Вы находитесь на странице: 1из 13

PROPOSED G+1 OFFICE,CHEMICAL STORAGE, TANK FARM AND ISO TANK CLEANING FACILITY

ON PLOT NO: S61108,JAFZA


BILL OF QUANTITIES
OFFICE BLOCK
SL.NO DESCRIPTION UNIT QUANTITY RATE AMOUNT
SUB STRUCTURE
1 EARTH WORK EXCAVATION M3 795.00 16.00 12,720.00
2 ROAD BASE FILLING 200 mm thk. (BELOW PCC) M3 111.00 98.00 10,878.00
3 PCC IN FOOTINGS M3 25.00 580.00 14,500.00
4 RCC IN FOOTINGS M3 85.00 990.00 84,150.00
5 RCC IN PEDESTALS M3 3.00 995.00 2,985.00
6 RCC IN TIE BEAM M3 15.00 980.00 14,700.00
7 SOLID BLOCKS M2 146.00 90.00 13,140.00
8 BITUMEN PAINTING M2 912.00 5.00 4,560.00
9 BACKFILIING IN FOUNDATION M3 537.00 18.00 9,666.00
10 PCC BELOW WALL FOOTING M3 2.00 580.00 1,160.00
11 WALL FOOTING M3 2.00 930.00 1,860.00
12 ROAD BASE FILLING 200 mm thk. (BELOW GRADE SLAB) M3 77.00 98.00 7,546.00
13 POLYTHENE SHEET M2 1,099.00 5.00 5,495.00
14 GRADE/FLOOR SLAB M3 47.00 740.00 34,780.00
15 ANTI TERMITE TREATMENT M2 945.00 5.00 4,725.00
16 DISPOSAL M3 261.00 20.00 5,220.00
17 RCC WALL M3 2.00 1,180.00 2,360.00
18 FLOOR POLYFOAM INSULATION M2 349.00 30.00 10,470.00

SUPER STRUCTURE
1 STIFFNER COLUMNS M3 4.00 1,100.00 4,400.00
2 RCC COLUMNS M3 23.00 1,050.00 24,150.00
4 STIFFNER BEAMS M3 4.00 1,100.00 4,400.00
5 LINTEL BEAMS M3 2.00 1,050.00 2,100.00
6 R.C.C FOR STAIR, SLAB AND BEAM M3 135.00 1,200.00 162,000.00
7 R.C.C FOR PARAPET M3 19.00 1,100.00 20,900.00

BLOCK WORK
1 THERMAL BLOCK WORK - 200 mm thk. M2 285.00 125.00 35,625.00
2 INTERNAL BLOCK WORK- 200 mm thk. M2 129.00 105.00 13,545.00
3 INTERNAL BLOCK WORK- 100 mm thk. M2 278.00 100.00 27,800.00

