CIVIL WORKS
1 CIVIL WORKS MATERIALS
1.1 HDPE SCD Pipe (c29) Lm 1,500 546 819,000
1.2 Cable Route Marking Lm 1,974 180 355,320
Warning Tape
1.3 Cable tie wrap (Large Size) Bundle 5 13,680 68,400
1.4 Manhole cover and its Number 13 216,000 2,808,000
frame
1.5 Marking Post Number 13 12,000 156,000
Sub-total for Civil Works 4,206,720
Materials
2 SERVICES FOR CIVIL WORKS
A Excavation (trenching)
works
1 Excavation for SCD pipe, Lm 2,512.93 1,800 4,523,274
depth 100cm soil
2 Excavation for SCD pipe, Lm 477.09 2,100 1,001,889
depth 100cm footway
3 Excavation for SCD pipe, Lm 1,154.11 3,400 3,923,974
depth 100cm concrete
4 Excavation for SCD pipe, Lm 422.33 3,400 1,435,922
depth 100cm asphalt
5 Laying SCD pipe 2way Lm 1,343.99 550 739,194.5
(c29x2)
6 Laying of Cable Route Lm 3,170.36 75 237,777
Marking Warning Tape
7 Tie together SCD Pipes EA 342 150 51,300
(using cable ties on each)
8 Reinstatement of asphalt Lm 477.09 45,000 21,469,050
road
10 Reinstatement of concrete Lm 1,154.11 19,500 22,505,145
road
11 Reinstatement of footway Lm 477.09 10,000 4,770,900
12 Indoor work EA 78 25,000 1,950,000
13 Services for Culvert Lm 123 35,000 4,305,000
Crossing attachment
14 Services for Road Crossing Lm 267 25,000 6,675,000
attachment
15 Service for Wall &Building Lm 78 17,000 1,326,000
attachment
16 Marking Post Installation EA 6 9,000 54,000
(To be installed each)
17 Manhole (MH) construction Each 6 450,000 2,700,000
(1,400x1,250mm)
18 Breaking a hole into existing Each 1 5,000 5,000
MH
19 FO cable pulling into SCD Lm 3,416 700 2,391,200
pipe (c29x1)
20 Supply Legrand truncking Lm 5 5,000 75,000
50x50
21 Supply GI Pipes (c50) Lm 6 15,000 90,000