Академический Документы
Профессиональный Документы
Культура Документы
VENEZUELA
GENERAL INSTRUCTIONS
AND INFORMATION
COPY N°
CAUTIONARY NOTICE
INDEX
ITEM PAGE
Introduction
I.1 General Requirements I-3
I.2 Design Requirements I-3
I.3 Unit Performance I-4
I.4 Other Requirements I-4
I.5 Reliability I-5
I.6 Economic Basis for Selection of Equipment and Design Alternatives I-5
I.7 Environmental Requirements I-6
SECTIONS
INTRODUCTION
These General Instructions and Information apply to the preparation of the Process
Specifications Book and/ or Detailed Engineering of the HNAY Cat Naphtha
Hydrotreatment Project.
The plant shall be designed in accordance with the applicable agreements, these
General Instructions and Information, the Design Basic Memorandum, and/or the
Process Specification Books, all as modified from time to time by agreement with
PDVSA. Any ambiguities or contradictions between any of these documents or
sections thereof must be resolved with PDVSA. None of the requirements set forth
in the aforementioned documents shall relieve the contractor of his responsibility to
design for additional requirements consistent with the usual and normal practices of
the profession.
The plant and equipment design should incorporate all proven modern techniques.
The contractor will be expected to consider recent developments, but PDVSA must
be consulted before these are incorporated in the plant design.
The plant design shall allow as much routine maintenance as possible to be carried
out on the run or during downtime inherently necessary for process reasons. Areas
of high maintenance must be highlighted and advice given on possible solutions for
reducing maintenance. Facilities to minimize the time required for the start-up and
shutdown of the units shall be provided.
The contractor shall use uniform piping arrangements and instrumentation around
similar pieces of equipment to assist in case of operation. The contractor shall
make new equipment piping and instrumentation similar to existing equipment.
The maximum permissible noise level at worker exposure locations shall be 85 dBA.
The designation B.P. or I.P. refers to Exxon Basic Practices. The referenced
sections will be provided as necessary.
All equipment and units must be capable of reaching and maintaining design
performance and throughput from mechanical completion. In addition, careful
consideration must be given to operability and safety under normal operation,
° The contractor shall determine the final loads on utilities, waste disposal and
sewer and firewater systems.
Utility stations at grade shall have a one inch water, steam, air and nitrogen
hose connections with a valve immediately upstream. The hose connections
and valves shall be approximately 3 feet 6 inches above grade or floor level.
Structures and towers shall have stations at alternate levels with one inch
water and steam hose connections with valve.
° Branch connections from the headers to the utility stations shall be from the
top of the header.
° The number and location of utility stations and convenience outlets shall be
developed by the contractor and reviewed by PDVSA. The number and
location of utility stations, containing utility nitrogen outlets shall be developed
by the contractor and reviewed by PDVSA.
° Drinking fountains shall be provided for all new units. The total number of
fountains will be according to the final layout.
I.5 RELIABILITY
The following reliability philosophy shall be incorporated in the design of the new
facilities.
The contractor must base his design work on the Process Design Specification.
However, in the course of optimizing equipment within the limits permitted by the
individual Design Specifications, alternatives having different operating costs and
investment requirements shall to be considered. The contractor is also encouraged
to critically review the flow plans and equipment arrangements and to list separately
for PDVSA review all proposed alternatives that will make the project more
economical.
All alternatives which meet the above criteria are to be reviewed with and approved
by PDVSA before adoption. Information on incremental costs for this project is
given below. These costs include capital charges and delivery to the battery limits,
but not distribution within the unit. The specified cost for steam also includes credit
for production of condensate.
Notes:
The plant and equipment design shall comply with all environmental requirements
mandate by Venezuelan laws; or if more restrictive requirements are deemed
necessary, PDVSA will advise.
SECTION N° I
CHARACTERISTICS OF UTILITIES
I-1
GENERAL INSTRUCTIONS AND INFORMATION
Utilitis
CRP Amuay Rev. Dic. 2001
CHARACTERISTICS OF UTILITIES
The utility characteristics given below for process design are the conditions at the
utilities generation units battery limits. The contractor shall design the distribution system
within utilities units and battery limit of the new unit to supply the requirements. Provide
flow meter at battery limits for all continuous utilities consumption.
1.0 UTILITIES
EBAP
Supply Temperature, °F 85 125
Supply Pressure, psig 40 70
ANSI Flange Rating - 150
Cast Iron 125
Process Mechanical
I-2
GENERAL INSTRUCTIONS AND INFORMATION
Utilitis
CRP Amuay Rev. Dic. 2001
Design Design
EBAS-II
Supply Temperature, °F 85 125
Supply Pressure, psig 60 125
ANSI Flange Rating - 150
I-3
GENERAL INSTRUCTIONS AND INFORMATION
Utilitis
CRP Amuay Rev. Dic. 2001
Temperature, °F 85 130
Pressure, psig 30 100
ANSI Flange Rating - 150
I-4
GENERAL INSTRUCTIONS AND INFORMATION
Utilitis
CRP Amuay Rev. Dic. 2001
Process Mechanical
Design Design
250 psig BW
Temperature, °F 250 300
Pressure, psig 250 350
ANSI Flange Rating - 300
Temperature, °F 85 135
Pressure, psig 70 100
ANSI Flange Rating - 150
° Demineralized Water
to Hydrogen Units (DW)
Parameter
I-5
GENERAL INSTRUCTIONS AND INFORMATION
Utilitis
CRP Amuay Rev. Dic. 2001
H2S (ppm) 39
NH3 (ppm) 1200
Process Mechanical
Design Design
° Stripped Sour Water BK-21 (SW-1/2)
Temperature, °F 110 160
Pressure, psig 30 55
ANSI Flange Rating - 150
Parameter
H2S (ppm) <10
NH3 (ppm) <50
MEA (ppm) 55
HCl (ppm) 15
Process Mechanical
I-6
GENERAL INSTRUCTIONS AND INFORMATION
Utilitis
CRP Amuay Rev. Dic. 2001
Design Design
Nominal Condensing
Pressure, psig 600 145 60 4.5"Hg
Temperature Sat. Sat. Sat. Sat.
Min. Required Return
Pressure at Battery
Limits, psig 150 60 40 65
Mechanical Design
Temperature. °F 550 400 360 200
Mechanical Design
Pressure, psig 650 155 90 90
ANSI Flange Rating 400 150 150 150
Where:
- HC High pressure condensate
- MC Medium pressure condensate
- LC Low pressure condensate
- VC Vacuum condensate
I-7
GENERAL INSTRUCTIONS AND INFORMATION
Utilitis
CRP Amuay Rev. Dic. 2001
I-8
GENERAL INSTRUCTIONS AND INFORMATION
Utilitis
CRP Amuay Rev. Dic. 2001
Utilization
Drivers: Voltage Phase
I-9
GENERAL INSTRUCTIONS AND INFORMATION
Utilitis
CRP Amuay Rev. Dic. 2001
Process Mechanical
Design Design
1.5 Nitrogen (N2)
° Service Nitrogen
° Purge Nitrogen
Temperature, °F 80 150
Pressure, psig 500/180 650/250
ANSI Flange Rating - 300/150
Composition, mol %
Carbon Dioxide 4.2
Nitrogen -
Methane 82.9
Ethane 10.3
Propane 2.1
Butanes and Heavier 0.5
100.0
I-10
GENERAL INSTRUCTIONS AND INFORMATION
Utilitis
CRP Amuay Rev. Dic. 2001
Process Mechanical
Design Design
I-11
GENERAL INSTRUCTIONS AND INFORMATION
Utilitis
CRP Amuay Rev. Dic. 2001
Process Mechanical
Sour Clean Design
Typical Composition, Mole %
Temperature, °F 80 150
Pressure, psig 180 250
ANSI Flange Rating - 150
Composition, Mole %
I-12
GENERAL INSTRUCTIONS AND INFORMATION
Utilitis
CRP Amuay Rev. Dic. 2001
Process Mechanical
Design Design
° Liquid Fuel (FO)
Process
HY´S CHP
Typical Composition, Mole %
I-13
GENERAL INSTRUCTIONS AND INFORMATION
Utilitis
CRP Amuay Rev. Dic. 2001
Temperature, °F 90 120
Pressure, psig 100 150
Gravity Degree Baume 20
ANSI, Flange Rating - 150
API 21.47
Temperature, °F 110 150
Pressure, psig 100 150
ANSI, Flange Rating - 150
I-14
GENERAL INSTRUCTIONS AND INFORMATION
Utilitis
CRP Amuay Rev. Dic. 2001
° Temperatures
° Precipitation
Precipitation Frequency (1 mm or
more), days/year 3-6
Design Precipitation Intensity,
inches/hr 2.0
Maximum Precipitation,
inches/24 hr 5.0
Snow Days, days/year 0
Precipitation Data see Table Nº 1
° Wind
° Wind Rose
° Earthquake
I-15
GENERAL INSTRUCTIONS AND INFORMATION
Utilitis
CRP Amuay Rev. Dic. 2001
I-16
GENERAL INSTRUCTIONS AND INFORMATION
Utilitis
CRP Amuay Rev. Dic. 2001
TABLE N° 2
I-17
GENERAL INSTRUCTIONS AND INFORMATION
Exchangers
CRP Amuay Rev. Dic. 2001
SECTION N° II
HEAT EXCHANGERS
II-
GENERAL INSTRUCTIONS AND INFORMATION
Exchangers
CRP Amuay Rev. Dic. 2001
HEAT EXCHANGERS
1. DESIGN CODES
2. DESIGN CONDITIONS
Exchangers operating between 32°F and 750°F shall be designed for the
maximum anticipated operating temperature plus 50°F but not less than
150°F.
Exchangers operating at 32°F and below are to be designed for the minimum
anticipated operating temperature.
When, due to the possible loss of cooling medium, the tubes, tube sheets
II-
GENERAL INSTRUCTIONS AND INFORMATION
Exchangers
CRP Amuay Rev. Dic. 2001
and floating heads may be subject to the full inlet temperature, these
components shall be designed for the maximum anticipated temperature of
the hotter medium, plus 50 °F.
3. CORROSION ALLOWANCE
All carbon steel pressure parts, except tubes, are to have a corrosion
allowance of 0.125 inch unless the conditions of service require a higher
value. A 0.0625 inch minimum corrosion allowance is acceptable for
services like steam or dry air.
3.2 Alloy
4. GENERAL CRITERIA
For shell and tube exchangers, pressure drop values must be calculated
based on a nominal ID equal to the nominal OD minus twice the wall
thickness shown on the exchanger specification sheet. They include
allowances for tube wall thickness variation and fouling as follows:
The pressure drop is the sum of the frictional clean pressure drop
multiplied by the appropriate pressure drop allowance factor given
below plus the nozzle pressure drop and the entrance, expansion and
turnaround pressure drop.
Pressure Drop Allowance Factors
II-
GENERAL INSTRUCTIONS AND INFORMATION
Exchangers
CRP Amuay Rev. Dic. 2001
Tube Tube
Diam. Thickness Carbon steel, Copper,
Inches Inches Alloy Tubes Copper Alloy Tubes
The pressure drop for all liquid and for vaporizing services shall
include a 15 percent allowance for fouling. The pressure drop for all
vapor and for condensing services shall not include an allowance for
fouling (fouling allowance is not required).
For cooling services, air fins shall not be used for the following services:
° For viscous materials where tube side heat transfer coefficients are
low.
II-
GENERAL INSTRUCTIONS AND INFORMATION
Exchangers
CRP Amuay Rev. Dic. 2001
For shell and tube heat exchangers the normal cold end temperature
approach should not be less than 18°F. For reboilers, a temperature
difference of at least 25°F shall be used between condensing steam
temperature and the process fluid.
4.5 Overdesign
° Where HIC Resistant Steel has. been specified, the plate steel used
shall be fully killed made to fine-grain practice and normalized.
Type AET for shell and tube exchanger is preferred. If type AES is specified
in an individual design specification, the contractor shall submit the design for
owner approval (GIG and Maintenance).
5. DESIGN CRITERIA
II-
GENERAL INSTRUCTIONS AND INFORMATION
Exchangers
CRP Amuay Rev. Dic. 2001
All shell and tube heat exchangers shall be designed to the following guides unless
otherwise specified:
(1) Square pitch shall be used if shell side mechanical cleaning is required.
(2) 15/16" triangular pitch layout may be considered only for nonferrous alloys.
5.2 Minimum tube wall thickness for process heat exchangers shall be 0.109
inch for carbon steel, 0.083 inch for nonferrous alloys, 0.049 for titanium shell
and tube condensers and 0.028 for titanium fixed tube sheet coolers. Lube
oil coolers may use 0.049 inch tube wall thickness for nonferrous alloys.