PLASTERING
1 EXTERNAL PLASTERING M2 242.00 44.00 10,648.00
2 INTERNAL PLASTERING M2 1,178.00 39.00 45,942.00

PAINTING
1 EMULSION PAINTING M2 796.00 45.00 35,820.00
2 EPOXY PAINTING M2 242.00 47.00 11,374.00

TILES, MARBLE & FALSE CEILING


1 NON SLIPPERY CERAMIC TILES M2 99.00 90.00 8,910.00
2 GLAZED CERAMIC TILES M2 397.00 90.00 35,730.00
3 SKIRTING - GRANITE TILES RM 189.00 39.00 7,371.00
4 GRANITE TILES M2 398.00 140.00 55,720.00
5 GRANITE - (STEPS/RAMP) M2 89.00 530.00 47,170.00
6 SKIRTING - GRANITE RM 48.00 200.00 9,600.00
7 CARPET FLOORING M2 13.00 160.00 2,080.00
8 THRESHOLD RM 18.00 230.00 4,140.00
9 DECORATIVE GYPSUM FALSE CEILING -60X60 M2 279.00 115.00 32,085.00
10 VINYL FACED ALU. FALSE CEILING M2 380.00 98.00 37,240.00
11 WATER PROOFING AT ROOF M2 389.00 150.00 58,350.00
12 WATER PROOFING AT MEZZANINE TOILET AND PANTRY M2 145.00 85.00 12,325.00
13 GYPSUM BOARD PARTITION M2 284.00 135.00 38,340.00
14 PANTRY CABINET RM 8.00 1,850.00 14,800.00
15 PANTRY CABINET LOWER RM 8.00 1,700.00 13,600.00
16 TOILET /PANTRY SLAB - GRANITE/MARBLE FINISH RM 13.00 1,800.00 23,400.00
ROOF CONCRETE TILES M2 386.00 70.00 27,020.00
-
DOORS AND WINDOWS
1 ED1 Nos. 2.00 8,900.00 17,800.00
2 D1 Nos. 19.00 4,200.00 79,800.00
3 D2 Nos. 1.00 4,285.00 4,285.00
4 D3 Nos. 2.00 4,370.00 8,740.00
5 D4 Nos. 3.00 4,200.00 12,600.00
6 D5 Nos. 6.00 1,450.00 8,700.00
7 ALUMINIUM CLADDING M2 720.00 300.00 216,000.00
8 GLASS CLADDING M2 265.00 665.00 176,225.00
9 STEEL CANOPY LS 1.00 3,400.00 3,400.00
11 S.S HANDRAIL RM 54.00 975.00 52,650.00
12 ALUMINIM PROFILE SECTION RM 340.00 60.00 20,400.00

TOTAL AMOUNT 1,668,100.00


PROPOSED G+1 OFFICE,CHEMICAL STORAGE, TANK FARM AND ISO TANK CLEANING FACILITY ON
PLOT NO: S61108,JAFZA
BILL OF QUANTITIES
WORKERS FACILITY
SL.NO DESCRIPTION UNIT QUANTITY RATE AMOUNT

SUBSTRUCTURE
1 EXCAVATION M3 192.00 16.00 3,072.00
2 ROAD BASE FILLING M3 28.00 98.00 2,744.00
3 P.C.C.UNDER FOOTINGS & TIE BEAM M3 5.00 580.00 2,900.00
4 R. C. CONCRETE IN FOOTING M3 7.00 990.00 6,930.00
5 R. C. CONCRETE IN PEDESTAL M3 1.00 995.00 995.00
6 R.C.C CONCRETE IN WALL FOOTING M3 3.00 930.00 2,790.00
7 R. C. CONCRETE IN TIEBEAM M3 4.00 980.00 3,920.00
8 SOLID BLOCK WORK M2 49.00 90.00 4,410.00
9 BITUMEN PAINTING M2 185.00 5.00 925.00
10 BACK FILLING M3 128.00 18.00 2,304.00
11 DISPOSAL M3 64.00 20.00 1,280.00
12 P.C.C BELOW WALL FOOTING M3 2.00 580.00 1,160.00
13 ROAD BASE BELOW FLOOR SLAB M3 18.00 98.00 1,764.00
14 FLOOR SLAB M3 8.00 740.00 5,920.00
15 POLYTHENE SHEET M2 295.00 5.00 1,475.00
16 ANTI TERMITE TREATMENT M2 272.00 5.00 1,360.00
17 POLY FOAM INSULATION M2 82.00 25.00 2,050.00

SUPERSTRUCTUR
1 RCC LINTEL M3 2.00 1,100.00 2,200.00
2 RCC COLUMNS M3 3.00 1,050.00 3,150.00
3 RCC BEAM M3 7.00 1,200.00 8,400.00
4 RCC ROOF SLAB M3 16.00 1,200.00 19,200.00
5 RCC PARAPET M3 2.00 1,100.00 2,200.00
6 RCC STIFFNER COLUMN M3 1.00 1,100.00 1,100.00
7 RCC STIFFNER BEAM M3 2.00 1,100.00 2,200.00
8 50MM THK INSULATION RM 39.00 70.00 2,730.00

