeration tank during this phase of the study was pilot trick
40-
-40
3O
O
o -50
50-
o
5Q
m CTi
ACTIVATEO SLUDGE PERFORMANCE
AS SECOND- STAGE UNIT
o -20
w> 20-
o REGRESSION LINE:
s
SLOPE = 0 869
o Y-INTERCCPT a -1.09
o
m R = 0.G95
Ma OF SAMPLES 42 -10
10-
"T" ~T~ ~r
10 20 T 40 50 60 70
Figure 25. Pilot activated sludge plant (Oxigest) performance as the second-stage
biological process
117
40 -40
3O
o
o
o
30- -50
>•
aUJ
M
o>
COMPARISON Of FIRST - STAGE AND SECOND - STAGK
ACTIVATED SLUDGE PERFORMANCE 00
-20
z 20-
w
IE
O
O
m
-10
10-
I 1~ —T
10 Î0 30 40 OO «0 70
this study.
-40
-»o
FOR
K)
-to
O
ALL DATA HAVING A FIRST STAGE EFFLUENT
BOO ^ 20M«/I
-to
"r~ "T" T-
K) JO 30 40 T ao TO
BOD APPLIED, LB /DAY/1,000 CU FT
Figure 27. Activated sludge and trickling filter plant second-stage performance
comparison
121
applied BOD load, and the process design decisions would have
to be based upon something other than system performance
tion.
122
Parallel Performance
the flow between the activated sludge process and the trickling
when each was serving alone. This was not observed, indicating
REGRESSION LINE
SLOPE
Y-INTERCEPT
NO OF SAMPLES
BOO APPLEO
90- -fo
o -40
o 40-
o
o
o
I 50-
COMPAHISOII or OVCRALL MMALLCL
PCRFOAMANCe WFTH PIRST STAtE
ACTIVATED SLUDSE AND FIRST STASE
TRICKLIN8 FILTER PERFORMANCE
ow
> M
M
so -lO
W 20-1
O
o
10-
-40
Figure 29. Comparison of overall parallel process performance with activated sludge
and trickling filter performance
125
noted that the flow and load were not always equally divided
and at no time was the flow to the trickling filter less than
split the flow equally between the aeration tank and the
trickling filter during the study, and the flow to the pilot
-40
-IB
-10
T"
T T T X 40 IE #0 70
-90
80-
»
11.
-40
I) 40-
c>
îio -30
50-
<•
j
o M
ly
>
o 1-20
:i 20-
lUte
o
o
I#
10-
-K)
Figure 31. Comparison of overall TF-A process performance with activated sludge and
trickling filter performance
128
tank of the TF-A process that was not realized in the A-TF
systems.
w r-M
20-
-to
3
O
—15
s.
•e-
i
X SCNIfS A-TF OVCNALL PCttFOttMANCC
o
u -40
M
10 neMCStioN LINE : W
O
SI JOFE » 0#4*
o Y -«Tt«CePT « III
o
R » 0*#4
NO. Of SAMPLE* « I#
-5
T T" T~
zo
~r
•O
10 19 2S
• 00 APPLIED, Lm/OAY/l/XX)Cy FT
-so
50-
3
O
o 40- -40
s
;
o
•WO
50- COMMRISOK Of OVEHAU. A-TF
PEWOHMAHCE WITH ni*ST STME
ACTIVATED SLUOflE AND FIRST
> STA«E TRICKLING FILTEB PERFORMANCE
o U)
%
hiK M
-20
20-
10-
-to
Figure 33. Comparison of overall A-TF process performance with activated sludge and
trickling filter performance
132
Supplemental Analyses
pilot plant study, including the time table for the various
BOD was extremely low during the first half of the TF-A data
the hydraulic and organic loads were increased during the TF-A
During the A-TF portion of the study, the hydraulic loads had
to be reduced in order to obtain satisfactory operation of the
process.
Comparison of BOD and COD load applied and load removed data
Parallel BOD and COD analyses were made on the PE, A, TF,
0 0
\iO 160
150 150
\*0 140
130. 130
120
1?0
no flO
100 100
90
90
00
90
70
70
60
60
50
SO
AO
40
30 30
20
20
10 10
0
0
5
JUNE JULY AUGUST SEPTEWWR OCTOBER NOVEMBER DECCM6ER JANUARY
1970
the linear regression analyses of the pilot plant BOD and COD
BOD data.
Curve fit analyses of BOD load applied and load removed data
Tables 5 and 6. A straight line was the best fit for the
performance data from both the Ames and pilot trickling filters
when they were used to treat the Ames primary effluent. The
Index
Curve^ of b Best
System type determination A^ B^ fit
Index
Curve^ of Best
System type determination A B fit
Y = X/(A + BX)
observed.
presented in this report as Figures 18, 19, 22, 23, 25, 28,
However, since the straight line did not pass through the
^ ^ ^ J" ^ ^^ ^ ^ ^ ^ 3^A
W ^ W W^ O w w «w&wf w ^ ^ WW** w
and 36, it is evident that settling not only increased the BOD
IOOH
•o-
°o
80-
%
o dSy o
o
: 70-
% ^J©
&
û.
< O o o O
o
OLL #0 O O
O PILOT TRICKLING
Z
Ui FILTER PERFORMANCE
O
Og
UJ
60-
a GO
o
UJ
40-
â
s
w
oc
o 50-
o
m
20-
10-
20 40 60 alo
BOD A P P L I E D, LB /DAY/l,000 CU FT
-70
c «0
-90
K)
— BO
-20
-10
10 40 60 «0
Figure 36. Percentage BOD removal trends with the pilot trickling filter as a first-
stage process (excluding settling) and as a second-stage process
(including settling)
143
process.
