Вы находитесь на странице: 1из 10

Contractor: Kevin Levene

Telephone: 1(876) 378-9660

Preliminaries

Description Amount

Setting up of building $35,000

Removal of rubbish and completion $30,000

Excavation and Earth work 160 ft * $600 $99,000


per ft
Casting foundation 165 ft * $400 per ft $66,000

Back fill with selected excavation material $30,000


around all foundation and column

Steel work @ $45,000 per tonne $45,000

total $305,000

1|Page
Block Work

Description Amount

Block work 2,500 block @ $8,000 per $200,000


100
Box and cast include lintel and beam
and columns

Column box and case 677ft * $450 $304,650

total $504,650

2|Page
Decking
Description Amount

Setting up of decking and board work $180,000


9sq @ $20,000 per sq

Steel work 1 tonne @$45,000 per tonne $45,000

Casting decking 81 sq yd @ $750 per sq $60,750


yd
Total $285,750

3|Page
Casting

Description Amount

Casting of floor 76 sq yd @ $750 per sq $57,000


yd

Flashing all wall and door edge $95,450

Rendering all wall and door and window $170,000


edge

total $322,450

4|Page
Electrical material

Quantity Materials Unit price Price total


10 flush plug and cover

10 handy box

12 octagon box

14 receptacles

16 way breaker pan

12 switches

6 wall case

7 single switch plate

2 double switch plate

2 triple switch plate

1 60 double amp breaker

4 15 amp breaker

3 20 amp single pole breaker

1 30 amp breaker

1 G-O-5 breaker

3 3 ¾ pot head

1 metre box

6 10 mm male cupling

50 20 mm cupling

30 20 male cupling

5|Page
6 10 mm cupling

4 30 Amp Strip connector bars

4 Bundle of 20 mm pipes

6 Roll of 2.5 wires

5 Roll of 1.5 wires

160 ft 10 mm red

80 ft 10 mm black

15 32mm electrical pipe

8 32 electrical bend

15 32 mm cupling

- Total

6|Page
Foundation material estimate

Amount material Unit price Total price


1 Tonne steel $91,500.00

½ Tonne 3/8 steel $540.00 $48,600.00

50 LBs Binding wire $90.00 $4,500.00

150 bags Cement $940.00 $141,000.00

1 load Sand $66,500.00

1 load Gravel $38,000.00

- Total - $390,100.00

Block work estimate


2000 Block $90.00 $180,000.00

50 bags Cement $940.00 $47,000.00

2 box 2 in cc concrete nails $147.00 $14,700.00

- Total - $241,700

7|Page
Decking

1 load Sand $66,500.00

1 load Gravel $38,000.00

20 2*4*14 treated lumber $1000.00 $20,000.00

30 1*3*14 Rough pitch pine $451.25 $13,537.00

30 5/8 ply $2,700 $81,000.00

100 Cement $940.00 $94,000.00

100 LB 2 ½ inch Head nail $97.09 $9,709.00

10 LB 3 inch Head Nail $94.74 $947.40

6 LB 4 inch Head Nail $98.18 $589.08

- Total - $324,282.48

8|Page
Flashing, rendering and floor estimate

Amount Material Unit Price Price


4 yd Rendering sand
40 bags Cement

9|Page
Item Description Qty Unit Rate Amount
Engineering Service
Electrical installation
All electrical work should include all
necessary chasing of walls, installation
of conduits, wiring oxogonal boxes,
junction boxes, p.v.c wire connectors
and make good all work disturbed and
done by an approved electrician

allow a ps of $240,000.00 to be used to


A complete all necessary electrical works Sum $ 240,000.00
including wiring switches, light outlets,
plugs outlets

allow provision of Government


B electrical inspection certificate fees

plumbing installation
provide the following to complete
plumbing installation and accessories
complete with American standard band

all a ps of $ 55,000.00 to be used to


A complete all necessary plumbing work Sum $55,000.00

Drainage
Manhole
Man hole 900mm × 900mm × 900mm
A deep complete with 150 mm thick
block, steel bars render and metal cover 2 No $28,000.00 $56,000.00

Trapped gully Basin


B Trapped gully basin 350mm × 350mm ×
400mm deep complete with 150mm
thick block, steel bars render and metal 2 no $12,500.00 $$25,000
cover

Septic tank
C $100,000.00
To supply and construct septic tank and
reed bed

Total

10 | P a g e

Вам также может понравиться