BLOCK WORK
1 THERMAL BLOCK WORK M2 116.00 125.00 14,500.00
2 INTERNAL BLOCK WORK M2 99.00 105.00 10,395.00

PLASTERING
1 EXTERNAL PLASTERING M2 219.00 40.00 8,760.00
2 INTERNAL PLASTERING M2 394.00 40.00 15,760.00

PAINTING
1 EXTERNAL PAINTING M2 219.00 49.00 10,731.00
2 INTERNAL PAINTING M2 299.00 47.00 14,053.00

TILES, MARBLE & FALSE CEILING -


1 GLAZED CERAMIC TILES M2 185.00 90.00 16,650.00
2 NON SLIPPERY CERAMIC TILES M2 88.00 90.00 7,920.00
3 SKIRTING RM 61.00 15.00 915.00
4 CARPET FLOORING M2 8.00 160.00 1,280.00
5 THRESHOLD RM 10.00 180.00 1,800.00
6 ENTRANCE STEP-MARBLE M2 3.00 600.00 1,800.00
7 GRANITE SLAB FOR PANTRY & TOILET M2 9.00 1,750.00 15,750.00
8 PANTRY CABINET RM 4.00 1,700.00 6,800.00
9 URINAL PARTITION RM 2.00 2,000.00 4,000.00
10 TOILET WATER PROOFING M2 79.00 80.00 6,320.00
11 ROOF WATER PROOFING M2 97.00 150.00 14,550.00
12 ROOF TILE M2 92.00 70.00 6,440.00
13 FALSE CEILING M2 85.00 120.00 10,200.00
14 PANTRY COUNTER TOP RM 4.00 1,850.00 7,400.00
- -
DOORS & WINDOW - -
1 D1(1x2.1) Nos 2.00 4,400.00 8,800.00
2 D2(0.9x2.1) Nos 1.00 4,300.00 4,300.00
3 D3(0.9x2.1) Nos 1.00 4,700.00 4,700.00
4 D4(0.8x2.1) Nos 4.00 4,200.00 16,800.00
5 V1(1.2x0.6) Nos 2.00 1,300.00 2,600.00
6 V2(2.4x0.6) Nos 1.00 1,000.00 1,000.00
7 W1(1.5x1.2) Nos 6.00 1,800.00 10,800.00
-
TOTAL AMOUNT 312,203.00
PROPOSED G+1 OFFICE,CHEMICAL STORAGE, TANK FARM AND ISO TANK CLEANING
FACILITY ON PLOT NO: S61108,JAFZA
BILL OF QUANTITIES
CLEANING BAY
SL.NO DESCRIPTION UNIT QUANTITY RATE AMOUNT
SUB STRUCTURE
1 MOBILIZATION LS
2 EARTH WORK EXCAVATION M3 3231.00 16.00 51,696.00
3 ROAD BASE FILLING 200 mm thk. (BELOW PCC) M3 315.00 98.00 30,870.00
4 PCC IN FOOTINGS M3 53.00 580.00 30,740.00
5 RCC IN FOOTINGS M3 63.00 990.00 62,370.00
6 RCC IN PEDESTALS M3 6.00 995.00 5,970.00
7 RCC IN TIE BEAM M3 17.00 980.00 16,660.00
8 RCC FOR TANK BASE SLAB M3 126.00 1200.00 151,200.00
9 RCC FOR TANK WALL M3 118.00 1200.00 141,600.00
10 R.C.C FOR TANK COVER SLAB M3 73.00 1200.00 87,600.00
11 SOLID BLOCKS M2 156.00 90.00 14,040.00
12 BITUMEN PAINTING M2 1255.00 5.00 6,275.00
13 BACKFILIING IN FOUNDATION M3 1751.00 18.00 31,518.00
14 ROAD BASE FILLING (BELOW GRADE SLAB) M3 195.00 98.00 19,110.00
15 POLYTHENE SHEET M2 1736.00 5.00 8,680.00
16 GRADE/FLOOR SLAB M3 127.00 790.00 100,330.00
17 ANTI TERMITE TREATMENT M2 2350.00 5.00 11,750.00
18 DISPOSAL M3 1482.00 75.00 111,150.00
19 RAMPS & STEPS M3 16.00 950.00 15,200.00
20 EPOXY COATING+ FLOOR HARDNER M2 790.00 70.00 55,300.00
21 CONSTRUCTION /EXPANSION JOINT LS 1.00 8000.00 8,000.00
22 EMERGENCY EYEWASH NOS. 1.00 5000.00 5,000.00
23 HDPE MEMBRANE FOR ETP TANK M2 1126.00 40.00 45,040.00
24 TRENCH CONCRETE M3 14.00 1200.00 16,800.00
25 HDPE MEMBRANE BELOW FLOOR SLAB M3 832.00 40.00 33,280.00
26 50MM SANDBED M2 1661.00 20.00 33,220.00
27 MANHOLE COVER NOS. 9.00 1200.00 10,800.00
28 GRP LINING 3MM THK. M2 740.00 80.00 59,200.00
29 RUBBER WATER STOPPER RM 149.00 65.00 9,685.00
30 4MM PROTECTION BOARD M2 388.00 40.00 15,520.00
31 COLUMN ENCASING M3 6.00 1100.00 6,600.00