II-
GENERAL INSTRUCTIONS AND INFORMATION
Exchangers
CRP Amuay Rev. Dic. 2001
5.5 Unless otherwise noted, fixed tube sheet exchangers in which the difference
between the average shell metal temperature and the average metal
temperature of any one tube pass is less than 50°F shall be designed for
50°F differential. The owner shall be notified if this requirement results in an
unconventional design. Startup, shutdown, emergency conditions or other
unusual operations (e.g. steam out) must be considered when determining
the design temperature difference.
Tube Layout
5.7 Unless otherwise specified, baffle cut for segmental baffles shall be 25
percent of the shell inside diameter. Unless otherwise specified, baffle cuts
for double segmental (modified disc and donut) baffles shall be such that the
sum of the window area for the single central baffle and the area of the hole
in the double baffle are equal and shall be 40 percent of the exchanger cross
sectional area.
5.8 Modified disc and donut (double segmental) baffles or divided flow (TEMA
Type J) shall be considered where pressure drop is critical. First choice shall
be modified disc and donut baffles.
II-
GENERAL INSTRUCTIONS AND INFORMATION
Exchangers
CRP Amuay Rev. Dic. 2001
5.9 For salt water coolers, water should be placed on the tube side. Fouling
resistance to be used for salt water cooling exchanger design are shown in
Figure 1 of this section. Tube side water velocity shall be between 6 and 12
ft/sec., and preferably 7 to 8 ft/sec (for 90/10 Cu Ni or 70/30 Cu Ni).
5.10 The maximum outlet bulk salt water temperature is 120°F, provided the
highest water film temperature (not average film temperature) does not
exceed 140°F.
5.11 Unless otherwise noted, materials for shell and tube exchangers with salt
cooling water on the tube side shall be as follows:
Notes:
(1) Full face cathodic protection is required with aluminum brass tubes
(see drawings on page 2-16,17).
II-
GENERAL INSTRUCTIONS AND INFORMATION
Exchangers
CRP Amuay Rev. Dic. 2001
5.12 Shell and tube exchanger components subjected to both shell and tube side
pressures shall be designed for the most severe condition of the specified
pressure with atmospheric pressure on the other side. Proposals for the
differential design shall be submitted to the owner for approval.
5.13 If drumless flooded condensers are used, they shall be designed according
to the following guides:
° The condenser shall be positioned with its liquid outlet end on the
pump side of the structure.
II-
GENERAL INSTRUCTIONS AND INFORMATION
Exchangers
CRP Amuay Rev. Dic. 2001
° Pumps shall be of the heavy duty refinery type or API 610 last edition.
° If 600 psi steam is used for reboiling, the tubes must be strength
welded to the tube-sheet.
A=
0.25Ac
II-
GENERAL INSTRUCTIONS AND INFORMATION
Exchangers
CRP Amuay Rev. Dic. 2001
B= 0.10Ac
N
Q
Where: Ac=
Vc
0.5
ρl - ρv
Vc=0.15 ρv
5.15 For all heat exchangers specified in the individual design specifications, the
contractor and/or vendor shall confirm:
° That the pressure drops (dirty) of the units selected are not greater
than shown in the design specification.
II-
GENERAL INSTRUCTIONS AND INFORMATION
Exchangers
CRP Amuay Rev. Dic. 2001
All air fin heat exchangers shall be designed according to the following:
6.1 The maximum design air temperature (dry bulb) for air cooled exchangers, if
not specified, is 95°F for coolers and 105 °F for condensers (These values
include a 5°F allowance for hot air recirculation).
6.2 The minimum design dry bulb is 70°F (for fan motor rating per BP6-4-1).
6.3 Manufacturer shall design air cooled exchanger units for the most
economical combination of surface and power, using the economic criteria
given in the Economic Basis for Selection of Equipment section of this
specification.
6.4 The Contractor shall supply air fin vendors with the following information:
6.5 Single tube pass condensers shall be sloped down a nominal 1/8 inch per
foot toward the outlet. For total condensers the slope shall be 1/4 inch per
foot. Multipass condensers shall be horizontal.
6.8 Minimum tube wall thickness shall be 0.109 inch for carbon steel, 0.083 inch
for nonferrous alloys and 0.049 inch for titanium.
6.9 Air coolers shall be provided with galvanized frames and galvanized wire
mesh fan protectors.
II-
GENERAL INSTRUCTIONS AND INFORMATION
Exchangers
CRP Amuay Rev. Dic. 2001
6.10 Air coolers shall be provided with HTD pulleys and belts for all motor drives:
° Louvers are preferred to variable pitch fans for air fin control, but their
use shall be minimized and require owner approval.
7. STEAM GENERATORS
° Non return valve (Stop Check) in steam production line. This valve shall be
calculated. Whenever the size of this valve is not standard line size (see
section 10 page 10-7 item 2.10) flange connections to the standard size line
are required to permit easy valve removal and maintenance without cutting of
the line.
FIGURE 1
II-
GENERAL INSTRUCTIONS AND INFORMATION
Exchangers
CRP Amuay Rev. Dic. 2001
0.006
0.005
(1)
0.004
3FT/SEC (1)
0.003
5FT/SEC (1)
0.002
10FT/SEC
0.001
0
100 200 300 400 500 600
II-
GENERAL INSTRUCTIONS AND INFORMATION
Exchangers
CRP Amuay Rev. Dic. 2001
FIGURE 2
LIFT LUG
REMOVABLE
TUBE
BUNDLE
ONLY
FIGURE 3
SUSPENDED BELT DRIVE, MOTOR SHAFT UP
II-
GENERAL INSTRUCTIONS AND INFORMATION
Exchangers
CRP Amuay Rev. Dic. 2001
NOTES: Nº SERVICE
1. BAFFLES EXTEND ACROSS WIDTH 1N CHANNEL INLET
OF SHELL. 2N CHANNEL OUTLET
3N H.C. LIQUID INLET
2. LEVEL TAPS MAY BE EITHER ON 4N H.C. VAPOR OUTLET
SHELL OR HEAD. 5N H.C. LIQUID OUTLET
3. DIMENSION "L" REFERS TO TUBE 1CN LIC (2) NOTE 2
LENGTH. 2CN LG (2) NOTE 2
4. FOR AREA "A" AND "B" AND CRP. AMUAY REFINERY
NOZZLE DIAMETER "D" REFER TO GENERAL SKETCH FOR KETTLE
THE TEXT. REBOILERS DETAILS.
II-
GENERAL INSTRUCTIONS AND INFORMATION
Exchangers
CRP Amuay Rev. Dic. 2001
NOTES:
1) WHERE FULL FACE CATHODIC PROTECTION IS SPECIFIED, THE ANODE SHALL BE PER
FIG. 1 INCLUDING DETAIL A. THE ANODE SHALL BE ELECTRICALLY CONNECTED BY
ATTACHING ONE END OF A PIECE OF No. 12 AWG COPPER WIRE TO THE ¼ IN. BRASS
MACHINE BOLT ON THE ANDE AND THE OTHER END TO THE TUBE SHEET WITH THE ¼ IN.
BRASS CAP SCREW.
3) WIDTH OF WEB SHALL BE ONE INCH THICKER THAN TIP OF PARTITION PLATE.
II-
GENERAL INSTRUCTIONS AND INFORMATION
Exchangers
CRP Amuay Rev. Dic. 2001
NOTE:
+1/32”
1) TUBE PROJECTION AT BOTH ENDS (A) SHALL BE 3/16" - 0”
2) TUBES SHALL BE FLARED BY ROLLER EXPANSION AT 15 DEG. WITH TUBE CEN-TERLINE
@ BOTH ENDS.
II-
GENERAL INSTRUCTIONS AND INFORMATION
Pumps
CRP Amuay Rev. Dic. 2001
SECTION N° III
PUMPS
III-
GENERAL INSTRUCTIONS AND INFORMATION
Pumps
CRP Amuay Rev. Dic. 2001
PUMPS
1. CENTRIFUGAL PUMPS
Centrifugal pumps shall normally be rated for 110% of the maximum process
flow. Reflux pumps shall be rated at 115% of maximum process flow. For
pumps in controlled systems, the rated head shall be that calculated at 100%
of normal process flow. For pumps in uncontrolled systems, transfer pumps
and pump-out pumps, the rated head shall be calculated on the basis of the
rated flow and the driver specified for 115% of rated pump power.
(Max. Suction Pressure) + (A) x (B) x (∆P at rated capacity & max SG*
conditions)
A= 1.0 for motor driven and 1.21 for turbine driven pumps.
B= 1.2.
*= Maximum SG may not be the same as design case.
1.3 Net Positive Suction Head (NPSH)
III-
GENERAL INSTRUCTIONS AND INFORMATION
Pumps
CRP Amuay Rev. Dic. 2001
The contractor shall confirm that the actual values of items a, b and c do not
negatively affect NPSH values specified. Inform owner if adjustments of
available NPSH values are necessary.
The contractor shall insure that the pump requirement is compatible with
actual available NPSH.
1.4 Pump casing as well as downstream equipment might have been designed
based on a pump shutoff head of 120%. Owner shall be informed if the
shutoff head of any pump head exceeds 120% of specified differential head.
1.6 The minimum continuos stable flow shall be less than the minimum operation
flow. If a recirculation is required to get this condition, it should be less than
25% of the normal operation flow. The contractor shall advise the purchaser
of any pumps which require a recirculation system for continuous operation
at flows down to the 30 percent level. The recirculation system shall be
approved by the owner. The vendor shall specify the minimum stable flow
and the minimum thermal flow for each pump. The suction specify speed
(NSS) shall be less than 11000. In case of NSS greater than this value, the
pump shall be submitted to owner for review and approval.
III-
GENERAL INSTRUCTIONS AND INFORMATION
Pumps
CRP Amuay Rev. Dic. 2001
For pump selection shall be checked suction specify speed (NSS) at the best
efficiency point (BEP) as it is shown on figure 3-1.
1.7 Casings which are not self-venting type, pumps handling C4 and lighter,
pumps handling liquids containing dissolved toxic gases, or pumps operating
under vacuum shall be vented back to the vessel from which the pump
draws suction. Vent line shall have a valve at the pump and slope up
continuously to suction vessel.
Pump drains are to be provided for all pumps. Drain disposal should be
as follows:
° Heavier than lights ends at temperature above flash point and no pour
point problem - pipe to the funnel connection to the sewer.
° Heavier than light ends at a temperature above flash point with a pour
point problem - pipe to the funnel connection and provide flushing oil
to a 2 inch connection upstream of the pump strainer.
° Heavier than light ends at a temperature below the flash point and no
pour problem - provide a valved drain to the baseplate (which drains
to the funnel connection).
° Heavier than light ends at a temperature below the flash point with a
pour point problem - provide a valved drain to baseplate and flushing
oil to a 2 inch connection upstream of the pump strainer.
The location of pump vents and drains are to be per BP3-3-2; i.e., casing
vents and drains are not required if adequate venting and drainage can be
obtained via piping vents and drains, otherwise vendors must ensure that the
valves at the vents or drains are as close to the casing as possible.
1.9 The vendor shall provide pump curves for maximum and minimum impeller
III-
GENERAL INSTRUCTIONS AND INFORMATION
Pumps
CRP Amuay Rev. Dic. 2001
1.11 All onsite pumps in critical service shall be spared. Critical service is defined
as any service required to prevent a unit shutdown or required for an orderly
and safe unit shutdown during an emergency. A common spare may be
used for two non critical services.
1.13 For pumps where oil cooling is mandatory, radiator air coolers are preferred
instead water coolers. Oil cooling with salt water must be approved by the
owner. Oil cooling with raw or recovered water shall be avoided.
1.14 General purpose type steam turbines shall be provided with Woodward TG-
10 or equal hydraulic type governors except where NEMA C or D class
governors are required.
1.15 Oil mist lubrication shall be provided for all onsite and utility block general
purpose type equipment such as centrifugal pumps, fans, gears, and
steam turbines which have nonpressure oil feed type bearing lubrication.
III-
GENERAL INSTRUCTIONS AND INFORMATION
Pumps
CRP Amuay Rev. Dic. 2001
Oil mist lubrication of offsite centrifugal pumps and their drivers shall be
considered where a number of pumps are centrally located, the required
utilities are available, and the system installation can be justified.
Oil mist systems shall be designed for wet sump lubrication "purge mist".
Purge mist installation method shall be per the original Figure 2 of BP3-3-12,
last edition. Future conversion to dry sump lubrication "pure mist" shall be by
the Owner. Grease lubricated antifriction bearing type electric motors shall
be designed to be compatible for future conversion to dry sump lubrication
"pure mist" by the Owner.
