Вы находитесь на странице: 1из 8

FM 5-277

CHAPTER 7
ASSEMBLY OF DOUBLE-STORY BRIDGES
THE DOUBLE-DOUBLE BRIDGE 94
THE TRIPLE-DOUBLE BRIDGE 97
LAUNCHING AND JACKING DOWN 98
REINFORCING BRIDGE AND CONVERTING BRIDGE 99

Methods of assembly for double-story bridges possible to assemble the second story during assembly. For long heavy bridges, it maybe
are similar to those used for single-story bridge assembly or after the bridge has been necessary to use trucks or a bulldozer. The
bridges. The second-story panels, however, entirely launched. It is preferable, however, composition of the launching nose for the
can be hand carried from trucks or other to assemble the entire bridge before pushing various combinations of spans and truss
platforms. Truck-mounted cranes, 5-ton it across the gap. The same methods of types is given in Tables 7-1 and 7-2. The
wreckers, or gin poles can also be used. It is launching are used as for single-story tables must be followed exactly.
THE DOUBLE-DOUBLE BRIDGE
FIRST BAY OF BRIDGE Panels must be loaded on trucks to allow e Tighten chord bolts and bracing frame
When the nose is completed, proceed with the standing room in the truck for the working bolts.
first bay of the bridge as follows: parties. The second story is assembled as
follows: f When footwalks are not used and trucks
1 Assemble three bays of double-single cannot be maneuvered alongside the
bridge as shown in Figure 7-1 (page 96) a Lift panel from truck at side of bridge. bridge, second-story panels can be
and as described in Chapter 6. Place flat on top chord of bridge. Slide placed from a temporary deck inside
panel in toward center of bridge. the bridge or by the use of gin poles.
2 Begin double-story assembly in the first
bay of bridge with a separate working b Lift panel upright. Pivot so it is parallel REMAINDER OF BRIDGE
party (Figure 7-1). Continue bottom-story to existing truss. Position and pin The remainder of the bridge is built the same
assembly at the same time, using the panel. Insert chord bolts, but do not as the first bay except that bracing frames
procedure for the single-story bridge. The tighten them. are positioned only on the rear verticals and
second story always lags by two bays. top chord of the second story (Figure 7-1).
Use an erection platform when placing c Repeat process with panels on outer When enough bays of bridge have been built
second-story panels. Footwalks can be truss. to counterbalance the nose, move the bridge
used as a working platform or panels can forward so the first bay is over the rocking
be hand carried from trucks maneuvered d Position bracing frames on front and rollers. Movement will not be necessary again
alongside the bridge (Figure 7-2, page 96). rear verticals and on top chord. during assembly unless the overhang at the

94
This change supersedes page 95. FM 5-277

tail causes excessive sag. When adding panels


from outside the bridge, place inner panels
first with panel pins inserted from the outside.
Then place outer truss panels with pins in-
serted from the outside. When adding panels
from inside the bridge, place the outer panels
first and insert all pins from the inside.

9 5
FM 5-277

96
FM 5-277
THE TRIPLE-DOUBLE BRIDGE
METHOD OF ASSEMBLY
The triple-truss, double-story assembly
(Figure 7-3) is essentially the same as double
truss, double-story assembly. With triple-truss
assembly, however, the outer truss in both
the lower and second story must lag by one
bay to allow insertion of the panel pins in the
middle truss when panels are added from
outside the bridge. When second-story panels
are added from inside the bridge, the inner
and middle trusses must lag by one bay to
allow insertion of the panel pins in the outer
truss.
LAUNCHING NOSE
The composition of the launching nose is the
same as that for the double-double bridge.
For the length and assembly of nose required
for various spans, see Table 7-2.
FIRST BAY OF BRIDGE
When assembly of the nose is completed,
proceed with the first bay of the bridge as
follows:
1 Assemble four bays of single-story bridge
as shown in Figure 7-4 (page 98) and
described in Chapter 6.
2 Add double-story assembly using the same
assembly method as for the double-double
bridge (Figure 7-1).
3 Position bracing frames on the front and
rear verticals and on the top chord of the
first bay of bridge before the chord bolts
are tightened.