SUPER STRUCTURE -
1 STIFFNER COLUMNS M3 10.50 1100.00 11,550.00
2 RCC COLUMNS M3 7.26 1100.00 7,981.05
3 R.C.C IN COPING BEAMS M3 5.78 1150.00 6,641.25
4 STIFFNER BEAMS M3 5.48 1100.00 6,029.10
5 LINTEL BEAMS M3 0.89 1100.00 981.75
6 R.C.C FOR STAIR, SLAB AND BEAM M3 10.49 1200.00 12,587.40
-
BLOCK WORK -
1 THERMAL BLOCK WORK - 200 mm thk. M2 346.00 125.00 43,250.00
2 INTERNAL BLOCK WORK M2 143.00 105.00 15,015.00

PLASTERING
1 EXTERNAL PLASTERING M2 393.00 44.00 17,292.00
2 INTERNAL PLASTERING M2 633.00 39.00 24,687.00

PAINTING
1 EMULSION PAINTING M2 633.00 45.00 28,485.00
2 EPOXY PAINTING M2 393.00 47.00 18,471.00

TILES, MARBLE & FALSE CEILING


1 NON SLIPPERY CERAMIC TILES (30dhs. Tile cost) M2 44.00 90.00 3,960.00
2 GLAZED CERAMIC TILES M2 107.00 90.00 9,630.00
3 DECORATIVE GYPSUM FALSE CEILING -60X60 M2 39.00 115.00 4,485.00
4 VINYL FACED ALU. FALSE CEILING M2 39.00 98.00 3,822.00
5 WATER PROOFING AT MEZZANINE TOILET AND PANTRYM2 32.00 85.00 2,720.00
-
DOORS AND WINDOWS -
1 LD1 Nos. 1.00 5100.00 5,100.00
2 LD2 Nos. 2.00 3300.00 6,600.00
3 LW Nos. 2.00 2100.00 4,200.00
4 W1 Nos. 1.00 3150.00 3,150.00
5 W2 Nos. 2.00 1350.00 2,700.00
6 D1 Nos. 1.00 8300.00 8,300.00
7 D2 M2 3.00 4650.00 13,950.00
-
METAL & STEEL -
1 STEEL STRUCTURE KG 22450.00 8.00 179,600.00
2 ROOF SHEETING M2 1294.00 190.00 245,860.00
3 M.S HANDRAIL RM 74.00 360.00 26,640.00
4 Z PURLIN RM 1335.00 44.00 58,740.00
5 ANCHOR BOLT Nos. 100.00 38.00 3,800.00
6 GRATINGS RM 53.00 950.00 50,350.00