1.16 Pumps requiring water quench shall be referred to the owner for approval
and selection of the water system available. The use of raw water (RW)
should be minimized by providing rotameter indication and globe valve
control of the raw water quench. If recovered water (AR) is used provide a
double filter.
1.17 Reflux pumps from the condenser shall be equipped with recirculation line
returning upstream of the condenser. The recirculation line shall be provided
with a block valve and restriction orifice or a control valve sized to maintain at
least 20 percent of the pump capacity at the best efficiency point. When the
recirculation is over 20 percent a local control loop is preferred. These
pumps shall be of the heavy duty refinery type. Choke-tube on recirculation
line required be approved by owner.
1.18 All sump pumps shall be fitted with an automatic on-off switch on level
control.
1.19 Oil flingers shall be provided. Oil cups shall be "Trico" constant level oiler
type.
1.20 "Labour" horizontal self priming pump is preferred for sump service of suction
lift up to 10 ft.
1.21 All onsite pumps shall be equipped with a wet sump oil mist system. System
shall be "Alemite" or equal.
1.22 (API 610 exception) Pumps shall be capable of at least a 10% head increase
at rated conditions by replacement of the impeller(s) with ones of larger
diameter.
III-
GENERAL INSTRUCTIONS AND INFORMATION
Pumps
CRP Amuay Rev. Dic. 2001
2.1 Contractor shall use the update Table 1, and Attachment 3.1, to develop
mechanical seal specification and selection. Seal details shall be approval
by owner. In general, the following sealing control levels (arrangements)
shall be used:
Control Level 3: Low emission single mechanical seal with abeyant seal
backup and leakage detection alarm. Low emission
indicates the vendor can provide test and/or experience
data proving the seal will emit less than 1000 ppm on a
continuous basis in the intended service as measured
by an organic vapor analyzer per established
procedures.
Control Level 1: Single mechanical seal with fixed, API 610 clearance
bronze throtte bushing.
The sealing control level shall be increased (but never decreased) as needed
to provide appropriate control for the considerations in attachment 3.1.
III-
GENERAL INSTRUCTIONS AND INFORMATION
Pumps
CRP Amuay Rev. Dic. 2001
2.2 Sealing systems shall be design using section 4 of the fourth draft of API
Standard 682, "Shaft Sealing Systems for Centrifugal and Rotary Pumps".
2.3 Approved seal vendors are: "John Crane", "Borg Warner" and "Sealol".
2.4 All seal gland plates shall be of the distributed inlet (multiport or peripheral
inlet) design. This applies to both rotating and stationary flexible element
seal designs. particular attention shall be paid to installations where the
radial clearance between the seal OD and seal chamber bore is less than 6
mm in order to avoid high inlet velocities which can cause erosion on
stationary seal components. The contractor shall advise the owner this
requirement causes a reductions in flush flow rate or reduced cooling
effectiveness due to space limitations in the gland or seal chamber.
2.5 Cartridge design mechanical seals shall be provided for "between bearing
pumps", to facilitate seal installation and removal.
Pumping Temperature: Low Temperature (≤ 350 °F) High Temperature (> 350 °F)
b.- Seal Faces per Seal Program Silicon Carbide and Antimony impreg-
nated Carbon
e.- Approved Seal Vendor "John Craine" "Sealol" and "Born Warner"
2.7 Whenever a metallic gasket or graphite is used to seal the sleeve to the
shaft, a second sleeve to shaft sealing element (an o-ring) shall be installed
in order to prevent the buildup or foreign material under the sleeve. For
service below 350 °F this o-ring shall be Viton, over 350 °F the o-ring shall be
Kalrez. The seal vendor shall advise alternate material recommendations in
III-
GENERAL INSTRUCTIONS AND INFORMATION
Pumps
CRP Amuay Rev. Dic. 2001
the event these materials are incompatible with the sealed fluid.
2.8 The contractor shall ensure that the seal chamber conditions of pressure and
temperature meet the seal vendor's requirements for satisfactory margin to
vaporization to provide reliable, low emission performance and long life.
Where special provisions must be added to the real seal chamber or pump
(such as close clearance floating throat bushings) to achieve satisfactory
seal chamber conditions. These provisions shall be submitted to the owner
for review and approval.
2.9 The sleeve drive shall be capable of transmitting full seal torque and
resisting seal axial forces under all operating and standby conditions.
Designs which utilize six or more set screws require submission of the
highest axial and radial load developed by the seal versus the capability of
the drive system for approval of the owner.
2.10 Final seal selection and seal system design shall be approved by owner.
III-
GENERAL INSTRUCTIONS AND INFORMATION
Pumps
CRP Amuay Rev. Dic. 2001
TABLE 1
LEVEL 1.
Non-Sour, Clean or Dirty Water, Default: Single mechanical seal
<150 ºF. with API throttle bushing.
High Pressure Option 1: Single seal with floating
carbon bushing.
Option 2: Single seal with segmented,
floating carbon bushing.
LEVEL 2.
Minimum Requirement for All Default: Single mechanical seal services
except services except Water <150 ºF with floating carbon
bushing.
- Use if little chance of
forming an explosive vapor
cloud.
- use if emission limits are
>10000 ppm.
LEVEL 3.
Absolute Minimum Requirement Default: Single seal with for services which
can
Form and Cloud. segmented floating Explosive
Vapor carbon bushing & leakage
detection alarm (usually a
pressure switch).
Service Recommended Pump Sealing.
III-
GENERAL INSTRUCTIONS AND INFORMATION
Pumps
CRP Amuay Rev. Dic. 2001
LEVEL 4
Preferred Minimum Requirement Default: Single seal with for contacting
abeyant.
Services which can form Explo- back-up seal & leakage detection
alarm
sive Vapor Cloud. (usually a pressure switch).
Bearing monitoring should also be
considered and is recommended
when there is high potential for
leakage to form a vapor cloud.
LEVEL 5
Minimum Requirement for Ser- Default: Dual seal, unpressurized with
appropri-
vices Where no Material Should ate gauges & leakage detection
alarms.
be Released to the atmosphere Primary Seal. Bearing
monitoring
on Failure (HF, H2S, Methanol). should be strongly considered with
local readout for on-site units and
III-
GENERAL INSTRUCTIONS AND INFORMATION
Pumps
CRP Amuay Rev. Dic. 2001
NOTES:
1.- Unpressurized dual seals and some abeyant seals commonly require the space
between the primary and backup seals to be vented to a safe location or a collection
system. If such a vent is required, the user must ensure a suitable disposal site is
available. If not, then a pressurized dual seal may be more economical/required.
Note that for vents on emission regulated services, activated carbon canisters and
filters are available to dispose of vapor before it enters the atmosphere. The
problem of finding a suitable vent location for reservoirs and abeyant seals is
specially acute in offsite areas.
2.- Continuous bearing monitoring should be considered an integral part of reducing the
potential hazard of seal leakage.
3.- Alternate means to a pressure switch for leakage detection such as a thermocouple
for auto-refrigerating service or a hydrocarbon detector can be considered.
4.- Any sealless pumps must be referred to PDVSA for approval. When sealless
pumps are used, the contractor must provide the appropriate instrumentation.
III-
GENERAL INSTRUCTIONS AND INFORMATION
Pumps
CRP Amuay Rev. Dic. 2001
Steam turbine shall be fitted with oil relay "Woodward" governor. Mechanical
governor is not acceptable.
4.1 Dry seals are not allowed in any service with solids. Use of dry seal required
PDVSA approval.
4.3 Pump seal and flushing connections and drains shall be piping instead of
tubing and not be seal welded at the pump connection.
4.4 Mechanical seals shall be selected to agree with "The Mechanical Seals
Standard Project of Amuay Refinery".
5.1 All pumps in wet H2S service shall meet the requirements specified in BP10-
1-1 or BP10-1-2.
5.2 Carbon steel pressure containing parts in wet H2S service shall meet the wet
H2S requirements of BP5-1-1 (paragraph 8.5 and 9.23). Avoid use of carbon
steel plate. Use forgings and castings instead.
III-
GENERAL INSTRUCTIONS AND INFORMATION
Pumps
CRP Amuay Rev. Dic. 2001
FIGURE N° 3.1
ATTACHMENT 3.1
SEAL CONFIGURATION TO MEET SAFETY
III-
GENERAL INSTRUCTIONS AND INFORMATION
Pumps
CRP Amuay Rev. Dic. 2001
Auto Ignition Potential - Bottoms pump around (PA). High temperature metal bellows
where normal pumping - ATM and Vacuum bottoms. with restriction device and steam
temperature exceeds - (APS and VPS). quench for secondary
600 °F. containment.
Vapour Cloud Potential. - C5 and lighter. Single mechanical seal with tight
- APS and Fractionator Overhead shut off short life auxiliary con-
Product, Reflux and tainment seal plus seal failure
Unstabilized alarm.
Naphtha.
- APS light ends processing. OR
° Deethanizer Feed.
° Deethanizer O/H Product and Liquid Tandem Seal with seal pot
Reflux. plus seal failure alarm.
° Debutanizer O/H Product and * Guidelines:
Reflux. If Pv > 200 psia @ 100 °F and
° Depropanizer O/H Product the fluid is a Narrow Boiling Point
and range or a Medium/Wide Boiling
Reflux. Point range in which more than
° Depropanizer Btms. 40% of the fluid vaporizes at PT
- Hot Naphtha. and atmospheric conditions use
Liquid Tandem Seal.
Potential for fatality rom - Phenol an Phenol extracts. Liquid Tandem seal with clean
short team exposure. - Sulphuric Acid. barrier fluid from sealpot plus seal
- H2S. failure alarm (Standard selection
° Rich MEA. for Phenol).
° GO hydrofined naphtha.
° Fractionator O/H product OR
reflux.
° Stream from fractionator up- Liquid Double seal with clean
stream of sweetening process. barrier fluid from process stream
- HF acid. or seal pot plus seal failure alarm
(Standard selection for HF-acid)
ATTACHMENT 3.1
(Continue)
III-
GENERAL INSTRUCTIONS AND INFORMATION
Pumps
CRP Amuay Rev. Dic. 2001
Potential for burns - Crude and Refined Benzene Liquid tandems seal with clean
from skin contact or Extract. barrier fluid from seal pot plus seal
asphyxiation from - Powerformer Product. failure alarm.
absorbed H2S. - Streams from APS units
upstreams of sweetening
process.
° APS fractionator Product and
Reflux.
° Deethanizer Feed.
° Deethanizer O/H Product and
Reflux.
° Debutanizer O/H Product and
Reflux.
° Depropanizer O/H Product
and
Reflux.
° Depropanizer Btms.
° Spent Caustic.
Congested layout (fire Not covered by any of the previo- Single mechanical seal with tight
risk). usly mentioned services but with shut off short life auxiliary contain-
spacing less than Section 10 ment seal plus seal failure alarm.
requi-rements of the design
specification or difficult fire
fighting access.
Proximity to high risk Proximity to Chlorine area. Single mechanical seal with tight
equipment. shut off short life auxiliary contain-
ment plus failure alarm.
Remote location (with LPG Shipping or loading pumps See "Vapour Cloud Potential".
potential for vapour in offsite area. Also remote monitoring and/or gas
cloud). detection to be considered.
ATTACHMENT 3.1
III-
GENERAL INSTRUCTIONS AND INFORMATION
Pumps
CRP Amuay Rev. Dic. 2001
Normal risk (other Services not listed above. - Single mechanical seal with
Hydrocarbon services). lipseal or floating carbon bushing.
NOTES:
III-
GENERAL INSTRUCTIONS AND INFORMATION
Compressors and Turbines
CRP Amuay Rev. Dic. 2001
SECTION N° IV
IV-1
GENERAL INSTRUCTIONS AND INFORMATION
Compressors and Turbines
CRP Amuay Rev. Dic. 2001
- API 617
- API 612/614
2. DESIGN REQUIREMENTS
2.3 Turbines operating in the nominal 600 psig steam system (STM-600) shall
develop rated horsepower with 580 psig, 700°F steam at the throttle valve
inlet.
2.4 Turbines operating on the nominal 145 psig steam system (STM-145) shall
develop rated horsepower with 130 psig, 455°F steam at the throttle valve
inlet.
2.5 Backpressure turbines shall develop rated horsepower with the exhaust
steam header at the process design pressure plus 10 psi.
IV-1
GENERAL INSTRUCTIONS AND INFORMATION
Compressors and Turbines
CRP Amuay Rev. Dic. 2001
2.8 Steam turbines for auxiliary lube and seal oil pump drivers shall be per BP10-
14-1 and API 614 and shall be provided with Woodward TG-10 hydraulic
type governors or equal. Model and "Nema Class" shall be referred to
PDVSA for review.