-to
-ao
-70
-so
-SO
AS FIRST-STAGE PROCESS — 40
-BO
-20
-K)
1 r T~ 1 1 1 1 r T" ~T~
10 to so 40 eo •0
BOO APPLIED, L B / D A r / 1 , 0 0 O C U FT
Figure 37. Percentage BOD removal trends with the Oxigest as a first-stage process
lOO
»o
• •
so
70
«0 • f
50 #
40
OXIOEST PERFORMANCE
AS SECOND-STAGE PROCESS
30
20
K)
0
"T 1 ' ir I T , JT'
BOO APPLIED, Ui / DAY / I.OOO CU. FT
creased. The same situation was also observed with the TF-A
since the trickling filter was not capable of the same BOD
When one considers Figures 39 and 40, the reason for the
80 — 00
O
ro-- •TO
0 0
6 0 - 0 \ -60
oW c\
1 0 -
-10
p . CL.
n——1 T r—
10 20 SO 40 so 80 TO «0 «0 100
Figure 39. First- and second-stage percent BOD removal relationships in the A-TF
process
-lOO
O % G •o
- o o o o o
o ~ ^ (?0 oG #o
O G
O r.
O ®
O O
G ® GO
\ 70
G
\ *0
-SO
-40
FIRST-ANO SECOND-STAGE O
BOO REMOVAL WITH
TF-A PROCESS
-50
O
•20
^O
-0
10 20 30 40 50 •© 70 «0 »0
TF-A process.
Nitrification
process influent and effluent are shown for the entire study
Cn
,LLl-LU_i_LL 1 i M I I i I ; I : • ! I i 1 1 I 1 I I I 1 I 1 1 I 1
5 15 2:i 5 15 25 5 15 25 5 15 25 5 15 25 5 15 25 5 15 25 55 15 25
155 15 25
25 5 15 25
WA*CH AfRIl kVkY AJNE JULY AUGUST SCfTfMKI OCTOW* NOVlMêEI DtCfMMR JANUARY
1770
flow rates were below 10 gpm and warm weather prevailed. After
studies.
153
Summary
design engineer.
•a eo
-40
3 40
-50
SO
PILOT UNIT PERFOmUNCe COMPARISON
o
kl M
O> Ln
4^
-20
to-
O
o
-10
*0
.0
T" ~T" '—s ' ï" M)
lO T so
• CD APPLIED, Lt/DAV/l,000 eu FT
filter alone.
process.
The experience with the TF-A process during this study was
tion with the TF-A system. In the TF-A system, the plant
ment plant has the required volume and hydraulic capacity for
APPLICATION OF RESULTS
Design Considerations
Parallel
and thereby determine the most desirable load range for each
criterion. One must assume thaz there will be days when the
During wet weather, with high hydraulic plant loads and high
either the TF-A or A-TF process, but not with the parallel
aeration tank.
TF-A
20 mg/1 range.
tanks.
tank. Knowing this load, the volumetric BOD load and removal
166
project.
167
A-TF
The A-TF process has the greatest potential for expansion
should be based upon the same biological concepts (22, 52) one
39).
when possible.
this report.
during periods of low stream flow with not more than 10 mg/1
the existing plant would enable the City of Ames to meet these
One must now decide how large the aeration tank should be
cates that the higher the loading to the aeration tank, the
day aeration tank detention time would be only 1.5 hours and
noted that a 6-hour aeration tank for the average day design
reflected by Figures 25, 38, and 40, one could expect approxi
approximately 12 mg/1.
$7,500,000.
plant was intended to point out some of the factors that must
common settling tank, and also as series A-TF and series TF-A
combination.
than two unit volumes, and one unit volume of trickling filter
loads with the TF-A process than with the A-TF process under
parallel system, and the trickling filter sludge did not have
loaded organically.
investigated.
should be determined.
5. Relative solids handling costs for rhe three processes
should be studied.
various combinations.
9. The relationship between second-stage performance
SELECTED REFERENCES
14. Cleasby, John L., Mische, Eric F., and Jensen, Harold M.
Disposal of pesticide dip at public stockyards:
Evaluation of two disposal methods for lindane and
toxaphene solutions. Iowa State University Engineering
Research Institute. Project No. 5755. 1968.
15. Cyclo-nitrifying filter, the. The Surveyor and Municipal
and County Engineer 10 3: 113-116. 1944.
16. Dorr Company. Process for clarifying and purifying
polluted and impure waste liquids. British Patent 691,
879. May 20, 1953. Abstracted in Great Britain Ministry
of Technology, Water Pollution Abstracts 158. 1955.
48. Lackey, James B., Calaway, Wilson T., and Morgan, George
B. Biological purification of citrus wastes. Sewage
and Industrial Wastes 28: 538-546. 1956.
ACKNOWLEDGEMENTS
ment he received from the City of Ames and its employees, his
people, the writer's pilot plant study would not have been
possible.
A thank you also goes to Dr. E. Robert Baumann and Dr.
APPENDIX A. ABBREVIATIONS
Abbreviation Meaning
A y-axis intercept
cm centimeter
cu cubic
°C degrees Centigrade
diam diameter
°F degrees Fahrenheit
ft feet
gal gallons
gpd gallons per day
hr hour
hp horsepower
in. inches
1 liter
193
Abbreviation Meaning
lb pounds
mm millimeters
No. number
sq square
SS suspended solids
VSS volatile suspended solids