TOTAL AMOUNT 2,021,781.55


PROPOSED G+1 OFFICE,CHEMICAL STORAGE, TANK FARM AND ISO TANK CLEANING FACILITY
ON PLOT NO: S61108,JAFZA
DRUM STORE, PUMP ROOM & WATER TANK
BILL OF QUANTITIES
SL.NO DESCRIPTION UNIT QUANTITY RATE AMOUNT
SUB STRUCTURE
1 EXCAVATION M3 2,652.00 16.00 42,432.00
2 ROAD BASE FILLING M3 157.00 98.00 15,386.00
3 P.C.C. UNDER FOOTING & TIE BEAM M3 33.00 580.00 19,140.00
4 R. C. CONCRETE IN FOOTING M3 50.00 990.00 49,500.00
5 R. C. CONCRETE IN PEDESTAL M3 5.00 995.00 4,975.00
6 R.C.C CONCRETE IN WATER TANK ROOF SLAB M3 109.00 1,150.00 125,350.00
7 R.C.C CONCRETE IN WALL M3 147.00 1,200.00 176,400.00
8 R.C.C RAFT TANK M3 176.00 1,150.00 202,400.00
9 R.C.C CONCRETE IN COLUMN M3 4.00 990.00 3,960.00
10 R.C.C IN TIE BEAM M3 5.00 980.00 4,900.00
11 R. C. CONCRETE IN BEAM M3 35.00 1,100.00 38,500.00
12 R.C.C IN STAIRCASE M3 1.00 1,100.00 1,100.00
13 R.C.C PLATFORM SLAB M3 16.00 750.00 12,000.00
14 COLUMN ENCASING M3 7.00 1,100.00 7,700.00
15 HDPE MEMBRANE M2 611.00 40.00 24,440.00
16 BACK FILLING M3 652.00 18.00 11,736.00
17 ROAD BASE BELOW FLOOR SLAB M3 123.00 98.00 12,054.00
18 PLINTH FILLING M3 591.00 18.00 10,638.00
19 DISPOSAL M3 1,477.00 20.00 29,540.00
20 FLOOR SLAB M3 115.00 780.00 89,700.00
21 BITUMEN PAINTING M2 995.00 5.00 4,975.00
22 POLYTHENE SHEET M2 1,404.00 5.00 7,020.00
23 ANTI TERMITE TREATMENT M2 1,389.00 5.00 6,945.00
24 FLOOR EPOXY COATING+ FLOOR HARDNER M2 627.00 70.00 43,890.00
25 50MM SAND BED M2 1,254.00 20.00 25,080.00
26 WATER STOPPER RM 83.00 65.00 5,395.00
27 3MM THK. GRP LINING M2 773.00 80.00 61,840.00
28 EXTERNAL MEMBRANE WATER PROOFING M2 392.00 150.00 58,800.00
29 MANHOLE COVER NOS 1.00 1,100.00 1,100.00

SUPERSTRUCTURE
1 RCC COLUMNS M3 12.00 1,050.00 12,600.00
2 STIFFNER BEAMS M3 4.00 1,100.00 4,400.00
3 COPING BEAM M3 7.00 1,150.00 8,050.00
4 LINTEL M3 2.00 1,050.00 2,100.00
5 PUMP ROOM GRADE BEAMS M3 6.00 1,100.00 6,600.00
6 AC PLATFORM LS 1.00 55,000.00 55,000.00

BLOCK WORK
1 THERMAL BLOCK WORK M2 678.00 130.00 88,140.00
-
PLASTERING -
1 EXTERNAL PLASTERING M2 896.00 44.00 39,424.00
2 INTERNAL PLASTERING M2 677.00 39.00 26,403.00