For Lube System, main oil pump only can be directly coupled to the shaft of
the turbine if the speed is less than 1800 r.p.m. Otherwise, a separate main
oil pump shall be required.
2.9 Automatic startup facilities shall be provided for both the electric motor and
steam turbines driven auxiliary lube and seal oil pumps. A selector switch
shall be provided to designate the pump in standby autostart service.
2.11 For critical and special purpose equipment, anti-surge system C.C.C.
(Compressors Control Corporation) is preferred.
2.12 Lubrication shaft- Sealing and Control Oil Systems for special purpose
applications shall follow API 614.
2.13 For transmitter vibration and bearing temperature systems, Bently Nevada or
equivalent is preferred.
2.14 An oil heater for the lubrication system reservoir is not required.
3. BLOWERS
When is required use Bently Nevada or equivalent for transmitter vibration and
bearing temperature system.
IV-2
GENERAL INSTRUCTIONS AND INFORMATION
Instruments and Control Valves
CRP Amuay Rev. Dic. 2001
SECTION N° V
° Temperature ° Fahrenheit
3. Board mounted display stations, if any, shall be miniature electronic. Control valves
are to be pneumatically operated. Local control loops are to be pneumatic or
electronic depending on distance and application.
4. Final control elements shall drive in the direction indicated in the individual design
specification upon loss of instrument signal, power or instrument air failure. If no
direction is indicated, the contractor shall determine the fail safe position. On three-
way valves, the specified fail safe position and pressure drop are indicated for the
5. Measuring Instrument
- The minimum pipe size for conventional orifice is 2 in, and the
minimum flange rating class shall be 300 ANSI. The use of higher
rated flanges or of facing other than raised face shall be as required
by the piping specifications.
- The ratio of orifice diameter to internal pipe diameter does not exceed
0.7.
- Orifice meter differential range shall be 20, 25, 50, 100 or 200 in of
water. Differential range of 100 in of water is preferred.
- Normal design flow rate shall be between 60% and 80% of capacity.
-
Provided anticipated minimum and maximum flow rate between 10%
and 95% of capacity. The maximum rate should be selected to use
manufacturer's standard tube and float.
CONTROL VALVES
6. Control valves in flashing service are denoted on the design flow plans by the letters
"FS".
All control valves in flashing service shall be sized per I.S.A. Handbook of Control
Valve. For multicomponent liquids, use the same method but use the inlet pressure
for the vapor pressure and the critical pressure (i.e., ∆P max = 0.3 KmP1).
7. All control valves (including three-way control valves) shall be equipped with blocks
and bypasses unless approved by the owner. Those control valves not blocked
and bypassed shall be provided with handwheels.
8. In general, the minimum pressure drop for control valves (except three-way control
valves) at design flow shall be:
20 percent of the friction drop in the circuit (excluding the valve) plus 10 percent of
the static differential pressure in the circuit up to differential pressures of 200 psig,
20 psi from 200 psig to 400 psig, and 5 percent above 400 psig (this pressure drop
can be omitted in circuits such as recycle and reflux circuits in which any change in
pressure level in the receiver will be reflected through the entire circuit). However,
for these circuits the minimum valve pressure drop shall be 10 psi.
Lower pressure drops may be used in gas and vapor services where available
pressure is limited. These applications shall be stated as exceptions by the
contractor.
9. Minimum rating for process control valves shall be 300 psi for flanged and 600 psi
for screwed valves. Screwed end valves shall be limited to body size smaller than 1
inch.
10. The use of ODD size control valves, 1 ¼, 2 ½ and 5 inches shall be avoided.
12. Control valves in sulfur service shall be jacketed in addition to internal steam tracing
to make sure that the heat transfer the valve body is adequate.
GENERAL
13. External displaced type instruments shall not be used in any level instruments with
very dirty service, or subject to high vibration.
14. Gauge glass column drains shall be provided with drain line to sewer or closed
system as appropriate. This is in addition to BP15-5-1. In addition a separate fill
3/4" connections shall be added to drain line of level instruments to allow testing.
Steam drums shall use Clark Reliance or equal water columns and level glasses
with Ball Type stop check valves.
15. When necessary to prevent corrosive or solids bearing fluids from entering
instrument or instrument lines, seals or purges will be provided.
16. Independent high level alarm shall be installed on high risk tanks:
17. Instruments in vapor or gas service shall be mounted above the sensing point.
18. Instruments in liquid, steam or condensable vapor service must be mounted below
the sensing point.
19. Instrument block valves (take off connections) at piping shall be accessible in
Accessibility Chart
Access Required
Type of Instrument I II III IV V
Transmitters X
Local Indicators X
Pressure Gauges X X
Thermowells X X
Self-Contained Regulators X
Control Valve X
Local Controllers X
Local Recorders X
Process Actuated Switches X
Frequently Adjusted Instruments X
Emergency Instruments X
Analyzer X
Thermocouples X
Where:
25. In critical equipment for anti-surge system, Compressor Control Corporation (C.C.C)
system is preferred.
26. Analyzer Panel connections and sampling systems to process analyzers shall be
referred to PDVSA for review and approval.
27. On high pressure or high temperature process lines, flanged connections shall be
used. Union connections are not allowed.
28. All connections from process to instruments shall allow for rodding-out in case of
plugging. No elbows shall be used.
29. All entrances to Junction Boxes and Field Panels shall be from the bottom
(preferred) or side (alternative),no top entrance should be used.
Computer reliability has been excellent, but some computer downtime must be
expected and designed for. Therefore, a backup system which is capable of
keeping the units operating and on control during computer downtime must be
specified. The backup control systems must assure safe and stable operation of
the process units for extended periods (roughly up to six hours) although some
product giveaway and increased operator attention may be expected while on
backup. All control valves which are driven by the computer must have a backup
station from which the valve may be operated when the computer is unavailable.
Controllers requiring backup are identified by the symbol "X" next to the instrument
control function on the flow plans. Purchaser will provide guidelines for selecting
panel versus CRT backup station. The type of backup station is specified on the
instrument section of each design specification.
31. All annunciator panels and push button stations with associated lamp shall be
provided with a “lamp test” button.
34. Solenoid valve resetting shall be done manually at the local stations.
36. All components and equipment related with local panels shall be provided by the
supplier including the integration to the DCS.
37. Sample taps for analyzers or instruments located in sulfur lines, shall be traced with
145 psig steam to achieve the temperature requirement of 266ºF or higher.
38. Protective system shall move their protective positions on loss energy (e.g. electrical
power, instrument air). Protective system on rotating machinery are exceptions to
this and shall not move to the protective position on loss of energy.
Rotating machinery support and auxiliary equipment shall move to their protective
position on loss energy.
39. All sensors associated to the rotating machinery equipment shall be routed with rigid
conduit into the local control panel.
40. All system associated to the air flow measurement in blowers and compressors
shall use a primary element with an accuracy of 0.5%. A Venturi tube is
recommended for such applications.
41. Shared trend recording capability shall be provided only for critical instrument
signals which are brought into the control center. PDVSA will advise the number of
pens required for each project.
42. All manually or automatically initiated emergency trip, cut-in and cut-out systems
shall be provided with control center annunciators, logged into the computer system
(in control center and local panels). PDVSA will advise these requirements for each
particular project.
For local alarm systems with multiple alarm initiators, e.g., compressors and boilers,
one or more control center "group" annunciators shall be provided. Local
annunciator indication shall reveal which device caused the alarm First-out alarm
feature. Each time one of the local annunciators indicates an alarm condition, the
related control center group annunciator shall begin flashing and the warning horn
shall sound even if the alarm was initially active (reflash). When this group alarm is
acknowledged by the control center operator, the control center warning horn shall
stop and the annunciator shall continue flashing until the alarm is acknowledged at
the local panel, the annunciator shall provide a continuous light until all alarm
conditions are corrected. The group alarm shall sound on loss of power to the local
annunciator. The alarms to be logged into the computer will be selected for each
particular case.
43. All emergency trips, cut-ins and cut-outs shall be reset locally unless otherwise
specified. Process shutdown and interlock systems shall be reviewed with
purchaser for location of control equipment, detailed operation, development of
checkout procedure, test capability, and other items. Interlock systems must be
44. Online testing of all manually or automatically initiated emergency trip, cut-in and
cut-out systems with a minimum of complexity and with minimum manpower is
required. Therefore, each input (initiating device) and each output (emergency
action) shall have the capability of being bypassed or defeated, unless otherwise
specified. One noncancellable control Center Flashing Light shall be provided for
each system indicating that a trip initiator or emergency action of the system has
been bypassed or defeated. All these actions shall be logged into the computer
system. Individual indication shall be provided to identify which component has
been bypassed or defeated.
45. The following is a list of general guidelines to be used in selecting an alarm display
priority with systems utilizing hardwired annunciators, instrument CRT's, and
computer CRT's (or printer):
° Priority 1 Alarm
- Definition
- Examples
- Display
- Electrical wiring
Related with ESD. All the alarms are directed from PLC to the
Ronan annunciator and continue to the DCS by software link.
Bypass switches from the valves will be directed first to DCS and
then to the Ronan annunciator (Common alarm)
° Priority 2 Alarms
- Definition
All abnormal conditions which do not fit into the categories of Priority 1
alarms. Computer system shall have inherent alarm logging
capabilities.
- Display
Instrumentation/Computer CRT's.
49. Fuse protection shall be provided on an individual basis to all circuits feeding into
local panels. A shorted or grounded element should no propagate to the rest of the
circuits.
50. On local control panels with liquid crystal displays the roof should extend such that
sun's rays can not damage the instruments.
51. For equipment such as IPS, UPS, Fire Protection Systems, PDVSA shall advise
names of approved manufactures. All UPS systems shall be provided with an
external by-pass to permit on-line maintenance.
52. Terminations or splices to fiber optic cables shall be done in specially provided
junction boxes. Pig-tails shall be used at the terminations to allow easy
maintenance.
53. Bypass switches shall be normally closed. In general, there are two kinds of
bypasses that could be used: a general type for the final element bypass and a
particular bypass for each initiator which activates a common alarm at the panel
alarm.
SECTION N° VI
PROCESS VESSEL
PROCESS VESSELS
1. DESIGN CODES
2. DESIGN CONDITIONS
Vessels operating between 32°F and 750°F shall be designed for the
maximum anticipated operating temperature plus at least 50°F.
3. CORROSION ALLOWANCE
3.2 Alloy
For vessels constructed of alloys, a 0.01 inch corrosion allowance shall be
specified.
4.1 Carbon steel in wet H2S service used for vessels that are not fully lined shall
be tested in accordance with NACE TM-02-84 but using the test solution of
NACE TM-01-77.
- The acceptance criteria is a Crack Length Ratio of less than 15% for
each of the three sections from each coupon.
- One set of three speciments shall be tested from each end of each
plate as rolled.
4.2 Where Hydrogen Induced Cracking (HIC) Resistance Steel is specified, the
plate steel used shall be fully killed, made to fine grain practice and
normalized.
5. Manholes are required for access to all process vessels 30 inches in diameter and
larger. Manholes shall have a minimum diameter of 20". All parts which are to be
installed or removal after fabrication shall be designed to pass through the
manholes provided on the vessel. Handholes and/or flanged heads shall be
provided for vessels less than 30 inches in diameter. Process nozzles shall not be
used as vessel vents. Vessel vent minimum sizes are specified in Paragraph 9
below.
- Clean service - one manhole above the top tray, one at the main feed
tray, and one at the bottom of the tower, and one at each product or
pump around drawoff tray.
Whenever a manhole (20”) is located between two trays, the minimum space
between the trays shall be 2 feet.
5.2 Drums
One manhole minimum to be provided where entry is required.
6. Process nozzles shall be line size and flush unless otherwise specified. It is
required that all vessels and piping in amine service including entrained amine, to
be PWHT at all service temperature.
7. Vessel connections shall be minimized by placing safety valves, TI's, process vents
(not vessel vents), PI's and other connections (except level taps) on piping instead
of on vessels, wherever possible and will be by BP3-6-1. Contractor's vessel
drawings shall show all connections and nozzles. Level connections shall be 2 inch
minimum.
8. In addition to the vessel vent, all process vessels shall have a valved and blinded
process vent at least equal to the size shown below. This vent shall be located at
the high point of the overhead vapor line provided the vapor line take-off is from the
top of the vessel. If the vapor line is not from the top, then a vent with a block valve
must be provided on the top. Process vent lines shall be provided with a line size
block valve at the take-off point and the valve shall be readily accessible from an
operating platform.