97
FM 5-277 This change supersedes page 98.

REMAINDER OF BRIDGE
Assemble the remainder of the bridge the
same as the first bay, but position bracing
frames only on the rear verticals and top
chords of the second story. Connect outer
truss to middle truss with tie plates bolted to
the top raker holes in the forward panel
uprights of both stories. See Chapter 4 for
ramp construction and Chapter 9 for traffic
control.

LAUNCHING AND JACKING DOWN


LAUNCHING agonals. Apply it against the end posts, Rig a line to control lateral movement of
Launching of double-story bridges normally or a transom at the junction of the diag- the bridge.
begins after the assembly of the entire bridge. onals (Figure 7-5). When applying power
Use the same launching methods and pre- against a transom, make sure it is distri- If the bridge requires two trucks or bull-
cautions as for launching single-story buted across the length of the transom. dozers to move it, use one against the end
bridges. When launching with bulldozers or post of each girder.
trucks, take the following precautions: Roller heights must be fixed so that the
tail of the bridge is at least 6 inches (15.2 When using a bulldozer, bolt ribbands at
Do not apply power directly to the end of a centimeters) off the ground during the the tail of the bridge so they extend
panel except at the junction of the di- entire launching. beyond the end of the bridge. Place a

98
FM 5-277

transom on its side on the ribbands so the


transom rests against the end vertical at
the junction of the diagonals. Face tran-
som lugs toward the nose of the bridge.
Control lateral movement of the bridge by
fastening winch lines from two trucks to
male panel holes for positive control.
Launch the bridge with the bulldozer
blade pushing against the transom
(Figure 7-5).

JACKING DOWN
Use the same jacking methods and precau-
tions used for single-story bridges (Chapter
6).

REINFORCING BRIDGE AND CONVERTING BRIDGE


METHOD Erect outer truss first (Figure 7-6, page a Place first panel of second story at
The class of existing single-story bridges can 100). Before raising panels, insert center of bridge and insert chord bolts.
be increased by adding extra stories. For all wrenches in the top chord of the existing Do not tighten bolts.
assemblies over class 70, the decking system bridge to prevent the panel from skidding
must be reinforced by increasing the number out. The inner truss assembly should b Place a panel at each end of the center
of transoms per bay from two to four, and by follow closely behind the outer truss in panel of the second story. Insert chord
adding a 3-inch (7.6 centimeters) longitudinal order to speed construction. bolts and upper panel pins.
wear tread.
3 Insert chord bolts and panel pins. Where c Tighten all chord bolts to reduce sag.
CONVERTING DOUBLE-SINGLE necessary, use chord jacks (Figure 7-7, Drive lower panel pins with a sledge
TO DOUBLE-DOUBLE page 100) to overcome sag when inserting hammer.
To convert an existing double-single bridge panel pins. Tightening chord bolts also
to a double-double bridge, proceed as follows: helps reduce difficulty caused by sag. d After the first three panels are in place,
Chord jacks are not required when adding add other panels, one at a time, working
1 Remove bracing frames. a second story to double-truss spans 120 toward both ends of the bridge.
feet (36.6 meters) or less in length if the
2 Carry first panel to midpoint of bridge following method is used simultaneously
and place on top chord of existing bridge. on both sides of the bridge:

99
FM 5-277

e As each panel is placed, insert chord


bolts. Do not tighten until the upper
panel pin has been inserted.
f It maybe necessary to drive upper and
lower panel pins simultaneously,
starting at the ends of the bridge.
Tighten chord bolts to reduce sag.
g Place bracing frames vertically on the
same end of successive panels and
horizontally along the top chord of the
second story.
See Figure 7-8 for partially completed bridge.

100
FM 5-277

101

Вам также может понравиться