PAINTING
1 EXTERNAL PAINTING M2 897.00 47.00 42,159.00
2 INTERNAL PAINTING M2 678.00 45.00 30,510.00

METAL & STEEL -


1 STEEL STRUCTURE KG 21000.00 8.00 168,000.00
2 ROOF SHEETING M2 965.00 190.00 183,350.00
3 M.S HANDRAIL RM 86.00 460.00 39,560.00
4 Z PURLIN RM 1035.00 44.00 45,540.00
5 ANCHOR BOLT Nos. 88.00 38.00 3,344.00

DOORS AND WINDOWS


1 FD NOS 1.00 2,000.00 2,000.00
2 RUD (4X3) - MANUAL NOS 1.00 17,000.00 17,000.00
3 FW NOS 2.00 4,100.00 8,200.00
4 PD NOS 1.00 3,800.00 3,800.00
-
TOTAL AMOUNT 1,883,076.00

Discount 167,076.00

GRAND TOTAL AMOUNT 1,716,000.00


PROPOSED G+1 OFFICE,CHEMICAL STORAGE, TANK FARM AND ISO TANK CLEANING FACILITY ON
PLOT NO: S61108,JAFZA
BILL OF QUANTITIES
SUBSTATION & SECURITY ROOM
Sl No DESCRIPTION UNIT QUANTITY RATE AMOUNT

SUBSTRUCTURE:
1 EXCAVATION M3 275.00 16.00 4,400.00
2 ROAD BASE FILLING M3 36.00 98.00 3,528.00
3 P.C.C.UNDER FOOTINGS & TIE BEAM M3 7.00 580.00 4,060.00
4 R. C. CONCRETE IN FOOTING M3 11.00 990.00 10,890.00
5 R. C. CONCRETE IN PEDESTAL M3 1.00 995.00 995.00
6 R.C.C CONCRETE IN STRAP BEAM M3 4.00 990.00 3,960.00
7 R.C.C CONCRETE IN WALL FOOTING M3 4.00 950.00 3,800.00
8 R. C. CONCRETE IN TIE BEAM M3 3.00 980.00 2,940.00
9 SOLID BLOCK WORK M2 42.00 90.00 3,780.00
10 BITUMEN PAINTING M2 199.00 5.00 995.00
11 BACK FILLING M3 212.00 18.00 3,816.00
12 DISPOSAL M3 73.00 20.00 1,460.00
13 P.C.C BELOW WALL FOOTING M3 2.00 580.00 1,160.00
14 ROAD BASE BELOW FLOOR SLAB M3 28.00 98.00 2,744.00
15 FLOOR SLAB M3 13.00 750.00 9,750.00
16 POLYTHENE SHHET M2 248.00 5.00 1,240.00
17 A.T.T M2 315.00 5.00 1,575.00
18 FLOOR-POLY FOAM INSULATION M2 115.00 30.00 3,450.00
-
SUPERSTRUCTURE: -
1 RCC COLUMNS M3 3.00 1,050.00 3,150.00
2 LINTEL BEAMS M3 2.00 1,050.00 2,100.00
3 RCC BEAM M3 8.00 1,200.00 9,600.00
4 RCC ROOF SLAB M3 23.00 1,200.00 27,600.00
5 RCC PARAPET M3 4.00 1,100.00 4,400.00

BLOCK WORK
1 THERMAL BLOCK WORK M2 113.00 125.00 14,125.00
2 INTERNAL BLOCK WORK M2 112.00 105.00 11,760.00
- -
PLASTERING - -
1 EXTERNAL PLASTERING M2 263.00 44.00 11,572.00
2 INTERNAL PLASTERING M2 329.00 39.00 12,831.00

PAINTING
1 EXTERNAL PAINTING M2 263.00 47.00 12,361.00
2 INTERNAL PAINTING M2 269.00 45.00 12,105.00

TILES, MARBLE & FALSE CEILING


1 WALL TILES M2 57.00 90.00 5,130.00
2 FLOOR TILES M2 56.00 90.00 5,040.00
3 SKIRTING Rm 42.00 15.00 630.00
4 THRESHOLD Rm 4.00 190.00 760.00
5 GYPSUM TILE FALSE CEILING M2 57.00 85.00 4,845.00
6 ROOF WATER PROOFING M2 148.00 150.00 22,200.00
7 ROOF TILES M2 140.00 70.00 9,800.00