9. All vessels shall have valved and blinded drain and process vent connections sized
according to vessel volume as shown below. These are minimum size. The drain
line may originate from a bottom liquid drawoff line of at least equal size. It should
terminate with a line size block valve, and blind. Vessel vent connections shall be
blinded without a valve.
Up to 7500 3 3 6
7500 to 15.000 3 4 6
15,000 to 25,000 4 6 6
Above 25,000 6 8 8
DRUMS
° For drums with a continuous flow of vapor, the cross sectional area for vapor
flow above high liquid level, or emergency high liquid level if applicable, must
be large enough to limit the vapor velocity to the values given below (split
flow may be used in horizontal drums to reduce vapor velocity by installing
inlet nozzles at each end with one center outlet nozzle):
No CWMS - - -
CWMS 150 120 100
CWMS refers to crinkled wire mesh screen. For vertical drums, the minimum
distance from the gas outlet nozzle to the top of the screen shall be equal to
one half the difference of the drum diameter and the outlet nozzle diameter,
all in inches. For horizontal drums, the CWMS shall be sized so that its
horizontal projected area is at least equal to the vertical cross section above
high liquid level. For horizontal and vertical drums, the minimum distance
from the screen to the outlet nozzle shall be equal to one-half the difference
of the screen diameter if a round CWMS, or the long side if rectangular, and
the outlet nozzle diameter, all in inches. The CWMS must be secured
sufficiently to withstand a minimum of 2 psi pressure differential without being
dislodged. CWMS shall be type 304 stainless steel unless otherwise
specified.
° The vapor space in two phase horizontal drums above high liquid level (or
emergency high liquid level, if present) must be at least 20 percent of the
° Horizontal drum inlet nozzles shall terminate in a 90° bend pointing toward
the near end of the drum. For nozzles handling liquid and gas mixtures or
gas only, the bend shall be above high liquid level and discharge against a
wear plate. For nozzles handling liquid only, the nozzle shall be below
normal liquid level.
° All vessels that continuously accumulate water shall have water drawoff
connections. In addition, the oil outlet nozzle shall be provided with a straight
internal extension to a level above high water level or a water drawoff pot
shall be provided.
° For drums that contain two liquid phases, sufficient holdup must be supplied
to assure good separation. The maximum settling rate allowed is 10 inches
per minute. Vertical settling pots may be used on horizontal drums if they
meet these criteria.
GENERAL
11. The CET (Critical Exposure Temperature) for pressure vessels 2 inches or less in
thickness shall be 60°F in order to use a hydrotest temperature of 70°F per BP18-6-
1.
12. Anti-vortex baffles: All process vessels with liquid holdup shall be provided with
anti-vortex baffles located between the liquid outlet nozzle and low liquid level. It
shall be designed per BP-5-2-1.
13. For vapor/liquid towers the design pressure given on the vessel specification is the
design pressure of the vessel at the tower top. The static head term represents the
additional loading at the tower bottom tangent line and includes the normal pressure
drop through the tower plus the static head of liquid when the level is at high liquid
level.
14. The following guides shall be used for establishing drum and tower hold up require-
ments:
14.1 Reflux drum residence time (low liquid level to high liquid level)
Basis for residence time defini- Recommended
Operating tion residence
Condition time, min
Volume Flow
Product goes to storage HLL to LLL Product 2
Product goes to another HLL to LLL Product 5
tower
Product goes to heater HLL to LLL Product 10 - 12
Product goes to heat HLL to LLL Product 10
exchanger along with other
process streams
Tower reflux HLL to LLL Product 5
Whichever is larger HLL to LLL Reflux + product 2
SECTION N° VII
FURNACE
FURNACES
2. DESIGN REQUIREMENTS
2.1 Every furnace with a stack temperature below 1,000°F shall be supplied with
a damper of 5 percent Cr steel. Damper shaft shall be 13 percent Cr alloy.
For all radiant furnaces or furnaces with stack temperatures above 1,000°F,
stainless steel dampers should be used. A pneumatic actuator shall be
provided on the stack damper operable from grade and from the control
house. The actuator shall be located at the damper level, connected directly
to the shaft. A damper position indicator shall be located at grade and in the
control house. The damper shall open 100% upon failure of the pneumatic
actuator.
2.2 Air tight flue gas sampling connections constructed of Type 316 stainless
steel shall be provided. These connections shall be designed for vacuum
conditions and shall be used for field sampling.
2.3 Readings from draft gauges shall be transmitted to indicators at the furnace
at grade. A separate indicator shall be provided for the draft gauge
connection below the convection section. Other points may be manifolded
into one common indicator.
2.4 The block valves in the steam lines for emergency coil injection and box
i
purge are to be located 50 feet minimum from the furnace and on the upwind
side of the furnace. Purge steam lines shall enter the furnace box through
the floor and shall be oriented to avoid steam impingement on the furnace
tubes.
2.5 For multipass furnaces, in all liquid or vaporizing services, each pass shall
have a flow controller with signals to the control house.
2.6 For all furnaces, pilot gas shall be natural gas, independent of the burner fuel
supply system.
2.7 All furnaces larger than 100 MBtu/hr (heat release) shall have their bridge-
wall and stack temperatures and bridgewall draft readings brought to the
control house.
2.8 Stacks (including vent stacks from unfired equipment) shall not be fabricated
from bolted sections unless approved by PDVSA.
2.9 The fire box radiant section shall be seal welded from the inside.
SECTION N° VIII
SAFETY FACILITIES
SAFETY FACILITIES
1. The safety facilities (pressure relief valves, flare, flare blowdown and seal drums,
etc) are to be designed to handle the largest load resulting from any possible single
contingency (i.e., non-remote). Contingencies, including fire, are considered as
unrelated if there is no process, mechanical or electrical interrelationship between
them. However, when analyzing any single contingency (such as cooling water
failure), all directly related effects resulting from that contingency should be conside-
red.
For non-related double contingencies (i.e., remote), the safety facilities shall be
designed such that the maximum pressure in any equipment item protected by the
safety facilities does not exceed 150% of its design pressure. This sets the basis for
the maximum superimposed pressure relief valve backpressures cited in this
section of the GII. In addition, the velocity in the flare seal drum, if applicable, shall
not exceed 230% of critical velocity during remote contingencies (versus 150%
during non-remote contingencies), the velocity in the flare blowdown drum, if
applicable, shall not exceed 175% of critical velocity (versus 100% for non-remote
contingencies), and the depth of the flare seal drum water seal leg, if applicable,
shall be at least equal to 110% of the maximum pressure in the flare seal drum
during remote contingencies (versus 175% of the maximum non-remote
contingency flare seal drum pressure). Critical velocity is defined as:
2. All unfired pressure vessels subject to overpressure either by fire or operating failure
i
must be protected by pressure relieving devices that will prevent the pressure from
rising more than permitted by the ASME Unfired Pressure Vessel Code Section VIII
unless:
° The vessel is under 2 feet 0 inches diameter and is constructed of pipe, and
the pressure relief valve is required for fire only.
° The vessel normally contains no liquid and a pressure relief valve would be
required for fire only.
3. In designing for fire contingency, the plot areas affected as part of a single fire
contingency depend on accessibility and spacing. A group of equipment is to be
considered a single fire risk area if it is separated from another area by a clear
spacing of at least 20 feet, on all sides, to permit firefighting attack into all parts of
the area. The maximum plot area to be considered a single fire contingency is 5000
square feet.
4. The capacity of pressure relief valves on vessels must be sufficient to release the
vapor generated during a fire contingency, as well as any other contingency. API-
RP-520, as amended by this document, should be used as the basis for calculating
the vapor rate generated during a fire. It should be noted that unless the insulation
and insulation support is known to withstand direct flame and fire water
impingement, as specified in BP3-2-4, no credit can be taken for it. The wetted
surface used to calculate heat
absorption for a practical fire situation is normally taken to be the total wetted
surface within 25 feet of grade. "Grade" usually refers to ground level, but any other
level at which a major fire could be sustained, such as a solid grating platform,
should also be considered. In the case of vessels containing a variable level of
liquid, the high liquid level is considered. Specific interpretations to be used for
various vessels are as follows:
A. Horizontal Drums
° Less than half full (to HLL) - The wetted vessel surface up to high
liquid level is used, regardless of distance above grade. This applies
to all types of grating, solid or open.
° More than half full (to HLL) - The total wetted vessel surface within 25
feet of "grade" ("Grade" means actual grade or a solid grating platform
beneath the drum), or up to the vessel equator, whichever is greater,
is used. If open-type grating is used and the vessel is more than 25
feet above grade, the total wetted vessel surface up to the equator
shall be used.
B. Vertical Drums - The wetted vessel surface within 25 feet of "grade" ("Grade"
means actual grade or a solid grating platform beneath the drum), based on
high liquid level, is used. If the entire vessel is 25 feet or more above
"grade", and open-type grating is used, then only the surface of the bottom
head need be included.
D. Heat Exchangers, Air Fins and Piping - These items of equipment are
normally not considered for establishing the wetted surface of exposed
vessels in a fire risk area. However, there may be special situations, such as
congestion and substandard spacing, or an unusually large piece of
equipment, such as a reboiler with liquid holdup of about 1,000 gallons or
more, which warrant their inclusion.
In these cases, the total wetted area exposed to fire (or in the case of airfin
exchangers, the total surface area) should be used.
E. Storage Spheres and Spheroides - The total surface area within 25 feet of
grade, or up to the elevation of the centerline, whichever is greater, should
be used.
i
The heat absorbed by the liquid in a vessel during fire exposure is calculated by the
equation Q= C1 F A0.82 where Q is in Btu/hr, F is the environmental factor (1.0 for
bare vessel) and A is the wetted surface in Ft2. C1 equals 21,000 for typical onsite
units in which good drainage exist. C1 equals 34,500 for facilities that lack good
drainage (e.g., typical offsite facilities, such as diked areas around tanks which
increases the level of fire involvement).
For insulation that meets the requirements of BP3-2-4 and for gunite/concrete, the F
factor is as follows:
Thickness, inches F
If a vessel contains liquid, its pressure relief valve and associated piping, as well as
the flare collection system, may have to be sized for two-phase vapor/liquid flow
during fire exposure. The following procedure shall be used to determine if two-
phase vapor/liquid flow can occur during fire exposure for either horizontal and
vertical drums.
For vertical vessels, the maximum usable volume shall exclude the volume of the
top head. If two-phase vapor/liquid flow is predicted to occur, the Contractor shall
contact the owner for the procedure to be used for sizing the pressure relief valve
and its associated piping.
° Pressure relief valves normally in vapor service, but which under any
single contingency may discharge flammable, corrosive or hazardous
liquids.
° Pressure relief valves located in the vapor space of partially liquid-
filled vessels when all of the following are not provided:
° Pressure relief valves discharging vapors which do not fall into the
above categories but which would be significant contributors to at-
mospheric pollution. Such releases should not normally be used to
size the closed system but should be tied in up to the limit of its
capacity. The order or preference for tying in to the closed system is
(1) malodorous vapors, (2) unsaturated hydrocarbons, (3) saturated
hydrocarbons.
B. Pressure relief valves can be discharged to the atmosphere only if all of the
following conditions are satisfied:
Outlet piping for pressure relief valves that discharge to the atmosphere should be
designed in accordance with the following:
1. Leakage:
2. Release:
a) The Contractor shall ensure that the pressure drop and back pressure
requirements of BP-3-2-4 and this document are met. Contractor's pressure
drop, back pressure, and other pressure relief valve calculations shall be
submitted to the Owner for review.
b) The inlet line to a pressure relief valve must be at least the size of the
pressure relief safety valve inlet. When multiple pressure relief valves are
manifolded, the cross sectional area of the manifold piping must be equal to
or greater than the sum of all the inlet areas of valves open to the manifold.
c) Pressure relief valve inlet line size must be checked independently of sizing
the pressure relief valve. The maximum allowable frictional pressure drop
between the vessel and the pressure relief valve inlet shall be 3 percent of
valve set pressure in psig units and shall consider only friction losses,
including contraction and expansion losses. Effect of liquid acceleration on
static head is excluded. This 3% limit applies to conventional, pilot operated,
and balanced bellows valves. Equipment with a design pressure of 50 psig
or less shall be referred to the owner if the 3% criteria is impractical to
achieve.
h) Discharge piping from an individual relief valve should not be smaller than
the valve outlet.
7. Pressure relief valve discharge piping shall be designed such that the following
backpressure limits are not exceeded:
Conventional Bellows
This applies when the pressure relief valve is not discharging. If the
valve discharges to a closed flare system, this is the maximum
pressure in the flare system considering all contingencies during
which this valve does not discharge.
TBP: total backpressure = BUBP + SIBP(for bellows, the 50% maximum TBP
equals BUBP + SIBP).
The SIBP limits are based on not exceeding 150% of the equipment's design
pressure in the event a non-blowing valve discharges as a result of a non-related
(i.e, double) contingency.
For pressure relief valves discharging to a closed flare system, the normal pressure
in the flare system shall be assumed to be zero. The maximum superimposed
backpressure is a function of location in the flare system, and shall be provided to
the Contractor by the Owner. As an approximation, the maximum superimposed
backpressure on any pressure relief valve discharging to a closed flare system is
approximately 20 psig.
8. The following considerations shall be taken into account in the design of heat
exchange equipment to cover the possibility of tube leaks or tube rupture:
° The entire low pressure system must be checked for mechanical adequacy
relative to overpressure in the case of a split tube.
° If the design pressure of the entire low pressure side is more than two-thirds
that of the high pressure side, no further consideration of a tube split is
necessary.
° If the design pressure of the entire low pressure side is less than two-thirds
that of the high pressure side, the system must be examined to determine
the need and size of pressure relief valves for a split tube contingency per
BP3-2-4.
° In determining the flow into the low pressure side resulting from a tube split,
the following shall be considered:
- Flow from the high pressure to low pressure side occurs through two
fully open tube ends.
normal operating pressure of the high pressure side and 110 percent
of the design pressure of the low pressure side (or critical pressure
drop, whichever is smaller). The relief valve is set at the low pressure
side design pressure and 10 percent accumulation is allowed.
Normal process flow into the low pressure side is assumed to stop.
The effect of flashing as liquid flows from the high pressure side to the
low pressure side, vaporization of any liquid in the low pressure side
due to contact with high temperature fluid, and loss of normal process
flow into the low pressure side must be taken into account.
° Where a control valve is present in the low pressure system piping downs-
tream of the exchanger, it shall not be considered to fail simultaneously with
the tube split. However, if process control would cause the valve to shut as a
result of conditions developed in the low pressure system resulting from the
split, the valve must be considered to shut. If the process control would
cause the valve to open or remain in a stationary position, the valve opening
shall be considered that existing under minimum normal flow conditions
through the valve.
° When the high pressure and low pressure fluids are at different temperature
levels, the effect of vaporization due to heating of the cooler fluid must be
considered.
° Piping or vessel material on the low pressure side may not be suitable for
cold temperatures resulting from a tube split. If a brittle fracture is possible in
the low pressure system as a result of a tube split, this condition shall be
referred to the Owner for further review.
block valves, and if the piping is of adequate size to handle vapor or liquid displaced
by design vapor generation in the equipment and is not subject to plugging, then the
system may be considered as one unit when calculating the required relief valve
relieving capacity.
In the case of block valves installed on the cooling water outlet line of an exchanger,
the block valves shall be CSO if a free path is required for the condition of a split
tube.
10. Pressure relief valve types have been specified as Consolidated valves, which are
the preferred type conventional pressure relief valve. The Owner will specify
preferred vendor(s) of pilot operated pressure relief valves. An integrally reinforced
bleeder shall be provided between the pressure relief valve and the upstream
pressure relief valve block valve. A valve bleeder shall also be provided between
the pressure relief valve and any downstream pressure relief valve block valve for
pressure relief valve outlets routed to process equipment (not the flare system).
11. All pressure relief valves shall be located for easy accessibility for maintenance
including manual unbolting and shall have "in place" mechanical equipment
handling per BP4-2-1.
12. Contractor shall determine the need for and design the required "thermal relief"
pressure relief valves, caution signs, small open bypass valves, liquid drainage
facilities, etc., per BP3-2-4 for heat exchangers and long piping sections. All
designs must be reviewed by the Owner. In addition to the requirements of BP3-2-
4, the following shall apply:
° Each "thermal relief" pressure relief valve shall be provided with an inlet CSO
block valve and an oulet CSO valve if the discharge is to a closed system.
Depressurizers 3/4" drain valves are required between the block valves and
the relief valves.
Depressurizers ¾" drain valves are required between the block valves and
the pressure relief valves.
13. The provision of valves, manually or remotely operated from a safe location, and
installed at strategic points throughout the equipment, is required to permit the
affected section to be isolated from other sections of the plant, so that the inventory
of fuel feeding a fire or emergency is limited to a small area or group of vessels.
These emergency isolation valves shall be provided in accordance with the
following guidelines. Valves required for equipment isolation are referred to as Type
A, B, C and D. Requirements for these valves are given in BP3-7-4, BP3-12-1,
BP15-9-2. Valve actuators should preferably be located upwind of equipment
protected.
Actuator buttons for type D valves should be located at least 25 feet from the fire
risk zone, preferably upwind. The same applies to type C emergency isolation
valves. Note that for a vessel feeding a pump, the push button must be at least 25
feet from the pump, the most likely source of fire. In addition, the emergency
isolation valve should be visible from the push button.
13.1 Compressors
can not be pumped out in ten minutes or less, isolation valves are
required in the interstage suction and discharge lines.
13.2 Pumps
° When the inventory in a pump suction vessel meets any of the criteria
listed below, a Type B, C or D valve is required, according to size and
location. Inventory is to the top of working level range; piping holdup
is neglected. In the case of towers, inventory is calculated at the top
of the working level range, with the addition of tray and reboiler holdup
if they are draining into the tower.
13.3 Vessels
° Vessels containing light ends, heavier than light ends above its flash
point, or severely toxic liquids require isolation valves as follows:
- The vessel contains light ends or heavier than light ends above
its flash point.
13.4 Reboilers
Tower reboilers are considered integral with their towers for isolation
purposes, contents to be included with tower inventory, and emergency
isolation valves are not required between tower and reboiler.
13.5 Furnaces
14. Emergency valves used in vapor blowdown (depressuring) service or for remote
shutdown of critical streams shall be tight shutoff type control valves. This is an
exception to BP15-9-2, Paragraph 5.2. Valves shall meet other requirements
applicable to Type D emergency valves given in BP3-7-4.
Emergency block valves which are fireproofed shall have additional requirements
per BP15-9-2 Paragraph 5.1 as follows:
16. The vent line from a balanced bellows valve shall be routed as follows:
In all cases, the 3/4" bellows vent line should be supported such that the first
support is no more than 4 feet away from the pressure relief valve. In addition, the
3/4 vent line should be supported on a handrail. Both supports should be loose-fit.
Follow RP520 and BP 3-2-4. In addtion, the bellows vent for all cases shall be
i
provided with a 3/4" CSO valve followed by a 3/4" plugged stub for testing and
cleaning. The takeoff for the vent line shall be downstream of this CSO valve and
shall also be provided with a 3/4" CSO valve.
17. All pressure relief valves and car-sealed valves shall be painted yellow. Bellows
type pressure relief valves shall be painted yellow with a red band.
18. Control valves indicated to have a specified maximum valve Cv, thereby ensuring
adequacy of safety facilities, shall be painted yellow and provided with a sign in
spanish warning against replacement with a valve having a Cv greater than the
specified maximum.
When a control valve failure affects the pressure relief valve sizing, e.g wide open
failure position of a control valve admitting fluid (liquid or vapor /gas) from a high
pressure source into a lower pressure system, the pressure relief valve should be
designed in accordance with the following, whichever is controlling:
In both cases, credit can be taken for vapor being relieved through the
normal channels (if the control scheme does not bottle-up the
equipment) as well as through the pressure relief valve.
c.- During startup, Control valve 100% open, bypass fully closed, only
source of vapor relief is the PR valve (assume downstream exit not
available).
19. Sample outlets for toxic gases (e.g. H2S) and non-viscous, volatile, toxic liquids
(e.g., sour water) should be designed to accommodate sample bombs in a closed
loop. Sample outlets for viscous, non-volatile toxic liquids (e.g., high boiling
aromatics) should be drawn from a closed loop and located near a funnel. The
funnel should have a screen to support a sample container with the funnel outlet
connected to a drain. However, sample outlets for viscous liquids containing a
fraction of volatile, toxic materials (such as H2S and benzene) should be located in a
closed housing box with local ventilation exhausted to a safe location (closed
system or an atmospheric location as determined by dispersion calculations). A
funnel (with a screen to support a sample container) connected to a drain should
also be located in the box. Sample outlets for toxic solids (such as coke) should be
located in a closed box. The connection of the funnel outlet into the drain should
prevent skin contact and prevent any flow onto the slab.
20. Sour gas monitoring systems will be required in areas where gas and/or liquid
streams are handled, containing H2S in sufficiently high concentrations so that any
liquid or gas release may cause hazardous situations.
21. All locations where off the road traffic can damage equipment or piping shall be
protected by a handrail.
SECTION IX
1.1 This section covers certain the general criteria as a guide for electrical
designs within the PDVSA Amuay Refinery located in Judibana, Estado
Falcón, Venezuela.
2.1 The equipment and material to be furnished and the work to be done shall
conform to the following codes and standards.
3.1 The electrical system shall be designed for reliable service, safety to
personnel and equipment, ease of maintenance and operation, minimum
power losses, mechanical protection of equipment, and the addition of future
loads.
3.3 System protective devices (relays, fuses, breaker trip units, etc.) shall be
selected and coordinated to ensure that the interrupter nearest the point of
fault (or high overcorrect) will open first and minimize equipment damage
and disturbances on the system. Similar criteria is applicable on selection of
ct’s, pt’s, etc.
3.5 All electrical equipment and material shall be new and supplied by approved
manufacturers. Equipment and materials shall be protected from damage
and the weather during transportation to site, site storage and construction.
3.7 For cable installation in underground duct banks, cable derating will be based
on "ETAP" program or by using another similar computer program in lieu of
Paragraph 6.25 of Exxon Basic Practice BP16-2-1.
4. DRAWINGS
Standard format and symbols NEMA/IEEE shall be used for manufacturer's and
construction's drawings.
5. ENVIRONMENTAL CONDITION
See Section N° 1.
6. AREA CLASSIFICATION
6.1 Areas and/or process units shall be classified as to the type and degree of
hazard as defined by the National Electrical Code supplemented by the
recommendations in the American Petroleum Institute "Recommended
Practices" RP-500 and National Fire Protection Association Standard 70C
and others, where applicable.
6.3 Electrical equipment and materials for use in classified areas shall be
certified by an approved testing authority for the specific classifications.
The system shall have a steady state voltage regulation of +/- 5%.
7.1.6 System Calculation
0.6 30 45
5.0 60 75
15.0 95 110
SWITCHGEAR
TRANSFORMER BREAKER TERM CABLE
TERMINAL OR BUS BAR PHASE
H1 A A or 1
H2 B B or 2
H3 C C or 3
X1 A A or 1
X2 B B or 2
X3 C C or 3
7.4.1 4160 volt, 2400 volt and 480 volt switchgear line-up shall be as
defined on 7.1.1. The 480 V switchgear line-up shall provide power
circuit breakers for the large motors. Line-ups of 2400 volt and 480
V motor controllers (MCC's) are also fed from its respective
switchgears through Bus Ducts. 480 V power circuit breakers will
be used to protect 480V MCC. The design of switchgears will
comply with BP16-2-1.
7.4.2 Motor protection when supplied from a power circuit breaker shall
include a thermal relay (49) besides overcurrent and ground fault
relays. Microprocessor based relays for motor protection are
acceptable, provided that they are fed from a 125 VDC battery
source or 120 VAC UPS systems.
7.4.3 Motor control circuit and control relays shall be designed to meet
reacceleration requirements described in 7.9 125 VDC shall be
used for trip and close circuits.
h. In the transformer yard the traditional design related to the use of rigid
steel galvanized conduit for underground service it is now being
replaced by an approved concrete e channel with metalic cover.
7.7 Motors
7.8.1 Motor and motor enclosure shall conform to PDVSA Sp- 46-11.
7.8.5 Each 2300 and 4000 volt motor shall have sufficient space in its
main junction box for stress cone termination of the incoming power
cables
7.8.7 Motors 1000 horsepower and above shall have surge capacitors
and lightning arresters supplied by the motor manufacturer and
mounted in the main junction box.