DOORS & WINDOW -


1 D1(1.8x2.4) Nos 3,500.00 3,500.00
2 D2(1x2.1) Nos 1,750.00 3,500.00
3 D3(0.8x2.1) Nos 1,250.00 2,500.00
4 W1(3.6x1.2) Nos 3,300.00 6,600.00
5 W2(2.4x1.2) Nos 2,200.00 2,200.00
6 LD(3.05x2.75) Nos 6,000.00 6,000.00
7 LW(2.4x2.15) Nos 3,500.00 7,000.00
8 V1(0.7x0.6) Nos 800.00 1,600.00
9 FIX GLASS IN TOILET (0.60x1.8m) Nos 2,100.00 2,100.00
-
-
TOTAL AMOUNT 269,552.00
PROPOSED G+1 OFFICE,CHEMICAL STORAGE, TANK FARM AND ISO TANK CLEANING FACILITY
ON PLOT NO: S61108,JAFZA
TANK FARM
BILL OF QUANTITIES

SL.NO DESCRIPTION UNIT QUANTITY RATE AMOUNT


SUB STRUCTURE
1 EARTH WORK EXCAVATION M3 935.00 16.00 14,960.00
2 ROAD BASE FILLING 200 mm thk. (BELOW PCC) M3 311.00 98.00 30,478.00
3 PCC IN FOOTINGS M3 73.00 580.00 42,340.00
4 RCC IN RAFT SLAB M3 570.00 1,100.00 627,000.00
5 BUND WALL M3 61.00 1,200.00 73,200.00
6 BACK FILLING M3 193.00 18.00 3,474.00
7 DISPOSAL M2 742.00 75.00 55,650.00
8 BITUMEN PAINTING M2 86.00 5.00 430.00
9 EMERGENCY EYE WASH + QUICK SHOWER Nos. 1.00 5,000.00 5,000.00
10 HDPE LINER M3 1,594.00 40.00 63,760.00
11 POLYTHENE SHEET M2 3,307.00 5.00 16,535.00
12 ATT M2 1,569.00 5.00 7,845.00
13 RCC WALL PAINTING M2 668.00 48.00 32,064.00
14 HANDRAIL & STAIR CASE LS 1.00 18,000.00 18,000.00
15 STEEL STRUCTURE FOR STAIRCASE KG 3,000.00 8.00 24,000.00
16 TRENCH GRATING RM 148.00 900.00 133,200.00

TOTAL AMOUNT 1,147,936.00


DOWN LOADING STATION
1 EXCAVATION M3 58.00 16.00 928.00
2 ROAD BASE FILLING 200 mm thk. (BELOW PCC) M3 11.00 98.00 1,078.00
3 PCC IN FOOTINGS 100 mm thk. M3 6.00 600.00 3,600.00
4 RCC IN FLOOR M3 18.00 990.00 17,820.00
5 POLYTHENE SHEET M2 74.00 5.00 370.00
6 ATT M2 74.00 5.00 370.00
7 RCC WALL M3 8.00 1,200.00 9,600.00
8 DISPOSAL M3 57.00 75.00 4,275.00

TOTAL AMOUNT 33,766.00


PROPOSED G+1 OFFICE,CHEMICAL STORAGE, TANK FARM AND ISO TANK CLEANING
FACILITY ON PLOT NO: S61108,JAFZA
NITROGEN TANK
BILL OF QUANTITIES
SL.NO DESCRIPTION UNIT QUANTITY RATE AMOUNT
SUB STRUCTURE