7.8.9 Motors rated for 4 kV and higher voltage shall be provided with a
coupling sensor in order to monitor stator insulation for partial
discharges. Sensors shall be mounted and connected in the power
terminal box. Terminal box size will be adecuate. External
connector for data acquisition shall be also provided. IRS
technology for partial discharges shall be used and confirmed by
the owner.
e. Fused contactors shall be used for medium voltage motors below 2000
HP to 151 HP. Ground Sensor relays are required in addition to motor
protection for protection of motor feed cables. Solid state relays shall
be used for motor protection as well.
f. Low voltage 480V switchgear breakers used for motor control shall be a
electrically operated air circuit breakers type. Fused switches in 480
volt switchgear are not acceptable. Solid state overcurrent protective
devices acceptable.
g. Low voltage combination motor starters shall be used for low voltage
motors up to 100 HP rated 460 V. Ground sensor 50 GS relay are
required in addition to motor protection as protection of motor feed
The allowable voltage drop in the cables, based on full load, shall
not exceed:
b. Power Transformer ( )
a. The Initial Design Load shall consist of: The nameplate rating
of all normally operating motors; the nameplate rating of
motors designated as "future" on drawings and the mechanical
b. Each transformer shall be sized such that its fan cooled rating
is equal to or grater than the product of the substation initial
design load in Kva, multiplied by a factor of 1.2.
c. During the find stage of the detailed engineering the design
load shall be calculated again and the transformer sizing shall
be checked.
a. Maximum available short circuit duties shall not exceed the interrupting
and short circuit (momentary) rating of standard metal clad switchgear
ANSI standards shall be applied. Transformer impedances are
selected to meet this requirement (besides of voltage drop
requirements).
• 480V, bus tie air breakers shall be normally open and shall have
auto transfer scheme.
• 2.4 kV and 4.16 kV bus tie vacuum breakers shall be normally open
and shall have auto transfer schemes.
9. PROTECTIVE RELAYING
a. Amuay Refinery follows the protecting relays scheme indicated in Exxon BP16-
12-2 in its electrical substations. Electromechanical relays for 50/51 protection
has been replaced by solid state relays GE MDP type for 50/51/51G protection.
10. DC SYSTEMS
10.1 Types
d. VAC Power supply for IPS and UPS will be redundant: one
480VAC supply shall be provided from the 480V TAPC located in the
low voltage substation. The second 480V supply will be provided from
MCC located in the low voltage substation.
10.2 Location
10.3 Voltages
10.4 Batteries
The battery chargers for station batteries shall be sized to recharge a fully
discharged battery to 95 percent full charge in not more than 8 hours while
supplying 100 percent of the rated load. Batteries and battery chargers are
further discussed in PDVSA Specification, "Station Battery and Battery
Charger".
10.6 DC Distributions
11.1 Types
The UPS systems shall consist of the following components: rectifier, battery,
battery disconnect, inverter, automatic transfer switch, bypass transformer,
manual/-maintenance bypass switch, and power distribution panels.
11.2 Location
UPS power supply for the plant control system shall be located in the control
building. UPS modules are installed in separate room from the batteries.
a 60 Hertz basis.
d. Redundant UPS modules are sized to carry 100 percent of the total of
all loads on the system.
The UPS Systems shall be equipped with a local alarm panel and a form "C"
(DPDT) dry contact for the following critical alarms:
c. Main 4.16 kV and 2.4 kV switchgear rooms are provided with a minimum
of 6 feet of spare room length for future addition of switchgear cubicles in
addition to required working clearance spaces.
d. Barrier walls between electrical equipment rooms have 3-hour fire rated
walls. This apply for busses machines within power supply building.
12.2 Switchgear
12.5.2 The neutral point of secondary windings rated 2400 volts through
34.5 kV shall be low resistance grounded. The neutral point of
secondary windings rated 600 volts and less shall be solidly
grounded.
The Stationary Bus Bars shall carry out the following requirements:
12.5.5 Refer to section 8.2 for Transformer Initial Design Load guidelines.
- Lighting panels.
- Welding outlets.
- Air conditioning equipment.
- Battery Changers.
- Space heaters.
In double ended substation, TAPC will be connected to both sides of the low
voltage switchgear and key-interlock will be provided to avoid simultaneous
closing of both sources.
13. CONTROL AND METERING
- Test switches shall be provided for all current and potential circuits for
equipment rated 5 kV and above.
- Multilin solid state relay shall be used to conform the power management
system (PMS) in substation. Fiber optic cable shall be used to communicate
- For buildings and groups of equipment located greater distances from the
main loop, supplemental Nº 4/0 AWG loop connected to the main loop shall
be utilized. Isolated equipment, remote from process area, shall be
grounded by using a local Nº 4/0 AWG ground loop attached to ground rods.
16. LIGHTING
a. Mercury vapor fixtures shall be used for outdoor lighting and high-bay
lighting areas.
Design of underground and above ground conduit system shall comply with the
requirements of BP16-3-1, Wiring Method and Material Selection. The following
guidelines further supplements the BP's.
b. Riding steel galvanized conduit shall be used for all lateral runs
from nonmetallic conduit duct banks, bends 45° through 90°, and
risers.
i. Where conduit rises above grade, the red encasing concrete shall
be extended a minimum of 6 inches above grade and be sloped for
water runoff.
o. Fiberglass ladder type cable trays and conduit with PVC coating
shall be used for coke handling areas.
For low voltage power and control cables, 600 V and below, see PDVSA
Specifications.
a. Wire and cable for service 600 volts and below shall be stranded
copper conductor, with a 600 volt insulation. The insulation shall
be a heat resistant, thermoplastic rated 75°C copper temperature in
wet or dry locations for revamp of existing installations.
For new installations will be cable type XHHW or RHH-RHW as
defined PDVSA Specification "Wire and Cable 600 V Power and
Control". In high temperature locations, wire with suitable insulation
shall be used.
f. Lighting branch circuit wires shall be color coded black, red, blue for
phases A, B and C respectively and white for the neutral.
c. For either 4.16 KV, 2.4 KV and .480 KV motor feeder, an isolated
ground return cable will be provided. Sizing and installation will be
according to Exxon Basic Practice, paragraph 7.9 to 7.14.
19.6 Cable for installation in cable trays shall be approved for cable tray
installation.
19.7 Cables shall be identified with a heat shrinkable plastic sleeve or approved
equal at each end.
19.6 For cable derating studies, the theoretical brake horsepower loads shall be
used.
20.1 Materials
20.2 Installation
c. Wire and cable types are based on the type of signal as listed
below:
f. In general, shield drain wires for individual pairs, triads and quads
shall be terminated and grounded at only one end. The other end
shall be cut and taped. The individual shield drain wire shall be
grounded at the end of the loop from which power for the loop
originates. Individual shield drain wires for thermocouples shall be
grounded at the thermocouple head. Generally, all other individual
shield drain wires are grounded at the control room.
g. When individual shields are provided for the individual pairs, triads
and quads in the home run cable, the shield for the field wires shall
be connected to the corresponding shield in the home run cable at
the junction box. The overall shield for the home run cable shall be
cut and taped at the junction box and grounded at the control room.
h. All shields and drain wires shall be insulated from ground at the
junction box.
21. COMMUNICATIONS
21.1 Provision for a dial type plant telephone system shall be made . Conduit with
a pull wire and space on pole lines shall be furnished, but all other material,
equipment and labor for the telephone system will be by others.
22. RECEPTACLES
b. All 480 V power receptacles shall be of the same size and rating.
The ground pole of each receptacle shall be solidly and
permanently connected to the plant grounding system through the
conduit or a separate ground wire.
23. NAMEPLATES
Equipment and materials shall be inspected for shipping damage immediately after
receipt at jobsite. In general, checkout and testing of systems and equipment shall
be done.
Procedures for Tie-Ins field connection shall be issued by contractor to PDVSA for
approval. The contractor to prepare a complete design and material procurement
for tie-ins, regardless of the works be made by them or PDVSA.
c. Air Conditioning.
d. Air filtration in Air Conditioning System.
Drawings:
a. Area Clasification.
b. One Lines/ Phasing Diagram/ Three Line Diagram/ Connection Diagram/
Interconnection Diagram/ Vendor Drawings.
c. Above Ground: Power, Control, Alarm and Signals.
d. Under Ground: Power, Control, Alarm and Signals.
e. Conduit/ Cable Schedules.
f. Substation-Equipment Arrangement.
g. Instrumentation.
h. Motor/ Transformer/ SWGR/ MCC/: ANSI/ IEEE Final Factory Test Report,
including all results and associated documentation.
i. Sistem (Associated to Drawings to be performed) Fire/ Lighting/ Ground/ H2S
Detection/ PMS/ Load Scheduling/ Transfered Trips/ Relays Setting
Tabulation/ Substation: Air Conditioning, electrical interfase/ Ground Grid.
j. The Consultant will also be responsible for updating the following materials:
k. General drawings and documents.
l. 13.8 kV Distributions System (Underground System) General Drawing.
m. 2.4 kV Distribution System (Serial Line).
n. Power supply and electrical distribution operation manuals.
The a, b and c studies will be developed by contractor with his own resources using
PDVSA-Amuay computer program. The Consultant shall be familiar with Magnet
Program (Available Operation Manuals). For remainder calculations other
programs may be used.
PDVSA also wants in relation to these equipments participate on RFQ'S and vendor
drawings revision.
SECTION N° X
MISCELLANEOUS
MISCELLANEOUS
Page N°
Fireproofing X-4
Machinery X-4
Gasketing X-4
Piping X-5
Pipe insulation for operating temperature above 650ºF to 1200ºF shall be according
to
these characteristics:
Option 1: Performed covering of calcium silicate, nominal density 15 lbs./cu ft. ,
Marsville “Thermo-12”, Owens Corning “Kailo 10”Pabco, “Super
Caltemp”.
For equipment (towers, drums, exchangers, etc.) which have design temperatures
less than 300°F but which would be steamed-out during startup or shutdown
operations, provisions shall be made for thermal expansion at 300°F. Product
rundown lines will not be steamed out. Steam-out is required during start up for the
following services: steam, instruments air and nitrogen.
SELECTION OF MATERIALS
All new materials selected will be reviewed by the owner, otherwise follow SP-50-5.
“Piping Material Specification”, last issued.
The following general rules shall be used for establishing equipment design
temperatures and design pressures.
Design Temperature
1. Below 60°F, the minimum design temperature shall be equal to the lowest
temperature reached during upset, startup, or normal operations.
3. Above 650°F for carbon steel and above 850°F for alloys, the temperature
increment added to operating temperature to set design temperature shall be
minimized. Only if variations in operating temperature are expected or if
operating flexibility with respect to temperature is important shall any
4. Towers operating over a wide temperature range from top to bottom may
have graded design temperatures for the purpose of reducing flange ratings
in the top. Usually the tower is divided into sections at the points of
significant temperature changes such as pump around and feed trays.
Design Pressure
FIREPROOFING
MACHINERY
Oil mist lubrication shall be provided for all onsite general purpose type equipment
such as centrifugal pumps, fans, gears and steam turbines which have non
pressure oil feed type bearing lubrication. Oil mist lubrication of offsites centrifugal
pumps and their drivers shall be considered where a number of pumps are centrally
located, the required utilities are available, and the system installation can be
justified.
Oil mist systems shall be designed for dry sump lubrication ("pure mist"). However,
equipment and oil mist systems shall be designed and supplied for initial operation
of the systems on "purge mist". Purge mist installations method shall be per the
original Figure 2 of BP3-3-12, last revision. Future conversion to dry sump
lubrication ("pure mist") shall be by the Owner. Grease lubricated antifriction
bearing type electric motors shall be designed for future conversion to dry sump
lubrication ("pure mist") by the Owner.
GASKETING
Cardboard gaskets shall not be used for any service or for hydrotest.
Where compressed asbestos is permitted or approved by the owner use only
compressed asbestos gasket with "NBR" binder anti-stick agent and minimum
tensile strength across the grain of 4000 psi. Klingerit Universal and Mamusa MM-
4078 are preferred. The perimeter of the gasket must be painted orange,
PIPING
1. Flexibility Analysis
1.1 Tower overhead lines are to be designed for the tower design
temperature. Temperatures lower than the design temperature may
be more limiting with respect to flexibility analysis.
1.3 Piping circuits which can be alternately hot or cold must be analyzed
for the worst condition. For example:
° Water drawoffs.
° Flexibility analysis must allow for steam out with 145 psig
steam.
2. General
2.2 Tower drawoff and reboiler feed/drawoff lines shall drop at least 5 feet
vertically from horizontal drawoff nozzles before a diameter reduction
and/or any horizontal run. For vertical reboiler drawoff nozzles, such
as tower bottoms nozzle for feeding a kettle reboiler, the drawoff line
shall drop at least 5 feet vertically below the tower normal liquid level
before a diameter reduction and/or any horizontal run.
2.3 Block valves and bypasses are not to be provided around heat
exchangers, coolers, and condensers except where required for
control or for services where frequency of cleaning or tube leakage is
known to be greater than frequency of plant shutdown and economic
justification exists.
2.4 Where connections between equipment and closed system (safety
valve header, fuel gas header, etc) are 2 inches or less and are all
welded lines, one pair of flanges shall be provided at the proper
location to permit installation of a blind during startup or shutdown
operation in accordance with BP3-7-4, Paragraph 3.7, last issue.
2.5 Only in critical heat loss service e.g. aeration steam, provide
insulation on flanges for all steam services and on flanges and valve
bodies for all steam valves 6 inch and larger, otherwise is not
required.
2.6 The following water side valves must be provided on all sea water
coolers and condensers:
a. Block valves (preferably butterfly type) are required on both
2.7 Cast iron valves shall not be used in any refinery service except salt
water.
2.8 Carbon steel piping shall be sized in accordance with the guidelines
given on Table 1, Page 10-10.
2.9 Flange ratings as specified on the design flow plans are based on
ANSI B 16.5. The contractor shall ensure compliance with ANSI
B16.5 and B16.34 last edition.
2.10 Lines sizes of 1¼, 2½, 5, 14 and 18 inches and 400 lbs. flange rating
are not to be used unless approved by the owner. This is applicable to
piping and equipment connections of any type. Unions are only to be
used in potable water, instrument air or another services where
threaded pipe is permit without seal welding. Unions can be used in
60 psi steam tracing service.
2.11 Lines for the following services shall be sized in accordance with the
maximum velocity guides given below:
a. Salt water cooling lines: Maximum velocity in main header or
branch lines may be 15 ft/sec.
C.S. S.S
a. Hydrocarbon Service
2.13 Block valves locations and branch take off locations shall be in
accordance with the guidelines given on Table 2, page 10-11.
Steam, instrument air and fuel gas connections shall be from the top
of the supply header or sub-header. All small piping connections < 2
inch shall be fabricated using a minimum length of pipe between the
takeoff point and valve and without the use of elbows between the
valve and takeoff point so that the outlet of the valve is within 9 inch of
the branch connection.
2.15 Slip on flanges shall be avoid. Use only with PDVSA approval and all
slip on flanges 4 inches or larger require 1/8" NPT hole before field
installation on any hydrocarbon service. A 15 psig air test must be
performed and recorded for slip on flanges.
2.16 Lines shall be identified at battery limit. Valve hand-wheels for Battery
Limit (BL) valves shall be directly accessible and positioned to be
within normal reach for operation. For elevated locations, platforms
with ladders for direct access from grade shall be provided.
Limitations governing the installation of EBV design type B or C on
Battery Limit Valves are given on PDVSA Manual de Ingenieria de
Riesgos. ( IR-P-01.Emergency Shutdown and Isolation ).
Provide a warm-up connection at battery limit valve for 600 and 145
psi steam lines.
Dummy pipe supports, where used, shall have sealed ends and be
provided with a low point drain hole.
2.19 The minimum orifice and control valve Flange Rating shall be class
300 ANSI.
2.20 Car seal open (CSO) valves shall be installed with the stem in a
horizontal to downward position. A seal or any other adequate device
shall be provided for these valves,
2.21 Nitrogen connectors at the utility stations shall be Bowes Quick lock
type or equivalent and must be approval by the owner.
2.22 Steam, instruments air, fuel gas, pilot gas piping are generally
cleaned by blowing all header terminations shall be designed with
flanges/blind flanges to permit cleaning. Terminations shall be
provided with drain valves.
Chemical cleaning is required for piping serving steam generating
equipment and rotating machinery.
2.23 Vent and drain lines from a balanced bellows safety valve shall be in
accordance with BP3-2-4 and RP520.
2.24 Hot tap tie-ins are not allowed in 600 psi steam and air instrument
lines.
Any hot tap and stopples connections shall be per “Manual de
Normas y Prevención de Accidentes de la Refinería de Amuay”.
2.25 Valves on orifice taps will be offset by using different size nipples.
2.26 Rotating equipment skids shall be directly drained to the open drain
system.
2.27 PWHT in seal welds is not required. PWHT requirements shall be in
accordance with ASME 31.3.
3.1 The requirement for piping in Wet H2S Service is that all welds to be
stress relieved.
3.2 All piping in amine service including entrained amine shall be PWHT
at all service temperatures.
TABLE 1
(1) An economic evaluation will be necessary to determine the optimum pressure drop of lines constructed of
other than carbon steel.
(2) For slurry lines, sized base on minimum and maximum velocity considerations.
Maximum Velocity 3.0 ft/sec (saltation)
Maximum Velocity 15.0 ft/sec (erosion)
(3) Short ≤300 feet
1. Safety ladders, platforms, stairs, and railing shall comply with the requirements of
the U.S. Occupational Safety and Health Standards.
2. Ladders except for stacks shall be caged when the vertical length between the
ladder base and the platform it serves is more than 20 feet.
Ladders under 29 feet shall also be caged when the base of the ladder is above
grade and the ladder serves a platform more than 20 feet above grade. The cage
shall extend down to a point 7 to 8 feet from the ground or platform.
SECTION N° XI
SCOPE
Pages 11-1 through 11-26 of this section give requirements for abbreviations,
equipment, instrument and line numbering and certain flow diagrams guides.
° Process streams
B/SD - Barrels (42 U.S. Gallons) per stream day at 60°F
GPM - U.S. gallons per minute at conditions
Lb/Hr - Pounds per hour
MSCF/SD - Million standard cubic feed per stream day at 1 atm,
60°F
BHP - Brake horsepower
MW - Molecular weight
SGc - Specific gravity at conditions
Cp (Cs) - Viscosity in centipoises (centistokes) at conditions
∆P - Differential pressure in pounds per square inch
ACFM - Actual cubic feet per minute at conditions
SCFM - Standard cubic feed per minute at 1 atm, 60°F
° Utilities
Utilities
PG - Pilot Gas
N2 - Nitrogen
UA - Utility Air
IA - Instrument Air
PA - Process Air
° Safety
° Waste Disposal
° Valves
Valves
FL - Fail last position
FS - Flashing service
TS - Tight Shutoff
CSO - Car Seal Open
CSC - Car Seal Close
° Materials
Note: Only for Process Flow Diagram, for Detail Engineering use piping material
specification SP-478150-50-3, last issue.
Materials
TI - Titanium
CI - Cast Iron
CS - Carbon Steel
1¼ Cr - 1¼% Cr - ½% Molybdenum Steel
5 Cr - 5% Cr - ½% Molybdenum Steel
9 Cr - 9% Cr - 1% Molybdenum Steel
410 - Type 410 Stainless Steel
304 - Type 304 Stainless Steel, 18-8
310 - Type 310 Stainless Steel, 25 Cr - 20 Ni
316 - Type 316 Stainless Steel, 18-8 Mo
321 - Type 321 Stainless Steel, 18-8 Ti
347 - Type 347 Stainless Steel, 18-8 Cb
KCS - Killed Carbon Steel
CS/Inconel Clad - Carbon steel - Inconel clad
1¼Cr 0.5 Mo/ - 1 ¼% Cr - ½% Molybdenum - Type 321 Stainless
Type 321SS Steel.
° Corrosion Allowance
BP3-10-1 - Piping
BP5-1-1 - Pressure Vessels
BP5-2-1 - Vessel Internals
BP5-2-2 - Reactor internals
BP9-2-1 - Storage Spheres
Example
- Boiler Feed
Water System
- Lube Oil
System
40 - P - 4101 A
+- Use to Identify multiple items
| | | | | of alike equipment in parallel
| | | +---------+ or series in the same service (A, | | |
B,C, etc)
| | |
| | +----------Equipment Series Number
| |
| +---------------Equipment Code (Note 1)
|
+--------------------Area Code
41 - F 101 - RC
| | | |
|
| | | On
flow plans
| | | |
|
| | +--- Function (Note 2) F-
101
|
| +-------- Instrument series number
R
C
| +------------ Instrument type (Note 2)
+----------------- Unit code
Note 2: For function and instrument type symbols see PDVSA's Drawings
46 - P101 - SV
| | +---- Safety valve prefix letters
| +------------ Safety valve series numbers (3 or |
4 digits)
+-------------------- Unit code
2. Line numbering
° All process and utility headers in the main interconnecting pipeway will be
assigned line numbers keyed to the interconnecting pipeway unit number.
° Within each area, line numbers for utility headers will be prefixed with the
pipeway unit code.
° Utility branch lines within an area will be prefixed with the unit number and
numbered in series with the mechanical flow diagram they serve.
6" - P 41 O34 - A A 4 G
| | | | | | | |
| | | | | | | |
| | | | | | | +---Open Modifier (Note 3)
| | | | | | +------Corrosion allowance (Note 3)
| | | | | |
| | | | | +---------Material of construction (Note 3)
| | | | |
| | | | +------------Rating (Note 3)
| | | |
| | | +-----------------Line Number (three digits)
| | |
| | +----------------------Unit Code (one or two
| | digits)
| +--------------------------Service (Note 3)
|
+-------------------------------Line Size
Note 3: For the appropriate symbols see PDVSA's Drawings MT.1-7-03-11 and
MT.1-7-03-12.
Example:
Example:
ATTACHMENT 1
EXISTING UNITS
Future Units
Naphtha Fractionator 25 15 DPAY
/TAME 25 15 TMAY
Future 25 16
Unit block
ATTACHMENT 2
Deviations from these instructions may be permitted for the sake of specific
circumstances but such deviations should be approved by PDVSA.
The process flow diagram shows the basic process philosophy. It transmits
process information for the design and specification of equipment and
development of the piping and instrument flow diagram. It serves as a guide
for operation of the plant. Process flow and operation are readily apparent
on a well-drawn diagram.
The utility balance diagram describes a major utility system. It shows the
relationship between the usage by consumers, for more than one case (start-
up, peak usage, seasonal, etc.) if necessary, and the generation by
equipment or other sources.
- Inert Gases
- Steam and Condensate
- Cooling Water
- Fuel Gas
- Waste Water Collection
- Chemical Products
The piping and instrument flow diagram serves as the basic document to
show the scope of work and provides the detailed plant design definition
required for the engineering and construction of the plant. It reflects all piping
needs based on hydraulic calculations performed and instrumentation
required for plant operation.
The PFD does not necessarily show all equipment. For example, parallel
units or spares are not normally shown. However, the presence of these
items is indicated by the equipment number.
b. Process & Design condition for piping can be located either on the
bottom of the drawing or on a separate sheet.
c. Paper size, format type "D" 560 mm (22 in) x 880 mm (34½ in) is
preferred.
Note: For more details see PDVSA L-TP 1.1, May, 94.
- Equipment
c. Title of equipment.
d. Mechanical design pressures and temperatures (see Table N° 1).
° Drains, vents and purges required for operating reasons and the type
of sump where they discharge.
° Utility piping serving the equipment items, such as fuel gas and steam
to furnaces; steam to turbines and reboilers/reheaters; cooling water
to exchangers and pumps.
° Drain valves between relief valves and block valves with CSO in the
inlet and discharge lines of these.
° Steam traps for process purpose are shown with a note indicating the
destination of the condensate return.
Note:
° The set points for alarms and emergency switches (pressure, flow,
level, temperature, etc.).
° Safety valves and thermal relief valves with size, set pressure and
inlet and discharge lines.
The general guidelines for laying out the equipment and piping on Process
° Paper format Type "D" - 560 mm (22 in) x 880 mm (34½ in) is
preferred.
° Equipment Distribution.
box. This line will define the battery limits of the system and
the tie- in points for piping and instrumentation.
° Lines.
a) Process lines will enter and leave the drawing at the right or
left side.
b) Venting and relief lines will leave from the top section of the
drawing.
e) All process and utility lines will be drawn with the least possible
changes in direction. Whenever the line drawn changes
direction, the direction of flow will be indicated with a heavy
triangular arrow.
g) Main process lines will be of a heaver line weight (#3) than the
secondary process, utility, drain lines and lines to and from
relief valves. Main process equipment will be of a heavier line
weight (#2) than spare equipment. Control valve bypasses will
be shown using the light weight line (#1), similar to secondary
process lines.
a) Headers and branches of the utility systems serving each plant, for
example water (utility water, cooling water , raw water and potable
water), steam and condensate, relief system, instrument and utility air,
nitrogen and fuel gas. The representation of this systems should
reflect close relationship with the actual location of the equipment
items being served (Plot Plan).
o) Breathing air stations, safety monitors alarms and horn are shown on
the fire protection drawings "in plot plant fashion".
° The general guidelines given on section 3.2 applies for the Utility
Systems Piping and Instrumentation Flow Diagrams.
° Use format type "D" - 560 mm (22 in) x 880 mm (34½ in).
ATTACHMENT 2
TABLE 1
Information to be included on P&ID Flow Diagrams.
(1) Heat tracing insulation and other provisions and process protection against ambient
temperatures shall be indicated for all facilities to be treated.