1 EARTH WORK EXCAVATION M3 89.00 16.00 1,424.00


2 ROAD BASE FILLING 200 mm thk. (BELOW PCC) M3 18.00 98.00 1,764.00
3 PCC IN FOOTINGS M3 3.00 580.00 1,740.00
4 POLYTHENE SHEET M2 85.00 5.00 425.00
5 ANTI TERMITE TREATMENT M2 90.00 5.00 450.00
6 RCC FOUNDATION M3 53.00 990.00 52,470.00
7 BITUMEN PAINTING M2 37.00 5.00 185.00
8 BACK FILLING M3 23.00 18.00 414.00
9 DISPOSAL M3 57.00 20.00 1,140.00

TOTAL AMOUNT 60,012.00


PROPOSED G+1 OFFICE,CHEMICAL STORAGE, TANK FARM AND ISO TANK CLEANING
FACILITY ON PLOT NO: S61108,JAFZA
DUMPSTER COLLECTION
BILL OF QUANTITIES
SL.NO DESCRIPTION UNIT QUANTITY RATE AMOUNT
SUB STRUCTURE
1 EARTH WORK EXCAVATION M3 14.00 16.00 224.00
2 ROAD BASE FILLING 200 mm thk. (BELOW PCC) M3 14.00 98.00 1,372.00
3 PCC IN FOOTINGS 100 mm thk. M3 4.00 580.00 2,320.00
4 RCC IN FOOTINGS M3 3.00 1100.00 3,300.00
5 BITUMEN PAINTING M2 9.00 5.00 45.00
6 BACKFILIING IN FOUNDATION M3 8.00 18.00 144.00
7 POLYTHENE SHEET M2 61.00 5.00 305.00
8 ANTI TERMITE TREATMENT M2 26.00 5.00 130.00
9 DISPOSAL M3 9.00 20.00 180.00
10 RCC WALL M3 1.00 1200.00 1,200.00
11 MANHOLE NOS. 5.00 1200.00 6,000.00
12 FLOOR TILE M2 32.00 120.00 3,840.00

TOTAL AMOUNT 19,060.00


PROPOSED G+1 OFFICE,CHEMICAL STORAGE, TANK FARM AND ISO TANK CLEANING FACILITY ON
PLOT NO: S61108,JAFZA
EXTERNAL WORKS
BILL OF QUANTITIES
SL.NO DESCRIPTION UNIT QUANTITY RATE AMOUNT

MOBILIZATION LS 1.00 200,000.00 200,000.00

CIVIL WORKS -
CONSTRUCTION OF BOUNDARY WALL AND PLAIN COMPOUND
1 RM 556.00 795.00 442,020.00
WALL COMPLETE IN ALL RESPECT
SUPPLY AND INSTALLATION OF GATES AND AUTOMATIC
2 60,000.00
BARRIERS LS 1.00 60,000.00
3 INTERLOCK WORKS M2 8,500.00 80.00 680,000.00
4 KERB STONE RM 1,350.00 60.00 81,000.00
RCC CONCRETE PAVED AREA, HUMPS, RAMPS INCLUDING HDPE
5 10,000.00
MEMBRANE LS 1.00 10,000.00
6 ROAD BASE COMPACTED AREA M3 1,560.00 95.00 148,200.00
7 AREA LIGHT POLE RC FOUNDATION LS 1.00 60,000.00 60,000.00
8 RAIN WATER DISPERSAL SYSTEM LS 1.00 14,000.00 14,000.00
9 DOMESTIC WATER TANK INCLUDING PUMP SHELTER LS 1.00 24,000.00 24,000.00
10 DOMESTIC HOLDING TANK(26500GL) LS 1.00 96,000.00 96,000.00
11 INDUSTRIAL HOLDING TANK LS 1.00 140,000.00 140,000.00
12 COVERED CAR PARKING NOS. 14.00 4,000.00 56,000.00
13 DIRECTION SIGNS,SPEED BUMPS,CRASH BARRIERS LS 1.00 40,000.00 40,000.00
14 WEIGHTBRIDGE CIVIL WORKS LS 1.00 100,000.00 100,000.00
15 SWEET SOIL FOR LANDSCAPING M2 740.00 25.00 18,500.00

TOTAL AMOUNT 2,169,720.00